MATERIALS REVIEWER NOTES

1. Scales for weighing aggregates and cement shall be accurate within ____ % throughout
the range of use. Scales shall be inspected and sealed as often as the Engineer may deem necessary to
assure their continued accuracy.
a) 1.0 % c) 0.5 %
b) 1.5 % d) 2.0 %

2. When cement is placed in contact with the aggregate, batches may be rejected unless mixed within
_____ hours of such contact.
a) 1.5 hours c) 0.5 hours
b) 2.0 hours d) 2.5 hours

3. When mixed at the site or in a central mixing plant, the mixing time shall not be less than ______ nor
more than ____ unless mixer performance test prove adequate mixing of concrete in a shorter time
period.
a) 30 seconds nor more than 90 seconds
b) 50 seconds nor more than 90 seconds
c) 60 seconds nor more than 120 seconds
d) 90 seconds nor more than 120 seconds

4. The flow of water shall be uniform and all water should be in the drum by the end of the first ____
seconds of the mixing period.
a) 45 seconds c) 15 seconds
b) 30 seconds d) 20 seconds

5. Concrete not place within ____ minutes from the time the ingredients were charged into the mixing
drum shall be used.
a) 120 minutes c) 60 minutes
b) 150 minutes d) 90 minutes

6.When concrete is delivered in truck mixers, additional water may beaded to the batch and additional
mixing performed to increase the slump to meet the specified requirement if permitted by the Engineer,
provided all these operation are performed within ____ after the initial mixing operation and the water and
cement ratio is not exceeded.
a) 30 minutes c) 45 minutes
b) 15 minutes d) 60 minutes

7. A sample from a bituminous mix weighs 1000 grams. At extraction, it was found out that the dry
aggregate weighed 950grams. What is the % of asphalt by weight of mix?
a) 5.2 % c) 5.4 %
b) 5.0 % d) 4.8%

8. The minimum penetration of the preservative with the surface of the timber piles shall be ____
a) 150 mm c) 250 mm
b)200 mm
d) 100 mm
9. The contractor shall submit in writing a job-mix formula for the mixture supported by laboratory test
data along with samples of resources of components and viscosity – temperature relationships to the
Engineer for testing and approval at least ____.
a) two weeks c) one week
b) three weeks d) four weeks

10. The concrete samples should be stored in a moist conditioned temperature within the range of ____
until the time of test.
a)18* C to 24* C c) 14* C to 24* C
b) 15* C to 18* C d) 18* C to 28* C
11. This is used in soil stabilized road surface due to its high ____ property, that is, it absorb and retain
water.
a) Potassium Chloride c) Magnesium Chloride
b) Calcium Chloride d) Sodium Chloride

12. The mass % wear of soil aggregate used in cement/lime proportions should not be more than ____ .1
-
a) 40 % c) 45 %
b) 50 % d) 55 %

13. The uniform rate at which the movable head of the CBR machine travel is _____ .
a) 0.05 in/ min c) 0.08 in /min
b) 0.10 in /min d) 0.09 in /min

14. Cast in place concrete shall not be post – tensioned until at least ____ and until the compressive
strength has reached the strength specified.
a) 7 days c) 14 days
b) 10 days d) 20 days

15. The penetration test is an indication of the ____ of asphalt.


a) Consistency c) Hardness
b) Softness d) Flash Point

16. Specification requires one (1) Quality test for every ____ of asphalt
a) 20 tons c) 50 tons
b) 200 tons d) 40 tons

17. The ____ is the most commonly used method in the design and evaluation of bituminous concrete
mixes.
a) Job mix formula c) Marshall Stability
b) Design mix d) Extraction

18. Vibration shall operate a frequency of 8,300 to 9,600 impulses per minute under load at a maximum
spacing of ____ cm.
a) 30 cm c) 60 cm
b) 50 cm d) 40 cm

19. The specific gravity of Sodium Sulfate used in soundness test for aggregate should be within the
range of ____.
a)1.151 to 1.174 c) 1.051 to 1.154
b) 1.250 to 1.178 d) 1.058 to 1.184

20. The specific gravity magnesium sulfate solution used in soundness test for aggregate should be
within the range of ____ .
a) 1.280 to 1.408 c) 1.295 to 1.308
b) 1.180 to 1.308 d) 1.195 to 1.318

