Documente Academic
Documente Profesional
Documente Cultură
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
Digitally signed by
EPC Contractor: SOUMYAJIT
MUKHERJEE
LARSEN & TOUBRO LIMITED DN: cn=SOUMYAJIT
MUKHERJEE, c=IN,
o=NTPC,
Architect Engineer: ou=KHARGONE TF,
email=soumyajitmuk
L&T – SARGENT & LUNDY LIMITED
harjee@ntpc.co.in
Reason: cat-IV
Date: 2017.12.27
Vendor: 10:33:14 +05'30'
QSGM:
Digitally signed
by Debabrata
STAMP: FOR INFORMATION Kundu L&T-S&L Date Name
Date: 2017.12.11
11:27:00 +05'30' Checked 11.12.2017 JB
REVISION STATUS
Rev Prepared Reviewed Approved
No. Name Date Name Date Name Date
0 ---- ----- PKS 06.10.2017 RP 06.10.2017
1 ---- ----- PKS 06.11.2017 RP 06.11.2017
2 ---- ----- PKS 11.12.2017 RP 11.12.2017
Digitally signed by P.Kandasamy Digitally signed by RAJARSHI
DN: cn=P.Kandasamy, o=L&T-MHPS Boilers PAUL
Pvt. Ltd, ou=Engineering, Date: 2017.12.11 10:13:30
email=p.kandasamy@lntmhps.com, c=IN
Date: 2017.12.11 10:09:12 +05'30'
+05'30'
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
O&M MANUAL FOR Doc. No.: 9578-001-102-PVM-W-074
BOILER CIRCULATION PUMP (BCP) Rev. No.: 02
Larsen & Toubro Ltd. Date: 11.12.2017
Rev
Details / Description Date
No.
00 First submission 06/10/2017
Page 2 of 245
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
O&M MANUAL FOR Doc. No.: 9578-001-102-PVM-W-074
BOILER CIRCULATION PUMP (BCP) Rev. No.: 02
Larsen & Toubro Ltd. Date: 11.12.2017
INDEX
Page 3 of 245
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
O&M MANUAL FOR Doc. No.: 9578-001-102-PVM-W-074
BOILER CIRCULATION PUMP (BCP) Rev. No.: 02
Larsen & Toubro Ltd. Date: 11.12.2017
Page 4 of 245
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
O&M MANUAL FOR Doc. No.: 9578-001-102-PVM-W-074
BOILER CIRCULATION PUMP (BCP) Rev. No.: 02
Larsen & Toubro Ltd. Date: 11.12.2017
SECTION – A
O&M MANUAL
Page 5 of 245
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
G3C0002606 - 1 / 58 2
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Rev
Details / Description Date
No.
0 FIRST ISSUE 5/8/2016
1 REVISED 9/9/2016
2 REVISED 18/8/2016
G3C0002606 - 2 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
G3C0002606 - 3 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Contents
Page
GENERAL 6
SAFTY PRECAUTIONS 7
1. Introduction 8
1.1 Pumping Set 8
1.2 Pump 8
1.3 Motor 8
1.4 Motor Cooler 9
1.5 Purge Cooler 9
1.6 Secondary Cooling Water 10
1.7 Life Time of Major Part (for recommendation) 11
G3C0002606 - 4 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Page
7. Supervision of Operation 36
7.1 Supervision during operation 36
7.2 Inspection Sheet 1. 38
G3C0002606 - 5 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
General
●The Torishima boiler recirculation pumpset forms an integral part of the system in which
it is installed.
The following instructions should therefore be read in conjunction with the operation and
maintenance manual for the system.
●In order to ensure trouble-free operation of the pumpset, it shall be carefully installed and
properly maintained according to the relevant manuals and instructions.
●The pumpset must not be operated beyond the limit values for the medium handled, flow, speed,
pressure, temperature and motor rating specified in the technical documentation.
Make sure that operation is in accordance with the instructions in this manual and other contract
documents.
●Modifications or alterations of the equipment supplied shall not be made without prior permission
from the manufacturer. Original spare parts and accessories authorized by the manufacturer ensure
safety. The use of third party parts invalidates any liability of the manufacturer for the damage
caused.
●During the validity period of guarantee by Torishima, NO dismantling of the pump or its
individual components shall be carried out without obtaining Torishima’s consent in this respect.
●The pump name plate indicates pump type, main operating data, production No. and unit No.
Please quote this information in all queries, repeat orders and when ordering spare parts.
G3C0002606 - 6 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
SAFETY PRECAUTIONS
This manual contains fundamental information and instructions that must be complied with during
operation of the pumpset.
Non-compliance with the instructions can cause injury of operator, failure of unit functioning and
damage to the pumpset. Therefore, this manual must be read and understood by operators
prior to commissioning and operation.
This manual must always be kept close to the location of operation for easy access and
reference.
SYMBOL DESCRIPTION
Informational notes
Operator qualification
Never allow any person other than operators qualified to operate the pumpset to engage in the
operation of pump.
G3C0002606 - 7 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
1. Introduction
1.1 Pumping Set
1.2 Pump
- Type HLAV250-630/1K
- Fluid pumped Boiler water
- Operating temperature 303.6 deg C
- Capacity 830 m3/h
- Total head 120 m
- NPSHr 5.5 m
- Minimum flow 90 m3/h
- Nominal size
- Suction nozzle OD508 mm X ID382.9 mm
- Discharge nozzle OD406.4mm X ID306.3 mm
1.3 Motor
- Type HLV55/4FQ45-335
- Nominal rating 450 kW
- Nominal speed 1460 rpm
- Frequency 50 Hz
- Voltage 3300 V
- Nominal current 118.2 A
- Starting current 709 A
- Insulation of motor winding Cu-VPE
- Motor trip temp. 66 deg C (at upper motor cavity)
- Motor alarm temp. 63 deg C (at upper motor cavity)
G3C0002606 - 8 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
G3C0002606 - 9 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
The plant operator is responsible for the provision and monitoring of the secondary cooling water
supply in respect of temperature, quality and rate of flow.
- Heat Barrier
- cooling water quantity required 2.7 m3/h
- Inlet temperature 37.6 degC
- cooling water pressure loss 5 or less m
- emergency cooling water required 1.9 m3/h
- Motor Cooler
- inlet temperature 37.6 degC
- quantity of heat to be eliminated 189000 kJ/h
- cooling water quantity required 11.5 m3/h
- cooling water pressure loss 4 or less m
- Purge Cooler
- inlet temperature 37.6 degC
- quantity of heat to be eliminated 311110 kJ/h
- cooling water quantity required 15 m3/h
- cooling water pressure loss 5 or less m
G3C0002606 - 10 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Clean, softened water should be provided as low-pressure cooling water. It should be free
from suspended matter, should not precipitate matter out of solution at the prevailing
operating temperatures, and should not be aggressive. pH value ≧ 8.5
The cooling water circuit between the motor cooler and the heat barrier, together with the
required monitoring devices, must be installed in accordance with the flow sheet attached.
During initial pump operation stages, strainer should be provided in front of flow switch to
protect flow switch from dirt.
Note
The design life listed above is not guaranteed life but the expected life in case pump would be used in
general operating condition with appropriate regularly maintenance.
The actual life of parts should vary depending on each individual environment i.e. start-up frequency,
operating time, water quality or surrounding temperature etc.
G3C0002606 - 11 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
The pumped fluid flows axially into the pump through the suction nozzle. The pressure and
the kinetic energy levels of the fluid are raised in the impeller (2300), and a portion of the
kinetic energy is converted into pressure energy in the diffuser (1710). The discharge nozzle
diffuser (1710). The discharge nozzle (or nozzles) (7231) is/are arranged radially.
The heat barrier is provided to prevent the heat flow from the hot pump to the cold motor.
The motor is a submersible (wet) three-phase squirrel cage rotor motor. The stator winding is
plastic-insulated.
The shaft of the pumping set is guided in two water-lubricated radial plain bearings (3100.1
and 3100.2) and in a water-lubricated thrust bearing (3840,3870.1, 3870.2 and 3920). A motor
cooler attached to the pumping set and connected by piping to the motor is arranged to
dissipate the heat generated in the motor and in the bearings during operation of the pumping
set.
The thrust bearing plate (3840) arranged in the motor is shaped in the form of an auxiliary
impeller, and circulates the cold fluid from the motor cooler through the motor and back
to the motor cooler (high pressure cooling circuit). The fluid absorbs heat from the motor
during its passage through it, and delivers it to the motor cooler. The fluid in the high
pressure cooling circuit is at the same pressure as the fluid pumped in the pump
compartment, but is maintained within the temperature limits permissible for the
insulation material of the winding. The three phases of the stator winding of the motor are
led out individually through the wall of the motor casing via pressure-tight insulation bushings
into the terminal box. The power supply cable from the network is connected to the motor in
this terminal box.
G3C0002606 - 12 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
For the hydrostatic pressure test and for the hydraulic trial runs, the pumping set is first of
all completely assembled at manufacturer's Workshop, in accordance with our Scope of Supply.
After completion of these tests, the set is dismantled and all components are thoroughly
cleaned.
The pump casing and studs are supplied as loose components whilst motor assembly is supplied
with heat barrier and complete motor unit. All the apertures and connections are sealed with
covers. The complete motor is filled with nitrogen gas.
The pump casing (1010) and the motor cooler also have all their apertures sealed with covers.
The components despatched to the site in the condition described above should be stored in a dry
room, in order to avoid any possible damage. The covers should only be removed immediately
before installation of the required components, in order to preserve the highest
possible degree of cleanliness. In addition, the relevant individual covers should only be
removed as required by the sequence of erection, i.e. immediately before connection of the
relevant pipeline or other item.
Despatch and packing of the pumping set components described above are effected in accordance
with the stipulations of the contract.
For hydrostatic pressure test at site of BRP, the following actions should be required.
・The erection of motor, motor cooler, HP piping, etc. should be completed.
・The test pressure should be less than the specified value. (See item 1)
・The water filling of the motor should be completed. (See item 5.1)
・The cold, clean water to motor should be filled. (See item 5.1)
・All wall surfaces and joints of each pressure parts should be cleaned.
G3C0002606 - 13 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
3.2 Preservation
3.2.1 General
Depending on plant specific situations and preservation time intervals, the following table applies
to pump motor preservation.
Hydrazine Preservation
No. Method Note
(ppm) time
In case 4 - 5 months preservation time
Normal boiler Max. 4 – 5
1 0-5 is exceeded, each pump should run for
water filled months
30 minutes, every 4 weeks.
In case 3 - 4 months preservation time
Max. 3 - 4
2 Ditto Max 500 is exceeded, each pump should run for
months
30 minutes, every 4 weeks.
In order to avoid local corrosion, each
Cold clean
3 0-5 Long time pump should run for 30 minutes, every
water filled
4 weeks.
Max. 3 - 4
4 Ditto Max 500 Ditto
months
Dry N2 Gas Long time Dry preservation procedure should be
5 -
filled (Item 3.2.2) observed.
If the pump can not be run each every 4 weeks, the water in motor should be replaced by
purge water.
N2 Gas
*Piping removed
G3C0002606 - 14 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
For motor drain procedure, Item, 5.4 should be strictly observed. After completion of motor
drainage, N2 gas is filled according to the following procedure.
(1) Dry up pump motor internals by compressed dry air (max. 55℃).
(2) Close pump suction discharge valves and all other valves to isolate pump motor compartment
from the system.
(3) Supply N2 gas from high pressure cooling water inlet and outlet connections. During N2 gas
supply, keep open air vent valve of the suction pipe line.
(4) Continue N2 gas supply until N2 gas replaces air inside, by checking at air vent valve at the
suction pipe line.
(5) Close air vent valve. Stop N2 gas supply, when inner pressure reaches to 0.1 - 0.2 kg/cm2g
Leave 2 - 3 hours for O2 absorption.
(6) Repeat the above step (3), (4), (5), until O2 absorption is completed. Pump motor is ready for
preservation.
(7) Repeat the above step (3) - (6) once every 2 - 3 months.
G3C0002606 - 15 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
A motor is filled with nitrogen gas at manufacturer's Workshop, and all apertures will be sealed.
It should be kept either lying or standing, in a room .
The nitrogen gas fill should be renewed twice a year or more. The filling pressure should be 0.2 to
0.5 kg/cm2g.
When a motor is installed, the relevant instructions contained in this operating instruction manual
which relate to the connection of the motor cooler, to the monitoring instruments and the
commissioning of the motor should be carefully observed.
For tentative storage of all the delivered motors at site, the above storage instruction should be also
observed.
In case the motor inner room is expected to be frozen or to form dew condensation during storage
time, wet preservation(water + glycol anti-freezing agents)of the unit is recommended alternatively.
And in this case, prior to the initial pump operation, please replace the filled water (glycol solution)
by regular priming water acc. to Item 5.1.
In the case of opening the terminal box cover, if the silica-gel color has changed to pink or is
color-less, the silica-gel should be replaced by new charge before closing the terminal box cover.
Use silica-gel : PQ5up blue 500g (Fuji Gel Sangyo Ltd.) or equivalent.
G3C0002606 - 16 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
A skilled erector should be entrusted with the installation of the pumping set. The set should
be installed vertically (as illustrated in outline drawing) with the motor below the pump.
As a general rule, no special or additional support is required for the set, which is suspended
freely in the pipeline. If an additional support is required for the set for any special reason, it
is absolutely essential that such a support should be elastic and free to move, to enable the
pumping set to freely follow the movements of the piping, despite the support. Such
arrangement of the support must receive manufacturer's prior approval before the set is
commissioned.
Use only the original Lifting Lugs of the motor casing when suspending the motor weight!
If it is intended to provide thermal lagging for the set, make sure that only the pump casing
(1010) is lagged. On no account should the motor (8110), the motor cooler, the connecting
piping to the motor cooler, the stud bolts (9020.1) and the heat barrier (1520) be lagged as well.
Prior to installation of pumping set, enable the supply of cold clean water for motor filling
(See Item 5.1).
G3C0002606 - 17 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
The suction line is to be such as to promote favourable flow conditions, i.e. sharp bends,
abrupt changes in the cross sections and features likely to encourage the formation of air
pockets must be avoided.
In case of welded construction, the burrs and welding beads must be removed carefully.
In order to prevent evaporation in the pump, the value of NPSH (AV.)(static suction head
minus all losses in the suction line) must be at least as high as the value of NPSH (REQ.) as
prescribed by us, as, otherwise, this will result in reductions in pump performance and severe
damage by cavitation to the pump.
The NPSH (REQ.) as given by manufacture is to be understood for steady operating conditions
where there are only minor pressure variations.
Should there be, however, major rates of pressure decrease in the plant, the NPSH (AV.) must
be increased, or the suction flow must be subcooled, to avoid cavitation. Consequently, the
velocity of a pressure drop as incurring may, under any one phase of operation, not be
higher than the allowable rate of pressure decrease as established for the plant. Also, the
necessary minimum flow of the pumps may not drop below the admissible value specified by
manufacture. (Minimum flow : 90 m3/h)
Since the minimum flow rates of the plants are very different ones, these must always
be determined and are subject to our consent.
The discharge line must also be laid such as to ensure that the flow is not unnecessarily
impeded or restricted.
The suction and the discharge line must be suitably supported in the vicinity of the pump.
G3C0002606 - 18 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
The cooler and the motor of the pumping set should be primed with clean, cold water
immediately after erection of the cooler (See Item 5.1)
As previously mentioned under item 2, it is necessary to provide a motor cooler for each of
the pumping sets, for the purpose of removing the heat generated in the motor and in the
bearings during operation of the set. The motor cooler is designed on the high pressure side
for the max. operating pressure of the pumping set. It is connected to the pumping set by
a short length of piping, as illustrated in our arrangement drawing. It must be bolted onto
the cooler retaining shackles arranged on the motor casing.
The arrangement of the motor cooler and of its connecting piping to the pumping set must be
such that the possibility of formation of air pockets is excluded anywhere within the cooler
itself or the piping during subsequent venting and priming operations.
The motor cooler and its connecting piping must be carefully cleaned before connection to
the pumping set, in view of the water-lubricated bearings.
Make sure that the regular gaskets are fitted and tightened securely.
In order to preclude the heat flow from the hot pump casing to the cold motor, it is absolutely
essential that the low pressure cooling water supply should remain switched on (e.g. in the
case of a stand-by pump or stopped pump kept "warm") for as long as the temperature in the
pump casing (or the temperature of the fluid) remains above 60℃.
