SERIOUS INSPECTION PLTU REMBANG UNIT 20 TAHUN 2017 LAPORAN PROGRESS PEKERJAAN HARI KE 07 TANGGAL 22 SEPTEMBER 2017 Bobot Bobot Total Progress Item Pekerjaan Remark Kurva S Rencana Realisasi Real. / Pekerjaan Turbin Utama 100,00% Main Turbin 0,03% 0,24% 2,99% On Progress Valve Turbin 0,00% 0,11% 3,86% On Progress NDT 0,00% 0,00% 0,00% On Progress Turbin Aux. 90,00% Pompa 0,00% 0,00% 0,00% On Progress BFPT 0,00% 0,04% 3,11% On Progress Oil System 0,00% 0,00% 0,00% On Progress Hapernas 0,00% 0,00% 0,00% On Progress 80,00% CWP & Common 0,00% 0,00% 0,00% On Progress Boiler Utama Boiler Evaporator System 0,18% 0,10% 6,05% On Progress Aux. Steam Piping SH, Reheat, Economizer 0,08% 0,12% 8,92% On Progress 70,00% Main Burner 0,06% 0,05% 5,91% On Progress Steam Sootblowing Sistem 0,06% 0,11% 4,80% On Progress Boiler Aux. Coal Feeder 0,07% 0,32% 30,00% On Progress 60,00% Mill 0,35% 0,27% 5,17% On Progress Fan & Damper 0,27% 0,38% 14,70% On Progress APH 0,04% 0,15% 10,00% On Progress SAC dan IAC 0,35% 0,00% 0,00% On Progress 50,00% Coal & Ash Handling Coal & Ash Hadling 0,04% 0,27% 8,00% On Progress ESP 0,04% 0,12% 8,00% On Progress Listrik 40,00% Generator 0,05% 0,17% 7,58% On Progress Motor & MOV 1,07% 1,35% 8,51% On Progress Trafo 0,00% 0,00% 0,00% On Progress Listrik Kontrol 0,34% 0,33% 5,77% On Progress 30,00% ESP 0,28% 0,15% 6,58% On Progress Kontrol dan Instrumen Control Cabinet 0,00% 0,09% 9,46% On Progress Turbin Area 0,04% 0,34% 4,25% On Progress 20,00% Boiler Area 0,69% 0,50% 4,58% On Progress Start Up Pekerjaan Pengetesan Jacking Oil 0,00% 0,00% 0,00% On Progress Listrik Motor Fase Pengujian 0,00% 0,00% 0,00% On Progress Leading 10,00% Filling H2 0,00% 0,00% 0,00% On Progress Backwash 0,00% 0,00% 0,00% On Progress Leakage Test H2 dengan Udara 0,00% 0,00% 0,00% On Progress Boiler Firing 0,00% 0,00% 0,00% On Progress 0,00% Turbine Start & Syncronizing 0,00% 0,00% 0,00% On Progress 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 TOTAL PROGRESS 4,04% 5,22% Note : Mengetahui, Menyetujui, Yang Membuat, *) Total progress keseluruhan : Leading 1,17% Spv. S. Management Outage Project Manager Rendal Project
I Ketut Suardana Mudjianto I Gede Tias Eka Buana
PT PEMBANGKITAN JAWA BALI SERVICES SIAP INTEGRATED MANAGEMENT SYSTEM SERIOUS INSPECTION PLTU REMBANG UNIT 20 TAHUN 2017 LAPORAN PROGRESS PEKERJAAN HARI KE 07 TANGGAL 22 SEPTEMBER 2017 Item Pekerjaan Rencana Realisasi Kondisi Keterangan Turbin Utama Main Turbin 0,38% 2,99% Leading 2,60% Valve Turbin 0,00% 3,86% Leading 3,86% NDT 0,00% 0,00% On Schedule 0,00% Turbin Aux. Pompa 0,00% 0,00% On Schedule 0,00% BFPT 0,00% 3,11% Leading 3,11% Oil System 0,00% 0,00% On Schedule 0,00% Hapernas 0,00% 0,00% On Schedule 0,00% CWP & Common 0,00% 0,00% On Schedule 0,00% Boiler Utama Boiler Evaporator System 11,36% 6,05% Lagging 5,31% Manhole Steam Drum belum aman untuk personil bekerja, temperature 49 ˚C Aux. Steam Piping SH, Reheat, Economizer 6,02% 8,92% Leading 2,91% Main Burner 7,56% 5,91% Lagging 1,65% Pemasangan Scaffolding belum selesai, karena PTW baru release 21 Sep 2017 Steam Sootblowing Sistem 2,54% 4,80% Leading 2,26% Boiler Aux. Coal Feeder 6,25% 30,00% Leading 23,75% Mill 6,77% 5,17% Lagging 1,59% Fan & Damper 10,71% 14,70% Leading 3,99% APH 2,56% 10,00% Leading 7,44% SAC dan IAC 49,15% 0,00% Lagging 49,15% PTW belum release, menunggu outservice unit #10 Coal & Ash Handling Coal & Ash Hadling 1,16% 8,00% Leading 6,84% ESP 2,50% 8,00% Leading 5,50% Listrik Generator 2,39% 7,58% Leading 5,19% Motor & MOV 6,77% 8,51% Leading 1,75% Trafo 0,00% 0,00% On Schedule 0,00% Listrik Kontrol 5,89% 5,77% Lagging 0,11% Masih ada beberapa breaker 6 KV yang belum diberi tagging ESP 11,81% 6,58% Lagging 5,23% PTW belum release, karena masih ada transport fly ash Kontrol dan Instrumen Control Cabinet 0,00% 9,46% Leading 9,46% Turbin Area 0,47% 4,25% Leading 3,77% Boiler Area 6,28% 4,58% Lagging 1,70% Sedang fokus penggantian seal line actuator valve oil to burner (24 ea) Start Up Pengetesan Jacking Oil 0,00% 0,00% On Schedule 0,00% Fase Pengujian 0,00% 0,00% On Schedule 0,00% Filling H2 0,00% 0,00% On Schedule 0,00% Backwash 0,00% 0,00% On Schedule 0,00% Boiler Firing 0,00% 0,00% On Schedule 0,00% Turbine Start 0,00% 0,00% On Schedule 0,00% Syncronizing 0,00% 0,00% On Schedule 0,00%
Mengetahui, Menyetujui, Yang Membuat,
Spv. S. Management Outage Project Manager Rendal Project