Subrack Installation

Ericsson SPO 1410

QUICK GUIDE
Subrack Installation

Tools Required

TX 8
Crimping tool for cable lugs
Screwdriver Torx T 8 Used for: Uninsulated Cable Lug
Used for: 2 x M2,5 screws for subrack earth bonding
for fixing the cards
into the shelf Phillips
M2,5
Phillips Screwdriver
TX 10 Used for: Panel Screw 12-24 5/8 “
Screwdriver Torx T 10 for fixing the brackets to the rack
Used for: 8 x M3x4 screws
for fixing the brackets 2 mm
to the subrack
Slotted Screwdriver
M3x4
Used for: Shelf Earth Bonding
TX 20

Screwdriver Torx T 20
Used for: 1 x M4x10 screw 7 mm

for subrack earth bonding


Ratchet Wrench + hex. 7mm socket
M4x10 Used for: Shelf Earth Bonding
TX 30
1.8 Nm ±10%
Screwdriver Torx T 30 16 ft-lb ±10%
Used for: 4 x M6x16 screws
for fixing the brackets
to the rack
M6x16

2 | 2013-10-28
Subrack Installation

NTM 101 1854/1 - Kit Content Mount Brackets - NTM 101 1854/1
Left Bracket Rigth Bracket 1 Cable Lug

1 M4x10

8 M3x4

1 Washer

4 M6x16

4 M6 Captive Nuts

Note: in NTM 101 1854/1, there is no difference between left and rigth
bracket.

SCREW MRT ISO14583, M 3X4 D1=4


USE SCREWDRIVER TORX T 10

NTM 101 1854/3 - Kit Content Mount Brackets - NTM 101 1854/3
Left Bracket Rigth Bracket 1 Cable Lug

1 M4x10

8 M3x4

1 Washer

4 M6x16

4 M6 Captive Nuts

Note: in NTM 101 1854/3, left and rigth brackets are different.

SCREW MRT ISO14583, M 3X4 D1=4


USE SCREWDRIVER TORX T 10

| 2013-10-28 3
Subrack Installation

NTM 101 1854/4 - Kit Content Mount Brackets - NTM 101 1854/4
Left Bracket Rigth Bracket 1 Cable Lug

1 M4x10

8 M3x4

1 Washer

4 M6x16

4 M6 Captive Nuts

Note: in NTM 101 1854/4, left and rigth brackets are different.

SCREW MRT ISO14583, M 3X4 D1=4


USE SCREWDRIVER TORX T 10

NTM 101 1854/5 - Kit Content Mount Brackets - NTM 101 1854/5
Left Bracket Rigth Bracket
1 Shelf Earth Bonding

2 M4x10

8 M3x4

2 Washer

Panel Screw
4
12-24 5/8 inch

Note: in NTM 101 1854/5, left and rigth brackets are different.

SCREW MRT ISO14583, M 3X4 D1=4


USE SCREWDRIVER TORX T 10

4 | 2013-10-28
Subrack Installation

NTM 101 1854/7 - Kit Content Mount Brackets - NTM 101 1854/7
Left Bracket Rigth Bracket 1 Cable Lug

1 M4x10

8 M3x4

1 Washer

4 M6x16

4 M6 Captive Nuts

Note: in NTM 101 1854/7, there is no difference between left and rigth
bracket.

SCREW MRT ISO14583, M 3X4 D1=4


USE SCREWDRIVER TORX T 10

NTM 101 1853/1 - Kit Content Mount Brackets - NTM 101 1853/1
Top Bracket
1 Cable Lug

1 M4x10

8 M3x4

1 Washer

4 M6x16

4 M6 Captive Nuts
Bottom Bracket
SCREW MRT ISO14583, M 3X4 D1=4
Note: in NTM 101 1853/1, there is no difference between top and bottom USE SCREWDRIVER TORX T 10
bracket.

| 2013-10-28 5
Subrack Installation

NTM 101 1853/2 - Kit Content Mount Brackets - NTM 101 1853/2
Top Bracket SCREW MRT ISO14583, M 4X10 D1=2
8 M4x10
USE SCREWDRIVER TORX T 20

2 Left Bracket
8 Washer

2 Rigth Bracket
8 M6x16

M6
Bottom Bracket 8
Captive Nuts

Note: in NTM 101 1853/2, there is no difference between left and rigth
bracket, and between top and bottom bracket.

NTM 101 1853/3 - Kit Content Mount Brackets - NTM 101 1853/3
Top Bracket SCREW MRT ISO14583, M 4X10 D1=2
8 M4x10
USE SCREWDRIVER TORX T 20

2 Left Bracket
8 Washer

2 Rigth Bracket
8 M6x16

M6
8
Bottom Bracket Captive Nuts

Note: in NTM 101 1853/3, there is no difference between left and rigth
bracket, and between top and bottom bracket.