The pressure of the cooling water at the inlet into the heat barrier should be at least
4 kg/cm2g.
2
G3C0002606 - 19 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
In operation, the thrust bearing plate mounted within the motor assembly effects a continuous
circulation of the liquid in the HP cooling circuit, between the motor assembly and the cooling
water heat exchanger. The pollution, if any, contained in this circuit or forming there in the
course of the time, such as deposits from the water, corrosion products or small metal particles,
are, thus, partly circulated, too, and may, if entering the water-lubricated bearings, destroy
their contact face, no longer ensuring the formation of a very thin liquid film-necessary in view
of the lubrication by the water. Therefore, the thrust bearing case (3540) is fitted with a filter
the required cleanliness of the HP circulating water.
During the operation of the pump, the water within the HP cooling circuit of the motor
continuously flows through the filter.
4.4.1 Disassembly
After removal of socket head cap screw (9140.10), the filter set (7911) may be withdrawn from
the thrust bearing case (3540). By loosening the hex. nuts (9200.7), the screen (7931) may be
removed. The dismantled components of the filter set must be cleaned using gasoline used for
cleaning purposes; water is to be employed for cleaning the O-rings (4120.6).
The housing must equally be cleaned internally.
4.4.2 Maintenance
The filter set must be cleaned at the time of the routine maintenance of the boiler. The dirt collecting
chamber is of ample capacity. The routine maintenance is shown in Item 9.2.2.
G3C0002606 - 20 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
The temperature of the high pressure cooling water (circulation water) at the outlet of the
motor should not exceed 50℃ approx. during normal operation. This temperature can be
regulated by the admission of a larger or smaller quantity of low pressure cooling water
through the motor cooler. On account of the plastic insulation of the motor winding and of the
cooling of the bearings, the max. temperature of the high pressure cooling water should not
2 exceed 66℃. Such a high temperature should, however, only occur in case of fouling of the
motor cooler or of an excessive temperature rise of the low pressure cooling water.
In order to protect the motor and the bearings against possible damage in such an eventuality, a temperature
monitor has been incorporated in the motor cavity. The sensors of these instruments protrude right into
the motor compartment and thus detect the highest motor temperature in the area
of the top winding end.
The motor temperature monitored, on the one hand, can be read directly at the pump itself,
and on the other hand it can be transmitted to alarm, interlock trip system.
When the alarm is triggered, steps should immediately be taken to find the reason of the
temperature rise and to lower the temperature, e.g.
(1) Check for possible leakage at the connection between the motor cooler and the motor in the
HP cooling system as well as all connections.
(2) Check the LP cooling system (rate of flow, temperature, leakages).
(3) Increase the flow of LP cooling water through the motor cooler or through the heat barrier.
(4) Switch over to another available cooling system if possible (emergency cooling system) in
case of cooling water failure.
If the above measures do not produce the desired result almost immediately, and if the motor
temperature should continue to rise, the pump must be switched off, or it will switch itself off
automatically when the limit temperature has been reached.
G3C0002606 - 21 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
See Item 1.4 for operating data and LP cooling water requirements and specification.
The operational safety of the pumping set is intimately related to the correct and reliable
operation of the low pressure cooling water system. If LP cooling water supply to the motor cooler
is interrupted for a few minutes during the motor running or LP cooling water supply to the heat
barrier is interrupted for a few minutes when the pump is hot condition and the motor is switched
off (e.g. in the case of a standby condition), motor temperature may be raised up and so the motor
may be alarmed at 63 deg. C or tripped at 66 deg. C. Eventually the insulation of the motor winding is
liable to suffer damage as a result of overheating.
Therefore an uninterrupted flow of LP cooling water must be maintained and
safeguarded under all circumstances.
In order to achieve this, it is necessary to incorporate a cooling water flow monitor in the
cooling water supply line to the motor cooler and to the heat barrier, which will trigger a pulse for
a visual or audible alarm signal immediately in case of the latter drops below 70% of the rate of flow
specified under Item 1.4. Thereupon when usual cooling line come to be unusable, the cooling water
supply should be switched over manually or automatically to another cooling water supply line (e.g.
from an emergency overhead water reservoir).
Being different of upper usual condition, in case of usual cooling water stopped during pump hot
condition, motor is surely maintained at a safe temperature in the condition that emergency cooling
water of heat barrier in secured. This emergency cooling water of heat barrier should be prepared
from water source not to break due to another power source, or, from head tank. A time required for
cooling water supplying to heat barrier is changed by pump operation temperature. Emergency
cooling water shall be continued to supply to heat barrier until the temperature of pump casing goes
down to 200 deg. C.
G3C0002606 - 22 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
In the case of the motor temperature rising and the alarm or the trip is triggered, the motor
may be temporarily cooled down by the purge water.
Purging of the motor should be carried out at a filling rate of 0.3 m3/h, at a temperature of max.
45℃ and at (pump system pressure) + (2~3 kg/cm2g)
To protect the motor against overload, it is necessary to provide a motor protection cutout
switch, in the same way as for conventional electric motors.
The permissible impulse voltage of the motor is max. 18.0kV – 1.2 x 50μs.
G3C0002606 - 23 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Immediately after erection, the complete pumping set (i.e. the motor and the pump, also the
motor cooler and its connecting piping) should be primed with cold, clean water to prevent
any hot water penetrating inside the motor compartment, when the set is subsequently
started up. The pumping set should be primed with pure water or cold, clean boiler feed
water.
If the above water could not be prepared immediately after erection, the drinking water may
be used to prime the motor, the pump, the motor cooler and connecting piping.
Water Quality: Halogen (specially Cl)≦ 50 ppm
PH > 6.5 (at 25℃)
Solid content ≦ 5 ppm
Temperature ≦ 45℃
During the priming operation, the set should be vented at its apex, to prevent the formation
of air pockets inside the set.
Priming of the set and of the cooler should be carried out slowly, at a filling rate of max.
0.3 m3/h approx., until the water overflows at the vent aperture.
If there is any danger of freezing, it will be necessary to protect the circulating pumps.
The air surrounding the set can for instance be warmed up by an external heat source
(e.g. a radiant heater).
G3C0002606 - 24 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
(1) the high-pressure isolating valves in the priming line must be closed.
(2) the low-pressure cooling water supply for the motor cooler and for the heat barrier should
be turned on.
Thereafter, the pumping set can be pressurized. After checking the correct setting and
operation of the monitoring devices, the pumping set is ready for start-up.
Although the set should be filled carefully and slowly, complete venting cannot always be
ensured. In order to remove, nevertheless, the remaining air inclusions, it is necessary to start
the motor in a short time 1- or 2- times for approx. 5 - 10 seconds. The frequency of switching-
on as given in Item 6.2 may, however, not be exceeded.
It is, of course, unnecessary to prime the pumping set with cold water before every subsequent
start-up, because it remains filled with water when stopped. In case of doubt, however, the
water fill should be checked again before a renewed start-up.
G3C0002606 - 25 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
To obtain the proper direction of rotation, the motors must be connected in compliance with
the information plate on the terminal box:
Cable phase " R" to be connected
to terminal phase " U" in the terminal box
Cable phase " S" to be connected
to terminal phase " V" in the terminal box
Cable phase " T" to be connected
to terminal phase " W" in the terminal box
Care must be taken to make sure that the time phase sequence - R, S, T - is available at
the end of the current supply cable.
Further check of the direction of rotation can be made by comparing the discharge shut off
head, and that at an operation under cold water (density = 1000 kg/m3 ).
For this purpose - after filling up and complete preparation of the pump for start-up - the
motor is to be switched on for a short period (approx. 2 ~3 sec.) and started against the
discharge valve closed.
If shut off head is considerably lower than the values given, the leads of the terminals must be
interchanged to suit the other direction of rotation.
The axial bearing (thrust bearing) is designed for a certain direction of rotation, so that
it will be damaged in case of improper direction of rotation during a major period,
resulting in a failure of the set.
G3C0002606 - 26 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
The insulation resistance of the motor winding should be measured when the pumping set is
primed with water at a temperature of 20℃ (Max. 45℃).
This test should be carried out before the initial start-up of the set, and every time the
pumping set is subjected to a general inspection. The insulation test can be carried out
direct at the lead-out bushings, taking care to observe the following precautions:
(1) Disconnect the power supply cable from the cable lead-out bushings.
(3) Connect the leads of the measuring instrument to U, V or W of the lead-out bushing and
to earth (casing) and carry out the measurement.
The insulation resistance under the conditions outlined above should be 200 megohms,
and in the case of a motor under hot running conditions (50℃) and under pressure, it
should be more than 3 megohms.
G3C0002606 - 27 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
2000MΩ
G3C0002606 - 28 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Because each motor has been completed high-voltage test (2E+1000V・・・1 min.) at Works,
it is not necessary to apply the test again at Site.
After installation, if the test is attempted to carry out for some reasons, the following
apparatus should be provided.
*Remark
Test voltage for aged or repaired motor
shall be decreased correspondingly.
・The above-mentioned numerical value is for a single motor (without power cables).
・Do not apply DC-voltage.
・Test shall be performed to the above-mentioned cold water filled motor.
・The cold water filled condition in the motor should be kept for 4 hours or more.
G3C0002606 - 29 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
The water filling of the pump and/or from valve to valve is necessary for reasons of
preservation, and to prevent any particle entering into the motor.
The pump should only be drained and later refilled for the following purposed.
(1) Pump, Motor overhaul (See item 9.2)
(2) Partial dismantling (See item 9.1)
(3) Dismantling and Inspection of the Cooler H.P. side
(4) Inspection of the Filter
In order that the entire boiler water must not be led through the pump during every boiler
drainage - what will be the case more frequently during the first operating phase - the
following steps should be taken:
(1) Close the suction and discharge line valves, as far as such valve (s) is (are) provided.
(2) Separate boiler piping water drainage up to the pump valves.
(3) Separate pump casing water drainage via the discharge branch drainage
(with free inspectable outlet hopper).
Such a drainage should only be carried out when revisions will be necessary in this part of
the plant.
(4) After the above drainage has been completed, the motor should be rinsed via the motor
bottom feed line with approx. 3 - 5 m3/h clean, cold water. The rinsing procedure
shall be continued until the water will leave the discharge branch drainage clear and
drainage clear and colourless.
(5) Then, open drainage branch (7100.1) of pump casing, the water must also emerge clear
and colourless. If this is the case, the rinsing procedure is completed.
If it is not envisaged to remove the motor, the pump must, in order to avoid corrosion, be
refilled with water up to the boiler line valves after completion of the revision in this part
of the plant.
(6) If drainage of the motor is necessary because of revisions or removal of the motor,
the water emerging from the drainage branch of the motor must first of all be checked
with regard to its purity according to Item (4) and (5).
Then the residual water in the motor can be drained via the motor drainage.
As according to our experience abnormally high contamination in the motor part does derive
from irregular drainage procedures, please observe the above mentioned points, especially
during the first operating phase (pressure test, cleaning of boiler, starting operation).
G3C0002606 - 30 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Recommendation is given below, for the following special pump operational modes;
(1) Pump motor filling after the pumping set installation (Item 5.1)
(2) Pump motor filling for hydrostatic pressure test (Item 5.1)
(3) Boiler clean up with pump operation (Item 8)
(4) Boiler clean up without pump operation (Item 8)
(5) Pump commissioning operation (Item 6)
(6) Pump re-start-up after boiler stand still (Item 6)
(7) Pump re-start-up after boiler inspection. (Item 6)
For the above special pump operational modes, there is a fear that boiler water dirty
particles can enter into the motor compartment. In such a case, the following provision
should be taken;
(1) Cold clean water should be flushed from motor filling connection at more than
(pump discharge pressure) + (2~3 kg/cm2g)
In order to avoid reversal flow of motor water, reliable check valve (with spring) should
be incorporated at each motor in the motor flushing water pipe line.
Especially for pump parallel operation, this check valve at each motor is of vital
importance. The motor priming valve for each of motors should be controlled to keep the
required flushing water pressure for the running pump.
G3C0002606 - 31 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
G3C0002606 - 32 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
After the pumps have been prepared for service in accordance with Item 5, they can be started
up after making sure that the following conditions have been carried out:
(1) Is the pumping set primed with water? (See Item 5.1)
(2) Does the pump rotate in the correct direction? (See Item 5.2)
(3) Has the insulation resistance of the motor winding been measured? (See Item 5.3)
(4) Has an operational check of the temperature and cooling water flow monitors, ammeters
and motor protection cutout switches been carried out? (See Items 4.5, 4.6, 4.8)
(5) Is there a supply of LP cooling water available for the motor cooler and for the heat barrier?
(See 4.5)
(6) HP cooling water temperature ≦ 63 ℃ (See Item 4.5) 2
(7) Water level in suction vessel above, or at least as high as the minimum prescribed water
level.
(8) Is motor flushing cleaning completed, in case of special pump operation mode? (Item 5.5)
(9) Are pressure tight seals at motor cooler, valves and connecting pipes assured?
G3C0002606 - 33 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
If possible, the pumps should be started up against a closed isolating valve in the discharge
line, in order not to overload the motor too much during start-up. The valve should be opened
immediately after switching on the pump, in order to prevent excessive heating of the water
and the consequent dangers of dry running and cavitation.
Pumps operated at any capacity range (from 0 to design capacity) must be equipped with a
minimum flow recirculation control assembly and are only allowed to be started with the
flow line opened.
The pumps can be started up against an open valve in the discharge line. The automatically-
controlled pumps must, however, have been previously made ready for start-up at any time,
as described under Item 5.
The rate of flow should be adjusted solely by means of the valve in the discharge line.
The valve in the suction line must remain fully open all the time the pump is running.
In the case of routine starts, only Item 6.1, (5), (6), (7) and (8) above need to be checked.
Frequent start and stop may shorten the motor life time, then less than 750 times per year
is recommended. In the case of per one day, less than 2 times is recommended.
Less than 2 times starting per one day are permissible. Only two switchings-on in
immediate succession in cold condition, and one in hot condition are permissible.
Excessive frequent switching will damage the stator coil insulation.
G3C0002606 - 34 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Please put the cooling-down period in the table below according to the state
immediately before.
Succeeded and
Failed
continuous running
from COLD 2
It's possible to restart It's possible to restart
condition(*1) times
only once after only once after
3 times
continuous running continuous stopping / hour
more than more than
from HOT 1
10 minutes. 30 minutes.
condition(*2) time
(*1) COLD condition : Internal temperature of the motor comes to be ambient temperature,
or the motor has been stopped for 6 hours or more.
(*2) HOT condition : Internal temperature of the motor is in operating temperature, or the
motor has been operated for a few minutes. And it is the condition
with the exception of COLD condition.
G3C0002606 - 35 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
7. Supervision of Operation
7.1 Supervision during operation
After the pump has been switched off, the following points must be kept under observation for
as long as the temperature in the pump compartment exceeds 60 ℃.
The above also applies to pump standby mode which are kept at operating temperature.
G3C0002606 - 36 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
In general, the leak-tightness of the entire high-pressure cooling circuit should be kept under
observation. And also it should be observed that the water leak has not occurred from the
detection hole (Fig 7.1).
Refer to Daily Check Sheet Item.9. If the water leak has occurred and is left as it is, it could cause
the insulation deterioration, line-to-ground fault or serious condition.
Any exposure to excessive heat or cold from the surrounding atmosphere must be
avoided.
G3C0002606 - 37 / 58
D A I LY C H E C K f o r P U M P I S I N S E R V I C E
1 Suction tank Water level Level detector Min. water level Daily
2 Pump suc.& dis.pipes Pump differential press. Press. gauge Specified head Daily
7.2 Inspection sheet
3 Pump flow rate Flow rate Flow meter Specified flow Daily
Daily
9 HP cooling water lines Leak Visual No leak
(Important)
2 × 660 MW KHARGONE SUPER THERMAL
G3C0002606 - 38 / 58
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
Date: 18/8/2017
Rev. No.: 2
DAILY CH ECK for PUMP IS IN STAND BY MODE
1 Suction tank Water level Level detector Min. water level Daily
O & M Manual
2 × 660 MW KHARGONE SUPER THERMAL
G3C0002606 - 39 / 58
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
Date: 18/8/2017
Rev. No.: 2
MO NTH LY CH EC K
O & M Manual
2 × 660 MW KHARGONE SUPER THERMAL
G3C0002606 - 40 / 58
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
Date: 18/8/2017
Rev. No.: 2
AN N UA L C HE CK
Clean
Through hand cover
2 Motor cooler (LP side) Inside inspection No abnormal deposit or Every year
Visual
corrosion
No abnormal wear or
3 Thrust bearing Disassembly inspection Visual Every year
score mark
No abnormal wear or
4 Lower plain bearing Disassembly inspection Visual Every year
score mark
No abnormality on coil,
POWER PROJECT
5 Stator coil end External Visual taping and binding Every year
O & M Manual
materials.
