Documente Academic
Documente Profesional
Documente Cultură
BY
SEPTEMBER, 2016.
i
ACKNOWLEDGEMENT
I am truly indebted to my family for their invaluable support. I wish to express my profound
gratitude to Prof. A.O. Ibe for his exceptional guidance and direction throughout the work. My
appreciation also goes to Dr. R. Uhunmwangho for his motivation during the work, as well as to
ii
DECLARATION
I declare that this report is my unaided work and it was not copied or written in collaboration with
any other person.
Signed
______________________
iii
CERTIFICATION
I certify that this report is an independent work carried out by UNU, OCHUKO VALERIE for
registration as corporate member of the Nigerian Society of Engineers (NSE).
Signed: ____________________
Name: ____________________________
Date: ____________________
iv
DEDICATION
v
TABLE OF CONTENTS
Cover Page i
Acknowledgement ii
Declaration iii
Certification Page iv
Dedication v
Table of Contents vi
List of Figures x
List of Tables xi
PART A xii
PART B xvi
Abstract xviii
1.1 Background 1
vi
1.5 Methodology 3
2.7 Converter 13
vii
3 .8 Sensitivity Analysis 19
References 23
Project Two: Electrical Design/Installation of Lighting and Power Points for a Three
Bedroom Bungalow 24
Abstract 25
1.1 Background 26
4.1 Recommendation 41
References 44
ix
LIST OF FIGURES
Project One:
Project Two:
x
Figure 2.3 PVC Pipes 31
xi
LIST OF TABLES
Project One:
Project Two:
xii
PART A
xiii
PERSONAL DETAILS
SURNAME: UNU
NATIONALITY: NIGERIAN
SEX: FEMALE
xiv
EDUCATIONAL INSTITUTION ATTENDED
WAEC (2005)
xv
SUMMARY OF POST-GRADUATE WORK EXPERIENCE
1. EMPLOYER: NYSC
PERIOD: 2012-2013
JOB DESCRIPTION:
Teach students Computer appreciation and applications.
JOB DESCRIPTION:
Produce Electrical designs for both commercial and residential buildings. Such designs include
the power, lighting, fire alarm, CCTV, audio/tv and intercom layouts where applicable.
xvi
PART B
xvii
PROJECT ONE:
xviii
ABSTARCT
Instability in power supply in the Choba campus of the University of Port Harcourt has led to the
disruptions in both academic and administrative activities in recent times. Over-reliance on diesel
has become very expensive as fuel cost keeps increasing, whilst pollution has recorded from the
emissions of the engines. This work is about the development of an alternative renewable energy
source using PV/Diesel hybrid system based on simulated results of HOMER (Hybrid
Optimization Model for Electrical Renewables) software. The hybrid system is designed and the
calculated results are then simulated using HOMER in order to obtain the optimal system
configuration with the least cost of energy, operation and net present cost. The result shows that
the optimal system consists of a 33kW solar PV, 33kW Diesel generator, a 33kW bidirectional
converter and 20 x 6FM200D batteries for energy storage.
xix
CHAPTER 1
INTRODUCTION
1.1 Background
The World Energy Outlook (2014) report shows that nearly 1.3 billion people are without access
to electricity and 2.7 billion people rely on the traditional use of biomass for cooking, which causes
harmful indoor air pollution. These people are mainly in either developing Asia or sub-Saharan
According to a special report in the Africa Energy Outlook(2014) contained in the World Energy
Outlook series, more than 620 million people in sub-Saharan Africa (two-thirds of the population)
live without electricity, and nearly 730 million people rely on dangerous, inefficient forms of
cooking. According to the World bank data on energy (2014), only 48% of the population in
Nigeria has access to electricity. Nigeria has an enormous solar energy resource with up to
Solar PV systems convert sunlight energy into electricity through solar cells, which are composed
of semiconductor materials. When these solar cells are combined they form a solar panel with a
peak capacity of 80-200W according to Wiki-solar, depending on size and technology used.
