Documente Academic
Documente Profesional
Documente Cultură
1
STORED PROGRAM CONTROLLED PABX, ASB 20
CABLE FOR RURAL NETWORKS
1981 0.7 AND 2 MBIT/S SYSTEMS FOR PAIR CABLES
ERICSSON REVIEW
Vol.58. 1981
Contents Cable
Cable for Rural Networks
Page
38
Components
The Development of Custom Design Circuits 9
Manufacture of Monolithic Circuits 50
Manufacture of Hybrid Circuits 142
LSI Design Center 168
Subscriber Equipment
Stored Program Controlled PABX, ASB 20 30
ASB 900 in the Finnish Railway Network 175
Transmission Technology
0.7 and 2 Mbit/s Systems for Pair Cables 42
PCM Signalling Equipment in the BYB Construction Practice 134
Higher-Order Digital Multiplexors 196
Miscellaneous
ERICARE 96
Mobile Telephony in the Nordic Countries 120
CONTACT R L 4 0 0 - a New Radio Relay Equipment 128
Ericsson Towards the 1990s 150
Ericsson Information S y s t e m s - A New Company 152
A G A - E R I C O N - a Marine Radar Beacon 180
A Cooling System for Electronic Telephone Exchanges 188
P U B L I S H E D IN S W E D I S H , E N G L I S H , F R E N C H
AND S P A N I S H W I T H FOUR I S S U E S PER YEAR
T H E A R T I C L E S M A Y BE R E P R O D U C E D
AFTER C O N S U L T A T I O N WITH THE EDITOR
Contents
2 Power Units and Power Distribution in the BYB Construction Practice
9 The Development of Custom Design Circuits
18 Operational Experience of ARE 11 in Seinajoki
22 A u t o m a t i c Train C o n t r o l
30 Stored Program Controlled PABX, ASB 20
38 Cable for Rural Networks
42 0.7 and 2 Mbit/s Systems for Pair Cables
COVER
A production line at one of LM Ericsson's
factories for power supply units for telecom-
munication equipment
Power Units and Power Distribution in
the BYB Construction Practice
CHRISTER BOIJE AF GENNAS ers or is converted by inverters for a.c. devices and fans. However, fans are
Power Supply Department rarely used since the construction prac-
feeding, fig. 3.
Telefonaktiebolaget LM Ericsson
tice provides satisfactory cooling by
INGEMAR WEBRELL Both methods can be used in the BYB means of natural convection.
ELLEMTEL Utvecklings AB construction practice, but the d.c. feed-
ing method is commonly used. It is more Inverters are also used in equipment
cost-effective because of its higher that is normally intended to operate
Fig. 3 overall efficiency and smaller batteries. without standby batteries in the rare
Uninterruptible power feeding. In addition it gives higher reliability sin- cases where uninterrupted feeding is re-
a. Electronic equipment which has been designed quired.
ce it has a simpler structure and allows
with the option of uninterruptible operation and
with functional modularity. It the equipment is the introduction of redundancy by
small, the battery can be placed in the equip- means of parallel coupling. Knock-out units
ment.
In BYB associated magazines can be
b. Electronic equipment which has not initially
Inverters are used, for example, to placed together horizontally in a shelf or
been designed for uninterruptible operation. A
converter, battery and inverter must be added provide uninterrupted feeding of units vertically in several shelves, fig. 2. Each
to obtain uninterruptible feeding intended for a.c. feeding, such as I/O magazine can contain one or several
function units. The units can be depen-
dent on each other or independent with
respect to the system functions con-
cerned. From the point of view of re-
liability the function units can be
grouped in knock-out units. A knock-
out unit consists of a number of interde-
pendent units and is the largest unit that
may be affected by a single fault.
Internal distribution
The internal distribution can comprise
both electronic voltages and the system
voltage. Bars are used for the distribu-
tion from the converters to the printed
board assemblies. The magazines can
be equipped with up to four packages,
Fig. 4
The basic principles of the power distribution in Distribution in BYB 101 each consisting of t w o bars. The bars
BYB. One or more magazines form a knock-out are connected to the converters via
BYB 101 is the variant of the con-
unit, which is fed via a fuse in the distribution printed boards and to the printed board
rack. The power units in the magazines are struction practice that is primarily used
assemblies via wire straps. In certain
protected by a fuse in a connector, fig. 5 for large systems. The power distribu-
cases, where only small converters are
tion consists of external distribution to
used, the d i s t r i b u t i o n can be done en-
and between the magazines, and also
tirely with wired c o n n e c t i o n s .
internal distribution within the maga-
zines.
There are two types of earth distribution
used in older magazines. When a signal
earth plane in the f o r m of copper foil is
used, it is also used for the earth dis-
tribution. In magazines w i t h o u t any
earth plane the earth d i s t r i b u t i o n is car-
ried out via bars paired with voltage
bars.
connectors are constructed with eight With small systems it may be difficult to
earth pins per connector. obtain a sufficiently low impedance in
the feeding source to enable the high-
Several of the converters have a floating ohmic distribution method to be used
output, and the polarity can thus be In such cases an electronic fuse unit is
chosen by earthing one or the other of used instead of the distribution unit. The
the output poles. fuse unit then serves as a current Iimiter
and filter as well as a fuse.
Any distribution of the system voltages
within the magazine can be carried out The earthing element in the cables that
in the same way as the distribution of the connect the system voltage to the load is
other voltages. The system voltage is connected to mechanical earth close to
usually connected to the magazine via the load.
Table 1 the d.c./d.c. converter, whose feeding
DC/DC converters
Units with one output voltage, floating relative the voltage is taken through to the back Theearthing in BYB 201 hassufficiently
input voltage plane. The converters usually also low resistance to meet the requirements
Units with two output voltages having optional
polarity provide the possibility of connecting of the high-ohmic distribution method
Units with three output voltages having fixed
polarity through another, optional voltage from
the power connector at the front to the The electronic printed board assem-
back plane. blies are connected to the d.c. d.c. con-
verters via bars in the magazines in the
Distribution in BYB 201 same way as in BYB 101.
BYB 201 is the cabinet variant of the
BYB construction practice. The system Power units
voltage is connected via a distribution The most common types of power units
unit at the top of the cabinet. The divi- for the BYB construction practice are
sion into knock-out units can be done by - d.c./d.c. converters, which convert
running separate cables to the various the system voltage (usually 48 V) to
units. The high-ohmic distribution d.c. voltages for feeding, for example,
method is used in this case also, in order electronic components, relays or
to prevent any short-circuit transients magnetic tape units
from being propagated from one knock- - rectifiers, which convert the a.c.
out unit to another, fig. 7, mains voltage to a suitable system
voltage
- inverters, which convert the system
voltage to an a.c. voltage for feeding.
for example, I/O devices
DC/DC converters
The d.c./d.c. converter is the predomi-
nant type of power unit This is because
the conversion to the feeding voltage is
carried out in the magazine. Local con-
Fig. 7
A BYB cabinet with an electronic fuse unit at the
version has advantages as regards mod-
top of the cabinet ularity, reliability and cost. The number
6
Fig. 8
A simplified diagram for a d.c./d.c. converter
Fig. 10
Block diagram of the primary switched rectifier,
DOL
are fed from the same inverter there is a technology has an obvious field of use
BFD 200006/1 BMS 602
risk that the c o n n e c t i o n of one unit will in small inverters and ringing genera-
Input voltage 43-56 V 44-56 V tors built up on printed boards. Hitherto
cause serious disturbances in the o t h -
Output voltage 2x24 V 220 V ±5 %
Output power ers. The best way of avoiding this is to there have been considerable practical
2x60 W 500 VA
Wave shape Square Sinusoidal connect only one loading unit to each difficulties with c o n s t r u c t i o n s of this
Regulation Unregulated Magnetic inverter. This also c o n f o r m s very well type, but these are now on the way to
stabilizer with the applied d i s t r i b u t i o n m e t h o d being resolved.
Synchronization - Yes
with knock-out units. Thus large inver-
ters are not needed for the BYB con-
Table 3 struction practice. Table 3 shows the
Summary
Inverters available inverters. The standard inver- Modern electronic systems, such as
ter for 500 VA has been described pre- AXE 10. have the f o l l o w i n g main fea-
viously 4 . The highest required a m o u n t tures:
of power per loading unit is 1 kVA, w h i c h - highly developed modular structure
is obtained by means of a special type of - high reliability, partly through being
parallel c o u p l i n g of t w o 500 VA units. built up of knock-out units
- great adaptability to new technology,
Future trends such as new mechanical and electri-
The present inverters c o n t a i n transistor cal c o m p o n e n t s and new system de-
or thyristor switches, w h i c h operate at signs
the mains frequency, f o l l o w e d by trans- - simple operation and maintenance
formers and filters. In the 500 VA inverter routines.
the transformer is c o n s t r u c t e d as a fer-
romagnetic stabilizer in order to obtain The BYB c o n s t r u c t i o n practice and its
the desired regulation characteristics. power units are developed to suit such
systems. The chosen range of power
Work on i m p r o v i n g the characteristics units and the methods selected for the
of these magnetic stabilizers is g o i n g on distribution of power make this con-
all the time. Improved core materials struction practice extremely suitable for
and refined calculation will in the near all types of electronic equipment.
future give both greater efficiency and
smaller dimensions. For small inverter Many of the units can also be used in
units, perhaps up to 200 VA, it will be other c o n s t r u c t i o n practices, for exam-
possible to use high frequency t e c h n o l - ple in BAF 201 for large power plants
ogy. The principle is simple. The output and in the c o m m o n 19" construction
voltage from a pulse w i d t h regulated practice.
converter is m o d u l a t e d by a low fre-
quency sinusoidal voltage. The advan- These features mean that the BYB con-
tages of this m e t h o d are, a m o n g others, struction practice and its power units
better wave form t h r o u g h faster regula- are well e q u i p p e d to satisfy all require-
tion and smaller dimensions, due to the ments made on a c o n s t r u c t i o n practice,
fact that it is not necessary to use low- even in the rapidly c h a n g i n g technical
frequency transformers and filters. This environment of the 1980s.
References
1. Alexandersson, R. and Rorstrom. H.
O New Packaging Structure.
Ericsson Rev. 53(19761:2, pp 100-
107.
2. Orevik, A.: Power Supplies for Elec-
tronic Telephone Exchanges
Ericsson Rev. 57(1974) 4 pp K 120-
127.
3. Michelsen, S. et al.: A New Genera-
tion of Power Supply Equipment
Type BZD 112. Ericsson Rev 55
(1978):2, pp. 46-57.
4. Hansson, A.: Uninterruptible AC
Power Supply System. Type BZV
102. Ericsson Rev. 56 (1979) 1 Pnn
34-39. ' P'
The Development of Custom Design
Circuits
Fig. 1
A block diagram for an integrated circuit
GUNINAR BJORKLUND components manufactured using design requires special c o m p o n e n t data
JAN JOHANSSON monolithic technique is that c o m p o - which cannot be obtained with stan-
LARS-ANDERS OLOFSSON
JACKIE SUNDVALL nents w h i c h are geometrically alike are dardized elements. A t e s t circuit is man-
ABRIFA also almost identical f r o m an electrical ufactured in order to verify the data of
point of view. Table 1 gives some typical the new c o m p o n e n t s .
comparative values for absolute and rel-
ative tolerances. The small area require- Standardized c o m p o n e n t s , for example
Absolute Relative
Resistor
ment and good matching characteris- transistors, have been separately en-
tolerance tolerance
tics of transistors are utilized w h e n capsulated for use in bread-board mod-
Resistance ±10-20% ±0.2-2%
designing circuits in m o n o l i t h i c tech- els. The geometrical data of such com-
Transistor
nique, and give such circuits their ponents are stored in a data base in an
Current gain ±25 % ±5-10% characteristic feature, w h i c h may make interactive graphic system for circuit
Current ratios - ±1-5%
them difficult to understand for some- layout, and their electrical data are
body who is used to circuit engineering stored in another data base for use in
Table 1 with discrete c o m p o n e n t s . However, all circuit simulating programs, fig. 4.
Tolerances for integrated components in mono-
circuit diagrams can be converted into
lithic technique
block diagrams, w h i c h give a better pic- Transistors, i n c l u d i n g JFETs, diodes,
ture of the circuit f u n c t i o n . thyristors, zener diodes, resistors and
capacitors can all be manufactured
Circuit design using bipolar circuit engineering.
On the basis of the first, rough block
diagram and the specification, work is The detailed diagram design is verified
started on a more detailed diagram and by means of circuit simulations and by
the design of the blocks or sub-assem- building a c o m p l e t e circuit with stan-
blies. Computerized aids are used, part- dardized c o m p o n e n t s , fig. 5, a bread-
ly to provide verification and partly to board circuit. Electrical measurements
simplify optimization and other calcula- are carried out on this circuit to check
tions. that its f u n c t i o n is in accordance with
the specifications and that the circuit
The monolithic t e c h n i q u e gives the cir- design meets the given electrical data
cuit designer great freedom of choice as After these measurements the design is
regards the geometry of the c o m p o - discussed in detail with the customer,
nents, but certain rules regarding spac- so that the latter can assess at this early
ing must be observed. However, the stage whether the finished product will
most rational way is to use standardized meet the set requirements.
circuit elements with well d o c u m e n t e d
electrical data as far as is possible. In The r e q u i r e m e n t s f o r t h e c o m p o n e n t s i n
Fig. 4 certain cases new circuit elements are the circuit are specified in detail in con-
Components stored in a data base designed, for example w h e n a circuit nection with the calculations for the
Fig. 3
The chip area requirement for some integrated
components in monolithic technique
11
whole circuit. These data are compiled as the smallest units. These blocks are
in a design report, which also includes connected together by a conductive
the geometrical data for the compo- pattern. The blocks are moved about
nents. The design report forms part of and the wiring is changed until an ac-
the basic data for the layout work and ceptable packaging density with few
for the work on determining the per- conductor crossover points has been
missible tolerances for the manufactur- obtained. The detailed layout of the
ing process. blocks can either be done manually or in
a Computer Aided Design system, CAD,
The design and design report are exam- in which the component geometries are
ined by at least two designers who have stored. The components vary in com-
not previously participated actively in plexity from simple transistors to. for ex-
the work. The intention is to discover ample, complete logic circuit units. This
any weaknesses in good time and also stage comprises extensive, interactive
to enable other designers to benefit work which results in a first detailed cir-
from the experience gained from the de- cuit layout.
sign. An examination is also carried out
together with the staff responsible for The various layers in the detailed layout
measurements and production. are drawn in several colours on a drum
plotter. The degree of magnification is
Directives for the layout design are also usually between 200 and 400, fig. 6. The
compiled in connection with the design designer then scrutinizes this drawing
examination. They comprise a prelimin- against the circuit diagram as regards
ary layout of the blocks in the circuit, the connectionsand electrical design rules.
dimensions for the conductors with re- The CAD system carries out a computer
spect to the current density and descrip- check with regard to geometrical design
tions of other freedoms or limitations. rules.
The layout work is carried out in close After any corrections the production
collaboration with the circuit designer. tools are manufactured. In this case they
This is essential, since a part of the func- consist of one photographic mask for
tion and the performance are deter- each stage in the production process.
mined during the layout work, for exam- Each mask comprises a large number of
ple by giving matching components the the circuit pattern. These masks are
same orientation in relation to the crys- used both for manufacturing the pro-
tal direction. totypes and for the series production of
the circuit. A normal production pro-
The first stage in the layout work is car- cess for bipolar integrated circuits con-
ried out manually, with schematic tains between 7 och 12 different masks.
blocks of approximately the correct size The first prototypes are then made. This
Fig. 5
A bread-board model of a monolithic circuit
12
Fig. 6
A circuit layout for a monolithic circuit
13
The most common simulation programs Fig. 7 shows a detailed block diagram.
are node analysis programs. In such a When working out the detailed design of
program the network is described as a the blocks it has proved to be advan-
number of numbered connection tageous to carry out simulations and at
points, nodes, between which the ele- the same time make measurements on a
ments in the network are connected. bread-board model. The general func-
The network is described in the input tion can quickly be determined by
data by specifying the nodes to which an means of the measurements, and simu-
element is connected, the type of ele- lation gives the properties of the true
ment and its parameter values. The ele- circuit, without the parasitic effects ob-
ments can be simple, such as resistors tained in the bread-board model caused
with a single resistance value, or more by stray capacitances and wire induc-
complicated, such as transistors with tances. When checking temperature
non-linear characteristics which are de- properties it is easy to introduce thermal
scribed by means of equations with coupling and matching between com-
some tens of parameter values. The de- ponents in simulation, but it is almost
signer specifies which type of analysis is impossible to do so on the bread-board
to be carrried out, for example transient model.
analysis, and which nodes and
branches are to be analysed. The desir- The parameter values of standardized
ed currents and voltages are listed and components have been calculated and
plotted in the output data as a function stored in a data bank. During the simula-
of time, frequency or temperature. tion it is then only necessary to specify
the transistor type, and the program
Circuit simulation is often used as early fetches the parameter values. The
as when the first block diagram is pre- model for bipolar transistors is usually a
pared. The circuit function is then de- modified version of the one originally
scribed by means of a number of simple described by Ebers and Moll1. The pro-
blocks, each block being a simple grams usually contain a macrofunction,
model of a complex network. The analy- i.e. the possibility of building network
sis is done so quickly that many alterna- sections, which can be used in more
tive circuit designs can be compared, than one place in the same circuit.
for example with regard to sensitivity to
defects in components or imperfections The programs described above give op-
in amplifier stages. As the block dia- timization because the designer as-
gram develops, the models of the dif- sesses the result of a simulation, modi-
ferent blocks can be made more de- fies the input data and carries out a new
tailed so that the requirements for each simulation. In certain cases this pro-
block can be determined. cedure is not sufficient. Special optim-
Fig. 7
A detailed block diagram for an integrated mono-
lithic circuit
Fig. 8 ization programs have therefore been - integrated circuits in both MOS and
Optimization of an integrated line interface cir-
developed. The input data for such an bipolar t e c h n i q u e
cuit, SLIC
Left: Data before optimization optimization program consist of a net- - discrete c o m p o n e n t s , e.g. transis-
Right: Data after optimization work description and also a require- tors, diodes and thyristors
ment table and a list of the parameters - chip capacitors, both the ceramicand
that may be changed in the attempt to the dry tantalum type
meet the requirements. The p r o g r a m
automatically carries out iterations until The c o m p o n e n t s can be mounted after
the requirements have been met. This they have been encapsulated, in which
type of program is more difficult to han- case they are soldered or glued to the
dle and usually requires the user to have substrate, or they can be mounted be-
a certain amount of p r o g r a m m i n g fore encapsulation. This is then done
knowledge. Fig. 8 shows a printout from afterwards, for example by encapsula-
the optimization program FORNAP. tion in plastic.
Specification
The specification for a custom design
hybrid circuit describes the electrical
and mechanical requirements for the
circuit. The circuit specification is nor-
mally divided into three parts:
- an electrical requirement specifica-
tion comprising limits and charac-
teristic data for the circuit
Electrical diagram - a mechanical specification compris-
ing requirements for the encapsula-
tion and the connect ions to the circuit
- a quality specification comprising tol-
erance and reliability requirements
for the circuit.
Circuit design
The design work starts with a thorough
examination of the customer's specifi-
cation, and preparation of drafts for the
circuit design. Preliminary drafts may
have been made previously in order to
estimate the circuit size and manufac-
turing costs. The various drafts are then
assessed by means of calculations and
Completed circuit measurements on a bread-board model.
In the design work the range of tested
and type approved components, which
are already documented, are used
wherever possible. When it is necessary
to introduce new component types or
use a new supplier, evaluation and test-
ing must first be carried out.
be built up either on a printed circuit term stability. The designer must also try
board or on a ceramic substrate. The to achieve the most favourable com-
circuit characteristics can be evaluated bination of component placing and wir-
in detail by means of measurements on ing. Components, conductors and resis-
such a bread-board model. Factors that tors are placed on the substrate surface
affect the layout, such as matching re- in a layout sketch which is then used to
quirements, permissible tolerances and generate the pattern in a CAD system.
sensitivity to stray capacitances, can be The sketch that is to be input into the
assessed and the final choice of addi- system is placed on a drawing board. Its
tional components can be made. Fig. 10 data are fed into the computer store by
shows the development of a circuit from means of commands together with digi-
theelectrical diagram to the final hybrid. talization of the position of the drawing
board index, fig. 11. An original produc-
The layout work is based on docu- tion master is then generated on the
mented rules that specify how the film basis of the stored information, fig. 12.
pattern of the circuit is to be dimen-
sioned in order to obtain the optimum The work on the final mechanical di-
values for the characteristics of the mensioning of the circuit is carried out
finished circuit. The electrical circuit simultaneously with the layout work. A
design often leads to special require- suitable mechanical circuit con-
ments. Different circuit functions must struction can provide considerable ad-
be separated, for example because of vantages, such as
their sensitivity to disturbances or to - ability to withstand high power
stray capacitances. The choice of volt- - small dimensions
age and the requirements regarding - simplified mounting
ability to withstand currents influence - ability to withstand extreme climatic
the choice of conductor widths and re- conditions
Fig. 12
An original mask pattern for a hybrid circuit sistor areas. When positioning the addi- - ability to withstand mechanical vibra-
tional components the designer must tions and shocks.
also pay attention to the power dissipa-
tion, the mounting facilities, terminal Figs. 13-15 show some hybrid circuits
positions, substrate dimensions etc. with different mechanical con-
structions.
The layout work also includes calculat-
ing the dimensions of the resistors on Basic data for measurements and
the basis of the given resistance values, documentation
Fig. 11 tolerances, power values, temperature Series production of hybrid circuits re-
Digitalization by means ot a computerized
coefficients and requirements for long- quires documentation of
graphic aid - the substrate manufacture including
pattern printing and trimming
- component mounting
- pin mounting
- encapsulation
- final measurements and final check-
ing
- type testing.
Fig. 14
Special encapsulations for screw mounting
Fig. 15
Hermetic encapsulation for military use
References
1. Ebers, J.J. and Moll, J.L: Large-Sig-
nal Behaviour of Junction Transis-
tors. Proceedings of the IRE, De-
cember 1954, pp. 1761-1772.
2. Bjbrklund, G. and Johansson, J.:
Custom Design Circuits for Tele-
communications. Ericsson Rev. 57
(1980):4, pp. 166-172.
Operational Experience of ARE 11
in Seinajoki
Sakari Uitti
groups of terminal exchanges in the
The Seinajoki concession area comprises the whole of the Seinajoki group of area was started in 1960. The system
primary centres and a part of the Vasa group in western Finland. Seinajoki chosen was the automatic rural ex-
contains six ARE 11 local exchanges (SPC system with crossbar switches) and a change system ARK 50, supplemented
four-wire transit exchange. Control system ANA 30 is used for these exchanges. by transit exchange ARM 503 in the pri-
The operational experience has in all respects met the expectations of the mary centres. Today about 21 000 sub-
operating staff. The ARE 11 system can interwork with different signalling scribers are connected to 117 ex-
changes ARK 500.
systems and has a large traffic handling capacity It provides many valuable
operation and maintenance facilities, which can also be utilized for other
In the 1970s it was necessary to replace
exchanges in the group.
the local exchange ARK 50 in the largest
primary centres and to increase the ca-
pacity of Seinajoki exchange, and after
U D C 6 2 1 395 772 The Seinajoki Telephone Administra- careful study of different exchange sys-
654 01
tion was formed in 1893. Its concession tems the Administration decided, in
area covers 6400 km 2 and the number of 1974, to install LM Ericsson's system
subscribers is now around 33 000, fig. 1. ARE 11 and thus make use of the many
advantages offered by SPC. ARE 11 was
In 1951 the first automatic exchange chosen because
was taken into service in the town of - it provides smooth interworking with
Seinajoki, which is the zone centre. It existing exchanges
was a 500-line selector exchange, sys- - the basic version of the crossbar
tem AGF from LM Ericsson. The ex- switch system had long proved to be
change originally had 1500 lines. It is very reliable
still in operation. - the ARE 11 system is easy to under-
stand and handle, and thus requires
In order to provide better service for the very little training and maintenance
subscribers, automatization of the 13 - operation and maintenance can be
rationalized throughout the whole
group of primary centres by means of
the facilities offered by ARE 11
- several new functions and services
could be offered to the subscribers.
Operational experience of
ARE 11
Table 2 summarizes the total number of
faults and disturbances that occurred in
Fig. 1 1978 and 1979 in all ARE 11 exchanges
Seinajoki concession area with approximately
33 000 subscribers
listed in table 1. Some comments on the
figures in table 2 are given below.
type
The Finnish recommendations allow
two faults per 100 numbers and year.
The fault rate for 1979 is considerably
Primary centre with ARK 50 and ARM 503
lower than this.
Urban local exchange ARE 11
under Seinajoki exchange
The number of breakdowns was higher
Border of the Seinajoki concession area
in 1978 than in 1979 because in 1978
Border between the Seinajoki group of primary control system ANA 30 for the control of
centres and the part of the Vasa group of
primary centres that belongs to the concession the four-wire transit exchange in Seina-
area
19
SAKARI UITTI joki was installed, w h i c h caused opera- For example, if a fault occurs on one or
Seinajoki T e l e p h o n e A d m i n i s t r a t i o n
tional disturbances. Thus seventeen more circuits between a terminal ex-
Finland
Sakari Uitti g r a d u a t e d f r o m the Finnish Institute ANA 30 faults were f o u n d in the Seina- change and a g r o u p centre, this is de-
of T e c h n o l o g y , H e l s i n k i , in 1956. F r o m 1953 to joki exchange in 1978. They constituted tected because ARE 11 supervises the
1969 he w o r k e d for the A d m i n i s t r a t i o n as a de- 8 0 % of the total number of such faults in alarm state in the transit exchange ARM
signer and t e c h n i c a l c o n s u l t a n t w i t h the excep-
the whole g r o u p of primary centres. In 503. Other types of faults are detected
t i o n of the years 1 9 5 5 - 1 9 5 7 , w h e n he was e m -
p l o y e d by PTT in F i n l a n d Since 1970 Sakari spite of this, the average breakdown by means of the error rate m o n i t o r i n g .
Uitti has been the M a n a g i n g Director of Seina- time during 1978 and 1979 was An alarm is given if a limit value is ex-
joki Telephone Administration. ceeded. Certain devices in ARE 11 can
(8.5 + 2.8)x3 _ 3.4 hours per exchange then be marked so that the signalling
5x2 and three-year period can be traced even in traffic with ARK
and ARM exchanges. Faulty connec-
The calculations are based on the times tions can be analyzed and the exact
given in table 1 w h i c h show when the six position of the fault in the switched con-
local exchanges were taken into ser- nection is shown on a visual display unit
Seinajoki Transit 10x80 Successively vice. This gives an average value of five or a printer, fig. 2, It specifies the ex-
exchange inputs during local exchanges that were in operation change and even the unit where the fault
1978/79 during the fwo-year period in question. is located, so the repairman just reads
Seinajoki Local 3000 lines 15.12.1976 off the information. This means that a
exchange
The calculated average of 3.4 hours fault can often be repaired before the
Tornava 2000 " 15.12.1976
llmajoki 2000 " 25.10.1977 should be compared with the Finnish subscribers notice it.
Kurikka •* 2000" 7.3.1978 purchase recommendations for SPC ex-
Lapua 1 000 " 10.7.1978 changes, w h i c h permit a total break-
Kauhava 2000" 13.3.1979 Personnel requirement with
d o w n time of up to 8 hours per ex-
change and three-year period. centralized maintenance
Table 1 Three people within the Administration
The table shows when the exchanges were taken
into service and also their capacity
As regards the faulty printed board as- are specialists in ARE 11. They spend
semblies the Administration themselves approximately 10 % of their time locat-
were able to repair 10 in 1978 and 9 in ing and clearing faults in all ARE 11 ex-
1979. changes. In addition they are mainte-
Number of faults per year 1978 1979 nance experts for all other exchanges in
Number of faults in the whole
exchange, per 100 lines 0.36
The ARE 11 supervisory the group of primary centres and also
- handle certain operational matters.
Number of faults in ANA 30 only 21 14 system also serves the
Number of breakdowns caused
by faults in ANA 30 6 3
interworking exchanges The Seinajoki exchange is the only man-
Number of faulty printed board The continuous operational supervision ned exchange. The other ARE 11 ex-
assemblies (of a total of 9000
of ARE 11, w h i c h also extends to the changes are supervised from Seinajoki
assemblies) 14 12
Total breakdown time in hours 8.5 2.8 interworking with other exchanges, via data links, fig. 3. The maintenance of
makes it possible to also improve the the ARM and ARK exchanges has also
quality of service for the ARM, ARK and been centralized successfully by means
Table 2
The table shows the n u m b e r and types of faults
AGF exchanges in the whole g r o u p of of the facilities offered by the ARE 11
during 1978 and 1979 primary centres. supervisory system.
Fig. 2
Marking of the signal transfer unit, STU, in ARE
11 so that the signalling can also be traced in
traffic with A R M and ARK. The example shows
that a fault has occurred in the code receiver, KM,
in an ARK exchange and a fault printout is
obtained on a visual display unit in the mainte-
nance centre
RS Line Finder
STU Signal transfer unit
TCP Traffic control processor
OMP Operation and maintenance processor
n"M Cnrtet receiver
Fig. 3
All ARE 11 exchanges are supervised from
Seinajoki
The total training time for all seven par- ARE 11 can easily be
ticipants amounted to 54 man-weeks,
distributed in the following way: adapted to new requirements
- ARE 11 courses at LM Ericsson O/Y, As time goes by the need arises to intro-
Helsinki, 36 man-weeks duce new functions and services in ARE
Fig. 4
Existing devices in ANA 30 in a primary centre
can be used to provide the subscribers with new
services in connected ARK 50 exchanges. (The
relevant devices are coloured green in the figure)
The subscribers connected to the ARK exchange
can themselves change certain data in SCS and
ADS
FIR/S Sensor for hook signals when electronic
charging is used
KMK Tone receiver for push-burton dialling
SCS Subscriber category store
ADS Abbreviated dialling store
FDR Junction line relay set for duplex traffic
RS Register finder
REG-N Register for the group of primary centres
STU Signal transfer unit
TCP Traffic control processor
11. Thanks to the flexibility of the system The ARK 50 primary centres moderni-
this is easy to do. A few instances are zed by the introduction of control sys-
described below. tem ANA 30
Four primary centres in the concession
Electronic charging and other new area are e q u i p p e d with ARE 11 in c o m -
functions bination with ARM 503, fig. 1. In order to
The Administration intend to introduce increase the life of these ARM 503 ex-
electronic charging in all ARE 11 ex- changes with the associated terminal
changes. The o u t p u t from the charging exchanges ARK 50, the Administration
data store can then be processed by would like to carry out technical im-
computer, w h i c h will mean considera- provements so that these exchanges
ble savings. The program store of the will be almost equivalent to existing
existing operation and maintenance ARE 11 exchanges as regards opera-
processor will be enlarged for this pur- tional functions and subscriber facili-
pose. A m o n g other services that can be ties.
introduced at the same time, the A d m i n -
istration has decided u p o n : Minor changes in the software of ANA 30
- subscriber-controlled changing of will enable the ANA 30 processors to
numbers for abbreviated dialling and also control ARM 503 and interwork
connection and disconnection of cer- with ARK 50. This has made it possible
tain subscriber facilities, such as ab- to realize the above-mentioned im-
sent subscriber's service and block- provements. Thus the subscribers c o n -
ing of certain traffic routes nected to ARK 50 can be offered new
- supervision of the central alarm sys- services, such as push-button dialling,
tem and of external alarms, so that abbreviated dialling and remotely con-
alarm information from ARM 503 to trolled subscriber facilities, fig. 4. Elec-
the maintenance centre can also be tronic charging can also be introduced
obtained via ARE 11 for the subscribers at these exchanges.
- a new I/O system, w h i c h enables up to
8 local I/O devices to be connected
up, and which makes possible c o m -
munication with the operation and
maintenance centre via a data link
etc.
References
1. Ericsson Rev. 54 (1977):2, pp. 5 4 -
92.
2. Christensson, J. and Jansson, H.:
Further Development of the ARE
Systems. Ericsson Rev. 56 (1979):3,
pp. 134-140.
Automatic Train Control
Anders Sjoberg
The railway administrations are intro-
The Nordic Railway Administrations have decided to increase the safety of the ducing systems for automatic train con-
railway lines by introducing automatic train control systems on lines carrying a trol (ATC) in order to reduce the risk of
large amount of traffic. The systems, which are based on LM Ericsson's system accidents caused by the train driver.
JZG 700, will provide assistance for the driver and. if necessary, brake the train. ATC systems must
In this article the reasons, possible methods and safety requirements for - transmit information from the track to
automatic train control are discussed, and the functions and facilities of system the train
JZG 700 are described. The emphasis is placed on the method for track-to-train - present the information in such a way
transmission and the ways and means of using computers in safety systems. that the driver's work is simplified
- supervise that the train is driven safe-
Finally a summary is given of the current installation programs
ly, warn the driver in the case of dan-
ger and, if necessary, brake the train.
UDC656 25 The low friction between wheel and rail
means that the railway is a transport me-
dium with low energy consumption, but Different types of ATC
it also means that the braking distances ATC systems can work with continuous
of trains are very long. A freight train at or intermittent transfer of information,
100 km/h can have a braking distance of and the amount of information can be
1200 m. An express train at 130 km/h small or large.
needs about 700 m to stop. In many
cases the train driver's range of vision is Continuous systems, where information
less than that. is continuously transmitted from the
track to the train, are comparatively ex-
The driver is therefore informed about pensive, but are suitable for under-
the situation ahead by means of light ground railways and other tracks with a
signals and signs. Knowing the charac- high traffic load. LM Ericsson have sup-
teristics of the train, such as the braking plied continuous systems since 1950.
distance, he can then adjust the speed
to provide safe and steady driving The predecessor of the ATC systems
with intermittent transmission of infor-
Safety systems ensure that the signals mation was mechanical train stops. LM
cannot give dangerous information Ericsson have delivered such systemsto
even if a fault occurs. Thus, if the driver several countries. The transmission to
acts upon the signal information, no col- the train is carried out by a lever which
lisions can occur nor any derailment be- hits a brake valve on the passing train
cause of excessive speed that is to be braked.
Train drivers, like all other human Nowadays the intermittent track-to-
beings, can make mistakes. How often train transmission is usually inductive.
depends on, for example, how compli- The track is equipped with beacons, fig.
Fig. 1
The beacons are installed in pairs in order to
cated his job is. Increasing traffic vol- 1. The previous beacon systems have
increase the reliability ot the system. The ume, with more information to the driv- 'only been able to send a few messages
beacons are encoded so that the evaluation er, additional tasks and higher speeds, to the train, but both the demands and
equipment can determine for which direction of make the driver's job more difficult. the available facilities are now greater.
travel the information applies
Fig. 2
The units in an ATC system that are installed in
the track and the locomotive
23
ANDERSSJOBERG Demand regarding quantity of informa- faults. For example, if a fault occurs, the
Signalling Systems Department
tion ATC system may interpret a " p r o c e e d -
Telefonaktiebolaget LM Ericsson
A m o d e r n ATC system must messageas "stop" and brake the train A
- warn or brake in all situations that can stop message, on the other hand, must
be dangerous never be interpreted as "proceed".
- not warn or brake unnecessarily, sin- Availability, i.e. t h e a m o u n t o f t i m e w h e n
ce this w o u l d reduce the traffic ca- the equipment works accurately, and
pacity and reduce the driver's con- fail safe are to a certain extent in opposi-
fidence in the system. tion. Redundancy in code words or du-
plication of equipment can be used to
The ATC system must therefore handle increase the safety, but it then reduces
approximately the same amount of in- the availability.
formation as the driver whose driving
the system is to supervise, Fail safe means that
- no probable fault, including second-
JZG 700 has the required high informa- ary faults, may create a situation in
tion capacity. Furthermore it is possible which the train can be driven faster
to start by installing a simple system, than w o u l d have been allowed if the
which has certain limitations as regards fault had not occurred
traffic capacity. Later on. when the de- - a fault must be detected and cleared
mand grows and experience has been so quickly that the probability is very
gained, the ambition level can be in- low that another fault will occur
creased and additional equipment in- w h i c h , in c o m b i n a t i o n with the first,
stalled, for example at a certain signal, can lead to a dangerous situation.
Fig. 3 along a line, for a certain type of loco-
Encoder motive or more generally t h r o u g h o u t The safety requirement determines how
the system. low these probabilities must be. The
safety demands on an equipment mean
Safety requirements that the design and manufacture be-
For reasons of safety the ATC system come considerably more difficult and
must never let trains be driven at a speed expensive.
that exceeds the permissible limit. The
system must be safe even if a fault oc-
curs. This applies for all types of faults, System JZG 700
including design and p r o g r a m m i n g JZG 700, the latest ATC system de-
faults. veloped by LM Ericsson, transmits a
considerable amount of information
Fig. 4 Fail safe does not mean freedom from
A driver's cabin with control panel and evaluation
from beacons in the track, via an anten-
unit (top, right) na on the locomotive, to the evaluation
and presentation equipment in the loco-
motive. The system, fig. 2, consists of
- an encoder w h i c h senses the signal
information
- beacons in the track, w h i c h transmit
the information to the train. The
beacons are powered by the passing
locomotive
- an antenna and transmission unit on
the locomotive, f o r s c a n n i n g the track
and receiving the information from
the beacon
- an evaluation unit, w h i c h , on the
basis of information received from
beacons, panel, speedometer and
braking system, supervises that the
driver drives safely
- a panel for displaying information to
the driver and for feeding information
regarding the characteristics of the
train to the evaluation unit.
Fig. 5
A driver's panel for the Swedish and Norwegian
State Railways. The ATC panel is shown framed
in white. The left-hand part of the panel contains
digit displays that show the speed limits for the
current line section and the next speed restric-
tion. The right-hand part contains thumbwheels
for entering data concerning the train, such as
the maximum permissible speed for this particu-
lar train, its length and the reaction time and the
retardation capacity of the brakes. It is also
possible to enter whether the train may exceed
certain types of speed limits. For example, future
special high-speed trains may go through bends
at higher speeds.
