Sunteți pe pagina 1din 417

Loughborough University

Institutional Repository

Pipe jacking forces in sand


This item was submitted to Loughborough University's Institutional Repository
by the/an author.

Additional Information:

• A Doctoral Thesis. Submitted in partial fullment of the requirements for


the award of Doctor of Philosophy of Loughborough University

Metadata Record: https://dspace.lboro.ac.uk/2134/15343

Publisher: c Shak Joseph Yonan


Please cite the published version.


This item was submitted to Loughborough University as a PhD thesis by the
author and is made available in the Institutional Repository
(https://dspace.lboro.ac.uk/) under the following Creative Commons Licence
conditions.

For the full text of this licence, please go to:


http://creativecommons.org/licenses/by-nc-nd/2.5/
- - - - - - -- -- -- -

LOUGHBOROUGH
UNIVERSITY OF TECHNOLOGY
LIBRARY
AUTHOR / FILING TITLE

________________yQr::'_~+-- ~,'!.~.:-- _________ _


. .,.~~ .

" - 'vi"
- - - -- - ---- -- - ------ -----.-.-.;;.:~ ---- --- - - -- - - - ----- --_ .
ACCESSION / COPY ,!'iO,' , --
....... I. _~.',' .;P'"
)f'r\~t'." ______
- _____.. '~"V" ~CI':>
,. . ~ ____ _ _ -:- _ 'S
_ '____
<f- 'if_10·'
_ .J _________ _ _ _ _ _ _ _ _ •

VOL. NO. CLASS MARK

(' • !_ r

28 FE

0400848562

11111111111111111 1111111 111111 11111


PIPE JACKmG FORCES m SAND

By

Shafik Joseph Yonan

A Doctoral Thesis Submitted in Partial Fulfilment of The


Requirements for The Award of Doctor of Philosophy of
Loughborough University of Technology

October 1993

Supervisor; Dr CDF Rogers


Department of Civil Engineering

@ ShaflkJoseph Yonan, 1993


Loughborough Unive rsity
of T~chnolog y Library
- .... .... -~

Dale \vi c;.r '1 v(


Class
'ACe.
No. (!\{ (io 'b' 't '6 ) b
TO ny :F'ATH:ER JOS:E:PH
& ny nOTH:ER JA.N£T
"Fat" lwet"yone that exatts ft.i.msdf wiU be ft.umbted
amt ft.e that ft.umbtes ft.i.msdf wiU be e"attm"
L..r.e 14:12
ABSTRACT

In this research work, a comprehensive review of investigations into pipe jacking


operations, and in particular the forces generated during the process, is presented.

The factors affecting these forces were examined and their influence was studied in

order to give a clear indication on the their magnitude and behaviour .

A model scale testing facility, based on a 1.8m X 1.5m X 1.5m high steel tank, has

been developed together with hydraulic jacking facilities and scale model pipes of
200mm diameter having both steel and concrete surfaces. In this facility the actual

pipe jacking operation can be simulated, so that a study of the jacking forces could

be made with the use of appropriate instrumentation techniques and computerised


data recording.

A series of tests was conducted to examine the influence of several parameters on the

jacking forces, such as overcut ratio, type of soil, type of pipe surface, overburden

pressure, and the rate of jacking. These parameters were in relation to the distance

jacked.

Two granular soils, uniformly graded Leighton Buzzard sand and well-graded River

sand, were used as the material surrounding the pipeline, that is the material through

which the pipes were jacked . Laboratory analysis on the soil materials was

conducted and the relationship between results obtained from these tests and scale

model testing were established. The interface friction between the surface of the

pipeline and the surrounding soil was determined. The results show a peak in the

jacking forces at the start of the jacking process, followed by a decrease and

i
-- --- ----------- ---

leveling off as the jacking continued. The graph is very similar to the stress/strain

relationship of a typical granular soil . Both steel and concrete pipes were used in

the tests to detennined the influence of pipe surface, and to a lesser degree pipe joint,
characteristics. Higher forces were recorded for concrete pipes. The jacking rate
was kept constant and consistent for all tests. It was found to have little effect on the
magnitude of the jacking forces.

The jacking forces were measured automatically using a computer. The results

show a clear trend of increase in the jacking forces when the overburden pressure
and jacking length were increased . Tests using different overcut ratios have

indicated that a minimum jacking force might be achieved at a specific overcut ratio.

The results of this research show that the jacking forces are influenced by a number
of parameters. These include the overburden pressure, overcut ratio, pipe diameter,

jacking length and the influence of the surrounding material . This is fully
demonstrated by establishing I a method of jacking forces prediction, termed herein
Ithe Loughborough Method. I

ii
LIST OF SYMBOLS

A - Skempton's pore pressure parameter for undrained triaxial tests.


B - Pipe diameter (m), or width of circular tunnel (m) .
B0 - Half width of rectangular tunnel (m) .

BI - Width of rectangular tunnel (m) .


C - Cohesion (kN/m2) .
Cu - Undrained cohesion (kN/m2) .
D - Depth of pipeline (m), or height of soil cover (m) .
F Jacking Force (kN) .
Fb - Net positive buoyancy per metre (kN/m2) .
F0 _ Shield resistance (kN) .

Fr - Frictional Resistance (kN) .

Fs - Resistance force per unit length of tunnel (kN/m) .

Fu - Force per unit length of tunnel (kN/m) .

Fw - Coefficient of frictional resistance due to the weight of the pipe


(kN/m2) .
Gs - Specific gravity .
H - Loughborough rate of frictional increase (kN/m2) .
HI - Height of rectangular tunnel (m) .
K - Loughborough Coefficient of pipe jacking friction (kN/m2) .
Ko - Coefficient of earth pressure at rest (empirical coefficient) .

KI - Loughborough Coefficient of overburden pressure.


L - Jacking Distance (m) .

LI - Distance of propulsion (m) .

LF - Load factor.
M - Slope of the critical state line.
N - Stability number, or stability ratio.
Ne - Stability ratio at collapse.
N' - Normal Effective Force (kN) .
P Cutting edge force (kN) .

ill
Po - Radial pressure on tunnel (kN/m2) .

P1 - Total force on the top half of the tunnel (kN) .

P2 - Total force on the bottom half of the tunnel (kN) .

PID - Skin friction of pipeline (kN/m2) .

p. - Strength of soil face (kN/m2) .


p. 1 _ Heading resistance (kN) •

p.2 - Cutting resistance (kN) .


Pv - Vertical pressure at the crown of the pipe allowing for arching
(kN/m2) .
Ph - Average horizontal pressure on side of the pipe allowing for arching
(kN/m2) .
Ps - Penetration resistance (kN) .
Pu - Total normal force on the surface per unit length (kN/m) .

Pw - Water pressure (kN/m2) .


R - Overcut Ratio.
Rf - Frictional resistance between the pipe and the soil (kN/m2) .
SI - Circumference of the pipe (m) .
S External surface area of pipeline = 1t D L (m2) .
V - Specific volume (m3) •
W - Weight per unit length of pipe (kN/m2) .
X - Distance from the front face of the Model Test Box (m) .
a Adhesive force (kN) .
b Radius of pipe (m) , or half width of circular tunnel (m) .
c Rate of increase in frictional resistance, (Loughborough constant) .
f Coefficient of the frictional resistance due to the weight of the pipe
(kN/m2) .
g Gravity force (rn/s2) .
p Tip resistance (kN/m2) .
p' - Mean normal effective stress (kN/m2) .
q Overburden Pressure (kN/m2) .
q' - Effective deviator stress (kN/m2), or Effective shear stress (kN/m2) .
r Radius of excavation (m) .

iv
t Thickness of the cutting edge (m) .
u' - Change in pore water pressure for undrained triaxial test (kN/m2).
v Volumetric change (m3).
w - Soil pressure perpendicular to pipe (kN{m2) .
wl'w2- Soil pressure horizontal to pipe (kN{m2) .

wg - Weight per unit length of pipe (kN/m2) .

a. Parabola constant.
Constant angle iof friction between the soil and
- -- -- - -
the pipe
-....,.
surface (degree) .,
,

Coefficient of Friction.
Internal angle of friction of soil (degree) .
Drained internal angle of friction of soil (degree).

Internal angle of friction between concrete /steel and soil from


the shear box test (degree). .

<I>'c - Internal angle of friction at critical state (degree) .

Internal angle of friction between the pipline and the surrounding


soil (degree) .

<1>. - Internal angle of friction of the soil from the shear box test (degree) .

<l>p Peak internal angle of friction (degree).

<1>', - Residual internal angle of friction (degree) ,

<l>u - Undrained internal angle of friction of soil (degree),

<l>s/c - Internal angle offriction of soiVconcrete interface (degree) .

<1>'/51 - Internal angle of friction of soiVsteel interface (degree) .

'l' - Dilation angle of soil (degree) .


'Y Soil density (kN/m3) .
er Applied direct stress per unit area (kN{rn2) .
er! _ Major principal stress (kN/m2) .

er3 - Triaxial cell pressure, or minor principal stress (kN/m2) •

er. - Shear stress (kN/rn2) .

v
O"t - Internal stress inside a tunnel (kN/m2) .

<>r - Tunnel support pressure (kN/m2) .

O"v - Vertical pressure on tunnel (kN/rn2) .

O"h - Horizontal pressure on tunnel (kN/m2) .


A. Coefficient ofload bearing capacity .
't Shear strength (kN/m2) .

vi
ACKNOWLEDGEMENTS

First of all I wish to thank the Department of Civil Engineering, Loughborough


University of Technology, headed by Professor R McCaffer, for allowing me

to conduct this research work . My special gratitude goes to my supervisor


Dr CDF Rogers for his guidance, valuable discussions and helpful suggestions

throughout the entire research project. The assistance of the laboratory staff, who
made it possible for this project to be conducted smoothly, is greatly appreciated.

I am grateful to Brian Colquhoun and Partners for their permission to publish


information relevant to my case study.

I wish to express my thanks to all my friends and fellow researchers for their help
and support especially Ghada Eid for her continuous encouragement and assistance
in preparing this thesis.

Finally I have to acknowledge the very considerable contribution of my parents who


supported me through all my education. I would like to thank them for their
encouragement in persuing this work, therefore, to them I would dedicate this
thesis.

vii
TABLE OF CONTENTS

ABSTRACT i

LIST OF SYMBOLS Hi
ACKNOWLEGDEMENTS vii

TABLE OF CONTENTS viii

CHAPTER ONE 1

1- INTRODUCTION 2

1.1- Tunnels and pipelines 2


1.2- The construction of pipelines 4
1.3- Trenchless techniques 7
1.3.1- Pipe jacking 9
1.3.2- Microtunnelling 10
1.3.3- Auger boring 11
1.3.4- Earth displacement hammer 13
1.3.5- Pipe ramming 14
1.3.6- Pipe bursting 15
1.3.7- Horizontal drilling 16
1.4- Factors affecting the choice of pipeline construction 17
1.4.1- Engineering cost 18
1.4.2- Social cost 19
1.4.3- The size of the market 21
1.4.4- The need of the client 21

viii
1.4.5- The cost of trenchless construction 23

1.4.6- Comparisons between trenching and 24

trenchless pipe laying costs

1.5- Aims of the research 25

1.6- Guide to the thesis 27

CHAPTER TWO 29

2- REVIEW OF PIPE JACKING 31

2.1- Introduction and brief history of pipe jacking 31

2.2- Installation techniques 36


2.2.1- Introduction 36
2.2.2- Pipe jacking techniques 37
2.2.2.1- The jacking shaft 37
2.2.2.2- Conventional pipe jacking 39
2.2.2.3- Mechanised pipe jacking 40
2.2.2.4- U ni-Tunnel system 42

2.2.2.5- Large-Bore pipe jacking 43


2.3- Soil mechanics aspects of pipe jacking 44

2.3.1- Introduction 44

2.3.2- The theory of ground pressure on tunnels 44

2.3.3- Tunnels through soft ground 47


2.4- Pipe jacking forces 48
2.4.1- Introduction 48
2.4.2- Theoretical analysis 49

ix
2.4.2.1-CIRIA approach 50
2.4.2.2- Auld's analysis 53
2.4.2.3- Haslem's analysis 56
2.4.2.4- Japanese analysis 58
2.4.2.5- Herzog's study 59

2.4.3- Experimental and field investigation 64

2.5- Factors affecting the jacking forces 66


2.5.1- Type of soil 66
2.5.2- Amount of overcut 70
2.5.2.1- Non-closure of overcut 70
2.5.2.2- Closure of overcut 71
2.5.3- Overburden pressure 72
2.5.4- Misalignment 72
2.5.5- The length of the pipeline 73
2.5.6- The rate of jacking 74
2.6- Methods of reducing the jacking forces 75
2.6.1- Introduction 75
2.6.2- Lubrication 75
2.6.3- Special jacking pipes 77

2.6.3.1- Pipe surface 78


2.6.3.2- High strength pipes 78
2.6.3.3- The use of special materials 79
2.6.4- Intermediate jacking station 79
2.6.5- Overcut ratio 80
2.7- Concluding discussion 81

x
CHAPTER THREE 86

3· THE IDEOLOGY OF THE RESEARCH 87


3.1- Introduction 87
3.2- Methods of investigation 88
3.3- Factors influencing the jacking forces 92
3.3.1- Type of soil 92
3.3.1.1- Cohesive soil 92
3.3.1.2- Cohesionless soil 93
3.3.1.3- The density and dilation of 94
cohesionless soil
3.3.2- Overburden pressure 96
3.3.3- Overcut ratio 96
3.3.4- The size and length of a pipeline 97
3.3.5- Pipe surface 97
3.3.6- Pipe joint 98
3.3.7- The rate of jacking 98
3.3.8- Misalignment 99
3.4- Boundary conditions 99
3.5- Testing programme 101

xi
CHAPTER FOUR 103

4- MATERIAL CHARACTERIZA nON 104


4.1- Introduction 104
4.2- Geology 105
4.2.1- Leighton Buzzard sand 105
4.2.1- River (Concrete) sand 105
4.3- Material properties and laboratory testing 105
4.3.1- Particle size distribution 106
4.3.2- Density 107
4.3.3- Specific Gravity 108
4.4- Shear Resistance 109
4.4.1- Direct shear test 109
4.4.2- The triaxial test 111
4.4.3- Special shear test 112
4.5- Test results 114
4.5.1- Soil parameters and comparison of 114
shear resistance
4.5.2- Dilation, contraction and critical state of sand 117
4.6- The concept of soiVsoil friction and its relation 120
to soiVpipe surface friction
4.7- The need for laboratory testing and correlation 121
with pipe jacking scale model testing

xii
CHAPTER FIVE 123

S· EXPERIMENTAL STUDY OF PIPE JACKING 124


5.1· Introduction 124
5.2· Equipment 125

5.2.1· The test box 125


5.2.2· The test rig 127

5.2.3· Application of the overburden pressure 127

5.2.4· The model pipes 128


5.2.4.1- Concrete pipes 129
5.2.4.2· Steel pipes 130
5.2.5· The loading arrangement 130
5.2.6· The excavation technique 131

5.3- Instrumentation 132


5.3.1- Measurement of the jacking forces 132
5.3.2- Measurement of pipe displacement 133
5.3.3- Measurement of overburden pressure 133
5.3.4- Data logging arrangement 134

5.3.4.1- Signal conditioning module 134-


5.3.4.2- A-D converter 134
5.3.4.3- Micro-Computer 135
5.3.4.4- Displacement transducer 135
5.3.4.5- Load cell 136
5.3.5- Instrumentation accuracy and tolerances 136
5.4- Experimental procedure 136
5.4.1- Experimental preparation 137

xiii
5.4.2- Experimental installation procedure 137
. 5.4.3- Method of excavation 140
5.4.4- Measurement of overcut 141
5.4.5- Measurement of jacking forces and pipe 141
displacement

5.4.6- Completion of the test 142


5.5- Programme of experimental work 143

CHAPTER SIX 145

6- RESULTS OF EXPERIMENTAL WORK 146


6.1- Introduction 146
6.2- Preliminary test results 147
6.3- Main test results 148
6.4- Jacking forces behaviour 149
6.4.1- Overburden pressure 149
6.4.2- Overcut ratio 153
6.4.3- The type of soil 158
6.4.4- Pipe surface 160
6.4.5- Jacking distance 161
6.4.6- Pipe joints 161
6.5- Concluding remarks 163

xiv
CHAPTER SEVEN
164

7. INTERPRETATlONOF THE RESULTS 166

7.1- Introduction 166

7.2- Jacking forces 167

7.2.1- Penetration resistance 167

7.2.2- Frictional resistance 171

7.2.2.1- Effect of overburden pressure 177

7.2.2.2- Effect of jacking distance 181

7.3- Reduction of frictional resistance 183

7.3.1- Overcut ratio 183

7.3.2- Pipe joints 185

7.3.3- Soil/Pipe surface interface 186

7.4. Comparison between laboratory and model testing 188

7.4.1- Shear force 188

7.4.2- cJ>m value 197

7.4.3- Particle size distribution 199

7.5- Case studies 201

7.S.1- Tyneside sewerage scheme 201

7.S.1.1- Geology and construction operations 201

7.S.1.2- Drive (E w ·El) 204

7.S.1.3- Drive (E2-El) 20S

7.S.1.4- Drive (E3-E2) 206

7.S.1.S- Concluding discussion 207

xv
7.5.2- MI-Al Scheme 209
7.5.2.1- Geology and ground conditions of the area 209
7.5.2.2- Pipe jack details 210
7.5.2.3- Jacking forces 211
7.5.2.4- Conclusion 212
7.5.3- Previous studies 213
7.5.3.1- CIRIA technical Note 112 213
7.5.3.2- Herzog's investigation 215
7.5.3.3- Methods reported by 217
Stein, Mollers and Bielecki
7.5.3.4- Work by Auld 219
7.5.4- Concluding discussion 221

CHAPTER EIGHT 223

8- CONCLUSION AND FUTURE WORK . 224

8.1- Introduction 224


8.2- Jacking forces 224
8.3- Overcut ratio 226
8.4- Pipe/Soil interface and jacking forces 229
8.5- Pipe joints 230
8.6- Recommendationsfor future work 231

xvi
REFERENCES 234
BIBLIOGRAPHY 244
APPENDIX (I) : THE GEOLOGICAL AND PHYSICAL 250
PROPERTIES OF THE MATERIALS

APPENDIX (I1) : INSTRUMENTATION CALIBRATION 258


AND TOLERANCES

APPENDIX (HI) : PHOTOGRAPHS 260

xvii
Chapter 1 IntroductiDn

CHAPTER ONE

1 INTRODUCTION

1.1 TUNNELS AND PIPELINES

1.2 THE CONSTRUCTION OF PIPELINES

1.3 TRENCHLESS TECHNIQUES


1.3.1 PIPE JACKING
1.3.2 MICROTUNNELLING
1.3.3 AUGER BORING
1.3.4 EARTII DISPLACEMENT HAMMER
1.3.5 PIPE RAMMING
1.3.6 PIPE BURSTING
1.3.7 HORIZONTAL DRILLING

1.4 FACTORS AFFECTING THE CHOICE OF PIPELINE


CONSTRUCTION
1.4.1 ENGlNEERING COST
1.4.2 SOCIAL COST
1.4.3 THE SIZE OF THE MARKET
1.4.4 THE NEED OF THE CLIENT
1.4.5 THE COST OF 1RENCHLESS CONSTRUCTION
1.4.6 COMPARISONS BETWEEN· TRENCHlNG AND
1RENCHLESS PIPELAYING COSTS

1.5 AIMS OF THE RESEARCH

1.6 GUIDE TO THE THESIS

1
Chapter 1 Introduction

1 INTRODUCTION

1.1 TUNNELS AND PIPELINES

Ever since the world was created, nature has contributed to building passages and

tunnels through the ground. Since ancient times, when the civilizations began, men

have used tunnels for transporting peoples, goods and water . The first arched

passage was built in the 22nd century B.C under the temporarily diverted River
Euphrates in Mesopotamia (Szechy, 1966).

The Greeks, as poineers of ancient tunnel engineering, built a l000m long tunnel for

water supply on the island of Samos in the 6th century BC . During the Roman

Empire, many advances were achieved in road and tunnel engineering. Most of the

tunnels were built for water supply, especially those linked to the aqueducts

which supplied Rome with water . They also used underground passages for

drainage and sometimes for transportation (Szechy, 1966 and Beaver, 1972) .

These ancient tunnels were built by simple and crude methods using hard labour and

a large number of men. Only simple and basic tools and machinery were used

during construction. In modem history, tunnel building has changed dramatically

and become a more complicated process requiring special machinery, highly skilled

labour, large quantaties of materials and technical knowledge.

Different systems have been adopted in this century. The submerged tube technique
has been used for river crossings, in which the tunnel is prefabricated in long

2
Chapter I Introduction

lengths in a dry dock. Excavating machines working within a tunnel have been

developed and been combined with shields in very powerful tunnelling machines.

Ground treatment by injecting different types of chemical grout has improved the

ground conditions and reduced its permeability. Freezing can also provide

temporary strength and impermeability . In rock, rock bolting can be used as a

method of preserving the integrity of a rock mass during tunnelling . Sprayed


concrete lining, applied immediately after exposure, can prevent progressive

loosening of the rock.

As a type of tunnel, pipelines are constructed for a large number of reasons

including conveying water from springs, reservoirs or rivers, and conveying other

fluids and gasses. They also can be used for public utility services for carrying

power, telephone and other cables. Sewer pipelines are constructed for the removal

of domestic and industrial sewage. These pipelines are usually built in urban areas

and they commonly pass under roads and buildings. Construction of these pipelines

or tunnels can be carried out either by open cut excavation (trenching technique) or

by eliminating the necessity of open trenches and disturbance to the other services
(trenchless technique) .

The demand for new pipelines has increased in busy cities and under congested

urban areas, and there is also a growing need for replacement of existing pipes,
especially those built during the last century, which are wearing out.

---- -----------------------
Chapter 1 I ntroduc!ion

1.2 THE CONSTRUCTION OF PIPELINES

A pipeline is provided according to the basic requirements of the service it is to

provide . The size, shape, level, line and the length of a pipeline is chosen

according to the type of service and this information is used to determine the
installation techniques that can be used for the system. Pipeline systems have to

withstand the physical properties of the fluids or services that they are transporting
and the surrounding medium. They must also prevent the permeability of fluids

through their wall lining i, unless used as porous drains.

Installation of the pipelines can be achieved in many different ways . The

Babylonians, used a long tube of bricks, waterproofed with asphalt, for building

tunnels under water to provide a passage (Fry and Twaits, 1985) . Rock ducts were

used to form a tunnel called "quaats", which was used in ancient civilizations to

carry water from its source on a mountainside down to the valleys. The Romans
were perhaps the major pioneers of water supply systems, especially the aqueducts
which supplied Rome with water, (Szechy, 1966 and Fry and Twaits, 1985) .

The fIrst major use of tunnel construction in modern history began with the age of

canals. BruneI's great Thames tunnel was the first to pass under a tidal river and

was the fIrst shield driven tunnel. BruneI used the fIrst shield tunnel-lining due to

the difficulty of temporary support in poor soil conditions where the tunnel passed

under the bed of the river. He therefore suggested that they should open the ground
in such a manner that no more earth shall be displaced than is to be fIlled by the shell

or the body of the tunnel. The tunnel was built between 1825 and 1841 and

BruneI's shield was designed to provide a skin covering the ground on all sides, a

------
Chapter 1 Introductinn

means to suppon the face and yet provide access for excavation. He also devised a

method of moving the shield forward into the excavated space so that the permanent

lining could be built at the back (Boardman, 1960, Sandstrom 1963 and Beaver,

1972) .

Due to recent developments, pipelines can be constructed by two different methods,

depending on the structural requirement, kind of service and the economy of

construction. The first involves the use of the trenching system, where the pipeline

is positioned on a rigid bed after digging an open trench in the ground . This

method has the advantages of being cheap and easy to construct in open areas, but

requires deeper consideration in highly built up areas. It is thus most suitable for

laying pipelines through large, or green field sites or in areas where construction

access to the site is permitted and where there is minimal disturbance to the flow of

traffic above ground.

The second method involves the use of tunnels for opening a hole through the

ground with no disturbance to the soil on the top. This method requires traditionally

sufficient size for man-entry to allow excavation to be carried out at the front while

the lining is placed immediately behind . It is considered to be one of the most

difficult construction methods in civil engineering because proper site investigation


is needed, a high degree of accuracy is required for alignment and good planning for
the installation of the temporary and permanent linings . It is expensive and time
consuming, and can require large resources and a big construction site.

In Japan and Germany where microtunnelling was poineered, new microtunnelling

machines were developed for the demand of the market. Two machines emerged,

5
Chapter 1 Introduction

the Slurry Tunnel Boring machine (STB) and the Earth Pressure Balance machine

(EPB) (Moss,1989) . The EPB machines are most suited to cohesive and fine
grained soils, and they are also capable of handling coarse granular materials

including cobbles and even homogeneous rocks. Other developments include the
Super Mini Micro tunnelling system which was developed and used for many small
pipe jacking projects. The tunnelling method is based on the proven slurry shield
technology and the use of temporary pipes, a computer-aided control panel and a
laser guidance system (Hayashi and Miyata, 1989) . This machine is capable of
jacking pipes up to l5Qm with good accuracy, and having adaptable excavation

heads to suit almost all types of soils. The German Witt system was developed for a
full range of rnicrotunnelIing installations of pipe diameters ranging from 150 to
800rnm (Beaumount, 1989).

Underground services are usually encased in a pipeline to protect service lines and
fluid pipelines must have integrity to keep fluids flowing inside. The pipeline
should be capable of withstanding the overburden pressure from the soil above, in
addition to surface surcharges if applicable. It also should be durable against
corrosion from contact with the internal and external materials. Special pipeline
materials may be required when dealing with special substances or soils.

For most underground services, trenching systems have proved adequate for many
years, but recently tunnelling techniques have been prefered due to several factors.
These techniques, known as trenchless pipelaying techniques, will be fulIy
explained in due course.

6
Chapter 1 Introduction

1.3 TRENCHLESS TECHNIQUES

In recent years, there has been increasing concern at the total cost, both socially and
economically, of installing services in trenches and attention has focused on
trenchless pipelaying . Trenchless pipelaying includes the techniques of
microtunnelling, pipe jacking, pipe bursting, pipe ramming, moling and other
systems where small-diameter tunnels are constructed using remote-controlled
equipment where no man entry into the tunnel is possible or where hand excavation
is not practical for larger diameter tunnels.

Generally, tunnelling is a suitable method of constructing larger sewers in deep


significant
ground without causing any'disturbance to the surroundings. As a result, different
manufacturing industries have developed and supplied suitable boring equipment,
both manual and remote-controlled. The introduction of different methods of

excavation has occured to meet the growing demand for such technology. These

initiatives have resulted in a reduction in the size of pipes that can be installed
trenchlessly .

The estimation of the potential market for trenchless techniques has fluctuated in
different countries. Three countries, Japan, West Germany, and the UK, appear to
have established a significant lead over other countries in adopting this technique. In
both the UK and West Germany, the technique has developed due to the density of
! ageing urban infrastructure in which new underground services are needed . In
Japan, the need for less disruptive construction methods arises from the need to
install new pipe infrastructures within cities that do not have them.

7
Chapter 1 Introduction

Irvine (1985) concluded that non-man entry tunnels are cheaper than pipe

construction in manually excavated tunnels. In bad ground the costs of forming a

man entry hole by pipe jacking, segmental tunnelling and minitunnelling are all very

similar. Man entry tunnel and pipe jack systems become less competitive for the

smaller size of service pipeline because the excavation and installation of the main

lining are in effect temporary works allowing the construction of the main pipeline.

However, if the unused part of the tunnel space could be used for installing other

services, then the unit costs would be reduced considerably. The provision of a

tunnel is an asset which may be underused in economic tenus if only one service

runs through it, and the provision of easy access may reduce the maintenance cost.

Akesaka & Rooke (1985) suggested that both the manufacturers of machines and

contractors can provide the necessary equipment for trenchless construction, but,

without a real market, the experience required to improve the techniques and reduce

the cost of site operations will not be obtained. The potential benefits to the industry

will therefore never fully materialise.

They list the main disadvantages of trenching as

1. Permanent reinstatement for public utilities is necessary

2. Damage to roads, especially with deep trenches

3. Damages to pipes and cables

4. Damage to the ground in deep excavation

5. Distruption of traffic

6. Disruption to trade

7. Damage to small volume roads caused by diversions

In addition, the problems of noise, dirt and smell are all mainly overcome

- - - - - - - - - --_. -_.
Chapter 1 Introduction

by using trenchless techniques .

According to Jones (1987), the interest in trenchless construction techniques has


accelerated recently, especially if conventional tunnelling is discounted. An

introduction to trenchless systems is given in the following sections.

1.3.1 Pipe Jacking

Pipe jacking is a technique of jacking prefabricated pipes into the ground while

excavation is carried out at the face of the pipeline (Figure 1.1) . It is suitable for
most soil conditions including rock, sand and clay, whether below or above the
water table . The pipe diameter typically ranges from 900mm up to 2500mm,
although in some cases larger sections can be used. The technique has been
described by Drennon (1979), Pipe Jacking Association (PJA, 1980) and Clarkson
and Thomson (1983) .

The jacking process can be divided into two stages. Face excavation is usually
carried out manually, but over recent years excavation machines of ever-increasing
sophistication have been introduced. The leading pipe is fitted with a steel shield

that has a cutting edge. A set of steering jacks are positioned between the leading
pipe and the shield to control the direction of the shield, and hence the excavation by
trimming the excavation as it is jacked forward. The spoil is extracted by means of
muck trains on rails or a conveyor belt .

The pipes are then jacked immediately behind the shield from a jacking pit. The
jacking pit consists of a set of hydraulic rams or jacks placed in the line of the drive

9
Chapter 1 IntroductiDn

and load transfer units, or spacers, provide the connection between the jacks and the

pipes. The jacks are positioned against a wall which is designed to provide an
adequate reaction to the forces generated during jacking and to distribute them to the
soil .

The length of the jacked pipeline in a single drive is dependent on a number of


factors. Higher jacking loads are needed for longer drives, and these loads are

related to the surface friction between the pipe and the soil and also to other
parameters, notably face resistance. Bentonite slurry lubrication and intermediate
jacking stations can be used to reduce the magnitude of the jacking loads required to
advance the pipe and therefore to achieve longer drives. Intermediate jacking

stations, consisting of a number of small jacks equally distributed around the


circumference, are placed between two pipes in a steel housing at regular distances
along the pipeline, depending on the total length of the pipeline and on the magnitude
of the jacking forces.

Different types of pipes can be used, such as concrete, steel, clay, ductile iron,
plastic, glassfibre reinforced plastic (GRP), glass reinforced concrete or a
combination of these materials. Concrete pipes are most commonly used except
when special circumstances exist, and these may be reinforced or unreinforced .

1.3.2 MicrotunneIling

Microtunnelling usually refers to the equipment used for installing smaller diameter

pipes in the range 250 to 900mm . MicrotunneIling machines are one of the most

significant and sophisticated developments in the field of trenchless pipelaying .

10
Chapter 1 Introduction

Microtunnelling was fIrst developed in Japan in the 1970sas part of the existing
sewer installation programme. (Hayashi and Miyata, 1989) . More recently, West

Germany has undergone a large sewer installation programme, most notably in


Hamburg (Kuntze, 1985), while in the UK and USA microtunnelling machines
have steadily been introduced (Beaumount,1989) .

Microtunnelling is a technique used for installing pipes by means of

remote-controlled excavating machines where man-entry is impossible. It is also


known as small bore pipe jacking (Kraeme-Wasserka, 1987) . The principle behind
the technique is similar to that of pipe jacking, except that most of the operation is
carried out by remote control (Harding, 1981) . There are two types of
microtunnelling machines, slurry shield and steerable bores, and these will be fully

discussed in later sections . Slurry shield machines have the advantage of being

comparatively easy to use within ground water without extensive prior treatment of
the ground and/or the use of compressed air . It is suitable for virtually all types of
ground and has an operational distance of up to 200m .

1.3.3 Auger Boring

Auger boring is the technique of creating a hole through the ground from which the
excavated spoil is removed by the rotating action of auger drills (Thomson, 1967) .
It is one of the oldest forms of horizontal boring and has been available since the
early 1940s . The process is illustrated in Figure 1.2.

The boring unit, which is set up in the bottom of a shaft, consists of the boring

machine and a base . The boring machine provides the rotational power to the

11
Chapter 1 Introduction

augers. The base supports the machine and provides the forward and reverse

motion by means of a thrust mechanism. There are two basic types of boring unit in

use, the co-axial thrust ram type and the scissor ram type. The boring unit is

supplied by hydraulic power produced by an above ground unit. The speed of

rotation and the size of the bore is dependent on the type of machine and the specific

boring requirement.

Auger heads are used as the cutters for forward boring, while reamers enlarge the

hole when pulled back towards the machine by the augers. Different heads are

available for clay, hard or soft mudstone and basalt. Augers and extension rods are

used to transmit the thrust and rotation to the head .. and at the same time to transfer

the spoil from the head to the shaft. There are different sizes of augers depending on
the required pipeline diameter. Extension rods are jointed, using either spring clips

or bearings on wheels. Normally the length of the augers and rods are 900mm,
although other lengths can be obtained.

There are two methods of auger boring. The fITst involves separate casing, in which

the hole is first completely augered out and the casing or pipe is driven into the hole.

The second method involves simultaneous casing where the casing is inserted as the

hole is augered out. The latter is clearly necessary in unstable ground and is more

similar to pipe jacking, whereas the former is more similar to tunnelling in relation to
the response of the ground (Munro and McMurdie, 1985) .

The boring proceeds after setting the equipment in position . Boring starts with

screw-jointed lead augers. More auger flights are added as the bore progresses until

the flight length reaches the distance between the driving and the fITst reception

12
Chapter 1 Introduction

shafts . Extension rods are then added and boring continues to the second and
subsequent reception shafts. Spoil removal takes place from the last shaft that the
head had passed through. When the bore is completed in one direction, it can be
either reamed out to a larger diameter, or the rods and augers can be withdrawn to
the machine shaft and removed. When the boring is completed, the shaft is filled to
just below the invert level of the pipe. Pipes are then sequentially jointed and
pushed along the proposed line by the boring unit or by a jack. In unstable ground
and where no reaming is required, the pipes can be inserted progressively behind the
lead auger.

The range of casing diameters installed by auger boring equipment is typically from
150mm to l500mm . The driving range can be from 30 to 50 m, and over lOOm has
been achieved on some occasions. It is mainly a soft ground technique, although it

has been used in soft rocks. Its accuracy depends on many factors, such as the size
of the sleeve (the bigger the bore the less the deviation), the rotation of the augers
and other constructional factors (Thomson, 1985 B) .

1.3.4 Earth Displacement Hammer

Earth displacement hammers are a noh-steerable means of trenchless pipe and cable

laying, and are commonly known as impact moles. They were introduced and
developed in Eastern Europe . They have now become more sophisticated and
include equipment which can be recovered if faced with difficulties in overcoming
the ground conditions. Modifications include reciprocating heads, which have a
better impact at the face. The technique is commonly used for telecommunications

because of the portability, and low capital cos~ofthe equipment (Etherton, 1985).

13
Chapter 1 Introduction

This method is based on compressed air powered impact, or percussive, moling

. which forms a hole through the ground by compacting or consolidating the

surrounding soil . There are two types of hammer, having either a fixed or a

moving head.

The technique is ideally suited to service connections and short, small diameter

drives. Its installing accuracy is mainly dependent on the direction of the initial

launching, the ground conditions and the machine characteristics. The type and the

moisture content of the soil can affect the operating performance, since the stronger,

stiffer and denser the soil is the more difficult it is for the machine to displace the

ground. In this respect the ability to generate and sustain pore water pressure in the

soil will affect the ease of advancement. Therefore more resistant;, . soils reduce the

driving distance and slow the progress of the operation.

The operating size ranges from 50 to 175rnrn in diameter, and pipes can be driven up

to 30m . It is typically suitable for medium stiff to moderately soft soils, control of

line and level being lost in very soft soils.

1.3.5 Pipe Ramming

Pipe ramming, also called impact ramming, uses a particular type of earth

displacement hammer. It is considered to be an alternative to pipe jacking, but it is

less steerable and this can be a problem when installing sewer lines. In simple

terms, the hammers are positioned in the start shaft and are connected to the pipe to

be driven through adaptors. The pipe has a cutting shoe attached to its front end.

The spoil enters the sleeve as the pipe is rammed into the ground and can be

14
Chapter 1 Introduction

removed at the end of the ramming operation by auger, water jet or compressed air.
Steel pipes from 400 mm to up to 1200mm diameter are typically installed by this
method. One major operational disadvantage is the time taken to weld lengths of

pipes together. It is suitable for most soil types, including strong soils, and the
driving distance can reach up to 35m .

1.3.6 Pipe Bursting

Pipe bursting is the method of inserting a new pipe into an existing pipeline of an
internal diameter equal to or slightly smaller than its replacement by means of
fragmenting the existing pipework and forcing the material into the surrounding soil
to form access for the following replacement pipe (Poole et aI, 1985) .

It is mainly used for gas main replacement since it is a renovation technique that can
be used for maintaining or increasing (up-sizing) the capacity of the original line . It
was originally developed in the UK for British Gas .Development work is being

carried out to improve reliability in replacing larger diameter sewer pipes. Up-sizing
at small diameter is standard practice for this technique, but some side effects may
develop such as ground pressure on adjacent services and structures . New

developments have recently been adopted. such as hydraulic methods of pipe


bursting which apply direct radial force on the old pipe to break it .

It can be used to replace different varieties of pipe materials such as concrete, cast
iron. uPVC, virtifiedclay and asbestos cement. Machines were typically available
for pipes ranging in diameter from 200 to 300 mm, but a greater size range now

exists.

15
Chapter 1 Introduction

Other replacement techniques are available, including pipe excavation, extraction, or

excavation and swaging, and rolldown methods, but these will not be considered
herein.

1.3.7 Horizontal Drilling

Drilling is a method of laying cables and pipes in variable ground conditions without

other excavation. This technique is based on oilfield drilling technology, using a shoe to

deflect the mud and drill at the required angle under the obstacle to form a pilot hole.

This method was developed in the USA, where it has become established, and it is

growing elsewhere around the world (Hair and Shiers, 1985, and Turner, 1978),.

Drilling is used for the rapid installation of pipelines under large obstacles, such as

rivers or embankments, (Szczpak, 1989) .;The diameter range is 50-1000mm, and

distances up to 150m can be covered in a single operation. This method is ideally

suited to smooth profile pipelines with joints resistant to tensile forces, such as the

welded steel pipelines used for oil, gas or water transmission and cable conduits.

The drilling method is carried out by a smooth curved pilot hole of 70-80mm in

diameter (Figure 1.3) . The pilot hole follows the proposed centreline of the

pipeline. The ground entry angle on one side (entry pit) is usually 5-20 degrees and

the drilling line passes through a sagbend . Once the pilot hole has passed by the

obstacle, it rises through another sag bend to the exit on the other side at the
predetermined target peg and at an angle to the horizontal of around 8 degrees. The

pilot hole is drilled by a specially built rig which pushes the drill rods into the

ground. The progress of the pilot hole is recorded by a specially designed steering

16
Chapter 1 Introduction

tool system . Both the drilling and steering operations are controlled using

immediate feedback of the drill bit position, which allows the pilot hole to be rapidly

drilled along the designed path. This method is suitable for firm to stiff clay and

coarse sand up to 2 mm particle size.

It can be concluded from the above discussion that trenchless systems should be

chosen to suit the required utility . Microtunnelling is a type of trenchless

construction that most public authorities and engineers see as the appropriate

technology for such construction for the present and the future.

1.4 FACTORS AFFECTING THE CHOICE OF PIPELINE

CONSTRUCTION

The demand for NO-DIG techniques has increased in comparison with other

trenching techniques over the past few years. This change has radically affected all

of those who work within the statutory authorities, consultants, pipe suppliers and

manufacturers of the equipment. It is important to realise that the public will gain the

most from these techniques, if trenchless construction techniques dominate future

construction trends, by not being affected by the construction. In addition to this

social advantage, it is essential to emphasize the need to provide new services, and

maintain and refurbish the old systems, with the minimum overall expenditure and

with the maximum overall effect.

The demand for the trenchless techniques is dependent upon factors such as, the size

of the market, the needs of the client, the cost of trenchless construction , and the

17
Chapter 1 I ntroductfon

social cost.

During recent years there has been increasing concern at the total cost of installing
services in trenches. It has been increasingly appreciated that in addition to the direct
costs of the works on site there are significant additional social costs, particularly in
urban areas . The development of alternative trenchless construction has been

stimulated by the prospect of reducing the social costs while trying to achieve direct
costs which compare favourably with those oftrenched construction (Iones, 1987).
The cost of a proposed pipeline scheme will be treated under the two main cost
headings of Engineering Cost and Social Cost in this section (Green and Wood,
1987) . A breakdown of these costs is given in Figure 1.4 .

Flaxman (1993) reported that the cost of trenchless methods is falling as their use
has been more widely adopted during the past ten years. Trenchless methods for
new installation are also increasingly competitive with open cut.

1.4.1 Engineering cost

This refers to the total incurred cost of the whole pipeline scheme regarding
planning, engineering and construction, including public planning and preparation.

Engineering cost can also be split into the two categories of direct cost and
indirect cost.

The direct cost is the cost of physically constructing a pipeline project including
planning of the scheme, design and specification, other consultancy aspects, and the

construction work. The latter includes the cost of the materials, machinery and the

18
Chapter I Introduction

cost of carrying out all temporary and permanent works .

Indirect costs are considered to be those incidental costs arising from the
construction of the pipeline, and can include the following:

(i) The cost of road reinstatement, and / or ultimate reduction in design


life of the road.

(ii) Any damage caused to other utilities during construction, including

existing cables, ducts, pipes and other services . In addition, any damage
caused by gtound movement to surrounding buildings and structures.
(iii) Loss of other utilities and services when mains and cables are needed

to be shut down during construction, and damage caused by overloading


the remaining infrastructure.

(iv) Damage caused to adjacent roads, often Iow volume roads, by diversion
of traffic onto them during construction.

1.4.2 Social cost

The social cost cannot be defined precisely, and sometimes as a consequence it is


ignored or underestimated when preparing the contract and tender documents. The
social cost is mainly concerned with the public and public services. It can be divided
into many catogories .

Construction of a pipeline can cause disrnption of traffic in the form of delays and
diversions, and hence increase the journey times and consumption of extra fuel
which can damage the environment. It also creates more congested traffic around

the working area and consequently disturbance to residents and businesses. Loss of

19
Chapter 1 Introduction

business can also result from diverted traffic and the difficulty of conducting a

nonnal business without regular passing customers or easy access. Closing roads

around the working area could cause a problem for delivery vehicles and prevent

customer access totally (Glennie and Reed, 1985) .

Open cut excavation typically causes more long-tenn damage to the road surface than

trenchless techniques. The extent of the damage is dependent on the quality and type

of the road construction. The reinstatement of a damaged road can not be carried out

to the same quality as the original, in general. Therefore, the overall expected life of

the road is reduced considerably and more money is needed for subsequent repairs.

Also damage to adjacent roads can occur by the extra diverted traffic that it has to

carry while construction is taking place.

Settlement, and sometimes heave, at the surface, and underground movements can
also be caused by open cut excavation and consequently wi11 qffect the foundations

of buildings and other structures adjacent to the site . Structural defects and

defonnation of cladding and services are all symptoms of soil disturbance around the

influence zone of building foundations. The type of soil can contribute greatly to

the seriousness of these faults.

In addition, trenchless techniques usually cause less noise, smell, dirt and visual

intrusion. No large machinery is required at the surface at any point along the

proposed line of the pipeline. Spoil can be disgarded cleanly and no dirt need be

created in the surrounding areas. Only a small working area is required, when

compared with other types of tunnelling and open cut excavation, and consequently

the work can be carried out without the notice of, or inconvenience to, the public at

20
Chapter 1 Introduction

the surface. Finally, the construction site looks tidier and cleaner than conventional

sites and that is a considerable advantage when construction is taking place in the

heart of the big cities and busy urban areas.

1.4.3 The Size of the Market

Whatever criteria may be examined in determining the size of the market, a

potentially huge volume of work is available for application of trenchless methods.


The trenchless revolution has already started, which is evidenced by the work

underway in Japan, West Germany and the U.K.

Thomson (1985A and 1985B) and Elvidge (1987) have assessed the size of the total

market. The utilities throughout the western world ins'tall approximately 600,000

km of pipes and cables per annum. Notthen American and European markets

combined account for 400,000 km of services per annum, while including those of

Japan and S.E Asia probably brings the total up to around 500,000 km per annum.

Figure 1.5 shows the size of the total market of utilities instaIlation for different pipe

diameters. Moss (1989) has studied the market potential between the water

authorities and the pipe jacking contractors by listing pipeline contracts in tennsof

size, depth, position and overall cost. The results show that a likely market of
some 20-30 km a year exists.

1.4.4 The Need of the Client

The client's decision in selecting the type of trenchless technique to be used is

considered to be the key factor in evaluating the future markets for trenchless

21
Chapter 1 Introduction

pipelaying . In order to consider which pipelaying technique to use, the client must
differentiate between the cases of mains services running below a road containing
existing services, the crossing of a road, railway or similar obstacle and replacement
of existing services. The client must also know the cost effectiveness of the
trenchless techniques when compared with alternative methods and have an
independent evaluation of the different current techniques available for trenchless
pipelaying .

Thomsom (198SA and 1985B) listed the characteristics that the client may be
seeking when considering trenchless techniques as
I-Length of the pipeline
2-The diameter of the pipeline
3-Installation without damage to existing services and structure
4-Ability to overcome minor obstructions occuring in the ground
S-Ability to work in different soil conditions
6-Ability to work in unstable ground
7-Ability to work below the water table
8-Bore tracing location
9-Steerability
10-Installation of final service to accurate line and level
11-Installation of flexible service to a reasonable line and level
12-Installation of duct in which the service is to be threaded
13-Routine operation with own men
14-Work from restricted access sites
IS-Simple and economic drive shafts coinciding if possible with
permanent access chambers

22
Chapter 1 Introduction

16-Need to make lateral connections without disturbance.

1.4.5 The Cost of Trenchless Construction

Economic studies by Irvine(1985)and Newman(1986)are concerned with making

comparisons between a number of alternative ways of investing resources in order to

select the one which gives the optimum future return for the investment. The

difficulties of economical comparisons in this area are the problems in assessing the

true initial cost of a project since this can be greatly influenced by the social cost

within the economic system.

Judgements vary on the degree of responsibility for risk and damage, and hence on

what constitutes an element of direct cost. The risk oflong-term damage to adjacent

roads, buildings and services must be increased whenever ground is disturbed by

construction and the cost of this damage will be ultimately paid by the owners of the

damaged items. Therefore, to simplify the study of direct cost it has generally been

limited to a comparative assessement of the contractor's costs plus the cost of design

and supervision for sewers up to 2000mm diameter by the following methods.

(i) Traditional pipelaying in trenches

(ii) Trenchless pipelaying techniques

(ill) On-line replacement of pipes

(iv) Renovation of existing pipes

23
Chapter 1 Introduction

1.4.6 Comparisons between Trenching and Trenchless Pipelaying

Costs

In order to compare the costs of trenchless pipelaying with trenching, it is important

to examine the indirect costs and the social costs in addition to the actual direct
contract cost. Considerable work has been done to show that the social costs that

arise from engineering work could be a significant factor in the overall cost of a

project (Glennie and Reed, 1985) .

Social costs in certain critical locations can be several times higher than the direct

construction costs, and those locations tend to be in busy city centres and urban

areas where a substantial amount of rehabilitation of public services is being done.

Trenchless techniques reduce the social cost significantly, but do not eliminate them,

as was shown for a typical case by Flaxman in 1985 (Figure 1.6).

Flaxman (1993) stated that with trenchless methods now often being cheaper

(in direct cost) than the open-cut alternative, this is unlikely to be necessary in many

cases. The avoidance of social costs in such circumstances is an added bonus to the

community, but it does not need to be calculated .

Studies in this field have been conducted at UMIST, Middlesex Polytechnic and the

WRC and these show that evaluation of the social cost is possible in some cases and

depends on the type of trenchless technique being used. Further studies are being
out
carried"with the aim of greatly reducing the social costs as trenchless techniques

improve in the future (Green and Wood, 1987).

24
Chnpter 1 Introduction

l.S AIMS OF THE RESEARCH

This research work was introduced to study the jacking forces, with regard to

different parameters, for pipe jacking operations. Any investigation of this kind will

require the use of controlled experimental conditions in which variation of different

specific experimental factors may be examined, and care was taken to achieve this in

the research work presented in this thesis.

After a thorough review of the literature, it was proposed that a scale model
apparatus should be built at Loughborough University. The adoption of scale model
testing was dictated by economical aspects and the testing facilities available in the

laboratory. All other experimental factors and boundary conditions were considered

thoroughly, together with the pipe materials used and jacking operations followed,

after which the experimental work commenced. Consistency was maintained

during all experimental work for the provision of analytical data results in relation to

a spectrum of parameters that will be fully discussed later on .

The primary aim of this research is thus to study the factors that influence jacking

forces during pipe jacking operations. This type of work has never been executed
under controlled laboratory conditions. Therefore the design of a scale model testing

facility, which takes into consideration the influence of boundary conditions on the

results and which will allow an accurate simulation of actual pipe jacking to be

achieved, was necessary. By employing scale model testing, both the magnitude

and behaviour, or pattern, of these forces can be studied and recommendations for

practice can be made .

25
Chapter 1 Introduction

Knowledge of the jacking forces is essential in practice and their definition under

different conditions will provide the means for more efficient pipe designs. thrust

walls. definition of numbers and capacity of the jacks. and consequently estimation
of jacking length for various ground conditions. In addition. it is anticipated that

the friction between the surface of the jacked pipeline and the surrounding soil will
contribute greatly to the magnitude of forces generated during the operation.

Therefore. the material used in manufacturing the jacked pipeline should be studied.

together with different surrounding soils.

A further factor that can be varied in practice to reduce the jacking forces is the
overcut ratio. This determines the amount by which the soil can collapse onto the

pipeline once the shield has passed. and thereby will also set up arching mechanisms
within the soil above the pipeline.

Although the results of this research work will depend upon the effects of the

experimental boundary conditions. with careful interpretation they will nevertheless


provide the basis for proper engineering design and good installation practice for

jacked tunnel linings. as well as the basis for further scale model testing.

26
Chapter 1 Introduction

1.6 GUIDE TO THE THESIS

The research work reported herein is based on well-defined methods of investigation,


'as follows

Chapter one provides an introduction to work relating to all pipelines and small
tunnels. It also acknowledges the role of trenchless technology in engineering
practice and explains the methods of construction available in practice. The cost and
other factors that affect the market's capacity for this work are also reviewed.
Finally the aims of the research are presented.

A thorough review of the literature on this subject is given in chapter two. The

review was conducted to determine whether sufficient information relating to

methods of investigation was available for pipe jacking techniques and to establish
what is known, either by experiment or practical knowledge, about the jacking
forces expected under different site conditions . A summary of all relevant

published work is given. Finally a comparison of the methods of investigation of


various researchers is: tabulated in order to give a clear indication of their
achievements .

Chapter three describes the philosophy behind the research work and the methods of
investigation chosen for this work. It also includes a discussion of the factors that

might influence the behaviour of the jacking forces and the effect of experimental
boundary conditions .

27
Chapter 1 Introduction

The characterisation of the soils used in the experimental work is fully described in

chapter four . Details of the experimental programme, the equipment and

instmmentation developed, and experimental procedures are given in chapter five.

Chapter six presents the experimental results obtained during the research work, and
discusses them in the light of previous research and existing theories.

The interpretation of the results is given in chapter seven, together with a number of

case studies which examine the findings of this work in relation to practical
situations .

Conclusions and recommendations drawn from research work are given in chapter
eight, together with suggestions for further work.

Finally, the geological and physical properties of the materials used during the
course of the research, as provided by the suppliers, are shown in appendix I .

Calibration tolerances of the instmmentation used to monitor the results are given in

appendix 11 . Appendix ill illustratesthe experimental equipment and instmmentation


in a series of coloured photographs with relevant text section reference number
shown at each plate title.

28
10 ___......_ _--.

