Detailed Estimate
Construction of Kadavu and Protection works to the Right bank of Chalakudy river near
Vathakkattukulangara temple at Chenathunadu in Chalakudy municipality.
(Cost Index Applied for this estimate is 37.25%)
1 Detailed estimate
1 60.1.2
RING BUND Type II Putting up ring bund with earth fille gunny bags of top width 1.0m bottom width 2.0m
height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof
till the completion of the work and clearing the site by dismantling the bund after completion of the
work.etc.complete.
Ring bund
2 60.2.2
Irrigation
Bailing out water Using 5HP Pump- Bailing out water with 5HP engine and pump set including
PRICE
conveyance to site and erection,cost of fuel, lubrication oil and other stores, pay of staff etc complete
25 5.000
Bailing out
125.000
25 days 5
hrs / day
3 2.6.1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas
(exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated
earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of
soil
Earthwork
b)For Kadavu(from
bottom to top)-Earth 1.42-
1 13.400 4.000 1.420 76.112
removing infront of Average
kadavu
3.58-
1 0.800 4.000 3.580 11.457
Average
3.33-
1 3.100 4.000 3.330 41.292
Average
3.90-
1 0.500 4.000 3.900 7.800
Average
3.77-
1 0.400 4.000 3.770 6.032
Average
2.97-
1 3.200 4.000 2.970 38.017
Average
2.17-
1 0.400 4.000 2.170 3.472
Average
1.47-
1 2.800 4.000 1.470 16.464
Average
1.00-
1 0.600 4.000 1.000 2.400
Irrigation Average
PRICE
Total Quantity 925.506 cum
4 60.7.1
DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality
blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials
labour charges etc. complete as per direction of Departmental officers at site
DR masonry
(1.360+0.5 (2.42+2.69
Super structure 1 150.00 366.004
5)/2 )/2
b)For Kadavu(From
1 0.800 4.000 1.000 3.200
bottom to top)
(0.60+0.40
1 4.000 0.600 1.200
)/2
(0.60+0.40
1 4.000 0.600 1.200
)/2
5 od1969/2018_2019/IA
Random rubble masonry in cement mortar 1:8 for top belt of retaining wall including simultaneous
pointing to the exposed faces of masonry, labour charges, cost and conveyance of materials,
etc.complete as per the direction of departmental officers at site.<br>
RR masonry
For Kadavu-Parapet
wall(from bottom to 2 0.600 0.500 0.900 0.540
top)
2 Irrigation
3.580 0.500 0.900 3.222
PRICE
2 0.400 0.500 0.900 0.361
6 4.1.3
Providing and laying in position cement concrete of specified grade excluding the cost of centering and
shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size)
RCC
For Kadavu-(Steps
From bottom to top)- 1 3.000 0.800 0.100 0.241
Landing
7 4.1.5
Providing and laying in position cement concrete of specified grade excluding the cost of centering and
Irrigation
shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm
nominal size)
b)For Kadavu
PRICE1
2
150.00
0.600
(0.55+0.50
)/2
0.500
0.150
0.075
11.813
0.045
8 5.22.6
Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and
binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
Reinforcement
(150/0.3+1
Rings 501 1.250 0.39 244.238
)=501
from
Width wise-Landing 4 2.950 0.39 4.602 bottom to
top
Steps ( 4 nos/each
28 2.950 0.39 32.215
steps)
Steps ( 4 nos/each
28 2.950 0.39 32.215
steps)
Steps ( 4 nos/each
28 2.950 0.39 32.215
steps)
Landing 3
Irrigation
2.950 0.39 3.452
PRICE
1 13.97
Total Quantity
675.609 kilogram
0.000 kilogram
9 4.3.1
Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations,
footings, bases for columns
Form work
b)For Kadavu(From
bottom to top)- 1 3.000 0.100 0.301
Landing
TOTAL Rs 2250000.00
PRICE