All units and the communication be- required between signal and beacon, by
tween them meet stringent safety re- means of different encoders. Further-
quirements. more the locomotives can have different
braking systems, different powersupply
The ATC system is designed for inter- and different speedometers. In these
working with train radio on the locomo- cases also, adaption is required.
tives. The train radio can via the ATC
system be provided with information re- The administrations have different safe-
garding the position of the train and the ty regulations and different opinions re-
radio channel number. Via the radio it is garding the information to be provided
also possible to quickly inform the eval- for the train driver. This affects the panel
uation equipment about changes in the design and computer program. The pro-
signal information, so that initiated gram in JZG 700 hasa modularstructure
braking can be interrupted. This elimi- and is to a large extent written in a high-
nates the disadvantage of an intermit- level language in order to simplify
tent system compared with a continu- adaption to different requirements.
ous system.
Fig. 6
Warning and braking when the speed limit is
exceeded.
a. The display shows the speed limit (VMaI)
b. Acoustic and visual alarms are given when the
speed limit is exceeded by between 5 and 10
km/h
c. Automatic braking is carried out when the
speed limit is exceeded by more than 10 km/h.
The braking is indicated by a lamp. When the
speed of the train is reduced to the permissible
level the driver can cancel the braking by
depressing a button
25
Advance signals and signs along the The environmental requirements are
line inform the train driver about speed that the system must be able to with-
limits on the following sections. Via en- stand
coders, beacons and inductive trans- - ambient temperatures between - 4 0
Fig. 8 mission to the locomotive the evalua- and +70 C
Choice of frequencies for JZG 700 tion equipment receives the same infor- - impact acceleration on the beacon up
Relative interference level from the traction current mation, supplemented by information to 300 m/s2 (30 g)
Attenuation by 10 mm iron ore concentrate
Attenuation by 100 mm water
regarding track gradient and distance to - blows on the locomotive antenna
Information frequency the beginning of the section with the from bouncing gravel
Scanning frequency
new speed limit. On the basis of this - oil on the antenna and beacon
information and the data regarding the - 100 mm water or ice on top of the
braking characteristics of the train, beacon
which were fed in via the driver s panel - the train antenna covered with ice or
before the train started, the equipment snow
calculates when the train must be - 10 mm iron ore concentrate on top of
braked in order to slow down to the set the beacon
speed limit at the beginning of the rele- - electrical and magnetic interference
vant section. On the Swedish and Nor- from the locomotive
wegian State Railways this information - interference from radio transmitters.
is displayed for the driver when the train
is at the normal braking distance (8 sec- These environmental requirements af-
onds before the ATC system intervenes). fect the choice of material and transmis-
After that a warning that the train must sion frequency. Low frequencies suffer
be braked immediately is given 3 sec- more from interference from the loco-
onds before the ATC system acts. If the motive traction system. In addition low
driver still does not apply the brakes, frequency means large dimensions. The
this is done automatically. choice of higher frequencies is mainly
limited by the effects of water, dirt and
Track-to-train transmission ore on the beacons, fig. 8
The demands madeon the track-to-train
transmission are severe as regards abil- The telecommunications administra-
ity to withstand adverse environment, tions accept the use of the interna-
quantity of information and safety. tionally standardized ISM band at
Fig. 7
The function of the ATC system on the Swedish
state railways for a train at 70 km/h which
approaches a stop signal without the driver
applying t h e brakes.
S is the distance between the point where the
ATC system intervenes and the beginning of the
section with lower speed limit
S = t h e advance warning distance + the brake
application distance + the braking distance
27 MHz for the scanning signal from the risk of a message being misinterpreted
locomotive to the beacons. The fre- is negligible.
quency is at the upper limit for what is
called inductive transmission. As can be seen from fig. 9, more than
256 bits must be transmitted while the
The level of the signal from the beacon locomotive passes over a beacon. With
to the locomotive is so low that there is train speeds of up to 300 km/h and a
no risk of it causing interference. The beacon and antenna size of only 0.5 m a
locomotive motors cause more inter- transmission rate of 50 kbit/s is re-
ference than this signal. A frequency of quired.
4.5 MHz was chosen for this direction to
avoid any disturbance from radio trans- The safety requirements demand that
Fig. 9
mitters. beacons must be detected and that it
The quantity of information per message.
The message from a beacon consists of three must be impossible to misinterpret a
eight-bit data words, D,, D2 and Dv and a syn- The quantity of information which it message. The risks of misinterpretation
chronization word, S, alternating with S2. The must be possible to transmit to the loco- have already been discussed. The
message must be transmitted at least eight times
while the locomotive travels over the beacon. motive corresponds to more than 3000 beacon is designed so that no individual
different messages. This is achieved by fault or probable combination of faults
sending 3 words, each with 4 informa- can lead to the beacon transmitting a
tion bits, from each beacon. Four redun- less restrictive message than the cor-
dancy bits per word are added in order rect one.
to reduce the risk of errors. The 8-bit
words thus obtained are encoded so The beacons are installed in groups of
that 4 bits in a word must be wrong if it is not less than two. If one beacon de-
to be possible to mistake one code word velops a fault the driver of a train that
for another. passes this beacon receives an alarm
The equipment in the locomotive
In order to reduce the error risk further, checks that the beacon groups are com-
the equipment in the locomotive will plete and that the distance between ad-
only accept messages that have been jacent groups is correct.
identical at least four times of the eight
times it has been received during the For reasons of safety and maintenance
passage over a beacon. Each three- the transmission of information to the
word message is preceded and followed train has been made independent of bat-
by different eight-bit synchronization teries etc. in the track equipment. The
word. These precautions mean that the energy for the beacon logic and the sig-
Fig. 10
A block diagram of the electronics in a beacon
27
Fig. 12
An evaluation unit, mounted in a driver's cabin.
The unit consists of a power unit and transmis-
sion, processor, data storage and interlace units
in the form of printed board assemblies. They are
placed in a cabinet having the dimensions
400x300x325 mm. The problems with inter-
ference from the locomotive have been overcome
by galvanic insulation and filtering of all incom-
ing and outgoing conductors at the input to the
evaluation unit. Communication with the panel
takes place over two-wire lines, with data sent in
series form.
28
The 4.5 MHz signal from the beacon is ware faults in c o m p u t e r systems.
received by t w o loops in differential
coupling in the antenna. This c o u p l i n g Two independent channels are often
suppresses the 27 MHz signal from the used for the processing of information
send loop, w h i c h is placed between the in order to detect any random compo-
two receive loops. It also suppresses ra- nent faults. Checks that the results are
dio interference. the same are made at the channel out-
puts and at suitable points in the chan-
In order to ensure that the antenna and nels. If this c h e c k i n g is made frequently
transmission function satisfactorily and is extensive e n o u g h , the risk is neg-
they are frequently tested by means of a ligible that both channels develop the
test beacon placed in the antenna. This same, independent fault w i t h o u t it being
beacon can never be more sensitive or detected.
send a stronger 4.5 MHz signal than the
faintest beacon w h i c h the equipment Complex c o m p o n e n t s sometimes con-
must be able to detect. The test beacon tain systematic faults, i.e. faults that oc-
is activated every 50 ms by the computer cur in all circuits of a certain type or in a
in the locomotive. An alarm is given if no certain p r o d u c t i o n batch. For example,
signal is then detected. a certain c o m b i n a t i o n of data can cause
a functional fault since the component
may be pattern sensitive. The risk of
The evaluation equipment and its safety such faults affecting the function is
level small e n o u g h to be acceptable as re-
The evaluation equipment, fig. 12, has to gards the availability requirements for
process so m u c h information that c o m - most systems, and the c o m p o n e n t s are
puters have to be used. Hitherto the use therefore sold in spite of the faults. In
of computers in safety systems has been safety systems such faults must be ren-
restrained, although development and dered harmless.
experiments have been carried out in
many countries. Solutions have been In safety systems it is also important that
sought that make the systems safe in dangerous o u t p u t data are not pro-
spite of the fact that c o m p o n e n t s in the duced even outside the specified tem-
computers can develop faults. The fault perature range, and thus faulty func-
types that must be considered in a c o m - tions must also be considered in these
puter system are areas.
- hardware faults, such as random
component faults, systematic c o m p o - Systematic c o m p o n e n t faults can be de-
nent faults and interference tected by designing the two calculation
- software faults. channels differently, or by not using
them in the same way. Differences be-
Much of the experience gained from re- tween the channels also mean that the
lay and electronic systems w i t h o u t c o m - results obtained will be affacted in dif-
puters can be drawn u p o n to clear hard- ferent ways by any interference.
Fig .13
The two-program method means that
- tests and checks are carried out at the specifi-
cation stage in order to find any faults before
the work is divided between the two teams of
programmers
- each program is made so sate that the proba-
bility that both programs have the same, inde-
pendent fault is negligible
- the interdependency of the two programs is at
a level where checks and tests can be carried
out
- faults in the programs are detected by compari-
son
- all possible cases are tested when they occur
29
Of all the possible types of faults in a all equipment. In Sweden and Denmark
computer system, software faults are LM Ericsson supplies all g r o u n d and
most difficult to clear. It is well k n o w n transmission equipment, whereas the
that it is practically impossible to design majority of the evaluation equipment
faultless programs unless the programs and panels are supplied by another
are very simple. It is even more difficult manufacturer.
to prove that they are faultless.
However, to put an ATC system into op-
However, it is fairly easy to make a pro- eration requires more than just the de-
gram f u n c t i o n properly in normal situa- livery of the described equipment. The
tions, since any faults are quickly de- input signals to the system must be gen-
tected d u r i n g functional tests in the real erated and the output signals from the
environment and d u r i n g simulations. system must be dealt with. The equip-
But safety systems require that the pro- ment must be installed. The mainte-
gram functions properly even in abnor- nance organization must be prepared to
mal situations. The safety requirements take on the ATC system The train drivers
for ATC systems are about six powers of must be trained. The cost of the auxiliary
ten more stringent than the availability equipment and the work connected with
Fig. 14
The program cost as a function of the maximum requirements. the installation of ATC is approximately
permissible number of faults for one and two of the same order as the cost of the ATC
Droarams Since there is no method or combina- equipment itself.
tion of methods that makes the program
faultless, the system design must be The Swedish State Railways calculate
such that residual program faults do not that the installation of the 1200 locomo-
have any dangerous effects. tive equipments will take about three
years The installation is contracted to
The method chosen by LM Ericsson for different installation firms.
the p r o g r a m m i n g of the ATC system is
based on redundancy p r o g r a m m i n g The State Railways themselves are car-
Two independent programmer teams rying out the installation of the about
each design and test a program version 11000 encoders and 40 000 beacons.
that they make as safe as possible. The work is expected to take five years,
When the two programs are executed, but so far it has gone better than plan-
an alarm is given if any intermediary re- ned. Great efforts have been made to
sult or the final result differ, fig. 13. ensure that the planning and installa-
tion of the g r o u n d equipment proceed
Both these programs and the compari- smoothly and efficiently without any of
son program are stored in the equip- the safety aspects being neglected, fig.
Fig. 15 ment, and during the operation the pro- 15.
Installation.
The Swedish State Railways have made great grams are tested against each other for
efforts to get the ATC system installed and taken every c o m b i n a t i o n of input data that is In Sweden, area after area are taken into
into service as quickly as possible. Several aids used. The ATC system is too complex to operation and locomotive after locomo-
have been developed to simplify the installation allow testing of all possible combina- tive is put into service as soon as the
in the track. The picture shows one of the three
special vehicles that plough down the cables tions of input data before it is put into installation work is completed All c o m -
which connect the encoders and the beacons operation. muter train traffic in the S t o c k h o l m re-
gion will be equipped with ATC in 1981.
The method using two programs means The lines S t o c k h o l m - M a l m o (south
that any remaining faults are harmless Sweden) and S t o c k h o l m - G o t h e n b u r g
The faults that remain concern only very (west Sweden) will also be completed in
odd and abnormal situations, and thus 1981.
they do not affect the availability of the
system. The first lines in Norway will be taken
into service in 1981, in Denmark in 1983
and in Finland in 1984. Outside the Nor-
dic countries an early variant of the sys-
Installation and putting into tem was put in operation in Taiwan in
operation 1979.
LM Ericsson designs and manufactures
encoders, beacons, antennas, evalua-
tion units and drivers's panels for ATC Reference
system JZG 700. In Norway and Finland, L A n d e r s s o n , H.S.: Railway Signal-
the countries that have most recently ling Systems. Ericsson Rev. 57
ordered ATC, LM Ericsson is the main (1980):4, pp. 1 1 8 - 1 2 3 .
contractor for the system and supplies
Stored Program Controlled PABX,
ASB 20
Lennart Nyberg
All sizes of ASB 20 can be supplied with
LM Ericsson have, in collaboration with their Italian subsidiary. FATME. an operator console. Alternatively, it is
developed a microcomputer-controlled PABX for up to 28 extensions. possible to use a conventional tele-
The PABX offers many facilities which have previously only been available in phone to expedite incoming and outgo-
large PABXs. The revolutionary development in the semiconductor field has now ing calls.
made this economically feasible. Particular care has been taken to give the
system a rational mechanical construction and make the operation and The use of modern electronic compo-
maintenance functions simple and efficient. nents and stored program control have
made it possible to equip the system
with many valuable facilities such as
DTMF-signalling, abbreviated dialling
and automatic call back. The service su-
pervision is also stored program con-
trolled. An alarm is sent to the operator if
a fault occurs.
UDC 621 395.22 ASB 20 is a microprocessor-controlled
621.3 049 774
PABX with programs and data stored in Mechanically the PABX is designed as a
semiconductor stores. The PABX is de- compact unit with the power supply unit
signed for analog speech transmission. and the connection field as integral
The switching elements in the switching parts ASB 20 can be equipped with one,
network consist of semiconductors. two or three printed board assemblies
depending on the desired number of ex-
Conventional rotary dial and/or push- tensions. The PABX is delivered from the
button telephones can be connected to factory completely assembled and test-
ASB 20. Register access during a con- ed.
versation is gained by pressing the re-
call button (R-button). ASB 20 can be On installation of ASB 20 the installer
connected to virtually all public ex- feeds in specific customer data via the
change types available on the market operator console. Existing customer
via its programmable public trunk cir- data can subsequently be changed or
cuits. Signalling towards the public ex- more added by the operator or other
change can be achieved using different personnel at any time. No special train-
types of decadic signalling, alternatively ing is required for this purpose. Altera-
by means of Dual Tone Multi-Frequency tion and addition of data can be made
(DTMF)-signalling. quickly and at short notice.
Fig. 1
Operator console and cabinet for PABX ASB 20
31
LENNART NYBERG
Subscriber Equipment Division
System structure Telephony subsystem
The subsystem consists of a switching
Telefonaktiebolaget LM Ericsson ASB 20 consists of a telephony sub- network and the associated line circuits
system and a control subsystem. The for the extensions and the operator,
exchange of information between them public trunk circuits, devices for tone
is carried out over a bus system. Fig. 2 sending and receiving etc.
shows a block diagram of the PABX. The
units with solid outlines are always in- ASB 20 has a single-pole switching net-
cluded in the PABX, whereas the units work. The semiconductor elements that
with broken outlines constitute auxiliary are used in the crosspoints are of the
equipment, which can be provided if re- MOS type. The switching network has a
quired. bus structure and is divided into two
Fig. 2
Block diagram for stored program controlled
PABX. ASB 20
32
groups of links, one for internal and one the ring signal is connected to the called
for external traffic. Each external link is extension (B-extension) and the ring
connected to one public trunk circuit. control tone to the calling extension (A-
The crosspoint matrices of the switch- extension). When the B-extension an-
ing network are placed on the same swers, both ring signal and ring control
printed board assembly as the tele- tone are disconnected and the speech
phony devices they serve. The switching path is through-connected.
unit is used not only to set up calls but
also to connect the tone sender, dial If the extension is equipped with a rotary
tone receiver, DTMF-tone sender and dial telephone, the digits are received in
DTMF-receiver. ASB 20 possesses up to the line circuit and the DTMF-receiver is
four DTMF-receivers but only one tone released after detection of the first
sender, tone receiver and DTMF sender, break pulse.
all three of which are time-shared. The
crosspoint in the switching network is If the digit analysis shows that the exten-
used to generate the various tone sion has dialled the digit for external
cadences for dial tone, busy tone etc., calls, a free public trunk circuit is se-
fig. 3. lected, the public exchange is called
and, using a time-division mode, the dial
A call from an extension is detected in tone receiver scans the public trunk cir-
the line circuit fig. 2. The control sub- cuits in order to detect dial tone. After
system, which regularly scans the line receipt of dial tone the extension dials
circuits, selects a free internal link, con- the number of the external subscriber.
nects a DTMF-receiver and a tone send- The dialled digits are stored temporarily
er for dial tone. The extension can then in the data store and under processor
Fig. 3 start dialling. The digits are analyzed in control are then sent towards the public
The switching network in ASB 20 utilizes MOS- exchange by decadic signalling or
transistors as crosspoinls Each switch element
the control subsystem. If the dialled
contains a matrix with 2x8 crosspoints with number corresponds to an internal DTMF-signalling
integrated latches number the DTMF-receiver is released,
All external traffic can be subjected to
Trunk Call Discrimination, TCD. Up to 5
digits are compared with a digit table
compiled according to customer re-
quirements and contained in the data
store.
fast and congestion-free service for the tains the stored information for about
operator. The information provided on 100 hours in the case of a mains failure.
the display panel in the console, in the
form of digits, letters or symbols, is sim- Fig. 4 shows the program structure. The
ple and easy to understand. A feature of main aim has been to produce a pro-
interest is that the number of queuing gram system with small volume and
calls is stated on the display panel. rapid program execution. It c o m p r i s e s a
block for telephony functions and a
block for operation and maintenance
Control subsystem programs.
The central unit in the control sub-
system is an 8-bit microprocessor with The telephony block consists of func-
program and data stores, fig. 2. The pro- tion programs and traffic handling pro-
gram store consists of EPROMs which grams with defined signal relations. The
retain their information in the case of a function programs work direct with the
power failure. The data store for the pro- hardware for the sensing and scanning
grammed system parameters, specific of signal states and for operating the
customer data and temporary storage of hardware. The traffic handling pro-
digits and other parameters consists of grams control the various traffic pro-
C-MOS RAMs. This store is supple- cesses and facilities.
mented by a battery w h i c h is charged
during normal operation and w h i c h re- The operation and maintenance pro-
grams consist of interrupt programs
and supervisory programs. The inter-
rupt programs are controlled by dif-
ferent types of hardware signals and in-
terrupt the ordinary program handling.
When a PABX is put into operation for
the first time an interrupt program is
calles in, and using the basic system
data it automatically starts the PABX, i.e.
prepares it for traffic handling.
Extension facilities:
- internal calls
- outgoing calls, direct or via operator
- incoming calls via operator, alter-
natively signalled on c o m m o n bells
and answered by an extension dial-
ling digit " 8 " answer code
- inquiry d u r i n g external calls
- call transfer, before or after answer
Fig 6
The cabinet for PABX ASB 20 with two of the four
printed board assemblies pulled out
1 and 5. The operator console is easy to In addition to the facilities provided for
handle and provides a good overview of the extensions the operator can.
the traffic situation. An 8-window dis- - park calls
play unit allows the operator to follow - camp calls on to busy extensions
Fig. 7
A printed board assembly tor ASB 20 containing the progress of a call quite simply. The - set up serial call procedures
power connectors in the far edge and connectors display unit shows: - program system data
for bus cables and the cable to the connection - call type - read off system data
field in the near edge - read off metered call data.
- number of relevant trunk circuit
- serial call marking
- extension number The operator can program:
- extension state - extension classes of service
- amount of queuing calls - common night service extension and
universal night service
An explanatory symbol exists above - call number for extension group
each window. The information for all hunting, extensions in the group and
traffic cases is simple and unam- hunt method
biguous. - exclusive trunk circuits
- permitted area code numbers for ex-
The operator console also contains indi- tensions for trunk call discrimination
vidual busy lamps for each extension - external abbreviated numbers
and trunk circuit plus two alarm lamps. - device blocking
The console is equipped with five func- - reading of call meters for extensions
tion buttons each marked with a symbol, and public trunk circuits.
a volume control button for the call sig-
nal and a unit with 12 pushbuttons for The operators programming functions
dialling and programming. can be limited. The limitations are pro-
grammed by the installer of the PABX.
Night switching of the console is
achieved by the operator dialling a pre- The operator console is normally con-
determined code or by not answering nected direct to theexchange viaa plug-
Fig. 8 incoming calls. in cable. The distance between console
The PABX cabinet dropped forwards with connec- and exchange can be up to 25 m.
tion field fully accessible
Mechanical construction
Cabinet and printed board assemblies
The exchange cabinet is built up from
three pairs of extruded aluminium sec-
tions. The main top and bottom sections
are U-shaped and lock together. The
end pieces are screwed to the top and
bottom sections. The cabinet is hinged
to a wall bracket and. when upright,
covers the bracket, fig. 6. The connec-
tion field is also mounted on the wall
bracket.
Fig. 10
The power supply unit (to the right) with the
connectors for the printed board assemblies at
the top
Technical data 37
Capacity
Extensions
Trunk
circuits
Internal
lines
Telephone
operator
DTMF-
receivers
Printed
board
assemblies 2"
Traffic in Installation and testing - short mains failures. If a failure is
erlangs per shorter than 100 ms all calls in pro-
extension ASB 20 is a compact unit which requires gress will be unaffected
for a fully very little space. It works silently and is - too low working voltage for the micro-
equipped preferably placed in an ordinary office processor
system 0.2 environment, near the telephone opera-
- faulty program execution
* One printed board assembly partly equipped tor. The installation work consists of fix-
- the content of the data store, i.e.
ing the PABX to a suitable wall, con-
Telephones Pushbijtton telephone for whether it is still correct after a power
necting the telephone lines and power,
DTMF- signall ing in accor- failure.
programming the customer data and
dance with CCITT recom- If a fault occurs, an indication is ob-
mendations and with a recall testing the functions. The installation
tained on the alarm lamp in the operator
button time is short because:
Rotary dial telephone for a console. The operator can determine
- the whole PABX system, with supple- the type of alarm by means of special
pulse frequency of 8 - 1 6 Hz
and a pulse ratio of 30/70- mentary printed board assembly and alarm read-out commands. The opera-
50/50 the operator console, is tested at the tor can also take a faulty device out of
Extension numbers Two digits, fixed
factory before delivery operation temporarily by blocking it.
numbers - restrapping for adaption to different Any such blocking is indicated by a spe-
Current feed resistance ohms 2x400 markets is done by means of movable cial lamp in the operator console.
Extension line U-links
loop resistance ohms 1800 incl.
telephone - all connections are made by means of Aids
leakage resistance kohms 40 slot strips or plug-in connectors All programming of ASB 20 can be car-
Attenuation at 800 Hz - the customer data are programmed ried out using the operator console or a
external circuit dB 1 by means of commands. No program-
internal circuit dB 7 pushbutton telephone. The operator
Crosstalk attenuation
ming is required for the basic system console can also be used to read out
at 1100 Hz dB >80 data. These data are read into the data stored data for checking. Two four-fig-
Power supply store from the program store by an ure codes, "passwords", one for the in-
a.c. voltage V 110. 117. 127, interrupt when the PABX is connected
220, 230. 240 staller and one for the operator, are
frequency Hz 50 or 60
to the mains used to switch the operator console into
power consumption W 90 to 130 - customer data can be programmed the programming mode. The codes are
Ambient temperature °C +5 to +40 before installation if required. The arbitrary and are selected during in-
Relative humiditty % 20 to 80 data store with programmed custom-
Dimensions stallation. The installer can also specify
height mm 370
er data can withstand a transport time the programming facilitiesthat areto be
width mm 645 of 100 hours available to the operator.
depth mm 146 - the software includes test programs
depth with connection which simplify fault locating.
field mm 193 Fault localization
Weight (fully equipped Faults are located by means of test con-
exchange) ^ 27 nectionsfrom any extension. Theopera-
tor programs the desired extension. The
Operation and maintenance extension can then be used to enter
The operation and maintenance of ASB commands which specify the switching
20 is very simple since the system only paths and devices that are to be tested,
contains one power supply unit and and thus to localize the fault to a certain
three types of printed board assemblies. printed board assembly. These test con-
If a fault occurs the test programs indi- nections can be carried out without in-
cate the faulty printed board assembly. terfering with the normal operation of
It takes only a minute or two to change the PABX
the board. The data store battery should
be changed approximately every fifth Command language
year. No other preventive maintenance The command language used to com-
is required. municate with ASB 20 is the same as
used in LM Ericsson's other PABXs in
Service supervision the ASB series. It has been modified and
The following circuits and functions are simplified in some respects. A com-
supervised automatically: mand consists of a two-digit command
- data stores code and in certain cases also a param-
- switch circuits eter part.
Cable for Rural Networks
THORAARUM An optimum cable can be dimensioned calculated so that the repeater spacing
Headquarters by minimizing the sum of the cable cost can be decided in order to optimize the
Swedish Telecommunications Administration
ARNEERNBO and the repeater cost. Calculations have cost. A cable consisting of a star quad
Transmission Division shown that with set conductor dimen- inside a metallic screen is a rewarding
Telefonaktiebolaget LM Ericsson sions the cost reaches a minimum at a object for such calculations since its ge-
certain pair capacitance. The position of ometry is simple and well defined. The
this minimum is dependent on the ratio attenuation and characteristic imped-
between the cable and repeater costs. ance of the cable are calculated from its
Low cable costs and high repeater costs resistance, impedance, capacitance
give a minimum at a low pair capaci- and leakage. These parameters in their
tance. High cable costs and low repea- turn are functions of the frequency, the
ter costs, on the other hand, give a cost geometrical dimensions of the conduc-
minimum at higher capacitances. These tors, the insulation and the screen, and
relation chips are illustrated in fig. 2. The the characteristics of the materials used
upper curves apply for 2 Mbit/s systems, for these.
the lower for 0.7 Mbit/s systems. The
diagram shows that the cost minimum A computer program, which is specially
for 2 Mbit/s is found at lower capaci- adapted for a star quad or pair placed
tances than that for 0.7 Mbit/s. Since the centrally in a cylindrical cover made of a
minima are rather flat it is possible to conducting material, was developed for
use the same cable dimensions for both the calculations. The program is used to
systems. In this case the choice was a calculate the characteristic impedance
conductor diameter of 0.6 mm and a pair and attenuation of the cable in the fre-
capacitance of 42 nF/km. quency range 1 kHz - 10 MHz. Compari-
sons with later measurements made on
The other technical data are given at the a real cable show good agreement. The
end of the article. In Sweden loading cable model used in the calculations is
coils are not used on cables with con- shown in fig. 1.
ductors smaller than 0.6mm,andhence
the 0.5 mm conductor diameter was not Operation
considered. This alternative would The repeater spacing will be limited by
otherwise have given better handling near-end or far-end crosstalk in the ca-
characteristics and a slightly lower ble, by thermal noise or by crosstalk or
overall cost for 0.7 Mbit/s systems. the available amplification in the inter-
mediate repeaters, depending on how
Attenuation and characteristic imped- the pairs in the cable are used for digital
ance systems.
The attenuation of the cable must be
With single-cable, i.e. when both direc-
tions are transmitted over the same ca-
ble, near-end crosstalk is the major
source of disturbance. The nominal re-
peater spacing is then 2.2 km for 2
Mbit/s and 4.4 km for 0.7 Mbit/s, corre-
sponding to about 29 and 34 dB cable
attenuation at 1024 kHz and 352 kHz re-
spectively.
Repeater housing
Intermediate repeaters for 0.7 and 2
Mbit/s systems or loading coils are in-
stalled in a housing that is jointed to the
line cable. The housings are normally
mounted on poles, but other methods
may be used. A cylindrical housing has
Fig. 2 been designed for connection to
The relative costs as a function of the pair screened TUKA cables. It is made of
capacitance for screened TUKA cable acid proof stainless steel, has a diameter
of 150 mm and is 260 mm high.
The housing holds two two-way inter- can normally be retained when the bare
mediate repeaters, i.e. amplifier for two wire is replaced by screened TUKA. A
screened TUKA cables, or alternatively housing with overvoltage protectors
loading coils for four pairs, and the re- and, if necessary, intermediate repea-
quired number of overvoltage protec- ters, is then connected in at the joint
tors. between the TUKA and the multi-pair ca-
ble.
When connecting the housing to the ca-
ble the same tools and jointing materials Screened TUKA cable is normally used
are used as for ordinary cable joints. The as line cable on existing poles. However,
Fig. 3 housing is described in more detail in in certain cases it is advisable to con-
A pole with a housing for connecting a screened the following article2. tinue with the TUKA cable right into the
TUKA cable exchange. It can therefore be buried or
run in ducts over short distances. The
Line construction TUKA cable must not be used as station
The TUKA cable is mounted on poles as cable because of the fire risk, since its
an aerial cable. The same method and sheath is made of polyethylene.
suspension devices are used for both
screened and unscreened cables. The
unscreened cable is delivered in lengths
of 250 mandisrunouteitherbyhandor Field trials
from a cable trolley. The first field trial with a 2 Mbit/s system
was started in the Swedish Telecom-
The^'Pinting of the screened cable is munications Administrations network
more complicated. This is because the in 1979. It is expected to be completed
extra jointing of the screen and because during 1981. The measurements carried
greater demands are made on the trans- out so far have indicated that the cable
mission characteristics. It is necessary characteristics agree well with the spec-
to reduce the number of joints to a mini- ification. Climatic conditions have not
mum, and the cable is therefore deliv- influenced the transmission charac-
ered in the greatest possible lenghts. teristics abnormally, neither at low nor
high frequencies.
The chosen delivery length. 1100 m, cor-
responds to a whole loading coil sec- Further trials will be carried out in the
tion. Two lengths are required for a 2 Administration's network during 1980-
Mbit/s repeater section and four lengths 81. They will comprise about 380 km
for a 0.7 Mbit/s repeater section. screened TUKA cable with coil-loaded
Fig. 4, left as well as digital circuits for 0.7 and 2
A pole with a suspension device for TUKA cable Bare wire lines usually contain sections Mbit/s. Figs. 3 - 5 show details from one
with aerial or buried cable. These cables of the first installations.
Fig. 5. right
A joint on a screened TUKA cable
41
References
1. F r i z l e n . H . - J . a n d W i d l . W . : 10-Chan-
nel PCM System. Ericsson Rev. 56
(1979):2, pp. 7 2 - 7 9 .
2. Arras, J. and Danielsen, D. 0.7 and 2
Mbits Systems for Pa r Cable.
Ericsson Rev. 58 (1981):1 pp. 4 2 -
48.
0.7 and 2 Mbit/s Systems for Pair Cables
Fig. 1
Normal repeater and power feeding spacings with
transmission over cables having a conductor
diameter of 0.4-1.4 mm
43
JUHO ARRAS Adapters have therefore been designed nal equipment, for example in a supervi-
DAGFINN DANIELSEN
Transmission Division
for c o m p l e m e n t i n g line systems ZAD 2 - sion room.
Telefonaktiebolaget LM Ericsson 2 and ZAD 2 - 3 in this way.
Changeover to a standby
Terminal equipment system
The line terminating shelf used for ZAD The line terminating shelves can be
2 - 4 is the same as that used in ZAD 2 - equipped with a switching unit w h i c h , in
3V An adapter has been designed for the case of an alarm in the receive direc-
connecting the terminal repeater to the tion, automatically switches over to a
fault localization system. The adapter is standby system. The automatic
connected to the alarm interface of the changeover can only be used with sin-
shelf and can easily be introduced in gle-cable w o r k i n g .
previously installed shelves.
The line terminating shelves can also be
New terminal repeaters and alarm units equipped with pattern generators for
have been developed for ZAD 0 . 7 - 1 and test purposes. The pattern generators
ZAD 2 - 5 . Since the systems have the are also used to provide the standby sys-
same structure, one and the same line tems with a signal, so that they can be
terminating shelf can be used for both of supervised in the normal way when they
them, for example in small terminal ex- are not in use.
changes or branching exchanges where
both systems are installed. A block dia- Intermediate repeaters
gram of the line terminating equipment Modern semiconductor technology
is shown in fig. 2. with a high degree of integration has
been used for the new intermediate re-
Both the terminal and intermediate re- peaters. Almost all active c o m p o n e n t s
peaters are dimensioned to allow cable are assembled in two identical mono-
attenuations up to 40 dB. The terminal lithic circuits w h i c h are manufactured
repeaters also contain circuits for loop using b i p o l a r t e c h n o l o g y . T h e b l o c k d i a -
connection of the transmission signal gram of the circuit is s h o w n in fig. 3. The
for fault localization purposes. fixed equalization network, BETA, the
adjustable line building-out network,
The alarm unit monitors a number of ALBO, and the selective tank circuit are
system parameters and sends alarm in- all manufactured using discrete c o m p o -
dications if any values deviate from the nents. All elements that determine the
specified ones. The front of the alarm frequency have been assembled in
unit is equipped with diode lamps for these networks, and identical mono-
optical alarm indications. A derived sys- lithic circuits can therefore be used for
tems alarm can be connected to exter- the 704 kbit/s and 2048 kbit/s repeaters.
Fig. 2
A block diagram of the line terminating equip-
ment for ZAD 0.7-1 and ZAD 2 - 5 . The equipment
can be mounted in a line terminating shelf, which
holds up to four systems, in combination shelves
or in digital branching shelves
The transmission performance of a re- The electrical environment for the re-
peater is to a great extent dependent on peaters is extremely varied. In rural
its equalization characteristics. Consid- areas with aerial cable and in areas with
erable efforts have been made to opti- high earth resistance the repeater can
mize the equalization for the various ca- be exposed to very high voltages in con-
ble types concerned. The attenuation nection with lightning and short-circuits
curves for some cables with different to earth in adjacent power lines. The
conductor diameters and different in- equipment is protected by rare-gas
Fig. 4 sulation materials are shown in fig, 4. tubes, connected in accordance with
The attenuation characteristics of three cable With transmission at 704 kbit's equaliza- fig 5, and by robust diode protectors on
types in the frequency range that corresponds to tion is difficult to achieve below 200 kHz the inputs and outputs and in the power
transmission at 704 kbit/s because there are large deviations from feeding path. All printed board conduc-
the normal attenuation characteristic of tors that are exposed to overvoltages
\ T. have a width of 2 mm and the same isola-
tion space. The connector contacts are
gold plated and are of the same type as
The optimization of the performance of those used in the M4 construction prac-
a repeater for a wide range of opera- tice. This type of contact has proved to
tional cases requires powerful compu- have particularly good overvoltage and
ter aids. LM Ericsson have therefore de- overcurrent characteristics.
signed an extensive simulation and
optimization program, which can be
A characteristic feature of the mechan-
used for any part of a transmission sys-
ical construction practice is that both
tem. The program is fed with data con-
the housing fittings and the repeater
cerning the relevant cable types, the de-
cassettes are made of plastic. This has
sired operating range, repeater config-
given the repeater the ability to with-
uration, line code (AMI, HDB3) etc. The
stand such high overvoltages that there
optimization program dimensions the
is no need to protect the repeaters with
equalizer so that the lowest possible er-
rare-gas tubes to earth. This has consid-
ror rate is obtained over the whole desir-
erably reduced the risk of cable
ed equalization range, with considera-
damage, since a striking rare gas tube
tion paid to near-end and far-end
Fig. 5 can cause such large difference volt-
crosstalk. The program selects a solu-
Overvoltage protection for a digital repeater. It ages relative earth in the cable that dis-
provides protection against longitudinal and tion that takes all relevant cable types
ruptive discharges can occur between
transversal voltages and voltages between the into account
two directions of transmission. The protection the pairs.
can be earthed via strap S in the housing if the
safety requirements demand it The equalization range is divided into The repeaters have been dimensioned
two, corresponding to a line attenuation to withstand surge voltages and cur-
of 0-20 dB and 15-40 dB respectively. rents from lightning strokes up to 5 kV
Fig. 3
One transmission direction in a digital repeater,
not including the fault localization equipment and
protective devices. The blocks within the broken
outline are contained in the integrated circuit
45
and 200 A with a pulse shape of 10/700 opened without tools. Strapping and
/JLS (rise time and time to half value). checking of the units can therefore be
They thereby meet even more stringent carried out quickly.
demands for overvoltage protection
than those given in CCITT recommen-
dation K. 17. Housing
Very large currents at the mains fre- The new generation of line systems is
quency can momentarily be induced in complemented by a new series of cylin-
the telecommunications network if a drical repeater housings, consisting of
breakdown occurs in the power line net- top and bottom parts of equal size. Each
work. All line systems have therefore part has a flange, so that they can be
been dimensioned to withstand 20 A made gastight and watertight by means
r.m.s. for 0.5 seconds. of a ring seal and a number of bolts. The
ring seal and bolts stay in place even
In many applications, particulary in ur- when the top is removed, which sim-
ban networks, the high level of protec- plifies installation and maintenance
tion which has been described above is work considerably.
not necessary. A repeater variant has
therefore been developed for ZAD 2 - 4 The housing is fitted with a holder made
which meets the requirements of CCITT of expanded polystyrene, with the dif-
recommendation K.17 (1.5 kV and 37.5 A) ferent repeater positions marked. The
as regards overvoltages and which can connectors and units are locked in
withstand induced currents of a magni- place by a polystyrene disc placed in the
tude of 5 A r.m.s. for 0.5 seconds. top, and which is pressed against the
units when the top is put on.
Fig. 6 shows the mechanical con-
struction of the intermediate repeaters The stub cable is a 6 m lead-sheathed
The choice of power feeding arrange- cable with an outer sheath of poly-
ment is made by means of soldered ethylene and screened units with cross-
straps. The equalization range and fault stranded 0.5 mm PVC insulated pairs. In
localization addresses are set by means the housing the stub cable is connected
of plug-in U-links. to 10-pole connectors, which are plug-
ged straight into the repeaters. The con-
The cassette containing the repeater nection to the detector unit in the fault
consists of two parts and can easily be localization system is made with a sepa-
Fig. 6
A digital intermediate repeater for ZAD 2 - 4 with
extra overvoltage protection. The dimensions of
the cassette are 218x100x20 mm and it holds the
equipment for both directions of transmission.
