Sunteți pe pagina 1din 13

Cost Estimate for Platforms

Sl. No. Particulars HSR Rate, M^3 Thicness, Length, M Width, M Volume, M Unit Rate, RS/ M^2
1.0. Excavation 6.6 66.8255 0.45 12 5 27 1804.3
2.0. PCC, 1:3:6 10.4 4764.20 0.08 12 5 4.8 22868.2
3.0. RCC M20 10.65 5728.50 0.9 12 5 54 309338.7
4.0. Steel 18.22 61162.28 0.54 33028
5.0. Shuttering, M^2 9.6 347.40 5315
Total 372354
Rates/ RM 6206
Say 6206

For Comprehensive Envirotech Engineers Pvt.


Ltd.

69
Cost Estimate for Roads, Annexure- F
Sl. No. Particulars HSR Rate, M^3 Thicness, M Width, M Volume, M^3 Unit Rate, RS/ M^2
1.0. Excavation, filling & rolling 6.2+a+iii+iva 129.192 1.2 3.75 4.5 697.6368
2.0. PCC, 1:3:6 4764.20 0.15 3.75 0.5625 714.6299133333
3.0. PCC M25 5437.11 0.175 3.75 0.65625 951.4949188889
4.0. Kurb+Channel 10.77 5437.11 0.15 0.45 55.89 196.05
2363.8
71

& Prevailing Rates of Sand, Bajri, Bricks & Labour.


Sl. No. Particulars Quantity RS/ unit Total (Rs)
1.0. Cement OPC grade 42
1.1. Beg 1 290 290
1.2. GST, % 290 0% 0
1.3. Transportation, % 0 0 0
1.4. Unloading, % 1 1.08 1.08
FOR Rates 291.08
2.0. Reinforcement
2.1. Material: -
a MT 1 45000 45000
b Wastage, % 5 0 2250
c Binding wire 12 50 600
d Unloading, % 1 20.25 20.25
e FOR Rates 47870.25
f Contractor marging, % 10 4787.025
g Total 52657.275
2.2. Labour MT
a Blacksmith 1st class 5 550 2750
b Blacksmith 2nd class 5 450 2250
c Mazdoor 5 400 2000
d Contractor marging, % 21.5 1505
e Total 8505
Total RS(Mat+Lab) 61162.275
GST, % 0% 0
Total 61162.275
3.0. Brick work (1:5) M^3
F&P
3.1. Material
a Bricks 480 6 2880
b Cement OPC grade 43 1.45 291.08 422.066
c Sand 0.25 1560 390
d Contractor Margin, % 10 369.2066
Total 4061.2726
e Less rates of Brick Bats, @19.35+600% 5 135.45 6.7725
f Total 4054.5001
3.2. Labour 23M^3 Out put
a Massion 1st class 6 550 3300
b Massion 2nd class 6 450 2700
c Majdoor 24 400 9600
d Bhisti 3 400 1200
e Water Charges 1 200 200
f Labour 23 M^3 17000
g Contractor Margin, % 21.5 3655
Labour/ M^3 898.04
3.3 Total 4952.54
GST, % 0% 0
Grand Total RS. 4952.54
4.0. Brick work (1:5) M^3
S&S
4.1. Material

Comprehensive Envirotech Engineers Pvt. Ltd


72

a Bricks 480 6 2880


b Cement OPC grade 43 1.45 291.08 422.066
c Sand 0.25 1560 390
d Contractor Margin, % 10 369.2066
Total 4061.2726
e Less rates of Brick Bats, % 5 135.45 6.7725
f Total 4054.5001
4.2. Labour 17M^3 Out put
a Massion 1st class 9 550 4950
b Massion 2nd class 3 450 1350
c Majdoor 24 400 9600
d Bhisti 3 400 1200
e Water Charges 1 200 200
f Scaffolding 1 200 200
g Labour 17 M^3 17500
Contractor Margin, % 21.5 3762.5
h Labour/ M^3 1250.74
4.3. Total 5305.24
GST, % 0% 0
Grand Total RS. 5305.24
5.0. Design Mix Concrete RCC (1:2:4) M^3
F&P
5.1. Material
a Cement OPC grade 43 6.3 291.08 1833.8
b Bajri 20 mm 0.88 1450 1276.0
c Sand (quarry) 0.44 1450 638.0
d Contractor Margin, % 10 311.0
Total 4058.8
f Total 4058.8
5.2. Labour 12M^3 Out put
a Mazdoor 16 400 6400
b Massion 2nd class 1 500 500
c Peshtkar 1 400 400
d Bhisti 1 400 400
e Mazdoor extra 0.1666666667 400 66.6666666667
f Labour 12 M^3 7766.6666666667
Contractor Margin, % 15 1165
Labour/ M^3 744.31
5.3. Hiring Charges for Vidrator + Mixer 1 200 200.00
5.4. Water Charges 1 200 200.00
5.5. Total 5203.09
GST, % 0% 0.00
Grand Total RS. 5203.09
6.0. Design Mix Concrete RCC (1:2:4) M^3
Super structure
6.1. Material
a Cement OPC grade 43 6.3 291.08 1833.8
b Bajri 20 mm 0.88 1450 1276.0
c Sand (quarry) 0.44 1450 638.0
d Contractor Margin, % 10 311.0
Total 4058.8

