Documente Academic
Documente Profesional
Documente Cultură
2B FORM-1
Sector - 94, Noida,
FORM -1
“CAPITAL CITY”
COMMERCIAL PROJECT
at
APPENDIX I
(See paragraph – 6)
FORM 1
(i) Basic Information
1.1 Permanent or temporary change in Yes The land is allocated from NOIDA for setting up
land use, land cover or topography Commercial project and building plan of revised
including increase in intensity of area also approved from the authority which are in
land use (with respect to local land accordance with the land usage defined in the
use plan) NOIDA Master Plan 2021
1.2 Clearance of existing land, No Not required since site developed as per approved
vegetation and buildings? building plan
1.3 Creation of new land uses? No The land is allocated from NOIDA for setting up
Commercial project as per defined land use in the
NOIDA master plan 2021
1.4 Pre-construction investigations Yes Soil testing has already been done, which shows that
e.g. bore houses, soil testing? the soil consistency is strong enough with load
bearing capacity.
1.5 Construction works? Yes Building construction and lying of services such as
water supply, storm water drainage, sewerage and
lighting and green.
1.6 Demolition works? No No demolition work.
1.7 Temporary sites used for No No, temporary residential facilities for labours
construction works or housing of provided within project premises as labours during
construction workers? construction engaged and hired from nearby area
1.8 Above ground buildings, No Nil
structures or earthworks including
linear structures, cut and fill or
excavations
1.9 Underground works including No No underground works required except construction
mining or tunneling? of basements.
1.10 Reclamation works? No Not Applicable, as the proposed project is
Commercial project.
1.11 Dredging? No Not Applicable, as the proposed project is Building
project.
1.12 Offshore structures? No Not Applicable.
1.13 Production and manufacturing No This is a Commercial project, so there will be no
processes? production and manufacturing.
1.14 Facilities for storage of goods or No During construction phase, temporary sheds for
materials? storage of cement and other material has been
provided within the project premises.
1.15 Facilities for treatment or disposal Yes The solid waste generated from project during
of solid waste or liquid effluents? operational phase will be temporarily stored for 48
hours and suitably segregated in to mainly organic
(wet waste) and recyclable (dry waste) and to be
managed as per Solid waste management Rules
4.3 Hazardous wastes (as per Hazardous Yes Only used lube oil (category 5.1) from DG set
Waste Management Rules) operated during power failure as per Hazardous and
Other Wastes (Management and Transboundary
Movement) Rules, 2016 dated 04/04/2016
4.4 Other industrial process wastes No Not Applicable, as it is a Commercial project.
5.4 Emissions from construction Yes Fugitive dusts from various activities of construction
activities including plant and are expected, which are temporary in nature and to
equipment be controlled by regular water sprinkling.
5.5 Dust or odours from handling of Yes Dust generation is related only during earth work
materials including construction and it is temporary in nature and activities
materials, sewage and waste completed. There will be no source of odour
5.6 Emissions from incineration of No Not Applicable
waste
5.7 Emissions from burning of waste in No Not Applicable
open air (e.g. slash materials,
construction debris)
5.8 Emissions from any other sources No Nil
8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment
S. Information/Checklist confirmation Yes/ Details thereof (with approximate
No. No quantities/rates, wherever possible) with
source of information data
8.1 From explosions, spillages, fires etc No Construction/Operation of Commercial Project
from storage, handling, use or shall follow all applicable guidelines imposed
production of hazardous substances under part 04 (Fire and Life safety) as per
National Building Code of India 2005.
Fire safety measures include Fire extinguishers,
Water tanks, Yard hydrants, hose reels, automatic
detection system, illuminated Exit site, basement
sprinkler system and compartmentalization etc.
8.2 From any other causes No Not Applicable
8.3 Could the project be affected by natural No No cases are reported so far. The site is selected
disasters causing environmental damage carefully keeping in view all the factors to avoid
(e.g. Floods, earthquakes, landslides, any environmental damage due to natural
cloudburst etc)? disasters.
“I hereby given undertaking that the data and information given in the application for
modernization/revision application and enclosures are true to the best of my knowledge and
belief and I am aware that if any part of the data and information submitted is found to be
false or misleading at any stage, the project will be rejected and clearance give, if any to the
project will be revoked at our risk and cost.