The unit can withstand overvoltages of more than
5 kV without flash-over to the environment
rate cable. This cable is e q u i p p e d with The cables are stripped of their sheaths
four-pole connectors w h i c h are also in the housing and are jointed to the
plugged direct into the repeaters. c o n n e c t i o n cables, w h i c h are equipped
with 10-pole connectors. The jointing
The housings are pressure-tight to- and sealing between the housing and
wards the cable and the environment the line cable are carried out in the same
Fig. 7
Housing ZDD 53501 with the top removed. Holds and can be pressurized via the line cable way and using the same tools as for ordi-
3 two-way repeaters for ZAD 0.7-1 or ZAD 2-5. or an external valve. nary j o i n t i n g of the TUKA cables. This
Dimensions: 0 = 150 mm, h = 160 mm. Weight: has meant considerable simplification
approximately 10 kg when fully equipped, inclu-
and rationalization of the installation
ding the stub cable The housings are often placed in very
work. The j o i n t i n g m e t h o d was de-
corrosive environments, for example in
veloped in close collaboration with the
manholes or concrete boxes w h i c h may
Swedish Telecommunications Admin-
at times be filled with polluted water.
istration.
When placed above g r o u n d the hous-
ings can be subjected to temperatures
between - 4 0 ° and +50° C. All this puts All housings can be equipped with load-
great demands on the material and ing coil units for temporary re-loading
finish. The housings are therefore made or with t h r o u g h - c o n n e c t i o n units for
of acidproof, stainless steel. Housings testing the transmission pairs.
that are to be placed u n d e r g r o u n d are
coated with epoxy tar. Fault localization
A reliable and efficient system for lo-
The choice of material has meant that calizing repeater and cable faults is a
the weight of the housing has been re- prerequisite for e c o n o m i c a l mainte-
duced by about 50 % c o m p a r e d with nance of transmission systems. In view
older housings, w h i c h facilitates trans- of the often very difficult installation
port and installation. conditions in cities it is necessary to be
able to pinpoint the faulty equipment
Three types of housings are intended for directly.
jointing to conventional cables, figs. 7 -
9. The two larger ones also contain a The trio m e t h o d was long the most com-
fault detector and a service unit. mon fault localization m e t h o d , but it
Brackets and sun shields are available proved to be very unreliable. The main
for m o u n t i n g the housings on w o o d e n reason for this was that the method was
or concrete poles. based on measurements of analog
Fig. 10 quantities, w h i c h were affected by many
Housing ZDD 53502 for jointing to TUKA cable.
A similar housing is intended for joint- irrelevant factors. LM Ericsson have
Capacity: 2 two-way repeaters for ZAD 0.7-1 or
ZAD 2-5. Dimensions: 0 = 150 mm, h = 260 mm. ing to TUKA cables 3 , fig. 10. It is equip- therefore developed fault localization
Weight when fully equipped: approximately 3 kg ped with four input tubes for line cables. methods that are based on digital condi-
Fig. 8. left
Housing ZDD 53601 with the top removed. Holds
10 two-way repeaters for ZAD 0.7-1, ZAD 2-4 or
ZAD 2-5. Dimensions: 0 260 mm, h = 320 mm.
Weight: approximately 24 kg when fully equipped,
including the stub cable
Fig. 9, right
Housing ZDD 53701. Holds 24 two-way repeaters
for ZAD 0.7-1, ZAD 2-4 or ZAD 2-5. Dimensions:
0 = 400 mm, h = 320 mm. Weight: approximately
46 kg when fully equipped, including the stub
cable
Fig. 11
Fault localization in accordance with the loop
connection method
Fig. 12
Fault location instrument
The front is equipped with
- thumbwheel switches for addresses
- error rate indicator, the rate being given by one
digit
- switches for selecting the bit rate, 704 or
2048 kbit/s
- switches for selecting the line code, HDB3 or
AMI
- connectors for outgoing and incoming signals
and for external instruments
Technical data
Electrical data
Line signal
Bit rate
Code
Impedance
Pulse amplitude
Intermediate repeater
Equalization range
Power consumption per
two-way repeater,
Summary
typically The main features of LM Ericsson's new
Temperature range
line systems for 704 kbit/s and 2048
Power supply kbit/s transmission on pair cables are:
Primary current source
- a flexible network structure since the
Feeding of the inter- line systems complement each other
mediate repeaters - efficient fault localization systems for
Nominal regulated both urban and rural networks
current
Maximum output voltage - ability to withstand high overvoltages
- equalization well adjusted to different
Fault localization
Method
cable types
- low power consumption
Number ot station - high reliability through the use of
addresses modern circuit engineering
Mechanical data
- new housings that withstand aggres-
Line terminal
sive environments
Shelf dimensions - housings and intermediate repeater
Capacity per line equipment are easy to install.
terminating shelf
Housing
Dimensions, Oxh, mm
Weight fully equipped
Number of two-way
repeaters
2
A RECTIFIER FOR LARGE PLANTS
CENTRAL EXPERT SUPPORT FOR MAINTENANCE AND INSTALLATION
1981 ERICARE
ERICSSON REVIEW
NUMBER 2 • 1981 VOLUME 58
P U B L I S H E D IN S W E D I S H , E N G L I S H , F R E N C H
AND S P A N I S H W I T H FOUR I S S U E S PER YEAR
T H E A R T I C L E S M A Y BE R E P R O D U C E D
AFTER C O N S U L T A T I O N WITH THE EDITOR
Contents
50 Manufacture of Monolithic Circuits
56 Digital Transit Exchanges AXE 10
68 Time Division Multiplex for Telex and Data Transmission
74 Computer Controlled Interlocking System
81 A Rectifier for Large Plants
88 Central Expert Support for Maintenance and Installation
96 ERICARE
COVER
Inspection of silicon discs for monolithic circuits.
An intense, yellow light is used which makes it
easier to spot any defects
Manufacture of Monolithic Circuits
Oxidation
The cleaned silicon wafers are oxidized
by heating to approximately 1000 C in
an atomosphere of nitrogen, oxygen
and water vapour. Careful control of
time and the composition of the at-
51
ULFJERNDAL mosphere gives the desired oxide thick- and have dimension tolerances of the
EVA NOVAK
ness, approximately 1 ±0.05 fim, fig. 1. magnitude ±1 M m The circuit pattern is
AB RIFA
defined and reproduced pho-
Photolithography tographically. The circuit layouts forthe
The various elements in monolithic cir- different process stages are prepared
cuits are very small, down to a few /xm, with the aid of a computer and are trans-
ferred to masks, glass plates, which look
like photographic negatives. The glass
plates, which are first coated with a thin
chrome layer, are then covered with a
light-sensitive organic material called a
photo-resist. A step camera, which can
be programmed so that the glass plate is
moved in exact steps, is then used to
project a greatly reduced picture of the
circuit layout on to the glass plate by
means of ultraviolet light. When the
plate is developed the photo-resist is re-
moved from the exposed parts The
chrome layer is then etched away from
these parts.
Fig. 2
A flow chart for the manufacture of a monolithic
circuit
1. Substrate
2. Collector
3. Epitaxial layer
4. Insulation
5. Base
6. Emitter
7. Ion implanting
8. Plug
9. Oxide
10. Metal
Fig. 3
Equipment for applying photo-resist. At the rear a
pattern aligner
Fig. 5
Diffusion ovens in the RIFA factory
53
Process testing
The microcircuit manufacturing pro-
cesses are sensitive and the desired tol-
erances are close to the limits of what is
technically possible. It is therefore nec-
essary to carry out tests after almost
every process stage. The process test-
ing usually consists of measuring the
physical or electrical characteristics of
a special test wafer or an individual test
circuit on a wafer. Some characteristics
that are checked are the thickness of the
oxide layers, the thickness and re-
sistivity of the epitaxial layers, the re-
sistivity of the diffused layers, the di-
mensions of the etched patterns, the
guality of the metal layer and the param-
54
eters of the test transistors. The results uids, fig. 9. Thanks to the separate sup-
of the process testing are necessary to ply floors it is possible to carry out most
obtain the o p t i m u m settings for the vari- of the installation w o r k for new ma-
ous process stages. chines w i t h o u t causing pollution of the
m a n u f a c t u r i n g processes.
Wafer testing, assembly, final testing
A silicon wafer contains 2 0 0 - 2 0 0 0 iden- A separate part of the b u i l d i n g contains
tical integrated circuits, future chips. A fans, heat exchangers and filters for the
certain p r o p o r t i o n of them are accept- air treatment. There is also supervision
able. Since the subseguent m o u n t i n g and control e q u i p m e n t that monitors
and encapsulation is costly, all ICs must the continuity and purity of the supply of
be tested before the wafer is cut up. gases and liquids.
Stored program controlled test equip-
ment is used to carry out mesurements
at the test points on the ICs, fig. 8. A few Yield
hundred measurements is a typical The yield is a basic factor in all discus-
number, and the total test time per cir- sions c o n c e r n i n g the manufacture of in-
cuit is between 0.5 and 2 seconds. tegrated circuits. It is defined as the
Fig. 8
Detail of a test station proportion of accepted ICs out of the
After microscope inspection the wafers total number of circuits that it would be
are packed and sent for encapsulation. possible to manufacture from the mate-
The encapsulation is carried out in fac- rial used. The yield for different stages
tories in the Far East using materials and can also be considered, for example
work routines in accordance with RIFA from the handling, w a f e r t e s t i n g , assem-
specifications. The chip packages are bly and final testing stages.
tested for gas-tightness and the final
testing is carried out using stored pro- It is desirable to be able to calculate the
gram controlled test equipment. Any re- yield for a circuit in advance, so that the
marks concerning faults that have oc- importance and effect of different con-
curred in connection with the encap- struction parameters can be considered
sulation are brought to the notice of the before p r o d u c t i o n starts. Experiments,
encapsulation factory. The long-term manufacture of prototypes and previous
performance of the circuits is checked experience of similar designs are used
by means of accelerated testing with in- to decide statistically the parameters
creased voltage and temperature. that determine how the yield is affected
by process techniques and design rules.
The RIFA monolithic circuit
Wafer yield
factory A silicon wafer normally passes through
When describing the various process 1 0 0 - 2 0 0 different substages during the
stages it has been stressed that the pro- m a n u f a c t u r i n g process. The wafers are
Fig. 9 duction requires extreme cleanliness often handled manually by different
A supply floor in the factory
and also demands clean, filtered, people and can be d r o p p e d , broken or
cooled and dehydrated air, clean, de- scratched. Handling damage con-
ionized and filtered water and a large stitutes a not inconsiderable cost and
number of special gases, such as nitro- one aim is therefore to automatize the
gen, hydrogen and oxygen. These re- processes to a greater degree.
quirements are so stringent that they
have greatly influenced the design and Wafer probe yield
equipment of the RIFA factory for m o n o - The p r o d u c t i o n yield is determined by
lithic circuits. In addition the layout of the size of the circuit and the fault rate,
the premises has been made as flexible i.e. the number of imperfections per unit
as possible, in view of the rapid develop- of area in the basic material and produc-
ment of m a n u f a c t u r i n g techniques. The tion masks, and by the number of faults
ground floor of the building contains that are i n t r o d u c e d on the wafers during
plants for water purification and waste the m a n u f a c t u r i n g process. Faults oc-
water treatment, c o o l i n g compressors cur in groups along the edges of the
and stores. Two floors are used for the wafer and along surface scratches, as
manufacture of m o n o l i t h i c circuits and well as randomly. The larger the area of
two for the supply of air, gases and liq- a circuit, the larger the probability that
55
the circuit contains at least one fault cesses already include a number of au-
and must be rejected. The relation be- tomatic substages. It is also possible to
tween yield, circuit area and fault rate is work with large batches. A million tran-
illustrated in fig. 10. sistors can be built op on one three-inch
silicon wafer, and a few hundred such
Faults on a wafer can occur in the sub- wafers can be processed simul-
strate, epitaxial layer, photo-resist pro- taneously in a diffusion oven.
cess, diffusion, oxidation and metalliz-
ing. Pinholes in the oxide and irreg- The p r o d u c t i o n cost consists primarily
ularities in the crystal structure are of the cost of investing in machines and
some spot faults. Scratches and grind- eguipment, and not of material and per-
ing marks caused by impurities during sonnel costs.
mechanical grinding are line faults.
The main p r o d u c t i o n problems today
The most c o m m o n causes of rejection are how to assemble data, compile data
are random faults in photo masks and in an acessible form and evaluate them,
photo-resist processes. Such faults can control and supervise the processes
occur in any stage in the manufacturing and minimize the need of operators. In
process because of impurities in the en- view of the large number of process
vironment, careless handling or bad stages and batches in p r o d u c t i o n and
process control. However, new methods the relatively long m a n u f a c t u r i n g time,
for manufacturing masks, using elec- it is necessary to have a very well de-
tronic beam exposure, do not automat- veloped control and follow-up system.
ically reduce the fault rate. Information is required c o n c e r n i n g
every batch, each type of product, the
The yield can be improved by increasing number of wafers in the batch, the
the degree of automatization, by keep- equipment used for each individual pro-
ing the number of process stages low, cess, when each process was carried
by consciously aiming at a low fault rate, out, measurements and test values,
by improving production masks and yields and machine utilization.
processes in each stage and by improv-
ing the design of the circuit. RIFA therefore intends to use an on-line
process control and data collection sys-
Assembly yield tem for its manufacture of integrated
The assembly yield is defined as the pro- circuits. The yield can be improved
portion of faultless chips that have suc- when the process and product engi-
cessfully been mounted and encapsul- neers have better access to the relevant
ated. The yield is determined by such data. The dependence on operators can
factors as the type of package and n u m - be reduced by using m i c r o c o m p u t e r s
ber of pins. The b o n d i n g , i.e. the con- for process control as far as possible
nection of the pins to the outputs on the and by providing detailed instructions,
chip, isthe most labour-demanding part via data terminals, for each process in
of the m o u n t i n g . An assembly yield of the p r o d u c t i o n .
9 5 % is normal.
Fig. 1
A transit exchange in Kolding. Denmark, for 8000
junction lines
57
Fig. 2
An example of a network management action in
an AXE 10 network, aimed at reducing the effect
of an important route having been put out of
operation
^ _ ^ _ Ordinary route
_ ^_ Secondary route
_ Link from NMC (OMC) to AXE 10
Fig. 4
The s u b s y s t e m s that are u s e d in different types
of telephone e x c h a n g e s
Hardware
Regional software
• • • • • Central software
SYSTEM CORE
TSS Trunk and signalling subsystem, consisting of
function blocks associated with the connected
signalling systems
GSS Digital group selector subsystem, consisting of
a number of time and space switch modules and
clock modules for synchronization
TCS Traffic control subsystem, which contains pro-
grams and data for traffic routing, number
analysis and supervision of connection and
disconnection
OMS Operation and maintenance subsystem, com-
prising aids for the administration and supervi-
sion of AXE 10 exchanges
ADDITIONAL SUBSYSTEMS FOR DIFFERENT
APPLICATIONS
CHS Charging subsystem, containing function blocks
for pulse metering, toll-ticketing and accounting
between adminslstrations
OPS Operator position subsystem for manual hand-
ling of calls
CCS Common channel signalling subsystem, for ex-
ample for signalling in accordance with CCITT
signalling system no. 7
MTS Mobile telephone subsystem, interfacing with
base radio stations for traffic with mobile sub-
scribers 1
SSS Subscriber switching subsystem, which is divid- has been replaced by direct input of cide w h i c h of the optional subsystems
ed into groups of 2048 suscribers, with an are to be included in an exchange. The
extension module of 128 subscribers order data from a keyboard with a dis-
SUS Subscriber services subsystem, comprising play unit at the operator's position, fig. interfaces between the subsystems are
function blocks that vary depending on the
requirements for facilities over and above the 3. The operator fills in a f o r m , w h i c h is well defined, w h i c h means that the sub-
ordinary telephone traffic between subscribers systems can be further developed inde-
displayed on the screen, with the infor-
mation for each ordered call. The sys- pendently of each other 2 .
tem processes these data in order to
establish the desired c o n n e c t i o n . The Each subsystem c o m p r i s e s a numberof
handling procedure is simple and the function blocks, w h i c h can consist of
handling time short. The method offers just software or software and the con-
the possibility of new operator services. trolled hardware. In the latter case the
The operators' positions can also be re- software is divided between the central
motely connected, w h i c h gives consid- processor and a n u m b e r o f regional pro-
erable flexibility as regards the location cessors.
of the operators' room.
Fig. 4 shows all subsystems that are
Efficient aids for operation and used in any type of telephone exchange.
maintenance
Automatic supervision, built-in aids for The subsystems used in transit ex-
testing and fault localization and the changes are described below.
possibility of remote control of opera-
tion and maintenance functions help to
Control system
make the work more efficient and re-
duce the work load. The control system consists of a central
p r o c e s s o r a n d a n u m b e r o f regional pro-
Commands and printouts are f o r m u l - cessors w h i c h are placed together with
ated in the man-machine language, the e q u i p m e n t that is to be controlled,
MML, recommended by CCITT. Its fig. 5, A brief description of the control
structure is simple, and it is easy to han- system is given below. A more detailed
dle and simplifies the work. description will be given later in a sepa-
rate article.
Fig 5.
Central and d i s t r i b u t e d control
CP Central processor with duplicated central pro-
cessing unit, data store, program store, refer-
ence store and the associated software
RP Regional processors placed together with the
controlled equipment
59
board assembly very quickly. One pro- modified f u n c t i o n blocks can there-
cessor part works in the executive fore always be a c c o m m o d a t e d w i t h -
mode, handling the traffic t h r o u g h the out special correction areas being
exchange, and the other works in paral- needed. Extensions can be given the
lel in the standby mode. A fault in the necessary data areas t h r o u g h real-
executive part never has time to inter- location of the data store by means of
fere with the traffic since the other part commands.
is always ready to take control, and this
is done w i t h o u t any break in the opera- The central and regional processors are
Fig. 6 tion. The fault localization is carried out m i c r o - p r o g r a m m e d . This makes for very
The f u n c t i o n a l u n i t s in the c e n t r a l p r o c e s s o r
automatically. powerful machine instructions w i t h o u t
CPU Central processing unit
PS Program store complicating the hardware. The central
DS Data store The duplication also simplifies the intro- processor stores are also self-admin-
RS Reference store
MAU Maintenance unit duction of new f u n c t i o n blocks or the istering and have a pre-planning func-
modification of existing ones, since tion that calculates store addresses in
changes can be carried out in one part good time before they are to be used.
at a time. This increases the processor speed and
gives it a high data processing capacity.
A processor consists of central units,
CPU, data stores, DS, program stores, Complicated tasks that o c c u r relatively
PS, and reference stores, RS, fig. 6. The infrequently, for example digit analysis,
reference stores contain addresses to routing, tariff analysis and fault localiza-
the program areas in each function tion, are handled by the central pro-
block and the data areas in each store. cessor.
This addressing principle, w h i c h has
been described in detail in a previous Regional processors
article 3 , gives easy handling and great Simple tasks of a repetitive nature that
Fig. 7 software reliability, fig. 7, since occur frequently, such as signal sens-
The m e t h o d off a d d r e s s i n g in AXE 10 u s i n g the - t h e programs in a f u n c t i o n block can ing, d e c o d i n g of digit i n f o r m a t i o n , mea-
reference s t o r e only address the data areas in that suring time and operating relays, are al-
PSA Program start address block. This protects the other store located to the regional processors. They
BSA Basic start address
areas and prevents faulty addressing. also handle the control of input and out-
Each program signal from one function block to another
contains the block number of the addressed block. This All interworking with other f u n c t i o n put devices. A regional processor con-
number gives the start address of the program area in PS
allocated to this block and the required basic addresses blocks is carried out by means of pro- sists of a central processing unit, CPU, a
in RS. Each basic address indicates the data area in DS gram signals. A function block can data store, DS, and a p r o g r a m store, PS.
that contains the relevant type of data. This addressing
method permits automatic reallocationn of the programs therefore only get access to informa-
and data areas for the different function blocks
tion in the data area of another func- Two regional processors normally c o n -
tion block t h r o u g h questions and an- trol a number of equipment modules,
swers using such signals EM, w h i c h form a magazine group. An
- t h e address calculations are automat- EM contains a number of telephone de-
ic and are included in the normal read vices of the same type.
and write instructions
- t h e areas in the data and program
Maintenance
stores that belong to a certain func-
The maintenance unit, MAU, supervises
tion block are movable. Corrected or
the control system and is p r o g r a m m e d
to carry out automatically the necessary
actions when faults occur so that the
traffic handling in the exchange can
proceed u n i n t e r r u p t e d . The f o l l o w i n g
tasks must be h a n d l e d :
- f a u l t detection. The processors are
monitored and faults in printed board
assemblies and other disturbances
are detected and recorded automat-
ically
- f a u l t localization. The effects of a fault
are limited by the faulty unit imme-
diately being b l o c k e d . Diagnosis pro-
grams are then used to locate the
faulty printed board assembly
60
-checking that the fault-clearing ac- grams then pinpoint the faulty printed
tions carried out by the staff, e.g. board assembly
change of printed board assembly,
have had the desired effect. Input and output
The following types of input and output
The supervisory function utilizes the devices can be connected:
fact that all central equipment is dupli- -data display units with keyboards and
cated, that stores and buses also in- printers or typewriters for the input of
clude parity bits, that there are different commands and output of operating
types of store protection and time su- messages
pervision, that special routine tests are -cassette tape recorders and magnetic
carried out by both the central and the tape units for feeding in large amounts
regional processors and that abnormal of programs and data, and for feeding
data processing gives rise to an alarm. out charging data and other informa-
Fig. 8
tion for further processing.
The digital group selector When a fault is detected the faulty pro-
Speech data (or the incoming traffic direction cessor part is blocked while the other The input and output devices can be
Speech data tor the outgoing traffic direction continues with the traffic handling. The remotely connected via point-to-point
Incoming and outgoing speech directions for a
total of 16 first-order PCM systems faulty unit in the blocked part is then or switched data links. Output can be
Time switch module
Space switch module located and diagnosed. Diagnosis pro- made simultaneously to several devices
Sample store for the incoming speech direction in different places.
Sample store for the outgoing speech direction
sample in each speech direction is turn are synchronized with highly stable
stored in SSA, read from SSA to SSB, at external reference clocks or with clock
a time that suits SPM, and is finally signals from another exchange over
transferred from SSB to the time slot in PCM lines. The clock modules w o r k in
the o u t g o i n g PCM channel. parallel, and the time control is regul-
ated by regional and central software.
Each time switch module has
1 6 x 3 2 = 512 multiple positions for the
connection of 16 first-order PCM sys-
Traffic control
tems. 480 multiple positions are used for The traffic control subsystem, TCS, in
speech transmission and 32 for signall- AXE 10 is realized entirely in software.
ing and synchronization. When analog TCS controls and coordinates all ac-
lines are connected, all 512 multiple tivities in the exchange for the setting
positions can be used for speech trans- up, monitoring and d i s c o n n e c t i o n of
mission. One time switch module often calls. The B-number is transmitted to
gives suffficient capacity for the group TCS for analysis, routing and choice of
selector in small primary centres. secondary route. The setting up over a
free line in the chosen route is initiated
Group selectors with more than 512 from TCS, as is the digit and signal
multiple positions are equipped with a transmission for establishing the re-
space switch module, SPM. 32 TSM can mainder of the switching path. TCS also
be connected to an SPM, w h i c h can monitors the c o n n e c t i o n and controls
thus serve 5 1 2 x 3 2 = 3 8 4 multiple posi- the disconnection and exchange of sig-
tions. A TSM can be connected to sever- nals associated with this.
al SPM, with a m a x i m u m of four. Con-
necting each TSM to four SPM requiers The charging i n f o r m a t i o n for a call, the
a total of 16 SPM and gives a space B-number and perhaps also the A-num-
switch matrix with 128 inputs and 128 ber, are assembled in TCS and transmit-
Fig. 9
The digital group selector outputs. The m a x i m u m size of the g r o u p ted to the charging subsystem.
selector will then be 5 1 2 x 1 2 8 = 65,536
multiple positions. When a call is set up, the c o m b i n a t i o n of
incoming and o u t g o i n g route is also
The selector equipement is duplicated. analyzed. The analysis result and in-
All calls are set up along identical paths coming signalling i n f o r m a t i o n is used,
in two selector planes, and the final for example, for c o n n e c t i n g or disabling
choice of plane is made in the o u t g o i n g echo suppressors and to prevent pro-
junction line equipment, after a check hibited c o n n e c t i o n of satellite routes,
that both speech directions have been fig. 10.
t h r o u g h - c o n n e c t e d . This method en-
ables any call to be automatically TCS also controls the various cases of
switched over f r o m a faulty to a faultless operator handling and o p e r a t o r - c o n -
plane. trolled setting up of conference calls.
The group selector synchronization can The assembling in TCS of number analy-
be arranged, in different w a y s 2 4 5 . The sis, routing and traffic control facilitates
synchronization is ensured by three flexible traffic management. The data
identical clock modules, w h i c h in their for these f u n c t i o n s can be changed by
Fig. 12a
F u n c t i o n a l d i a g r a m of c o m o n c h a n n e l s i g n a l l i n g
in a c c o r d a n c e w i t h CCITT s y s t e m n o . 7
Fig. 12b
H a r d w a r e for c o m m o n c h a n n e l s i g n a l l i n g in ac-
c o r d a n c e w i t h CCITT s y s t e m n o . 7 in AXE 10
Speech channels
Signalling channel
Trunk and signalling subsystem
Terminal circuit tor first-order PCM systems
Digital group selector
Common channel signalling subsystem
Fig. 13
The system provides pulse metering or toll ticket-
ing
Box no. 1
OPERATOR FUNCTIONS
Call allocation. The calls are allocated to
certain operators' positions with considera-
tion given to the type of call, language group
etc
Call queue. If all operators positions are
engaged, the calls are put in queues for each
type of origin, language, category or similar
factor.
Direct completion. The call is set up while the
subscriber waits.
Delayed completion. The call is set up as soon that national calls are metered and toll- efficiently. In order to achieve this it is
as possible or at a prearranged time. ticketing is used for international calls. necessary to abandon the earlier meth-
Inquiry. This function is used, for example, If the metering method is used, a limited od of writing, sorting and distributing
when an operator must make an inquiry to number of subscribers can have their tickets, which is very time-consuming.
another operator in order to be able to set up
a call.
calls specified on request. There is also a need of new facilities, for
example to be able to pay for calls by
Transport. Used when a call has to be trans-
ferred from one operator to another during The price information can be obtained means of credit cards.
the setting-up process. as soon as a call is finished, which is of
Conference call. A call with several partici- particular advantage to hotels. Subsystem OPS contains functions for
pants, who are connected to centrally placed operator handling, and the system has
conference equipment.
Assistance operator funtions An assistance The account-settling facility is always been designed to meet this and future
operator can be connected in on international needed for international traffic and also demands. The operators are provided
calls, for example if there are language prob- for national traffic if the telecom- with data display units and keyboards,
lems. munications of a country are operated which can be connected to OPS either
Chief operator functions. The chief operator by several administrations. The settling direct or remotely via data links.
supervises the traffic intensity with the aid of of accounts is based on the measure-
queue indicators, ensures that a suitable num-
ber of positions are manned and redistributes
ment of the total number of call minutes Extensive ergonomic studies preceded
the traffic to the positions if necessary. over each route concerned. Alter- the designing of the operators' posi-
Automatic toll-ticketing charging. The charg- natively, in the case of national settling, tions. The environment has also been
ing information is stored on magnetic tape or and if the charging is handled by the taken into consideration. Recommend-
cassette tape. transit exchanges, the number of charg- ations for layout, lighting and colour
Immediate pricing. The price information is ing pulses per route can be counted. schemes have been prepared, fig. 14.
given to the A-subscriber directly after the
call.
The result is stored in the data store.
The operators positions can be used for
For safety's sake the charging and sett- all types of traffic. The chief operator
ling data in the data store are copied decides which type of traffic each oper-
regularly in the form of output to a cas- ator is to handle. The right type of calls
sette tape recorder. The ordinary read- will automatically be routed to an oper-
ing is carried out using a cassette tape ator's position when it is marked as at-
recorder or another I/O device as desir- tended.
ed.
When a call comes in, all available data
on the call are shown on the operator's
Operator handling display, arranged on a form. The A-sub-
Subscribers want rapid connection scriber number is shown if it can be
through the long distance network even transmitted from the local exchange.
when the calls are set up by operators. It The operator uses the keyboard to com-
is therefore essential that calls handled plete the form, mainly with the area code
Fig. 14
A recommended layout of operators' positions by operators can be set up quickly and and B-subscriber number. OPS auto-
with data display units and keyboards matically processes these data and initi-
ates the setting up of the call.
Fig. 15
The control room in the Kolding transit exchange,
Denmark
Fig. 16a
AXE 10 as an i n t e r n a t i o n a l e x c h a n g e
— Satellite circuits
iNational and international PCM circuits with
common channel signalling in accordance with
signalling system no. 7
- < National PCM circuits with channel-associated sig-
nalling, e.g. in accordance with signalling system R2
International analog lines with common channel
signalling in accordance with signalling system no. 6
— •' ' National and international analog circuits with
channel-associated signalling in accordance
with signalling systems R2 and 5 respectively
Circuits to base radio stations tor traffic to
mobile units
TSS Trunk and signalling subsystem
ETC-S Exchange terminal circuit tor satellite circuits
ETC Exchange terminal circuit for PCM system
ITC Incoming trunk circuit for analog traffic
OTC Outgoing trunk circuit tor analog traffic
BTC Bothway trunk circuit for analog traffic
GSS Group switching subsystem (digital group selec-
tor)
TSM Time switch module
SPM Space switch module
TCS Traffic control subsystem
OMS Operation and maintenance subsystem
CHS Charging subsystem
OPS Operator position subsystem
CCS Common channel signalling subsystem
ST Signalling terminal
Fig.1
Connection of ZATF 46 CD to the telecommunica-
tion network
TDM Time division multiplex equipment
DCE Data circuit terminating equipment
S MUX Multiplexor towards the synchronous data net-
work
69
ARTURO GATTA
GIORGIO SQUARTINI
FATMES.p A
Rome. Italy
Fig. 2
ZATF 46 CD used for circuits between two telex
exchanges other than AXB 20
TDM Time division multiplex equipment
normal 4-wire telephone channel, w h i c h as a c o m b i n e d local and transit ex-
can be a carrier channel or a physical change for both national and interna-
circuit for the frequency band 0 . 3 - 3 . 4 tional traffic. It is particularly suitable
kHz. for the c o n n e c t i o n of remote subscrib-
ers via concentrators or multiplexors
If required, a 2400 bit/s baseband such as ZATF 46 CD, since it contains a
modem can be used instead of the inter- built-in multiplexor and m o d e m . This
nal data modem, fig. 1, for transmission means that no channel interface units
over physical circuits. are needed on the exchange side 2 3 .
Two or four ZATF 46 CD systems can ZATF 46 CD contains functions for the
also share a telephone channel equip- operation and maintenance of unat-
ped with a modem for 4,800 bit/s and tended system terminals. One of the 46
9,600 bit/s respectivley. channels in the system is then used as a
maintenance channel for the necessary
The TDM equipment can also be con- signalling.
nected to a higher order multiplex, for
instance by using a multiplex. S MUX. in Lines to teleprinters can be c o n n e c t e d
accordance with CCITT Recommen- in three ways:
dation X.50, fig. 1. A DCE must then also - d o u b l e current in full duplex. 4-wire
be used. The e n c o d i n g format is 6 + 2 circuits on two wires with an earth re-
bits and the bit rate of the data signals is turn circuit
Fig. 4
ZATF 46 CD used to connect another telex 3.2 kbit/s in the baseband. S MUX allows - s i n g l e current in half duplex on 2-wire
exchange or remote subscribers to LM Ericsson s 20 data channels at 3.2 kbit/s to be multi- circuits
telex exchange AXB 20 plexed to a standard 64 kbit/s digital - V . 2 1 subscriber modems in full duplex
TDM Time division multiplex equipment channel for PCM. The total capacity is on 2-wire circuits.
•) One of the 46 channels is used for mainte- then 920 channels for 50 bauds.
nance. The telegraph signals c o m i n g from each
System operation subscriber or from the telex exchanges
have a standardized speed and charac-
System ZATF 46 CD is primarily intended ter structure, since 7.5 unit elements (20
for use in telex networks, figs. 2 and 3. It ms) and the international telegraph al-
is very suitable both for connections be- phabet no 2 are used.
tween telex exchanges and for remote
connection of g r o u p s of subscribers to A central logic device in the TDM scans
an exchange. Fig. 4 shows how the sys- the channel inputs in turn, and a f t e r s i g -
tem is connected to the LM Ericsson nal generation c o m b i n e s the signals for
telex exchange AXB 20. all the 46 channels into a single bit
stream. The resultant signal, with a bit
AXB 20 is a stored program controlled rate of 2.4 kbit/s, is then taken to the
exchange for telex and asynchronous internal m o d e m , w h i c h converts it to a
data traffic. It has been designed for use VF signal for transmission over the line.
Fig. 3
ZATF 46 CD used to connect remote suscribers to
a telex exchange other than AXB 20
70
Connection panel
Data modem
Data modem
Fig. 8
ZATF 46 CD for single current working
Fig. 6, left
Central logic unit
Fig. 7, right
Service unit
Fig. 9, left subscriber equipment. The unit is e- takes place when this particular unit is
Channel interface unit for double current and
quipped with efficient lightning protec- addressed.
high voltage
tion.
Fig. 10, right The strapping field, fig. 12, permits indi-
Channel interface unit for single current Double current and low voltage vidual strapping of each channel as re-
This unit is designed for matching to gards speed and code structure.
new electronic telex exchanges having
an interface in accordance with CCITT The information in the strapping field
Rec. V.28. In this case the voltage is can be transferred to the central unit
±12 V and the line current not more store by pressing a reprogramming but-
than 12 mA ton. It is then possible to remove the
strapping board for changes without
Single current disturbing the operation of the equip-
This unit, fig. 10, is designed for a nomi- ment. This gives the system complete
nal current of 40 mA and ±60 V voltage flexibility and the possibility of re-
and has efficient lightning protection. programming on site.
VF signalling in accordance with
Recommendation V.21 The action to be taken in the case of a
This unit is designed for V F signalling multiplexor fault can also be arranged
using frequency shift modulation. by means of straps. The following three
alternatives are available:
Central logic equipment -switching over to steady start polarity
The central logic unit consists of a cen- -switching over to steady stop polarity
tral processing unit, astore, a multiplex- -switching over to steady start polarity
ing unit, a demultiplexing unit and a after loop connection of the channel
strapping field. towards the local end for 5 seconds.
Fig. 12
Strapping field
The channel interface units are con- All timing information is derived from a
nected to the central unit via buses. Fig. central crystal-controlled clock. This
13 shows a simplified block diagram of timing gives scanning of every channel
the system. In this diagram three buses input at the centre of each unit element,
are shown: the address bus and the counted from the beginning of the start
send and receive data buses. Exchange element, and forming of a common sin-
of data with a channel interface unit gle bit stream.
Fig. 11
Simplified block diagram of ZATF 46 CD
Fig. 13
Simplified block diagram of ZATF 46 CD with a
supervision unit
Technical data
Type of system Code and speed de-
pendent time division
multiplex in accor-
dance with CCITT
Recommendation A bit interleaving multiplexing tech- The same type of exchange of messages
R.101
nique is used in order to achieve mini- is used when a remote multiplex is oper-
System capacity mum transfer delay Two different code ating in c o n j u n c t i o n with AXB 203-4.
-Alternative A Modula- Number of
structures can be used as recom-
tion rate, channels
bauds mended in CCITT Recommendation Data modem
50 46 R.101. The modem equipment operates at a
75 22 data rate of 2,400 b i t s , synchronously
-Alternative B Modula- Number of The 2400 bit/s bit stream is converted over 4-wire telephone lines The m o d e m
tion rate, channels from TTL levels to the electrical charac- interfaces are in accordance with CCITT
bauds
teristics specified in CCITT Recommen- Recommendations V.24. V.26 and V.28.
50 46
75 30 dation V.28. This is the standard inter-
150 or face between the multiplex equipment
1345 22 and the external or internal data
100 or 110 15 modem.
200 10
300 7
Supervision equipment
Speed tolerance Max. + 2 % for 50 and
75-baud signals. The supervision unit, w h i c h contains a
Max. +1.8% for all microprocessor, is a powerful device for
other permitted speeds monitoring and fault tracing. It is par-
Highest acceptable ticularly useful when one ZAFT 46 CD
distortion of the unit terminal is unattended.
pulse to the receiver 46.6%
Maximum start-stop
distortion at the One of the 46 channels in the circuit is
channel output 3% used as a maintenance channel, fig. 12.
Types of channel in- This allows the supervision unit to
terface units -Double current, high check the operation of the system. The
voltage quality of the incoming telegraph sig-
-Double current, low
nals can be monitored and open line
voltage
-Single current conditions detected. If there is an alarm References
-V.21 signalling at the far end terminal, for example if the 1. CCITT: Recommendation R.101.
distortion exceeds a preset value or Orange Book, Vol. VII, Geneva 1977.
Channel interleaving On a bit basis 2. Strindlund, E. et al.: AXB 20-All
Bit rate after multi- there is an open line, the supervision Electronic. Stored-Program-Con-
plexing 2,400 bit's unit sends a message to the attended trolled System for Telex and
Internal data modem multiplex. The message includes the Asynchronous Data Traffic.
Modulation method Differential 4-phase. number of the affected channel. Ericsson Rev. 54 (1977):1, pp. 3 2 -
code A or code B 40.