The output of the solar PV system is determined by the insolation, which is the amount of solar
energy received at a specific location. According to Insight Guides, the insolation value is higher
at regions closer to the Equator than at other regions. This is why PV systems tend to have more
performance in Africa. Choba region of Port Harcourt has an average solar radiation of 4.4
kWh/m2/d which is sufficient for the production of electricity, thus solar PV installation is feasible.
1
During warmer months, the insolation is higher than in cold months. Similarly, insolation is higher
during the dry season than the rainy season. Thus, the lower production of PV during the rainy
season can be offset with a diesel generator which will operate at higher levels. Unlike solar PV
systems, conventional generators utilize fossil fuel (in this case, diesel) in order to generate
electricity. Combining the renewable energy generation with conventional diesel power generation
will enable the power generated from renewable energy sources to be more reliable and affordable.
In recent times, the electricity demand by consumers has increased in the University of Port
Harcourt. This is a result of the infrastructural development and population which in turn have led
to the establishment of more hostels, offices and classrooms. The same cannot be said of the
electricity supply from the utility companies. Choba campus barely has power supply for 4-8 hours
inconsistently each day. This means for the period when there is no electrical power supply, diesel
Photovoltaic systems however, do not produce pollutants. They operate without noise to convert
sunlight energy to electricity. Choba has high solar resource suitable for the operation of PV
system. PV systems are easy to install, require very insignificant maintenance and does not use
fuel to operate. This makes the project useful in determining the most cost efficient PV system
size to be used (in addition to the diesel generator) to meet the power demand of the department.
The main aim of this report is to determine the optimum size of PV-Diesel system that sufficiently
serves the load of a typical office administrative block in the University of Port Harcourt, Choba,
2
Rivers State. This is achieved using HOMER (Hybrid Optimization Model for Electric
An hourly load data for a day is calculated using the power rating of appliance in
use
2) Determining the appropriate sizes and amount of the PV, inverter and battery and diesel
generator
HOMER uses the data obtained in steps 1 and 2 to perform simulations from
This report focuses on how HOMER technically and economically selects the optimal PV-Diesel
systems configuration that meets the daily load demand of the administrative building.
1.5 Methodology
The optimum PV-Diesel system size for a commercial building load will be determined and
analyzed mathematically to determine the appropriate size of the individual energy sources. The
obtained data are then simulated using HOMER in order to determine the techno-economically
feasible system configurations and properties. The load data of the building, the PV system data
(including the solar resource data) and the diesel generator data (including fuel price) will be
entered into HOMER as input values. HOMER then performs simulations using these inputs and
3
1.6 Review of Related Work
Kazem et al (2013) evaluated PV systems against diesel generator system for 4.7kWh/day average
load with a peak load of 520W, using intuitive and numerical techniques. For the intuitive
technique, the optimal system comprises of a 1.7kW PV module, six batteries and 1.5kW inverter.
From the numerical technique and using HOMER, the optimal result is achieved when the system
Al-Asadi and Kazem (2013) designed a hybrid PV/Wind/Battery system in Oman for loads which
included street lights, billboards, traffic lights and telephones, for a distance of 880km. For this
load, 4500kW PV modules, 20,000 batteries, 5000kW inverter and 100 wind turbines were
Nfah et al (2007) modeled a Solar/Diesel/Battery hybrid system to meet the energy demands of a
typical rural domestic region and concluded that a hybrid power system comprising a 1440Wp
solar PV array and a 5kW diesel generator with a load factor of 0.7, met the demand.