First 1 year and
Overhaul
6 Pump motor Overhaul Instruction manual thereafter every
at Maker's Works
2 × 660 MW KHARGONE SUPER THERMAL
4-5 year
G3C0002606 - 41 / 58
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
Date: 18/8/2017
Rev. No.: 2
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
The boiler circulating pumps may be used for the purpose of cleaning out the boiler, on condition that
they are correctly prepared for commissioning (Item 5) and that they can be properly supervised
during this duty (Item 7).
In addition, the following measures must be taken during the cleaning out of the boiler:
(1) If possible, the rate of flow needed for cleaning out the boiler should be selected in such a way
that one pump is operating only. Other pumps should be completely isolated from the boiler
piping and the system.
(2) In case chemical cleaning liquid is used for boiler clean up, the following points should be
observed;
(2.1) Not to use fluoric hydride acid as inhibitors of chemical cleaning liquid.
(2.2) When planning boiler chemical cleaning, chemical liquid suitable to the pump material
should be selected.
(2.3) Before chemical cleaning or before motor assembly, it is recommended to check that
thrust bearing is clean and without damage.
G3C0002606 - 42 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
(2.4) After completion of the boiler cleaning process, it is recommended to dismantle and
inspect the thrust bearing. The inspection is mainly concerned with dirt deposits, signs
of incipient seizure and mechanical abrasion at the throttling gaps.
If the thrust bearing was damaged, the motor should be dismantled. The damaged
components should be replaced by new ones or touched up.
(2.5) Should components be replaced or touched up, it is, for reasons regarding insurance,
absolutely necessary to have the damage documented by an insurance expert.
The cost of damage occurred, as well as insurance premium, inspection of the pump and
new parts or repair, if any, will be charged to the order.
(3) Flushing of the motor compartment with clean, cold water, at the rate of 0.3 m3/h approx.,
via the motor filling line. (The flushing procedure should commence before the pump is
switched on, and should proceed without interruption until one hour approx. after the
boiler cleaning procedure has been completed.)
Refer to Item 5.5 Motor Flushing.
The flushing water pressure for the motor is more than (pump discharge
pressure) + (2~3 kg/cm2g).
Insufficient pressure will cause a reverse flow from the pump to the motor and
silldamage the stator coil.
G3C0002606 - 43 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
In the case of major overhauls, or of damage to the motor winding, please contact our Head Office or
nearest agency in order to arrange for our service.
If the pump casing (1010) is welded in, it can remain in the piping.
If the inspection after dismantling reveals that it will be necessary to send the pumping set back to
our Works for repair, it should be reassembled and set with the covers prior to despatch.
For dismantling and assembling of the unit, please use lifting tools suitable to weight of
corresponding components. Dismantling weight is indicated on pump name plates.
In any case, lifting lug at pump casing shall not be used for lifting the motor complete. For
dismantling motor complete, pull-out-space below the motor end (min. 1600 mm) is necessary
G3C0002606 - 44 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
9.1 Dismantling
Dismantling should only be commenced after the pumping set has been made pressureless and is cold.
Sectional Drawing should be referred to when dismantling the pump.
(See 41400-1041-Lifting Plan Drawing) 2
9.1.1 Dismantling the Complete Motor Assembly from the Pump Casing
(1) Cut off the power supply cable to the motor, disconnect it at the terminal box, and safeguard
it against accidental switching on.
(2) Register the exact position of the individual components by a suitable marking on the
outside.
(3) Open drain valves in pump casing and drain off the water content of the pump casing.
In addition Item 5.4 must be observed.
(4) Drain off the water content of the motor and cooler via the motor drain connection.
In addition Item 5.4 must be observed.
(5) Dismantle low pressure cooling water piping to the motor cooler and to the heat barrier.
(6) Dismantle motor cooler together with HP connecting piping.
(7) Remove temperature monitoring devices on the motor flange.
(8) Slacken cap nuts (7342), while complete motor weight must be lifted by hoist. To do this,
heat all the stud bolts (9020.1) by means of the bolt heaters for as long as necessary to
enable the nuts to be slackened by hand with the aid of a conventional spanner (a single
heating period will be sufficient). For further details of this procedure and duration and
temperature of the heating up, See Items 9.4.1 to 9.4.6.
(9) Unscrew the nuts and disconnect the complete motor (8110) together with thrust bearing
case (3540), heat barrier (1520), shaft (2100) and impeller (2300), from pump casing (1010).
During lowering down the complete motor, please be careful so as not to damage the terminal box.
In case the heat barrier is tightly wedged inside the pump casing, heat the pump casing flange
uniformly at its outer periphery with the aid of three welding torches. During this heating
process, low pressure cooling water should be allowed to flow through the cooling channels of
the heat barrier.
It is vitally important to pull the heat barrier out of its seat in the pump casing first, and not
out of its seat in the motor casing, as the latter procedure might lead to bending of the shaft.
After the complete motor is dismantled, please be careful so as not to damage the sealing faces
of the pump casing and of the heat barrier. Anti-rust-grease should be applied on these faces.
When the complete motor assembly has been separated from the pump casing, dismantling of
the remaining components can proceed as follows:
G3C0002606 - 45 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
(1) After removal of hex. bolt (9010.1)(first bend back lock washer (9311.1)) impeller (2300) will
be removed.
(2) Unscrew hex. nuts (9200.6) and remove heat barrier (1520) together with upper plain
bearing (3100.1).
(1) Unscrew hex. nuts (9200.2) and remove thrust bearing case (3540) together with bottom
half of thrust bearing (3870.2, 3920, 1311.2).
(2) After removal of hex. bolt (9010.2)(first bend back lock washer (9311.2)), the thrust bearing
plate (3840) can be pulled off from the shaft (2100).
(3) After removal of socket head cap screw (9140.6), the top half of the thrust bearing (3870.1
and 3920) and the bearing bracket (3500) can be dismantled together with the complete
bottom plane bearing (3100.2).
(4) Then the rotor (8180) can be pulled out of the motor casing (8110).
During pulling out the rotor, please be careful so as not to damage the motor windings and
coil ends by using a soft (e.g. rubber) sheet.
If the integrated separator element is to be dismantled in addition to the routine overhaul of the boiler,
this may be done without the necessity of removing the motor cooler.
The pump set must be drained, and it must be rendered pressureless.
Consequently, the system temperature must be less than 60℃. When draining the pump set,
it is absolutely necessary to observe the relevant instructions given in Item 5.4. of this
operating instructions.
(1) By removing the socket head cap screw (9140.10), the filter set can be withdrawn attached
to the Insert ring (5131).
G3C0002606 - 46 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
9.2 Inspections
On the occasion of the regular boiler inspections, the following inspections should be carried
out on the pumps:
G3C0002606 - 47 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
For the first time approx. 1 year after the commissioning and thereafter once every 4 to 5 years,
the pumps are recommended to be completely stripped.
On this occasion, at least the following inspections should be carried out:
(1) Inspection of all parts subject to wear and of their fastenings, including fits, bolts and
screws, locking devices, pins and dowels. These components should be replaced by new ones,
depending on their condition. Criteria for replacement: See table of clearances, Item 9.2.3.
(2) Measurement of insulation resistance (See Item 5.3).
(3) Cleaning of pumping set (the motor winding ends should be lightly rinsed with water).
(4) Out-of-round (true running) check of rotor (max. permissible out-of-round: 0.08 mm).
If a new impeller is fitted, the rotor must be dynamically balanced (See Item 9.3.).
(5) Check of flow conditions through the cooling channels in the heat barrier (clean out same if
necessary). Pressure drop through heat barrier at the nominal rate of flow: 1 mAq approx.
(6) Cleaning out of LP side of the motor cooler.
Hydrostatic testing of the HP side (test pressure, See Item 1.1).
(7) Cleaning out of the Filter.
(8) Visual examination of the motor winding.
G3C0002606 - 48 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
G3C0002606 - 49 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
(1) All the parts should be cleaned up. Stator coil and coil heads should be cleaned up by cold
clean water (chemical or mechanical clean up is not allowed).
(2) All the potential wear surfaces and sealing surfaces should be inspected.
(3) All the pressure retaining gaskets and O-rings should be replaced by new ones at each re-
assembly.
(4) For checking out-of-roundness of the rotor shaft, rotor shaft without shaft sleeve, impeller
and thrust bearing plate is supported at radial bearing area by roller. If out-of-roundness
measured by dial gauge at impeller area and at thrust bearing plate area is 0.08 mm,
please contact pump maker for corrective action.
(5) When impeller is replaced, rotor assembly (with impeller, shaft sleeve and thrust bearing
plate) should be dynamically balanced. For balance criteria value, please contact us.
(6) Insulation resistance of motor windings is checked acc. to item 5.3. Stator winding and
terminal penetration parts need not to be disassembled.
(7) Low pressure side of motor cooler should be cleaned up and inspected. High pressure side
of motor cooler should be subjected to hydrostatic pressure test.
(8) Potential wear parts should be touched up within clearance tolerance values acc. to Item
9.2.3.
Hex. bolts, washers, stud bolts, etc. should be replaced by new ones so far as necessary.
(9) In case of measured clearances beyond the tolerance value acc. to item 9.2.3, related parts
should be replaced by new ones.
(10) Pump casing seal faces should be protected by application of anti-rust-agents, after
inspection.
G3C0002606 - 50 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
9.3.1 Reassembly
φ730
PCD φ620
11
9
67
77
30
40
M64X2
M56 ×2 M
5041
895
5
G3C0002606 - 51 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
9.4 Assembly
With each assembly, a new spiral wound gasket (4113) must be fitted. In this respect, make sure that
the spiral wound gasket fits properly in the groove before commencing reassembly of the pump,
and also make sure that the mating face on the pump casing is in perfect condition.
Prior to assembling the complete motor into the pump casing, it is advisable to check smooth running
of the shaft by turning the impeller by hand (has been assured for the pumps assembled at
Maker's Works).
Coat threads of stud bolts (9020.1) and washers (5500.1) with molybdenum sulphide.
G3C0002606 - 52 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
When a pump is started up, the following, conditions must be fulfilled, in addition to the
general preparations (i.e. priming, venting, checking direction of rotation):
(1) Discharge valve open.
(or to be opened after attaining operating speed).
(2) Adequate water level in suction vessel.
(3) LP cooling water supply for motor cooler (not less than 8.1 m3/h). (01/02PGA02CF201) 2
(4) LP cooling water supply for heat barrier (not less than 1.9 m3/h). (01/02PGA02CF203) 2
(5) Temperature of HP cooling water below 63 ℃ at motor cavity. 2
If the "On" criteria mentioned in Item 10.1 (1) to (3) inclusive are not fulfilled, and in the
event of the faults listed below, the pump must be shut down:
(1) Water level in suction vessel below minimum water level, resp. for differential pressure of
the pump.
(2) Temperature of HP cooling water above 66 ℃ at motor cavity.
(3) Excessive current (over current) or short circuit.
(4) Increase in diff. temperature of pump casing and suction tank more than 80 ℃. 2
In addition, the conditions of the plant demand that the following measures should be taken
into account:
G3C0002606 - 53 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Note: Prior to beginning of revisional action, assure the relevant instruments and protection
protection devices are accurate.
And also investigate the abnormality by comparing with normal operating condition.
G3C0002606 - 54 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Incorrect connection of Make certain the cable Reconnect the cables acc. to
2
motor terminals connection acc. to drawing. drawing.
Low terminal voltage of Examine the power source Investigate power source and
4
motor voltage. make it correct.
Dry up by dryer.
Humidity of terminal box
8 Inspect the terminal box. Exchange gaskets if
inside
necessary.
G3C0002606 - 55 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
Research abnormality of
Metallic contact of running Overhaul and exchange parts
16 sound (metal to metal
clearance. if necessary.
contact) and vibration.
G3C0002606 - 56 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
G3C0002606 - 57 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No. 51006-41400-1055
O & M Manual Rev. No.: 2
Larsen & Toubro Ltd.
Date: 18/8/2017
G3C0002606 - 58 / 58
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
O&M MANUAL FOR Doc. No.: 9578-001-102-PVM-W-074
BOILER CIRCULATION PUMP (BCP) Rev. No.: 02
Larsen & Toubro Ltd. Date: 11.12.2017
SECTION – C
DRAWINGS & DOCUMENTS
Page 64 of 245
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
H H
G G
F F
E E
D D
B B
A A
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q4C0005280 - 1/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Data sheets for Boiler Start-up Doc. No.: 51006-41400-1040
Rev
Details / Description Date
No.
0 FIRST ISSUE 26/2/2016
1 REVISED 11/4/2016
2 REVISED 14/6/2016
3 REVISED 28/7/2016
Q4C0005280 - 2/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Data sheets for Boiler Start-up Doc. No.: 51006-41400-1040
Q4C0005280 - 3/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Data sheets for Boiler Start-up Doc. No.: 51006-41400-1040
CLAUSE
NO. DESCRIPTION VALUE
operating pressure
2
(Kg/cm abs)
1
iii) Feed water temperature at 305.9 deg. C
Eco inlet (deg. C)
iv) Mixed water temperature 303.6 deg. C
(deg.C) at Startup water
Recirculation pump inlet
v) Mixed water specific gravity 679 kg/m3 1 3
vi) Pump speed 1460 rpm
vii) Pump design capacity 588.47 t/h (830m3/h) 1
(Tonnes/hr.)
viii) Suction pressure at 111.4 kg/cm2 abs (110.4 kg/cm2g)
2
rated capacity (kg/cm abs)
ix) Discharge pressure at 116.51 kg/cm2 abs (115.51 kg/cm2g) 1
rated capacity (kg/cm2 abs)
x) Pump design pressure 315.6 kg/cm2g 1
(kg/cm2 g)
xi) Pump design temperature 345 deg. C 1
(deg. C)
xii) Total dynamic head 9.5 kg/cm2 abs (120m)
2
(kg/cm abs)
Q4C0005280 - 4/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Data sheets for Boiler Start-up Doc. No.: 51006-41400-1040
CLAUSE
NO. DESCRIPTION VALUE
xi) Maximum discharge 118.99 kg/cm2 abs (117.99 kg/cm2g) 1
2
pressure (kg/cm abs)
xii) NPSH available (MLC) 285 m
xiii) NPSH required (MLC) 5.5 m
xiv) Pump efficiency at design 70%
point (%)
xv) Pump break horse power 263.0 kW 1 3
xvi) Power consumption at 326.7 kW 3
design point
xvii) Power consumption at Approx. 150 kW
shut off condition
xviii) Pumps type Glandless Circulation Pump
xix) Type of casing Spherical
xx) Type of impellers Centrifugal, Closed
xxi) Type of shaft Vertical
xxii) Type of drive Wet stator three phase induction motor
xxiii) Type of seal Glandless
xxiv) Type of coupling N. A.
xxv) Type of mounting Pipe suspended
xxvi) Nozzle orientation -
a) Suction Axial
b) Discharge Radial
xxvii) Motor type Squirrel Cage Induction Motor (Wet motor)
xxviii) Liquid data -
a) Liquid temp. (degC) ≦ 45 deg. C (Motor priming water)
Q4C0005280 - 5/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Data sheets for Boiler Start-up Doc. No.: 51006-41400-1040
74.08
CLAUSE
NO. DESCRIPTION VALUE
b) Chemical composition Halogen (specially Cl) ≦ 50pm
Solid content ≦ 5pm
(Motor priming water)
c) Nature Pure water / Clean boiler feed water
(Motor priming water)
d) pH . > 6.5 @ 25deg. C (Motor priming water)
xxix) Materials of construction
a) Pump casing SF490A 2
b) Casing ring SUS420J2
c) Impeller SCS1-T2
d) Shaft SUS420J2
e) Journal bearing FRP
f) Motor housing cover SF490A
g) Thrust disc N/A
h) Thrust bearing pads FRP
i) Bearing sleeves SUS420J2
j) Motor housing SF490A
k) Stator Si - Steel
xxx) Rotor
a) Heat barrier SFVA F11B 2
b) Bolt SNB16 / SNB21-2
c) Nut SCM435H
xxxi) Whether following accessories
provided
a) Discharge Pressure
gauge Yes (LMB scope)
b) Suction pressure gauge Yes (LMB scope)
Q4C0005280 - 6/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Data sheets for Boiler Start-up Doc. No.: 51006-41400-1040
xxxii) Reference drawing No. 41400-1018 ( 0910015234 ) Sectional Drawing of Pump / Motor
Q4C0005280 - 7/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q4C0005282 - 1/6 6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1005
BCP - Data sheet Rev. No.: 6
Larsen & Toubro Ltd. Date: 11/11/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 4/3/2016
1 REVISED 13/5/2016
2 REVISED 14/6/2016
3 REVISED 4/8/2016
4 REVISED 30/9/2016
5 REVISED 24/10/2016
6 REVISED 11/11/2016
Q4C0005282 - 2/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1005
BCP - Data sheet Rev. No.: 6
Larsen & Toubro Ltd. Date: 11/11/2016
Q4C0005282 - 3/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1005
BCP - Data sheet Rev. No.: 6
Larsen & Toubro Ltd. Date: 11/11/2016
HLAV-PDS-E-A00
PUMP DATA SHEET (1/3)
Glandless Circulation Pump
Marked ■ means the application for this Item.