Line connection 4-wire 3. Strindlund, E. et at.: AXB 20~De-
Nominal impedance, The near-end supervision unit receives scription of System. Ericsson Rev.
line side 600 ohms the alarm message and displays it on an 54(1977):1, pp. 4 1 - 5 1 .
Send level limits -0.5 and - 4 6 d B m indicator. It also records the number of 4. Logdberg, L.E. et al.: AXB 20-Op-
Receive level limits - 3 and - 4 3 dBm eration and Maintenance Charac-
resynchronizations and on request teristics. Ericsson Rev. 55(1978):3,
Power supply transmits this information to the remote pp. 106-112.
Mains voltage 220 V terminal. 5. Gatta, A. et al.: Sistema TDM per la
Limits + 10 and - 1 5 % transmissione di segnali telegrafici
Frequency 45 and 65 Hz e dati tipo ZATF 46 CD. Not. Teen.
Battery voltage 48 or 60 V Subscriber equipment can be tested FATME No. 23, June 1978.
Limits +20and - 1 5 % from the supervision unit, w h i c h then 6. Squartini, G.: Sistema TDM per la
Rack transmits a special distorted test mes- transmissione di segnali telegrafici
Height 2.600 mm sage. Similarly it can also check a dis- e dati. XXV International Scientific
Width 120 mm Meeting on Electronics, March
torted message received from the sub- 1978, Rome.
Depth 225 mm
scriber.
Computer Controlled Interlocking
System
Fig. 2
The LM Ericsson computer UAC 1610 P for stored
program control of the signal box for the Malmo
railway yard area, in south Sweden
75
HANSS ANDERSSON
GUNNAR HAGELIN
computer control for the interlocking Control and supervision
Signalling Systems Department
function makes the matching to the re- subsystem
Telefonaktiebolaget LM Ericsson mainder of the signalling equipment
easier. The overall cost is lower, not only In the new interlocking system colour
for the equipment itself but also for the displays replace the old type of indica-
planning and installation. tion panels, where lamps were used to
indicate train positions, signal condi-
The trackside devices, such as track cir- tions, point positionsetc. Each operator
cuits, points, signals etc., are connected now has a work position with two dis-
in groups to concentrators, which are play units and a keyboard which is used
then connected, via transmission links, to give all commands, figs. 4 and 5. One
to the interlocking computers. Mes- display gives an overall picture of the
sages are transmitted in both directions supervised track area, and the other
in serial form, and each message is sup- gives detailed information for a selected
plemented with redundant information part of the track.
in order to ensure fail-safe function.
Different types of alarms are also shown
The system comprises (see fig. 3): on the display units, and the operator
-control and supervisory subsystem can enter commands via the keyboard
-interlocking subsystem to display alphanumerical information
-transmission network between the in- concerning a particular alarm.
terlocking subsystem and the track-
side concentrators The system also permits automatic com-
-subsystem for interfacing between the mands. Such commands are pro-
concentrators transmission terminals grammed in advance and are released
and the trackside devices. when certain conditions are met. The
operator can also compile automatic
The first two subsystems are computer functions himself, for example for fre-
controlled and the computers are dupli- quently recurring shunting movements.
cated to ensure availability. The trans-
mission network is supplemented with Commands to the interlocking system,
alternative routes. forexample the setting up of a train rou-
te, are always reviewed before the inter-
A documentation system, which uses a locking system starts to arrange safe-
separate computer has also been de- guards, block devices, change points
veloped for the planning of installations. etc. This is done to prevent the system
Fig. 3
The main parts of the interlocking system
Fig. 4
The control office for the Gothenburg railway
yard area, western Sweden
Fig. 6
The processing stages during an operating cycle
Fig. 7
The basic principle of the geographical method
77
tion. The conditions are described in ac- - s t a t e the type of train route that is to be
cordance with the geographical meth- established, and w h i c h c o m m a n d the
od, which means that they are related to locking of the route
the various trackside devices: points, - i n d i c a t e the type of flank protection
signals, derailers etc.' For each device and the length of the overlap area re-
the conditions for every possible state quired for the train route
and every possible change of state are - i n f o r m that flank protection and over-
set. Fig. 7 shows the geographical meth- lap protection are achieved
od in principle. Each device has an asso- - i n d i c a t e clear track along the train
ciated block with interfaces towards route, in the overlap area and in the
- t h e control system flank protection areas
- t h e trackside device - s t a t e the m a x i m u m speed for the train
- t h e blocks for the "geographical route
neighbours ". - c o n t r o l the level crossing devices
Fig. 8
- r e l e a s e the devices in the train route
A set train route is marked with a green line on The interfaces towards the neighbours
the display -creen and a shunting route is when the train has passed.
are the same for all devices, whereas the
marked with yellow or blue alternatively
interfaces towards the control system
and towards the trackside device are the Types of blocks
same for each type of device.
For each block there is a description of
When a train route is set up, figs. 7 and 8. how the block must react to an incom-
the block for signal C receives an order ing message, and w h i c h messages the
from the control system to seek the nec- block is to send to its neighbours, its
essary protection for the train route, so own device and the control system.
that c o m m a n d to show green light can
be sent to the signal. At the same time The system contains the f o l l o w i n g eight
the other blocks in the train route are types of blocks:
ordered to assume states that form the - s i g n a l blocks for signals
conditions for establishing the route. - a d v a n c e signal blocks for indepen-
Forexample, signal D is ordered to form dent advance signals
the end point of the train route, w h i c h in - p o i n t blocks for points and stop
its turn means that signal D must seek blocks
the necessary protection for the overlap - c r o s s s i n g blocks for track crossings
area beyond the signal. Messages are - r o a d blocks for level crossing devices
then exchanged between the blocks in - b o u n d a r y blocks for the boundary to-
accordance with the p r o g r a m , and the wards areas w i t h o u t interlocking
blocks successively change state until -line blocks forming boundaries
the states of the whole chain of blocks in against lines between stations and
the train route agree with the interlock- against other signal box areas
ing conditions. The changes of state of - o b s t a c l e blocks, w h i c h add depen-
the blocks also mean that the points in dence on extra track circuits.
the train route and the flank protection
are set and locked in the correct posi-
Processing of blocks
tion etc. When all this has been c o m -
pleted, all conditions for the train route The conditions for each type of block
have been fulfilled and the block for sig- are described by a number of equations
nal C can send a c o m m a n d to set the in algebra that is similar to Boolean al-
signal to " c l e a r " . gebra, fig. 9. However, each variable can
normally take up more than two values.
The messages that are exchanged be-
tween blocks w h i c h are geographical When processing a block, for example
neighbours can be divided into the fol- signal block D, the computer program
lowing categories, namely messages uses the equations that apply for signall-
that ing blocks on the data of signal D, fig.
IF(K.EQ.4.AND.(P1.EQ.2.OR.P1.EQ.3).AND.R0.EQ.1.AND.
Fig. 9
*(PK.NEJ.0R.R6.EQ.1.AND.(U2.NE.8.0R.
An equation that describes a sub-condition for a *I205.EQ.0,AND.T2.EQ.0)))R6=1.
device
Fig. 10
The basic principle ot the processing of the data
concerning an object block
10. The processing, including the ex- can be served to less than the total ad-
change of messages with neighbouring dressing capacity. Two important pa-
blocks, continues until the equations rameters in this connection are the in-
have been satisfied and have resulted in terdependence of the devices and the
- a change of state for the block in ques- number of simultaneous train move-
tion ments in the track area served.
- a change of state for the geographical
neighbours The exchange of messages between the
-the necessary commands to the de- interlocking computer and the con-
vice associated with the block centrators is serial in half duplex form
-information to the control system. over two-wire circuits. The transmission
rate is 4,800 bit/s. Two concentrators
Fig. 11 can be connected to each two-wire cir-
Transmission terminal and interfacing relay units Transmission network cuit. The transmission terminals can be
in a concentrator
Concentrators are placed in the track reached from the computer via two al-
area near groups of devices. Each con- ternative routes.
centrator contains interfacing equip-
ment for the various devices and a trans- The exchange of messages must meet
mission terminal, fig. 11. The system is the fail-safe requirement. Each mes-
dimensioned so that each terminal can sage therefore contains a number of
serve 24 track circuits and 31 other de- check bits in addition to the actual infor-
vices. The system can address 64 termi- mation, which ensure that distorted
Fig. 12 nals. However, the cycle time, one sec- messages cannot be misinterpreted and
The format of telegrams between the interlocking
ond, limits the number of devices that cause danger. Fig. 12 shows the struc-
computer and the concentrators
79
ture of the messages to and from the - t h e point is locked in the normal posi-
interlocking computer. tion
- t h e point is released for local opera-
tion.
Trackside interfacing
equipment
The equipment for interfacing towards
the trackside devices is realized in con- Fail-safe function
ventional relay technology. It also in- The useof c o m p u t e r s in equipment with
cludes relays for the d e c o d i n g and fail-safe function requires a system de-
checking of orders from the interlock- sign that can never set the controlled
ing system. In addition it contains equip- devices in dangerous positions, even if
ment for e n c o d i n g the information faults occur in the hardware or the soft-
about device states that has to be sent ware. Thus the data processing that
back to the interlocking system, fig. 13. leads to such c o m m a n d s as " c l e a r " for
Fig. 13
Block diagram of the interfacing circuits for a signals is always carried out in t w o sepa-
trackside device For example, for a point the f o l l o w i n g rate program sequences, and the results
information is exchanged between the must be compared outside the c o m p u -
interlocking system and the interfacing ter oefore the c o m m a n d can be ex-
equipment: ecuted, fig. 14.
E
Project planning system The G o t h e n b u r g yard area is extensive
and includes a large number of pas-
A project planning system is used to pre- senger stations as well as goods, har-
pare installation d o c u m e n t s and the in- bour and industrial yards. Before the in-
dividual data for the control computers. stalltion of the new system the five
An off line computer is used for the pro- passenger stations had individual signal
ject planning system. The input data for boxes. These were w o r n and the opera-
this system are specified on standard- tion was very personnel-demanding.
ized forms by the customer's project The goods yards, and the tracks be-
planners. The input data consist mainly tween them, lacked adequate safety ar-
of information c o n c e r n i n g the structure rangements, w h i c h meant that a large
of the track network and the individual staff was required for the traffic hand-
characteristics of the yard devices. ling and that the traffic capacity was
low.
The system provides
- d a t a files for the control computers With the new system the traffic control
- i n f o r m a t i o n f o r t h e installation of con- and the safety interlocking have been
Fig. 15 centrators, cabinets, cables etc. centralized to one place, fig. 4. The
The control office for Malmo railway yard area - m a t e r i e l lists. trackside devices are successively
being connected into the system. At
The project planning system is also present over 600 devices are under con-
used to plan extensions, handle version trol, i n c l u d i n g 115 points, 216 signals
numbering etc. The data c o n c e r n i n g and 203 track circuits. The central
each installation are stored in a data equipment c o m m u n i c a t e s with the de-
base. vices via 15 concentrators. When fully
extended the installation will comprise
Installations about 1,200 devices.
Interlocking systems of the type de-
scribed above are in operation in The Malmo installation will comprise
Gothenburg and Malmo yard areas. three passenger stations, two of which
were completed in February 1981 and
which contain about 330 trackside de-
Trial operation started in a small part of
vices, including 40 points, 145 signals
the Gothenburg yard area in May 1978.
and 110 track circuits. The d c ices are
The results were satisfactory, and after
connected to the central equipment via
minor modifications to the program sys-
nine concentrators.
tem the installation was extended in
November 1979 to include the central
parts of the yard area.
References
1. Andersson. H.S.: Railway Signall-
ing Systems. Ericsson Rev. 57
(1980):4, pp. 118-123.
2. Sjoberg. A.: Automatic Train Con-
trot. Ericsson Rev. 55(1981)' 1 pp
22-29.
for Large Plants
Fig. 1
Power supply system BZD 412.
The picture shows, from the left, distribution rack
BMG 651, a rectifier BMT 343 with front cover, a
rectifier without the front cover and two 400 A
converters, BMR 273. Each rack has the dimen-
sions 600x600x2200 mm
LEIFHANSSON Function in the system Technical description
RENZOSANTI
Power Supply Department The rectifier, BMT 343, can be used in The rectifier consists of the following
Telefonaktiebolaget LM Ericsson different power supply systems con- units:
taining batteries, fig. 2. During opera- - d . c . c o n t r o l l e d c o n t a c t o r for connec-
tion the battery is float-charged in the tion to the a.c. mains
conventional way. The rectifier voltage - t w o transformers for transforming
is kept so high that the self-discharge of d o w n to a twelve-phase secondary
the battery is c o m p e n s a t e d . voltage
- t h y r i s t o r s with control circuits for the
rectifying f u n c t i o n
After a heavy battery discharge, for ex-
- i n t e r p h a s e transformers for con-
ample after a mains failure, the rectifier
necting together the neutral points in
output voltage is raised to the recharg-
the star w i n d i n g s of the secondary
ing level. When the battery is fully re-
sides
charged, the voltage is decreased to the
- a filter for s m o o t h i n g the d.c. voltage.
float level. The state of the battery is
monitored continuously by automatic
The rectifier also contains devices for
charging equipment, previously de-
operation and alarm, m o u n t e d on the
scribed in Ericsson Review 2 .
front, and circuits for receiving and ex-
ecuting remote control commands.
Several rectifiers can be connected in There are also internal protective de-
parallel and the current load is then vices w h i c h disconnect the rectifier in
shared equally between them. Step- the case of overvoltage and then auto-
connection equipment can also be matically start it up again. In addition the
used, which connects and disconnects rectifier contains phase failure protec-
rectifiers according to the load. This tion and electronic fuse alarms.
step-connection equipment is only
provided where the current c o n s u m p - Rectifier circuit
tion varies considerably. The three primary w i n d i n g s are star-
connected in o n e t r a n s f o r m e r a n d delta-
Special Master Voltage Control (MVC) connected in the other, fig. 3. The sec-
equipment is used in very large systems ondary w i n d i n g s of each transformer
if the power supply is sectioned. MVC is are connected as two three-phase stars
connected to the rectifier group in each with 180° phase shift between them. In
section and provides them with correc- this way each transformer gives six pha-
tion signals, so that the different parts of ses with 60° shift relative to each other.
the powered t e l e c o m m u n i c a t i o n s plant The different c o n n e c t i o n s of the respec-
receive exactly the same voltage from tive primary w i n d i n g s to the mains mean
each rectifier group. The rectifier design that the two six-phase stars have a pha-
also allows for control from a cen- se shift of 30 and thus the overall result
tralized microcomputer supervision is a twelve-phase star with 30 : between
system. the phases.
Fig. 2
Power supply system BZD 412 with thynstor
rectifiers BMT 343 and high-frequency booster
converters.
The block diagram shows the position of the
various units in the system
83
On thesecondary side the neutral points two electrolytic capacitor banks with
of the two stars in each transformer are fuses in the shunt branch, an LCL filter.
connected to an interphase trans- The a.c. voltage component is attenu-
former. The centre points of the two in- ated in two steps in the filter, first by the
terphase transformers are then con- choke nearest the interphase trans-
nected to a third interphase trans- former and the capacitor banks, then by
former, the centre point of which con- the second choke and the battery. The
stitutes the negative pole of the rectifier. chokes limit the ripple current, and the
capacitor and battery shunt the current,
The interphase transformers maintain so that the resultant noise voltage at the
the voltage differences that occur be- output across the battery is very low.
tween the neutral points of the stars and
constrain the current to divide equally A fuse which also functions as an isola-
between the two halves of the windings. tor is included in the rectifier output
This means that each three-phase star When the rectifier is to be connected to
will contribute a quarter of the total cur- the battery, the filter capacitors must be
rent. There is no d.c. magnetization of charged before the fuse is inserted. This
the interphase transformers since the charging is carried out automatically by
currents in their two winding halves are a special circuit. An LED indicates when
equal and oppositely directed. the charging is completed. Slow charg-
ing is necessary, otherwise the large ca-
The rectifier consists of twelve thyris- pacitor banks would experience a cur-
tors. one for each phase. Each thyristor rent surge that could shorten their life.
normally conducts for a third of the Furthermore the filter capacitor fuses
mains cycle, i.e. the conducting angle is would not withstand a rapid charging.
120°. This means that four thyristors,
one in each three-phase star, conduct On the d.c. side the rectifier satisfies the
simultaneously. The peak current radio interference requirements of
through each thyristor is thus a quarter CISPR Recommendation No 43 On the
of the output current. mains side, radio interference suppres-
sion filters are not standard but can be
The output voltage from the inter-con- included in the rectifier as optional ex-
nected thyristors is a d.c. voltage with a tras.
ripple frequency that is twelve times the
mains frequency, namely 600 Hz. This Control circuits
high ripple frequency means that the Voltage-control of the rectifier is
smoothing filter that follows can be effected by changing the trigger phase
made with small mechanical dimen- angle of the thyristors so as to keep the
sions. The filter isaT-type low pass filter output voltage constant. When the out-
with chokes in the series branches and put current exceeds the rated value, the
Fig. 3
The rectifier circuit.
Three-phase mains voltage is fed to the two
transformers via the mains contactor. The thyris-
tors in the thyristor unit rectify and control the
voltage, which is then smoothed in the filter unit.
The thyristors receive trigger pulses at the cor-
rect instants so that the output voltage is kept
constant
Fig. 5
The printed board assemblies with the control
circuits. At the top the printed board assembly tor
the internal power supply, below those for all
control circuits
Filter unit
Interphase
transformer
unit
Further short-circuit protection is is prevented by a phase failure protec-
provided by two cartridge fuses, which tion, which blocks the thyristor trigger
protect the transformers and current pulses and gives an alarm if there is an
measuring shunts against short circuits interruption in any of the phases. Re-
Thyristor unit in the thyristor unit. start is carried out automatically when
the fault has been cleared
The rectifier has a selective overvoltage
protection c o m b i n e d with automatic re- All fuses in the rectifier are supervised
start, fig. 6. If the output voltage exceeds by an electronic circuit, w h i c h discon-
Mains c o n - a predetermined level, the thyristor trig- nects the mains contactor and gives an
tactor ger pulses will be momentarily blocked, alarm for a blown fuse
thereby cutting off the power output
from the rectifier The rectifier is then Operation
restarted in the walk-in mode. If the The rectifier can be operated directly or
Transformer overvoltage recurs and at the same time remotely.
unit the current from the rectifier exceeds a
certain value, the rectifier will be com- Direct operation is by means of push-
pletely switched off via the mains con- botton switches placed on the front of
t a c t o r a n d an alarm given. Current sens- the rectifier With direct operation it is
ing is carried out in order to achieve possible to
selectivity. The rectifier that causes the - c o n n e c t and disconnect the rectifier
overvoltage will be delivering all of the - i n c r e a s e the output voltage for battery
Fig. 7
current to the load. This means that the charging
A complete rectifier.
The units are installed and the cabling is done rectifiers which have overvoltage on - r e s e t alarms
from the front their output but do not deliver current - t e s t the overvoltage protection
have not caused the overvoltage These
rectifiers therefore do not have to be Remote operation is carried out over a
disconnected. cable plugged into the rectifier. With re-
mote operation it is possible to
Automatic restart effectively prevents - i n c r e a s e the rectifier output voltage
spurious shut-downs due to voltage for battery charging
transients of external origin, for exam- - c o n t r o l the rectifier output voltage so
ple caused by a fuse b l o w i n g . that it follows an external voltage
(MVC)
If an interruption occurs in one phase, - b l o c k the thyristor trigger pulses and
the rectifier w o u l d work as a single-pha- thus obtain momentary disconnection
se rectifier with a risk of overloading the - o p e r a t e the rectifier mains contactor.
thyristors. Moreover the noise voltage at for example with control from a step
the rectifier output w o u l d increase. This connection device.
Overvoltage limit
Output voltage (vol-
tage across the bat-
tery)
Output current
Fig. 6
The operation of the overvoltage protection. Current limit
If the rectifier output voltage becomes too high,
the rectifier is first blocked momentarily, then
restarted. If the overvoltage recurs, and at the
same time the current exceeds a certain preset
value, the rectifier is completely disconnected.
However, no disconnection takes place if the
rectifier operates normally after the restart. Thus
transients cannot cause disconnection
Mechanical construction three printed board assemblies for the
The rectifier is m o u n t e d in a rack, BAF control electronics, an ammeter and all
201, with dimensions 6 0 0 - 6 0 0 - 2 2 0 0 secondary circuitry for the plug in con-
mm, fig 7. It is covered with three front nection of the other units.
plates. The six units in the rectifier rack
are mounted in the f o l l o w i n g order The interphase transformer unit con-
(from the bottom): transformers, mains tains the three transformers and two
contactor, thyristor unit, interphase fuses. The filter unit contains the two
Fig. 8
transformers and filter unit. The rack chokes, the electrolytic capacitors, the
The transformers are equipped with wheels, sides are equipped with guide rails, so 500 A output fuse and the capacitor
which simplifies their handling during installa- that the units, with the exception of the charging circuit.
tion. The front cross-member of the rack is transformers, can be slid in and out of
removed when the transformers are installed.
the rack. The units are cooled in accor-
Clear labelling ensures correct connection to the
dance with the parallel c o o l i n g princi-
Installation, operation and
secondary side. The fixed cables on the primary
side are connected direct to the mains contactor ple, which means that there are several maintenance
air inlets in the front panels. Simple and quick installation was one of
the main aims when designing the rec-
The transformers are placed direct on tifier. It is delivered f r o m the factory in
the floor, fig. 8. They are mounted on fully tested, easy-to-handle units. The
wheels, which simplifies installation rectifier is connected to the system bus-
and reduces acoustic noise (hum) dur- bars by means of bar contacts, fig. 10.
ing operation. Fixed cables on the p r i m -
ary side of each transformer are con- The installation only requires ordinary
nected to the mams contactor. The hand tools, and the installation testing is
secondary side has a terminal strip with reduced to a visual inspection to detect
screws to fix cable lugs. any transport damage, followed by a
functional test.
The thyristor unit contains four heat
sinks on which the twelve thyristors are The rectifier w o r k s wholly automatically
mounted, fig. 9. At the front of the unit a and all operational changes take place
cassette is mounted which holds the without any manual intervention.
Fig. 9. left
The thyristor unit, the control circuitry and cable
connections to the other units can easily be
pulled out from the rack The components are
then accessible for measurements and service
Lars Estberger
LM Ericsson's telephone exchange sys-
LM Ericsson s stored program controlled telephone exchanges are equipped tems have long been well-known forthe
with a fault diagnosis system which gives detailed information on how to clear small amount of effort needed to main-
any faults that may occur in the exchange hardware. The fault clearing is usually tain the equipment. High reliability and
simple and a matter of routine. However, expert assistance may be necessary for comprehensive supervision equipment
rare faults of a complicated nature. Such assistance is normally organized with g o o d coverage permit controlled
centrally within the country, but during an introductory stage it may be desirable corrective maintenance 1 . The introduc-
to be able to consult an external group of specialists. In this article a description tion of stored program control (SPC)
has ied to further improvement of the
is given of the expert support provided by LM Ericsson in Stockholm. Sweden, in
maintenance f u n c t i o n s . LM Ericsson's
the form of guidance for complicated fault tracing. The expert support can also
SPC exchanges have a very extensive
include regular inspections of telephone exchanges to determine the condition maintenance system, with automatic
of the equipment and to locate any faults. Assistance can also be provided for analysis and reporting of equipment be-
processor installation and extensions. haviour. The maintenance functions in
system AXE 10 and the centralization of
UDC 621.3.95.34.004.5 the maintenance f u n c t i o n s in a tele-
phone network have been described
previously 2 3 .
LARSESTBERGER
Telephone Exchange Division In SPC exchanges the control functions c o m m o n support centre for an admin-
Telefonaktiebolaget LM Ericsson are primarily realized in software. The istrative area such as an entire country.
powerful processors run extensive diag- Such a maintenance support centre
nostic programs. Normally only a lim- (MSC) is e q u i p p e d with all necessary
ited number of faults occur in such ex- documentation and the special instru-
changes, and the majority of these are ments and test equipment required for
automatically identified and reported to complex fault localization.
the maintenance staff. This has sim-
plified the maintenance work consider- Having a centralized team of experts
ably, and it iscomparatively easy to train makes it easier for the specialists to
maintenance staff for these routine keep their system knowledge up to date,
tasks. At same time, the possibility to since it gives them the opportunity of
improvise the maintenance w o r k has more regular fault localization. This is
largely disappeared, and hence it is suit- very important, since there are other-
able to divide the tasks a m o n g person- wise few opportunities for practical
nel groups with different training. training in complex fault localization, ei-
ther during the installation or the opera-
tion of SPC exchanges. During the short
Team of experts within the
installation time the functions of the
country equipment are tested mainly by means
The main part of the maintenance work of special automatic test programs and
in a network with AXE 10 exchanges can this results in there being few oppor-
be centralized to one or more operation tunities for normal fault tracing. More-
and maintenance centres, OMC The overthe equipment is delivered from the
OMC staff can localize most faults. factory so thoroughly tested that the
However, if a complicated fault should processors usually work perfectly from
occur, it may be necessary for this staff the beginning and no fault tracing is
to have access to experts with a thor- necessary.
ough knowledge of both the hardware
Fig. 2 and the software. Seldom occurring
LM Ericsson have established a Maintenance, faults, for instance in the fixed ex- Central expert support from
Installation and Production Support Centre, change cabling, could be very difficult LM Ericsson in Stockholm
MIPSC. in Stockholm. The picture shows an AXE
10 exchange in MIPSC. It is employed for detailed to localize. The expert assistance Scope and organization
analysis of complex problems should therefore be concentrated to a A previous article has described several
systems w h i c h have been developed to
aid the work on LM Ericsson's tele-
phone exchange systems 4 . These sys-
tems have now been supplemented by
the Maintenance. Installation and Prod-
uct Support Centre. MIPSC. which LM
Ericsson have established in Stock-
holm. Sweden. The centre, w h i c h is also
used for normal p r o d u c t i o n , was set up
in connection with the introduction of
SPC technology. MIPSC consists of five
separate units, w h i c h are responsible
for
1. AXE and AXB exchanges
2. ARE exchanges and subsystems.
such astoll ticketing, o p e r a t o r a n d I O
systems
3. AKE exchanges
4. PABX systems with SPC
5. Test equipment for SPC exchanges.
type of assistance can be given on every ductory stage, before the maintenace
Fig. 4
When a fault occurs, the AXE 10 exchange
occasion. This assistance can vary form staff have acquired sufficient experi-
normally indicates the faulty unit. The quality telephone consultation to active aid on ence.
supervision gives an alarm and carries out block- site.
ing if the number of unsuccessful connection The services offered by MIPSC for AXE
attempts via a device exceeds a preset percen-
tage Since the technicians in OMC or the ex- 10 exchanges are indicated in the fol-
changes will normally contact their na- lowing. Firstly, the normal procedurefor
tional MSC for assistance with complex clearing faults in an AXE 10 exchange is
fault clearing, the MIPSC staff in Stock- described together with some examples
holm will be approached only if the MSC of how the OMC or exchange staff carry
out such work.
The exchange gives an A2 alarm and indicates Typical fault clearance in AXE 10
that RP (Regional Processor) number 68 has a The maintenance functions in AXE 10
check sum fault on program page 4. (The fault
code is explained in the exchange manual )
(see the previous article on this sub-
PROM boards 4 and 5 are listed as having a high ject2) cover the various subsystems in
probability of being faulty the exchange. When a fault occurs, the
fault report received is normally so spe-
cific about the nature of the fault that
the repair work is more routine. In most
cases the faulty printed board assembly
is indicated directly, fig. 4, and can be
replaced by a spare one from the spares
store.
The printed board assemblies have been changed
and a test of RP no. 68 is ordered. The response Sometimes the caracteristics of the
confirms that RP is working properly fault are such that there could be more
than one possible cause. In such casesa
Deblocking of RP is ordered This command has fault printout is obtained that lists the
been classified as an important one and is there- possible faulty printed board assem-
fore repeated by the processor. After acceptance blies together with the fault probability
the order is executed
for each one, fig. 5. The repair work
The exchange informs that the alarm condition
starts by replacing the printed board as-
for RP no 68 has ceased sembly with the highest fault probabili-
ty If the fault remains the next printed
board assembly is replaced and so on.
staff need assistance. Contact with
MIPSC can therefore be considered as In certain cases the alarm printout infor-
Fig. 5
an extra safeguard in the case of rare mation may be insufficient to directly
If there are possible alternative fault causes, the and especially complicated faults. identify the fault, and fault tracing with
fault diagnosis system in the AXE 10 exchange the aid of built-in test functions must be
will list all printed board assemblies involved, Access to such expert assistance can be carried out. The procedure is described
together with the fault probability for each one
particularly important during an intro- in the operation and maintenance man-
Fig. 3
The MIPSC unit dealing with the telex exchange
systems, AXB 20
ig.6
on toll ticketing equipment in the MIPSC
nit dealing with the ARE systems
ual for the exchange. The fault localiza- is automatically started to identify the
tion is usually carried out from OMC, as faulty processor side. This side is auto-
has been described in a previous arti- matically blocked and then the faulty
cle3. unit is pinpointed and an alarm is given.
The maintenance functions cover faults Som incidental faults are not reported to
in the switching network, and associ- the maintenance staff until the same
ated devices, faults in memories and fault has occurred several times. This
power supply equipment and faults in avoids unnecessary investigation of cir-
maintenance circuits and switch-over cuits where the faulty state no longer
functions. The hardware in the AXE 10 exists. However, the maintenance staff
control system is supervised by compar- can at any time request a printout of the
Fig. 7 ing the output of the duplicated, syn- stored information concerning such in-
Measurements on the processor part of control chronous working processors. If a com- cidental faults.
system ANA 30 in the MIPSC unit dealing with the parison fault is detected, a test program
ARE system
The powerful automatic recovery
capabilities of AXE 10 mean that
MIPSC need seldom be called upon
The automatic blocking of faulty de-
vices limits the effects of faults and con-
sequently the traffic handling ability is
not noticeably impaired by a small num-
ber of individual faults. Furthermore,
faults in the common sections of the
exchange do not normally affect the
traffic. This is because such sections
are at least duplicated, and the faulty
unit is automatically blocked until the
repair has been carried out.
ER
92
Whenever there is a processing failure, the system. MSC normally provides the
not involving hardware faults, the sys- required assistance, but help can also
tem recovers automatically with the aid be obtained from MIPSC in Stockholm.
of a minor restart. In most cases the The printout gives very detailed infor-
effects of a software fault are thus elimi- mation so that the necessary corrective
nated as result of the central processor measures can be carried out at an early
being cleared of all work in progress. stage.
Connections that have already been es-
tablished are not affected, but the lim- Commmunication with MIPSC as and
ited number of calls that are in the regis- when required
ter stage are disconnected, and the A request for assistance is normallysent
subscribers in question receive a new to MIPSC via telex, fig. 9 The distur-
dialling tone bances should be described in suffi-
cient detail to enable the system expert
If a further processing failure occurs to analyze the situation. The MIPSC staff
within ten minutes of a minor restart, a can also simulate the fault situation in a
major restart is initiated All variable model exchange. The result of the anal-
data are reset and all established con- ysis and a recommendation for suitable
nectionsare released. If thisaction does action are then sent back via telex.
not rectify the situation, degeneration of
programs or data has probably oc- In certain cases a technician may need
curred. Another processing failure with- guidance for fault localization in a tele-
in ten minutes therefore automatically phone exchange. It is then possible to
initiates reloading of both programs and telephone MIPSC, where a system ex-
data from a magnetic tape unit. pert is available to give advice.
Fig. 8
Processors of type APZ 130 and APZ 150 in the
MIPSC unit dealing with the AKE system
93
MIPSC system expert, who will then impossible to give sufficient assistance
make the required contact as quickly as from a distance However the need of
possible such visits is expected to be very small.
Fig. 9
Communication with MIPSC c a n take place via
telephone, telex, telefax or p e r s o n a l v i s i t s
ERIC
Fig. 11
PABX type ASB 900 installed in the MIPSC unit
dealing with stored program controlled PABXs
Special test equipment makes it possi- cedure means that any remaining faults
ble to load the exchange with concen- are detected at a sufficiently early stage
trated traffic, so that problems w h i c h to permit correction before the software
only appear in such circumstances can is needed for testing of the exchange on
be investigated. The load i s t h e n consid- site.
erably greater than any load that can
occur in a telephone exchange. This Testing of hardware and
simulation facility is particularly useful
for testing system revisions before they
software before complicated
are introduced in exchanges that are al- extensions
ready in operation. Additional hardware has to be installed
when an SPC exchange is to be ex-
tended and this means that new data,
Testing of programs and data
and sometimes new programs, must
before installation also be i n t r o d u c e d . The various stages
Programs and data for an SPC ex- in an extension have been described in a
change are normally compiled indepen- previous article 2 . In the case of a compli-
dently of each other and are then tested cated extension, or when the staff who
separately in automatic test equipment. are to carry out the extension have lim-
However, it is possible that certain faults ited experience, it may be advantageous
remain in newly designed software in to first simulate the extension in the
spite of such tests. Further testing can model exchange. The methods used are
be carried out by loading the programs the same as in the actual extension
and the exchange data in the MIPSC work, and the staff thus receive on-the-
model exchange, and then checking job training. At the same time the soft-
that the programs are correct. This pro- ware is checked and any faults are cor-
Fig. 12
Calibration of stored program controlled traffic
generators in the MIPSC unit dealing with test
equipment
95
References
I.Eriksson, V.: CCM-A Weil-Tried
and Economic Maintenance Sys-
tem. Ericsson Rev. 53 (1976):3, pp.
134-137.
2. Soderberg, L: Operation and Main-
tenance of Telephone Networks
with AXE 10. Ericsson Rev. 59
(1979):3, pp. 104-115.
3. Nordqvist, G.: AOM 101. an Opera-
tion and Maintenance System.
Ericsson Rev. 56(1979)3. pp. 116-
123.
4. Svenle, I.: Auxiliary Systems for
AXE 10 Networks. Ericsson Rev. 56
(1979):4, pp. 170-178.
5. Hagberg, P.-O. et al.: Installation of
AXE Exchanges. Ericsson Rev. 56
(1979):1. pp. 14-21.
ERIC
ERICARE
Fig. 1
Loudspeaking calls provide information and aid
the decisionmaking, and thus reduce the number
of emergency visits to the old-age pensioners
and handicapped people.
The person on duty at the alarm centre learns
what has happened, can advise and reassure the
pensioner and arrange help when necessary.
It is not possible to set up a loudspeaking call
from the alarm centre for listening-in on the
pensioner. It is only when an alarm has been sent
that the loudspeaking two-way speech circuit is
opened
97
ANDERS LENNSTROM overto a wall button, which would often The central equipment is mounted in a
CURTSUNDMALM
LM Ericsson Telematenal AB
be impossible, for example if the person wall rack and consists of the standard
had a fractured thigh. The portable al- printed board assemblies used in tele-
arm button is available as a bracelet or phone attendance system AVE 100
as a medallion on a band round the
neck. The control equipment at the alarm cen-
tre consists of a telephone base with two
The range of the radio signal transmitter units The lower one has buttons for
is sufficient to penetrate reinforced connecting up 3 - 6 alarm lines The up-
walls and reach the receiver even in a per unit has six control buttons and a
large house, and it is the best and safest digit indicator. One of the buttons is
method for a pensioner etc. to send an used to change the speech direction in
active alarm. the home equipment. The button is de-
pressed for speech and released for lis-
A person cannot set off an active alarm if tening In the home equipment there is
he or she is unconscious or cannot corresponding switching between mi-
reach the alarm button. For this reason crophone and loudspeaker
supplementary equipment for passive
alarm is often also installed. This type of The telephone set at the alarm centre
alarm is released when a normal activity can be a standard set. e.g. DIALOG or
is not repeated within a certain time DIAVOX. However, it is more convenient
ERICARE has an electronic clock which if the switching of speech direction can
measures the time, for example from the be done with a key in the handset in-
last time the toilet was used. After, for stead of a panel button If the telephone
example, 12 hours a passive alarm is set has a carbon microphone, changing
sent to the alarm centre it to a dynamic microphone with ampli-
fier will give better sound quality in the
Alarm centre equipment loudspeaker in the home equipment
In the telephone exchange a group Theoretically. 10.000 alarm sources can
number for three or more lines is re- be identified with a four-digit indicator.
served for the alarm centre and used A recorder can be connected to the cen-
only for alarm calls The person on duty tral equipment to record the time and
can switch between incoming alarms identity of incoming alarms.
and deal with them according to urgen-
cy. A separate telephone line at the a- The alarm centre does not have to be
larm centre is used for outgoing calls. manned It can be equipped with an
The staff on duty can use this line to call ERICALL radio transmitter which, when
an ambulance, a doctor, a caretaker an alarm comes in. automatically pages
etc., or make ordinary calls to the pen- the person in charge, who is thereby
sioners called to the alarm centre
Fig. 2
The telephone base unit has a large red button
for alarms. A second button gives easy, single-
handed calling of an optional telephone number,
usually to a close relative.
The button at the far left cancels an initiated
alarm call
Fig. 3
The portable alarm button gives a wireless alarm
signal to a radio receiver built into the telephone
base unit. The receiver then automatically initi-
ates a call to the alarm centre.
The portable alarm button is worn as a bracelet or
as a medallion on a band round the neck.
The radio signal transmitter is equipped with
automatic battery checking. When a change of
battery is due. a special signal is sent to the
receiver in connection with an alarm or test
signal. The green diode lamp in the telephone
base unit starts to flash. Moreover the digit
indicator in the alarm centre displays the letter C.
which indicates that the battery should be
changed
98
The alarm code and identity are dis- In the subscriber's home:
played on the digit indicator used by the -registering an alarm situation
person on duty. He can request new -automatically calling when an alarm is
transmission of the information, by de- given
pressing the button New code, if it is not -sending predetermined telephone
shown or is shown distorted. numbers
-receiving control signals from the al-
The person on duty can carry out a con- arm centre
versation with the pensioner by means -sending an identity number
Fig.4 of the key on the handset or the button -loudspeaking communication, sim-
The block diagram for ERICARE Speech control. If he finds it difficult to plex.
