Sunteți pe pagina 1din 2

Domestic Gas Pipework

Part 2 - Installation and Testing

Copper tube and fittings be fitted before the meter is Installing tube in walls and floors
Copper tube to EN 1057 can be used disconnected, dust caps fitted, and the Typical methods of installing gas
for gas installations. It can be jointed using end of the pipework sealed. The existing piping in walls and floors are shown in
EN 1254 capillary or compression fittings. pipes should be purged out of service to Figure 3. Where copper tube is to be
According to BS 6891 compression remove fuel gas before using a blow buried in solid floors or walls, the number
fittings should only be used where they lamp. Any open ends of pipework must of joints should be kept to a minimum.
are readily accessible for tightening and be sealed before the work is left Ideally the tube should be run in a
inspection. This means that they cannot unattended. preformed duct with a suitable
be buried underground, buried in the
structure or used in ducts or under floors. Screed
Pipe in screed Pipe in brick or block wall
Corrosion
Jointing protected pipe
When using capillary fittings it is
important to visually examine every joint T
to ensure that the solder has run. The
flux used must only be corrosive during Gas pipe in chase in plastered wall
heating and any residue should be Maximum chase depth: T÷3 vertical pipes
Base concrete T÷6 horizontal pipes
removed after making the joint. Apply a
thin coating of flux to the outside of the Pipe behind plasterboard on dabs
cleaned tube only, not into the mouth of Pipe in ground
the fitting. Twist the tube as it is bearing slab Adhesive dabs
assembled into the cleaned fitting to Soft copper tube
spread the flux and then wipe off any in plastic sleeve
Gas pipe behind plasterboard
excess before completing the joint. Use
only EN 751 approved non-setting
jointing compound on threads or the Individual
thicker type of approved PTFE adhesive dabs
Insulation
tape wrapped with a 50% overlap,
as in Figure 2. Concrete slab

Pipe in precast Chipboard over


PTFE tape beam & block insulation Continuous dabs
Pipe laid in to surround pipe
insulation layer

Pipe behind plasterboard on battens


Full length
50% overlap Precast beam timber batten
Figure 2
& block

Pipe in raft Gas pipe behind plasterboard


Installation Chipboard over
During installation prevent dirt and insulation
Pipe in timber wall
water entering the tube by use of Pipe laid in
insulation layer Ply sheathing
adhesive tape over the ends. Remove
burrs left by tube cutters to minimise Vapour barrier
pressure drop due to turbulent flow.
Full length
If work has to be done on existing timber blocking piece
Timber studs
pipes already connected to a meter, a Figure 3 Gas pipe behind plasterboard
temporary earth continuity bond should
protective cover. Use plastic sheathed point. Slowly turn on the gas
copper laid on top of the base concrete and note the reading; this
and soundness test the installation piping should be 20mbar or a little
before wrapping any joints and covering above. If the pressure reading
with a suitable screed. is above 25mbar the meter
governor may be faulty and
Alternatively, pass plastic sheathed the gas supplier should be
soft coiled copper through a larger tube informed. The reading should
Solid or cavity wall
that has been previously set into the Flexible mastic then be checked with the
concrete.Try to run vertical pipes in walls appliances operating, this
in ducts, with access if possible, never gives the meter outlet
inside the cavity. If the wall is thick enough working pressure. If the
to provide proper cover the pipe can be pressure drop across the
run in a chase. If the pipe is to be installed meter and governor is
behind plasterboards, timber battens or greater than 1.25mbar there
continuous adhesive dabs should be used could be a problem, due
Sleeve
to surround the pipe. Cement mortar Tube perhaps to overloading the
meter or an inadequate or
Flexible mastic
Where tube is to be laid in timber partially blocked service pipe.
floors running across the joists, these Consider extending In any event the gas supplier
sleeve above floor in
should be notched or drilled to areas like kitchens should be informed.
accommodate the tube. Care should be
taken to mark floor boards so that fixing Checking the installation
nails and screws do not damage the piping for pressure drop
tube.Tubes installed parallel to the joists Once the meter outlet
should be properly supported. If tube Sleeve working pressure is known,
has to be installed in purpose-designed Solid Floor Figure 4
ducts, these must be sealed to prevent the installation pipework can
the passage of gas into the wall cavity. If person before the meter is connected. If be checked for pressure drop. Attach a
the duct has a cross-sectional area of work is to be carried out on an existing manometer to the inlet pressure test
more than 10,000mm2 it should be installation it must be tested before point before the appliance governor and,
vented at high level to allow any escape starting and any faults traced and with the appliances lit, take a reading. If
of natural gas to dissipate into the rectified or the installation made safe. On this is more than 1mbar below the meter
rooms, and if possible cover the duct completion of the work a further test outlet working pressure, the pipework is
with a metal plate to minimise the risk must be carried out and if satisfactory either too small in diameter for its length,
from nail punctures. the installation purged into service. The or a section of piping may have been
testing and purging of domestic crushed or be partially blocked by debris.
Sleeves installations must be carried out in
Always sleeve the pipe where it accordance with BS 6891. Whatever the cause, the problem is
passes through solid walls or floors. Build within the installation. If the installation
the sleeve into the wall or floor and seal Dynamic performance testing gas pressure drop is satisfactory, and the
the gap between the gas pipe and sleeve installations burner pressure cannot be achieved,
with flexible fire-resistant compound at Note that once the gas piping then the problem lies within the
at least one end, as in Figure 4. installation is completed and the appliance, possibly in the appliance
installation has been tightness tested, governor.
Other services purged and brought into service the gas
Keep a gap of at least 25mm appliances must also be tested to make Brian Curry: March 2008.
between gas pipes and other services sure that they operate in accordance
and keep at least 150mm away from with the manufacturer’s instructions and
electricity meters and fuse boxes. Where the Gas Safety Regulations. In cases
electrical cross bonding is necessary, a where the correct burner pressure or
clamp is used to connect the protective gas rate cannot be achieved, taking
conductor near (ideally within 600mm) pressure readings at the meter and the
the outlet side of the meter in inlet pressure test points on the
accordance with BS 7671 Requirements appliances can identify the likely source
for Electrical Installations. of the problem.

Checking the service entry piping


Testing for soundness and meter installation for pressure
The Gas Safety Regulations require drop
that new installations be installed and Turn off all appliances and connect a
tested for gas tightness by a competent mano-meter to the meter outlet test

www.copperplumbing.org.uk

S-ar putea să vă placă și