Documente Academic
Documente Profesional
Documente Cultură
Business and other permits required by Government of Cainta, Rizal lot 1 350,000.00 350,000.00 350,000.00
Development Permits-By Contractor lot 1 700,000.00 700,000.00 700,000.00
6 Temporary Power and Lighting lot 1 1,000,000.00 1,000,000.00 1,000,000.00
7 Temporary water supply lot 1 800,000.00 800,000.00 800,000.00
8 Survey and Stake-out lot 1 650,000.00 650,000.00 650,000.00
9 As-built drawing/progress reports & photographs lot 1 100,000.00 100,000.00 100,000.00
10 Traffic signs, barricade, steel plates, lights lot 1 650,000.00 650,000.00 650,000.00
11 Provision of security personnel lot 1 800,000.00 800,000.00 800,000.00
12 Others (Please specify) lot -
SUB-TOTAL I 11,650,000.00
II. SITE WORKS
SUB-TOTAL 5.2 -
X CATV
CONDUITS -including all accessories needed to complete the
10.1 -
systems
4R-110mm diameter PVC conduit lm - -
32mm dia. PVC homerun from service to unit owner lm - -
10.2 EARTHWORKS
Excavation cu.m. - -
Backfilling cu.m. - -
Concrete Encasement-ductline cu.m. - -
Hauling and disposal cu.m. - -
10.3 MANHOLE - including all accessories needed to complete the
systems such as: 20mmdia. pulling-in iron, end bell, cable rack
assemby, manhole cover and with sump pit
Manhole, 1.5m L x 1.5m W x 1.6m Depth set - -
Concrete Service Box 700mm x 600mm x 700mm Depth set - -
10.4 PEDESTAL AND PAD
Primary Pedestal set - -
Amplifier pad set - -
10.5 TESTING AND COMMISSIONING
Testing and Commissioning lot - -
10.6 OTHERS TO COMPLETE (Please specify)
Warning/Cautious Tape lot - -
Miscellaneous (specify) -
SUB-TOTAL X -