99
3 1981
PCM SIGNALLING EQUIPMENT IN THE BYB CONSTRUCTION PRACTICE
MANUFACTURE OF HYBRID CIRCUITS
ERICSSON REVIEW
NUMBER 3 • 1981 • VOLUME 58
P U B L I S H E D IN S W E D I S H , E N G L I S H , F R E N C H
AND S P A N I S H W I T H FOUR I S S U E S PER YEAR
T H E A R T I C L E S M A Y BE R E P R O D U C E D
AFTER C O N S U L T A T I O N WITH THE EDITOR
Contents
102 Digital local exchanges AXE 10
111 Power Supply Equipment for Large Telecommunication Plants
120 Mobile Telephony in the Nordic Countries
128 CONTACT R L 4 0 0 - a New Radio Relay Equipment
134 PCM Signalling Equipment in the BYB Construction Practice
142 Manufacture of Hybrid Circuits
COVER
Prototype plant BZD 412, 1600 A, undergoing
type testing in the Power Supply Department
laboratory. In the background a plant of the BZD
112 type.
Digital local exchanges AXE 10
System characteristics
A summary will now be given of the
functions of the subsystems that are
characteristic of an AXE 10 local ex-
change.
Fig. 2
Digital subscriber stage placed in a container for
remote location
E
Fig. 3
Comparisons between the function of the
analog and the digital subscriber stages
Analog functions
Digital functions
Analog line circuit
Analog digital line circuit
Digital line circuit
Analog subscriber stage
Time Switch in digital subscriber stage
Cord circuit for A- and B-subscriber
functions
Analog/digital converter for 32 channels
Link to group selector
Digital group selector
Incoming and outgoing analog trunk
circuits
ETC Terminal for first order PCM system
Functions
The digital Group S w i t c h i n g Sub-
system, GSS, the C o m m o n Channel Sig-
nalling Subsystem, CCS, The Operator
Position Subsystem, OPS, and the
Mobile Telephone Subsystem, MTS,
have been described in earlier arti-
c l e s ' 2 3 5 . The digital subscriber stage
and the f u n c t i o n s in the s w i t c h i n g and
Fig. 5
Simplified d i a g r a m of t i m e s w i t c h , T S
Speech data
E x t e r n a l c o n t r o l data
I n t e r n a l c o n t r o l data
DEVSB D e v i c e S p e e c h B u s t o w h i c h l i n e cir-
c u i t s , LIC, Key t o n e r e c e i v e r s . K R D , a n d
links, JTC, to the g r o u p selector are
connected
TSB Time S w i t c h Bus u s e d tor equalization
of t r a f f i c b e t w e e n t h e 128-line g r o u p s
DEVCB Device Control Bus c o n n e c t i n g the de-
v i c e p r o c e s s o r of t h e t i m e s w i t c h t o t h e
regional processors, EMRP
A c o n n e c t i o n f r o m a LIC t o a l i n k t o t h e g r o u p
s e l e c t o r i n t h e s a m e 128-line g r o u p r u n s f r o m L I C -
D E V S B - S p e e c h s t o r e - D E V S B - J T C . a n d the r e v e r s e
in the o t h e r s p e e c h d i r e c t i o n .
W h e n t h e r e is n o f r e e l i n k t o t h e g r o u p s e l e c t o r in t h e
o r i g i n a t i n g 128-line g r o u p t h e c o n n e c t i o n is p a s s e d
via T S B t o J T C in a n o t h e r 128-line g r o u p as f o l l o w s :
L I C - D E V S B - s p e e c h s t o r e - T S B speech s t o r e -
D E V S B - J T C . a n d t h e r e v e r s e in t h e o t h e r s p e e c h
direction.
I n c o m i n g s p e e c h s a m p l e s f r o m D E V S B t o T S B are
written successively into the speech store under
c o n t r o l of t h e t i m e s l o t c o u n t e r . O n r e a d - o u t to
D E V S B a n d T S B t h e t i m e s l o t c o u n t e r i d e n t i f i e s the
relevant p o s i t i o n in t h e c o n t r o l s t o r e w h e r e t h e
a d d r e s s of the r e l e v a n t p o s i t i o n in the s p e e c h s t o r e
is s t o r e d .
On t h e s e t - u p of e v e r y c o n n e c t i o n , data are c h a n g e d
in t h e c o n t r o l s t o r e by t h e d e v i c e p r o c e s s o r , w h i c h is
controlled by the central processor
control systems that are unique to local version is done before access to the
Fig. 6 exchanges are described in the follow- switch. Thus all " c o r d c i r c u i t f u n c t i o n s "
T h e w a y in w h i c h t r a f f i c e q u a l i z a t i o n t a k e s ing part. Furthermore the control sys- must be performed in the line circuit as
p l a c e p e r 2 0 4 8 - l i n e g r o u p in t h e d i g i t a l s u b -
tem will be described in more detail in a they require DC-connection with the
s c r i b e r s t a g e of A X E 10
later article. analog subscriber line. This solution
TSB T i m e s w i t c h b u s w i t h 512 t i m e s l o t s
JTC L i n k t o t h e g r o u p s e l e c t o r f o r 32 s p e e c h permits use to be made of developments
channels
TS Time switch with one speech sample
DIGITAL SUBSCRIBER STAGE in c o m p o n e n t technique and at the
s t o r e per 768 p o s i t i o n s The digital subscriber stage shall have same time constitutes a natural step to-
LIC Line circuit
LSM L i n e s w i t c h m o d u l e f o r 128 l i n e s the same functions as an analog sub- wards the i n t r o d u c t i o n of digital sub-
E a c h l i n e s w i t c h m o d u l e L S M c a n , via t h e t i m e scriber stage: current feed, ringing and scriber lines.
s w i t c h . T S . e i t h e r be c o n n e c t e d t o t h e g r o u p s e l e c t o r digit reception in addition to the con-
GSS o v e r its o w n PCM s y s t e m l i n k J T C w i t h 32
s p e e c h c h a n n e l s or utilize o n e of t h e 512 t i m e s l o t s centration f u n c t i o n , fig. 3. Functions of the subscriber stage
in t h e t i m e s w i t c h b u s T S B for a c c e s s t o a free
s p e e c h c h a n n e l i n JTC in a n o t h e r l i n e m o d u l e . The digital subscriber stage has a line
A s all l i n e c i r c u i t s h a v e a c c e s s t o all s p e e c h In the digital subscriber stage the con- circuit for each c o n n e c t e d subscriber
channels to the g r o u p selector, the selector has full
a v a i l a b i l i t y a n d is t h u s i n s e n s i t i v e t o a s y m m e t r i c a l
centration takes place in a digital line. In the line circuit the speech is con-
loading. switch, TS. The analog/digital c o n - verted between analog and digital f o r m .
Fig. 4 shows the various parts of the line
circuit and their f u n c t i o n s .
line modules need not have their own Structure of the line module
speech channels to the group selector. Each line module, LSM, fig. 8, contains
The group of altogether 16 line modules 128 line circuits, time switch, key tone
can be equipped with the number of receiver, printed circuit board assembly
speech channels required by the total for speech channels to the group selec-
traffic. tor, and equipment for testing of sub-
scriber lines and line circuits. Each line
Control module also contains a regional pro-
The control functions in the subscriber cessor, EMRP. The various units in the
stage are highly decentralized. The line line module are interconnected over
circuit boards, time switch board, key three bus systems, one for speech,
Fig. 8 tone receiver board and the board for DEVSB, one for control, DEVCB, and
Principle of the line module LSM one for tests, TESTB.
speech channels to the group selector
Control path
Speech path
are all provided with microprocessors,
Test path DEVP, with permanently stored pro- Connection
LIC Line circuit
TESTB Test Bus grams, fig. 7. These microprocessors in The digital subscriber stage can be con-
DEVSB Device Speech Bus
DEVCB Device Control Bus
a line module for 128 subscribers are in nected direct to the group selector or as
KRD Key tone receiver turn controlled by a regional processor, a remote unit. In the former case the
JTC Link to group selector
LCT Line and Line Circuit Tester EMRP, also of microprocessor type. The regional processor, EMRP, of the sub-
TS Time Switch
EMRP Regional processor
same high level language, PLEX, is used scriber stage is connected via a bus con-
TSB Time Switch Bus for its programming as for the central verter, RPBC, to the regional processor
EMRPB Regional processor bus
processor software. bus, RPB, of the central processor, fig.
9, top At the bottom of the same figure
is shown the connection of a remote
subscriber stage to the parent ex-
change. The connection is made over
the number of 2.048 Mbit/s PCM sys-
tems necessary for the traffic.
Synchronization
In the digital network, group selector
and digital line systems work in syn-
chronism. The digital subscriber stage
must work in synchronism as well It re-
Fig. 10
Function block LI for connection of subscriber
107
lines
^^^^" Speech path
Signal paths within the (unction block
•*-*•— Signal paths to other (unction blocks
LIC Line circuit
LIR Subscriber line Interface, regional software
LIU Subscriber line Interface, central software
ceives its synchronizing information both hardware and central and regional
from the digital g r o u p selector. All 128- software.
Fig. 9, down
Block diagram of AXE 10 local exchange with line groups have an oscillator for syn-
exchange-located and remote digital sub- chronization. Two of these groups re- The hardware consists of line circuit
scriber stage ceive synchronizing information from boards with a microprocessor for c o n -
Common equipment for exchange-located and re- the group selector and control the other trol. The permanently stored programs
mote digital subscriber stage
LIC Line circuit groups over the time switch bus. in this processor exchange software
KRD Key tone receiver signals with the regional software in
TS Time switch
EMRP Regional processor Function block structure EMRP.
Specific equipment for remote digital subscriber The function blocks in the digital sub-
stage
ETC, ETB Exchange terminals, near and far end scriber stage are s h o w n in Technical Interworking between f u n c t i o n blocks
ST-C, ST-R Signal terminals Box 3 at the end of the article. Fig. 10 normally takes place only in the central
Specitic equipment (or exchange-located digital sub- shows the f u n c t i o n block for connec- processor by the exchange of p r o g r a m
scriber stage
JTC Link to group selector tion of subscriber lines, LI. It comprises signals. Regional interworking occurs,
RPBC Bus converter
however, in the exceptional case w h e n
internal traffic is c o n n e c t e d direct in a
remote subscriber stage because of link
failure.
Components
Modern c o m p o n e n t t e c h n i q u e has been
introduced for the f u n c t i o n s in the line
circuit. Standard LSI circuits are used
for
- s t o r e s in processors and time s w i t c h -
es
-microprocessors
- s i n g l e channel codec and filter.
SUBSCRIBER FACILITIES
AXE 10 offers a wide range of optional
subscriber facilities, as appears f r o m
Technical Box 2 at the next side. Most
facilities are limited to the home ex-
change, but means exist for introduc-
tion of overall network facilites also.
Digital subscriber lines will make addi-
tional facilities possible.
Technical Box 2
SUBSCRIBER FACILITIES ference is that the normal " c o r d circuit nected to the EMRP-bus.
The subscribers in AXE 10 can be allotted a
f u n c t i o n s " have been placed in the line
number of special facilities, the procedures for
circuit. This has the f o l l o w i n g con- Measurement on subscriber lines must
the use of which are as recommended by CEPT
and CCITT. sequences: be possible also for remote units and
- c o n n e c t i o n to a subscriber line for can be done with the line and circuit test
Subscriber facilities within an exhange:
tests is done in the line circuit equipment. For more extensive mea-
- Pushbutton dialling
- Abbreviated dialling - t h e increased n u m b e r o f f u n c t i o n s per surements separate measuring equip-
- Hot line line circuit calls for regular f u n c t i o n ment is used w h i c h is controlled from
- Registered call the parent exchange.
- Do not disturb
tests
- Call waiting - e x t r a n e o u s voltage on a subscriber
- Enquiry line does not affect equipment c o m - C o m m o n e q u i p m e n t in the 128-line
- Conference call mon to several subscribers. No special group, time switches, clock circuits and
- Subscriber-controlled restriction of calls on speech buses are supervised by means
certain routes
indication of extraneous voltage is
therefore needed in c o n j u n c t i o n with of parity checks and similar methods.
- Automatic alarm-call service
the setting up of a call.
Facilities with overall network function: Traffic measurements can be made in
- Tracing of malicious calls each direction for every remote unit and
- Registered call Each line circuit has a test relay for split-
- Call transfer every 2048-line g r o u p in the exchange
ting of the line and c o n n e c t i o n of test
- Priority
equipment to the line side and the ex- SIGNALLING
change side. One line and circuit test Signalling from subscriber to exchange
equipment exists per line module of 128 is done on analog circuits in the con-
subscriber lines. With this equipment a ventional way by loop signalling or key
simple subscriber line test can be made tone signalling. Small PABXs can be
in c o n j u n c t i o n with clearing or as part of connected over subscriber lines with
a routine on lines that are used spo- the same simple signalling. Large
radically. Line circuit tests can be made, PABXs can be c o n n e c t e d over lines with
furthermore, on suspicion of fault, e.g. more complex signalling. The lines can
on line lock-out or absence of answer. in such cases be c o n n e c t e d directly to
The line circuit test covers all analog the g r o u p selector and the signalling
functions in the line circuit. PCM codec can then include also in-dialling to the
and hybrid units are also tested on a PABX.
routine basis by transmission of test pat-
terns over the speech path. The line and The new facilities that will be possible
circuit test equipment can also be used with digital subscriber lines require
for controlling test connections over a more advanced signalling between ex-
given line circuit. Portable I/O devices change and subscriber terminal. Provi-
for maintenance w o r k on site are con- sion has been made in the digital sub-
Fig. 11
Laboratory testing of the digital subscriber stage
109
scriber stage of AXE 10 for this extended alternative is, when the signalling sche-
signalling facility. The signalling rela- me so permits, to transmit special tariff
tions which now exist as far as the line messages to the local exchange.
Fig. 12 circuit board in the subscriber stage
Functional testing of the digital subscriber stage can, with digital subscriber lines, be ex- The charging information is conveyed
tended right out to the subscriber termi- to the I/O devices of the system. Nor-
nal. mally it is stored on cassette or magnet-
ic tape for later processing, but it may
Signalling between local AXE 10 ex- also be conveyed to a typewriter or via a
changes and other exchanges in the data channel to charging centres.
network has been dealt with in the re-
ferred articles15. Adaptation is suc- LOCAL NETWORKS
cessively taking place to different na- Digital networks can be very efficiently
tional signalling systems. In the digital utilized3. This applies also to the parts of
part of the network CCITT system no. 7 the subscriber network where the digi-
is standard, but function blocks for talization is brought nearer the sub-
channel associated signalling are also scribers through remote digital sub-
available. scriber stages.
Fig. 13
Laboratory testing of circuit board assembly with
microDrocessor
Technical Box 3
FUNCTION BLOCKS IN DIGITAL SUBSCRIBER
STAGE
The following function blocks are always in-
cluded in the digital subscriber stage:
LI Subscriber line functions
- call detection
- reception of digits
- current feed
- translation, multiple position-directory
number
- blocking
- connection of lines for PBX number
- special subscriber functions
CJ Combined cord function are linked together over direct routes or
- reception of digits from LI and KR via tandem exchanges. Local and tan-
- initiation of time slot seizure on PCM link dem exchanges can advantageously be
- time-outs combined and tandem exchanges can
- initiation of seizure of TCS and digit
transmission to TCS
also be used for national transit traffic.
- clearing
RT Terminal functions for remote subscriber In the peripheral areas of large cities
stage both autonomous exchanges and re-
- selection of PCM link
- selection of time slot on PCM link
mote subscriber stages can be placed.
- maintenance of PCM link On growth of the network the remote
TS Time switch functions units can be built out into autonomous
- selection of time slot on time switch bus exchanges which, after further growth,
- setting up of connection
- check of through-connection
can have their own remote subscriber
- supervision of connection stages.
- clearing
CD Clock signal distribution functions Networks for medium-sized and small
- clock regulation
- synchronization towns
PX PBX number functions In medium-sized towns a network of a
- selection of PBX route few exchanges without tandems is usu-
- selection of circuit in PBX route ally sufficient. If the traffic warrants only
- administration of PBX route data
small direct routes between the ex-
KR Key tone reception changes, these can have the form of
The subscriber stage can also be equipped, if high usage routes and the overflow traf-
necessary, with the following function blocks: fic can be passed via one of the other
SE One or more standardized or market-adapt-
ed function blocks for special subscriber
local exchanges. One of the local ex-
line signalling, e.g. for public call boxes, changes can also be used for national
subscribers' private meters and special transit traffic.
PBX functions
ATLFunction block for remote subscriber stage
which, on total link failure, permits internal Summary
traffic within the stage and calls to alarm
numbers. The AXE 10 system comprises all the
functions and building blocks neces-
sary to modernize and extend ex-
changes in the analog telephone net-
works by adding digital equipment. It
permits both successive introduction of
digital technique and more extensive
conversion of entire zones. Since the
digital subscriber stage occupies little
space and can also be located as a re-
mote unit, the introduction of AXE 10 References
permits buildings in central city areas to
1. N i l s s o n , B . A . a n d S 6 r m e , K . : A X E - / 4
be released for other purposes. The re- Review. Ericsson Rev. 5 7 (1980):4,
mote units can be optimally placed in pp. 1 3 8 - 1 4 8 .
the subscriber line network. 2. Ericson, B. and Roos, S.: Digital
Group Selector in the AXE 10 Sys-
tem. Ericsson Rev. 55 (1978):4, pp.
The AXE 10 system was developed for 140-149.
the digitalization of telephone networks 3. B r a u g e n h a r d t , S. and N o r d i n , J.-E.:
that is now in progress and is so de- AXE 10 with Digital Group Selector
in the Telephone Network. Ericsson
signed that it can be further developed
Rev. 55(1978) :4, pp. 150-163.
to cater for successively changing re- 4. Nordqvist, G.: AOM 101, an Opera-
quirements. tion and Maintenance System.
Ericsson Rev. 56(1979):3, pp. 1 1 6 -
123.
5. A n d e r s s o n , T. and L j u n g f e l d t , O.:
Digital transit exchanges AXE 10.
Ericsson Rev. 58 (1981):2, pp. 5 6 -
67.
6. S o d e r b e r g , L.: Operation and Main-
tenance of Telephone Networks
with AXE 10. Ericsson Rev. 56
( 1 9 7 9 ) : 3 p p . 1 0 4 - 115.
Power Supply Equipment for Large
Telecommunication Plants
Fig. 1
Type testing the power supply plant BZD 412 in
the laboratory
KJELLRUNDKVIST
PER-UNOSANDSTROM
ROLAND WALD
Power Supply Department
Telefonaktiebolaget LM Ericsson
Fig. 2
The power supply system BZD 412 with high
frequency booster converters
Battery
age so that the sum of the battery volt- When the mains voltage is restored, the
age and the converter voltage is c o n - rectifiers automatically take over the
stant during the discharge stage. supply of power while at the same time
they start to recharge the battery. The
booster converters successively reduce
System Description their output voltage and revert to a pure-
The f u n c t i o n of BZD 412 can be best ly filtering f u n c t i o n w h e n a normal volt-
described by studying figs. 2 and 3. Fig. age level has been reached. Operational
2 is a simplified block diagram and fig. 3 battery charging now starts to bring the
shows the voltage variation t h r o u g h battery quickly back to a fully-charged
a cycle of normal o p e r a t i o n - m a i n s state. On an order f r o m the automatic
f a i l u r e - r e c h a r g i n g - n o r m a l operation. control, the rectifiers increase their out-
put voltage to the operational charging
During normal operation the battery level w h i c h is typically 2.35 V per cell
voltage is kept at a specified level, 51 V and a total of 54 V. When the process
± 0.5%, by the rectifiers w h i c h are has been c o m p l e t e d , the order is dis-
powered from the mains. This voltage, continued and the rectifiers return to
corresponding to 2.22 V per cell, float- the normal level.
charges the batteries, that is they re-
ceive a small maintenance current System characteristics
which compensates for self-discharge. Some distinctive features are:
- The system delivers a constant dis-
In this situation the booster converters tribution voltage both d u r i n g normal
function as active filters and provide an operating c o n d i t i o n s and when there
additional 0.5 V d.c. bringing the sys- is a mains failure, when the battery
tem's output voltage U D to about 51.5 V. voltage drops. Thus the telecom-
When a mains failure occurs, the battery munication e q u i p m e n t and the bat-
takes over the task of supplying power teries can be designed in a rational
and the voltage across it sinks. way and safe operational conditions
However, the booster converters' out- obtained.
put voltage successively increases so - Transient voltage ratings and
that the total sum of the battery voltage periodic noise voltages are limited to
and the booster converter voltage will very low values. This is achieved by a
be constant. special transient-limiting distribution
Fig. 3
The booster converter system for 48 V with 23
battery cells. The cycle of events for a mains
failure and subsequent recharging
113
for the BZD 412 system and by letting has two transformers and a thyristor
the booster converter function as an unit, twelve-phase coupled on the sec-
active filter4. ondary side. The output voltage and the
- The booster converters work at a high output current are regulated by means
frequency, 20 kHz, which gives ad- of phase angle control. The voltage from
vantages in the form of small dimen- the thyristor unit is filtered with an LCI-
sions, silent operation and fast reg- filter. The rectifier has the following
ulation. characteristics:
- The system is completely automatic - it can be used in all types of power
and suitable for unattended ex- supply systems
changes In particular, a new auto- - it is designed for use with bad mains,
matic battery charging principle in- that is mains with major voltage and
corporating digital logic 3 is used. The frequency variations, frequent mains
system can also be upgraded with mi- failures or weak mains with high im-
crocomputer control and digital com- pedance such as local standby gener-
munication with a supervision centre ating sets
Fig. 4 monitoring several exchanges. - it has protective and control equip-
Two thyristor rectifiers BMT 343, one with front - The new packaging structure is com- ment suitable for completely auto-
panels and one without
pact and installation, operation and matic operation in unattended ex-
maintenance are simple. The design changes
provides a high degree of staff safety. - it can be connected in parallel with an
- BZD 412 is extremely flexible, easy to unlimited number of rectifiers, elec-
extend and to use. tronically controlled so as to divide
- The system design gives a high de- the load equally
gree of reliability. - it has all live parts protected from in-
advertent contact.
Thyristor rectifier
The rectifier BMT 343 for 400 A and 48 V Booster converter
has been described in detail in a pre- The BMR 273 booster converter is a d.c.
vious article in Ericsson Review1. The convertersupplied with 48 V battery and
rectifier is three-phase connected and with an output rating of 0-8 V and 400 A.
Fig. 5
Simplified circuit diagram for BMR 273
CM1 Converter module 1
CM2 Converter module 2
FU Filter unit
T1-T4 Transistor units 1-4
TR Transformer
D1-D2 Rectifier bridge
BD Base drive circuits
rn P.nntrol unit
114
It adds its output voltage to the battery into carefully f o r m e d drive pulses in
voltage and regulates the system output order to ensure g o o d functional charac-
to the desired level, for instance w h e n teristics d u r i n g all possible operational
battery discharge occurs due to a mains situations.
failure. Because of g o o d control charac-
teristics the converter also f u n c t i o n s as The transistors, their heat sinks and the
an active filter, suppressing low-fre- base drive circuit are m o u n t e d in a com-
quency ripple voltages in the 0 - 6 0 0 Hz pact unit, fig. 6. Each inverter bridge
frequency range. contains four s u c h units.
in the frequency range 0-600 Hz is sup- made by a wire strap on one of the con-
pressed to levels in the 1 mV range. trol unit boards.
The filtering function makes it neces- The loss of any of these external signals
sary for the converter always to be in causes the converter to revert imme-
active operation and to provide an out- diately to normal constant-voltage con-
put voltage of at least 0.5 V. For this trol.
purpose the control unit has a special
regulator which interworks with the Protective circuits
main converter regulator. Switching be- The converter has the following protec-
tween these regulators takes place tive functions built into the control unit:
smoothly without overshoot. - current limiting to the rated current,
which prevents thermal overloading
If required, the filtering function can during operation
easily be disconnected, turning the con- - high-speed overcurrent protection,
verter into the passive operation mode which blocks the converter when ma-
in which the pulse width is brought jor surge currents occur, for instance
down to zero when the distribution volt- when there is a short-circuit in the
age exceeds the preset control level. distribution. Restart takes place auto-
Fig. 8
Units forming part of BMR 273. The converter secondary circuit then in- matically
Two converter units and one filter unit. The troduces a voltage drop of about 1 V. - undervoltage monitor, which blocks
control unit is located on three printed boards Selection of the operational mode is the converter when the battery is dis-
charged to a very low level. At the
same time an alarm is given. The
blocking is automatically cancelled
when the voltage returns to the nor-
mal level
- selective overvoltage monitor, which
blocks a converter that generates too
high a voltage. Afterwards the moni-
tor initiates a restart. If overvoltages
occur repeatedly, the converter is dis-
connected and an alarm is given. The
monitor must then be reset manually
- limitation of the converter output volt-
age so that excessive voltage is avoid-
ed during filter operation or master-
slave operation
- slow start-up, which is initiated when
a restart takes place after blocking.
This gives a smooth regulation back
to the correct level so as to prevent
voltage overshoot
- encapsulated fuses to protect against Distribution
internal short circuits
The distribution in BZD 412 can either
- electronic fuse alarm.
be transient-limiting or low-ohmic.
Parallel operation
The transient-limiting method of dis-
An unlimited number of converters can
tribution 5 has been developed to supply
operate in parallel and share the load
electronic telecommunication equip-
both in active and passive operation.
ment. Supply is effected over individual
cables directly from the distribution
Design
rack to the units in question. One typical
The complete converter consists of two
feature of the system is that the resis-
identical converter modules and a com-
tance in each of the distribution
mon filter unit, which contains the con-
Fig. 9 branches is at least 10 times greater
The converter rack viewed from the rear and from
verter input and output fuses and the
than the total internal resistance of the
the side. control unit, fig. 8.
power supply. It is possible to connect a
The four vertical copper bars in the rack rear
plane form the internal circuitry between the resistor in series with each fuse to modi-
The control unit consists of three fy the conductor resistance for different
units. The equipment is connected to the main
busbars via the bars shown to the left in the printed board assemblies plugged into a distribution distances. This method of
illustration board magazine. The push buttons and distribution effectively limits trouble-
the indicating diodes are placed on the some voltage transients when there is a
front of one of the boards. An ammeter short circuit in the distribution network.
is mounted on a separate front panel.
All signal connections are made via The low-ohmic distribution method is
plugs and jacks to the front of the units. used in electro-mechanical telephone
Power is supplied to the units via fork exchanges where brief transients do not
contacts from the busbar system in the affect the operation. Here supply is car-
rack's rear plane. Connection to the sys- ried out from the distribution rack fuses
tem is made to the busbars in the rack to the telephone exchange over heavy
via a switch on the right-hand side of the cables, which are then split up into
filter unit, fig. 9. smaller cables and run to the equip-
ment. Thus each distribution branch will
have a relatively low resistance com-
Each rack holds two converters.
pared with the internal resistance in the
power supply.
The distribution rack tors are provided, one for each distribu-
The distribution rack contains the dis- tion fuse and one common to each
tribution fuses, the battery fuses and, battery fuse unit. A plastic protector is
sometimes, equipment for automatic located in front of the fuses to prevent
battery charging. The fuse units are sus- live parts being touched when fuses are
pended between the vertical power bus- changed. For this reason distribution
bars in the left and right-hand rack up- fuses may be replaced by staff without
rights. special authorization to work on high
voltage plants.
The battery fuse unit contains three
fuses for a maximum of 630 A each, fig. Mechanical packaging
13. The battery cables are connected to
Fig. 11 the battery fuse unit with clamps or ca- structure
Low-ohmic distribution
ble lugs. A maximum of eight 150 mm2 The same packaging structure has been
Cartridge fuses for a maximum of 400 A
cables can be connected per pole and used for the BZD 412 system as for BZD
battery fuse. 1122. The systems can thus be combined
in one and the same installation.
The rack for transient-limiting distribu-
tion can have 112 or 168 fuses, each for The objectives which have been consid-
a maximum of 35 A. Outgoing cables are ered when designing both BZD 112 and
connected with a solderless terminal BZD 412 are:
with a maximum of two 10 mm2 cables - great flexibility
per pole, fig. 10. In order to make cab- - simple handling during installation,
ling in the distribution rack easier, a ca- operation and maintenance
ble holder has been mounted in the rear - a high degree of staff safety
corner of the rack. - rational utilization of the space avail-
able
The rack for low-ohmic distribution has - esthetically pleasing appearance.
28 fuses each for a maximum of 35 A and
four fuses each for a maximum of 400 A Rack design
or, as an alternative, eight fuses for a The rack is 600x600x2200 mm with 30
maximum of 400 A. The outgoing dis- mm square steel tube sections in the
tribution cables are attached by clamps corners. The corner uprights are linked
onto copper bars, one for negative and together with U-sectionsand aluminium
one for positive for each fuse. There is joints. There are attachment bars on the
room for a maximum of six 150 mm2 uprights with 100 mm vertical spacing
cables per pole and fuse, fig. 11. on which guide rails or units can be
mounted at the desired height for the
The alarm wires from the fuse units are equipment. The front of the racks con-
connected by plug-in cables to the sig- sists of equipment panels or doors. The
nal and alarm unit. Visual alarm indica- side and rear surfaces are covered with
Fig. 12
Jack strip for connection of the plant alarm and
operational signals
aluminium plates which are secured by indication lamps and push buttons for
screws. the normal operation of the units are
visible through windows in the front
Test instrumentation, alarm lamps for panel; the latter has a perforated lower
the system and the equipment survey edge.
diagram are placed in a metal hood on
the top of the rack. The hood is sloped The units are convection cooled. Cold
Fig. 13 towards the observer making it easier to airentersthrough the bottom of the rack
Battery tuse unit with automatic charging control read the instruments. Behind the hood and through the perforations in the front
equipment of the BMP 130 type for a maximum of there is a box containing the signal ca- panel.
630 A fuses
bles in which the signal and alarm
equipment is mounted; alarm and oper- The units are slid in on guide rails in the
ational signals can easily be connected rack and connected to the vertical
here, fig. 12. power buses in the rack via a switch or
directly with cables. The signal wires
The rack equipment is linked to vertical from the units to the plant and between
power bus bars in the rack end plates. the units are connected with plugged
These are connected at the top of the cables. Installation can be carried out
rack to horizontal bars which join all the using simple hand tools by staff without
racks in the plant. The racks are any special training, fig. 15.
provided with adjustable baseplates to
make it easier to set them up on uneven
flooring. The rack frames are lacquered
Design of a power supply
in light grey and the other plate surfaces plant
have a blue hammer-finished lacquer. The design and packaging structure of
the units results in power supply equip-
Equipment design ment offering very great flexibility. It can
Each piece of equipment is built up of easily be upgraded and adapted to vari-
one or several units either 470 or 500 ous types of telecommunication plant,
mm wide, 570 mm deep and the height is fig. 14.
in multiples of 100 mm. An example is
shown in fig. 8. The units consist of side A power supply plant consists of racks
plates and between these, either a per- 600x600x2200 mm in size, containing
forated plate or a framework for mount- either:
ing the components. The instruments, - one rectifier for 400 A
Fig. 14
The illustration shows two plant modules, each
for 800 A, consisting of two rectifiers between
which the converters and distribution have been
placed to limit the current in the top bars
Technical data for BMR 273
119
Input data
Voltage, permissible
variations V 38 to
56
Maximum current at U,N=40 V
and lOUT=400 A A 115
Efficiency with 50% of rated
power % 80
Output data
Current A 400
Maximum voltage with U,N = 41 V
and lOUT=400 A V 8
Static regulation accuracy % ±0.5 exceeds the number of redundant units.
- two converters for 400 A
Dynamic regulation
- distribution equipment in the tran- This normally means only a degradation
-response time for step
changes in load with 100 A ms <1 sient-limiting mode f o r a m a x i m u m of of the plant f u n c t i o n and not an inter-
Noise voltage over the load 800 A ruption in operation. The life of the
-psophometric mV <0.5 equipment has been estimated to be 40
- distribution equipment in the low-
-peak value at 40 kHz mV <100
ohmic mode for a m a x i m u m of 1200 years. The probability of a system failure
Operational data for the converter system A. during this period will be less than 1 %.
Regulation level for distribution
voltage
-normal value V 49 The plant has been designed so that a
-setting interval V 45 to m i n i m u m of current will flow in the con-
54 nection bars between the various racks.
System efficiency, active opera-
tion
Extensions to the distribution equip-
% 95 ment and battery take place in step with
Voltage drop across the output
with passive operation and the upgrading of the rectifier and con-
l OUT =400A V 1.05 verter equipment.
For the noise voltage in active
filter application the ratio between
the levels for the converter out of The equipment and rack design permit
and in operation is considerable freedom of layout. The
- a t 100 Hz >40 plant can be assembled in stand-alone
- a t 300 Hz >10
rows, double-sided rows or against a
Power consumption with active
filtering wall and additions can be made both to
-l O U T =400 A, UOUT=0.43 V the right and left of the row. This makes
w 925
-l O U T =100A. U OUT =0.48V w 200 for considerable ease in planning new
or extending existing plant, and avail-
able premises can be utilized rationally.
Reliability
The power supply equipment for a tele-
phone exchange must be extremely re-
liable. This has been achieved by the
following precautions:
Thomas Haug
The working group, which took the
The collaboration between the Nordic Telecommunications Administrations name Nordic Mobile Telephone Group,
originally concerned only matters that related to the handling of the traffic NMT, first prepared outline specifica-
between the countries. Since then the collaboration has successively been tions for a manual system, almost of an
extended to other fields and has also included technical development projects. interim type, which was later built in
Such a project is the Administrations' joint development of a Nordic mobile Denmark, Norway and Sweden. This
telephone system. This article describes the Nordic collaboration in this field and was followed by the considerably more
gives the background to some of the problems and their solutions. Technical extensive work on specifications and
other necessary data for an automatic
descriptions of the system have been published earlier5 6. For details of the
system.
system, reference should be made to these articles and to the publications of the
Nordic Mobile Telephone Group''4.
Fig. 1
The base station for mobile telephony at Nacka.
outside Stockholm, Sweden. As far as possible,
existing radio and TV masts and buildings are
used for the base stations. In this case the mobile
telephone antennas are placed in the left-hand
mast, at a height of approximately 200 m. The
other base station equipment is placed in the
building immediately to the right of the mast
121
THOMAS HAUG 467.5 MHz were suitable for most of the across the border, at least in the border
Headquarters of the countries. As far as Sweden was con- regions. The older systems did not per-
Swedish Telecommunications Administration
cerned, the problem was that an agree- mit such joint traffic, and exhaustive
ment with the defence establishment discussions were necessary before all
prevented these bands from being used countries could agree to give blanket
for civilian purposes in wartime and dur- permission. In one case the law had to
ing periods of military preparedness. In be changed.
view of the large investments in military
equipment for these frequency bands it
was difficult to obtain any changes in
the agreement quickly. It was only after Technical principles
long negotiations that the problem The main part of the work of the NMT
could be solved satisfactorily. The group has been to specify the automatic
Swedish Administration was then able system and verify that the ideas were
to inform the other countries that it feasible. The group started the work on
could agree to the new system using the the automatic system by laying down
above-mentioned frequency bands, some preliminary basic operational re-
which with a channel spacing of 25 kHz quirements. One of the main principles
gave 180 duplex channels By this time was that the system should, as far as
the problem had become acute, since possible, function as an extension of the
the manual system was almost ready to fixed network. Consequently the be-
be put into operation. This system was haviour of the system, as experienced
to use some of the channels in the by both mobile and ordinary subscrib-
agreed bands. The automatic system ers, has to be as similar as possible to
would later successively take over these that of the fixed network. This require-
channels, and the manual system could ment had to apply for all parts of the
then be closed down. system in both traffic directions, for the
handling of the mobile exchanges, for
The second problem was that existing calls from the fixed network, for the ser-
regulations had to be changed so that vices offered and for the security func-
mobile subscribers could also use the tions. It was also desirable that the sys-
equipment during journeys in the neigh- tem should offer the same traffic facili-
bouring countries. The usefulness of ties as the fixed network. Thus it had to
compatible systems to the subscribers be possible for any A-subscriber to es-
depends on their being able to use the tablish contact with a mobile station
Fig. 2 systems in the other countries without without any special operations, as long
The base station equipment at Nacka. To the left any bureaucratic procedures and also
is the line rack and to the right the base station, a
as the mobile station was within the
version for eight channels
being allowed to use radio circuits range of the system, even if it was away
from its home area. It was also clear that
for economical and practical reasons it
was impossible to make any appreciable
changes in the fixed networks, which
must therefore be accepted as they
were.
will itself in some respects function as channel that has already been estab-
such an exchange. MTX must also con- lished, it can distinguish this case from
tain many of the functions which in the the cases where it must insert its own Z,
fixed network are placed in the local ex- figs. 3 and 4.
changes, such as rating, charging and
other subscriber functions. The set re- However, the call connection method
quirement are considerably more de- described here means that calls to a
manding than those set for previous mobile subscriber away from his home
mobile telephone systems, and this nat- area would use a longer path than that
urally affected the solutions found for for which the caller is charged. The prin-
the various problems. ciple of always charging the A-subscrib-
er had to be adhered to. Hence the use
As a result of the requirement that the of the long distance circuits would not
system should be compatible with the bring the Ad ministrations any additional
existing telephone network without income. The proposed connection
changes it was necessary to find new method would thus introduce a new rat-
ways of solving the numbering prob- ing principle, but the Administrations
lems. Since the digit capacity of the lo- accepted it unanimously since its ad-
cal registers in the fixed networks was vantages were considered to outweigh
limited to seven digits (eight in Sweden) the disadvantages.
in addition to the trunk code, and since
it was not possible to use an access The possibility of switching a call from
number that was shorter than the trunk one base radio station to another while
code followed by two digits, in general the call is in progress 56 helps to give
only five dig its were available to indicate good speech quality. The advantages of
a mobile subscriber on the radio route. this facility become even more apparent
This capacity was obviously too small, when the range of the base radio sta-
particularly if it was to be spread over tions is reduced and a small cell system
four countries. Sufficient number ca- is introduced. In a few years this will
pacity was obtained by equipping MTX be done in the region comprising
with the possibility of inserting a coun- Copenhagen and Malmo, where the traf-
try code, Z, before the subscriber num- fic is expected to increase most rapidly.
ber in the case of calls to mobile sta-
tions. This means that a call to a mobile
subscriber will always first be routed to
his home MTX (MTXH). In order to en- Trial system
able the callers to reach mobile sub- At an early stage the NMT group realized
scribers who are out of reach of their that the proposed functions would re-
MTXH, the latter must add further digit quire processor control of both the base
information. This means that on the radio stations and the mobile stations.
basis of its knowledge of the mobile This fact was not considered a problem
subscriber's whereabouts, the MTXH in view of the rapid development in the
sets up a call to the MTX concerned, microprocessor field. However, the de-
regardless of in which country that MTX mands made on the signal transmission
is situated. The information concerning over the radio route could cause prob-
the identity of the sought subscriber, in- lems, and practical tests were required
cluding the country code Z, is then to verify the ideas.
transmitted using MFC signalling end-
to-end. Since the MTX concerned re- A small joint trial system was designed
ceives the information over a speech by a subgroup within NMT and was built
Fig. 4
A mobile station which is reached from an MTX
(MTXV) other than the MTXH
123
Fig. 7
Different makes of mobile station equipment
based equipment is identical every- The group devoted a considerable
where and for all makes. This interface amount of time and labour to specifying
is rather complicated, and it is essential the testing method and equipment in
that the type testing is carried out metic- order to ensure the desired uniformity of
ulously and under exactly identical con- tests. Certain functional tests must be
ditions for each test, regardless of place repeated many times under different,
or time. If this uniformity can be carefully specified conditions, after
achieved, it should normally be suffi- which statistical evaluation is carried
cient to carry out detailed type testing of out. This requires a system simulator,
a mobile station in only one country. The which simulates the land-based system
acceptance in the other countries where and which quickly carries out the re-
the manufacturer desires to market his quired number of measurements. The
equipment will then usually be only a simulator was specified jointly by the
formality. Administrations, and each Administra-
tion has purchased one. The uniformity
of the evaluations is now assured as far
as possible.
of six mobile exchanges, to be delivered NMT group, like many other Nordic
in accordance with atime plan prepared working groups, has not been troubled
jointly by the Administrations. The good by the confrontations that so often oc-
collaboration between the Administra- cur in international working groups.
tions, which had started during the Naturally there have been several vig-
tendering stage, has continued during orous discussions concerning difficult
the follow-up period. problems where the members have
been of different opinions. Nevertheless
Coordination was also needed for the the group has always been able to keep
base radio stations, and a joint technical the discussions on the technical plane.
specification was therefore prepared by The dividing lines have more often lain
an expert group. For several reasons the between representatives of different
Administrations desired to distribute technical branches than the representa-
the orders among three manufacturers. tives of different Administrations. Un-
Extensive, coordinated follow-up work like political problems, technical prob-
is now also being carried out for the lems can generally be analyzed and
base stations. solved with the aid of common sense
and a will to compromise. When the Nor-
Another field that needed coordination dic mobile telephone system is now
was tariffs. The fact must be accepted taken into service, the NMT group hopes
that the tariffs differ in the Nordic coun- that the system will meet the technical,
tries. The tariff levels in the wire net- traffic and economical demands made
works vary and the countries have dif- on it by the Administrations and the sub-
ferent tariff policies. However, a similar scribers.
tariff structure seemed feasible, so that
the same principles were applied when
charging for the various services. Tariff
experts from the Nordic countries pre-
pared a proposal for such uniform prin-
ciples. This proposal formed the basis
for the tariff regulations.