4
CHAPTER 2
METHODOLOGY
The system consists mainly of the solar PV, Diesel generator, Converter and batteries. The inputs
for each of these system components comprise of both calculated and existing variables. The load
data for this system, for example was calculated using the known ratings of each appliance in the
building. The PV size was calculated using the selected type specifications, while the cost was
obtained from the website of the manufacturer. The battery and generator data were also gotten
HOMER is a computer model that simplifies the task of designing hybrid renewable micro grids,
whether remote or attached to a larger grid. It simulates the operation of a system with the
calculated and existing information for the various components and resources by making energy
balance calculations for each of the 8,760 hours in a year. It performs energy balance calculations
for each system configuration that considered. It then determines whether a configuration is
feasible, i.e., whether it can meet the electric demand under the conditions specified, and estimates
the cost of installing and operating the system over the lifetime of the project. The system cost
calculations account for costs such as capital, replacement, operation and maintenance, fuel, and
5
Fig.2.1 System Design
The system design above consists of the primary load of daily average of 142kWh/d with a peak
of 30kW, a 33kW diesel generator connected to the ac bus bar along with a 33kW converter (with
inverter and rectifier characteristics). Both the 33kW PV array and the 6FM200D batteries are
The load under consideration is that of an office block located in the University of Port Harcourt
in Choba, Rivers State. This is situated at 4.78oN 6.98oE according to Maplandia (2014). The table
below shows the rated appliances as well as the time of use each day.
6
Laptops 70 15 1050 4 4200
The above data is split into a 24-hour profile and then entered into HOMER.
𝑇𝑜𝑡𝑎𝑙 𝑑𝑒𝑚𝑎𝑛𝑑(𝑊𝑎𝑡𝑡𝑠)
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑 = …3.1
𝐻𝑜𝑢𝑟𝑠
The peak load is the greatest demand of load on the power station during a given period. The load
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑
𝐿𝑜𝑎𝑑 𝐹𝑎𝑐𝑡𝑜𝑟 = …3.2
𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑
7
Fig. 2.1 Load Profile
The daily profile graph above shows the load (in kW) for each hour in a typical day of the month.
Next to it is the DMap (data map) which is a type of graph showing one year of hourly data. The
DMap allows daily and seasonal patterns to be seen much more easily than would be possible with
a simple time series plot. The seasonal profile indicates the maximum, mean and minimum load
When the sun rays strike the Solar PV panels, it produces electricity. A PV module is composed
glass) and back plate (usually a plastic laminate). It will also have one or more protective by-pass
diodes. The output terminals, either in a junction box or in a form of output cables, will be on the
back. Most modules have frames, but those without frames are called laminates. Some have glass
back plates, which gives a higher fire rating. This however, almost doubles the weight.
8
Solar PV modules are connected in series-parallel. Cells connected in series increases the voltage
output while cells connected in parallel increases the current. A group of several PV modules
To calculate the appropriate PV array size for the load under consideration, the cell temperature
has to be calculated first. For this work, Evergreen ES-A-210 solar polycrystalline panels have
YPV 210 W
Ƞmp,STC 13.4 %
o
Ta,NOCT 20 C
o
Tc,NOCT 45.4 C
o
Tc 134.05 C
o
Tc,STC 25 C
αp -0.43 %/ oC
Fpv 60 %
ḠT 4.37 kW/m2
ḠT,STC 1 kW/m2
These are very useful in calculating the cell temperature as seen in the equation given by Tesfaye
(2011) below:
9
𝑇𝐶,𝑁𝑂𝐶𝑇 −𝑇𝑎,𝑁𝑂𝐶𝑇 𝜂
𝑇𝑐 = 𝑇𝑎 + 𝐺𝑇 ( )(1 − 𝜏 𝑐 ) …3.3
𝐺𝑇,𝑁𝑂𝐶𝑇 𝛼
The next step is to calculate the PV array output by using the equation:
Ḡ𝑇
𝑃𝑃𝑉 = 𝑌𝑃𝑉 𝑓𝑃𝑉 (Ḡ ) [1 + 𝛼𝑝 (𝑇𝑐 − 𝑇𝑐,𝑆𝑇𝐶 )] …3.5
𝑇,𝑆𝑇𝐶
The maximum installed power capacity of PV Array is therefore 33 KW. The cost of installing a
33kW PV module taken from Renesol consumer fact sheet (2014) is ₦12,375,000. The
replacement cost is ₦11,550,000. Since the operation and maintenance cost is minimal, HOMER
assumes it to be done once a year, which amounts to ₦10,000/year. This is shown below:
Note: All the dollar symbols as used in HOMER are assumed to represent naira.
