Documente Academic
Documente Profesional
Documente Cultură
FOR
WIRES AND CABLES INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1.SCOPE
This procedure to clear the method of the supply, installations of Wires
and Cables for the project.
This document details Wires and Cables Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Excavation:
No wiring be carried out until the appropriate tests required or in the
electrical testing section have been done and the consultant has
given his clearance for wiring to commence.
A loop in form of wiring shall be used as far as practicable or unless
otherwise indicated. Joints in conductors shall be made using
insulated terminal blocks complying with requirements of this
specification.
At expansion joints adequate slack shall be left in the cable.
Where Conduits are installed for wiring by others, a draw wire shall
be provided between each draw in position.
Where three-phase circuits comprising single-core cables are
installed in trunking, all cables of a shall be tied together at intervals
not exceeding 200mm.
Cables forming part of alarm, control, communication or monitoring
circuits shall have identification sleeves at their terminations.
Identification shall be consistent with the relevant wiring diagrams.
Pulling:
Make sure that all conduits and boxes in both ends are free from
damages and blockages etc and installation is approved.
Blockage shall be checked by inserting the draw wire and checking
that it reaches to the other end without any disturbance.
Once the conduit is not blocked the wires shall be pulled using the
draw wires while ensuring no damage occurs while pulling.
Pulling compound or lubricant shall be used for pulling the wires
where required.
Use soap based pulling compound for short runs i.e. less than 20
meters for semi conductive insulated wires.
Use wax based pulling compound for the runs greater than 20
meters for semi conductive insulated wires.
While pulling the wires care should be taken to not insert the pull
tension greater than the manufacturer allowed limits.
Termination::
Erect scaffolding where required as per the site requirements.
Cable rollers shall be placed under the cable during pulling over
longer distances and standoff rollers for acute bends, to ensure that
the cable is pulled with minimum effort and the cable outer jacket is
free of scouring lines.
The cable shall be pulled by using pulling means such as fish tape,
rope and basket weave wire/cable grips so as not to damage cable
or its containment system. Care will be taken to ensure that the
maximum pulling tension of all the cables is not exceeded at any
time.
Cable should be free of any static load i.e. to be places side by side
parallel on the cable tray or ladders. Any kind of dead weight on the
cable shall be avoided.
The cables shall be secured to the containment system using
approved cable ties for horizontal runs and cable cleats for vertical
runs.
Termination shall be done by using the approved termination
materials that include glands, lugs and other accessories part of
termination kit, by using proper crimping tools. Matching colour
gland sheaths shall be provided.
Commissioning:
Set the Meggar meter to 1000 volts DC for cables and 500 volts DC
for wires.
Take reading between phase, phase and neutral, phase and earth
neutral and earth.
Note that resistance reading must not exceed 2 megaohms(MΩ).
Check and record the resistance readings as per specification on
the approved insulation resistance test forms.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Wires and Cables Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Wires and Cables Installation will
be as follows:
Measuring tape
Cutting plier
Bending spring
Pipe Wrench
Drilling Machine
Crimping tool
Screw driver
Pulling spring
Hammer
Common tools
The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper