Documente Academic
Documente Profesional
Documente Cultură
Fire-fighting Design
Requirements
Wed 15 June 2016
Q&A Discussion
Ben Wilson
Senior Water Master Planner
Triggers
• New Development
• Utility Infrastructure Design Projects
Who
• Development: Endorsed Consultant(s) engaged by Developer/Builder
Scope
Operational Customer Service Standard: “Minimum flow or pressure at the
connection to the customer’s property”
Triggers
• General Water Operations eg.
» Zoning/Boundary Valve Selection
» Pump/Control Valve Pressure Setpoints etc.
• Service Pressure/Flow Inquiries or Complaints
» Less than 0.42 L/s Service Pipe / Standpipe; or
» Less than 210 kPa static @ Connection Point (General Urban)
Who
• QUU Operations
Recommendations
1. Default Water Supply = Tank(s) + Pump(s)
2. Delete Pump(s) only if Town Main Connection Min pressure calculated and
verified as > Min On-Site Required Pressures
3. Seek advice from Water Agency for Min Available Mains Residual Pressure
4. Consider Project Infrastructure Solution Options to secure compliant Supply
(ie. Connection Residual Pressure)
Recommendations
1. Seek Pressure/Flow Advice from Water Agency, noting:
• Availability/Reliability of Hydraulic Modelling
• Advice Services on Offer
• Limitations of Advice
QUU reference TEM142
© 2016 Queensland Urban Utilities
© 2012 Queensland Urban Utilities 13
Town Mains
Hourly Pressure Variations
Sandgate Network Background Pressures
Feb-Mar 2011
450
420
Pressure (kPa)
410
Before work:
400 Showering demand = lower pressures
Weekend = Get up later: 3:30 - 4:15 pm
Showering times later/more variable Watering Gardens!
390
High load on network =
lower pressures
380
370
0:00
0:45
1:30
2:15
3:00
3:45
4:30
5:15
6:00
6:45
7:30
8:15
9:00
9:45
10:30
11:15
12:00
12:45
13:30
14:15
15:00
15:45
16:30
17:15
18:00
18:45
19:30
20:15
21:00
21:45
22:30
23:15
Time of Day
800
700
650
600
95th percentile: 8 years
~600 kPa Network designed to operate at
minimum: 560 kPa
550
1/01/2003
8/09/2003
15/05/2004
20/01/2005
27/09/2005
4/06/2006
9/02/2007
17/10/2007
23/06/2008
28/02/2009
5/11/2009
13/07/2010
QUU reference TEM142
© 2016 Queensland Urban Utilities
© 2012 Queensland Urban Utilities 15
Town Main – Field Pressure Tests
Raw Mains Test Pressures: Do Not use as Design Pressures!
• Not referenced by AS2419.1 as Design Pressure Calc Method
• AS2419.1: Design Pressure = Minimum Pressure (95th percentile)
» Raw field test pressures are greater than minimums, often
significantly more
• AS2419.1 recognises that water mains pressures Vary with time:
• Raw field test pressures vary depending on hour, day, month or
year of measurement
• AS2419.1 Clause 2.3.3: Select “Most Appropriate” method:
a) Water Agency Hydraulic Modelling (95th percentile). Preferred by AS2419.1
b) Water Agency Pressure Records (95th percentile) + Extra Calculated Losses
c) System Reference Point (95th percentile) + Extra Calculated Losses to
Connection
d) Testing Method Approved by Water Agency
Recommendations
1. Default to Water Agency Hydraulic Modelling as most reliable for 95th percentile
2. Verify Modelled Pressure Drops with Field Testing Pressure Drop Measurements
3. If Field Test Pressure Drop > Modelled: Conservative Approach – Adjust Modelled
Pressure
QUU reference TEM142 Drop by Field Measured Pressure Drop (See©similar © AS2419.1-Cl
2016 Queensland F3.1)
Urban Utilities
2012 Queensland Urban Utilities 16
Additional Hydraulic Losses
Pressure/Flow @ Building Hydrants does not equal Mains Pressure/Flow!
• Additional Losses: Hydraulic Engineering-Published Formulae
» Darcy-Weisbach / Hazen-Williams Equations
» AS2200-2006 Design Charts for Water Supply and Sewerage
Hydraul𝐢𝐢𝐢𝐢 Friction Loss𝐞𝐞𝐞𝐞 (𝐤𝐤𝐤𝐤𝐤𝐤)
Pipe Friction Factor × Pipe Length × Fluid Velocity 2
=�
Pipe Internal Diameter × 2
Fitting k Factors × Fluid Velocity 2
+ �
2
AS2419.1 – References
Cl 2.2.1: “Hydraulic Analysis of Fire Hydrant Systems shall be carried out to
demonstrate that, when the specified number of fire hydrants are
discharging…the residual pressure at each fire hydrant is within a range
suitable…”
Water is Heavy!
• Lower Mains/Pipes/Hydrants have Higher Pressure (More water column weight)
• Higher Mains/Pipes/Hydrants have Lower Pressure
Two Approaches
1. Hydraulic Grade Line
PressurePoint A = 9.8 x (Hydraulic Head – ElevationPoint A)
P=?
PG = 300 kPa Static Q = 0 L/s
Elev Diff = 10m P=
300kPa – 9.8x(65-55) =
H1 Elev = 55 mAHD 202 kPa Static!