10
2.5 Battery Sizing
The battery chosen for this work is a 12 volts deep cycle Vision 6FM200D model because they
are lead-acid batteries designed to be regularly deeply discharged using most of its capacity, whilst
ensuring quicker recharge time. Battery sizing is simply calculating the number of batteries needed
for a hybrid renewable energy system. This mainly depends on the days of autonomy desired. Days
of autonomy are the number of days a battery system will supply a given load without being
recharged by a PV array, wind turbine or another source. If the load being supplied is not critical
then 2 to 3 autonomy days are commonly used. For critical loads 5 days of autonomy are
recommended. A critical load is a load that must be used all the time.
Another important factor is maximum depth of discharge of the battery. The depth of discharge
refers to how much capacity will be use from the battery. Most systems are designed for regular
discharges of up to 40 to 80 percent. Battery life is directly related to how deep the battery is
generally rate their batteries at 25ºC. The battery capacity will decrease at lower temperatures and
increase at higher temperature, while the battery life increases at lower temperature and decreases
at higher. The required battery bank capacity for a hybrid renewable energy system according to
Where 𝐿𝐴ℎ/𝑑𝑎𝑦 is the Amp-hour consumed by the load in a day (Ah/day), 𝐷𝑆𝑇 is the number of
autonomy days, 𝑀𝐷𝐷 is the maximum depth of discharge, 𝐷𝑓 is the derating factor and 𝐵𝑅 is the
11
Since we have considered loads of 100, 125, 142, 150,175 and 200 kWh/day, we would have to
specify different battery sizes for each of them. From the equation above, approximately 20, 40,
60 and 70 batteries are sufficient for the loads. This is shown below:
We have used a 33kW Mikano soundproof diesel generator for the load. The cost of this generator,
including its installation is ₦2,200,000, while the replacement cost is ₦1,800,000 as obtained from
the Mikano website. The lifetime of the generator is taken to be 25,000 hours. The fuel
consumption of the diesel generator depends on the rated power of the generator and the actual
output power supplied by it. The fuel consumption of the diesel generator (FCG) in (l/h) according
where PG, PR-G are the output power and the rated power of the generator in (kW) respectively. AG
and BG are the coefficients of the consumption curve in (l/kWh) where AG = 0.246 l/kWh and BG
12
= 0.08145 l/kWh for the diesel generator. The figure below gives a summary of the diesel generator
details.
2.7 Converter
A power electronic converter is needed to maintain flow of energy between the ac and dc
components. For a 1 kW system the installation and replacement costs are taken as ₦22,000 and
₦20,000 respectively. Cost analysis is shown below. Lifetime of a unit is considered to be 15 years
with an efficiency of 85%. We have used a 33kW converter. The number of inverters for a
𝑃𝐿𝑜𝑎𝑑
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑖𝑛𝑣𝑒𝑟𝑡𝑒𝑟𝑠 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = 𝑃 …3.8
𝑖𝑛𝑣𝑒𝑟𝑡𝑒𝑟
where Pload is the load of ‘the system in kW. Pinverter is the kW rating of the inverter.
13
Fig.2.5 Converter Details
The solar resource for the solar PV is gotten from NASA. It is shown in the table below:
14
CHAPTER THREE
When the software is run, the results will be displayed in the form of tabular and graphical plots
showing the optimal system combinations. Each of these combinations has details about the cash
flow, equipment details and the emissions. For this system, two optimal systems have been chosen
The optimal system consists of a 33kW solar PV, 33kW Diesel generator, a 33kW bidirectional
converter and 20 6FM200D batteries. The outputs of each of these components are further
discussed here.
The cost summary comprises a graphical and tabular breakdown of the capital, replacement and
O&M costs. It also includes the fuel cost (if applicable) and the salvage cost.
15
Fig.3.3 Graphical Cost Summary
The total production of the solar PV is given as 50,555kWh/yr. The hours of operation of the PV
16
3.4 Diesel Generator Output
The diesel generator which has a lifetime of 25,000 hours operates for 1,765hr/yr. It produces
34,641kWh/yr with a fuel consumption of 13,320l/yr. More details are presented in the figure
below.
