Documente Academic
Documente Profesional
Documente Cultură
00 31-Mar-15
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Inspection of Pressure Test Preparation SAIC-A-2011 30-Apr-17 MECH-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Test Preparation - General Requirements ... USE SATR-A-2001, 2002, 2003, 2004, 2005 & SATR-A-2006 as req'd.
All joints including welded joints are accesible and left exposed for
visual leak detection during the strength test. External coating and SAES-L-150,
A8
priming of such joints are not allowed unless approved. Para. 7.3
Note: This excludes joints subject to 24-hr recorded test
Work permit is obtained for pressure testing and associated work G.I.-2.102,
A9
within restricted areas, as per G.I. 2.100, Work Permit System. Para. 5.1.6
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Access/Egress for Test areas is marked & warning signs posted to G.I.-2.102,
A 14
alert approaching personnel of pressure testing activities. Para. 5.1.11
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Manifold Arrangement Drawings attest to the following:
A) Fabrication was per code construction with component
details listed such as Class, size, schedule, type isolation valve, etc.
B) Maximum Safe Test
Pressure Rating based on limiting factor. C)
G.I.-2.102,
C3 Each test manifold is identified with a unique number (certificate)
Para. 5.1.2.5
D) Shows actual arrangement including hose
configuration used Note 1:
Manifold permanent marking (unique ID #, pressure rating) is legible,
traceable & certified (Engineering support docs).
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
D Test Relief Valve(s)
Relief valve is located in the system under test and near the test
G.I.-2.102,
D1 pump with Isolation valves on the inlet and outlet of the relief valve
Para. 5.1.5.1
sealed open during the test. (SAEP-1160, Bullet Item # 3)
Relief valve(s) are tested, dated, and tagged (as valid) for a period of SAES-A-004
D3
one week for project pressure tests. Stickers are legible & valid. Para 5.5.1
A minimum of two pressure gages are required for test systems, with
accuracy within 5% of one another.
Note 1: When large systems are tested, Inspection personnel will
determine the need for additional gages.
Note 2: Elevation changes (hydrostatic head SAES-A-004
E1
considerations) & hot weather create pressure testing problems with Para 8.1.5.4
frequent popping of relief valves. For this reason, gage accuracy
within 2% is best. Note 3: Careful handling of
delicate instruments like test gages is practiced by test crews. No
gage damage or mishandling is found.
Pressure gages and pressure recorders are calibrated within (1) SAES-A-004
E2
month prior to test. Stickers applied indicate latest calibration date. Para 8.1.5.2
G.I.-2.102,
Avoid the following typical examples of poor practices:Testing
Sec.4 &
E3 equipment with the test gauge located at the bottom of the equipment
SAES-A-004,
reading the test pressure,including the head of test water
Para 5.3
All gages have a range such that the test pressure is within 30% to SAES-A-004
E4
80% of the full range. Para 8.1.5.3
F Temperature Gages and Recorders (When Required, ie: 24-hr Recorded Tests)
REMARKS: Critical Safety Note 1: Surveys of test manifolds used on projects have resulted in many findings of inadequate ratings for isolation
valves. Test manifolds for testing specific pressure rating Classes require isolation valves of the next higher class. Example: Manifolds for testing
Class 300 # systems require Class 600 # isolation valves as a general rule. For Pressure tests against closed seats follow the 110% rule for safe
test pressure calculation. See ASME B16.34, Para 7.2 as applicable. Also, this same requirement must be carefully considered when determining
test pressures where an isolation valve serves as a test boundary limit and the valve seat will be pressurized. Ensure system test pressures are
reduced to 110% as applicable and show the valve seat as the test "limiting factor". Safety Note 2: Fabricated test
implements of proper code construction receive inspection and properly identification/marking for pressure rating, inspection acceptance/fitness
(Insp Ok, initial, date). Never allow uninspected non-code test implement use or those that are unfit for testing (deteriorated, damaged, heavily
corroded). Unsafe/unfit test implements found are reported/removed ASAP from Company Projects.
REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, (30-Jan-2011)
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
2. GI-2.102, Saudi Aramco General Instruction-Pressure Testing Safely, (28 October, 2008)
3. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (24-Dec-2014)
4. Pro Forma Contract Schedule Q (Project Specific)
5. SAEP-1160-- Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects (10-July-2011)