11

1- Cutt!n~ Shield
2- Muck Container
3- Muck Rail
4- Intermediate Jacking Station
5- Thrust ring
6- Spacers
7- Hydraulic Jacks
8- Jacking Wall
9- Power Unit
10- Crane
11- Jacking Pipes
12- Jacking Shaft
13- Soli

1 2 3 4 12 13

Figure 1.1 General Arrangement of a Pipe Jacking Operation


1

1- Cutting head
2- Steady bearing
3- IntelIDediate shaft
.4- Driving and bearing rods
5- Pipe Jack
6- Machine shaft
7- Boring unit
8- Soil

Figure 1.2 General Arrangement of an Auger Boring Operation


1· Target point
2- Pilot hole
3- Washover pipe
4- Selting point

1- Pipe line
2· Swivel
3· Barrel reamer
4· Fly cutter
5· Washover pipe

Figure 1.3 Horizontal Drilling


(a)-General Arrangement
(b)-Detail of Head Of Back Reaming Operation
1500 1· DIRECT COST ENG.COST
m BUS.LOSS
o CLAIM
• TOTALCOST
1000 I~ __________

500

TRENCHING TRENCHLESS

1500 2· SQClAL COST I2l


o DAMAGES

~ 1000r~---------
o
o
§
l-<

8 500~=~~

TRENCHING TRENCHLESS

3000 3· TOTAL COST E::2I DIRECT COST


o SOCIAL COST
TOTAL COST

2000

1000

TRENCHING TRENCHLESS

Figure 1.4 Comparison of Cost Between Trenching and Trenchless


Techniques for a Pipeline (after Green and Wood, 1987)
Figure 1.5 Underground Installation Expenditure by Diameter
Catagortes: Around The World (after Thomson 1985)
COST (£OOO'S)

I
o 10
STRAIGHT FORWARD CASE
TRENCHING

PROBLEM CASE
TRENCHING ,. .. ..,..,
, , ,."
......
"'... ,'/.,.'.
.. .., ... ,

Figure 1.6 Total Cost Of Pipelaying to the Communlly (after Flaxman,1985)


Chapter 2 Review of Pipe Jacking

CHAPTER TWO

2 REVIEW OF PIPE JACKING

2.1 INTRODUCTION AND BRIEF HISTORY OF PIPE JACKING

2.2 INSTALLATION METHODS


2.2.1 INTRODUCTION
2.2.2 PIPE JACKING TECHNIQUES
2.2.2.1 THE JACKING SHAFT
2.2.2.2 CONVENTIONAL PIPE JACKING
2.2.2.3 MECHANISED PIPE JACKING
2.2.2.4 UNI-TUNNEL SYSTEM
2.2.2.5 LARGE-BORE PIPE JACKING

2.3 SOIL MECHANICS ASPECTS OF PIPE JACKING


2.3.1 INTRODUcrION
2.3.2 THE THEORY OF GROUND PRESSURE ON TUNNELS
2.3.3 TUNNELS THROUGH SOFT GROUND

2_4 JACKING FORCES


2.4.1 INTRODUCTION
2.4.2 THEORETICAL ANALYSIS
2.4.2.1 CIRIA APPROACH
2.4.2.2 AULD'S ANALYSIS
2.4.2.3 HASLEM'S ANALYSIS
2.4.2.4 JAPANESE ANALYSIS
2.4.2.5 HERZOG'S STUDY
2.4.3 EXPERIMENTAL AND FIELD INVESTIGATIONS

29
Chapter 2 Review of Pipe Jacking

2.5 FACTORS AFFECTING THE JACKING FORCES


2.5.1 TYPE OF SOIL
2.5.2 AMOUNT OF OVERCUT
2.5.2.1 NON-CLOSURE OF OVERCUT
2.5.2.2 CLOSURE OF OVERCUT
2.5.3 OVERBURDEN PRESSURE
2.5.4 MISALIGNMENT
2.s.5 THE SIZE AND LENGTH OF THE PIPELINE
2.5.6 THE JACKING RATE

2.6 METHODS OF REDUCING JACKING FORCES


2.6.1 INTRODUCTION
2.6.2 LUBRICATION
2.6.3 SPECIAL JACKING PIPES
2.6.3.1 PIPE SURFACE
2.6.3.2 HIGH STRENGTH PIPES
2.6.3.3 THE USE OF SPECIAL MATERIALS
2.6.4 INTERMEDIATE JACKING STATIONS
2.6.5 OVERCUT RATIO

2.7 CONCLUDING DISCUSSION

30
Chapter 2 Review of Pipe Jacking

2 REVIEW OF PIPE JACKING

2.1 INTRODUCTION AND BRIEF HISTORY OF PIPE JACKING

Tunnels are used as a convenient method for conducting public services in densely

populated areas . The increasing demand for construction and renewal of the

underground public utilities in urban areas around the world has led to the introduction

of trenchless construction techniques as an alternative to traditional trenching .

Trenchless construction has developed over recent years, with the aim of reducing the
social costs and damage to existing surroundings caused by pipelaying . Pipe jacking

is one of the trenchless construction systems that is widely used in urban areas for

construction of tunnels ranging from 800mm to 3000mm or more in diameter.

Pipe jacking was fIrst introduced in the USA in the late 1890s as a means of culvert

installation without surface disruption (Drennon, 1979) . It was introduced in the UK

in the late 1950s, mainly for use in tunnels of short length to cross roads or railway

embankments. At this time a sleeve was constructed and the pipe was installed at a

later time. Thus as a lining installation method, rather than as a tunnelling method,

pipe jacking has been in use in the UK for over 25 years, chiefly with a manual means

of soil extraction (Jones,1987). Pipe jacking has become increasingly popular over

the last 15 years, particularly in Japan and West Germany where major works have
been undertaken (Clarkson and Thomson, 1983) . These countries started to use pipe

jacking in thel960s, and now lead the world in research and development of the

technique.

31
Chapter 2 Review of Pipe Jacking

Pipe jacking is generally accepted as a good ground technique for both short crossings

under roads, rivers and canals, embankments and railways, and for multiple length

contracts. In unstable ground, chemical stabilisation and suspension grout have been

used for ground stabilisation and control of water. The technique has the advantages

of a good quality tunnel lining, little risk of settlement during and after construction,

and speedy construction. It is often used for short drive lengths, but by reducing the

. jacking resistance by lubrication and using intermediate jacking stations, longer drives

are possible.

There are three methods of pipe jacking: jacking a pipeline with hand excavation at the

face, jacking a pipeline with mechanical excavation, and the Uni-tunnel system.
Mechanised excavation methods have been introduced relatively recently and many

pipelines are currently being constructed in the UK by these methods. The Uni-tunnel

system was introduced in 1980, but has not been used much.

Alternative tunnel linings are available and are often found to be acceptable, especially

in soft ground tunnelling projects. The engineer must assess the benefits of using
such alternatives, together with cost and risk involved . Usually the cheapest

alternative is adopted.

Hough (1986) cites the lack of research into pipe jacking techniques in the UK as the
reason for the uncertainty in its use, whereas West Germany, Japan and the USA have

invested more in pipe jacking research and now are more innovative. In 1980 the Pipe

Jacking Association (PIA), with coorperation from the Construction Industry

Research and Information Association (CIRIA), instigated research that has

influenced the design of jacked pipes and joints. The PJA required three optimum

32
Chapter 2 Review of Pipe Jacking

design points to be researched with regard to the joint. These were:

1. the specified thrust it would sustain during jacking

2. the angnlar deflection allowable during jacking, and

3. the external hydrostatic loading design.

Following this the PJA summarised the need for future research into five main areas as

follows:

I-The likely future markets.

2-Pipe joint design.

3-Joint packings and the effect of jacking misaligned pipes.

4-Pipe lubrication.

5-Establishment of" friction values" for soil.

The need for research was further highlighted by Craig (1983) in his state-of-the-art

review on pipe jacking for CIRIA . The main areas in which research was thought to

be needed were: friction loads in different types of ground condition, load-deflection

characteristics of the joints with different packing materials, the effect of cyclic

loading on the pipes at intermediate jacking stations, the effect of lubricants on

reducing friction along a pipe, and the development of a site investigation test suitable

for predicting frictional forces. Research work has been initiated in some of the above

areas.

Research work is being done in different countries, the most notable being Japan,

West Germany, the USA and the UK. The main aims of the work are to create an

understanding of the behaviour of jacked pipes and develop methods of design and

production of the basic elements of pipes and joints.

33
Chapter 2 Review of Pipe Jacking

The UK research programme has been summarised by MiIIigan (1986). Research is

being supported by the PJA in conjuction with the Science and Engineering Research

Council (SERC), after both the PJA and CIRIA promoted the programme. SERC

have been developing a programme of research work in civil engineering with a strong
emphasis on testing at large or full scale. This programme has included work at

Oxford University to investigate the load transfer between pipes and the contact

pressures between pipes and soil for misaligned pipes, using model pipes in a test rig

in the laboratory (Milligan and Ripley, 1989) . This work has been extended into the

field, with the first field work project being recently completed (Norris, 1993) . It also

includes research into the mechanisms controlling the deformation of soil around

trenchless pipelaying operations at Loughborough University of Technology, a project

that is complementary to the research reported herein (Chapman and Rogers, 1991).

Haslem (1986) describes the development of a method of predicting jacking forces

related to the ground conditions and including the effects of lubrication by bentonite

slurry. Most of the work has been based on field observations from contractors,

supplemented by laboratory tests on samples of the materials through which the

tunnels were driven.

In West Germany the ministery for research and development implemented a

programme in Hamburg in 1981, which succeeded in improving the performance

characteristics of the Tele-Mole system. In addition to tunnelling machine

developments, research was also concentrated on pipes for jacking systems, with the
particular aim of providing maximum resistance against corrosion (Stein and Bielecki,
1984) .

34
Chapter 2 Review of Pipe Jacking

In Japan, pipe jacking is a well-established technique for sewer construction with

a length of about 400 km per annum being constructed (Thomson,1982).

Downey (1984) has shown that there is a clear trend in the Japanese pipe jacking

industry of increasing mechanisation and sophistication due to the evident popularity

of this method of construction .

Pipes are also being developed in Japan. Glass reinforced concrete jacking pipes have

been developed by the Japan Superline Pipe Association using technology licensed

from the UK . Laboratory tests have shown that the pipes have high axial compressive

strength and are particularly suitable for long distance jacking (Takada, 1987) . In

addition a method of installation using a membrane wrapping having high water

proofing properties has proved successful in laboratory tests and in field work

executed in very gravelly ground (Tohyama & Koiwa, 1987) .

A more recent development has been the introduction of fully remotely controlled
equipment in different sizes. This has resulted in a range of small diameter machines

which are able to deal with bad ground conditions, including mechanically balanced

slurry shields that are able to balance soil pressure and water pressure independently.

35
Chapter 2 Review of Pipe Jacking

2.2 INSTALLATION TECHNIQUES

2.2.1 Introduction

Pipe jacking has been defined in a number of publications . Craig (1983) described it
as a technique of installing pipes by driving a line of them through the ground with
hydraulic rams from a prepared jacking pit. Excavation is carried out at the forward,
shield end of the pipe as the pipeline is pushed from the jacking pit. After pushing a
full pipe length into the ground a new pipe is placed into the pit and the process is
repeated. The method provides a flexible structural, finished pipeline, duct or culvert
on completion of the tunnelling works. This process is illustrated in Figure 2.1 .

Parry (1978) summarised the process as follows:

1- It is a method by which the jacked pipes can constitute the finished

lining, whether steel or concrete pipes are used .


2- The lining is stable.
3- The method means that section other than circular in shape can be
thrust, therefore having uses in construction of pedestrian tunnels,
under-passes, etc.
4- It is a simple mining operation as no ring erection is necessary. As long
as continuous surveying is carried out, then the accuracy should be
good.

5- Instant support is provided and there should be no over-break, thus


considerably reducing the chances of any settlement at the surface.

6- It is a cleaner method than conventional tunnelling because there is no


need to send material back into the tunnel .

36
Chapter 2 Reuiew of Pipe Jacking

7- The shield should ideally be equipped with bentonite lubrication


facilities and individually controlled jacks for steering.

8- Intermediate jacking stations can be inserted on long thrusts to control


the magnitude of jacking forces.

Although he mentions that there should be no over-break, over-break is considered to


be essential in reducing the jacking forces required for pushing the pipes and a small
over-break is generally used. Also little consideration has been given to curved jacked
tunnels and the build up of jacking forces associated with them. Sulinski (1972) also

cites a reduced volume of excavation and relatively early stabilisation of the water table
as further advantages of pipe jacking.

2.2.2 Pipe Jacking Techniques

2.2.2.1 The Jacking Shaft

A shaft or pit is constructed at the start and finish of the tunnel section to be driven.
The size of the shaft is designed to suit the size of the pipe jacking equipment. A
thrust wall, capable of taking the anticipated horizontal force generated during the
thrusting of the pipes, is constructed at the back of the start, or jacking, shaft. The
shield, or the tunnelling machine, with the lead pipe are lowered into the pit and
positioned to the correct line and level on guide rails. A set of steering jacks' is

located between the shield and the lead pipe. The direction of travel is controlled by
the operation of the steering jacks acting against the lead pipe. The thrust wall acts as a

buffer to transfer the horizontal forces through the length of the pipeline to the cutting
edge of the shield by means of high power hydraulic jacks acting through a steel

37
Chapter 2 Review oJPipe Jacking

thrust ring and, as appropriate, steel spacers in the jacking pit. Therefore the pipeline

is progressively pushed forward into the ground along the proposed line.

The ram diameter and stroke of the jacks vary depending upon the method of operation

(O'Reilly et ai, 1986) . Short stroke jacks with multiple spacers permit the use of

smaller pits, although with a consequent loss in production. The method results in a

regular release and application of jacking pressure . Medium stroke jacks with spacers

keep the pit size within manageable proportions and also maintain a degree of

flexibility and continuity of jacking pressure. Long stroke jacks, usually with

sufficient stroke to allow a full pipe to be installed without the use of spacer blocks,

result in a lack of flexibility and require a longer thrust pit, but speed up the

operation. There is also a limitation in the total pressure which can be applied through

long and slender jacks . Either two or four jacks can be used, depending on the thrust

force required. The jacking forces should be evenly distributed around the

circumference of the pipe.

Different conventional jacking systems, as described in Craig (1983), have been

developed by individual contractors. In the UK, pipe jacks are normally relatively

short, with ground cover to the crown of generally I.S to 7 m. The size of the jacking

shaft is dependent on the jacking system the diameter and length of the pipe, and the

required access for skips. Typical access shaft sizes for small diameter pipes are 3m

wide by 4 to Srn long. Alternatively, a small diameter shaft has been used with a

heading at the bottom of the shaft to give a working area of sufficient size for pipe

jacking.

38
Chapter 2 Review of Pipe Jacking

2.2.2.2 Conventional Pipe Jacking

There are two main types of jacking system. In a flexible system the rams operate

against a vertical thrust wall with spacers between the head of the ram and the pipe

thrust ring. A rigid ring system has the same movement of the jacks, but after each
thrust long rigid beams are placed and pinned in different positions so that the thrust

may be transmitted to the floor through the beams rather than to back wall of the shaft.

The capacity and numbers of jacks are dependent on the forces required to push the

pipes through, additional jacks being required for long distance drives. These can be

inserted at intervals along the pipe length (intermediate jacking stations) in case high

loads are experienced later in the drive. Intermediate jacking stations are normally

introduced when the loads have reached more than approximately half of the jacking

capacity .

The excavation is either done manually, where a shield is provided for the miners'

protection, or, in a large diameter pipe. a mechanical excavator may be used. The small

hydraulic jacks placed just behind the shield are solely for alignment purposes. In

unstable ground a hood or other face support may be required, as in other tunnelling

methods.

The external diameter of the pipes varies from one manufacturer to another for the
same internal diameter. An overcut is generally adopted around the external diameter

of the pipe, the amount of the overcut varying depending on the type of the soil and the

method of excavation. Lubrication for the pipes may be required to eliminate the high
friction around the pipes, bentonite or mud or a similar substance being used.

39
Chapter 2 Review of Pipe Jacking

The constructional tolerance recommended for most conditions in the PIA specification
is 75mm for line and level, a target within which the majority of pipe jacks can be
maintained. Conventional pipe jacking in the U.K is achieved with a small gang of
men. The rates of progress depend on ground conditions, and they vary considerably
from one contract to another.

2.2.2.3 Mechanised Pipe Jacking

This more recent form of pipe jacking uses mechanical excavators to aid the process,
which is usually carried out in soft ground by a full-face boring machine, or by a
mechanical excavator within the shield (Figure 2.2) . The thrust forward on the leading
pipe and the forces required from the pipe jacking system are reduced when a full face
machine is used. Lubricant is often used on top of the pipe to reduce the friction
forces.

For this technique a larger jacking shaft is required than with conventional pipe
jacking, due to the large size of single or telescopic jacks used to drive a full length of
the pipe at one time. Long straight or curved lengths without changes Iin direction at
manholes are preferable, with fast rates of progress possible (Washbourne, 1985 and
1986) .

Small bore pipe jacking is commonly known as minitunnelling or microtunnelling .


This technique uses pipe jacking methods but with remote controlled excavation

techniques utilising specially designed tunnel boring machines. These machines are
mainly adopted for construction of sewers in urban areas with difficult ground
conditions and a high water table.

40
Chapter 2 Review of Pipe Jacking

Two main groups of tunnel boring machines exist . Slurry shields are really

miniaturized versions of the mechanical shields used for conventional tunnelling. In

the more sophisticated form they have a full face cutting head which can be moved

backwards relative to the body of the shield, allowing the cutter to exert a constant

pressure on the soil irrespective of the rate of advance of the pipe. Spoil from the

excavation is transported to the surface in a slurry, and the slurry pressure at the tunnel

face can be adjusted to match the external water pressure.

Alignment is monitored using a laser directed at a target on the shield. The target is

viewed by a television camera built into the shield and the picture is displayed on a

remote monitor at the surface. An operator viewing it can adjust steering jacks on the

shield to maintain alignment. The same operator controls the pipe jacking part of the

operation.

Steerable bores are usually steerable at the head by use of jacks. Alignment is

controlled by a visual survey from the launch pit or by use of a remotely viewed laser

system. Pipe installation may either be single-stage concrete pipe being jacked in

behind the borer, or multi-stage involving either a small diameter pilot bore or special

steel boring pipes which are subsequently thrust out and replaced by permanent pipes.

The spoil is removed either by aid of screw conveyors, which take the soil through the

pipes to the starting pit where it is collected and removed, or in a similar way with the

aid of hydraulic conveyance. An exception to this is the Swedish Lundby method for

pipes with a nominal diameter of 400mm and more. This method, specialised for soft

clay soil, consists of driving an open shield in a controlled way into the ground while

removing the soil plug from the pipe by water and a scraper (Stein et aI, 1985/86) ..

41
Chapter 2 Review oJ PIpe Jacking

Stein and Kipp (1985) describe the different methods of pipe jack construction for
pipes less than 800mm in diameter, where steel protective jacking pipes are used. In
cases where the jacking pipes are smaller than the steel protective pipes, the steel
protective pipes can be either left in place or drawn out of the ground, and the gap is
normally filled up with a propriety material . If the jacking pipes have the same
diameter as the steel protective pipes, the steel protective pipes are pushed out into the

receiving pit by jacking in the jacking pipes coupled with the aid of an adaptor.
Similarly, larger jacking pipes can be used by pushing the steel protective pipes to the

receiving pit with a reaming head in front of the jacking pipes. The extra soil is
removed through the pilot (steel) protective pipe. By using the steel protective pipe
method, the face resistance is reduced, as are jacking force peaks when obstacles are
encountered. It also gives better alignment control.

2.2.2.4 Uni- Tunnel System

This is a novel system in which inflatable rubber bladders are inserted between the
pipes and movement is accomplished by inflating the bladders sequentially, so that
every third pipe is driven forward sequentially (Richardson and Scruby, 1981 and
Craig, 1983) . The frictional resistance, against the ground, of the two following
pipes acts in reaction to the thrust. The system contrasts with conventional pipe
jacking where frictional resistance increases with drive length.

This technique requires specially manufactured pipes with butt ends to provide the

required area of contact for the installed bladder and a steel collar to prevent the bladder
from coming into contact with the excavated surface. The thrust corresponds to the
friction forces along a single pipe length only, so that the end loads of the pipe are

42
Chapter 2 Review of Pipe Jacking

small . The amount of advance of each cycle is different, ranging from a few
millimetres to 15mm.

The process is carried out twice to advance the remaining sections and the sequence is

then repeated so that virtually continuous movement of the lining takes place while

spoil is excavated from the face. Although this technique was invented in 1981 and

fIrst used in Japan (NCE, 1986), it has been little used due to its comparatively high
cost when compared with the typical cost of pipe jacking.

2.2.2.5 Large-Bore Pipe Jacking

In contrast to small diameter tunnels, Clarkson and Ropkins (1977) have i11ustrated

pipe jacking applied to large structures such as bridge foundations, abutments and

subways. Since 1976, over twenty projects have been executed in the UK concerning

foundations and abutments for various types of bridge and subway, the majority under

existing railway tracks but some under roads. In each case the method served to
minimize the high cost and inconvenience of traffIc disruption which would have

resulted from the use of conventional methods . All the earlier projects featured

rectangular pre-cast concrete units delivered to site and installed into the drive pit by

crane. Subsequently, however, the concept of jacking massive rectangular cast in-situ
units was successfully implemented.

43
Chapter 2 Review ofPipe Jacking

2.3 SOIL MECHANICS ASPECTS OF PIPE JACKING

2.3.1 Introduction

Tunnels are constructed in variable ground conditions from soft clays to hard rock. In
order to decide which method of excavation to use, a knowledge of the ground
properties, insitu stresses, and other soil characteristics should be gained. In pipe
jaCking, similar problems are encountered as for tunnels but further study of the
behaviour of the ground movement and its resistance to the forward movement of the
jacked pipeline, together with the magnitude of the ground pressure exerted on the
crown of the pipeline, are needed.

2.3.2 The Theory of Ground Pressure on Tunnels

Most analyses of the pressure acting on a tunnel are concerned with the vertical stress
on the roof of the tunnel, although in some instances lateral stress is more important
than the roof stress. The insitu stresses are detennined approximately from earth
pressure theory .

Before dealing with the evaluation of ground pressures, it is necessary to understand


the behaviour of the soil mechanisms around the tunnel, since arching phenomena
have some contribution to the vertical pressure on the tunnel. Terzaghi (1943) defined
arching using his famous yielding trap door experiments. The movement between the
yielding sand and the adjacent sand is opposed by the frictional resistance along the

contact line between them . Therefore, the decrease of the vertical pressure on the
yielding strip must be associated with an increase of the vertical pressure on the

44
Chapter 2 Review of Pipe Jacking

adjoining parts.

According to Szechy (1966), Kunczl conducted experiments on the behaviour of the

sand during arching over a slot. The slot was opened wider without attaining,

however, the intensity of the original geostatic pressure acting on the cover

(Figure 2.3) .

Terzaghi (1943) analysed the pressure on tunnels through sand by considering the

movement of the sand according to arching principles (Figure 2.4) . At the top of a

rectangular or square tunnel, the width of the yeilding strip (2BI) is approximately

equal to

2Bl = 2 [Bo + HI tan (45 - <1>/2H (2.1)

and for a circular tunnel, the width is

2B = 2b [1 + sin ( 45- <1>/2 H/( cos (45 - <1>/2)) (2.2)

where

BI = width of rectangular tunnel,


130 = half width of rectangular tunnel,

HI = height of rectangular tunnel,

B = width of circular tunnel,

b = half width of circular tunnel, and

$ =internal angle of friction.

The vertical pressure (av) on the horizontal section b I b I of width 2BI is determined

by

45
Chapter 2 Review of Pipe Jacking

cry'" ya (1 - C e- Ko tan $ D/B) • (l / Ko tan $) (2.3)

where Ko '" empirical coefficient

Also according to Terzaghi an approximate estimate oflateral pressure is given by the

following formula:

crh ", 0.3 'Y (0.5 HI + D) (2.4)

For granular soil on the basis of Rankine's ratio

(2.5)

The effect of depth of the tunnel on the magnitude of the vertical pressure at the crown

of the tunnel was studied by Bierbaumer, according to Szechy (1966) . He developed

Bierbaumer's theory, which was developed during the construction of the great Alpine

tunnels. According to this theory, the tunnel is acted upon by the mass bounded by a

parabola of height h = a D (Figure 2.5) . The pressure at the crown will be

P=aDy (2.6)

The value of Cifor a rectangular or square tunnel is given by

a = 1 - ([tan<jl * tan2<jl(45-<jl/2)D) / [(Bo+2HI) * tan(45-<jl/2)lJ (2.7)

46
Chapter2. Review of Pipe Jacking

2.3.3 Tunnels Through Soft Ground

The conclusion of Muirwood (1975 ), is that loading problems should be treated in

effective stress terms. Atkinson and Pons (1977A) investigated, both theoretically and

experimentally, the stability of a circular tunnel in a cohesionless soil with support

conditions similar to those found during construction, with due regard to effective

stress conditions. They carried out experimental work to analyse the behaviour of dry

cohesionless soil along an unlined circular tunnel, and derived the following

expression for the lower bound on the tunnel support pressure (aT) required for

stability.

(2.8)

where ~ = (1+5In<l>')/(1-5In<l>')

<1>' is the maximum angle of shearing resistance of the soil (degree),

B is the tunnel diameter (m), /

g is the force due to gravity (rn/s2), and

'Y is soil density (kN/m3 ) •

Atkinson and POltS (1977B), by using tunnel modelling, defined a load factor (LF) as

the ratio between the acnial stability ratio (N) and the stability ratio at collapse (Ne) .

They also suggested that there is little need to differentiate between drained and

undrained deformations in overconsolidated clays, because of the relatively small

volumetric strains observed above their model tunnel.

47
Chapter 2 Review of PIpe Jacking

Davis et al (1980), have used the stability ratio (N), proposed originally by Broms and

. Bennermark (1967), to provide a convenient frame work for estimating tunnel

stability. Values of N less than 6 indicate that the excavation heading would be stable

and that no support is required.

2.4 PIPE JACKING FORCES

2.4.1 Introduction

The resistance to tunnel driving is generated from the pressures on the shield and by

sliding resistance between the soil and the outside surface of the pipe along its length.

This resistance must be overcome by the applied jacking forces,and the factors

affecting it are illustrated in Figure 2.6 .

In particular, two sets of parameters must be considered:

(i) Frictional resistance due to ground pressure

This can be used in a theoretical approach for calculating the required forces. Many

factors can influence these calculations, including

a- pipe shape

b- pipe self-weight

c- pipe overall diameter

d- surface surcharge

e- unit weight of the soil

f- type of soil

g- assumed soil loading mechanism

48
Chapter 2 Review of Pipe Jacking

h- rigidity of the pipe structure

i- coefficient of friction of the pipe-soil interface

(ii) Construction factors

These factors can affect the magnitude of the calculated forces required for installation

of the pipeline, and include

a- face resistance

b- overcut

c- variation of ground conditions

d- rate of installation and magnitude of delays

e- joint deformation, both angular and lateral (steps)

f- lubrication

g- use of intermediate jacking stations

h- jacking around curves

2.4.2 Theoretical Analysis

It is important to predict the jacking forces during construction for the following

reasons:

1- Provision of jacks, and associated equipment, capable of providing

such forces.

2- Design of an adequate thrust pit •

3- Intermediate jacking station(s) may be required.

4- Provision of pipes to sustain the forces without damage.

5- The strength of the joints.

6- Economy of operation, uncertainty leading to overdesign .

49
Chapter 2 Review ofPipe Jacking

There are two fundamentally different ways of estimating the jacking forces required
for pipe jacking as illustrated in Figure 2.7 . These methods are elaborated below and
are summarised in Table 2.7 at the end of the section.

2.4.2.1 CIRIA Approach

CIRIA produced a state-of-the-art review on pipe jacking as a Technical Note by


Craig( 1983) . The objective of the study was to determine the design criteria of the
pipe, the joint detail, the allowable end thrust on the pipe and the frictional forces due
to radial loading. The aim of the work was consequently to enable the industry to

establish the most competitive techniques for jacked pipe construction. The study was
based on direct experience, partly from literature but mainly from discussions with
representatives from all sides of the industry, who supplied information from
contracts.

The jacking loads provided in practice are normally in the range 0 - 4000kN on
average, although peak values at the end of jacking runs can reach up to 10000kN .
Variation in frictional resistance can occur as a result of minor changes in ground
conditions and properties, thus can therefore only be estimated within wide limits.
Craig (1983) produced a table showing some typical values for jacking forces,
expressed in terms of drag per unit area of the external pipe surface, for jacking
operations in different ground conditions . These were produced as a guide for
estimation of forces and are reproduced in Table 2 .1 .

50
Chapter 2 Review ofPipe Jacking

Table 2.1 Empirical Jacking Forces ( after Craig, 1983 )


SoU Type Drag Force kN/m2

Rock 2-3
Boulder Clay 5- 8
Finn Clay 5 - 20
Wet Sand 10 - 15
Slit 5 - 20
Dry Loose Sand 25 - 45
Fill up to 45

Typically, different formulae or tables are used in different countries to estimate the

jacking forces. In Japan, the jacking force is estimated using

(2.9)

where

F = the total pipe jacking force,


Fa = shield resistance,

Rr = frictional resistance between the pipe and the soil,


SI = circumference of the pipe,

W = weight of the pipe,

Fw = the coefficient of the frictional resistance due to the weight of the

pipe,

Ll = distance of propulsion, and

I = coefficient for curved section

51
Chapter 2 Review ofPipe Jacking

The shield resistance is given by


. 2· .
Fo = P + (Pw • B /4·__ 1t)
._ (2.10)

where P = force on cutting edge,

Pw = water pressure, and


B = external diameter of the pipe

In Australia, the jacking force is calculated using

F=aS+FoB (2.11)

where a = adhesive force,

F 0 = force per metre for the leading edge to penetrate the soil (shield

resistance),

B = external diameter of the pipe, and

S = external surface area of pipe = 1tBL .

The adhesive force is calculated from Table 2.2

Table 2.2 Adhesive Force Used in Australia (after Craig, 1983) .


Soil Type Friction Value (kN/m2)

Shale 1
Clay 5 - 7.5
Sand 13

In France jacking force calculations are based on recorded friction values during

construction (Table 2.3), although higher peak measurements have been recorded in
some cases.

52
Chapter 2 Review ofPIpe Jacking

Table 2.3 Frictional Forces used in France (after Craig, 1983).


Soil Type FIictlon Value (kN1m2)
Clay 8 - 10
Silt 17
Sand 20 - 30
Gravel 50

In Germany, the jacking forces are determined by a combination of the resistance at the

face of the tunnel and the friction between the pipe and the surrounding soil . An

average pressure of 9 kN/m2 must not be exceeded in design, although jacking loads

are sometimes said to be in the range 5-50 kN/m2 .

2.4.2.2 Auld's Analysis

Most of the theoretical methods for estimating the jacking forces use earth pressure

calculations and coefficient of friction. Auld (1982) analysed the problem by using

Terzaghi's earth pressure theory, allowing for the effect of arching of the soil above

the pipe on the vertical and lateral pressures.

The yielding strip width for a circular pipe is shown in Figure 2.8. From the bottom

surface of the pipe the inclined boundries of the zone of subsidence rise at an angle of

(45+~/2 ), and thus

2B = 2b [ 1 + sln(45+<I>/2) I / cos(45 - <1>/2) (2.12)

A uniformly distributed vertical earth pressure can be taken as cr per unit area at any
v

53
Chapter 2 Reuiew oJ Pipe Jacking

depth z in the region of the sliding surface ac and bd (Figure 2.8) . The vertical

pressure can be detennined by considering the equilibrium of a horizontal thin slice of

thickness dD and the shearing resistance of the soil, as

Shearing resistance = C + cs tan$ (2.13)

where cr= applied stress per unit area

C = cohesion per unit area

To calculate the horizontal earth pressure, Coulomb's theory for active pressure is

applicable on the basis that the sides of the pipe are simple retaining walls, behind

which the backfill carries a unifonnly distributed surcharge cry per unit area, the

vertical pressure at the roof level. Lateral pressure on the sides of a pipe buried in the

sand or gravel can be obtained by considering the equilibrium of the soil mass lying

inside the wedge shaped zones defined by the shearing planes extending upwards at an

angle of 45+$/2 from the bottom surface of the pipe. Thus using Terzaghi's approach

(2.14)

ffiIy = cry/y

or by using Rankine's equation

(2.15)

In order to achieve the total force acting on the circumference of a circular pipe, the

ground pressure must be established. Figure 2.9 shows a suitable method. By

resolving the vertical and horizontal pressures in the radial direction, the radial

54
Chapter 2 Review oJ PIpe Jacking

pressure component at any point on the pipe is given by :

Po = cry eosS + ah sinS (2.16)

The total force on the top half of the pipe is thus

(2.17)

or

Pl = 2b(cry + crh) (2.18)

The total force on the bottom half of the pipe is given by

P2 = 2b( cry + self weIght of the pIpe per m 2 + crh ) (2.19)

and therefore the total force can be established as

P o =P1 +P2 (2.20)

By approximation of the normal pressures on the external surface of the pipe, he

therefore derived an expression for the total normal force on the surface per unit length

of the pipe (pu) as

P u = B.(2.Py + 2Ph + W/B) (2.21)

Where B = external diameter of the pipe,

Py = venical pressure at the crown of the pipe allowing for arching,

Ph = average horizontal pressure on side of the pipe allowing for

arching, and

W =weight per unit length of pipe

The frictional resistance which needs to be overcome per unit length of pipe is thus
given by

55
Chapter 2 Review of Pipe Jacking

Fu =Pu ' tan~ (2.22)

where ~ = angle of friction between the soil and the pipe and ~ < cp •

Auld has thus considered the ground pressures on pipes as the sole parameter for

calculating the jacking forces, whereas it is known that other factors affect the forces

and these should be taken into account. Norris (1993) demonstrated from his basic

theory .. · that there is an error in Auld analysis resulting in a 25% overestimate of

jacking resistance. Further research is needed to define accurately what effect the other

parameters have on the jacking force. In addition, it appears that the conversion of

ground pressure on the pipe into frictional resistance has been treated very simply

using the angle of wall- friction. Further research is required to investigate this

approach and also to establish more accurate friction relationships for various pipe

and soil conditions.

2.4.2.3 Haslem's Analysis

Haslem (1986) studied jacking forces both in theory and in practice. Based on field

measurements, a new theoretical approach was developed allowing for the effects of

bentonite lubrication on both the buoyancy of the pipes and on the sliding resistance.

This method involves initial prediction of the jacking force for an ideal drive to provide
a base value, which is then adjusted to account for construction factors.

He summarised the observations from six tunnels through overconsolidated clay.

Improved prediction of jacking forces was achieved by determining the contact area

between pipe and soil from elastic theory and applying values of sliding resistance,
measured in the laboratory, over this area.

56
Chapter 2 Review of Pipe Jw::ktng

Figure 2.10 shows the jacking forces for several drives of a single contract onto which

is superimposed theoretical lines A to E where

A = simple earth pressure theory used at Kochi City with l! = 0.17

B = as for A but with l! = 0.34 (representing the required restarting


force)

C = elastic contact at the roof of the tunnel with an adhesion of 72 kPa

D = elastic contact at the floor of the tunnel with an adhesion of 72kPa

E = as D but with adhesion equal to the cohesion of the soil (200kPa)

Figure 2.11 supports the concept of elastic deformation of the soil in contact with the

pipe and resistance based on laboratory values of adhesion over the contact area.

Figure 2.12 shows the results and predictions for an earlier drive with the measured

forces lying between theoretical lines D and E for elastic deformation of the floor of the

tunnel excavation.

His conclusion can be summarised as follows

1- The range of forces from site measurements was wide and not related

to specific properties, when compared with the empirical resistance.

2- Theoretical calculation based on simple earth pressure overestimates

the jacking forces.

3- An alternative theoretical method has been proposed for calculating

the jacking forces by treating the pipeline as an elastic cylinder resting

on a cylindrical void in an elastic medium. This method underestimates

the jacking forces when compared with the laboratory values of sliding

resistance applied over the area of contact based on elastic deformation.

57
Chapter 2 Review oJ Pipe Jacking

4- It was found that, despite varying misalignment of the pipeline

studied, the curvature was similar and the increase in forces due to

misalignment predicted by the theory was negligible . This suggests that

if the theory is appropriate the differences in the measured jacking

forces must have another cause.

It appears from his work that the elastic deformation of the soil around the pipe

produces an increase in the jacking forces due to the greater contact areas causing more

adhesion resistance around the surface of the pipeline. More studies should be carried
out in a variety of ground conditions and types of soil. Investigation is also needed to

examine the variation of the jacking forces at different depths for the same ground

conditions. Other construction factors, such as overcut ratio, should also be

considered.

2.4.2.4 Japanese Analysis

A Japanese analysis (Anon, 1981) has used simple earth pressure theory to derive the

following expression for the jacking forces at Kochi city, Japan.

F = ([1t 12. B. ml [w + 1/2. (wl+w2) I + 1/4 .Wg • ~) . L (2.23)

where B = diameter of the pipe (m)

W = soil pressure perpendicular to pipe (tonne/ m2)= yD

° =cover to the pipe (m)


w1.w2 = soil pressure horizontal to pipe (kN/m2)
wl =KoD and w2 = Ko(D+B)

Ko=( 1-s!n<l» / (1 +s!n<l»

58
Chapter 2 Review of PIpe Jacking

Wg = weight per unit length of pipe (kN/m2)

The pipeline was jacked through a ground which consists of sand and gravel layers
iI
fonned by the build up of sand fronfnearby river, together with silt and cohesive sand

and gravel. Seepage of water was detected in (he coarse non-cohesive gravel layer .
iron
Jacking operatioll5involved the use of ductile'pipe and the employment ofintennediate
jacking stations.

This expression was used to give the jacking forces using a coefficient of friction of

0.4 between gravel and the pipe, and 0.2 between clay and the pipe. Practically it was
the
found, during'jacking operation, that the coefficient of friction in cohesive soils stayed

at around 0.2 and increased to around 004 on occasions. This increase is due to the

cohesion of the clay layer when the surface concrete of the pipeline is separated after a
certain period of contact with soil. Injected lubricant was found to reduce the driving
force by 15% .

2.4.2.5 Herzog's Study

Herzog (1985) studied the jacking forces in loosely packed earth by referring to

Kuhnhann's (1977) statistical analysis of jacking forces (in MN), which states

F =0.21 Fk -1.18 (2.24)

in which Fk (in m 2) is made up of steel skin surface area and heading area, see Table

2.4 .

59
Chapter 2 Review ofPipe Jacking

Table 2.4 Replacement Shield Area (after Kuhnhann,1977)

Type of Shield Fk
.. .

Fully mechanised shield, heading supported Fm +3 FB


partially mechanised or hand shield, heading supported Fm + FB
Partially mechanised. heading half obstructed Fm + O.5FB
Fully mechanised or hand shield. heading open Fm
Fully mechanised shield. free cutting O.7m

Note: Fk is shield area, Fm is steel skin surface, and FB is heading area

He suggested that it should be possible to calculate the jacking forces from the relevant

influences, such as

Type of shield

Heading support

Primary stress condition

Skin friction

Face resistance

He based his study on the pile model concept, where the two resistances, skin

resistance and face resistance, have to be overcome.

The skin friction can be determined by making the assumption that the primary earth

pressure (dependent on soil density, y, cover depth, D, and pipe external diameter, B )

acts on the pipe. In the vertical direction

Pv = 'Y ( D + B/2 ) (2.25)

60
Chapter 2 Review oJPipeJackfng

and in the horizontal direction

(2.26)

where Ko = side pressure coefficient, which is tenned more properly coefficient

of earth pressure at rest.

The frictional coefficient for a pipeline in the ground (f) is given in Table 2.5, from

which the skin friction (Pn0 can be calculated as follows

Table 2.5 Coefficient of Friction Between the Ground, The Shield and Pipe
Surface (after Herzog, 1985)
Soil Steel Shield Concrete Shield

Gravel 0.55 0.80


Sand 0.45 0.65
Loam.Marl 0.35 0.40
Low Grade Clay 0.30 0.35
Clay 0.20 0.25
-

Note: Low Grade Clay is assumed to mean a clay of low plasticity

Pm =f1tDL ( Pv + Ph ) /2 (2.27)

where L is the length of the pipeline.

The face resistance can be divided into two resistances, cutting resistance and heading

resistance. The heading resistance results from construction processes, such as the

resistance caused by compresed air or bentonite support. The heading resistance (Psl)

is given by the horizontal earth primary stress (Ph) and the heading area of the pipe or

shield as

61
Chapter 2 Review of Pipe Jacking

(2.28)

The cutting resistance is given by the cutting thickness (t) of the shield and the strength

of the soil face ( Ps), as defined in Table 2.6 .

Table 2.6 Resistance to Ground Cutting in Terms of the Strength of The

Soil Face (Ps)

Soil Ps (MN/m2)

Rocky Ground 12

Gravel 7
Dense Sand 6
Medium Sand 4
Loose Sand 2

Mar! 3
Clay 1

Poor Clay 0.4

The cutting resistance is therefore given as

Ps2 = Ps 1tB t (2.29)

The complete face resistance is given by

Ps =Ps 1+ Ps2 (2.30)

The heading resistance can be ignored if the heading is totally self-supported.

A summary of the jacking force analyses is given in Table 2.7, which serves to

provide a direct, simple comparison of the different approaches.

62
.............. --~------------------------------------

Table 2.7 Summary of the Methods of Jacking Force Analysis

ANALYSIS BY SUMMARY OF ANALYSIS CONCLUSION REMARKS


Based on experience of contractors and A set of ranges of Jacking resistance Is Minor changes In ground Condition can cause
records of jacking forces from various achieved from records of previous a significant variation In fnctlonal forces. with
CRAIG(CIRIA) s1tes . The study covers predicttve methods contracts in similar ground condtttons . vartation of more than 50% In Jacking forces
from many countries worldwide. found In some contracts. The jacking drag
values are thus only a very approximate
guldltne and are of little use In design .

Based on the arching prindple of the soll. It. Introduces a better estimation of the The conversion of the ground pressure Into
converts the vertical and the hOrizontal Jacking loads by considering mainly the a Jacking load Is very simple. It relates
ground pressures around the pipeline tnto a earth pressures around the plpeUne . angles of fnctlon to the Jacking load •
AULD Jacking load equation. However it does overestimate the Other factors are not taken into consideration.
Jacking resistance. Accurate fnetlon relationships between the
soil and the surface of the pipeline should be
established •
Based on treating the pipeline as an elastic It appears to underestimate the Jacking Construction factors are needed to adjust
cylinder resting In a cylindncal void In an forces tn practice. probably as a result, the Jacking forces . It Is applicable to an
HASLEM elastic medium . It relates the sliding of plasUc deformation causing contact elastic medium. whIch the ground is not. but
resistance to the amount of area tn contact area to Increase. It is applicable to an nevertheless represents a valuable
with the surrounding soil . Ideal. straight line pipe Jack. conU1b .....t.i~". which can
be refined .

, Based on a simple earth-pressure theory . It was found that the coefficient of The coefficient Is stIlI an assumption and It
Developed to analyse the Jacking forces at frlct!on between the pipeline and has not been tested practically . The theory
Kochl city. Japan. gravel Is 0.4. and clay Is 0.2 • Is of little practical value Without considerable
JAPANESE Bentonite lubr1catlon reduces the empirical experience to detennlne constants.
(ANON) JackIng forces by 15%.

Based his stUdy on Kllhnhann's statistical Calculation of the Jacking forces gives a It does not consider the amount of the overcut
study related to jacking forces . Also. he reasonable estimation .It includes the around the face and the time depend;nt
HERZOG studied the Jacking forces using the pile calculaUon of the skin friction and the behaviour of the soUlround the pipeline
model concept, skin resistance and face face fL'Sistancc of the plpeUne and is dunng the Jacking process. A contnbullon
resistance. based on simple, logical concepts. worthy of refinement.
Chapter 2 Review DJ Pipe Jacking

2.4.3 Experimental and Field Investigation

Detailed field investigations have been conducted by Haslem (1983 and 1986), and

this has been mentioned in relation to his jacking force analysis in section 2.4.2.3 .

Experimental work has concentrated mainly on small project research to define some

problems associated with pipe jacking. This work has been clearly demonstrated by

O'ReilIy and Rogers (1987) . They concluded that, in a self-supporting ground, the

resistance to jacking is simply the shear strength of the line contact. (In rock point

contacts can arise at an angle to the vertical since the excavation will not be perfectly

circular) .

They have also considered the contact area between the pipe and the soil (in this case a

clay) according to elastic theory, by conducting a scale model experiment. A graph

( Figure 2.13 ) was achieved, from which it was concluded that the elastic theory

underestimates the contact area by a factor of approximately 2.5 for a clay with

(PL=20%, LL=85%) and a load applied for 15 minutes. Using clay with higher

water content (LI = 0.36), the contact area was underestimated by a factor of 1.6 .

The area of contact was also not constant and increased with time. If this change in
contact is applied to the data of Haslem reported earlier, a better fit is obtained

(Figure 2.14 ) .

A larger project has been carried out at Oxford University on the cyclic loading of

jacked concrete pipes. Scale model apparatus was used to examine the behaviour of the f

concrete pipes and its packing within joints during the jacking process.

64
Chapter 2 Review DJ Pipe Jacking

The aim of the work was to determine the magnitude of the forces that pipes can
sustain during construction (Milligan and Ripley, 1989), and thus this has little bearing

on the discussion herein.

lA f()llow on project has been conducted to extend the work to the field (Norris and
Milligan, 1992A and Norris, 1993), for fi~e different schemes. Both the progress

and jacking forces were recorded to demonstrate the effect of the pipe soil interface.
The field experiments were conducted in five types of ground conditions, stiff Glacial

Clay (scheme 1), weathered Mudstone (scheme 2), London Clay (scheme 3), dense

Silty Sand (scheme 4) and loose Sand Gravel (scheme 5) . The records of the jacking

forces for all the schemes are demonstrated in Figure 2.15 a,b,c,d, and e . It seems

that the rate of the jacking resistance for cohesionless soil in schemes 4 and 5 was

decreased dramatically when lubrication was used. Schemes!, 2 and 3, where the

jacking process· occurred in cohesive soils, show changes in the rate of jacking

resistance due to stoppages, rate of jacking and weather conditions. However, he has
failed to relate the effect of the overburden pressure (cover) to the magnitude of the
jacking forces, where the jacking force was 54 kN/m for scheme 3 under 11-2!m of

soil cover, 8-54 kN/m for scheme 2 for 7 - Ilm of soil cover and 7.2 - 29.8 kN/m

for scheme 11 at ·1.5 - 1.7m below the ground level. No mention was given to the

amount of the overcut ratios adopted for each scheme and their effect on the magnitude
of the jacking forces. It is expected that more detailed results will appear in a thesis to

be published in early 1994.

Rogers et al (1989A) have investigated the jacking forces from site data by referring to

case studies on pipe jacking projects. In their paper, they relate the magnitude of
measured jacking forces with the stability number of the soil, and hence the ability of

65
Chapter 2 Review of PIpe Jacking

the ground to support itself. They plotted their results as shown in Figure 2.16, in
which they demonstrated that higher jacking forces were needed in weak alluvial clay
::I
with'stability number of 7 (Figure 2.16a) than much stiffer glacial clay of stability
number of 3. . (Figure 2.16b) . It is recognised that full collapse of an unlined tunnel

will occur at values of stability numbers of about 6 according to Peck (1969) and Mair

(1979) . Rogers et al (1989B), studied a pipe jacking operation at Bumham-on-Seaand


concluded that the jacking forces were considerably lower in self-supporting ground

with little misalignment and with overbreak around the driving shield (overcut) . Stein et al

(1986) defined the jacking forces for a small diameter pipe jack in terms of cover depth
and jacking distance from site data in Hamburg, Figure 2.17.

2.5 FACTORS AFFECTING THE JACKING FORCES

2.5.1 TYPE OF SOIL

Pipe jacking can be performed in different types of soil and ground conditions. The

Pipe Jacking Association has classified the types of soil which are likely to be
encountered during pipe jacking.

(a-) Non-cohesive: sands, gravel, ballasts and silts.

(b-) Cohesive: clays, mads with up to 20% of gravel and having a moisture content
less than the plastic limit. Also chalks having a saturation moisture content of 20% or

greater.

(c-) Mixed: sand and clay, sand and silt, non saturated clays and silts, and boulders.

(d-) Fills: mixed materials of recent deposition such as domestic refuse containing

ash, vegetable matter, etc, and materials of varying content and compaction used for

66
Chapter 2 Review oj Pipe Jacking

embankments for railways, roads, etc.


(e-) Rock: hard material of geological origin or other comparable hard inert material
(concrete, brick, etc ) .

Prior to pipe jacking, information should be provided on the characteristics of the soils
likely to be encountered together with details of the strata with depth to a point
significantly below the pipeline and water table, such as its rate of inflow into an

excavation and any tidal or seasonal changes. For particular types of soils these
characteristics include the following.

(a) Non-cohesive soils


grading analysis to fmd particle size distribution.
permeability of soil .
soil densi ty .
standard penetration test of soil (N-factor) .
(b) Cohesive soils
Atterberg limits

u ndrained shear strength (apparent cohesion or unconfined compressive


strength is called for in the literature, although more closely controlled
testing appear to be better)
permeability of soil (to enable determination of time dependent collapse
of soil onto pipe)
s oil density .
.standard penetration test of the soil .
(c) Mixed soils

information as above together wi th evidence of artesian or perched water

67
Chapter 2 RevieW ojPfpeJack1Ilg

tables.

(d) Fill materials

information as above with particular reference to compaction and the

nature of the material .

(e) Rock

colour, grain size, geological type.

rock strength (MN/m2) and fracture state (R.Q.D)

planar structure (bedding, etc.) .

Phillips (1985) suggests that a site investigation should involve a number of boreholes
both along the line of the proposed drive and in the area of the associated temporary

works. The author considers lOOm to be the maximum spacing unless very uniform

ground conditions can be ensured.

Ingold and Thomson (1989) categorised pipe jacking site investigation according to

application such as crossing, large diameter line installation (2000mm-1500mm) and

small diameter line installation «250 mm) . In all pipe jacking geotechnical

investigation, particle size distribution and,in the case of cohesive material,the shear

strength and consolidation· constitute the standard lab\lratory tests, while the insitu testing

will mainly involve the Standard Penetration Test for determination of the relative
density and strength of granular soils or shear vane test for cohesive soils.

Although Stein et al (1985) show a linear relationship for jacking forces in a small

diameter pipe jack (Figure 2.17) they suggested that this relationship is not necessarily

the case in practice because the condition of the soil along the pipeline has been shown
vary considerably in practice.

68
Chapter 2 Review of PIpe Jacking

Drennon (1979) stated that selection of pipe jacking as the preferred method of tu~nel
installation depends largely upon the soil. Since long run jacking almost always
requires use of a tunnel boring machine, the soil must be suitable for that sort of
mining operation . This effectively precludes jacking in mixed face conditions,
although it should be noted that this comment was made thirteen years ago and recent
equipment developments would appear to have rendered the statement invalid for
current practice . The best ground for jacking is clay with a minimum unconfined

compressive strength of lOOkN/m2 . The higher the percentage of silt or sand in the
clay, the more difficult the frictional conditions become since permeability of the clay

will rise and collapse of the soil onto the pipe is more likely to occur. Jacking has

been done very successfully in shales that have both good stand up times and that turn
to clay immediately around the pipe.

Materials that prove very difficult for successful pipe jacking include squeezing clays,

since the contact area between the pipe and the soil rapidly become large and
considerable forces are generated. In addition a weak clay will cause problems in
maintaining alignment of the pipe jack since shield resistance against the surrounding
soil is required for steering . Sand or gravel, especially in a loose or running

condition, also can prove very difficult for pipe jacking. Friction on the pipe is the
major problem with sands and gravels where these materials do not develop a strong
arching mechanism above the pipe, such as the case with loose materials that have a
low, or non-existent, angle of dilation.

69
Chapter 2 Review of PIpe Jacking

2.5.2 AMOUNT OF OVERCUT

Overcut is the creation of a small gap around the pipes that follow a slightly oversized
steel shield at the face of the tunnel. The shield usually has an outside diameter of
1O-20mm greater than the outside diameter of the jacking pipes. The magnitude of the

overcut is usually defmed in terms of overcut ratio (R), as shown in Figure 2.18. This
gap is not usually precisely uniform around the pipe, except for a full face cutter
working in ideal ground conditions or trimming shields in clay. Hand excavation
produces more overcut, or overbreak, than shield tunnelling . In some cases, an
overcut of 2S-S0mm is created, depending on the type of the soil. For example,
Manlow (1984) stated that the mini tunnel system shield creates an overcut of
approximately 6% of the bore.

There are two distinct situations in which the magnitude of the overcut influences the
jacking forces, and these are detailed below.

2.5.2.1 Non-closure of overcut

This occurs in a fmu to stiff cohesive soil and in a cemented soil or rock. In this case
a large proportion of surface area of the pipe does not make contact with the
surrounding soil .

Washbourne (1982) analysed the non-closure of overcut by referring to Kirsch

equations. He observed that the jacking distance can be increased if the overcut can be
maintained. The Kirsch equations assume that the material surrounding the excavation

will shear at an angle of (45 + <\112)0 to the horizontal from the extremities of the

70
Chapter 2 Review oJ Pipe Jacking

horizontal diameter. In addition the elastic closure of the vertical diameter will cause
the top of the excavation to bear down on the crown of the pipes. The shear failure at

the horizontal diameter of the excavation will be associated with a compressive

stress l.of 2Ctan(4S+$!2) acting· . circumferentially . The Kirsch elastic theory equation

may be applied to a long horizontal excavation of radius (r) and stress field of (Pv) in the
(KoPv) in the direction
vertical and A· horizontal'in material of modulus of rigidity G and Poissons

ratio Cv) .

The overcut will not close if

Pv [ 3 - Ko J < 2C tan [45 + $1 2 )0 (2.31)

2.5.2.2 Closure of overcut

Closure of overcut happens when the surrounding soil collapses onto the pipeline.

This occurs in non cohesive soils (gravel, sand, and silt) and is manifested by full

contact between the surrounding material and the surface of the pipeline. In this case
the jacking resistance will be considerable and the support pressure to the jacking
thrust wall, at the back of the jacking pit, in such material can also be low, for this also

depends upon the strength of the surrounding soil .