Comprehensive Envirotech Engineers Pvt. Ltd


73

f Total 4058.8
6.2. Labour 12M^3 Out put
a Mazdoor 18 400 7200
b Massion 1st class 1.0833333333 500 541.6666666667
c Peshtkar 1 400 400
d Bhisti 1 400 400
e Mazdoor extra 0.8333333333 400 333.3333333333
f Labour 12 M^3 8875
Contractor Margin, % 15 1331.25
Labour/ M^3 850.52
6.3. Hiring Charges for Vidrator + Mixer 1 200 200.00
6.4. Water Charges 1 200 200.00
6.5. Total 5309.31
GST, % 0% 0.00
Grand Total RS. 5309.31
7.0. Design Mix Concrete RCC (M20) M^3
F&P
7.1. Material
a Cement OPC grade 43 8.1 291.08 2357.7
b Bajri 20 mm 0.84 1450 1218.0
c Sand (quarry) 0.4 1450 580.0
d Contractor Margin, % 10 351.8
Total 4507.5
f Total 4507.5
7.2. Labour 12M^3 Out put
a Mazdoor 18 400 7200
b Massion 2nd class 1 500 500
c Peshtkar 1 400 400
d Bhisti 1 400 400
e Mazdoor extra 0.1666666667 400 66.6666666667
f Labour 12 M^3 8566.6666666667
Contractor Margin, % 15 1285
Labour/ M^3 820.97
7.3. Hiring Charges for Vidrator + Mixer 1 200 200.00
7.4. Water Charges 1 200 200.00
7.5. Total 5728.50
GST, % 0% 0.00
Grand Total RS. 5728.50
8.0. Design Mix Concrete RCC (M20) M^3
Super structure
8.1. Material
a Cement OPC grade 43 8.1 291.08 2357.7
b Bajri 20 mm 0.84 1450 1218.0
c Sand (quarry) 0.4 1450 580.0
d Contractor Margin, % 10 351.8
Total 4507.5
f Total 4507.5
8.2. Labour 12M^3 Out put
a Mazdoor 18 400 7200
b Massion 1st class 1.0833333333 500 541.6666666667
c Peshtkar 1 400 400

Comprehensive Envirotech Engineers Pvt. Ltd


74

d Bhisti 1 400 400


e Mazdoor extra 0.8333333333 400 333.3333333333
f Labour 12 M^3 8875
Contractor Margin, % 15 1331.25
Labour/ M^3 850.52
8.3. Hiring Charges for Vidrator + Mixer 1 200 200.00
8.4. Water Charges 1 200 200.00
8.5. Total 5758.04
GST, % 0% 0.00
Grand Total RS. 5758.04
9.0. Design Mix Concrete RCC (M30) M^3
F&P
9.1. Material
a Cement OPC grade 43 8.2 291.08 2386.9
b Bajri 20 mm 0.84 1450 1218.0
c Sand (quarry) 0.4 1450 580.0
d Contractor Margin, % 10 354.7
Total 4539.5
f Total 4539.5
9.2. Labour 12M^3 Out put
a Mazdoor 18 400 7200
b Massion 2nd class 1 500 500
c Peshtkar 1 400 400
d Bhisti 1 400 400
e Mazdoor extra 0.1666666667 400 66.6666666667
f Labour 12 M^3 8566.6666666667
Contractor Margin, % 15 1285
Labour/ M^3 820.97
9.3. Hiring Charges for Vidrator + Mixer 1 61.6 61.60
9.4. Water Charges 1 15 15.00
9.5. Total 5437.11
GST, % 0% 0.00
Grand Total RS. 5437.11
10.0. Design Mix Concrete RCC (M30) M^3
Super structure
10.1. Material
a Cement OPC grade 43 8.2 291.08 2386.9
b Bajri 20 mm 0.84 1450 1218.0
c Sand (quarry) 0.4 1450 580.0
d Contractor Margin, % 10 354.7
Total 4539.5
f Total 4539.5
10.2. Labour 12M^3 Out put
a Mazdoor 18 400 7200
b Massion 1st class 1.0833333333 500 541.6666666667
c Peshtkar 1 400 400
d Bhisti 1 400 400
e Mazdoor extra 0.8333333333 400 333.3333333333
f Labour 12 M^3 8875
Contractor Margin, % 15 1331.25
Labour/ M^3 850.52