1 Service BOILER RECIRCULATION PUMP DE SIG N
2 Product No. PU0137910/28/36 Pump Casing ■ Spherical □ Annular □ Volute
3 Type & Size HLAV250-630/1K Impeller Centrifugal, Closed
4 Quantity 1Pump /Unit x 2 (Total 2 pumps) + 1 Spare pump Number of Stage 1
5 Location Outdoor Radial Bearing Plain Bearing
6 Thrust Bearing Tilting Pads
7 PUMP Unit Specified Lubrication Forced Water Lubrication
8 Design Pressure kg/cm²g 315.6 1 Press. Retaining Pump : Spiral wound Gasket
9 Design Temperature ℃ 345 1 Seal Motor: O Ring
10 Hydrostatic Test Pressure kg/cm²g 473.4 1 CO NNE CTIO N
11 Medium handled - Boiler Water OD508 x Thickness 68(AWT)
12 Operating Temperature ℃ 303.6 Pump Inlet Butt weld
13 SF490A
14 Density kg/m³ 679 1 3 No. of Nozzle: ■Single ,□Double
15 Pump Outlet OD406.4 x Thickness 54(AWT)
16 NPSH(a) m 285 Butt weld
17 NPSH(r) m 5.5 SF490A
18 Suction Pressure kg/cm²g 110.4 TE R MINA L B O X
19 Discharge Pressure kg/cm²g 118.5 Protection IP55
20 Capacity m³/h 830 Location Side Bottom of Motor Casing
21 Minimum Flow m³/h 90 No. of Box 3 Boxes
22 Main Cable 4
3Rx1Cx150Sqmm AL/XLPE/AL/Unarmoured Cable
Q4C0005282 - 4/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1005
BCP - Data sheet Rev. No.: 6
Larsen & Toubro Ltd. Date: 11/11/2016
PUMP DATA SHEET (2/3)
Glandless Circulating Pump
Marked ■ means the application for this Item.
1 HEA T B AR RIE R Unit RE CO MMEN DE D C O O LIN G W A TE R Q UA LITY
2 Fluid - Cooling Water ・ Cooling tower water, surface or well water.
3 Normal Cooling Flow Rate L/min 45 2 ・ Clear, colorless, without suspended matter.
4 Water Inlet Temp. ℃ 37.6*1 ・ Without corrosive and erosive contents.
1
5 Inlet Press. kg/cm²g TBA RE CO MMEN DED MO TO R FILLIN G W ATER Q U ALITY
6 Press. Loss m 5 or less ・ Boiler feed water ( ≦ 45℃ ) or drinking water.
7 Fluid - Cooling Water ・ Cl- ≦ 50ppm, pH ≧ 6.5, Suspending solid ≦ 5ppm
8 Emergency (1) Flow Rate L/min 27 2 FILLIN G ,PUR G E AN D FLU SHIN G W ATE R R EQ U IR EME N TS * 2
9 Cooling Water Inlet Temp. ℃ 37.6*1 (1) Motor initial filling flow rate: max. 5 L/min
1
10 Inlet Press. kg/cm²g TBA (2) Purge water flow rate during cleaning: approx. 5 L/min
11 Press. Loss m 2 or less (Press. more than Pump discharge press. + 0.2 ~ 0.3 MPa)
12 MO TO R CO O LER Unit Shell Tube (3) Flow rate of motor pre-drain flushing: min.50 ~ 80 L/min
13 Type - Shell & Tube PR O TEC TIO N DE VIC E ( SE T PO INT)
14 Capacity kJ/h 189000 Motor Cavity Temp. high (ANN) more than 63 oC ON
15 Fluid - Cooling Water Boiler Water Motor Cavity Temp. high high (TRIP) more than 66 oC ON
16 Flow Rate L/min 191.6 (11.5m3/h) 130 (7.8m3/h) Motor Cooler LP CW Flow low (ANN) less than 70% ON
17 Inlet Temp. ℃ 37.6 50 Heat Barrier LP CW Flow low (ANN) less than 70% ON
1
18 Outlet Temp. ℃ 40.6 44 1
1
19 Press. Loss m 4 -
20 Design Press. kg/cm²g 10 1 3 315.6 Rods (incl. 2 spares)
1
21 Design Temp. ℃ 60 345 B O LT HEA TE R PO W ER SU PPLY ■ req'd □ not req'd
2 1
22 Test Press. kg/cm²g 15 473.4 Quantity of Bolt Heater 22 Rods (incl. 2 spares)
1 3 1
23 Switch Box Power Supply AC 240V 1 Phase 1Cable 4
24 Shell SA106 Gr.B Max. Power Consumption 37.8 kW
25 Material Tube SA213 TP 316L
Please be provided with above mentioned panel board within 10 meters distance from pump.
26 Tube sheet SA240 316L
27 Bonnet SA 350 LF2 APPR O X . MA SS ( DR Y ) kg
1
28 PU RG E W A TE R Pump Motor unit 19600 1 2 4
29 C O O LE R Unit Shell Tube Motor Cooler 295 4
30 Type - Shell & Tube Dismantled Motor mass*3 12000
1 2 4
31 Capacity kJ/h 311110
32 Fluid - Cooling Water Boiler Water
33 Flow Rate L/min 250 (15m3/h) 5 (0.3m3/h)
34 Inlet Temp. ℃ 37.6 305.9 1 TES T & IN SPE CTIO N
1
35 Outlet Temp. ℃ 43.6 45 ・ Test procedure (cold water) acc to JISB8301, JEC2137.
1
36 Press. Loss m 5 25 ・ Design, material and welding of pump and accessories
37 Design Press. kg/cm²g 10 354.3 acc to Maker's standard.
1 3 1
38 Design Temp. ℃ 60 306
2 1
39 Test Press. kg/cm²g 15 531.5 G UA RA N TEE S
1 3 1
40 ・ Guarantee period acc to commercial contract.
41 Shell SA240 304 ・ Proof of guarantee on Maker's test bed at cold water.
42 Material Tube SA213 TP 304
43 Cover SA182 F304
44
45
46 【 NOTES】
47 (1) In Blackout condition, Emergency cooling water shall be supplied to Heat Barrier, until the temperature of Pump casing gose down to 200 deg.C.
48 (2) *1: Outlet Temp: Normal - Approx 39.6℃ / Emergency - Approx 40.6℃
1
49 (3) *2: The details are given in O&M manual.
50 (4) *3: Please do not dismantle at wet condition.
51 (5) Operating cases
3
52 1.Cold clean-up (25%MCR) : Flow rate-640 m /h , Total head-60 m
3
53 2.Start-up (5%MCR) : Flow rate-830 m /h , Total head-120 m
54 (6) Purge water strainer: Mesh 150 or more, Design Pressure / Temperature - 354.3kg/cm2g / 306 ℃ 2
55
56
57 【 REMARKS】
58 The temperature of high pressure cooling water leaving the motor cavity to the cooler shall not exceed 60 deg C. The cooler has been adequately sized to reduce
59 this temperature to less than 50 deg C.
60
61
62
Q4C0005282 - 5/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1005
BCP - Data sheet Rev. No.: 6
Larsen & Toubro Ltd. Date: 11/11/2016
PUMP DATA SHEET (3/3)
Glandless Circulating Pump
Marked ■ means the application for this Item.
1 SC O PE O F SU PPLY Per One Pump Total Q'ty Remarks
2 PUMP & STAN DAR D ACC ESSO RIES
3 Pump Motor unit 1 2
4 Motor Cooler (HP Coil Tube, LP Shell) 1 2
5 High Press , Connection Pipings 1 2
6 RTD (Pump Casing Temp. monitoring) 3 6
7 Flow Switch (Motor Cooler LP CW Flow less 70% ANN) 1 2
8 Flow Switch (Heat Barrier CW Flow less 70% ANN) 1 2
9 Special Tool - 1
10 Erection Spare Parts (Pump Gasket, HP Flange Gaskets ) 1set 2sets
11
12
13
14
15
16
17
18
19 O PTIO NAL AC CES SO RIE S
20 Purge Water Cooler 1 2
21 Y-type Strainer 1 2
22 RTD (Motor Cavity Temp) 3 6
23 Thermometer (Pump Casing) 1 2
24 Thermometer (Motor Cavity) 1 2
25 Thermometer (Heat Barrier Cooling Water Outlet) 1 2
26 Thermometer (Motor Cooler Cooling Water Outlet) 1 2
27 Thermometer (Purge Cooler Cooling Water Outlet) 1 2
28 Flow Switch (Purge Cooler LP CW Flow less 70% ANN) 1 2
29 Pipe for LP CW Thermometer 3 6
30 Companion Flanges - 2sets Incl. Bolts, Nuts & Gaskets
31 Pump Casing Cover Out of scope Out of scope
1 1
32 Bushing Out of scope Out of scope For Punp Casing Cover
1 1
33
34
35
36 SPAR E PARTS
37 Complete Pump and Motor Assembly (Mandatory Spare) - 1 Incl. Pump Casing sets
38 Plain Bearing compl. (Mandatory Spare) - 1set Incl. upper & lower
39 Incl. upper & lower, Thrust
Thrust Bearing Segment (Mandatory Spare) - 2set
40 Bearing Plate
41 Casing Wearing Ring (Mandatory Spare) - 2sets
42 Set of gaskets - 3sets Incl. Motor Cooler gaskets
43 Set of O-rings - 3sets
44 Motor Cooler - 1set
45 RTD (Pump Casing : 3nos./unit, Motor Cavity : 3nos./unit ) - 6
46 Flow Switch (Motor Cooler : 1no./unit, Heat Barrier : 1no./unit, Purge Cooler:1no./unit) - 6
47 SHIPPING STY LE ■ Motor separated from Pump □ Pump and Motor assembled
48 ・ Pump casing installed with main stud bolts. ・ Pump motor unit fully assembled, branches
49 ・ Motor unit with heat barrier and impeller closed with steel closed with steel covers, filled with nitrogen gas
50 cover and filled with nitrogen gas.
51 ・ Cooler and instruments separately.
52
53
54
55
56 【 REMARKS】
57
58
59
60
61
62
Q4C0005282 - 6/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q4C0005333 - 1/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1004
Pump Performance Curve Rev. No.: 3
Larsen & Toubro Ltd. Date: 8/12/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 4/3/2016
1 REVISED 19/5/2016
2 REVISED 28/7/2016
3 REVISED 8/12/2016
Q4C0005333 - 2/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1004
Pump Performance Curve Rev. No.: 3
Larsen & Toubro Ltd. Date: 8/12/2016
Q4C0005333 - 3/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1004
Pump Performance Curve Rev. No.: 3
Larsen & Toubro Ltd. Date: 8/12/2016
180
Min. Flow (90m3/hr)
160
140
120
Total Head m
100 Rated
(5%MCR)
80
60
40
Max. Wet operation
(30%MCR) 2 3 Cold clean-up
20 (25%MCR) 3
0
0 500 1000
100
90
80 Pump Eff.
70
Efficiency %
60
50
Total Eff. (ρ=679) 1 2 Total Eff. (ρ=1000)
40
30
20
10
0
0 500 1000
10
NPSH3 m
0
0 200 400 600 800 1000 1200
700
600
Motor Input (ρ=1000)
500 Pump Shaft Power (ρ=1000)
400
Shaft Power kW
300
200 Pump Shaft Power (ρ=679) 1 2
100 Motor Input (ρ=679) 1 2
0
0 500 1000
Capacity m3/h
Q4C0005333 - 4/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q4C0005416 - 1/10 4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 24/3/2016
1 REVISED 27/5/2016
2 REVISED 24/6/2016
3 REVISED 21/9/2016
4 REVISED 28/10/2016
Q4C0005416 - 2/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
Q4C0005416 - 3/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
DE-1A HT MOTORS -
A. GENERAL -
1. Frame size 55
2. Type of duty S1
3. Type of enclosure /Method of cooling/ Degree of protection IP68
Q4C0005416 - 4/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
20. Safe stall time with 100% and 110% of rated voltage -
21. Torques : -
Q4C0005416 - 5/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
a. Velocity (mm/s) N. A.
b. Displacement (microns) N. A.
C. CONSTRUCTIONAL FEATURES -
b. Space heater N. A.
c. Temperature detectors(RTDs,BTDs) N. A.
Q4C0005416 - 6/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
3. Bearing -
b. Manufacturer Torishima
e. Oil quantity N. A.
h. Lubrication type N. A.
a. Range N. A.
c. Accuracy N. A.
Q4C0005416 - 7/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
12. Weight of -
D. List of accessories. -
i) Nos. N. A.
ii) Fault Level (MVA)/Fault Level duration (secs) 250 MVA for 0.12 sec
vii) Cable glands & lugs details (shall be suitable for power cable) Double compression nickel
plated Brass cable Glands
(BS-6121) & tinned copper
lugs (JIS C 2805) 3 4
viii) Neutral Terminal box Type N. A.
Q4C0005416 - 8/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
9. Current Transformer -
i) Nos. N. A.
ii) Ratio N. A.
v)Exciting Current N. A.
b. Cold Air N. A.
iv) Range N. A.
v) Supply Voltage N. A.
Q4C0005416 - 9/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1006
BCP Motor Data Sheet (NTPC format) Rev. No.: 4
Larsen & Toubro Ltd. Date: 28/10/2016
ii) Location N. A.
E. List of curves. -
Q4C0005416 - 10/10
c "THIS DRAWING IS THE PROPERTY OF AND CONTAINS CONFIDENTIAL PROPRIETARY INFORMATION OF L&T-MHPS BOILERS PRIVATE LIMITED AND SHALL UNLESS OTHERWISE STATED ALL DIMENSIONS ARE
NOT BE REPRODUCED, USED, DISCLOSED OR TRANSMITTED IN WHOLE OR IN PART UNLESS AUTHORISED IN WRITING BY L&T-MHPS BOILERS PRIVATE LIMITED" IN MILLIMETRES. DO NOT SCALE. IF IN DOUBT, ASK.
A
B
E
C
D
H
16
16
15
15
14
14
13
13
12
12
11
11
10
10
9
9
8
8
7
7
6
6
5
5
4
4
L&T
3
3
NTPC LIMITED
2
2
1
1
A
B
E
D
H
G
c "THIS DRAWING IS THE PROPERTY OF AND CONTAINS CONFIDENTIAL PROPRIETARY INFORMATION OF L&T-MHPS BOILERS PRIVATE LIMITED AND SHALL UNLESS OTHERWISE STATED ALL DIMENSIONS ARE
NOT BE REPRODUCED, USED, DISCLOSED OR TRANSMITTED IN WHOLE OR IN PART UNLESS AUTHORISED IN WRITING BY L&T-MHPS BOILERS PRIVATE LIMITED" IN MILLIMETRES. DO NOT SCALE. IF IN DOUBT, ASK.
A
B
E
C
D
H
16
16
15
15
14
14
13
13
12
12
11
11
10
10
9
9
8
8
7
7
6
6
5
5
4
4
L&T
3
3
NTPC LIMITED
2
2
1
1
A
B
E
D
H
G
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
H H
G G
F F
E E
D D
B B
A A
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q4C0005380 - 1/8 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1034/35/36/37/38/46
BCP Motor Curve Rev. No.: 1
Larsen & Toubro Ltd.