21. Aggregate accounts for 92 – 95 % of the weight of the bituminous mixture asphalt accounts for 5 – 8
% of the weight of the mix. The exact percentage to be used is determined by the _____
a) Trial mix c) Job mix
b) Design mix d) Job order

22. _____ is an indication that the asphalt mix is overheated.


a) Blue smoke c) Rising steam
b) Stiff appearance d) Mix slumps in truck
23. In checking the temperature of the mix, the thermometer should be inserted into the mix at least ____.
a) 2 inches c) 4 inches
b) 6 inches d) 6.0 mm

24. _____ is applied on existing bit, or cement concrete surface with bituminous materials.
a) Bituminous Prime Coat c) Bituminous Seal Coat
b) Bituminous Tack Coat d) Bituminous Surface Treatment

25. The solution used in the soundness test of aggregate shall be cooled to a temperature of
21 +or – 1* C and maintain at that temperature for at least _____.
a) 24 hours c) 48 hours
b) 36 hours d)18 hours

26.Proper compaction of the fill materials is very important, as it will ______.


a) Increase the shear strength
b) Decrease permeability
c) Minimize compressibility
d) All of the above

27.In which DPWH item is emulsified asphalt not suitable?


a) Item 301 c) Item 304
b) Item302 d) Item 308

28.Unconfined compressive strength test is usually performed on______.


a) Sandy soils c)Organic soils
b) Silty soils d) Clayey soils

29. Consolidation test is usually performed on ____ samples


a) Disturbed c) Consolidated
b) Undisturbed d) both a & b

30. A concrete core sample having a maximum height of less than_____ of its diameter before capping or
height less than its diameter after capping shall not be tested.
a) 93 % c) 95 %
b) 94 % d) 96 %

31. The cohesion and internal friction of soil is tested by


a) Tri axial shear test c) Bearing test
b) Direct shear test d) All of the above

32. In concrete acceptance, core will be considered adequate if the average strength of the cores is equal
to what?
a) 80% of specified strength & if no single core is less than 75% of specified strength
b) 90% of specified strength & if no single core is lessthan 80% of specified strength
c) 85% of specified strength& if no single core is less than 75% of specified strength

33. Before the cement is to be used, sampling must be done at least _____ before use.
a) one week c) two weeks
b) 14 days d) 12 days

34. Asphalt cement shall not be used while it is foaming nor shall be heated at ____ at anytime after
delivery.
a) 107* c) 120*
b) 159*
35. Moisture content of aggregate in bit mix shall not exceed ____ of the time it is introduce into the
mixing unit.
a) 1.5 mass % c) 1 mass %
b) 2.0 mass %

36. Batching tolerance for Sand and Aggregate is ____.


a) 1 % c) 3 %
b) 2 %

37. Between stage of curing, concrete shall not be exposed for more than how many hours?
a) 24 hours c)½ hour
b) 3 hours d) 72 hours

38. As a Materials Engineer, what will you do with major honeycombed area that is considered as
defective work?
a) Plaster
b) Payment of the concrete will be made an adjustment
c) Removed and replaced at the expensed of the contractor

39.If the strength of control specimen does not meet the requirement and not feasible to obtain cores due
to structural consideration, as a Materials Engineer what will be your decision?
a) Removed and replaced
b) Area will not be paid
c) Payment will be made at an adjusted price

40. After concrete has been placed, it is advisable to maintain fully welted and in position for how many
hours?
a) 14 hours c)72 hours
b) 24 hours d) 15 – 18 hours

41. Rock shall be excavated to a depth ____ below sub grade within the limit of the roadbed
a) 100mm c) 200 mm
b) 150 mm

42. Minimum penetration of all piles shall be ____.


a) 3 meter c) 7 meter
b) 6 meter d) 4.5 meter

43. Piles shall not be driven within 7 meters of concrete less than _____ old.
a) 7 days c) 28 days
b) 14 day

44. Paint contains _____ of pigment and _____ vehicle.


a) 20 % & 80 % c) 79 % & 21 %
b) 21 % & 79 % d) 80 % & 20 %

45. Minimum thickness of bedding materials beneath the pipe is _____.


a) 100 mm c) 200 mm
b) 150 mm

46. Tolerance of gabion dimension is _________________.


a) +/- 1% c) +/- 3 %
b) +/- 2 % d) +/- 4 %
47. Minimum size of galvanized wire mesh is ____________.
a) 2.0 mm c) 2.7 mm
b)2.2 mm d) 3.4 mm

