Sunteți pe pagina 1din 128

SECOND DIVISION make their own arrangements to resolve their disputes.

Towards this end, the State shall encourage and actively


[ G.R. No. 225051, July 19, 2017 ]
promote the use of Alternative Dispute Resolution as an
DEPARTMENT OF FOREIGN AFFAIRS (DFA), PETITIONER, important means to achieve speedy and impartial justice
VS. BCA INTERNATIONAL CORPORATION & AD HOC and declog court dockets. Same; Same; Same;
ARBITRAL TRIBUNAL, COMPOSED OF CHAIRMAN DANILO Alternative Dispute Resolution Act of 2004; Court
L. CONCEPCION AND MEMBERS, CUSTODIO O. PARLADE intervention is allowed under Republic Act (RA) No. 9285
AND ANTONIO P. JAMON, JR., RESPONDENTS. in the following instances: (1) when a party in the
arbitration proceedings requests for an interim measure
of protection; (2) judicial review of arbitral awards by
Civil Law; Contracts; Established in this jurisdiction is the the Regional Trial Court (RTC); and (3) appeal from the
rule that the law of the place where the contract is made RTC decisions on arbitral awards to the Court of Appeals
governs, or lex loci contractus.—Under Article 33 of the (CA).—Court intervention is allowed under RA No. 9285
UNCITRAL Arbitration Rules governing the parties, “the in the following instances: (1) when a party in the
arbitral tribunal shall apply the law designated by the arbitration proceedings requests for an interim measure
parties as applicable to the substance of the dispute.” of protection; (2) judicial review of arbitral awards by
“Failing such designation by the parties, the arbitral the Regional Trial Court (RTC); and (3) appeal from the
tribunal shall apply the law determined by the conflict of RTC decisions on arbitral awards to the Court of Appeals.
laws rules which it considers applicable.” Established in
this jurisdiction is the rule that the law of the place
where the contract is made governs, or lex loci
Same; Same; Same; Same; Remedies Through Which
contractus. As the parties did not designate the
Court Intervention is the Special Alternative Dispute
applicable law and the Agreement was perfected in the
Resolution (ADR) Rules is Allowed.—Court intervention in
Philippines, our Arbitration laws, particularly, RA No.
the Special ADR Rules is allowed through these
876, RA No. 9285 and its IRR, and the Special ADR Rules
remedies: (1) Specific Court Relief, which includes
apply. The IRR of RA No. 9285 provides that “[t]he
Judicial Relief Involving the Issue of Existence, Validity
arbitral tribunal shall decide the dispute in accordance
and Enforceability of the Arbitral Agreement, Interim
with such law as is chosen by the parties. In the absence
Measures of Protection, Challenge to the Appointment of
of such agreement, Philippine law shall apply.”
Arbitrator, Termination of Mandate of Arbitrator,
Assistance in Taking Evidence, Confidentiality/Protective
Orders, Confirmation, Correction or Vacation of Award in
Same; Arbitration; Alternative Dispute Resolution; The Domestic Arbitration, all to be filed with the RTC; (2) a
State shall encourage and actively promote the use of motion for reconsideration may be filed by a party with
Alternative Dispute Resolution (ADR) as an important the RTC on the grounds specified in Rule 19.1; (3) an
means to achieve speedy and impartial justice and appeal to the Court of Appeals through a petition for
declog court dockets.—RA No. 9285 declares the policy of review under Rule 19.2 or through a special civil action
the State to actively promote party autonomy in the for certiorari under Rule 19.26; and (4) a petition for
resolution of disputes or the freedom of the parties to certiorari with the Supreme Court from a judgment or
final order or resolution of the Court of Appeals, raising In an Amended Build-Operate-Transfer (BOT)
only questions of law. Agreement[1] dated April 5, 2002 (Agreement), petitioner DFA
awarded the Machine Readable Passport and Visa Project
(MRP/V Project) to respondent BCA International Corporation.
Remedial Law; Civil Procedure; Appeals; Petition for In the course of implementing the MRPN Project, conflict arose
Review on Certiorari; An appeal by certiorari to the and petitioner sought to terminate the Agreement.
Supreme Court (SC) is from a judgment or final order or
resolution of the Court of Appeals (CA) and only Respondent opposed the termination and filed a Request for
questions of law may be raised.—It is clear that an Arbitration on April 20, 2006. The Arbitral Tribunal was
appeal by certiorari to the Supreme Court is from a constituted on June 29, 2009.[2]
judgment or final order or resolution of the Court of
Appeals and only questions of law may be raised. There In its Statement of Claims[3] dated August 24, 2009,
have been instances when we overlooked the rule on respondent sought the following reliefs against petitioner: (a) a
hierarchy of courts and took cognizance of a petition for judgment nullifying and setting aside the Notice of Termination
certiorari alleging grave abuse of discretion by the dated December 9, 2005 of the DFA, including its demand to
Regional Trial Court when it granted interim relief to a BCA to pay liquidated damages equivalent to the corresponding
party and issued an Order assailed by the petitioner, performance security bond posted by BCA; (b) a judgment
considering the transcendental importance of the issue confirming the Notice of Default dated December 22, 2005
involved therein or to better serve the ends of justice issued by BCA to the DFA and ordering the DFA to perform its
when case is determined on the merits rather on obligation under the Amended BOT Agreement dated April 5,
technicality. However, in this case, the appeal by 2002 by approving the site of the Central Facility at the Star
certiorari is not from a final Order of the Court of Appeals Mall Complex in Shaw Boulevard, Mandaluyong City, within five
or the Regional Trial Court, but from an interlocutory days from receipt of the Arbitral Award; (c) a judgment
order of the Arbitral Tribunal; hence, the petition must ordering the DFA to pay damages to BCA, reasonably estimated
be dismissed at P100,000,000.00 as of this date, representing lost business
DECISION opportunities; financing fees, costs and commissions; travel
expenses; legal fees and expenses; and cost of arbitration,
PERALTA, J.: including the fees of the members of the Arbitral Tribunal; and
(d) other just or equitable relief.
This is a petition for certiorari under Rule 65 of the Rules of
Court, seeking to annul and set aside Procedural Order No. 11
On October 5, 2013, respondent manifested that it shall file an
dated February 15, 2016 and Procedural Order No. 12 dated
Amended Statement of Claims so that its claim may conform to
June 8, 2016, both issued by the UNCITRAL Ad Hoc Arbitral
the evidence they have presented.[4]
Tribunal in the arbitration proceedings between petitioner
Department of Foreign Affairs (DFA) and respondent BCA
Petitioner opposed respondent's manifestation, arguing that
International Corporation.
such amendment at the very late stage of the proceedings will
cause undue prejudice to its interests. However, the Arbitral
The facts are as follows:
Tribunal gave respondent a period of time within which to file
its Amended Statement of Claims and gave petitioner time to premise that respondent would no longer present any additional
formally interpose its objections.[5] evidence in-chietPetitioner was given a period of 20 days from
receipt of the Order to file its Answer to the Amended
In the Amended Statement of Claims[6] dated October 25, Statement of Claims and to manifest before the Tribunal if it
2013, respondent interposed the alternative relief that, in the will present additional evidence in support of its Amended
event specific performance by petitioner was no longer Answer in order for the Tribunal to act accordingly.
possible, petitioner prayed that the Arbitral Tribunal shall
render judgment ordering petitioner to pay respondent Procedural Order No. 11 reads:
P1,648,611,531.00, representing the net income respondent is
For resolution by the Tribunal is BCA's Motion to Admit the
expected to earn under the Agreement, and P100,000,000.00
Amended Statement of Claim dated 30 April2015 objected to by
as exemplary, temperate or nominal damages.[7]
DFA in its Opposition dated 6 November 2015.
In an Opposition dated December 19, 2013, petitioner objected
BCA's Counsel made representations during the hearings that
to respondent's Amended Statement of Claims, averring that its
the Amendment is for the simple purpose of making the
belated filing violates its right to due process and will prejudice
Statement of Claim conform with what BCA believes it was able
its interest and that the Tribunal has no jurisdiction over the
to prove in the course of the proceedings and that the
alternative reliefs sought by respondent.[8]
Amendment will no longer require the presentation of any
additional evidence-in-chief.
On August 6, 2014, respondent filed a Motion to Withdraw
Amended Statement of Claims[9] in the light of petitioner's
Without ruling on what BCA was able to prove, the Tribunal
opposition to the admission of the Amended Statement of
hereby grants the Motion to Admit on the premise that BCA will
Claims and to avoid further delay in the arbitration of its claims,
no longer present any additional evidence-in-chief to prove the
without prejudice to the filing of such claims for liquidated and
bigger claim in the Amended Statement.
other damages at the appropriate time and proceeding.
Thereafter, respondent filed a motion to resume proceedings.
For the additional claim of 300 million pesos, BCA should pay
the additional fee of 5% or 15 million pesos. Having paid 12
However, on May 4, 2015, respondent filed anew a Motion to
million pesos, the balance of 3 million pesos shall be payable
Admit Attache,d Amended Statement of Claims dated April 30,
upon submission of this case for resolution. No award shall be
2015, increasing the actual damages sought to
issued and promulgated by the Tribunal unless the balance of
P390,000,000.00, plus an additional P10,000,000.00 for
40% in the Arbitrators' fees for the original Claim and
exemplary, temperate or nominal damages.[10]
Counterclaim, respectively, and the balance of 3 million for the
Amended Claim, are all fully paid by the parties.
On November 6, 2015, petitioner filed an Opposition to the
Motion to Admit Attached Amended Statement of Claims.
DFA is hereby given the period of 20 days from receipt of this
Order to file its Answer to the Amended Statement of
In Procedural Order No. 11 dated F bruary 15, 2016, the
[11]
Complaint, and to manifest before this Tribunal if it will present
Arbitral Tribunal granted respondent's Motion to Admit Attached
Amended Statement of Claims dated April 30, 2015 on the
additional evidence in support of its Amended Answer in order the Parties in their pleadings, the Tribunal hereby decides to
for the Tribunal to act accordingly.[12] allow the submission of additional documentary evidence by
any Party in support of its position in relation to the Amended
On February 18, 2016, respondent filed a Motion for Partial
Statement of Claims and to which the other may submit its
Reconsideration[13] of Procedural Order No. 11 and prayed for
comments or objections. The Tribunal, however, will still not
the admission of its Amended Statement of Claims by the
allow the taking of testimonial evidence from any witness by
Arbitral Tribunal without denying respondent's right to present
any Party. The Tribunal allowed the amendment of the
evidence on the actual damages, such as attorney's fees and
Statement of Claims but only for the purpose of making the
legal cost that it continued to incur.
Statement of Claims conform with the evidence that had
already been presented, assuming that, indeed, it was the case.
On February 19, 2016, petitioner filed a Motion for
In resting its case, Respondent must have already dealt with
Reconsideration of Procedural Order No. 11 and, likewise, filed
and addressed the evidence that had already been presented
a Motion to Suspend Proceedings dated February 19, 2016.
by Claimant and that allegedly supports the amended Claim.
Further, on February 29, 2016, petitioner filed its
However, in order to give the Parties more opportunity to prove
Comment/Opposition to respondent's Motion for Partial
their respective positions, additional evidence shall be accepted
Reconsideration of Procedural Order No. 11.
by the Tribunal, but only documentary evidence.

The Arbitral Tribunal, thereafter, issued Procedural Order No.


Wherefore, Procedural Order No. 11 is modified accordingly.
12 dated June 8, 2016, which resolved respondent's Motion for
The Claimant is given until 25 June 2016 to submit its
Partial Reconsideration of Procedural Order No. 11, disallowing
additional documentary evidence in support of the Amended
the presentation of additional evidence-in-chief by respondent
Statement of Claims. Respondent is given until 15 July 2016 to
to prove the increase in the amount of its claim as a limitation
file its Answer to the Amended Statement of Claims, together
to the Tribunals' decision granting respondent's Motion to
with all the documentary evidence in support of its position.
Amend its Statement of Claims. In Procedural Order No. 12, the
Claimant is given until 30 July 2016 to comment or oppose the
Tribunal directed the parties to submit additional documentary
Answer and the supporting documentary evidence, while
evidence in support of their respective positions in relation to
Respondent is given until 14 August 2016 to file its comment or
the Amended Statement of Claims and to which the other party
opposition to the Claimant's submission, together with any
may submit its comment or objections.
supporting documentary evidence. Thereafter, hearing of the
case shall be deemed terminated. The periods allowed herein
Procedural Order No. 12 reads:
are non-extendible and the Tribunal will not act on any motion
For resolution is the partial Motion for Reconsideration of the for extension of time to comply.
Tribunal's Procedural Order No. 11 disallowing the presentation
of additional evidence-in-chief by Claimant to prove the The Parties shall submit their Formal Offer of Evidence, in the
increase in the amount of its Claim as a limitation to this manner previously agreed upon, on 20 September 2016 while
Tribunal's decision granting Claimant's Motion to Amend its their respective Memorandum shall be filed on 20 October
Statement of Claims. 2016. The Reply Memoranda of the Parties shall be filed on 20
November 2016. Thereafter, with or without the foregoing
After a careful consideration of all the arguments presented by
submissions, the case shall be deemed submitted for IV. PROCEDURAL ORDER NO. 12 DATED 8 JUNE 2016
Resolution.[14] VIOLATES PETITIONER DFA'S RIGHT TO DUE
PROCESS.[16]
As Procedural Order No. 12 denied petitioner's motion for
reconsideration of Procedural Order No. 11, petitioner filed this Petitioner states that Article 20 of the 1976 UNCITRAL
petition for certiorari under Rule 65 of the Rules of Court with Arbitration Rules grants a tribunal the discretion to deny a
application for issuance of a temporary restraining order and/or motion to amend where the tribunal "considers it inappropriate
writ of preliminary injunction, seeking to annul and set aside to allow such amendment having regard to the delay in making
Procedural Order No. 11 dated February 15, 2016 and it or prejudice to the other party or any other circumstances." It
Procedural Order No. 12 dated June 8, 2016. further proscribes an amendment where "the amended claim
falls outside the scope of the arbitral clause or separate
Petitioner stated that it opted to file the petition directly with arbitration agreement."
this court in view of the immensity of the claim concerned,
significance of the public interest involved in this case, and the Petitioner contends that respondent's Motion to Admit Attached
circumvention of the temporary restraining order issued by this Amended Statement of Claims dated April 30, 2015 should
Court in Department of Foreign Affairs v. BCA International have been denied by the Arbitral Tribunal as there has been
Corporation, docketed as G.R. No. 210858. It cited Department delay and prejudice to it. Moreover, other circumstances such
of Foreign Affairs, et al. v. Hon. Judge Falcon,[15] wherein the as fair and efficient administration of the proceedings should
Court overlooked the rule on hierarchy of courts and took have warranted the denial of the motion to amend. Finally, the
cognizance of the petition for certiorari. Arbitral Tribunal did not have jurisdiction over the amended
claims.
Petitioner raised these issues:
Petitioner prays that a temporary restraining order and/or writ
THE AD HOC ARBITRAL TRIBUNAL COMMITTED GRAVE ABUSE
of preliminary injunction be issued enjoining the Arbitral
OF DISCRETION AMOUNTING TO LACK OR EXCESS OF
Tribunal from implementing Procedural Order No. 11 dated
JURISDICTION WHEN IT ADMITTED THE AMENDED STATEMENT
February 15, 2016 and Procedural Order No. 12 dated June 8,
OF CLAIMS DATED 30 APRIL 2015 NOTWITHSTANDING THAT:
2016; that the said Procedural Orders be nullified for having
I. THE AMENDMENT CAUSES UNDUE DELAY AND been rendered in violation of the 1976 UNCITRAL Arbitration
PREJUDICE TO PETITIONER DFA; Rules and this Court's Resolution dated April 2, 2014 rendered
in G.R. No. 210858; that respondent's Amended Statement of
II. THE ALTERNATIVE RELIEF IN THE AMENDED Claims dated April 30, 2015 be denied admission; and, if this
STATEMENT OF CLAIMS FALLS OUTSIDE THE SCOPE OF Court affirms the admission of respondent's Amended
THE ARBITRATION CLAUSE; HENCE, OUTSIDE THE Statement of Claims, petitioner be allowed to present
JURISDICTION OF THE AD HOC ARBITRAL TRIBUNAL; testimonial evidence to refute the allegations and reliefs in the
Amended Statement of Claims and to prove its additional
III. THE AMENDMENT CIRCUMVENTS THE TEMPORARY
defenses or claims in its Answer to the Amended Statement of
RESTRAINING ORDER DATED 02 APRIL 2014 ISSUED BY
Claims or Amended Statement of Defense with Counterclaims.
THIS HONORABLE COURT IN G.R. NO. 210858; AND
Petitioner contends that the parties in this case have agreed to determine whether the documents and records sought to be
refer any dispute to arbitration under the 1976 UNCITRAL subpoenaed are protected by the deliberative process privilege
Arbitration Rules and to compel a party to be bound by the as explained in the Decision.
application of a different rule on arbitration such as the
Alternative Dispute Resolution (ADR) Act of 2004 or Republic The issues to be resolved at the outset are which laws apply to
Act (RA) No. 9285 transgresses such vested right and amounts the arbitration proceedings and whether the petition filed before
to vitiation of consent to participate in the arbitration the Court is proper.
proceedings.
The Agreement provides for the resolution of dispute between
In its Comment, respondent contends that this Court has no the parties in Section 19.02 thereof, thus:
jurisdiction to intervene in a private arbitration, which is a
If the Dispute cannot be settled amicably within ninety (90)
special proceeding governed by the ADR Act of 2004, its
days by mutual discussion as contemplated under Section
Implementing Rules and Regulations (IRR) and the Special
19.01 herein, the Dispute shall be settled with finality by an
Rules of Court on Alternative Dispute Resolution (Special ADR
arbitrage tribunal operating under International Law,
Rules).
hereinafter referred to as the "Tribunal," under the UNCITRAL
Arbitration Rules contained in Resolution 31/98 adopted by the
Respondent avers that petitioner's objections to the admission
United Nations General Assembly on December 15, 1976, and
of its Amended Statement of Claims by the Arbitral Tribunal,
entitled "Arbitration Rules on the United Nations Commission on
through the assailed Procedural Order Nos. 11 and 12, are
the International Trade Law." The DFA and BCA undertake to
properly within the competence and jurisdiction of the Arbitral
abide by and implement the arbitration award. The place of
Tribunal to resolve. The Arbitral Tribunal derives their authority
arbitration shall be Pasay City, Philippines, or such other place
to hear and resolve the parties' dispute from the contractual
as may mutually be agreed upon by both parties. The
consent of the parties expressed in Section 19.02 of the
Arbitration proceeding shall be conducted in the English
Agreement.
language.
In a Resolution dated July 25, 2016, the Court resolved to note Under Article 33 of the UNCITRAL Arbitration Rules governing
the Office of the Solicitor General's Very Urgent Motion for the the parties, "the arbitral tribunal shall apply the law designated
Issuance of a Temporary Restraining Order and/or Writ of by the parties as applicable to the substance of the dispute."
Preliminary Injunction dated July 5, 2016. "Failing such designation by the parties, the arbitral tribunal
shall apply the law determined by the conflict of laws rules
In regard to the allegation that the Amended Statement of which it considers applicable." Established in this jurisdiction is
Claims circumvents the temporary restraining order dated April the rule that the law of the place where the contract is made
2, 2014 issued by the Court in DFA v. BCA International governs, or lex loci contractus.[17] As the parties did not
Corporation, docketed as G.R. No. 210858, it should be pointed designate the applicable law and the Agreement was perfected
out that the said temporary restraining order has been in the Philippines, our Arbitration laws, particularly, RA No.
superseded by the Court's Decision promulgated on June 29, 876,[18] RA No. 9285[19] and its IRR, and the Special ADR Rules
2016, wherein the Court resolved to partially grant the petition apply.[20] The IRR of RA No. 9285 provides that "[t]he arbitral
and remand the case to the RTC of Makati City, Branch 146, to tribunal shall decide the dispute in accordance with such law as
is chosen by the parties. In the absence of such agreement,
Philippine law shall apply."[21] Court intervention is allowed under RA No. 9285 in the
following instances: (1) when a party in the arbitration
In another earlier case filed by petitioner entitled Department proceedings requests for an interim measure of
of Foreign Affairs v. BCA International Corporation,[22] docketed protection;[25] (2) judicial review of arbitral awards[26] by the
as G.R. No. 210858, petitioner also raised as one of its issues Regional Trial Court (RTC); and (3) appeal from the RTC
that the 1976 UNCITRAL Arbitration Rules and the Rules of decisions on arbitral awards to the Court of Appeals.[27]
Court apply to the present arbitration proceedings, not RA No.
9285 and the Special ADR Rules. We ruled therein thus: The extent of court intervention in domestic arbitration is
specified in the IRR ofRA No. 9285, thus:
Arbitration is deemed a special proceeding and governed by the
special provisions of RA 9285, its IRR, and the Special ADR Art. 5.4. Extent of Court Intervention. In matters governed by
Rules. RA 9285 is the general law applicable to all matters and this Chapter, no court shall intervene except in accordance with
controversies to be resolved through alternative dispute the Special ADR Rules.
resolution methods. While enacted only in 2004, we held that
Court intervention in the Special ADR Rules is allowed through
RA 9285 applies to pending arbitration proceedings since it is a
these remedies: (1) Specific Court Relief, which includes
procedural law, which has retroactive effect.
Judicial Relief Involving the Issue of Existence, Validity and
Enforceability of the Arbitral Agreement,[28] Interim Measures of
xxxx
Protection,[29] Challenge to the Appointment of
Arbitrator,[30] Termination of Mandate of
The IRR of RA 9285 reiterate that RA 9285 is procedural in
Arbitrator,[31] Assistance in Taking
character and applicable to all pending arbitration proceedings.
Evidence,[32] Confidentiality/Protective Orders,[33] Confirmation,
Consistent with Article 2046 of the Civil Code, the Special ADR
Correction or Vacation of Award in Domestic Arbitration,[34] all
Rules were formulated and were also applied to all pending
to be filed with the RTC; (2) a motion for reconsideration may
arbitration proceedings covered by RA 9285, provided no
be filed by a party with the RTC on the grounds specified in
vested rights are impaired. Thus, contrary to DFA's contention,
Rule 19.1; (3) an appeal to the Court of Appeals through a
RA 9285, its IRR, and the Special ADR Rules are applicable to
petition for review under Rule 19.2 or through a special civil
the present arbitration proceedings. The arbitration between
action for certiorari under Rule 19.26; and (4) a petition
the OFA and BCA is still pending, since no arbitral award has
for certiorari with the Supreme Court from a judgment or final
yet been rendered. Moreover, DFA did not allege any vested
rights impaired by the application of those procedural rules. order or resolution of the Court of Appeals, raising only
questions of law.
RA No. 9285 declares the policy of the State to actively
promote party autonomy in the resolution of disputes or the Under the Special ADR Rules, review by the Supreme Court of
freedom of the parties to make their own arrangements to an appeal by certiorari is not a matter of right, thus:
resolve their disputes.[23] Towards this end, the State shall
RULE 19.36. Review Discretionary. - A review by the Supreme
encourage and actively promote the use of Alternative Dispute
Court is not a matter of right, but of sound judicial discretion,
Resolution as an important means to achieve speedy and
which will be granted only for serious and compelling reasons
impartial justice and declog court docl [24]
resulting in grave prejudice to the aggrieved party. The RULE 19.37. Filing of Petition with Supreme Court. - A party
following, while neither controlling nor fully measuring the desiring to appeal by certiorari from a judgment or final order
court's discretion, indicate the serious and compelling, and or resolution of the Court of Appeals issued pursuant to these
necessarily, restrictive nature of the grounds that will warrant Special ADR Rules may file with the Supreme Court a verified
the exercise of the Supreme Court's discretionary powers, when petition for review on certiorari. The petition shall raise only
the Court of Appeals: questions of law, which must be distinctly set forth.

a. Failed to apply the applicable standard or test for judicial It is clear that an appeal by certiorari to the Supreme Court is
review prescribed in these Special ADR Rules in arriving at its from a judgment or final order or resolution of the Court of
decision resulting in substantial prejudice to the aggrieved Appeals and only questions of law may be raised. There have
party; been instances when we overlooked the rule on hierarchy of
courts and took cognizance of a petition for certiorari alleging
b. Erred in upholding a final order or decision despite the lack grave abuse of discretion by the Regional Trial Court when it
of jurisdiction of the court that rendered such final order or granted interim relief to a party and issued an Order assailed
decision; by the petitioner, considering the transcendental importance of
the issue involved therein[35] or to better serve the ends of
c. Failed to apply any provision, principle, policy or rule justice when the case is determined on the merits rather on
contained in these Special ADR Rules resulting in substantial technicality.[36] However, in this case, the appeal by certiorari is
prejudice to the aggrieved party; and not from a final Order of the Court of Appeals or the Regional
Trial Court, but from an interlocutory order of the Arbitral
d. Committed an error so egregious and harmful to a party as Tribunal; hence, the petition must be dismissed.
to amount to an undeniable excess of jurisdiction.
WHEREFORE, the Court resolves to DISMISS the pet1t1on for
The mere fact that the petitioner disagrees with the Court of
failure to observe the rules on court intervention allowed by RA
Appeals' determination of questions of fact, of law or both
No. 9285 and the Special ADR Rules, specifically Rule 19.36
questions of fact and law, shall not warrant the exercise of the
and Rule 19.37 of the latter, in the pending arbitration
Supreme Court's discretionary power. The error imputed to the
proceedings of the parties to this case.
Court of Appeals must be grounded upon any of the above
SO ORDERED.
prescribed grounds for review or be closely analogous thereto.

A mere general allegation that the Court of Appeals has


committed serious and substantial error or that it has acted
with grave abuse of discretion resulting in substantial prejudice
to the petitioner without indicating with specificity the nature of
such error or abuse of discretion and the serious prejudice
suffered by the petitioner on account thereof, shall constitute
sufficient ground for the Supreme Court to dismiss outright the
petition.
[G.R. No. 135362. December 13, 1999.] enforce them to the same extent as the assignor could have
enforced them against the debtor or in this case, against the
HEIRS OF AUGUSTO L. SALAS, JR., namely: TERESITA D. heirs of the original party to the Agreement.
SALAS for herself and as legal guardian of the minor
FABRICE CYRILL D. SALAS, MA. CRISTINA S. LESACA, and DECISION
KARINA TERESA D. SALAS, Petitioners, v. LAPERAL
REALTY CORPORATION, ROCKWAY REAL ESTATE
CORPORATION, SOUTH RIDGE VILLAGE, INC., DE LEON, JR., J.:
MAHARAMI DEVELOPMENT CORPORATION, Spouses
THELMA D. ABRAJANO and GREGORIO ABRAJANO,
OSCAR DACILLO, Spouses VIRGINIA D. LAVA and RODEL Before us is a petition for review on certiorari of the Order 1 of
LAVA, EDUARDO A. VACUNA, FLORANTE DE LA CRUZ, Branch 85 of the Regional Trial Court of Lipa City 2 dismissing
JESUS VICENTE B. CAPELLAN, and the REGISTER OF petitioners’ complaint 3 for rescission of several sale
DEEDS FOR LIPA CITY, Respondents. transactions involving land owned by Augusto L. Salas, Jr., their
predecessor-in-interest, on the ground that they failed to first
Remedial Law; Arbitration; Court has recognized arbitration resort to arbitration.cralawnad
agreements as valid, binding, enforceable and not contrary to
public policy.—In a catena of cases inspired by Justice Salas, Jr. was the registered owner of a vast tract of land in
Malcolm’s provocative dissent in Vega v. San Carlos Milling Co., Lipa City, Batangas spanning 1,484,354 square meters.
this Court has recognized arbitration agreements as valid,
binding, enforceable and not contrary to public policy so much On May 15, 1987, he entered into an Owner-Contractor
so that when there obtains a written provision for arbitration Agreement 4 (hereinafter referred to as the Agreement) with
which is not complied with, the trial court should suspend the respondent Laperal Realty Corporation (hereinafter referred to
proceedings and order the parties to proceed to arbitration in as Laperal Realty) to render and provide complete (horizontal)
accordance with the terms of their agreement. Arbitration is the construction services on his land.
“wave of the future” in dispute resolution. To brush aside a
contractual agreement calling for arbitration in case of On September 23, 1988, Salas, Jr. executed a Special Power of
disagreement between parties would be a step backward. Attorney in favor of respondent Laperal Realty to exercise
general control, supervision and management of the sale of his
Same; Same; As a contract, the Agreement containing the land, for cash or on installment basis.
stipulation on arbitration, binds the parties thereto, as well as
their assigns and heirs.—A submission to arbitration is a On June 10, 1989, Salas, Jr. left his home in the morning for a
contract. As such, the Agreement, containing the stipulation on business trip to Nueva Ecija. He never returned.chanrobles.com
arbitration, binds the parties thereto, as well as their assigns : virtual law library
and heirs. But only they. Petitioners, as heirs of Salas, Jr., and
respondent Laperal Realty are certainly bound by the On August 6, 1996, Teresita Diaz Salas filed with the Regional
Agreement. If respondent Laperal Realty had assigned its rights Trial Court of Makati City a verified petition for the declaration
under the Agreement to a third party, making the former, the of presumptive death of her husband, Salas, Jr., who had then
assignor, and the latter, the assignee, such assignee would also been missing for more than seven (7) years. It was granted on
be bound by the arbitration provision since assignment involves December 12, 1996. 5
such transfer of rights as to vest in the assignee the power to
Meantime, respondent Laperal Realty subdivided the land of the foregoing arbitration clause.
Salas, Jr. and sold subdivided portions thereof to respondents
Rockway Real Estate Corporation and South Ridge Village, Inc. Hence this petition.chanrobles.com : virtual law library
on February 22, 1990; to respondent spouses Abrajano and
Lava and Oscar Dacillo on June 27, 1991; and to respondents Petitioners argue, thus:jgc:chanrobles.com.ph
Eduardo Vacuna, Florante de la Cruz and Jesus Vicente Capalan
on June 4, 1996 (all of whom are hereinafter referred to as "The petitioners’ causes of action did not emanate from the
respondent lot buyers). Owner-Contractor Agreement."cralaw virtua1aw library

On February 3, 1998, petitioners as heirs of Salas, Jr. filed in "The petitioners’ causes of action for cancellation of contract
the Regional Trial Court of Lipa City a Complaint 6 for and accounting are covered by the exception under the
declaration of nullity of sale, reconveyance, cancellation of Arbitration Law."cralaw virtua1aw library
contract, accounting and damages against herein respondents
which was docketed as Civil Case No. 98-0047.chanrobles law "Failure to arbitrate is not a ground for dismissal." 10
library : red
In a catena of cases 11 inspired by Justice Malcolm’s
On April 24, 1998, respondent Laperal Realty filed a Motion to provocative dissent in Vega v. San Carlos Milling Co. 12 , this
Dismiss 7 on the ground that petitioners failed to submit their Court has recognized arbitration agreements as valid, binding,
grievance to arbitration as required under Article VI of the enforceable and not contrary to public policy so much so that
Agreement which provides:jgc:chanrobles.com.ph when there obtains a written provision for arbitration which is
not complied with, the trial court should suspend the
"ARTICLE VI. ARBITRATION. proceedings and order the parties to proceed to arbitration in
accordance with the terms of their agreement. 13 Arbitration is
All cases of dispute between CONTRACTOR and OWNER’S the "wave of the future" in dispute resolution. 14 To brush
representative shall be referred to the committee represented aside a contractual agreement calling for arbitration in case of
by:chanrob1es virtual 1aw library disagreement between parties would be a step backward. 15

a. One representative of the OWNER; Nonetheless, we grant the petition.cralawnad

b. One representative of the CONTRACTOR; A submission to arbitration is a contract. 16 As such, the


Agreement, containing the stipulation on arbitration, binds the
c. One representative acceptable to both OWNER and parties thereto, as well as their assigns and heirs. 17 But only
CONTRACTOR." 8 they. Petitioners, as heirs of Salas, Jr., and respondent Laperal
Realty are certainly bound by the Agreement. If respondent
On May 5, 1998, respondent spouses Abrajano and Lava and Laperal Realty had assigned its rights under the Agreement to a
respondent Dacillo filed a Joint Answer with Counterclaim and third party, making the former, the assignor, and the latter, the
Crossclaim 9 praying for dismissal of petitioners’ Complaint for assignee, such assignee would also be bound by the arbitration
the same reason. provision since assignment involves such transfer of rights as to
vest in the assignee the power to enforce them to the same
On August 9, 1998, the trial court issued the herein assailed extent as the assignor could have enforced them against the
Order dismissing petitioners’ Complaint for non-compliance with debtor 18 or in this case, against the heirs of the original party
to the Agreement. However, respondents Rockway Real Estate procedure and unnecessary delay. On the other hand, it would
Corporation, South Ridge Village, Inc., Maharami Development be in the interest of justice if the trial court hears the complaint
Corporation, spouses Abrajano, spouses Lava, Oscar Dacillo, against all herein respondents and adjudicates petitioners’
Eduardo Vacuna, Florante de la Cruz and Jesus Vicente Capellan rights as against theirs in a single and complete proceeding.
are not assignees of the rights of respondent Laperal Realty
under the Agreement to develop Salas, Jr.’s land and sell the WHEREFORE, the instant petition is hereby GRANTED. The
same. They are, rather, buyers of the land that respondent Order dated August 19, 1998 of Branch 85 of the Regional Trial
Laperal Realty was given the authority to develop and sell Court of Lipa City is hereby NULLIFIED and SET ASIDE. Said
under the Agreement. As such, they are not "assigns" court is hereby ordered to proceed with the hearing of Civil
contemplated in Art. 1311 of the New Civil Code which provides Case No. 98-0047.
that "contracts take effect only between the parties, their
assigns and heirs" . Costs against private respondents.chanrobles.com.ph : virtual
law library
Petitioners claim that they suffered lesion of more than one-
fourth (1/4) of the value of Salas, Jr.’s land when respondent SO ORDERED.
Laperal Realty subdivided it and sold portions thereof to
respondent lot buyers. Thus, they instituted action 19 against
both respondent Laperal Realty and respondent lot buyers for
rescission of the sale transactions and reconveyance to them of
the subdivided lots. They argue that rescission, being their
cause of action, falls under the exception clause in Sec. 2 of
Republic Act No. 876 which provides that "such submission [to]
or contract [of arbitration] shall be valid, enforceable and
irrevocable, save, upon such grounds as exist at law for the
revocation of any contract" .

The petitioners’ contention is without merit. For while


rescission, as a general rule, is an arbitrable issue, 20 they
impleaded in the suit for rescission the respondent lot buyers
who are neither parties to the Agreement nor the latter’s
assigns or heirs. Consequently, the right to arbitrate as
provided in Article VI of the Agreement was never vested in
respondent lot buyers.chanroblesvirtual|awlibrary

Respondent Laperal Realty, as a contracting party to the


Agreement, has the right to compel petitioners to first arbitrate
before seeking judicial relief. However, to split the proceedings
into arbitration for respondent Laperal Realty and trial for the
respondent lot buyers, or to hold trial in abeyance pending
arbitration between petitioners and respondent Laperal Realty,
would in effect result in multiplicity of suits, duplicitous
[G.R. No. 115412. November 19, 1999.] proceedings as required by the PCHC rules and regulations, and
pending arbitration has sought relief from the trial court for
HOME BANKERS SAVINGS AND TRUST measures to safeguard and/or conserve the subject of the
COMPANY, Petitioner, v. COURT OF APPEALS and FAR dispute under arbitration, as sanctioned by section 14 of the
EAST BANK & TRUST CO., INC., Respondents. Arbitration Law, and otherwise not shown to be contrary to the
Actions; Arbitration Law (R.A. 876); Section 14 of Republic Act PCHC rules and regulations.
876, otherwise known as the Arbitration Law, allows any party
to the arbitration proceeding to petition the court to take Same; Same; Arbitration, as an alternative method of dispute
measures to safeguard and/or conserve any matter which is the resolution, is encouraged.—At this point, we emphasize that
subject of the dispute in arbitration.—We find no merit in the arbitration, as an alternative method of dispute resolution, is
petition. Section 14 of Republic Act 876, otherwise known as encouraged by this Court. Aside from unclogging judicial
the Arbitration Law, allows any party to the arbitration dockets, it also hastens solutions especially of commercial
proceeding to petition the court to take measures to safeguard disputes. The Court looks with favor upon such amicable
and/or conserve any matter which is the subject of the dispute arrangement and will only interfere with great reluctance to
in arbitration, thus: Section 14. Subpoena and subpoena duces anticipate or nullify the action of the arbitrator
tecum.—Arbitrators shall have the power to require any person DECISION
to attend a hearing as a witness. They shall have the power to
subpoena witnesses and documents when the relevancy of the
testimony and the materiality thereof has been demonstrated BUENA, J.:
to the arbitrators. Arbitrators may also require the retirement
of any witness during the testimony of any other witness. All of
the arbitrators appointed in any controversy must attend all the This appeal by certiorari under Rule 45 of the Rules of Court
hearings in that matter and hear all the allegations and proofs seeks to annul and set aside the decision 1 of the Court of
of the parties; but an award by the majority of them is valid Appeals 2 dated January 21, 1994 in CA-G.R. SP No. 29725,
unless the concurrence of all of them is expressly required in dismissing the petition for certiorari filed by petitioner to annul
the submission or contract to arbitrate. The arbitrator or the two (2) orders issued by the Regional Trial Court of Makati
arbitrators shall have the power at any time, before rendering 3 in Civil Case No. 92-145, the first, dated April 30, 1992,
the award, without prejudice to the rights of any party to denying petitioner’s motion to dismiss and the second, dated
petition the court to take measures to safeguard and/or October 1, 1992 denying petitioner’s motion for reconsideration
conserve any matter which is the subject of the dispute in thereof.chanroblesvirtuallawlibrary
arbitration.
The pertinent facts may be briefly stated as follows: Victor
Same; Same; Banks and Banking; Philippine Clearing House Tancuan, one of the defendants in Civil Case No. 92-145, issued
Corporation; Participants in the regional clearing operations of Home Bankers Savings and Trust Company (HBSTC) check No.
the Philippine Clearing House Corporation cannot bypass the 193498 for P25,250,000.00 while Eugene Arriesgado issued Far
arbitration process laid out by the body and seek relief directly East Bank and Trust Company (FEBTC) check Nos. 464264,
from the courts.—Simply put, participants in the regional 464272 and 464271 for P8,600,000.00, P8,500,000.00 and
clearing operations of the Philippine Clearing House Corporation P8,100,000.00, respectively, the three checks amounting to
cannot bypass the arbitration process laid out by the body and P25,200,000.00. Tancuan and Arriesgado exchanged each
seek relief directly from the courts. In the case at bar, other’s checks and deposited them with their respective banks
undeniably, private respondent has initiated arbitration for collection. When FEBTC presented Tancuan’s HBSTC check
for clearing, HBSTC dishonored it for being "Drawn Against
Insufficient Funds." On October 15, 1991, HBSTC sent In a Decision 9 dated January 21, 1994, the respondent court
Arriesgado’s three (3) FEBTC checks through the Philippine dismissed the petition for lack of merit and held that "FEBTC
Clearing House Corporation (PCHC) to FEBTC but was returned can reiterate its cause of action before the courts which it had
on October 18, 1991 as "Drawn Against Insufficient Funds." already raised in the arbitration case" 10 after finding that the
HBSTC received the notice of dishonor on October 21, 1991 but complaint filed by FEBTC." . . seeks to collect a sum of money
refused to accept the checks and on October 22, 1991, from HBT [HBSTC] and not to enforce or confirm an arbitral
returned them to FEBTC through the PCHC for the reason award." 11 The respondent court observed that" [i]n the
"Beyond Reglementary Period," implying that HBSTC already Complaint, FEBTC applied for the issuance of a writ of
treated the three (3) FEBTC checks as cleared and allowed the preliminary attachment over HBT’s [HBSTC] property" 12 and
proceeds thereof to be withdrawn. 4 FEBTC demanded citing section 14 of Republic Act No. 876, otherwise known as
reimbursement for the returned checks and inquired from the Arbitration Law, maintained that" [n]ecessarily, it has to
HBSTC whether it had permitted any withdrawal of funds reiterate its main cause of action for sum of money against HBT
against the unfunded checks and if so, on what date. HBSTC, [HBSTC]," 13 and that" [t]his prayer for conservatory relief
however, refused to make any reimbursement and to provide [writ of preliminary attachment] satisfies the requirement of a
FEBTC with the needed information. cause of action which FEBTC may pursue in the courts." 14

Thus, on December 12, 1991, FEBTC submitted the dispute for Furthermore, the respondent court ruled that based on section
arbitration before the PCHC Arbitration Committee, 5 under the 7 of the Arbitration Law and the cases of National Union Fire
PCHC’s Supplementary Rules on Regional Clearing to which Insurance Company of Pittsburg v. Stolt-Nielsen Philippines,
FEBTC and HBSTC are bound as participants in the regional Inc., 15 and Bengson v. Chan, 16." . . when there is a condition
clearing operations administered by the PCHC. 6 requiring prior submission to arbitration before the institution of
a court action, the complaint is not to be dismissed but should
On January 17, 1992, while the arbitration proceeding was still be suspended for arbitration." 17 Finding no merit in HBSTC’s
pending, FEBTC filed an action for sum of money and damages contention that section 7 of the Arbitration Law." . .
with preliminary attachment 7 against HBSTC, Robert Young, contemplates a situation in which a party to an arbitration
Victor Tancuan and Eugene Arriesgado with the Regional Trial agreement has filed a court action without first resorting to
Court of Makati, Branch 133. A motion to dismiss was filed by arbitration, while in the case at bar, FEBTC has initiated
HBSTC claiming that the complaint stated no cause of action arbitration proceedings before filing a court action," the
and accordingly." . . should be dismissed because it seeks to respondent court held that." . . if the absence of a prior
enforce an arbitral award which as yet does not exist." 8 The arbitration may stay court action, so too and with more reason,
trial court issued an omnibus order dated April 30, 1992 should an arbitration already pending as obtains in this case
denying the motion to dismiss and an order dated October 1, stay the court action. A party to a pending arbitral proceeding
1992 denying the motion for may go to court to obtain conservatory reliefs in connection
reconsideration.chanrobles.com:cralaw:red with his cause of action although the disposal of that action on
the merits cannot as yet be obtained." 18 The respondent court
On December 16, 1992, HBSTC filed a petition discarded Puromines, Inc. v. Court of Appeals, 19 stating that."
for certiorari with the respondent Court of Appeals contending . . perhaps Puromines may have been decided on a different
that the trial court acted with grave abuse of discretion factual basis." 20
amounting to lack of jurisdiction in denying the motion to
dismiss filed by HBSTC. In the instant petition, 21 petitioner contends that first, "no
party litigant can file a non-existent complaint," 22 arguing jurisprudence confirms, one requirement in the issuance of an
that." . . one cannot file a complaint in court over a subject that attachment [writ of preliminary attachment] is that the debtor
is undergoing arbitration." 23 Second, petitioner submits that" has no sufficient security." 36 Petitioner asserts further that a
[s]ince arbitration is a special proceeding by a clear provision of writ of preliminary attachment is unwarranted because no
law, 24 the civil suit filed below is, without a shadow of doubt, ground exists for its issuance. According to petitioner,." . . the
barred by litis pendentia and should be dismissed de plano only allegations against it [HBSTC] are that it refused to refund
insofar as HBSTC is concerned." 25 Third, petitioner insists the amounts of the checks of FEBTC and that it knew about the
that" [w]hen arbitration is agreed upon and suit is filed without fraud perpetrated by the other defendants," 37 which, at best,
arbitration having been held and terminated, the case that is constitute only "incidental fraud" and not causal fraud which
filed should be dismissed," 26 citing Associated Bank v. Court of justifies the issuance of the writ of preliminary attachment.
Appeals, 27 Puromines, Inc. v. Court of Appeals, 28 and
Ledesma v. Court of Appeals. 29 Petitioner demurs that the Private respondent FEBTC, on the other hand, contends that." .
Puromines ruling was deliberately not followed by the . the cause of action for collection [of a sum of money] can
respondent court which claimed that:jgc:chanrobles.com.ph coexist in the civil suit and the arbitration [proceeding]" 38
citing section 7 of the Arbitration Law which provides for the
"x x x stay of the civil action until an arbitration has been had in
accordance with the terms of the agreement providing for
It would really be much easier for Us to rule to dismiss the arbitration. Private respondent further asserts that following
complaint as the petitioner here seeks to do, following section 4(3), article VIII 39 of the 1987 Constitution, the
Puromines. But with utmost deference to the Honorable subsequent case of Puromines does not overturn the ruling in
Supreme Court, perhaps Puromines may have been decided on the earlier cases of National Union Fire Insurance Company of
a different factual basis. Pittsburg v. Stolt-Nielsen Philippines, Inc., 40 and Bengson v.
Chan, 41 hence, private respondent concludes that the
x x x." 30 prevailing doctrine is that the civil action must be stayed rather
than dismissed pending arbitration.
Petitioner takes exception to FEBTC’s contention that
In this; petition, the lone issue presented for the consideration
Puromines cannot modify or reverse the rulings in National of this Court is:jgc:chanrobles.com.ph
Union Fire Insurance Company of Pittsburg v. Stolt-Nielsen
Philippines, Inc., 31 and Bengson v. Chan, 32 where this Court "WHETHER OR NOT PRIVATE RESPONDENT WHICH
suspended the action filed pending arbitration, and argues that" COMMENCED AN ARBITRATION PROCEEDING UNDER THE
[s]ound policy requires that the conclusion of whether a AUSPICES OF THE PHILIPPINE CLEARING HOUSE
Supreme Court decision has or has not reversed or modified [a] CORPORATION (PCHC) MAY SUBSEQUENTLY FILE A SEPARATE
previous doctrine, should be left to the Supreme Court itself; CASE IN COURT .OVER THE SAME SUBJECT MATTER OF
until then, the latest pronouncement should prevail." 33 Fourth, ARBITRATION DESPITE THE PENDENCY OF THAT ARBITRATION,
petitioner alleges that the writ of preliminary attachment issued SIMPLY TO OBTAIN THE PROVISIONAL REMEDY OF
by the trial court is void considering that the case filed before it ATTACHMENT AGAINST THE BANK THE ADVERSE PARTY IN THE
"is a separate action which cannot exist," 34 and." . . there is ARBITRATION PROCEEDING." 42
even no need for the attachment as far as HBSTC is concerned
because such automatic debit/credit procedure 35 may be We find no merit in the petition. Section 14 of Republic Act 876,
regarded as a security for the transactions involved and, as otherwise known as the Arbitration Law, allows any party to the
arbitration proceeding to petition the court to take measures to Ledesma v. Court of Appeals 45 in contending that" [w]hen
safeguard and/or conserve any matter which is the subject of arbitration is agreed upon and suit is filed without arbitration
the dispute in arbitration, thus:chanroblesvirtual|awlibrary having been held and terminated, the case that is filed should
be dismissed." 46 However, the said cases are not in point. In
SECTION 14. Subpoena and subpoena duces tecum. — Associated Bank, we affirmed the dismissal of the third-party
Arbitrators shall have the power to require any person to attend complaint filed by Associated Bank against Philippine
a hearing as a witness. They shall have the power to subpoena Commercial International Bank, Far East Bank & Trust
witnesses and documents when the relevancy of the testimony Company, Security Bank and Trust Company, and Citytrust
and the materiality thereof has been demonstrated to the Banking Corporation for lack of jurisdiction, it being shown that
arbitrators. Arbitrators may also require the retirement of any the said parties were bound by the Clearing House Rules and
witness during the testimony of any other witness. All of the Regulations on Arbitration of the Philippine Clearing House
arbitrators appointed in any controversy must attend all the Corporation. In Associated Bank, we declared
hearings in that matter and hear all the allegations and proofs that:jgc:chanrobles.com.ph
of the parties; but an award by the majority of them is valid
unless the concurrence of all of them is expressly required in ". . . . Under the rules and regulations of the Philippine Clearing
the submission or contract to arbitrate. The arbitrator or House Corporation (PCHC), the mere act of participation of the
arbitrators shall have the power at any time, before rendering parties concerned in its operations in effect amounts to a
the award, without prejudice to the rights of any party to manifestation of agreement by the parties to abide by its rules
petition the court to take measures to safeguard and/or and regulations. As a consequence of such participation, a party
conserve any matter which is the subject of the dispute in cannot invoke the jurisdiction of the courts over disputes and
arbitration. (Emphasis supplied) controversies which fall under the PCHC Rules and Regulations
without first going through the arbitration processes laid out by
Petitioner’s exposition of the foregoing provision deserves scant the body." 47 (Emphasis supplied)
consideration. Section 14 simply grants an arbitrator the power
to issue subpoena and subpoena duces tecum at any time And thus we concluded:jgc:chanrobles.com.ph
before rendering the award. The exercise of such power is
without prejudice to the right of a party to file a petition in "Clearly therefore, petitioner Associated Bank, by its voluntary
court to safeguard any matter which is the subject of the participation and its consent to the arbitration rules cannot go
dispute in arbitration. In the case at bar, private respondent directly to the Regional Trial Court when it finds it convenient to
filed an action for a sum of money with prayer for a writ of do so. The jurisdiction of the PCHC under the rules and
preliminary attachment. Undoubtedly, such action involved the regulations is clear, undeniable and is particularly applicable to
same subject matter as that in arbitration, i.e., the sum of all the parties in the third party complaint under their obligation
P25,200,000.00 which was allegedly deprived from private to first seek redress of their disputes and grievances with the
respondent in what is known in banking as a "kiting scheme." PCHC before going to the trial court." 48 (Emphasis supplied)
However, the civil action was not a simple case of a money
claim since private respondent has included a prayer for a writ Simply put, participants in the regional clearing operations of
of preliminary attachment, which is sanctioned by section 14 of the Philippine Clearing House Corporation cannot bypass the
the Arbitration Law. arbitration process laid out by the body and seek relief directly
from the courts. In the case at bar, undeniably, private
Petitioner cites the cases of Associated Bank v. Court of respondent has initiated arbitration proceedings as required by
Appeals, 43 Puromines, Inc. v. Court of Appeals, 44 and the PCHC rules and regulations, and pending arbitration has
sought relief from the trial court for measures to safeguard
and/or conserve the subject of the dispute under arbitration, as
sanctioned by section 14 of the Arbitration Law, and otherwise
not shown to be contrary to the PCHC rules and regulations.

Likewise, in the case of Puromines, Inc. v. Court of Appeals, 49


we have ruled that:jgc:chanrobles.com.ph

"In any case, whether the liability of respondent should be


based on the sales contract or that of the bill of lading, the
parties are nevertheless obligated to respect the arbitration
provisions on the sales contract and/or bill of lading. Petitioner
being a signatory and party to the sales contract cannot escape
from his obligation under the arbitration clause as stated
therein."cralaw virtua1aw library

In Puromines, we found the arbitration clause stated in the


sales contract to be valid and applicable, thus, we ruled that
the parties, being signatories to the sales contract, are
obligated to respect the arbitration provisions on the contract
and cannot escape from such obligation by filing an action for
breach of contract in court without resorting first to arbitration,
as agreed upon by the parties.

At this point, we emphasize that arbitration, as an alternative


method of dispute resolution, is encouraged by this Court.
Aside from unclogging judicial dockets, it also hastens solutions
especially of commercial disputes. 50 The Court looks with
favor upon such amicable arrangement and will only interfere
with great reluctance to anticipate or nullify the action of the
arbitrator. 51

WHEREFORE, premises considered, the petition is hereby


DISMISSED and the decision of the court a quo is
AFFIRMED.cralawnad

SO ORDERED.
G.R. No. 141833 March 26, 2003 covers the asserted dispute, an order to arbitrate should be
LM POWER ENGINEERING CORPORATION, petitioner, granted. Any doubt should be resolved in favor of arbitration.
vs.
CAPITOL INDUSTRIAL CONSTRUCTION GROUPS, Same; Same; Same; Construction Industry Arbitration
INC., respondent. Commission (CIAC); Recourse to the CIAC may now be availed
of whenever a contract “contains a clause for the submission of
Alternative Dispute Resolution; Arbitration; Courts; Jurisdiction; a future controversy to arbitration.—On the other hand, Section
The inclusion of an arbitration clause in a contract does not ipso 1 of Article III of the new Rules of Procedure Governing
facto divest the courts of jurisdiction to pass upon the findings Construction Arbitration has dispensed with this requirement
of arbitral bodies, because the awards are still judicially and recourse to the CIAC may now be availed of whenever a
reviewable under certain conditions.—We side with respondent. contract “contains a clause for the submission of a future
Essentially, the dispute arose from the parties’ incongruent controversy to arbitration,” in this wise: “SECTION 1.
positions on whether certain provisions of their Agreement Submission to CIAC Jurisdiction.—An arbitration clause in a
could be applied to the facts. The instant case involves construction contract or a submission to arbitration of a
technical discrepancies that are better left to an arbitral body construction dispute shall be deemed an agreement to submit
that has expertise in those areas. In any event, the inclusion of an existing or future controversy to CIAC jurisdiction,
an arbitration clause in a contract does not ipso facto divest the notwithstanding the reference to a different arbitration
courts of jurisdiction to pass upon the findings of arbitral institution or arbitral body in such contract or submission.
bodies, because the awards are still judicially reviewable under When a contract contains a clause for the submission of a
certain conditions. future controversy to arbitration, it is not necessary for the
parties to enter into a submission agreement before the
Same; Same; Same; Being an inexpensive, speedy and claimant may invoke the jurisdiction of CIAC.” The foregoing
amicable method of settling disputes, arbitration—along with amendments in the Rules were formalized by CIAC Resolution
mediation, conciliation and negotiation—is encouraged by the Nos. 2-91 and 3-93.
Supreme Court; Arbitration is regarded as the “wave of the
future” in international civil and commercial disputes; PANGANIBAN, J.:
Consistent with the policy of encouraging alternative dispute Alternative dispute resolution methods or ADRs -- like
resolution methods, courts should liberally construe arbitration arbitration, mediation, negotiation and conciliation -- are
clauses.—Being an inexpensive, speedy and amicable method encouraged by the Supreme Court. By enabling parties to
of settling disputes, arbitration—along with mediation, resolve their disputes amicably, they provide solutions that are
conciliation and negotiation—is encouraged by the Supreme less time-consuming, less tedious, less confrontational, and
Court. Aside from unclogging judicial dockets, arbitration also more productive of goodwill and lasting relationships.1
hastens the resolution of disputes, especially of the commercial The Case
kind. It is thus regarded as the “wave of the future” in Before us is a Petition for Review on Certiorari 2 under Rule 45
international civil and commercial disputes. Brushing aside a of the Rules of Court, seeking to set aside the January 28, 2000
contractual agreement calling for arbitration between the Decision of the Court of Appeals3 (CA) in CA-GR CV No. 54232.
parties would be a step backward. Consistent with the above- The dispositive portion of the Decision reads as follows:
mentioned policy of encouraging alternative dispute resolution "WHEREFORE, the judgment appealed from is REVERSED and
methods, courts should liberally construe arbitration clauses. SET ASIDE. The parties are ORDERED to present their dispute
Provided such clause is susceptible of an interpretation that to arbitration in accordance with their Sub-contract Agreement.
The surety bond posted by [respondent] is [d]ischarged."4
The Facts warranty clause of the Agreement, and whether it should
On February 22, 1983, Petitioner LM Power Engineering reimburse respondent for the work the latter had taken over.15
Corporation and Respondent Capitol Industrial Construction Hence, this Petition.16
Groups Inc. entered into a "Subcontract Agreement" involving The Issues
electrical work at the Third Port of Zamboanga. 5 In its Memorandum, petitioner raises the following issues for
On April 25, 1985, respondent took over some of the work the Court’s consideration:
contracted to petitioner.6 Allegedly, the latter had failed to "A
finish it because of its inability to procure materials.7 Whether or not there exist[s] a controversy/dispute between
Upon completing its task under the Contract, petitioner billed petitioner and respondent regarding the interpretation and
respondent in the amount of P6,711,813.90.8 Contesting the implementation of the Sub-Contract Agreement dated February
accuracy of the amount of advances and billable 22, 1983 that requires prior recourse to voluntary arbitration;
accomplishments listed by the former, the latter refused to pay. "B
Respondent also took refuge in the termination clause of the In the affirmative, whether or not the requirements provided in
Agreement.9 That clause allowed it to set off the cost of the Article III 1 of CIAC Arbitration Rules regarding request for
work that petitioner had failed to undertake -- due to arbitration ha[ve] been complied with[.]"17
termination or take-over -- against the amount it owed the The Court’s Ruling
latter. The Petition is unmeritorious.
Because of the dispute, petitioner filed with the Regional Trial First Issue:
Court (RTC) of Makati (Branch 141) a Complaint10 for the Whether Dispute Is Arbitrable
collection of the amount representing the alleged balance due it Petitioner claims that there is no conflict regarding the
under the Subcontract. Instead of submitting an Answer, interpretation or the implementation of the Agreement. Thus,
respondent filed a Motion to Dismiss,11 alleging that the without having to resort to prior arbitration, it is entitled to
Complaint was premature, because there was no prior recourse collect the value of the services it rendered through an ordinary
to arbitration. action for the collection of a sum of money from respondent.
In its Order12 dated September 15, 1987, the RTC denied the On the other hand, the latter contends that there is a need for
Motion on the ground that the dispute did not involve the prior arbitration as provided in the Agreement. This is because
interpretation or the implementation of the Agreement and there are some disparities between the parties’ positions
was, therefore, not covered by the arbitral clause. 13 regarding the extent of the work done, the amount of advances
After trial on the merits, the RTC14 ruled that the take-over of and billable accomplishments, and the set off of expenses
some work items by respondent was not equivalent to a incurred by respondent in its take-over of petitioner’s work.
termination, but a mere modification, of the Subcontract. The We side with respondent. Essentially, the dispute arose from
latter was ordered to give full payment for the work completed the parties’ ncongruent positions on whether certain provisions
by petitioner. of their Agreement could be applied to the facts. The instant
Ruling of the Court of Appeals case involves technical discrepancies that are better left to an
On appeal, the CA reversed the RTC and ordered the referral of arbitral body that has expertise in those areas. In any event,
the case to arbitration. The appellate court held as arbitrable the inclusion of an arbitration clause in a contract does not ipso
the issue of whether respondent’s take-over of some work facto divest the courts of jurisdiction to pass upon the findings
items had been intended to be a termination of the original of arbitral bodies, because the awards are still judicially
contract under Letter "K" of the Subcontract. It ruled likewise reviewable under certain conditions.18
on two other issues: whether petitioner was liable under the In the case before us, the Subcontract has the following arbitral
clause:
"6. The Parties hereto agree that any dispute or conflict as Supposedly, as a result of the "take-over," respondent incurred
regards to interpretation and implementation of this expenses in excess of the contracted price. It sought to set off
Agreement which cannot be settled between [respondent] and those expenses against the amount claimed by petitioner for
[petitioner] amicably shall be settled by means of arbitration x the work the latter accomplished, pursuant to the following
x x."19 provision:
Clearly, the resolution of the dispute between the parties herein "If the total direct and indirect cost of completing the remaining
requires a referral to the provisions of their Agreement. Within part of the WORK exceed the sum which would have been
the scope of the arbitration clause are discrepancies as to the payable to [petitioner] had it completed the WORK, the amount
amount of advances and billable accomplishments, the of such excess [may be] claimed by [respondent] from either of
application of the provision on termination, and the consequent the following:
set-off of expenses. ‘1. Any amount due [petitioner] from [respondent] at the time
A review of the factual allegations of the parties reveals that of the termination of this Agreement."22
they differ on the following questions: (1) Did a take- The issue as to the correct amount of petitioner’s advances and
over/termination occur? (2) May the expenses incurred by billable accomplishments involves an evaluation of the manner
respondent in the take-over be set off against the amounts it in which the parties completed the work, the extent to which
owed petitioner? (3) How much were the advances and billable they did it, and the expenses each of them incurred in
accomplishments? connection therewith. Arbitrators also need to look into the
The resolution of the foregoing issues lies in the interpretation computation of foreign and local costs of materials, foreign and
of the provisions of the Agreement. According to respondent, local advances, retention fees and letters of credit, and taxes
the take-over was caused by petitioner’s delay in completing and duties as set forth in the Agreement. These data can be
the work. Such delay was in violation of the provision in the gathered from a review of the Agreement, pertinent portions of
Agreement as to time schedule: which are reproduced hereunder:
"G. TIME SCHEDULE "C. CONTRACT PRICE AND TERMS OF PAYMENT
"[Petitioner] shall adhere strictly to the schedule related to the xxx xxx xxx
WORK and complete the WORK within the period set forth in "All progress payments to be made by [respondent] to
Annex C hereof. NO time extension shall be granted by [petitioner] shall be subject to a retention sum of ten percent
[respondent] to [petitioner] unless a corresponding time (10%) of the value of the approved quantities. Any claims by
extension is granted by [the Ministry of Public Works and [respondent] on [petitioner] may be deducted by [respondent]
Highways] to the CONSORTIUM."20 from the progress payments and/or retained amount. Any
Because of the delay, respondent alleges that it took over some excess from the retained amount after deducting [respondent’s]
of the work contracted to petitioner, pursuant to the following claims shall be released by [respondent] to [petitioner] after
provision in the Agreement: the issuance of [the Ministry of Public Works and Highways] of
"K. TERMINATION OF AGREEMENT the Certificate of Completion and final acceptance of the WORK
"[Respondent] has the right to terminate and/or take over this by [the Ministry of Public Works and Highways].
Agreement for any of the following causes: xxx xxx xxx
xxx xxx xxx "D. IMPORTED MATERIALS AND EQUIPMENT
‘6. If despite previous warnings by [respondent], [petitioner] "[Respondent shall open the letters of credit for the importation
does not execute the WORK in accordance with this Agreement, of equipment and materials listed in Annex E hereof after the
or persistently or flagrantly neglects to carry out [its] drawings, brochures, and other technical data of each items in
obligations under this Agreement."21 the list have been formally approved by [the Ministry of Public
Works and Highways]. However, petitioner will still be fully the Construction Industry Arbitration Commission (CIAC) shall
responsible for all imported materials and equipment. submit its Request for Arbitration in sufficient copies to the
"All expenses incurred by [respondent], both in foreign and Secretariat of the CIAC; PROVIDED, that in the case of
local currencies in connection with the opening of the letters of government construction contracts, all administrative remedies
credit shall be deducted from the Contract Prices. available to the parties must have been exhausted within 90
xxx xxx xxx days from the time the dispute arose."
"N. OTHER CONDITIONS Tesco was promulgated by this Court, using the foregoing
xxx xxx xxx provision as reference.
"2. All customs duties, import duties, contractor’s taxes, income On the other hand, Section 1 of Article III of the new Rules of
taxes, and other taxes that may be required by any Procedure Governing Construction Arbitration has dispensed
government agencies in connection with this Agreement shall with this requirement and recourse to the CIAC may now be
be for the sole account of [petitioner]."23 availed of whenever a contract "contains a clause for the
Being an inexpensive, speedy and amicable method of settling submission of a future controversy to arbitration," in this wise:
disputes,24 arbitration -- along with mediation, conciliation and "SECTION 1. Submission to CIAC Jurisdiction — An arbitration
negotiation -- is encouraged by the Supreme Court. Aside from clause in a construction contract or a submission to arbitration
unclogging judicial dockets, arbitration also hastens the of a construction dispute shall be deemed an agreement to
resolution of disputes, especially of the commercial kind.25 It is submit an existing or future controversy to CIAC jurisdiction,
thus regarded as the "wave of the future" in international civil notwithstanding the reference to a different arbitration
and commercial disputes.26 Brushing aside a contractual institution or arbitral body in such contract or submission.
agreement calling for arbitration between the parties would be When a contract contains a clause for the submission of a
a step backward.27 future controversy to arbitration, it is not necessary for the
Consistent with the above-mentioned policy of encouraging parties to enter into a submission agreement before the
alternative dispute resolution methods, courts should liberally claimant may invoke the jurisdiction of CIAC."
construe arbitration clauses. Provided such clause is susceptible The foregoing amendments in the Rules were formalized by
of an interpretation that covers the asserted dispute, an order CIAC Resolution Nos. 2-91 and 3-93.31
to arbitrate should be granted.28 Any doubt should be resolved The difference in the two provisions was clearly explained
in favor of arbitration.29 in China Chang Jiang Energy Corporation (Philippines) v. Rosal
Second Issue: Infrastructure Builders et al.32 (an extended unsigned
Prior Request for Arbitration Resolution) and reiterated in National Irrigation Administration
According to petitioner, assuming arguendo that the dispute is v. Court of Appeals,33 from which we quote thus:
arbitrable, the failure to file a formal request for arbitration with "Under the present Rules of Procedure, for a particular
the Construction Industry Arbitration Commission (CIAC) construction contract to fall within the jurisdiction of CIAC, it is
precluded the latter from acquiring jurisdiction over the merely required that the parties agree to submit the same to
question. To bolster its position, petitioner even cites our ruling voluntary arbitration Unlike in the original version of Section 1,
in Tesco Services Incorporated v. Vera.30 We are not as applied in the Tesco case, the law as it now stands does not
persuaded. provide that the parties should agree to submit disputes arising
Section 1 of Article II of the old Rules of Procedure Governing from their agreement specifically to the CIAC for the latter to
Construction Arbitration indeed required the submission of a acquire jurisdiction over the same. Rather, it is plain and clear
request for arbitration, as follows: that as long as the parties agree to submit to voluntary
"SECTION. 1. Submission to Arbitration -- Any party to a arbitration, regardless of what forum they may choose, their
construction contract wishing to have recourse to arbitration by agreement will fall within the jurisdiction of the CIAC, such that,
even if they specifically choose another forum, the parties will
not be precluded from electing to submit their dispute before
the CIAC because this right has been vested upon each party
by law, i.e., E.O. No. 1008."34
Clearly, there is no more need to file a request with the CIAC in
order to vest it with jurisdiction to decide a construction
dispute.
The arbitral clause in the Agreement is a commitment on the
part of the parties to submit to arbitration the disputes covered
therein. Because that clause is binding, they are expected to
abide by it in good faith.35 And because it covers the dispute
between the parties in the present case, either of them may
compel the other to arbitrate.36
Since petitioner has already filed a Complaint with the RTC
without prior recourse to arbitration, the proper procedure to
enable the CIAC to decide on the dispute is to request the stay
or suspension of such action, as provided under RA 876 [the
Arbitration Law].37
WHEREFORE, the Petition is DENIED and the assailed Decision
AFFIRMED. Costs against petitioner.
SO ORDERED.
Puno, (Chairman), Sandoval-Gutierrez, Corona and Carpio-
Morales, JJ., concur.
LUZON IRON DEVELOPMENT GROUP CORPORATION AND a party in the first case and a party in the second case, even if
CONSOLIDATED IRON SANDS, LTD., PETITIONERS, V. the latter was not impleaded in the other case. Consolidated
BRIDESTONE MINING AND DEVELOPMENT Iron and Luzon Iron had a common interest under the TPAA as
CORPORATION AND ANACONDA MINING AND the latter was a wholly-owned subsidiary of the former.
DEVELOPMENT CORPORATION, RESPONDENTS.
Same; Same; Same; Identity of Causes of Action; The test to
Remedial Law; Civil Procedure; Forum Shopping; Forum determine whether the causes of action are identical is to
shopping is committed when multiple suits involving the same ascertain whether the same evidence will sustain both actions,
parties and the same causes of action are filed, either or whether there is an identity in the facts essential to the
simultaneously or successively, for the purpose of obtaining a maintenance of the two (2) actions.—A reading of the
favorable judgment through means other than appeal or complaints filed before the RTC and the DENR reveals that they
certiorari.—Forum shopping is committed when multiple suits had almost identical causes of action and they prayed for
involving the same parties and the same causes of action are similar reliefs as they ultimately sought the return of their
filed, either simultaneously or successively, for the purpose of respective Exploration Permit on the ground of the alleged
obtaining a favorable judgment through means other than violations of the TPAA committed by the petitioners. In Yap v.
appeal or certiorari. The prohibition on forum shopping seeks to Chua, 672 SCRA 419 (2012), the Court ruled that identity of
prevent the possibility that conflicting decisions will be rendered causes of action did not mean absolute identity. Hornbook is
by two tribunals. the rule that identity of causes of action does not mean
Same; Same; Same; Elements of Forum Shopping.—There is absolute identity; otherwise, a party could easily escape the
forum shopping when the following elements are present: (a) operation of res judicata by changing the form of the action or
identity of parties, or at least such parties representing the the relief sought. The test to determine whether the causes of
same interests in both actions; (b) identity of rights asserted action are identical is to ascertain whether the same evidence
and reliefs prayed for, the relief being founded on the same will sustain both actions, or whether there is an identity in the
facts; and (c) the identity of the two preceding particulars, such facts essential to the maintenance of the two actions. If the
that any judgment rendered in the other action will, regardless same facts or evidence would sustain both, the two actions are
of which party is successful, amounts to res judicata in the considered the same, and a judgment in the first case is a bar
action under consideration. All the above stated elements are to the subsequent action. Hence, a party cannot, by varying the
present in the case at bench. form of action or adopting a different method of presenting his
case, escape the operation of the principle that one and the
Same; Same; Same; Identity of Parties; The requirement is same cause of action shall not be twice litigated between the
only substantial, and not absolute, identity of parties; and there same parties or their privies. In the case at bench, both
is substantial identity of parties when there is community of complaints filed before different fora involved similar facts and
interest between a party in the first case and a party in the issues, the resolution of which depends on analogous evidence.
second case, even if the latter was not impleaded in the other Thus, the filing of two separate complaints by the petitioners
case.—In both the complaints before the RTC and the DENR, with the RTC and the DENR clearly constitutes forum shopping.
Luzon Iron was impleaded as defendant while Consolidated Iron It is worth noting that the very evil which the prohibition
was only impleaded in the complaint before the RTC. Even if against forum shopping sought to prevent had happened — the
Consolidated Iron was not impleaded in the DENR complaint, RTC and the DENR had rendered conflicting decisions. The trial
the element still exists. The requirement is only substantial, court ruled that it had jurisdiction notwithstanding the
and not absolute, identity of parties; and there is substantial arbitration clause in the TPAA. On the other hand, the DENR
identity of parties when there is community of interest between
found that it was devoid of jurisdiction because the matter was order by registered mail at the last known address of the
subject to arbitration. defendant; c) By facsimile or any recognized electronic means
that could generate proof of service; or d) By such other means
Same; Same; Service of Summons; Section 12 of Rule 14 of as the court may in its discretion direct.”
the Revised Rules of Court provides that “[w]hen the defendant
is a foreign private juridical entity which has transacted Corporations; Subsidiary Corporations; A wholly-owned
business in the Philippines, service may be made on its resident subsidiary is a distinct and separate entity from its mother
agent designated in accordance with law for that purpose, or, if corporation and the fact that the latter exercises control over
there be no such agent, on the government official designated the former does not justify disregarding their separate
by law to that effect, or on any of its officers or agents within personality.—The respondents err in insisting that Luzon Iron
the Philippines.”—Section 12 of Rule 14 of the Revised Rules of could be served summons as an agent of Consolidated Iron, it
Court provides that “[w]hen the defendant is a foreign private being a wholly-owned subsidiary of the latter. The allegations in
juridical entity which has transacted business in the Philippines, the complaint must clearly show a connection between the
service may be made on its resident agent designated in principal foreign corporation and its alleged agent corporation
accordance with law for that purpose, or, if there be no such with respect to the transaction in question as a general
agent, on the government official designated by law to that allegation of agency will not suffice. In other words, the
effect, or on any of its officers or agents within the Philippines.” allegations of the complaint taken as whole should be able to
convey that the subsidiary is but a business conduit of the
Same; Same; Same; Under the present legal milieu, the rules principal or that by reason of fraud, their separate and distinct
on service of summons on foreign private juridical entities had personality should be disregarded. A wholly-owned subsidiary is
been expanded as it recognizes additional modes by which a distinct and separate entity from its mother corporation and
summons may be served.—Under the present legal milieu, the the fact that the latter exercises control over the former does
rules on service of summons on foreign private juridical entities not justify disregarding their separate personality. It is true that
had been expanded as it recognizes additional modes by which under the TPAA, Consolidated Iron wielded great control over
summons may be served. A.M. No. 11-3-6-SC thus provides: the actions of Luzon Iron under the said agreement. This,
Section 12, Rule 14 of the Rules of Court is hereby amended to nonetheless, does not warrant the conclusion that Luzon Iron
read as follows: “SEC. 12. Service upon foreign private juridical was a mere conduit of Consolidated Iron. Civil Law; Arbitration;
entity.—When the defendant is a foreign private juridical entity Consistent with the state policy of favoring arbitration, the
which has transacted business in the Philippines, service may present Tenement Partnership and Acquisition Agreement
be made on its resident agent designated in accordance with (TPAA) must be construed in such a manner that would give life
law for that purpose, or, if there be no such agent, on the to the arbitration clause rather than defeat it, if such
government official designated by law to that effect, or on any interpretation is permissible.—Consistent with the state policy
of its officers or agents within the Philippines. If the foreign of favoring arbitration, the present TPAA must be construed in
private juridical entity is not registered in the Philippines or has such a manner that would give life to the arbitration clause
no resident agent, service may, with leave of court, be effected rather than defeat it, if such interpretation is permissible. With
out of the Philippines through any of the following means: a) By this in mind, the Court views the interpretation forwarded by
personal service coursed through the appropriate court in the the petitioners as more in line with the state policy favoring
foreign country with the assistance of the Department of arbitration. Paragraphs 14.8 and 15.1 of the TPAA should be
Foreign Affairs; b) By publication once in a newspaper of harmonized in such a way that the arbitration clause is given
general circulation in the country where the defendant may be life, especially since such construction is possible in the case at
found and by serving a copy of the summons and the court bench. A synchronized reading of the above mentioned TPAA
provisions will show that a claim or action raising the restraining order (TRO) seeks to reverse and set aside the
sufficiency, validity, legality or constitutionality of: (a) the September 8, 2015 Decision[1] of the Court of Appeals (CA) in
assignments of the EP to Luzon Iron; (b) any other assignments CA-G.R. SP No. 133296, which affirmed the March 18,
contemplated by the TPAA; or (c) any agreement to which the 2013[2] and September 18, 2013[3] Orders of the Regional Trial
EPs may be converted, may be instituted only when there is a Court, Branch 59, Makati City (RTC), in the consolidated case
direct and/or blatant violation of the TPAA. In turn, the said for rescission of contract and damages.
action or claim is commenced by proceeding with arbitration, as The Antecedents.
espoused in the TPAA. On October 25, 2012, respondents Bridestone Mining and
Development Corporation (Bridestone) and Anaconda Mining
Same; Same; The petitioners’ failure to refer the case for and Development Corporation (Anaconda) filed separate
arbitration does not render the arbitration clause in the present complaints before the RTC for rescission of contract and
Tenement Partnership and Acquisition Agreement (TPAA) damages against petitioners Luzon Iron Development Group
inoperative.—The petitioners’ failure to refer the case for Corporation (Luzon Iron) and Consolidated Iron Sands, Ltd.
arbitration, however, does not render the arbitration clause in (Consolidated Iron), docketed as Civil Case No. 12-1053 and
the TPAA inoperative. In Koppel, Inc. v. Makati Rotary Club Civil Case No. 12-1054, respectively. Both complaints sought
Foundation, Inc. (Koppel), 705 SCRA 142 (2013), the Court the rescission of the Tenement Partnership and Acquisition
explained that an arbitration clause becomes operative, Agreement (TPAA)[4] entered into by Luzon Iron and
notwithstanding the lack of a formal request, when a party has Consolidated Iron, on one hand, and Bridestone and Anaconda,
appraised the trial court of the existence of an arbitration on the other, for the assignment of the Exploration Permit
clause, viz.: x x x The operation of the arbitration clause in this Application of the former in favor of the latter. The complaints
case is not at all defeated by the failure of the petitioner to file also sought the return of the Exploration Permits to Bridestone
a formal “request” or application therefor with the MeTC. We and Anaconda.[5]
find that the filing of a “request” pursuant to Section 24 of R.A. Thereafter, Luzon Iron and Consolidated Iron filed their Special
No. 9285 is not the sole means by which an arbitration clause Appearance with Motion to Dismiss[6] separately against
may be validly invoked in a pending suit. Bridestone's complaint and Anaconda's complaint. Both motions
to dismiss presented similar grounds for dismissal. They
Same; Same; Generally, the action of the court is stayed if the contended that the RTC could not acquire jurisdiction over
matter raised before it is subject to arbitration.—Generally, the Consolidated Iron because it was a foreign corporation that had
action of the court is stayed if the matter raised before it is never transacted business in the Philippines. Likewise, they
subject to arbitration. In the case at bench, however, the argued that the RTC had no jurisdiction over the subject matter
complaints filed before the RTC should have been dismissed because of an arbitration clause in the TPAA.
considering that the petitioners were able to establish the On December 19, 2012, the RTC ordered the consolidation of
ground for their dismissal, that is, violating the prohibition on the two cases.[7] Subsequently, Luzon Iron and Consolidated
forum shopping. The parties, nevertheless, are directed to Iron filed their Special Appearance and Supplement to Motions
initiate arbitration proceedings as provided under Paragraph to Dismiss,[8] dated January 31, 2013, seeking the dismissal of
15.1 of the TPAA the consolidated cases. The petitioners alleged that Bridestone
and Anaconda were guilty of forum shopping because they filed
DECISION similar complaints before the Department of Environment and
MENDOZA, J.: Natural Resources (DENR), Mines and Geosciences Bureau,
This petition for review on certiorari with prayer for the Regional Panel of Arbitrators against Luzon Iron.
issuance of a writ of preliminary injunction and/or temporary The RTC Orders
In its March 18, 2013 Order, the RTC denied the motions to ISSUES
dismiss, as well as the supplemental motion to dismiss, finding I
that Consolidated Iron was doing business in the Philippines, WHETHER THE COURT OF APPEALS ERRED IN RULING
with Luzon Iron as its resident agent. The RTC ruled that it had THAT THE TRIAL COURT ACQUIRED JURISDICTION OVER
jurisdiction over the subject matter because under clause 14.8 THE PERSON OF CONSOLIDATED IRON;
of the TPAA, the parties could go directly to courts when a II
direct and/or blatant violation of the provisions of the TPAA had WHETHER THE COURT OF APPEALS ERRED IN RULING
been committed. The RTC also opined that the complaint filed THAT THE TRIAL COURT HAS JURISDICTION OVER THE
before the DENR did not constitute forum shopping because SUBJECT MATTER OF THE CONSOLIDATED CASES; AND
there was neither identity of parties nor identity of reliefs III
sought. WHETHER THE COURT OF APPEALS ERRED IN RULING
THAT BRIDESTONE/ANACONDA WERE NOT GUILTY OF
Luzon Iron and Consolidated Iron moved for reconsideration, FORUM SHOPPING.[9]
but the RTC denied their motion in its September 18, 2013 Petitioners Luzon Iron and Consolidated Iron insist that the RTC
Order. has no jurisdiction over the latter because it is a foreign
corporation which is neither doing business nor has transacted
business in the Philippines. They argue that there could be no
Undaunted, they filed their petition for review with prayer for
means by which the trial court could acquire jurisdiction over
the issuance of a writ of preliminary injunction and/or TRO
the person of Consolidated Iron under any mode of service of
before the CA.
summons. The petitioners claim that the service of summons to
Consolidated Iron was defective because the mere fact that
The CA Ruling Luzon Iron was a wholly-owned subsidiary of Consolidated Iron
In its September 8, 2015 Decision, the CA affirmed the March did not establish that Luzon Iron was the agent of Consolidated
18, 2013 and September 18, 2013 RTC Orders in denying the Iron. They emphasize that Consolidated Iron and Luzon Iron
motions to dismiss and the supplemental motions to dismiss. It are two distinct and separate entities.
agreed that the court acquired jurisdiction over the person of
Consolidated Iron because the summons may be validly served
The petitioners further assert that the trial court had no
through its agent Luzon Iron, considering that the latter was
jurisdiction over the consolidated cases because of the
merely the business conduit of the former. The CA also
arbitration clause set forth in the TPAA. They reiterate that
sustained the jurisdiction of the RTC over the subject matter
Luzon Iron and Consolidated Iron were guilty of forum shopping
opining that the arbitration clause in the TPAA provided for an
because their DENR complaint contained similar causes of
exception where parties could directly go to court.
action and reliefs sought. They stress that the very evil sought
Further, the CA also disregarded the averment of forum
to be prevented by the prohibition on forum shopping had
shopping, explaining that in the complaint before the RTC, both
occurred when the DENR and the RTC issued conflicting orders
Consolidated Iron and Luzon Iron were impleaded but in the
in dismissing or upholding the complaints filed before them.
complaint before the DENR only the latter was impleaded. It
stated that there was no identity of relief and no identity of
cause of action. Position of Respondents
In their Comment/Opposition,[10] dated January 7, 2016,
respondents Bridestone and Anaconda countered that the RTC
Hence, this appeal raising the following:
validly acquired jurisdiction over the person of Consolidated
Iron. They posited that Consolidated Iron was doing business in
the Philippines as Luzon Iron was merely its conduit. Thus, they Filing of complaints
insisted that summons could be served to Luzon Iron as before the RTC and the
Consolidated Iron's agent. Likewise, they denied that they were DENR is forum shopping
guilty of forum shopping as the issues and the reliefs prayed for Forum shopping is committed when multiple suits involving the
in the complaints before the RTC and the DENR differed. same parties and the same causes of action are filed, either
Further, the respondents asserted that the trial court had simultaneously or successively, for the purpose of obtaining a
jurisdiction over the complaints because the TPAA itself allowed favorable judgment through means other than appeal or
a direct resort before the courts in exceptional circumstances. certiorari.[12] The prohibition on forum shopping seeks to
They cited paragraph 14.8 thereof as basis explaining that prevent the possibility that conflicting decisions will be rendered
when a direct and/or blatant violation of the TPAA had been by two tribunals.[13]
committed, a party could go directly to the courts. They faulted In Spouses Arevalo v. Planters Development Bank,[14] the Court
the petitioners in not moving for the referral of the case for elaborated that forum shopping vexed the court and warranted
arbitration instead of merely filing a motion to dismiss. They the dismissal of the complaints. Thus:
added that actions that are subject to arbitration agreement Forum shopping is the act of litigants who repetitively avail
were merely suspended, and not dismissed. themselves of multiple judicial remedies in different fora,
simultaneously or successively, all substantially founded on the
Reply of Petitioners same transactions and the same essential facts and
In their Reply,[11] dated April 29, 2016, the petitioners stated circumstances; and raising substantially similar issues either
that Consolidated Iron was not necessarily doing business in pending in or already resolved adversely by some other court;
the Philippines by merely establishing a wholly-owned or for the purpose of increasing their chances of obtaining a
subsidiary in the form of Luzon Iron. Also, they asserted that favorable decision, if not in one court, then in another. The
Consolidated Iron had not been validly served the summons rationale against forum-shopping is that a party should
because Luzon Iron is neither its resident agent nor its not be allowed to pursue simultaneous remedies in two
representative in the Philippines. The petitioners explained that different courts, for to do so would constitute abuse of
Luzon Iron, as a wholly-owned subsidiary, had a separate and court processes which tends to degrade the
distinct personality from Consolidated Iron. administration of justice, wreaks havoc upon orderly
The petitioners explained that Paragraph 14.8 of the TPAA judicial procedure, and adds to the congestion of the
should not be construed as an authority to directly resort to heavily burdened dockets of the courts.
court action in case of a direct and/or blatant violation of the xxxx
TPAA because such interpretation would render the arbitration
clause nugatory. They contended that, even for the sake of What is essential in determining the existence of forum-
argument, the judicial action under the said provisions was shopping is the vexation caused the courts and litigants
limited to issues or matters which were inexistent in the by a party who asks different courts and/or
present case. They added that a party was not required to file a administrative agencies to rule on similar or related
formal request for arbitration before an arbitration clause causes and/or grant the same or substantially similar
became operational. Lastly, they insisted that the respondents reliefs, in the process creating the possibility of
were guilty of forum shopping in simultaneously filing conflicting decisions being rendered upon the same
complaints before the trial court and the DENR. issues.
xxxx
The Court's Ruling
The petition is impressed with merit.
We emphasize that the grave evil sought to be avoided by the causes of action are identical is to ascertain whether the
rule against forum-shopping is the rendition by two competent same evidence will sustain both actions, or whether
tribunals of two separate and contradictory decisions. To avoid there is an identity in the facts essential to the
any confusion, this Court adheres strictly to the rules maintenance of the two actions. If the same facts or
against forum shopping, and any violation of these rules evidence would sustain both, the two actions are
results in the dismissal of a case. The acts committed and considered the same, and a judgment in the first case is
described herein can possibly constitute direct a bar to the subsequent action. Hence, a party cannot, by
contempt.[15] [Emphases supplied] varying the form of action or adopting a different method of
There is forum shopping when the following elements are presenting his case, escape the operation of the principle that
present: (a) identity of parties, or at least such parties one and the same cause of action shall not be twice litigated
representing the same interests in both actions; (b) identity of between the same parties or their privies. xxx[20] [Emphases
rights asserted and reliefs prayed for, the relief being founded supplied]
on the same facts; and (c) the identity of the two preceding In the case at bench, both complaints filed before
particulars, such that any judgment rendered in the other different fora involved similar facts and issues, the resolution of
action will, regardless of which party is successful, amounts which depends on analogous evidence. Thus, the filing of two
to res judicata in the action under consideration.[16] All the separate complaints by the petitioners with the RTC and the
above-stated elements are present in the case at bench. DENR clearly constitutes forum shopping.
First, there is identity of parties. In both the complaints before It is worth noting that the very evil which the prohibition
the RTC and the DENR, Luzon Iron was impleaded as defendant against forum shopping sought to prevent had happened—the
while Consolidated Iron was only impleaded in the complaint RTC and the DENR had rendered conflicting decisions. The trial
before the RTC. Even if Consolidated Iron was not impleaded in court ruled that it had jurisdiction notwithstanding the
the DENR complaint, the element still exists. The requirement is arbitration clause in the TPAA. On the other hand, the DENR
only substantial, and not absolute, identity of parties; and there found that it was devoid of jurisdiction because the matter was
is substantial identity of parties when there is community of subject to arbitration.
interest between a party in the first case and a party in the
second case, even if the latter was not impleaded in the other Summons were not
case.[17] Consolidated Iron and Luzon Iron had a common validly served
interest under the TPAA as the latter was a wholly-owned Section 12 of Rule 14 of the Revised Rules of Court provides
subsidiary of the former. that "[w]hen the defendant is a foreign private juridical entity
Second, there is identity of causes of action. A reading of the which has transacted business in the Philippines, service
complaints filed before the RTC and the DENR reveals that they may be made on its resident agent designated in accordance
had almost identical causes of action and they prayed for with law for that purpose, or, if there be no such agent, on the
similar reliefs as they ultimately sought the return of their government official designated by law to that effect, or on any
respective Exploration Permit on the ground of the alleged of its officers or agents within the Philippines."
violations of the TPAA committed by the petitioners.[18] In Yap The Rule on Summons, as it now reads, thus, makes the
v. Chua,[19] the Court ruled that identity of causes of action did question whether Consolidated Iron was "doing business in the
not mean absolute identity. Philippines" irrelevant as Section 12, Rule 14 of the Rules of
Hornbook is the rule that identity of causes of action does not Court was broad enough to cover corporations which have
mean absolute identity; otherwise, a party could easily escape "transacted business in the Philippines."
the operation of res judicata by changing the form of the action
or the relief sought. The test to determine whether the
In fact, under the present legal milieu, the rules on service of provided in Section 15, Rule 14 of the Rules of Court is a
summons on foreign private juridical entities had been specific provision dealing precisely with the service of summons
expanded as it recognizes additional modes by which summons on a defendant which does not reside and is not found in the
may be served. A.M No. 11-3-6-SC[21] thus provides: Philippines. On the other hand, Section 12, Rule 14 thereof,
Section 12. Rule 14 of the Rules of Court is hereby amended to specifically applies to a defendant foreign private juridical entity
read as follows: which had transacted business in the Philippines. Both rules
may provide for similar modes of service of summons,
"SEC. 12. Service upon foreign private juridical entity. — When nevertheless, they should only be applied in particular cases,
the defendant is a foreign private juridical entity which has with one applicable to defendants which do not reside and are
transacted business in the Philippines, service may be made on not found in the Philippines and the other to foreign private
its resident agent designated in accordance with law for that juridical entities which had transacted business in the
purpose, or, if there be no such agent, on the government Philippines.
official designated by law to that effect, or on any of its officers In the case at bench, it is crystal clear that Consolidated Iron
or agents within the Philippines. transacted business in the Philippines as it was a signatory in
If the foreign private juridical entity is not registered in the the TPAA that was executed in Makati. Hence, as the
Philippines or has no resident agent, service may, with leave of respondents argued, it may be served with the summons in
court, be effected out of the Philippines through any of the accordance with the modes provided under Section 12, Rule 14
following means: of the Rules of Court.

a) By personal service coursed through the appropriate court in In Atiko Trans, Inc. v. Prudential Guarantee and Assurance,
the foreign country with the assistance of the Department of Inc.,[23] the Court elucidated on the means by which summons
Foreign Affairs; could be served on a foreign juridical entity, to wit:
On this score, we find for the petitioners. Before it was
amended by A.M. No. 11-3-6-SC, Section 12 of Rule 14 of the
b) By publication once in a newspaper of general circulation in
Rules of Court reads:
the country where the defendant may be found and by serving
a copy of the summons and the court order by registered mail
at the last known address of the defendant; SEC. 12. Service upon foreign private juridical entity. — When
the defendant is a foreign private juridical entity which has
transacted business in the Philippines, service may be made on
c) By facsimile or any recognized electronic means that could
its resident agent designated in accordance with law for that
generate proof of service; or
purpose, or, if there be no such agent, on the government
official designated by law to that effect, or on any of its officers
d) By such other means as the court may in its discretion or agents within the Philippines.
direct." Elucidating on the above provision of the Rules of Court, this
Court declared in Pioneer International, Ltd. v. Guadiz, Jr. that
The petitioners are mistaken in arguing that it cannot be served when the defendant is a foreign juridical entity, service
summons because under Section 15, Rule 14 of the Rules of of summons maybe made upon:
Court, extrajudicial service of summons may be resorted to 1. Its resident agent designated in accordance with law
only when the action is in rem or quasi in rem and not when for that purpose;
the action is in personam. The premise of the petitioners is
erroneous as the rule on extraterritorial service of summons
2. The government official designated by law to receive concerns of a subsidiary company does not by itself call
summons if the corporation does not have a resident agent; for disregarding its corporate fiction. There must be a
or, perpetuation of fraud behind the control or at least a fraudulent
or illegal purpose behind the control in order to justify piercing
3. Any of the corporation's officers or agents within the the veil of corporate fiction. Such fraudulent intent is lacking in
Philippines.[24] [Emphasis supplied] this case.[29] [Emphasis supplied]
The Court, however, finds that Consolidated Iron was not In the case at bench, the complaint merely contained a general
properly served with summons through any of the permissible statement that Luzon Iron was the resident agent of
modes under the Rules of Court. Indeed, Consolidated Iron was Consolidated Iron, and that it was a wholly-owned subsidiary of
served with summons through Luzon Iron. Such service of the latter. There was no allegation showing that Luzon Iron was
summons, however, was defective. merely a business conduit of Consolidated Iron, or that the
latter exercised control over the former to the extent that their
It is undisputed that Luzon Iron was never registered before the separate and distinct personalities should be set aside. Thus,
Securities and Exchange Commission (SEC) as Consolidated Luzon Iron cannot be deemed as an agent of Consolidated Iron
Iron's resident agent. Thus, the service of summons to in connection with the third mode of service of summons.
Consolidated Iron through Luzon Iron cannot be deemed a
service to a resident agent[25] under the first mode of service. To reiterate, the Court did not acquire jurisdiction over
Likewise, the respondents err in insisting that Luzon Iron could Consolidated Iron because the service of summons, coursed
be served summons as an agent of Consolidated Iron, it being a through Luzon Iron, was defective. Luzon Iron was neither the
wholly-owned subsidiary of the latter. The allegations in the resident agent nor the conduit or agent of Consolidated Iron.
complaint must clearly show a connection between the principal
foreign corporation and its alleged agent corporation with On the abovementioned procedural issues alone, the dismissal
respect to the transaction in question as a general allegation of of the complaints before the RTC was warranted. Even granting
agency will not suffice.[26] In other words, the allegations of the that the complaints were not procedurally defective, there still
complaint taken as whole should be able to convey that the existed enough reason for the trial court to refrain from
subsidiary is but a business conduit of the principal or that by proceeding with the case.
reason of fraud, their separate and distinct personality should
be disregarded.[27] A wholly-owned subsidiary is a distinct and
Controversy must be
separate entity from its mother corporation and the fact that
referred for arbitration
the latter exercises control over the former does not justify
The petitioners insisted that the RTC had no jurisdiction over
disregarding their separate personality. It is true that under the
the subject matter because under Paragraph 15.1 of the TPAA,
TPAA, Consolidated Iron wielded great control over the actions
any dispute out of or in connection with the TPAA must be
of Luzon Iron under the said agreement. This, nonetheless,
resolved by arbitration. The said provision provides:
does not warrant the conclusion that Luzon Iron was a mere
conduit of Consolidated Iron. In Pacific Rehouse Corporation v.
CA,[28] the Court ruled: If, for any reasonable reason, the Parties cannot resolve a
Albeit the RTC bore emphasis on the alleged control exercised material fact, material event or any dispute arising out of or in
by Export Bank upon its subsidiary E-Securities, "[c]ontrol, by connection with this TPAA, including any question regarding its
itself, does not mean that the controlled corporation is a mere existence, validity or termination, within 90 days from its
instrumentality or a business conduit of the mother notice, shall be referred to and finally resolved by arbitration in
company. Even control over the financial and operational Singapore in accordance with the Arbitration Rules of the
Singapore International Arbitration Centre ("SIAC Rules") for all courts in the Philippines which shall be governed by such
the time being in force, which rules are deemed to be rules as the Supreme Court may approve from time to time.
incorporated by reference in this clause 15.1.30 Our policy in favor of party autonomy in resolving
disputes has been reflected in our laws as early as 1949
The RTC, as the CA agreed, countered that Paragraph 14.8 of when our Civil Code was approved. Republic Act No. 876
the TPAA allowed the parties to directly resort to courts in case later explicitly recognized the validity and enforceability of
of a direct and/or blatant violation of the provisions of the parties' decision to submit disputes and related issues to
TPAA. Paragraph 14.8 stated: arbitration.
Arbitration agreements are liberally construed in favor of
proceeding to arbitration. We adopt the interpretation
Each Party agrees not to commence or procure the
that would render effective an arbitration clause if the
commencement of any challenge or claim, action, judicial or
terms of the agreement allow for such
legislative enquiry, review or other investigation into the
interpretation.[33] [Emphases supplied]
sufficiency, validity, legality or constitutionality of (i) the
Thus, consistent with the state policy of favoring arbitration,
assignments of the Exploration Permit Applications(s) (sic) to
the present TPAA must be construed in such a manner that
LIDGC, (ii) any other assignments contemplated by this TPAA,
would give life to the arbitration clause rather than defeat it, if
and/or (iii) or (sic) any agreement to which the Exploration
such interpretation is permissible. With this in mind, the Court
Permit Application(s) may be converted, unless a direct and/or
views the interpretation forwarded by the petitioners as more in
blatant violation of the provisions of the TPAA has been
line with the state policy favoring arbitration.
committed.[31]
In Bases Conversion Development Authority v. DMCI Project
Developers, Inc.,[32] the Court emphasized that the State Paragraphs 14.8 and 15.1 of the TPAA should be harmonized in
favored arbitration, to wit: such a way that the arbitration clause is given life, especially
The state adopts a policy in favor of arbitration. Republic since such construction is possible in the case at bench. A
Act No. 9285 expresses this policy: synchronized reading of the abovementioned TPAA provisions
SEC. 2. Declaration of Policy. — It is hereby declared the policy will show that a claim or action raising the sufficiency, validity,
of the State to actively promote party autonomy in the legality or constitutionality of: (a) the assignments of the EP to
resolution of disputes or the freedom of the parties to make Luzon Iron; (b) any other assignments contemplated by the
their own arrangements to resolve their disputes. Towards TPAA; or (c) any agreement to which the EPs may be
this end, the State shall encourage and actively promote converted, may be instituted only when there is a direct and/or
the use of Alternative Dispute Resolution (ADR) as an blatant violation of the TPAA. In turn, the said action or claim is
important means to achieve speedy and impartial justice commenced by proceeding with arbitration, as espoused in the
and declog court dockets. As such, the State shall TPAA.
provide means for the use of ADR as an efficient tool and
an alternative procedure for the resolution of appropriate The Court disagrees with the respondents that Paragraph 14.8
cases. Likewise, the State shall enlist active private sector of the TPAA should be construed as an exception to the
participation in the settlement of disputes through ADR. This arbitration clause where direct court action may be resorted to
Act shall be without prejudice to the adoption by the Supreme in case of direct and/or blatant violation of the TPAA occurs. If
Court of any ADR system, such as mediation, conciliation, such interpretation is to be espoused, the arbitration clause
arbitration, or any combination thereof as a means of achieving would be rendered inutile as practically all matters may be
speedy and efficient means of resolving cases pending before directly brought before the courts. Such construction is
anathema to the policy favoring arbitration.
A closer perusal of the TPAA will also reveal that paragraph 14 Attention must be paid, however, to the salient wordings of
and all its sub-paragraphs are general provisions, whereas Rule 4.1. It reads: "[a] party to a pending action filed in
paragraphs 15 and all its sub-clauses specifically refer to violation of the arbitration agreement xxx may request the
arbitration. When general and specific provisions are court to refer the parties to arbitration in accordance with such
inconsistent, the specific provision shall be paramount and agreement."
govern the general provision.[34] In using the word "may" to qualify the act of filing a
The petitioners' failure to refer the case for arbitration, "request" under Section 24 of R.A. No. 9285, the Special
however, does not render the arbitration clause in the TPAA ADR Rules clearly did not intend to limit the invocation of
inoperative. In Koppel, Inc. v. Makati Rotary Club Foundation, an arbitration agreement in a pending suit
Inc. (Koppel),[35] the Court explained that an arbitration clause solely via such "request." After all, non-compliance with an
becomes operative, notwithstanding the lack of a formal arbitration agreement is a valid defense to any offending suit
request, when a party has appraised the trial court of the and, as such, may even be raised in an answer as provided in
existence of an arbitration clause, viz: our ordinary rules of procedure.
xxx The operation of the arbitration clause in this case is In this case, it is conceded that petitioner was not able to file a
not at all defeated by the failure of the petitioner to file a separate "request" of arbitration before the MeTC. However, it
formal "request" or application therefor with the is equally conceded that the petitioner, as early as in
MeTC. We find that the filing of a "request" pursuant to Section its Answer with Counterclaim, had already apprised the
24 of R.A. No. 9285 is not the sole means by which an MeTC of the existence of the arbitration clause in the 2005
arbitration clause may be validly invoked in a pending suit. Lease Contract and, more significantly, of its desire to have the
Section 24 of R.A. No. 9285 reads: same enforced in this case. This act of petitioner is enough
valid invocation of his right to arbitrate. xxx[36] [Emphases
SEC. 24. Referral to Arbitration. — A court before which an supplied; italics in the original]
action is brought in a matter which is the subject matter of an It is undisputed that the petitioners Luzon Iron and
arbitration agreement shall, if at least one party so requests not Consolidated Iron never made any formal request for
later that the pre-trial conference, or upon the request of both arbitration. As expounded in Koppel, however, a formal request
parties thereafter, refer the parties to arbitration unless it finds is not the sole means of invoking an arbitration clause in a
that the arbitration agreement is null and void, inoperative or pending suit. Similar to the said case, the petitioners here
incapable of being performed. made the RTC aware of the existence of the arbitration clause
The "request" referred to in the above provision is, in turn, in the TPAA as they repeatedly raised this as an issue in all
implemented by Rules 4.1 to 4.3 of A.M. No. 07-11-08-SC or their motions to dismiss. As such, it was enough to activate the
the Special Rules of Court on Alternative Dispute arbitration clause and, thus, should have alerted the RTC in
Resolution (Special ADR Rules): proceeding with the case.
RULE 4: REFERRAL TO ADR Moreover, judicial restraint should be exercised pursuant to the
competence-competence principle embodied in Rule 2.4 of the
Special Rules of Court on Alternative Dispute Resolution.[37] The
Rule 4.1. Who makes the request. — A party to a pending
said provision reads:
action filed in violation of the arbitration agreement, whether
RULE 2.4. Policy Implementing Competence-Competence
contained in an arbitration clause or in a submission
Principle. — The arbitral tribunal shall be accorded the first
agreement, may request the court to refer the parties to
opportunity or competence to rule on the issue of whether or
arbitration in accordance with such agreement.
not it has the competence or jurisdiction to decide a dispute
xxxx
submitted to it for decision, including any objection with respect
to the existence or validity of the arbitration agreement. When
a court is asked to rule upon issue/s affecting the
competence or jurisdiction of an arbitral tribunal in a
dispute brought before it, either before or after the
arbitral tribunal is constituted, the court must exercise
judicial restraint and defer to the competence or
jurisdiction of the arbitral tribunal by allowing the
arbitral tribunal the first opportunity to rule upon such
issues.
Where the court is asked to make a determination of whether
the arbitration agreement is null and void, inoperative or
incapable of being performed, under this policy of judicial
restraint, the court must make no more than a prima
facie determination of that issue.
Unless the court, pursuant to such prima facie determination,
concludes that the arbitration agreement is null and void,
inoperative or incapable of being performed, the court must
suspend the action before it and refer the parties to arbitration
pursuant to the arbitration agreement. [Emphasis supplied]
Generally, the action of the court is stayed if the matter raised
before it is subject to arbitration.[38] In the case at bench,
however, the complaints filed before the RTC should have been
dismissed considering that the petitioners were able to establish
the ground for their dismissal, that is, violating the prohibition
on forum shopping. The parties, nevertheless, are directed to
initiate arbitration proceedings as provided under Paragraph
15.1 of the TPAA.
WHEREFORE, the petition is GRANTED. The September 8,
2015 Decision of the Court of Appeals in CA-G.R. SP No.
133296, affirming the March 18, 2013 and September 18, 2013
Orders of the Regional Trial Court, Branch 59, Makati City, is
hereby SET ASIDE. The complaints in Civil Case Nos. 12-1053
and 12-1054 are DISMISSED. The parties, however,
are ORDERED to commence arbitration proceedings pursuant
to Paragraph 15.1 of the Tenement Partnership and Acquisition
Agreement.
SO ORDERED.
GR. No. 196072, September 20, 2017 in the Supreme Court, the Court of Appeals or different
divisions, or any other tribunal or agency[.]” In this
STEAMSHIP MUTUAL UNDERWRITING ASSOCIATION certification, the petitioner must state the status of any other
(BERMUDA) LIMITED, Petitioner, v. SULPICIO LINES, action or proceeding, if there is any, and undertakes to report
INC., Respondent. to the courts and other tribunal within five (5) days from
learning of any similar action or proceeding. Failure to comply
G.R. NO. 208603 with the foregoing mandates constitutes a sufficient ground for
the denial of the petition.
SULPICIO LINES, INC., Petitioner, v. STEAMSHIP MUTUAL
UNDERWRITING ASSOCIATION (BERMUDA) Corporations; Verification; Certification Against Forum
LIMITED, Respondent. Shopping; In case the petitioner is a private corporation, the
verification and certification may be signed, for and on behalf of
Remedial Law; Civil Procedure; Appeals; Petition for Review on this corporation, by a specifically authorized person, including
Certiorari; A Rule 45 petition is the proper remedy to reverse a its retained counsel, who has personal knowledge of the facts
decision or resolution of the Court of Appeals (CA) even if the required to be established by the documents.—In case the
error assigned is grave abuse of discretion in the findings of petitioner is a private corporation, the verification and
fact or of law.—A Rule 45 petition is the proper remedy to certification may be signed, for and on behalf of this
reverse a decision or resolution of the Court of Appeals even if corporation, by a specifically authorized person, including its
the error assigned is grave abuse of discretion in the findings of retained counsel, who has personal knowledge of the facts
fact or of law. “The existence and availability of the right of required to be established by the documents. The reason is
appeal prohibits the resort to certiorari because one of the that: A corporation, such as the petitioner, has no powers
requirements for the latter remedy is that there should be no except those expressly conferred on it by the Corporation Code
appeal.” Allegations in the petition of grave abuse of discretion and those that are implied by or are incidental to its existence.
on the part of the Court of Appeals do not ipso facto render the In turn, a corporation exercises said powers through its board
intended remedy that of certiorari under Rule 65 of the Rules of of directors and/or its duly authorized officers and agents.
Court. In Microsoft Corporation v. Best Deal Computer Center Physical acts, like the signing of documents, can be performed
Corporation, 389 SCRA 615 (2002), this Court discussed the only by natural persons duly authorized for the purpose by
distinction between a Petition for Certiorari under Rule 65 and a corporate bylaws or by a specific act of the board of directors.
Petition for Review on Certiorari under Rule 45. “All acts within the powers of a corporation may be performed
by agents of its selection; and, except so far as limitations or
Same; Same; Same; Same; Under Rule 45 of the Rules of restrictions which may be imposed by special charter, bylaw, or
Court, a petition for review must be verified and must contain a statutory provisions, the same general principles of law which
sworn certification against forum shopping.—Under Rule 45 of govern the relation of agency for a natural person govern the
the Rules of Court, a petition for review must be verified and officer or agent of a corporation, of whatever status or rank, in
must contain a sworn certification against forum shopping. “A respect to his power to act for the corporation; and agents once
pleading is verified by an affidavit that the affiant has read the appointed, or members acting in their stead, are subject to the
pleading and that the allegations therein are true and correct of same rules, liabilities and incapacities as are agents of
his [or her] personal knowledge or based on authentic records.” individuals and private persons.” . . . . For who else knows of
On the other hand, a certification against forum shopping is a the circumstances required in the Certificate but its own
petitioner’s, statement “under oath that he [or she] has retained counsel. Its regular officers, like its board chairman
not . . . commenced any other action involving the same issues and president may not even know the details required therein.
Same; Certification Against Forum Shopping; A certification Birkhann + Nolte, Ingeniurgesellschaft mbh, 435 SCRA 246
not signed by a duly authorized person renders the petition (2004), was misplaced. That case was decided on the basis of
subject to dismissal.—A certification not signed by a duly Republic Act No. 876 or the Old Arbitration Law, which did not
authorized person renders the petition subject to dismissal. provide for instances where some of the multiple impleaded
Moreover, the lack of or defect in the certification is not parties were not covered by an arbitration agreement. It adds
generally curable by its subsequent submission or correction. that now, Section 25 of the ADR Law specifically provides that
However, there are cases where this Court exercised leniency “the court shall refer to arbitration those parties who are bound
due to the presence of special circumstances or compelling by the arbitration agreement although the civil action may
reasons, such as the prima facie merits of the petition. In some continue as to those who are not bound by such arbitration
cases, the subsequent submission of proof of authority of the agreement.” Even from a procedural standpoint, Steamship
party signing the certification on behalf of the corporation was contends that the claim against it may be separated from
considered as substantial compliance with the rules and the Pioneer Insurance and Seaboard-Eastern as these local
petition was given due course. insurance companies were impleaded as solidary
obligors/debtors.
Same; Verification; Certification Against Forum Shopping;
Forum Shopping; The rules on forum shopping are not to be
interpreted with “absolute literalness” as to subvert the
procedural rules ultimate objective of achieving substantial Same; Contracts; Freedom of Contract Principle; Under the
justice as expeditiously as possible. These goals would not be freedom of contract principle, parties to a contract may
circumvented by the Supreme Court’s (SC’s) recognition of the stipulate on a particular method of settling any conflict between
authorized counsel’s signature in the verification and them.—It is the State’s policy to promote party autonomy in
certification of non-forum shopping.—The rules on forum the mode of resolving disputes. Under the freedom of contract
shopping are “designed . . . to promote and facilitate the principle, parties to a contract may stipulate on a particular
orderly administration of justice.” They are not to be method of settling any conflict between them. Arbitration and
interpreted with “absolute literalness” as to subvert the other alternative dispute resolution methods like mediation,
procedural rules’ ultimate objective of achieving substantial negotiation, and conciliation are favored over court action.
justice as expeditiously as possible. These goals would not be Republic Act No. 9285 expresses this policy: Section 2.
circumvented by this Court’s recognition of the authorized Declaration of Policy.—It is hereby declared the policy of the
counsel’s signature in the verification and certification of non- State to actively promote party autonomy in the resolution of
forum shopping. disputes or the freedom of the parties to make their own
arrangements to resolve their disputes. Towards this end, the
Civil Law; Arbitration; Alternative Dispute Resolution Act of State shall encourage and actively promote the use of
2004; Section 25 of the Alternative Dispute Resolution Act of Alternative Dispute Resolution (ADR) as an important means to
2004 (ADR Law) specifically provides that “the court shall refer achieve speedy and impartial justice and declog court dockets.
to arbitration those parties who are bound by the arbitration As such, the State shall provide means for the use of ADR as an
agreement although the civil action may continue as to those efficient tool and an alternative procedure for the resolution of
who are not bound by such arbitration agreement.”—Steamship appropriate cases. Likewise, the State shall enlist active private
argues that a referral of the case to arbitration is imperative sector participation in the settlement of disputes through ADR.
pursuant to the mandates of Republic Act No. 9285 or the ADR This Act shall be without prejudice to the adoption by the
Law. It adds that the trial court’s reliance on the ruling in Supreme Court of any ADR system, such as mediation,
European Resources and Technologies, Inc. v. Ingenieuburo conciliation, arbitration, or any combination thereof as a means
of achieving speedy and efficient means of resolving cases Same; Arbitration; In domestic arbitration, the formal
pending before all courts in the Philippines which shall be requirements of an arbitration agreement are that it must “be
governed by such rules as the Supreme Court may approve in writing and subscribed by the party sought to be charged, or
from time to time. by his lawful agent.” In international commercial arbitration, it
is likewise required that the arbitration agreement must be in
Insurance Law; Insurance Policy; Words and Phrases; Title VI, writing.—The Court of Appeals ruled that the arbitration
Section 49 of Presidential Decree (PD) No. 612 or the Insurance agreement in the 2005/2006 Club Rules is not valid because it
Code defines an insurance policy as “the written instrument in was not signed by the parties. In domestic arbitration, the
which a contract of insurance is set forth.”—Title VI, Section 49 formal requirements of an arbitration agreement are that it
of Presidential Decree No. 612 or the Insurance Code defines an must “be in writing and subscribed by the party sought to be
insurance policy as “the written instrument in which a contract charged, or by his lawful agent.” In international commercial
of insurance is set forth.” Section 50 of this Code provides that arbitration, it is likewise required that the arbitration agreement
the policy, which is required to be in printed form, “may contain must be in writing. An arbitration agreement is in writing if it is
blank spaces; and any word, phrase, clause, mark, sign, contained (1) in a document signed by the parties, (2) in an
symbol, signature, number, or word necessary to complete the exchange of letters, telex,telegrams or other means of
contract of insurance shall be written on the blank spaces.” Any telecommunication which provide a record of the agreement, or
rider, clause, warranty, or endorsement attached and referred (3) in an exchange of statements of claim and defense in which
to in the policy by its descriptive title or name is considered the existence of an agreement is alleged by a party and not
part of this policy or contract of insurance and binds the denied by another. The reference in a contract to a document
insured. Section 51 of the Insurance Code prescribes the containing an arbitration clause constitutes an arbitration
information that must be stated in the policy, namely: the agreement provided, that the contract is in writing and the
parties in the insurance contract, amount insured, premium, reference is such as to make that clause part of the contract.
property or life insured, risks insured against, and period of
insurance. However, there is nothing in the law that prohibits Same; Same; An arbitration agreement that was not embodied
the parties from agreeing to other terms and conditions that in the main agreement but set forth in another document is
would govern their relationship, in which case the general rules binding upon the parties, where the document was incorporated
of the Civil Code regulating contracts will apply. by reference to the main agreement.—An arbitration agreement
that was not embodied in the main agreement but set forth in
Civil Law; Contracts; Interpretation of Contracts; When the text another document is binding upon the parties, where the
of a contract is explicit and leaves no doubt as to its intention, document was incorporated by reference to the main
the court may not read into it any other intention that would agreement. The arbitration agreement contained in the Club
contradict its plain import.—“[W]hen the text of a contract is Rules, which in turn was referred to in the Certificate of Entry
explicit and leaves no doubt as to its intention, the court may and Acceptance, is binding upon Sulpicio even though there
not read into it any other intention that would contradict its was no specific stipulation on dispute resolution in this
plain import.” The incorporation of the Club Rules in the Certificate. Furthermore, as stated earlier, Sulpicio became a
insurance policy is without any qualification. This includes the member of Steamship by the very act of making a contract of
arbitration clause even if not particularly stipulated. A basic rule insurance with it. The Certificate of Entry and Acceptance
in construction is that the entire contract, and each and all of issued by Steamship states that “[its] name has been entered
its parts, must be read together and given effect, with all its in the Register of Members of the Club as a Member.” Sulpicio
clauses and provisions harmonized with one another. admits its membership and the entry of its vessels to
Steamship.
Same; Contracts; A party is not relieved of the duty to exercise Same; Same; Where a motion is filed in court for the referral of
the ordinary care and prudence that would be exacted in a dispute to arbitration, Section 24 of Republic Act (RA) No.
relation to other contracts.—“[A] party is not relieved of the 9285 ordains that the dispute shall be referred “to arbitration
duty to exercise the ordinary care and prudence that would be unless it finds that the arbitration agreement is null and void,
exacted in relation to other contracts. The conformity of the inoperative or incapable of being performed.”—Where a motion
insured to the terms of the policy is implied from [its] failure to is filed in court for the referral of a dispute to arbitration,
express any disagreement with what is provided for.” The Section 24 of Republic Act No. 9285 ordains that the dispute
agreement to submit all disputes to arbitration is a long shall be referred “to arbitration unless it finds that the
standing provision in the Club Rules. It was incumbent upon arbitration agreement is null and void, inoperative or incapable
Sulpicio to familiarize itself with the Club Rules, under the of being performed.” Thus, the Regional Trial Court went
presumption that a person takes due care of its concerns. Being beyond its authority of determining only the issue of whether or
a member of Steamship for 20 years, it has been bound by its not there was a valid arbitration agreement between the parties
Rules and has been expected to abide by them in good faith. when it denied Steamship’s Motion to Dismiss and/or to Refer
Case to Arbitration solely on the ground that it would not be the
Same; Estoppel; “In estoppel, a person, who by his [or her] most prudent action under the circumstances of the case. The
deed or conduct has induced another to act in a particular Regional Trial Court went against the express mandate of
manner, is barred from adopting an inconsistent position, Republic Act No. 9285. Consequently, the Court of Appeals
attitude or course of conduct that thereby causes loss or injury erred in finding no grave abuse of discretion on the part of the
to another.”—Sulpicio is estopped from denying knowledge of trial court in denying referral to arbitration.
the Rulebook by its own acts and representations, as evidenced
by its various letters to Steamship, showing its familiarity with Remedial Law; Special Civil Actions; Contempt; The court’s
the Rulebook and its provisions. “In estoppel, a person, who by contempt power should be exercised with restraint and for a
his [or her] deed or conduct has induced another to act in a preservative, and not a vindictive, purpose. “Only in cases of
particular manner, is barred from adopting an inconsistent clear and contumacious refusal to obey should the power be
position, attitude or course of conduct that thereby causes loss exercised.”—The court’s contempt power should be exercised
or injury to another.” It further bars a party from denying or with restraint and for a preservative, and not a vindictive,
disproving a fact, which has become settled by its acts. Hence, purpose. “Only in cases of clear and contumacious refusal to
this Court finds a preponderance of evidence showing that obey should the power be exercised.” In Lorenzo Shipping
Sulpicio was given a copy and had knowledge of the 2005/2006 Corporation v. Distribution Management Association of the
Club Rules. Moreover, the 2005/2006 Club Rules’ provision on Philippines, 656 SCRA 331 (2011), this Court held that: There
arbitration is valid and binding upon Sulpicio. is no question that in contempt the intent goes to the gravamen
of the offense. Thus, the good faith, or lack of it, of the alleged
Same; Arbitration; The present rule on multiple parties contemnor should be considered. Where the act complained of
manifests due regard to the policy of the law in favor of is ambiguous or does not clearly show on its face that it is
arbitration.—The present rule on multiple parties manifests due contempt, and is one which, if the party is acting in good faith,
regard to the policy of the law in favor of arbitration. In light of is within his rights, the presence or absence of a contumacious
the express mandate of Republic Act No. 9285 and the intent is, in some instances, held to be determinative of its
subsequent 2009 Special ADR Rules, this Court’s ruling in character. A person should not be condemned for contempt
European Resources and Technologies, Inc. v. Ingenieuburo where he contends for what he believes to be right and in good
Birkhann + Nolte, Ingeniurgesellschaft mbh, 435 SCRA 246 faith institutes proceedings for the purpose, however erroneous
(2004), is deemed abrogated. may be his conclusion as to his rights. To constitute contempt,
the act must be done willfully and for an illegitimate or World, evidenced by a Certificate of Entry and Acceptance
improper purpose. issued by Steamship, which provided:

DECISION CERTIFICATE OF ENTRY AND ACCEPTANCE


by the Club of your proposal for entering the ship(s) specified
LEONEN, J.: below, and of
the tonnage set out against each, in:
An insured member may be compelled to arbitration pursuant
Class 1 PROTECTION AND INDEMNITY
to the Rules of the Protection and Indemnity Club, which were
of the Club from
incorporated in the insurance policy by reference. Where there
Noon 20th February 2005 to Noon 20th February 2006
are multiple parties, the court must refer to arbitration the
parties covered by the agreement while proceeding with the
civil action against those who were not bound by the arbitration
agreement.
or until sold, lost, withdrawn or the entry is terminated in
accordance with the rules, to the extent specified and in
G.R. No. 196072 is a Petition for Review1 seeking to set aside
accordance with the Act, By(e)-Laws and the Rules from time to
the November 26, 2010 Decision2 and March 10, 2011
time in force and the special terms specified overleaf.
Resolution3 of the Court of Appeals in CA-GR. SP No. 106103.
Your name has been entered in the Register of Members of the
GR. No. 208603 is a Petition for Indirect Contempt4 filed by
Club as a Member.
Sulpicio Lines, Inc. (Sulpicio) against Steamship Mutual
Underwriting Association (Bermuda) Limited (Steamship). It
prays, among others, that Steamship be (a) declared guilty of
FOR ACCOUNT CERTIFICATE
indirect contempt; (b) imposed a fine of P30,000.00; and (c) NUMBER
OF
ordered to restitute to Sulpicio the amount of US$69,570.99 or
Sulpicio
its equivalent in Philippine currency plus interest, computed
Lines Inc., 155,534
from December 3, 2012 until fully restituted.5
1st Floor,
Reclamation
Steamship was a Bermuda-based Protection and Indemnity
Area,
Club, managed outside London, England.6 It insures its
P.O. Box
members-shipowners against "third party risks and liabilities"
No. 137
for claims arising from (a) death or injury to passengers; (b)
Cebu City,
loss or damage to cargoes; and (c) loss or damage from
Philippines.
collisions.7

Sulpicio insured its fleet of inter-island vessels with Steamship NAME OF BUILT ENTE CLA PORT
for Protection & Indemnity risks through local insurance agents, SHIP RED SS OF
Pioneer Insurance and Surety Corporation (Pioneer Insurance) GROS REGI
or Seaboard-Eastern Insurance Co., Inc. (Seaboard- S STRY
1975
Eastern).8 One (1) of these vessels was the M/V Princess of the
"PRINCESS B.V S OF ORATIN
TONN
OF THE . ENTRY G ALL
AGE
OCEAN" 1983 6,150 BEING PREVIO
CANCEL US
LED ALTERA
Cebu B.V AND AS TIONS
"PRINCESS 1979 City . 13,52 TO AND A
OF THE 6 THE COPY IS
UNIVERSE" CIRCUM SENT
1972 B.V STANCE TO
Cebu
. 3,768 S OF AN EACH
City
"PRINCESS ALTERA MEMBE
OF THE TION IN R.
1984
CARIBBEAN" THE ALTERA
(Rebuilt Cebu B.V 9,627
RULES TIONS
1990) City . OR CAN BE
BY(E)- MADE
"PRINCESS 19,32 LAWS. BY
OF THE 9 ORDINA
Cebu X.X
WORLD" RY
City .
RESOLU
TION
"PRINCESS FOLLOW
OF THE Cebu ING A
STARS" City GENERA
L
MEETIN
....
G
NOTES NOTIFIE
D TO
1. REFERE 2. THE ALL
NCE IS RULES MEMBE
REQUES ARE RS.[9
TED TO PRINTE
THE D
RULES ANNUAL
AS TO LY IN
THE BOOK On July 7, 2005, M/V Princess of the World was gutted by fire
CIRCUM FORM, while on voyage from Iloilo to Zamboanga City, resulting in
STANCE INCORP total loss of its cargoes. The fire incident was found by the
Department of Interior and Local Government to be "accidental"
in nature.10 November 26, 2010 Decision.26 It found no grave abuse of
discretion on the part of the trial court in denying Steamship's
Sulpicio claimed indemnity from Steamship under the Motion to Dismiss and/or to Refer Case to Arbitration27 or any
Protection & Indemnity insurance policy. Steamship denied the convincing evidence to show that a valid arbitration agreement
claim and subsequently rescinded the insurance coverage of existed between the parties.28 Steamship's Motion for
Sulpicio's other vessels on the ground that "Sulpicio was grossly Reconsideration of this Decision was likewise denied in the
negligent in conducting its business regarding safety, Resolution29 dated March 10, 2011.
maintaining the seaworthiness of its vessels as well as proper
training of its crew."11 On April 29, 2011, Steamship filed before this Court this
Petition for Review, docketed as G.R. No. 196072. In
On June 28, 2007, Sulpicio filed a Complaint12 with the Regional compliance with this Court's June 13, 2011
Trial Court of Makati City against Steamship; one (1) of its Resolution,30 Sulpicio filed its Comment31 on August 31, 2011
directors, Gary Rynsard; and its local insurance agents Pioneer and Steamship filed its Reply32 on October 20, 2011.
Insurance and Seaboard-Eastern for specific performance and
damages. This Complaint was docketed as Civil Case No. 07- On September 6, 2013, Sulpicio filed with this Court a Petition
577, was amended on August 10, 2007,13 and further amended for Indirect Contempt33 under Rule 71 of the Rules of Court
on September 11, 2007.14 against Steamship. This Petition was docketed as GR. No.
208603.
Steamship filed its Motion to Dismiss and/or to Refer Case to
Arbitration15 pursuant to Republic Act No. 9285, or the Sulpicio alleges that sometime in September 2012, it settled its
Alternative Dispute Resolution Act of 2004 (ADR Law), and to judgment liability of P4,121,600.00 in Civil Case No. CEB-
Rule 4716 of the 2005/2006 Club Rules, which supposedly 24783, entitled Verna Unabia v. Sulpicio Lines, Inc.34 However,
provided for arbitration in London of disputes between the actual amount reimbursed by Steamship was not
Steamship and its members.17 The other defendants filed P4,121,600.00, equivalent to US$96,958.47, but only
separate motions to dismiss.18 US$27,387.48.35 Steamship deducted US$69,570.99, which
allegedly represented Sulpicio's share in the arbitration costs
Branch 149, Regional Trial Court, Makati City denied the for the arbitration in London of the dispute in Civil Case No. 07-
motions to dismiss. In its July 11, 2008 Order, 19 denying 577.36
Steamship's motion and supplemental motion to dismiss and
citing20European Resources and Technologies, Inc. v. Sulpicio accuses Steamship of indirect contempt for its
Ingenieuburo Birkhann + Nolte, Ingeniurgesellschaft "improper conduct tending directly, or indirectly, to impede,
Gmbh21 the Regional Trial Court held that "arbitration [did] not obstruct, or degrade the administration of justice" 37 consisting
appear to be the most prudent action, . . . considering that the of the following acts:
other defendants . . . ha[d] already filed their [respective]
[a]nswers."22 Steamship filed its Motion for (a) Without Sulpicio's knowledge or consent, Steamship
Reconsideration,23 but it was likewise denied in the initiated and "concluded" during the pendency of this case an
Order24 dated September 24, 2008. alleged "arbitration proceeding" in London for the "Arbitrator"
there to "resolve" the very dispute involved in this case;
Steamship assailed trial court orders before the Court of
Appeals through a Rule 65 Petition, docketed as CA-G.R. SP No. (b) Without Sulpicio's knowledge or consent, Steamship
106103.25 The Court of Appeals dismissed the petition in its proclaimed itself the "victor" entitled to arbitration costs from
Sulpicio;
This Court addresses first the procedural issue raised by
(c) Without Sulpicio's knowledge or consent, Steamship Sulpicio.
unceremoniously deducted from the refund due to Sulpicio in
the separate "Unabia Case" the huge amount I.A
of U.S.$69,570.99 despite the fact that: (a) Said "Unabia
Case" is unrelated to the instant case; (b) The propriety of a
London arbitration is still to be resolved in this case by this Sulpicio contends that Steamship's Petition for Review should
Honorable Court; (c) Steamship "enforced" by itself said be dismissed outright on procedural grounds.42
"arbitration costs" against Sulpicio without the courtesy of even
informing this Honorable Court about it[; and] First, this Petition, couched as a Rule 45 Petition, is actually a
Rule 65 Petition because it contained arguments dealing with
(d) Without Sulpicio's knowledge or consent, and more "grave abuse of discretion" allegedly committed by the Court of
importantly, without the prior approval of this Honorable Court, Appeals.43
Steamship initiated and "concluded" said London "arbitration"
during the pendency of this G.R. No. 196072 and before this Second, the Petition's Verification and Certification Against
Honorable Court could render its ruling or decision.38 (Emphasis Forum Shopping is defective because it was signed and
in the original) executed by Steamship's lawyer. Additionally, the Power of
Attorney appended to the Petition did not indicate its
signatory's name and authority.44
Steamship filed its Comment/Opposition39on January 30, 2014,
to which Sulpicio filed its Reply40 on July 2, 2014.
Third, the issue of whether or not Sulpicio has been furnished
with the Club's Rulebook, which contained the arbitration
In its Resolution41 dated January 15, 2014, this Court resolved
clause, is factual and beyond the realm of a Rule 45 petition.45
to consolidate G.R. Nos. 208603 and 196072.
In its Reply, Steamship avers that its counsel's law firm was
The issues for this Court's resolution are:
duly authorized to sign its Verification and Certification against
Forum Shopping. Moreover, Sulpicio never assailed this law
First, whether or not the petition in G.R. No. 196072 is proper
firm's authority to represent Steamship before the Regional
under the Rules of Court;
Trial Court, and therefore, is estopped to deny its authority
before this Court.46 Together with its Reply, Steamship
Second, whether or not there is a valid and binding arbitration
submitted a copy of the Secretary's Certificate47 to the July 24,
agreement between Steamship Mutual Underwriting (Bermuda)
2007 Board of Directors' resolution authorizing Scott Davis
Limited and Sulpicio Lines, Inc.;
(Davis) or his Assistant Secretaries to sign a Power of Attorney
on behalf of Steamship. It also appended a Secretary's
Third, whether or not the Court of Appeals gravely erred in
Certificate48 to the Jvly 26, 2011 Board of Directors' resolution
affirming the Regional Trial Court Order denying referral of
re appointing Davis and John Charles Ross Collis49 to their
Sulpicio Lines, Inc.'s complaint to arbitration in London in
current positions as Secretary and Assistant Secretary,
accordance with the 2005/2006 Club Rules; and
respectively.
Finally, whether or not Steamship Mutual Underwriting
Steamship further contends that the basic issues raised in the
(Bermuda) Limited is guilty of indirect contempt.
petition are questions of law that are cognizable by this Significantly, even assuming that the orders were erroneous,
Court.50 It adds that a reversal of some factual findings is such error would merely be deemed as an error of judgment
warranted because the Court of Appeals committed a grave that cannot be remedied by certiorari. As long as the
abuse of discretion in concluding that Sulpicio was ignorant of respondent acted with jurisdiction, any error committed by him
the 2005/2006 Club Rules and its arbitration clause, when or it in the exercise thereof will amount to nothing more than
Steamship had presented ample evidence to establish an error of judgment which may be reviewed or corrected only
otherwise.51 Steamship submits that this Court may exercise its by appeal. The distinction is clear: A petition for certiorari seeks
power of review to reverse errors committed by the lower to correct errors of jurisdiction while a petition for review seeks
courts including grave abuse of discretion of the Court of to correct errors of judgment committed by the court. Errors of
Appeals.52 judgment include errors of procedure or mistakes in the court's
findings. Where a court has jurisdiction over the person and
This Court finds for Steamship. subject matter, the decision on all other questions arising in the
case an exercise of that jurisdiction. Consequently, all errors
The appeal from a final disposition of the Court of Appeals is a committed in the exercise of such jurisdiction are merely errors
petition for review under Rule 45 and not a special civil action of judgment. Certiorari under Rule 65 is a remedy designed for
under Rule 65.53 Rule 45, Section 1 is clear that: the correction of errors of jurisdiction and not errors of
judgment.56 (Citations omitted)
Section 1. Filing of petition with Supreme Court. A patty
desiring to appeal by certiorari from a judgment or final order
or resolution of the Court of Appeals, the Sandiganbayan, the
In this case, what Steamship seeks to rectify may be construed
Regional Trial Court or other courts whenever authorized by
as errors of judgment of the Court of Appeals. These errors
law, may file with the Supreme Court a verified petition for
pertain to Steamship's allegations of the Court of Appeals'
review on certiorari. The petition shall raise only questions of
failure to rule that a valid arbitration agreement existed
law which must be distinctly set forth.
between the parties and to refer the case to arbitration. It does
not impute any error with respect to the Court of Appeals'
exercise of jurisdiction, As such, the Petition is simply a
A Rule 45 petition is the proper remedy to reverse a decision or continuation of the appellate process where a case is elevated
resolution of the Court of Appeals even if the error assigned is from the trial court of origin, to the Court of Appeals, and to
grave abuse of discretion in the findings of fact or of law. "The this Court via Rule 45.
existence and availability of the right of appeal prohibits the
resort to certiorari because one of the requirements for the The basic issues raised in the Petition for Review are: (1)
latter remedy is that there should be no appeal."54 whether or not an arbitration agreement may be validly
incorporated by reference to a contract; and (2) how the trial
Allegations in the petition of grave abuse of discretion on the court should proceed to trial upon its finding "that only some
part of the Court of Appeals do not ipso facto render the and not all of the defendants are bound by an arbitration
intended remedy that of certiorari under Rule 65 of the Rules of agreement[.]"57 These are questions of law properly cognizable
Court. In Microsoft Corporation v. Best Deal Computer Center in a Rule 45 petition.
Corporation,55 this Court discussed the distinction between a
Petition for Certiorari under Rule 65 and a Petition for Review In BCDA v. DMCI Project Developers, Inc..58 citing Villamor v.
on Certiorari under Rule 45: Balmores59:
[T]here is a question of law "when there is doubt or controversy misapprehension of facts;63 and (3) when the Court of Appeals'
as to what the law is on a certain [set] of facts." The test is findings of fact are premised on the absence of evidence but
"whether the appellate court can determine the issue raised such findings are contradicted by the evidence on record.64
without reviewing or evaluating the evidence." Meanwhile,
there is a question of fact when there is "doubt . . . as to the Here, this Court finds grave abuse of discretion by the Court of
truth or falsehood of facts." The question must involve the Appeals in its appreciation of facts. As will be discussed later,
examination of probative value of the evidence presented.60 the evidence on record shows that Sulpicio was furnished a
copy of the Club Rulebook and was aware of its provisions.
Other pieces of evidence were Sulpicio's letters 65 to Steamship
and the affidavits of Director and Head of Underwriting of the
Sulpicio denies being bound by the arbitration clause in the
Club Rules since neither the Certificate of Entry and Club and In-Charge of Far East membership including the
Philippines, Jonathan Andrews;66 Vice-President of Pioneer
Acceptance, which covers M/V Princess of the World, mentioned
Insurance who was in charge of Sulpicio's account, Roderick Gil
this arbitration agreement, nor was it given a copy of the Club
Rulebook. Narvacan;67 and Manager of Seaboard-Eastern's Marine
Department who was in charge of Sulpicio's account, Elmer
Felipe.68
In sustaining the denial of Steamship's Motion to Dismiss
and/or to Refer Case to Arbitration, the Court of Appeals ruled:
I.B
Unfortunately, the Court is not convinced that a valid and
binding arbitration agreement exists between the Steamship
The Verification and Certification against Forum Shopping
and Sulpicio. And even assuming that there is such an
agreement, it does not comply with Section 4 of the Arbitration signed by Steamship's counsel substantially complied with
Law which provides that "a contract to arbitrate a controversy the requirements of the Rules of Court.
thereafter arising between the parties, as well as a submission
Under Rule 45 of the Rules of Court, a petition for review must
to arbitrate an existing controversy shall be in writing and
subscribed by the party sought to be charged, or by his lawful be verified69 and must contain a sworn certification against
forum shopping.70
agent."
"A pleading is verified by an affidavit that the affiant has read
As correctly pointed out by Sulpicio, there is no proof that it
was served a copy of the Club Rules in question and that it the pleading and that the allegations therein are true and
signed therein.61 (Emphasis supplied) correct of his [or her] personal knowledge or based on
authentic records."71

On the other hand, a certification against forum shopping is a


A factual question on whether or not Sulpicio was given a copy petitioner's, statement "under oath that he [or she] has not . . .
of the Club Rulebook must be resolved because it has a bearing commenced any other action involving the same issues in the
on the legal issue of whether or not a binding arbitration Supreme Court, the Court of Appeals or different divisions, or
agreement existed between the parties. Factual review, any other tribunal or agency[.]72 In this certification, the
nonetheless, may be justified: (1) when there is a grave abuse petitioner must state the status of any other action or
of discretion in the appreciation of facts;62 (2) when the proceeding, if there is any, and undertakes to report to the
judgment of the Court of Appeals is premised on a courts and other tribunal within five (5) days from learning of
any similar action or proceeding.73 any of the partners of Del Rosario & Del Rosario . . . to sign the
verification or certification"78 against forum shopping of
Failure to comply with the foregoing mandates constitutes a petitions and appeals in appellate courts necessary in
sufficient ground for the denial of the petition.74 representing and defending Steamship. It was notarized,
apostilled in accordance with the law of Bermuda and
In case the petitioner is a private corporation, the verification authenticated by the Philippine consulate in London, United
and certification may be signed, for and on behalf of this Kingdom. However, a closer look into the Power of Attorney
corporation, by a specifically authorized person, including its reveals that the signatory of the document was not identified.
retained counsel, who has personal knowledge of the facts This was pointed out by Sulpicio in its Comment.79
required to be established by the documents.75 The reason is
that: Nonetheless, Steamship subsequent filed its Reply,80 to which it
attached two (2) Secretary's Certificates81 signed by Davis
A corporation, such as the petitioner, has no powers except containing excerpts of the July 24, 2007 and July 26, 2011
those expressly conferred on it by the Corporation Code and board resolutions showing Davis' authority to execute the
those that are implied by or are incidental to its existence. In Power of Attorney on its behalf, and Davis' reappointment as
turn, a corporation exercises said powers through its board of Corporate Secretary, respectively. The signature in the Power
directors and/or its duly authorized officers and agents. Physical of Attorney was similar in form and appearance to Davis'
acts, like the signing of documents, can be performed only by signature in the Secretary's Certificates, which lends credence
natural persons duly authorized for the purpose by corporate to Steamship's submission that the Power of Attorney was
bylaws or by a specific act of the board of directors. "All acts executed and signed by Davis.82
within the powers of a corporation may be performed by agents
of its selection; and, except so far as limitations or restrictions The rule on verification of a pleading is a formal, not
which may be imposed by special charter, by-law, or statutory jurisdictional, requirement.83 This Court has held that:
provisions, the same general principles of law which govern the
relation of agency for a natural person govern the officer or Non compliance with the verification requirement does not
agent of a corporation, of whatever status or rank, in respect to necessarily render the pleading fatally defective, and is
his power to act for the corporation; and agents once substantially complied with when signed by one who has ample
appointed, or members acting in their stead, are subject to the knowledge of the truth of the allegations in the complaint or
same rules, liabilities and incapacities as are agents of petition, and when matters alleged in the petition have been
individuals and private persons." made in good faith or are true and correct.84 (Citation omitted)
....
For who else knows of the circumstances required in the
Certificate but its own retained counsel. Its regular officers, like On the other hand, a certification not signed by a duly
its board chairman and president may not even know the
authorized person renders the petition subject to
details required therein.76
dismissal.85 Moreover, the lack of or defect in the certification is
not generally curable by its subsequent submission or
correction.86 However, there are cases where this Court
In this case, Steamship's Petition's Verification and Certification exercised leniency due to the presence of special circumstances
against forum shopping was signed by its counsel. A Power of or compelling reasons, such as the prima facie merits of the
Attorney77 dated August 1, 2007 was appended to the Petition, petition.87 In some cases, the subsequent submission of proof
which purportedly authorized "Atty. Charles Jay D. Dela Cruz or of authority of the party signing the certification on behalf of
the corporation was considered as substantial compliance with counsel's signature in the verification and certification of non-
the rules and the petition was given due course. 88 forum shopping.

In Shipside Incorporated v. Court of Appeals,89 this Court held: This Court now proceeds to the substantive issues of whether
or not there was a valid arbitration agreement between the
Moreover, in Loyola, Roadway, and Uy, the Court excused non- parties and whether or not referral to arbitration was
compliance with the requirement as to the certificate of non- imperative.
forum shopping. With more, reason should we allow the instant
petition since petitioner herein did submit a certification on II
non-forum shopping, failing only to show proof that the
signatory was authorized to do so. That petitioner subsequently
submitted a secretary's certificate attesting that Balbin was Steamship contends that the arbitration agreement set forth in
authorized to file an action on behalf of petitioner likewise its Club Rules, which in turn is incorporated by reference in the
mitigates this oversight.90 Certificate of Entry and Acceptance of M/V Princess of the
World,94 is valid and binding upon Sulpicio,95 pursuant to this
Court's ruling in BF Corporation v. Court of Appeals.96
Likewise, this Court ho1ds that there is substantial compliance
Steamship further avers that the Court of Appeals' finding that
with the rules on verification and certification against forum
shopping. Steamship's subsequent submission of the there was no proof that Sulpicio was given a copy of the Club
Rules was incorrect and contradicted by the evidence on
Secretary's Certificates showing Davis' authority to execute the
record.97 Steamship adds that by Sulpicio's own declarations in
Power of Attorney in favor of Del Rosario & Del Rosario cured
the defect in the verification and certification appended to the its letter-application98 for membership of its vessels, Sulpicio
petition. Under the circumstances of this case, Steamship's acknowledged that it had received a copy of the Club Rules and
that its membership in Steamship is subject to them. 99 It
counsel would be in the best position to determine the
contends that Sulpicio was "provided with copies of the Club's
truthfulness of the allegations in the petition and certify on non-
forum shopping considering that "it has handled the case for . . Rule books on an annual basis by Pioneer Insurance and
Seaboard-Eastern who acted as brokers [for Sulpicio's]
. Steamship since its inception."91 This Court also considers
entry."100 Moreover, throughout Sulpicio's almost 20 years of
Steamship's allegations that the same Power of Attorney was
membership,101 it has been aware of, and relied upon, the
used in its Answer Ad Cautelam filed on August 12, 2008 before
the Regional Trial Court and in its Petition for Certiorari before terms of the Club Rules, as revealed in its various
correspondences through its brokers with Steamship.102 Thus,
the Court of Appeals on November 12, 2008. Significantly,
Sulpicio is estopped to deny that it was aware of, and agreed to
Sulpicio never questioned the authority of Del Rosario & Del
Rosario to represent Steamship in the proceedings before the be bound by, the Club Rules and their provisions.103
lower courts.92
Steamship argues that a referral of the case to arbitration is
imperative pursuant to the mandates of Republic Act No. 9285
The rules on forum-shopping are "designed . . . to promote and
facilitate the orderly administration of justice." They are not to or the ADR Law.104 It adds that the trial court's reliance on the
ruling in European Resources and Technologies, Inc. v.
be interpreted with "absolute literalness" as to subvert the
Ingenieuburo Birkhann + Nolte, Ingeniurgesellschaft
procedural rules' ultimate objective of achieving substantial
justice as expeditiously as possible.93 These goals would not be Gmbh105 was misplaced. That case was decided on the basis of
circumvented by this Court's recognition of the authorized Republic Act 876 or the Old Arbitration Law, which did not
provide for instances where some of the multiple impleaded Sulpicio further contends that the Certificate of Entry and
parties were not covered by an arbitration agreement. 106 It Acceptance did not provide for arbitration as a mode of dispute
adds that now, Section 25 of the ADR Law specifically provides resolution, that the rules referred to was not particularly
that "the court shall refer to arbitration those parties who are identified or described, and that it never received a copy of the
bound by the arbitration agreement although the civil action Club Rules.117
may continue as to those who are not bound by such arbitration
agreement."107 Even from a procedural standpoint, Steamship Assuming there was valid arbitration agreement between them,
contends that the claim against it may be separated from Sulpicio submits that the trial court correctly relied on the ruling
Pioneer Insurance and Seaboard-Eastern as these local in European Resources in denying the referral of the case to
insurance companies were impleaded as solidary arbitration.118 Arbitration in London would not be the "most
obligors/debtors.108 prudent action" because the arbitral decision will not be binding
on Pioneer Insurance and Seaboard-Eastern and it would result
Steamship further submits that "a Philippine court is an in a "split jurisdiction."119 Sulpicio further contends that the
inconvenient forum to thresh out the issues involved in exception laid down in European Resources still applies because
Sulpicio's claim."109 First, Sulpicio's claim is governed by the the ADR Law was already in effect when the case was decided
English Law, as expressly stated in the 2005/2006 Club by this Court.120
Rules.110 Second, a Philippine court would be "an ineffective
venue" to enforce any judgment that may be obtained against In its Reply, Steamship maintains that there is a valid
Steamship, a foreign corporation.111 Thus, on the basis of the arbitration clause between them and that Sulpicio was well
doctrine of forum non conveniens alone, Steamship contends aware of its Club Rules. It adds that Sulpicio is merely feigning
that the claim against it should be referred to arbitration in ignorance of the Club Rules to escape the obligatory nature of
London.112 the arbitration agreement. Steamship further reiterates that
Section 25 of the ADR Law is plain and clear that when there
Finally, Steamship holds that "Sulpicio should participate in the are multiple parties in an action, the court must "refer to
London Arbitration as [it] is already progressing . . . [i]nstead arbitration those parties bound by the arbitration agreement
of wasting its time on prosecuting its claim before a Philippine and let the action remain as to those who are not
court that is devoid of jurisdiction[.]113 bound."121 "Moreover, as the relationship between . . .
Steamship and . . . Sulpicio are governed by English Law[,] it
Sulpicio counters that the Court of Appeals was correct in ruling may be more prudent to refer the disgute to arbitration in
that there was no arbitration agreement between the London under the doctrine of forum non conveniens."122
parties.114 The arbitration clause in the 2005/2006 Club Rules is
not valid and binding for failure to comply with Section 4 of the Finally, Steamship avers that under Rule 47 of the 2005/2006
ADR Law, which requires that an arbitration agreement be in Club Rules, it has "the right to pursue legal action against a
writing and subscribed by the parties or their lawful [m]ember before any jurisdiction at its sole discretion."123 Even
agent.115 Sulpicio adds that "[i]n White Gold Marine Services, if there is no such provision, Steamship contends that it may
Inc. vs. Pioneer Insurance and Surety Corporation, . . . waive its rights to compel arbitration in individual cases. 124 It
Steamship did not invoke arbitration but filed suit before a adds that the waiver of such right in White Gold has no effect to
Philippine court, which . . . proves that [the 2005/2006 Club this case because Sulpicio is not a party in that case.125
Rules' arbitration clause] is neither mandatory nor binding"
upon the parties.116 II.A
Consistent with State policy, "arbitration agreements are
liberally construed in favor of proceeding to
It is the State's policy to promote party autonomy in the mode arbitration."132 Every reasonable interpretation is indulged to
of resolving disputes.126 Under the freedom of contract give effect to arbitration agreements. Thus, courts must give
principle, parties to a contract may stipulate on a particular effect to the arbitration clause as much as the terms of the
method of settling any conflict between them. 127 Arbitration agreement would allow.133 "Any doubt should be resolved in
and other alternative dispute resolution methods like mediation, favor of arbitration."134
negotiation, and conciliation are favored over court action.
Republic Act No. 9285128 expresses this policy: II.B

Section 2. Declaration of Policy. — It is hereby declared the


policy of the State to actively promote party autonomy in the Sulpicio contends that there was no valid arbitration agreement
resolution of disputes or the freedom of the parties to make between them, and if there were, it was not aware of it.
their own arrangements to resolve their disputes. Towards this
end, the State shall encourage and actively promote the use of This Court rules against Sulpicio's submission.
Alternative Dispute Resolution (ADR) as an important means to
achieve speedy and impartial justice and declog court The contract between Sulpicio and Steamship is more than a
dockets. As such, the State shall provide means for the use of contract of insurance between a marine insurer and a
ADR as an efficient tool and an alternative procedure for the shipowner. By entering its vessels in Steamship, Sulpicio not
resolution of appropriate cases. Likewise, the State shall enlist only obtains insurance coverage for its vessels but also
active private sector participation in the settlement of disputes becomes a member of Steamship.
through ADR. This Act shall be without prejudice to the
adoption by the Supreme Court of any ADR system, such as A protection and indemnity club, like Steamship, is an
mediation, conciliation, arbitration, or any combination thereof association composed of shipowners generally formed for the
as a means of achieving speedy and efficient means of specific purpose of providing insurance cover against third-
resolving cases pending before all courts in the Philippines party liabilities of its members.135 A protection and indemnity
which shall be governed by such rules as the Supreme Court club is a mutual insurance association, described in White Gold
may approve from time to time. (Emphasis supplied) Marine Services, Inc. v. Pioneer Insurance and Surety
Corp.136 as follows:

[A] mutual insurance company is a cooperative enterprise


Arbitration, as a mode of settling disputes, was already
where the members are both the insurer and insured. In it, the
recognized in the Civil Code.129 In 1953, Republic Act No. 876
members all contribute, by a system of premiums or
was passed, which reinforced domestic arbitration as a process
assessments, to the creation of a fund from which all losses and
of dispute resolution. Foreign arbitration was likewise
liabilities are paid, and where the profits are divided among
recognized through the Philippines' adherence to the United
themselves, in proportion to their interest. Additionally, mutual
Nations Convention on the Recognition and Enforcement of
insurance associations, or clubs, provide three types of
Foreign Arbitral Awards of 1958, otherwise known as the New
coverage, namely, protection and indemnity, war risks, and
York Convention.130 Republic Act No. 9285 sets the basic
defense costs.137
principles in the enforcement of foreign arbitral awards in the
Philippines.131
A shipowner wishing to enter its fleet of vessels to Steamship
Reclamation
must fill in an application for entry form, which states:
Area,
P.O. Box
PLEASE ENTER IN THE ASSOCIATION, SUBJECT TO THE RULES,
No. 137
RECEIPT OF WHICH WE ACKNOWLEDGE, THE
Cebu City,
UNDERMENTIONED VESSEL(S).138
Philippines.

NAME OF BUILT ENTE CLA PORT


The application form is signed by the shipowner or its SHIP RED SS OF
authorized representative. GROS REGI
S STRY
Steamship then issues a Certificate of Entry and Acceptance of 1975
TONN
the vessels, showing its acceptance of the entry. The Certificate "PRINCESS B.V
AGE
of Entry and Acceptance for M/V Princess of the World states: OF THE .
OCEAN" 6,150
1983
CERTIFICATE OF ENTRY AND ACCEPTANCE
Cebu
B.V
by the Club of your proposal for entering the ship(s) specified City
"PRINCESS . 13,52
below, and of the tonnage set out against each, in: 1979
OF THE 6
UNIVERSE"
Class 1 PROTECTION AND INDEMNITY Cebu
of the Club from B.V
1972 City
Noon 20th February 2005 to Noon 20th February 2006 . 3,768
"PRINCESS
OF THE
CARIBBEAN" 1984 Cebu
B.V 9,627
or until sold, lost, withdrawn or the entry is terminated in (Rebuilt City
.
accordance with the rules, to the extent specified and in 1990)
accordance with the Act, By(e)-Laws and the Rules from time to "PRINCESS
time in force and the special terms specified overleaf. 19,32
OF THE Cebu
X.X 9
WORLD" City
Your name has been entered in the Register of Members of the .
Club as a Member.

"PRINCESS Cebu
FOR ACCOUNT CERTIFICATE OF THE City
OF NUMBER STARS"
Sulpicio
Lines Inc., 155,534 ....
1st Floor,
NOTES NOTIFIE
D TO
1. REFERE 2. THE ALL
NCE IS RULES MEMBE
REQUES ARE RS.[139
TED TO PRINTE
THE D
RULES ANNUAL
AS TO LY IN
THE BOOK Thus, a contract of insurance is perfected between the parties
CIRCUM FORM, upon Steamship's issuance of the Certificate of Entry and
STANCE INCORP Acceptance.
S OF ORATIN
ENTRY G ALL [A] contract of insurance, like other contracts, must be
BEING PREVIO assented to by both parties either in person or by their agents.
CANCEL US So long as an application for insurance has not been either
LED ALTERA accepted or rejected, it is merely an offer or proposal to make a
AND AS TIONS contract. The contract, to be binding from the date of
TO AND A application, must have been a completed contract, one that
THE COPY IS leaves nothing to be done, nothing to be completed, nothing to
CIRCUM SENT be passed upon, or determined, before it shall take effect.
STANCE TO There can be no contract of insurance unless the minds of the
S OF AN EACH parties have met in agreement.140
ALTERA MEMBE
TION IN R.
THE ALTERA Title VI, Section 49 of Presidential Decree No. 612141 or the
RULES TIONS Insurance Code defines an insurance policy as "the written
OR CAN BE instrument in which a contract of insurance is set forth."
BY(E)- MADE Section 50 of this Code provides that the policy, which is
LAWS. BY required to be in printed form, "may contain blank spaces; and
ORDINA any word, phrase, clause, mark, sign, symbol, signature,
RY number, or word necessary to complete the contract of
RESOLU insurance shall be written on the blank spaces." Any rider,
TION clause, warranty, or endorsement attached and referred to in
FOLLOW the policy by its descriptive title or name is considered part of
ING A this policy or contract of insurance and binds the insured.
GENERA
L Section 51 of the Insurance Code prescribes the information
MEETIN that must be stated in the policy, namely: the parties in the
G insurance contract, amount insured, premium, property or life
insured, risks insured against, and period of insurance.
However, there is nothing in the law that prohibits the parties Notwithstanding any other term or condition of this insurance,
from agreeing to other terms and conditions that would govern the Directors may in their discretion cancel this special cover
their relationship, in which case the general rules of the Civil giving 7 days' notice to the Members (such cancellation
Code regulating contracts will apply.142 becoming effective on the expiry of 7 days from midnight of the
day on which notice of cancellation is issued by the Club and
The Certificate of Entry and Acceptance plainly provides that the Directors may at any time after the issue of notice of such
the Class 1 protection and indemnity coverage would be to the cancellation resolve to reinstate special cover pursuant to the
extent specified and in accordance with the Act, the By-Laws, proviso to the terms of the cover issued pursuant to Rule 21 on
and the Rules of the Club in force at the time of the coverage. such terms and conditions and subject to such limit as the
The "Notes" in the bottom portion of the Certificate states that Directors in their discretion may determine.
these Rules "are printed annually in book form" and
disseminated to all members. M/V Princess of the World was When either a Demise, Time, Voyage, Space or Slot Charterer
insured from February 20, 2005 to February 20, 2006. Hence, and/or the Owner of the Entered Ship are separately insured for
the 2005/2006 Club Rules apply. losses, liabilities, or the costs and expenses incidental thereto
covered under Rule 21 of the Club and/or the equivalent Rule of
Moreover, attached to the Certificate of Entry and Acceptance is any other Association which participates in the Pooling
a War Risk Extension clause and Bio-Chem clause which refer Agreement and General Excess Loss Reinsurance Contract, the
to Rule 21 of the 2005/2006 Club Rules relating to war risk aggregate of claims in respect of such losses, liabilities, or the
insurance. costs and expenses incidental thereto covered under Rule 21 of
the Club and/or the equivalent Rule of such other
WAR RISK EXTENSION Association(s), shall be limited to the amount set out in the
Certificate of Entry in respect of any one ship, any one incident
or occurrence.143
Cover excluded under Rule 21 is hereby reinstated subject to
the terms set out in this Certificate of Entry and any
Endorsement thereto, and to the following conditions.
Sulpicio's acceptance of the Certificate of Entry and Acceptance
....
manifests its acquiescence to all its provisions. There is no
showing in the records or in Sulpicio's contentions that it
At any time or times before, or at the commencement of, or
objected to any of the terms in this Certificate. Its acceptance,
during the currency of any Policy Year of the Club, the Directors
likewise, operated as an acceptance of the entire provisions of
may in their discretion determine that any ports, places,
the Club Rules.
countries, zones or areas (whether of land or sea) be excluded
from the insurance provided by this [Protection and Indemnity]
When a contract is embodied in two (2) or more writings, the
war risks cover. Save as otherwise provided by the Directors,
writings of the parties should be read and interpreted together
this [Protection and Indemnity] war risks cover shall cease in
in such a way as to render their intention effective.144
respect of such ports, places, countries, zones or areas at
midnight on the seventh day following the issue to the Members
With the exception of the War Risk Extension clause, the Bio-
of notice of such detem1ination in accordance with the terms of
chem clause, and a succinct statement of the limits of liability,
the cover provided pursuant to Rule 21 of the Club's Rules
warranties, exclusion, and deductibles, the Certificate of Entry
....
and Acceptance does not contain the details of the insurance
coverage. A person would have to refer to the Club Rules to
have a complete understanding of the contract between the bound by the Act and By(e)-Laws of the Club and
parties. by these Rules.

The Club Rules contain the terms and conditions of the ....
relationship between the Steamship and its members including
the scope, nature, and extent of insurance coverage of its iv. All contracts of insurance with the Club shall be
members' vessels. The 2005/2006 Club Rules145 of Class 1, deemed to be subject to and incorporate all the
which cover protection and indemnity risks provide, insofar as provisions of these Rules except to the extent
relevant: otherwise expressly agreed in writing with the
Managers.
3 Scope of Cover
v. Each Member or other person whose application
i. The terms upon which a Member is entered in the for insurance or reinsurance is accepted shall be
Club are set out in the Rules and any Certificate deemed to have agreed both for itself and its
of Entry for that Member. successors and each of them that both it and
they and each and all of them will be subject to
ii. The risks against which a Member is insured by and bound by and will perform their obligations
entry in the Club are set out in Rule 25 and are under the Rules, Act and By(e)-Laws of the Club
always subject to the conditions, exceptions, and any contract of insurance with the Club.
limitations and other terms set out in the
remainder of these Rules and any Certificate of ....
Entry for that Member.
45 Amendments to Rules
....
The Rules of this Class may be altered or added to by Ordinary
6 Entry
Resolution passed at a separate meeting of the Members of this
....
Class provided that no such alterations shall be effective unless
and until the same shall be sanctioned by the Directors. 146
iv. The provisions of this Rule apply throughout the
period of entry of the Ship in the Club . . .

.... The 2005/2006 Club Rules also provide the nature of


Steamship's Protection and Indemnity cover and the terms on
8 Members which it is provided. In particular, Rule 25(i) to (xxi) identify a
member's liabilities, costs, and expenses covered by the
insurance, Rules 18 to 24 set out the general exclusions and
i. Every Owner who enters any ship in the Club
limitations, Rule 26 provides the requirements for classification
shall (if not already a Member) be and become a
and condition surveys, and Rule 28 addresses general terms
Member of the Club as from the date of the
and conditions for recovery of claims. The 2005/2006 Club
commencement of such entry. Each Member is
Rules also contain provisions on double insurance (Rule 23),
claims handling (Rules 30 and 31), cessation of membership
(Rule 35), cessation of insurance of individual vessels (Rule 36) thereon, or shall have made default for three
deduction and set-off (Rule 40), and assignment and months in so doing; and, if such decision be not
subrogation (Rules 41 and 42). accepted by the Member or such default be
made, unless and until the difference or dispute
The arbitration clause is found in Rule 47 of the 2005/2006 shall have been referred to arbitration in the
Club Rules: manner provided in this Rule, and the Award
shall have been published; and then only for such
47 dispute resolution, Adjudication sum as the Award may direct to be paid by the
Club. And the sole obligation of the Club to the
i. in the event of any difference or dispute Member under these Rules or otherwise
whatsoever, between or affecting a Member and howsoever in respect of any disputed claim made
the Club and concerning the insurance afforded by the Member shall be to pay such sum as may
by the Club under these rules or any amounts be directed by such an Award.
due from the Club to the Member or the Member
to the Club, such difference or dispute shall in the iv. In any event no request for adjudication by the
first instance be referred to adjudication by the Member shall be made to the Directors in respect
Directors. That adjudication shall be on the basis of any difference or dispute between, or matter
of documents and written submissions alone. affecting, the Member and the Club more than
Notwithstanding the terms of this Rule 47i, the two years from the date when that dispute,
Managers shall be entitled to refer any difference difference or matter arose unless, prior to the
or dispute to arbitration in accordance with sub- expiry of this limitation period, the Managers
paragraph ii below without prior adjudication by have agreed in writing to extend the same.
the Directors.
v. Nothing in this Rule 47 including paragraph i, or
ii. If the Member does not accept the decision of the in any other Rule or otherwise shall preclude the
Directors, or if the Managers, in their absolute Club from taking any legal action of whatsoever
discretion, so decide, the difference or dispute nature in any jurisdiction at its absolute
shall be referred to the arbitration of three discretion in order to pursue or enforce any of its
arbitrators, one to be appointed by each of the rights whatsoever and howsoever arising
parties and the third by the two arbitrators so including but not limited to: -
chosen, in London. The submission to arbitration
and all the proceedings therein shall be subject to a. Recovering sums it considers to be due
the provisions of the English Arbitration Act, 1996 from the Member to the Club;
and the schedules thereto or any statutory b. Obtaining security for such sums; and/or
modifications or re-enactment thereof. c. Enforcement of its right of lien whether
arising by law or under these rules.
iii. No Member shall be entitled to maintain any
action, suit or other legal proceedings against the
Club upon any such difference or dispute unless
and until the same has been submitted to the vi. These rules and any contract of insurance
Directors and they shall have given their decision between the Club and the Member shall be
governed by and construed in accordance with subscribed by the party sought to be charged, or by his lawful
English law.147 (Emphasis in the original) agent."151 In international commercial arbitration,152 it is
likewise required that the arbitration agreement must be in
writing.

Under Rule 47, any dispute concerning the insurance afforded An arbitration agreement is in writing if it is contained (1) in a
by Steamship must first be brought by a claiming member to document signed by the parties, (2) in an exchange of letters,
the Directors for adjudication. If this member disagrees with telex, telegrams or other means of telecommunication which
the decision of the Director, the dispute must be referred to provide a record of the agreement, or (3) in an exchange of
arbitration in London. Despite the member's disagreement, the statements of claim and defense in which the existence of an
Managers of Steamship may refer the dispute to arbitration agreement is alleged by a party and not denied by another. The
without adjudication of the Directors. This procedure must be reference in a contract to a document containing an arbitration
complied with before the member can pursue legal proceedings clause constitutes an arbitration agreement provided that the
against Steamship. contract is in writing and the reference is such as to make that
clause part of the contract.153
There is no ambiguity in the terms and clauses of the Certificate
of Entry Acceptance. Contrary to the ruling of the Court of In BF Corp. v. Court of Appeals,154 one (1) of the parties denied
Appeals, the Certificate clearly incorporates the entire Club the existence of the arbitration cause on the ground that it did
Rules—not only those provisions relating to cancellation and not sign the Conditions of Contract that contained the clause.
alteration of the policy.148 This Court held that the arbitration clause was nonetheless
binding because the Conditions of Contract were expressly
"[W]hen the text of a contract is explicit and leaves no doubt as made an integral part of the principal contract between the
to its intention, the court may not read into it any other parties. The formal requirements of the law were deemed
intention that would contradict its plain import."149 complied with because "the subscription of the principal
agreement effectively covered the other documents
The incorporation of the Club Rules in the insurance policy is incorporated by reference [to them]."155 In, arriving at this
without any qualification. This includes the arbitration clause ruling, this Court explained:
even if not particularly stipulated. A basic rule in construction is
that the entire contract, and each and all of its parts, must be A contract need not be contained in a single writing. It may be
read together and given effect, with all its clauses and collected from several different writings which do not conflict
provisions harmomonized with one another.150 with each other and which, when connected, show the parties,
subject matter, terms and consideration, as in contracts
II.C entered into by correspondence. A contract may be
encompassed in several instruments even though every
instrument is not signed by the parties, since it is
The Court of Appeals ruled that the arbitration agreement in the sufficient if the unsigned instruments are clearly
2005/2006 Club Rules is not valid because it was not signed by identified or referred to and made part of the signed
the parties. instrument or instruments. Similarly, a written agreement of
which there are two copies, one signed by each of the parties,
In domestic arbitration, the formal requirements of an is binding on both to the same extent as though there had been
arbitration agreement are that it must "be in writing and
only one copy of the agreement and both had signed In that case, plaintiffs sought to recover the amount of 16
it.156 (Emphasis supplied) checks that were honored by Associated Bank despite the
apparent alterations in the name of the payee. Associated Bank
filed a Third-Party Complaint against Philippine Commercial
International Bank, Far East Bank & Trust Company, Security
Thus, an arbitration agreement that was not embodied in the
Bank and Trust Company, and Citytrust Banking Corporation for
main agreement but set forth in another document is binding
upon the parties, where the document was incorporated by reimbursement, contribution, and indemnity. This Complaint
was based on their being the collecting banks and by virtue of
reference to the main agreement. The arbitration agreement
their bank guarantee for all checks sent for clearing to the
contained in the Club Rules, which in turn was referred to in the
Philippine Clearing House Corporation (PCHC). The trial court
Certificate of Entry and Acceptance, is binding upon Sulpicio
even though there was no specific stipulation on dispute dismissed the Third-Party Complaint for lack of jurisdiction,
citing Section 36 of the Clearing House Rules and Regulations of
resolution in this Certificate.
the PCHC, which provides for arbitration. This Court, in
Furthermore, as stated earlier, Sulpicio became a member of affirming the dismissal, held:
Steamship by the very act of making a contract of insurance
Under the rules and regulations of the Philippine Clearing House
with it. The Certificate of Entry and Acceptance issued by
Corporation (PCHC), the mere act of participation of the parties
Steamship states that "[its] name has been entered in the
concerned in its operations in effect amounts to a manifestation
Register of Members of the Club as a Member." 157 Sulpicio
of agreement by the parties to abide by its rules and
admits its membership and the entry of its vessels to
regulations. As a consequence of such participation, a party
Steamship.
cannot invoke the jurisdiction of the courts over disputes and
controversies which fall under the PCHC Rules and Regulations
Rule 8(v) of the 2005/2006 Club Rules provides that:
without first going through the arbitration processes laid out by
the body. Since claims relating to the regularity of checks
Each Member or other person whose application for insurance
cleared by banking institutions are among those claims which
or reinsurance is accepted shall be deemed to have agreed both
for itself and its successors and each of them that both it and should first be submitted for resolution by the PCHC's
Arbitration Committee, petitioner Associated Bank, having
they and each and all of them will be subject to and bound by
voluntarily bound itself to abide by such rules and regulations,
and will perform their obligations under the Rules, Act and
is estopped from seeking relief from the Regional Trial Court on
By(e)-Laws of the Club and any contract of insurance with the
Club. the coattails of a private claim and in the guise of a third party
complaint without first having obtained a decision adverse to its
claim from the said body. lt cannot bypass the arbitration
Sulpicio's agreement to abide by Steamship's Club Rules, process on the basis of its averment that its third party
including its arbitration clause, can be reasonably inferred from complaint is inextricably linked to the original complaint in the
its submission of an application for entry of its vessels to Regional Trial Court.
Steamship "subject to the Rules, receipt of which we
acknowledge."158 ....

The ruling of this Court in Associated Bank v. Court of Section 36.6 is even more emphatic:
Appeals159 is applicable by analogy to this case.
36.6 The fact that a bank participates in the clearing operations
of PCHC shall be deemed its written and subscribed consent to sent a copy" of the Rulebook as stated in the affidavits of its
the binding effect of this arbitration agreement as if it had done Executive Vice President, Atty. Eusebio S. Go and its Safety and
so in accordance with Section 4 of the Republic Act No. 876 Quality Assurance Manager, Engr. Ernelson P. Morales.161 It
otherwise known as the Arbitration Law. also quoted a portion of the Affidavit of its Executive Vice
President and Chief Executive Officer, Carlos S. Go, who
declared that "[Sulpicio] and Steamship have not signed any
Thus, not only do the parties manifest by mere participation
their consent to these rules, but such participation is deemed arbitration agreement" and "[n]o such agreement exists."162
(their) written and subscribed consent to the binding effect of
Sulpicio cannot feign ignorance of the arbitration clause since it
arbitration agreements under the PCHC rules. Moreover, a
was already charged with notice of the Club Rules due to an
participant subject to the Clearing House Rules and Regulations
of the PCHC may go on appeal to any of the Regional Trial appropriate reference to it in the Certificate of Entry and
Acceptance. Assuming its contentions were true that it was not
Courts in the National Capital Region where the head office of
furnished a copy of the 2005/2006 Club Rules, by the exercise
any of the parties is located only after a decision or award has
been rendered by the arbitration committee or arbitrator on of ordinary diligence, it could have easily obtained a copy of
questions of law.160 (Emphasis supplied, citation omitted) them from Pioneer Insurance or Seaboard-Eastern.

In any case, Sulpicio's bare denials cannot succeed in light of


the preponderance of evidence submitted by Steamship.
This Court held that mere participation by the banks in the
clearing operations of the PCHC manifest their consent to the The Affidavit163 dated August 29, 2007 of Jonathan Andrews,
PCHC Rules, including the binding effect of the arbitration Director and Head of Underwriting of the Eastern Syndicate of
agreements under these Rules. the Managers of Steamship and in charge of Steamship's Far
East membership, including the Philippines, stated:
In this case, by its act of entering its fleet of vessels to
Steamship and accepting without objection the Certificate of 4. The contract of insurance between the Club and a
Entry and Acceptance covering its vessels, Sulpicio manifests its Member is contained in, and evidenced by:
consent to be bound by the Club Rules. The contract between
Sulpicio and Steamship gives rise to reciprocal rights and
obligations. Steamship undertakes to provide protection and a) The Rules of the Club for whichever Class or Classes the
indemnity cover to Sulpicio's fleet. On the other hand, Sulpicio, vessel is entered, for the time being in force; and
as a member, agrees to observe Steamship's rules and
b) A Certificate of Entry.
regulations, including its provisions on arbitration.

III.A 5.

....
The Court of Appeals' finding that there was no proof that
Sulpicio was given a copy of the 2005/2006 Club Rules is
5. The Club's policy year runs from noon on
contradicted by the evidence on record.
20th February of each year until noon on
20th February of the year following . . . The Rule
In its Comment, Sulpicio contends that it "was never given or
book is published on an annual basis prior to the
commencement of the Policy year to which it of that correspondence are produced and shown
applies. Although the Rules can be amended to me, marked "JHDA 5". As the Court will note
pursuant to Rule 45, the dispute resolution from that correspondence, it contains numerous
provisions of the Rules have provided for and frequent references to various of the Club's
arbitration in London since well before the Rules, e.g.:
Plaintiff's entry in the Club.
 Rule 22, dealing with double insurance
....  Rule 25 xix, dealing with towage
 Rule 23 i, dealing with classification
10. In addition, it is quite clear that throughout their  Rule 23 v b and c, dealing with defect
lengthy membership of the Club, the Plaintiffs warranties
were aware of, and relied upon, the terms of the  Rule 23 iv, dealing with safety audits.
Club's Rules. Produced and shown to me, marked
"JHDA 4", is a copy of a letter164 from the 12. The fact that Plaintiffs possessed and were fully
Plaintiffs, dated 4th June, 1993, seeking a refund conversant with the Club's Rules is most clearly
of premium for the "SURIGAO PRINCESS" on the demonstrated by the correspondence provided
grounds that the vessel was laid up. That letter's and shown to me, marked "JHDA 6". After the
enclosures consist of: grounding of the "PRINCESS OF THE PACIFIC",
due to the concerns arising out of this casualty,
the Club initially reserved cover pending further
(a) The Club's printed form for returns of premium when a
investigation and required an independent audit
vessel is laid-up . . . signed by Mr. Carlos S. Go on
of the Plaintiffs Safety Management System.
behalf of the Plaintiffs;
When this decision was conveyed to the Plaintiffs
(b) A photocopy of the relevant provision in the Club's Rules via their brokers, Seaboard-Eastern, they replied:
dealing with laid-up returns, Rule 29; and
As expected, Carlos Go was so upset and expressed
(c) A Certificate from the Philippines Port Authority . . . disappointment when the undersigned spoke to him about the
report of Noble Denton and the club's decision to suspend any
action on the claim especially so since owners believe the
11.
findings of the surveyors to the club are inaccurate and after
relating such findings to the club rules owners find no basis for
The fact that Sulpicio's application for a laid up
club's decision to suspend action on the claim.165
return attached a photocopy of the Club's Rule
book demonstrates both that this was physically
in their possession and that they were familiar
with its contents. Roderick Gil Narvacan, Vice-President of the Hull Unit of Pioneer
Insurance which handled Sulpicio's account, also narrated in his
11. Throughout the lengthy period of this entry, as Affidavit[166 dated September 4, 2007:
might be anticipated, there was a considerable
volume of correspondence between the Plaintiffs 7. I know for a fact that Sulpicio received a copy of the Club's
and the Club via the former's brokers. Examples Rule Book and had full knowledge of the Club's Rules during the
length of time that it was a member of the Club.  Letter-request171 for refund of lay-up premiums
for the vessel M/V Manila Princess dated 10 June
8. [I]n all Entry Forms signed and submitted by Sulpicio to the 1998 as Annex '"6";
Club throughout its years of membership in the Club, Sulpicio  Letter request172 for refund of lay-up premiums
always acknowledged that it received a copy of Club's Rule for the vessel M/V Filipina Princess dated 21 June
Book. A sample of Sulpicio's duly signed Entry Form submitted 1999 as Annex "7";
to the Club on 6 February 1997 is hereto attached as Annex  Letter-request173 for refund of lay-up premiums
"1." for the vessel M/V Manila Princess dated 17 May
2001 as Annex "8"; and
9. The Company, through my department, also makes it a point  Letter-request174 for refund of lay-up premiums
to remind all the Club's Members including Sulpicio to for the vessel M/V Nasipit Princess dated 16
familiarize themselves with the Club's Rulebook as the rules August 2002 as Annex "9";
therein provided are applied to all Club related matters
including claims procedures. A copy of Ms. May Valles'
email167 to Sulpicio dated 27 August 2002 is hereto attached as In each of the above letters, Sulpicio declared to both the
Annex "2" and her letter168 to Sulpicio dated 17 October 2002 is Company and the Club that "(w)e shall therefore be glad to
hereto attached as Annex "3." Ms. Valles was a former member receive a credit note for the return of premium under the Rules
of the Company's Hull Department and in both written of the Association."175 (Emphasis in the original)
communications, she reminded Sulpicio through its Executive
Vice-President and CFO Mr. Carlos S. Go of certain Club Rules
such as the prescriptive period to claim for lay-up premium
Finally, Elmer Felipe, Manager of Marine Department of
refund.
Seaboard-Eastern in charge of Sulpicio's account, also
narrated:
10. In reply to the 27 August 2002 email, Mr. Carlos S. Go, by
a 28 August 2002 email169 to Ms. Valles, explained his
11. As insurers for the Hull & Machinery of Sulpicio's Fleet, the
understanding of the provision on the prescriptive period to
Company, through my department, assisted Sulpicio in regard
claim for lay-up premium refund under the Club's Rules,
to its [Protection and Indemnity] cover by sending copy of the
thereby clearly showing that Sulpicio was aware of the Club's
Club's Rulebook while it was an active Member of the Club.
Rules. A copy of the 28 August 2002 email of Mr. Go is hereto
attached as Annex "4."
12. By way of example, in the year 2002, the Company sent
five (5) copies of the Club's Rulebook to Mr. Carlos S. Go,
11. To further prove Sulpicio's knowledge of Club's Rules, I
Executive Vice-President and CEO of Sulpicio as evidenced by a
hereto attach the following copies of letters from Sulpicio
transmittal letter dated 11 April 2002 duly signed by the
addressed to the Company with attached letter by Sulpicio to
Company's First Vice-President Joli Co-Wu. A copy of said
the Club:
transmittal letter176 dated 11 April 2002 is hereto attached as
Annex "1."
 Letter-request170 for refund of lay-up premiums
for the vessel M/V Surigao Princess dated 4 June 13. The other transmittal letters proving distribution of the
1993 as Annex "5"; Club's Rulebook to Sulpicio in its other years of membership
with the Club were among those discarded by the Company
when it moved . . . to a smaller office . . . with what is provided for."181 The agreement to submit all
disputes to arbitration is a long standing provision in the Club
14. [Sulpicio is presumed to] know the Club's Rules as it was Rules. It was incumbent upon Sulpicio to familiarize itself with
provided with copies of the Rulebook on an annual basis. the Club Rules, under the presumption that a person takes due
care of its concerns. Being a member of Steamship for 20
15. In fact, in a 8 May 2004 letter addressed to the Company, years,182 it has been bound by its Rules and has been expected
Sulpicio claimed for refund of lay-up premiums from the Club in to abide by them in good faith.
connection with the vessel M/V Princess of the World and in
Sulpicio's letter to the Club attached to the said 8 May 2004 In Development Bank of the Philippines v. National
letter, Sulpicio declared that "(w)e shall therefore be glad to Merchandising Corp.,183 the parties, who were acute
receive a credit note for the return of premium under the Rules businessmen of experience, were presumed to have assented
of the Association." This was followed by December 2004 letter to the assailed documents with full knowledge:
for refund of lay-up returns for the vessel M/V Princess of the
World where Sulpicio also invoked the Club Rules. A copy of the The principal stockholders and officers of NAMERCO, particularly
8 May 2004 letter177 with attachment is hereto attached as the Sycips who co-signed the promissory notes in question,
Annex "2" and a copy of the 8 December 2004 letter178 is were, as the lower court found, businessmen of experience and
hereto attached as Annex "3." intelligence . . . We might say — paraphrasing Tin Tua Sia vs.
.... Yu Biao Sontua, 56 Phil. 707 — that they being of age and
businessmen of experience, it must be presumed that they had
18. More importantly, after the Club denied cover for the vessel acted with due care and to have signed the documents in
M/V Princess of the World and prior to the date when the question with full knowledge of their import and the obligations
termination of Sulpicio's entry in the Club took effect, our EVP, they were assuming thereby; that this presumption of law may
Mr. Jose G. Banzon, Jr. sent an emai1179 dated 30 November not be overcome by the mere testimony of the obligor or
2005 to Mr. Carlos Go reminding Sulpicio of the remedy of obligors; that, to permit a party, when, sued upon a contract,
voluntary arbitration under Rule 47 of the Club's Rulebook and to admit that he signed it but to deny that it expresses the
attaching a copy of Rule 47. Copies of these documents are agreement he had made, or to allow him to admit that he
attached as Annex "4."180 signed it solely on the verbal assurance given by one party,
however high his station may be, that he would not be held
liable thereon, would destroy the value of all contracts. Indeed,
These foregoing affidavits and the attached supporting
it would be disastrous to give more weight and reliability to the
documents consistently declared that Sulpicio was given copies
self-serving testimony of a party bound by the contract than to
of the Rulebook on an annual basis and had even invoked its
the contents thereof. Verba volant, scripta manent.184
provisions in making a claim from Steamship. Sulpicio's
previous letters to Steamship referring to provisions of the Club
Rules show its knowledge. Sulpicio was also reminded of the
arbitration clause during the negotiations preceding the Sulpicio is estopped from denying knowledge of the Rulebook
institution of the present case. by its own acts and representations, as evidenced by its various
letters to Steamship, showing its familiarity with the Rulebook
"[A] party is not relieved of the duty to exercise the ordinary and its provisions.
care and prudence that would be exacted in relation to other
contracts. The conformity of the insured to the terms of the "In estoppel, a person, who by his [or her] deed or conduct has
policy is implied from [its] failure to express any disagreement induced another to act in a particular manner, is barred from
adopting an inconsistent position, attitude or course of conduct b. Not all of the parties to the civil action are bound
that thereby causes loss or injury to another." 185 It further bars by the arbitration agreement and referral to
a party from denying or disproving a fact, which has become arbitration would result in multiplicity of suits;
settled by its acts.186
c. The issues raised in the civil action could be
Hence, this Court finds a preponderance of evidence showing speedily and efficiently resolved in its entirety by
that Sulpicio was given a copy and had knowledge of the the court rather than in arbitration;
2005/2006 Club Rules. Moreover, the 2005/2006 Club Rules'
provision on arbitration is valid and binding upon Sulpicio. d. Referral to arbitration does not appear to be the
most prudent action; or
III.B
e. The stay of the action would prejudice the rights
The Regional Trial Court should suspend proceedings to give of the parties to the civil action who are not
way to arbitration. Even if there are other defendants who are bound by the arbitration agreement.
not parties to the arbitration agreement, arbitration is still
proper.

Republic Act No. 9285 was approved on April 2, 2004 and was The present rule on multiple parties manifests due regard to
the controlling law at the time the original and amended the policy of the law in favor of arbitration. In light of the
complaints were filed. express mandate of Republic Act No. 9285 and the subsequent
2009 Special ADR Rules, this Court's ruling in European
Section 25 of Republic Act No. 9285 is explicit that: Resources and Technologies, Inc. v. Ingenieuburo Birkhann +
Nolte, Ingeniurgesellschaft Gmbh188 is deemed abrogated.
[W]here action is commenced by or against multiple parties,
one or more of whom are parties to an arbitration agreement, Notably, the Regional Trial Court did not rule on whether or not
the court shall refer to arbitration those parties who are bound a valid and existing arbitration .agreement existed between the
by the arbitration agreement although the civil action may parties. It merely stated in its Order. citing European
continue as to those who are not bound by such arbitration Resources, that:
agreement.
["]Even if there is an arbitration clause, there are instances
when referral to arbitration does not appear to be the most
Rule 4.7 of the Special Rules on Alternative Dispute prudent action. The object of arbitration is to allow the
Resolution187 (2009 Special ADR Rules) further expresses: expeditious determination of a dispute. Clearly, the issue before
us could not be speedily and efficiently resolved in its entirety if
The court shall not decline to refer some or all of the parties to we allow simultaneous arbitration proceedings and trial, or
arbitration for any of the following reasons: suspension of trial pending arbitration."

Moreover, it is noted that defendants Seaboard-Eastern


a. Not all of the disputes subject of the civil action
Insurance Co. Inc. and Pioneer Insurance and Surety
may be referred to arbitration;
Corporation already filed their respective Answers to the second
amended complaint.189
the Philippines.191

On this basis, the Regional Trial Court denied Steamship's In its Comment/Opposition192 to the Petition for Indirect
Motion to Dismiss and/or to Refer Case to Arbitration and Contempt, Steamship contends that it "exercised its right to
directed it to file an answer. set-off in good faith"193 and that the amount set-off represents
costs of obtaining the Anti-Suit Injunction awarded to it by the
This Court finds that the Regional Trial Court acted in excess of English Commercial Court and are not arbitration costs as
its jurisdiction. contended by Sulpicio.194 It also holds that Sulpicio's prayer for
restitution of the offset amount was improper in a petition for
Where a motion is filed in court for the referral of a dispute to indirect contempt.195
arbitration, Section 24 of Republic Act No. 9285 ordains that
the dispute shall be referred "to arbitration unless it finds that Steamship emphasizes that even before the denial of its Motion
the arbitration agreement is null and void, inoperative or to Dismiss in Civil Case No. 07-577 on July 11, 2008, it already
incapable of being performed." commenced arbitration in London196 on July 31, 2007.197 It had
also "obtained a permanent Anti-Suit Injunction [with interim
Thus, the Regional Trial Court went beyond its authority of award for costs]198 from the English Commercial Court on
determining only the issue of whether or not there was a valid 4th April 2008[.]"199 The April 4, 2008 Order enjoined Sulpicio
arbitration agreement between the parties when it denied from proceeding with Civil Case No. 07-577 and to refer the
Steamship's Motion to Dismiss and/or to Refer Case to dispute to arbitration in London.200
Arbitration solely on the ground that it would not be the most
prudent action under the circumstances of the case. The Steamship further avers that "Sulpicio was served a copy of an
Regional Trial Court went against the express mandate of Order to file Claims Submissions in the London arbitration and a
Republic Act No. 9285. Consequently, the Court of Appeals copy of the Anti-Suit Injunction but it refused to participate in
erred in finding no grave abuse of discretion on the part of the the London Arbitration."201 It also did not pay the costs of the
trial court in denying referral to arbitration. Anti-Suit Injunction. Sulpicio refused "service of all orders,
notices, pleadings and documents related to the London
IV arbitration and the Commercial Court proceedings."202

Steamship adds that in 2012, Sulpicio filed a claim for


In G.R. No. 208603, Sulpicio contends that Steamship's acts reimbursement of US$96,958.47 representing passenger
were contumacious because they were intended to defeat Civil liabilities arising from the capsizing of one (1) of Sulpicio's fleet
Case No. 07-577 and oust the Regional Trial Court of its in 1998.203 Pursuant to Rule 32 of the Club Rules for the 1998
jurisdiction, without the approval of this Court. policy, which gave Steamship "the right to make deduction
'from any claims . . . due to a Member' of 'any liabilities of such
Sulpicio further contends that there was no valid off-setting of Member to the Club,'"204 Steamship set-off the costs awarded
the amount of US$69,570.99 from the refund payable to it in by the English Commercial Court from the amount reimbursed
the Unabia case because the issue on the propriety of the to Sulpicio. Sulpicio's brokers and lawyers were informed of the
referral to arbitration had yet to be resolved by this Court. 190 It set-off through an email dated December 3, 2012.205
adds that the "arbitration – anti-suit injuction" cost was not a
debt of Sulpicio but a unilateral charge arising from an Steamship contends that there was no legal impediment when
arbitration that it had not participated in, or was enforceable in it initiated arbitration proceedings in London.206 The action was
taken in good faith to preserve its rights while defending its and for a preservative, and not a vindictive, purpose. "Only in
position that Sulpicio's filing of Civil Case No. 07-577 cases of clear and contumacious refusal to obey should the
constituted a breach of the Club Rules.207 On the other hand, power be exercised."212
Sulpicio's acts were far from desirable for it did not only fail to
participate in the London arbitration proceedings but also In Lorenzo Shipping Corporation v. Distribution Management
evaded service of all notices so that it could feign ignorance of Association of the Philippines,213 this Court held that:
the existence of arbitration proceedings."208

This Court finds Sulpicio's arguments to be untenable. There is no question that in contempt the intent goes to the
gravamen of the offense. Thus, the good faith, or lack of it, of
Steamship's commencement of arbitration even before the the alleged contemnor should be considered. Where the act
Regional Trial Court had ruled on its motion to dismiss and complained of is ambiguous or does not clearly show on its face
suspend proceedings does not constitute an "improper conduct" that it is contempt, and is one which, if the party is acting in
that "impede[s], obstruct[s] or degrade[s] the administration of good faith, is within his rights, the presence or absence of a
justice."209 contumacious intent is, in some instances, held to be
determinative of its character. A person should not be
In Heirs of Trinidad de Leon vda. de Roxas v. Court of condemned for contempt where he contends for what he
Appeals,210 this Court explained the concept of contempt of believes to be right and in good faith institutes proceedings for
court: the purpose, however erroneous may be his conclusion as to
his rights. To constitute contempt, the act must be done
Contempt of court is a defiance of the authority, justice or willfully and for an illegitimate or improper
dignity of the court; such conduct as tends to bring the purpose.214 (Citations omitted)
authority and administration of the law into disrespect or to
interfere with or prejudice parties litigant or their witnesses
during litigation . . .
In Lim Lua v. Lua,215 the father's deferral in giving monthly
support pendente lite granted by the trial court was held not
Contempt of court is defined as a disobedience to the Court by
contumacious, considering that "he had not been remiss in
acting in opposition to its authority, justice and dignity. It
actually providing for the needs of his children." It was also
signifies not only a willful disregard or disobedience of the
taken into account that he "believed in good faith that the trial
court's orders, but such conduct as tends to bring the authority and appellate courts, upon equitable grounds, would allow him
of the court and the administration of law into disrepute or in
to offset the substantial amounts he had spent or paid directly
some manner to impede the due administration of justice . . .
to his children." This Court explained:
This Court has thus repeatedly declared that the power to Contempt of court is defined as a disobedience to the court by
punish for contempt is inherent in all courts and is essential to acting in opposition to its authority, justice, and dignity. It
the preservation of order in judicial proceedings and to the signifies not only a willful disregard or disobedience of the
enforcement of judgments, orders, and mandates of the court, court's order, but such conduct which tends to bring the
and consequently, to the due administration of justice . . .211 authority of the court and the administration of law into
disrepute or, in some manner, to impede the due
administration of justice. To constitute contempt, the act must
The court's contempt power should be exercised with restraint be done willfully and for an illegitimate or improper purpose.
The good faith, or lack of it, of the alleged contemnor should be to determine the validity of the set-off and to make a factual
considered.216 determination relating to the propriety of ordering restitution.

WHEREFORE, the Petition for Review in G.R. No.


196072 is GRANTED. The Decision dated November 26, 2010
This Court finds no dear and contumacious conduct on the part
of the Court of Appeals in CA-G.R. SP No. 106103 and the
of Steamship. It does not appear that Steamship was motivated
by bad faith in initiating the arbitration proceedings. Rather, its Order dated July 11, 2008 of the Regional Trial Court, Branch
149, Makati City in Civil Case No. 07-577 are SET ASIDE. The
act of commencing arbitration in London is but a bona fide
dispute between Sulpicio Lines, Inc. and Steamship Mutual
attempt to preserve and enforce its rights under the Club Rules.
Underwriting (Bermuda) Limited is referred to arbitration in
There was no legal impediment at the time Steamship initiated London in accordance with Rule 47 of the 2005/2006 Club
Rules.
London arbitration proceedings. Steamship commenced
arbitration on July 31, 2007 even before the Regional Trial
Court denied its Motion to Dismiss and/or Refer Case to The Petition for Indirect Contempt in G.R. No.
208603 is DISMISSED for lack of merit.
Arbitration on July 11, 2008. There was no order from the
Regional Trial Court enjoining Steamship from initiating
SO ORDERED
arbitration proceedings in London. Besides, the 2009 Special
ADR Rules specifically provided that arbitration proceedings
may be commenced or continued and an award may be made,
while the motion for the stay of civil action and for referral to
arbitration is pending resolution by the court. 217

This Court notes that while the arbitration proceeding was


commenced as early as July 31, 2007, it is only six (6) years
later that Sulpicio filed its Petition218 to cite Steamship for
indirect contempt. Sulpicio cannot invoke lack of knowledge of
the London arbitration proceedings due to several reasons.
First, it received and replied219 to the notice of commencement
of arbitration proceedings220 dated July 31, 2007. Second,
Steamship presented evidence showing Sulpicio's refusal to
receive any notices, orders, or communications related to the
arbitration proceedings. Lastly, the pendency of the London
arbitration was made known to the Court of Appeals and this
Court through Steamship's petitions. Sulpicio's belated filing of
its Petition, only after Steamship has deducted from the refund
due it the alleged "arbitration costs," indicates its lack of
sincerity and good faith.

Finally, this Court finds Sulpicio's claim for damages to be


improperly raised. It should be addressed in an ordinary civil
action. Its petition for indirect contempt is not the proper action
shopping, unlike that of verification, is generally not cured by
its submission after the filing of the petition.” Nevertheless,
exceptions exist, as in the case at bar, and it is more prudent to
resolve the case on its merits than dismiss it on purely technical
grounds.

Moot and Academic; Exceptions exist that would not prevent a


court from taking cognizance of cases seemingly moot and
academic.—Indeed, the rule is that courts will not rule on moot
cases. However, the moot and academic principle is “not a
magical formula that can automatically dissuade the courts in
resolving a case.” Exceptions exist that would not prevent a
court from taking cognizance of cases seemingly moot and
academic.
G.R. No. 179732, September 13, 2017
Remedial Law; Civil Procedure; Exhaustion of Administrative
DEPARTMENT OF PUBLIC WORKS AND Remedies; Under the doctrine of exhaustion of administrative
HIGHWAYS, Petitioner, v. CMC/MONARK/PACIFIC/HI-TRI remedies, the concerned administrative agency must be given
JOINT VENTURE, Respondent. the opportunity to decide a matter within its jurisdiction before
an action is brought before the courts, otherwise, the action will
Pleadings and Practice; Certification against Forum Shopping; It be declared premature.—Under the doctrine of exhaustion of
is settled that certification against forum shopping must be administrative reme-dies, the concerned administrative agency
executed by the party or principal and not by counsel.—This must be given the oppor-tunity to decide a matter within its
Court has long enforced the strict procedural requirement of jurisdiction before an action is brought before the courts,
verification and certification against non-forum shopping. It is otherwise, the action will be declared premature. In this case,
settled that certification against forum shopping must be CIAC found and correctly ruled that respon-dent had duly
executed by the party or principal and not by counsel. In complied with the contractual obligation to exhaust
Anderson v. Ho, 688 SCRA 8 (2013), this Court explained that administrative remedies provided for under subclause 67.1 of
it is the party who is in the best position to know whether he or the Conditions of Contract before it brought the case before the
she has filed a case before any courts. It is clear in this case tribunal.
that counsel for petitioner, Atty. Valderama, was not clothed
with authority to sign on petitioner’s behalf. Construction Industry; Construction Industry Arbitration
Com---mission; Jurisdiction; Construction Industry Arbitration
Same; Same; The Supreme Court (SC) ruled before that: “the Commission’s (CIAC’s) specific purpose is the “early and
lack of a certification against forum shopping, unlike that of expeditious settlement of disputes” in the construction industry
verification, is generally not cured by its submission after the as a recognition of the industry’s role in “the furtherance of
filing of the petition.” Nevertheless, exceptions exist, as in the national development goals.”—CIAC was created under
case at bar, and it is more prudent to resolve the case on its Executive Order No. 1008, or the “Construction Industry
merits than dismiss it on purely technical grounds.—This Court Arbitration Law.” It was originally under the administrative
ruled before that: “the lack of a certification against forum supervision of the Philip-pine Domestic Construction Board
which, in turn, was an imple-menting agency of the
Construction Industry Authority of the Philip-pines. The commercial arbitration, voluntary arbitration under Article
Construction Industry Authority of the Philippines is presently a 219(14) of the Labor Code, and construction arbitration,
part of the Department of Trade and Industry as an attached Freuhauf Electronics Philippines Corporation v. Technology
agency. CIAC’s specific purpose is the “early and expedi-tious Electronics Assembly and Management Pacific, 810 SCRA 280
settlement of disputes” in the construction industry as a (2016), ruled that commercial arbitral tribu-nals are purely ad
recog­nition of the industry’s role in “the furtherance of national hoc bodies operating through contractual consent, hence, they
development goals.” are not quasi-judicial agencies. In contrast, voluntary
arbitration under the Labor Code and construction arbitration
Same; Same; Same; As a general rule, findings of fact of derive their authority from statute in recognition of the public
Construction Industry Arbitration Commission (CIAC), a quasi- interest inherent in their respective spheres. Furthermore,
judicial tribunal which has expertise on matters regarding the voluntary arbitra-tion under the Labor Code and construction
construction industry, should be respected and upheld.—As a arbitration exist independently of the will of the contracting
general rule, findings of fact of CIAC, a quasi-judicial tribunal parties: Voluntary Arbitrators resolve labor disputes and
which has expertise on matters regarding the construction grievances arising from the interpretation of Collective
industry, should be respected and upheld. In National Housing Bargaining Agreements. These disputes were specifically
Authority v. First United Constructors Corp., 657 SCRA 175 excluded from the coverage of both the Arbitration Law and the
(2011), this Court held that CIAC’s factual findings, as affirmed ADR Law. Unlike purely commercial relationships, the
by the Court of Appeals, will not be overturned except as to the relationship between capital and labor are heavily impressed
most compelling of reasons: As this finding of fact by the CIAC with public interest. Because of this, Voluntary Arbitrators
was affirmed by the Court of Appeals, and it being apparent authorized to resolve labor disputes have been clothed with
that the CIAC arrived at said finding after a thorough quasi-judicial authority. On the other hand, commercial
consideration of the evidence presented by both parties, the relationships covered by our commercial arbitration laws are
same may no longer be reviewed by this Court. The all too purely private and contractual in nature. Unlike labor
familiar rule is that the Court will not, in a petition for review on relationships, they do not possess the same compelling state
certiorari, entertain matters factual in nature, save for the most interest that would justify state interference into the autonomy
compelling and cogent reasons, like when such factual findings of contracts. Hence, commercial arbitration is a purely private
were drawn from a vacuum or arbitrarily reached, or are system of adjudication facilitated by private citizens instead of
grounded entirely on speculation or conjectures, are conflicting government instrumentalities wielding quasi-judicial powers.
or are premised on the supposed evidence and contradicted by Moreover, judicial or quasi-judicial jurisdiction cannot be
the evidence on record or when the inference made is conferred upon a tribunal by the parties alone. The Labor Code
manifestly mistaken or absurd. This conclusion is made more itself confers subject-matter jurisdiction to Voluntary
compelling by the fact that the CIAC is a quasi-judicial body Arbitrators. Notably, the other arbitration body listed in Rule 43
whose jurisdiction is confined to construction disputes. Indeed, — the Construction Industry Arbitration Commission (CIAC) —
settled is the rule that findings of fact of administrative is also a government agency attached to the Department of
agencies and quasi-judicial bodies, which have acquired Trade and Industry. Its jurisdiction is likewise conferred by
expertise because their jurisdiction is confined to specific statute. By contrast, the subject matter jurisdiction of
matters, are generally accorded not only respect, but finality commercial arbitrators is stipulated by the parties.
when affirmed by the Court of Appeals.
Remedial Law; Civil Procedure; Factual Findings; Findings of
Arbitration; “Commercial Arbitration” and “Voluntary fact of administrative agencies and quasi-judicial bodies are
Arbit­ration,” Distinguished.—In distinguishing between entitled to great respect and even finality when affirmed by the
appellate court.—To reiterate, findings of fact of administrative Same; Same; Same; The denial in the answer must be definite
agencies and quasi--judicial bodies are entitled to great respect as to what is admitted and what is denied, such that the
and even finality when affirmed by the appellate court. In this adverse party will not have to resort to guesswork over “what is
case, the Court of Appeals found that respondent was entitled admitted, what is denied, and what is covered by denials of
to the time extensions as evaluated by CIAC, the agency tasked knowledge as sufficient to form a belief.”—In Aquintey v.
to resolve issues regarding the construction industry. Both Spouses Tibong, 511 SCRA 414 (2006), this Court held that
tribunal found that respondent was entitled to the extensions using “specifically” in a general denial does not automatically
due to petitioners delayed payments, peace and order situation, convert that general denial to a specific one. The denial in the
and Variation Order No. 2. These findings are clearly supported answer must be definite as to what is admitted and what is
by the facts on record. denied, such that the adverse party will not have to resort to
guesswork over “what is admitted, what is denied, and what is
Executive Agreements; Foreign Loan Agreements; A foreign covered by denials of knowledge as sufficient to form a belief.”
loan agreement with international financial institutions, such as
a multilateral lending agency organized by governments like the Civil Law; Contracts; It is fundamental that a contract is the law
Asian Development our government procurement system.—This between the parties and, absent any showing that its provisions
Court has held that a foreign loan agreement with international are wholly or in part contrary to law, morals, good customs,
financial institu-tions, such as a multilateral lending agency public order, or public policy, it shall be enforced to the letter
organized by govern-ments like the Asian Development Bank, is by them courts.—It is fundamental that a contract is the law
an executive or inter-national agreement contemplated by our between the parties and, absent any showing that its provisions
government procure-ment system. are wholly or in part contrary to law, morals, good customs,
public order, or public policy, it shall be enforced to the letter
Remedial Law; Civil Procedure; Specific Denials; Under Rule 8, by the courts. Respondent was not able to establish the basis of
Section 10 of the Rules of Court, the “defendant must specify its claim that it is entitled to an award of 24% interest.
each material allegation of fact the truth of which he does not Moreover, as found by the Court of Appeals and CIAC, the
admit and, whenever practicable, shall set forth the substance parties had agreed to delete the provision on interest on
of the matters upon which he relies to support his denial.”— delayed payments, since the project was funded by the Asian
Under Rule 8, Section 10 of the Rules of Court, the “defendant Development Bank. There is also no basis to award respondent
must specify each material allegation of fact the truth of which 24% interest as actual damages for the additional expenses it
he does not admit and, whenever practicable, shall set forth the incurred due to petitioner’s delayed payments.
substance of the matters upon which he relies to support his
denial.” There are three (3) modes of specific denial provided Same; Damages; Actual Damages; The issue on the amount of
for under the Rules: 1) by specifying each material allegation of actual or compensatory damages is a question of fact, and
the fact in the complaint, the truth of which the defen-dant except as provided by law or by stipulation, one is entitled to
does not admit, and whenever practicable, setting forth the adequate compensation only for pecuniary loss duly proven.
substance of the matters which he will rely upon to support his Before actual damages may be awarded, it is imperative that
denial; (2) by specifying so much of an averment in the the claimant proves its claims first. The issue on the amount of
complaint as is true and material and denying only the actual or compensatory damages is a question of fact, and
remainder; (3) by stating that the defendant is without except as provided by law or by stipulation, one is entitled to
knowledge or information sufficient to form a belief as to the adequate compensation only for pecuniary loss duly proven. In
truth of a material averment in the complaint, which has the this case, respondent has not sufficiently shown how awarding
effect of a denial. it 24% interest per annum on delayed payments corresponds to
the actual damages it allegedly suffered. Respondent failed to computed by the CIAC, should earn legal interest at the rate of
show a causal relation between the alleged losses and the 12% per annum until June 30, 2013, after which, it shall earn
injury it suffered from petitioner’s actions. legal interest at the rate of 6% per annum until full satisfaction.