Date: 24/6/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 23/3/2016
1 REVISED 24/6/2016
Q4C0005380 - 2/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1034/35/36/37/38/46
BCP Motor Curve Rev. No.: 1
Larsen & Toubro Ltd.
Date: 24/6/2016
Q4C0005380 - 3/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1034/35/36/37/38/46
Rev. No.: 1
Larsen & Toubro Ltd.
Date: 24/6/2016
Q4C0005380 - 4/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1034/35/36/37/38/46
Thermal Limit & Time vs Current Curve Rev. No.: 1
Larsen & Toubro Ltd.
Date: 24/6/2016
Q4C0005380 - 5/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Load vs Efficiency, Power Factor, (FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1034/35/36/37/38/46
Current and Input Power Rev. No.: 1
Larsen & Toubro Ltd.
Date: 24/6/2016
Q4C0005380 - 6/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1034/35/36/37/38/46
Negative Sequence Curve for Motor Rev. No.: 1
Larsen & Toubro Ltd.
Date: 24/6/2016
Q4C0005380 - 7/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1034/35/36/37/38/46
Heating and Cooling Time Constant Curve Rev. No.: 1
Larsen & Toubro Ltd.
Date: 24/6/2016
Q4C0005380 - 8/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q3C0006029 - 1/11 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1010
Utility List Rev. No.: 1
Larsen & Toubro Ltd.
Date: 3/6/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 11/3/2016
1 REVISED 3/6/2016
Q3C0006029 - 2/11
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1010
Utility List Rev. No.: 1
Larsen & Toubro Ltd.
Date: 3/6/2016
Q3C0006029 - 3/11
CLOSED CIRCUIT COOLING WATER CONSUMPTION LIST
No's of
No's of
CCCW Flow Rate per Total Flow
No. Equipment name No's of Equip. Operating Inlet Temp. Outlet Temp. Heat Duty Remarks
Larsen & Toubro Ltd.
4
5
Utility List
POWER PROJECT
6
7
8
2 × 660 MW KHARGONE SUPER THERMAL
1 1
TOTAL 29.2 129.9
Pressure Loss (From / To Terminal Point between Boiler and Closed Cooling water supplier) :
kg/cm2g
Q3C0006029 - 4/11
L&T-MHPS BOILERS PRIVATE LIMITED
Date: 3/6/2016
Rev. No.: 1
DEMINERALIZED WATER CONSUMPTION for Lot 1
1. Demineralized Water Consumption
3
Consumption (m /h per one Boiler)
No. Item before Start-up Start-up Load Operation Remarks
Larsen & Toubro Ltd.
1 Motor Priming (Initial) 0.3 Max. - - BRP require the water at Motor installation stage.
4
Utility List
5
POWER PROJECT
6
2 × 660 MW KHARGONE SUPER THERMAL
2. Required Total Quantity of Demineralized Water for Boiler Water Filling and Hydrostatic Test
Consumed
No. Items
Quantity *c
The quantity listed on the table is the total volume of water which is filled
1 Normal Wet Lay up (Before Start-up) 0.8 (m3 /unit) in BRP, Motor Cooler and Purge Cooler
3. Required Head
Required head for Boiler water filling 10 [m] (from Ground level)
Bottom of each equipment
Note :
Q3C0006029 - 5/11
L&T-MHPS BOILERS PRIVATE LIMITED
Date: 3/6/2016
Rev. No.: 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1010
Utility List Rev. No.: 1
Larsen & Toubro Ltd.
Date: 3/6/2016
Please refer to the following instruction and make sure to prepare the suitable water
source required for each case.
Q3C0006029 - 6/11
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1010
Utility List Rev. No.: 1
Larsen & Toubro Ltd.
Date: 3/6/2016
Flow Diagram
Water shall be supplied as slow as possible to prevent air from remaining inside the motor
casing.
Note
The air remaining will be compressed as system pressure rises and allow hot water of the same
volume enter the motor casing.
Q3C0006029 - 7/11
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1010
Utility List Rev. No.: 1
Larsen & Toubro Ltd.
Date: 3/6/2016
Flow Diagram
Q3C0006029 - 8/11
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1010
Utility List Rev. No.: 1
Larsen & Toubro Ltd.
Date: 3/6/2016
Flow Diagram
Since cooling water jacket of heat barrier has complex construction for efficient heat
removal and high internal surface temperature, it is very important to supply clean water
which has less tendency of scaling.
Note Cooling water supply shall be started prior to pump operation.
Continuous cooling water supply is required during hot stand-by.
BRP is required inlet pressure of 1 kg/cm2g or more for heat barrier.
Q3C0006029 - 9/11
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1010
Utility List Rev. No.: 1
Larsen & Toubro Ltd.
Date: 3/6/2016
Flow Diagram
Emergency cooling water (EMG. C.W.) should be provided from reliably continuous flow
line with emergency power or head tank. And EMG. C.W. line should be separated from
Normal cooling water (NOR. C.W.) line.
If plant is blackout, Suction and Discharge valve for BCP should be closed in order to
Note restrict thermal source and EMG. C.W. should be provided immediately.
And then, EMG. C.W. should be provided continuously until pump casing temperature turns
into below 200 degree C.
If EMG. C.W. capacity is insufficient, NOR. C.W. should be restored or Pump should be
carried out forced cooling before EMG. C.W. is stopped.
Q3C0006029 - 10/11
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1010
Utility List Rev. No.: 1
Larsen & Toubro Ltd.
Date: 3/6/2016
Utility For Flushing before Motor Drainage Low Pressure Cooling Water for Purge Cooler
Flow Diagram
Flushing water shall be supplied Cooling water quantity will be calculated based on
Note continuously until drainage is clean and the condition of purge water source ( temperature
clear. and flow rate )
Q3C0006029 - 11/11
c "THIS DRAWING IS THE PROPERTY OF AND CONTAINS CONFIDENTIAL PROPRIETARY INFORMATION OF L&T-MHPS BOILERS PRIVATE LIMITED AND SHALL UNLESS OTHERWISE STATED ALL DIMENSIONS ARE
NOT BE REPRODUCED, USED, DISCLOSED OR TRANSMITTED IN WHOLE OR IN PART UNLESS AUTHORISED IN WRITING BY L&T-MHPS BOILERS PRIVATE LIMITED" IN MILLIMETRES. DO NOT SCALE. IF IN DOUBT, ASK.
A
B
E
C
D
H
12
12
11
11
10
10
9
9
8
8
7
7
6
6
5
5
4
4
3
3
2
2
1
1
A
B
E
C
D
H
G
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q3C0006584 - 1/4 2
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1012
Valve List Rev. No.: 2
Larsen & Toubro Ltd.
Date: 20/7/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 17/6/2016
1 REVISED 12/7/2016
2 REVISED 20/7/2016
Q3C0006584 - 2/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1012
Valve List Rev. No.: 2
Larsen & Toubro Ltd.
Date: 20/7/2016
Q3C0006584 - 3/4
Larsen & Toubro Ltd.
BOILER
1 01HAG03AA916 BRP PUMP CASING DRAIN 1 GLOBE A105 315.60 345 1" BW CLASS 2500 1" 41400-1011
WATER
BOILER
2 01HAG03AA917 BRP PUMP CASING DRAIN 1 GLOBE A105 315.60 345 1" BW CLASS 2500 1" 41400-1011
WATER
3 01HAG03AA918 BRP MOTOR COOLER - AIR VENT 1 GLOBE A105 2 10.0 60 CW 1" RF CLASS 150 1" 41400-1011
4 01HAG03AA919 BRP MOTOR COOLER - DRAIN 1 GLOBE A105 2 10.0 60 CW 1" RF CLASS 150 1" 41400-1011
5 01HAG03AA932 BRP PURGE COOLER - AIR VENT 1 GLOBE A105 2 10.0 1 120 CW 1" RF CLASS 150 1" 41400-1011
6 01HAG03AA910 BRP PURGE COOLER - DRAIN 1 GLOBE A105 2 10.0 120 CW 1" RF CLASS 150 1" 41400-1011
8 01HAG03AT992 BRP PURGE WATER STRAINER 1 - A182 F316 354.3 306 CW 1" SW CLASS 2500 1" 41400-1011 mesh 150 or more
10
2 × 660 MW KHARGONE SUPER THERMAL
11
12
Note : Counter flanges w ith Gaskets, Nuts and Bolts at all flanged terminal points are in
RF : RAISED FACE (ASME B16.5-2009)
Torishima scope of supply.
Q3C0006584 - 4/4
L&T-MHPS BOILERS PRIVATE LIMITED
Date: 20/7/2016
Rev. No.: 2
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q3C0006083 - 1/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1013
Instrument List Rev. No.: 5
Larsen & Toubro Ltd. Date: 28/10/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 23/3/2016
1 REVISED 7/7/2016
2 REVISED 15/7/2016
3 REVISED 28/7/2016
4 REVISED 2/8/2016
5 REVISED 28/10/2016
Q3C0006083 - 2/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1013
Instrument List Rev. No.: 5
Larsen & Toubro Ltd. Date: 28/10/2016
Q3C0006083 - 3/6
RESISTANCE TEMPERATURE DETECTOR (TE)
INSTRUMENT LIST
2 1 THERMOWELL
SERIAL Q' TY Q' TY OPERATING CABLE RTD PROCESS THERMOWELL REFERENCE
Larsen & Toubro Ltd.
TAG No. *1 SERVICE NAME TYPE OF TE ELEMENT PROCESS MAKER MODEL No. REMARKS
No. / PUMP UNIT / TOTAL TEMP. CONNECTION CONNECTION MATERIAL DWG. No.
1 CONNECTION
SF490A 41400-1002 Duplex
1 01HAG03CT034 BRP PUMP CASING TEMPERATURE 1 2 Pt 100 SHEATH 303.6 ℃ Plug in NPT1/2" G 1" / Welding YAMARI LS
/ SUS316 41400-1011 4-Wire
SF490A 41400-1002 Duplex
2 01HAG03CT035 BRP PUMP CASING TEMPERATURE 1 2 Pt 100 SHEATH 303.6 ℃ Plug in NPT1/2" G 1" / Welding YAMARI LS
/ SUS316 41400-1011 4-Wire
SF490A 41400-1002 Duplex
3 01HAG03CT036 BRP PUMP CASING TEMPERATURE 1 2 Pt 100 SHEATH 303.6 ℃ Plug in NPT1/2" G 1" / Welding YAMARI LS
/ SUS316 41400-1011 4-Wire
41400-1002 Duplex
4 01HAG03CT031 BRP MOTOR CAVITY TEMPERATURE 1 2 Pt 100 SHEATH 50 ℃ Plug in NPT1/2" G 1" / Welding SF490A YAMARI LS
41400-1011 4-Wire
41400-1002 Duplex
5 01HAG03CT032 BRP MOTOR CAVITY TEMPERATURE 1 2 Pt 100 SHEATH 50 ℃ Plug in NPT1/2" G 1" / Welding SF490A YAMARI LS
41400-1011 4-Wire
41400-1002 Duplex
6 01HAG03CT033 BRP MOTOR CAVITY TEMPERATURE 1 2 Pt 100 SHEATH 50 ℃ Plug in NPT1/2" G 1" / Welding SF490A YAMARI LS
41400-1011 4-Wire
9
POWER PROJECT
Instrument List
10
The first two digits of the tag No. (01) is to be replaced with 02 for Unit 2.
2 × 660 MW KHARGONE SUPER THERMAL
Q3C0006083 - 4/6
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1013
Date: 28/10/2016
Rev. No.: 5
THERMOMETER (TI)
INSTRUMENT LIST
Larsen & Toubro Ltd.
THERMOWELL
SERIAL Q' TY Q' TY OPERATING SCALE THERMOWELL TI PROCESS REFERENCE
TAG No. *1 SERVICE NAME PROCESS MAKER MODEL No. REMARKS
No. / PUMP UNIT / TOTAL TEMP. RANGE MATERIAL CONNECTION DWG. No.
1 CONNECTION
SF490A 41400-1002
1 01HAG03CT532 BRP PUMP CASING TEMPERATURE 1 2 303.6 ℃ 0~500 ℃ NPT3/4" G 1" / Welding WIKA F73.160 Dial type
/ SUS316 41400-1011
41400-1002
2 01HAG03CT531 BRP MOTOR CAVITY TEMPERATURE 1 2 50 ℃ 0~100 ℃ SF490A NPT3/4" G 1" / Welding WIKA F73.160 Dial type
41400-1011
4 3 BRP MOTOR COOLER
3 01PGA02CT542 1 2 43 ℃ 0~100 ℃ SUS316 NPT3/4" Rc 1" WIKA F73.160 41400-1011 Dial type
C.W. OUTLET TEMPERATURE
3 BRP HEAT BARRIER
4 01PGA02CT543 1 2 41 ℃ 0~100 ℃ SUS316 NPT3/4" Rc 1" WIKA F73.160 41400-1011 Dial type
C.W. OUTLET TEMPERATURE
4 3 BRP PURGE COOLER
5 01PGA02CT541 1 2 45 ℃ 0~100 ℃ SUS316 NPT3/4" Rc 1" WIKA F73.160 41400-1011 Dial type
C.W. OUTLET TEMPERATURE
8
POWER PROJECT
Instrument List
10
The first two digits of the tag No. (01) is to be replaced with 02 for Unit 2.
Q3C0006083 - 5/6
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1013
Date: 28/10/2016
Rev. No.: 5
FLOW SWITCH (FS)
INSTRUMENT LIST
5 PRESSURE
Larsen & Toubro Ltd.
SERIAL Q' TY Q' TY BODY SET No. OF SWITCH OPERATING DESIGN CABLE CONNECTION END REFERENCE
TAG No. *1 SERVICE NAME RATING MAKER MODEL No. REMARKS
No. / PUMP UNIT / TOTAL MATERIAL POINT CONTACT RATING PRESS. PRESS. CONNECTION SIZE DETAILS DWG. No.
1 DESIGNATION 1
FLAPPER TYPE
5A, 250VAC/
1 01PGA02CF201 BRP MOTOR COOLER C.W. FLOW RATE LOW 1 2 SUS316 8.1 m3/h 2XSPDT - 10 kg/cm2 g Plug in 2" RF CLASS 150 KAWAKI SF-MAA 41400-1011 Range:0~15㎥/h
0.28A, 220VDC Nor.:11.5㎥/h
FLAPPER TYPE
2 5A, 250VAC/
2 01PGA02CF203 BRP HEAT BARRIER C.W. FLOW RATE LOW 1 2 SUS316 2XSPDT - 10 kg/cm2 g Plug in 1" RF CLASS 150 KAWAKI SF-MAA 41400-1011 Range:0~4㎥/h
1.9 m3/h 0.28A, 220VDC Nor.:2.7㎥/h
FLAPPER TYPE
5A, 250VAC/
3 01PGA02CF202 BRP PURGE COOLER C.W. FLOW RATE LOW 1 2 SUS316 10.5 m3/h 2XSPDT - 10 kg/cm2 g Plug in 2" RF CLASS 150 KAWAKI SF-MAA 41400-1011 Range:0~20㎥/h
0.28A, 220VDC Nor.:15㎥/h
10
POWER PROJECT
Instrument List
1 *1: Tag No. indicated on the list are for Unit 1. RF:RAISED FACE (ASME B16.5-2009)
The first two digits of the tag No. (01) is to be replaced with 02 for Unit 2.
Q3C0006083 - 6/6
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1013
Date: 28/10/2016
Rev. No.: 5
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
0940015343 - 1/4 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Logic Diagram Doc. No.: 51006-41400-1014
Rev
Details / Description Date
No.
0 FIRST ISSUE 4/3/2016
1 REVISED 17/6/2016
0940015343 - 2/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Logic Diagram Doc. No.: 51006-41400-1014
0940015343 - 3/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Logic Diagram Doc. No.: 51006-41400-1014
0940015343 - 4/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q3C0006030 - 1/5 3
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1016
I/O List (BRP) Rev. No.: 3
Larsen & Toubro Ltd.
Date: 26/7/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 11/3/2016
1 REVISED 17/6/2016
2 REVISED 29/6/2016
3 REVISED 26/7/2016
Q3C0006030- 2/5
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1016
I/O List (BRP) Rev. No.: 3
Larsen & Toubro Ltd.
Date: 26/7/2016
Q3C0006030- 3/5
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1016
I/O List (BRP) Rev. No.: 3
Larsen & Toubro Ltd.