48. Minimum density of gabions is ___________.


a) 1,000 kg/cu. M c)1,400 kg/cu. m
b) 1,200 kg/cu. m d) 1,500 kg/cu. m

49. Soundness loss of field gabions is __________________.


a) 9 % after 5 cycles c) 11 % after 5 cycles
b) 10 % after 5 cycles d) 12 % after 5 cycles

50. The heating temperature of reflectorized thermoplastic material during application is _____
a) 130 +/- 7* C c) 200 +/- 7* C
b) 150 +/- 7* C d) 211 +/- 7* C

51. Submission of sample minimum quantity of material for asphalt cement is -------.
a) 5 kg c) 20 kg
b) 10 kg d) 100 kg

52. For how many years does the small Contractor given to procure necessary testing equipment?
a) 2 years c) 5 years
b) 4 years d) 6 years

53. The depth of the weakened joints must not be less than ____ and a width of___.
a) 40 mm & 6 mm c) 40 mm & 5 mm
b) 50 mm & 5 mm d) 50 mm & 6 mm
54. Used of bituminous cold mix for potholes patching during rainy/wet period is acceptable
a) False b) true

55. In soil, all boring shall be carried to a depth of at least ____ below the proposed grade line.
a) 0.50m c) 1.5 m
b) 1.0 m d) 1.8 m

56. The test that determines pile bearing capacity by loading one or more pile and measuring settlement
under load is _____.
a) Vane shear test c) Pile load test
b) Plate bearing test

57. The weight of disturbed samples from hard auger or split spoon shall be at least ____.
a) 1 kg c) 10 kg
b) 20 kg d) 100 kg

58. Submission of sample for testing for cement is _____.


a) 10 kg c) 15 kg
b) 20 kg d) 40 kg

59. The length of Shelby Tube of an undisturbed sample is _____.


a) 10” long c) 20” long
b) 18” long

60. For small project where quantity of steel bars is 10,000 kg or less, what is the basis for acceptance of
material?
a) No testing c) Mill certificate
b) P.E, certificate
61.______ determines the best combination of the material that will produce a potentially stable & durable
mixture.
a) Job mix formula c) Design of bituminous mix
b) Marshall formula

62. _______ is the rate of loading for concrete cylinder sample subject to compression test
a) 20 - 40 psi/sec c) 15 – 40psi/sec
B)20 - 50psi/sec d) 15 – 40 psi/sec

63.I n a soil exploration, if the characteristic of rock is questionable, the minimum depth of boring into the
bedrock should be _______.
a) 1.5 m c) 2.5 m
b) 2.0 m d)3.0 m

64. Determine soil bearing capacity by loading a steel plate usually 30” diameter.
a) Vane shear test c) Pile load test
b) Plate bearing test d) None of the above

65. How many hours do aggregate stockpile or binned for draining before being batch?
a) 1 hour c)12 hours
b) 6 hours d) 24 hours

66. What is the relative strength of mortar at 7 & 28 days of fine aggregates, when tested for the effect of
organic impurities, which is higher than the standard?
a) not less than 90 % c) not less than 95 %
b) not less than 80 % d) not less than 98 %

67. What is the rate of loading for concrete beam tested for flexural stress?
a) 110 – 150 psi/sec c)125 – 175 psi/sec
b) 115 – 150 psi/sec d) 130 - 175 psi/sec

68.In concrete sampling paste shall be of normal consistency of _____ when the rod settles to a point
below the original surface in 30 secs.
a) 10 +/- 1 mm c) 15 +/- 1mm
b) 11 +/- 1 mm d) 20 +/- 1 mm

69.What the temperature of a concrete sample?


a) 10 – 15 * C c) 15 – 18* C
b)18 – 24 * C

70.What is the wash loss of fine aggregates in the no. 200 sieve?
a) 1 % c) 3 %
b) 2 % d) 4 %