Interest Rates; On May 16, 2013, the Monetary Board of the DECISION
Bangko Sentral ng Pilipinas (BSP) issued Resolution No. 796,
which revised the interest rate to be imposed on the loan or LEONEN, J.:
forbearance of any money, goods, or credits.—On May 16,
2013, the Monetary Board of the Bangko Sentral ng Pilipinas As the administrative agency tasked with resolving issues
issued Resolution No. 796, which revised the interest rate to be pertaining to the construction industry, the Construction
imposed on the loan or forbearance of any money, goods, or Industry Arbitration Commission enjoys a wide latitude in
credits. This was implemented in Bangko Sentral ng Pilipinas recognition of its technical expertise and experience. Its factual
Circular No.799 Series of 2013, which reads: The Monetary findings are, thus, accorded respect and even finality,
Board, in its Resolution No. 796 dated 16 May 2013, approved particularly when they are affirmed by an appellate court.
the following revisions governing the rate of interest in the
absence of stipulation in loan contracts, thereby amending This is a Petition for Review on Certiorari 1 assailing the Court of
Section 2 of Circular No. 905, Series of 1982: Section 1. The Appeals Decision2 dated September 20, 2007 in CA-G.R. SP
rate of interest for the loan or forbearance of any money, goods Nos. 88953 and 88911, which affirmed the March 1, 2005
or credits and the rate allowed in judgments, in the absence of Award of the Construction Industry Arbitration Commission
an express contract as to such rate of interest, shall be six (CIAC).
percent (6%) per annum. Section 2. In view of the above,
Subsection X305.1 of the Manual of Regulations for Banks and On April 29, 1999, Republic of the Philippines, through the
Sections 4305Q.1, 43058.3 and 4303P.1 of the Manual of Department of Public Works and Highways (DPWH), and
Regulations for Non-Bank Financial Institutions are hereby CMC/Monark/Pacific/Hi-Tri J.V. (the Joint Venture) executed
amended accordingly. This Circular shall take effect on 1 July "Contract Agreement for the Construction of Contract Package
2013. 6MI-9, Pagadian-Buug Section, Zamboanga del Sur, Sixth Road
Project, Road Improvement Component Loan No. 1473-
Civil Law; Before Nacar v. Gallery Frames, 703 SCRA 439 PHI"3 (Contract) for a total contract amount of
(2013), and Bangko Sentral ng Pilipinas-Monetary Board (BSP- P713,330,885.28.4
MB) Resolution No. 796 dated May 16, 2013, the rate of legal
interest was pegged at twelve percent (12%) per annum from Parts I (General Conditions with forms of tender + agreement)
finality of judgment until its satisfaction, “this interim period and II (Conditions of Particular Application + Guidelines for
being deemed to be by then an equivalent to a forbearance of Preparation of Part II Clauses) of the "Conditions of Contract for
credit.”—Before Nacar v. Gallery Frames, 703 SCRA 439 Works of Civil Engineering Construction of the Federation
(2013), and Bangko Sentral ng Pilipinas-Monetary Board International Des Ingenieurs - Conseils" (Conditions of
Resolution No. 796 dated May 16, 2013, the rate of legal Contract) formed. part of the Contract.5 DPWH hired BCEOM
interest was pegged at 12% per annum from finality of French Engineering Consultants to oversee the project.6
judgment until its satisfaction, “this interim period being
deemed to be by then an equivalent to a forbearance of credit.” On October 23, 2002, or while the project was ongoing, the
With this Court’s pronouncement in Nacar, the rate of interest Joint Venture's truck and equipment were set on fire. On March
imposed should be modified. The monetary awards, as 11, 2003, a bomb exploded at Joint Venture's hatching plant
located at Brgy. West Boyogan, Kumalarang, Zamboanga del Php10,297,090.42 +
Sur. According to reports, the bombing incident was caused by (US$118,094.93@34.90)
members of the Moro Islamic Liberation Front.7

The Joint Venture made several written demands for extension


and payment of the foreign component of the Contract. There Equipment and financial loses 5,080,000.00
were efforts between the parties to settle the unpaid Payment
Certificates amounting to P26,737,029.49. Thus, only the
foreign component of US$358,227.95 was up for negotiations Additional costs in the contract
subject to further reduction of the amount on account of price under Clause 69.4
payments subsequently received by the Joint Venture from 20,311,072.66
DPWH.8

In a letter dated September 18, 2003, BCEOM French


Engineering Consultants recommended that DPWH promptly
pay the outstanding monies due the Joint Venture.9 The letter Adjustment in the contract price
also stated that the actual volume of the Joint Venture's under Presidential Decree No. 1594
accomplishment was "2,732m2 of hardrock and 4,444m3 of 18,626,805.81
rippable rock," making the project 80% complete when it was (9,313,402.91 in pesos and
halted.10 266,859.68 in dollar)

On March 3, 2004, the Joint Venture filed a Complaint11 against


DPWH before CIAC. Joint Venture' claims, which amounted to Effect of the bomping incident 6,267,410.48
P77,206,047.88, were as follows:

CLAIMANT'S CLAIM
TOTAL CLAIMS Php77,206,047.8812

Foreign component of the project Meanwhile, on July 8, 2004, the Joint Venture sent a "Notice of
of Mutual Termination of Contract",13 to DPWH requesting for a
Php12,502,155.46 mutual termination of the contract subject of the arbitration
(US$358,227.95 @Php34.90) case. This is due to its diminished financial capability due to
DPWH's late payments, changes in the project involving
payment terms, peace and order problems, and previous
agreement by the parties.
Interest as of December 3, 4003
On July 16, 2004, then DPWH Acting Secretary Florante
(Computation for the damages & Php14,418,603.47 Soriquez accepted the Joint Venture's request for mutual
losses incurred: termination of the contract.14

After hearing and submission of the parties' respective


memoranda,15 CIAC promulgated an Award16 on March 1, 2005,
directing DPWH to pay the Joint Venture its money claims plus
legal interest. CIAC, however, denied the Joint Venture's claim The Court of Appeals held that CIAC did not commit reversible
for price adjustment due to the delay in the issuance of a error in not awarding the price adjustment sought by the Joint
Notice to Proceed under Presidential Decree No. 1594 or the Venture under Presidential Decree No. 1594 since it was the
"Policies, Guidelines, Rules, and Regulations for Government Asian Development Bank's Guidelines on procurement that was
Infrastructure Contracts."17 The dispositive portion of the Award applicable and not Presidential Decree No. 1594.22
read:
WHEREFORE, premises considered and in view of the resolution The Court of Appeals also held that CIAC did not err in not
of the issues presented, an Award is hereby rendered ordering awarding actual damages in the form of interest at the rate of
the Respondent DPWH to pay the Claimant the following: 24% since there was no provision for such interest payment in
the Contract. However, the Court of Appeals ruled that CIAC
1. Foreign Component of US$358,227.95 plus legal interest of was correct when it awarded legal interest.23
US$18,313.79;
The Court of Appeals sustained the Joint Venture's argument on
2. Equipment and Plant Losses of P5,080,000, plus legal the non-inclusion of a clear finding of its entitlement to time
interest of P464,298.08; extensions in the dispositive portion of the CIAC Award.24 The
Court of Appeals held that CIAC did not clearly dispose of the
3. Additional Costs resulting from the Bombing of matter:
P6,267,410.48 plus legal interest of P320,410.63, and Yet, a close scrutiny of the foregoing disposition shows that it
does not refer to the 133 days as per Variation Order No. 2
4. Additional Costs in the contract price under Clause 69.4 of since CIAC made mention that the project is already terminated
P20,311,072.66 plus legal interest of [P]1,038,368.78. and the entire volume under said Order "will not be consumed".
Whether or not the Claimant then deserves to get the full 133
The claim of Claimant for adjustment under [Presidential calendar days is a matter that has to be clearly resolved. On
Decree No.] 1594 of P18,626,805.81 is hereby denied. this, We hold that this Court is not prepared to engage into a
technical bout that only the expertise of the CIAC can pass
Pursuant to the case of Eastern Shipping Lines vs. Court of upon.25
Appeals, 234 SCRA 78, the foregoing monetary awards shall
On the other hand, the Court of Appeals did not accept DPWH's
earn interest at the rate of 12% per annum from the date the argument that the case was already moot and academic.
Award becomes final and executor until its satisfaction.
According to the Court of Appeals, when the Joint Venture
requested for the mutual termination of the Contract on July 8,
SO ORDERED.18
2004, it did not waive its right to be paid the amounts due to
DPWH and the Joint Venture filed their respective petitions for it.26
review before the Court of Appeals.19
The Court of Appeals, however, raised a concern with regard to
The Court of Appeals in its Decision20 dated September 20, CIAC's order for DPWH to pay its liabilities in US dollars. It held
2007, sustained CIAC's Award with certain modifications and that the parties have agreed that "all payments for works
remanded the case to CIAC for the determination of the carried out after 31 May 2003 and related price escalation
number of days' extension that the Joint Venture is entitled to claims and retention releases in the contract will be in pesos
and "the conversion rate in pesos of the awarded foreign only, therefore no foreign exchange payments." This was never
exchange payments stated."21 contested by the Joint Venture; hence, it may be presumed that
it acquiesced to the request of the DPWH.27 Fourth, whether or not the Joint Venture is entitled to time
extensions due to Variation Order No. 2, peace and order
The dispositive portion of the Court of Appeals Decision read: problems, and delay in payment;
WHEREFORE, premises considered, the assailed Decision is
hereby AFFIRMED with MODIFICATION to include the award Fifth, whether or not the Joint Venture is entitled to a price
to the Claimant of time extensions per: 1) delay in payment at adjustment due to the delay of the issuance of the Notice of the
One Hundred Eight (108) days, and 2) extension Twenty Nine Proceed;
(29) days due to peace and order situation.
Sixth, whether or not the Asian Development Bank Guidelines
Re 1) the award of time extension per Variation Order No. 2-as on Procurement or Presidential Decree 1594 applies with regard
stated earlier elsewhere in the Decision, the CIAC must make a to once adjustments due to the delay of the issuance of the
vivid presentation of the number of calendar days the Claimant Notice to Proceed;
is entitled to, and 2) the conversion rate in pesos of the
awarded foreign exchange payments states, supra, in the Seventh, whether or not the Joint Venture is entitled to its
assailed Decision, these matters are hereby REMANDED to the claim for equipment and financial losses due to peace and order
CIAC for proper disposition. Accordingly, the rest of the situation (additional costs);
challenged Decision STANDS.
Eighth, whether or not the Joint Venture is entitled to actual
SO ORDERED.28 (Emphasis in the original) damages and interest on its claims; and
Petitioner DPWH filed the present Petition for Review29 assailing
the Court of Appeals Decision. In a Resolution30 dated January. Finally, whether or not the Joint Venture should be paid in local
28, 2008, this Court required respondent Joint Venture to file currency or in U.S. dollars.
its Comment.
I
On March 27, 2008, respondent filed its
According to respondent Joint Venture, the Petition suffers from
comment/opposition.31 Petitioner thereafter filed its Reply32 on
a fatal defect in its certification against non-forum shopping.
September 3, 2008.
The verification and certification against non-forum shopping
was signed only by petitioner's counsel, Atty. Mary Jean D.
The issues for resolution in this case are:
Valderama, from the Office of the Solicitor General.33
First, whether or not the case has become moot and academic
This Court has long enforced the strict procedural requirement
due to the parties' mutual termination of the Construction
of verification and certification against non-forum shopping.34 It
Contract;
is settled that certification against forum shopping must be
executed by the party or principal and not by
Second, whether or not the case is premature due to Joint
counsel.35 In Anderson v. Ho,36 this Court explained that it is
Venture's non-compliance with the doctrine of exhaustion of
the party who is in the best position to know whether he or she
administrative remedies;
has filed a case before any courts.37 It is clear in this case that
counsel for petitioner, Atty. Valderama, was not clothed with
Third, whether or not the Joint Venture is entitled to the foreign
authority to sign on petitioner's behalf.
component of the Project in the amount of US$358,227.95;
In Resolution38 dated December 10, 2007, this Court noted not apply in this case "because respondent has incurred
petitioner's Manifestation that after the petition was posted, the negative slippage/delay in carrying out their contractual
verification page signed by DPWH Secretary Hermogenes E. obligations due to reasons attributable to it. Moreover, the
Ebdane was submitted to the Office of the Solicitor General. In parties' mutual termination of the contract rendered the
the same Resolution, this Court granted the Office of the proceedings before the CIAC moot because there was no more
Solicitor General's motion to admit the attached verification and contract to be enforced."45
to substitute and attach it to the petition.
Petitioner's argument is untenable.
This Court ruled before that: "the lack of a certification against
forum shopping, unlike that of verification, is generally not Indeed, the rule is that courts will not rule on moot
cured by its submission after the filing of the cases.46 However, the moot and academic principle is "not a
petition."39 Nevertheless, exceptions40 exist, as in the case at magical formula that can automatically dissuade the courts in
bar, and it is more prudent to resolve the case on its merits resolving a case."47 Exceptions exist that would not prevent a
than dismiss it on purely technical grounds.41 court from taking cognizance of cases seemingly moot and
academic.48
II
In Carpio v. Court of Appeals,49 this Court held that a case
In the assailed Decision, the Court of Appeals held that the could not be deemed moot and academic when there remains
mutual termination of the Contract by the parties did not render an unresolved justiciable controversy. In that case, this Court
the case moot and academic.42 Accordingly, when respondent affirmed the Court of Appeals' assailed resolutions, which
requested for the mutual termination of the Contract, it did not denied petitioner's prayer for dismissal based on the argument
waive its right to be paid the amounts due to it as shown in its that the Sheriff's execution pending appeal of the trial court's
letter: decision rendered the case moot and academic. This Court held
In view of the above considerations, we hereby respectfully that:
request for MUTUAL TERMINATION of our Contract. Our [I]t is obvious that there remains an unresolved justiciable
availment of this remedy does not mean though that we are controversy in the appealed case for accion publiciana. In
waiving our rights (1) to be paid for any and all monetary particular, did respondent-spouses Oria really encroach on the
benefits due and owing to us under the contract such as but not land of petitioner? If they did, does he have the right to recover
limited to payments for works already done, materials delivered possession of the property? Furthermore, without preempting
on site which are intended solely for the construction and the disposition of the case for accion publiciana pending before
completion of the project, price escalation, etc., (2) and without the CA, we note that if respondents built structures on the
prejudice to our outstanding claims and entitlements that are subject land, and if they were builders in good faith, they would
lawfully due to us.43 (Emphasis supplied) be entitled to appropriate rights under the Civil Code. This
Petitioner argues that the Court of Appeals erred in rendering Court merely points out that there are still issues that the CA
the assailed Decision, considering that the case is already moot needs to resolve in the appealed case before it.
and academic. Petitioner insists that "the parties' mutual
termination of their contract prior to the adjudication of this Moreover, there are also the questions of whether respondents
case by the CIAC on March 1, 2005, rendered the proceedings should be made to pay back monthly rentals for the alleged
before CIAC moot and academic."44 encroachment; and whether the reward of attorney's fees,
which are also being questioned, was proper. The
According to petitioner, the principle of unjust enrichment does pronouncements of the CA on these issues would certainly be of
practical value to the parties. After all, should it find that there Works, whether during the execution of the Works or after their
was no encroachment, for instance, respondents would be completion and whether before or after repudiation or other
entitled to substantial relief. In view of all these considerations, termination of the Contract, including any dispute as to any
it cannot be said that the main case has become moot and opinion, instruction, determination, certificate or valuation of
academic.50 (Emphasis supplied.) the Engineer, the matter in dispute shall, in the first place, be
referred in writing to the Engineer, with a copy to the other
In this case, issues arising from the mutually terminated
Contract are not moot and academic. As the Court of Appeals party. Such reference shall state that it is made pursuant to
this Clause. No later than the eighty-fourth day after the day on
found, there are actual substantial reliefs that respondent is
which he received such reference the Engineer shall give notice
entitled to. There is a practical use or value to decide on the
of his decision to the Employer and the Contractor. Such
issues raised by the parties despite the mutual termination of
the Contract between them. These issues include the decision shall state that it is made pursuant to this Clause.
determination of amounts payable to respondent by virtue of
Unless the Contract has already been repudiated or terminated,
the time extensions, respondent's entitlement to price
adjustments due to the delay of the issuance of the Notice to the Contractor shall, in every case, continue to proceed with
the Works with all due diligence and the Contractor and the
Proceed, additional costs, actual damages, and interest on its
Employer shall give effect forthwith to every such decision of
claims. The agreement to mutually terminate the Contract did
the Engineer unless and until the same shall be revised, as
not wipe out petitioner's obligation to pay respondent on works
done before the Contract's termination on October 27, 2004. hereinafter provided, in an amicable settlement or an arbitral
award.
III
If either the Employer or the Contractor be dissatisfied with any
According to petitioner, the filing of the claim before CIAC was decision of the Engineer, or if the Engineer fails to give notice of
premature, since under CIAC rules, there must be an his decision on or before the eighty-fourth day after the day on
exhaustion of administrative remedies first before government which he received the reference, then either the Employer or
contracts are brought to it for arbitration.51 the Contractor may, on or before the seventieth day after the
day on which he received notice of such decision, or on or
Respondent, on the other hand, denies violating the rule on before the seventieth day after the day on which the said
exhaustion of administrative remedies. It claims that it sent at period of 84 days expired, as the case may be, give notice to
least 17 demand letters to petitioner, four (4) of which were the other party, with a copy for information to the Engineer, of
sent to the DPWH Secretary directly.52 his intention to commence arbitration, as hereinafter provided,
as to the matter in dispute. Such notice shall establish the
Petitioner's argument fails to convince. entitlement of the party giving the same to commence
arbitration, as hereinafter provided, as to such dispute and,
The case is not premature. The pertinent provision on available subject to Sub-Clause 67.4, no arbitration in respect thereof
administrative remedies can be found in Sub-Clause 67.1 of the may be commenced unless such notice is given.
Conditions of Contract:
Settlement of Disputes If the Engineer has given notice of his decision as to a matter in
dispute to the Employer and the Contractor and no notice of
Engineer's Decision 67.1 If a dispute of any kind whatsoever intention to commence arbitration as to such dispute has been
arises between the Employer and the Contractor in connection given by either the Employer or the Contractor on or before the
with, or arising out of, the Contract or the execution of the seventieth day after the day on which the patties received
notice as to such decision from the Engineer, the said decision
shall become final and binding upon the Employer and the In the last paragraph of the letter on September 10, 2004
Contractor.53 (Emphasis supplied) (Annex "R"), Claimant has requested Respondent for a
Under the doctrine of exhaustion of administrative remedies, definitive ruling on the disputes which were enumerated therein
so that Claimant could avail of the remedies given to it by the
the concerned administrative agency must be given the
aforesaid Clause 67.1. In spite of Claimant's request,
opportunity to decide a matter within its jurisdiction before an
action is brought before the courts, otherwise, the action will be respondent DPWH did not act on the same.
declared premature.54
The evidence also disclosed that as far as delayed payments
are concerned, Claimant made various verbal and written
In this case, CIAC found and correctly ruled that respondent
had duly complied with the contractual obligation to exhaust demands for payment as evidenced by Exhibits "E" to "E-16" or
starting December 5, 2000. The demands were not heeded.55
administrative remedies provided for under sub-clause 67.1 of
the Conditions of Contract before it brought the case before the A total of 17 demand letters were sent to petitioner to no avail.
tribunal: To require respondent to wait for the DPWH Secretary's
The Claimant further alleged that, despite of such knowledge, response while respondent continued to suffer financially would
no relief from the Secretary was forthcoming. It would be to condone petitioner's avoidance of its obligations to
therefore be an exercise in futility if Claimant, after it had sent respondent. Hence, even assuming that subclause 67.1 was not
respondent the seventeen (17) demand letters and despite the applicable, the case would still fall within the exceptions to the
unequivocal admission by Respondent's foreign consultant in doctrine of exhaustion of administrative remedies 56 since strict
charge of the project of respondent's liability and failure to pay application of the doctrine will be set aside when requiring it
(Annex C of the Complaint), will further be required to undergo would only be unreasonable under the circumstances.57
another series of presentation and exchange of documentation.
Moreover, Respondent has not indicated any practical benefit of IV
resending the demand to the Secretary nor any prejudice for
not doing so. Petitioner avers that the Court of Appeals gravely erred in
rendering the assailed decision because it completely ignored,
In this particular contract project, the procedural requirements overlooked, or misappreciated facts of substance, which, if duly
governing the Settlement of Disputes is specifically provided considered, would materially affect the outcome of the case.
under Clause 67 of the Conditions of the Contract which Petitioner argues that the present case is an exception to the
Claimant has complied with pursuant to the first paragraph of rule that only questions of law may be raised in a Petition for
its letter dated September 10, 2004 (annex R) pertinent Review under Rule 45 of the Rules of Court.58
provisions thereof is read, as follows:
Before delving into the issues raised, it is imperative to
"Pursuant to the provision of Clause 67.1 of the conditions of understand CIAC's role as the arbitral tribunal at the center of
contracts, we are formally referring to your good office several this dispute.
office several [sic] points of disagreement between the position
you have taken and the position we have argued for. These CIAC was created under Executive Order No. 1008, or the
were already the subject of voluminous correspondence "Construction Industry Arbitration Law." It was originally under
between your good self and our company but no clear-cut the administrative supervision of the Philippine Domestic
resolution of the issues raised was ever made." Construction Board59 which, in turn, was an implementing
agency of the Construction Industry Authority of the
Philippines.60 The Construction Industry Authority of the that will be executed pursuant to the provisions of this Act:
Philippines is presently a part of the Department of Trade and Provided, That by mutual agreement, the parties may agree in
Industry as an attached agency.61 writing to resort to alternative modes of dispute resolution.
(Emphasis supplied)
CIAC's specific purpose is the "early and expeditious settlement
CIAC's authority to arbitrate construction disputes was then
of disputes"62 in the construction industry as a recognition of
incorporated into the general statutory framework on
the industry's role in "the furtherance of national development alternative dispute resolution through Republic Act No. 9285,
goals."63
the "Alternative Dispute Resolution Act of 2004". Section 34 of
Republic Act No. 9285 specifically referred to the Construction
Section 4 of the Construction Industry Arbitration Law lays out
Industry Arbitration Law, while Section 35 confirmed CIAC's
CIAC's jurisdiction: jurisdiction:
Section 4. Jurisdiction. - The CIAC shall have original and
CHAPTER 6 - ARBITRATION OF CONSTRUCTION DISPUTES
exclusive jurisdiction over disputes arising from, or connected
with, contracts entered into by parties involved in construction Section 34. Arbitration of Construction Disputes: Governing
in the Philippines, whether the dispute arises before or after the
Law. - The arbitration of construction disputes shall be
completion of the contract, or after the abandonment or breach
governed by Executive Order No. 1008, otherwise known as the
thereof. These disputes may involve government or private
Constitution Industry Arbitration Law.
contracts. For the Board to acquire jurisdiction, the parties to a
dispute must agree to submit the same to voluntary arbitration.
Section 35. Coverage of the Law. - Construction disputes which
fall within the original and exclusive jurisdiction of the
The jurisdiction of the CIAC may include but is not limited to Construction Industry Arbitration Commission (the
violation of specifications for materials and workmanship; "Commission") shall include those between or among parties to,
violation of the terms of agreement; interpretation and/or
or who are otherwise bound by, an arbitration agreement,
application of contractual time and delays; maintenance and
directly or by reference whether such parties are project owner,
defects; payment, default of employer or contractor and contractor, subcontractor, quantity surveyor, bondsman or
changes in contract cost.
issuer of an insurance policy in a construction project.
Excluded from the coverage of this law are disputes arising
The Commission shall continue to exercise original and
from employer-employee relationships which shall continue to exclusive jurisdiction over construction disputes although the
be covered by the Labor Code of the Philippines.
arbitration is "commercial" pursuant to Section 21 of this Act.
Republic Act No. 9184 or the "Government Procurement Reform
As a general rule, findings of fact of CIAC, a quasi-judicial
Act," recognized CIAC's competence in arbitrating over
tribunal which has expertise on matters regarding the
contractual disputes within the construction industry: construction industry, should be respected and upheld.
Section 59. Arbitration, Any and all disputes arising from the In National Housing Authority v. First United Constructors
implementation of a contract covered by this Act shall be
Corp.,64 this Court held that CIAC's factual findings, as affirmed
submitted to arbitration in the Philippines according to the
by the Court of Appeals, will not be overturned except as to the
provisions of Republic Act No. 876, otherwise known as the most compelling of reasons:
"Arbitration Law": Provided, however, That, disputes that are
As this finding of fact by the CIAC was affirmed by the Court of
within the competence of the Construction Industry Arbitration
Appeals, and it being apparent that the CIAC arrived at said
Commission to resolve shall be referred thereto. The process of
finding after a thorough consideration of the evidence
arbitration shall be incorporated as a provision in the contract
presented by both parties, the same may no longer be reviewed On the other hand, commercial relationships covered by our
by this Court. The all too-familiar rule is that the Court will not, commercial arbitration laws are purely private and contractual
in a petition for review on certiorari, entertain matters factual in in nature. Unlike labor relationships, they do not possess the
nature, save for the most compelling and cogent reasons, like same compelling state interest that would justify state
when such factual findings were drawn from a vacuum or interference into the autonomy of contracts. Hence, commercial
arbitrarily reached, or are grounded entirely on speculation or arbitration is a purely private system of adjudication facilitated
conjectures, are conflicting or are premised on the supposed by private citizens instead of government instrumentalities
evidence and contradicted by the evidence on record or when wielding quasi-judicial powers.
the inference made is manifestly mistaken or absurd. This
conclusion is made more compelling by the fact that the CIAC is Moreover, judicial or quasi-judicial jurisdiction cannot be
a quasi-judicial body whose jurisdiction is confined to conferred upon a tribunal by the parties alone. The Labor Code
construction disputes. Indeed, settled is the rule that findings of itself confers subject-matter jurisdiction to Voluntary
fact of administrative agencies and quasi-judicial bodies, which Arbitrators.
have acquired expertise because their jurisdiction is confined to
specific matters, are generally accorded not only respect, but Notably, the other arbitration body listed in Rule 43 - the
finality when affirmed by the Court of Appeals.65 (Emphasis Construction Industry Arbitration Commission (CIAC) - is also a
supplied) government agency attached to the Department of Trade and
In distinguishing between commercial arbitration, voluntary Industry. Its jurisdiction is likewise conferred by statute. By
contrast, the subject matter jurisdiction of commercial
arbitration under Article 219(14) of the Labor Code,66 and
arbitrators is stipulated by the.parties.68 (Emphasis supplied)
construction arbitration, Freuhauf Electronics Philippines
Corporation v. Technology Electronics Assembly and V
Management Pacific67 ruled that commercial arbitral tribunals
are purely ad hoc bodies operating through contractual consent, Petitioner argues that respondent is not entitled to
hence, they are not quasi-judicial agencies. In contrast, US$358,227.95, as the foreign component of the Contract,
voluntary arbitration under the Labor Code and construction because it is not yet legally demandable.69 In declaring that
arbitration derive their authority from statute in recognition of petitioner should pay the amount as the foreign component of
the public interest inherent in their respective spheres. the project, CIAC held that petitioner did not deny said amount
Furthermore, voluntary arbitration under the Labor Code and in its answer and that respondent's failure to renew its Letter of
construction arbitration exist independently of the will of the Credit does not justify petitioner's act in withholding the dollar
contracting parties: component of the project.70
Voluntary Arbitrators resolve labor disputes and grievances
arising from the interpretation of Collective Bargaining Petitioner maintains that the delay in payment was due to the
Agreements. These disputes were specifically excluded from the negative slippage incurred by respondent and its failure to
coverage of both the Arbitration Law and the ADR Law. renew its Letter of Credit. Petitioner argues that under Clause
60.11 of the Conditions of the Contract, Part II, an irrevocable
Unlike purely commercial relationships, the relationship standby letter of credit is required before petitioner can release
between capital and labor are heavily impressed with public the advance payment.71 Petitioner states:
interest. Because of this, Voluntary Arbitrators authorized to In this case, respondent does not deny that its LC No. OIDS-
resolve labor disputes have been clothed with quasi-judicial 00022-00027-0 issued by the United Coconut Planters
authority. Bank (UCPB) expired on October 15, 2003. Petitioner
reminded respondent several times on the imperative need for
the renewal of its LC to avoid delay in the processing of its admonished Respondent DPWH and reiterated that it should
billing. The purpose of said LC is to guarantee the return of the take prompt action to effect payment of outstanding monies
advance payment by petitioner to respondent.72 due, and nothing was ever mentioned of the failure to renew
Hence, petitioner claims that respondent cannot compel the the Letter of Credit. (paragraph 3.2 of affidavit by Ferdinand
Mariano)
payment of the foreign component of the Contract because it
did not comply with the letter of credit requirement. Moreover,
petitioner asserts that "In directing petitioner to pay the said Moreover, Claimant explained to the Respondent why the Letter
of credit could not be renewed in its letter of 01 and 15 March
award to respondent without the latter posting the said letter of
2004 (Exh. "C-16" and "C-17"). It appears that one of the
credit, the CIAC and the Court of Appeals effectively amended
bank's requirements for issuance of the Letter of Credit was the
the stipulation thereon in the contract which is legally
impermissible."73 approved time extension and the extension of the contract, but
Respondent refused to issue any document extending the
contract.
For respondent's part, it argues that it was impossible to renew
the Letter of Credit. It explained that banks refused the renewal
On the other hand, the Respondent's justification was only
of the Letter of Credit since the original contract period had
based on its accounting requirement. It asserted that the LC
already expired and petitioner did not act on respondent's
guaranteed the advance payment as well as the work
requests for extension.74 In addition, evidence shows that "the
main reason of the non-payment of dollar component was due completion. It further stated that the LC was a requirement by
the funding bank (By Subair S. Diron, paragraph 3.1.1 of Joint
to unresolved issues, the right of way acquisition problem
Affidavit by Heinz Reister, Diron and Pandapatan)78 (Emphasis
between ADB and the [government], wherein ADB was forced
supplied)
to suspend the loan disbursement for the entire 6th Road
Improvement Project effective 01 June 2003 due to this In National Housing Authority v. First United Constructors
conflict."75 Nevertheless, respondent admitted that the mutual Corp.,79 this Court held that the respondent contractor was
termination of the Contract rendered the requirement of a entitled to the payment of its claims, as the non-posting of the
Letter of Credit for the release of the $358,227.95 moot and required Payment Guarantee Bond was due to the inaction of
academic.76 petitioner National Housing Authority:
Petitioner's subsequent refusal to process and pay these claims
This Court affirms the findings of CIAC and the Court of Appeals despite FUCC's willingness to submit a surety bond to secure
that respondent is entitled to the foreign component of the the balance of the advance payment still to be recouped by
Contract. NHA - as the parties had agreed upon which bond would be
submitted when the check payment for the claim is about to be
CIAC found that petitioner was not justified in withholding the released, clearly constitutes a violation by NHA of FUCC's right
payment for the dollar component of the Contract.77 Further, it to be paid these acknowledged and recognized claims. Thus,
found that respondent was justified and not at fault for not respondent had an accrued cause of action against petitioner
reviewing the Letter of Credit. It held that: for these claims at the time it filed its Complaint, the
The Arbitral Tribunal is persuaded that the main reason for the constitutive elements of which are clearly set forth
nonpayment of the dollar component was due to the unresolved therein.80 (Emphasis supplied)
issues (right of way acquisition) between the ADB and the
In the present case, the renewal of the Letter of Credit hinged
Government of the Philippines where the Loan Disbursement
on the extension of the contract period. Despite notice by
was suspended by ADB for the 61 Road Improvement Project
respondent of the bank's requirement for the renewal of the
effective 01 June 2003 . . . The foreign Consultant even
Letter of Credit, petitioner chose to ignore respondent's time extension due to delayed payments [were] revised and
requests for time extensions. Therefore, petitioner cannot shift modified."88
the blame to respondent and claim that the Letter of Credit was
a condition sine qua non for the payment of the dollar Respondent points out that petitioner, through Engr. Pierre
component of the project. Castelli, had acknowledged that the delayed payment had
greatly affected respondent's cash flow.89
VI
Respondent likewise asserts that it is entitled to a time
Petitioner also assails the findings of the Court of Appeals with extension due to peace and order problems. Petitioner did not
regard to the time extensions respondent is entitled to. object to respondent's entitlement to an extension due to the
Petitioner argues that both the CIAC and the Court of Appeals peace and order situation. Hence, the only thing required is to
failed to consider the subsequent payments made to determine the number of calendar days' extension respondent
respondent after the conclusion of the arbitration hearings. is entitled to based on the circumstances.90
Thus, the tribunal's finding that petitioner still owes respondent
US$358,227.95 is factually erroneous. Chief Resident Engineer Andre Drockur of BCEOM French
Engineering Consultant recommended a time extension of 29
Petitioner claims that "respondent failed to prove that it is calendar days due to the peace and order situation. While
entitled to the time extensions of: (1) 133 calendar days in respondent did not agree with the consultant's
addition to the 144-calendar days previously agreed by the recommendation, it still adopted such recommendation to
parties and (2) 108-calendar days due to delayed payments."81 expedite the computation of time extension due to peace and
order problems.91
On the other hand, respondent argues that it is entitled to time
extensions in addition to the 144 calendar days granted to it According to CIAC, respondent was entitled to time extensions
under Variation Order No. 2.82 Respondent claims it is entitled in addition to the 144-calendar day extension agreed upon by
to a total of 277 calendar days based on the approved revised the parties, as per Variation Order No. 2:
Project Evaluation Review Tracking Critical Path Method (PERT- The Arbitral tribunal finds that the computation presented by
CPM) diagram and S-Curve,83 As explained by witness Engr. the Claimant based form the approved revised PERT/CPM and
Reyes, rock excavation requires special skills, equipment, and S-Curve is acceptable and the 277 calendar days should have
explosives. These factors were not considered when the original been granted by the Respondent or an additional of 133
contract schedule was prepared.84 calendar days. However, the project is now terminated. The
actual accomplishment as per letter of [Chief Resident
Respondent further claims that it is entitled to another time Engineer] to DPWH dated September 18, 2003 shows that the
extension due to the delay in payment. Respondent maintains actual volume of accomplishment was only 2,732 m2 of
that it infused more than double the 10% credit line amounting hardrock an 4,444 m3 of rippable rock. Thus, the entire volume
to P157,747,945.00.85 Respondent also claims that it had under Change Order #2 [or Variation Order No. 2] will not be
already mobilized working and state-of-the-art equipment.86 consumed as the work is no 80% comp1ete[.]92
The Court of Appeals affirmed that respondent was entitled to a
The DPWH Bureau of Construction evaluated respondent's
133-day time extension in addition to the 144 calendar days
request for time extension and recommended its approval to
under Variation Order No. 2.93 However, the Court of Appeals
the Secretary.87 However, the recommendation was withdrawn
noted that CIAC did not specify whether respondent was
"on the pretext that said DPWH guidelines for computation of
entitled to the full 133 days' extension, considering that it
found that the entire volume in Variation Order No. 2 will not be
fully used up due to respondent's 80% accomplishment.94 On the other hand, petitioner claims that respondent did not
question the findings of the Court of Appeals regarding price
CIAC also held that respondent was entitled to a time extension adjustment and claim for actual damages. Hence, it should not
of 108 calendar days due to petitioner's delayed be allowed to assail the Court of Appeals' ruling on this issue
payments95 and another time extension of 29 calendar days before this Court.99
due to the peace and order situation in the project area.96
Both CIAC and the Court of Appeals found that respondent was
This Court sees no reason to deviate from the findings of both not entitled to a price adjustment:
CIAC and the Court of Appeals with regard to respondent's As to the first issue raised by the Claimant, this Court finds that
entitlement to time extensions: 1) under Variation Order No. 2; the CIAC committed no reversible error in not awarding the
2) due to the delay in payment; and 3) due to the peace and price adjustment being sought by the Claimant under P.D.
order situation, since these are supported by the evidence on 1594, finding as flawed its claim based on the alleged DPWH's
record. delay in the issuance of the notice to proceed.