Summary
The mobile telephone system has now
been or is being installed in the Nordic
countries and was in part put into ser-
vice in the summer of 1981. It will suc-
cessively be extended in accordance
Fig. 9 with the plan shown in fig. 8. The corre-
Prognosis for the number of subscribers in the sponding subscriber prognosis is
Nordic mobile telephone systems shown in fig. 9.
References
1. System Description. NMT Doc. 1,
1980.
The system is in many respects a com- 2. MTX Specification. NMT Doc. 2,
promise between conflicting demands. 1977.
The requirements that were originally 3. Mobile Station Specification. NMT
formulated by the NMT group have been Doc. 3, 1979.
4. Base Station Specification. NMT
met in general, if not in every detail. Doc. 4, 1978.
However, the great interest which the 5. Haug, T.: Common Automatic
work of the group has aroused abroad Mobile System in Denmark, Fin-
concerns not only the design and land, Norway and Sweden. Third
World Telecommunication Forum,
characteristics of the system, but also Geneva, 1979.
the fact that the project has been carried 6. Billstrom, O. and Troili, B.: A Public
out in collaboration between Telecom- Automatic Mobile Telephone Sys-
munications Administrations. This col- tem. Ericsson Rev. 57 (1980):1, pp.
26-36
laboration has been considerably more 7. Makitalo, 6. and Verri, B.:
far-reaching than is usual outside the Signalling in the NMT System.
Nordic countries. The excellent result is Stockholm 1980.
largely dependent on the fact that the
CONTACT RL400-a New Radio Relay
Equipment
Einar Lundblad
dio means that the transmitters can be
SRA Communications AB, a Swedish subsidiary of LM Ericsson, has developed a
detected, monitored and located. The
radio relay equipment, CONTACT RL400, for telecommunication between mobile changeover to digital time multiplexing,
military units. The equipment works in the UHF band, providing 24 telephone with equipment for bulk encryption, has
channels when analog transmission is used and 120 channels with digital now made monitoring useless.
transmission. The equipment is microprocessor controlled, which makes it easy
to handle and provides efficient supervision. The possibility of locating transmitters
The article describes the equipment, its supervisory system, which also provides increases the risk of attacks or jamming.
protection against jamming, and how this protection can be developed further. One countermeasure is to use the vari-
ous radio circuits only for short periods.
This necessitates light, mobile com-
munication units which can be used to
set up new connections quickly to re-
UDC 621.396.93 Modern warfare requires a high degree place others. The increasing number of
of mobility and good telecommunica- equipments and the complexity of the
tions for coordinating activities. Most combined networks mean that flexibility
defence forces are provided with equip- and easy operation are two prere-
ment that enables them to quickly es- quisites for such communication units.
tablish and rearrange telephone net-
works between military staffs. Frequen- These operation prerequisites and the
cy multiplexing is used in order to requirement for protection against jam-
obtain sufficient capacity over the con- ming have all been considered when de-
nections, and the original transmission signing CONTACT RL400, fig. 1. The de-
medium consisted of cable. However, as sign and construction have been
the staff have to move often and quickly chosen so that the protection against
in order to adapt to the tactical situation, jamming can easily be improved further.
the cable connections have gradually
been supplemented with or replaced by Theequipment isdesigned fortransmit-
radio relay links. ting signals from both the older, fre-
quency multiplex systems and the new,
Radio relay equipment which operates encrypted, digital time multiplex sys-
in the UHF band has therefore been tems in order to facilitate a gradual
used in military telephone networks for changeover from the older to the newer
some decades. However, the use of ra- systems.
Fi9-1
Radio relay equipment CONTACT RL400
129
A transmission fault causes a test point The display panel is normally ex-
alarm but also an intermittent audio tinguished 30 seconds after a command
alarm, a visual alarm signal on the front has been received. It can be lit again or
panel and a contact closure for external switched off earlier by means of the but-
alarm. The audio alarm and the external ton LIGHT. The button marked LED is
alarm can be disconnected by depress- used to test all light emitting diodes in
ing TEST. A return to normal alarm func- the display panel.
tion takes place automatically when the
fault that caused the alarm has been
cleared. Electrical design
CONTACT RL420 is the first version in a
Simple local testing of the equipment series of equipments with the common
can be carried out by means of two dif- designation CONTACT RL400. RL420
ferent loop connections. These are set has four 50 MHz bands in the frequency
up with the LOOP button. With the high range 610-960 MHz. The four 50 MHz
frequency loop the transmitter is cou- bands can either be combined to form
pled back to the receiver for a complete one 200 MHz band or they can be placed
functional check of the equipment, in- separately within the range. The fre-
cluding any multiplex equipment. Any quency coverage can be altered by
functional faults can then be further lo- changing the duplex filter unit. The new
cated with the aid of the low frequency unit provides the processor with infor-
loop alowing functional testing of the mation regarding its frequency
low frequency parts of the equipment coverage.
including the multiplex and intercon-
necting cables. Both analog (FDM) and digital (TDM)
Fig. 3
Block diagram of CONTACT RL420
131
Mechanical construction
CONTACT RL400 is a robust equipment
designed for use in rough conditions in
the field. The equipment withstands
stringent mechanical testing, which in-
cludes six fall tests of 1 metre, corre-
Fig. 5
Block diagram of the scrambler and internal
multiplex for the service channel and internal
control channels
Fig. 6
Block diagram of the power regulating system
Technical data for CONTACT 133
RL420
Frequency range 610-960 MHz
RF bandwidth 4x50 MHz
Channel spacing 100 kHz
Number of RF channels 2000
Duplex spacing Fixed or variable
Modulation method FM
Output power 10-15W,0.5-1 Wor
0.05-15 W
Noise factor 8dB
FDM transmission 4, 12, 24 telephone
channels
TDM transmission 256,512. 1024,2048
kbit/s
Service channel subsystem channel is then used to transmit the ser-
0.3-2.5 kHz analog
vice channel information until thesignal
Service channel CONTACT RL400 contains a built-in ser-
with FDM strength has been improved, e.g. by ad-
16 kbit/s digital with
vice channel subsystem for fast and effi- justing the antenna direction, and the
TDM cient communication, fig. 7. The system multiplex signal can be connected
Power supply 185-275 V 4 5 - 6 5 Hz is of the omnibus type, i.e. everybody again. In this case the service channel
21-32 V battery hears everybody else. With digital oper-
Dimensions 310x345>440 mm transmission will be analog, and any ex-
ation the service channel is also digital ternal digital service channels will be
Weight 35 kg
and can be encrypted using external disconnected. The receive side of the
equipment. The handset is normally equipment is always automatically
connected to the connector marked switched over to analog reception when
HANDSET. The connector marked MUL- no digital signal can be detected.
TIPLEX EQUIPMENT can be used for
four-wire connection of a service chan-
nel from the multiplex equipment or a Development possibilities
relay station. Two-wire connection is Almost all functions in CONTACT RL400
also possible, via the AUXILIARY are controlled by the built-in micro-
EQUIPMENT connector, for encrypting processor. This means that functions
equipment and for an extended service and handling procedures can easily be
channel circuit, for example to a quar- changed by changing program stores.
ters tent. These connections can be External control systems can be con-
used in parallel. The speech control key nected to the interface in the OPERAT-
on the handset must be used, since the ING MODE connector for communica-
service channel is of the omnibus type tion with the processor. Among the
and the transmission is digital. When an possible new functions are: automatic
operator has depressed his key, the connection of a standby station, auto-
speech facility is blocked for the other matic change of channel and cen-
operators. However, calling over the tralized control and supervision at com-
service channel can be carried out even plex communication nodes.
if the channel is engaged, by depressing
the button EOW CALL. A calling signal is The system design has also been
then transmitted which makes it possi- chosen with a view to facilitating further
ble to attract attention even during a development of the protection against
call. interference. Thus all circuits are wide-
band in order to avoid manually or elec-
When radio operators are trying to set trically controlled tuning. The division
Fig. 8 up a connection over difficult radio into 50 MHz bands makes it possible to
Radio relay equipment CONTACT RL420 with field paths the transmission quality of the use an even wider spectrum for the
telephones, bulk encryption equipment, digital
service channel can be improved by dis- transmission. Such band spreading
multiplexors and digital node switches are some
of the units that are now available for building up connecting the multiplex signal inter- can, for example, be carried out by com-
digital encrypted telephone networks nally in the equipment. The whole radio bining the present frequency shift mod-
ulation with encrypted phase shift mod-
ulation. The regulation system that is a
prerequisite for using such a band
spreading method for transmission in
complex networks has already been in-
troduced.
Lars-Erik Larsson
packages, which are individually syn-
When developing new generations of PCM equipment, LM Ericsson is designing chronized. Channel-associated signal-
them for the same construction practice, BYB, that is used in the digital ling is usually the best method when at
telephone exchanges AXE 10. This mechanical integration will become least one PCM terminal has to cooper-
increasingly important as digital technology is introduced into the telephone ate with an analog exchange.
networks. Mechanical compatibility simplifies redeployment of equipment in
connection with rearrangements in the network. CCITT Recommendation Q.421 for sig-
In this article the signalling facilities and signalling requirements on PCM circuits nalling system R2 proposes a signalling
are discussed. The signal conversion equipments that are available for different diagram, figs. 2 and 16, for use with
channel-associated signalling in which
applications are described, with a detailed description of one of the signalling
only bits a and b are used.
equipments, ZAK 03-03, which is used for matching between an analog exchange
and timeslot T16 in a 30-channel PCM system.
When a PCM system is used as a link
between a digital and an analog ex-
change special attention must be given
to the signalling diagram. Procedures
UDC 621.376:
621.395.38
Signalling capacity of a must be specified for all signalling
30-channel PCM system states, even those that are not part of the
A first-order PCM system in accordance normal signalling sequence, otherwise
with CCITT Recommendation G.732 is blocking or self-oscillation can easily
intended for transmission of 30 simul- occur. It is also important to standardize
taneous calls. It contains 32 timeslots of in order to avoid expensive reprogram-
eight bits each. Timeslot TO is used for ming.
frame synchronization and T16 for sig-
nalling. Since T16 only contains eight Standardization of the signalling dia-
bits, it must undergo further time divi- gram also reduces the number of pro-
sion if channel-associated signalling is gram blocks per exchange needed for
used A multiframe is formed for this signalling, which simplifies the opera-
purpose. tion and maintenance of digital ex-
changes.
In a multiframe, T16 is used once for
multiframe synchronization (frame 0)
and in the other fifteen frames for the Signalling requirements
Fig. 1
The allocation ot T16 with channel-associated signalling for two speech channels at a When PCM systems terminate in analog
signalling. In bit 6, frame 0, loss of multiframe time,fig. LThusfoursignalling bits,a-d, exchanges, signal converters are
alignment is transmitted to the other terminal. are allocated to each speech channel needed to convert the d.c. signals from
X = 0: no errors; x = 1: multiframe alignment with a time spacing of 16x125 = 2000 the exchange to digital signals in T16.
error.
(is. The transmission speed per signal-
ling channel is 500 bit/s. As analog techniques have evolved, the
exchanges themselves and the signal-
Between digital exchanges, common ling over the junction lines between
channel signalling can also be used, for them have been successively improved.
example CCITT signalling system no. 7. This means that several d.c. signalling
Fig. 2
CCITT signalling diagram R2, digital variant
In this system no multiframe is formed diagrams may be in use even for the
but the information is transmitted in same type of exchange. New variants of
signal converters must therefore often
Signalling code be developed for slightly different d.c.
signalling diagrams.
Fig. 3
The d i f f e r e n t i n t e r f a c e s t o w h i c h t h e PCM
s i g n a l l i n g e q u i p m e n t c a n be a d a p t e d :
IDF Interface between the group selector and
FUR or FIR
MOF The traditional Interface between the ex-
change and the analog junction line
4W Four-wire interface for the speech path of
the PCM equipment
E&M E&M Interface between E&M signalling
equipment and the signal converter FUP or
FIP
64 kbit/s The 64 kbit/s interface of the PCM system
Line Interface towards the 2 Mbit/s line system
136
In the first two cases the need of a stan- phone network the various signalling
dardized PCM signalling diagram is ob- equipments can be used. The signalling
vious. The digital version of the CCITT equipments that have been developed
signalling diagram R2 is well suited to are listed below, with their applications:
such standardization. However, there - ZAK 01 is used w h e n the exchange is
are a number of signals in the analog equipped with j u n c t i o n line relay sets
local networks w h i c h are not included in for E&M signalling
the CCITT diagram, and complete stan- - ZAS 01-07 is used for subscriber line
dardization is therefore not possible. signalling, for example in rural areas
with few subscribers, or in urban net-
In the third case the E&M signalling dia- works for c o n n e c t i n g subscribers to
gram already in use towards the transit foreign local exchanges
exchange must be applied, and in the - ZAK 02 is used for signal conversion
last case the difficulties of designing a towards LM Ericsson's exchange sys-
channel-associated network can be tem ARF 101, i.e. register signalling
overwhelming. with d.c. code
- ZAK 03 is used for matching to LM
PCM signalling equipment must there- Ericsson's exchange system ARF 102,
fore be easy to adapt to different PCM w h i c h has a standardized line signal-
signalling diagrams. LM Ericsson's sig- ling system with direct current in a
nalling control unit, w h i c h is c o m m o n to loop and r e g i s t e r s i g n a l l i n g with com-
30 channels, is then doubly useful. It is pelled MFC signalling. ZAK 03 is avail-
used not only to control the test and able in several versions, e.g. for de-
operate points of the channel boards, as cadic impulsing as used in Strowger
has already been mentioned, but also to exchanges
implement the signalling diagram to- - ZAK 04 is used for m a t c h i n g to ex-
wards the digital side. The program- changes with signalling in accor-
ming facility makes it easy to implement dance with Siemens' EMD system
custom designs. - ZAK 05 is used for matching to LM
Ericsson's 500-selector exchanges,
AGF, with translation registers for
Alternative signalling MFC.
equipments A m o n g these types ZAK 03-3 has been
The position of the signalling equip- chosen for a more detailed description
ment in the PCM hierarchy is s h o w n in of its development, system design and
fig. 4. Fig. 5 shows where in the tele- signalling diagram.
Fig. 4
The position of the signalling equipment in
the PCM hierarchy. The figure shows the
interconnection of the various systems and
their association to AXE 10
137
Fig. 5
A telephone region with different types of
signalling
ZAK 01
ZAK 01 alt. 03
ZAK 02-05
ZAS01-7
ninltal line
RC network, which makes the polarity ways, fig. 8.
inversions less steep. Charging pulses
If no demands are made on the digital
can then be transmitted without inter-
signalling code except that the analog
fering with calls in progress, fig. 7, while
signals are to be transmitted, the meth-
at the same time loop detection is so fast
od using channel-associated logic is
that decadic impulsing is possible.
usually preferable, fig. 8a. However, if
MP1 C o n t r o l of the an advanced digital signalling diagram
polarity inversion Coding using a microprocessor
transistor
such as CCITT R2 is required, this meth-
In the signalling equipment coding is
od is less attractive, because it gives a
carried out between the received signal-
Fig. 7 large array of gates per channel.
The basic principle to obtain quiet polarity ling information, a b andb b , and the oper-
inversion together with fast loop detection. ate points for d.c. conditions towards The alternative using clock-controlled
The figure shows only one of the polarity the exchange, and also between the test logic, fig. 8b, is a method relying on re-
inversion transistors, for the a-wire
points for d.c. conditions from the ex- designing hardware. When modifica-
TP Test point
MP Operate point change and the transmitted signalling tions or new designs are required the
code, a, and bf. In principle the coding unit with the clock-controlled logic
can be performed in three different must be entirely redesigned
Fig. 8a
Symbolic diagram of a channel-associated
gate network for decoding received signals,
a„ and b b , and c o d i n g t h e transmitted signal, a,
MP Operate point
Fig. 8b
Clock-controlled g a t e network for t h e same
function as shown in Fig. 8a
MUX Data selector, multiplexor, in the send direc-
tion
LCH Data selector with memory, M, in the receive
direction (latch)
Fig. 8c
The gate network in f i g . 8b r e p l a c e d by
microprocessor control
Fig. 9
Through-connection of PCM channels from
exchange A t h r o u g h B to exchange C
^^m"^ Mux + line system
-^—— Physical line < 1300 ohms
With microprocessor c o n t r o l , fig. 8c, ciently free from interferences that the
such a change in hardware is replaced equipment can be used up to the resis-
by a change in p r o g r a m . This alternative tance limit of about 1000 ohms.
therefore gives greater flexibility and
more reliable f u n c t i o n . Optimization of Construction practice BYB
the logic f u n c t i o n s is easier to carry out The BYB c o n s t r u c t i o n practice, w h i c h
in programs than in hardware. The pro- has been chosen for this generation of
gress in the s e m i c o n d u c t o r industry has PCM signalling equipments, has pre-
brought d o w n the cost of alternative 8c viously been described in several arti-
to such a level that it is now quite rea- cles 1,23 .
sonable in view of its advantages This
alternative has therefore been chosen The use of this c o n s t r u c t i o n practice for
for ZAK 03-3. However, the micro- transmission equipment also provides
processors available on the market were mechanical compatibility between the
all too slow to serve 30 PCM channels, digital exchange and transmission
and hence a special PROM-controlled equipment. This will b e a n advantage for
processor has been developed. the rearrangement of transmission
equipment that will become necessary
Modified requirement for extension during the evolution of the digital net-
over physical circuits work. In many cases the trunk circuit
In an earlier version (ZAK 03-1) in the M5 equipments, OTC and ITC, in system
construction practice 4 , the PCM chan- AXE 10 can also be used as signal con-
nels could be t h r o u g h - c o n n e c t e d over verters for PCM systems.
physical circuits, fig. 9. This ability has
been reduced in ZAK 03-3. It is only SYSTEM STRUCTURE
rarely used, and transistorized sensing Signalling e q u i p m e n t ZAK 03-3 consists
circuits and polarity inverters that are of five different units, figs. 6 and 10.
immune to interference have proved to
be very expensive. The disturbances The signal converters FUP and FIP each
that normally occur in a telephone net- contains equipment for four PCM chan-
work consist of longitudinal and trans- nels. FUP is used for the o u t g o i n g and
versal interferences caused by dif- FIP for the incoming traffic direction.
ferences in potential, lightning or near-
by power lines. However, a study has The control unit, the 64 kbit/s interface
been started to investigate whether ca- unit and the d.c./d.c. converter are c o m -
ble networks in large cities are suffi- mon to all 30 channels.
Fig. 10
Block diagram of signalling equipment
ZAK 03-3
Fig. 11 F U P a n d FIP,figs. 10. 11 and 12, contain facilities are seldom needed in one de-
Signal converter FUP
a hybrid circuit w h i c h provides the tran- sign.
Fig. 12 sition to the four-wire speech path. The
Signal converter FIP fourwire speech path is connected to The PCM multiframe structure is gener-
the PCM multiplex magazine. The ated in the 64 kbit/s interface unit, fig.
Fig. 13
hybrid circuit is also used to separate 14.
Control unit
the speech and signalling paths. The
signalling path contains the tran- The send direction contains a 16-coun-
sistorized converters for conversion be- ter w h i c h is stepped once for each
tween analog d.c. signals and TTL lev- frame. The multiframe synchronization
els. w o r d is transmitted w h e n the counter is
in the position for frame 0. In the other
The transmission between the signal frame positions the signalling code for
converters and the control unit is done the relevant channel pair is transmitted.
over a c o m m o n bus that is divided into
send, receive and control paths, see fig. The receive d i r e c t i o n also c o n t a i n s a 16-
8c. counter w h i c h is stepped in synchro-
nism with the counter in the transmit-
In addition to the bus leads s h o w n in fig. ting terminal. When the former is in
8c there is still another i n f o r m a t i o n position 0, a check is made that the syn-
path, over w h i c h the control unit is in- chronization w o r d has been received,
formed whether an FUP or an FIP board otherwise a resynchronization routine is
is inserted, so that the correct signal initiated. If the system is in synchronism
converter program can be activated. the received signalling code is con-
nected t h r o u g h to the control unit dur-
The PROM circuits in the control unit, ing each of the subsequent frames.
fig. 13, contain the programs for setting
Fig. 14
the operate points and c o d i n g the test SIGNALLING DIAGRAM
64 kbit s interface unit point information to the signalling dia- A signalling diagram for ZAK 03-3, with
gram. They also contain t i m i n g pro- signalling between two analog localex-
grams, w h i c h are needed for example c h a n g e s o f type ARF 102, is s h o w n in fig.
when the d.c. signalling of analog ex- 16. The time axis points downwards in
changes is not full duplex. Fig. 15 shows the diagram. The signalling sequences
a typical case where t i m i n g is neces- are specified by the state numbers. All
sary. The control unit can also be pro- states having the same number are iden-
grammed for pulse c o r r e c t i o n , double tical, i.e. the signalling sequence can
Fig. 15 current detection of polarity inversions, continue with any of the signals that
The interworking between two analog ex-
generation and detection of timed sig- start with the same state (same colour).
changes where the sending of a charging
pulse, a polarity inversion, momentarily gives nalling elements etc. However, all these
a false clear forward because of the high
inductance of the relays in SR.
Fig. 16
Signalling diagram for ZAK 03-3 used be-
tween two ARF 102 exchanges
"Bover PCM"
(line) = 1
{no line) = 0
High-ohmic loop
Low-ohmtc loop
-f-polarity on the a-wire
-polarity on the b-wire
Technical data
Transmission characteristics
Frequency range, speech path 300-3400
Hz
N o m i n a l i m p e d a n c e . IN/OUT 600/600
o h m s , bal
Return loss on the t w o - w i r e side
measured against 600 o h m s
3 0 0 - 6 0 0 Hz 15 d B
6 0 0 - 3 4 0 0 Hz 20 d B
L o o p a t t e n u a t i o n w h e n the line
side is t e r m i n a t e d in a n o m i n a l
c o m p r o m i s e balance
300 Hz 27 d B
1000 Hz 40 d B
3400 Hz 34 dB
Balance a t t e n u a t i o n t o w a r d s eartr
3 0 0 - 3 4 0 0 Hz 50 d B
Attenuation 2-wire-4-wire.
nominally 5dB
Attenuation distortion
3 0 0 - 6 0 0 Hz +0.6 t o
-0.2 dB
6 0 0 - 3 4 0 0 Hz t0.2dB
G r o u p delay d i s t o r t i o n
5 0 0 - 6 0 0 Hz 200 lis
6 0 0 - 3 4 0 0 Hz 100 (is
General data
Feeding voltage -48 V
limits - 1 0 to
+ 15%
Power consumption, equipped
magazine
w i t h 8 FUP a n d all c h a n n e l s
idle 40 W
w i t h 1 e r l a n g per c i r c u i t 60 W
w i t h 8 FIP a n d all c h a n n e l s idle 25 W
w i t h 1 e r l a n g per c i r c u i t 25 W
D i m e n s i o n s of the m a g a z i n e
height 244 m m
width 488 m m
depth 220 m m
W e i g h t fully e q u i p p e d 10 8 kg
Manufacture of Hybrid Circuits
Resistor networks
Organization The resistor networks consist of ce-
In orderto increase the work motivation, ramic substrates on which conductor
and thus reduce process times, run- patterns and resistors have been screen
Fig. 5
Laser trimming of thick film resistors
printed, figs. 4 and 11. The printing pas- A lead frame is mounted on the ceramic
tes used are a mixture of, for example, a substrate, and is connected to the resis-
conducting material in powdered form, tor contact surfaces by means of dip-
glass powder and an organic binding ping in a solder bath, fig. 9. The leads are
agent. A palladium-silver paste is nor- then cut to the correct length and the
mally used for the conductors and resistor network is ready for final electri-
different metal oxide pastes, e.g. cal testing. This is done in processor-
ruthenium oxide, for the resistors The controlled test stations with automatic
conductor and resistor patterns are handling of the circuits.
then made electrically and mechan-
ically stable by sintering at 850°C. Chip & wire circuits
When manufacturing chip & wire cir-
Since the screen printing gives a well cuits an additional gold layer is screen
defined printing thickness, the resis- printed which overlaps the palladium-
tance of each resistor made of a certain silver layer. The gold layer is used to fix
paste will be determined solely by its semiconductor chips on the substrate
length and width. The width of the resis- by means of eutectic soldering. At the
tor can be reduced by laser trimming, eutectic temperature 380°C gold and sil-
which increases its resistance to the de- icon form an alloy which gives good
sired value, fig. 5. contact between the chip and the con-
Fig. 6
Ceramic substrates and printing pastes undergo
incoming goods inspection before the printing.
Conductive patterns, resistors and protective
glass are screen printed in 5—10 layers with
drying and sintering in between. Each layer is
10-15 fim thick. The resistors are laser trimmed to
a limit of 0.5 %. The picture shows printed and
trimmed "snapstrates" of a chip & wire circuit, a
circuit with soldered components and a resistan-
ce network
Fig. 7
The gold wire connects the chip to the conducti-
ve pattern on the substrate
145
Fig. 8 ductive pattern on the substrate. During te. The circuits are fed through an IR
The components are mounted after the substra-
the subsequent bonding the chip and oven, where the solder paste melts and
tes have been snapped. The chip & wire circuit to
the left has semiconductors soldered on and then gold pattern are connected by means of the components are soldered to the sub-
connected via gold wires to the gold conductors a 25 (xm thick gold wire, figs. 7 and 14. strate. After this the solder joints are in-
on the substrate. The circuits with soldered spected, the leads are assembled, and
components, to the right, are first screen printed
with solder paste, after which the components
This process results in a chip & wire the circuit is encapsulated and tested.
are soldered in an IR furnace circuit, i.e. a circuit that consists of
printed conductors, printed resistors, Circuits with soldered components are
printed capacitors and semiconductor mechanically insensitive. They can be
chips as diodes, transistors and other repaired by changing a faulty compo-
monolithic circuits. nent. This is particularly advantageous
when manufacturing large and compli-
The chip & wire technique is very space- cated circuits.
saving. Many circuit types manufac-
tured in this way are less than 3 mm Production techniques
thick, with an area of less than 4 cm2.
RIFA's series manufacture of hybrid cir-
After the assembly and soldering of cuits is characterized by sophisticated
leads the circuits are encapsulated for production techniques and a high de-
mechanical and environmental protec- gree of automatization. Among the so-
tion. The chip & wire circuits are phisticated process techniques may be
moulded in silicone and epoxy resin. mentioned laser trimming of thick film
The final testing is then carried out. resistors to an absolute tolerance of
0.5% and a relative tolerance of 0.1 %,
Circuit with soldered components and through-plating of holes on the ce-
In these circuits encapsulated semicon- ramic substrate. (Computer-controlled
ductor chips are connected direct to the machines, test systems and multi-oper-
conductive pattern on the substrate by ation machines are some examples of
means of surface soldering. Semicon- the high degree of automatization).
ductor chips are available as standard 3-
module DIP. Other common encapsula- Large production series and strict stan-
tions are TO 92, TO 220 and SOT-23. dardization of dimensions and compo-
Other components, such as ceramic ca- nents have also enabled many opera-
Fig. 9
The next stage in the manufacturing process is pacitors and tantalium capacitors, are tions to be automatized, such as the
the lead assembly. The picture shows a chip & also available for soldering. mounting of soldered components,
wire circuit, a circuit with soldered components bonding, the mounting of leads and the
and a strip with resistor networks, where the
Surface soldering of circuit compo- final testing. Several projects for further
leads are soldered on by means of dipping in a
solder bath nents starts with screen printing of sol- automatization of the production are in
der paste on certain parts of the con- progress. The main advantages of auto-
ductive pattern on the substrate. The matization are, apart from the lower di-
components are then positioned on the rect cost, a higher yield and a better
circuits, with the pins in the solder pas- quality.
Fig. 10
After encapsulation and cutting of the leads to
the correct length the circuits are ready for the
final testing. The figure shows various types of
encapsulated circuits
146
Fig. 11
Printing of substrates for speech circuits
Fig. 14
Processor-controlled bonding machine
147
Fig. 16
The package welding takes place in a glove box
containing pure nitrogen
All circuits undergo a final test, which manufacture of high reliability circuits,
for all series produced circuits is carried fig. 13. This unit is housed in a separate
out in processor-controlled test sta- department, supplied with hydrogen,
tions. These can provide direct print- nitrogen, oxygen, vacuum chambers,
outs of fault specifications for each indi- compressed air, return air, cooling
vidual circuit and a statistical fault water and deionized water. The ventila-
distribution for a whole batch. Many tion system provides the premises with
types of circuits are tested both at room filtered air with constant humidity.
temperature and at a higher tempera- "Laminar flow" hoods are used for the
ture. process stages that require extreme
cleanliness (class 100). The machinery
After the final testing, fig. 12, thequality includes two processor-controlled
control department, which operates as bonding machines and a seam welding
an independant unit, carries out a machine for hermetic encapsulation,
screening of the circuits. A statistically figs. 14 and 15.
chosen sample is tested with regard to
the electrical and mechanical charac- The tasks of the unit can be summarized
teristics. Some circuits are also selected as:
for more comprehensive quality control. - manufacture of small series of high
Fig. 17 reliability circuits and circuits with a
Hermetically encapsulated circuits high degree of complexity, for exam-
Manufacture of high ple for military and medical equip-
reliability circuits in small ment
- development of new processes and
series technical preparation of new prod-
The factory also contains a unit for the ucts using new techniques.
Fig. 19
The whole batch is inspected after most process
steps
E
Box
Production flow for high reliability circuits
1 Thick film substrates
1.1 Screen printing of thick film patterns with
conductor widths down to 0.15 mm in seve-
ral layers (fine line and multi-layer printing),
tig. 4
1.2 Sintering of the pastes at 850'C
1.3 Laser trimming of resistors
2 Hybrid circuits
2.1 Glueing of semiconductor chips and cera-
mics capacitors on thick film substrates
with silver polymers
2.2 Bonding of semiconductors and substrate
using gold wire (d = 25 fim), fig. 7 One characteristic of high reliability cir- A high degree of work motivation is re-
2.3 Glueing of thick film substrates with com- cuits is that they are usually her- quired of the staff if the high quality is to
ponents in the package base metically encapsulated, mostly in metal be maintained. For this reason project
2.4 Gold wire bonding to the package leads or ceramics. The package protects the groups of about five persons have been
2.5 Electrical testing and pre-cap inspection of
the whole batch hybrid from the environment and also formed. Each group manufactures simi-
2.6 Changing any faulty components (repair) gives good mechanical protection, fig. lar circuits. Each operator is responsi-
2.7 Sealing 17. ble for and carries out all process steps
2.8 Electrical test and leakage test for a batch of circuits. The operator
3 Screening
3.1 High-temperature baking (e.g. 125°C, 24 h) Hermetic sealing of packages is carried knows the calculated time and yield for
3.2 Centrifugal test (e.g. 20000 g) out by welding or soldering. It is per- each process step, and can thus judge
3.3 Temperature cycling test (e.g. -65/+150C, formed in a glove box containing pure the amount of work required to com-
10 cycles) nitrogen, fig. 16. The quality of the her- plete the product.
3.4 Electrical test
3.5 Electrical burn-in (e.g. pulsed load at 125°C
metic sealing is tested by means of a
during 168 h) helium spectograph. The humidity of The wide knowledge of the staff in the
3.6 Electrical test the nitrogen in the glove box is fields of printing (fine line, multi-layer),
3.7 Helium leakage test monitored continuously. Before sealing connection of semiconductors and en-
3.8 Bubble leakage test
the circuits are baked in an oven. capsulation (both hermetic and plastic
moulding) has been a prerequisite for
The high reliability circuits manufac- the manufacture of prototypes and pilot
tured are more complex and are man- versions of sophisticated hybrid cir-
ufactured by means of more compli- cuits, for example for telecommunica-
cated processes than the mass-pro- tions.
duced circuits. A typical production
flow for a high reliability circuit is shown The interest and wide technical skills of
in the box to the left. the staff in the manufacturing unit have
contributed to the development of pro-
The whole of each batch is inspected totypes and the pre-series manufacture
after practically every process step, fig. of several new and important circuits,
19, in order to obtain the required for example for new exchange equip-
quality. Acceptance tests of samples are ment. The circuits have then been pre-
carried out after items 1.3, 2.2, 2.6 and pared for series production in close col-
3.8. A screening procedure is carried laboration with the production prepara-
out to remove weak circuits. tion unit and quality control unit of the
hybrid factory.
References
1. Larsson, S. and Sternbeck, O.: RIFA
- a Modern Component Manufac-
turer. Ericsson Rev. 5 7 ( 1 9 8 0 ) : 1 , pp.
TELEFONAKTIEBOLAGET LM ERICSSON
4 1981
AGA-ERICON-A MARINE RADAR BEACON
A COOLING SYSTEM FOR ELECTRONIC TELEPHONE EXCHANGES
HIGHER-ORDER DIGITAL MULTIPLEXORS
ERICSSON REVIEW
NUMBER 4 1981 VOLUME 58
P U B L I S H E D IN S W E D I S H . E N G L I S H , F R E N C H
A N D S P A N I S H W I T H F O U R I S S U E S PER Y E A R
T H E A R T I C L E S M A Y BE R E P R O D U C E D
AFTER C O N S U L T A T I O N WITH THE E D I T O R
Contents
150 • Ericsson T o w a r d s the 1990s
152 • Ericsson Information S y s t e m s - A New C o m p a n y
159 • A X E 10 in S w e d e n
168 • LSI Design C e n t e r
175 • ASB 900 in the Finnish R a i l w a y N e t w o r k
180 • A G A - E R I C O N - a M a r i n e Radar B e a c o n
188 • A C o o l i n g System for Electronic T e l e p h o n e E x c h a n g e s
196 • H i g h e r - O r d e r Digital Multiplexors
COVER
The radar beacon AGA-ERICON installed
on the caisson lighthouse Trubaduren at
the entrance to the harbour of Gothenburg
on the west coast of Sweden
ERICSSON
Ericsson Towards the 1990s
For more than a century the activities of the Ericsson Group have been devoted almost
exclusively to the telecommunications field - development, manufacture and marketing.
Although the emphasis has been placed on public equipment for telecommunications ad-
ministrations, and particularly on telephone exchanges, the Group holds a prominent
position in the whole field of telecommunications.
