Unload the tanker only after sunrise and before sunset and never during heavy
rains, thunderstorms or lightning.
Check all documents relating to the tanker, such as LPG transport license, TREM
card, SRV test report, driving license, invoice of LPG etc.
Weigh the LPG tanker on the weighbridge and record readings properly
Fix spark arrestor to LPG tanker exhaust pipe before the tanker enters the LPG
yard.
Park the tanker on hard stand and apply hand brakes. Put wheel chokes on all the
four wheels and then position the DCP fire extinguisher near unloading point
Turn 'OFF' the master switch of battery
Exit gate of LPG yard must always remain open during unloading operation
Ensure proper earthing connections for tank and truck body
During unloading, the tanker driver and LPG yard operator should always be
present at the site.
Connect both liquid and vapour balancing hoses to the tanker
Check the rotogauge reading of storage tanks as well as that of the tanker. Record
volume, temperature and pressure of LPG tanker and static tanks
Open the liquid and vapour valves of the tanker slowly and vent out air trapped in
hose through vent pipes
Unload the tanker first by pressure difference. When pressure is balanced, start
the unloading pump. Remember to open the vapour balancing line while
unloading through pump
Monitor the liquid level in static tanks by checking rotogauge at regular intervals.
Ensure that static tanks are not filled beyond 85%
After unloading of the tanker is complete, check rotogauge of static tanks and
tankers, and stop unloading pump
Close the ball valves of tanker and fill point. Empty LPG from unloading hoses by
venting off and disconnecting hoses
Check if the earthing connection and LPG hoses are disconnected and wheel
chokes are removed before moving the tanker
Weigh the tanker again. Difference between initial weight and final weight is net
gas receipt.
LPG tanker driver must check brake pressure and then move the tanker from the
LPG yard
LPG Maintenance
Stop all operations, close all isolation valves, and raise alarm
Use personal protective equipments/clothes while fighting fire or controlling
leakages
In case of fire, start water sprinkler spray system directing water jet to the flame
source
If fire is small, use DCP type fire extinguishers
Those not performing any duty in emergency must assemble at emergency
assembly point
Isolate main electrical system except the fire fighting system
Stop the spread of fire by closing isolation ball valves
Avoid all source of ignition. Block any traffic movements in case of major leakage.
Inform plant manager, fire brigade and police if leakage/fire is not controlled.
Give first aid and life saving treatment to injured persons