Documente Academic
Documente Profesional
Documente Cultură
UNIT OVERHAULS
6X210 MW & 4X500 MW UNITS
OF
PLANNING
UNIT SHUT DOWN
COOLING DOWN OF MACHINES
DISMANTLING
INSPECTION FOR CONDITION
REPAIR & RECTIFICATION
ASSEMBLY
TESTING & INSPECTION
REVIVAL OF EQUIPMENT & SYSTEM
REVIVAL & RECOMMISSIONING OF UNIT
NTPC/VINDHYACHAL
CONTD…
IDENTIFICATION OF CRITICAL MATERIALS REQUIRED
FOR UNIT OVERHAULS AND REVIEW ON MONTHLY BASIS.
PREOVERHAUL MEETING FOR REVIEW OF CONSTRAINTS
& PREPAREDNESS INVOLVING ALL.
PRE OVERHAUL CONDITION MONITORING REPORT
PREOVERHAUL UNIT SURVEY
UNIT OUTAGE ANALYSIS FROM LAST OVERHAUL
FEED BACK OF UNIT FROM FIRST SYNCHRONIZATION
REVIEW OF STATUS & COORDINATION OF WELDING
SUPPLY, LIGHTING, LIFTS, HOISTS, CRANES ETC.
NTPC/VINDHYACHAL
CONTD…
PAST OVERHAULS AT A GLANCE (HISTORY OF UNITS)
PREPARATION OF MILESTONES (PLANNED)
COMPILATION OF UNIT DEFECT LIST
CONTD…
BOILER TUBE LEAKAGE COMMITTEE RECOMMENDATIONS
OS RECOMMENDATIONS
CONDITION MONITORING GROUP RECOMMENDATIONS
SAFETY REQUIREMENT
R&M REQUIREMENT
PREPARATION OF:
PTW & CLEARANCE BOOKS FOR BOILER & AUX.
PTW & CLEARANCE BOOKS FOR TG & AUX.
CLEARANCE & RECOMMISSIONING BOOK FOR VALVES,
DAMPERS, IGVs, SOOT BLOWERS & LRSBS
NTPC/VINDHYACHAL
CONTD...
CHECK SHEET FOR MOTOR TRIALS, EQUIPMENT
RECOMMISSIONING & PROTECTION CHECKING
CHECK SHEET FOR VALVES REQUIRED FOR CONDENSER
FLOOD TEST
CHECK SHEET FOR VALVES REQUIRED FOR BOILER
HYDRO TEST
PROCESS IMPROVEMENTS
• BOILER EXTERNAL WATER WASHING WAS CAUSING
DAMAGE TO INSULATION AND DELAY IN START OF
OVERHAUL ACTIVITIES, DRY BOILER CLEANING
STARTED.
• QUICK ERECT SCAFFOLDING IS BEING USED FOR BOILER
INTERNAL CLEANING & INSPECTION
• HIGH PRESSURE WATER JET CLEANING IS BEING DONE
FOR BOILER TUBES
• ALL PA FANS & MILL MOTORS VIBRATION MEASUREMENT
ALSO STARTED DURING UNIT OVERHAULS
• ALL HT MOTORS TRIAL RUN IS BEING TAKEN FOR 8 HRS
AND LT MOTORS FOR 4 HRS
NTPC/VINDHYACHAL
PROCESS IMPROVEMENTS
ADDITIONAL RESPONSIBILITIES
CONSTRAINTS
• UNIT OVERHAUL REPORTS: INSPITEOF ALL BEST POSSIBLE
EFFORTS, PROBLEM IS BEING FACED TO GET THE FEEDBACK
FROM OTHER DEPARTMENTS FOR THE JOBS COMPLETED,
MEASUREMENTS TAKEN AND EXPENDITURE INCURRED
DURING UNIT OVERHAULS, WHICHCAUSES DELAY IN
COMPILATION OF UNIT OVERHAUL REPORTS.
THANK YOU