Within the Group, which has large re- tions, which forms part of the parent com-
sources as regards technology, production, pany, develops and markets all types of
marketing and management, a number of public telecommunication exchanges for
changes have been carried out, during the telephony, data and telex, analog and digi-
last two years. A certain degree of restruc- tal transmission equipment, manual tele-
Bjorn Svedberg turing and augmentation of these resources phone systems and power equipment. The
Head of has enabled the Ericsson Group to offer a division is thus very well equipped for im-
the Ericsson Group
wider product range and has resulted in a plementing complete telecommunication
more market-oriented structure. networks, which is becoming an in-
From the point of view of the Ericsson creasingly common method of marketing
Group the telecommunications market can and purchasing. The Ericsson Company
be divided into three main sectors: has recently successfully completed such
turnkey contracts in Saudi Arabia and
Tele- Telecommunications Oman.
communications administrations and
Administrations: public companies etc.
Private enterprises
which provide public
networks for telepho- and administrations
ny, data and telex. Telecommunications and data processing
Private enterprises Companies, public and are becoming more closely integrated, and
and private administrations the requirements of computer systems as
administrations: and organizations re- regards communication and network func-
quiring internal tele- tions have both increased and become more
communications ("the technically demanding. The Ericsson
private sector"). Group has therefore made use of its exten-
Defence: Defence administra- sive communication know-how to enlarge
tions, naval and air its product range within the private sector
force administrations. by introducing systems for administrative
data processing, office management and
The Ericsson Group offers a very wide organization. The Group is now also estab-
product range for all three market sectors, lished as a manufacturer of complete
supplemented by a number of additional systems for information handling, i.e. the
facilities, such as servicing, training, instal- transfer, processing, storing and presenta-
lation etc. tion of speech, data, text and visual dis-
plays. This has been achieved through the
Telecommunications purchase of Datasaab by the parent com-
pany and by the Group's own earlier
Administrations development work in the field. A new com-
The division for public telecommunica- pany, Ericsson Information Systems AB,
was formed from the Datasaab group, sup- dustry in the form of telecommunications sents an increasingly large part of the
plemented by the divisions for information and telemetry for pipelines. overall system cost and the number of
systems and subscriber equipment, which Planning, installation, operation and programmers available tends to be limited.
were transferred from the parent company. maintenance and the training of customer
Ericsson Information Systems is described staff are all services of great importance to
Strengthening of the
in a subsequent article in this issue of Erics- all the branches of the Group. To these can
son Review. now be added services in the field of data Group internationally
The product range available to the pri- processing. A new company, Ericsson This brief, general description of the Group
vate sector has been further supplemented Programatic AB, has been formed, and and its aims would not be complete without
by the inclusion of Autotank AB in the another company, AU-System Network reference to the international aspect. In
Group, and by the parent company becom- AB, has joined the Group to provide re- 1980 a new company, Anaconda-Ericsson
ing part owner of AB ID-Kort. Autotank sources in the software field. The consulta- Inc., was formed in the USA jointly by
AB develops and markets petrol station ter- tive and project work, as well as develop- Ericsson and the American enterprise
minals which enable customers to purchase ment work on application software carried Atlantic Richfield Corporation. The main
petrol by means of credit cards or bank- out by these companies, constitutes an im- production of Anaconda-Ericsson now
notes even if the station is unattended. This portant addition, particularly within the consists of cable and wire manufactured in a
technology will have a number of other ap- private sector. number of factories in the USA and Latin
plications in the retail trade. AB ID-Kort America. The Anaconda-Ericsson Tele-
manufactures different types of bank, credit communications Division, which already
and identity cards, and is thus a logical addi- Technology markets PABXs, transmission systems and
tion to the Group. The Ericsson group uses advanced technol- bank terminal systems, constitutes a valua-
ogy, which requires extensive research and ble addition to the Ericsson Group, form-
development work. R & D are carried out ing a basis for the activities of Ericsson In-
Defence in all units, although only three cases of formation Systems in the USA. The private
particular interest will be mentioned here. sector in the USA constitutes about 50% of
Several units within the Group are engaged the world's private market, and establish-
in the design, manufacture and sale of de- In the optical field the Group has carried
out research and development work for ing the Ericsson Group in the USA is an
fence equipment. The marketing side has extremely important move, intended to
been reinforced, and this has enabled the over a decade, and optical fibre cables and
the associated transmission equipment are reach a large potential market as well as
Group to offer complete strategic and tacti- adding to the development resources.
cal telecommunication networks with now being marketed. This technology is
already well established in public city net- The changes that have been described
associated operating centres. The networks
works, and is expected to be an important here will quickly penetrate other foreign
include products from the parent com-
alternative to both traditional cable and markets, and the initial effect will be a
pany's divisions for defence electronics and
other transmission media in all types of net- strenthening of the marketing side.
for public telecommunications as well as
from SRA Communications AB and Erics- works within a few years.
Rapid advances are taking place in com-
son Information Systems. Some well- Ericsson
known Ericsson defence products are in- ponent development in both the telecom-
munication and data processing fields. The Ericsson Group has entered the 1980s
teractive computer systems for air traffic
Custom design circuits are of particular in- as a stronger enterprise, with a wider pro-
control, radar, IR and laser systems for air,
terest. Such circuits are developed for duct range and with an organization for
marine and ground use and equipment for
specific applications in particular products, more efficient marketing. The changes that
satellite communication.
and as resources for such production are have already been carried out and others
available within the Group, alternative sup- that are still to be made are important and
plies are ensured and the need for external necessary measures in order to maintain
Network installation manufacture is reduced. AB Rifa and a spe- the position of the Group as one of the
and other services cial development unit, LSI Design Center, leading enterprises in the field of telecom-
In addition to the activities that can be con- handle these activities. munications. The Group with its changed
sidered to be aimed at a certain market The world-wide success of the AXE 10 identity faces a new epoch.
sector, the Group has extended its range of system is partly due to the revolutionary This new Ericsson Group is symbolized
more general services. The Group is well principles applied in the design and hand- by a new visual Ericsson identity, the new
established in the field of planning and in- ling of its software. In the software field logo.
stallation of public networks, including the special projects are now in progress which
supply of network material. The range of are aimed at providing more efficient
services offered here has been supple- programming aids and software that is
mented to give the Group greater scope for simpler to handle.
installing entire networks, and to extend The investments made by the Group in
these activities to include private, military this field, as well as the increase in service
and industrial networks. Thus the Group resources provided by the software com-
provides equipment for railway signalling, panies, are essential for attaining the over-
for the mining industry, and for the oil in- all goal, since the cost of the software repre-
Ericsson Information Systems
- A New Company
LARS RAMQVIST
Division for the customers complete software pack-
MARTIN THOR£N ages, as well as consultative and service
Division for Information Systems Information Systems facilities in both EDP and technical fields,
Telefonaktiebolaget LM Ericsson
The first stage of the venture into informa- such as data communication. The Ericsson
tion systems for the private sector was initi- group has extensive know-how in the soft-
ated in the middle of 1980 with the setting ware field based on experience from its
up of a new division within the parent com- own large computer centre, and also from
pany, the division for Information Systems. development work on the computer-con-
The aim of the division was to be able to trolled telephone exchange system AXE
provide complete systems for data/text/ 10.
video, which are based on LM Ericsson's
extensive know-how in modern telecom- It was decided that collaboration with inde-
munication and computer technology. pendent software companies was desira-
ble in order to gain further experience in
The activities of the division cover three this field. At the end of 1980 LM Ericsson
fields, namely data transmission with therefore purchased a third of the shares in
modems and other network equipment, pri- AU-System Network AB, and on January
vate data networks for packet switching, 1st, 1981 a new company, Ericsson Pro-
and office automation comprising work sta- gramatic AB, was formed in collaboration
tions with word processing, document with Programator. The ownership details
handling, telex communication etc. are illustrated in fig. 5.
Since its inception the division has carried AU-System Network AB is a consultant
out development projects to meat specific company which has concentrated its ac-
commercial requirements. During the first tivities within the fields of data communica-
year of operation customer orders were tion and distributed data processing. The
already being received for both ERIPAX company is primarily marketing software
data networks and ERITEX office automa- products and systems in the Nordic coun-
tion equipment. Modems, which were pre- tries, but it can also undertake contracts
viously marketed by the parent company, outside Scandinavia, e.g. as a subcontrac-
have also been a well established product tor to LM Ericsson.
for a long time.
Programator is one of the foremost Swed-
Software is important ish companies for qualified and complete
It is often said that there is an international consultative services in the EDP field. The
software crisis. Development and mainte- company offers an all-embracing service,
nance of software is often a burden to from the preliminary studies to the follow-
Fig. 3 customers who have purchased office up and maintenance, and sells software
The whole world market tor the type of private sec- automation and information systems, and it for, for example, minicomputers, distrib-
tor products marketed by LM Ericsson
forms an increasingly large part of the total uted processing systems, display termi-
cost of data processing, fig. 4. The Erics- nals, data base systems and real time sys-
son group has therefore decided to offer tems.
Fig. 5
The ownership of the software companies that are
affiliated to LM Ericsson
154
In markets outside Sweden the new com- achieve the substantial growth of the pri-
pany, Ericsson Programatic, will offer con- vate sector activities planned for the Group.
sultant services similar to those provided In view of the integration of the telecom-
by Programator and AU-System Network munication and computer fields that was
AB in Sweden operating as a company taking place, the interest was concentrated
called E-P Data, which is owned jointly and on Datasaab, the largest Swedish manu-
equally by LM Ericsson and Programator. facturer of terminals and computers.
An American subsidiary, Ericsson
Programatic Inc., has also been formed, It was soon obvious that Datasaab's ex-
primarily for the purpose of marketing the perience of minicomputer systems and ter-
services of AU-System Network in the very minals was an excellent complement to LM
important US market, particularly in banks. Ericsson's know-how in the fields of tele-
communication, computer technology and
This investment in software companies has complex integrated systems.
several purposes. There is of course the
purely commercial interest, since the com- Extensive negotiations led to LM Ericsson
panies operate independently and have to acquiring 90.5% of the Datasaab shares
prove profitable in a rapidly expanding in- on April 1st, 1981. The remaining 9.5%
ternational market. However, it is also a were obtained by the Swedish Telecom-
means of increasing contact with the mar- munications Administration through its
ket with a view to obtaining better informa- subsidiary Teleinvest.
tion regarding the demand for hardware
and software as well as application trends. At the same time a survey was carried out
There are certain possibilities of collabora- to investigate the possibility of coordinating
tion with the software companies in tenders the activities of Datasaab and LM Ericsson
and purchasing. In such situations these in the private sector, both as regards mar-
companies can contribute system studies keting and production. Since the require-
and other consultative services in the initial ments of the private sector are somewhat
stages, while LM Ericsson provides the different from those of telephone ad-
products and systems. The companies can ministrations, which are LM Ericsson's tra-
also be considered as a programming ditional customers, it was soon clear that a
source, necessary when the current scar- private sector subsidiary ought to be
city of programmers is considered. formed.
Fig. 6
The Ericsson and Datasaab divisions forming
Ericsson Information Systems
155
for Business Systems, Bank Systems and grated system. This also provides further
Alfaskop, fig. 6. Legally the activities in opportunities for the marketing of service
question were to be based on Datasaab facilities.
and were to be operated as a subsidiary of
LM Ericsson. The company's products will successively
be developed into components in such an
It was also decided that the remaining divi- integrated information system, which it
sion within Datasaab, Interactive Data must be possible to structure in different
Systems, should be transferred to SRA ways to meet different customer require-
Communications AB, another subsidiary of ments. The customers must be able to
LM Ericsson. The division in question pro- purchase individual system components
duces air traffic control systems, simulators and extend the system when necessary,
and defence electronics, which all fall out- starting with an arbitrary unit. Advanced
side the planned scope of the new com- operation and maintenance functions will
pany, but which are well in line with the also form an important part of the inte-
activities of SRA. grated system.
Fig. 7
The functional structure of Ericsson Information
Systems
Fig. 8 Products
MD 110, a new stored program controlled PABX for
Certain of the products of Ericsson In-
voice and data. The system has a modular structure
and can be extended to 10 000 extensions formation Systems have already been
described in Ericsson Review, and
others will successively be presented in
subsequent issues. A brief list is given
here:
Communication systems
- MD 110, a digital, stored program con-
trolled PABX with facilities for
simultaneous data transmission, fig.
8.
- ASB 20,100 and 900, stored program
controlled PABXs1^4, DIAVOX 406
and 824, stored program controlled
office communication systems8
- ERIPAX, a data network for packet
switching
Fig. 9 Fig. 12 - ERIBUS, a local data network for
Series 16, a minicomputer system for offices, The terminal system ALFASKOP System 41 transmission at Mbit/s rates
developed by Datasaab - ERIMAIL, asystem for computer con-
trolled telex and teletex
- Modems, from 50 bit/s to 64 kbit/s
Business systems
- Series 16, an administrative minicom-
puter system for work positions with
display units, fig. 9
- System LXT for distributed data pro-
cessing in offices
- Bank systems with cashier terminals,
note dispensers, cash dispensers etc,
and a version of system LXT, fig. 10
- Terminal systems for the retail trade
Terminals
- ERITEX, an office support system
Fig.10 Fig. 13 with word processing document
The Datasaab bank system The digital special telephone set for MD 110 handling, information retrieval and
teletex communication
- ERITEX 10, a typewriter terminal for
word processing and teletex com-
munication, fig. 11
- ALFASKOP System 37, an editing ter-
minal for input of data to large compu-
ters
-ALFASKOP System 41, a terminal
with local data processing and stor-
age, fig. 12
- DIAVOX, standard telephone set 5 6
and special set7 8
- Special digital telephone set for MD
110, fig. 13
- Authorization terminal for credit
cards, fig. 14
Fig. 11
ERITEX 10, a typewriter terminal with word process- Fig. 14
ing and teletex communication Authorization terminal for credit cards
157
Fig. 15
The structure of an integrated information system
Fig. 16
A functional analysis of an integrated information
svstem
Fig.17 shown in fig. 17. The private ERIPAX net-
A hypothetical example of an integrated informa- work is used for global communications.
tion system
The local communications are handled by
MD 110, or by ERIBUS if integrated voice
communication is not required. ALFASKOP
systems, connected via a concentrator
unit, are used for communication with the
main computer. Local computers of type
Series 16 are used for extensive local pro-
cessing, and terminals are connected via
terminal buses, or via ERIBUS if a very high
communication capacity is required. Termi-
nals can be accessed via a special com-
munication computer if the required
amount of local processing is not too large.
Computers and terminals can also be con-
nected direct to ERIPAX via standardized
interfaces.
Kurt Katzeff
KURT KATZEFF
The digital telephone exchange system AXE 10 has been developed jointly by the Swedish Telecommunications Administration
Swedish Telecommunications Administration and LM Ericsson. The main part of the Headquarters
development was carried out by the jointly owned ELLEMTEL Development Company.
The system replaces both 500-line selector exchanges and crossbar exchanges, and it
was also clear that digital exchange sys-
is now the standard system of the Swedish Telecommunications Administration.
tems would have to be considered in the
A changeover to digital equipment in the transmission network is also taking place in near future. It was therefore decided to start
parallel with the installation of AXE 10. The AXE 10 equipment is manufactured for the closer collaboration on joint projects. In
Telecommunications Administration by its industrial division Teli and by LM Ericsson. April 1970 an agreement was made to set
In this article the author describes briefly the decisions and activities that led to the up a jointly owned development company
development and introduction of AXE 10 in Sweden and also the introduction process. with the main task of developing electronic
equipment for telecommunication. This
also meant a broadening of the long-stand-
UDC 621 395 34(485)
The forming of ELLEMTEL ing development cooperation. The com-
65.012 2 pany was designated ELLEMTEL Develop-
Collaboration between the Swedish Tele- ment Company1.
communications Administration and LM
Ericsson regarding development work has
existed for a long time in different forms. For Development of AXE
example, in 1956 joint development work The development of AXE started in the
started on electronic exchange systems. autumn of 1970 within ELLEMTEL with a
However, the two parties wished to try system survey, which was to form the basis
different solutions, and two systems were for the choice of a new local exchange
therefore developed. LM Ericsson's AKE system. Naturally the experience gained
12 was put in operation in the Stockholm from A 210, AKE and ARE was utilized.
suburb of Tumba in 1968, and the Ad- AKE and ARE are LM Ericsson's stored
ministration's A 210 was put in trial opera- program controlled telephone exchange
tion in another suburb, Storangen, in 1970. systems with code switches and crossbar
switches respectively.
The experience gained from the Tumba
and Storangen exchanges showed that the The first report, in July 1971, recommended
computer-controlled switching systems a reed switch system with central and
had great advantages, but that it was un- regional processors. The system was
profitable to run two projects in parallel. It designed so that both the group selector
Fig. 1
The first Swedish stored program controlled
telephone exchange, AKE 12, was put in operation
in 1968 at Tumba, a suburb of Stockholm
and the subscriber stage could be ex- A high-level computer language, PLEX,
changed for digital variants. The technol- was developed in order to simplify the
ogy available at the time justified an initial programming of the system. This language
version with reed switches. However, the is specially adapted for telephone ex-
system was to be optimized for digital change functions, and later became one of
operation. the foundation stones for CHILL, the lan-
guage recommended by CCITT in 1980.
One of the characteristics of the AXE de- The central processor, APZ 210, which was
sign is that the control functions are divided developed for AXE, was of course op-
up between regional and central proces- timized for PLEX.
sors and the software and hardware is
Fig. 2 divided into modular units. This division
Rack a nd shelves in the BYB construction practice, simplifies operation and maintenance, and In 1972 the Telecommunications Ad-
Magaz ines are placed on the shelves also the introduction of new functions. It ministration specified model stations for
also enables the system to be adapted and 3000, 8000 and 25 000 subscribers. These
developed further as new components and models were used to evaluate the cost,
ciruits become available. capacity and space requirements of the
AXE system. The Administration also pro-
As soon as the development work had vided the exchange and network in Soder-
been initiated, both the Telecommunica- talje, 35 km west of Stockholm, for a field
tions Administration and LM Ericsson trial.
started preparing requirement specifica-
tions for different types of exchanges,
beginning with large local exchanges. The The equipment at Sbdertalje, for 3000
basic characteristics and function prere- subscribers, was taken into service in
quisites were formulated in 1971 and were March 1977 and has performed according
used to evaluate the system designs to expectations. However, it differs in many
developed by ELLEMTEL. respects from the AXE 10 system which
during recent years has been widely in-
The new exchange system also required a stalled in the Swedish network, since the
new construction practice adapted for Administration decided in January 1977
automatic production, easy installation and that new local tandem and transit ex-
simple maintenance. The development of changes were to be equipped with digital
such a general construction practice for group selectors. It has also been decided to
electronic equipment, designated BYB 101, introduce digital subscriber stages and
was started in 1971 at ELLEMTEL. digital concentrators.
Fig. 3
The control room in the AXE 10 exchange at Sbder-
talje, completed in 1977
161
Strategy for modernizing the change line and year. However, the earn-
ings trend during the remainder of the
Swedish telephone network 1980s is such that the traffic volume per
In 1980, when AXE 10 was first introduced household cannot be expected to increase
in the Swedish telephone network, the net- materially.
work contained installed equipment for
nearly six million subscribers. Three million In the business sector and the public sector
of these lines were connected to the cross- the situation is different, since telecom-
bar system A 204,2.5 million to the 500-line munication plays an essential role in the
selector system AGF and 0.4 million to efforts to increase efficiency and produc-
rural exchanges with crossbar selectors. tivity. This also requires new facilities,which
Fig. 4 can easily be provided with modern digital
A magazine in the BYB construction practice, with a Sweden has 80 telephone sets per 100 in-
circuit board assembly for a digital switch extracted switching systems of the AXE 10 type.
habitants, which islhe second highest den- Since the oldest equipment in the Swedish
sity in the world. The density of subscribers' telephone network is to be found in the
main stations is the highest in the world. In cities, where the number of business sub-
spite of this, the annual growth is about scribers is largest, it is natural that the re-
110 000 subscribers. This figure is ex- placement of old equipment by AXE 10 is
pected to fall to about 75 000 during the carried out in these areas first.
second half of the 1980s. 60% of the
growth is in exchanges with less than 8000
It is the objective of the Swedish Telecom-
subscribers and 15% in exchanges with
munications Administration to be able to
less than 200 subscribers.
offer its customers the same telecom-
munication facilities regardless of geogra-
The traffic volume is approximately 0.07
phical position. Customer-tailored solu-
Fig 5. erlangs per subscriber and the number of
tions will therefore be used in regions
The Sodertalje exchange during the installation call metering pulses exceeds 3000 per ex-
where the telephone network will not be
digitalized in the near future, in order to
meet the business requirements for ad-
vanced telecommunication facilities also in
these areas. Such customer-tailoring may
consist of special terminals, auxiliary
equipment in exchanges and special
transmission equipment. The need for
such special measures is expected to be
greatest during the next five years, after
which it will successively decrease as the
digitalized part of the network increases.
restructured and simplified, and centrally show an acceptable financial result this
situated premises can be freed for other must be done at a cost per line that is less,
purposes. The transmission network will or no more than the present cost for cross-
also be simplified and easier to maintain. bar and 500-line selector equipment.
There will be greater possibilities of offering
digital transmission right up to the subscri- In Sweden the AXE 10 system will be used
ber terminal. for all types of exchanges, i.e. small termi-
nal exchanges, local exchanges, local tran-
New, digital PABXs are being installed in sit exchanges, national transit exchanges
parallel with the introduction of AXE 10. The and complex international exchanges. The
majority of such PABXs are installed in the terminal exchanges consist of concentra-
cities and are digitally connected to the tors, which in rural applications must be
AXE 10 group selector stage. This means able to handle internal traffic and alarm
that in a few years a large part of Sweden's traffic even if the connection to the main
business telecommunications will be digital exchange is broken. The concentrators can
from PABX to PABX. be extended from 128 to 2000 lines. The
maximum capacity for a unit with a central
processor is 65 000 subscribers at 0.07
Modernizing with AXE 10 erlangs, but with normal growth such a unit
Since the oldest 500-line selector ex- is already economically viable for an ex-
changes in Sweden are almost 60 years change with 1000-2000 subscribers in-
old, one aim of the modernization program itially. All exchanges have digital group
had to be to replace all such exchanges. selectors, to which PCM line systems can
According to the present plans this work be connected. The digital concentrators
will be completed by the end of the century. and PABXs are also connected via such
By the year 2020 it is probable that all line systems.
crossbar exchanges will also have been
replaced. However, it is likely that for vari- The rural areas of Sweden are very spar-
ous reasons, e.g. simpler maintenance, the sely populated, and the concentrators used
modernization will be speeded up and in these areas must therefore be excep-
more than 150000 lines will be replaced tionally reliable. The maintenance costs
each year. If growth is also taken into ac- will otherwise be far too high. It will also
count this means that the Administration take time to train staff for this type of opera-
Fig. 7
will install at least 250000 lines of AXE 10 tion, and therefore the concentrators can-
The Savedalen exchange in Gothenburg was taken
into service in 1980 per year for the next 40 years. In order to not be introduced on a large scale until after
1985.
The second alternative means that a When planning the Gothenburg network it
central AXE 10 exchange for 8000 numbers was discovered that no suitable premises
would be built and that 26 digital concentra- were available for the replacement of one of
tors for a total of 28 000 numbers would be the city's oldest and most central ex-
connected to the exchange. In the primary changes, Drottningtorget. One solution
network 82 km of 25-year old cable would would be to divide the 25 000 numbers of
be replaced by 36 km of modern cable for this exchange between 10-20 digital con-
PCM. centrators, which would then be connected
to two adjacent AXE 10 exchanges, Kall-
The advantages of alternative no. 2 are that torp and Kaserntorget. At the same time
it would cost less for the rebuilding and the cable network and conduit routes would
extension of premises, and that a centrally be restored in the same way as in
situated building could be used for the Ad- Eskilstuna and with corresponding profits.
ministration's sales activities. The cost of The introduction of digital concentrators
cable vaults, culverts, ducts and manholes will be later in Gothenburg than in Eskilstu-
would also be considerably lower, and the na, but before that a large number of digital
Fig. 8
Computer-controlled exchanges in the Gothenburg
area, with the year they were or are to be put into
operation. Framed names indicate AXE exchanges
City exchange
Suburban exchange
Automatic rural exchange
AKE 13, AXB 20 and 30
Fig. 9
An AXE exchange being assembled in the Teli facto-
ry at Nynashamn
PABXs will have been taken into service in to be converted to AXE 10 was made partly
the Gothenburg area, for example a separ- on the basis that the need for adaptive
ate PABX network for Volvo. design should be minimized. A system
study showed that 21 program blocks had
Planning, adaptive design, to be designed for the Swedish market. LM
Ericsson designed nine of these, the Ad-
operation and maintenance ministration ten and ELLEMTEL two.
In 1977 it was decided to replace 20 ex-
changes for 380000 subscribers between During the years 1977-79 the Telecom-
the middle of 1980 and the middle of 1982. munications Administration built up the re-
Of these LM Ericsson is to supply 11 ex- quired design resources, which were
changes for 240 000 subscribers and Teli, dimensioned for the adaptive design work
the Administration's Industrial Division, is to come and in order to be able to adminis-
to supply eight exchanges for 140 000 ter the blocks designed by the Administra-
subscribers. The scedule for the subse- tion.
quent two-ear period comprises approx-
imately 400 000 lines, with a comparatively LM Ericsson and the Telecommunications
larger proportion for Teli. In addition an in- Administration have agreed that the pro-
ternational transit exchange, which will also duction of programs for all AXE 10 ex-
handle satellite traffic, has been ordered changes in Sweden should be carried out
from LM Ericsson for the Hammarby ex- by the Administration. All exchanges will
change in Stockholm. have the same software in order to keep the
amount of work required for both the pro-
The size of the orders and the stringent duction and the maintenance of programs
time schedule meant that the Administra- within reasonable limits. In practice this
tion's central resources for project planning means that two program packages are
and dimensioning were not sufficient. maintained simultaneously. One of these is
These tasks had to be delegated to the used for new installations and the other is in
local telecommunication centres, which operation in previously installed ex-
necessitated an extensive training pro- changes. In order to achieve the goal of the
gram. Each conversion object was so large same software in all exchanges, the soft-
that it had to be coordinated by a project ware in the previously installed exchanges
group led by the local telecommunication is successively being replaced by the latest
centre, with the central technical units as version. In most cases a third program
Fig. 10
Computer-aided designing of printed board assem-
consultants. package is also being developed.
blies at ELLEMTEL
The above-mentioned decentralization of Each AXE 10 has its own, unique exchange
the project planning and dimensioning ac- data. In the case of an exchange with com-
tivities had been planned, but not at such plex traffic cases it may be necessary to
an early stage. It meant that at first there compile about 10000 parameters for input.
was a lack of instructions, which put the Instructions and training material had to be
knowledge and resources of the telecom- prepared very quickly in order to be able to
munication centres to the test. However, on carry out this work for the first 20 ex-
the whole the conversion projects are run- changes, with their stringent time
ning according to plan and the centres have schedules. The most laborious part of the
managed the tasks very well. work, the collection of data, was imme-
diately delegated to the telecommunication
The selection of the first twenty exchanges centres.
165
The use of AXE 10 was originally limited to possible by the very low fault rate of AXE 10
Stockholm and Gothenburg, but was and by the automatic aids for traffic ad-
quickly extended to another six of the 20 ministration and fault clearing that form part
telecommunication areas in Sweden. Ex- of the system. The stringent standardiza-
tensive course and training packages have tion of both hardware and software is
been prepared, so that the whole of the another contributory factor.
operating organization can become ac-
quainted with the AXE 10 system. Courses Successful introduction of a new telephone
for the training of technicians and repair- exchange system like AXE 10 also requires
men for AXE 10 were first started in the thorough training of the personnel in the
middle of 1979. The training exchange, in- field. The need for training has been so
stalled in the Administration's Traning great within the Administration that during
Centre by Teli in 1979, has been very use- the first years the introduction of AXE 10
ful. The courses have been supplemented had to be limited to certain telecommunica-
by practical training since the summer of tion areas. The operating staff have a very
1980, when the first AXE 10 exchanges heavy work load just now, since new types
were put in operation. of PABXs, telephone sets, teleprinters and
data services, and also the new facilities
At the beginning of 1978, when the Ad- teletex and telefax are being introduced
ministration ordered the first AXE 10 ex- simultaneously with AXE 10.
changes, priority was given to the work on
conversion methods, choice of products for AXE 10 is designed so that it can be con-
adaptive design, project planning instruc- nected to operation and maintenance
tions and dimensioning standards. How- centres, from which the field activities can
ever, during 1980 and 1981 the resources be administered. However, if such centres
for system design, requirement specifica- are to be efficient they must serve a number
tions for new facilities and adaption to local of exchanges within the area. This means
conditions have been increased considera- that in the near future such centres can only
bly. be of use in Stockholm and Gothenburg,
and centres for these areas are now being
Another aim when introducing AXE 10 was installed. Operation and maintenance
to reduce the operation and maintenance centres are also planned for the rest of the
staff in the exchanges. It is expected that for country, but they must also be able to han-
the first seven exchanges, with a total of dle PBXs and older exchange systems.
150 000 lines, the staff in the station and
MDF areas can be reduced from 56 to 36 Experience shows that a large number of
people. This reduction is of course made faults and disturbances must be expected
Fig. 11
The Telecommunications Training Centre at Kal-
mar, in south-east Sweden
166
during the hectic period when a new ex- and the manufacture of telephone sets
change system is being introduced. Ex- from DIALOG to DIAVOX 100
changes in the start up phase are par-
ticularly prone to disturbances. Both LM In 1975 extensive rationalization was car-
Ericsson and Teli have therefore set up ried out within Teli in order to create the
support groups, which can intervene in prerequisites for the manufacture of new
difficult and abnormal situations. Since products. The manufacture of AXE 10 is
such situations can also occur after the now one of the largest production branches
manufacturer has handed over respon- at Teli. The new technology means new
sibility to the Administration, for example production equipment and methods.
during program change-overs, staff from
the Administration will take part in these The series production of AXE 10 within Teli
central operational support activities. was prepared by a project group, formed in
These activities will be combined with fault March 1976 and containing representa-
clearing, introduction of corrections and tives from Teli's technical staff and the AXE
development of special operation and factory at Nynashamn. The group was
maintenance functions. responsible for the whole planning of a five-
year manufacturing and delivery program.
The group had to decide whether details
Changeover to manufacture and components should be bought or
of AXE 10 at Teli manufactured, and make decisions regard-
Teli, the Industrial Division of the Swedish ing product and production documentation,
Telecommunications Administration, has space requirements and the use of pre-
factories situated in several places mises, production equipment, investment
throughout Sweden. Its main products are frameworks, personnel and training plan-
exchanges, PABXs and telephone sets. ning, project and product calculations,
Practically all the crossbar equipment in the delegation of responsibility and time
Administration's network was supplied by schedules.
Teli. The decision to introduce AXE 10
meant that the demand for electromechani- The project also included the planning and
cal equipment would decrease very rapidly. installation of AXE 10 systems. The aim
Fig. 12
The AXE 10 exchange at Ulriksdal, Stockholm, deli- Teli had to change over its production from was to deliver exchanges that were ready
vered by Teli in 1980 crossbar technology to digital technology, to be put into operation.
that a large amount of the cabling can be telephone exchanges. The decision to
prefabricated. Each such exchange is also develop AXE 10 was taken in 1971-72, the
assembled and undergoes complete func- first orders were placed in 1977, the first
tional testing at the factory, and thus the exchanges were put in operation in 1980
amount of final testing required on site is and the last of the old exchanges will not
very small. The software and exchange have been replaced until the year 2020. A
data have been thoroughly tested before system with such a long life cycle has to be
delivery. The magazines are delivered on flexible, so that new functional require-
site fully equipped and tested. This method ments can be met and new technology in-
is particularly valuable as regards pro- troduced. With its modular structure, its
cessors and group selectors. combination of central and distributed con-
trol, and its facilities for modifying the soft-
The new production and testing methods ware, AXE 10 provides the necessary flex-
required extensive investment in produc- ibility. This ensures that the Swedish Tele-
tion and testing equipment. New produc- communications Administration, by intro-
tion premises were also needed to provide ducing the system in its network, is able to
an environment that met the stringent re- maintain its position as one of the world's
Fig.13 leading telecommunications administra-
quirements of the new technology.
The training exchange at the Telecommunications
Training Centre, Kalmar
tions.
The work on the AXE 10 system has also
necessitated additional training of the fac-
tory and installation personnel. Some of The material in this article has been ob-
this training has been carried out internally tained from previous articles and internal
within Teli, and the remainder has con- reports written by the Technical Director
sisted of courses arranged at the Ad- Torsten Larsson, engineer-in-chief Evert
ministration's Training Centre. Jarnbhnk, division heads Anders Sundblad
and Stig Johansson, section head Lars
Rydin and the head of Teli's AXE factory,
Conclusion Sten Zalle, and other people within the Ad-
Few products have such a long life as ministration.
References
1. Eriksen, E.J.: ELLEMTEL 10 Years
Old. Ericsson Rev. 57 (1980):2, pp.
71-72.
LSI Design Center
Organization
RIFA, which is a subsidiary of LM Ericsson,
designs and manufactores integrated cir-
cuits in bipolar technique. This technique
has previously been predominant and is
still the obvious choice when fast operation
or the ability to withstand high voltages is
essential.
KLAS-HAKAN EKLUND following up new techniques and for ma- The USA is predominant as regards techni-
AB RIFA nufacturing prototypes and small series. cal development in the semiconductor
GORAN NORRMAN
Department for Technology and Development Work on new techniques requires field, although Japan and certain Western
Telefonaktiebolaget LM Ericsson modern equipment, qualified staff and European countries contribute considera-
good contacts with the technical develop- bly. However, the American companies are
ment abroad superior when it comes to realizing new
a central unit for designing advanced cir- techniques in products and adapting their
cuits has been formed. This unit also has product engineering and marketing.
the overall responsibility within the Erics-
son Group for design methods, aids, LM Ericsson has increased its contacts
training and contact with suppliers with development centres on,the West
Fig. 2 Coast of the USA. The main purposes are
• local groups for designing integrated cir-
Plasma etching equipment.
Conventional etching of patterns, for example in an cuits have been formed within design de- to obtain
oxide layer, is done by immersing the wafers in a partments in the divisions and subsidi- - knowledge and possibly also manufac-
chemical bath. In such cases the etching procedure aries in the Ericsson Group. The main turing licences for the LSI activities
is isotropic, i.e. the etching is carried out to the part of the circuit design work will be car- - early and reliable information regarding
same extent in all directions under the photoresist.
By etching in plasma it is possible to make the ried out close to system projects, but with development trends, new techniques
etching process mainly anisotropic and directional, method training and computer program and new methods in the LSI field.
which is necessary in order to achieve the desired support from the central unit.
tolerances, which are of the order of Mm.
LSI laboratory
The main aim of the LSI laboratory is to
build up a MOS process for the manufac-
ture of prototypes and pilot series. LSI
Design Center must be able to design cir-
cuits for this process and quickly obtain
prototypes and experimental results. The
closeness to the process provides a more
dynamic environment for the designers,
and they can fully utilize all the possibilities
offered by the process in their designs.
Table 1 The chosen process exploits present tech- However, the interest in CMOS is growing
Characteristic data for the n-MOS process nology to the full, although a few semicon- noticeably. It is reflected in large invest-
ductor companies have used conductor ments in advanced CMOS technique by
widths down to 2-3/j.m. LM Ericsson have the large semiconductor companies. The
also acquired equipment which can be reasons for such investments are the pos-
used with conductor widths down to 3 jum. sibilities offered by CMOS of combining an-
alog and digital functions, and the ex-
Status tremely low power consumption, which
The building up and manning of the labora- becomes increasingly important with in-
tory is a gradual process which was started crease in the number of functions that have
in January 1981. Hitherto ten people, most- to be integrated on one and the same chip.
ly engineers, have been employed.
CMOS technique is used for such circuits
The equipment was installed and put into as operational amplifiers, which have a per-
operation in the spring of 1981. A standard formance similar to that of bipolar circuits.
circuit, a 4 kbit static memory, has been
produced in order to check the possibility of In the telecommunications field there is a
maintaining electrical parameter values great need for circuits where analog and
and obtaining a satisfactory yield. The first digital functions can be mixed. At the same
circuits were manufactured in the summer time the power consumption per gate must
of 1981, and the process was fully evalu- be low, since the CMOS technique permits
ated and established in the autumn. the manufacture of array circuits with 2000
Fig. 3
Diffusion line.
The wafers are fed into the oven automatically. The
process is controlled by a microprocessor, to the
left in the figure, which also regulates the tempera-
ture and gas flow in the oven to give a reproducible
growth of oxide
171
gates. Such a circuit can replace a large tom circuits intended for LM Ericsson
number of standard MSI circuits in TTL systems which are made in such small
technique. numbers that the semiconductor manufac-
turers will not undertake the design work, or
The demand for CMOS circuits for tele- which have such important system charac-
communication purposes is expected to in- teristics that they should not be revealed by
crease sharply, and a process line for such contracting out the design.
circuits will therefore be installed in the
laboratory in the spring of 1982. The pro- When manufacturing semiconductor cir-
Fig. 4 cuits, silicon wafers are treated in several
cess will use conductor widths of between
A plasma nitride reactor.
The last layer, on top of the aluminium conductor 2 and 3 /xm. process stages. In many of these stages
pattern, consists of a silicon nitride layer, which the areas on the wafer that are to be treated
protects the circuit better than an oxide layer which are defined by a mask. An MOS process
has been deposited in the conventional way at a low Design activities requires a total of between 7 and 16 masks,
temperature (vapox, silox). This increased protec-
tion is very important for circuits which are to be LSI Design Center designs primarily cus- depending on its complexity. The work of
encapsulated in plastic designing a semiconductor circuit includes
defining the appearance of all such masks.
Fig. 5
Decoding a layout.