71. Retarder can delay the setting time of concrete up to how many hours?
a) 1 hour c) 4 hours
b) 2 hours d) 8 hours

72. Super plasticizer can increase the strength of concrete up to how many percent?
a) 40 –60 % c) 50 – 70 %
b) 50 – 60 % d) 60 – 70 %

73.___________ is the moisture in an air – dried soil


a) Moisture Content
b) Natural Moisture Content
c) Hygroscopic Moisture Content
d) Hydrometer Moisture Content

74._________ is the tolerance of mix in bituminous.


a) 10* C c) 15* C
b) 12* C d) 18* C

75._________ Number of measurement taken in a core sample for thickness determination of the finish
asphalt pavement
a) 3 c) 5
b) 4 d) 8

76. In the absence of beam mold in site, cylinder mold is allowed by specification. What is the required
strength?
a) 2,500 psi c) 3500psi
b) 3,000 psi d) 4,000 psi

77. Prime coat shall be left undisturbed for at least _____


a) 6 hours c) 24 hours
b) 12 hours

78. The first phase of rolling the spread bituminous mix is called breakdown rolling which is carried out by
pneumatic roller, temperature requirement must be _____.
a) 200 – 225* F c) 160 – 180* F
b) 190 – 199* F d)150 – 185* F

79. How many gradation ranges for hot plant mix bituminous pavement are there in the blue book?
a) 5 c) 7
b) 6 d) 8

80. What is the plasticity index of mineral filler?


a)not greater than 4 c) not greater than 8
b) not greater than 6 d) zero

81. If no core had been taken at the end of each day of operation and the project has already been
completed, a core shall be taken ________.
a)for every 75 l.m,/lane c) for every 100 l.m/lane
b) for every 150 l.m/lane d) for every 1,000 l.m/lane

82. ________ is the slump of workable concrete if vibrated.


a) 10 – 20 mm c) 40 – 50 mm
b) 10 – 40 mm d) 40 – 75 mm

83.________ Burnt product which is used by Gypsum and pulverized to form Portland cement.
a) Hydraulic cement c) Fly Ash
b) Clinker d) Volcanic Ash

84. When group index = 0, what is the grade of soil?


a) Weak soil c) good soil
b) Poor soil
85.______ is a process of breaking down of rocks into small pieces of various sizes that can range from
large boulders to very small clay particles.
a) Consolidation c) Weathering
b) Unconsolidation

86.________ is the limit were further loss of water due to evaporation which will not result in reduction of
volume.
a) Plastic limit c) Shrinkage limit
b) Liquid limit

87.________ a classification of soil which 35% or less the particles pass through no. 200 sieve.
a) Grain size soil c) Silty clay materials
b) Granular materials d) clayey materials

88.________ a classification of soil which 35% or more of the particles pass through no. 200 sieve
a) Course Sand Soil c) Silty-Clay Materials
b) Granular Materials d) Clayey Materials

89.It evaluate the quality of soil as highway subgrade material.


a) Atterberg Limit c) Group Index
b) Plasticity Index d) Liquid Limit

90.When soil has plasticity index value of 10, what is the criteria of the material?
a) Coarse grain c) Clayey
b) Sandy d) Silty

91. When plasticity index is equal


a) Coarse grain c) Clayey
b) Sandy d) Silty

92. _______ is an empirical number used in evaluation for G.I.


a) 0 – 15 c)0 – 20
b) 5 – 20 d) 0 – 25

93.It indicates good subbase materials when G.I. is equal to _____.


a) 0 c) 10
b) 5 d) 20

94.It indicates very poor subbase materials when G.I. is equal to _____.
a) 0 c) 10
b) 5 d)20

95. ______ indicates the composition of soil.


a)Atterberg Limit
b) Plasticity Index

96.The higher the value of PI of the soil, the weaker will be the soil performance as a _____.
a) True c) Depend
b) False d) None of the above

97. _______ the Plasticity Index of group of soil


a) 0 c)10
b) 6 d) 11

98. _______ is the minimum percent of A-6 group classification of soil.


a) 0 % c) 35 %
b) 25 % d) 36 %

99. _______ is the maximum of G.I. of Silty Clay Materials


a) 0 c)20
b) 25 d) 35

100. When the value of G.I. is negative, what will be the soil performance?
a) Poor Subgrade c) Good subgrade
b) Very good subgrade d) None of the above