Milestone plan for City Gate Station and Mother CNG station at Jategaon

Target Dates January February March April


It No Activity
01#07 08#15 16#23 24#31 01#07 08#15 16#23 24#28 01#07 08#15 16#23 24#31 01#07 08#15 16#23 24#30
1 Consultants, Architects,
Consultants Finalised : Building permission , Fire Noc , Mpcb , DM NOC PESO , Architectural
and structural Drawings
Consultant for Access permission from SH
2 Work Orders
Civil Works 12/2/2019
Mechanical Works ( Loading unloading of Equipments )
Electrical works
DG sets
Fire Fighting ,and CCTV 2/28/2020
3 MSEB Connection ( 100 KVA LT ) 2/15/2020
4 Equipment PO
Comp. , Cascade LCV Filling post, Metering & Odorising skid, Steel Piping and accessories,
tubings and fittings, IJ ETC
5 Statutory Approval
Received : Basic Layout Approval from PESO ,MSEB NOC ,Building plan Approval and Fire 1/25/2020
NOC PMRDA ,NOC From PWD
DM NOC
Acces permission from PWD
6 Construction
Retention and Compound Wall 1/31/2020
Equipment foundation 2/20/2020
Sales Office 4/15/2020
Filling compacting 4/15/2020
Tubing TRENCING ,utilities , Draqinage Fabrication work etc 4/1/2020
7 Equipment and Accessories deliverys and Installation
Online Compressor , Storage Cascade , Odorising skids , metering skid 3/25/2020
Tubings fittings, Steel piping and fittings 3/31/2020
Fire Fighting System 1/31/2020
Electrical Works (Main Panel, Equip. cables, Yard and office lighting, DG sets , CCTV 4/10/2020
8 Final Satutory Approvala and Commissioning
Fire NOC and Builidng Occupancy 4/1/2020
Final Grant of License
Commissioning 4/15/2020

1 Basic Layout Approval from PESO ,MSEB NOC ,Building plan Approval and Fire NOC
PMRDA ,NOC From PWD is pending
2 Application for MSEB connection (100 KV LT) is pending.