A manually designed circuit section is decoded by
means of a computer-controlled graphic aid,
Calma. The screen shows what is being decoded on
the drawing board. All cells in a circuit are decoded
and combined in the Calma system so that a com-
plete layout is obtained. The information is then
stored for subsequent manufacture of masks or
drawings
173
CMOS, present-day technology gives for the generation of test programs are also
delays of 5-15 ns, but a reduction to 3 - 5 available.
ns can be obtained with processes that
give a conductor width of 3 /xm. A circuit simulator is used to study in detail
the function of a small group of transistors.
A CMOS array with 600 gates has been
designed by the LSI Design Center. It Layouts can often be prepared manually,
differs from other array circuits in that it also but computer-controlled aids are usually
contains a number of linear circuits, such employed in order to simplify the drawing
as operational amplifiers and comparators. work. Programs for automatic positioning
and connection of cells are also available.
System designers who have to learn circuit
design could most suitably start with array Control programs are available for verifying
circuits. The designer needs computer aids that all design rules have been observed.
(CAD) for logic simulation, for automatic
test program generation and for automatic Computer aids for the design work are ex-
connection, in order to be able to work effi- tremely important. The input of data and
ciently. LM Ericsson's resources in the the interpretation of the results must be
CAD field, together with its considerable done in a way that seems natural to the
process know-how, enable the company to designer. Large resources are rquired for
design its own CMOS array family in the the purchasing of aids and adaption or
size range above 2000 gates. development of programs.
Training
CAD The staff to be trained in LSI design are
There are several computer aids for the assigned to the LSI Design Center and
design of semiconductor circuits. given the task of designing a full custom
circuit. Three people can be trained simul-
Fig. 6 Logic simulators are used to verify that the
Detailed testing of a circuit.
taneously. They must first have taken a
A probe station is used for making measurements designed logic diagram meets the func- one-month course in the function of MOS
in a circuit. The probes are controlled by means of tional requirements. They can also be used transistors. This course is given by a con-
micro manipulators and can be positioned to an to check the ability of test programs to sultant company which specialises in train-
accuracy of 1 ^ m . Normal laboratory instruments detect all possible types of faults. Programs
are connected to the probes
ing staff for semiconductor companies.
Effects on systems
The use of custom design circuits can
reduce the number of printed board assem-
blies required for systems, since the cir-
cuits need very little space. Furthermore
the system speed can be increased be-
cause of shorter connections. Less power
is required to operate the equipment, and
fewer external connections are needed.
Greater reliability can therefore be expec-
ted.
Fig. 7
Test of a chip on a 4" wafer.
Faulty chips are coloured and rejected. Acceptable
chips are passed on to the encapsulation stage.
The figure shows the testing of a 4k static n-MOS
memory manufactured in the MOS laboratory. The
size of the chip is 3.3x4.1 mm.
References
1. Larsson, S. and Sternbeck, 0.: RIFA -
a Modem Component Manufacturer.
Ericsson Rev. 57(1980):1, pp. 2 - 7 .
2. Bengtsson, P. et al.: Choice of Monoli-
thic Technique. Ericsson Rev. 57
(1980):2, pp. 64-70.
3. Bjorklund, G. and Johansson, J.: Cos-
torn Design Circuits for Telecommuni-
cations. Ericsson Rev. 57(1980):4, pp.
166-172.
4. Bjorklund, G. et al.: The Development
of Custom Design Circuits. Ericsson
Rev. 58 (1981)-.1, pp. 9-17.
5. Jerndal, U. and Novak, E.: Manufac-
ture of Monolithic Circuits. Ericsson
Rev. 58(1981 ):3, pp. 50-55.
ASB 900 in the Finnish
Railway Network
Pekka Koski
PEKKA KOSKI
The Finnish State Railways has its own telephone network, which has successively Finnish Stale Railways, VR
been modernized with LM Ericsson's crossbar exchanges. In a further modernization
stage the exchange in Helsinki has been replaced by a code switch exchange, AKD
792, with a transit stage AKM 302, and certain network centres are now being that the telephone is the telecommunica-
equipped with the stored-program controlled PABX ASB 900. A total of 14 such PABXs tion facility which is most frequently used.
have been ordered, and six of these have already been put into operation. This
The rail traffic is supervised using point-to-
modernization stage will be completed in 1982.
point connections, which are separated
In this article the author describes the development of the telephone network of the from the rest of the network. The greater
Finnish State Railways, how the network is used and also the motive and procedure for part of the telephone network is automa-
the modernization with the introduction of the ASB 900. tized.
Fig. 2 Thus the operators in these exchanges the 1970s the telephone network included
The telephone network of the Finnish State Rail- could dial direct to the extensions in the about 40 automatic exchanges. The tem-
ways at the beginning of the 1970s
automatic exchanges, without going via the porary through-dialling system had by then
operator at the automatic exchange. been replaced by a permanent system,
Transit exchange which was better suited to the telephone
Group centre At the beginning of the 1960s the main requirements of the railways.
stage of the automatization of the VR net-
Terminal exchange
work was started, and by the beginning of At this stage the automatic part of the tele-
Manual exchange phone network had reached the extent
Trunk line shown in fig. 2. Its main features were that
Junction line - crossbar exchanges were used through-
out, with a few exceptions. The number of
extensions and the position of the ex-
change in the network decided the
choice between LM Ericsson's ARD 321,
ARD 326, ARD 331 and ARM 301.
- all transit traffic had to go via the VR
network. Only local calls were allowed on
the lines between the VR exchanges and
the public network.
- cali connections between the A and B
extensions were set up automatically
without A having to know the route. Seve-
ral alternative routes were arranged for
the telephone traffic in order to improve
the capacity and the reliability of the net-
work. The choice of route for the connec-
tion path was free.
- because of the oblong shape of the
telephone network a call could pass
through as many as six transit ex-
changes. A high signalling speed and
good transmission quality were therefore
necessary. MFC signalling was used in
the trunk network, with four-wire through-
connection in the exchanges.
- locally the exchanges operated as
PABXs.
During the years the VR telephone exten- also be possible to establish contact via
sions have to a great extent been moved radio and the telephone network. A radio
from function points along the railway lines communication system that operates in ac-
to braching stations and regional admini- cordance with this principle, so-called
strative centres. This is partly because on maintenance radio, has been developed
certain railway lines the railway signalling for VR. The system operates with selection
system has been supplemented by remote in both directions between radio and the
control (CTC). The selector traffic has also telephone network. Connection between
decreased on such routes. two radio telephones is either established
direct or connected via the telephone net-
On certain railway lines it was necessary to work, depending on the distance.
increase the capacity of the network when
CTC was introduced. It was then possible,
at a fairly low marginal cost, to obtain more Guidelines for the modernization
channels for the telephone traffic. There
were no difficulties in connecting the rail- of the VR telephone network
way line telephones to the nearest ex- The operational activities of the railways
change. In certain cases it has then been cover a large geographical area. The long
possible to discard the selector tele- distances mean that the activities require
phones. The exchanges are placed at a good telephone circuits and rapid connec-
distance of 40-50 kilometres along these tion. This in its turn means that the railway
railway lines. requires a whole network to itself.
The cost of maintaining the selector tele- The automatization of the network has
Fig. 3
phone batteries is high. For this reason it is made the telephone service considerably
The building and mast of a radio relay link station in desirable to reduce the number of selector more efficient. Further improvement can be
Ruukki telephones. However, in certain, quite com- achieved with the current modernization
mon cases the selector system offers the phase, the aims of which are to
only possibility of automatic selection. It is - introduce push-button dialling in a part of
therefore desirable to retain the possibility the telephone network
of connecting selector lines to the ex- - introduce abbreviated dialling, primarily
changes. for international calls. Abbreviated dial-
ling gives faster calling and can, in com-
Maintenance of railway lines with high bination with trunk traffic restriction, limit
traffic must be carried out without disturb- superfluous calls and thus reduce the
ing the traffic. This means that the work has telephone charges
to be divided up into carefully specified - make the signalling between exchanges
periods. In order to be able to use the pe- faster through the introduction of MFC
riods efficiently the work teams must be in signalling in parts of the network other
radio contact with the traffic staff. It must than the trunk network
Fig. 4
Connection of the radio relay link and cable to the
ASB 900 exchanges on the route Seinajoki-
Uleaborg
R&H Intermediate station and branching point of the
radio relay link
Cable branching point
- introduce other exchange functions this year been replaced by a code switch
which make telephony more efficient. exchange AKD 792/AKM 302, which in-
Many of the desired functions are stan- cludes a stored program controlled number
dard features of the more recent types of translator. The number translator is pri-
PABXs. marily used to register and process exten-
sion data during the setting-up stage.
Another aim within VR is to rationalize the
operation and maintenance of the tele- In Hyvinge a 500-line selector exchange of
phone network itself. For example, it should type AGD will be replaced by an exhange of
be possible to change extension numbers type ASB 900. ASB 900 exchanges have
without having to make alterations in the also been ordered for the 340 km long line
main distribution field. The possibilities Seinajoki-Uleaborg, which is now being
offered by stored program control as re- electrified. On this line the whole telecom-
gards centralized supervision of the net- munication system, including the selector
work and fault localization are gradually lines, will be replaced by ten ASB 900 ex-
being utilized. changes. The former open wire line is
being replaced by a radio relay link and a
cable, to which the new exchanges will be
connected, fig. 4.
Modernization stage 1981-82
The telephone network that was completed A total of 14 ASB 900 exchanges have been
at the beginning of the 1970s contained ordered. By May 1981 six had already been
exchanges with electromechanical compo- taken into service very successfully. The
nents. These exchanges made it expen- whole stage will be carried out by degrees
sive and difficult to achieve the aims during the years 1981-82. Fig. 6 shows
described in the previous section. how the ASB 900 exchanges will be con-
However, many of these aims can be nected to the electromechanical VR transit
achieved, at an acceptable cost, with the system.
aid of stored program control.
Fig. 5
An ASB 900 exchange
Fig. 6
The method ot connecting the ASB 900 exchanges
to the VR transit system containing crossbar
switches
179
- facilities for tone frequency key sending, The first figure specifies the exchange to
using push-button telephones, or deca- which the extension belongs. A group of
dic impulsing, using dial sets. Both types exchanges has a common area code,
of sets can be connected to one and the which is used for calls from other groups.
same exchange Good accessibility between the exchanges
- five extension categories, from fully open in a group is obtained by utilizing the facili-
extensions to those that are only allowed ties for alternative routing provided in ASB
calls to other extensions in the exchange 900.
- abbreviated dialling
- enquiry and transfer The junction lines are supervised, so that a
- add-on conference line which is found to be faulty when a call
- diversion to a common answering posi- attempt is made is automatically blocked to
tion in the case of no answer traffic and an alarm is given.
- direct in-dialling from the public network
- paging The exchanges can be tested and their ex-
- group calls tension data can be changed from termi-
- follow-me nals with typewriter keyboards. Such termi-
- automatic call back. nals are installed both in the exchange
rooms and in remote operation and mainte-
Fig. 7 From the point of view of the telephone nance centres. Circuits for remote control
An example of the numbering system tor different operator the functions of the new exchange of the ASB 900 exchanges are connected
trunk code areas type are versatile and help to speed up the over the telephone network.
handling of calls. This also applies for calls
which, when necessary, are connected
over the railway long-distance network by
operators. The importance of ASB 900 to VR
The introduction of the ASB 900 exchanges
Night service is available for calls both from in the VR telephone network constitutes a
the public network and over the VR junction new, decisive stage. The new exchanges
lines. offer the extensions better services and
facilities than previous exchanges. How-
The ASB 900 exchanges in the VR network ever, the maintenance characteristics are
are equipped for MFC signalling in order to of greater importance. The stored program
speed up connection over junction lines. control offers new possibilities as regards
Other signalling systems are also possible. maintenance. The staff can easily learn
A new signalling system can be introduced both the actual exchange technology and
in the transit system by entering the corres- the maintenance principles. The modular
ponding program blocks in the exchange structure of the hardware and, above all,
memories. the software in ASB 900 has contributed to
the very successful changeover to stored
The local extensions in the new ASB 900 program controlled operation by the Fin-
exchanges are numbered in groups, fig. 7. nish State Railways.
AGA-ERICON - a Marine Radar Beacon
Bo Morwing
are today not sufficient to ensure safety.
AGA-ERICON is a new type of radar beacon, developed by the Defence and Space
The largest ships require information at a
Systems Division of LM Ericsson, in close collaboration with the Swedish Administra- distance of over 10 nautical miles in order to
tion of Shipping and Navigation. When the beacon intercepts pulses from an X or S- be able to manoeuvre out of dangerous
band radar it gives a coded response at the frequency of the searching radar. New situations.
types of microwave semiconductors, together with extensive system studies, have
made it possible to develop a product that meets most of the demands which can be New systems for reducing the risk of acci-
made on a modern radar beacon. AGA-ERICON is now in series production and the dents at sea are being developed or plan-
marketing outside Sweden is handled by AGA Navigation Aids. ned. Among other things radar beacons,
In this article the author describes the demands made on radar beacons, the design also called racons, have attracted an in-
and structure of AGA-ERICON and different applications. Operational experience has creasing amount of interest during the last
been obtained from the first AGA-ERICON, which was installed in October 1980, and it decade, and the number of installations is
expected to grow rapidly. In parallel with
is most satisfactory.
further development of conventional racon
types, systems are being studied which
would present the racon response on the
ship's radar indicator without the normal
UDC 621.396.967: The development towards ever increasing radar picture being displayed. Strong land
627.715 tonnage in modern shipping has accentu- echoes and sea clutter can mask the re-
ated the need for advanced navigational sponse from present-day racons.
aids to improve safety at sea. More than
3000 ship collisions and groundings occur
each year in North European waters. Ap- Racons
proximately the same number of accidents Radar is an invaluable navigation aid for
occur along the coasts of the USA and are shipping. In difficult weather with reduced
estimated to cost shipping lines more than visibility the radar is often the only instru-
3 billion US$ per year. Supertankers load- ment that enables ships to move in busy
ed with oil or other chemicals represent waters. The range of a large ship's radar is
large sums and also constitute potential usually over 20 nautical miles, which
threats to marine ecology, fig. 1. Amoco means that action can be taken at such an
Cadiz, Torrey Canyon and Argo Merchant early stage that dangerous situations can
Fig. 1 are just a few names associated with en- be avoided.
Supertankers which are very difficult to manoeuvre vironmental catastrophes.
transport oil products and minerals in shipping However, radar has certain limitations. The
lanes along coasts where a wreckage could cause
an environmental catastrophe. In unfavourable
Conventional navigation aids, such as echoes from small buoys and navigation
weather conditions efficient aids are needed to en- lighthouses, buoys and navigation markers markers are often masked by noise or sea
sure safe navigation
181
BO MOWRING clutter, and in complicated passages the radar pulses from a ship it responds mo-
Defence and Space Systems Division mentarily with an extended pulse at the
display can be difficult to interpret, fig. 2.
Telefonaktiebolaget I_M Ericsson
Ever since radar was introduced there has frequency that is generated by the oscilla-
therefore been a need for equipment which tor at that moment. Since the oscillator con-
can improve the possibility of detecting tinuously varies its frequency over the
specific targets and also make identifica- whole of the radar band, all ships will at
tion easier. Passive reflectors, which give a some time have their radar frequency
larger target area, were available quite matched by the racon, and the racon
early on and they are still widely used. response will then be shown on the indica-
However reflectors only give a stronger tor, superposed on the normal radar
echo and do not make identification any display. The sweep rate of the oscillator
easier. and the bandwidth of the radar receiver are
the factors that determine how often and for
In order to meet both demands some type how long the racon response will be
of active equipment was required which displayed.
could respond at the frequency used by the
searching radar, the response being coded The whole frequency band is usually swept
or modulated, fig. 3. Many different solu- in about 2 minutes, or at a rate of 1.5 MHz/s,
tions were suggested and tested. This type which means that the racon response is
Fig. 2
In many situations it can be difficult to distinguish
of equipment was designated radar beacon displayed every second minute, for 5 to 10
and identify specific targets on the radar display. or racon. seconds. The low updating rate and the
The echo from a navigation buoy can easily be short display time necessitates incessant
confused with an echo from a small ship radar observation. In spite of this weakness
Radar frequencies
The main difficulty proved to be returning a most present-day racons are of the slow
response at the frequency of the searching sweep type.
radar. Different ship radars operate at
different frequencies in the frequency Fast sweep racon
bands allocated to shipping, fig. 4. In a fast sweep racon the oscillator frequen-
cy is swept over the frequency band at a
The receive bandwidth of the radar is in the high speed and frequency matching be-
order of 10 MHz or approximately 5-10% tween the racon and a ship's radar will oc-
of the allocated frequency band. Some cur several times during the radar sweep,
type of tunable oscillator is required in the fig. 6.
racon if it is to be able to serve all ships
within its range. Each time the racon oscillator sweeps over
the radar receive band a dot-shaped in-
Slow sweep racon dication is obtained on the indicator. Since
The first racon in practical use was the slow the racon frequency is not swept synchron-
sweep racon, fig. 5. An oscillator con- ously with the transmitted radar pulses,
nected to the common transmit receive an- and since the racon response is received
tenna is swept slowly over the frequency for up to 25 sweeps during an illumination
band in question. When the racon receives period, the overall effect of the response
Fig. 3
If the buoy is equipped with a racon its position and Fig. 6
Fig. 5
identity can be determined unambiguously The principle of the fast sweep racon
The principle of the slow sweep racon
Racon oscillator
Racon oscillator
frequency
frequency
Fig. 4
The frequency bands allocated to civil marine radar
182
Fig. 7
The drawing to the left shows a typical antenna
diagram, and the picture to the right shows the
effect of side lobe activated racon response on the
ship's radar display
Fig. 8
A passenger ferry with radar antennas tor the X and
S bands. The S-band antenna is at the top
In many situations the radar is the only tremely dangerous. From the point of view
instrument that enables the ship to navig- of safety it is therefore extremely important
ate. A radar fault can mean that further that future racon systems can serve all
movement is made impossible or ex- ships, regardless of the type of radar car-
ried or in operation. Today there are only a
few S-band racons in operation.
Functional description
The block diagram in fig. 9 gives a general
picture of the signal flow between the
various function blocks in AGA-ERICON.
Fig. 11
Frequency regeneration, right.
During the frequency regeneration the racon
oscillator frequency is adjusted in a closed loop to
match the frequency of the received radar pulse.
The building-up time is approximately 0.3 ,is
Fig. 14
The normal coverage of the basic version of AGA-
ERICON extends to the radar horizon (left). During
the time a ship passes close by, the sensitivity of
the racon receiver is reduced in order to avoid side
lobe activation. This means a temporary reduction
of the range (right)
Fig. 15
A n AGA-ERICON w i t h a s i d e lobe m e m o r y s u p -
185
presses s i d e lobe r e s p o n s e s t o n e a r b y s h i p s a n d at
the s a m e t i m e p r o v i d e s c o v e r a g e t o t h e radar
horizon
sitivity in order to avoid triggering by side when a ship passes close by. The racon
lobes. Nearby ships give high levels in the can therefore be programmed for a "non-
racon receiver. When a ship has come so restrictive operational mode" during 3 or 6
close to the racon that its pulses exceed the seconds every minute. This ensures a
upper threshold, TRLH, there is a risk of basic availability for all ships in the normal
side lobe triggering, fig. 14. The output sig- coverage area of the racon, but nearby
nal from the threshold circuit is integrated ships can then suffer side lobe interfe-
and drives a voltage-controlled attenuator rence, fig. 16.
in the receiver input circuits. The attenua-
tion is increased until no pulses above the
Availability
upper threshold are detected. The reduc-
One of the most essential characteristics of
tion of the receiver sensitivity means that
a racon is its availability, i.e. how often it can
the coverage of the racon is reduced tem-
be seen and for what length of time. The
porarily. The range is reduced to approx-
way AGA-ERICON operates, establishing
imately 20 times the distance to the nearest
the frequency of the received radar pulse
ship. When the nearby ship has passed,
and responding at the same frequency,
the sensitivity is restored to normal level
means that a racon response can be given
after a certain period of time.
for each antenna rotation. Since each re-
ceived radar pulse is treated individually,
AGA-ERICON can be equipped with a spe-
AGA-ERICON can deal simultaneously
cial side lobe memory if the operational
with what is in practice an unlimited number
requirements demand maximum range
of ships.
even when ships are passing close by.
Ships in the range of the racon are given an
The range is determined by how high the
identity which is based on the frequency of
racon and radar antenna are mounted, and
Fig. 17 the received pulses. The analog frequency
the output power of the radar. Fig. 17 shows
Calculated r a n g e s a s a f u n c t i o n of t h e height at value at the discriminator output is A/D con-
w h i c h t h e r a c o n is m o u n t e d the range of AGA-ERICON as a function of
verted to 8 bits and if the received pulse
Pulse power Antenna the height at which it is installed, for four
exceeds the upper threshold TRLH the
(kW) (m) different types of ship radar.
A: Small X-band radar 3 5 digital frequency value is stored in a special
B: Medium X-band radar 25 20
C: Large X-band radar 50 40 frequency memory. When pulses are
D: Large S-band radar 60 40 received that exceed only the lower thresh- Voltage supply
old, TRLL, the memory is read. If the fre- Many isolated lighthouses and most light
quency is found in the memory the re- buoys are today powered by batteries or
sponse is blocked. The frequency memory chargeable accumulators with a limited
is erased and updated twice every minute. capacity. The cost of changing batteries or
accumulators is high, which means that the
Operation electrical apparatus installed in such units
AGA-ERICON can be programmed for must have low power consumption.
different operational modes, which meet
different operational requirements. The All versions of AGA-ERICON require a pri-
racon is passive for at least nine seconds mary input voltage in the range 9-35 volts.
during each 30-second interval in order to The mean power consumption is depen-
ensure that the racon response shall not dent on type, programming and traffic in-
hide other echoes of interest. The passive tensity. Fig. 18 shows the calculated mean
period can be increased to 24 seconds in power consumption for the different ver-
steps of 3 seconds. During the active peri- sions as a function of the number of ships
od the racon responds, with suppression of within range of the racon. The calculations
side lobe responses. The adaptive sen- are based on a racon programmed to res-
sitivity regulation means that distant ships pond for 15 seconds during each 30-se-
Fig.18 can temporarily lose contact with the racon cond interval.
Calculated mean power consumption for the
different versions of AGA-ERICON as a function of
the number of ships within range
Fig. 16
The 6 0 - s e c o n d o p e r a t i n g c y c l e of t h e r a c o n c a n be
p r o g r a m m e d f o r different o p e r a t i o n a l m o d e s w i t h
varying intervals
SLS Side lobe suppression
NR Non-restrictive
AGA-ERiCON - The subunits are mounted in magazine and
construction and technology are connected together by means of cab-
ling at the rear. Semi-rigid coaxial cables
AGA-ERICON has a modular structure. are used for RF connections to the antenna
Five subunits can be combined to give four system and between the microwave cas-
Fig.19
AGA-ERICON equipped with the S-band subunit
different versions: settes. The magazine is mounted under-
and side lobe memory UKT 10101 X-band racon with adaptive neath a sturdy flange made of anodized
sensitivity regulation aluminium, with feed-through connectors
Fig. 20 UKT 10102 X + S-band racon with adaptive
Small-signal amplifier with two GaAs-FET transis-
for the power supply cable and coaxial ca-
tors
sensitivity regulation bles to the antenna system. The magazine
UKT 10103 X-band racon with side lobe is protected by a strong container made of
Fig. 21 memory anodized aluminium. It is screwed on to the
An X-band cassette with integrated microwave UKT 10104 X + S-band racon with side
modules
flange and the joint is sealed, fig. 19.
lobe memory
The flange also contains a dessication cap-
A basic version can quite easily be equip- sule with colour indication. The antennas
ped with additional facilities on site at any are mounted on top of the flange and are
time. Subunits can be replaced or added covered by a radome made of structured
without any readjustments of the other cellular plastic.
subunits being necessary.
Technology
The quality standards applied for the devel-
opment and manufacture of AGA-ERICON
are those used by the division for military
electronic equipment. A main customer re-
quirement for this type of equipment is high
reliability, since it often has to be installed in
isolated and inaccessible places, where
replacements and repairs would be costly.
The MTBF for the most extensive version is
calculated to be 25 000 hours.
Ragnar Almquist
tems. To ensure this, it is important that the
LM Ericsson have developed a system for cooling electronic telephone exchanges. reliability of surrounding equipment, such
It differs from conventional systems in that water is used instead of air to remove the as the power supply system and the cooling
dissipated heat from the exchange premises. In particular this makes it possible to system, should be on a par with the tele-
store the coolant and so ensure operation during a mains failure. phony system.
The author deals with the general requirements which must be satisfied when cooling
electronic telephone exchanges and describes the function of the system and its units. Coolant reserve
The article shows how these requirements are met. Finally the advantages of the The cooling system should function even
system are listed. when the switching equipment is powered
from the exchange battery because of a
mains failure.
UDC 621 395.34: Electronic telephone exchanges take up far
621.3-71 Simple extension
less space than electromechanical sys-
697 97
tems. Power consumption is not reduced It can be difficult to forecast the rate at
proportionally and the amount of heat radi- which a telephone exchange will be ex-
ated per unit area will be higher, which tended and what its final capacity will be. It
means that the cooling system is of in- may not be expedient to install a cooling
creased importance for the functioning of system for the planned final capacity right
the telephony system. If cooling is interrup- from the initial stage. The cooling system
ted, the temperature in the exchange room should therefore be modular so that it can
rises. If the temperature exceeds the per- be extended at the same rate as the ex-
mitted value, there is a risk of disturbances change.
in operation and should the temperature
continue to increase, components may be Minimum of maintenance
damaged. It is possible to concentrate the operation
and maintenance activity for SPC ex-
A cooling system for electronic telephone changes to a small number of centres and
exchanges should meet the following re- leave the exchanges unmanned. Mainte-
quirements: nance of the cooling system, which should
not require special training, should there-
High reliability fore be restricted to limited service at regu-
High reliability is sought in electronic sys- lar intervals.
Fig. 1
All cooling of the electronic equipment takes place
by means of self-convection (without fans for
forced air circulation). This method gives effective
cooling and a quiet and draught-free environment.
Red arrows: Warm air
Blue arrows: Cold air
189
Functional description
LM Ericsson's electronic telephone sys-
tems have components mounted on prin-
ted board assemblies and these are
grouped in magazines. The heat which the
components dissipate must be removed.
The packaging structure is designed for pa-
rallel cooling. This means that air enters
each magazine from the front, takes up the
heat while passing through it and rises by
convection through a duct at the back, fig. 1.
tion. The chance of a leak occuring is very - a moisture-sensitive strip has been
slight because of the low pressure, nor- placed along the water tubes in the ex-
mally about 0.3 kg/cm2, and the minimal change room. Moisture alters the resis-
temperature variations. The probability of a tance between two conductors enclosed
fracture in a tube or cooling coil can be in the strip, and this causes an alarm. The
disregarded. The parts of the system re- LM Ericsson cooling system can also be
quiring most attention are the junction supplemented with equipment which
points. automatically turns off the water supply
to a faulty coolant circuit.
The design incorporates the following
safety features: Fresh-air unit controls the humidity
- the number of junction points has been Fresh-air ventilation is needed in the ex-
reduced to a minimum change room to provide a good working
- only tried and tested junction technology environment. This is supplied by means of
has been used a separate unit. The unit adjusts the tem-
- the cooling coils and junction points are perature of the incoming air to 25°C and the
located between the rack suites and not relative humidity is kept at 50%. Overpres-
over the switching equipment sure in the exchange room prevents dust
and heat leaking in.
Simple installation
When developing the system emphasis
has been placed on simple installation and
small space requirements.
standard cable chutes. Only 50 cm free the cooling unit, the coolant loop has been
ceiling height is required above the ex- placed in the tank, fig. 10. The water tem-
change equipment, and the ceiling design perature in the tank is reduced to almost
is of no importance. 0°C. The circulation of the cold water
through the mixing valve, pump and cool-
The cooling unit, the water tanks and pump ing coils takes place as described pre-
units should be located in a separate cool- viously.
ing equipment room. The water flows be-
tween this room and the exchange room in Heat recycling
flexible plastic tubes placed in normal cable By the use of simple additional equipment
ducts. the heat dissipated from the telephone ex-
change can be recycled and used to heat
All the units in the equipment room are adjacent premises. In this way heating
designed to be located out-of-doors, under costs for the building can be considerably
a screen roof or in a separate container. reduced. For example in a Scandinavian-
type climate the amount of the heat dissi-
All units have been tested in the factory, so pated from a 10,000 line electronic ex-
the installation test is confined to a test change can be used to heat about 600 m2
pressurization of the system and some of office space.
functional checks.
The LM Ericsson cooling system
System variants compared with air conditioning
System variant for temperate climates
systems
In localities where the average daily tem- Greater reliability
perature during 10 months of the year is To secure acceptable reliability values with
less than 20°C, one or some of the cooling a conventional air conditioning (A/C) sys-
units can be replaced by a heat exchanger tem, the system should be duplicated and,
in which the water is cooled by the outdoor in the event of a mains failure, it must be
air, fig. 9. This method saves energy. The supplied from the reserve power unit, for
cooling unit will be in continual use only which there should be redundancy. Fig. 11
during the warmest days of the year and for shows a conventional A/C system and its
the rest of the time will be connected inter- reliability block diagram. As has previously
mittently to keep the tank water tempera- been mentioned in connection with fig. 4,
ture low. the LM Ericsson cooling system offers con-
siderably greater reliability even without an
Simplified system for small plants emergency power plant.
A simplified variant has been developed for
small plants. The cooling unit, pump unit Better environment
and water tank have been combined to both for staff and equipment
form a single unit. The cooling circuits are Water has a higher heat-absorption capaci-
unchanged. Instead of cooling the water in ty than air. To achieve the same cooling
Fig. 10
For small exchanges the cooling unit, pump unit
and water tank are combined into a single unit. It is
designed for housing in a container together with
the exchange
194
Fig. 11
Conventional cooling system.
a. Functional block diagram
b. Reliability block diagram. The dashed blocks
show the duplicated system
c. Table of the number of failures per year
Reliability calculations show a failure frequency as
in the table. The number of failures only refers to
system failures in the cooling system of such a
duration that there is a risk of operational distur-
bances in the exchange equipment
Table c
Number of failures per year
Reliable Unreliable
mams voltage mains voltage
with without with without
emergency emergency emergency emergency
power power power power
Single
system 1.2 1.7 1.4 16
Duplicated
system 0,006 0,24 0.08 15
195
Fig. 1
Higher-order multiplexors in the digital network
197
HANS-HENRIK HAMACHER
STIG KARLSSON
Division for Public Telecommunications
Telefonaktiebolaget LM Ericsson
Fig. 2 Fig. 3
ZAK 480/1920. The wide ventilation slots between ZAK 30/480 fully equipped for 16 tributary bit flows
the printed board assemblies give good cooling of 2 Mbit/s
ZAK 30/480
The comparison in fig. 4 shows that direct
multiplexing between the 2 Mbit/s and 34
Mbit/s interfaces, with no facilities for
through-connection at the 8 Mbit/s level,
reduces the required amount of equipment
from two and a half shelves to one
magazine, and the number of units or
printed board assemblies from 55 to 20.
This reduction certainly justifies the use of
the ZAK 30/480 variant from the points of
view of space, power and economy.
Fig. 6
The frame structure for ZAK 30/480
Frame alignment word 1111010000
Alarm to the far end bit 11
For national use bit 12
Spare bits bits 13-16
Frame length 1536 bits
Maximum justification
rate per tributary 22 375 bit/s
In ZAK 30/480 a total of 16 tributary bit flows speed units. The 34 Mbit/s interface unit
at 2 Mbit/s, each corresponding to 30 which has previously been developed for
telephone channels, are multiplexed to ZAK 120/480 is also used in both ZAK 30/
form a joint 34 Mbit/s bit flow, correspond- 480 and ZAK 480/1920.
ing to 480 telephone channels. Fig. 5
shows a block diagram of the equipment.
ZAK 480/1920
The frame structure has been chosen so The digital multiplexor ZAK 480/1920 com-
that a high pulse insertion capacity is ob- bines four 34 Mbit/s tributaries to one 140
tained, fig. 6. This makes it possible to keep Mbit/s bit flow. Its function is illustrated in
the buffers for the tributaries small and the the block diagram in fig. 8.
equipment can be made very compact. At
Fig. 7 the same time the signals have less jitter The incoming tributary signals are received
The limit for acceptable jitter as a function of fre- than they would if two second and third- in the interface units. The signal elements
quency. The CCITT requirement (red curve) is ad-
ded for comparison purposes
order standard multiplexors were used, are converted from the HDB3 line code to
connected in tandem. The limit for accepta- binary code and are stored in the buffer
ble jitter in the tributaries is therefore higher stores. These stores are then read out one
than the limit recommended by CCITT, fig. after another by the common logic circuits,
7. This means that connections can be built at a slightly higher speed than that required
up with an unlimited number of through- by the transmission capacity. Breaks in the
connections for 2 Mbit/s. reading are made under control of the
pulse justification logic and thus the butter
Fig. 5 TTL technology is used throughout, with stores are never emptied. In the common
Block diagram of ZAK 30/480. The printed board low-power Shottky circuits for the tributary circuits check bits are added for frame
assemblies are outlined in broken lines units and with Shottky circuits for the high- alignment, alarm and pulse justification,
199
Fig. 9 and the resultant signal is fed to the CMI The power density and chip temperature
The CMI code for 140 Mbit/s transmission recom- unit, where code conversion and level can be reduced by reducing the number of
mended by CCITT gates and flip-flops on each chip, but this
adaption to the line code is carried out. The
CMI encoding for 140 Mbit/s transmission means an undesirable increase in the num-
recommended by CCITT is illustrated in fig. ber of chips. A detailed study of possible
9. structures gave a solution that is optimized
from the point ov view of reliability. Fig. 10
The receiver works in a corresponding way. shows a printed board assembly equipped
The incoming signal elements are con- mainly with ECL circuits.
verted from the line code to binary code,
after which frame alignment and analysis of The highest transmission speed within the
alarm and pulse justification information is magazine is 34 Mbit/s for the tributaries.
carried out. The inserted extra bits are The corresponding connections between
removed and the reconstructed interleaved the printed board assemblies consist of
signal is divided up and stored in the buffer balanced wire pairs.
stores for the different tributaries. The read-
out rate from these stores is slowly regu-
lated so that they always contain the same The control information is processed in TTL
Fig.10
amount. This regulation method means circuits, which contain low-power Shottky
A control unit for ZAK 480/1920 equipped with ECL
components. Multi-layer printed boards have been that the high-frequencyjitter is minimized in elements. These circuits have a high func-
used in order to obtain impedance-matched con- the signal that is passed on. The conver- tion capacity and low power requirement
nections between the components per chip, but they cannot operate at speeds
sion to line code for each tributary takes
place in the 34 Mbit/s interface units. above 10 Mbit/s. The time difference that
occurs is bridged by delaying the tributaries
Emitter-coupled logic circuits, ECL, are in a number of buffer flip-flops, so that deci-
used in order to obtain sufficint reliability for sions from the slower decision circuits can
the high bit rates. The ECL circuits are fast catch up. In this way the best features of the
and have excellent transmission charac- two circuit families have been combined
Fig. 8
Block diagram for ZAK 480/1920. The printed board teristics at high speeds. However, one and the number of power-demanding ECL
assemblies are outlined in broken lines problem is that they require high power. circuits has been limited.
Technical data
ZAK ZAK
30/480 480/1920
Nominal bit
rate kbit/s 34 368 139 264
Limits x10- 6 ±20 ±15
Bit rate tor
tributaries kbiVs 2 048 34 368
Number of
tributaries
max. 16 4
Multiplexing Cyclic bit interleaving with
method positive pulse justification
Frame
structure See fig. 6 CCITT G.751
Summary
Frame The introduction of ZAK 480/1920 com-
alignment pletes the range of higher-order digital
loss and
CCITT G.751
multiplexors up to 140 Mbit/s. ZAK 30/480
recovery
Jitter G.703, G.742, G.751 is a valuable addition in those cases where
multiplexing direct from 2 to 34 Mbit/s is
Electrical
interfaces CCITT G 703 possible. Fig. 11 shows an example of a M5/
Signalling BYB bay fully equipped for digital multiplex-
channel bit 12 14 ing of 64 2 Mbit/s tributaries to one 140
type E&M E&M
Mbit/s flow, using the two multiplexors
bits 15 and 16
type TTL described here.
External
timing kHz 8 592 34 816
Level dBu 0 ECL
Limits dB + 1,-3
Alarm CCITT G.751 supplementec
for bit error supervision
(>10"3)
Power supply
from battery W 90 120
Battery Fig. 11
voltage V -30 to -72 Bay equipped with four multiplexors ZAK 30/480
Mains rectifier Hz 45 to 65 and one ZAK 480/1920 for the multiplexing of 64
(optionally V AC 110, 127 or 220 tributaries at 2 Mbit/s to form one 140 Mbit/s bit flow
Limits % + 10 t o - 1 0
Magazine
dimensions
Height x width
x depth mm 244x488x220
Weight
approx. kg 14 13
References
1. Karlsson, S. and Widl, W.: Digital Mul-
tiplex Equipment for 8 and 34 Mbit/s
Line Systems. Ericsson Rev. 55
(1978)2, pp. 7 6 - 8 3 .
2. Hallberg, P.-A. and Viklund, B.:
Construction Practice BYB for Trans-
mission Equipments. Ericsson Rev.
57(1980):4, pp. 1 2 4 - 1 2 8 .
3. Alexandersson, R. and Rdrstrdm,
H.O.: New Packaging Structure for
Electronic Switching Equipment.
Ericsson Rev. 53 (1976):2, pp. 1 0 0 -
107.
4. Hamacher, H.-H. and Pettersson, G.:
First-Order PCM Multiplex in the BYB
Construction Practice. Ericsson Rev.
57(1980):4, pp. 1 2 9 - 1 3 7 .
TELEFONAKTIEBOLAGET LM ERICSSON