The converter (inverter and rectifier) has a lifetime of 15 years. The inverter and rectifier operate
for 8,391 and 368 hrs/yr respectively. The output of the inverter is 40,222kWh/yr, while that of
17
Fig.3.6 Converter Output
The output of the battery is 1,035kWh/yr with a 255kWh/yr loss. The figure below shows further
3.7 Emissions
The optimal system has 87,656kg/yr less carbon dioxide than the second system. Figures 3.6 (a
and b) below shows that the first optimal system produced fewer emissions than the other, which
18
Fig.3.8a Optimal System (PV/Diesel/Battery)
3 .8 Sensitivity Analysis
When you define sensitivity variables as inputs, HOMER repeats the optimization process for each
sensitivity variable that you specify. For example, if you define wind speed as a sensitivity
variable, HOMER will simulate system configurations for the range of wind speeds that you
specify. For this work, a sensitivity analysis was done for different loads of 100, 125, 142, 150,
175 and 200 kWh/day against the solar resource data of 3.0 to 6.0 kWh/m2/d. The result is as
shown below:
19
Fig. 3.9 Sensitivity Analysis
From the optimal system type graph above, the PV/Gen/Battery systems are optimal for most of
the sensitivity space. Diesel/Battery systems are optimal at the bottom right of the sensitivity space.
20
CHAPTER FOUR
CONCLUSION
In this work, a PV/Diesel system has been designed and results were obtained from simulations
using HOMER to determine the optimal system combination to serve the load of a University
administrative block of about 16 offices. The result shows that the PV/Diesel system with batteries
incorporated is optimal because the excess electricity produced by this system is being stored by
it for future use, saving fuel cost. The system is thus very efficient and reliable with less emission.
Furthermore, HOMER has been able to select the optimal system size as a function of the net
present cost.
The major challenge for this work lies in accurate data collection. It is however, recommended
that other renewable energy sources be studied and their suitability for electricity production
21
CHAPTER FIVE
BILL OF ENGINEERING MEASUREMENT EVALUATION (BEME)
S/N DESCRIPTION UNIT QUANTITY COST (₦)
PRICE(₦)
9 Total 15,715,500
22
REFRENCES
23
PROJECT TWO:
ELECTRICAL DESIGN/INSTALLATION OF LIGHTING AND POWER POINTS FOR
A THREE BEDROOM BUNGALOW
24
ABSTRACT
Every engineering model starts with a design that forms the foundation on which the respective
segments are built. In this report, a three bedroom residential bungalow is presented and its design
and installation sequences are discussed. The design was done with the AutoCAD software to
ensure a precise design model. The result shows a well-planned lighting and power layout that
have been protected using the appropriate miniature circuit breakers.
25
CHAPTER ONE
INTRODUCTION
1.1 Background
During the last century and a half, electricity has evolved from a scientific curiosity, to a luxury
for wealthy people and to a daily necessity in the developed and developing world. Just as water
is necessary for survival, electricity is indispensable in daily life. Without electricity, our way of
life comes to a grinding halt. Modern society requires smart, simple, safe, reliable, and economical
electric power infrastructure for social, political, and economic activities (WBDG, 2015). The
Electrical drawings, specifications, reports and other documents are thus necessary in setting forth
the overall design and requirements for the construction, alteration, modernization, repair,
(RMIT, 2016).
As both commercial and residential structures are constantly been developed, it has become very
important to take the electrical system into consideration, as it is the source of luminance, power
and in some cases, electronic security. However, if an improper design and installation is
implemented, it could lead to system breakdown and if not promptly addressed, fatal accidents.