Date:
Rajeev Gupta
Place: New Delhi-01 (Authorized Signatory)
C/O BPTP International Trade Centre Ltd
M-11, Middle Circle, Connaught Circus,
New Delhi-110001
Signature of the applicant
With Name and Full Address
(Project Proponent / Authorized Signatory)
FORM- 1A
“CAPITAL CITY”
COMMERCIAL PROJECT
at
APPENDIX II
(See paragraph 6)
FORM-1 A
(Only for construction projects listed under item 8 of the Schedule)
1. LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity)
1.1. Will the existing land use get Commercial Project at Plot No. 2B, Sector 94, Noida, Uttar
significantly altered from the project that Pradesh
is not consistent with the surroundings?
(Proposed landuse must conform to the The proposed project site does not involve any leveling of
approved Master Plan / Development land outside the leased property.
Plan of the area. Change of landuse if
any and the statutory approval from the The existing topography will not be altered due to the
competent authority be submitted). construction activity. Hence, impacts on topography and land
Attach Maps of use will not be envisaged.
(i) Site location, Site location plan attached as annexure 4
(ii) Surrounding features of the proposed site
(within 500 meters) and Surrounding features of site (within 500 meters) enclosed as
(iii) The site (indicating levels & contours) to annexure 5
appropriate scales. If not available attach
only conceptual plans. Conceptual plan enclosed as annexure 3
1.2. List out all the major project Plot Area: 57344.10 Sqm. or 14.17 Acs.
requirements in terms of the land area, Built-up Area: 273130.2 Sqm.
built up area, water consumption, power Ground Coverage: 14,261.85 Sqm.
requirement, connectivity, community
facilities, parking needs etc.
1.3. What are the likely impacts of the The likely impacts of the proposed activity on the existing
proposed activity on the existing facilities adjacent to the proposed site will be very meager.
facilities adjacent to the proposed site? The proposed project will not have any adverse impact on the
(Such as open spaces, community surrounding environment. However, the development of the
facilities, details of the existing landuse, project in this area will increase employment opportunities.
and disturbance to the local ecology). There is no major disturbance to local ecology as no tree
felling or clearing of vegetation is involved. The proposed
project has a proposal of green belt development, which will
increase the aesthetic value of the area. The project has a
provision for planting of common variety / local trees and
2.1. Give the total quantity of water The total water requirement for all purpose of the proposed
requirement for the proposed project with project will be 1003 KLD which will be met from Municipal
the breakup of requirements for various water supply.
uses. How will the water requirement
met? State the sources & quantities and
furnish a water balance statement.
2.2. What is the capacity (dependable flow or The daily requirement of fresh water for the proposed project
yield) of the proposed source of water? during operational phase will be approx.. 302 KLD, which
will be met from Municipal water supply (Noida Jal Board
authority).s
2.3. What is the quality of water required, in The quality of Existing Bore well water samples has been
case, the supply is not from a municipal analyzed. All the parameters are well within the permissible
source? (Provide physical, chemical, limits and water can be used for drinking and domestic
biological characteristics with class of purposes.
water quality)
2.4. How much of the water requirement can The estimated treated water available from Sewage Treatment
be met from the recycling of treated Plant will be approximately 791 KLD. The re-use of treated
wastewater? (Give the details of water will be directly Green belt development, Flushing and
quantities, sources and usage) water body make up. There will be zero discharge outside the
boundary.
2.5. Will there be diversion of water from No there will be no diversion of water from other users.
other users? (Please assess the impacts of
the project on other existing uses and
quantities of consumption)
2.6. What is the incremental pollution load The waste water generated in the process will be approx. 791
from wastewater generated from the KLD. The waste water will be treated in the STP and then the
proposed activity? (Give details of the treated water will be recycled and used for Green belt
quantities and composition of wastewater development, flushing, etc. within the premises and no water
generated from the proposed activity) will be discharged outside. There will be zero discharge.
2.7. Give details of the water requirements The rainwater harvesting will be done to recharge the ground
met from water harvesting? Furnish water table.
details of the facilities created. However, the company has already installed number of RWH
pits as per requirements.
