Doc. No: MD-502-7000-CO-CO-MCC MCC Number:


MECHANICAL COMPLETION
-0021, D01
PROCEDURE

MECHANICAL COMPLETION CERTIFICATE

System Number: Sub-System Number

S-05-01 TR FOR MAIN SUBSTATION

S-05-02 TR FOR SUBSTATION-1

System Process Description: S-05 UNIT (Steel structure TR in building)

It is hereby certified that the scope of work referenced has been inspected and / or tested and has achieved Mechanical Completion, in

accordance with the contract requirements, and is ready for commissioning. Any exception items, as per attached punch list(s), will be

completed as agreed upon by the undersigned. EMPLOYER’s acceptance does not relieve CONTRACTOR of any risk, liabilities or

obligations under the contract.

SCOPE OF ACCEPTANCE
Exceptions
Discipline Applicable Comments
(yes/no)*

Static Equipment No No

Rotating Equipment No No

Piping No No

Electrical No No

Instrumentation No No

Steel Structure Yes No

READY FOR COMMISSIONING ACCEPTANCE


CONTRACTOR
QA Manager Site Manager
Name H. D. Min Y. G. Choi
Sign
Date 20 February 2010 20 February 2010
EMPLOYER
PMC PMC PMC
PMC MPC
General Construction Commissioning
Project Manager Representative
Superintendent Director Manager
Name
Sign
Date
Note:* Yes requires an approved punch list attached with agreed with completion date and reinstatement plans

Doc. No: MD-502-7000-CO-CO-MCC-0021, D01 Page 1/1