6 | 2013-10-28
Subrack Installation

NTM 101 1853/4 - Kit Content Mount Brackets - NTM 101 1853/4
Top Bracket
8 M4x10 SCREW MRT ISO14583, M 4X10 D1=2
USE SCREWDRIVER TORX T 20

2 Left Bracket
8 Washer

2 Rigth Bracket 8 M6x16

M6
8
Captive Nuts
Bottom Bracket
Note: in NTM 101 1853/4, there is no difference between left and rigth
bracket, and between top and bottom bracket.

NTM 101 1853/5 - Kit Content Mount Brackets - NTM 101 1853/5

Top Bracket SCREW MRT ISO14583, M 4X10 D1=2


USE SCREWDRIVER TORX T 20
Shelf
Top-rigth 1
Earth Bonding
Bracket
2 Left Bracket

10 M4x10

10 Washer

Panel Screw
Bottom Bracket Bottom-rigth 8 12-24 5/8 inch
Bracket

Note: in NTM 101 1853/5, there is no difference between top-left,


bottom-left, and bottom-right bracket, and between top and bottom
bracket. Top-rigth and bottom-right brackets are different.

| 2013-10-28 7
Subrack Installation

NTM 101 1853/6 - Kit Content Mount Brackets - NTM 101 1853/6

Top Bracket SCREW MRT ISO14583, M 4X10 D1=2


Shelf USE SCREWDRIVER TORX T 20
1
Earth Bonding
Top-rigth
Bracket
2 Left Bracket

10 M4x10

10 Washer

Bottom Bracket Panel Screw


Bottom-rigth 8 12-24 5/8 inch
Bracket

Note: in NTM 101 1853/6, there is no difference between top-left,


bottom-left, and bottom-right bracket, and between top and bottom
bracket. Top-rigth and bottom-right brackets are different.

NTM 101 1853/7 - Kit Content Mount Brackets - NTM 101 1853/7
Top Bracket SCREW MRT ISO14583, M 4X10 D1=2
8 M4x10
USE SCREWDRIVER TORX T 20

2 Left Bracket
8 Washer

2 Rigth Bracket
8 M6x16

M6
Bottom Bracket 8
Captive Nuts

Note: in NTM 101 1853/7, there is no difference between left and rigth
bracket, and between top and bottom bracket.

8 | 2013-10-28
Subrack Installation

NTM 101 1853/8 - Kit Content Mount Brackets - NTM 101 1853/8
SCREW MRT ISO14583, M 4X10 D1=2
Top Bracket USE SCREWDRIVER TORX T 20
8 M4x10

2 Left Bracket
8 Washer

2 Rigth Bracket
8 M6x16

M6
Bottom Bracket 8
Captive Nuts

Note: in NTM 101 1853/8, there is no difference between left and rigth
bracket, and between top and bottom bracket.

NTM 101 1674 - Kit Content (Desktop Mount Sets - NTM 101 1674 (Desktop
Installation) Installation)

5 Mounting Set

| 2013-10-28 9
Subrack Installation

Install Shelf Earth Bonding. Install Captive Nuts in Top and


Bottom Brackets.

Example of Installing Shelf Earth Bonding in NTM 101 1854/5

Mount Shelf with Brackets.

10 | 2013-10-28
Subrack Installation

Identify Where to Fix Shelf into Rack (MR55A-ETSI and BYB Racks).

56 2
53 1

1 Lower fixing point


2 Upper fixing point

Fixing points example

| 2013-10-28 11
Subrack Installation

Install Captive Nuts in Rack (Not Connect Earth Cable into ETSI Rack
Applicable to NEBS Racks) (Applicable Only to MR55AB and
MR55AD Racks).

Connect the “Ground Cable M4-Faston” in the


faston connector closest to the lower end cage nut.

12 | 2013-10-28
Subrack Installation

Install Shelf in ETSI Rack.

| 2013-10-28 13
Subrack Installation

Connect Lug to Earth Cable Coming from Connect Earth Cable to Right Bracket.
Exchange (Applicable Only to BYB Racks).
BYB racks have not any earth connector availble.
Earth cable comes directly from exchange and has to be connected to the rigth bracket.

Use Crimping Tool


Cable Lug to secure the cable to the lug

Screw M4x10

Earth Cable coming from exchenge

Example of Connecting Earth Cable in NTM 101 1854/1

Connect Earth Cable Coming from


Exchange to Shelf Earth Bonding.

Use slotted screwdriver

Example of Connecting Earth Cable in NTM 101 1854/5

14 | 2013-10-28
Subrack Installation

Slide Card into Shelf. Open Clips before Insert Card Completely into Shelf
Inserting Card Completely. by Closing Clips.

Screw Pressed Card into Shelf.

| 2013-10-28 15
Subrack Installation

© Ericsson AB 2013. All rights reserved. No part of this


document may be reproduced in any form without the written
permission of the copyright owner.

The contents of this document are subject to revision without


notice due to continued progress in methodology, design and
manufacturing. Ericsson shall have no liability for any error or
damage of any kind resulting from the use of this document.

Condensed information, for experienced users, based on


document Ericsson SPO 1400 - Installation Guide

1/1531-CSA 113 007/30 Uen.


Ericsson AB
SE-164 80 Stockholm
Sweden