2.8. What would be the impact of the land The proposed project activity involves construction of
use changes occurring due to the buildings and development work such as construction of
proposed project on the runoff roads, lying of water supply, storm water drainage lines,
characteristics (quantitative as well as sewer lines, street lighting and landscaping as such there will
qualitative) of the area in the post be no change in the land use of the site. Rainwater harvesting
construction phase on a long-term basis? will be practiced to recharge the ground water during
Would it aggravate the problems of monsoon period. Therefore, the run-off characteristics of
flooding or water logging in any way? water in the area on long term basis will not change, as there
will be no water logging and flooding problems. The project
site does not fall in a flood prone area and hence no
lead to unsanitary conditions around the unsanitary conditions in and around the project site.
project site (Justify with proper
explanation)
2.13. What on-site facilities are provided for It is proposed to connect all the soil and waste Outlet pipes
the collection, treatment & safe disposal from Toilets, Kitchens, pantries, laundry and waste from floor
of sewage? (Give details of the quantities washings etc. from all the floors into Vertical down take soil
of wastewater generation, treatment and waste pipes and bring them down to ground level and
capacities with technology & facilities connect them to centralized sewer network for final disposal
for recycling and disposal) and treatment in the Sewage Treatment Plant.
2.14. Give details of dual plumbing system if 711 KLD treated water will available for the project. Treated
treated waste used is used for flushing of water will be used in green belt development, Flushing &
toilets or any other use. water body make up.
3. VEGETATION
3.1. Is there any threat of the project to the There will be no report of any adverse impacts on the
biodiversity? (Give a description of the biodiversity due to the construction of the proposed project.
local ecosystem with it’s unique features,
No threatened, rare, endangered or endemic species were
if any)
observed during the survey in core zone.
3.2. Will the construction involve extensive No. The proposed site to be developed as commercial
clearing or modification of vegetation? complex. The acquired land earlier was occupied by NOIDA
(Provide a detailed account of the trees & authority and said development as per NOIDA master plan
vegetation affected by the project) 2021.
3.3. What are the measures proposed to be Extensive plantation and green belt development is planned in
taken to minimize the likely impacts on the proposed project along with landscaping and creation of
important site features (Give details of water bodies. The total green area shall be 43.88 % (25,162.92
proposal for tree plantation, landscaping, sqm) of plot area.
creation of water bodies etc along with a
layout plan to an appropriate scale)
4. FAUNA
4.1. Is there likely to be any displacement of There is no report of any direct or indirect impact on the fauna
fauna- both terrestrial and aquatic or due to this proposed Commercial project and there is no report
creation of barriers for their movement? of existence of any specific fauna required special protection.
Provide the details.
4.2. Any direct or indirect impacts on the There is no direct or indirect impact on avifauna is envisaged.
avifauna of the area? Provide details. However, after the commissioning of the project the better
environmental conditions may provide a better habitat to the
avifauna of the area.
4.3.Prescribe measures such as corridors, For the commercial colony project site, the area designated as
fish ladders etc to mitigate adverse green area will be about 43.88 % (25,162.92 sqm) of plot
impacts on fauna area. Common native varieties of trees and ornamental
flowering species will be planted in the green space.
Landscaping can have direct positive impact on the local
5.6. What will be the impact of DG sets & Presently DG sets of 2000 KVA and 1000 KVA proposed to
other equipment on noise levels & meet the power requirement during power failure and Fuel
vibration in & ambient air quality around shall be ULSD. The power back up will be 100%. DG set will
the project site? Provide details. be the main source of noise pollution. The DG sets shall be
used only in case of power failure and will be provide with
acoustic enclosures. Gaseous pollutants like NOx, SO2 & CO
shall also be generated from activities like burning of fuel
through DG sets.
6. AESTHETICS
6.1. Will the proposed constructions in any The proposed proposal will not in any way result in the
way result in the obstruction of a view, obstruction of a view scenic amenity or green belt. The
scenic amenity or landscapes? Do the present project itself is planned with provisions of green belt
proponents take these considerations into development and afforestation. This will surely enhance the
account? aesthetic value of the area.
6.2. Will there be any adverse impacts from There will not be any adverse impacts from new constructions
new constructions on the existing as there are no existing structures nearby.
structures? What are the considerations
taken into account?
6.3. Whether there are any local The proposed project land is located in the commercial zone
considerations of urban form & urban as per Master plan of Noida 2021. The proposed project shall
design influencing the design criteria? follow all the rules and regulations described by State
They may be explicitly spelt out. Government, National Building Code and other relevant
Departments.
