Connect 2020 Schedule
3
PHASE Connect 2020 Sequence
1 January - February Preparing the work area
Platform Closed - NB
Stadium Station
Single Tracking - SB
4
PHASE Connect 2020 Sequence
1 January - February Track and Systems installation
Turnback track
Platform Closed - NB
from Angle Lake
5
PHASE Connect 2020 Sequence
2 February - March Track and Systems installation
Single Tracking - NB
6
POST
CONSTRUCTION
Connect 2020 Sequence
at Completion
IDS platform - NB
Stadium Station
IDS platform - SB
7
Adjacent Construction
8
Track-bed Preparation
9
Track Installation
10
Systems Work
11
Testing and Safety Certification
12
Operations
13
Operations
14
Public Safety
• Security operating 24/7, increased
staffing from 6am – 10pm.
15
Temporary Signage:
16
Ambassador Program
• 705 staff have
participated.
• Ambassadors answering
questions and receiving
feedback.
17
Feedback
Customer Service
81 total
• Announcements (29)
• Early/Late Operations
(29)
Social - Twitter
183 total
• Neutral or positive (133)
• Negative (50)
18
Partner Agencies
19