Electrocutions, fire outbreaks, physical injuries, loss of lives and properties have been recorded
26
1.3 Aim and Objectives
The main aim of this project is to design the lighting and power points for a three bedroom
residential duplex to ensure proper installations. This will be achieved by first obtaining the ground
floor plan prepared by the architect and then determining the appropriate lighting and power points
for each sections. Next step is to prepare the load schedule which requires the consumer unit or
This report centers on only discussions of lighting and power points layout and installation. It does
not include other appliances like CCTV, audio/tv, intercom or any other points. It also presents the
load schedule for the building under consideration. Finally, it discusses the basic installation
27
CHAPTER TWO
METHODOLOGY
According to a UNEP report (2006), before costing the project, it was important to determine first,
what the building was designed for -in this case, residential. With this, specifications as to what
electrical appliances to include are made. Therefore, since it is a residential building, it should
have 13 Amps sockets for common appliances, 15A sockets for the air conditioning units and
Cooker Control Unit for the kitchen. After deciding which to use and where to use each, the total
number of items to be used was recorded. The total number of lighting and power points
determines the quantity of U boxes, through boxes, looping boxes, cables, and bushings to use.
Next, is to select the lighting fixtures to use which includes where to use fluorescent fittings, down
lights, bowl fittings, ceiling fittings, wall fittings and cables. The cost of each of these materials is
drafted and summed up in addition to the cost of labour (Vatapoulos et al, 2016). This includes
transportation during the period of the project that is, cost of transporting the workers and materials
to and from the site during all working days. Finally, the cost of the job is recorded. Miscellaneous
To achieve this, knowledge of AutoCAD is essential. In AutoCAD, lines, rectangles, circles, arcs
and polygons are the basic tools to any electrical drawing. However, other tools like text writing
(which describes the drawing) is needed. To ensure quicker drawing, commands like Mirror
(drawing the same object opposite the source object), Copy (duplicate of the source object), Move
(to change the position of an object), are used. In the case of using symbols to represent appliances
in the electrical design, it is important to have knowledge of circles, arcs, circles and rectangles.
28
Then to modify them, commands such as Chamfers and Fillets are used to produce diagonal and
curved edges respectively. Where mistakes are made in the drawing, the eraser and the trim tools
are used. The ORTHO mode is used to enable drawings to be made in 90 degrees only, that is,
only vertically and horizontally. Polar tracking is for drawings at angles other than 90 degrees.
Here contains the lighting fixtures (fluorescent lamps, down lights, the appropriate switches to
control each lighting, expeller fans as well as ceiling fans together with each regulator. The
electrical appliances using symbols. The switches and fan regulators are usually not placed on the
wall partition towards which a door opens, for easy access. Also they are placed 150cm on the wall
Here, we normally have 13Amps SSO (switch socket outlet) single and double, CCU (cooker
control unit), Distribution boards, 15Amps SSO (for air conditioners), TV distribution/signal
booster, Water heaters, etc. The power schematics has its own legend. In the drawing, circuit
numbers are been placed on each 13Amps socket point so that all the sockets on the same circuits
are easily identified during installation and maintenance. The height of 13A sockets is 50-60cm
above the ground, while that of 15A sockets is 180cm above ground.
29
2.3 Materials and Use
When fixing boxes, it is important to note that the walls will later be plastered by bricklayers so
each box will have to be fitted two-third into the wall so that they do not get totally submerged by
mortar. Moreover, during termination, the fittings would have no hold on the boxes. As the boxes
are placed into the wall, a little bit of mortar is used to hold them in position. But to ensure leveling
of the boxes, a spirit-level is used by placing it on the box and watching the spirit level. After
making sure that it is straight, more mortar is used to hold the boxes firmly. The boxes used are 3
x 3 and 3 x 6 knock-out boxes. However, it is important to note that there are standard
measurements for each installation e.g. for switches; 140-150 cm, air conditioning; 180 cm,
sockets; 50-60 cm, etc. This measurement is taken from ground level.
After the mortar dries up, the conduit pipes are then laid next.
30
2.3.2 Laying of Pipes
PVC pipes come in different standard sizes. The common ones are 20 mm and 25 mm. But before
these pipes are fixed to the boxes, male bushes are screwed in to the boxes to ensure that the pipes
sit properly. Sometimes, PVC adhesive is rubbed on the tip of the pipe to be slotted in to hold the
pipes firmly.