6.4. Are there any anthropological or There are no any anthropological or archaeological sites or
archaeological sites or artifacts nearby? artifacts or any other significant features in the vicinity of the
State if any other significant features in proposed project site.
the vicinity of the proposed site have
been considered.
7. SOCIO-ECONOMIC ASPECTS
7.1. Will the proposal result in any changes No
to the demographic structure of local
population? Provide the details.
7.2. Give details of the existing social Telecommunication facilities in the study area are adequate;
infrastructure around the proposed electronic telephone exchange is working the study area.
project.
7.3. Will the project cause adverse effects on No, the proposed project will not cause any adverse effects on
local communities, disturbance to sacred local communities or disturbance to sacred sites or other
sites or other cultural values? What are cultural values.
the safeguards proposed?
8. BUILDING MATERIALS
8.1. May involve the use of building The major materials used for the construction of the proposed
materials with high-embodied energy. project will be RMC, steel, cement, bricks, metal, flooring
Are the construction materials produced tiles/stones, sanitary and hardware items, electrical fittings,
with energy efficient processes? (Give water etc. All the items used in construction will be as per the
details of energy conservation measures National Building Code specification.
in the selection of building materials and
The fly ash for mixing with the cement has been done and
their energy efficiency)
hence the disposal of fly ash which is a serious issue can be
managed and will reduce the consumption of sand. Effort
made to use bricks made of fly ash in place of loose earth for
filling purposes within the building. Use of tiles made of fly
ash as insulation material for the terrace.
8.2. Transport and handling of materials During the construction phase the air quality will have
during construction may result in adverse impact. Construction activities especially related to
pollution, noise & public nuisance. What handling of loose material like to cause generation of fugitive
measures are taken to minimize the dust, that adversely impact the air quality of the surrounding
impacts? area of the project site. To minimize the impact loose material
will be either stacked or transported with proper covering.
During construction phase the expected noise levels will be
between 70 – 85 dB (A) which decrease with increase in
distance. Administrative as well as engineering control of
noise will be implemented.
8.3 Are recycled materials used in roads and There is no availability of the recyclable building material in
structures? State the extent of savings the vicinity of the proposed project site.
achieved?
8.4. Give details of the methods of Solid waste generated during the construction phase shall be
collection, segregation & disposal of the properly collected and segregated as plastic, paper, metal and
garbage generated during the operation other and shall be disposed off as per the standard practice.
phases of the project.
The solid waste generated from project in operational phase
shall be 5232 kg /day.
The solid waste so generated shall be first segregated as
plastic, glass, paper separately and disposed off as per
standard practice.
9. ENERGY CONSERVATION
9.1. Give details of the power requirements, The power requirement for entire Project would be around
source of supply, backup source etc. 19.2 MVA. The power will be made available from UPPCL.
What is the energy consumption assumed
per square foot of built-up area? How
have you tried to minimize energy
consumption?
9.2. What type of, and capacity of, power Presently DG sets of 2000 KVA and 1000 KVA proposed to
back-up do you plan to provide? meet the power requirement during power failure and Fuel
shall be HSD (Ultra-low Sulphur diesel). The power back up
will be 100%.
9.3. What are the characteristics of the glass Tinted float glass will be used in the project.
you plan to use? Provide specifications During commissioning of proposed project, 8 mm thick, blue /
of its characteristics related to both short grey reflective glasses will be used in fenestration. These
wave and long wave radiation? panels will have light transmission, but low solar heat inflow.
This will reduce the quantity of heat inflow into the building,
lessens cooling loads on AC induces energy saving.
9.4. What passive solar architectural features Solar energy will be utilized for providing Hot water supply to
are being used in the building? Illustrate the buildings.
the applications made in the proposed
project?
9.5. Does the layout of streets & buildings Orientation is done in such a manner so that surface of the
maximize the potential for solar energy building is prevented from exposure to direct sunlight and
devices? Have you considered the use of thus heat gain of the building will less.
street lighting, emergency lighting and
solar hot water systems for use in the
building complex? Substantiate with
details.
9.6. Is shading effectively used to reduce The units on the top floor may have a false ceiling. The air in
cooling/heating loads? What principles between the ceiling & slabs shall act as on insulator.
have been used to maximize the shading
The passive solar architecture is used for the maximum use of
of Walls on the East and the West and
the solar energy. Large south facing windows are the easiest
the Roof? How much energy saving has
and cheapest way to increase light in a building, since the
been effected?
south side of a building receives the more sunlight.