Comprehensive Envirotech Engineers Pvt. Ltd


75

10.3. Hiring Charges for Vidrator + Mixer 1 200 200.00


10.4. Water Charges 1 200 200.00
10.5. Total 5790.06
GST, % 0% 0.00
Grand Total RS. 5790.06
11.0. CC Concrete RCC 1: 3: 6 M^3
F&P
11.1. Material
a Cement OPC grade 43 4.4 291.08 1280.8
b Bajri 20 mm 0.92 1450 1334.0
c Sand (quarry) 0.46 1450 667.0
d Contractor Margin, % 10 261.5
Total 3543.2
f Total 3543.2
11.2. Labour 12M^3 Out put
a Mazdoor 18 400 7200
b Massion 2nd class 1 500 500
c Peshtkar 1 400 400
d Bhisti 1 400 400
e Mazdoor extra 0.1666666667 400 66.6666666667
f Labour 12 M^3 8566.6666666667
Contractor Margin, % 15 1285
Labour/ M^3 820.97
11.3. Hiring Charges for Vidrator + Mixer 1 200 200.00
11.4. Water Charges 1 200 200.00
11.5. Total 4764.20
GST, % 0% 0.00
Grand Total RS. 4764.20
12.0. Bed brick lining M^2
12.1. Material
a Bricks 76 6 456
b Cement OPC grade 43 0.35 291.08 101.878
c Sand 0.049 1450 71.05
d Contractor Margin, % 15 94.3392
Total 723.2672
12.2. Labour 46 M^2 Out put
a Massion 1st class 3 500 1500
b Majdoor 10.5 400 4200
c Water Charges 1 200 200
d Labour 46 M^2 5900
e Dressing of sub grade 46 3.965 182.39
f Contractor Margin, % 15 912.3585
Labour/ M^3 148.09
12.3. Total 871.36
GST, % 0% 0
Grand Total RS. 871.36
13.0. Side Brick Lining upto 3.5 M height M^2
13.1. Material
a Bricks 76 6 456
b Cement OPC grade 43 0.35 291.08 101.878
c Sand 0.049 1450 71.05

Comprehensive Envirotech Engineers Pvt. Ltd


76

d Contractor Margin, % 10 62.8928


Total 691.8208
13.2. Labour 116 M^2 Out put
a Massion 1st class 10 500 5000
b Majdoor 35 400 14000
c Water Charges 1 200 200
d Labour 116 M^2 19200
e Extra labour for sub grade 116 4.947 573.852
f Contractor Margin, % 15 2966.0778
Labour/ M^3 191.09
13.3. Total 882.91
GST, % 0% 0
Grand Total RS. 882.91
14.0. Side Brick Lining upto 3.5 M height M^2
14.1. Material
a Bricks 76 6 456
b Cement OPC grade 43 0.35 291.08 101.878
c Sand 0.049 1450 71.05
d Contractor Margin, % 10 62.8928
Total 691.8208
14.2. Labour 116 M^2 Out put
a Massion 1st class 11 500 5500
b Majdoor 40 400 16000
c Water Charges 1 200 200
d Labour 116 M^2 21700
e Extra labour for sub grade 116 5.917 686.372
f Contractor Margin, % 15 3357.9558
Labour/ M^3 216.02
14.3. Total 907.84
GST, % 0% 0
Grand Total RS. 907.84
15.0. Centering & Shuttering
Walls
15.1. Material
a HSR 9.6 (Through rate) 1 54.85
HSR 9.6 (Labour rate) 1 19.65
b Net material rate (a-b) 1 35.2
b Premium 1 350
c HSR+CP 1 158.4
c M^2/ M3 at 0.2 M Thickness M^2 10
d Shuttering Cost for walls/ M^3 1 1584
15.2. Labour cost, 48 M^2
a Carpenter 2nd class 17 500 8500
b Mazdoor 15 400 6000
c Contractor Margin, % 15 2175
d Labour 16675
e Labour/ M^2 347.40
f Labour/ m^3 3473.9583333333
Total 5057.9583333333
15.3. Extra for Centering & Shuttering for circular
works, % 20 1011.5916666667

