Documente Academic
Documente Profesional
Documente Cultură
2
The Importance of Design Basis
• The design basis has tremendous impact on all aspects
of a project-
• Investment and Operating Cost
• Safety Basic Engineering
Design Construction
• Operability Feasibility
Concept Operation
• Constructability Study Maintenance
• Maintainability Concept
Revamp/
HAZOP
• Profitability
• The conceptual and feasibility stage help to set up the
design basis.
3
The Impact of Initial Phase of
Design Activities
• The development of design basis is often overlooked by the owner as well as the
engineering consultant.
• The conceptual and feasibility stage help to set up the design basis.
• Every single line in a design basis should have thought and analysis behind it. A
thorough study of key issues is needed to establish a proper design basis.
• The graph in the next slide shows the impact of actions taken in early stages of
project.
• The best cost reduction exercise can be done at the design basis stage itself.
4
The Impact of Initial Phase of
Design Activities
• Oilfield-
– In oilfield it is described by oil production in BPD or MMTPA, Gas Oil Ratio (e.g. SM3 gas per M3 oil) and
water percent.
– Production profile over field life also is important capacity parameter.
• Refinery-
– Crude Processing capacity in BPSD
– Product Slate
• Petrochemical Plants-
– Often defined by product capacity
7
On-Stream Factor (Plant Availability)
• On-Stream factor depends on-
– Planned maintenance shutdown requirements.
– Unplanned shutdowns.
• Normally in a complex process plant, 330 days a year is considered a good basis.
• Some may require operation for a few months or even a few weeks a year.
• But certain critical projects may call for 365 days a year. It is quite common in oil/gas production
facilities.
• On-Stream factor has a huge influence on the process concept and costs of the project.
– Sparing Philosophy
– Layers of Protection & Safety Shutdown systems
8
On-Stream Factor - Exercise
• A basic scheme for oil and
gas production is given
below. The owner wants to
M Cooling
be able to deliver gas to Gas
Gas to
Dehydrator
the gas pipeline 98% of the Pipeline
HP Compressor
time. What are things to Separator
–
consider given:
LP
– vessels have a 99% Availability.
Separator Water Oil (Liquid) Separator
Dehydrators require 8 hour regeneration Water Atm.
time every 2 days. Treatment Water Storage
– Oil Oil /Liquid
Historical data shows rotating equipment is
Dehydration Pipeline
M
available 90% of the time Water discharge
Pump
– valve loops can fail multiple times
Control Or re-injection
per year and take a few hours
to repair each time
9
Impact of Site Data on Process
Design and Costs
• Critical site data for process design are-
– Contour diagram
– Elevation
– Maximum Design Ambient Temperature
– Minimum Design Ambient Temperature
– Ambient Pressure
– Humidity
– Wind Direction
– Rainfall data
10
Case Study
How Site Affects Design & Cost
• The scheme below had to be implemented….
Natural gas Gas M Cooling Gas to
Dehydrator Pipeline
Well Fluid HP Compressor
Separator
(15 bar)
LP
Separator
Water Oil (Liquid) (3 bar)
Water Atm.
Treatment Water Storage
10 MMTPA 600,000 M3 Oil /Liquid
Oil
Pipeline
Dehydration
Water discharge M
Or re-injection Pump
• Cooling considerations
11
Case Study
Maximum Design Ambient Temp
• Metrological department gives temperature profile around the year for several
years.
• Designer should recommend maximum and minimum design ambient
temperatures and maximum solar radiation temperature.
Air
Cooler
• Propane Refrigerant Make-up Plant
• Desert Location
PACKING
• Maximum Design Ambient Temp.
LPG Feed Propane
TRAYS
taken as 55 oC
• Required propane temperature < 50 oC
Butane
• Turnkey skid mounted supply.
• Solar radiation requires protection
against thermal expansion
12
Wind Direction
• Gas Processing Plant producing LPG
out of natural gas
Prevailing
• Wind direction reported 75% times Wind Direction
South East to North West
• Large Flare to be located 90 M away.
• Where shall you locate the flare
stack? Control Room?
Administration Building?
• Muster Points
13
Wind Direction
• Bhopal MIC leak was a major disaster.
• Thousand died or were affected. Prevailing
Wind Direction
• Lesson Learned: Location of a plant Leaked MIC
dealing with hazardous materials
must:
– Have Emergency Management Plans that
• Identify mitigative measures to manage
risks
– Buffer zones around the plant - downwind
• Emergency Response Plan that includes
– Train operators so that they can save
themselves. – understand evacuation plan Operators Escape
and importance of wind direction.
– Community Involvement – ACC Right to 14
Know
Raw Material and Product
Specification
• Processing scheme and operating conditions are dictated by
product specification.
• The plant needs to be designed with some flexibility on raw
18
Utilities Design Basis
Key Issue
• Optimization between Fuel, Power and Steam is of great
importance at today’s energy cost.
• Keeping the utility parameters floating at design basis stages helps in evolving cost saving
concepts.
20