Date: 26/7/2016
COLUMN
DESCRIPTION
NUMBER
1 SERIAL NO. :This column shows a serial sequence of the field instruments.
2 TAG NO : Instrument identification number as per KKS numbering system
3 INST. TYPE : Detail description of field instrument type.
4 SERVICE NAME : Service description of each instrument.
5 FROM/TO : "FROM" means the signal source of the equipment or device and
"TO" means the signal destination of the equipment or device.
FLD : FIELD (or Local)
DCS : Distributed Control System (Out of Torishima scope)
6 UNIT : The measuring units in the list are shown as follows:
DI : Digital Input
8 SET POINT :
Q3C0006030- 4/5
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1016
I/O List (BRP) Rev. No.: 3
Larsen & Toubro Ltd.
Date: 26/7/2016
Q3C0006030- 5/5
c "THIS DRAWING IS THE PROPERTY OF AND CONTAINS CONFIDENTIAL PROPRIETARY INFORMATION OF L&T-MHPS BOILERS PRIVATE LIMITED AND SHALL UNLESS OTHERWISE STATED ALL DIMENSIONS ARE
NOT BE REPRODUCED, USED, DISCLOSED OR TRANSMITTED IN WHOLE OR IN PART UNLESS AUTHORISED IN WRITING BY L&T-MHPS BOILERS PRIVATE LIMITED" IN MILLIMETRES. DO NOT SCALE. IF IN DOUBT, ASK.
A
B
E
C
D
8
8
7
7
6
6
5
5
4
4
3
3
2
2
1
1
A
B
E
C
D
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
0920016017 - 1/4 3
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1020
Detailed Drawing of Motor Cooler Rev. No.: 3
Larsen & Toubro Ltd.
Date: 23/9/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 27/4/2016
0920016017 - 2/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1020
Detailed Drawing of Motor Cooler Rev. No.: 3
Larsen & Toubro Ltd.
Date: 23/9/2016
0920016017 - 3/4
0920016017 - 4/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
0930016256 - 1/5 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1021
Detailed Drawing of Purge Cooler Rev. No.: 1
Larsen & Toubro Ltd.
Date: 19/8/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE (COOLER MAKER REV.2) 20/5/2016
0930016256 - 2/5
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1021
Detailed Drawing of Purge Cooler Rev. No.: 1
Larsen & Toubro Ltd.
Date: 19/8/2016
0930016256 - 3/5
0930016256-4/5
0930016256-5/5
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
0940016705 - 1/4 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1022
Detailed Drawing of Strainer Rev. No.: 1
Larsen & Toubro Ltd.
Date: 15/7/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 15/6/2016
1 REVISED 15/7/2016
0940016705-2/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1022
Detailed Drawing of Strainer Rev. No.: 1
Larsen & Toubro Ltd.
Date: 15/7/2016
0940016705-3/4
0940016705 - 4/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
0940016794 - 1/10 2
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1023
Detailed Drawing of Valves Rev. No.: 2
Larsen & Toubro Ltd.
Date: 13/10/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 17/6/2016
1 REVISED 15/7/2016
2 REVISED 13/10/2016
0940016794 - 2/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1023
Detailed Drawing of Valves Rev. No.: 2
Larsen & Toubro Ltd.
Date: 13/10/2016
0940016794 - 3/10
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1023
Detailed Drawing of Valves Rev. No.: 2
Larsen & Toubro Ltd.
Date: 13/10/2016
CONTENTS
0940016794 - 4/10
Tag No.
01HAG03AA918, 02HAG03AA918
01HAG03AA919, 02HAG03AA919
01HAG03AA932, 02HAG03AA932
01HAG03AA910, 02HAG03AA910
Tag No.
01HAG03AA916, 01HAG03AA917
02HAG03AA916, 02HAG03AA917
0940016794 - 6/10
2
P&ID No. 1
Tag No. 2 01HAG03AA102/02HAG03AA102
CALCULATION
Service Line 3 SHELL
L * Calculation of Area
A Number Required 4 2
R
E Nozzle Type, Full or Semi 5 Full Nozzle A1 = 11.78*W1*(√
N G/(1.25P-Pb))/(Kd*Kb*Kc*Kv*Kp)
E Design Type 6
G
A.Conventional or Bellows Conventional = 11.78 *191.667 * (√1 / ( 1.25 *980 -0)) /
B.Full Bore, Low or High Lift Full Bore Type (0.62 *1 *1 *1 *0.6)
Bonnet Type. Open or Close 7 Close
N
O
I Size. Inlet / Outlet 8 1"X2"
T
C = 173.41 ㎟
E
N Inlet. Rating / Facing 9 ANSI 150LB RF
N
O
C Outlet. Rating / Facing 10 ANSI 150LB RF
Body 11 A351 CF8 * Calculation of Capacity
S Bonnet 12 A351 CF8 W = A*Kd*Kb*Kc*Kv*Kp/(11.78*√
L
A Seat 13 A351 CF8-st. (G/(1.25P-Pb)))
I
R Disc 14 A276 304-st.
E = 283.529 *0.62 *1 *1 *1 *0.6 / ( 11.78 * √(1
T Guide 15 A351 CF8 / ( 1.25 *980 -0)))
A Gasket 16 PTFE
M
Spring 17 SWOSC
Bellows 18 = 313.4 ℓ/min
Y 19 Screwed
R Cap. Type 18.8 m3/h
O
S Lever. Plain or Packed 20 None Lever
S
E 21
C Test Gag No
C
A Paint Color 22 None
C
I Code 23 API RP 520 W = Valve Capacity ........................ 313.40 ℓ/min
S Fire 24 No
A W1 = Required Capacity .................. 191.67 ℓ/min
B Sizing Basis 25 NA P = Set Pressure ............................. 980 KPag
Fluid and State 26 COOLING WATER(L)
A1 = Calculated Area ....................... 173.41 ㎟
Required Capacity 27 11.5 m3/h
Mol. Weight or Specific Gravity 28 1 A = Selected Area .......................... 283.529 ㎟
Viscosity 29 Kd = Coefficient of Discharge ........ 0.62
Operating / Set Pressure 30 10 Kgf/㎠g G = Specific Gravity
E Operating / Blowout Temp 31 37.6 / 40.6 ℃ ................................................. 1.000
C
I Constant Back Pressure 32 Kgf/㎠g
V Pb = Back Pressure............................... 0 KPag
R
Variable Back Pressure 33 Kgf/㎠g
E Built-up Back Pressure 34 Kgf/㎠g Kb = Correction Factor Due to Back Pressure 1
S
Total Back Pressure 35 0 Kgf/㎠g Kc = Correction Factor for a rupture disk 1
Closing Pressure 36 Min. 0 Kgf/㎠g Kv = Correction Factor due to Viscosity.......... 1
Hydrostatic Test 37 15 Kgf/㎠g
Kp = Correction Factor due to Overpressure... 0.6
Allowable Overpressure 38 10 %
Compressibility Factor 39 Remark
Ratio of Specific Heat 40 *Required capacity : 191.67 L/min
*CDTP : 10 Kgf/㎠g
E Calculated Area 41 173.41 ㎟
C
I Selected Area 42 283.529 ㎟
F Orifice Dia.(mm) 43 F(19)
I
R Valve Capacity 44 18.8 m3/h
O
Model No. 45 JSV-FF21
Cert. Approved by 46 /
0
0
0
0
0 4
MODEL JSV-FF21
DIMENSION UNIT : mm
INLET FLANGE ASME B 16.5 CL150 RF OUTLET FLANGE ASME B 16.5 CL150 RF Wt(kg) DATE 2016-07-11 J.Y.LIM Y.S.KIM J.K.KIM
SIZE d d1 dt L H1 H FULL BORE TYPE SAFETY RELIEF VALVE REV
D g k c T f N-H D1 g1 c1 T1 f1 n-h
12.45
1xFx2 25 50 19 103 104 338 108 51 - 79.5 22 7 4-16 152 92 120.5 19.1 1.6 4-19 JOKWANG I.L.I CO.,LTD. 4
2
P&ID No. 1
Tag No. 2 01HAG03AA101/02HAG03AA101
CALCULATION
Service Line 3 SHELL
L * Calculation of Area
A Number Required 4 2
R
E Nozzle Type, Full or Semi 5 Full Nozzle A1 = 11.78*W1*(√
N G/(1.25P-Pb))/(Kd*Kb*Kc*Kv*Kp)
E Design Type 6
G
A.Conventional or Bellows Conventional = 11.78 *250 * (√1 / ( 1.25 *980 -0)) / (0.62
B.Full Bore, Low or High Lift Full Bore Type *1 *1 *1 *0.6)
Bonnet Type. Open or Close 7 Close
N
O
I Size. Inlet / Outlet 8 1"X2"
T
C = 226.19 ㎟
E
N Inlet. Rating / Facing 9 ANSI 150LB RF
N
O
C Outlet. Rating / Facing 10 ANSI 150LB RF
Body 11 A351 CF8 * Calculation of Capacity
S Bonnet 12 A351 CF8 W = A*Kd*Kb*Kc*Kv*Kp/(11.78*√
L
A Seat 13 A351 CF8-st. (G/(1.25P-Pb)))
I
R Disc 14 A276 304-st.
E = 283.529 *0.62 *1 *1 *1 *0.6 / ( 11.78 * √(1
T Guide 15 A351 CF8 / ( 1.25 *980 -0)))
A Gasket 16 PTFE
M
Spring 17 SWOSC
Bellows 18 = 313.4 ℓ/min
Y 19 Screwed
R Cap. Type 18.8 m3/h
O
S Lever. Plain or Packed 20 None Lever
S
E 21
C Test Gag No
C
A Paint Color 22 None
C
I Code 23 API RP 520 W = Valve Capacity ........................ 313.40 ℓ/min
S Fire 24 No
A W1 = Required Capacity .................. 250.00 ℓ/min
B Sizing Basis 25 NA P = Set Pressure ............................. 980 KPag
Fluid and State 26 COOLING WATER(L)
A1 = Calculated Area ....................... 226.19 ㎟
Required Capacity 27 15 m3/h
Mol. Weight or Specific Gravity 28 1 A = Selected Area .......................... 283.529 ㎟
Viscosity 29 Kd = Coefficient of Discharge ........ 0.62
Operating / Set Pressure 30 10 Kgf/㎠g G = Specific Gravity
E Operating / Blowout Temp 31 37.6 / 43.6 ℃ ................................................. 1.000
C
I Constant Back Pressure 32 Kgf/㎠g
V Pb = Back Pressure............................... 0 KPag
R
Variable Back Pressure 33 Kgf/㎠g
E Built-up Back Pressure 34 Kgf/㎠g Kb = Correction Factor Due to Back Pressure 1
S
Total Back Pressure 35 0 Kgf/㎠g Kc = Correction Factor for a rupture disk 1
Closing Pressure 36 Min. 0 Kgf/㎠g Kv = Correction Factor due to Viscosity.......... 1
Hydrostatic Test 37 15 Kgf/㎠g
Kp = Correction Factor due to Overpressure... 0.6
Allowable Overpressure 38 10 %
Compressibility Factor 39 Remark
Ratio of Specific Heat 40 *Required capacity : 250 L/min
*CDTP : 10 Kgf/㎠g
E Calculated Area 41 226.19 ㎟
C
I Selected Area 42 283.529 ㎟
F Orifice Dia.(mm) 43 F(19)
I
R Valve Capacity 44 18.8 m3/h
O
Model No. 45 JSV-FF21
Cert. Approved by 46 /
0
0
0
0
0 4
MODEL JSV-FF21
DIMENSION UNIT : mm
INLET FLANGE ASME B 16.5 CL150 RF OUTLET FLANGE ASME B 16.5 CL150 RF DATE 2016-07-11 J.Y.LIM Y.S.KIM J.K.KIM
Wt(kg)
SIZE d d1 dt L H1 H FULL BORE TYPE SAFETY RELIEF VALVE REV
D g k c T f N-H D1 g1 c1 T1 f1 n-h
12.45
1xFx2 25 50 19 103 104 338 108 51 - 79.5 22 7 4-16 152 92 120.5 19.1 1.6 4-19 JOKWANG I.L.I CO.,LTD. 4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q3C0006598 - 1/5 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Detailed Drawing of Doc. No.: 51006-41400-1024
Rev
Details / Description Date
No.
0 FIRST ISSUE 17/6/2016
1 REVISED 9/9/2016
Q3C0006598 - 2/5
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Detailed Drawing of Doc. No.: 51006-41400-1024
Q3C0006598 - 3/5
Item No. Name of Parts Sketch Size Material ( Eq. ASTM Mat. ) Weight [kg] Remarks
L W H Approx.
ROTOR SET
Larsen & Toubro Ltd.
SCS1-T2
3 IMPELLER (2300) 334 φ630 - 100
( A743 Gr. CA15 )
POWER PROJECT
Detailed Drawing of
Major Pump Components
2 × 660 MW KHARGONE SUPER THERMAL
*1:The detail are given in Sectional Drawing of Pump / Motor ( 41400-1018) and Main Terminal Box ( 41400-1019).
Q3C0006598 - 4/5
L&T-MHPS BOILERS PRIVATE LIMITED
Date: 9/9/2016
Rev. No.: 1
Item No. Name of Parts Sketch Size Material ( Eq. ASTM Mat. ) Weight [kg] Remarks
L W H Approx. Larsen & Toubro Ltd.
SF490A
5 THRUST BEARING CASE (3540) 411 φ800 - 1155
(A266 Gr.2)
*1:The detail are given in Sectional Drawing of Pump / Motor ( 41400-1018) and Main Terminal Box ( 41400-1019).
Q3C0006598 - 5/5
L&T-MHPS BOILERS PRIVATE LIMITED
Date: 9/9/2016
Rev. No.: 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
0940016810 - 1/25 2
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Drawing & Data sheets Doc. No.: 51006-41400-1025
Rev
Details / Description Date
No.
0 FIRST ISSUE 17/6/2016
1 REVISED 6/7/2016
2 REVISED 5/8/2016
0940016810 - 2/25
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Drawing & Data sheets Doc. No.: 51006-41400-1025
0940016810 - 3/25
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Drawing & Data sheets Doc. No.: 51006-41400-1025
CONTENTS
0940016810 - 4/25
0940016810 - 5 / 25
0940016810 - 6 / 25
0940016810 - 7 / 25
0940016810 - 8 / 25
0940016810 - 9 / 25
0940016810 - 10 / 25
0940016810 - 11 / 25
0940016810 - 12 / 25
0940016810 - 13 / 25
0940016810 - 14 / 25
0940016810 - 15 / 25
0940016810 - 16 / 25
0940016810 - 17 / 25
0940016810 - 18 / 25
0940016810 - 19 / 25
0940016810 - 20 / 25
0940016810 - 21 / 25
0940016810 - 22 / 25
0940016810 - 23 / 25
0940016810 - 24 / 25
0940016810 - 25 / 25
"THIS DRAWING IS THE PROPERTY OF AND CONTAINS CONFIDENTIAL PROPRIETARY INFORMATION OF L&T-MHPS BOILERS PRIVATE LIMITED AND SHALL UNLESS OTHERWISE STATED ALL DIMENSIONS ARE
NOT BE REPRODUCED, USED, DISCLOSED OR TRANSMITTED IN WHOLE OR IN PART UNLESS AUTHORISED IN WRITING BY L&T-MHPS BOILERS PRIVATE LIMITED" IN MILLIMETRES. DO NOT SCALE. IF IN DOUBT, ASK.
"THIS DRAWING IS THE PROPERTY OF AND CONTAINS CONFIDENTIAL PROPRIETARY INFORMATION OF L&T-MHPS BOILERS PRIVATE LIMITED AND SHALL UNLESS OTHERWISE STATED ALL DIMENSIONS ARE
NOT BE REPRODUCED, USED, DISCLOSED OR TRANSMITTED IN WHOLE OR IN PART UNLESS AUTHORISED IN WRITING BY L&T-MHPS BOILERS PRIVATE LIMITED" IN MILLIMETRES. DO NOT SCALE. IF IN DOUBT, ASK.
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
0930016642 - 1/7 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Detail drawing of Doc. No.: 51006-41400-1033
Larsen & Toubro Ltd. Bolt heater & Switch box Rev. No.: 1
Date: 29/9/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 9/6/2016
1 REVISED 29/9/2016
0930016642 - 2/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Detail drawing of Doc. No.: 51006-41400-1033
Larsen & Toubro Ltd. Bolt heater & Switch box Rev. No.: 1
Date: 29/9/2016
0930016642 - 3/7
0930016642-4/7
0930016642-5/7
0930016642-6/7
0930016642-7/7
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
G5C0003366 - 1/28 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 21/6/2016
1 REVISED 9/9/2016
G5C0003366 - 2/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
G5C0003366 - 3/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
Contents
0. General ・・・・5/28
G5C0003366 - 4/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
General
● In order to ensure trouble-free operation of the pumpset, it shall be carefully installed
according to the instructions contained herein.