Comprehensive Envirotech Engineers Pvt. Ltd


77

Total 6069.55
16.0. Centering & Shuttering
Roofs
16.1. Material
a HSR 9.1 (Through rate) 1 40.65
HSR 9.1 (Labour rate) 1 16.2
b Net material rate (a-b) 1 24.45
b Premium 1 600
c HSR+CP 1 171.15
c M^2/ M3 at 0.125 M Thickness M^2 8.0
d Shuttering Cost for Roof/ M^3 1 1369.2
16.2. Labour cost, 9 M^2
a Carpenter 2nd class 2.5 500 1250
b Mazdoor 2.5 400 1000
c Contractor Margin, % 21.5 483.75
d Labour 2733.75
e Labour/ M^2 303.75
f Labour/ m^3 2430
Total 3799.2
17.0. Centering & Shuttering
Columns
17.1. Material
a HSR 9.9 (Through rate) 1 49.45
HSR 9.9 (Labour rate) 1 18.75
b Net material rate (a-b) 1 30.7
b Premium 1 600
c HSR+CP 1 214.9
c M^2 at 0.35*0.35 M M 11.4
d Shuttering Cost for Columns/ M^3 1 2456
17.2. Labour cost, 7 M^2
a Carpenter 2nd class 2.5 500 1250
b Mazdoor 2.5 400 1000
c Contractor Margin, % 21.5 483.75
d Labour 2733.75
e Labour/ M^2 390.54
f Labour/ m^3 4463.2653061225
Total 6919.2653061225
17.3. Concrete rates with Centering & Shuttering
where ever applicable
a (1:2:4) F 1 5203.09
b (1:2:4) SS without shuttering 0 5309.31
Walls with shuttering 1 11378.86
Columns 1 12228.57
Roofs 1 9108.51
a M20 F 1 5728.50
b M20 SS without shuttering 0 5758.04
Walls with shuttering 1 10816.00
Columns 1 12677.31
Roofs 1 9557.24
15.3. M30F 1 5437.11
15.4. M30SS 0 5790.06

Comprehensive Envirotech Engineers Pvt. Ltd


78

Walls 1 10848.02
Columns 1 12709.33
Roofs 1 9589.26
Circular walls 1 11859.61
17.0. Plaster (1:4) 12 mm thick
17.1. Material
a Cement OPC grade 43 0.11 291.08 32.0188
b Sand 0.015 1450 21.75
c Contractor Margin, % 10 5.37688
d Total 59.14568
17.2. Labour 170 M^2
a Masson 1st class 12 500 6000
b Majdoor 12 400 4800
c Bhisti 12 400 4800
d Contractor Margin, % 15 2340
e Water Charges 1 200 200
f Scaffolding 1 200 200
17.3. Labour, Total 170 18340
17.4. Labour, M^2 107.8823529412
17.5. Total 1 M^2 167.03
17.6. GST, % 0% 0.00
17.8. Total 167.03
18.0. Excavation
18.1. Structures
6.7 HSR M^3
a up to 2 meter 100 9.32
b up to 7.5 M 100 0.2265
Total 9.5465
c Premium, % 600 66.8255

For Comprehensive Envirotech Engineers Pvt. Ltd

Comprehensive Envirotech Engineers Pvt. Ltd


Cost Estimate for Boundary Walls, Annexure- G
Sl. No. Particulars HSR Rate, M^3 Thicness, M Length, M Width, M Volume, M^3 Unit Rate, RS/ M^2
1.0. Excavation 6.6 66.8255 0.55 7.3 0.6 2.409 161.0
Column 6.6 66.8255 0.9 2.7 0.9 1.9683 131.5
2.0. PCC, 1:3:6 4764.20 0.1 7.3 0.6 0.438 2086.7
Column 4764.20 0.1 2.7 0.9 0.243 1157.7
3.0. RCC M20 5728.50 0.3 2.7 0.9 0.729 4176.1
12677.31 0.19 7.2 0.19 0.25992 3295.1
4.0. Braces 12677.31 0.19 20 0.19 0.722 9153.0
5.0. Brick work 5305.24 0.23 10 2.4 7.59 40266.7
6.0. Reinforcement 61162.275 0.1026552 6278.6
7.0. Plaster 167.03 20 2.4 45 7516.3
74223
Rates/ RM 7422