When jacking in certain ground conditions, the material may be non-closing at the start
of the excavation, but will progressively collapse onto the pipe as negative porewater

pressure reduces with time. This will tend to induce high sliding, or frictional,

resistance.

71
Chapter 2 Review oJ Pipe Jacking

2.5.3 OVERBURDEN PRESSURE

Little investigation has been carried out on the relationship between the overburden

pressure and the magnitude of the jacking forces generated during the construction of a
pipeline at different depths. Stein et al (1985) postulated the linear relationship shown

in Figure 2.17, in which the jacking forces are related to cover depth and jacking

distance, but this can be considered as an approximate model only . Overburden is

accounted for in several of the theoretical analyses described in section 2.4.2, but no

serious attempt has made to measure this effect in the laboratory or in the field .

2.5.4 MISALIGNMENT

As a pipe jack progresses, errors in the position of the excavation can often cause the

pipeline to deviate from the proposed line . It is important to keep the pipeline

properly aligned because any deviation will cause ground resistance to increase and
will additionally cause the forces in the pipes to rise considerably.

Haslem (1983) analysed the misalignment of the jacked pip,eline. terming it wriggle.

Misalignment can occur in any direction. but is generally resolved horizontally and

vertically. By considering an elemental length of the tunnel and the components of

horizontal and vertical deviation. he obtained the resultant normal force between the

tunnel element and the soil (t.N) . This can be expressed as a force per unit length of

tunnel (FJ. from which the resistance force per unit length (Fs) can be obtained as

Fs= Futan p (2.32)

where p = angle of friction between the soil and the pipe surface.

72
Chapter 2 Review oJ Pipe Jacking

Rogers et al (1989B) demonstrate in a case study that sharp changes in both line and

level can cause the jacking force to rise by typically 20 tonnes. It was also stated that

the force tends to be more sensitive to changes in level than in line, since the major

principal stress is usually vertical .

It can be concluded that the jacking force is expected to increase when the line of

tunnelling deviates from a straight line, due to the increase in the normal force between

the surrounding soil and the pipeline. A simple analogy to explain the reason for this

is that a greater area than that of the face of the shield is directly opposing the thrust

of the jacks (Le some component of force in a misaligned drive acts directly towards

the jacks) . Such analysis is, however, too simple since it assumes a single pipe rather

than discrete pipe sections, which attempt to realign due to the differential forces acting

across the ends of the pipes . These result in a moment being set up and large,

localised forces normal to the pipewall are generated to maintain equilibrium.

In a similar manner, tunnel curvature has a great effect on the jacking forces. Nomura

et al (1985) showed in field tests that a lOOm length of jacked pipeline with a curvature

of radius 200m is possible in either cohesive or sandy soil. Clearly as the curvature

increases, so the normal (and hence jacking) force increases.

2.5.5 THE SIZE AND LENGTH OF THE PIPELINE

The pipe diameter and the total length of the proposed pipeline have a considerable

influence on the magnitude of jacking forces (Anon, 1981, and Herzog, 1985) . These

parameters increase the surface area of the pipeline, and consequently total contact area

73
Chapter 2 Review of Pipe Jacking

with the surrounding soil. In addition the span (or diameter) of the pipeline will have
an influence on the ability of the soil to develop arching above the pipeline.

2.5.6 THE RATE OF JACKING

The rate at which the pipes are jacked is dependent on the difficulties encountered in
construction, such as the rate of excavation, the speed of spoil removal and the rate of

installing the lining. The fonner is generally the dominant influence. In good ground

conditions using mechanical excavation, jacking rates reach 4m/hr, while in bad

ground conditions and using hand excavation the jacking rates may be reduced

dramatically to O.4m/hr, (Basu, 1973) . Washboume (1984A) stated that for small

diameter tunnelling in soft ground, 3-6 m/hr might be jacked if a boring machine is

used for excavation.

Time is an important factor in changing the behaviour of the soil around the pipeline.

Rogers et al (1989A) have shown the that slow progress causes an increase in the

jacking forces. In addition, they demonstrated that a break in production can lead to

significantly increased restart forces, which in some cases reach 50% of the forces

prior to the stoppage (Figure 2.16) . Norris and Milligan (1992A), concluded that the

time factor effect is pronounced in. high plasticity clay and may be related to rate of

jacking rather than increases in ground pressure during stoppages as shown in Figure
the
2.19. They also demonstrated that'pipe-soil interface is effected by the localised radial

and frictional stresses.

74
Chapter 2 Review of PIpe Jacking

2.6 METHODS OF REDUCING JACKING FORCES

2.6.1 INTRODUCTION

By jacking further pipes into the ground forces will progressively increase, the

magnitude of these forces being dependent on many factors as discussed above. In

this section, methods of reducing these forces are investigated . The most popular

method of reducing jacking forces is the application of a lubricant around the pipes.
relatively
Bentonite, polymer mud or any chemical substance that produces aAfrictionless

medium around the pipes can be used. An alternative method of reducing jacking

forces is to coat the pipes with a smooth material.

Mechanical means can also be used to reduce the forces required of the main jacks,
such as intermediate jacking stations whereby sets of hydraulic jacks are placed at

regular intervals along the length of the pipeline in order to reduce jacking distance

over which the pipe train is jacked. In addition, adjustment of the amount of overcut

around the tunnel lining can reduce the jacking forces in some types of soil .

2.6.2 LUBRICATION

Lubricating slurry for jacked tunnel linings is usually based on bentonite with a water

content of about 98% by volume. It is usually pumped uniformly around the outside
of the jacked lining through injection points in the rear of the shield or through

specially provided holes in the pipe line, or a combination of both. As the linings are
normally lighter than the weight of slurry they displace, injection of slurry through the

top of the lining counteracts the tendency of the lining to float upwards. In addition to

75
Chapter 2 Review of Pipe Jacking

reducing the frictional forces, the bentonite supports the ground immediately behind

the cutting edge of the shield, thereby limiting any settlement and reducing the

possibility of future soil collapse onto the pipeline. Slurry lubrication offers the
opportunity of installing longer runs of jacked tunnel linings with fewer points.

Washbourne (1986) has investigated the use of thixotropic slurries in the tunnelling

industry as a result of a programme of research. The use of bentonite slurry smear is a


common practice in the UK (Washbourne, 1982) . In this technique bentonite slurry is

injected over the pipe prior to its entry into the ground, although this has a negligible

effect in granular soils where the lubrication would be most useful. By contrast

injection of lubricating slurry behind the shield and/or through the pipe wall acts to

separate the outside of the jacked tunnel lining from the surrounding ground, and this

can reduce sliding resistance in granular soils.

As friction is greatly reduced by lubrication, slurries can greatly increase the distance

to which the tunnel can be jacked in a single run without intermediate jacking.
Washboume (1984) concluded that

Fb = (weight/m) slurry - (weight/m)linlng (2.33)

where Fb is the net positive buoyancy per metre, giving a tendency for floatation of a

tunnel lining in a slurry .

Haslem (1983) also concluded that lubrication has a great effect on reducing the

frictional force between the surrounding soil and the surface of the pipeline. He

stated that the conventional theory of the pressure induced underneath the pipe is
attributable to the weight of the pipe itself. By adding bentonite, the pipe displaces a

76
Chapter 2 Review oJ Pipe Jacking

weight of slurry greater than its own weight which results in an upthrust pressure on

the pipe. If the pressure provided by the bentonite is sufficient to maintain the overcut

void along the length of the pipe, the contact area between the soil and the pipe will be

limited to a strip along the crown of the pipe. The bentonite slurry offers no resistance
to the pipeline and hence the only resistance to forward movement is generated by

pipe-soil resistance at the crown of the pipeline, together with face resistance.

The effect of the slurry lubrication has been well observed from a number of on-site

pipe jacking operation by Rogers et al (1989A and B) and Norris (1993) as

demonstrated by Figures 2.16 and 2.15e respectively. The observation has shown a
dramatic reduction in the jacking forces.

It can be concluded that, in order to achieve the greatest benefits of slurry lubrication,
the slurry must be injected round the forward end of the pipe run as jacking proceeds.

Slurry injection into the overcut annulus tends to make the pipes float, although this
sometimes requires a very difficult slurry-sealing operation. Reduction of jacking
forces by typically up to 50% can be achieved by lubrication .

. 2.6.3 SPECIAL JACKING PIPES

Special jacking pipes are needed in certain circumstances, such as where :

1. high friction values between the surface of the pipe and the
surrounding soil occur,

2. high strength pipes are required, for example adjacent to the shield or
inteIjacking stations, and

3. the use of special materials in jacking the pipes is required by local

77
Chapter 2 Review oJ Pipe Jacking

conditions.

2.6.3.1 Pipe surface

Jacking pipes can be made from steel, concrete, clay, ductile iron and other materials,
to which can be added coatings. The magnitude of the sliding resistance is dependent
on the friction between the surface of the pipe and the surrounding soil. This value of
friction varies for anyone pipe surface because of the different frictional characteristics
of the surrounding soil. In addition the value can change markedly with the type of
pipe surface. For example, steel pipes have less frictional resistance than concrete
pipes due to the nature of the surface.

In order to reduce jacking forces concrete pipe manufacturelS are trying to produce a
smooth surface finish for their jacking pipes. Research is underway on how to
achieve Iow surface friction values either by using conventional concrete or by coating
the pipes with different materials, such as reinforced plastic matrix, paint and
polyuretha ne varnish.

2.6.3.2 High strength pipes

High strength pipes are required adjacent to the jacks and for long distance drives to
sustain the large forces involved. The development of glass reinforced concrete
jacking pipes has contributed to improved site operations, as reported by Takada
(1987), who studied the feasibility of long distance jacking using glass reinforced
pipes. Laboratory tests demonstrated that these pipes have high axial compressive
strength .

78
Chapter 2 Review ofPipe Jacking

2.6.3.3 The use of special materials

High ground water tables can cause problems during pipe jacking since water can
infiltrate during construction . Tohyama & Koiwa (1987) discussed the use of
membrane wrapping in pipe jacking. They noted that infiltrationlinflow of water
during tunnel driving worsens the working conditions inside the tunnel. Preventative
measures to reduce infiltration/inflow required labour, time and cost. Membrane
wrapping was developed to counteract this effect and has proved successful. In this
method, the tunnel is completely covered with a waterproof vinyl sheet . The sheet is
sufficiently strong for use in very gravelly ground. In addition they showed that the
jacking forces required were far lower than the standard values (Figure 2.20) . Even in
the case of the longest pipe jack, approximately only one third of the standard force
was required. It also demonstrated that the membrane prevents lubrication from

dispersing into the ground, thus greatly contributing to lower jacking forces. These

combined effects prove that the jacking distance could be significantly extended, thus
reducing the number of jacking shafts and greatly reducing the cost of the project.

2.6.4 INTERMEDIATE JACKING STATIONS

Intermediate jacking stations are used when the pushing force of the main jacking
station is no longer adequate to overcome the friction between the pipes and the soil or
where an increase in force would result in the load bearing capacity of the pipes being
exceeded.

They are most commonly used in very long drives. An intermediate jacking station
consists of a steel shield introduced in the line of pipes with hydraulic jacks mounted

79
Chapter 2 Review of Pipe Jacking

inside the periphery (Figure 2.21) . The front section of pipes are jacked using the

pipeline behind as the reactive force. The jacks are then retracted and the back section

of pipes are jacked forward using the thrust pit rams. As at the thrust pit, the pipes at

the intermediate shield are protected with load spreading steel rings. One or both of

the pipes adjacent to the intermediate shield have a rebate so that on completion of the

pipe jack all hydraulic rams, strengthening rings and load spreaders can be removed

and the gap can be closed to form a joint. Very long pipe sections can be jacked using

a section by section jacking sequence.

The number of intermediate stations required will clearly depend on the length of the

pipe sections, the resistance at the face, and the friction acting on the jacked pipes.

Care has to be taken to install intermediate jacking stations well before the forces rise

high enough to require their use, since changes in ground conditions could increase the

forces on the front section considerably. Intermediate stations are normally designed

to be as strong as the main stations in terms of their jacking capacity. In contrast with

main stations, intermediate jacking stations are equipped with a large number of short
stroke hydraulic cylinders with a relatively Iow pushing force per cylinder. This

results in a short construction length with narrow, short thrust collars for a uniform

transfer of force.

2.6.5 OVERCUT RATIO

The magnitude of the overcut around the tunnel lining can affect the sliding resistance

because it influences the interaction between the surface of the pipe and the

surrounding soil. In particular it affects the arching mechanisms set up in granular


soils. Washbourne (1982), for example, describes the overcut as a method of

80
Chapter 2 Review DJ Pipe Jacking

relieving some of the interactive pressure between the lining and the surrounding

ground, and thereby reduce the sliding resistance.

2.7 CONCLUDING DISCUSSION

The finding;of the literature review can be summarised as follows .

1- Pipe jacking has increased in popularity for new pipeline and tunnel construction,

and renovation of existing underground utilities in busy urban areas. The technique

is most used in Japan, Germany, the UK, and the USA, although other countries

around the world are starting to adopt this tunnelling method .

2- Pipe jacking has both advantages and disadvantages over trenching and traditional

tunnelling techniques, and these are summarised in Table 2.8 .

3- One construction problem concerns the length of the jacked pipeline. Large jacking

forces are needed for long drives and these are restricted by the capacity of hydraulic

jacks, the resistance of the supporting wall, the strength of the pipes and the deviation

of the pipeline. The type of the surrounding soil and the contact area between the pipe

and the soil generate different jacking, or sliding, resistances for the whole pipeline

and these need to be accurately, if not precisely, predicted. Intermediate jacking

stations can be used to'reduce the problems, but these are expensive to install and

require a good appreciation of the likely forces generated by the ground to ensure good

engineering, hence economic design. It is also important that they are installed in

sufficient time to ensure that the front section(s) of pipes do not become immovable.

81
· Chapter2 Review ojPipeJacking

4- Little research work has been done towards understanding jacking forces. The
current method of predicting these forces in the UK is based on contractors'
experience and empirical relationships determined from site records for different types
of soil (Craig, 1983) . In some countries empirically based formulaehave been used to
calculate jacking forces. Theoretical solutions have been postulated, for example Auld
(1982) produced a theory for calculating jacking forces based on the arching principle,
expounded by Terzaghi . Nevertheless estimates of certain parameters, based on
empirical observations, are required in the calculation such as values of the face

resistance . Much more information on this subject is required before accurate


predictions can be made.

5- The factors that influence the frictional component of the jacking forces are the

overcut ratio at the face of the excavated tunnel, the type of the soil around the
pipeline, the insitu stress conditions, and the amount of the contact area between the
pipeline and the surrounding soil .

6- The methods of reducing the jacking forces are the use of lubrication around the
pipeline, the use of smooth external surfaces for the pipes, the use of overcut, the
installation of intermediate jacking stations at intervals along the length of the pipeline,
and the use of a membrane placed between the pipe and the soil, between which
lubrication can be injected. This latter technique can also be used to overcome the
problems of a high water table.

7- Special cases of pipe jacking include curved tunnels. For practical purposes,
straight drives-are usually adopted and shafts have to be built at points where the

82
Chapter 2 Review of Pipe Jacking

out
pipeline has to go through a bend. However, recent work has been carried"in Japan to

overcome this problem and some projects have been successfully carried out with

large radius curves. Special laser guidance systems and strong concrete pipes were

used to overcome the problems associated with a curved pipeline.

It is clear from these findings that there are several areas in which research is required.

These are described below.

1- Sliding resistance is influenced greatly by the type of soil surrounding the jacked
lining . Investigation should be made to specify the limits of this variation by

considering theoretical aspects of the surrounding soil and the soil-structure friction
phenomena of different types of soil. Some study of jacking resistance in a cohesive

soil has been done. The contact area between pipe and soil has been studied relation to

the elastic theory, and its influence on the forces recorded in practice has been

estimated (Haslem, 1983 and 1986, Q'Reilly and Rogers, 1987) . This remains a

complex problem. However a more profitable area of research concerns cohesionless

soils in which the mechanism of soil-pipe interaction and generation of frictional forces

can be more easily determined.

2- It has been noted that the magnitude of the overcut can have a significant effect on

the sliding resistance of the jacked tunnel, especially in granular soils where collapse
of the soil over the pipeline occurs immediately (Washbourne, 1984B) . Research

should be undertaken to establish the magnitude of this effect and optimum values for
design. Whilst larger values of overcut might not be feasible in certain situations

where ground movements are critical, in many cases a relatively small increase in

overcut might permit longer driving distances and hence more efficient site operations.

83
Chapter 2 Reuiew of PIpe Jack1ng

3- In predicting the jacking forces required for a particular type of soil, little

consideration has been given to the magnitude of the overburden pressure that will
occur in dilating soils above the pipeline. This should likewise be researched since

free field horizontal and vertical effective stresses, although providing an upperbound,

might provide a considerable overestimation of forces in practice.

4- Research is also required to investigate the increase of jacking forces caused by


misalignment of the pipeline. The jacking capacity of the pipes required to sustain

these forces during installation should be taken into consideration in this work.

5- More research is required into methods of reducing jacking forces by lubrication

and/or coating the pipes with material of Iow frictional resistance. The material should

be tough enough to resist damage to its surface during the jacking process, and hence

should remain relatively smooth.

6- Determination of the coefficients of friction between the pipe surface and

surrounding soil, for different types of soil and pipe surfaces, are required to permit
better estimation of jacking forces in practice.

84
Chapter 2 Reuiew of Pipe Jacking

.
Table 2 8 Advantages and Disadvantages of Pipe Jacking .
ADVANTAGES DISADVANTAGES
1. It can be used In different ~es 1. The total length of the jacked
of soil. and in conditions were pipes may be restricted
compressed air would otherwise during construction ( although
be necessary . this can be overcome) .
2. The ~cked pipes form the 2. The amount of permissible
finis ed lining, and there Is no CUlVature of the tunnel is
need for temporary l1rl1ng . minimal.
3. Good and stable lInIng with 3. The build up of the jacking
little risk of soil and pipe forces can prove excessive if
settlement . unexpected ground is
encountered.
4. Fast construction technique in
comparison with traditional 4. Misalignment of the
tunnelling and trenching . f,lpellne may cause pipe
racture and spalllng of
5. The volume of excavation concrete at the joints, which
required is significantly nlight not be apparen t from
reduced. Inside the tunnel.
6. No damage to roads or public 5. Pipe joint seal cannot be seen,
utilities, and no disruption to and thus damage might not be
traffiC when compared apparent.
with trenching techniques.
7. Less smell, nOise, dirt and
visual Intrusion.
8. Smaller access requiredfor the
starting and finishing pits than
conventional tunnelling
techniques.
9. No subsequent grouting
required.

85
"'~D~"""--~--~~--~~--~--e
-----------------

Figure 2.1 Typical Pipe Jacking Pit, (after PJA)


1. Excavation machine 5. Crane
2. Disposal system 6. Pipes
3. intennedlate jacking station 7. Control unit
4. Hydraulicjacks 8. Power supply unit

Figure 2.2 Mechanised Pipe Jacking System


" ,
',,'...
,',,','
,,,,
,,,
,,, ,,, ,
,, ,,,
,, ,, ,
,,,
",','
,,
,",,','
,,
,,, ,,,,
,,.

cover
plate (kg)

(a)-Experimental layout

2.5

2.0 1\ I loose
I sand
~ i-"

1.5
/'
....V'
'61l
~
Cl) 1.0
\.-- V dense
sand
I
0.5

0.0
o 2 4 6 8 10
dh (mm)

(b)-Experimental results

Figure 2.3 Pressure Upon a Cover Plate Governed by Arching


(after Kunczl in Szechy, 1966 )
........... .~ .............................. ............ ;... .....................
~

..., ,
.'
, 2B1
soil
D
, 280 ,
,'... IP/,

Bo=b
B1=b1

Tunnel
45 - <1>/2

Figure 2.4 Tunnel In Sand (after Terzaghl. 1943) .

Figure 2.5 The Pressure Bulb on a Tunnel


(after Blerbaumer In Szechy. 1966
Figure 2.6 Factors Required for Estimation of Jacking Forces
....................---------------------------------------

FIgure 2.7 Methods of Estimating (he Jacking Forces


,,

e e
~
§
...
2BO
...
CIl
J:
J: \::>
\::> +
+ U
u

cr h

Figure 2.8 Vertical Pressure on a Pipe Close to the Surface


( after Auld. 1982)
Civ

-------~---- '- -

, Il Il 'Il ~

Civ + self weight per rr?-

Figure 2.9 Ground Pressure on Pipes


(after Auld. 1982)
7 B , A
I
I 0 0 Measured Values

/,
6

z 0
0
e ,
~
&
5

4 ,I
I
0
0
• 0

- 72 kpa

""c I 0 0
);l
..,
~
~
3
I 0

2 ! .. ~~~~ ..........
.....C •• 72 kpa
f .............
....., ..

0
0 100 200
Jacking Steps
Figure 2.10 Jackinf. Forces for Several Drives In Clay
(after laslem. 1986)

z
e~
~
6 / .C·
.2 ..,........
,......
,-..•.•...
if 4 ...'.
);l . ..,-.-
..,
~
~
., ...............
........•...

o
o 100 200 300 400 500

Jacking steps
Figure 2.11 Jacldn~ Forces for Drive I
(after Has1em. 1986)

5 B

Z
e 4

"~
.2 3
'"
c
);l
~

.!l 2

/ c
.......
..... .........
....
.... ......
o
o 50 100 150
Jacking Steps

Figure 2.12 Jackin~ Forces for Drive M


(after Haslem.1986)
w

10000 ............... ... ........... .


,
A
............
'" ". A"' ..
~ .................................

7500 area

"
Experimental arrangement
'" S Relates to
.§ time delay
Scaled weight of
~'" 5000 1200mm OD pipe
l ,,
~
,,,
" ,,
~
'"
Cl
0
,, Experimental results
,,
U
,,,
2500 ,,
, Prediction of elastic theory
,,~____--~e~--~O
~
,~-e,
,,,
0
0 5 10 15 20 25
Normal force (kN/m)

Figure 2.13 The Relationship Between Contact Area and Applied


Normal Stress (after O'Reilly and Rogers, 1987)

rIn A· Ass...-ntt. lUll tIuOrO"Cy conlOCI Cl cro-n


ro.c.
,,",H, L •. AU....,.,U l~ ~r . (Ql"i10(1 01 ",......,


ModolllfCl
prf'(hC:IJ(lt\S
""... on
~~""""'IQI
(0"110(1 OOIQ

Figure 2.14 Correlation Between Jacking Force Data and the Predictions
of a Range of Models (after O'Reilly and Rogers 1987)
20,-------------------------------------------~

Short weekend
12th Aug 1990

o
w
en Delay due to fractured water
0...
« r,P. inserted includes main. includes weekend
-'
w 'Weekend 4th, 5th Aug 1990 18th. 19th Aug 1990
en 10
~
o

Diverted clay pipe land drain

I.P. =instrumented pipe


O~~---.-----.------r_----,_----._----_r----~
o 20 40 60
LENGTH OF DRIVE (m)

1.4,---------------------------------------------~

BOLTON
1.2 +---------------------------------+,......,.------~

Z
::=.
w~ 1.0+---------------------------------.--+--------~
0'"
a:'g
om
~ ~ 0.8 -!~----------------------------------------~~-4------------_4
C!Jo 29.8 kN{m
z.c Waler main fracture

S2 C
25m from entrance

~ 0.6+---------------------------~~~--------------~
...,
0.4 +-------------;---+--rtt1boo:!lrrt.f'!.l'--'-----------------~

I--------to..- Heavy rain throughout


0.2 +-,....--,IJ)y.~~~L-----.I:====-.:...:......-=-_l

O.O+-----_r-----.-----,------r-----.-----~----~
o 20 40 60
LENGTH OF DRIVE (m)

Figure 2.15a Jacking Records for Scheme 1 (after Norris, 1993)


26
24
22
20
Mine shaft
0
18 encountered

r r- t
UJ
en
a.. 16
::5UJ 14
en ~ Weekend
~ 12 16th,17th
0
10 Feb 1991

8
6
4
2
0
0 10 20 30 40

LENGTH OF DRIVE (m)

2.6
NEWCASTLE
2.4 Mudstone
in the invert
.. I
Boukler cia
in the invert
~ r Mudstone ~
I in the invert
2.2
lA
Z
6
UJ<i)
O-c
2.0
1.8
I.P. inserted ,~y
\,' j(f \lIf' (

Cl: c: 1.6
o
u..
ctl
~ 1.4
~ trV
<!l
~E 1.2
:.:::
0
j ~. 'A. VII \ I

~
-, 1.0
0.8 "
,It..; "'
"I .
If
'
8 kN/m
UlfNC
\j';IJ
54 kNfm

0.6
0.4
0.2
0.0 -r

o 10 20 30 40
LENGTH OF DRIVE (m)

Figure 2.15b Jacking Records for Scheme 2 [after Noms. 1993)


19
17
Weekend
16
16th,17th
15 March 1991

Cl
w
(/)
14
13
12
,I

a.. 11
:5W 10 Weekend

(/) 9 9th, 10th


>-
« 8 Match 1991
Cl
7
6
5
~
4
3
2
1
0
0 20 40 60 80
LENGTH OF DRIVE (m)

6.0
HONOR OAK
12 hourWOl'king Continuous working

5.0

Z
6 V
w~ 4.0

~_54kN/m
(J '"
a:-g
0
u..
. C!J
''""
::l
0 3.0
Z'::
~~(I
Face sampling
~~

t I~ ~
(J
«
-, I
TUnnel noticeably damper
2.0

\)ltL hr ~~
1
t
I.P. inserted
1.0

0.0
V
o
-,
40 60
, ,
80
20
LENGTH OF DRIVE (m)

Figure 2.15c Jacking Records for Scheme 3 (after Norris. 1993)


26
24 Short weekend
4th Aug 1991
22
20 t
0 18 Short weekend
W
(/) 28th Ju~ 1991
0... 16
~
w
(/)
14
~

Jl
12 Weekend
~ 21st, 22nd
0 10 July 1991
8
6 Pit bottom data
acquisition failure
4
2
0
0 20 40 60 80 100 120
LENGTH OF DRIVE (m)

3.5 UNWBAICATED .. .. WBRICATED


ABBEY VILLAGE
3.0 Boulder clay in invert • I' .. I
limited trimming
~

z
,:. 2.5
w~ Trimming 20mm with shield
0'"
a:-g
0'" 2.0 ..
u.~
(!lO
z..c:
s;;:t:. 1.5 •
0 Running sand
Shield used
<I: in the invert.
...., ' - Intermittent trimming
Trimming B.C.
1Omm with sh;eld
1.0 In Clown 0
avoid tipping of
shield

0.5
Miner excavating 20mm past shield

0.0
0 20 40 60 80 100 120
LENGTH OF DRIVE (m)

Figure 2.15d Jacking Records for Scheme 4 (after Noms, 1993)


30
Further pipe
damage sustained

+
repairs

Interjack 2
20
incorJXlraled
0 Weekend 30th NOli
W
U) Weekend 16th. 1st Oec 1991
Q.
17th Nov 1991
SW
~
C3
Inlerjack 1
incorporated ~ ·f
Damage to pipe 34
10
Weekend 9th. first observed
Breakthrough
10th Nov 1991
1 into shaft 5 Weekend 23rd.
24th Nov 1991

+ t
LP inserted

0
0 40 80 120 160 200 240
CHAINAGE (m)

CHELTENHAM

5i-----------------------__~--~--,_._------~

Z 4
e Lubrication
W
U
-;n commenced
a: "0c
0
u. ""' 3
+
z "
(!) 0

52 E.
u
~ 2

Misalignment 2 Closing-up interjack 1

160 200 240


LENGTH OF DRIVE (m)

Figure 2.15e Jacking Records for Scheme 5 (after Norrls, 1993)


... 0lil .... .nth. spoil
r......II.ocIing to

...'"
on

...j
VI
20
30

""hind
27th.28th
tong weekend
4th,Sth.!,h
I
lov ...oduction

_Hof.-J:..----
I
?c Apra i9l_5~ ________- I
'" 10 I
I
I
I
I
25 so 75 100 125 ISO
I
175 200 250 Z75 300
LENGTH OF DRIVE (melrts)
I I
I
700 I ' ...0lil •• vith "FC being
I
feI puonp"~ ~~di
t
600 ~~FC' j!
"continued to :
I
"Fe
be..,..
: usod"l
I
:
I I

500 I

~
~ 400
...
u

'" 300
:2
~ "FC b.ing •• od -
j><king pr..."," Iov"
""
u
!!i 200
.

100

25 so 75 100 125 ISO 115 200 225 250 215 300


LENGTH OF DRIVE Imetresl

Figure 2.16a Jacking Records for Drive E8-E7 (after Rogers et aI, 1989)
so
weekend
29th. 30th
40 June
weekend I
Very slow 22nd. 23rdt
progress
8VI 30 recorded weekend Junl
...
a.
.....
.....
weekend
15th. 16th
June
VI 20 weekend 8t~. 9th ~
...
>-
o
1$1. 2nd
June 1985
June! _ _---"1

50 75 100 ) 125 150 175 200 225 250 275 300


) )
LENGTH OF DRIVE (metresl l
I ) I
)
"Jacking pressures I "FC b.ing .comm~ncod "FC b4ing
) dropp.d con,id ...b)y I ustd" u.ing FC" /1 puonp<!d
500 since Fe ring used" I "Pumping
• FC"
1 I . "sloth
FC")
)

400 I

~ 300
- o

.....
u FC·~
"Stoppod t
"Stopp\d
!5
... 200
I!I
IISing fC-
"Started
Z
;;: FC'·
:;;! 100
~

25 SO 75 100 125 150 175 200 22S 250 275 300


LENGTH OF DRIVE (metres)

Figure 2.16b Jacking Records for Drive E8-E9 (after Rogers et al. 1989)
_dry gm
8

• ___ . water at G.L 7m


7
Sm
Z 6
~
(])
u
~
S 3m
0
u.. gm
./
0>
c 4 . .// 7m
:;;: //
u Sm
..,'" ././
.// ;'
;'
3 // ,/ ., 3m
/ . / ./ ./ ,./

2 //
.
~
/'
./
;'
",,/
, ,-

// '/./..., ""'"
"'// . / ,., "".
7"// ~ '"
~/"
/..,,-'" ,
,/

0
0
i
SO 100
i
1S0 200
i i .-
Distance (m)
Figure 2.17 Variation of Jacking Forces with Cover
(after Stein, 1985)

OVERCUT RATIO (R) =( B - b )/ b

Figure 2.18 Definition of Overcut Ratio


(after O'Reilly and Rogers, 1987)
l.P. CHAINAGE (m)
9.9 10.3
7...~5__~_7~.~9__J -__~~__e_.7L-~__9_.~1__J -_ _L-~__- L__J -_ _L--!
8.3 9.5
5.0 ~
:;minute 4minuta 3.5 hour 2 minute
stoppage stoppege
"""""- sto~.

4.0
7"""'"
stoppage
\
+ "" .....
7 rr.ir.ute

I
~
~"N"""U""O""NQoeuy

It 2.D ..... ~

"M

1.0
• HONOROAK

•.•7:8
1 :'-......,::;---;;-;;-'-,,;;-.
B.2 B.B .0
,.. .~~,;:;.,:-" TOTAL JACKING LOAD
..\-__..:-__,.......!'•.;~~~_~.~E!:.. ---r---'--~:::---r--~::--'----:;:;.--r--:;;;;;-'
!,'
0.0 44 .0 44.4 44.S 45.2 45.6 46.0 46.4 46.8
DRIVE LENGTH (m)

a) Jacking load

400
+ TOP
350 ////'/
• RIGHT
" LEFT /"/ +
300 ~
BOTTOM ////
C?
a. 250 "
/"/"/
6 +
<.: 200 /"/" +
/" " "
::;; " /"/"+
(!l +
+
ii5 150 ,/////
" +

.
--'
<.:
z 100 /"/" +
u:: /"
/"

~c/l. 6A~
50

0
,.,~ ...:. •
/,/
-50
-50 50 150 250 350
INITIAL SIGMA (kPa)

b) Total radial interface stresses

Figure 2.19 Time Dependent Changes During Stoppages on Scheme 3


(after Noms. 1993)
Thrust
Force
(t) Inner Diameter of
A-~--­ Reinforced concrete pipes
1,OOOnun
900
A-2--- - ditto - ~,OOOmm

800 A-3--- - ditto - l,lOOmm


B-lv--~ - ditto - l,200nun
700 B-2--- - ditto - l,200mm
600

500

400

300

Figure 2.20 Thrust Force Against Jacking Distance for Special


Jacked Pipes [after Tohyama and Koiwa. 1987)

Jacking pipes Hydraulic Jacks

Figure 2.21 Intermediate Jacking Station


Chapter 3 The Ideology of The Research

CHAPTER THREE

3 THE IDEOLOGY OF THE RESEARCH

3.1 INTRODUCTION

3.2 METHODS OF INVESTIGATION

3.3 FACTORS INFLUENCING THE JACKING FORCES


3.3.1 TYPE OF SOIL
3.3.1.1 COHESIVE SOIL
3.3.1.2 COHESIONLESS SOIL
3.3.1.3 TIlE DENSITY AND DILATION OF
COHESIONLESS SOIL
3.3.2 OVERBURDEN PRESSURE
3.3.3 OVERCUT RATIO
3.3.4 TIlE SIZE AND TIlE LENGTH OF THE PIPELINE
3.3.5 PIPE SURFACE
3.3.6 PIPE JOINTS
3.3.7 THE RATE OF JACKING
3.3.8 MISALIGNMENT

3.4 BOUNDARY CONDITIONS

3.5 TESTING PROGRAMME

86
Chapter 3 'The Ideology of The Research

3 THE IDEOLOGY OF THE RESEARCH

3.1 INTRODUCTION

As reviewed in Chapter 2, most of the research work on jacking forces has been based

either on the theoretical aspects or on practical data obtained from various pipe jacking

contracts and from small research projects. Pipe jacking research has been mainly

concerned with improvement of construction methods and equipment, and the

reduction of the jacking forces by means of lubrication and intermediate jacking


stations. Most of the work has been carried out in Japan by the equipment

manufacturing industry, although similar work has also been carried out in Germany,

the USA and the UK .

The main interest of this research work is the study of jacking forces in model tests

with the aim that the results will be applicable to full size pipe jacking work after

appropriate adjustment by similarity analysis. All of the experimental work reported

herein is based on similar jacking equipment and methods of site operation to those
used in practice . Recent experimental research has been conducted at Oxford

University, where a small scale model has been used to analyse the cyclic loading on
jacked pipes (Milligan and Ripley, 1989) . A similar test set up, with due regard to the

particular problem being investigated here, has been used.

Other research work has been carried out on the improvement of jacking distance by

using different means of force reduction. None of these investigations have studied

rigorously the effect of the various influencing factors on the jacking force behaviour.

The most relevant theoretical work was carried out by Auld (1981), who developed a

87
Chapter 3 'The Ideology oJThe Research

relationship, based on the arching principle of Terzaghi, for calculating the jacking

forces from soil data and by Herzog (1985), which is based on the statistical analysis

of the data obtained from a particular situation.

There is still relatively little published information on the magnitude of jacking forces

in practice, with the significant contributions concerning the work carried out by
Haslem (1983,1986), Rogers et al (1989A and B), and Norris (1993) *. Also a little

work was done on the elastic theory of clay around the pipeline and its relationship to

the magnitude of the jacking forces generated during construction. There is scope for
this work to be built upon.

Therefore the aims of this project are to develop suitable equipment for measuring

jacking forces in relation to different parameters, to produce such data, and hence to

relate the effects of the various parameters to the likely magnitude of the jacking forces

generated during construction.

3.2 METHODS OF INVESTIGATION

There are several different techniques that can be adopted during the investigation of a

practical problem. Each technique has its own advantages and disadvantages for a
particular application.

To monitor the jacking forces during construction is the simplist method of

investigation. This will provide a wide range of data to estimate the magnitude of

jacking forces, in terms of the resistance per square metre of pipeline for a particular

, * Also O'Reilly and Rogers (1987)

88
Chapter 3 The Ideology oJThe Research

type of ground condition. Such a study on the drag forces occurring during pipe
jacking, based on existing evidence, is reported by Craig (1983) . Other researchers
have studied the relationship between site data and the jacking forces expected to be
encountered during construction, in particular Rogers et al (1989B) . The variation in
field data for a particular site may causeinaccuracy in the investigation. In addition,
the different construction methods used by different contractors can cause variation in
the jacking forces recorded . The most important problem with this approach,
however, is the necessity for very large amounts of information about the precise

ground conditions and the construction operations, and for these data to be collected
from a large number of sites to provide statistical significance. Neither objective is
easily met and the former is often not possible. Thus while high quality site data are
necessary for calibration of theoretical and laboratory models, they will not provide an
answer to the problem being addressed here.

Full-scale experimentation at a field site provides an accurate simulation of the


construction process, a high degree of certainty of ground conditions and good control

over site operations and instrumentation. Accurate site parameters, such as in situ
pressure
stresses, deformations and pore water'measurements, could be obtained and the data
obtained would have a high degree of accuracy. Instrumentation and logging facilities
are expensive to provide away from the laboratory. The other disadvantages of this
method include the high costs of both developing and performing the field
experiments, and the site specific nature of the results. It would also be difficult to
ensure uniform soil conditions, although the actual conditions could be well defined.
Significant variation of the soil type and state would be practically impossible.

89
Chapter 3 The Ideology of The Research

In order to overcome some of the problems of full-scale field experiments, full-scale

model testing can be adopted in the laboratory. The overall control of the experiment

can be easily achieved. Applying surface loading, or surcharge due to overburden,


would require simulation and suitable test equipment would also be required if accurate

data are to be obtained. Preparation and testing can be slow, although a high degree of

accuracy can be achieved. In addition, the cost of providing appropriate simulation of

site operations, with proper site equipment, can be high, and the cost involved using

different soil materials can be significant. Thus if this approach were adopted, a

limited number of high quality, realistic experiments could be carried out.

Another laboratory technique is the use of scale model equipment. The advantages of

using this method are that there is a high degree of control over experimental

conditions, a reduction in the total cost of the experimental work and the facility for

carrying out a large number of tests in which different parameters can be studied. The

main purpose of using the scale model is thus to reveal the relationships between
various parameters in a pattern that can be investigated further either by full scale

model testing or by real site experiments. In addition, preliminary investigation can

be achieved with a high degree of accuracy for various parameters, whereas the use of

full scale testing for this would be costly and cause considerable delay. Similar

programmes of work were carried out at Cambridge University for scale modelling on

soft tunnels (Caimcross, 1973, and Atkinson et al, 1974 ) .

Theoretical work is another option for studying jacking forces. Most of the theoretical

work in this respect involves the use of earth pressure theory to estimate the vertical

and horizontal pressures around the jacked pipeline. The combination of the various

influencing parameters is used to establish a relationship that may predict the jacking

90
Chapter 3 The Ideology oJThe Research

forces. Theoretical work in this area has been carried out by several researchers, but

only on a simplified level, probably because of the difficulty in modelling the

considerable variation in ground conditions . While sophisticated finite element

modelling could be carried out, it would require full-time attention over a long period

and would not guarantee accurate site simulation. Indeed, the only study in which
finite element analysis has played an important role is in the prediction of settlement

above, and the movement of soft ground around. tunnels by Attewell et al (1986) .

The validity of this method is dependent on the accuracy of the assumptions made

during the analysis. and can only be proved by experimental work and data obtained

from site in any case. These validation data do not currently exist in sufficient number

or quality .

Finally. it is important to appreciate that scale model tests. such as those initially
undertaken by Cairncross (1973). are not necessarily intended to reproduce precisely

to scale a real tunnel during construction . The main purpose in this case was to
illustrate the way in which soil around a circular cavity behaves as other parameters

vary so that. based on this understanding. the prototype situation can be designed for ..

The results of scale model testing provide a source of experimental data for

comparison with existing methods of calculation and with measurements from site.

The test results may thus lead to new methods of calculation for predicting the jacking
forces. A summary of methods of investigation is shown in Figure 3.1 . Scale model
testing was chosen as being the most appropriate method of investigation for this

work.

91
Chapter 3 The Ideology of The Research

3.3 FACTORS INFLUENCING THE JACKING FORCES

There are many factors that influence the magnitude of pipe jacking forces. The
factors that have been considered in this research are shown in Figure 3.2 .
Lubrication and misalignment are the only two significant factors that have not been
included, because of their complex and variable nature as highlighted by Haslem
(1983, 1986) and Washbourne (1982,1986) .

3.3.1 Type of soil

3.3.1.1 Cohesive soil

The ideal ground for pipe jacking operations is stiff clay or dense fine sand with
apparent cohesion, as these soils require the minimum of suppon and can be easily

excavated. However, predominantly cohesive soils of a firm to stiff consistency,


cemented granular materials and component soft rocks are also suitable.

The reason for the suitability of these soils for pipe jacking can be explained by
considering their apparent cohesion. Coulomb's equation relates shearing resistance,

or shear strength ('t), of soil to normal stress as follows

t' =C' + cr' tan <p'

Cu , C' = undrained, effective cohesion,

<Pu. <P' :: undrained, effective angle of internal friction of the soil

92
Chapter 3 The Ideology of The Research

cr. cr' = total, effective nonnal stress

Thus it follows that the shear resistance will equal the apparent cohesion if the normal

stress is zero, and immediately after excavation it will be the undrained cohesion that

will apply.

By assuming that (J = 0 at the face of the pipe jack, the cohesion of the soil is equal to

the undrained shear resistance, and, if the cohesion is sufficiently great, the face will

be self-supporting. This will apply equally to the excavated bore as the pipe is jacked

through it if the apparent cohesion, which is in reality a negative pore water pressure

unless the soil is cemented, remains.

The contact area between the pipeline and the surrounding soil is theoretically minimal

in such a soil, depending on the tidiness of the excavation, and is restricted only to the

area between the bottom of the pipeline and the soil at the invert of the excavation .

Progressive collapse of the soil will occur in such soils as the negative pore water

pressures reduce in magnitude, which will occur over time and depends upon the

permeability of the soil and the availability of water.

3.3.1.2 Cohesionless soil

Coarse sands, gravels and cobbles, or mixtures of these materials, having a loose

consistency often create difficulties, as their structure is disturbed by the jacking

process and the particles readily collapse onto the pipe, giving rise to high jacking

loads. It is usual to attempt to stabilize such ground by grout injection prior to jacking

in order, in effect, to make it self-supporting. In water bearing sands and gravels it is

generally necessary to dewater the strata to below the underside of the drive in order to

93
Chapter 3 The Ideology oJThe Research

maintain stability, unless chemical stabilisation can be used in this case to reduce its
permeability and hence stop water flow.

Again the reason behind the difficulties in these materials can be explained by

Coulomb's equation, which in this case reduce;to

Shearing resistance = cr tan <1>

Since there will be no apparent cohesion. The shear resistance of the soil is zero if the

normal stress is zero, as in the case at the excavation surface, and hence the soil tends

to collapse around the pipeline such that the contact area would be at its maximum.

This results in a high total sliding resistance during the jacking process.

Very soft clays and silts are also liable to collapse since they have insufficient shear

strength to be self-supporting . These prove to be difficult strata for jacking

techniques, as- in any form of tunnelling, for they can rarely be stabilized
economically.

3.3.1.3 The density and dilation of cohesionless soil

The behaviour of cohesionless soil at constant volume and the behaviour under

constant confming pressure can be tied together as follows. If a dense sand is to fail in

shear, the high degree of interlocking must somehow be overcome. This can happen

either by shearing, hence fracturing, of the particles, or by an increase in the volume of

the soil as the particles rise up over adjacent particles in order to create a shear surface.

94
Chapter 3 The Ideology of The Research

It will take more energy to cause either of these happenings than will be necessary
simply to slide soil particles over a plane shear surface. If the soil is free to expand,
the path of least resistance is to expand and to overcome the interlocking in this way.
If the soil is prevented from expanding, the path of least resistance may lie in
,
fracturing the soil particles, in which case energy is expended in the fracturing

process.

The case of shear at constant volume is of little importance when dealing with dry
typically:
sands ~ since their specific volumes will be'on the dry side of the critical state and the
energy required for particle fracture is, in general, for greater than that required for
volume expansion.

The angle of friction of a soil will vary with stress and density, which thus have a
great significance in any calculations. A number of theoretical models have been

developed by engineers to investigate this variation . They are reviewed by


Bolton(1979) as follows

1- A particular soil has a roughly unique ultimate angle of friction, no matter what its
initial density.
2- Initially dense soils have a peak strength that is higher than their ultimate strength.

Beyond the peak thin rupture zones can be detected in the previously uniform soil,
within which the density falls towards some critical value below which it will not

drop. The soil in this zone dilates (becomes larger) due to the reductions in density .
3- Soils that are initially very loose take a good deal of straining in order to mobilise
their ultimate strength. The soil sample contracts (become smaller) as it is sheared,
and the density rises towards the same order of critical density as that observed in the

95
Chapter:) The Ideology of The Research

rupture zones of dense samples.

4- The magnitude of the peak strength for dense soils is related to the rate at which the

soil dilates.

During the jacking process, the dilation of granular soil caused by shearing may cause

very high interface pressures between the pipe and the surrounding ground. These

pressures may be greater than the overburden pressure and, consequently, jacking will

be limited to a relatively small distance. This problem can be relieved by creating an

overcut, as described in section 3.3.3 .

3.3.2 Overburden pressure

The overburden pressure and surface surcharge haveaneffect on the resistance of soil

to collapse during excavation, and consequently on the total jacking forces required

during the process. In addition they will determine the normal stresses acting on the

pipe, and hence the frictional resistance of the ground. The total overburden pressure

on the pipeline is associated with the overcut ratio and the type of the soil surrounding

the pipes. Detennination of the normal stress on the shear planes surrounding a jacked

pipeline is thus a complex procedure.

3.3.3 Overcut ratio

The overcut ratio is the ratio of the gap between the excavation and the outer surface of

the pipe to the diameter of the pipeline (Figure 2.18).Overcut is used to reduce the

sliding friction between the pipeline and the surrounding soil by creatin g an annular

gap or by allowing granular soils to dilate. It will thus dictate the contact area and/or

96
Chapter 3 The Ideology of The Research

contact pressures between the pipe and soil . The overcut ratio is detennined by the
to
contractor prior"Construction and is governed by the shield diameter.

3.3.4 The size and the length of a pipeline

The size of the jacked pipe clearly has an effect on the magnitude of the jacking

resistance. The larger the size of the pipe, the larger the contact area between the pipe
and the surrounding soil, hence producing more frictional resistance, and the larger the

face of excavation, hence producing more face resistance.

The length of the driven tunnel is dependent upon the jacking forces that can be

provided and the frictional forces generated while pushing the pipe into the soil. The

frictional resistance increases as the length of the drive increases and, in some cases,

contractors can only achieve a long drive by using techniques to reduce the ground

resistance. Face resistance is not affected by this parameter.

3.3.5 Pipe surface

The surface of the pipeline influences the sliding friction between the pipeline and the

surrounding soil. If the surface is rough, the soil in contact with the surface tends to

penetrate through the trough in the surface and therefore generates a resistance against

the forward movement of the pipeline. Consequently, extra jacking forces are needed

to overcome this resistance. It is important to investigate the magnitude of the jacking

forces for different types of pipeline surface.

97
Chapter 3 The Ideology qfThe Research

3.3.6 Pipe joint

Different types of joints are used in pipe jacking construction. Depending on the type

of the joints, they can act as a source of sliding resistance against the movement of the
whole pipeline. The gap in the joints creates a place for the sUlTounding soil to
become trapped and cause a bearing resistance as the pipe is advanced.

3.3.7 The rate of jacking

The rate of jacking the pipes into the ground is dependent on the type of soil and
method of excavation. The rate of jacking progress varies from one contract to
another. There is no consistent information on this subject, the contractors tending to
drive the pipeline at the rate they consider most suitable for productivity and the

ground conditions.

As the rate of jacking a pipeline reduces, especially in a cohesive soil, the jacking
forces increase. The soil tends to close in on the pipeline and increases the contact area
and/or the normal stresses with time, and hence increases the jacking resistance. In
addition, increases in the jacking resistance when restarting jacking operations in

clayey materials have been noticed, especially after weekend breaks during
construction . For cohesionless soil, delay is less critical because the soil tends to
collapse immediately after excavation around the pipeline. Therefore time contributes
very little to the magnitude of the jacking forces in a cohesionless soil .

98
Chapter 3 The Ideology oJThe Research

3.3.8 Misalignment

Misalignment is an important factor to be considered during the jacking operation.


When the pipes tend to deviate from the proposed line of construction, the jacking
forces increase according to the magnitude of misalignment . In addition,
misalignment can cause a considerable stress concentration on the joints between the
pipes and sometimes breakage occurs, which causes a large extra resistance to the
movement of the pipeline.

3.4 BOUNDARY CONDITIONS

The choice of the boundary conditions for experimental work is important in order that
an accurate simulation of site practice can be achieved. Figure 3.3 shows the
boundary conditions operational in the test box.

A large scale model was considered necessary to simulate the pipe jacking process
practically. The chosen soils were placed in the box, which has five rigid boundaries.
The front and back faces, through which the pipeline penetrates, impose a condition of

plane strain deformation during testing. The sides and the bottom of the box are
sufficiently far from the pipeline to prevent these boundaries from having any
significant influence on the behaviolllOf the soil surrounding the pipeline.

The soils chosen for the tests were uniformly-graded, coarse Leighton Buzzard Sand
and well-graded, medium River Sand. These were chosen because they represent
severe practical situations with high friction values, or drag forces, operating during

99
Chapter 3 The Ideology of The Research

the jacking process. The Leighton Buzzard sand was placed dry while wet River

Sand, at approximately the optimum moisture content, was used . The pore water

pressure is likely to be negligible prior testing. The density of the soil was kept as

consistent as possible during all the tests. Two methods were used in order to achieve

the required density, free fall from a constant drop height followed by compaction by

applying a load of 200 kPa for the dry sand and uniform hand compaction for the wet

River Sand.

The pipe external diameter was kept constant at 0.200 m for the concrete covered pipes

and 0.197m for the steel pipes throughout all the tests. Misalignment of the pipe train

during jacking was avoided, for practical reasons, by specially designed joints.

A surcharge load was applied to the surface of the soil in the box by the use of a water

pressure of up to 200 kPa in a rubber membrane bag. Its magnitude was chosen to

represent the surcharge loads on a pipeline, buried at a typical depth of approximately

10m, from overlying soil. Different loading regimes, in general surface surcharges of

10, 100, and 200 kPa, were applied to the pipeline in the tests in order to examine the

influence of surface loading.

Other important parameters that have been investigated include the overcut ratio, the

length of the tunnel and the type of pipe joints. The overcut ratio, as defined in

Chapter 2, was varied from values ofD to a maximum 0.140 in order to examine its

influence on the jacking loads. The overcut ratio was created by varying the annular

gap between the shield diameter and the pipe diameter. The shield cutting face was

formed at an angle of 30 degrees in order to limit the resistance during excavation, the

chosen angle corresponding approximately to the internal angle of friction of the sand,

100
Chapter 3 The Ideology of The Research

while the outer surface of the shield is smooth and parallel with the following

pipeline.

All the boundary conditions were kept under tight experimental control in order to

achieve standard testing procedures for verifying the influence of all parameters.

3.5 TESTING PROGRAMME

As stated earlier, research work on jacking forces using scale model equipment has not

been studied before. It is intended to illustrate the way in which certain parameters

affect the jacking forces. The results should also provide a source of comparison

between the available theoretical models and practical data.

A testing programme was consequently set up with the following objectives;

I-To study the magnitude of the jacking forces, by pushing a pipeline, installed in the

box during filling, through the soil with different normal surface loadings .

2-To study the effect of different soil thickness on the jacking forces by the same

procedure.

3-To measure the jacking forces generated from jacking the pipeline after excavation

was carried out at the face of the tunnel, under different normal surface loadings .
Different overcut ratios were used in this study.

4-To investigate the influence on the jacking forces of type of soil, type of pipe

surface and type of join ts .

101
Chapter 3 711e Ideology of The Research

The experimental work was planned to collect as much data as possible from each
test. Some 55 tests were conducted using both types of sand, the tests being repeated
in some cases, both to demonstrate repeatability and in caseswhere the results showed

some abnormalities. Further details of the experimental programme are given in


Chapter 5.

102
I
I
:~
I
i:

I.
m Total cost
} Experimental cost

~ Research time

D Experimental control }
H Experimental results

~ Field validation

Figure 3.1 Methods of Investigation of Pipe Jacking Forces


q

IJACKING FORCES
VARIOUS PARAMETERS

1 - - - OVERBURDEN PRESSURE ------( D • q )

- - - LENGTH OF THE PIPELINE ------( L )

1 - - - SIZE OF THE PIPE ----------- (B )

1 - - - OVERCUT RATIO ------------- ( R)

1 - - - - TIPE OF SOIL --------------- ( M;A: .• C'. Cu • 'Y , <1>', <I> u

1---- THE PIPE' SURFACE ---------- ( Concrete. Steel)

L---JOINTS

"MIC = moisture content

Figure 3.2 Factors Iiilluenclng Pipe Jacking Forces


Figure 3.3 The Boundary Conditions Operational in the Test Box
Chapter 4 Material Characterization

CHAPTER FOUR

4 MATERIAL CHARACTERIZATION

4.1 INTRODUCTION

4.2 GEOLOGY
4.2.1. LEIGlITON BUZZARD SAND
4.2.2 RIVER (CONCRETE) SAND

4.3 MATERIAL PROPERTIES AND LABORATORY TESTING


4.3.1 PARTICLE SIZE DISTRIBUTION
4.3.2 DENSITY
4.3.3 SPECIFIC GRAVITY

4.4 SHEAR RESISTANCE


4.4.1 DIRECT SHEAR TEST
4.4.2 TRIAXIAL TEST
4.4.3 SPECIAL SHEAR TEST

4.5 TEST RESULTS


4.5.1 SOIL PARAMETERS AND COMPARISON OF SHEAR
RESISTANCE
4.5.2 DILATION, CONTRACTION AND CRITICAL STATE OF SAND

4.6 THE CONCEPT OF SOIL/SOIL FRICTION AND ITS RELATION TO


SOIL/PIPE SURFACE FRICTION

4.7 THE NEED FOR LABORATORY TESTING AND CORRELATION


WITH PIPE JACKING SCALE MODEL TESTING

103
Chapter 4 Material Characterization

4 MATERIAL CHARACTERIZATION

4.1 INTRODUCTION

Characterization of the soil material was carried out in order to both detennine its
structural properties and to observe the behaviour of the soil particles during testing.

The ultimate aim was to correlate the results obtained from laboratory tests on the soil
with those obtained from the model test.

To enable the complete characterization of the materials used for this project, several

different methods of soil characterisation, including triaxial, direct shear, density and

particle size distribution testing, were used. Special tests were also carried out in

which the soil was sheared against concrete and steel in a typical shear box test
apparatus.

Two kinds of sand were used during the course of the research work, Leighton

Buzzard sand and River (concrete) sand. The sands were chosen for their distinctly
of
different engineering behaviour, because"their ease to use in laboratory testing, and

most importantly, their frictional characteristics are known to cause problems in


practice. The two main mechanisms controlling behaviour of the sand particles during

deformation are volume change (dilation or contraction), which is dependent on sand

density, and the relative motion between the particles. The sliding of the sand particles

over each other can occur at all levels, and the amount of the stress required for its

initiation is related to the normal initial stress and void ratio. These mechanisms are

generally inter-dependent, according to the deformation process which is acting in


different parts of the sand.

104
Chapter 4 Material Characterization

4.2 GEOLOGY

4.2.1 Leighton Buzzard Sand

Leighton Buzzard sand is a material quarried near Leigh ton Buzzard in Bedfordshire .
Its petrological name is Quartz sand, and its geological classification is Lower
Greensand . It is a yellow, single sized, clean sand with angular particles and has a
smooth, occasionally rough or honeycombed surface texture. Its constituents are
mainly Quartz (around 81 %), Quartzite (14%), and opaque (4%). The geological and

chemical details are given in Appendix I .

4.2.2 River (Concrete) Sand

This sand is quarried from Croxden in Derbyshire . It is classified as a Quartzite

material and was retrieved from a deposit of the Bunter Pebble Beds. The particles are
rounded with a crystalline surface texture. It consists mainly of Silica (97%), Iron and
Alumina (2.1%), and about 0.7% of Calcium .See Appendix I for geological and
chemical details.

4.3 MATERIAL PROPERTIES AND LABORATORY TESTING

The Leighton Buzzard sand was chosen for its single sized particles, in which the pore
passages had an average diameter of the same order of magnitude as the smaller
particle diameters and no effective combination of particles to form an aggregate was
possible. The mechanism of the movement of each particle is strongly influenced by

105
Chapter 4 Material Characterization

the position of the adjacent particles due to the soirs uniform nature. The shape and the

size of the particles contribute to the strength of the sand, the relative movement of the

particles, and hence the pattern of distortion of the sand grains as a whole.

River sand is a mixture of different sized particles. A weJI- graded sand is usually

stronger than a single-sized sand, although the magnitude of its strength is dependent

on several factors concerning the aggregation of particles within the sand structure.

For example the mechanical properties of such sand depends on the relative density

and the manner of packing of the sand particles.

AIl of the material characterisation tests were carried out according to British Standard

1377 (BSI 1975), whenever applicable, and are described in the foIlowing sections.

4.3.1 Particle Size Distribution

The particle size distribution test for soil is an important and fundamental classification

test . The sand particle sizes were determined by the method of dry sieving from

representative samples of the materials. The British Standard sieves were positioned

in increasing order of size with the largest sieve at the top, taking care to produce an

appropriate distribution of the sieve sizes for each material. A dry material of known

total mass was added to the top of the stack of sieves, which were securely clamped

and mechanically vibrated for the specified period of time (10 minutes) . The mass of

the material retained on each sieve was measured, the percentage passing each sieve

was calculated, and the particle size distribution curves were plotted on a logarithmic

scale. These tests were conducted to confirm the particle size distributions provided

from the sand suppliers.

106
Chapter 4 Material Characterization

The results of the sieve analyses of both sands are shown in Figure 4.1 .

4.3.2 Density Tests

The detennination of soil density is simple, its value being dependent on the void ratio
of the soil. There are two soil states of interest herein: uncompacted (Loose) and
compacted (Dense) states.

Leighton buzzard sand was used in a dry condition only. A series of tests was
conducted to measure the densities in both compacted and uncompacted states, as
shown in Table 4.1 .

Table 4.1 Results of Bulk Density Tests for Leighton Buzzard Sand
Compacted (Dense) Uncompacted (Loose)

Method Density (kg/m1 Method Density (kg/m3 )

#Rod Tamping 1543


#Vlbratlon 1708
'Funnel 1540
Vibrating Hammer 1691
B.S 1377(1975) '2000mml Cyllder 1520
Test 14
~ Drop Hammer 1530
B.S 1377(1975)
Test 12
#Applylng Dead Load 1556

Note:
, Described In Laboratory Testing In 5011 Engineering by Alcroyd (1964) .
# Methods used similar to model scale test conditions.

For the River sand, the bulk density was dependent on the water content of the soil \

and the state of compaction . A standard drop hammer method, according to B.S

1377(1975): Test 12, was used to obtain the optimum dry density. The results of the

107
Chapter 4 Material Characterization

tests are shown in Figure 4.2. A water content of 6% was used throughout the
research, which under conditions of standard compaction would yield a dry density

approaching the maximum of 'Yd at a water content of approximately 6.5% :=

1754kglm3 •

4.3.3 Specific Gravity

The specific gravity (Gs) of the soil is the ratio of the weight of a given soil particle to
the weight of the same volume of water. Specific gravity is used in the
determination of various soil parameters and is primarily dependent on the mineral
constituents of the soil. The determination of specific gravity for Leighton Buzzard
and River sands was based on BS1377 (1975) using the Gas-Jar method. The
specific gravity of three specimens of each type of sand was measured and recorded as
shown in Table 4.2, together with the average values.

Table 4.2 Specific Gravity of the sands


SOIL TYPE SPECIMEN AVERAGE
1 2 3
Lelghton Buzzard 2.676 2.673 2.675 2.67
River Sand 2.637 2.646 2.642 2.64

108
Chapter 4 Material Characterization

4.4 SHEAR RESISTANCE

Attempting to slide sand particles over each other causes friction between the grains,

and shear failure occurs by overcoming the frictional resistance generated by the

attempted motion. Interlocking of the grains can contribute considerably to the

strength of the material, especially in densely packed granular soil. The volume

change of the mass of soil particles and the relative motion between them constitute the
two basic mechanisms that control the deformation of granular soil . These

mechanisms are usually interdependent. At small stresses, crushing and fracturing of


soil particles is unlikely, but they become increasingly important when high stresses
are reached. For example, fracturing becomes important only when the stress level
exceeds 3.5MPa (Bell, 1983) .

The internal angle of friction of granular soil is caused by the friction generated during

the sliding, rolling and rotating of the soil particles against each other . A typical

stress-strain graph for sand is shown in Figure 4.3 for both dense and loose material.
The dense sand has a high peak stress (or strength) and is accompanied by volume

increase. Loose sand has a shear strength similar to the large strain strength of the

dense sand and it usually compacts under the shearing stress. To investigate the shear
resistance of the material used for this research work, three kinds of shearing tests

were carried out and these are described below.

4.4.1 Direct Shear Test

The shear box test is the oldest form of shear test and is considered to be the simplest

method of determining the internal angle of friction of a soil. The shear box simply

109
Chapter 4 Material Characterization

allows a soil sample to be compressed in a 100mm square split brass box under a

given vertical stress. The sample is then sheared when the two halves of the box slide
each
against'other by means of an electric motor. The vertical stress applied to the top of the

sample is obtained from dead weights placed at a predetermined lever arm on a

hanger. The driving motor slides the bottom part of the sample box at a constant

chosen speed, determined using a gear box. The shearing resistance of the soil is then

measured by means of a proving ring attached to the top part of the sample box. The

shear test data were recorded by a computer readout system, via LVDTs placed across

the proving ring and mounted on the frame to record the travel of the box .

Consistent procedures for preparation and testing of sampleswere used. The samples

were chosen randomly from a batch sample. The samples were placed and tamped in

two layers inside the shear box for both types of sands. Two rates of shearing were

used, fast (1.2mm/s) and slow (0.00192mm/s) . For dry Leighton Buzzard sand, the

weight of the soil in the shear box was measured and the density were computed to +
kN/m3
or - 0.5 Aof the compacted value. The same procedure was used for the wetRiversand,

but the water content was additionally measured to facilate the calculations. A series

of tests was conducted on similar soil samples . Both the moisture content and the
kNfm 3
density were kept within + or - 0.5 of optimum values. It must be stressed that the

method of placing and compacting the samples was intended to be similar to the model

testing. However, the density results of the samples show at least a 95% compaction

for the maximum density of the materials (Table 4.3) . The reason for adopting two

rates for shearing is to establish their effects on the results which then can be related to

the model testing. Different values of normal stresses were applied to the shearing
plane, as shown in Table 4.3 .
Due to equipment problems, only the lower range of normal stresses could be tested
and allowance for curvature at low normal stresses should be made when
interpreting the results.

110
Chapter 4 Material Characterization

Table 4.3 Testing Programme for the Direct Shear Tests


Type of SoU Nonnal Stress Rate of Shearing Moisture Density (Mg/m3)
(kPa) Content (%)

Lelghton Buzzard 10 Fast/Slow 0 1.68/1.64


Lelghton Buzzard 30 Fast/Slow 0 1.65/1.65
Lelghton Buzzard 50 Fast/Slow 0 1.64/1.67
River Sand 10 Fast/Slow 6.0/6.4 1.70/1.70
River Sand 30 Fast/Slow 6.2/6.9 1.72/1.73
River Sand 50 Fast/Slow 6.5/6.7 1.73/1.70

The magnitude of the shear force was recorded as a function of the shear

displacement. The results were then used to obtain the relationship between normal

stress and shear displacement by plotting data for various tests.

4.4.2 The Triaxial Test

Both drained and undrained triaxialcompression tests were conducted to characterise

both types of sand. Triaxial test procedures have been comprehensively described by

Bishop and Henkel (1962). A sample of 38mm diameter, 76mm in length was

prepared by placing the sand with appropriate water content in a rubber membrane
kN/m3 ,
inside a split former. The density of the sample was maintained within + or - OSof

the compacted sand density by tamping in thin layers of soil inside the former using a

thin plastic rod. The water contents for both samples were the same as those used in

the model testing.


A back pressure of 100 kPa was used for all tests and then released when the cell
pressure of 400 kPa or 700 kPa were applied to the samples.

III
Chapter 4 Material Characterization

Both drained and undrained triaxial compression tests were conducted. Standard

un drained tests were performed, in which the minor principal stress (()' 3) is

maintained at a constant value while the major principal stress ( ()'1) was increased until

sample failure occurred. The pore pressure was measured during testing in order to

obtain Mohr's circles from different cell pressure and enable a failure envelope in

terms of effective stress to be calculated. For the drained tests the sample was first

consolidated under a pressure of 300 kPa and then subjected to an increasing axial

stress at constant rate of 0.1524 mm/min until failure occurred. The pore pressure in

this case proved to be negligible. A summary of the testing programme is shown in

Table 4.4.

Table 4.4 Testing Programme for the Triaxial Compression Tests


Type of Soil Type of Test Cell Rate of Density BValue
Pressure Shearing
(kPa) (mm/Mln) (Mg/ffil)
Lelghton Buzzard Drained 400 0.1524 1.59 0.94

Lelghton Buzzard Drained 700 0.1524 1.61 0.94

LeJghton Buzzard Undralned 400 0.1524 1.58 0.99

Lelghton Buzzard Undralned 700 0.1524 1.59 0.99

River Sand Drained 400 0.1524 1.68 0.94

River Sand Drained 700 0.1524 1.67 0.97

River Sand Undralned 400 0.1524 1.68 0.97

River Sand Undralned 700 0.1524 1.68 0.96

4.4.3 Special Shear Test

Following both the direct shear and triaxial testing, it was apparent that a special shear

test was required to determine the relationship between the soil and the pipeline

112
Chapter 4 Material Characterization

surface . The primary purpose of this test was to obtain the appropriate frictional

coefficients.

An adapted shear box test was used in which concrete and steel blocks were made to
fit exactly in the bottom half of the shear box, Figure 4.4 . The soil was placed in the

top half of the box under the same conditions, and the test procedure was carried out,

as described above for the direct shear test. The applied normal stresses were in the

range of 0 to 50 kPa; in which the results could be compared to those used for mode!.
* Table 4.5 illustrates the testing programme. It is noticeable that no slow rate
testing.

of shear was conducted on the soil/steel for Leighton Buzzard sand as the other results

showed little significant changes in the results.

Table 4.5 Testing Programme for Special Shear Tests


Type of Soll Normal Rate of Moisture Density Interface Shear
Stress Shearing Content
(kPa) (%) (Mg/m3 )
Lelghton Buzzard 10 Fast/Slow 0 1.66/1.62 Soll/Concrete
Lelghton Buzzard 30 Fast/Slow 0 1.63/1.66 Soll/Concrete
Lelghton Buzzard 50 Fast/Slow 0 1.67/1.61 Soll/Concrete
Lelghton Buzzard 10 Fast 0 1.60 Soll/Steel
Lelghton Buzzard 30 Fast 0 1.63 Soll/Steel
Lelghton buzzard 50 Fast 0 1.63 Soll/Steel
River Sand 10 Fast/Slow 7.0/6.8 1.68/1.70 Soil/Concrete
River Sand 30 Fast/Slow 6.1/6.4 1.77/1.75 Soil/Concrete
River Sand 50 Fast/Slow 6.0/6.2 1.75/1.75 Soil/Concrete
River Sand 10 Fast/Slow 6.6/6.8 1.73/1.75 Soil/Steel
River Sand 30 Fast/Slow 6.2/6.5 1.76/1.74 Soil/Steel
River Sand 50 Fast/Slow 6.8/6.7 1.73/1.76 Soll/Steel
.

* It is believed that, even under higher surcharge loads, arching within the soil will
results in normal stresses on the pipes that approximate to this range.

113
Chapter 4 Material CharacterizatfDn

4.5 TEST RESULTS

4.5.1 Soil Parameters and Comparison of Shear Resistance

Three stress-displacement curves for the shear box tests carried out on Leighton

Buzzard sand are shown in Figure 4.5 . The results show that at early stages of the
tests, when the relative displacement of the two halves of the box is less than 5 mm,

the peak shear stress value, or strength, of the sand was achieved. After this point the

shearing force decreased until a displacement of 15 mm was achieved, after which the

tests were terminated. The results for River sand show similar behaviour to those for

the dry Leighton Buzzard sand, as iIIustrated in Figure 4.6, although with a markedly

less reduction in shear stress once failure has occurred and lower strengths recorded.

The mean parameters obtained from all tests are tabulated in Table 4.6 .

Table 4.6 Mean Direct Shear Results

Type of Soil Moisture Densl~ <l>s (0)


Content (%) (Mg/m ) [yeaJ<_ Ultimate

Lelghton Buzzard 0 1.66 49 37


River Sand 6.5 1.73 42 42

The results of the drained triaxial compression tests for 400 and 700 kPa ceII pressures

are iIIustrated in Figures 4.7 and 4.8 respectively for the Leighton Buzzard sand, and

Figures 4.9 and 4.10 for the River Sand. The peak stresses for both types of sands

were obtained at strains of less than 10%. The results of the undrained triaxial

compression tests similarly showed that the peak stresses occurred at a strain of

approximately 10% for both 400 and 700 kPa cell pressures, as shown in Figures

114
Chapter 4 Material Characterization

4.11 and 4.12 for Leighton Buzzard sand and Figures 4.13 and 4.14 for River sand.

The results of drained and undrained triaxial tests for Leighton Buzzard sand and

River sand are summarised in Tables 4.7a and b .

Table 4.7a Drained Triaxial Compression Test Results

'IJpe of Sol! a3 (kPa) a 1 (kPa) a 1 - a3


(kPa) G> 'P
2 ( 0 ) ( 0 )

Lelghton Buzzard 400 1389 494.5 39 13

Lelghton Buzzard 700 2260 780.0 39 10

River Sand 400 1140 370.0 29 6


River Sand 700 1755 527.5 29 7

Table 4.7b Undralned Trlaxlal Compression Test Results

'IJpe of Soil i<r3 (kPa) a 1 (kPa) a 1 - a 3 au oAr <l>u


(kPa) (kPa) ( 0 )
2
Lelghton Buzzard 400 525 62.5 400 -0.787 17
Lelghton Buzzard 700 1004 152.0 400 -0.415 17
River Sand 400 521 60.5 380 -0.737 19
River Sand 700 946 123.0 385 -0.411 19

Note l.t.u is the change in pore water pressure (kPa), and A is Skempton's pore

pressure parameter at failure. ;


I*AJ values are believed to be low due to experimental error ..
The load displacement curves for the special shear tests are shown in Figure 4.15 for

concrete/soil and Figure 4.16 for steel/soil, and the parameters obtained are

summarised in Table 4.8 . The results indicate that the values of the internal angle of

friction for these tests are less than those for soil/soil, as expected, and that the results

for the steel interface are only marginally lower than those for the concrete interface.

The results of the Leighton Buzzard sand with both concrete and steel surfaces are

115
~------------------------------------------------------------------------

Chapter 4 Materia! Characterization

very close to the critical state value, as they are for theRiver sand (see Table 4.7a) .'

Table 4.8 Special Shear Test Results


Type of Soil
<!>'s/c <!> ~/st

Lelghton buzzard 38 37
River Sand 28 27

It is noted that the internal angle of friction for Leighton Buzzard sand is greater than

that for River sand, due to its unifonn, large, angular grains. These types of panicles

will create larger interlocking forces during shearing, especially when dense. The

ultimate angle of friction for a particular soil is unique, regardless of its initial density

(Bolton, 1979), and this can be observed from the triaxial test results. The effects

of shearing rates show little significant differences between the peak resistances .

Many studies have examined the results of both direct shear and ttiaxial tests on sand.

It shows that the ignored intermediate principal stresses in direct shear tests can

contribute significantly to the behaviour of soils tested under plane strain conditions.

The results obtained from triaxial tests can be considered more reliable than those of

the direct shear test, due to the horizontal plane in the shear box not equating to the
plane of maximum shear stress (Cole, 1967) .

The critical state results from both direct and triaxiaI shear tests are shown in Table

4.9 for both types of sand and the parameters obtained are summarised in Table 4.9 .

Atkinson and Bransby (1978) stated that the most convincing experimental

demonstration of the existence of the critical state line for sands is provided by the data

116
Chapter 4 Material CharacteriZation

from the (plane strain) direct shear apparatus. The results from the,: shear tests
for the Leighton Buzzard sand show that the material was in a denser state than the

critical value. This material dilated during the shearing process which caused an

increase in the effective stresses and hence the internal angle of shear :, as did the !"

River sand but to a lesser degree since its angle of dilation is smaller (see Table
4.7a) .

Table 4.9 The Critical State Results


Direct
, Shear Triaxial
, Shear
Type of Soil
<l>c M <l>c M
(0) (0)

Leighton Buzzard 37 1.50 39 1.59


River sand 42 1.72 29 1.16

NB <Pc =42° for River sand is believed to be in error.


4.5.2 Dilation, Contraction and Critical State of the Sand

The main parameters that influence the effective internal angle of friction (<1>') for

sand are effective normal stress, pore water (and in some cases also pore air) pressure,
density, particle angularity and particle size distribution. It is significant for the

theoretical modelling of the experiments to establish the variation of <1>' with stress and
density for the material tested, as shown in Figure 4.18 .

The critical state concept is briefly explained herein due to its complexity and is

primarily used to verify the observed behaviour of the sand particles when sheared at

different densities. The concept of dilatancy, contraction and the critical state of sand

is interrelated with the initial density of the material. At the critical state, the sand

117
Chapter 4 Material Characterization

particles when sheared will flow in a constant movement (i.e at constant volume) .

Where the shear stress (q') to mean normal effective stress (p') ratio is equal to the

angle of friction of the soil material on the shearing plane, the soil is said to be at its

critical state, defined by a straight line relationship in q', p' space. Figure 4.19
shows the critical state line for a typical sand in q' , p' , v (specific volume) space, in

which the constant M is defined as the gradient of the line in q , p' space.

If the soil is denser than the critical state, then the particles need to push apart as the

soil is sheared. This phenomenn~is called dilation and can readily be visualised in the
shear box test by vertical displacement of the top cap upwards while the horizontal

plane of shear is created by the opposite movement of the two parts of the shear box.

This analogy can be used to explain the behaviour of the sand particles surrounding a
pipeline during jacking. Although the external surface of the pipeline is circular, it

defines the shear plane between the pipe and the surrounding soil. As the pipeline is

pushed forward the soil particles tend to move away from each other to permit shear

movement in dense material. It should be noted that sand is almost always dense, in
relation to the critical state, and dilation will almost certainly be necessary .

The laboratory test results show that the sand density was above the critical density

and that the sand dilated during shearing,as demonstrated in Figure 4.20 . Dilation
sand·
was obvious for Leighton Buzzard'during shearing in the shear box test when the top

cap was pushed upwards during the course of the test . The results of continuous
shearing of the sand in forward and reversal directions are shown in Figure 4.21,

which shows a steady state (or critical state) shear stress below that achieved during

the first traverse for all normal effective stresses. Considering the behaviour of the

sand during the jacking process, a similar philosophy of dilation can be discerned, in

118
Chapter 4 Material Characterization

which forward movement of the pipe creates a disturbance zone around the pipeline

and consequently causes soil movement. Soil movement around a pipeline is a subject

on its own will not be examined in more detail here, although confinement will restrict

the ability of the soil to move away from the pipeline and this will result in high

jacking resistance through the difficulty of sand dilation.

Analysis presented by Hughes et al (1977) on the expansion of a cylindrical cavity in

sand, assumed that in the strain region around the cavity, the sand may be considered

as elastic-perfectly plastic in its stress/strain response and to have a constant angle of

dilation (1jI) associated with the plastic deformation, as shown in Figure 4.22 . The

relationship between volumetric and shear strain is thus:

v=c-ysin1jl

where v =volumetric strain, c =constant, and y =shear strain


The angles of dilation (1jI) for drained triaxial tests are summarised in Table 4.7 and

may be useful in determining the behaviour of the sand particles around the jacked

pipeline.

Contraction is the opposite process to dilation, where the sand particles tend to become

more compact than in their original state. The density of the soil sample in this case is

lower than the critical density of the soil and the effective stress paths lie below the

critical state line in q' p' space, (Figure 4.19) . For the jacking process, this is mostly

likely to occur when. a loose sand is created just behind the excavation shield. The

loose sand particles, caused by local collapsing into the gap around the shield, will be

caused to contract during the pipeline forward movement, although high insitu stresses

could force the density of this sand to rapidly increase above the critical.

119
Chapter 4 Material Characterization

4.6 THE CONCEPT OF SOIL/SOIL FRICTION AND ITS RELATION


TO SOIL/PIPE SURFACE FRICTION

The principle of pipeline surface/soil contact is similar to that of soil/soil contact in a

sense of friction between two bodies. In all types of soil, friction is generated when

the particles are sheared, or moved across, each other. The magnitude of frictional

resistance is dependent on various factors such as particle shape and size, density,

void ratio and normal effective stresses. For many soils ranges of frictional resistance

have been established for experimentally and practically determined angles of friction.

In pipe jacking, values of soil/surface friction were established based on data obtained
from pipe jacking contracts. Herzog (1987) reported tables for these values from

various different case studies, as shown in Table 4.1 O.

Table 4.10 Coefficient of Pipe/Soil Friction, (after Scherle, 1977)


Surface Contact Type of Friction Coefficlent of Frictlon ( fL)

Concrete/Soli Static 0.5 to 0.6


Concrete/Soil Sliding 0.3 to 0.4
Steel/Soil Static 0.3 to 0.4
Steel/Soil Sliding 0.2 to 0.3

It is important to acknowledge that the soil/pipe surface results from laboratory testing

could differ from those obtained from model testing due to differences in surface

profile and joint profile . In laboratory testing it was proposed that steel/soil and
concrete/soil shear would be adequate to give an indication on the type of friction

which could be generated, but that interpretation of model testing results would have to

be carried out with due caution.

120
Chapter 4 Materta[ Characterization

An important factor in determining the frictional response is the vertical overburden

pressure and, more importantly, the variation in effective normal stress around the

pipe. An investigation into this subject would be necessary in order to define the

relationship between the results, and this could be done by examining the relationship

between model and shear test results and to backcalculate the mean normal effective

stresses that appear to be acting on the pipe. This will be further discussed in
Chapter 7 .

4.7 THE NEED FOR LABORATORY TESTING AND CORRELATION


WITH PIPE JACKING SCALE MODEL TESTING

Some assessment of soil behaviour must be obtained from a combination field and

laboratory testing prior to conducting a pipe jacking operation with respect to its

strength for face excavation, the resistance to penetration and friction generated from

jacking and the magnitude of soil stresses behind the jacking wall . The most important
laboratory tests needed for pipe jacking are listed in Table 4.11 .

Table 4.11 The Essential Laboratory Tests For Pipe Jacking


Test Type of Soil Reason For Testing

Grading Sand Particle Size Distribution Curve.


Water Content Sand Water Content
Permeability Sand kValue
Triaxial Test Sand Internal Angle of Friction
and Cohesion [Drained And
Undralnedl, and dilation angle
Direct Shear Test Sand Internal Angle of Friction and
Cohesion as above, and
soil/ structure parameters
I

'" NB "cohesion" in sands refers to cementation or porewater suction effects in tests


that are not fully drained.
121
Chapter 4 Material Characterization

However, laboratory tests have not been used to predict the forces that may be

encountered from the friction generated between the pipe surface and the surrounding
soil . It is therefore essential in this particular piece of research to determine the

relationship between the laboratory test results and the magnitude of forces obtained

from pipe jacking to facilitate development of predictive methods. Other laboratory


results, such as soil strength, are required to establish the stability number, which can

be used for calculating the resistance of the soil against collapse around the pipeline, or
deformation of the face of the excavation, for clays.

122
B.S TEST SIEVES
C') ID 0 o o 00
CD
o
C'I 0 o ID 00
.;0 CD o ~ oC') 0 .;0 0
c:i
I I I I
c:iI 0
I I
C'I C')
I
to cD r-4
I
r-4
I
~
I I I
100 100
I'i1
;11
90 90

80 /' Cl
80
W1I
't1
./
River sand 70
~
70

60
,. L
60
0
t'l
Z
~
50 I Lei hton Buzzard Sand 50 Cl
t'l
I

-~
I L
40 40
I
30 :1 30
Z
t'l
tj

20 I 20
/
10 J 10
V
o ./ o
O. 001 0.01 " 0.1 .0 10 10o
PARrICLE SIZE (mm)
0.002 0.06 2 60

Fine I MedIum I Coarse FIne I MedIum I Coarse Fine I MedIum I Coarse

I Silt Sand Gravel J


Particle Size Dist ribution
Figure 4.1 Particle Size Distribution of Leighton Buzzard and River Sand
1.85 ,--_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _---,

~
1.80
C1;!
l
~
1.75

-.,'"
.eo

~
;:
1.70
e:-
A

1.65

2 3 4 5 6 7 8 9 10

Moisture Content (%)

Figure 4.2 Optimum MOisture Content for River Sand


Dense

Displacement (mm)

Figure 4.3 Typical Shear Test Curves For Sand

Force

Figure 4.4 Special Shear Test Apparatus


80

60
.,.........
40
. '-
• .~
X
_A
30kPa

20
.X

~ lOkPa
. . ·'~+".I.i·H'''!J.~

o
o 5 10 15 20
Displacement (mm)

100

El Peak Values

80 • Ultimate Values

'2

-."'
~
"'
60

....Cl)"
.... 40

"
.et
Cl)

20

o 20 40 60 80 100

Normal Stress (kpa)

Figure 4.5 Results of Direct Shear for Leighton Buzzard Sand


80 .-----------------------------------1

60
'2

-..,..,.,
~
40
..... 40kPa
(Jl

..,1;1 7_73 III


.=
(Jl
20

o 5

Displacement (mm)

80

Peak Values=U1tlmate Values

60

40

20

o
o 20 40 60 80

Normal Stress (kPa)

Flgure 4.6 Results of Direct Shear Test for River Sand


* Best fit line through the origin was chosen for ideal situation, or alternatively best
fit line through the points with an intercept can be plotted .
2000 r-----------r=============:;]
~= 400 kPa

1500

-~
co
1000
III

.
III

...."
en
500

a 5 10 15 20 25 30

Strain (%)

0.01 r----------------------,

0.00

~
...
......
e -0.01
~co
.=
u
-0.02
"
~
~
-0.03

-0.04 L---"_....1.._..L-_.1.---"_-'-_-'-_.1.--'~_'__~_..J

o 5 10 15 20 25 30

Strain (%)

Figure 4.7 Results of Drained Triaxlal Test for Lelghton Buzzard Sand
3000
C!3= 700 kPa
2500 I-

(i
2000 I-
-
-~'"'" 1500 I-

...".
rJJ
1000 I-

500

0 I I 1, I L I
0 5 10 15 20 25 30

Strain (%)

0.01 .--_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _--,

0.00

~...
G
"
'OIl
-0.01
.==
os
u
§"
~ -0.02

-0.03 1---'_-'-_...J....._-'----'_--'-_-'--_-'----'_-'-_...J.....--'
o 5 10 15 20 25 30

Strain (%)

Figure 4.8 Results of Drained Triaxial Test for Leighton Buzzard Sand
1200 ~= 400 kPa

900

~ 600

'"....'o."
.
Cl)

300

o
o 5 10 15 20 25 30

Strain (%)

0.02 r-----------------------,

0.00
~
.....
...
e-o.
'cl)
I:: -0.02
os
.<:
()

]"
-0.04
~

-0.06 L-..----'-_-L_--'-_L__----'-_ _1._~_L___'_ _1._~______I

o 5 10 15 20 25 30
Strain (%)

Figure 4.9 Results of Drained Trlaxlal Test for River Sand


2000

~= 700 kPa

1500

Ci
~ 1000
en
..
en
Cl
....
Ul

500

o 5 10 15 20 25 30

Strain (%l

0.01

0.00
~...
G
:n
=
os
.<:
-0.01
(.)
Cl

-
§
~
-0.02

-0.03
o 5 10 15 20 25 30

Strain (%l

Figure 4.10 Results of Drained Triaxlal Test for River Sand


600
~= 400 kPa
500

400
'2
~
300
'"
...'"."
CIl
200

100

0
0 5 10 15 20 25 30

Strain(Ofo)

0.2

-0.0

-0.2

A -004

-0.6

-0.8

-1.0
0 5 10 15 20 25 30

Strain(%)

Figure 4.11 Results of Undrained Triaxial Test for Leighton Buzzard Sand
--------------------------- ----------

1200
~= 700 kPa
1000 r-

800 r- ""'-
<;'
~
~

. 600 t-
~
....
rn
400

200

0 1 1 I 1 _I
0 5 10 15 20 25 30

Strain(%)

0.4 ,...-_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _- - ,

0.2 !-

0.0
"\
A

-0.2 f-

-0.4 r-

-0.6 L----I._-'i'----'-_....Li_-'.'-_.l-
1---1._-,1,--_,-_-,-
1-,,---,
o 5 10 15 20 25 30

Straln(%)

Figure 4.12 Results of Undrained 1'riaxial Test for Leighton Buzzard Sand
600

0"3= 400 kPa


500

400

'2
~
~
300

''""
....~
(/J 200

100

0
0 5 10 15 20 25 30

Straln(%)

0.2 , -_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _--,

-0.0 11--------------------

-0.2

A -0.4 _

-0.6 _

-0.8 _

'_''---<-_-'-
,_..1.L..-_..l."---_-'-
-1.0 L---I..'---'- ,---'_-','----'-----'
o 5 10 15 20 25 30
Straln(%)

Figure 4.13 Results of Undralned Trla'CiaI Test for River Sand


1000 r-----------r========il
~= 700 kPa

800

Ci 600

-.,"''"
~

.
....
rJ)
400

200

o 5 10 15 20 25 30

Straln(%)

2.0 . -_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _---,

t-
1.5 t-

1.0

"\
A

0.0 ~

-0.5 r- ----------_

-1.0 L----'-_.l.-
,---'_..J.'_-'-'-_ _iL----'-_..l-'-----'-_.l.-
'---'_..J
o 5 10 15 20 25 30

Straln(%)

Figure 4.14 Results of Undralned Trlaxlai Test for River Sand


80 r---------------------------------------,

60

-....~
.,r .. =__ _ r
40
L 40kPa

• Lb

20
lOkPa
~.i.ii+!ii.i.i.i.!.I.iJ.I.i.I.j.I.I.j.!.i3.I.!.!+iJ.i.i1.i,j.jQ:rrry:rCl:1

o
o 5 10 15 20
Displacement (mm)

Leighton Buzzard

80

13 Peak Values

60
• Ult!mate Values

~
OS
~
~

.,.,
.....
~
UJ
40

OS
"
.<::
UJ
20

o L-__~____L __ _~_ _ _ _L __ _~_ _ _ _L __ _~_ _~

o 20 40 60 80

Normal Stress (kPa)


Lelghton Buzzard

Figure 4.15 Results of Shear Test for Concrete/Soil Interface


80~------------------ __________________--.

60

~
:::!

.....
III
III
40

..=..
m
os 50kPa
m
20 "mmc =I~IOII~I:Q~Q~O kPa
• lOkPa
~tf.if3~!JJ3·t?zdj.IJJ.IJJ.i.it.Elna:S

o 5 10 15 20
Displacement (mm)

River Sand

80 r-------------------------------____--,
Peak Values=U1timate Values

60

40

20

o L---~ ____L-__- L_ _ ~L- __- L_ _ _ _L__ _~_ _~

o 20 40 60 80
Normal Stress (kPa)

River Sand

Figure 4.15 Continued. Results of Shear Test for Concrete/Soil Interface


80 r---------------------------------------,

50kPa
?EJI'In "_E' ""-AP
- 30kPa

10 kPa
~:tI::lJlI.IJmtJj'ij..::m::!
.... :m:::..'llI:J:'~~dkJ

10 15 20

Displacement (mm)

100

80

~
IV
D-
0. 60
If>

'"
!!
iii
~
IV 40
"
.c
Cl)

20

o
o 20 40 60 80 100

Normal Stress (kPa)


River sand

Figure 4.16 Results of Shear Test for Steel/Soil Interface


------ - ----- -----

80r-----------------------------~----__,

60

<i

-~
on
.
{/)

...."
40 40 kPa

~ke'
UJ
...
to
.="
UJ
20
~ 10 kPa
1+' '+14 +t;lj.I.,.j.jJ '1-[3

o~~~----~--~----~--~~--~----~--~
o 5 10 15 20

Displacement (mm)
Leighton Buzzard sand

80 ~--------------------------------------__;

60
<i

-.
Po.
."i
{ /)
{/)
40
...."
.
UJ
to
.="
UJ
20

o L-__ ~ ____L __ _ ~ _ _ _ _L __ _ ~ _ _ _ _L __ _ ~ __ ~

o 20 40 60 80
Normal Stress (kPa)
Leighton Buzzard sand

Figure 4.16 Continued. Results of Shear Test for Steel/Soil Interface


60~ __________________________________ ~~~

50

40

30

20

10 IJLelghton Buzzard
• RiverSand
, oL-~L-~L-~L-~C=~C=~
I o 10 20 30 40 50 60

Normal Stress (kPa)

Figure 4.18 Shear Stress against N01mal Stress for Vartous


Densities of the Sands Tested In Direct Shear Test

q
(kPa)

Crttlcal State Line

.' .'.' p' (kPa)


l·~·i·

Projection on v : p'

Figure 4.19 Position of Critical State Line


Dense Sand
Dilation
Zone

-::::::====== Critical State

Contraction
Zone

Loose Sand

Displacement
a- Dilation And Contraction for Dense and Loose Sand

q'

ESP= Effective Stress Path

Dilation
Zone

ESPs for
dense sand

Contraction ESPs for


Zone loose sand

p'

b- Dilation And Contraction Zones In Critical State Space

Figure 4.20 The Principle Of Dilation and Contraction for Sand


BOr-------------------------------------,

60

• •••• • •••
40

X X X X X X X X X X- x ,,~I
.
...
• . . . . . 50kPa

X~

~~x'(~kPa
20
G El El Cl G G G GClG lOkPa
I:!J~
,.[!1.,.i·'·ZZt;;!

o 2 3 4 5

Strain (%)

a Leighton Buzzard Sand

80

60

-'"
Il.
.><
~

III
50kPa
III 40
I!
1ii
.,'"
~

.<:
CIl

o 2 3 4 5
Strain (%)
b River Sand

Figure 4.21 Results of the Reversal Shear Test


'y---------- <1>'

Shear Strain

a- Constant mobilised angle of friction In plastic phase

shear strain
C ••
....

b- Asoclated Ideal!sed volumetric response.


Constant mobilised angle of dHation, 'If •
In plastic phase

Figure 4.22 Idealised Elastlc - Perfectly Plastic Response


of Sand (after Hughes et al 1977) .
Chapter 5 Experimental Study oJ Pipe Jacking

CHAPTER FIVE

5 EXPERIMENTAL STUDY OF PIPE JACKING

5.1 INTRODUCTION

5.2 EQUIPMENT
5.2.1 THE1ESTBOX
5.2.2 THE 1ESTRIG
5.2.3 APPLICATION OF OVERBURDEN PRESSURE
5.2.4 THE MODEL PIPES
5.2.5 THE JACKING ARRANGEMENT
5.2.6 THE EXCAVATION 1ECHNIQUE

5.3 INSTRUMENTATION
5.3.1 MEASUREMENT OF JACKING FORCES
5.3.2 MEASUREMENT OF PIPE DISPLACEMENT
5.3.3 MEASUREMENT OF OVERBURDEN PRESSURE
5.3.4 DATA LOGGING ARRANGEMENT
5.3.4.1 SIGNAL CONDITIONING MODULE
5.3.4.2 A-D CONVERTER
5.3.4.3 MICRO-COMPU1ER
5.3.4.4 DISPLACEMENT TRANSDUCER
5.3.4.5 LOAD CELL
5.3.5 INSTRUMENTATION ACCURACY AND TOLERANCES

5.4 EXPERIMENTAL PROCEDURE


5.4.1 EXPERIMENTAL PREPARATION
5.4.2 EXPERIMENTAL INSTALLATION PROCEDURE
5.4.3 METHOD OF EXCAVATION
5.4.4 MEASUREMENT OF OVERCUT RATIO
5.4.5 MEASUREMENT OF JACKING FORCES AND PIPE DISPLACEMENT
5.4.6 COMPLETION OF THE TEST

5.5 PROGRAMME OF EXPERIMENTAL WORK

123
ChapterS Experimental Study of Pipe Jacking

5 EXPERIMENTAL STUDY OF PIPE JACKING

5.1 INTRODUCTION

After deciding on the use of a scale model as the main research tool, the entire testing
rig had to be manufactured at Loughborough University. Due to the necessarily
large size of the testing equipment, considerable effort and time had to be spent on
building the apparatus. Once previous experimental work on this subject had been
reviewed, careful design of the testing rig and the instrumentation was essential in
order that experimental work could be carried out efficiently. It was mentioned in
Chapter 3 that a large scale model has relatively small experimental boundary effects

during testing and careful consideration in the design of the testing equipment was

taken to minimise the effect of the boundary conditions and to keep these effects
consistent throughout the test programme. In addition a full test programme is
required and thus the cost and time required to conduct each experiment should be
kept to the minimum.

Preliminary tests were required in order to define an appropriate experimental


methodology, to test the equipment and instrumentation, and to ensure that the test
programme could be carried out without any difficulties. The test programme was
reviewed and updated frequently during testing to ensure efficiency.

124
ChapterS Experimental Study of Pipe Jacking

5.2 EQUIPMENT

The scale model testing rig was designed to simulate the entire pipe jacking operation

in practice. Figure 5.1 shows the general arrangement of the rig . It consists of a

large test box, a frame for the support of the jacking equipment, model pipes, a
rubber membrane pressure bag and a data logging system.

5.2.1 THE TEST BOX

The idea behind building a large test box is to enable the creation of a medium

through which the jacked pipe line is to penetrate . The test box was designed to

contain the soil. In addition, the box supports a loading arrangement in order that a

vertical effective stress can be applied to the soil, further details of which are

discussed in a later section.

The test box used in the course of this research has internal dimensions of 1.8m long

X 1.5m wide X 1.5m deep. The test box is made of steel and was designed to

withstand a pressure of up to 250 kPa on top of the soil sample inside the box. The
box is fixed to laboratory's floor to prevent any movement during testing.

The principle of using the test box is that it would provide rigid boundaries and

impose a condition of plane strain deformation on the front and rear faces, while the

sides and the bottom walls are sufficiently far from the pipeline to produce no
significant influence on the deformations of the soil around the pipeline. In addition,

it is important to reduce the shear stresses between the soil sample and the box walls,
therefore smooth steel sheets are used for this purpose.

125
ChapterS Experimental Study of Pipe Jacking

The detailed design of the test box is represented in Figure 5.2 . It consists of I.5m

x 1.5m front and rear panels, 1.8m x 1.5m panels for the sides and a 1.8m x 1.5m

panel for the bottom face; Steel sheets of 6mm thickness were used to build the

panels and these were strengthened by 120 x 60 x 10mm steel box sections, welded

together to form a rigid frame for the box. The bottom face was strengthened by

two small steel sections from the inside. The test box was fixed to the floor of the

laboratory inside the test rig .

The front and rear faces of the test box have 500mm square openings in order to

allow the pipeline to penetrate through the box. To provide a circular entrance and

exit for the pipeline, two steel plates were positioned inside the square openings .

These plates contained holes framed by two rings of rubber and steel to provide the '

required size for the pipeline opening by adjusting their circumferences.

It was clearly important, in determining accurately the jacking forces, to account for

the friction generated between the surface of the pipeline and the surrounding rubber

seals during penetration through the two openings. Similarly it is essential to contain

the soil sample inside the test box and thus allow no gaps around the pipeline for the
sand to escape through . Two types of rubber seals were used, one for each

opening. Soft rubber was used for the front because it is capable of folding slightly

inwards in the direction of the movement of the pipeline. For the rear opening the

situation is a little more complex because the pipeline in this case is leaving the test

box. It therefore carries the sand particles along its surface, due to adherence, and

tries to push the rubber outwards at the same time, which consequently causes a gap

for the soil to escape. To overcome this problem without creating high frictional
forces, a black hard thick rubber was used as a seal in this case. These solutions

126
ChapterS Experimental Study ofPipe Jacking

were chosen following a trial and error approach using different rubber of different

thicknesses and stiffnesses .

At the rear opening an adjustable plate, capable of moving horizontally and

vertically, was used. The purpose of this was to facilitate adjustment of the position

of the opening for the pipeline as it leaves the box in order that no resistance would

be caused from misalignment of the pipeline.

5.2.2 The Test Rig

A frame was used to contain the testing equipment and this is shown in Figure 5.3.

It is simply a steel frame made out of 100 x 100 x lOmm steel box section

surrounding the test box and creating the jacking facility. It is fmnly fixed to the

floor by means of heavy duty screws and is also used to clamp the test box on the

floor to prevent any uplift movement during the application of vertical loading .

The jacking equipment was mounted on the frame horizontally. The test box is

situated at one end of the rig and the jacking arrangement is placed on the other side.

An adjustable guide rail for carrying the pipes was used to maintain the required level

and direction of the pipelines as they enter the test box. This guide rail is also fixed

to the main frame at the front opening of the test box.

5.2.3 Application of The Overburden Pressure

As mentioned earlier, a vertical uniform stress was required to simulate the surcharge

of the overlying soil imposed on the pipeline. There were few options available

127
ChapterS Expertmental Study ofPIpe Jacking

including the use of a static dead load arrangement applied to the top of the sand

sample or by using water or air pressure. It was decided to use water pressure for

both practicality and safety, and therefore a rubber membrane was placed underneath

the lid and secured by clamping joints around its edges, as shown in Figure 5.4 .

The choice of the rubber material was made such that it would be able to take the

water pressure and expand without letting the water escape through the joints. The

rubber used for this device was a soft white rubber of 6 mm thickness and capable of

stretching to eight times its original length .

The water was delivered from the mains through an opening valve, then through a

water pressure regulator and then into the gap between the inner surface of the lid

and the rubber membrane (water bag) . The water pressure was controlled by

adjusting the water pressure regulator until the required normal stress was achieved.

The magnitude of the water pressure was monitored by the water pressure gauge, as

discussed in detail later . The reason for using this loading system was to impose an

artificial soil overburden pressure and thereby to simulate different depths of the

pipeline during jacking. The use of 200 kPa as a maximum overburden pressure

was modelled on the basis of an overburden of 12 m of soil, assuming a bulk

density of 16.5 kN/m3 for sand, or alternatively lOm of soil at a bulk density of20.0

kN/m3.

5.2.4 The Model Pipes

With the aid of appropriate modelling, the surface structure of the pipeline can be
accurately simulated .

128
Chapter 5 Experimental Study oJ PIpe Jacking

It has been mentioned in Chapter 3 that two types of pipe surfaces were used for this

research work, concrete and steel surfaces. It is important to acknowledge that the

strength of the pipes and the joints are not important for this research work and only
the surface texture was taken into consideration during the research. Therefore,

model pipes were required regardless of their loading strength and other pipe jacking

specifications, but with durable surfaces, i.e those able to withstand the friction

generated from the soil sample without damage. Details of the pipes are given in

Figure 5.5.

5.2.4.1 Concrete Pipes

These pipes are of 200mm external diameter and consist of steel pipes covered with
micro-concrete. A Smm thick steel pipe section of 167mm external diameter was cut

into 240mm long sections. Steel pipes were used to avoid the manufacture of

reinforced concrete pipes. They also can withstand, and transfer the jacking loads

during the jacking process and thereby reduce the stress on the concrete walls of the

pipes to an acceptable level . Another advantage of using the steel pipes as a

permanent central former was to ensure no misalignment in the joints of the pipeline,

tight-fitting joints being created between the pipes to achieve this. The steel pipes

were milled around both ends in a manner that allows one end of the pipe to be fixed

onto the opposite end of a second pipe by causing the joint's ends to be groved by
half the thickness of the pipe.

Each section represents the length, when scaled, of the prototype pipe . Before

casting the concrete around it, steel reinforcement sections were welded around the

steel pipes to act as a frictional key between steel and concrete and thus to prevent the

129
ChapterS Experimental Study of PIpe Jacking

concrete surface from slipping along the steel surface during jacking. The concrete

surface thus simulates the surface of prototype concrete pipes in contact with the

surrounding soil in practice.

5.2.4.2 Steel Pipes

The steel pipes were manufactured using the same principle, but without coating

with concrete. Steel pipe, 194.7mm in external diameter by 5 mm thick, was cut

into 240 mm long sections. These sections were milled to have the same joints as

those described above for the concrete pipes. It is necessary to note that the size of

steel pipes was chosen as a result of the availability of steel pipes in the market. It
would have been preferable to use the same diameter pipe as for concrete pipes for

easier comparison of the results, but this proved impossible. (The concrete pipes

were manufactured fIrst.)

5.2.5 The Jacking Arrangement

The jacking equipment provides the necessary jacking capacity to push the pipeline

through the test box . An hydraulic 50 tonne jack with a stroke of 120mm was used

as the main jack and was placed in a position that gave a perfect alignment for the
pipeline as it enters the test box. It was supported by a 100 x 100 x 10 mm steel
frame placed at a distance of 500mm from the front face of the test box and spanning

across the main testing frame. The jack was secured in position by means of a

large adjustable screw, in order to allow the jacking frame to be fmnly positioned
before jacking commences. A thick steel plate was welded on the jacking frame with

different sets of screw holes to allow the main jack to be positioned at different

130
ChapterS Experimental Study ofPipe Jacktng

levels if required.

Hydraulic pressure was used to supply the main jack with oil during the jacking

operation. After completion of each loading cycle, the main jack had to be retracted

mechanically. Two small hydraulic jacks, each of 1 tonne capacity, were used to

pull the main jack back to its original position. These were positioned on each side
of the main jack and were connected to the steel plate, as shown in Figure 5.6 . After

retracting the main jack, the small jacks were released back to their normal position

and retracted themselves to allow the main jack to perform.

5.2.6 The Excavation Technique

Excavation in practice is carried out at the face of the tunnel, often in front of the

driving shield. In pipe jacking, excavation at the front of the pipeline has an

important influence on the behaviour of other jacking parameters.

Excavation equipment for the experimental work had to be carefully designed to meet

the objectives of the project. A cage was used as a working access for excavation

and was situated between the load cell and the pipes. The cage was supported by a

steel rod through a hole in the load cell. The steel rod was welded to a circular steel

plate of 240mm diameter and connected to a circular ram by four 24mm diameter,

300mm long steel rods. The steel ram was cut to allow the pipes to be fitted in with

no movement, as shown in Figure 5.7.

At the front of the pipeline, ahead of the leading pipe, a steel shield with sharp
edges, a smooth outside surface and angled inner face of 300 was used (Figure

131
ChapterS Experimental Study ofPIpe Jacking

5.8) . Two methods of excavation were adopted for this work, one for the dry sand
and the other for the wet sand . A suction technique was used to excavate and
remove the sand from the face of the tunnel just in front of the shield for the dry
sand. For the wet sand, an auger was rotated and pushed at the same time to cut the
soil, and subsequently dragged backwards to remove the sand through opening

flaps. Further details are given in section 5.4.3 .

5.3 INSTRUMENTATION

5.3.1 Measurement of Jacking Forces

Jacking force is the most important performance parameter and its accurate
measurement was essential. The generation of the jacking forces during testing
should solely represent the real resistance between the surface of the pipeline and the

surrounding material (and in addition face resistance where relevant) . Friction due to

the contact between the pipeline and other materials should be either kept to a
minimum and calibrated out, or eliminated completely. As explained earlier, the use
of the rubber seals for the holes in the test box was studied carefully and any extra
forces generated from their resistance were later deducted from the measured jacking

forces. Misalignment was kept to a minimum by adopting the jointing techniques as


described earlier. Face resistance, or shield resistance, was modelled as accurately as
possible.

A data logging device was used to monitor the magnitude of the jacking forces. The

load cell mounted between the cage and the main jack measured the forces as an

132
ChapterS Experimental Study oJ Pipe Jacking

analogue signal, which was passed to the A-D converter through a signal

conditioning module. The A-D converter converted the analogue signals into digital

signals, which were passed to the BBC micro-computer for data recording .

Software was written to handle the data thus obtained. Data were recorded every 2 to

3 seconds throughout the jacking process to enable a continuous record of the forces
to be obtained and printed through a line printer.

5.3.2 Measurement of Pipe Displacement

The magnitude of the jacking forces encountered during construction is usually

related to the jacking steps (Haslem, 1983 and 1986 ) or to the total length of the

jacked pipeline (Stein at aI, 1986) .

The pipe displacement in this research work was measured by Linearly Variable

Differential Transformers (LVDTs) fixed onto the supporting frame. As the jacks
moved forward the transducer arm extended and the distance signal was passed

through a conditioning box to the A-D converter. The signal was converted from an

analogue to a digital form and passed to the BBC microcomputer, which recorded

and printed the data.

5.3.3 Measurement of Overburden Pressure

Overburden pressure above the pipeline is of interest in determininig the response of

the jacking forces to different loading conditions. Little research effort, if any, has

been devoted to this parameter and most of the methods of estimating the jacking
forces ignore this parameter, although it was considered important herein. The

133
ChapterS Experimental Study of Pipe Jacking

simulation of the overburden pressure was achieved by a rubber membrane bag

placed above the soil. A water regulated pressure from the main of up to 15 bar was

used to pressurize water within the rubber bag to obtain the required nonnal stress,

which was measured by a Budenberg water pressure gauge situated on the lid of the

box. The gauge is graduated from 0 to 10 bar and each bar is sub-graduated in

increments of 0.05 of a bar . The pressure was monitored and controlled by a water

pressure regulator. In each test, the required pressure was applied and kept at that

level throughout the whole test.

5.3.4 Data Logging Arrangement

The data were monitored via a signal conditioning module, a voltmeter, an A-D

converter and a BBC micro-computer. These devices are interconnected in the

arrangement shown in Figure 5.9 .

