MINUTES of SPECIAL MEETING No.6 - COVENT & GRT CEBU PROJECTS


11 October 2019, ABT Office Main Conference Room

PRESENT: ABDM Presiding Officer


FOD
FCC FGY
LPA IMA
PIR ABP
AMC BOS
CAP JAA PDB (Covent PMT)
RTA JCC (GRT Cebu PMT)
Action Due
Officer Date
The meeting was called to order at exactly 08:00 AM
Discussion for COVENT Project
1.1. Review of important figures – As of September 30 ABDM Info
Accomplishment 627,640
Cost ?
Site 469,661
HO ?
Profit
vs. Accomplishment 39,183
vs. Cost ?
Cash 666,823
DP 231,000
Collected Billing 355,885
Accounts Receivable 171,174
Retention 62,764
Balance till 17-April 142,360
Cost to Complete ?
 Come up with Cost from HO to fill out missing figures. LPA Info
 Come up with a comparative analysis from last reports in order to know if the PMT Info
presented prior projections are being met.
 Present on next meeting – Actual vs. Budget vs. Accomplishment PMT Info

1.2. FOD Meeting Agenda with RSL


(Prepare all needed documents for the following items) PMT Asap
 Time Extension
 Extended Prelims
 Deductions
 Reconciled
 Non-Reconciled
 Billing Registry
 Other Items & Complaints
 Hatch beams claims – Prepare summary of what happened
 Issued NCR for wire mesh of safety umbrella
 Issues with Mango Tree
 Issues with Zocalo for CHB

Page 1
2. Discussion for GRT Cebu Project
2.1. Management (Issues and Concerns)
2.1.1. RHBJ
 Resigned effective 10-October-2019.
 Has no plans of attending October 11 meeting at HO. ABDM Info
 Write a letter for replacement to advise the client. ABDM Info
 Company heads will go to Cebu on Monday to talk to the client regarding this ABDM Info
issue.
2.1.2. RTA
 Gave her word and assured that she will finish the project. RTA Info
2.1.3. IMA
 To finish requirements in Delimondo by the end of October – Certificate of IMA Info
Completion, Billing, and Retention.
 Will be transferred to GRT Cebu Project by the start of November.
2.1.4. COOP
 Current fund holder & signatory for checks – RHBJ; turnover to RTA due to RTA Info
resignation.
 LPA to come up with an organized system for the COOP funds, to be LPA Info
discussed further in Cebu.
2.1.5. Staff House
 In need of a bigger staff house; look for staff house near site. RTA, JCC Info

2.2. Tower 3 (Issues and Concerns)


2.2.1. Major Reworks
 Chipping Works
 One of the major issues.
 Every room with a difference varying from 0.5 to 2 inches.
 Can finish for one month (as per JDT). PMT Info
 6 chipping gun needed – 4 on-site, 2 additional. PIR, FCC Info
 Stairs
 3 stairs without finish.
 Teak Wood
 Floor sinks because during construction, carton was placed under under- PMT Info
sheathing.
 Stairs
 Rework – 3 stairs without finish. PMT Info
2.2.2. Accomplishment Report
 Reported 98% was based on billing; though most of the items that are RTA Info
already billed needs rework.
2.2.3. Roof Deck & Penthouse PMT Info
 Prioritize this item.
 All materials are delivered.
2.2.4. Site Engineers
 Request for site engineers for Tower 3. ABDM Info
2.2.5. Letter for Rework for Tiles at Balcony
 Damaged tiles were caused by railing works of subcon handled by ASEC.
 Report to ASEC, submit letter with attached pictures for rework caused by PMT Info
others for documentation in VOs.
2.2.6. Unit Turnover
Page 2
 Prioritize turnovers per floor, not per unit. PMT Info
2.2.7. Grand Land Work Takeovers
 Grand Land placed 2 groups on floors with small number of manpower for
repairs; supervised by ASEC.
 FODC being charged with poor workmanship for some of the items they
worked on; no document was signed regarding these takeovers.
 Record work items by others for documentation. PMT Info

2.3. Tower 4 (Issues and Concerns)


2.3.1. Project Status Report
 Accomplishment – Delay 5% equivalent to 55 days.
 Revise Cost Summary: For indirect cost, separate cost produced by tower 3 RTA Info
from tower 4.
2.3.2. Work Schedule Delays
 Due to work items (masonry, finishing, waterproofing, ceiling, STP) that PMT Info
started all at once.
2.3.3. Lack of Manpower
 Request for additional manpower for Tower 4 ceiling & masonry works. HO Info
 Look for subcons from Cebu or anywhere near Cebu. (masonry and ceiling
works) – To be discussed further during visit in Cebu.

As there are no other matters to discuss, the meeting was adjourned at 11:31 AM.