For Comprehensive Envirotech Engineers Pvt. Ltd


HSR Cost Analysis
Sl. No. HSR No. Specifications Quantity Unit Market Rates
1 6.7/1 Earthwork 1 M^3 66.8255
2 10.4 P.C.C 1:3:6 1 M^3 4764.20
3 10.39 CC1:4:8 1 M^3
4 10.28 CC1:8:16 1 M^3
5 RCC (1:2:4) - F&P 1 M^3 5203.09
6 RCC (1:2:4) - S&S 1 M^3 5309.31
7 10.65 M20 - F&P 1 M^3 5728.50
8 M20 - S&S 5758.04
9 10.66 M25 1 M^3
10 10.67 M30 - F&P 1 M^3 5437.11
11 M30 - S&S 5790.06
12 10.74 M30 above 4 Meter 1 M^3
13 11.23 Brick 1 to 5 - F&P 1 M^3 4952.54
14 11.24 1 to 4 1 M^3
15 11.28 Brick 1 to 5 - S&S 1 M^3 5305.24
16 11.29 1 to 4 up to first floor. 1 M^3
17 Bed Brick Lining 1 M^2 871.36
Side Brick Lining upto 3.5 M
18 height 1 M^2 907.84
19 18.22 Reinforcement 1 Qunitle 61162.275
20 15.5 12 mm 1 to 4 Plaster 1 M^2 167.03
21 15.3 12 mm 1 to 2 plater 1 M^2
22 15.1 15 mm 1 to 4 Plaster 1 M^2
23 9.6 Shuttering 1 M^2
24 9.5 + Note Centring & shuttering 1 M^2
25 9.7 + Note Centering & Shutering 1 M^2
26 9.9+ Note Centering & Shutering 1 M^2
27 9.1 + Note Centering & Shutering 1 M^2
28 Centering & Shutering 1 M^2 347.40
Analysis of Rates for Supplying, laying, jointing & cutting of Ductile Iron Pipes K/9 of 700 mm dia in the trenches including excavation & refilling the same and cost of specials complete in all respects

Unit - 100 Metre


HSR
Diduction Ceiling
S. No. Item Description Quantity Unit Rate Amount Base Price Total Amount Total Amount
5.25% Premium
No.
Material

1 NS Supplying of 700 mm dia Ductile Iron Pipes class K/9 as per analysis enclosed 100 Metre 14796.30 1479630.00 0% 1479630.00 1479630.00

Labour charges

(Excavation for pipelines running under pressure in trenches and pits, in streets &
lanes including trimming and dressing sides, levelling of beds of trenches to correct
6.9 grade, cutting joint holes, cutting trees and bushes, etc., refilling consolidation and
restoration of un-mettaled or unpaved surface to its original conditions and disposal
2 of surplus soil outside and inside the town involving lead upto 1 km in ordinary soil

(a) Without timbering and shoring upto 1.5 metres depth

100 x 1.20 x 1.50 180 100 cum 1183.00 2129.4 0.9475 2017.6065 370% 9482.75055 11500.35705
b) with timbering and Shoring
(ii) exceeding 1.5 metres depth, but upto 2.25 metres depth
100 x 1.20 x 0.65 78 100 cum 1623.00 1265.94 0.9475 1199.47815 370% 5637.547305 6837.025455

Stringing out DI pipes and specials castings along trenches and laying the same in
3 28.61 trenches to correct, alignment and gradients including cartage from Divisonal Stores 100 Metre 98.28 9828.00 0.9475 9312.03 0% 9312.03 9312.03
or nearest Railway Station to site of works and return of pieces of pipe to stores

4 28.63 Cutting of DI pipes and specials and chipping or filing the surface to a uniform finish 2 per cut 169.50 339.00 0.9475 321.2025 0% 321.2025 321.20

Jointing of DI socketted pipes, valves and specials with rubber tyton joints fitted
5 28.64 25 Each 111.45 2786.25 0.9475 2639.971875 0% 2639.971875 2639.97
complete including cost of labour and tools etc. and tested complete

Rate per 100 metre 1510240.59

Rate per metre 15102.41


Say 15103.00

83

S-ar putea să vă placă și