An open design, with glazed apertures, light shelves and light
pipes can transmit sunlight into building interiors.
Louvers and sunshades will be used around windows in order
to protect from direct sunlight.
Proper ventilation allows the heat from the sunspaces to
circulate through the rest of the building.
9.7. Do the structures use energy-efficient Suitable energy optimization will be adopted during
space conditioning, lighting and calculation of energy load of the proposed project. Proper
mechanical systems? Provide technical energy efficient system will be installed.
details. Provide details of the
The space heating load will be minimized using passive solar
transformers and motor efficiencies,
structure and suitable buildings envelop material.
lighting intensity and air-conditioning
load assumptions? Are you using CFC Uses of incandescent lamp and halogen lamps have been used
and HCFC free chillers? Provide for all common area and basement parking. The lights in
specifications. basement car park has been designed to operate through
timers to achieve 33%, 66% and 100% illustration to suit the
occupation of the premises.
The diesel generator sets shall be automatically controlled to
energy technologies are utilized in the meet electricity requirements. (For e.g.:- solar water heater,
overall energy consumption? Provide solar street light, use of Green CFL Lamps.
details of the renewable energy
technologies used.
Construction specifications
Purchasing construction materials
Reducing site Environmental impacts
Dust emission control during construction
Optimized energy and water Use
Runoff prevention and waste management.
1. Land-use Insignificant 1. Construction footprint will be well • Proper fencing of the area
pattern/ adverse defined and construction work will through contract
Ecology impact be carried out within the footprints
only.
2. Restoring all areas affected by • Audit of construction site to
establishment of both within (open check the implementation of
area) and adjacent to the plot area, all the measures by the
if any during Construction. company personnel
2. Soil Moderate 1. Stacking of excavated soil material • Implemented through
adverse (350,000 cu. m. approx.) in an construction contractor and
impact earmarked area for leveling and Audit and monitoring by the
every care shall be taken to prevent company personnel
soil erosion.
2. Area shall be properly fenced and –Do–
provided with proper drainage
pattern.
3. Retention wall/bund shall be –Do–
provided around the storage areas
flow of solid with storm water in
case of rain.
CONCEPTUAL PLAN
“CAPITAL CITY”
COMMERCIAL PROJECT
at
36
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
Table of Contents
37
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
The existing business districts in Delhi are near saturation levels with limited space availability
for future expansions. Majority of the developments undertaken have witnessed infrastructure
bottlenecks, parking related issues, etc. To capitalize on this need gap, this project is ideally
positioned to be developed as an iconic business district within the NCR region. Development
of skyscrapers as part of this project would result in creation of a landmark, comparable to
some of the popular business destinations worldwide
The development of the proposed project is expected to house green buildings with
sustainable design and green architecture to avail lower maintenance costs and environmental
impacts, integrated to create constructive synergies. The development will encompass: the
following components:
Well designed office spaces - Catering to the corporate offices of the following
sectors:
BFSI, Manufacturing, Advertising / Media, Consulting, Telecom, etc.
Hotels / Serviced Apartments /Conventional Centre – Catering to the luxury &
business needs
Integrated Shopping Malls / High Street Retail – Incorporating Retail and
recreational facilities.
Some of the key features of the development include:
Green building concept to ensure environment friendly structures
Multiple entry / exit points to the subject development to ensure smooth traffic
flow
38
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
On the whole, the pattern of development will optimize the flow and visibility of the site, with
hotels at the center of the development with commercial spread across the radial road
network. Further, retail developments through the circumference of the subject property are
expected to have continuous frontage, creating visual aesthetics with green spaces. In effect,
the development is envisaged to become one of a kind, integrated business hub in India
The project is envisioned to benchmark itself to international standards like Canary Wharf in
London, International Finance Centre in Hong Kong, and Dubai Business Bay in UAE with
respect to its scale of operation, highly conducive environment for undertaking business
operations and infrastructure which would in turn attract local, regional and international
players.