5.3.4.1 Signal Conditioning Module

This is used to operate all of the tranducers . It consists of three channels, one being

used for load and the others to measure the pipe displacement. The input voltages to

each transducer can be individually adjusted and measured. The output voltage from
the transducers can be monitored directly from each channel.

5.3.4.2 A-D Converter

An eight channel PCI 6380 analogue-to-digital converter made by C.I.L. was used
as a part of the instrumentation package. It received the analogue signals from the

134
ChapterS Experimental Study oJ Pipe Jacking

load cell and the transducer, and then translated them into a digital form compatible

with the computer. It required an input voltage for each channel depending on the

output range for the measuring devices. Then each channel can be transmitted to the

computer in a digital form with + or - 15 Bits resolution, which allowed

transmission of 32767 units for every 10 volts as a digital signal to the computer.

5.3.4.3 Micro-Computer

A BBC Master, 128k micro-computer was used to monitor the jacking load at

regular time intervals together with the pipeline displacement. It was interfaced with

a 50 T load cell and the displacement transducer through an A-D converter. The

measured data were recorded on a floppy disc for storage and printed on a line

printer for data presentation.

Software was developed to record the data with a list of options. These options
include the time interval at which the data are taken, pausing the recording, and

readjustment of the intervals and to allow additional data to be taken.

5.3.4.4 Displacement Transducer

The jacking displacement was measured using a linear variable differential

transfonner (LVD1) • To measure the jacking displacement, it was decided to measure

the relative displacement between the excavation cage and the jacking frame. The

core of the L VDT was attached to the jacking frame in a stationary position and the

body was attached to the moving cage. The LVDT had a linear range of 155mm and
was adjusted to give an output of 4650mV per millimetre deflection.

135
Chapter 5 Experimental Study of Pipe Jacking

5.3.4.5 Load Cell

The jacking forces were measured using a load cell . The load cell was an

M.C.B./M.R.E. 50 Tonne cell and measured the load directly from the jack. It

provides an electrical signal proportional to the applied load. The load cell had a

range of 500kgf and a sensitivity of lOmVIN .

5.3.5 Instrumentation Accuracy and Tolerances

Having decided what instruments to use for this research work, it is essential to

judge the value of the data obtained. It is also important to acknowledge the accuracy

and resolution of the load cell and transducer used for monitoring the jacking forces

and displacement. The instruments were regularly calibrated and checked during the
course of the research work.

5.4 EXPERIMENTAL PROCEDURE

It is important to adopt a well defined experimental procedure in order to provide

consistent experimental data throughout the entire test programme. This precaution,

together with isolation of the factors that influence the installation procedure and the

determination of the boundary conditions which may effect the performance


parameters, should result in reliable experimental data. Pipe jacking construction

practice was simulated wherever possible, and the installation of the equipment and

instrumentation were conducted in a manner such that no disruption of the soil or


construction practice could occur.

136
Chapter 5 Experimental Study of Pipe Jacking

The experimental procedures described hereafter were tested and examined in


preliminary experiments and, therefore, were well defined and remained unaltered

throughout the research work. The characterization of the soil used in the work is

discussed in Chapter 4.

5.4.1 Experimental Preparation

In order to ensure that the installations were fully ,representative of site practice and
achieved the required objectives of the research work, the model was prepared and

built as described earlier in sections 5.2 &5.3 .

The pipe jacking model testing rig is shown in Fig 5.1, and the jacking equipments
, \' ere placed at one side of the box. Model steel and concrete pipes were used to
form the pipeline. The scale ratio of the tunnel diameter (B) to the width of the box

is 1:7.5 .

A uniform surcharge pressure is exerted by means of a water rubber membrane bag


on top of the soil. The whole apparatus was supported and fixed to the ground by

a steel frame.

5.4.2 Experimental Installation Procedure

The pipe installation method has the greatest potential influence on the results. It

was evident that an approximately uniform distribution of the soil material in the test
box was necessary in order to assess realistic soil behaviour and achieve consistent
results during anyone test.

137
ChapterS Experimental Study ofPipe Jacking

The test box was filled with the appropriate sand to the required density and moisture
content, and then an appropriate nonnal stress was applied to its surface. Two basic
procedures were adopted: Type I where the whole pipeline is placed in position

before filling the box, and Type H where the box is filled completely with sand and
the pipeline is jacked into the soil via the entrance opening. Both types of tests have
similar boundary conditions during testing.

Leighton buzzard sand passing the 2mm sieve and retained on the I mm sieve was
used as a unifonnly graded sand. The behaviour of the sand will be similar to
granular soil occurring naturally above the ground water table with maximum

frictional resistance. The dry sand had a high void ratio and air penneability due to
the uniformity of its large particles. Pore water pressure and drainage in this case
will not arise at the rates of stress applied and therefore the total and effective
stresses within the soil will always be equal.

The sand was placed by pluviation from a hopper, falling through a constant height
of approximately 60mm into the testing box as the hopper moved across the test
box. For Type I tests, the pipeline was positioned in place inside the box, and
through the openings on a bed of sand. The sand was then poured around the
pipeline and compacted locally (particularly under the pipe haunches) to achieve a
uniform density before filling the remainder of the box . For tests of Type H, the
sand was poured straight from the hopper until the whole box was filled. The top
plate with the rubber membrane bag was placed on top of the sand and an initial
nonnal conditioning pressure of 200kPa was applied before testing to maintain a
consistent compacted state within the same boundary conditions for all types of test.
Once the initial stressing was complete, the stress was released and the surcharge

138
ChapterS Experimental Study DJ PIpe Jacking

pressure raised to the required level for testing. On completion of each test, the
was checked and
density of the sand"for all tests was found to be within 16.0 + or - 0.5 kN/m2 .

The well-graded River sand had a moisture content of approximately 6% . Due to the

high permeability of the sand, pore pressures would be dissipated relatively quickly

and, at the rates of stress applied, the sand can be considered to be in the fully

drained equilibrium state.

For tests of Type I, sand was compacted in layers below the pipe, carefully

compacted around the pipeline, and compacted as before above the pipeline . For

tests of Type n, the sand was compacted in layers throughout the whole depth of the

test box. The sand for both types of tests was placed in layers of 150mm thickness

and compacted by a drop hammer of weight of 8.87kg falling through a height of

300mm three times. This method of sample preparation produced a uniform density

of 16.5 + or - 0.5 kN/m2 and a moisture content of 6.0 + or - 1 % . The density and

moisture content were measured at the end of each test to ensure uniformity between

tests.

After filling the box, the same procedure as that described for the uniform sand

thereafter was adopted with the exception that for this sand the test was carried out

on the second day after preparation to ensure that the water content (and any pore

water pressure generated) had reached steady state conditions before testing.

139
ChapterS Experimental Study of Pipe Jacking

5.4.3 Method Of Excavation

Two methods of excavation were used depending on the type of the sand. Leighton

Buzzard sand excavation was carried out by means of a suction operation. The dry
sand was sucked behind the cutter shield until it reached its natural angle of repose.
Great care was taken to ensure that the sand was extracted without causing any
disturbance to the soil in front of the shield. The pipeline was jacked in by 80 to
90mm prior to the removal of sand, the procedure being repeated throughout the test,

and a constant stress was applied to the pipeline to help ensure no overexcavation .
The face resistance was minimised by using a sharp cutter shield with an inside
angled surface of 300 , an angle that approximately simulates the angle of internal
friction of the cohesionless soil. It should be noted that some face resistance will
have occurred as a result of arching in the sand in front of the shield, but that this
could not, and should not, have been affected.

For the well-graded River sand excavation was carried out by the rotation of an
auger on the central axis of the cutter shield. The excavation distance was fixed at

80mm in front of the shield. The soil was extracted by the reverse rotational action
of the auger and the pipeline was then jacked forward by a corresponding distance

of 80mm . Collapse of the sand did not occur prior to advancement of the shield at
anyone cross-section during this operation, which was carried out as swiftly as
possible. The same shield cutters were used as for the Leighton Buzzard sand.

140
ChapterS Experimental Study of Pipe Jacking

5.4.4 Measurement of Overcut Ratio

The overcut ratio is defined as the ratio of the amount of over· excavated radius,

bounded by the shield, to the radius of the pipe. It determines the amount by which
the soil can collapse onto the pipe once the shield has passed, and thereby also set up
arching mechanisms within the soil above the pipe. The over-excavated area around
the pipeline was achieved by using a larger diameter cutter shield than the pipe
diameter. Steel cutter shields of various diameters were used to obtain different
overcut ratios, as shown in Table 5.1 .

Table 5.1 Overcut Ratios used in the Experimental Work *


Shield Pipe Type of Overcut
diameter diameter pipe ratio
(mm) (mm) (R)

196 196 steel 0


200 196 steel 0.016
206 196 steel 0.048
213 200 steel 0.084
200 200 concrete 0
206 200 concrete 0.030
213 200 concrete 0.064
228 200. concrete 0.140

[ If r is the external radius of excavation and b is the external diameter of the pipe,
the overcut ratio (R) is calculated by the difference between rand b divided by b . 1

5.4.5 Measurement of Jacking Forces and Pipe Displacement

Preliminary tests were carried out to monitor the jacking forces in order to find out

how accurately the forces could be measured, this procedure being repeated a
number of times. It was found that the readings were consistent and represented the

magnitude of the forces generated fro~ the jacking resistance within the tolerances
* Overcut ratio of zero for the steel pipes was achieved by cutting down the cutter
diameter of overcut ratio of 0.140 . It was used at the latter stages of testing.
141
Chapter 5 Experimental Study of Pipe Jacking

described earlier. Initially the pipeline was jacked through the test box without the

surrounding soil and the forces were recorded. These forces represented the

resistance of the seals around the opening and friction from the portion of the pipe

resting on the guide rail. Seal tests were repeated and a constant friction was

achieved. The forces were subtracted from the forces obtained from the jacking tests

of the pipeline in the soil .

The total jacking distance of the pipeline was obtained by adding together the jacking

increments after completion of each test. Pipe displacement measurements thus

represent the jacking steps in which the pipeline is jacked forward.

5.4.6 Completion of the Test

On completion of each test, a number of steps were taken to ensure that all test
procedures were conducted, and results were recorded, in a manner that reduced the

potential for experimental errors and allowed the programme of experimental work
to be undertaken according to plan.

The test results were monitored by the micro-computer during the experimental work

and recorded on a print out by scanning at regular intervals. This allowed a good

definition of force generation throughout the test and enabled rogue results, for

example by power surges, to be isolated. When the jacking process was completed

for each step, the computer programme was paused, and monitoring stopped, until

the experimental work was restarted again.

142
ChapterS Experimental Study of Pipe Jacking

When the testing was completed, the first operation was to ensure that the applied

overburden pressure above the soil was released and the water drained out of the

pressure bag. Then the box lid was removed and various checking operations were

performed. The soil material was dug out if required depending on the type of the

test series. The vertical and horizontal misalignment of the pipeline was measured at

the end of the box to determine their effects on jacking forces and, where relevant,

ensure that they were kept to minimum. The moisture content for the River sand

was measured from samples taken from positions near to the top of the box and

adjacent to the pipeline.

The pipe surfaces were checked for damage such as surface cracks or any surface

roughness incurred from friction around the pipeline during the jacking process.

The pipes were then cleaned and replaced if necessary, and set aside for the next

test.

5.5 PROGRAMME OF EXPERIMENTAL WORK

The main aim of the experimental programme was to simulate current site practice

using a scale model and to gain knowledge of the various parameters that mayor

may not have any effect on the behaviour and magnitude of the jacking forces. A

series of preliminary tests was performed using the scale model in order to develop

a standard method of operation, to which other tests should be conducted

accordingly. The preliminary tests also provided a basic understanding of the

behaviour of the jacking forces in relation to various parameters. Additional

preliminary tests were conducted to investigate the loading pattern and the behaviour

143
ChapterS Experimental Study of Pipe JackfIlg

of the water bag, and in particular the magnitude of the maximum overburden

pressure which might be applied safely.

After completion of the preliminary testing, and assurance of the accuracy and

consistency of equipment and instrumentation, a programme of tests was devised.

Details of these tests and installations are given in Table 5.2 .

The research work was divided into two main series of tests, the fJI'st (1) where the

pipeline was placed in position inside the test box and through the openings, and the

second (H) where site practice was modelled as the pipeline was jacked inside the

box while excavation was carried out at the lace. The tests were carried out in

Leighton Buzzard sand and River sand with an overburden pressure of up to 200

kPa.

The first test series(Type I) was conducted to establish the influence of varying

overburden pressure on the magnitude of the jacking forces by determining the

friction between the pipeline and the surrounding soil. Various cover depth (D) to

pipe diameter (R) ratios were thus adopted. The results of the second series of tests

(Type mshows the relationship between the magnitude of the jacking forces and the
overcut ratio, length of jacking and the type of the pipeline surface.

144
........................-------------------------------
Table 5.2 Details Of Experlmental Installations

Test No. Test Reference Test Series DjB q (kPa) 1yPe Of Pipes 1yPe Of SoIl R Type Of Joint

1 la I 3.75 0-200 concrete L 0 ID


2 Ib I 1-3.5 0 concrete L 0 ID
3 2a 11 3.75 10 concrete L 0 ID
4 2al 11 3.75 150 concrete L 0 ID
5 2a11 11 3.75 100 concrete L 0 ID
6 2alll 11 3.75 150 concrete L 0 ID
7 2alv 11 3.75 200 concrete L 0 ID
8 2b 11 3.75 10 concrete L 0.030 ID

9 2bl 11 3.75 100 concrete L 0.030 ID


10 2b11 11 3.75 200 concrete L 0.030 ID
11 2c 11 3.75 10 concrete L 0.064 ID
12 2cl 11 3.75 100 concrete L 0.064 ID
13 2c11 11 3.75 200 concrete L 0.064 ID
14 2c11l 11 3.75 10 concrete L 0.140 ID
15 2clv 11 3.75 100 concrete L 0.140 ID
16 2cv 11 3.75 200 concrete L 0.140 ID
17 3a I 3.75 0-200 sleel L 0 SM
18 3b I 3.75 0 steel L 0 SM
19 4a 11 3.75 10 steel L 0.016 SM
20 4al 11 3.75 100 steel L 0.016 SM
.........................---------------------------------
Table 5.2 (Continued) Details Of Experimental Installations

Test No. Test Reference Test Series DIB q (kPa) 1ype of Pipes Type Of Soil R Type Of Joint

21 4all II 3.75 200 steel L 0.016 SM

22 4b 11 3.75 10 steel L 0.045 SM

23 4bi 11 3.75 100 steel L 0.048 SM

24 4bU 11 3.75 200 steel L 0.048 SM


25 4e 11 3.75 10 steel L 0.084 SM
26 4cl 11 3.75 100 steel L 0.084 SM
27 4eH 11 3.75 200 steel L 0 ID
28 Sa I 3.75 0-200 concrete RS 0 ID
29 5b I 1-3.75 0 concrete RS 0 ID
30 fa 11 3.75 10 concrete RS 0 ID
31 6aI 11 3.75 100 concrete RS 0 ID
32 6al! 11 3.75 200 concrete RS 0.030 ID
33 6b 11 3.75 10 concrete RS 0.030 ID
34 6bl 11 3.75 100 concrete RS 0.030 ID
35 6bU 11 3.75 200 concrete RS 0.064 ID
36 6c 11 3.75 10 concrete RS 0.064 ID
37 6el 11 3.75 100 concrete RS 0.064 ID
38 6ell 11 3.75 200 concrete RS 0 ID
39 7a I 3.75 0-200 steel RS 0 SM

40 7b I 3.75 0 sleel RS 0.016 SM


Table 5.2 (Continued) Details Of Experimental Installations

Test No. Test Reference Test SerIes DIB q (kPa) TyPe Of PIpes Type Of Soil R Type Of JoInt

41 &l 11 3.75 10 steel IS 0.016 SM


42 Ba! II 3.75 lOO steel IS 0.016 SM
43 Sall II 3.75 200 steel IS 0.016 SM
44 Bb 11 3.75 10 steel IS 0.048 SM
45 Sb! 11 3.75 100 steel IS 0.048 SM
46 8bH II 3.75 200 steel IS 0.04S SM
47 8c 11 3.75 10 steel IS 0.OB4 SM
48 Bc! I 3.75 100 sleel IS 0.084 SM
49 Scll I 1·3.75 200 sleel IS 0.084 SM
50 8d 11 3.75 10 steel IS 0 SM
51 8d! 3.75 lOO steel IS 0 SM
52 8dU " 3.75 200 steel IS 0 SM
53 lli
"
I 3.75 0-200 concrete IS 0 SM
54 9b 11 3.75 200 concrete IS 0 SM
55 lOa I 3.75 0-200 concrete RS 0 SM
56 lOb 11 3.75 200 concrete RS 0 SM

KEY:

RO=Rough
SM = Smooth
L = Le!ghton Buzzard Sand
RS =River Sand
R = Overcut
Wfl(fFR INLET

WATER

..
~
A

...
~

A
A
...

A A
A

".
#>
A

#>
A
A
A

A
#>

A
A
A
A
A
A A A A A
A A A A
A A
A"
A A
" .. ..
'" A....
.. ..
..
.. "","

EXIT

JA'CKlING SPACERS

STEEL BOX

PIPE SUPPORT

DATA LOGGING PANEL


- A TO D CONVERTOR
- COMPIJI'ER RECORDING
Figure 5.1 Cross-sectional View of Pipe Jacking Apparatus
Rear Elevation Side Elevation Front Elevation

Figure 5.2 Test Box Detalls


Jack
'--MoIM
Frame Cell
~f ~,,,'

L-Exca,vat:lon Cage
Pipe Guide

Figure 5.3 The Testing RIg

Water Regulater

Water Outlet ...~I-__ Water Inlet

L_:Rulbb<" Membrane Rubber Membrane Mounting

Figure 5.4 Pressure Bag Details


168mm
16mm -'-1 f.l1.t-~=':::""--I~~1 !+ 16mm
. ·· ···
·· ··
··· ··
··
~Co ncrete Cover
···
240 mm Steel Pipe
··
··· ·· V Steel Bar Reinforcement
·· ··
·
~ ~~,~---------------------- ·
Concrete SuIface Pipe

194mm

240mm

Ir

Steel SuIface Pipe

Typical Pipe Joint Detail

Figure 5.5 Model Pipes Details


Auger ~otatlng Bar
Jack Mo~n1:lng
Excavation Cage

Connection

Pipes

Figure 5.6 Loading Arrangement

Fitting groove for the pipes


24mm

\\\~\\
E!,il======:s~• ~• ~
~ II:.zzzzz:zzzz:z:zzz:z:zzz:~ i ~
I· ·1
300mm 290mm

Figure 5.7 Excavation Cage Details


--------------------------------------------------------------- -

Leading Pipe Steel Cutter

I..·.·' ·. ·.'·. ,.....


·. ·'.·, .·.··.·•. •. •.•. •.'.'. .'.•. '.• .• .'.•. . •'.....::);::;f~f::::~;
,. ,.'.".,." .• ".•.}}:;::;:i:::':':;:;.
. . ,""',.::.:., . •,. . •. . •. .'. .'. '. . ..

Figure 5.8 Cutter Details


........................-------------------------------
I

Signal
Voltmeter Condltlonlng -
Module

A-D Convertor
BBC Computer
~ ________________ ~r--

Signal
Conditioning -
Module

Printer
\.'--------

L.V.D.T
( Load Cell )

- Figure 5.9 Data Logging Arrangement


Chapter 6 Results ofExperimental Work

CHAPTER SIX

6 RESULTS OF EXPERIMENTAL WORK

6.1 INTRODUCTION

6.2 PRELIMINARY TEST RESULTS

6.3 MAIN TEST RESULTS

6.4 JACKING FORCES BEHAVIOUR


6.4.1 OVERBURDEN PRESSURE
6.4.2 OVERCUTRATIO
6.4.3 THE TYPE OF SOIL
6.4.4 PIPE SURFACE
6.4.5 JACKING DISTANCE
6.4.6 PIPE JOINTS

6.S CONCLUDING REMARKS

145
Chapter 6 Results ofExperimental Work

6 RESULTS OF EXPERIMENTAL WORK

6.1 INTRODUCTION

It has been established earlier that the magnitude of the jacking forces generated
during pipe jacking operations is the critical factor in detennining the required pipe

strength, the size and capacity of the thrust wall, the requiredjacking equipment and

the total length of the jacked pipeline. The results of the research work presented in

this chapter have the objectives of illustrating both the behavioural trends and the

absolute magnitude of the jacking forces arising from variation in the influencing

factors. Parameters have been introduced to explain the behaviour of these results

where appropriate. Consistency in measurement of test results was assessed by

repeating certain tests, while the majority of the tests concerned varying one or more

parameters. The results of the soil material testing, one of the variable parameters,

were fully discussed in Chapter 4 .

It is important to acknowledge the difficulty in putting all the results into perspective

due to the intercombination of the variable parameters that had to be investigated

during the course of this work. It was considered, therefore, that the results should

be explained in a simple, understandable manner to avoid confusion. Simplification

was achieved by looking at the effect of each parameter on the jacking forces as the
kept constant.
other factors were ;- in order to isolate their influence.

The preliminary tests were conducted with the aim of setting a standard testing

procedure for the main testing programme. The jacking forces, as described earlier,

are the forces needed to advance the pipeline and these are presented for the main test

146
Chapter 6 Results ofExperimental Work

programme in detail hereafter. The interpretation of these results, and their


comparison with other findings, are fully discussed in Chapter 7 .

6.2 PRELIMINARY TEST RESULTS

Several preliminary tests were carried out in order to establish a clear indication of
how the jacking forces will vary during the main test programme and to develop
standard test procedures. Each test was repeated at least twice, and typically four
times, under the same experimental conditions so that consistency of results could

be assessed and repeatable results achieved.

The preliminary tests, in which the pipeline was placed in position inside the test box
and surrounded by soil under vertical stresses of between 10 kPa and 200 kPa,
produced interesting trends. The jacking forces obtained from these tests are plotted
in Figure 6.1, in which it can be seen that a clear relationship exists. A straight line
could be drawn to describe the points, though has been omitted for clarity. The
intercepting point of the straight line with the jacking forces axis (starting
resistance), which is equal to 17 kN is caused by the normal stresses alone due to
the height of the surrounding soil above the pipeline* . At the same time a
force/displacement relationship for each jacking operation was established as
illustrated in Figure 6.2 . This is typical of the general trend of how the jacking

forces vary with displacement, regardless of overburden pressure which simply


affects the magnitude of the resistance. For a short displacement of up to 2Omm, the
jacking force increases steadily until it reaches a peak, after which it to levels off and
then decreases to a residual value. This relationship is similar to the force

* in addition to the resistance provided by the rubber seals as the pipe e;tered and
left the box.

147
Chapter 6 Results ofexperimental Work

displacement curve for a direct shear test in the shear test box, as would be
expected. The results of the force/pressure relationship are also similar to the

relationships from direct shear tests . This similarity will be further discussed in
Chapter 7 . From the results of the preliminary tests, it was decided that a series of
relationships should be established based on this analysis.

6.3 MAIN TEST RESULTS

The main test programme was structured according to the results of the preliminary
tests. The boundary conditions imposed by the test box, while remaining constant
between tests, were potentially influential on the results and likely to exaggerate any
differences in soil properties, such as water content and density. By keeping the

differences in soil properties to a minimum through good experimental techniques


and by measuring the properties of soil used in each test, boundary condition
influence was minimized. In addition, by choosing the boundary conditions to
match those in the field and maintaining constancy during testing, good quality test
data, and particularly comparative data, were obtained .

The stress applied to the surface of the soil to simulate overburden pressure was
chosen to cover likely practical load cases, the maximum stress of 200 kPa
simulating typically 10m of overburden . However interpretation of results should
be based on experience of stresses under actual site conditions. The comparisons of

behaviour between practical loading and the experimental loading, applied to the
surface of the soil as a uniform water pressure, are important in this respect.

148
Chapter 6 Results ofExper!mental Work

6.4 JACKING FORCES BEHAVIOUR

Jacking forces were found to be dependent upon several factors and varied

considerably between tests. The magnitude of the jacking forces was mainly

influenced by overburden pressure, overcut ratio, type of soil, pipe surface, pipe

joints and the jacking distance. A full explanation of the effect of these parameters is

discussed in the following sections.

6.4.1 Overburden Pressure

Overburden pressure was expected to be a dominant influence on the jacking forces

in sand. In practice, pipelines of 900mrn or more in diameter are typically jacked at

depths of at least 2m below the ground level and, therefore, it was important to

simulate the stress levels acting at such depths. Results were obtained for two series

of tests, one in which the overburden was applied naturally, as only the height of the

soil above the crown of the pipeline, and the other by applying a uniform normal

stress to a layer of soil above the the pipeline.

The results of the first series of tests (Type I), which was to investigate the effect of

the soil height above the crown of the pipeline, are shown for both types of soil and

pipe surfaces in Figure 6.3 . The jacking forces increased steadily as the pipeline

was moved forwards until maximum forces were reached at a displacement of

10-20mrn, after which the forces remained approximately constant or rose slightly.

This relationship can be compared with the force/displacement shear test results for a

loose material (Figure 4.5 and 4.15) . The results of these tests are summarised in
Table 6.1.

149
Chapter 6 Results ofExperimental Work

Table 6.1 Influence of Soil Cover on Jacking Forces


Type of Soil Pipe Surface Soil Cover Jacking Forces (kN)
(ml D!splacement: approx.
20mm 80mm
Le!ghton Buzzard Concrete 0.6 22.0 23.5
Le!ghton Buzzard Concrete 0.3 11.5 12.0
Le!ghton Buzzard Steel 0.5 1.25 1.25
Lelghton Buzzard Steel 0.3 0.73 0.85

River Sand Concrete 0.5 8.00 8.10


River Sand Concrete 0.2 3.90 3.80
River Sand Steel 0.55 8.00 7.50
River Sand Steel 0.25 3.20 3.20

The relationship between the jacking forces and the height of the soil cover indicates

a consistent pattern in which the jacking forces increase linearly with cover depth,

starting from a minimum height of O.lm, as shown in Figure 6.4 . As the depth (D)

increases to approximately 0.5m, the jacking forces tend in one case to reduce

slightly and the gradient of the line decreases, although the fall lies within the

experimental variation, or scatter, recorded in the data and in general the linear

pattern is conformed to well. Higher jacking forces were recorded for the Leighton

Buzzard sand with concrete pipes, indicating higher skin resistance (together with

any joint resistance) between the concrete and the uniformly sized sand particles _

of kN/mlhe River sand generated a lower skin resistance of 20kN/m between the

concrete pipes and the well graded sized sand particles. Similar hehaviour was also

produced between the steel pipes and both Leighton Buzzard and River sands with
skin resistance of 25kN/m and 19kN/m respectively.

The starting resistance for steel pipes is approximately zero while it exists for

concrete pipes in both types of sand. The difference in the starting resistance is

150
Chapter 6 Results ofExpertmental Work

attributed to a bearing resistance in which concrete surface irregularities and joints


between the concrete pipes combine to act as a bearing surface. This bearing

resistance would then need to be overcome prior to movement and frictional


resistance thereafter. Such a bearing resistance could only occur in steel pipes at the
joints,.and then only if a slight misalignment caused the joint to open slightly
(Rogers and Yonan, 1992) . It should be noted that the jacking distance is not
considered in this case since the pipelines were pushed through the entire box (ie x,
the distance jacked, divided by L, the length of the box, is unity) .

The study of the influence of overburden pressure produced the graphs shown in
Figure 6.5 . The pattern of these results is once again very similar to the stress/strain
relationship of the materials with the exception that in this case the forces reduce

once the peak force has been achieved, typically before 20mm displacement as
before, and hence the results reflect those of dense sand. The reason for this
discrepancy is believed to be that in the latter tests the material was fully confined,
and thus a distinct shear plane would necessarily be formed between the pipe and the
sand, whereas in the tests with soil cover alone some draw-along of material was
possible and this would have been resisted by the end of the box . Shear plane
development might not have been as well defined in this case . The graphs also
show a consistent pattern of higher jacking force peaks with higher overburden
pressure for all tests. Leighton Buzzard sand and concrete pipes produced the
highest jacking forces as before.

The jacking forces are plotted against overburden pressure (q) in Figure 6.6. The
jacking forces showed a linear increase with overburden pressures from 0 to 200
kPa . The effect of the soil type on the jacking forces is illustrated by higher forces

151

-----_ .. _-
Chapter 6 Results of Experimental Work

in Leighton Buzzard sand than River Sand. Similarly higher forces were required
for concrete pipes than for steel pipes. A summary of the results of this series of

tests is shown in Table 6.2 .

Table 6.2 Influence of Overburden Pressure on Jacking Forces


Type of Soil Pipe Surface Jacking Forces (kN) Overburden D!splacement
approx. D!splac.
20mm 80mm
Pressure
(kPa)
(mm)
.'
Le!ghton Buzzard Concrete 105 94 200 15
Le!ghton buzzard Concrete 62 58 100 12
Le!ghton Buzzard Steel 44 38 200 5
Le!ghton Buzzard Steel 26 24 100 2
River Sand Concrete 59 54 200 10
River Sand Concrete 31 31 75 10
River Sand Steel 30 29 200 18
River Sand Steel 13 12 75 10
,* Displacement at maximum jacking forces. ,

From these data it is clear that both sand type and the pipe material greatly influence

the resistance to jacking. For the maximum overburden pressure of 200kPa a force

of 105kN was achieved for concrete pipes in Leighton Buzzard sand, while for the

steel pipes the corresponding force was only 44kN . The jacking forces in River

sand for concrete pipe and steel pipes were 59kN and 30kN respectively. The effect

of the overburden pressure on the rate of frictional increase during the jacking

operation would be fully explained in section 7.2.2.1, Chapter 7 .

Where no surface surcharge was applied (q=O), a starting force was required in all

cases to overcome the skin resistance between the pipeline and the surrounding sand

and any bearing resistance. This starting force should correspond to the values

obtained from the ftrst series of tests at maximum depth when the only overburden

152
Chapter 6 Results ofExpertmental Work

on the pipeline is exerted from the soil cover itself, (Rogers and Yonan, 1992) .

6.4.2 Overcut Ratio

Overcutting or over-excavation of the face of the tunnel influences both the


behaviour and the magnitude of the jacking forces, as discussed previously .
Overcut was achieved by using a larger diameter cutter shield than the pipe
diameter. Experimental study of this phenomencnhas not been conducted in such a

manner before and no guidance was available, for example, on the influence of scale
(overcut ratio to particle size) on the resul ts .

The investigation of the influence of overcut ratio on the jacking forces was studied
using different overburden pressures, two sand types, two pipe surfaces and

varying jacking distance. The overcut ratio used for all tests ranged from 0 to

approximately 0.14, as discussed in Chapter 5. For each size of overcut ratio,


therefore, a complete interaction with the other parameters was established.

The results of the testS using concrete pipes in Leighton Buzzard sand are presented
in Figure 6.7a for an overcut ratio (R) of zero and four levels of overburden
pressure. An approximately linear trend was achieved in all cases, once initial
resistance had been overcome, although some curvature occurred after 11 OOmm at
the higher stress levels, most notably for the surcharge pressure of 200kPai. The
initial resistance was similar for all overburden pressures for R=O, but both varied
with overburden pressure and increased as R increased (Figures 6.7b to d) . The rate

of increase in the jacking forces with distance under higher pressures reduced
markedly as R increased such that the forces increased only marginally with distance

153
Chapter 6 Results ofExperimental Work

at the higher R values.

The magnitude of the maximum jacking force began to decrease as the overcut ratio
increased until it reached an overcut ratio (R=0.140) where the jacking force
increased, as illustrated in Figure 6.7d . The maximum force under the 200 kPa

overburden pressure was 100 kN for R=O, 45 kN for R=0.030, 100 kN for
R= 0.064 and 143 kN for R= 0.140, indicating that an overcut ratio of 0.030 was
most beneficial. However the rates of increase in the forces indicate that a higher
overcut ratio would be better in practice, there being no apparent difference between
the gradient for R = 0.064 and R = 0.140.

Similar, though somewhat more erratic, behaviour was observed for steel pipes

when jacked in Leighton Buzzard sand with different overburden pressures, as


shown in Figure 6.8 . For R=0.084 the maximum jacking force was 32 kN at
q=200 kPa, a value lower by a factor of approximately four when compared with
corresponding values for concrete pipe.

Measurement of the jacking forces using concrete pipes in River sand produced
results as shown in Figure 6.9 . At R=O the maximum force was 41 kN for
q=200 kPa, while for R=O.030 the corresponding maximum force was only 29 kN

and this decreased to 10 kN for R=0.064 . The gradients of the lines progressively
reduce with an increase in overcut ratio, as with Leighton Buzzard sand. Figure

6.10 shows similar graphs and similar trends of behaviour for steel pipes in River

sand, with the exception that for R = 0.084 and q=lO kPa, the curve rose
unexpectedly steeply. This is thought to be because with large overcut, arching
mechanisms cannot be sustained over the pipe and collapse occurs . This creates

154
Chapter 6 Results ofExperimental Work

to
resistance values that are similar'(or worse than) R~O case. The jacking forces

ranged from 7 to 21kN for the 200 to 10kPa overburden pressure, with the two
intermediate overcut ratios producing the lowest maximum jacking forces.

Although the results discussed above present a clear indication of the similarity in
behaviour and magnitude of the jacking forces for all the tests, it is important to
examine the influence of the overcut ratio on the jacking forces in isolation from any
other factors that may contribute to changes in behaviour. In practice, it is important
to know the amount of overcut that should be adopted in order to maintain the least
possible resistance during jacking operations . (The parallel considerations of
surface settlement and subsurface ground movement should also be judged in any
decision, but this subject falls without this thesis.)

It is necessary, therefore, to establish an appropriate relationship between the

overcut ratio and the jacking forces. From the relationships of jacking load against
displacement, the gradient for each overburden pressure was calculated to give the
jacking resistance as a force per metre jacking (kN/m), as shown in Table 6.3 .
These values were then plotted against the overcut ratio for each type of soil and pipe
surface, as presented in Figure 6.11 . It can be seen that a minimum jacking force is

achieved for anovercut ratio' of approximately 0.040. It should be noted that the
trends for the lowest overburden pressure of lOkPa were upwards with increasing

overcut ratio and did not, thus, indicate minima . Such an overburden pressure
would be remarkably low in practice and would in any case result in low jacking
forces. By referring to Figures 6.11b and 6.11c, the minimum jacking resistance
experienced for both types of sands using concrete pipes is approximately the same.
This gives an indication that, at the optimum overcut ratio, the jacking resistance is

155
----------------------------------------------------------------------- -

Chapter 6 Results ofExpertmental Work

only dependent on the pipe surface, and will be similar for any particular type of

granular soil when the pipeline is jacked at any depth below ground level. The

results for the steel pipes, shown in Figures 6.12b and 6.12d indicate a difference in

the minimum jacking resistances, although in both cases the resistance was _low

with values of approximately 4kN/m and IkN/m respectively. The results do appear

to be independent of overburden pressure.

Table 6.3 Influence of the overcut ratio on the jacking resistance

(kN/m per m run )


JaCkin~resistance
Type of Soil Pipe Surface Overcut Ratio (kN Im per m run
(RI
q=100 kPa q=200 kPa
Lelghton Buzzard concrete 0.0 36 65
0.030 17 20
0.064 18 22
0.140 13 20
Lelghton Buzzard steel 0.016 9 12
0.048 7 8
0.840 11 12
River Sand concrete 0.0 30 35
0.030 19 22
0.064 20 25
River Sand steel 0.0 7 13
0.016 4 10
0.048 1 3
0.084 6 20

It should be noted in any discussion of overcut ratio that the scaling effect of pipes at
typically one fifth to one tenth scale means that the effective particle diameters are

five or ten times greater than those used. It might be concluded, therefore, that the

results of this work are applicable to coarse sands and gravels. Alternatively the

absolute magnitude of the optimum overcut, 10mm on diameter, is the equivalent of

one half of that typically used in practice (10mm on radius) .

156
Chapter 6 Results ofExperimental Work

An estimation of the rate of increase in the jacking resistance for any overburden

pressure can be made from the relationships established in Figure 6.12 . The

relationships are approximately linear and tend to be minimal for an overcut ratio in

the region of 0.040, as estimated from Table 6.3. By multiplying the amount of the

overburden pressure above the pipeline by the factors shown in Table 6.4, the

jacking resistance may be calculated for any particular overcut ratio. It is apparent in

the case of the river sand, that the rate of increase seems to be reversed at the two

maximum overcut ratios of 0.064 and 0.084 . This indicates the possibility of

arching mechanisms occurring due to the annular gap at lower overcut ratios and that

these cease to be effective as the overcut ratios increase due to collapse in the soil

structure, and thus a breakdown in the arching mechanism .

Table 6.4 Factors ofIncrease in the Jacking Resistance at Various Overcut Ratios
Rate of increase in
SoU Type Pipe Surface the jacking resistance Overcut Ratio
for any overburden
pressure IkN/m2)
Surcharge Iq) Multiply by
Lelghton Concrete 0.396 0
Buzzard 0.019 0.030
0.063 0.064
0.039 0.140
Leighton Steel 0.027 0.016
Buzzard 0.014 0.048
0.009 0.840
River sand Concrete 0.197 0
0.037 0.030
0.043 0.064
River sand Steel 0.055 0
0.020 0.016
0.006 0.048
0.084 0.084

157
Chapter 6 Results of Experimental Work

6.4.3 The Type of Soil

The type of the soil through which the pipeline is jacked is one of the main factors
that dictate the magnitude of the jacking forces, both as a result of stand up times in
cohesive soils and frictional resistances and arching effects in cohesionless soils. In
sands only the latter case is relevant. The skin friction generated from the movement
of the pipeline in the surrounding material must be countered by the force from the
jacks pushing the pipeline forwards. Such relationships are shown in Figures 6.13
and 6.14 .

The results shown in Figure 6.13 explain the effect of the surrounding soil on the
magnitude of the jacking forces in terms of stresses on the pipe wall for tests of
Type I under an overburden pressure of 200kPa. The stresses indicate higher
resistance from the Leighton Buzzard sand/concrete interface than the River

sand/concrete interface, the same relationship also occurring for the steel pipes. For
pipe displacement not exceeding 20mm, the maximum jacking force produced was
to overcome the interface resistance between the pipeline and the surrounding soil in
all cases. The forces generated from the Leighton Buzzard sand on the concrete
pipes reached a maximum of 99kN while for River sand the corresponding value
was 58kN . When surrounding steel pipes, the Leighton Buzzard sand provided a
maximum resistance of 45kN and River sand 30kN . These graphs illustrate some
similarity with the shear-stress/shear-strain relationships for these soils shown in
Figures 4.15 and 4.16. After the pipeline had been jacked forward by 15mm, or
5mm in the case of Leighton Buzzard sand and steel pipes, the resistance reduced
until it reached a steady ultimate value . Graphs of force against overburden
pressure, as shown in Figure 6.6, were replotted for comparison purposes for both

158
Chapter 6 Results oJExperimental Work

Leighton Buzzard and River sand, for each type of pipe surface, and these are

shown in Figure 6.14 . The results in general conform well to linear relationships.

The gradients of these lines will give the skin friction resistance per unit surface area

between the external pipe surface and the surrounding soil, as presented in Table

6.5. The curves shown in Figure 6.14 can be compared with those in Figures 4.15

and 4.16 for the direct shear tests on the two sands.

Table 6.5 Skin Friction Measured in Tests of Type I


,
Type of Soil Pipe Surface Skin Friction $Int

Leighton Buzzard Concrete 0.44 38


Leighton Buzzard Steel 0.24 37
River Sand Concrete 0.15 28
River Sand Steel 0.10 27

The jacking forces required to push the pipeline forwards as excavation was
conducted at the face in the tests of Type IT are presented in Figure 6.15 against pipe

displacement. No overcut was used in these tests, which showed that higher forces

were needed to overcome the resistance between the pipeline and Leighton Buzzard

than the River sand. The results are tabulated in Table 6.6 . Full interpretation of
these results is· given in Chapter 7 .

* <1>' int = interface friction angles.

159
Chapter 6 Results ofExperimental Work

Table 6.6 Influence of the Pipe/Soil Interface on the Jacking Resistance


Jacking Force/m length
Type of Soil Pipe Surface (kN/m)
q= 10kPa q= 200kPa
Lelghton Buzzard Concrete 6.0 76.0
Lelghton Buzzard Steel 2.8 4.0
RlverSand Concrete 1.0 20.0
RlverSand Steel 1.0 3.0

6.4.4 Pipe Surface

The influence of pipe surface on jacking forces has been referred to in previous

sections, but will be repeated here for completeness . In pipe jacking, sliding

resistance is normally generated from the friction between the pipeline surface and
the surrounding material . This resistance is caused by the relative movement

between the pipeline surface and the soil particles, and it will be affected by the

magnitude of the vertical pressure (overburden), at the pipe levelJand hence the mean

effective stress acting normally to the pipe wall, and the total surface area of the

pipeline.

The results show higher sliding resistance for the concrete surface than the steel for

both types of sands, as shown in Figure 6.16 which is a plot of force per distance

jacked (taken as a ratio of jacking force tonB) against the proportion of distance
a
jacked over box length. For'surcharge of q=200kPajacking forces per metre length

of 75kN/m were recorded for the concrete surface and the Leighton Buzzard sand,

while for the steel surface the value was only 4kN/m . For the River sand, the

situation is similar for q=200kPa, where the forces required per metre length for the

concrete surface is 35kN/m and for the steel surface is 7.5kN/m .

160
Chapter 6 Resu[ts of Experimenta[ Work

6.4.5 Jacking Distance

The jacking distance is one of the main factors for detennining the ultimate capacity
required of the main jacks to push the pipeline forwards. In practice, long distance

jacking is usually subdivided into a number of shoner jacking distances, using

interjacking stations, depending on the type of the soil, and size and depth of the
pipeline. Longer jacking distances generate higher jacking forces, because they

create a larger surface area in contact with the ground.

To establish the relationship between jacking distance and the magnitude of the

jacking forces, the jacking force against distance relationship was divided by the

total length of the pipeline as it was pushed forwards in the model tank in tests of

Type H, as shown in Figures 6.16 and 6.17. The force per metre length in kN/m is

plotted against the dimensionless distance of XIL, where X is the distance measured

from the face of the tunnel to the front face of the tank and L is the total length of the
model tank.

It is apparent that for all tests, regardless of the type of soil, pipe surface,

overburden pressure and the amount of overcut ratio, the forces behave similarly in

that they rise according to approximately linear relationships. The gradient of each
line will illustrate the resistance that is required to be overcome per metre jacked.

6.4.6 Pipe Joints

The type of pipe joints merely contributesto the magnitude of the resistance generated

as the pipeline is pushed forwards. Various types of joints can be used for pipe

161
Chapter 6 Results of Experimental Work

jacking pipes, but for simplicity in this research the types of joints were divided into

smooth (closed) and rough (open) joints only. Tests using steel pipes were not

conducted because they have only smooth, perfectly fitting joints, and therefore, all

pipes joint testing was carried out with concrete pipes.

The effect of the joints on the jacking forces is best represented in tests with no

overcut, when the pipeline is in full contact with the surrounding material .

TheoreticaJly if the joints are rough, the resistance to forward movement caused by

the gap in the joints increases as the surrounding soil particles trap in the gaps during
the movement. This resistance can be considered as a partial bearing resistance. If

the joints are smooth the resistance will be less,as observed from the test results.

The results in Figure 6.18 represent the behaviour of the jacking force with distance

as the pipeline is jacked forward. The rough joints produced higher forces in

Leighton Buzzard sand than the River sand under the same overburden pressure.

The soil particles of the Leighton Buzzard sand are more uniform and larger than the

River sand and, when trapped in the joints, were expected to cause higher resistance

against the forward movement of the pipeline. It also can be seen from the results
that when the joints are smooth, the jacking forces are slightly higher than those for

steel pipes for the River sand but for Leighton Buzzard are much greater due to

higher skin friction.

Jacking forces against overburden pressure are illustrated for both types of joints in
Figure 6.19 . The jacking forces increase linearly with overburden pressure in aJl
cases, the rate of the increase being clearly higher for the rough joints in both types

of soil . The jacking forces required for an overburden pressure of 200kPa were

162
Chapter 6 Results ofExperimental Work

45% higher in Leighton Buzzard sand for rough rather than smooth joints. For the

River Sand, the rough joints caused an increase in force of 60% for the 200kPa

overburden pressure.

The other relationship drawn from the results is the force per metre length against the
dimensionless jacking length as shown in Figure 6.20 . The magnitude of the
force/metre length is higher for rough joints than those for smooth joints and steel

pipes in both types of soil .

6.5 CONCLUDING REMARKS

It has been shown that a complete set of relationships can be drawn from the graphs

and that, due to the interrelationship of the results, the same data have to be

presented (and hence some repetition is inevitable) . It can be seen, however, that the

relationships are considerably better defined in Leighton Buzzard sand than in River

sand, where much scatter of the results is prevalent.

The results have been shown to be consistent, especially when it is considered that
the sands are potentially variable in spite of the careful preparations. It should also

be remembered that much effort was expended to obtain each point on the graphs

and that one graph typically contains the results of several different tests and/or

averaged data from replicate tests. The results are considered in more detail: in the
following chapter.

163
120

100
§
80 Jh~B
~
III
~ 13
il
~
60 ~C
'ol) D~
3!=
Cl
40 [!]I;l ~
01
")
13 El'tJ
~l!H'l
~
20 [!]

0
0 50 100 150 200 250 300

Overburden Pressure (kPa)

Figure 6.1 Preliminary Test Results

100 ~ ________________________________________- ,

80

Leighlon Buzzard Sand


Concrete Pipes
q= 150 kPa

40 60 80 100 120

Displacement (mm)

Figure 6.2 Typical Force-Displacement Relationship for a


Preliminary Test Repeated 4 Times
30
Unlfonn sand t:l D-O.lm
Concrete Pipes
X/L= I • D-0.2m

"
...,. . ,f'"
." ., ..u.
""T
-'-
X
<>
D-0.3m
D-0.4m
L J. .L

•+
20
'-
"~
--- ~

::....: ~
D-O.Sm
D-0.6m
V"

.. .- ,v~
. '" .:.LY
-X

,/..
-n
10 ~

..... ..... """- .... ~

r ~ ~ .~

"" ...
t)<1
o I I I I I

o 20 40 60 80 lOO 120

Pipe Displacement (mm)

2.0p;::::======~-------~====i1
Unlfonn sand t:l D-O.lm
Steel Pipes
X/L= I
D-0.2m
X D-0.3m

1.5 <> D-O.4m
D-0.5m •

o 20 40 60 80 lOO 120

Pipe Displacement (mm)

Figure 6.3 Graphs Illustrating the Relationship Between Jacking Forces


and Pipe Displacement for the First Series of Tests .
10
Well graded sand
Concrete Pipes
X/L= 1
8

~ 6

..~8 0
X
D-O.OSm
D-0.20m
~
.8
".
4

0
D-0.3Sm
D-O.SOm
~"
2

o 20 40 60 80 100 120

Pipe Displacement (mm)

20

Well·Graded sand 0 D-0.I0m


Steel pipes
X/L= 1

X
D-0.2Sm
D-O.SSm
IS
0 D-0.70m

~0
".. 10
~
:se
".
"
~
'")
S

o
o 20 40 60 80 100 120

Pipe Displacement (mm)

Figure 6.3 (Continued), Graphs Illustrating the Relationship Between Jacking


Forces and Pipe Displacement for the First Series of Tests.
30
Unlfonn Sand
X/L= 1
25 Concrete pipes

20
~
!!
~
.
.s
15

"".,".. 10

OL---'----1-..1.,--L-J'--..l----l.--..JL--'---L_.L---L.---l.---I
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7

Depth (m)

15
Well-Graded Sand
X/L= 1
Concrete pipes

0
10
~..
~ El
~
~
;J;I
5
~

o ~~~--~~--~_L_ _L_-L~__~~__~-L~
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7

Depth (m)

Figure 6.4 The Relationship Between Jacking Force and Soli Cover
Above the Pipeline .
so
Unlfonn Sand
Steel Pipes
X/L= 1

20

~
"~
~
.Er
.>= 10
~

o
0.0 0.1 0.2 O.S 0.4 0.5 0.6 0.7

Depth (m)

15 G
Well-Graded Sand
Steel Pipes
X/L= 1

G
10
~ B
"~
~
E I:;]

....
.>=
~
5

o ~~ __L-~__L-~__L-~~~~~~~__L-~~
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7

Depth (m)

Figure 6.4 (Continued). The Relationship Between Jacking Force and


Soli Cover above the Pipeline
120

100 f- 200 kPa

---
'Q

~
80 f-
'r - l~kPa
-'L._

"".. 60 t- ~
~

0
r.. ~ 100 kPa
~
.~

~ 40 ,.r.1. . .. .... ... .


~ .-"'. "' . Oo .... .. . -=-1..8
W- 50 kP.a
20
Uniform sand
Concrete Pipes
D/B = 3.75
oI I I I I

o 20 40 60 80 100 120

Pipe Displacement (mm)

80
Well-Graded Sand
Concrete Pipes
D/B = 3.75

60 - ...... v .~~ 200 kPa


~ vv

V- - -
~~,
-
.125 kPa

~ J5kPa
",X;

20 lOkPa

1-'
- ."" ...".

o , I I , I I I

o 20 40 60 80 100 120

Pipe Displacement (mm)

Figure 6.5 Jacking Forces with Distance Under Different


Levels of Overburden Pressure
120
Unifonn sand -0- Q-10kPa
100
Steel Pipes
D/B = 3.75 * 'i-50kPa
... Q-100kPa

80 -<>- q -150kPa
-+- 'i -200kPa
~
e" 60
~
'ff
;;;l
40
~"

20

100 120

Pipe Displacement (mm)

80
Well-Graded sand 0 'i -10kPa
.. Steel Pipes
D/B=3.75 X Q-75kPa
60
l- • 'i -125kPa
Q 'i-200kPa

~
.

"e 40
~ l-
'ff ....... .....
;;;l t-
"
~
f" ~ ~
~
~ ~

20
I-
• ..r~ - •
--- ---- •
..
~

Ib.
,......t:I '! ~ ~

o I . I I I --'- I
o 20 40 60 80 100 120

Pipe Displacement (mm)

Figure 6.5 (Continued), Jacking Forces with Distance Under Different


Levels of Overburden Pressure.
120

100

80
~ G

"!:l 60
~ t;J

J
u 40
~

20 Uniform sand
D/B = 3.75
X/L= 1
Concrete pipes
0
0 50 100 150 200 250

q (kPal

60

50

40

30

20

10 Well-Graded Sand
D/B =3.75
X/L= 1
Concrete pipes
o
o 50 100 150 200 250

q (kPa)

Figure 6.6 Jacking Forces against Overburden Pressure (q).


120
Uniform sand
D/B = 3.75
100 X/L= 1
Steel Pipes

80

60

40

20

200 250

q (kPa)

60
Well-Graded Sand
50 D/B = 3.75
XIL = 1
0 Steel Pipes
Z 40

-...
.x

I!
~ 30
Cl
r::
:;;:
..."'" 20

10 .

0
0 50 100 150 200 250

q (kPa)

Figure 6.6 (Continued), Jacking Forces Against Overburden Pressure.


lOO
Unifonn sand
Concrete pipes
R=O.O
80 DIB = 3.75

~ 60
e0"
~

.s"OIl 40
~
..
'?

