Sunteți pe pagina 1din 1

Project Description : Proposed 6300 P/P Cold Storage Facility

PROJECT SCHEDULE
Client : E&L Faster Foods Imports Inc.
Location : Antipolo City
Month JANUARY FEBRUARY MARCH APRIL MAY JUNE JULY
P.O. No. :
Date Approved : Week No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Inclusive
1-4 5-11 12-18 19-25 26-1 2-8 9-15 16-22 23-29 1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-2 3-9 10-16 17-23 24-30 31-6 7-13 14-20 21-27 28-4 5-11 12-18 19-25 26-1
Items PARTICULARS Dates
I. Imported Portion Lead Time
1.0 Bitzer Germany Air Cooled Condensing Units 12 Weeks
2.0 Thermofin Germany Unit Coolers 12 Weeks
II. Local Portion
A. Components and Local Materials
1.0 Valves and Controls "Danfoss" 9 Weeks
2.0 Refrigerant R134a 6 Weeks
2.0 Compressor Oil 6 Weeks
3.0 Copper Pipes and Fittings 5 Weeks
4.0 Hangers and Supports 5 Weeks
5.0 PU Insulation & Aluminum Cladding GA 24 5 Weeks
6.0 Electrical Wires & Miscellaneous Materials 5 Weeks
7.0 Unit Cooler Panel Board 10 Weeks
8.0 A/C Drain Lines 3 Weeks
9.0 Consumables, Tools and PPE 1 Week
10.0 Temperature Gauges 10 Weeks
B. Mechanical
1.0 Installation of Hangers and Supports 3 Weeks
2.0 Installation of Air Coolers 1 Week
3.0 Installation of Condensing Units 2 Weeks
4.0 Installation of Copper Piping 7 Weeks
5.0 Installation of Valves 1 Week
6.0 Pressure and Leak Test 2 Weeks
8.0 Insulation and Cladding of Copper Piping 5 Weeks
9.0 Drain Piping Layout 2 Weeks
C. Electrical
1.0 Installation of Electrical Supports 2 Weeks
2.0 MCC Installation 1 Week
3.0 PVC and Pull Box Layout 2 Weeks
4.0 Cables and Wires Layout 3 Weeks
5.0 Termination(Refrigeration System) 1 Week
6.0 Megger Testing 1 Week
7.0 Test Rotation 1 Week
D. Commissioning
1.0 Refrigerant and Oil Charging 1 Week
2.0 Start-up and Temperature Pull Down 3 Weeks
3.0 Turn-over

S-ar putea să vă placă și