PROJECT: Two storey Apartment (Duplex)

LOCATION: Brgy. 4, P. herrera Batangas City


SUBJECT: Bill of Quantities

BILL OF QUANTITIES
MATERIAL COST LABOR COST
ITEM NO. DESCRIPTION QTY UNIT TOTAL COST
UNIT COST TOTAL COST UNIT COST TOTAL COST
I. GENERAL REQUIREMENTS
Building Plans and Permits (Demolition and Building) 1 lot 0 80000 80000 80000
Mobilization / Demobilization 1 lot 0 25000 25000 25000
Demolition 1 lot 0 100000 100000 100000
Scaffolding Rentals 1 lot 35000 35000 15750 15750 50750
II. FORMWORKS
2" x 3" Coco Lumber 450 pcs 135 60750 0 60750
1/2" thk Phenolic Board 80 pcs 650 52000 0 52000
III. EARTHWORKS
Excavation 27.83 cu. m. 0 550 15306.5 15306.5
Backfill 25 cu. m. 0 550 13750 13750
IV. FOUNDATION 5 cu. m.
16mm Rebar works 6m 20 pcs 385 7700 173.25 3465 11165
10mm Rebar works 6 m 30 pcs 175 5250 78.75 2362.5 7612.5
Cement 45 bags 250 11250 112.5 5062.5 16312.5
Gravel 3/4" 5 cu. m. 1500 7500 675 3375 10875
Sand (S -1) 2.5 cu. m. 1300 3250 585 1462.5 4712.5
V. COLUMN 6 cu. m.
16mm Rebar works 9 m 32 pcs 600 19200 270 8640 27840
10mm Rebar works 6 m 60 pcs 175 10500 78.75 4725 15225
Cement 54 bags 250 13500 112.5 6075 19575
Gravel 3/4" 6 cu. m. 1500 9000 675 4050 13050
Sand (S -1) 3 cu. m. 1300 3900 585 1755 5655
VI. SLABS 9 cu. m.
10mm Rebar works 10.5 m 90 pcs 280 25200 126 11340 36540
10mm Rebar works 7.5 m 120 pcs 200 24000 90 10800 34800
Cement 81 bags 250 20250 112.5 9112.5 29362.5
Gravel 3/4" 9 cu. m. 1500 13500 675 6075 19575
Sand (S -1) 4.5 cu. m. 1300 5850 585 2632.5 8482.5
VII BEAMS 9.5 cu. m.
16mm Rebar works 9 m 130 pcs 280 36400 126 16380 52780
10mm Rebar works 6 m 300 pcs 200 60000 90 27000 87000
Cement 85.5 bags 250 21375 112.5 9618.75 30993.75
Gravel 3/4" 9.5 cu. m. 1500 14250 675 6412.5 20662.5
Sand (S -1) 4.75 cu. m. 1300 6175 585 2778.75 8953.75
VIII MASONRY
5" CHB Wall with Plaster on both sides 225 sq. m. 1050 236250 472.5 106312.5 342562.5
Kitchen Sink 1 lot 25000 25000 11250 11250 36250
Tile Works 108 sq. m. 750 81000 337.5 36450 117450
IX CARPENTRY
Ceiling Works 90 sq. m. 1050 94500 472.5 42525 137025
Kitchen Cabinet 2 set 12500 25000 5625 11250 36250
Room's Cabinet 2 set 15000 30000 6750 13500 43500
X Paint Works
Paint Works 540 sq. m. 350 189000 157.5 85050 274050
XI DOORS & WIndows
0.8 m x 2.1m Panel Door with Door jamb 8 set 6500 52000 2925 23400 75400
0.7m x 2.1m PVC Door With door jamb 2 set 3500 7000 1575 3150 10150
1.8m x 1.5m Sliding window with frame 6 set 8500 51000 3825 22950 73950
0.6m x 1.5 m Awning Window with frame 4 set 6500 26000 2925 11700 37700
0.4m x 0.4 m Awning Window with frame 2 set 2500 5000 1125 2250 7250
XII SANITARY WORKS AND WATER LINES
Sanitary works and water lines including septik tank 1 lot 100000 100000 45000 45000 145000
XIII ELECTRICAL WORKS
Lightings and Electrical works including panel board 1 lot 100000 100000 45000 45000 145000
XIV Stairs and railings 2
12mm dia deformed bar 18 pcs 275 4950 123.75 2227.5 7177.5
10 mm dia deformed bar 16 pcs 200 3200 90 1440 4640
cement 18 bags 250 4500 112.5 2025 6525
Sand (S -1) 1 cu. m. 1300 1300 585 585 1885
Gravel 3/4" 2 cu. m. 1500 3000 675 1350 4350
stair railings 2 set 15000 30000 6750 13500 43500
balcony railings 2 set 15000 30000 6750 13500 43500
XV Roofing works
roofsheet 70 l.m. 420 29400 189 13230 42630
2 x 6 tubular 12 pcs 2300 27600 1035 12420 40020
2" x 3" c- purlins 25 pcs 550 13750 247.5 6187.5 19937.5
gutter 6 pcs 450 2700 202.5 1215 3915
Flashing 4 pcs 250 1000 112.5 450 1450
angle bar 1 x 1 1 pcs 450 450 202.5 202.5 652.5
2x6 c- purlins 6 pcs 750 4500 337.5 2025 6525
Flashing 4 pcs 250 1000 112.5 450 1450

Direct Cost 2568424


OCM 7 % 179789.68
Contractors Profit 10 % 256842.4
GRAND TOTAL 3005056.08
**note: say P 3,000,000.00 ( Three Million Pesos Only)

Prepared by : Engr. Allen Robert M. Wagan


Civil Engineer
PRC No: 131332