CENTRAL EXPRESSWAY PROJECT SECTION -2 FROM MEERIGAMA TO KURUNEGALA

PACKAGE -A FROM MEERIGAMA (37+090 ) TO RILOLUWA (46+800)


SUB PACKAGE - B FROM CH(46+050 ) TO CH(46+800) upto month of January
SUB PACKAGE-B FROM CH (46+050) TO CH (46+800) LEGTH: 0.75 Km
BILL NO.9 - DAY WORKS
B.O.Q S&K Vs ACCESS
Item Diif. In
Description Unit Claimed Paid
No Qty Rate (LKR) Amount (LKR) Claim Paid Diff. Amount(LKR)
Amount(LKR) Amount(LKR)

Schedule of Day work Rates - Contractor's Plant


38 Bulldozer up to 32 t hr 28 9,645.31 270,068.68 -
39 Bulldozer over 32t with blade or ripper hr 28 12,027.49 336,769.72 7.10 7.10 - 85,395.18 85,395.18 -
40 Motor Grader 3.6 m hr 9 4,218.38 37,965.42 46.00 17.30 (28.70) 194,045.48 72,977.97 (121,067.51)
41 Wheel Loader up to 1.5 cu.m. hr 4 2,729.50 10,918.00 - - - -
42 Wheel Loader over 1.5 cu.m. hr 26 4,158.81 108,129.06 20.20 20.20 - 84,007.96 84,007.96 -
43 Backhoe - up to 1.0 cu.m. hr 26 3,327.59 86,517.34 26.90 1.00 (25.90) 89,512.17 3,327.59 (86,184.58)
44 Dump Truck 4.0 to 6.0 t hr 105 1,895.59 199,036.95 - - - -
45 Dump Truck 10t hr 100 2,490.65 249,065.00 117.80 35.80 (82.00) 293,398.57 89,165.27 (204,233.30)
46 Dump Truck 15t hr 100 4,386.39 438,639.00 12.00 12.00 - 52,636.68 52,636.68 -
47 Cargo Truck 10 ton with crane hr 100 2,154.29 215,429.00 - - - -
48 Agriculture Tractor and Trailer hr 26 744.36 19,353.36 - - - -
49 Concrete Pump 100cu.m /hr hr 14 5,844.29 81,820.06 - - - -
50 Vibrating Roller - 2.5 ton hr 26 1,413.43 36,749.18 - - - -
51 Macadam Roller - 10 ton hr 37 2,977.73 110,176.01 47.50 41.20 (6.30) 141,442.18 122,682.48 (18,759.70)
52 Tire Roller 8 - 20 t hr 26 3,890.90 101,163.40 - - - -
53 Tamping Roller 20 t hr 51 4,049.71 206,535.21 - - - -
54 Asphalt Sprayer 1500L hr 26 730.53 18,993.78 - - - -
55 Asphalt Paver hr 12 8,559.51 102,714.12 - - - -
56 Crawler Crane 50 t hr 12 9,322.28 111,867.36 - - - -
57 Mobile Crane 10 ton hr 12 2,019.30 24,231.60 - - - -
58 Concrete Vibrator hr 12 254.10 3,049.20 - - - -
59 Water Bowser 3800L hr 26 1,985.16 51,614.16 - - - -
60 Generator Set 100 kVA hr 26 1,826.34 47,484.84 - - - -
61 Jack Hammer 40kg hr 10 397.03 3,970.30 - - - -
62 Water Pump 100mm hr 61 296.18 18,066.98 - - - -
63 Air Compressor 750 CFM hr 61 4,240.29 258,657.69 - - - -
64 Double cab 4WD hr 35 508.56 17,799.60 - - - -
65 Passenger van hr 35 1,291.19 45,191.65 - - - -
CENTRAL EXPRESSWAY PROJECT SECTION -2 FROM MEERIGAMA TO KURUNEGALA
PACKAGE -A FROM MEERIGAMA (37+090 ) TO RILOLUWA (46+800)
SUB PACKAGE - B FROM CH(46+050 ) TO CH(46+800) upto month of January
SUB PACKAGE-B FROM CH (46+050) TO CH (46+800) LEGTH: 0.75 Km
BILL NO.9 - DAY WORKS
B.O.Q S&K Vs ACCESS
Item Diif. In
Description Unit Claimed Paid
No Qty Rate (LKR) Amount (LKR) Claim Paid Diff. Amount(LKR)
Amount(LKR) Amount(LKR)

Subtotal of Day works Contractor's Plants 3,211,976.67 940,438.22 510,193.13 (430,245.09)

Access Paid VO

JCB - (Access Rate) rate instead of


backhoe loader hr 2,000.00 - 13.80 13.80 - 27,600.00 27,600.00

Excavator 200 - S&K Given rate 3800


but access paid it as a backhoe
upto1.50cu.m 3,800.00 6.90 - (6.90) 26,220.00 - (26,220.00)
Water bowser - S&K rate - 2000 2,000.00 10.50 10.50 - 21,000.00 21,000.00 -

Total of Bill No. 9 - Day works Carried to Main Summary 987,658.22 558,793.13 (428,865.09)
4.3+4.8+3.2+6.8+5.2+4.4 (46+460)

8.40 + 1.50 + 1.30 + 1.90

Not paid from november 2018

2.10 (pilot road)+ 1.80 + 1.30 + 1.10 (46+460)


45+720 Temp. bridge 3.80 + 1.00 + 1.10 ddt(46+460)