Before installation of the pumpset, read this manual and all and related documents to fully
understand the contents.
● Modifications or alterations of the equipment supplied shall not be made without prior
permission from the manufacturer. Original spare parts and accessories authorized by
the manufacturer ensure safety. The use of third party parts invalidates any liability of
the manufacturer for the damage caused.
● During the validity period of guarantee by Torishima, NO dismantling of the pump or its
individual components shall be carried out without obtaining Torishima’s consent in this
respect.
● The pump name plate indicates pump type, main operating data, production No. and unit No.
Please quote this information in all queries.
G5C0003366 - 5/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
Safety precautions
This manual contains fundamental information and instructions that must be complied with during.
the erection of the pumpset.
Non-compliance with the instructions contained herein can cause injury of operator, failure of unit
functioning and damage to the pumpset. Therefore, this manual must be read and understood
prior to the installation.
Qualification of Staff
The safety instructions and warning notes contained in this manual are marked by symbols as follows.
SYMBOL DESCRIPTION
Informational notes
● When lifting equipment or component using lifting device, check the center of gravity first and
apply appropriate arrangement of lifting tackle to prevent accidental drop of the goods.
● When moving heavy equipments or components, hang wire ropes to the positions as shown
in the instruction manual and use a chain block, etc.
● Never touch the Bolt heaters, Stud Bolts or other components of pump while is hot.
G5C0003366 - 6/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
1.Handling Instruction
1.1 Description of Major Component
Refer to the following documents for the detailed description of the pumpset.
TITLE DRAWING NO.
GA Drawing 41400-1002
P&I Diagram 41400-1011
Sectional Drawing of Pump Motor 41400-1018
Sectional Drawing of Main Terminal Box 41400-1019
Detailed Drawing of Motor Cooler 41400-1020
Special Tool List 41400-1051
O&M Manual 41400-1050
When it becomes necessary to store the equipment for a short time before erection, place the
pumpset in a dry location, protected from the elements if possible, where it cannot be affected
by ingress of moisture.
It is important that bearings, pipings, etc. are suitably protected against ingress of insects, grit
dust or other foreign matter.
In addition to the measure described for temporary storage, the following should be applied.
Check the condition of the painted surfaces every three months. If corrosion is observed, remove
it and apply a coat of paint again.
Check the condition of anti-corrosive coating on blank metal surfaces (e.g. screw of bolts) every
three months. If any corrosion is observed, remove it with a fine emery cloth and perform
the anti-corrosive treatment again.
In order to prevent the inside of motor from rusting, N2 gas should be filled in Motor every 2-3
month.
Refer to Operation and Maintenance manual - item 3.2.2 : Dry Preservation about detail procedure
for N2 gas filling.
G5C0003366 - 7/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
● When receive unit, inspect it that there are neither discrepancy from your requested
specifications nor damages during transportation. This unit is shipped after our inspection
is done under QA systems.
● Care must be taken in handing and installing equipment, particularly in protecting Rotor
extensions, machined faces, electric cables, instrumentation, small bore pipework and
ancillary parts. Use soft padding material as necessary to protect the equipments from
damage by lifting tackles.
Move equipments slowly when placing on the floor.
● Do not place equipments directly on the ground. Use protecting material like wooden block.
● Pay due attention to prevent the rusting of the goods before pump operation.
● Do not remove the desiccant (Silica-gel) in the terminal box in order to protect the terminal
box from the moisture.
G5C0003366 - 8/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
2.Delivery Condition
( Main components)
MOTOR SET
approx. 12000 kg 1
PUMP CASING
approx. 7600 kg 1
MOTOR COOLER
approx. 295 kg 1
G5C0003366 - 9/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
3.2 Misalignment
G5C0003366 - 10/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
G5C0003366 - 11/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
Bolts number
1 to 20
G5C0003366 - 12/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
Measuring point
① Bolt 3- 4
② Bolt 8- 9
③ Bolt 13-14
④ Bolt 18-19
G5C0003366 - 13/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
G5C0003366 - 14/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
G5C0003366 - 15/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
360
24
15
G5C0003366 - 16/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
G5C0003366 - 17/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
G5C0003366 - 18/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
Group No.1:●
(positionN0.:1, 3, 5, 7, 9, 11, 13, 15, 17, 19)
Group No.2:○
(positionN0.:2, 4, 6, 8, 10, 12, 14, 16, 18, 20)
G5C0003366 - 19/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
Nut Scale
(9) Switch off all bolt heaters and let the stud
bolts cool down to approx.60℃.
( Group No.1 Stud bolts)
Nut Scale
G5C0003366 - 20/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
(13) Switch on the Group No.1 bolt heaters. Group No.1 Stud bolts
G5C0003366 - 21/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
① 2" : 46 to 57
② 1" : 31 to 38
③- : 62 to 77
① : ASME2500 RJ 2”
BOLT SIZE : 1-8UNCx180
NUT SIZE : 1-8UNC
GASKET :R26OCTAGONAL
② : ASME2500 RJ 1”
BOLT SIZE : 7/8-9UNC X 130
NUT SIZE : 7/8-9UNC
GASKET : R18 OCTAGONAL
③:-
BOLT SIZE : 1.1/8-8UNC X 140
NUT SIZE : 1.1/8-8UNC
GASKET : φ5-ID100
G5C0003366 - 22/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
① : ASME150 RF 2”
BOLT SIZE : 5/8-11UNC
NUT SIZE : 5/8-11UNC
② : ASME150 RF 1”
BOLT SIZE : 1/2-13UNC
NUT SIZE : 1/2-13UNC
G5C0003366 - 23/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
② BW 1”
①, ③ : ASME150 RF 2”
BOLT SIZE : 5/8-11UNC
NUT SIZE : 5/8-11UNC
④, ⑤ : ASME150 RF 1”
BOLT SIZE : 1/2-13UNC
NUT SIZE : 1/2-13UNC
G5C0003366 - 24/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
(1) Drainage
( Procedure:refer to O&M manual item4.2 )
G5C0003366 - 25/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
G5C0003366 - 26/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
G5C0003366 - 27/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1041
Lifting Plan Drawing Rev. No.: 1
Larsen & Toubro Ltd.
Date: 9/9/2016
精度
又はデジタルデプス)
Bolt No.
by Inside Micrometer
Measure by Digital Depth Gauge
or Digital Depth Gauge View from Suction End
図面寸法 (scale:1/100mm) (scale:1/100mm) 吸込裏側 から見て
Nominal for reference
(140) (460)
No. 参考測定 For reference
ガスケット厚 取付溝
Thickness of Gasket Depth of Groove
(4.5 +0.2
0 ) (3.05 +0.05
0 )
平均:Average 計測位置
締付起点の計算(平均値使用)
Initial Starting Distance
A = C - B + 1.6 = ±0.1(mm)
( 測定値A - 計算値A ≦ ±0.1 [mm] )
Measured A Calculated A 計測位置 (Measure points)
A(締付前) A'(締付後)
寸法、位置、 A-A'
before tightening last tightening 締付前 (before tightening)
精度
内マイクロメータ 内マイクロメータ
Measure by inside micrometer by inside micrometer
計算値
Calculate
Bolt No. (scale:1/100mm) (scale:1/100mm)
締付後
備考 (1) B,C,A & A'各点は4ヶ所それぞれ等分位置とする。 (Measurement after last tightening)
Remark: The component dimensions (B, C ,A & A') should
be measured at 4 circumferentially distributed
points.
(2) A,B,C各点の測定寸法の各々のバラツキは0.05mm
以内とする。
Each point of B, C & Measured A shall have a
dispersion value of within 0.05mm.
(3) +2
SKT : 25
0
(4) ねじピッチ(Thread pitch) : 3
(5) A-A'の4点のバラツキは0.1mm以内とする。
A-A'shall have a dispersion value of within 0.1mm.
(6) 1度潰したガスケットを再使用すると完全なシール力が
発揮できません。
When the gasket crushed once was reused,
complete seal power will not be performed.
Signature
Name
Data
G5C0003366 - 28/28
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q3C0006688 - 1/6 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1058
Special Tool List Rev. No.: 1
Larsen & Toubro Ltd. Date: 14/12/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 1/7/2016
1 REVISED 14/12/2016
Q3C0006688- 2/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1058
Special Tool List Rev. No.: 1
Larsen & Toubro Ltd. Date: 14/12/2016
Q3C0006688- 3/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1058
Special Tool List Rev. No.: 1
Larsen & Toubro Ltd. Date: 14/12/2016
Item Size
Name of Parts Sketch Material Q'ty Remarks
No. L W H
BOLT
1 850 OD15 - SUS321 22 FOR MAIN STUD 9020.1
HEATER
SWITCH
2 600 250 600 SPCC 1 do.
BOX
Q3C0006688- 4/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1058
Special Tool List Rev. No.: 1
Larsen & Toubro Ltd. Date: 14/12/2016
Item Size
Name of Parts Sketch Material Q'ty Remarks
No. L W H
WITHDRAWING TOOL
FOR IMPELLER
12 PLATE 27 OD75 - S45C 1
ANDTHRUST
BEARING PLATE
JACKING
14 200 M20 - SS400 1 do.
BOLT
SOCKET
15 HEAD CAP 35 M10 - SCM435 2 do.
SCREW
WITHDRAWING TOOL
FOR
16 PLATE T6 OD525 - SS400 1
THRUST BEARING
PLATE
Q3C0006688- 5/6
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
Doc. No.: 51006-41400-1058
Special Tool List Rev. No.: 1
Larsen & Toubro Ltd. Date: 14/12/2016
Item Size
Name of Parts Sketch Material Q'ty Remarks
No. L W H
WITHDRAWING TOOL
FOR
17 BOLT 300 M16 - SS400 2
THRUST BEARING
PLATE
FOR COVER.
DON’T THROW AWAY
22 HEX. NUT 13 M16 - SS400 72 NUTS, BECAUSE NUTS
WERE DISPATCHED
WITH THE MOTOR.
Q3C0006688- 6/6
c "THIS DRAWING IS THE PROPERTY OF AND CONTAINS CONFIDENTIAL PROPRIETARY INFORMATION OF L&T-MHPS BOILERS PRIVATE LIMITED AND SHALL UNLESS OTHERWISE STATED ALL DIMENSIONS ARE
NOT BE REPRODUCED, USED, DISCLOSED OR TRANSMITTED IN WHOLE OR IN PART UNLESS AUTHORISED IN WRITING BY L&T-MHPS BOILERS PRIVATE LIMITED" IN MILLIMETRES. DO NOT SCALE. IF IN DOUBT, ASK.
A
B
E
C
D
8
8
7
7
6
6
5
5
4
4
3
3
L&T
2
2
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
1
1
A
B
E
C
D
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q3C0006686 - 1/4 1
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1054
Spare Parts List (Commissioning) Rev. No.: 1
Larsen & Toubro Ltd.
Date: 23/9/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 1/7/2016
1 REVISED 23/9/2016
Q3C0006686 - 2/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1054
Spare Parts List (Commissioning) Rev. No.: 1
Larsen & Toubro Ltd.
Date: 23/9/2016
Q3C0006686 - 3/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1054
Spare Parts List (Commissioning) Rev. No.: 1
Larsen & Toubro Ltd.
Date: 23/9/2016
Size Q'ty
Additional
Unit 1
Unit 2
Item No. Name of Parts Sketch Material Remarks
L W H
1
1 1 1
SUS304/
1 GASKET OD793.4 ID741.6 4.5 1 1 2 P/N.4113
GRAFOIL
1 1
2 O-RING - ID100 5 NBR 1 1 P/N.4120.5
FOR HP COOLING
RING JOINT
1 1 WATER COOLER INLET
3 OD112.71 ID90.49 15.88 SUS304L 2 2 & OUTLET FLANGE
GASKET
ASME 2500LB
R26
RJ 2''
Q3C0006686 - 4/4
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
Owner:
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
EPC Contractor:
LARSEN & TOUBRO LIMITED
Architect Engineer:
L&T – SARGENT & LUNDY LIMITED
Vendor:
Sub Vendor:
Q3C0006689 - 1/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1053
51006-41400-1055
Spare Parts List(Recommended) Rev. No.: 0
Larsen & Toubro Ltd.
Date: 8/7/2016
Rev
Details / Description Date
No.
0 FIRST ISSUE 8/7/2016
Q3C0006689 - 2/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1053
51006-41400-1055
Spare Parts List(Recommended) Rev. No.: 0
Larsen & Toubro Ltd.
Date: 8/7/2016
Q3C0006689 - 3/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1053
51006-41400-1055
Spare Parts List(Recommended) Rev. No.: 0
Larsen & Toubro Ltd.
Date: 8/7/2016
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻼㻸㻭㻵㻺
㻲㻯㻞㻡㻜㻛 㻼㻛㻺㻚㻟㻝㻜㻜㻚㻝
㻝 㻮㻱㻭㻾㻵㻺㻳 㻞㻞㻡 㻵㻰㻝㻡㻜 㻻㻰㻟㻝㻜 㻝
㻲㻾㻼 㻔㼁㻼㻼㻱㻾㻕
㻯㻻㻹㻼㻸㻚 㻿㻱㼀
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻼㻸㻭㻵㻺
㻲㻯㻞㻡㻜㻛 㻼㻛㻺㻚㻟㻝㻜㻜㻚㻞
㻞 㻮㻱㻭㻾㻵㻺㻳 㻞㻞㻡 㻵㻰㻝㻡㻜 㻻㻰㻞㻣㻤 㻝
㻲㻾㻼 㻔㻸㻻㼃㻱㻾㻕
㻯㻻㻹㻼㻸㻚 㻿㻱㼀
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㼀㻴㻾㼁㻿㼀
㻿㼁㻿㻠㻞㻜㻶㻞
㻟 㻮㻱㻭㻾㻵㻺㻳 㻞㻟㻜 㻻㻰㻝㻞㻡 㻻㻰㻟㻝㻜 㻴㻯㼞㻌㻼㻚
㻝 㻼㻛㻺㻚㻟㻤㻠㻜
㻼㻸㻭㼀㻱
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㼀㻴㻾㼁㻿㼀
㻼㻛㻺㻚㻟㻤㻣㻜㻚㻝
㻠 㻮㻱㻭㻾㻵㻺㻳 㻞㻜 㻵㻰㻝㻢㻜 㻻㻰㻟㻝㻡 㻲㻾㻼 㻝
㻔㼁㻼㻼㻱㻾㻕
㻿㻱㻳㻹㻱㻺㼀 㻿㻱㼀
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㼀㻴㻾㼁㻿㼀
㻼㻛㻺㻚㻟㻤㻣㻜㻚㻞
㻡 㻮㻱㻭㻾㻵㻺㻳 㻞㻜 㻵㻰㻝㻢㻜 㻻㻰㻟㻝㻡 㻲㻾㻼 㻝
㻔㻸㻻㼃㻱㻾㻕
㻿㻱㻳㻹㻱㻺㼀 㻿㻱㼀
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻿㼁㻿㻟㻜㻠㻛
㻢 㻳㻭㻿㻷㻱㼀 㻻㻰㻣㻥㻟㻚㻠 㻵㻰㻣㻠㻝㻚㻢 㻠㻚㻡 㻝 㻼㻛㻺㻚㻠㻝㻝㻟
㻳㻾㻭㻲㻻㻵㻸
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
Q3C0006689 - 4/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1053
51006-41400-1055
Spare Parts List(Recommended) Rev. No.: 0
Larsen & Toubro Ltd.