20 lOkPa

o L-__ ~ __ ~ ____L -_ _ ~_ _~_ _ _ _ L-__~__-J


o 500 1000 1500 2000

Jacking Distance (mm)

(a)

50 ~ ______________________________________,

200 kPa

la
Unlfonn sand
Concrete pipes
R = 0.030
D/B=3.75
o
o 500 1000 1500 2000

Jacking Distance (mm)


(b)

Figure 6.7 The Relationship Between Jacking Force and Distance


for Lelghton Buzzard Sand and Concrete Pipes Using
Vmous Overcut Ratios
120

100

80

60

40

q-lOkPa Uniform sand


20 Concrete Pipes
"*- q-IOOkPa R = 0.064
..... q-200kPa D/B = 3.75
0L-~~~L-~==~==~__~==~~~
o 500 1000 1500 2000

Jacking Distance (mm)

(c)

160

140

120

~
100

.&."" 80
'all
.S 60

.....
~ El q-l0kPa

40 X q-50kPa

20
Uniform sand
Concrete Pipes
•<> q-l00kPa
q-150kPa
R = 0.140
DIB = 3.75 q-200kPa
0 *
0 500 1000 1500 2000

Jacking Distance (mm)


(d)

Figure 6.7 (Continued). The Relationship Between Jacking Force and Distance
for Lelghton Buzzard,and Concrete Pipes Using Various Overcut Ratios.
'sand'
o
o 500 1000 1500 2000

Jacking Distance (mm)

(a)

20

15

~.. 10kPa
e
0 10
~

~
.~

.>4

~"
5
Uniform sand
Steel pipes
R = 0.048
DIB = 3.75
o
o 500 1000 1500 2000

Jacking Distance (mm)


(b)

Figure 6.8 The Relationship Between Jacking Forces and Distance


for Le!ghton Buzzard Sand and Steel Pipes USing Various
Overcut Ratios
40 r----------------------------------------,

30

~G
~ 20
rl!
.S:
,l(

~
10
-0- q-l0kPa
Uniform sand
"* q-l00kPa
R= 0.084
Steel Pipes
D/B = 3.75
-11- q-200kPa
OL-~~~ __ ~~~===c~~==~~
o 500 1000 1500 2000

Jacking Distance (mm)

(c)

Figure 6.8 (Continued). The Relationship Between Jacking Forces and


Distance for Leighton Buzzard Sand and Steel Pipes Using
Various Overcut Ratios
50 r.=======~~,----------------------,
Well-Graded Sand
Concrete Pipes
R=O.O
40 D/B=3.75 200 kPa

30

20

10
lOkPa

o 500 1000 1500 2000

Jacking Distance (mm)

4°rr===========~------------------____1
Well-Graded Sand
Concrete Pipes
R = 0.03 100 kPa
D/B =3.75
30
200 kPa

20

10

O~~~ __ ~ ____ ~ __- L____ ~ __ ~ __


~ __ ~

o 500 1000 1500 2000

Jacking Distance (mm)

Figure 6.9 The Relationship Between Jacking Forces and Distance for
River Sand and Concrete Pipes Using VaIious Overcut Ratios.
40 rr=============;--------------------------,
Well-Graded Sand
Concrete Pipes
R= 0.064
D/B=3.75
30

10

o
X q-100kPa
o ~~__~__~L-__~____~L_~q-~2~0~OkP~a~_L__~_____l
o 500 1000 1500 2000

Jacking Distance (mml

Figure 6.9 (continued). The Relationship Between Jacking Forces


and Distance for River Sand and Concrete Pipes USing
Various Overcut Ratios
15
Well-Graded Sand
Steel Pipes
R=O.O 200 kPa
D/B=3.75

10

10kPa

o
o 500 1000 1500 2000

Jacking Distance (mm)

8
Well-Graded Sand
Steel Pipes
R = 0.016
D/B=3.75
200 kPa
6

~
"e
& 4
"01)
.S
".
u
~
2

o ~ __ ~ ____ ~ __ ~ ____ ~ __ ~ ____ ~ ____ ~ __ ~

o 500 1000 1500 2000

Jacking Distance (mm)

Figure 6.10 The Relationship Between Jacking Forces and Distance


for River Sand and Steel Pipes Using Various Overcut Ratios
----- ---

8
Well-Graded Sand [J q-IOkPa
Steel Pipes
R= 0.048 X
D/B=3.75
6

~
~
..8
0
4

:s~
.,~ 2

o
o 500 1000 1500 2000

Jacking Distance (mm)

30
Well-Graded Sand El q-IOkPa
Steel Pipes
R = 0.084 X q-IOOkPa
DIB =3.75
• q-200kPa

20

~
..
~
~
u

...
.S
.>i
u 10
.!J

2000

Jacking Distance (mm)

Figure 6.10 (Continued), The Relationship Between Jacking Forces and


Distance for River Sand and Steel Pipes Using Various Overcut
Ratios
60r------------------r========~r=======~
Uniform sand t::J q·!OkPa
Concrete Pipes X q·!OOkPa
50 D/B = 3.75
• q-200kPa

40

30

20

10

o ~~ __- L__ ~ __~__~__L-~__~__~__~~

-0.02 0.02 0.06 0.10 0.14 0.18

R Overcut Ratio

(a)

10
Uniform sand t::J q-l0kPa
to Steel Pipes
D/B= 3.75 X q-l00kPa
8
t-
• q-200kPa

....e
~.,

~
6
t-
.".
~

: ~
•iIl
~ 4
t-
i [3-

~ 2 f-

o ...L I I I I
0.00 0.02 0.04 0.06 0.08 0.10

R Overcut Ratio
(b)

Figure 6.11 The Effect of Overcut Ratio on the Jacking Forces


30
WeJl-Graded sand D q-IOkPa
Concrete Pipes
DIB = 3.75 X q-IOOkPa
• q-200kPa

20

10

o L-__~~__~__-L__~__~__~__~__~~
-0.02 0.00 0.02 0.04 0.06 0.08

R Overcut Ratio

(c)

0.00 0.02 0.04 0.06 0.08 0.10

R Overcut Ratio
(d)

Figure 6.11 (Continued), The Effect of Overcut Ratio on The Jacking Forces
12 r-------------------------------------------,
10

~:::;.--X

2 [J R = 0.016
Unlfonn sand
Steel Pipes X R= 0.048

0
0 50 100
D/B=3.75

150

200
R= 0.084

250
b q (kPal

Figure 6.12 The Relationship Between The Rate of Increase in The


Jacking Resistance and Overburden Pressure for Various
Overcut Ratios
50
[;] R=O.O Well-Graded sand
Concrete Pipes
X R= 0.03 D/B = 3.75

~
40
• R= 0.064

~i
30
"u
;
....~
~ 20
III
~
.~

".
u
~ 10

q (kPa)
c

20 ~~______~====~======~========,-
o Well-Graded sand r::J R=O.O
__~
Steel Pipes
D/B =3.75 X R = 0.016

15 •
0
R= 0.048
R= 0.084

10

50 100 150 200 250

cl q (kPa)

Figure 6.12 (Continued), The Relationship Between The Rate of Increase in


The Jacking Resistance and Overburden Pressure for Various
Overcut Ratios
120
-Cl- Uniform-Graded
100 r- _. -+- Well-Graded
. ""
P' ~

" .,.
6 t:l
-
U
80 f-
z

.,
~
"
!:!
60
~ f- £ ~

Cl
c:
~

'" ....

....
:;;:
..,.," 40 f-

20 Concrete Pipes
q = 200 kPa

o
r; I I ,
D/B =3.75
. I

o 20 40 60 80 100

Pipe Displacement (mm)

60
Steel Pipes
q = 200 kPa
50 D/B = 3.75

40

30

20

10 iT Uniform-Graded
Well-Graded

o 20 40 60 80 100 120

Pipe Displacement (mm)

Figure 6.13 The effect of Surroundinl! Soil on The Jacking Force/Displacement


Relationship for Tests of Type I
120
Concrete Pipes
D/B =3.75
100
I:::J Uniform-Graded

Z 80
• Well-Graded

""
~

Cl)
l!
~ 60
Cl)
c:
32
..,"" 40

20

150 200 250

q (kPa)

60
Steel Pipes
D/B = 3.75
50
I:::J Uniform-Graded

40
• Well-Graded

~
"e I:::J
30
r2
'cl
:a
"
~
20

10

o L -__~__~__- L__~__~__~__~~__~__~__~

o 50 100 150 200 250

q (kPa)

Figure 6.14 The Effect of The Surrounding SoU and Overburden Pressure
on Pipe Jacking Force for Tests of Type I
120
-G- = 10kPa
q

100
...
"'*"
q = 200kPa
q = 10kPa

-<>- q = 200kPa
Uniform-Graded

80
~ Concrete Pipes
R= 0.0
~ 60 D/B = 3.75
~
'OD
.s". Well-Graded
Q 40
~

20 Uniform-Graded

Well-Graded
0
0 500 1000 1500 2000

Jacking Distance (mm)

20
-G- = 10kPa
q

15 ...
"'*" q = 200kPa
q = 10kpa

-<>- q =200kPa
Uniform-Graded

~ Steel Pipes
D/B=3.75
~ 10 R = 0.0038
~
:s
".
Q

~ Uniform-Graded
5

Well-Graded

o
o 500 1000 1500 2000

Jacking Distance (mm)

Figure 6.15 Jacking Forces Under Various Conditions for Tests of Type II
200
El q,IOkPa
• q-200kPa
• q- 10 kPa Unlfonn-Graded
150
o q- 200 kPa ••••
:[ Concrete Pipes •••••
~
R=O.O
D/8 = 3.75'
• •
..=
~
.!l
lOO

• •
• • Wen-Graded
~ 000 00
50
• 000
• • 0 0 0 Unlfonn-Graded
• 00 0-1'l 0 [;]
.OEl08()l!b6l~E10El 0-[;]0
o ~~~~~~~~.u~La~~~.~~.~~~~~~
0_0 0.2 0.4 0.6 1.0 1.2

X/L

30
El q ~ !UlU'a
Unlfonn-Graded
X q=200kPa X X
25
• q= 10kPa
X
o q = 200kPa o
20 X o
Steel PIpes Well-Graded
R=O.O X X 0
X
15 D/8=3.75 El
X X o
X X X o 0 0
X o 0
10 .... X XX a [J) 0 El Unlfonn-Graded
'XX o [;] "".... 0 o
o 0 El 0 0
5 .... E1 [;][;] 00 0
, 0 0 Well-Graded
o 0 •••
o _'Li ~ ••• ••,. • .... • •• ~ • I

0.0 0.2 0.4 0.6 O.B 1.0 1.2

X/L

Figure 6.16 The Effect of Pipe Surface on The Jacking Forces


For Tests of Type I
200
Unifonn sand c q-l0kPa
Concrete Pipes X q-50kPa

150
R=O.O
D/B=3.75

~
q-l00kPa
q-200kPa
L=2
i......
~
100
i
..!!
E!
r;
50
X

[J

0
0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

80
[!] q-l0kPa
X q-l00kPa

• q-200kPa
60

i......
~
40
i
-r;
u
E!
Unifonn sand
20
Concrete Pipes
R = 0.030
D/B = 3.75
L=2
0
0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

Figure 6.17 The Effect of Jacking Distance on The Magnitude of


The Jacking Forces For Tests of Type II
200 n---------~----------------------------__,
Unlfonn sand
Concrete Pipes

-
R=O.064

150
I-
D/B = 3.75
L=2 • •
• !..-:~~~~~~.~~~--~-
[1--';;""';;;---'
•• •• •
_ _- - .. . .
XX XX
~
I - ~

100 bt~~::~~~~~~X~X~~V~X~~~~'V~~~~~~
~ ~ 'll

c• •• '"
~ ElJ;]8[!l[;]
50 [!l r.1 r.1 '" El r.1
r- ..:..
'" I:J
'"'" I:J
1"-''''-----------..,\
[;] q-10kPa
[!l
)( q-100kPa
• q-200kPa
OL-~_~I~_~I~ __~I__~~__________~
0.0 0.2 0.4 0.6 0.8 1.0 1.2

160

-
140

120
r-
-

--..-... •• - ••
--- .- •
• J. •
••
r • y x.

I
XXXyXX ' X ~XX )<;
100 .... ~ ~

....
.=
~
-"
80 .
r I'l [!l [!l r.1 Ell'l [!lEl [!l G
El 60 I:J .~
r-
......

~
"~
40
- ~

[!l
[!l ..:. '"

Unlfonn sand
r- [!l q-l0kPa Concrete Pipes
X q-IOOkPa D/B = 3.75
20
r-
o I I
• q-200kPa R=O.140
L-2
0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

Figure 6.17 (continued), The Effect of Jacking Distance on The Magnitude


of The Jacking Forces for Tests of Type II
30
Uniform sand
Steel Pipes
R = 0.016 ••
D/B=3.75
L=2
20
i.....
~
.=
iu
-El
..... 10
'" q-l0kPa
t:l
X q-l00kPa

0 • q-200kPa

0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

40
Uniform sand t:l q-IOkPa
Steel Pipes
R= 0.048
X q-IOOkPa

30
D/B = 3.75
L=2
• q-200kPa

••
i.....
~ 20 ••
Yr
~

~ 10

X/L

Figure 6.17 (Continued). The Effect of Jacking Distance on The Magnitude


of The Jacking Forces For Tests of Type II
60

50

:§:
40
•• X
X

~
;9
~
30 • X

-"
El
;;; 20
X
[;)
[!J

r:J
[3
El
[!J
El Unlfonn sand
q-l0kPa Steel Pipes
[!J
10 R= 0.084
q-IQOkPa
X D/B = 3.75

0 • q-200kPa L=2

0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

Figure 6.17 (Continued), The Effect of Jacking Distance on The


Magnitude of The Jacking Forces For Tests Type II
80
Well-Graded sand
Concrete Pipes
R=O.O
60 D/B = 3.75
L=2
:g:
q-lO a
~ I!l
q-l00kPa
40
i" X
X

-
.....a
• q-200kPa

'" 20

60
Well-Graded sand X
Concrete Pipes
50 R=0.030
D/B = 3.75
40 L=2
8' q-l0kPa
~
El
q-lOOkPa
30 X
-=
i
.!l • q-200kPa

~
20

10 X
X
0
0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

Figure 6.17 (Continued). The Effect or Jacking Distance on The


Magnitude of The Jacking Forces for Tests Type II
60
Well-Graded sand
Concrete Pipes
50
R=O.064 X
D/B=3.75
El
40 L.-;L=-=..::2_ _ _ _-'O
:[
;g
30
~
.!l
e
..... 20

....

10 • El
X
q-10kPa
q-lOOkPa

0
• q-200kPa

0.0 0.2 0.4 0.6 O.S 1.0 1.2

Flgure 6.17 (Continued), The Effect of Jacking Distance on The


Magnitude of The Jacking Forces For Tests of Type I!
30
Well-Graded sand
Steel Pipes
R=O.O

20
D/B=3.75
L=2

i.....
~ El q- lOkPa
.c X q- 100kPa
i
.!!
.....El 10
• q- 200kPa

r..

o
0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

12
Well-Graded sand
10
Steel Pipes
R= 0.016 •
D/B = 3.75
X/L=2
8
i..... q-IOkPa
~
0
6 X q-IOOkPa
j X

-~
u
• q-200kPa

4
r..
XX
2

0
0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

Figure 6.17 (Continued), The Effect of Jacking Distance on The


Magnitude of The Jacking Forces For Tests of Type II
12
Well-Graded sand

10
Steel Pipes
• •
R= 0.048
D/B = 3.75 • •
i.....
8 X/L=2 • •• •
~
.= 6 X

iu
- X xX X
X
~ 4 X X
X
X XX t:l t:l ~El
2 .X
• [;J q-IOkPa
El q-IOOkPa
t:l X
t:l
0
0.0 0.2 0.4 0.6 0.8
• q-200kPa
1.0 1.2

X/L

Figure 6.17 (Continued), The Effect of Jacking Distance on The


Magnitude of The Jacking Forces for Tests Type II
50
Well-Graded sand
q = 200kPa
40 R=O.O
D/B =3.75

-£J- Rough Joints


~0
30
*- Smooth Joints
e Steel Pipes
~
.r 20
---
,!oI

.,=
u

10

o
o 500 1000 1500 2000

Jacking Distance (mm)

100
Unlfonn sand
R=O.O
80
q = 200kPa
-0- Rough Joints
D/B = 3.75 -*- Smooth Joints
~u 60
..... Steel Pipes

e
~
'OD
40
~u
.,=
20

o
~.-IIH.". __·--1.IH•.-a·H."""'.HI.I--I.t--I-------
L-__~____L -__~__~~__~__~____~__- J
..
o 500 1000 1500 2000

Jacking Distance (mm)

Figure 6.18 The Effect of Pipe Joints on The Force/Distance Relationship


120
r::;] Rough Joints
100
• Smooth Joints

80

~
"e 60
~
....s
~
40

Uniform sand
20 Concrete Pipes
D/B= 3.75
X/L= 1
0
0 50 100 150 200 250

q (kPa)

80

Well-Graded san
Concrete Pipes
60 D/B =3.75
X/L= 1

~
"e 40
~
...
~
"
cd
~
20
• •
El Rough Jotnts

0
• Smooth Joints

0 50 100 150 200 250

q (kPa)

Figure 6.19 The Effect of Pipe Joints on The Force/Overburden


Pressure Relationship
60
I!I Rough Joints
X Smooth Joints
50 • Steel PI es
[J
Unifonn sand El
q = 200kpa G
40
:[ R=O.O G
~ D/B = 3.75 G
X
oS 30 X/L=2 D

-I;;-!a
u

20

10

O~~::::::J
0.0 0.2 0.4 0.6 0.8 1.0 1.2

30
Well-Graded sand

25 R=O.O
q = 200kPa
D/B = 3.75
20
e
......
X/L=2

~ 15
D Rough Joints
.=
~
X SmoothJolnts
!u
-I;;-a 10
• Steel Pipes

0

0.0 0.2 0.4 0.6 0.8 1.0 1.2

X/L

Figure 6.20 The Effect of Pipe Joints on Force/Distance Relationship


Chapter 7 Interpretation of the Results

CHAPTER SEVEN

7 INTERPRETATION OF THE RESULTS

7.1 INTRODUCTION

7.2 JACKING FORCES


7.2.1 PENETRATION RESISTANCE
7.2.2 FRICTIONAL RESISTANCE
7.2.2.1 EFFECT OF OVERBURDEN PRESSURE
7.2.2.2 EFFECT OF JACKING DISTANCE

7.3 THE REDUCTION OF FRICTIONAL RESISTANCE


7.3.1 OVERCUTRATIO
7.3.2 PIPE JOINTS
7.3.3 SOIL/pIPE SURFACE INTERFACE

7.4 COMPARISON BETWEEN LABORATORY AND MODEL TESTING


7.4.1 SHEAR FORCE

7.4.2 <l>m VALUE


7 .4.3 PARTICLE SIZE DISTRIBUTION

7.5 CASE STUDIES


7.5.1 TYNESIDE SEWERAGE SCHEME
7.5.1.1 GEOLOGY AND CONSTRUCTION OPERATIONS
7.5.1.2 DRIVE (Ew-E1)

7.5.1.3 DRIVE (E2-E1)

7.5.1.4 DRIVE (E3-E21

164
Chapter 7 Interpretation of the Results

7.5.2 MI-Al SCHEME


7.5.2.1 GEOLOGY AND GROUND CONDmONS
7.5.2.2 PIPEJACK DETAILS
7.5.2.3 JACKING FORCES
7.5.2.4 CONCLUSIONS
7.5.3 PREVIOUS STUDIES
7.5.3.1 CIRIA TECHNICAL NOTE 112
7.5.3.2 HERZOG INVESTIGATION
7.5.3.3 METHODS REPORTED BY STEIN, MOLLERS
and BIELECKI. .
7.5.3.4 WORK BY AULD
7.5.4 CONCLUDING DISCUSSION

165
Chapter 7 Interpretation of the Results

7 INTERPRETATION OF THE RESULTS

7.1 INTRODUCTION

The results of the experimental work were tabulated and presented in a graphical

form in Chapter Six in order to provide a clear statement of the data. It is always

important to achieve a comparison between the experimental results obtained during

research and other published data so that a better explanation and confIrmation of the

validity of the test results can be achieved. The review of previous work revealed

that very little experimental laboratory work had been carried out on pipe jacking

forces, and it is therefore essential that the results obtained from this work should be
treated as an overall guide to the pattern of jacking forces behaviour with regard to
the changes in influencing parameters .

In this chapter the results will be presented in different ways to provide a more

practical meaning, by relating the jacking forces to individual parameters and ratios

such that they can be used in design. In addition, the results will be compared with
previous theoretical and practical findings.

166
Chapter 7 Interpretation of the Results

7.2 JACKING FORCES

The forces referred to herein are those needed to overcome the resistance which

opposes the forward movement of the pipeline during the jacking operation. These

jacking forces are the resultant of frictional resistance of the pipe in the gtound and

the penetration resistance of the shield as it is forced forwards. The assessment of

both frictional and penetration resistance is important for choosing the jacking

capacity, designing and/or selecting the jacking pipes, determining the safe jacking

distance and designing the methods of construction.

It is the primary aim of this work that the results from the model tests are interpreted

in such a manner that they provide the basis for the prediction of the magnitude of

the forces that are required to be overcome by pipe jacks in gtanular materials. An

initial attempt to do this is described in Rogers and Yonan (1992) .

7.2.1 Penetration Resistance

The penetration resistance is defined as the resistance to forward movement of the

cutting shield at the face of the tunnel and strictly it should consist of a combination

of face resistance and frictional resistance on the shield sides . It provides a


and
significant contribution to the total jacking forces that are required, AVaries depending

on the size, shape, and cutting angle of the shield, and the excavation technique.

There are several methods for estimating the penetration resistance based on

experimental and field data and theoretical modelS, and these are summarised by

167
Chapter 7 Interpretation 01 the Results

Stein et al (1990) . As the shield moves fOIWard shear failure is generated in the area

ahead of the cutting shield, and this causes the soil to flow. According to Stein et al

(1990), Herzog (1985) determines the penetration resistance by using an equation

devised for installation of cast iron piles, applying vertical loading instead of

horizontal loading, as indicated in the equation below:

Ps=B:ttp (7.1)

where Ps = penetration resistance (kN),

B = external diameter of the shield (m),

t = thickness of the cutting edge (m), and


p = tip resistance (kN/m2)

Stein et al (1990) also report the practical approach advocated by Scherle (l977), in

which he stated that cutting resistance ranges from 300 to 600 kN/m2 at the face.
a
These values were agreed by Salomo (1979), using"lnathematical model to establish
of
values based on the type of the soil, height"cover, and cutting shield design.

Weber (1981) used two equations for detennining the penetration resistance, the fITst

being used to calculate the face (in front) resistance which corresponds to the boring

head well in advance of the cutting edge while the other considers the effect of the

depth of the pipeline on the face resistance when the boring head is behind the

cutting shield. His experiments showed that the boring head's position in the cutting

head is an important influencing factor for determining the penetration resistance .

. These equations are reproduced below:

168
Chapter 7 Interpretation of the Results

PS"'('Y.D+C)A..It.B.t In front (7.2)

Ps'" ('Y. D . tan<l> + C) A.. It. B. t --------- effect of depth (7.3)

where Ps = penetration resistance (kN),


'Y = soil density (kN/m3),

C = soil cohesion (kN/m2),

A. = coefficient ofload bearing capacity,

t = thickness of the cutting edge (m),

B = external diameter of the pipeline (m),

D = height of soil cover (m), and

<I> = angle of internal friction (degree).

During this experimental work, the penetration resistance was kept to a minimum by

using a specially designed cutting shield, described in Section 5.2.6, in which the

angle of 300 was chosen as an appropriate match to the internal angle of friction of a

sand. By using relative dimensions for each particular test, the resistance to

penetration was determined from the above equations, these values being presented
in Table 7.1.

169
Chapter 7 Interpretation of the Results

Table 7.1 Penetration Resistance for the Model Tests


Penetration Resistance (kN)
Investigation
Lelghton Buzzard Sand River Sand
Herzog 2.50 1.90
Weber In front 0.80 0.75
Inside (1 Om cover) 6.60 5.30
Scherle (300) 0.19 0.19
(600) 0.38 0.38
Loughborough Test 6.00 3.00 Concrete
5.00 1.00 Steel
5.50 2.00 Average

The penetration resistance obtained from Type II experiments at zero overcut ratio,
as indicated by Loughborough Test in Table 7.1, agree well with Weber's equation

for the boring head behind the cutting edge (under lOm cover) for Leighton Buzzard

sand and with Herzog's equation in the case of River sand.

The comparison of the River sand results with the Herzog calculation is mainly

based on the passive soil pressure in front of the cutting shield while the Leighton

Buzzard sand provided higher pressure probably due to arching, and thus effectively

a plug forming, in front of the shield and possibly due to material instability. It is

suggested that the Weber inside value should normally be adopted to calculate the
penetration resistance since it has a better theoretical basis, particularly when the soil
in front of the shield is of a highly dilatent or an unstable (Le unlikely to be subject

to negative pore water pressures, or suctions) nature, as demonstrated by the

Leighton Buzzard sand.

170
Chapter 7 Interpretation of the Results

7.2.2 Frictional Resistance

Frictional resistance is the force between the surface of the pipeline and the

surrounding soil and is influenced by many factors, of which the most critical are the

applied overburden pressure, the bearing resistance at the joints and the skin friction .

. Basically, the principle of frictional resistance for pipe jacking is the same as that

propounded by Coulomb, in which the frictional resistance for a cohesionless soil is

the product of the coefficient of friction between two surfaces and the normal
effective force applied to the interface:

Fr=JlN' (7.4)

where Fr = frictional resistance (kN)

Jl = coefficient of friction, and

N' =normal effective force (kN)

Applying this principle to pipe jacking the frictional equation can be written as
follows:

(7.5)

where Fr = the frictional resistance (kN),

K1 = coefficient of overburden pressure,

D = the soil cover above the pipeline (m),

171
Chapter 7 Interpretation of the Results

y = the soil density (kN/m3),

B =the diameter of the pipeline (m), and


L = the jacking distance (m) .

By considering the applied overburden pressure on the crown of the pipeline as a


strictly simplified worst case, ignoring arching and considering the problem in one

dimension only, K j can be taken as unity. To allow for the practical effects of

arching and variation of stress around the pipe circumference, and thus to extend the

experimental data to practice, the K j value can be determined by plotting the jacking

forces obtained from the results of the model tests against the overburden pressure

applied to the top of the pipeline, as shown in Figure 7.1 . By relating K J and yD

(the overburden pressure to soil cover, or equivalent soil cover) values, K j can be

obtained for changes in the depth of the pipeline and hence the jacking forces can be
estimated from equation 7.5 for both types of soil (Leighton Buzzard and River

sand) against steel and concrete pipes. The K j value is obtained from tan ~m' where

~m is represented by ~ in Figure 7.1 . All of the K j values obtained from both the

confined and unconfined states are shown in Table 7.2 . It is apparent from Figures

7.1 a and b that the starting forces for the confined state at zero surcharge are
approximately the same as those for the maximum soil cover in Figures 7.lc and d in

the unconfined case for both types of soil and jacking pipe. It was also noticed that

the rate of increase in the jacking forces in the case of the unconfined state is higher

by approximately 3-5 times greater for Leighton Buzzard sand and by 4-9 times

172
Chapter 7 Interpretation of the Results

greater for the River sand than that of the confined case below the 125 kPa surcharge

pressure, depending on the pipeline surface. However, the rate of increase in the

jacking forces in the confined state decreases by approximately 45% and 20% on
average beyond the 125 kPa surcharge for Leighton Buzzard and River sands

respectively. This behaviour in the jacking forces may be related to the effect of the

soil cover (overburden and/or surcharge pressure) on the amount of the applied

pressure on the jacking pipes at various depths, which would be expected to be

dominated by the arching mechanism in the soil above the pipeline in the confined

cases. Further explanation will be given in Section 7.4 .

It is apparent that the Kt values for the confined state are higher when the

overburden pressure is less than 125 kPa . This indicates that the arching mechanism

is more influential when the pipeline is subjected to higher overburden stresses.

However, the higher values of Kt that were recorded for the unconfined state

indicate the occurrence of total instability of the surrounding material, and hence

dilation of the granular material on shearing, caused by collapse settlement onto the

pipe, which causes the frictional resistance to increase.

173
Chapter 7 Interpretation of the Results

Table 7.2 The KI values


KI Value
Sand Type Pipe Surface State
<125 kPa > 125kPa Average

Lelghton Buzzard Concrete Confined 0.38 0.21 0.30


Steel 0.15 0.08 0.12
River Sand Concrete Confined 0.19 0.15 0.17
Steel 0.07 0.09 0.08

-- -
Lelghton Buzzard Concrete Unconflned 1.60
Steel 1.00 -
River Sand Concrete Unconflned 0.87 - -
Steel 0.67 - -

The results for the unconfined state provide a clear comparison with the lateral earth

pressure factor of K=I, whilst in the confined state with the effect of arching in the

soil, the lateral pressure developed by the jacked pipeline is much lower . This

phenomenon is believed to have also contributed to the reduction in the KI values

beyond the overburden pressure of 125 kPa on the pipeline . Hence the confined

state would prove more realistic than the unconfined values.

In addition to the above data, which are for tests of Type I, the frictional resistance

generated from the surface contact between the pipeline and the surrounding soil can

be determined from the data from tests of Type II for different overburden stresses,

and this is shown in Figure 7.2 . The rate of increase in the jacking forces per unit

surface area is denoted as H and obtained from the gradient of the straight line

relationships in Figure 7.2 . Then the jacking forces can be related to the soil stresses
above the pipeline by the following equation

174
Chapter 7 Interpretation of the Results

F=HB1tL (7.6)

where F = jacking force (kN),

H = rate of frictional increase (kN/m2),

B = external diameter of the pipeline (m), and

L =jacking distance (m) .

The H values, obtained from model testing for all of the overcut ratios and for both

concrete and steel pipes in both types of sands, are plotted as shown in Figure 7.3 .
These graphs can be used to calculate the jacking forces, using equation 7.6, for

intermediate levels of surface surcharge . The determination of H for practical

calculation is dependent on the surrounding material type and the amount of overcut .

For the single-sized material (Leighton Buzzard sand), the upper bound is obtained

when the pipeline is in full contact with the surrounding material and the influence of
dilation in the material adjacent to the pipe (caused by the overcut) is minimal. The

lower bound of H is determined by maximum arching effects in the soil, and hence

minimum surface contact stresses with the surrounding material . The arching

mechanism, especially at higher surcharges, is thus the dominating factor in

controlling the surface stresses on the pipeline. However, as the annular gap.
between the pipe and the excavation increases (i.e overcut ratio increases), the

combination of both dilation and instability of the soil contribute to an increase in the

surface contact stresses, and hence the jacking forces, as demonstrated in Figure

7.3a with R=O.064 and 0.140 .

175
Chapter 7 Interpretation of the Results

The well-graded sand (River sand) in a more compacted form, has similar behaviour

but the arching mechanism plays a greater role in reducing the surface contact

stresses, hence jacking forces, as shown in Figure 7.3b with R=0.030 and 0.064 .

Below approximately 80 kPa, the material tends to loosen and produces an increase

in the skin friction as the pipeline is jacked forwards. At R=0.084 in Figure 7.3d,
the material is in a collapsable state up to approximately 100kPa especially when it is

subjected to low surface stresses.

It is important to emphasize that the state of the material at the face of the excavation

has a role in determining the amount of face resistance and surface contact with the

pipeline. If the material is unstable at the face, it tends to collapse as the pipeline is

pushed forwards and hence both the surface stresses and the interface resistance

increase as shown in Figure 7.3a, R=O.O . However, if the face is stable, the jacking

resistance experienced by the pipes is purely related to the arching mechanism of the

soil and the surface contact with the pipeline. Therefore, equation 7.6 representsthe

more practical approach for calculating the jacking forces as it is derived from the

Type IT tests, while equation 7.5 provide a total surface friction which can be used in

situation where the full collapse of the material occurs or where no overcut is used
with closed face excavating machines.

Interpolation for different types of sand should be carried out according to grading
and relative angles of internal friction (the latter accounting for variations in
density) . The particle size scaling effect should be taken into account when

considering the overcut ratio in equation 7.6 . In view of the fact that arching is an

important component in the calculation, judgements based on the relative angles of

176
Chapter 7 Interpretation of the Results

dilation would also be appropriate.

7.2.2.1 The Effect of Overburden Pressure

In Chapter 6, the relationship between the jacking forces and overburden pressure
was presented for both types of test. The overburden pressure above the pipeline

was studied by conducting two series of tests, the ftrst (Type I) concerning the

height of the soil cover (D) and the second (Type IT) by a surcharge applied at the
surface of 0.65 m of soil cover . These cases refer to the unconftned and conftned

states presented in Figure 7.1 c and d, and 7.1 a and b respectively.

The rate of increase in the jacking forces can be expressed by the following equation:

F/1tBL = c. q (7.7)

where F = jacking force (kN),


B = diameter of pipe (m),
L = length of the pipeline (m),

q = vertical stress at the level of the pipe crown (kPa), and

c = rate of increase in frictional resistance with normal stress.


Equation 7.7 is identical to equation 7.5, with q representing the "(D value and any

applied surcharge. The c values should thus be similar to Kt .

It appears that a straight line relationship generally exists between the jacking forces

and overburden pressure, and thus c will be constant, at least for distinct stress

177
Chapter 7 Interpretation of the Results

ranges, for specific combinations of pipe and soil type. It is apparent that the rate of
increase in the jacking stress is greater up to 125kPa surcharge than beyond this
point, as indicated in Figure 7.1 a and b . The differences tend to be more noticeable
for the higher jacking stresses, especially in the case of the concrete pipe in Leighton
Buzzard Sand. The values shown against the type of pipes at the top of each graph
indicate the values determined as an average, that is from a line drawn as a
continuous straight line through both zones. The values in Table 7.3 give the rate of
increase in the frictional resistance (c) from the changes in the overburden pressure
of the soil cover and the applied surcharge for tests of Type I . It can be established
from the results that the rate of increase is considerably greater in the case where the
overburden was unconfined than where it was confined.

Table 7.3 Rate of Frictional Resistance Increase from Changes in


Overburden Pressure in Tests of Type I
Rate of Increase In
Sand Type Pipe Surface Frictional ReSistance (c)
Soil Cover Surface Stresses

Lelghton Buzzard Concrete 0.38 <125 kPa


(urilform-graded) 0.21 >125 kPa
1.68 0.30 Average
Steel 0.15 <125 kPa
0.08 >125 kPa
1.00 0.12 Average
River Sand Concrete 0.19 <125 kPa
(well-graded) 0.15 >125 kPa
0.88 0.17 Average
Steel 0.07 <125 kPa
0.09 >125 kPa
0.68 0.08 Average

178
Chapter 7 Interpretation of the Results

It would appear, therefore, that the influence of surface confinement, which would
often be the case in practice where paved surfaces or vegetation exists, is to induce

arching within sandy soils. This observation is thus important when attempting to

apply laboratory model test data in practice.

The difference between the frictional resistance for steel and concrete pipes was less

pronounced in the unconfined than in the confined case. There was more difference

between the frictional resistance in the Leighton Buzzard sand than in the River sand
for the unconfined case, although it is the differences in the behaviour in the

confined case that are lik1ey to be most important in practice.

It can be noted in general the jacking forces tend to increase at a slower rate as the
surcharge (and by implication soil cover) reaches higher values.

In order to investigate the effect of the ratio of soil cover to pipe diameter (DIB) on

the relative skin friction between the pipeline and the soil particles, the jacking force

is divided by B2yn:L and plotted against DIB . This relationship has been investigated
by Scherle, Weber and Salomo based on their investigations of pipe jacking
operations. For comparison, the results obtained from the model testing, for both

confined and unconfined states, were plotted in Figure 7.4 together with the

predictions of Scherle, Weber and Salomo .

It is apparent from Figure 7.4 that the coefficients of the relative skin friction
obtained from the model testing are higher than those predicted theoretically. The

results of the confined state are approximately 22% and 42% less than the

179
Chapter 7 Interpretation of the Results

unconfined state for concrete and steel pipes respectively in the Leighton Buzzard

sand and 13% and 60% less for the River sand. It seems that a minimum of 27%
and 56% reduction in the relative skin friction can be achieved when using smooth

steel pipes in Leighton Buzzard and River sand respectively, as shown in Table 7.4 .

As practically most, if not all, D/B ratios are above 3.0, the results for the confined
state will therefore provide a more rel~StiC estimate than the unconfmed state.
~~--------------
Table 7.4 The Results of the Relative Skin Friction from D/B Ratio
Model Coefficient of
Relative Skin Friction Soil Type Pipe Surface
Confined D/B Unconflned D/B
O.SO 3-S 1.02 0-3 Leighton Buzzard Concrete
0.5S 3-S 1.00 0-3 Leighton Buzzard Steel
0.69 3-S 0.79 0-3 River Sand Concrete
0.30 3-S 0.75 0-3 River Sand Steel

During the experimental work, it was noticed that in River sand for q= 200 kPa, the

initial 400mm of the drive produced a smaller resistance before increasing to the

expected gradient and this was attributed to inconsistencies in experimental

procedure. Relating the forces under the maximum and minimum surface stresses,

the influence of overburden stress can once more be examined and this has been

done in the last colunm in Table 7.5 . The results are evidently consistent for the
concrete pipes, the value of c in River sand being slightly lower than expected

because of the initial 400mm of the drive.

180
Chapter 7 Interpretation of the Results

Table 7.5 Rate of Frictional Increase for different surface stresses in tests of

Type IT
Sand Type Pipe Surface Rate of Friction increase (c)
SoU Cover Smface Stress
Lelghton Buzzard Concrete 0.35 0.37
Unlfonn Sand Steel 0.13 0.04

River Sand Concrete 0.21 0.17


Well-graded Steel 0.10 0.02

7.2.2.2 The Effect of Jacking Distance

In practice, long jacking drives usually require higher jacking forces. During this

study, the relationship between jacking force and distance was examined in tests of
Type 11 (see Section 5.5) . Figure 6.17 shows graphs relating the magnitude of the

jacking forces to the distance over which the pipeline was driven through the test
box. For each test, the surcharge on top of the soil (q) was increased from 10 kPa to
100 kPa and then to 200 kPa . The results indicate an approximately linear increase

in jacking force with distance, with all of the data showing a similar trend while the
absolute values vary depending on the pipe surface, overburden, soil type and the

differences in the amount of overcut ratio.

The concrete pipeline followed a shield of four different diameters of up to 50mm

larger than the pipe diameter. The results of these tests show a similarity in their

pattern, with a starting, or initial, resistance resulting from a combination of face

resistance, other bearing surface resistance and frictional resistance on the shield.

The starting force is noticeably greater in Leighton Buzzard Sand (8 kN) than in

181
Chapter 7 Interpretation of the Results

River sand (2 kN) . After the starting resistance, an approximately linear increase in

resistance followed thereafter, the frictional resistance along the surface of the

pipeline being strongly dependent upon the applied surface stress (q) .

The use of steel pipes created a minimum overcut ratio of 0.016 due to the

difficulties in obtaining steel pipe of exactly 200mm diameter. Figure 7.5 shows the

reduction in the jacking forces achieved from an overcut around the pipeline, and

thus lower gradients of the lines, than would have been achieved without any
overcut . Nevertheless the patterns of frictional increase with distance and surface

stress area are evidently consistent. The initial resistance in the Leighton Buzzard

sand is once again significantly greater than in the River sand, and in both cases is

somewhat lower for steel pipes than for the concrete pipes.

In order to examine the effect of the jacking distance on the driving resistance, the
gradients of the lines have been divided by the surface area of the pipes to establish

the frictional resistance per metre length of drive shown in Table 7.6 . The trend of
the results for different pipes, materials and surface stresses is clear .

Table 7.6 The Frictional Resistance in (kN/m2)

Sand Type Pipe Surface Surface Stress (kPal


200 100 10
Leighton Buzzard Concrete 28.5 16.0 3.0
Steel 3.5 2.5 1.5
River Sand Concrete 13.5 8.5 1.0
Steel 1.5 1.0 0.5

182
Chapter 7 Interpretation of the Results

7.3 THE REDUCTION OF THE FRICTIONAL RESISTANCE

A reduction in the frictional resistance of the pipeline will consequently reduce the

magnitude of the jacking forces required for a particular jacking distance. There are

various methods by which this reduction can be achieved, from both the design and

the construction techniques of the jacking operation . During construction

lubrication, maintaining a straight alignment and overcut ratio are the main factors

that can be used to reduce the frictional resistance around the pipeline. For design

purposes, the selection of suitable pipes is the main factor in achieving lesser
friction. The pipe characteristics that should be considered include the type of

surface, type' of joints, diameter in relation to the shield and, to a lesser degree, its

self weight.

7.3.1 Overeut Ratio

Overcutting the face of the tunnel is typically carried out in order to reduce the

frictional resistance on the following pipes. The magnitude of the overcut in soil is
controlled by the size of the shield, which is usually 20mm larger than the pipe
diameter in practice. The magnitude of the overcut is chosen to minimise the surface

settlement above the pipeline, in addition to reducing the forces. A study of this kind

has not been undertaken previously and consequently the tests were planned to

examine different overcut ratios. The results of these tests were presented in
Chapter 6.

183
Chapter 7 Interpretation of the Results

Overcut can be maintained throughout the jacking distance in stable self-supporting

ground conditions, such as strong cohesive soil, sandstone and cemented soil, with

the result that frictional forces only occur on the bottom of the pipeline. Overcut in

unstable ground will not serve the same purpose, but will instead allow the soil

above the pipeline to loosen such that it achieves an active Rankine state. This

process will induce arching in most granular materials, and will additionally reduce

the shear force required to form the shear plane in looser material. However this

process of creating active failure zones could also result in significant soil

displacements, and hence surface settlements. If the overcut is too great, this will in

turn result in collapse of the arching mechanisms and higher forces . Thus the

magnitude of overcut in cohesionless soil is critical and a proper value should be

used to minimise the effect of ground settlement and soil collapse around the

pipeline. Thus limiting values of overcut, both high and low, should be determined

for different soil types.

The results for both concrete and steel pipes are presented in Figure 6.11 in terrnsof

force divided by length of pipeline against overcut ratio. The results show that the

forces reduce to a minimum at an overcut ratio of approximately 0.04 in both types

of sand and that the forces remain low as the overcut is increased. While care would

need to be taken in translating the results to practice, since the scale effects of particle

size to tunnel diameter require some consideration, the indications of other scale

model studies are that the influence of particle size is small. The results of this work

would thus indicate the jacking forces could be considerably reduced by increasing
the overcut ratio in cases where the level of surface settlement is not critical .

184
Chapter 7 Interpretation of the Results

7.3.2 Pipe Joints

Joints between jacking pipes generate additional resistance as the pipeline is moved

forward. The roughness of the joints and the width of the gaps trap the soil particles

and hence increase the frictional resistance along the pipeline surface. This increase
could be considered to be as a result of numerous small bearing surfaces along the

pipe length, a situation that is exacerbated if lateral displacement, or steps, at the joint
occur. These bearing areas force the shear plane into the soil mass. Reduction of

the frictional resistance can be achieved by the use of smooth clean joints between

the pipes. To investigate the influence two types of joints were used during this

study for the concrete pipe only, smooth and rough joints, while the steel pipe·

joints were smooth as they were manufactured with carefully machined joints, as

explairied in Section 6.4.6 .

Figure 6.20 shows the difference between the jacking forces of the rough and
smooth joints as the pipeline is jacked forwards. The reduction in the jacking forces

was most noticeable for the case of no overcut (i.e R=O), because of the existence of

full surface contact stress between the soil and the pipeline, which produced higher

joint resistance. Table 7.7 presents the magnitude of the jacking forces that are

needed to overcome the resistance per metre run for both rough and smooth joints in

a jacked pipeline. It can be seen that the required forces for the rough jointed

pipeline are greater by a factor of 2.6 than the smooth pipeline for the Leighton

Buzzard sand and by a factor of 3.2 for the River sand. In addition, it should be

noted the the effect of the soil type on the magnitude of the jacking forces for smooth

steel pipes is relatively very small, in contrast to the findings for the concrete pipes,

185
Chapter 7 Interpretation of the Results

emphasizing the effect that the joints apparently have. Therefore, it can be concluded

that the type and degree of opening of the joints of a pipeline contribute greatly to the

amount of the resistance along the surface contact of the pipeline with the

surrounding soil .

Table 7.7 Jacking Force per metre run for Rough and Smooth Joints
Jacking Force
Type of Soil Joint (kN/m)

Lelghton Buzzard Rough 52.0


Lelghton Buzzard Smooth 20.0
River Sand Rough 27.5
River Sand Smooth 8.5
Lelghton Buzzard Smooth (Steel) 7.1,
River Sand Smooth (Steel) 6.2

7.3.3 Soil/Pipe Surface Interface

is .
It"apparent from the test results, presented in Chapter 6, that the type of the pipe
surface influences the frictional resistance. Higher jacking forces were recorded in
the uniform, coarse, angular (Leighton Buzzard) sand than the well-graded
(Concrete) River sand. The interlocking of the sand particles contribute a large
proportion to the strength of the soil, the sliding resistance being a combination of
the frictional resistance and resistance to soil dilation. For this reason, creation of
the shear plane against a smooth pipe surface will result in reduced resistance to
sliding when compared with a shear plane formed within the soil mass. This
influence of dilation is greatest when the normal stress is large, since dilation
consists of doing work against the normal forces.

186
Chapter 7 Interpretation of the Results

The area of the contact surface between the sand and the pipeline will obviously

influence the forces that are needed to overcome the frictional resistance, although it
is assumed in this work that the contact area will be the full surface area of the pipe,

certainly in the Leighton Buzzard sand and probably also in the River sand. The

only reason that full contact might not be achieved in River sand is the possibility of

pore suctions allowing the material to be temporally self-supporting, but this is

considered to be unlikely. Close contact will necessarily occur with an overcut ratio

of zero and will probably occur, although with reduced normal stresses, as the

overcut increases.

The steel pipe required considerably smaller jacking forces, the forces representing

an average of 40% in Leighton Buzzard Sand, and 47% in River sand, of the jacking

forces required to advance the concrete pipe as presented in Figure 7.1 and Table

7.3 . Thus a smooth external surface on a jacking pipe equipped with close fitting
joints is likely to result in a considerable reduction in forces of typically more than

50% .

The jacking forces in the angular, single sized Leighton Buzzard sand were 43%

(concrete pipe) and 33% (steel pipe) greater than in the rounded, well-graded River

sand.

187
Chapter 7 Interpretation of the Results

7.4 COMPARISON BETWEEN LABORATORY AND MODEL


TESTING

It is important to establish a relationship between the results of pipe jacking model

testing and laboratory tests on the sands. Based on this relationship a prediction of
the engineering behaviour of the soils in pipe jacking can be made from standard

laboratory test data. It is apparent that both shear test and particle size distribution

data are necessary for prediction in sands.

7.4.1 Shear Force

The shear forces of the model testing can be represented as jacking forces per unit

surface area of the pipeline. Figure 7.6 shows a graph relating the forces obtained

from both laboratory and model tests, using rough jointed pipes, to the horizontal
shear displacement (refer to Chapter 4 for more details) .

In principle, the process of jacking pipes may be compared with the shear box test.

When a pipeline is jacked forwards, the surface shear between the pipes and the

surrounding soil can be represented by the surface shear between soil/concrete or

soil/steel in interface shear tests. The only considerations that should be taken into

account are the circular surface in the case of the pipe compared with a flat surface in

the shear test, the local loosening of soil caused by the overcut, the variation in

normal effective stresses around the pipe circumference and the effect of
discontinuities at joints. The results of the work reported herein can provide an

appropriate comparison, and thus establish the relationship between laboratory shear

188
Chapter 7 Interpretation of the Results

testing with pipe jacking surface resistance, by considering the model tests of Type I

in which the effects of loosening by overcut are removed and thus the results at

comparable densities can be considered. Thereafter the effects of overcut can be

considered by comparison.

The normal total stresses acting in the model tests are basically a combination of both

the soil cover above the pipeline and the vertical surcharge applied to the surface of

the soil, multiplied by an appropriate factor to account for the orientation of the

surface (unity for a horizontal surface and the coefficient of lateral earth pressure, in

this case at rest, for the vertical surface with no overcut, and intermediate values in

between) . The normal total stresses adopted for the laboratory shear testing ranged

from 10 kPa to a maximum of 50 kPa, while for the model testing the normal

stresses increased from the dead weight of the soil with no surcharge applied to the

soil surface to a maximum surface surcharge of 200 kPa .

The laboratory and model test results are presented in Table 7.8, which shows the

peak and ultimate shear stresses. The relationships between shear force and distance

for the various laboratory and model tests are shown in Figures 7.7 to 7.14.

189
Chapter 7 Interpretation of the Results

Table 7.8 Peak and Ultimate Shear Stresses for Laboratory and Model Tests.
surcharge Peak Shear Stress(kPa) Ultimate Shear Stress(kPa)
Shear Interface (kPa)
lab. Model lab. Model
Lelghto~nBuzzard
~an

Soli/Concrete 10 12.2 22.5 9.6 20.8


Soil/Steel 10 12.6 12.3 10.6 11.6
Soil/Concrete 50 45.0 34.8 36.4 30.4
Soil/Steel 50 43.9 17.8 31.7 14.7
SoU/Concrete 100 .- 54.0 -- 48.4
Soil/Steel 100 -- 22.9 -- 21.2
Soll/ Concrete 200 -- 92.5 -- 83.7
Soil/Steel 200 -- 39.8 -- 32.6

RlverSand

Soli/Concrete 10 11.7 14.4 7.9 13.9


Soli/Steel 10 8.9 8.0 7.9 8.0
Soli/Concrete 75 33.3 20.8 32.6 20.4
Soli/Steel 75 28.9 12.4 27.6 12.4
SoIl/ Concrete 125 -- 35.2 -- 33.2
Soli/Steel 125 -- 14.5 -- 13.7
Soli/Concrete 200 -- 51.6 -- 47.1
SoU/Steel 200 -- . 27.6 -- 26.7

The results of the laboratory shear tests show typical behaviour for a dense material
under normal shear, with both peak and ultimate values clearly obtained . In
contrast, the model testing produced results similar to those expected for a loose
material, with the maximum shear stress occurring at the ultimate shear value. It is
also apparent that the maximum shear stress is only mobilised after a significant
distance, typically 10 to 15mm, in the model tests and that in some cases careful

study of the curves shows a slight reduction in stress post peak. It is considered that
this behaviour results from progressive rearrangement of particles both along the

190
Chapter 7 Interpretation of the Results

length of the pipe, and possibly also circumferentially to a small degree, to create a
shear plane, a phenomenon known more usually as progressive failure . This,·
combined with the arching mechanism above the pipe, results in little observed

dilation for the whole system. For this latter (arching) reason also, the normal
stresses acting in the model tests will be artificially low in comparison with those in
the shear box tests . Clearly no overcut is present in the Type I tests, the small
particle rearrangements being responsible for the generation of arching, and if .
overcuts were used the normal stresses would be lower still. Thus the comparison
between surface surcharges (which are in addition to the self-dead weight of soil)
and the directly applied normal stresses in the shear box is somewhat arbitrary, but
appears from the data to be approximately equivalent. The full normal stress (ie.
increased by approximately 12 kPa due to the weight of soil) should be considered in
definitive site-laboratory test comparisons.

Higher shear forces were recorded for conventional shear box tests on the sand (ie
soil/soil) than for the soil/concrete or soil/steel interface tests, as the shear plane
within a dense soil medium generates greater forces than those between two surfaces
of different materials. The interlocking mechanism which usually occurs with a soil
medium, and certainly with a dense granular soil, does not exist in the case of

soil/concrete or soil/steel interfaces . This is further demonstrated by the higher


forces obtained from the soil/concrete interface, where a degree of interlocking may
occur between the soil and the rough surface of the concrete, than from the smooth
soil/steel interface (Figures 7.7 to 7.14).

191
Chapter 7 Interpretation of the Results

Figure 7.7 compares the results for concrete pipes in Leighton Buzzard sand under a

surface surcharge of 10 kPa with soil/concrete interface tests at normal stresses of 10


kPa. The ultimate shear stresses of the model testing are twice as high as the peak

of the soil/concrete laboratory shear for the concrete pipes with rough joints, while

the stresses for the pipes with smooth joints are greater by approximately 1.5 times.

Greater shear forces of approximately 15% were recorded for the soil/soil than the

soil/concrete interfaces. The River sand shows similar behaviour to the Leighton

Buzzard sand, but with less well defined peak shear stresses in the shear box (ie less

post-peak reduction) and approximate parity between the laboratory and model shear

stresses, the ultimate model testing result being approximately 20% greater than that

of the soil/concrete shear interface (Figure 7.8) . The effect of the joint roughness is

less noticeable in this case, the shear stresses being only 4% higher for the rough

joints. The difference between laboratory soil/soil and soillinterface shear stresses is
more significant than in Leighton Buzzard sand, the soil/soil shear stresses being

greater by 45% .

Figures 7.9 and 7.10 represent the results for the concrete pipes in both Leighton

Buzzard and River sands at the 50 kPa surcharge. The ultimate shear forces

obtained from the model testing are significantly lower than those from the shear
box, indicating a greater degree of arching. The shear stresses for the rough jointed

concrete pipeline are approximately 26% less than the Laboratory results of

soil/concrete interface, whereas the smooth jointed concrete pipeline showed a

reduction of approximately 43% . The soil/soil interface produced 20% greater shear
stresses than the soil/concrete interface.

192
Chapter 7 Interpretation of the Results

The same approach can be adopted to compare the results of the steel pipeline, as

shown in Figures 7.11 to 7.14 . At 10 kPa surcharge in Leighton Buzzard sand


the
(Figure 7.11), the model results for"smooth steel pipeline produced shear stresses
that were approximately the same as those for the soiVsteel interface laboratory tests.
The soil/soil interface results are about 14% greater than the soiVsteel in terms of
peak shear stress, but match closely at the ultimate stresses. In the case of the River
sand ( Figure 7.12 ), the model results are also approximately the same as the
soil/steel interface results. However, the soil/soil interface laboratory results are
approximately 40% greater than those of the soil/steel interface.

The results of the 50 kPa surcharge are shown in Figures 7.13 and 7.14 for
Leighton Buzzard and River sand respectively. Once again the model test results are
markedly lower than the shear box results, again attributed to the greater effects of

arching. The model results in Figure 7.13 are approximately 60% less than the
soil/steel interface results, while the peak shear stresses obtained from the soil/soil
interface are approximately 20% greater than the soil/steel interface results . The
same behaviour in the shear stresses for the River sand was experienced as for the
Leighton Buzzard sand, but with a greater difference of 35% between the shear
stresses between the soiVsoil and soiVsteel interfaces (Figure 7.14).