To get shorter lengths of pipes for switches or air conditioning, a cutter (saw blade) is used to cut
the long length into the required length. Two lengths of pipes can also be joined to get a longer
length with the use of a joining coupling often called a coupler. But to get a stronger joint, PVC
adhesive is applied to inside of the coupler so that when both pipes are slotted in from both sides
of the coupler, they can stay stronger. Some pipes would have to go through bends which means
the straight length will have to be bent. A bending spring is used to bend pipes to any degree or
angle required.
31
Figure 2.4 Bending Spring Figure 2.5 Hack Saw Blade
Most times, after the pipes have been laid, the lighting points is taken care of with the use of
looping boxes. After this is done, the pipes are linked between looping boxes. It is impossible to
A looping box is one that is circular in shape with a depression that has four openings into which
male bushes are placed to allow at most four pipes to be fitted in. Therefore, in linking of pipes,
one pipe is fitted into one opening of one box, bent to an angle of 90 degrees and joined with a
coupler to another pipe, bent again to same again and fixed into the other opening of the other box.
These above steps are basically involved in linking pipes for telecom, lighting, fire alarm,
television, etc.
Apart from looping boxes, other boxes are used for lighting and other installations. Some of them
include U box (for lights), Y box (for lights and through box), T box (used as a junction box), Four
way box (used as through and junction box), End box (used for end points connection), through
32
Figure 2.6 : 4-Way Boxes Figure 2.7: U-boxes
In laying cables, there are few steps to allow easy passage and to save time. Previously, the conduit
pipes have been laid and knock-out boxes have been mounted as well as distribution boxes. The
main tool used to pass cables through these pipes is the fishing tape which is a thin metal tape
To pass the cable, the insulation at the tip is peeled off a short length using an electrical knife. If
more than one cable is to be passed, then the tips are twisted together and passed through the head
of the tape and twisted again tightly to ensure easy passage through the pipes. Smoother passage
is achieved with the application of Vaseline to the cables from the tip through the length. As the
33
cables are passed, one person is at the sending end, aligning the cables and another person at the
receiving end, pulling the cable until the whole length comes fully out. After the cables are
successfully out, they are terminated. Termination is the process of fixing each cable in its allotted
position.
In residential wiring, the number of rooms, sitting room, toilets and other partitions are taken into
consideration. This will determine the type and quantity of distribution boards, consumer units,
low voltage boards, cables, etc to use. The various electrical appliances to be installed include:
The sitting room is fitted with at least 1 x double socket outlet, each rated 13 Amps as shown in
Figure 2.9.
The sockets are divided into circuits to prevent overload. The minimum cable size for such sockets
is 2.5mm2. Doubles are used mostly to create more space for appliances to be plugged in. This
sometimes cuts out the use of extension sockets which gets damaged easily and could cause
accidents if the extension cable gets caught with the leg or any other appliance. However, in a
34
typical socket, we find three points marked live L, neutral N, and earth (with symbol). The red
cable is normally the live cable, black is neutral and the green or yellow cable is for earthing.
Sometimes, distribution boards are used instead of consumer units for larger loads. The differences
of these boards are unique. In this residential building, a distribution board is used to feed the
respective circuits.
A consumer unit is a single phase board that has three busbars, live, neutral and earthing. There
are four way boards, six way, eight way, twelve way boards. A way is a distinct circuit. For a
consumer unit, four way would mean four circuits. For a distribution board and a low voltage
board however, a four way board would mean twelve circuits because they are both three phase
boards. The equation used to calculate the total number of ways is:
𝐶𝑡 = 𝑁𝑤 × 𝑝ℎ …2.1
Where Ct is the total number of circuits, Nw is the number of ways, and ph is the number of phases.
35
At the live busbars, breakers like MCBs (miniature circuit breakers) or RCDs are used as protective
devices designed to break at specific conditions to protect the various devices in each circuit.