The complex shall be designed and developed in various phases with a master network of all
services which can cater for the best Intelligent Buildings by any global standard. The
Landscape for the entire complex shall be so designed (43.88 % of total plot area) that with a
ground coverage restricted to 25%, the entire premises shall be plush green both in terms of
hard and soft landscape. The building designs shall be such that the Concept of Green
Building design is intact with a sound sustainability character.
This project site is located in a very important junction amongst connectivity from Delhi,
Greater Noida, Noida and Jasola. The importance of Traffic Management for such an
important junction has been realized and we will ensure through the inputs of one of the best
Traffic Consultants that the coordination between internal and external traffic is achieved as a
seamless traffic interface
The center of the complex shall be developed as the entertainment center running alive during
day and especially evening hours. The pedestrian movement of the entire complex shall be
controlled in a manner that the life is brought to the entire complex during all parts of day
and night
39
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
The retail has been placed in the periphery of the complex for a perfect horizontal spread-out
and a concept of high street shopping shall be implemented
The area details of the Proposed Capital City Commercial Project at Plot No. 1, Sector –94,
Noida (U.P.) is given in the below table: -
D.G. sets for power back- up: - 11 DG sets (10 x 2000 KVA & 1 x 1000 KVA)
40
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
2. WATER REQUIREMENT
Total Water Requirement during operation phase= 1003 KLD.
Total water requirement during construction phase = 100 m3 / day (source: STP treated
water from NOIDA Authority).
Total wastewater generation will be = 791 KLD. All of this water will be treated in STP,
which works on the principle of extended aeration.
Treated water available will be = 711 KLD. This treated water will be used for Flushing, and
Green belt development.
41
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
42
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
Total number of batches per day, when operating for a period of 7 hours per day = 4
batches/hour * 7 hour = 28 batches
Total number of batches required to convert 3,139 kg/day = 25.11 say 26 batches
43
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
1) Screening
2) De- gritting
3) Biological Oxidation
5) Coagulation- flocculation
6) Filtration
7) Disinfection
4. Final utilization of Treated Water – About 711 KLD of treated water will be available.
The treated water will be used in flushing and horticulture. The sludge generated from
the STP will be used as manure for gardening purpose within the project area.
44
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
3) For basement parking, the rainwater from ramps will be collected in the
basement storm water storage tank. This water will be pumped out to the nearest
external storm water drain.
The Rain water harvesting has been catered to and designed as per the guidelines of
CGWB. The ground water level in the area is 8-10 meters bgl. Peak hourly rainfall has been
considered as 50 mm/hr. The design specifications of the rain water harvesting plan are as
follows:
Catchments/roofs will be accessible for regular cleaning.
The roof will have smooth, hard and dense surface, which is less likely to be damaged
allowing release of material into the water. Roof painting will be avoided since most
paints contain toxic substances and the same may peel off.
All gutter ends will be fitted with wire mesh screen and a first flush device will be
installed. It is ensured that most of the debris viz leaves, plastic bags, paper pieces etc
carried by the rain water from the rooftop will get arrested by the mesh at the terrace
outlet and prevent contamination. It is ensured that the runoff of first 10-20 minutes
of rainfall will flush off completely.
No sewage or wastewater will be admitted into the system.
No wastewater from areas having oil, grease or other pollutants will be connected to
the system.
Estimation of storm water load, total volume of storm water and number of pits to
be developed
45
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
Hence No. of pits required = 230.9/84.78 = 2.72 pits say 3 pits. Thus three Rain Water
Harvesting pits are proposed for artificial rain water recharge within the project
premises.
Taking the effective length, breadth and depth of a rainwater storage tank as 5.5 m, 5m
and 3.5 m, Volume of a single rainwater storage tank = 96.25 m3
Thus 3 Rain Water Harvesting pits are proposed for artificial rain water recharge and 2
tanks for rainwater storage and reuse within the project premises.
Lighting and switching shall be designed by keeping in mind day light integration.
Insulated roofs will be provided which shall reduce the use of electrical energy.
46
BPTP International Trade Center Ltd.
Commercial Project namely “Capital city” Plot No. 2B CONCEPTUAL PLAN
Sector - 94, Noida,
Window design would ensure adequate solar access and this will reduce dependence
on artificial lightings.
High-energy efficient motors, CFC free & centrifugal water-cooled chillers shall be used
as per ECBC.
Energy efficient construction material will be used to achieve the desired thermal
comfort.
47
BPTP International Trade Center Ltd.