Clause 8.5.1: “The nominal size of a fire main shall comply with the
requirements for pressure, flow and velocity as further specified in Section
2…”
Recommendations
1. DN150 mm is recommended default for 20L/s
2. Adjust pipe sizes by full hydraulic analysis
Recommendations
QUU does not recommend building attack hydrants use unassisted town
mains pressure for compliance
a) Unreliable design performance and ongoing compliance
b) Town mains designed to supply domestic pressures and provide
access points (street hydrants) to Qld Fire Service as water source for
fire service appliance (“BRT”) onboard pumps
c) Town mains not designed/operated to supply pressure direct to Fire
Service attack hose branch nozzles. This is role of Fire Appliance
Pump / Booster Assembly / Building High Pressure Pump(s)
QUU reference TEM142
© 2016 Queensland Urban Utilities
© 2012 Queensland Urban Utilities 25
Field Testing Usage
Design Pressure Verification
Verification of Town Mains Design Pressure Calculations
• Absolute Pressure Readings should be > Calculated/Modelled Design Pressures
» But must compare at same System Reference Points!
– Apply Additional Hydraulic Loss + Elevation Correction Calculations to
align Field PG location with Design Pressure SRP
» Calculated/Modelled = 95th percentile Design Pressure
» Field Pressure Readings expect much greater than 95th percentile
• Verify Relative Pressure Drops vs Modelled Pressure Drops
» But must compare at same System Reference Points!
– Apply Additional Hydraulic Loss + Elevation Correction Calculations to
align Field PG location with Design Pressure SRP
Measure
Booster Flow Here
Assembly
H1
Recommendations
1. Establishing compliant Water Supply key to entire Design
2. High Risk = High Due Diligence Requirements
QUU reference TEM142
© 2016 Queensland Urban Utilities
© 2012 Queensland Urban Utilities 30
Common Design Issues
Hydraulically Risky Water Supply Design Methodologies
• Non-compliant / Miscalculated Town Mains Design Flow/Pressure
» Eg. Single-point-in-time Field Test
• Field Test Methodology and Result Usage
» Design of Test not optimized. For Example
– Test Points in different street(s) from connection
– Test Points on ring main when connection on branch main
– Insufficient Flow/Pressure Test Point installation Eg. Fire systems
drawing from End of cul-de-sacs/main dead-ends
» Raw Test Results not corrected for:
– Additional Pipe Lengths/Losses to Connection Point
– Elevation Pressure Corrections
– Ambient Condition Influences Eg. Temporary/Short-Term Utility
Network Configurations
DN100 CICL
ID= 92 mm
(Pre1945) ID= 110 mm
ID~ 40-90 mm
Recommendations
1. Connections fed by Cast Iron Mains do not reliably achieve 20 L/s
2. Make design allowances for On-Site Storage,©or
QUU reference TEM142
2016Infrastructure
Queensland Solution
Urban Utilities
© 2012 Queensland Urban Utilities 33
Common Design Issues
Project Management / Building Design Issues
Connection Civil Designer vs Building Hydraulics Consultant
• Hydraulic Consultant engaged late in Building Design process
• Insufficient Building Hydraulic Design Specifications @ Time of Connection
Design
• Unclear Project Responsibilities for achieving Fire System Design Compliance
» Who? Doing what?
• Time/cost penalty risks of non-compliant Fire System design not identified
» Identify need to install Fire Tank or Fire Pump to Building after been built and no
allowance in Building Plans / Project Costs?
» Pre-Design / Design Due-Diligence processes not carried out
» Pre-Commissioning / Design testing left too late eg. 1-2 weeks before handover
Water Approvals
• If recommended/adopted solution identifies additional infrastructure
required
» Submit (revised) connection design/application to QUU
Development Services
Toby Turner
Development Services Senior Engineer
Note on fire systems Queensland Urban Utilities does not guarantee minimum flow or pressure to private fire-fighting systems
reliant on Queensland (or meet private fire-fighting requirements).
Urban Utilities’ Town Mains
and fire system design Our Customer Service Standards for water supply commit to a minimum of 210 kPa static pressure, and
a minimum flow rate of 25 litres per minute, at the connection to each serviced property. While the
available flow and pressure in the majority of Queensland Urban Utilities’ water supply network
significantly exceeds our minimum Customer Service Standards, the additional capacity is
circumstantial and not guaranteed in the same way.
Due to changing operational circumstances, the available flow and pressure in town mains may vary
over time. Hydraulic designers are advised to make suitable provision during the design process
(acknowledging that the hydraulic performance of town mains may change over time) to ensure that
private fire systems are compliant with applicable standards.
Request For Information If this development is reliant on a private fire-fighting system, please confirm (in writing) that either:
a) the internal hydraulic design will be completed at a later date, and will incorporate the
limitations of the water supply network; or
b) field investigations into the water supply network have been undertaken, and any hydraulic
design assumptions relating to the private fire-fighting system have been validated.
It is the responsibility of the applicant to review this request and provide a response that
acknowledges the risks associated with reliance on Queensland Urban Utilities’ water supply
infrastructure
• If the fire system fails QFES testing, the developer should speak directly
with their hydraulic consultant.