Referring to Figures 7.7 to 7.14, it is apparent that the shear stresses recorded in the
shear box are normally greater than those of the model testing, the exception being
those obtained for the concrete pipes at lower overburden stresses where any effects
of arching are probably masked by the effects described below and the increase due
to soil dead weight of 12 kPa is relevant. The concrete pipes provide a somewhat

193
Chapter 7 Interpretation of the Results

undulating shear plane due to their surface roughness and joint gaps, thereby

probably causing the shear plane to be forced away from the pipe waJl, at least at
some points along the pipeline, and certainly resulting in the need for greater soil
dilation. However, as the nonnal stresses increase, the shear stresses generated
from the model testing tend to be less than those measured in the shear box . This is
almost certainly attributable to the effect of soil arching above the pipeline, as clearly
demonstrated between Figure 7.7 and 7.9, 7.8 and 7.10,7.11 and 7.13, and 7.12

and 7.14.

As the steel pipes provided smoother surfaces with no significant discontinuities at


the joints, the shear stresses were considerably lower than the concrete pipes with
both rough and smooth joints. A set of graphs has been drawn to demonstrate the

effect of the joints and surface roughness on the shear stresses of a jacked pipeline
(Figures 7.15 to 7.22) . In addition Table 7.9 presents the magnitude of the shear
stresses obtained from the model testing for steel pipes and concrete pipes with both
rough and smooth joints.

In Figures7.15 and 7.16, which represent the results for Leighton Buzzard and River
sands respectively at 10 kPa surcharge, the rough joints for the concrete pipes
produced the highest peak shear stresses, as expected. The reduction in peak shear
stress for the smooth jointed concrete pipes and the smooth steel pipes was
approximately 25% and 44% respectively in Leighton Buzzard sand. In the case of

the River sand the rough jointed concrete pipeline has approximately the same shear
stresses as the smooth jointed pipeline. The steel pipe shear stresses are 45% less
than those of the concrete pipes with rough joints.

194
Chapter 7 Interpretation of the Results

Table 7.9 Peak and Ultimate Shear Stresses with Different Pipe Joints, Surface

Roughness, and Surface Surcharge for Model Tests for Tests of Type 1.
Peak Stress (kPa) Ultimate Stress (kPa)
PIpe Surface Joint Surcharge
(kPa) Lelghton Buzzard River Sand LeIghton Buzzard River Sand

Concrete Rough 10 22.50 14.60 20.17 13.71


Concrete Smooth 10 17.69 13.36 15.13 13.30
Steel Smooth 10 12.75 8.02 11.80 8.01
Concrete Rough 50 34.57 20.80 30.31 18.14
Concrete Smooth 50 26.81 17.53 23.98 15.92
Steel Smooth 50 17.57 12.43 14.77 11.26

Concrete Rough 100 54.07 35.22 48.41 33.27


Concrete Smooth lOO 33.71 23.65 30.35 20.17
Steel Smooth lOO 22.97 14.86 21.17 13.78
Concrete Rough 200 92.48 51.68 83.73 47.16
Concrete Smooth 200 58.94 30.00 53.98 27.43
Steel Smooth 200 39.82 27.66 33.51 26.75

The behaviour of the shear stresses obtained from the model testing at 50, 100, and

200 kPa show a similar pattern to that at 10 kPa for both types of sands (Figures
7.17 to 7.22) . However, as the surcharge increases, the shear stresses of the
smooth jointed concrete pipeline in the River sand tend to decrease to the same value
as for the smooth steel pipeline, while in the Leighton Buzzard sand the pattern
continues to be approximately the same although the difference between the shear
stresses for the rough jointed concrete pipeline and the two smooth jointed pipelines
appears to increase at higher nonnal effective stresses. As expected the shear
stresses increase proportionately to the surcharge in both sands. The magnitude of
increase in the shear stresses with increase in surcharge is demonstrated in Figure
7.23 for the Leighton Buzzard sand and in Figure 7.24 for the River sand. The

intercept on the shear stress axis in these two figures relates to the shear resistance
due to the soil . cover and any boundary resistances, the most important being the

195
Chapter 7 Interpretation of the Results

resistance of the rubber seal as the pipe enters and leaves the test tank .

It is apparent that rough joints, or steps, in a jacked pipeline produce significantly

higher shear resistance as it penetrates through a soil medium. This is acknowledged

in practice, but the extent of its effect has not been fully. appreciated. It is generally

accepted that the jacking resistance is mainly related to the skin (shear) resistance of

the pipeline, in addition to a combination of other factors, but the joints effect has

always been disregarded during design calculation. It is perhaps for this reason that

both overcut and lubrication have been used in practice to reduce jacking forces, and

indeed that attempts to reduce misalignment have been made to reduce skin friction,

whereas little attention to the joint detail has been paid except in terms of structural
integrity. If the open face of a joint, or the protruding step at a joint, is considered as
a small bearing area within a confined soil mass then the increase in force can be
practically appreciated. Bearing in mind that joints will tend to open, and steps

protrude further, when pipes become misaligned, this effect will become more

prominent in poorly aligned drives. Thus reduction in misalignment will have a

significant effect, although not as a result primarily of reduced friction.

196
Chapter 7 Interpretation of the Results

7.4.2 <I>m Value

The <1>
m
value is the internal angle of friction between the pipeline and the

surrounding soil as determined from pipeline model tests . The <1>m value was

obtained from tests of Type I for both sands when the overburden pressure was

plotted against the required jacking forces per unit area of the pipeline inside the

model tank.

For comparison, the results of model tests of Type I are plotted with results obtained
from laboratory shear tests on both types of sands as shown in Figure 7.25 . The

values of <l>m • <l>L ,(the internal angle of friction between the concrete/steel and

soil from the shear box test)and <1>. (the internal angle of friction of the soil from the

shear box test)were obtained from the relationships shown in Figure 7.25 and are
tabulated in Table 7.10 . It should be noted that the intercept on the shear stress axes

for the shear box tests is a function of the slight curvature of the Mohr coulomb

failure envelope at Iow normal stresses, a best fit regression line having been fitted to

the data.

197
Chapter 7 Interpretation of the Results

Table 7.10 Friction Angles (in degrees) for Various Tests


Soil type $m <Pr. $s
Concrete Steel Concrete Steel (Peak)

Lelghton Buzzard 19 7.5 39 38 49


River sand 11 5 28 27 42

It can be seen that <l>m for the concrete pipe-Leighton Buzzard sand intetface is about

39% of the value for the sand alone (<I>s) and 49% of the laboratory value for the

concrete/soil intetface (<I>L) • The River sand produced <l>m for concrete that was 26%

of <1>8 and 38% of <l>L • The steel pipeline showed more consistent results with the

<l>m value being approximately 15% and 20% of <Ps and <l>L respectively in both

sands.

The relationship between <l>m and both <1>8 and <ilL for the concrete pipeline exhibits

significantly lower proportions in the case of River sand than for the Leighton

Buzzard sand. This difference is attributed to differential resistance generated from

the rough joints of the concrete pipeline, with the angular, uniform Leighton Buzzard

sand registering higher resistance than the rounded, well graded River Sand. This

confmns the earlier observation that rough joints generate more resistance when in

contact with Leighton Buzzard than the River sand.

198
Chapter 7 Interpretation of the Results

It can be concluded that the <1>m value of a concrete pipeline in sand is likely to be

approximately one third to one half of the <1>. value, depending on joint 'roughness' .

Where smooth steel pipes with close fitting joints are used, the values are likely to

reduce to 20% or less. However, Auld (1981) gave an estimated <1>m value of two

thirds to three quarters of <1>. when calculating the frictional resistance, and this

would appear to be conservative for design. It is recommended that a value of 50%

should be used in practice, unless a lower value can bejustifled by the use of pipes

with smooth external walls or, more importantly, a close fitting joint detail. If the

specification for the pipe permits a significant joint step, or lateral displacement at the

joint, to occur then a higher value of75% might be appropriate.

7.4.3 Particle Size Distribution

It has been shown from the model testing results that the nature of the sand particles

and their size distribution contribute to the magnitude of the jacking forces. It was

also noted that the unifonnity coefficient of the sand material will probably have a

greater effect than the size of the material itself when considering the influence of

different types of material during the design and construction of a pipe jacking
operation.

In order to relate the particle size of the material to the magnitude of the required

forces during the jacking operation, the uniformity coefficient (D60IDI0) from the

PSD curve can be used to estimate the H value when calculating the jacking forces

199
Chapter 7 Interpretation of the Results

using equation 7.6 . Figure 7.26 shows a tentative relationship between the
uniformity coefficient and the H value based on the observations of two sands only

and preconceptions of the fonn of the relationship. It should be noted that angularity

of the sands is likely to influence these data also, and yet no account can be taken of
this in this plot. This H value can be derived from both Figure 7.3 and 7.26 by

referring to the magnitude of the overburden pressure on the pipeline and unifonnity

coefficient (UC) of the excavated material respectively. It could be tentatively

concluded, from the strictly limited data, that the H value is related to the UC, the

lower UC the higher the H value.

It is practically impossible to study the effects of all the factors that may contribute to

the jacking forces in tenns of particle shape, size and size distribution. This research

has shown that all three factors are likely to influence the forces, with coarse,

angular unifonn particles providing greater resistance to shear than rounded, well

graded materials. It is apparent that <l>L (from laboratory interface tests in the shear

box) alone is insufficient to distinguish between materials that will provide small or

large resistance, and that the above factors should be considered.

200
Chapter 7 InterpretatiDn of The Results

7.5 CASE STUDIES

This section aims to compare predictionsbased on the research results, t=ed herein

the Loughborough Method, with both practical data from jacking sites and theoretical

prediction methods from the literature.

The first case will compare the relationships established from jacking operations for

a sewage scheme with the estimated values of the jacking forces based on this work,

while the second case wiII study the practical data from a jacking operation for the

installation of a culvert in a similar manner. The third case will relate the theoretical

and practical values obtained by other researchers to the results of this research

(Loughborough Method) . Each case is described separately in the following

sections.

7.5.1 TYNESIDE SEWERAGE SCHEME

7.5.1.1 Geology and Construction Operations

The scheme was designed for the removal of sewage from a large catchment area in

the area around Newcastle-upon-Tyne, Tyneside . This analysis is based on

information contained in a Loughborough University undergraduate project report

based on work supervised by Dr. C.D.F. Rogers .

The geology of the area concerned consists mainly of soft, silty alluvium overlying a

thick layer of loose river sands and gravels. The ground conditions of the site can be

summarised in terms of five major strata:

201
Chapter 7 Interpretatlon oJThe Results

(i) Made ground


(ii) Alluvial Clay

(iii) Sand

(iv) Gravel
(v) Glacial Clay

The choice of pipe jacking for the scheme was based on previous experience of the
technique and on the ground conditions which the tunnel was expected to encounter .
In addition, it was anticipated that problems encountered from water bearing strata
may affect face stability, and therefore it was decided that traditional tunnelling
operations using precast concrete segments would be difficult. Reinforced spun
concrete pipes with steel joint collers were adopted . The details of the pipe jacking
operation are as follows:-

external diameter of the pipeline: 1.78 m


internal diameter of the pipeline: 1.48 m
jacking shafts to accommodate the jacking operation of 3.6 m in diameter.
cmnching mole of external diameter: 1.80 m

During this operation, a lubrication system was used to reduce the jacking forces. It
was incorporated in the overcut gap around the pipeline and entered the void through
injection points spaced every 2.5m length along the length of the pipeline . The
lubricant was a mixture of bentonite and petroleum-based materials.

The overcut of 10mm was created from the difference between the 1.80m diameter
crunching mole excavator at the face of the tunnel and l.78m external diameter

202
Chapter 7 Interpretattnn of The Results

pipeline. Based on the research reported herein, the overcut ratio, calculated to be

0.011, and its effect on the magnitude of the jacking forces during this operation can

be established according to Figure 6.11, which indicates a reduction of

approximately 30·40% in the frictional force.

In order to produce a theoretical prediction for the jacking forces based on the

findings of this work, assumptions concerning some of the soil parameters have to

be made to obtain the jacking factor (H) referred to in equation 7.6 . These

assumptions were based on re-analysis of the site jacking forces data in terms of H
and q (surcharge), as shown in Figure 7.27 .

The surrounding soils that are most relevant to this study are of material types iii and

iv, due to their similarity to the materials used in the model testing. Therefore the

Loughborough results can be best applied to these types of materials. The geological
information and parameters are as follows

Material (iii) - Sandy Alluvium; Loose to medium dense sand with some pockets of
clay. The parameters that are required to calculate the jacking factors are assumed to

be:

<1>= 300

'Y = 19 kN/m3

KUI = tan (30/3) ------- refer to sections 7.2.2 & 7.4.2, Kiii decreases

by 20% if the surcharge> 125kPa

H;ii ------ refer to Figure 7.3

203
Chapter 7 Interpretation of'The Results

Material (iv) - Sand and Gravel; Silty fine to coarse sand and gravel. The assumed
parameters are:

Y= 19 kN/m3

Kjv = tan (35/3) ------- refer to sections 7.2.2 & 7.4.2, K iv decreases

by 20% if the surcharge> 125kPa

H.IV = ---------- refer to Figure 7.3

Correlations will only be attempted for the jacking forces data for the three drives in

areas of sand and gravel .

7.5.1.2 Drive (Ew - El)

In this drive, the first 32m of the pipeline was jacked through a mixed face of soil

type (iii) and (iv), and the rest of the drive is in the type (iv) soil. Using equation

7.6, theoretical predictions of the jacking forces can be calculated from H values

related to the line of R= 0.03 in Figure 7.3, as shown in Table 7.11 . The last
column in the table gives the jacking forces using equation 7.5 for comparison only.

204
Chapter 7 Interpretation ofThe Results

Table 7 .11 Jacking Forces for Drive Ew-El


Jacking Jacking Force (kN)
SoU Type Depth Distance
(m) H (m) Enu.7.6 Equ. 7.5.
Part Cum

lli&iv 12 20 32 3578 3578 6247


Iv 12 20 40 4473 8051 8424
Iv 16 22 63 7750 15801 17691
Iv 13 21 23 2700 18501 5241

Note: Cum. stands for Cumulative Force.

The jacking forces resulting from this drive are presented in Figure 7.28 in relation

to the jacking distance. The Loughborough Method values from Table 7.11 are also

plotted in Figure 7.28 in order to compare the theoretical and actual values. It
appears that the theoretical values are higher than the practical data by approximately
52% at a distance of 150m . This difference in forces, and more generally the fact

that the practical values are consistently lower, is attributed to the effect of the

bentonite lubrication. The effect ofthe pockets of clay might also contribute to the

lower practical values since if the granular materials had some cohesive element, then
the soil might exhibit some self-supporting behaviour, at least temporarily, due to

stress relief and pore suction.

7.5.1.3 Drive (E2 • El)

This drive was divided into two parts: PI and P2 . PI is predominantly through
material (iii) while P2 was jacked from a second thrust pit through varied strata of

type (iv) and some glacial clay. Based on these surrounding materials, the jacking

forces were similarly calculated from equation 7.6 and are presented in Table 7.12 .

205
Chapter 7 Interpretation oJThe Results

Table 7.12 Jacking Forces for Drive E2-E j


Jacking Jacking Force (kN)
SoU Type Depth H Distance
(m) (m) Eau. 7.6 Equ.7.5
. Part l.'um
PI
Iv 13.75 20 79 8835 8835 19043
III 14.5 22 21 2583 11418 4561
P2
Iv 14 21 114 13387 13387 27979
III & Iv 6.5 17 46 4373 17760 4765
III & Iv 11 20 18 2013 19773 3155

Note: Cum. stands for Cumulative Force.

The practical and theoretical jacking forces are plotted against the distance driven in
Figure 7.29 . The results show the theoretical forces to be greater than the practical

values by approximately 10% for PI and 67% for P2, the difference similarly being

attributed to the use of bentonite lubrication. A further factor that is likely to account

for the (considerable) difference between the results for P2 is the presence of the

glacial clay, which will tend to cause the material to stand up when excavated and

greatly reduce the forces on the pipes. Indeed the practical curve for P2 is typical of
a cohesive soil in which progressive collapse occurs and the forces increase
disproportionately at the end of the drive.

This drive is mainly in material (iv), although as the pipeline reaches jacking pit E3

the material changes to type (Hi) . The jacking forces obtained from the

Loughborough Method are presented in Table 7.13 and both the practical and

206
Chapter 7 Interpretation of The Results

theoretical data are presented in Figure 7.30 . The results shows that the theoretical
forces are approximately 46% of the practical values. The reduction in the jacking

forces in this case is attributed to lubrication.

Table 7.13 Jacking Forces for Drive E3-E2


Jacking Jacking Force (kN)
Soil Type Depth H Distance
(m) (m) Tqu.1.O
Part Equ.7.5
Cum

Iv 14 22 75 9226 9226 18407


Iv 12 20 158 17670 26896 33238
ill 13 21 75 8807 35703 14606

Note: Cum. stands for Cumulative Force.

7.5.1.5 Concluding Discussion

The re-analysis of the practical data, as presented in Figure 7.27, shows that all the

H values obtained from equation 7.6 lie in the lower bound region below the line of
R=0.03 in the case of both Leighton Buzzard and River sand with only one

exception. Although the use of bentonite contributed significantly to the scattering of


the results, it is, however, apparent that for design calculation the lower bound

should be adopted taking into consideration the amount of the overcut and the

particle size distribution of the surrounding material. The calculated jacking forces
presented in Tables 7.11, 7.12 and 7.13 are based on the assumption of H lying on

the line R=0.03 . This will provide a conservative estimate for jacking forces.

It can be concluded from the above comparison of results that the jacking forces can
be considerably reduced by the use of force reduction techniques such as bentonite

207
Chapter 7 Interpretation oJThe Results

lubrication and overcut . Despite the somewhat variable differences in the jacking

forces at certain points, the graphs showed a similarity in the trends between the

practical and theoretical results in tenus of rate of increase in the jacking forces. It is

also apparent from this study that the Loughborough Method can provide relevant

data from which to calculate upperbound predictions of the jacking forces, and that

the values thus calculated could be reduced to allow for other force reducing
Applying an
measures, such as lubrication .. 1',.) approximately 50% reduction in the calculated
produces values that equate to ;
theoretical forces "'. -~ the average reduction that can be achieved when

using bentonite.

It is worth mentioning that the theoretical values obtained by using equation 7.5

produced greater forces than equation 7.6. This is because equation 7.5 takes into

account the continuous peak interface resistance along the surface area of the pipeline,

whereas this normally reduces to lower values depending on the normal stresses and soil

arching around the pipeline. However, this equation may be valid for short drives
with no overcut ratio and in. unstable surrounding material, such as loose sand.

208
Chapter 7 Interpretation of The Results

7.5.2 M1·A1 SCHEME

A 2.4m diameter culvert was constructed approximately l.Om below ground level by

pipe jacking to serve as a passage for a stream underneath a 7.Sm high embankment,

which allows widening of the existing embankment to accommodate a new dual

carriageway as part of the Ml-Al scheme.

7.5.2.1 Geology and Ground Conditions

The geological records of the area, based on boreho1es, indicate the site to be

underlain by Oxford Clay to a depth of approximately 10m below the existing

ground level. The geological succession of strata in the vicinity of the pipejack area

is shown in Figure 7.31 and can be summarised as follows:-

i- MADEGROUND (7m height of embankment above G.L, extending to O.SOm


belowG.L)

Firm dark brown silty CLAY with occasional rounded gravel.

ii- GLACIAL TILL (O.SOm to l.S0m below G.L)

Firm dark brown, becoming brown, sandy CLAY with some gravel.

iii- FLUVIOGLACIAL DEPOSITS (1.S0m to 3.0m below G.L)

Brown angular to rounded clayey silly sandy to very sandy GRAVEL, lo<;ally very
clayey.

iv- OXFORD CLAY (3.0Om to end of Borehole)

209
Chapter 7 Interpretation oJThe Results

Firm light green grey, extremely closely fissured CLAY, locally very silty with

occasional shells.

No groundwater was encountered in the boreholes or during the jacking operation.

7.5.2.2 Pipejack Details

The jacking pipes were manufactured in accordance with B.S 5911, part 120 (BSI,

1984) and had the following characteristics:

External diameter: 2865mm

Internal diameter: 2375mm

Each pipe is 2.5m in length and can withstand 1200 T uniformly

distributed and 1000 T deflected loading.

The pipe jacking operation was carried out by means of manual face excavation. The

size of the jacking pit was designed to be large enough to accommodate six 300 T

jacks which were powered by a diesel power pack. A concrete base was constructed

in the shaft to locate two guide rails, parallel to line and on pipe gradient, to ensure

correct entry of the shield. The thrust wall was cast in concrete at the back of the pit

to distribute the jacking forces. A steel plate was placed against the thrust wall to

distribute point loading from the main jacks, which were positioned in the pit parallel

to line and on gradient below the axis level of the pipe . An air winch was fixed

between the jacks for operation of the muck skip. A steel thrust ring was fixed at the

end of the jacks to protect the concrete pipes and distribute the pushing forces from

the main jacks via spacer blocks onto the jacking pipes. Excavation was carried out

from within the shield and the pipes were jacked behind the excavated area. No

210
Chapter 7 Interpretation oJThe Results

bentonite lubrication was used.

7.5.2.3 Jacking Forces

The jacking forces encountered during the operation were recorded at the end of each

pipe driven into the tunnel. These forces were then plotted against the jacking

distance as shown in Figure 7.32 .

The theoretical jacking forces, based on the Loughborough Method, were calculated

using equation 7.6 , with jacking parameters obtained from Figure 7.3. The jacking

parameters were based on the soil and geotechnical information from the bore holes

and site investigation . The results used for the Loughborough Method for

calculating the jacking forces are summarised in Table 7.14 .

Table 7.14 Jacking Forces Calculated According to the Loughborough Method


Jacking Jacking Force (kN)
Soil Type Depth H Distance Eau. 7.6
(m) Equ.7.5
(m) Part Cum
ll. ill 1 12 17 1836 1836 600
H. ill 4 15 14.5 1834 3670 2048
H. ill 7.5 16 18 2429 6099 3889
II 4 15 17.5 2363 8462 2048

Note: Cum. stands for Cumulative Force.

The theoretical forces show little sensitivity to the depth of the tunnel

211
Chapter 7 Int€1pretatton of11te Results

7.5.2.4 . Conclusions

It can be seen from Figure 7.32 that the measured jacking forces are approximately

44% lower than those obtained from the Loughborough Method. The practical curve

shows that relatively large forces were required over the early part of the drive,

where the cover depth was relatively small. This can be explained by the large

tunnel diameter (2Am) which would cause a high face resistance to be generated.

Early misalignment could also account for higher early force requirements. It should

be noted that the values used to calculate H were obtained from Figure 7.3 and

related to the height of cover, which in this case are approximately 5 kPa, 10 kPa

and 12 kPa . The value of H is only an estimated value, depending on the unifonnity

coefficient of the material .

The major factor that is likely to contribute to the difference between the results,

however, is the fundamental difference between the ground conditions on this site

and the sands used in the laboratory modelling work. In addition to this the ground

conditions varied over the length of the drive. As shown in Figure 7.31 the top half

of the pipeline is in the cohesive Glacial Till, which will allow the material to stand

up during excavation and hence reduce the forces on the pipeline. This is clearly

reflected in the forces shown in Figure 7.32 . Thus the results for sand can only

provide an upperbound prediction in the case of competent clay. A very soft, weak

alluvium might be better modelled by sand data, and indeed might produce higher

results due to no facility for arching.

212
Chapter 7 InterpretatiDn of The Results

7.5.3 PREVIOUS STUDIES

This section examines the previously published practical and theoretical work in

relation to the results of this research project, referred to herein as the

Loughborough Method.

7.5.3.1 CIRIA Technical Note 112

The CIRIA Technical Note (Craig,1983) provides a method of empirical prediction

of pipe jacking forces based on the direct experience of contractors (see Section
2.4.2.1) .

Table 7.15 gives the empirical values for the V.K. , expressed as drag per unit area,

with the corresponding values obtained from the Loughborough Method for similar

soils.

For the wet sand, the Loughborough values seem to be reasonably close to the limits

of the empirical values. The minimum value of 8.5kN/m2, which was obtained from

an overburden pressure (q) of lOOkPa, falls below the lower limit, while the higher

value falls within the empirical range. However bearing in mind the approximate

nature of the empirical data, the correlation can be considered good. It could also be

concluded that the empirical values overestimate the drag forces by ignoring the

effect of the overburden pressure, and thus drag forces significantly lower than the

empirical values may be obtained for low overburden pressures. It should be noted,
however, that the description of wet sand is very broad, and therefore covers a

variety of sands and water saturation conditions from merely damp to sands below

213
Chapter 7 Interpretation oJ1he Results

the water table. A further point of conjecture is that the values quoted appear to

account also for face resistance, being global factors, For the dry loose sand the

situation is similar to the wet sand, the empirical values overestimating the jacking

forces . It can be concluded, therefore that the empirical values may be used as a

guide, and allowance should be made for the depth of the pipeline or the overburden

pressure applied to it when estimating the jacking forces.

Table 7.15 Comparison between the UK Empirical Skin Friction Values and

those Calculated using the Loughborough Method


SKIN FRICTION (kN/m2 )
SOIL TYPE
EMPIRICAL VALUES LOUGHBOROUGH VALUES
R=Q q =100 q = 200
Rock 2 to 3
Boulder Clay 5 to 18
Firm Clay 5 to 20
Wet Sand 10 to 15 Well-graded 8.5 13.5
(Wet Sand)
Silt 5 to 20
Dry Loose Sand 25 to 45 Uniform 16.0 28.5
(Dry Sand)
Fill uptp 45

Table 7.16 compares the frictional values of various countries with those from the

Loughborough Method for similar soil conditions. Once again the Loughborough

results are shown to be of the correct order of magnitude and similar explanationsto

those applied to the U.K. values may be used for this case. It should be reiterated

that the overburden pressure, or the depth of the pipeline, should be considered

when calculating to the frictional resistance in practice.

214
Chapter 7 Interpretatcon of The Results

Table 7.16 Comparison of Frictional Resistance from Various Countries with


those Calculated using the Loughborough Method
FRlCTIONAL VALUE (kN/m 2)
SOIL1YPE
Australia France Germany Loughborough
R=O. q=200

Shale 1
Clay 5 to 7.5 8 to 10 5
Silt 17
Sand 13 20 to 30 28.5 13.5
DIY Wet
Compacted Gravel 50 50

7.5.3.2 Herzog's Investigations

Herzog (1985) investigated the jacking forces in medium dense sand, see Section
2.4.2.5 . In order to compare the results of Herzog's analysis and the

Loughborough Method, the data for case study 2 (the 2.4m Culvert on the M1-Al
Link) will be used as an example due to similar pipe conditions. It should be noted,
however, that the results from the clay on this site will be very different to those
experienced by Herzog, and thus the comparison remains artificial and the lack of
correlation with the measured data should not be considered to be significant. The
calculation data are :

B=2865 mm

D= 7.Sm embankment with an average height on the slope of 4m .

L=67m

r= 19 kN/m3

215
Chapter 7 InterpretatiOn of1he Results

Based on Herzog's method, the values of the following equations are all summarised

in Table 7.17

Skin friction Pv---y(D+B/2)

Face resistance PsI = P 1t Dt

The calculationsfor the Loughborough Method are based on equation 7.6, as above,

and the forces are shown in Table 7.17 .

F=H ltBL (7.6)

Table 7.17 Summary of the Jacking Force Results


Herzog Method Loughborough Method
Depth Jacking Actual
(m) Distance Pm Ps Jacking Force
(m) (kN) (kN) H Force (m)
(kN)

1 17 4516 301 12 1836 1463


4 14.5 8756 669 15 1834 366
7.5 18 17872 1098 16 2429 1390
4 17.5 10567 669 15 2363 1902

216
Chapter 7 Interpretation of The Results

The statistical analysis by Herzog is mainly based on observations of large jacking


pipes, since all of the examples given in his paper refer to large diameter sewer

pipes well in excess of 2.5m . The study of these examples, with heavy self-weight

of the pipes and abnormal face resistance, appears to cause excessive forces when
calculating the jacking forces using his formulae. Herzog's method should thus be

used only with extreme care.

7.5.3.3 Methods reported by Stein, Mollers and Bielecki

The information used in this example is obtained from the reference book entitled
MicrotunneIling (Stein et al,1989), which describes several force prediction
methods.

The jacking forces calculated using the Japanese analysis are assumed to be a linear

function of the jacking distance (p. 51) . The given example, which is reproduced in

Figure 2.17, shows a linear relationship between the jacking forces and the driven
distance for various pipeline depths of 3, 5, 7 and 9 m . The surrounding material

for this case is cohesionless with the following soil and jacking parameters:

Soil type: Sand

<I> =35 0

Coefficient of friction = 0.32

External pipe diameter = 0.7 52 m

Using the above parameters, the values of the jacking forces can be calculated by the
Loughborough Method as shown below:

217
Chapter 7 Interpretation oJThe Results

Soil type: Sand

Y= 20 kN/m 3
K = tan (35/3)= 0.2

H = 12, 16, 17 and 18 (forD = 3, 5, 7 and 9m respectively)

F = H 1t B L ----------- 7.6

The jacking force' results are summarised in Table 7.18 and presented in Figure
7.33.

Table 7.18 Summary of the Jacking Forces


Jacking
Depth H Distance Jacking Force
(m) (m) (kNI

3 12 200 5669
5 16 200 7560
7 17 200 8032
9 18 200 8505

The comparison shows that the Loughborough Method gives slightly higher values

than the Japanese method, although the rate of increase in the jacking forces is
necessarily similar for each depth. Hard conclusions are difficult to draw since no

information on the consideration given to the effect of the overcut ratio on the jacking
forces when using the Japanese method is available. The consistency of the two
methods is encouraging, however.

218
Chapter 7 InterpretatiOn of The Results

Weber (1981), in his investigation into pipe jacking of 'non-man-entry' pipes


established the linear increase of the jacking forces required with an increase of the
skin area, or jacking distance. The results of his investigations are presented in

Figure 7.34, with skin friction of each line related to the height of the soil cover
above the pipeline.

Figure 7.34 shows the comparison between Weber's relationship and the values
obtained from the Loughborough Method. The soil material used by Weber has
similar parameters to the river sand. It seems that Weber's explanation of different
skin friction is not very clear, and only provides a guideline based on previous
practical experience. The results of the Loughborough Method, as shown in Figure
7.34, give the skin friction of a particular soil at different overburden pressures of

10,100 and 200 kN/m2 (equating to LM=3.7, 43.1 and 67.0 kN/m2 respectively on
the graph) . It is apparent that the higher the overburden pressure is, the larger the

skin friction that is generated during the jacking operation, a fact recognised by
Weber's prediction although his values are consistently lower than those of the
Loughborough Method. This presumably means that Weber's method reflects a
much greater influence of arching, or other force reduction effects.

7.5.3.4 Work by Auld

Auld in 1982 put forward a frictional resistance equation to calculate the frictional
forces needed for a pipeline during a jacking operation. His analysis and the
derivation of the equation are fully explained in Section 2.4.2.2 .

219
Chapter 7 Interpretation oJT11e Results

.An example taken from his paper (Auld, 1982) is used to compare his analysis with

the Loughborough Method. This example involves a circular pipe jacked through a

sandy GRAVEL material . Figure 7.35 shows a cross-section and the ground

conditions for the jacking operation. The comparison between the two methods is

summarised in Table 7.19.

For the Loughborough Method, the following data were used:

F = H 1t B L --------- 7.6

Compacted sandy Gravel with,

r=18 kN/m3 and <jl =40 0

K=tan (40/3) =0.237


H=34 for pipeline depth of (D)=7.6m from Figure 7.3 at R=O
H=19 for pipeline depth of (D)=5.1m from Figure 7.3 at R=O
B=2Am

For section 2,

F = 34"2.4"26" 1t = 6665 kN

For sections I and 3

F = 19"2.4"17" 1t = 2435 kN

Total jacking force = 2435 + 6665 + 2435 = II535 kN

220
Chapter 7 Interpretatton of The Results

Table 7.19 Comparison between the Auld and Loughborough Jacking Forces

Jacking Force (kN) Auld Calculation ~oughborough Method

Section 1 1597 2435


Section 2 4504 6665
Section 3 2610 2435
Face Resistance 3920
Total Jacking Force 12631 11535
Actual Jacking Force 11760 11760

It appears that the actual measured jacking force, according to Auld, is greater by

2% than that predicted by the Loughborough Method, while the Auld method gives a

value that is lower by 7% . Auld's assumption for the face resistance considerably

affected the overall value of the jacking force calculated by his method, whereas no

allowance has been made in the Loughborough Method . It is apparent that the

Loughborough Method is comparatively close to the practical value, although the

value was calculated using the line of R=O for the River sand in Figure 7.3, which

was considered to provide a suitable H value for the type of material used in equation

7.6 taking into account the higher value of <I> than the River Sand. This was thus a
subjective judgement.

7.5.4 CONCLUDING DISCUSSION

In order to establish the importance of the Loughborough Method, the H values

obtained from practical data in the case studies are plotted on Figure 7.3 for concrete

pipes for both types of sands in Figures 7.36 and 7.37, which show the re-analysed

values of the case studies in a linear fashion. It appears that all the values lie at the

221
Chapter 7 Interpretation ofTh.e Results

lower limit of Loughborough Method, with the exception of Herzog's method. The
rate of increase in the H value for R=O.030 compares well with the MI-Al and the

Japanese results, but the values lie below the R=O.030 line and thus it can be
assumed that the Loughborough Method provides conservative results. However, it
is apparent that the rate of increase of Herzog's line is approximately the same as for
the upperbound of Loughborough Method in Leighton Buzzard sand, although the
line is significantly above the Loughborough upperbound values . Herzog's
approach may prove to be correct for angular single size, perhaps large particles
where no force reduction techniques are used. It is also important to bear in mind
the effect of overcut ratio when using the Loughborough Method, as there is no
indication of whether greater or lesser overcut ratios than R=O.030 would produce
minimum H values. Obviously, further research into this area is needed to clarify

this uncertainty.

In conclusion, the Loughborough Method has been shown to produce generally


good results due to the rational consideration of the influence of various jacking
parameters in the model study. The development of the Loughborough equation,
using the scale model testing results, accounted for a combination of the depth
(overburden pressure), jacking distance, external diameter of the pipeline and the

overcut ratio and it is apparent from the above analyses that these factors should all
be taken into account if an accurate prediction is to result .

222
100 r-------------------------------__________,
l:l Concrete Pipes
80 • Steel Pipes

'"
"'" 60
~'iU
~~
:g~
40
"
~
l:l
• •
20 • ~=4.6

<1>=8.5

0
0 50 100 150 200

Surcharge (kPa)

a- confined state for Leighton


Buzzard Sand

50

l:l Concrete Pipes <1>=9.6


40 • Steel Pipes $=3.8

e''""
...(/)'iU 30

"OIl"-
=.>1
:g~

20 •
~"
•• $=3.6

10
~=4.0

0
0 50 100 150 200
Surcharge (kPa)
b- confined state,Jor River Sand
Note: All values of <p quoted In the graphs are In degrees

Figure 7.1 Jacking Stress Against Overburden Pressure: Confined State


50 r-----------------------------~--------_,
!:l Concrete Pipes ~=59
$=45
40 • Steel Pipes

.,
<Il 30
"
./:l
CIl(i
'O.O~
~~ 20
~"

10

o 2 4 6 8 10 12

Soil Cover (kPa)

c- unconfined state for Lelghton Buzzard Sand

20

[:J Concrete Pipes $=41

15 • Steel Pipes $=34

.,
In
O.l
./:l
CIl(i 10
~~
ll~

~"
5


0
0 2 4 6 8 10 12

SoU Cover (kPa)

d- unconfined state for River Sand


Note: All values of <jl quoted In the graphs are In degrees

Figure 7.1 Jacklni( Stress Against Overburden Pressure: Unconflned


State (Soil Cover)
o
0.0 0.5 1.0 1.5
Surface Area (Square metre)

a· concrete pipes

30

J::] q·lCkPa IR=O I


X q·lCOkPa

20
• q·200kPa

~ H=11.4
-.
~
u
~
'011
I':
:illu 10
~

OL-__ ~~ __ ~ ____ ~ ____ ~ ____ ~ ____ ~

0.0 0.5 1.0 1.5


Surface Area (Square metre)

b· steel pipes
Figure 7.2 Jacking Forces Against Surface Area· Lelghton Buzzard Sand
50

8 q-lOkPa IR=O I
X q-lOOkPa
40

• q-200kPa

~ 30
"~
~
...
.s 20
X

~
.!J
10

H=2.3
0 '8
0.0 0.5 1.0 1.5

Surface Area (Square metre)

c- concrete pipes

20

~ q- 10kPa I R=O I
• q- 100kPa
• q- 200kPa

11
~
"".. 10
~
~
liI
.,
~

H=1.44

o
0.0 0.5 1.0 1.5

Surface Area (Square metre)

d- steel pipes

Figure 7.2 Jacking Forces Against Surface Area - River Sand


100
[;] R=O.OOO Lelghton Buzzard Sand
Concrete Pipes
80 • R=0.030

•<> R=0.064

R=O.140

60

D
40

OL-____ ~ ____ ~ ____ ~ ____ ~ ____ ~ ____ ~

o 100 200 300

a Surcharge (kPa)

100

D R=O.OO River Sand


Concrete Pipes
80 • R=O.030

• R=O.064

60

J:

40

O~ ____ ~ ____ ~ ____ ~ ____ ~ ____ ~ __ ~

o 100 200 300

Surcharge (kPa)

Figure 7.3 H values against Surcharge for Concrete Pipes


20
J:I R=0.016 Leighton Buzzard Sand
Steel Pipes
• R=0.048
15 • R=O.084

10

o L-____ ~ ____L __ _ _ _ ~ _ _ _ _L __ _ _ _ ~ __ ~

o lOO 200 300

Surcharge (kPa)

25r-------------~======~~~===n
River Sand I;] R=O.oo
Steel Pipes 0 R=0.016
• R=0.048
20 <> o R=0.084

15

10

o
o 100 200 300

Surcharge (kPa)

Figure 7.3(contlnued) H Values against Surcharge for Steel Pipes


14
Unconfined Confined
12

10 G Salomo

• Scherle

~~
8 () We'rer
LBS/Con.
•*
~" 6
~ii: LBS/Steel
&I
4 0 RS/Con.
.4 RS/Steel
2

0
0 2 4 6 8

D/B

Figure 7.4 Relative Skin Friction against D IB Ratio for Results


of Model Testing and Theoretical Predictions
100
Concrete Pipes
0/8=3.75
R=O
80
-0- q = 10 kPa

.....
~
"~
60 ... q=100kPa
q = 200 kPa

~
~ 40
:g
u
;g
20

o
0.0 0.2 0.4 0.6 0.8 1.0

X/L

20
Steel Pipes
0/8=3.75
R=0.016

15 -0- q = 10 kPa
..... q = 100 kPa
~ q =200 kPa
"..u ---
.
0
r..
.5
~
10

.,=
u

o L-__ ~ __L-__~__L-__~__~__~__~__~~

0.0 0.2 0.4 0.6 0.8 1.0

X/L

Figure 7.5 The difference In the rate of frictional Increase between


R=O and R=O.016
50

40
~~ [;] [;] [;] [;] [;] [;] [;] [;] [;] 13 13
O~El
(;]

.. 0"...... ~ Leighton Buzzard sand


~

1'00 30 O. I Surcharge=50 kPa


El ModeVConcrete
""'"
~

• [;]

,•
~ ModeVSteel
l:: 0
"'.
.... 0 Lab./Concrete
.. 20 • ~
.c • • • •• Lab./Steel
'" 0

• • • •••• • • • •
10
l!J

~
0
0 10 20 30 40

Displacement (mm)

20 ~---------- __________________________--,

15 _

~
""ill.
~

-'"......... 10 f-


.c
'" ~~ •
River sand
Surcharge=lO kPa

5 -.~ El ModeVConcrete
• ModeVSteel
~<> • Q LabJConcrete

o !... I I
Lab./Steel
o 10 20 30 40

Displacement (mm)

Figure 7.6 The Shear Stress-Displacement Relationship


between Laboratory and Model Testing
30

-0- Lab. Soil/Soil

...
.....
-0-
Lab. Soil/1nl
Model/Rough
Model/Smooth
20
~
~

.e
la
rtl
!il
"
.c:
rtl
10

q=lO kPa
Concrete Pipes
Le hton Buzzard Sand
0
0 5 10 15 20

Displacement (mm)
Figure 7.7 Graph of Shear Stress against DISplacement for Soil/ Concrete
Interface Tests and Concrete Pipes tn Lelghton Buzzard Sand
at a Surface Surcharge of 10 kPa .

20
q=lO kPa
Concrete Pipes
River Sand
15

~.
....e
rtl
10

"=
"
.c:
rtl
5
Lab. Soil/Soil
Lab. SoU/1nl
Model/Rough
Model/Smooth
o~ __ ~ __ ~ ____ ~ __ ~ __ ~ ____ ~ __ ~ __ ~

o 5 10 15 20

Displacement (mm)

Figure 7.8 Graph of Shear Stress against Displacement for Soil/Concrete


Interface Tests and Concrete Pipes In Concrete River Sand
at a Surface Surcharge of 10 kPa .
6°rl~------------~========~1
q=50 kPa
Concrete pipes
50 Leighton Buzzard Sand

40

30

20

-a- Lab. Soil/Soil


10 .... Lab. Soil/1nl.
... Model/Con.Rough
-0- Model/Con.Smooth

o 5 10 15 20 25 30

Displacement (mm)
Figure 7.9 Graph of Shear Stress against Displacement for Soil/Concrete
Interface Tests and Concrete Pipes in Leighton Buzzard Sand
at a Surface Surcharge of 50 kPa .

50 r---------------------------------------,
q=50 kPa
Concrete Pipes
40 River Sand

30

20

-- Lab. Soil/Soil
10 .... Lab. Soil/1nl.
-- Model/Rough
..... Model/Smooth

o~~~----~--~----~--~
o 5
____ __ ~ ~~~
10 15 20
Displacement (mm)

Figure 7.10 Graph of Shear Stress against Displacement for Soil/Concrete


Interface Tests and Concrete Pipes in Concrete River Sand
at a Surface Surcharge of 50 kPa .
2°r-~==========~------------1
q= 10 kPa
Steel Pipes
Lelghton Buzzard Sand
15

10

5
~ Lab.Soil/Soil
.... Lab. Soil/lnt.
.. Model/Steel

o 5 10 15 20

Displacement (mm)

Figure 7.11 Graph of Shear Stress against Displacement for Soil/Steel


Interface Tests and Steel Pipes in Leighton Buzzard Sand
at a Surface Surcharge of 10 kPa .
20
q= 10 kPa
Steel Pipes
River Sand
15

'2
p.,
t!
III
III
10
...t::
(/J

"...
.=
(/J
5
~ Lab.Soll/Soll
... Lab. Soll/Int.
.... Model/Steel

o 5 10 15 20

Displacement (mm)

Figure 7.12 Graph of Shear Stress against Displacement for Soil/Steel


Interface Tests and Steel Pipes in Concrete River Sand
at a Surface Surcharge of 10 kPa .
60
q=50 kPa
Steel Pipes
50 Leighton Buzzard Sand

Lab. SoU/SoU
'2 40 Lab. Soil/lnt.
Model/Steel
-:l
~
I /l
30
~
.
<IS
~ 20
<IJ

10

0
0 5 10 15 20

Displacement (mm)

Figure 7.13 Graph of Shear Stress against Displacement for Soil/Steel


Interface Tests and Steel Pipes In Leighton Buzzard Sand
at a Surface Surcharge of 50 kPa .

50r---------------------~~~~
q=50 kPa
Steel Pipes
River Sand
40
-c- Lab. Soil/Soil
.... Lab. Soil/lnt.
30 ..... Model/Steel

20

10

O~~~----~--~--~----~--~----~
o 5 10 15
__ ~
20

Displacement (mm)

Figure 7.14 Graph of Shear Stress against Displacement for Soil/Steel


Interface Tests and Steel Pipes In Concrete River Sand
at a Surface Surcharge of 50 kPa .
30

q=lO kPa
Lelghton Buzzard Sand

-=..r:t ....."

20 I-
I" .
... '",
A
..:. ..:.
~
""U>
~

U>
r ... ~
A

2! ~

1ii
~
IV
~.
'- - --- - •
"
J:
(/)
10
~

-Q- Rough
~

o ~ I I I I
...
-+-

-,-
Smooth
Steel
I
o 20 40 60 80 100 120

Displacement (mm)

Figure 7.15 The Effect of Pipe Joints and Surface Roughness for Pipes
in Lelghton Buzzard Sand with a Suzface Surcharge of 10 kPa .

30

-0- Rough
q=lO kPa
River Sand -+- Smooth
...... Steel
20
"iO
a.
'"
~

U>
U>
2!
Iii
~

m
.<: 10
(/)

o 20 40 60 80 100 120

Displacement (mm)

Figure 7.16 The Effect of Pipe Joints and Surface Roughness for Pipes
in Concrete River Sand with a Suzface Surcharge of 10 kPa .
40
q=50 kPa
Lelghton Buzzard Sand
..,.
30 I-
( .:...
-.:r
..,.
'I~
""
~

&.
'"
~
., -y
.....

""i!! 20 1-..
1ii
~
~
ca
"
..c:
VI
10
.-
-0- Rough

o I I I I
...
...... Smooth
Steel

o 20 40 60 80 100 120

Displacement (mm)
Figure 7.17 The Effect of Pipe Joints and Surface Roughness for Pipes
In Lelghton Buzzard Sand with a Surface Surcharge of 50 kPa .

40

q=50 kPa -0- Rough


River Sand
30
...... Smooth
Steel
~
ca
a.
:.
---
""i!! 20
1ii
~
ca
"
..c:
VI
10

oa-~--~~--~~--~~ __ ~~ __ ~~ __ ~

o 20 40 60 80 100 120

Displacement (mm)

Figure 7.18 The Effect of Pipe Joints and Surface Roughness for Pipes
In Concrete River Sand with a Surface Surcharge of 50 kPa .
60

'" -n
If
~

50 f-
P "'" '"

-III
Il.
40 -
.....
"'...,"

.. - ---
~

1
-..
e
(jj
30 - ~
~
T

m
.J:
U)
20 - •

q=100 kPa -0- Rough


10
Lelghton Buzzard Sand
-+- Smooth

-It- Steel

o I , I , I -'- I

o 20 40 60 80 100 120

Displacement (mm)
Figure 7.19 The Effect of Pipe Joints and Surface Roughness for Pipes
In Lelghton Buzzard Sand with a Surface Surcharge of 100 kPa .

60

q=100 kPa -0- Rough


River Sand
50 - -+- Smooth

..... Steel

-"'.,"
III
Il.
40 r

. .. .. -=
"
~

., '"
e
(jj
30 r-?",
~

m
.J:
U)
20 r(
- - - - ----
10

0
o
ri, 20
I

40 60
I I

80
I

100 120

Displacement (mm)

Figure 7.20 The Effect of Pipe Joints and Surface Roughness for Pipes
In Concrete River Sand with a Surface Surcharge of 100 kPa .
100 ~------------------ ____________________--,

80

60

q=200 kPa -8- Rough


20 Lelghton Buzzard Sand
-+- Smooth
..... Steel

o 20 40 60 80 100 120

Displacement (mm)

Figure 7.21 The Effect of Pipe Joints and Surface Roughness for Pipes
In Leighton Buzzard Sand with a Surface Surcharge of 200 kPa .

100

q=200 kPa -Cl- Rough


River Sand
Smooth
80 r- -+-
Steel

-.
c-
---
-"'e''""" 60 _

r:1. -r.tr.l-

.
US
~ 40 _ f '"
~
'" r -
.
20
- 1;1.
n
"i.V
0 , I I I I l I
0 20 40 60 80 100 120

Displacement (mm)

Figure 7.22 The Effect of Pipe Jotnts and Surface Roughness for Pipes
In Concrete River Sand with a Surface Surcharge of 200 kPa .
lOO
ILelghton Buzzard Sand I
80 Concrete Rough
•'" Concrete Smooth
• steel

~ 60

..
eft
VI
"
...
~
en 40

en"
.cl

20

o L-__~__~__~~__~__~__~____L-~
o 50 lOO ISO 200

Surcharge (kPal
Figure 7.23 Graph of Shear Stresses against Surcharge for Rough
and Smooth Jointed Pipes in Lelghton Buzzard Sand.

lOO

IRiver Sand
80 I!I Concrete Rough
• Concrete Smooth .
• Steel
~ 60
~
~
2
..~.
~
en
40

en

20L~~~
.-
o L-__~__- L__~____~__~__~____L-~
o 50 lOO 150 200

Surcharge (kPal

Figure 7.24 Graph of Shear Stresses against Surcharge for Rough


and Smooth Jointed Pipes in Concrete River Sand.
80r---------------------~----~TI

60

III
III
Lelghton Buzzard
"
.t:~
(/JetS 40 Sand
El Lab./Concrete
:a~
"
.=
(/J •
X
Lab./Steel
Lab,/Soi!
20
0 ModeVConcrete

• Model/Steel

o 20 40 60 80 100

Normal Stress
(kPa)

50r-------------------~----~~~

40

III
III
30
River sand
"
,,~
..... etS
(/Jp..
El Lab./Concrete
",!4
etS~
20
"
.=
(/J • Lab./steel


0
Lab./Soi!
ModeVConcrete
10
• ModeVSteel

O~~ __L-~__~~__~~__~~~
o 20 40 60 80 100

Normal Stress
(kPa)

Figure 7.25 The Shear Stress-nonnal Stress Relationship


for Laboratory and Model Testing
300

Lelghton Buzzard sand


200 f- --.-
,
\
\\
100 f- \
\ River sand
r:-"., .........................................., 200 kPa
!Actual ...- .........., ........................................ .
values
• Predicted values
"':.. 10 kPa
o . ······r·.~.' .......~ ....... .......1••••••••••••••1
o 2 4 6 8 10

Unifonnity Coefficient

Figure 7.26 The Relationship Between Unifonnity Coefficient


And H Value For Sandy Granular Materials
100
Leighton Buzzard Sand [!I R=O.OOO
Concrete Pipes
• R=0.030
80

Q
R=0.064
R=0.140
+ Ew-El
60
c E2-El
X E3-E2

:r
40

20 ~~~~~~:;~~.~::~c;=~X-~x~----------~
If: CC
oL-__~__-L__~____i -__~=C__~__~__~
o 100 200 300 400

Surcharge (kPa)

100

R=O.OO
River Sand
C Concrete Pipes
80 • R=0.030


+
R=0.064
Ew-El
C E2-El
60 X E3-E2

40

+
20
X

lI' 0
+.0
0 100 200 300 400

Surcharge (kPa)
b

Figure 7.27 Site Data Plotted on H against Surcharge Graphs


for Case Study 1
20000

om- Practical
15000
....... Theoretical
Z
:.
e"
of 10000
Cl
c
:;;:
..,"
III
5000

O~--~----~--~--~--------~--~--~
o 50 100 150 200

Jacking Distance (m)


Figure 7.28 Jacking forces against distance for Ew-El drive

20000 .-------------------=----,
-G- Practical/P1
-- Practical/P2
15000
-0- TheoreticaVP 1
-0- Theoretical/P2

10000

5000

50 100 150 200


Jacking Distance (m)

Figure 7.29 Jacking forces against distance for E2-El drive

40000

-a- Practical
~ - - Theoretical
z 30000
:.
e"
of 20000
Cl
c
:;;:
..,"
III 10000

0
0 100 200 300 400
Jacking Distance (m)

Figure 7.30 Jacking forces against distance for E3-E2 drive


CL.