3. Circuit Breakers
The miniature circuit breaker to be used for protection of each circuit can be calculated using the
𝑷 = 𝑽𝑰 𝑪𝒐𝒔 𝝋 …(2.2)
𝑰 𝒊𝒔 𝒕𝒉𝒆 𝒄𝒖𝒓𝒓𝒆𝒏𝒕 =?
Therefore, the required current rating (to the nearest whole number) is obtained using the
equation:
4. Air Conditioners
The cable size is usually 2.5mmsquare. Sometimes, a 4mmsquare cable is used instead in the case
of highly rated air conditioners. In laying out the cables and terminating the socket outlets, three
core cabling is used-Live (red/brown), Neutral (black/blue) and Earth (yellow/green). These cables
are connected each to the corresponding terminals in the socket. The mains, supplies power to each
air conditioner in each circuit. This comes from the distribution board or consumer unit. In these
boards, an MCB is fitted to protect the appliance from damage resulting from short circuits and
36
over current. The red cable (Live) is connected to the MCB terminal, while the blue (Neutral) and
green (Earth) cables are connected to the neutral and earth bus bars, respectively.
4. Lighting
Lighting arrangement deals mainly with lights and the various control switches. There are
different types of fittings for this purpose. For example, incandescent, fluorescent, discharge,
37
Circuit diagram of Light points
The circuit diagram above is applicable to all lighting systems. The cable size used is 1.5mm2. It
shows that the switch is powered by from the mains through the live terminal and another cable
connects switch 1 to switch 2 and on. This cable now acts as the supply for the other switches. In
a typical switch, both cables are terminated at the point marked COM (common). Next is the cable
that links the switches to the lights. In a typical switch, it is marked L1. A switch should not have
neutral terminals except the above mentioned terminals. Switches can be two way, one way and
38
CHAPTER THREE
DESIGN ANALYSIS
3.1 The Lighting Load
There are a total of 32 lighting points in the three bedroom flat including ceiling fans. The design
layout is presented in Appendix A. Table 3.1 below shows the lighting points summary:
2 6 1 273
3 8 1 309
4 6 2 238
Each of the lights selected is an 18Watts energy saving bulb, while each fan is rated 65Watts. The
load schedule in Appendix C indicates that each of the lighting circuits utilizes a 6A circuit breaker
Table 3.2 presents the number of 13A and 15A sockets in each circuit. There are a total of four
socket and air-conditioning circuits. The socket circuits each have four 13A sockets, while there
are 1 x 15A sockets in each circuit. The power layout of the building is shown in Appendix B.
39
Table 3.2: Power Points Rating
Circuit Number Number of Total
No. of Sockets Air- Watts
Conditioners
1 4 1 191
2 4 1 273
3 4 1 309
4 4 1 238
40
CHAPTER FOUR
CONCLUSION AND RECOMMENDATION
From the foregoing it can be concluded that a proper design must be prepared to meet both the
standard and client requirements. Planning is also very important so that the workflow does not
get affected by improper planning which could be expensive and time-consuming. The design has
been considered essential in instances where a different contractor has to use his own technicians
to carry out the site layout and installations. Furthermore, time and resources are saved during
routine maintenance as it becomes clear from the design the affected circuit as well as the particular
4.1 Recommendation
It is here recommended that other schedules be included in the electrical design of residential
41
CHAPTER FIVE
42
15 Water Heater 25,000 1 25,000
17 Sand 2,500
20 Total 314,750
43
REFERENCES
https://www.wbdg.org/design/dd_electricaleng.php. Assessed 15/09/2016 3:04p.m.
http://www1.rmit.edu.au/courses/047059. Assessed 15/09/2016 5:12p.m.
Gupta, J.B. (2010). A Textbook of Electrical Technology, Student Edition. Kataria & Sons, New
Delhi.
UNEP report (2006). Energy Efficiency Guide for Industry in Asia. SCHAND, Vol II pp. 341-
342.
Vatapoulos K., Andrews D., Carlson J., Papaioannou I. and Zubi G. (2012). Study on the State of
Planning of Energy Efficiency of Heat and Electricity Production Technologies. JRC Scientific
and Policy Reports.
44