SERIOUS INPECTION UNIT 20

PT. PJB UBJ O&M REMBANG


TAHUN 2017

DAILY REPORT

Pekerjaan Yang Telah Dilaksanakan Pekerjaan Yang Akan Dilaksanakan


No Bidang Kondisi Target Pelaksana / Keterangan
(Work To be Done) (Work To Do)
Tanggal : 24 September 2017
Turbin Generator
Melepas Thermo Couple HP Turbin 6 ea 100% Melepas instrumentasi bearing 6 & Bearing 7 100%

BFPT BFPT
Kalibrasi Pressure Transmitter area mix bed 70% melepas sensor speed, key phasor BFPT 20 A 100%
melepas sensor speed, key phasor BFPT 20 A 100%
MBFP
Melepas koneksi RTD Booster (MBFP) 20 A 100% Kalibrasi PS LP Bypass 100%

Main burner Main burner


Penggantian seal pneumatic oil gun burner (22 ea) 40% peanggantian seal pneumatic oil gun burner 50%
(22 ea)

Mill A - E Mill A - E
Kalibrasi Pressure Transmitter 40% Kalibrasi Pressure Transmitter 50%

ESP ESP
melepas pneumatic valve, pressure switch, solenoid 50% melepas pneumatic valve, pressure switch, solenoid 100%
dan exhaust switch dan exhaust switch

Menyaksikan Mengetahui

I Ketut Suardana Mudjianto


Koordinator Overhoul Project Manager