Date: 8/7/2016
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻝㻝 㻻㻙㻾㻵㻺㻳 㻙 㻵㻰㻝㻜㻜 㻡 㻺㻮㻾 㻝 㻼㻛㻺㻚㻠㻝㻞㻜㻚㻢
㻼㻛㻺㻚㻡㻜㻞㻜㻚㻝
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻯㻭㻿㻵㻺㻳 㼣㼕㼠㼔㻌㻸㻻㻯㻷㻌㻿㻸㻱㻱㼂㻱㻿㻘
㻌㻌㻌㻿㻻㻯㻷㻱㼀㻌㻴㻱㻭㻰㻌㻯㻭㻼
㻝㻞 㼃㻱㻭㻾㻵㻺㻳 㻻㻰㻠㻝㻜 㻵㻰㻟㻠㻜 㻢㻡 㻿㼁㻿㻠㻞㻜㻶㻞 㻝 㻿㻯㻾㻱㼃㻿㻌㼍㼚㼐㻌㼃㻭㻿㻴㻱㻾㻿
㻾㻵㻺㻳 㻿㻱㼀 㻌㻝㻞㻌㼜㼏㼟㻛㼟㼑㼠㻌㽢㻝㼟㼑㼠
㻔㻼㻛㻺㻚㻌㻥㻟㻝㻣㻚㻝㻘㻌㻥㻝㻠㻜㻚㻞㻘㻌㻡㻡㻜㻜㻚㻠㻕
㻼㻛㻺㻚㻡㻜㻞㻜㻚㻞
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻯㻭㻿㻵㻺㻳 㼣㼕㼠㼔㻌㻸㻻㻯㻷㻌㻿㻸㻱㻱㼂㻱㻿㻘
㻌㻌㻌㻿㻻㻯㻷㻱㼀㻌㻴㻱㻭㻰㻌㻯㻭㻼
㻝㻟 㼃㻱㻭㻾㻵㻺㻳 㻻㻰㻠㻝㻜 㻵㻰㻟㻠㻜 㻟㻡 㻿㼁㻿㻠㻞㻜㻶㻞 㻝 㻿㻯㻾㻱㼃㻿㻌㼍㼚㼐㻌㼃㻭㻿㻴㻱㻾㻿
㻾㻵㻺㻳 㻿㻱㼀 㻌㻤㻌㼜㼏㼟㻛㼟㼑㼠㻌㽢㻝㼟㼑㼠
㻔㻼㻛㻺㻚㻌㻥㻟㻝㻣㻚㻟㻘㻌㻥㻝㻠㻜㻚㻝㻞㻘㻌㻡㻡㻜㻜㻚㻢㻕
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻮㻱㻭㻾㻵㻺㻳 㻿㼁㻿㻠㻞㻜㻶㻞 㻼㻛㻺㻚㻡㻞㻥㻜㻚㻝
㻝㻠 㻞㻠㻡 㻵㻰㻝㻞㻡 㻻㻰㻝㻡㻜 㻴㻯㼞㻌㻼㻚
㻝
㻿㻸㻱㻱㼂㻱 㻔㼁㻼㻼㻱㻾㻕
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻮㻱㻭㻾㻵㻺㻳 㻿㼁㻿㻠㻞㻜㻶㻞 㻼㻛㻺㻚㻡㻞㻥㻜㻚㻞
㻝㻡 㻞㻠㻡 㻵㻰㻝㻞㻡 㻻㻰㻝㻡㻜 㻴㻯㼞㻌㻼㻚
㻝
㻿㻸㻱㻱㼂㻱 㻔㻸㻻㼃㻱㻾㻕
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻿㼁㻿㻟㻜㻠
㻝㻢 㻯㻵㻾㻯㻸㻵㻼 㻙 㻵㻰㻝㻝㻤 㻝㻟㻥㻚㻤 㻞 㻼㻛㻺㻚㻥㻟㻞㻜㻚㻝
㻯㻿㻼
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻿㻼㻾㻵㻺㻳
㻝㻣 㻻㻰㻞㻠㻚㻠 㻵㻰㻝㻣 㻙 㻿㼃㻾㻴 㻤 㻼㻛㻺㻚㻥㻟㻜㻜㻚㻠
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻿㻼㻾㻵㻺㻳
㻝㻤 㻻㻰㻝㻢 㻵㻰㻝㻜㻚㻣 㻙 㻿㼃㻾㻴 㻝㻢 㻼㻛㻺㻚㻥㻟㻜㻜㻚㻡
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻿㻼㻾㻵㻺㻳
㻝㻥 㻻㻰㻝㻢 㻵㻰㻝㻜㻚㻣 㻙 㻿㼃㻾㻴 㻢 㻼㻛㻺㻚㻥㻟㻜㻜㻚㻢
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻿㻼㻾㻵㻺㻳
㻞㻜 㻻㻰㻞㻤 㻵㻰㻝㻢㻚㻞 㻙 㻿㼃㻾㻴 㻞㻜 㻼㻛㻺㻚㻥㻟㻜㻜㻚㻣
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻸㻻㻯㻷
㻞㻝 㻻㻰㻢㻟 㻵㻰㻟㻝 㻙 㻿㼁㻿㻟㻜㻠 㻝 㻼㻛㻺㻚㻥㻟㻝㻝㻚㻝
㼃㻭㻿㻴㻱㻾
Q3C0006689 - 5/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1055
51006-41400-1053
Spare Parts List(Recommended) Rev. No.: 0
Larsen & Toubro Ltd.
Date: 8/7/2016
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻸㻻㻯㻷
㻞㻞 㻻㻰㻢㻟 㻵㻰㻟㻝 㻙 㻿㼁㻿㻟㻜㻠 㻝 㻼㻛㻺㻚㻥㻟㻝㻝㻚㻞
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻸㻻㻯㻷
㻞㻟 㻞㻤 㻵㻰㻝㻟 㻟㻜 㻿㼁㻿㻟㻜㻠 㻤 㻼㻛㻺㻚㻥㻟㻝㻝㻚㻢
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻸㻻㻯㻷
㻞㻠 㻞㻤 㻵㻰㻝㻟 㻟㻜 㻿㼁㻿㻟㻜㻠 㻤 㻼㻛㻺㻚㻥㻟㻝㻝㻚㻣
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻞㻟㻠
㻸㻻㻯㻷
㻞㻡 㻞㻜 㻵㻰㻤㻚㻠 㻞㻞 㻿㼁㻿㻟㻜㻠 㻝 㻼㻛㻺㻚㻥㻟㻝㻝㻚㻤
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻞㻢 㻳㻭㻿㻷㻱㼀 㻤㻝㻜 㻙 㻟㻟㻜 㻺㻮㻾 㻟 㻼㻛㻺㻚㻠㻜㻜㻜㻚㻞㻜
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻠㼄㻝㻥
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㼂㻭㻸㻽㼁㻭
㻞㻤 㻳㻭㻿㻷㻱㼀 㻙 㻵㻰㻥㻜 㻻㻰㻞㻜㻜 㻟 㻼㻛㻺㻚㻠㻜㻜㻜㻚㻞㻞
㻢㻡㻜㻜
㻼㻯㻰㻩㻝㻡㻜 㼠㻩㻞
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻼㻛㻺㻚㻡㻞㻜㻞㻚㻞
㼀㻱㻾㻹㻵㻺㻭㻸
㻟㻝 㻠㻞㻣㻚㻡 㻙 㻙 㻙 㻟 㻼㻛㻺㻚㻣㻡㻡㻝
㼁㻺㻵㼀
㻔㻖㻝㻘㻌㻖㻞㻘㻌㻖㻟㻕
㻖㻝 㼀㼕㼙㼕㼚㼓㻌㼒㼛㼞㻌㼞㼑㼜㼘㼍㼏㼑㼙㼑㼚㼠㻌䠖㻌㻭㼠㻌㼠㼔㼑㻌㼠㼕㼙㼑㻌㼛㼒㻌㼙㼛㼠㼛㼞㻌㼞㼑㼣㼕㼚㼐㼕㼚㼓㻚㻌㻔㼃㼑㻌㼞㼑㼏㼛㼙㼙㼑㼚㼐㻌㼠㼛㻌㼞㼑㼣㼕㼚㼐㻌㼍㼠㻌㼀㼛㼞㼕㼟㼔㼕㼙㼍㻌㼣㼛㼞㼗㻌㼟㼔㼛㼜㻚㻕
㻖㻞 㻴㼍㼚㼐㼘㼕㼚㼓㻌䠖㻌㼁㼚㼐㼑㼞㻌㼟㼡㼜㼑㼞㼢㼕㼟㼕㼛㼚㻌㼛㼒㻌㼀㼛㼞㼕㼟㼔㼕㼙㼍㻌㻿㼂㻚
㻖㻟 㻿㼠㼛㼞㼍㼓㼑㻌䠖㻌㻿㼑㼑㻌㼛㼡㼞㻌㻻㻌㻒㻌㻹㻌㼙㼍㼚㼡㼍㼘㻚
Q3C0006689 - 6/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1055
51006-41400-1053
Spare Parts List(Recommended) Rev. No.: 0
Larsen & Toubro Ltd.
Date: 8/7/2016
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻟㻞 㻻㻙㻾㻵㻺㻳 㻵㻰㻠㻤 㻢 㻙 㻺㻮㻾 㻟 㻼㻛㻺㻠㻝㻞㻜㻚㻝㻝
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻟㻟 㻻㻙㻾㻵㻺㻳 㻵㻰㻡㻜 㻠 㻙 㻺㻮㻾 㻟 㻼㻛㻺㻚㻠㻝㻞㻜㻚㻝㻞
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻟㻠 㻻㻙㻾㻵㻺㻳 㻵㻰㻠㻜 㻞㻚㻡 㻙 㻺㻮㻾 㻟 㻼㻛㻺㻚㻠㻝㻞㻜㻚㻝㻟
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻿㻼㻾㻵㻺㻳
㻟㻡 㻙 㻵㻰㻝㻜㻚㻞 㻻㻰㻝㻤㻚㻠 㻿㼁㻿㻟㻝㻢 㻥㻜 㻼㻛㻺㻚㻥㻟㻜㻜㻚㻞㻜
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻿㻼㻾㻵㻺㻳
㻟㻢 㻙 㻵㻰㻝㻜㻚㻞 㻻㻰㻝㻤㻚㻠 㻿㼁㻿㻟㻝㻢 㻟㻢 㻼㻛㻺㻚㻥㻟㻜㻜㻚㻞㻝
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻿㻼㻾㻵㻺㻳
㻟㻣 㻙 㻵㻰㻝㻢㻚㻞 㻻㻰㻞㻤 㻿㼃㻾㻴 㻝㻞 㻼㻛㻺㻚㻥㻟㻜㻜㻚㻞㻞
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻿㻼㻾㻵㻺㻳
㻟㻤 㻙 㻵㻰㻝㻣 㻻㻰㻟㻜 㻿㼁㻼㻢 㻟 㻼㻛㻺㻚㻥㻟㻜㻜㻚㻞㻠
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻸㻻㻯㻷
㻟㻥 㻞㻣 㻝㻞㻚㻡 㻟㻜 㻯㻝㻝㻜㻜 㻟 㻼㻛㻺㻚㻥㻟㻝㻝㻚㻞㻜
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻸㻻㻯㻷
㻠㻜 㻞㻜 㻤㻚㻡 㻞㻞 㻿㼁㻿㻟㻜㻠 㻢 㻼㻛㻺㻚㻥㻟㻝㻝㻚㻞㻝
㼃㻭㻿㻴㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻠㻣㻥
㻸㻻㻯㻷
㻠㻝 㻞㻣 㻝㻞㻚㻡 㻟㻜 㻯㻝㻝㻜㻜 㻢 㻼㻛㻺㻚㻥㻟㻝㻝㻚㻞㻞
㼃㻭㻿㻴㻱㻾
Q3C0006689 - 7/8
2 × 660 MW KHARGONE SUPER THERMAL
POWER PROJECT
L&T-MHPS BOILERS PRIVATE LIMITED
(FORMERLY KNOWN AS L&T-MHI BOILERS PRIVATE LIMITED)
Doc. No.: 51006-41400-1053
51006-41400-1055
Spare Parts List(Recommended) Rev. No.: 0
Larsen & Toubro Ltd.
Date: 8/7/2016
㻲㻻㻾㻌㻴㻼㻌㻯㻻㻻㻸㻵㻺㻳
㻜㻥㻝㻜㻜㻝㻡㻞㻜㻢
㼃㻭㼀㻱㻾㻌㻯㻻㻻㻸㻱㻾
㻾㻵㻺㻳㻌㻶㻻㻵㻺㼀 㻵㻺㻸㻱㼀㻌㻒㻌㻻㼁㼀㻸㻱㼀
㻠㻞 㻻㻰㻝㻝㻞㻚㻣㻝 㻵㻰㻥㻜㻚㻠㻥 㻝㻡㻚㻤㻤 㻿㼁㻿㻟㻜㻠㻸 㻞
㻳㻭㻿㻷㻱㼀 㻲㻸㻭㻺㻳㻱
㻭㻿㻹㻱㻞㻡㻜㻜㻸㻮
㻾㻞㻢 㻾㻶㻌㻞㻎
㻼㼁㻾㻳㻱㻌㼃㻭㼀㻱㻾
㻜㻥㻝㻜㻜㻝㻡㻞㻜㻢
㻹㻻㼀㻻㻾㻌㻵㻺㻸㻱㼀㻌㻛
㻾㻵㻺㻳㻌㻶㻻㻵㻺㼀
㻠㻟 㻻㻰㻢㻤㻚㻞㻣 㻵㻰㻡㻞㻚㻟㻥 㻝㻞㻚㻣 㻿㼁㻿㻟㻜㻠㻸 㻝 㻹㻻㼀㻻㻾㻌㻰㻾㻭㻵㻺
㻳㻭㻿㻷㻱㼀
㻭㻿㻹㻱㻞㻡㻜㻜㻸㻮
㻾㻝㻤 㻾㻶㻌㻝㻎
㻜㻥㻞㻜㻜㻝㻢㻜㻝㻣
㻝㻚㻠㻡㻣㻝㻛 㻲㻻㻾㻌㻹㻻㼀㻻㻾㻌㻯㻻㻻㻸㻱㻾
㻠㻠 㻳㻭㻿㻷㻱㼀 㻙 㻥㻡 㻝㻝㻡 㻳㻾㻭㻼㻴㻚
㻝
㻔㼁㻼㻼㻱㻾㻕㻼㻛㻺㻚㻝㻞㻠
㻜㻥㻞㻜㻜㻝㻢㻜㻝㻣
㻝㻚㻠㻡㻣㻝㻛 㻲㻻㻾㻌㻹㻻㼀㻻㻾㻌㻯㻻㻻㻸㻱㻾
㻠㻡 㻳㻭㻿㻷㻱㼀 㻙 㻥㻡 㻝㻝㻡 㻳㻾㻭㻼㻴㻚
㻝
㻔㻸㻻㼃㻱㻾㻕㻼㻛㻺㻚㻝㻞㻠
㻜㻥㻟㻜㻜㻝㻢㻞㻡㻢
㻺㻻㻺㻙 㻲㻻㻾㻌㻼㼁㻾㻳㻱㻌㻯㻻㻻㻸㻱㻾
㻠㻢 㻳㻭㻿㻷㻱㼀 㻙 㻞㻣㻟 㻟㻠㻜 㻭㻿㻮㻱㻿㼀㻻㻿
㻝
㻼㻛㻺㻚㻢
㻜㻥㻟㻜㻜㻝㻢㻞㻡㻢
㻺㻻㻺㻙 㻲㻻㻾㻌㻼㼁㻾㻳㻱㻌㻯㻻㻻㻸㻱㻾
㻠㻣 㻳㻭㻿㻷㻱㼀 㻙 㻝㻝㻠 㻝㻣㻡 㻭㻿㻮㻱㻿㼀㻻㻿
㻝
㻼㻛㻺㻚㻝㻟
Q3C0006689 - 8/8
c "THIS DRAWING IS THE PROPERTY OF AND CONTAINS CONFIDENTIAL PROPRIETARY INFORMATION OF L&T-MHPS BOILERS PRIVATE LIMITED AND SHALL UNLESS OTHERWISE STATED ALL DIMENSIONS ARE
NOT BE REPRODUCED, USED, DISCLOSED OR TRANSMITTED IN WHOLE OR IN PART UNLESS AUTHORISED IN WRITING BY L&T-MHPS BOILERS PRIVATE LIMITED" IN MILLIMETRES. DO NOT SCALE. IF IN DOUBT, ASK.
I
J
L
A
B
E
K
P
C
D
H
N
G
O
16
16
15
15
14
14
13
13
12
12
11
11
10
10
9
9
8
8
7
7
6
6
5
5
4
4
3
3
L&T
2
2
NTPC LIMITED
(A GOVERNMENT OF INDIA ENTERPRISE)
1
1
A
B
E
K
P
C
D
H
N
G
O
M
Project KHARGONE SUPER THERMAL POWER PROJECT (2X660MW)
Package STEAM GENERATOR AND AUXILIARIES
Document Title O & M Manual for Boiler Circulation Pump (BCP)