Jacked
2m Pipeline
Direction

4m

6m

Bm
>> >
> >
>

Figure 7.31 The Geological Strata In the Vlclnlly of the Pipe Jack on Ml·Al Link
10000 . . . - - - - - -_ _ _ _ _ _ _ _ _ _ _ _ _ _--,

Actual D=4m
8000 Theoretical

eZ., 6000
~ Toe of Emb.
~
'"
c:
32
4000

~ D=lm
_ _ _ Top of Emb.
2000
Toe of Emb.

o~-~--~-~--~-~--~-~-~
o 20 40 60 80

Jacking Distance (m)

Figure 7.32 Companson between the Theoretical and Actual Values


of Jacking Force for the MI-Al Link
O~~~~ __- L_ _- L__ ~ __~~__- L__~__~

o 50 100 150 200 250

Jacking Distance (m)

Figure 7.33 The compaIison between the Japanese and Loughborough Method

12000
-0- Weber'1=3.0kN/m2

10000
...
~

~
Weber'2=8.3kN/m2
Weber'3=13.6kN/m2
L.Ml=3.7kN/m2
8000

I::'0" --- L.M2=43.lkN/m2


-0- L.M3=67.0kN/m2
~~ 6000
~~
~
'") 4000

o 50 100 150

External Surface of Pipes (square metre)

Figure 7.34 The CompaIison between Weber's Method


and the Loughborough Method
I l7m 26m l7m

t
lOm
~~~~~~~5m
1
f Jacking
pit
f

Ground Level
IC'C(cc',',(,d Om Top soil

Gravelly
Sand
Groul!c!. ~e::el !l~ j..a~~g pit
1O.Om

t
5.Om
y =18 kN/m 3
c=O
<I> =40
0
(compacted) Sandy
Gravel

1 0
Figure 7.35 Pipe Jacking Data for Case Study Reported In Section 7.5.3.4
100
/ Lelghton Buzzard Sand

Herzo g/
/ Concrete Pipes
t:J A=O.OOO

80 ~ • A=0.030

/
/ •<> A=0.064

R=0.140
j. X Ml-A1
60 / + Japanese

/ A Herzog

40 /
/
20
I ............-.................... , ..................1:.... I
.••.•••••••-1---.............."' •.••••••••.••••••• _.. •..-••••-••••-.. -....---•••-••••-...-•••
.__...._..0+-
- .
=~ ......X_...........
X
.••••••• 2S........ __ ..·.·,·····-··········-··
'",
MI·AI
Japanese

o
o 100 200 300 400

Surcharge (kPa)
Figure 7.36 The Relationship between the Loughborogh Method's H Value and Surcharge
for the Lelghton Buzzard Sand In Comparison with the Practical Data
100

I El R=O.OO River Sand


Concrete Pipes
I • R=0.030

80 ;i I R=O.064

/ X M1-A1
4- + Japanese
,
Herzog /
60
/ Herzog

x
/
I
/
40
/
f
20
-.- . _ _.L_~~:~:~:~"---'-J:--'-
o
o 100 200 300 400

Surcharge (kPa)

Figure 7.37 The Relationship between the Loughborough Method's H value and Surcharge
for River Sand In Comparison with the Practical Data
Chapter 8 Conclusions and Future Work

CHAPTER EIGHT

8 CONCLUSIONS AND FUTURE WORK

8.1 INTRODUCTION

8.2 JACKING FORCES

8.3 THE EFFECT OF OVERCUT RATIO

8.4 PIPE/SOIL INTERFACE AND JACKING FORCES

8.5 PIPE JOINTS

8.6 RECOMMENDATIONS FOR FUTURE WORK

223
ChapterS Conclusions and Future Work

8 CONCLUSIONS ANP FUTURE WORK

8.1 INTRODUCTION

A comprehensive review of the literature was conducted and the need for an

understanding of the behaviour of jacking forces under different influencing

parameters using scale model testing was established. A scale model test facility has

been developed, together with appropriate experimental procedures to test the scale

model steel and concrete jacking pipes manufactured to simulate those used in
practice.

8.2 JACKING FORCES

Based on the results of this research, it was found that the jacking forces are
influenced by a number of parameters. These include the overburden pressure,

overcut ratio, pipe diameter, jacking length and the influence of the surroundiIig

material. This was fully demonstrated by establishing an equation for calculating the

jacking forces. The equation is denoted the Loughborough Method and is given by

F=H1tBL

Factor H is obtained from the relationships between various parameters which were

established from the scale model testing during this research. It must be stressed that

this equation is most suitable for cohesionless, rather than the cohesive, soils as a

result·. of its genesis. Funher research is required in order to define H for different

224
Chapter 8 Conclusions and Futw"e Work

(in tenns of particle size, size distribution and particle shape and roughness) granular

soils and to detennine H for cohesive soils to enable the Loughborough Method to

predict the jacking forces for most practical cases.

By comparing the jacking forces reported herein with previous research and existing

theories, the following may be concluded:

1. The results have shown a linear relationship between the jacking forces and the

overburden pressure, and the rate at which the jacking forces increase is dependent

on the soil surrounding the pipeline and the type of pipe surface. It was found that

the jacking forces in the angular, single sized Leighton Buzzard sand are 1.5 to 2.0

and 1.3 to 2.0 times greater than the rounded, well-graded river sand for concrete

and steel pipes respectively. The difference in the results exhibits a similarity in

trend with the empirical values given in Craig (1983), and the jacking resistance

values reported by Herzog (1985) .

2. The empirical values of the jacking resistance given by Craig (1983) are

apparently conservative. Loughborough values have shown the frictional resistance

for wet sand to lie in a range of 8.5 to 13.5 kN/m2 for an overburden pressure of

100 and 200 kPa respectively, compared with empirical values of 10 to15 kN/m2 .

Thus good agreement exists here. The medium dense dry sand used during testing

produced frictional forces of 16.0 to 28.5 kN/m2 for 100 and 200 kPa overburden,

compared with empirical values of 15 to 45 kN/m2 for a loose dry sand. It is

appreciated, however, that loose dry sand would be subject to collapse settlement,

and thus a breakdown of any arching in the material would occur raising the forces

accordingly.

225
ChapterS Conclusions and Future Work

3. A linear relationship has been established between the jacking forces and the

jacking distance. This has provided the frictional resistance (kN/m) per metre length
as shown in Table 7.6 . The rate of increase of jacking forces with distance shows a

good agreement when compared with the Japanese method reported by Stein et al

(1990), as has been illustrated in Section 7.5.3.3 .

8.3 OVERCUT RATIO

Little investigation has been carried out on the effect of overcut ratio on jacking

forces until the commencement of this research work. Its influence on the magnitude

of the jacking forces is demonstrated by a series of test results ,shown in Figure

6.11 and described in Sections 6.4.2 and 7.3.1. The following conclusions can be
drawn from this investigation:

1. The results for both concrete and steel pipes showed that the forces reduce to a

minimum at an overcut ratio of approximately 0.04 in both types of sands at a

typical overburden pressure of 100 kPa, although at 200 kPa the values reduced still

further at an overcut ratio of approximately 0.05 . The scale effects of particle size

should be taken into consideration when translating the results to practice, although

the indications of other scale model studies are that the influence of particle size is
small. It should be noted that exaggerated overcut ratios were used in this research

project and that better definitions of the minima could be achieved by studying values
of overcut less than 0.030 .

226
ChapterS Conclusions and Future Work

2. The effect of the overcut ratio on the jacking forces may be applied to the

Loughborough Method as a percentage factor, determined from the results shown in

Figure 6.11 . Table 8.1 provides a guideline for the overcut ratio percentages that are

used in the Loughborough Method to predict jacking resistances where overcut is

applied during the jacking operation . It should be noted that these values are

necessarily approximate due to the imprecise definition of the curve, but nevertheless

they provide the first information of this kind in the public domain. The values for

an overburden pressure of 10 kPa have not been included since the sand surface was

unconfined and the results are thus likely to be misleading ~

3. The application of the overcut ratio percentage factors to the calculated jacking
forces values, using the Loughborough Method in conjunction with Figure 7.3,

showed good agreement with measured jacking forces in practice, as shown in

Section 7.5 . Therefore variation in overcut ratios in practice to considerably reduce

jacking resistance could thus be considered where surface settlement is not critical.

227
ChapterS Conclusions and Future Work

Table 8.1 Overcut Ratio percentage


Overcut Ratio Overburden Pressure
% q=100 kPa q=200 kPa

0.000 0 0
0.005 77 73
0.010 60 54
0.015 47 38
0.020 40 29
0.025 33 25
0.030 31 23
0.035 30 22
0.040 30 22
0.045 30 21
0.050 30 19

a- Lelghton Buzzard sand

Overcut Ratio Overburden Pressure


% q=100 kPa q=200 kPa

0.000 0 0
0.005 95 88
0.010 89 76
0.015 84 68
0.020 82 62
0.025 78 56
0.030 77 52
0.035 76 49
0.040 75 48
0.045 75 44
0.050 75 41

b- River sand

228
ChapterS Conclusions and Future Work

8.4 PIPE/SOIL INTERFACE AND JACKING FORCES

Laboratory tests were carried out to detennine the effect of the pipe/soil interface on

the jacking forces, using· shear box.· tests between the soil and pipeline surface.

Craig (1983) concluded that in granular soils the shear plane lies between the soil
particles and the pipeline surface, while in cohesive ground it may well be 5 to
10mm from the pipe/soil interface. The results of this work confmned the fonner
statement, the following conclusion being reached.

1. The worst possible values were obtained when the pipeline was in full contact
soil,
with the surrounding"and where no facility for dilation prior to shearing was present

(excepting that at the face during excavation) as in the case of zero overcut

ratio. The steel interface with both types of soil shows a decrease of 60% when
compared with the concrete interface.

2. The angle of frictional resistance between the pipeline and the surrounding soil is

approximately 0.3 to 0.5 times the internal angle of friction of the soil. This has

been accounted for by the Kt value from the relationship shown in Figure 7.1 .

3. The jacking force per unit surface area of pipe, denoted H, can be determined for
cohesionless soils from Figure 7.3 . The value of H may then be used to predict

jacking forces using the Loughborough Method. It appears that the H value can be

estimated from this relationship with reasonable accuracy if the U nifonnity


Coefficient of the cohesionless soil is known, although further research into this

relationship is necessary .

229
Chapter 8 Conclusions and Future Work

8.5 PIPE JOINTS

The type of joints between jacking pipes has a considemble influence on the jacking
forces for a jacked pipeline. This research has shown that the rough joints of the
concrete pipeline produced forces that were approximately 65% greater than the
smooth types, for both types of sand. This was well-demonstrated for an overcut
ratio of zero, where full surface contact exists between the pipeline and the
undisturbed surrounding soil. The resistance is generated from the disturbance of
the soil mass surrounding the pipeline as the joints move forwards, attributed to
small zones of bearing failure around each joint, which effectively force the shear
plane at these points into the soil body. Table 7.7 presents the magnitude of jacking

force that is needed to overcome the resistance per metre run for both smooth and
rough joints in both sands.

It can thus be concluded that the type of the joints in a pipeline contribute
significantly to the magnitude of the resistance between the pipeline and the
surrounding soil. Further research may be required to establish the extent of the
effect of the type of joints on the frictional resistance.

230
Chapter 8 Conclusions and Future Work

8.6 RECOMMENDATIONSFOR FUTURE WORK

The basic philosophy of the scale model testing was to identify the factors that

influence pipe jacking forces in sand and detennine their relative contributions. This
enabled a predictive equation to be developed. As with any project, the research
work acts as a feasibility study for any further model testing on pipe jacking, and the
equipment development and experimental procedures described herein should be
considered carefully.

The test results show an interesting relationship between the Loughborough


Method's constants, in particular the H value, with the overcut ratio and uniformity
coefficient of each type of sand. The re-analysis of the case studies compared well
with the theoretical work as presented in Figures 7.27,7.36 and 7.37 and show that
the H values lie in the lowerbound region without taking into account the actual
overcut ratio. Therefore, further investigation is required to predict the lowerbound
line of R in Figure 7.3 . As different granular materials have different uniformity
coefficients, it is therefore necessary to establish a precise relationship between the H
value and the uniformity coefficient. Such research will provide a more accurate
method of estimating the H values and hence the jacking forces. It will also be
useful to research into various types of gravels to establish their frictional resistance
and the behaviour of the Loughborough constants . Similar research can be
conducted using cohesive soils consolidated from a slurry as a jacking medium.
Different types of clays can be used to establish their constants and perhaps to
examine the validity of Loughborough Method for cohesive soils, where 'stand up'

effects will be important . In addition, study into correlating site data with
experimental work will be essential if the site material is well-characterised.

231
Chapter 8 Conclusions and Future Work

Further development of methods of establishing the granular friction characteristics

of soils in the laboratory is important for estimating the jacking forces, both as

soil/soil friction and more importantly, soil/pipeline interface friction. Such

development, perhaps, will concern a cylinderical concrete or steel section of pipe

pushed into a granular medium in a manner similar to the direct shear test. The

adoption of a method of pushing a small concrete pipe or cone horizontally into

cohesive material may be used to establish the laboratory frictional magnitude


soil
between cohesive"and the pipeline, although the interface resistance in practice will

depend on (negative) porewater pressures and hence the propensity for soil

collapse. Different types of pipe surfaces with various skin friction characteristics

can be used. Also field testing is important, and it is suggested that the development

of special cone testing for pipe jacking could be adopted, in which a cone with a (for

example) concrete coated sleeve would be driven into the ground, possibly after

driving the cone on its own. Concrete friction can then be establish as a skin friction

and used for calculating the jacking forces. It is important to take into account the

verticality effects on the results. Joints can be added to the concrete sleeve to

simulate the joint effects on the skin friction. A study of the differences of carrying

out such a test using horizontal driving rather than vertical driving could also be

conducted.

of
Research into reduction'the jacking forces should be conducted to study the effects

of lubrication on the soil/pipeline interface and the bouyancy of the pipeline. Type,

quantity and injected pressure of a lubricant slurry may be studied to establish the

most efficient and economic method. As another form of reducing the jacking

forces, the development of special pipe coatings that would lower the interface

232
Chapter 8 Conclusions and Future Work

friction as the pipeline is jacked forwards could be considered. Further study on the
use of plastic sheething as described by Tohyama and Koiwa (1987), can also be

carried out. Research on the joint details is needed to establish the most practical, yet.

least frictional resistant, type. Using of a plastic covering or special kind of sealant
rubber, or even possibly a hard lubricant material around pipe joints, could be

considered.

Although adventurous, the idea of using air as a lubricant should be considered.

Although it may be difficult to adopt in practice, it is worth persuing such research


by using a thin air bag covering the surface area of the pipeline and then inflating it

using compressed air as the pipeline is progressed forwards. The air bag must be
durable to withstand the frictional, or drag, forces. The air bag can be possibly fed

in front from the leading pipe and extended as corrugated plastic bag. The gap

generated by the air gap can then be backfilled with bentonite to reduce surface

settlement. This technique may be best suited to cohesive soils to maintain the void

created during excavation.

The rate of jacking can be investigated to establish its effect on the jacking forces,

especially in cohesive material as it has shown little importance on the granular


materials.

Finally, it can be concluded that this problem is suitable for further acadarnic study.

Direct practical application of the results achieved so far is feasible and further

research work is likely to contribute significantly to greater economic and

engineering benefits of pipe jacking operations, and consequently provide for better
engineering design for on site pipe jacking operations.

233
References

REFERENCES

AKESAKA T and ROOKE A, (1985), " Developement Of The Iseki Telemole And
Telemouse And Their Application To Trenchless Pipelying", Trenchless
Construction for Utilities, Proceeding of the First international Conference, IPHE,
London, No-Dig. 85, April, pp 182-191 .

ANON, (1981), "Long Distance Driving Method For Ductile Cast Iron Pipe", Water
Services, October, PP 516-522 .

AKROYD TNW, (1964), "Laboratory Testing in Soil Engineering", Soil Mechanics


Ltd., London .

ATKINSON JH, CAIRNCROSS AM and JAMES RG, (1974), "Model Tests On


Shallow Tunnels In Sand And Clay", Tunnels And Tunnelling, Vo1.6, July, PP
28-32.

ATKINSON JH and POTTS DM, (1977A), "Stability Of A Shallow Circular


Tunnel In Cohesionless Soil", Geotechnique 27, No.2, PP 203-215.

ATKINSON JH and POTTS DM, (1977B), "Subsidence Above Shallow Tunnels


In Soft Ground", Journal Of The Geotechnical Engineering Division, ASCE,
VoU 03,April .

ATKINSON JH and BRANSBY PL, (1978), "The Mechanics of Soils: An


Introduction to Critical State Soil Mechanics", McGraw-Hill , UK .

ATTEWELL PB, YEATES J and SELBY AR, (1986), "Soil Movement Induced
By Tunnelling And Their Effects On Pipelines And Structures", BIackie and Son
Ltd. Glasgow.

AULD FA, (1982), "Determination Of Pipe Jacking Loads" Renewing Our Sewege
Infrastructure, Pipe Jacking Association Conference, London.

234
References

BASU NK, (1973), "Pipe Jacking: A Technique for Soft Ground Tunnelling",
Indian Concrete Journal, Vol.47, No.9, September, PP 328-334.

BEAVER P, (1972), "A History Of Tunnels", Peter Davies, London.

BELL FG, (1983), "Engineering Properties of Soils and Rocks", Butterworths,


London.

BEAUMONT TC, (1989), "UK Experience And Developments Of The Witte


Microtunnelling Machines", Proceedingsof the Fourth International Conference on
Trenchless Construction, No-Dig 89, London.

BISHOP AW and HENKEL DJ, (1962), "The Measurement of Soil Properties in


the Triaxial Test" Edward Arno1d, Second Edition, London.

BOARDMAN FW, (1960), "Tunnels", Henry Walck Inc. NewYork .

BOLTON M, (1979), "A Guide To Soil Mechanics", The MacMillan Press Ltd,
Bristol.

BRITISH STANDARDS INSTITUTION, (1984), BS 5911, Part 3, "Guide To The


Planning, Design And Construction Of Sewers In Tunnel", Part 4, Concrete Jacking
Pipes.
*
BROMS Band BENNERMARK H, (1967), "Stability Of Clay At Vertical
Openings", Journal Of The Soil Mechanics And Foundation Division, Proceeding.;
Of The American Society Of Civil Engineers, Vol.93, January.

CAIRNCROSS AM, (1973), "Deformation around Model Tunnels in Stiff Clay",


PhD Thesis, University of Cambridge.

CHAPMAN D.and ROGERS CDF, (1991), "Ground Movement Associated with


Trenchless Pipelaying" Proceedings of the 4th International conference on Ground
Movements and Structures, Cardiff, July, PP 6.1-6.17.

* BRITISH STANDARDS INSTITUTION, (1975), BS 1377, Part 4, "Methods of


Test for Soils for Civil Engineering Purposes"

235
References

CLARKSON TE and ROPKINS JW, (1977), "Pipe Jacking Applied To Large


Structures", Proceedings Of Institution Of Civil Engineering, Part 1, Vo1.62,
November, PP 539-561 .

CLARKSON TE and THOMSON JC, (1983), "Pipe Jacking: State·Of-The Art In


The U.K And Europe", Journal Of Transportation Engineering, ASCE , Vol.109,
No.l, January, PP 57-72.

COLE ERL, (1967), "The behaviour of Soils in The Simple Shear Apparatus" PhD
Thesis, University of Cambridge.

CRAIG RN, (1983), "Pipe Jacking -A-State-Of-Art Review" CIRIA , Technical


Note 112.
DAVIS EH, GUNN MJ, MAIR RJ and SENEVIRATNE HN, (1980), "The
Stability Of Shallow Tunnels And Underground Opening In Cohesive Material",
Geotechnique 30, NoA, PP 397-416.

DOWNEY DB, (1984), "Pipe Jacking in Japan" International Conference on the


Planning, Construction, Maintance and Operation of Sewerage systems, BHRA,
Cranfield, 12-14 September, PP 305 - 316 .

DRENNON CB, (1979), "Pipe Jacking: State-Of-The-Art" Journal Of The


Construction Division, ASCE, VoI.10S, September, PP 217- 223 .

ELVIGE AF, (1987), "The Potential for Microtunnelling in the UK", No-Dig 87,
2nd International Conference and Exhibition on Trenchless Construction for
Utilities, April, London, pp 5.2.

ETHERTON PT, (1985), "Development of Impact Moling Techniques in the


UK:Design, Use and Cost Consideration", No-Dig 85, Trenchless Construction for
Utilities, Proceedingsof the First international Conference, IPHE, London, April,
pp99-108.

FLAXMAN EW, (1985), "Concluding Address; The Way Ahead", No-Dig 85,
Trenchless Construction for Utilities, Proceeding of the First international

236
References

Conference, IPHE, London, April, pp308-315 .

FLAXMAN EW, (1993), "Trenchless into the 21st Century", Proceedingsof the
Tenth International Conference on Trenchless Technology, No-Dig 93,
Birmingham, pp C1.l-C1.4 .

FRY PAC and TWAITS AR, (1985), "Tunnel Jacking-The New Alternative",
Municipal Engineering, 2 February, pp 23 - 35 .

GLENNIE EB and REED K, (1985), "Social Costs: Trenchless V Trenching",


No-Dig 85, Trenchless Construction for Utilities, Proceedings of the First
international Conference, IPHE, London, April, pp81-89.

GREEN C and WOOD J, (1987), "Current Research into the Social Cost of
Sewerage System", No-Dig 87, 2nd International Conference and Exhibition on
Trenchless Construction for Utilities, April, London, pp 5.3 .

HAIR ID and SHIERS GE, (1985). "Directionally-Controlled Drilling for


Pipelines", No-Dig 85, Trenchless Construction for Utilities, Proceedingsof the First
international Conference, IPHE, London, pp 160-166 .

HARDING PG, (1981), "Introducing the Teiemole, an Innovation from Japan"


Tunnels and Tunnelling, Vol.1March, Part 13, No.2, pp26-30 .

HASLEM RF, (1983), "Ground Resistance Forces During Tunnelling By Pipe


Jacking" Internal paper, Liverpool Polytechnic, Dept. Of Civil and Building
Engineering, PP 173 - 180 .

HASLEM R.F, (1986), "Pipe Jacking Forces: From Practice To Theory" The
CeItenary Conference, N.W Association of the LC.E, Manchester, April .
*
HERZOG M, (1985), "Die Pressenkraft! bei schild vortriebeund Rohrvorpressung
im Lokkergestein" BMT, Issue 6, PP 236-238.

HOUGH CM, (1978), "Pipe Jacking", Water Services, November, PP 741-745.

* Refer to Page 239 for Hayashi M and Miyata Y (1989) .


237
References

HOUGH CM, (1986), "Progress in Pipe Jacking Standards", Pipe jacking


conference, International press centre, 22 October, London.

HUGHES JMO, WROTH CP and WIND LE D, (1977), " Pressuremeter Tests in


Sands", Geotechnique 27, No. 4, PP 455-477 .

INGOLD TS and THOMSON JC, (1989), "Site Investigation Related to Trenchless


Techniques", proceedings of the Fourth International Conference on Trenchless
Construction, No-Dig 89, London.

IRVINE DJ, (1985), "The Comparative Costs Of Some Methods Of Trenchless


Construction", No-Dig 85, Trenchless Construction for Utilities, Proceeding of the
First international Conference, IPHE, London, April, pp74-80 .

JONES MB, (1987), "Trenchless Systems Gain Wider Acceptance", Civil


Engineering, October.

KRAEMER-WASSERKA T, (1987), "Small Bore Pipe Jacking", No-Dig 87, 2nd


International Conference and Exhibition on Trenchless Construction for Utilities,
April, London, pp 3.1 .

KUHNHANN K, (1977), "Neue Ansatze Zur Ermittlung der pressenkraft fur


Schildevortriebe", Stuva-Tagung, Forschung + praxis H21, PP 55-61 .

KUNTZE E, (1985), "MicIPtunnelling in Germany", No-Dig 85, Trenchless


Construction for Utilities, Proceeding;of the First international Conference, IPHE,
London, April, pp 176-181 .
MAIR RI, (1979), "Centrifugal Modelling of Tunnel Construction in Soft Clay" ,
PhD Thesis, University of Cambridge.

MANLOW T, (1984), "Adoptable Shields For Integrated System", TunnelsAnd


Tunnelling, Small-Bore Tunnelling And Pipe Jacking Supplement, October.

238
References

HAYASm M and MIYATA Y, (1989), "Okumura-Markham Super Mini Shield


Tunnelling Method" Proceedings of the Fourth International Conference on
Trenchless Construction, No-Dig 89, London.

MILLIGAN GWE, (1986), "Current Research in Pipe Jacking", Pipe Jacking


Conference, International Press Centre, London, 22 October.

MILLIGAN GWE and RIPLEY KJ, (1989), "Packing Material in Jacked Pipe
Joints", Proceedings of the Fourth International Conference on Trenchless
Construction, No-Dig 89, London.

MOSS AF, (1989), "Microtunnelling For Contractors", Proceedings of the Fourth


International Conference on Trenchless Construction, No-Dig 89, London.

MUIRWOOD AM, (1975), "The Circular Tunnel In Elastic Ground", Geotechnique


25, No.l, PP 115 - 127 .

MUNRO AG and McMURDIE WD, (1985), "Auger boring for Pipeline


Construction", No-Dig 85, Trenchless Construction for Utilities, Proceeding of the
First international Conference, IPHE, London, April, pp 109-117 .

NCE (1986), 20 November, Published by Thomas Telford, PP 12 .

NEWMAN A, (1986), "The Economics Of Non-Distruptive Construction", Pipe


Jacking Conference, International Press Centre, London, 22 October.

NOMURA Y et al, (1985), "Pipe Jacking Method For Long Curve Construction",
Journal Of Construction Engineering And Management, VoUll, No.2 , June, PP
138 - 148 .

NORRIS P , (1993), "The Behaviour of Jacked Concrete Pipes during Site


Installation" ,DPhUThesis, Oxford University, Oxford (Unpublished).

NORRIS P and MILLIGAN GWE, (1992A), "Frictional Resistance of Jacked


Concrete Pipes at FuU Scale", Proceeding>of International Conference on Trenchless

239
References

Construction, No-Dig 92, Paris, PP 121-128 .

NORRIS P and MILLIOAN OWE, (1992B), "Pipe End Load Transfer


Mechanisims During Pipe Jacking", Proceeding;of the 8th International Conference
on Trenchless Technology, No-Dig 92, Washington.

O'REILLY A, FROST PR and PLANT JW, (1986), "Lecture Given To Sensor


Engineers Of The Water Council At Derby", Thrustbore Construction Ltd.

O'REILLY MP and ROGERS CDF, (1987), "Pipe Jacking Forces", Foundations


and Tunnels, Goldsmiths College, London, March, PP 201 - 208 .

PARRY R, (1978), "Pipe Jacking As An Alternative To Shield Tunnelling", M&H


Tunnel And Civil Engineering Ltd .

PECK RB, (1969), "Deep Excavation and Tunnelling in Soft Ground", Proceeding
of the Seventh International Conference On Soil Mechanics and Foundation
Engineering, Mexico City, Mexico, pp 225-290.

PHILLIPS SHE, (1985), "Tunnel And Bridge Construction With Minimum


Disturbance To Overhead Services", Infrastructure Rehabilitation, Construction with
Minimum Disturbance, pp 172-183.

PIPE JACKING ASSOCIATION, (1980), Jacking Concrete Pipes, Design And


Specification Bulletin, No. 1.

, POOLE AG, ROBROOK RB and REYNOLDS JH, (1985), "Replacement of


Small-Diameter Pipes by Pipe Bursting", No-Dig 85, Trenchless Construction for
Utilities, Proceedings of the First international Conference, IPHE, London, April,
ppI47-159.

RICHARDSON M and SCRUBY J, (1981), "Earthworm Systems will Threaten


Conventional Tunnel Jacking", Tunnels and Tunnelling, April, PP 29-32.

ROGERS CDF, O'REILLY MP and ATKIN R, (1989A); "Predition of Pipe


Jacking Forc~ Based On Site Observation", Foundations and Tunnels - 89,

240
References

September, London.

ROGERS CDF, O'REILLY MP and ATKIN R, (1989B), "Pipe Jacking Beneath


BurnhamOn-Sea: A Case History", Foundationsand Tunnels - 89, September,
London, PP 37-41 .

ROGERS CDF and YONAN SJ, (1992), "Experimental Study of a Jacked pipeline
in Sand" Tunnels and Tunnelling, June, PP 35-38 .

SANDSTROM GE, (1963), "The History Of Tunnelling", Barrie and Rocklift,


London.

SCHERLE M, (1977), "Rohrvortrieb Part i: Bauverlag, WiesbadenlBerlin .


STEIN D and BIELECKI R, (1984),"Service Tunnel Construction in West
Germany", Small-bore Tunnelling and Pipe Jacking: Supplement to Tunnels and
Tunnelling, October, PP 8 .

STEIN D, KIPP Band BIELECKI R, (1985/86), "Small Jacking Pipes For


Sewers", Microtunnelling, YoU, Winter, pp 17 -18.

STEIN D and KIPP B, (1985), "Pipe Jacking For Sewer Pipeline Of Less Than
800mm Diameter. Current State Of Development And Future Trend", Vo1.26,
Tiefean Ingernieubau Strassenbun, Part7, July.

MOLERSK
STEIN D, - A and BIELECKI R, (1990), "Microtunnelling: Installation and
Renewal of Nonman-Size Supply and Se~Cge Lines by Trenchless Construction
Method", Verlag furArchitektur, Und Technische Wissenschaften, Berlin.

SULINSKI SJ, (1972), "The Jacking Method In Tunnel Construction", Proceedings


Conference
Of The 1st North AmericJan Rapid Excavation And Tunnelhnt, American Inst. Of
~
Mining Metallurgical & Petrolum Engineering, Chicago, Vol.3, June.

SZCZUPAK JR, (1989), "Horizontal Directional Drilling applications" ,


Proceedings of the Fourth International Conference on Trenchless Construction ,

241
References

No-Dig 89, London.

SZECHY K, (1966), "The Art Of Tunnelling", Akademiai kiado , Budapest,


published by Tankonyvkiado, Budapest.

TAKADA T , (1987), "A Case Study Of Long Distance Jacking With Glass
Reinforced Concrete Pipes" No-Dig 87, 2nd International Conference and
Exhibition on Trenchless Construction for Utilities, April, London, pp 3.4 .

TERZAGffi K, (1943/59), "Theoretical Soil Mechanics", 9th Edition, John


WiIey&sons, NewYork.

THOMSON JC, (1967), "Horizontal Earth Boring", Proceedings Of Institution Of


Civil Engineers, PP 819 - 835 .

THOMSON JC,(1982), "What's Going On Around The World-A Look A Pipe


Jacking Activities Around The World", Renewing Our Sewerage Infrastructure,
Pipe Jacking Association, Conference.

THOMSON JC, (1985A), "Trenchless Developments Spark World Scrutiny",


World Construction, November, PP 59 - 64.

THOMSON JC, (1985B), "The Size of the Market" No-Dig 85, Trenchless
Construction for Utilities, Proceeding;of the First international Conference, IPHE,
London, April, pp9-18 .

THOMSON JC, (1987), "Trenchless Pipelaying Applications and Market" No-Dig


87, 2nd International Conference and Exhibition on Trenchless Construction for
Utilities, April, London, pp 1.1 .

TOHYAMA Sand KOIWAS, (1987)," Pipe Jacking With The Use Of Membrane
Wrapping", No-Dig 87, 2nd International Conference and Exhibition on Trenchless
Construction for Utilities, April, London, pp 3.2 .

242
References

TURNER, (1978), "Pipelines Installed without Trenching" World Construction,


Feburary, PP 46-48 .

WASHBOURNE J, (1982), "Sliding Resistance Of Jacked Tunnelling", Tunnels &


Tunnelling, vol. 14, part 10, November, PP 17 -18.

WASHBOURNE J, (1984A), "Mechanicsed Pipe Jacking As A Method Of Sewer


Construction", International Conf. On The Planning, ConstructiOIy\1aintenanceAnd
Operation Of Sewerage Systems, British Hydraulic Research Association, Reading,
September, PP 289 - 304 .

WASHBOURNE J, (1984B), "Slurry Lubrication For Jacked Tunnel Linings",


Civil Engineering Technology, February, PP 7 - 9.

WASHBOURNE J, (1985), "Development Of Mechanised Pipe Jacking In The


United Kingdom", ProceedingsOf The 4th .International Symposium)Tunnelling '85 ,
Inst. Of Mining And Metallurgy.- Edited By MJ Jones, March. '.:

WASHBOURNE J, (1986), "The Use of Thixotropic Slurries in the tunnelling


Industry", Ground Engineering, Vol.19, No. 2, March, pp 33-36 .

WEBER W, (1981), "Experimentelle Untersuchungen in rolligen Boden zur


Dimensionierung von Prebbohranlagen" Dissertation, Wissenschaftlicher Bericht
aus der Arbeit des Institutes fur Baumaschinen und Baubetrieb der
Rheinisch-Westfalisch Technischen Hochschule Aachen, RWTH Aachen .

243
Bibliography

BIBLIOGRAPHY

ATKINSON JH and MAIR RJ, (1981), "Soil Mechanics Aspects Of Soft Ground
Tunnelling", Ground Engineering, No. 5, July, pp 20-28 .

ATKINSON J.H and MAIR R.J, (1983),"Loads On Leaking And Watertight


Tunnel Linings, Sewers And Buried Pipes Due To Ground Water", Technical Note,
Geotechnique, No. 3, Sept. PP 341-344 .

CLARK JL, GARAS FK and ARMER GST, (1984), "Design Of Concrete


Structures. The Use Of Model Analysis", Based On Proccedings Of An International
Seminar Organised By The Institution Of Structural Engineers" November.

CLARK JI and MEYERHUF GC, (1972), "The Behaviour Of Piles Driven In

Clay", Part. 1 An Investigation Of Soil Stress And Pore Water Pressure As Related
To Soil Properties. Canadian Geotechnical Journal, Vol. 9 .

COLE M, (1986), "2.1m Diameter pipe Jack At Greenwich", Pipe Jacking


Conference 1986, International Press Centre, London, 22 October.

COLE JM, REID R, HOUGH CM and THORNTON G, (1977), "Pipe Jacking


Case Histories", Tunnel and Tunnelling, Vo1.9, No.4, July.

CORDING EJ and HANSMIRE WH, (1975), "Displacement Around Soft Ground


Tunnels", General Report Session 5 Tunnels In Soil, 5th Pan.Amer.Conf.Soil
Mechanics, Buenos Aires.

244
Bibliography

CRAIG RF, (1974), "Soil Mechanics", Van Nostrand Reinhold Company Ltd.

DADSON J, (1984), "Mini Mechanised PipeJacking", New Civil Engineer, 12

April.

DAVID FW and NOLLE, H, (1982), "Experimental Modelling In Engineering", 1st

Edition, Butterworths , London.

FROST P, (1982), "What Will Tomorrow Bring ?", Renewing Our Sewerage

Infrastructure, Pipe Jacking Association, Conference.

FOLLET K, (1986), "Dartford Central Area Foul Water Drainage Scheme", Pipe

Jacking Conference, international Press Centre, London 22 October.

FULLALOVE S, (1983), "Hydraulics Boost Pipe Jacking", New Civil Engineer,

24 November.

GULLEN RM and DONALD IB, (1971), "Residual Strength Determination In

Direct Shear", Proceeding 1st Aust-NewZealand Conf. Of Geotechnics.

HARDING H, (1975), "Simplicity Pays off in Soft-Ground Tunnelling", New Civil

Engineer, Special Supplement, 12 June.

HOUGH CM, (1982), "Principles Of Pipe Tunnelling Design- The Six Basic

Questions To Ask When Considering Pipe Jack/Segmental Tunnel Design",

Renewing Our Infrastructure,Pipe Jacking Association Conference.

245
BtblfDgraphy

HUNT M, (1978), "Pipe Jacking The Habrurg Sewer", Tunnels And Tunnelling,

Vol. 10, Part 6, July/ August.

KIRKLAND C, (1982), "The Need For Strength", Renewing our Sewerage

Infrastructure Pipe Jacking Association Conference, Lecture 3.2.

LANZ B, (1973A), "Pipe Jacking" ,Tunnels And Tunnelling, Vol.5, March.

LANZ B, (1973B), "Disscusion", On Pipe Jacking, Tunnels And Tunnelling,


Vol.5, March.

LEENEY J, (1979), "The Case History For Tunnel Jacking", Tunnels And
Tunnelling, Vol. 11, No.!, Jan/Feb, PP 39 - 42 .

LEONARD CAPPER P and FISHER CASSIE W, (1976), "The Mechanics Of


Engineering Soil", Sixth Edition, E & F.N Spon Ltd. London.

MARKS P, (1975), "Pipe Jacking Presses On", New Civil Engineer, Special
Supplement, 12 June.

MEGA W TM and BARTLETT JV, (1981), "Tunnels, Planning Design,


Construction", VoU, Ellis Horwood Ltd. Chichester, G.B 1981 .

MUIRWOOD A, (1975), "U.K Must Act To Retain Its Lead", New Civil Engineer,
Special Supplement, 12 June.

246
Bibliography

MUSSO G, (1979), "Jacked Pipe Provides Roof For Underground Construction in

Busy Urban Area", Civil Engineering, ASCE, November, PP 79 - 82.

O'REILLY A, (1986), "Specification For Pipe Jacking", Pipe Jacking Conference,

International Press Centre, London, 22 October.

O'ROURKE ID (1985),"Ground Movements Caused By Trenchless Construction",


No-Dig 85, Trenchless Construction for Utilities, Proceeding of the First
international Conference, IPHE, London, April, pp 51-63 .

PALEMEIRA EM and MILLIGAN GWE, (1989), "Scale and Other Factors


Affecting the Results of Pull-out Tests of Grids Burried in Sand", Geotechnique,
Vo1.39, No.3, pp511-524.

PARRY R, (1982), "Mechanical Pipe Jacking And Other Developments", Renewing


Our Sewerage Infrastructure, Pipe Jacking Association, Conf.erence.

PIPE JACKING CASE HISTORIES, (1977), Tunnels and Tunnelling, August, PP


91-94 .

READ GF, (1982), "The State Of Britain's Sewer Network", Renewing Our
Sewerage Infrastructure, Pipe Jacking Association, Conference.

READ G, (1984), "Sewer Work Underway", Civil Engineering, June.

247
Bibliography

READ G, (1986), "New Construction Trechniques In Sewers", Civil Engineering


Journal, October.

REES DF, (1973), "Small Size Tunnels", Tunnels And Tunnelling, Vo1.5, March.

REYNOLDS J, (1989), "Pipeline Renovation", Municipal Engineering, Vo1. 6,


February, PP 41-52 .

SCHAFER A, (1987), "On Target Jacking Of Non-Man Entry Size Reinforced


Concrete Pipes ", Betronwerk und Fertigteil Technik, Vo1. 53, No. 4, PP 246-254 .

SCHOFIELD A and WROTH P, (1968), "Critical State Soil Mechanics"


McGraw-Hill, London.

SMALL-BORE AND PIPE JACKING, (1984), Tunnels And Tunnelling, Vo1.16,


August.

SMITH GN, (1982), "Element Of Soil Mechanics For Civil And Mining
Engineers", Granada.

TERZAGHI K and PECK R, (1967), "Soil Mechanics In Engineering Practice",


2nd Edition, John WiIey & sons Inc. Newyork.

TOHYAMA S , (1985), "MicrotunneIling in Japan" Discussion of Paper, No-Dig

85, Proceeding of 1st International Conference on Trenchless Technology, April,


London, pp 19-29 .

248
Btbllography

WALLIS S, (1982), "west Feltham Pipe lackers Push Into The Future", Tunnels

And Tunnelling, VoU4, Part 8, September.

W ALLIS S, (1985/86), "Stony Diet Suits Hamburg Development",

Microtunnelling, Vo1.1, No.2, Winter.

WALSH T, (1975), "Bentonite Bore In Hamburg", New Civil Engineer, Special

Supplement, 12 June .

WARD WH & PENDER, MJ, (1981), "Tunnelling In Soft Ground", Proceeding

10th International Conf. In Soil Mechanics, Stockholm, PP 261 - 275 .

WEBER W, (1985/86), "Microtunneller Cuts Variable Ground", Microtunnelling,

VoU, No.2, Winter, PP 23 - 27.

WILLIAM LAMBE T and WHITMAN RV, (1976), "Soil Mechanics", Wiley

Eastern ltd. , New Delhi.

YONG RN and WARKENTIN BP, (1966), "Introduction To Soil Behaviour ", The
MacMillan Company, NewYork.

ZOLLMAN PM, (1985), "Automated Guidance And Profiling Systems In Tunnel

And Shaft Construction", Proceeding Of The 4th International Symposium By


Inst. Of Mininig And Metallurgy. Edited by M.I Jones, Tunnelling'85, March.

249
APPENDIX (I)

GEOLOGICAL AND PHYSICAL PROPERTIES


OF THE MATERIALS

250
".oo~
00000
ece.e
Garside Industrial Sands
GOOCG
• • • Of»
00000 Garside silica sand has been quarried in the Leighton Buzzard area
00000
o 0 0 0 0
9 ? 9 ? ?
for around 100 years. During this period high quality industrial sand
has been supplied throughout the·United Kingdom and to virtually
every corner of the world.

early years the sand was recovered from


pits by manual labour, then it was
I:essed and transported by horse and cart
canal to wherever it was needed.
a light railway was constructed
linking all the pits to a
central point for improved
efficiency and growing
demand. Following on came a
railway link and together with
motor vehicles the business
expanded rapidly.

The silica sand is of a special nature which is required in industry


for many diverse needs. This meanS that the sand has to be
dried and graded to various specifications. Particular attention
has to be paid to the silica content, grain shape, size distribution
and the chetnica1 analysis, in addition to certain specialised
essential characteristics for particular applications.

Nowadays the washed sand is


fed into computer controlled
process equipment, where it is
dried by a Fluidised Bed Dryer
and then separated by vibrating
screens into the required
grades;' The storage-capacity-at" .
the works enables large tonnages of any of our
specialised grades to be held in stock
to meet customer reqmrements.

~). Garside industrial siliCl sands PrOOu<2d by ECC Quan'.es fuJly meet rhe

@
saingenr r<quiremen~ ofBS5750: Part 2: 1987IISO !IXJ2-1987/EN
IV:
q~
2!IXl2-1987. The Company has been awarded a QualilV
. . i
I
!UIIUIl
ICOIII!U!I t
Assu<2li C:rtificare and is ~ under Standard .
Industrial iJassifiClcion: 2310: Extrxtion of
Stone, Oay, Sand and Gravd.
G:rtific:Ite }.i0. Q5924
ECC QUARRIES LIMITED
GEOLOGY AND SURVEY DEPARTMENT

PETROGRAPHIC EXAMINATION

PART 1 - DESCRIPTION

LOCATION:
GROVE BURY QUARRY
LEIGHTON BUZZARD DATE SAMPLE TAKEN SAMPLE REFERENCE
BEDFORDSHIRE
NATIONAL GRID REF: SP 920 230 MARCH 1989 GS 8/16-89

PETROLOGICAL NAME: QUARTZ SAND

SAMPLING DETAILS: 640g of 8/16 sand were received from George


Garside (Sand) Ltd. Details of sampling procedures were not
supplied.

METHODS OF EXAMINATION: The sample was reduced to a


representative portion with a riffle box. The test portion was
examined with the aid of a low powersteroscopic microscope and
individual grains counted to determine constituent proportions.
The test portion was then examined in thin section under higher
power petrological microscope.

GENERAL DESCRIPTION:
Yellow, clean sand. Particle size range 1.00-2.00mm

PARTICLE SHAPE: Irregular, rounded.

PARTICLE SURFACE TEXTURE: Smooth, occasionally rough or


honeycombed.

PETROGRAPHIC COMPOSITION: Number of % by vol.


Grains
Quartz 851 81 (+3 )
Quartzite 145 14 (+2)
Opaques (mainly iron-oxide) 40 4 (:El)
Iron-bound sandstone 7 1
Glauconite 5 <1
Chert 3 <1
Sandstone --- -- .---. -. ---- ---2-- --< 1-
Vesicular lava 1 <1

Total 1053

REMARKS: There are no constituents present in significant


proportions to class this sample as potentially susceptible to
alkali-silica reaction.
The results shown relate specifically to the sample provided and
therefore cannot take account of possible variations in the
deposit or during processing.

252

-.,-, "',.
ECC QUARRIES LIMITED
GEOLOGY AND SURVEY DEPARTMENT

PETROGRAPHIC EXAMINATION

PART'2 - DETAILS OF INDIVIDUAL CONSTITUENTS

LOCATION: GROVEBURY QUARRY SAMPLE REFERENCE


GS 8/16-89
PARTICLE SHAPE/
CONSTITUENT SURFACE TEXTURE DESCRIPTION
Quartz Irregular, Colourless, white, yellow, often
rounded/smooth with some iron-oxide coating.
Mainly fresh, single crystal
grains, some polycrystalline.
Moderate straining.
Quartzite Irregular, Yellow, brown, fine-medium
rounded/smooth grained, compact, fresh
metaquartzite. Some iron-oxide
coating. Moderate straining.
Opaque Irregular, Brown. black, greenish brown, fine
Minerals rounded/smooth, grained, iron oxide fragments.
rough. Fairly fresh, but weak.
Iron-bound Irregular/ Brown, weak, porous, quartz grains
Sandstone granular cemented by iron oxide.
Glauconite Rounded/rough. Green, fine grained, weak.
honeycombed.

Chert Irregular/smooth Brown, hard, compact,


cryptocrystalline silica.
Sandstone Rounded/rough Yellowish brown, fine-medium
grained, fresh sandstone.
Vesicular Angular/rough, Black, fine grained, glassy lava.
lava honeycombed.
.. REMARKS':- -

253
Technical
Data Sheet

TYPICAL PROPERTIES
Source: Leighton Buzzard, Bedfordshire
Geological
Classification: Lower Greensand
Composition: Quartz
Chemical
Properties: SiO, Approx. 97%
Loss on ignition at 1025 °C Not more than 1.0%
Weight loss in acid
(24 hours, 20% HCr, 20 0 q Less than 1.0%
Physical
Properties: Specific Gravity 2.65
Uncompacred Bulk Density I 560kg/m'
Sarurated Porosity 0.41
Particle Shape: Sphericity 0.85 (Sphere = I)
Rittenhouse Scale 0.83-0.87
Durability Loss of weight
(100 hours accelerated washing test) less than 0.1%

Garside Industrial Sands


39,Hockliffe Street, Leighton Buzzard
Bedfordshire LU7 8HB
Telephone: Lefghton BuZzard (()S25) 372201
Telex: 825868
Fax: (0525) 851572

~
GdlSide industrial silica sands produced by ECC Quarries fully meet the
i'~ •~.

@
S1 stringent ttquiremenG ofBS5750:!':ut 2: 198711S0 'XXI2·19871EN

q -
• : 111mB i
Italll1lll.
IO'I'.!C1llhl
~IUL
=·1987. The Company has been awarded a Quaiity
Assured O:ttiJiclte and is registettd under St:llldarti
Industrial OassiflClcon: 231~ Exmction of
Stone, Oay, Sand and GtaveL
Certificate No. Q5924
Technical
Data Sheet

Mechanical Analysis: Grade 2.00-1.00mm (8-16)


PERCENTAGE BY lVElGHT RETAI~iED
APERTURE B.S.S.
mm MESH No. mICAL GRADING
FRACTIONAL CUMlilATIVE CUMULATIVE RANGE
2.36 7 TRACE TRACE NIL - 0.5
2.00. 8 1.5 1.5 NIL-S.O
1.70 10 18.0 19.5 5-35
1.40 12 35.5 55.0 25-80
1.18 14 29.5 84.5 70-95
1.00 16 13.5 98.0 95 - 100
-1.00 -16 2.0 100.0 99 -100
Nominal Effective Size Range 1.05 - 1.27 FIGURESINBOLDTIPERELATETOSPECIFICATIONLL\lITS.
Mean Uniformity Coefficient: Less than 1.4 THIS DATA SHEET SUPERSEDES ALL PREVIOUS ISSL'ES.

Garside Industrial Sands


39,Hockliffe Street, Leighton Buzzard
Bedfordshire LU7 8HB
"Telephone: I..eightonBmzard (0525) 372201
Telex: 825868
Fax: (0525) 851572

~
G""id, indusaial siliCl sands productd by ECC Quarries fully meet the
S'I":
@
stringent requirements ofBS5750: Parr 2: 1987/1S0 9002-19871EN

q ~~~
I : 2!Xm-1987. The Company has been awded a Quality
• • : unuu Assured Cerrifi",re and is registered under SIJl!ldard
: ItallHI1I1
Indusaial OassifiClrion: 2310: E=crion oC
Stone, Clay, Sand and Gravd.
Certificate No. QS924
Registered Office Registered in Englond . Number 453225
C H QueensRoad Penkhull Sfoke-on-TrenfST47LQ England
Tel. 0782 45431 . Telex 36228 SCRAG . Fax 0782412331

TESTING SERVICES
Client's name and address All communications to be addressed to the Chief Executive
r
George Garside (Sand) Limited,
39 HockIiffe Street,
Leighton Buzzard,
Bedfordshire.
LU7 SHB

FAO : MR I LONGFORD
L

REPORT OF XRF ANALYSIS ON SAND

Yout' Mat'K •••••••• : 8/15


BCRL Lab Number.. T 9072/89

Da t e ...................... .. 13 JuI S9 Order Ne.: 7412


Date Received •••• 29 Jun 89 Contact : MR I LONGFORD

Sample dried at 110·e

Silica (Si02) . . . . . . II •••••••••••••••• /,fjs~~


Ti tania (Ti02) ••.•••••••.••.•••••.•• 0.03
Alumina (A1203> ........................................ .. 0.35
Ferric Oxide (Fe203) •••••••••••••••• if.t4E!!1
Lime (CaO) .................................................. .. 0.02
Magnesia (MgO) .••••••••••••••.•.•••• 0.04
Potash (K20) .............................................. .. 0.05
Soda (Na20) ............................................. .. (0.03
Phosphorus Pentoxide (P20S) •.•••••.• 0.04
Manganic Oxide (Mn304) •••••••••.•••. 0.01
Zinc Oxide (ZnO) •.••••••••••••••• ; •• 0.01
Barium Oxide (BaD) . . . . . . . . . . . . . . . . .. 0.01

Loss on Ignition at 1025°C •••••••••• 0.71

T Qt a 1 ............................................................ .. 99.91

REef
17 .fI" ,.•.,,,

GEOR( 't ., •.
,,>. .
......-.:..-.--__._i
.. 1.. .+.. Page 1 of 1
Technical Supervisor

•• '''w••,
, .. , OUItIll '011
UCHotQIQGOC::", "CH""'"'''' , . , _
The reported results relate only to the sample(s) tested.
No responsibility is taken for the accuracy of the sampling unless this is done under our own
supervision. This report must not be reproduced in whole or in part in any way as to lead to
misrepresentation of the results or their implications.

256
PORTAWAY MINERALS (ELTON) LTD.
PORTAWA'r<., ELTON
NR MATLOCK, DE4 1 LZ
Tel. Winster (062 988) 797 Telex 37380

National Grid Rcfer.~nce - SK.037413 .~~ Q~ , Sv~,

Oroup Class1ftcatlon ot' Hater1B.l - Quartzite


Petrological Nrune fer Oep081t - Bunter Pebble Beds

"
Ccier~e Aggr~g!!te Fine AJ;gregate
(Gravel! (Sand) -

Loss on ignit10n A trace to n11 1.0%

SiUca 96.1% 97.01-


Iron & Alumi:1a 1.0j(, 2.1%
Calcium 1.1% 0.7j(,
M~!; .. "" I .. ,~ A1I,,\11e :I~l t!l 1,$~ O.OI~

SUt, content (% by weight) NIL·


Organic Impurity NiL NIL
Bull< DensHy (Dry, r'()o:le) 1~21. 75kg/m I 1601.8l<g/m '
1'1Irtlclo ,,10,,1'.
Surface textllre
AUl!."ll'l· &
c:'},s tall ine
n",,,,.,rl,.,.-j -
Relative Density (O.Ol 2.59 2.60
Relative (S.S.D.l
O~r.sity 2.61 2.61
Relative Danslty (A.P.P.) 2.63 2.(,3
Water Abso('p~lcn (,; of r,I'Y Weight) 0.61\ 0.4~
Shrinkage velue A trlice to n11
Asgregate crushing value tA.C.V.) 13.0
---,4'.0- -- --_ ... - -'--------- - - .- - -_., -
.- ·llggl'cgate--Impae-t-lielue·
1',,11.:.1\~,:j ct~"o (Cl.S. u.) 'il.0
Crushing strength 21;8209.2 KN/m'
(36000.0 Ibs/1n'
10'.10 Fines Value 340 K.N. •
Aggregate Abraoion Value 1.2
Total SUlphur S.O. 0.02% 0.07%
Chloride (c.r.) Trace Trace

s"'\/'r.nRer (Managmg), J. G. R. Walker 257


Registered In England No. 1523248

-.
APPENDIX (11)

INSTRUMENTATION CALIBRATION AND TOLERANCES

258
INSTRUMENTATION CALIBRATION AND TOLERANCES

The following table gives some of the calibration and tolerances data for the
intruments used during the course of the research work.

Calibration
Instrument
Bridge Volt Calibration Factor Calibration Tolerance (%)

L.V.D.T 5.152 0.155 1mm=33mV o to)


5.150 0.155 1mm=33mV 0.00038(0.38)
5.148 0.155 1mm=33mV 0.00078(0.78)

Load Cell 6.54 0.00654 1V=lkN 0(0)


6.52 0.00654 1V=lkN 0.00306(0.3)
6.45 0.00654 1V=lkN 0.01376(1.37)

259
APPENDIX (III)

PHOTOGRAPHS

260
Plate (1) : Scale model testing rig In operation (sec tion 5 .3) .

Plate (2) : Sca le Illod cl in s lrLllll c nlalion pa n el (sec lion 5.3 .4) .

261
Plate (3) : Mode l concret e pipeline , (section 5.2.4) .

Plate (4) : M odel st ee l pipeline, (secti on 5 .2.4) .

262
Plate (5) : Special reinforcement of the co ncrete model pipes . (section 5 .2 .4 . 1) .

Plate (6) Gen era l veiw s how ing both conc ret e a nd steel pipes. (s ec tion 5 .2 .4 ) .
263
Plate (7) Different sizes for model culler shields. (section 5.4.4) .

Plate (8) Cultlng shield infronl of lh e lead pipe. (sec tion 5.4.4)

264
Plate (9) : Jacking and auger boring arrangem ent. (section 5 .2.6) .

Plate (l0) : Auge r boring in ope ra ti on with pace rs. (section 5. 2. 6) .

265
Plate (11) : Test preparatio n for conc rete p ipe in

Plate (12) : Test preparalio n for steel pipes in tesls,Type T, (sec tion 5.4.2 )
d
266
Plate (13) : Excavation technique for the Leighton Buzzard sane!
In tests,1)rpe I!. (section 5.2.6) .
of

Plate (14) : Excavation techniqu e for the River sand


In tests,fYpe 11, (sec tion 5 .2.6) .
of
267
Plate (15) : View showinl( th e arrangement of the con crete block in th e
bollom h alf of the specia l shear test box . (section 4 .4.3) .

268

S-ar putea să vă placă și