To reiterate, findings of fact of administrative agencies and We quote with approval the pertinent ratiocination of the CIAC
quasi-judicial bodies are entitled to great respect and even on this point, thus:
finality when affirmed by the appellate court,97 In this case, the ....
Court of Appeals found that respondent was entitled to the time
extensions as evaluated by CIAC, the agency tasked to resolve However, the Claimant is not entitled to a price adjustment
issues regarding the construction industry. Both tribunal found under P.D. 1594 because it is the ADB Guideline[s] on
that respondent was entitled to the extensions due to Procurement which should be followed, and not the provisions
petitioners delayed payments, peace and order situation, and on P.D. 1594. In fact the bid of the Contractor was awarded
Variation Order No. 2. These findings are clearly supported by despite its being above the approved Agency Estimates (AAE),
the facts on record. based on the ADB guidelines, and against the provisions of P.D.
1594 (paragraph 7.2 of Joint Affidavit by Heinz Reister, Diron
However, in light of the mutual termination of the Contract, the and Pandapatan).
remand of the case to CIAC will serve no practical purpose and
is, therefore, unnecessary. The Arbitral Tribunal finds that the Guidelines of the Asian
Development Bank govern this subject Project. Moreover, P.D.
VII 1594 honors the treaties and international or executive
agreements to which the Philippine Government is a signatory.
According to respondent the delay in the issuance of the Notice Loan agreements such as those entered into with international
to Proceed entitles it to a price adjustment under Presidential funding institutions like ADB are considered to be within the
Decree No. 1594. Bidding was conducted in January 1998 and ambit of DOJ opinion No. 46, S. 1987 and are therefore exempt
respondent was declared the winning bidder. The Contract was from the application of P.D. No. 1594 as amended (Paragraph
signed on April 29, 1999. However, the Notice to Proceed was 7.1.1 of Joint Affidavit by Heinz Reister, Diron and Pandapatan).
issued on May 5, 1999, or after a delay of more than 120 days
from the bidding date, which entitles the bidder to an ....
adjustment in the contract unit price under Presidential Decree
If the Claimant's bid was awarded despite its being above the
No. 1594.98
approved Agency Estimates based on the ADB guidelines, and
against the provisions of P.D. 1594, We cannot see the have agreed upon, i.e., the Asian Development Bank
rationale on why the Claimant now refuses to abide by the ADB Guidelines, that should govern in case of issues arising from the
guidelines on procurement. After the claimant was benefited by contract. Respondent failed to proffer evidence on what the
the approved bid at the inception of the project, We hold that it Asian Development Bank Guidelines provide, if any, in the
is unjustified for the Claimant not to be bound by the ADB event of a delay in the issuance of a Notice to Proceed.
guidelines under the pretext that it fails to get the supposed
price adjustment.100 (Emphasis supplied) VIII
While respondent did not appeal the Court of Appeals' ruling
Petitioner argues that "CIAC and the Court of Appeals grossly
with regard to its entitlement to a price adjustment under
erred in awarding P5,080,000.00, plus legal interest of
Presidential Decree No. 1594, for purposes of clarity and to
P464,298.08 for the alleged equipment and financial losses;
finally settle the matter, this Court affirms the findings of CIAC
and additional cost resulting from the alleged bombing incident
and the Court of Appeals.
of P6,267,410.48, plus legal interest of P320,410.63."106
This Court has held that a foreign loan agreement with
Furthermore, petitioner asserts that "the award to respondent
international financial institutions, such as a multilateral lending
of additional costs in the contract price under Clause 69.4 of
agency organized by governments like the Asian Development
the General Conditions of the Contract in the amount of
Bank, is an executive or international agreement contemplated
P20,311,072.66, plus legal interest of P1,038,368.78 is
by our government procurement system.101
improper."107 Petitioner maintains that the award to respondent
of additional costs in the contract price under Clause 69.4 of
In Abaya v. Ebdane, Jr.,102 this Court upheld the applicability of
the General Conditions of Contract was baseless, since the
the Japan Bank for International Cooperation's Procurement
Engineer had not yet consulted with the parties to determine
Guidelines to the implementation of the projects to be
the amount of additional costs.108
undertaken pursuant to the loan agreement between the
Republic of the Philippines and Japan Bank for International
In contrast, respondent claims that it is entitled to equipment
Cooperation.103
and financial losses due to the peace and order situation.109
While the Implementing Rules and Regulations104 of Presidential
Petitioner's arguments are untenable.
Decree No. 1594 provide the formula for price adjustment in
case of delay in the issuance of a notice to proceed, the law
It has been sufficiently established that a peace and order
does not proscribe parties from making certain contractual
problem arose at the project site:
stipulations. In this case, the Construction Contract is clear that
The Arbitral Tribunal was persuaded by the fact that six (6)
in case of price adjustments, Clause 70 of the Conditions of
named persons and four (4) John Does were accused of
Contract will apply:
Destructive Arson in the Municipal Circuit Trial Court of
3. That computation and payment of contract prices adjustment
Dumalinao Zamboanga del Sur for feloniously setting on fire
will be applied in accordance with Clause 70 of the Conditions of
simultaneously one (1) unit of Kumatsu Payloader amounting to
Contract;105
Php3,000,000.00 and one (1) unit Isuzu 10 Wheeler Dump
It is unclear from the records, however, whether the Asian Truck amounting to Php800,000.00, both belonging to the
Development Bank Guidelines was substantially the same as Claimant. The accused are believed NP's with motives of hatred
Clause 70 of the Conditions of Contract. Nevertheless, as in due to vain collection of revolutionary taxes from Claimant
the Abaya case, it should be the guidelines that the parties (Exh. "C-5").
(c) ionising radiations, or contamination by radio-activity from
The burning of the Payloader and Dump Truck, subject of the any nuclear fuel, or from any nuclear waste from the
criminal case (Exh. "C-5'') was corroborated in its entirety by combustion of nuclear fuel, radio active toxic explosive, or
the testimony of Pedrito G. Palancos, operator of the burnt other hazardous properties of any explosive nuclear assembly
Payloader in his affidavit, paragraph 6.6 to 6.9, part of the or nuclear component thereof,
records of this case.
(d) pressure waves caused by aircraft or other aerial devices
The Chief of Police of Kumalarang, Zamboanga del Sur travelling at sonic or supersonic speeds,
submitted a Special Written Report to the PNP Provincial
Director, regarding the bombing at Claimant's hatching plant in (e) riot, commotion or disorder, unless solely restricted to
Boyugan, Kumalarang, del Sur on 11 March 2003. employees of the Contractor or of his Subcontractors and
arising from the conduct of the Works,
The bombing incident revealed that it resulted in conflagration
causing damage to the Generator Set, Caterpillar Brand KVA (f) loss or damage due to the use or occupation by the
180-180 and the Conveyor, with total estimated cost of Employer of any Section or part of the Permanent Works,
Php7,300,000.00. except as may be provided for in the Contract,

Intelligence Action Agent gathered information that MILF (g) loss or damage to the extent that it is due to the design of
Members, all armed with undetermined numbers, but believed the Works, other any part of the design provided by the
to be under Commander Susob Edris, were sighted by the Contractor or for which the Contractor is responsible,
barangay officials and the neighbor of the Plant location, when
the incident occurred. (Exh. "C-9"). (h) any operation of the forces of nature against which an
experienced contractor could not reasonably have been
The two incidents described above, one costing approximately expected to take precautions.111 (Emphasis supplied)
Php3,800,000.00 and the other costing approximately It is clear from the above provision that the assumed risks of
Php7,300,000.00, will have a total of approximately
the employer under Clause 20.4 of the Conditions of Contract
Php11,100,000.00 or Php11,347,410.48 to be exact. This is the
include rebellion, revolution, insurrection, or military or usurped
amount that Claimant is entitled due to the peace and order
power, or civil war.
situation at the Project site.110
This Court finds that CIAC and the Court of Appeals did not err Petitioner further insists that respondent is not yet entitled to
when they found that respondent was entitled to its claim for the claim because there is no determination by the Engineer of
equipment and financial losses. The situation was an assumed the costs incurred, as required under Clause 69.4 of the
risk of petitioner as employer and is, thus, compensable under Conditions of Contract.112
Clause 20.4 of the Conditions of Contract, which lists the
Employer's risks as: In its Answer before CIAC, petitioner denied respondent's
(a) war, hostilities (whether war be declared or not), invasion, claims for additional costs under Clause 69.4. Petitioner stated
act of foreign enemies, that its denial will be explained more specifically in its
Affirmative Defenses:
(b) rebellion, revolution, insurrection, or military or usurped 6. DENIES the allegations in paragraphs 12, 13, 14, 15 and 16
power, or civil war, of the complaint for being preposterous, misleading and
patently without legal and factual basis, the truth being that as
per the Conditions of Contract, complainant is not entitled to
9.1 Q: Is claimant entitled to additional cost/charges under
the payment of additional cost on slowdown or suspension of
Clause 69.4 of the General Conditions of Contract?
work on the project, reimbursement for alleged equipment
losses and additional time extensions to complete the
project specifically stated/discussed in the Affirmative Defenses
hereof.113 (Emphasis supplied) A: Not yet, the claimant should establish that it is
allowed.117
However, a perusal of petitioner's Affirmative Defenses reveals
that no such qualification was made. This Court finds that petitioner failed to specifically deny the
claims of respondent and had, therefore, admitted such claims.
Under Rule 8, Section 10 of the Rules of Court, the "defendant This Court agrees that respondent was able to establish its
must specify each material allegation of fact the truth of which claims before the CIAC. This Court notes that the project was in
he does not admit and, whenever practicable, shall set forth the Mindanao, and mobilization of workers and equipment is not an
substance of the matters upon which he relies to support his easy feat and not without cost. Respondent believed that the
denial." There are three (3) modes of specific denial provided suspension would only be temporary and work could resume at
for under the Rules: any time once petitioner settled its obligation. Petitioner must
1) by specifying each material allegation of the fact in the compensate respondent for the costs it incurred without any
complaint, the truth of which the defendant does not admit, fault on respondent's part.
and whenever practicable, setting forth the substance of the
matters which he will rely upon to support his denial; (2) by IX
specifying so much of an averment in the complaint as is true
and material and denying only the remainder; (3) by stating During the arbitration hearing before the CIAC, respondent
that the defendant is without knowledge or information itself admitted that there was no provision in the Conditions of
sufficient to form a belief as to the truth of a material averment Contract for interest at the rate of 24% per annum on delayed
in the complaint, which has the effect of a denial.114 payments.118
In Aquintey v. Spouses Tibong,115 this Court held that using
"specifically" in a general denial does not automatically convert Respondent tries to excuse the lack of contractual stipulations
that general denial to a specific one. The denial in the answer by claiming that the amount of 24% interest is payment for
must be definite as to what is admitted and what is denied, actual damages and not stipulated interest.119
such that the adverse party will not have to resort to guesswork
over "what is admitted, what is denied, and what is covered by Respondent claims that petitioner is liable for the amounts
denials of knowledge as sufficient to form a belief."116 respondent owes its creditors in the total amounts of
P10,297,090.42 and USD$118,094.93. In addition, respondent
The petitioner only tackled the issue on the claim for additional avers that petitioner should pay it 6% interest per annum
costs in the Joint Affidavit of petitioner's witnesses Heinz computed from the receipt of the first demand letter for
Reister, Subair S. Diron, and Abdulfatak A. Pandapatan: payment sent by respondent, as a result of delay in the
Issue No. 9. Is claimant entitled to additional cost under Clause payment for work accomplished.120
69.4 of the General Conditions of Contract? If so, how much?
The Court is not convinced.
Subair S. Diron and Abdulfatak A. Pandapatan testifying:
It is fundamental that a contract is the law between the parties
and, absent any showing that its provisions are wholly or in
part contrary to law, morals, good customs, public order, or paragraph 5 of the contract, supra, to fix the exchange rate at
public policy, it shall be enforced to the letter by the courts.121 P34.9 for every US$1.00, the Claimant itself has acknowledged
in its request that it was advised by the DPWH per its letter
Respondent was not able to establish the basis of its claim that dated 13 August 2003 that all payments for works earned out
it is entitled to an award of 24% interest. Moreover, as found after 31 March 2003 and related price escalation claims and
by the Court of Appeals and CIAC, the parties had agreed to retention releases in the contract will be in pesos only,
delete the provision on interest on delayed payments, since the therefore no foreign exchange payments. This fact was never
project was funded by the Asian Development Bank.122 contested by the Claimant thereby creating a presumption that
it has acquiesced to the request of the DPWH. Thus, We cannot
There is also no basis to award respondent 24% interest as see Our way through on why the CIAC has still to make a ruling
actual damages for the additional expenses it incurred due to on the Interest Computation of Delayed Payment at 6% Per
petitioner's delayed payments. Annum at US$45,206.14 as well as the Foreign Component of
US$358,227.95 plus legal interest at US$18.313.79 citing the
Before actual damages may be awarded, it is imperative that exemption of transactions where the funds involved are the
the claimant proves its claims first. The issue on the amount of proceeds of loans or investments made through bona fide
actual or compensatory damages is a question of fact,123 and intermediaries or agents, by foreign government and banking
except as provided by law or by stipulation, one is entitled to institutions such as the Asian Development Bank (ADB) from
adequate compensation only for pecuniary loss duly proven. 124 the coverage of Republic Act 529 otherwise known a[s] "An Act
to Assure Uniform Value to Philippine Coin and Currency".
In this case, respondent has not sufficiently shown how Worse, there was no mention about the subsequent notice by
awarding it 24% interest per annum on delayed payments the DPWH to the Claimant, supra about their subseq ent
corresponds to the actual damages it allegedly suffered. understanding on "no foreign exchange payments". This is
Respondent failed to show a causal relation between the alleged indeed one dubious area that nt, eds to he darified by no less
losses and the injury it suffered from petitioner's actions. than the CIAC itself.e DPWH to the Claimant, supra about their subsequent
understanding on "no foreign exchange payments". This is indeed one dubious area that needs to

X be clarified by no less than the CIAC itself.127 (Emphasis supplied)

Again, considering that respondent did not appeal the Court of


Respondent claims that it should be paid in U.S. dollars as Appeals decision, the appellate court's ruling on this issue is
specified in the Contract.125 It argues that the present case is deemed final as to respondent, and there is no need to remand
an exception to the general rule that obligations should be paid this issue to the CIAC. Issues not raised on appeal are already
in Philippine currency.126 final and cannot be disturbed.128

The Court of Appeals held that the parties subsequently agreed XI


that payments made after March 31, 2003 shall be in pesos
only: CIAC imposed legal interest in its Award as follows:
In view of the foregoing, the Claimant is entitled to payment of
However, one aspect in the CIAC decision is shrouded with legal interest of 6% per annum from the receipt of its
cloud. This concerns CIAC's order to DPWH to pay its alleged extrajudicial demand.
liability to the Claimant in US dollars. It is worthy to note that
aside from the agreement of the parties - particularly in Thus, under Issue No. 3 where the Claimant was awarded
US$358,227.95, the Claimant is entitled to legal interest of 6% in the absence of an express contract as to such rate of
per annum commencing from 2 March 2004 up to this date (or interest, shall be six percent (6%) per annum.
311 days) in the amount of US$18,313.79.
Section 2. In view of the above, Subsection X305.1 of the
Under Issue No. 8 where the Claimant was awarded Manual of Regulations for Banks and Sections 4305Q.1,
P11,347,410.48, the Claimant is entitled to legal interest of 6% 43058.3 and 4303P.1 of the Manual of Regulations for Non-
per annum for the Equipment and Plant of P5,080,000.00 Bank Financial Institutions are hereby amended accordingly.
commencing from 1 July 2003 (or 556 days) in, the amount of
P464,298.08 and for the resulting Additional Expenses of This Circular shall take effect on 1 July 2013.
P6,267,410.48 commencing from 2 March 2004 (or 311 days)
Nacar v. Gallery Frames131 then laid down the guidelines for the
in the amount of P320,410.63. imposition of legal interest:
To recapitulate and for future guidance, the guidelines laid
Under Issue No. 9 where the Claimant was awarded
down in the case of Eastern Shipping Lines are accordingly
P20,311,072.66, the Claimant is entitled to legal interest of 6% modified to embody BSP MB Circular No. 799, as follows:
per annum for Additional Cost under 69.4 of the Conditions of
Contract commencing from 2 March 2004 (or 311 days) in the
I. When an obligation, regardless of its source, i.e., law,
amount of P1,038,368.78.
contracts, quasi-contracts, delicts or quasi-delicts is breached,
the contravenor can be held liable for damages. The provisions
Under Issue No. 10 with respect to the delayed payment of
under Title XVIII on "Damages" of the Civil Code govern in
billings for various amounts and on various dates, the Claimant
determining the measure of recoverable damages.
is entitled to legal interest of 6% per annum as detailed in
Attachment 1, in the amount of US$45,206.14 and II. With regard particularly to an award of interest in the
P2,175,516.63.
concept of actual and compensatory damages, the rate of
interest, as well as the accrual thereof, is imposed, as follows:
However, pursuant to the Eastern Shipping Lines vs. Court of
Appeals, 234 SCRA 78 (1994), a monetary award shall earn
1. When the obligation is breached, and it consists
interest at the rate of 12% per annum from the date when the
in the payment of a sum of money, i.e., a loan or
award becomes final and executory until its satisfaction.129
forbearance of money, the interest due should be
On May 16, 2013, the Monetary Board of the Bangko Sentral ng that which may have been stipulated in writing.
Pilipinas issued Resolution No. 796, which revised the interest Furthermore, the interest due shall itself earn
rate to be imposed on the loan or forbearance of any money, legal interest from the time it is judicially
goods, or credits. This was implemented in Bangko Sentral ng demanded. In the absence of stipulation, the rate
Pilipinas Circular No.799130 Series of 2013, which reads: of interest shall be 6% per annum to be
The Monetary Board, in its Resolution No. 796 dated 16 May computed from default, i.e., from judicial or
2013, approved the following revisions governing the rate of extrajudicial demand under and subject to the
interest in the absence of stipulation in loan contracts, thereby provisions of Article 1169 of the Civil Code.
amending Section 2 of Circular No. 905, Series of 1982:
2. When an obligation, not constituting a loan or
Section 1. The rate of interest for the loan or forbearance of forbearance of money, is breached, an interest
any money, goods or credits and the rate allowed in judgments, on the amount of damages awarded may be
imposed at the discretion of the court at the rate computed by the CIAC, should earn legal interest at the rate of
of 6% per annum. No interest, however, shall be 12% per annum until June 30, 2013, after which, it shall earn
adjudged on unliquidated claims or damages, legal interest at the rate of 6% per annum until full satisfaction.
except when or until the demand can be
established with reasonable certainty. The other issues raised by the parties were no longer discussed
Accordingly, where the demand is established due to the mutual termination of the Contract by parties, which
with reasonable certainty, the interest shall begin rendered them moot and academic.
to run from the time the claim is made judicially
or extrajudicially (Art. 1169, Civil Code), but WHEREFORE, the Petition is DENIED. The Court of Appeals
when such certainty cannot be so reasonably Decision dated September 20, 2007 in CA-G.R. SP Nos. 88953
established at the time the demand is made, the and 88911 is AFFIRMED with MODIFICATION as follows: (1)
interest shall begin to run only from the date the that the order remanding the case to the Construction Industry
judgment of the court is made (at which time the Arbitration Commission for proper disposition is REVERSED for
quantification of damages may be deemed to being moot and academic; and (2) that the legal interest rate is
have been reasonably ascertained). The actual pegged at twelve percent (12%) per annum until June 30,
base for the computation of legal interest shall, in 2013, and then at six percent (6%) per annum until full
any case, be on the amount finally adjudged. satisfaction.

3. When the judgment of the court awarding a sum


of money becomes final and executory, the rate
of legal interest, whether the case falls under
paragraph 1 or paragraph 2, above, shall be
6% per annum from such finality until its
satisfaction, this interim period being deemed to
be by then an equivalent to a forbearance of
credit.

And, in addition to the above, judgments that have become


final and executory prior to July 1, 2013, shall not be disturbed
and shall continue to be implemented applying the rate of
interest fixed therein.132
Before Nacar and Bangko Sentral ng Pilipinas Monetary Board
Resolution No. 796 dated May 16, 2013, the rate of legal
interest was pegged at 12% per annurn from finality of
judgment until its satisfaction, "this interim period being
deemed to be by then an equivalent to a forbearance of
credit."133

With this Court's pronouncement in Nacar, the rate of interest


imposed should be modified. The monetary awards, as
question must involve the examination of probative value of the
evidence presented.

Civil Law; Alternative Dispute Resolution; Arbitration; Like


many alternative dispute resolution processes, arbitration is a
product of the meeting of minds of parties submitting a
predefined set of disputes.—Arbitration is a mode of settling
disputes between parties. Like many alternative dispute
resolution processes, it is a product of the meeting of minds of
parties submitting a predefined set of disputes. They agree
among themselves to a process of dispute resolution that
avoids extended litigation. The state adopts a policy in favor of
arbitration. Republic Act No. 9285 expresses this policy: SEC. 2.
Declaration of Policy.—It is hereby declared the policy of the
G.R. No. 173137, January 11, 2016 State to actively promote party autonomy in the resolution of
disputes or the freedom of the parties to make their own
BASES CONVERSION DEVELOPMENT arrangements to resolve their disputes. Towards this end, the
AUTHORITY, Petitioner, v. DMCI PROJECT DEVELOPERS, State shall encourage and actively promote the use of
INC., Respondent.
Alternative Dispute Resolution (ADR) as an important means to
achieve speedy and impartial justice and declog court
G.R. NO. 173170
dockets. As such, the State shall provide means for the use of
ADR as an efficient tool and an alternative procedure for the
NORTH LUZON RAILWAYS
CORPORATION, Petitioner, v. DMCI PROJECT DEVELOPERS, resolution of appropriate cases. Likewise, the State shall enlist
INC. Respondent. active private sector participation in the settlement of disputes
through ADR. This Act shall be without prejudice to the
Remedial Law; Civil Procedure; Appeals; Petition for Review on adoption by the Supreme Court of any ADR system, such as
Certiorari; Rule 45 is applicable when the issues raised before mediation, conciliation, arbitration, or any combination thereof
the Supreme Court (SC) involved purely questions of law.—At as a means of achieving speedy and efficient means of
the outset, we must state that BCDA and Northrail invoked the resolving cases pending before all courts in the Philippines
correct remedy. Rule 45 is applicable when the issues raised which shall be governed by such rules as the Supreme Court
before this court involved purely questions of law. In Villamor, may approve from time to time.
Jr. v. Umale, 736 SCRA 325 (2014): [t]here is a question of law Same; Contracts; At any time during the lifetime of an
“when there is doubt or controversy as to what the law is on a agreement, circumstances may arise that may cause the
certain [set] of facts.” The test is “whether the appellate court parties to change or add to the terms they previously agreed
can determine the issue raised without reviewing or evaluating upon. Thus, amendments or supplements to the agreement
the evidence.” Meanwhile, there is a question of fact when may be executed by contracting parties to address the
there is “doubt . . . as to the truth or falsehood of facts.” The circumstances or issues that arise while a contract subsists.—
There is no rule that a contract should be contained in a single
document. A whole contract may be contained in several usually in a limited way; a person in whose name a stock or
documents that are consistent with one other. Moreover, at any bond certificate is registered but who is not the actual owner
time during the lifetime of an agreement, circumstances may thereof is considered a nominee.” Corpus Juris
arise that may cause the parties to change or add to the terms Secundum describes a nominee as one: “. . . designated to act
they previously agreed upon. Thus, amendments or for another as his representative in a rather limited sense. It
supplements to the agreement may be executed by contracting has no connotation, however, other than that of acting for
parties to address the circumstances or issues that arise while a another, in representation of another or as the grantee of
contract subsists. another. In its commonly accepted meaning the term connoted
the delegation of authority to the nominee in a representative
Same; Same; Amended Contracts; When an agreement is
or nominal capacity only, and does not connote the transfer or
amended, some provisions are changed. Certain parts or
assignment to the nominee of any property in, or ownership of,
provisions may be added, removed, or corrected. These
the rights of the person nominating him.” (Citations omitted)
changes may cause effects that are inconsistent with the
Contrary to BCDA and Northrail’s position, therefore, the
wordings of the contract before the changes were applied.—
agreement’s prohibition against transfers, conveyance, and
When an agreement is amended, some provisions are changed.
assignment of rights without the consent of the other party
Certain parts or provisions may be added, removed, or does not apply to nomination.
corrected. These changes may cause effects that are
inconsistent with the wordings of the contract before the Same; Same; A beneficiary who communicated his or her
changes were applied. In that case, the old provisions shall be acceptance to the terms of the agreement before its revocation
deemed to have lost their force and effect, while the changes may be compelled to abide by the terms of an agreement,
shall be deemed to have taken effect. Provisions that are not including the arbitration clause.—There is, therefore, merit to
affected by the changes usually remain effective. DMCI-PDI’s argument that if the Civil Code gives third party
beneficiaries to a contract the right to demand the contract’s
Same; Same; Supplemented Contracts; When a contract is
fulfillment in its favor, the reverse should also be true. A
supplemented, new provisions that are not inconsistent with the
beneficiary who communicated his or her acceptance to the
old provisions are added.—When a contract is supplemented,
terms of the agreement before its revocation may be compelled
new provisions that are not inconsistent with the old provisions
to abide by the terms of an agreement, including the arbitration
are added. The nature, scope, and terms and conditions are
clause. In this case, Northrail is deemed to have communicated
expanded. In that case, the old and the new provisions form
its acceptance of the terms of the agreements when it accepted
part of the contract.
D.M. Consunji, Inc.’s funds.
Same; Same; “Assignment” and “Nomination,” Distinguished.—
Assignment involves the transfer of rights after the perfection Multiplicity of Suits; Judicial efficiency and economy require a
of a contract. Nomination pertains to the act of naming the policy to avoid multiplicity of suits.—Judicial efficiency and
party with whom it has a relationship of trust or agency. economy require a policy to avoid multiplicity of suits. As we
In Philippine Coconut Producers Federation, Inc. (COCOFED) v. said in Lanuza v. BF Corporation, 737 SCRA 275 (2014):
Moreover, in Heirs of Augusto Salas, Jr., this court affirmed its
Republic, 663 SCRA 514 (2012), this court defined “nominee”
policy against multiplicity of suits and unnecessary delay. This
as follows: In its most common signification, the term
court said that “to split the proceeding into arbitration for some
“nominee’’ refers to one who is designated to act for another parties and trial for other parties would result in multiplicity of
suits, duplicitous procedure and unnecessary delay.” This court and failing mutual agreement as to a location
also intimated that the interest of justice would be best within twenty-one (21) days after the occurrence
observed if it adjudicated rights in a single proceeding. While of the dispute, shall be held in Metro Manila and
the facts of that case prompted this court to direct the trial shall be conducted in accordance with the
court to proceed to determine the issues of that case, it did not Philippine Arbitration Law (Republic Act No. 876)
prohibit courts from allowing the case to proceed to arbitration, supplemented by the Rules of Conciliation and
when circumstances warrant. Arbitration of the International Chamber of
Commerce. All award of such arbitration shall be
DECISION final and binding upon the parties to the dispute.5

LEONEN, J.:
BCDA organized and incorporated Northrail.6 Northrail was
An arbitration clause in a document of contract may extend to registered with the Securities and Exchange Commission on
subsequent documents of contract executed for the same August 22, 1995.7chanroblesvirtuallawlibrary
purpose. Nominees of a party to and beneficiaries of a contract
containing an arbitration clause may become parties to a BCDA invited investors to participate in the railroad project's
proceeding initiated based on that arbitration clause. financing and implementation. Among those invited were D.M.
Consunji, Inc. and Metro Pacific
On June 10, 1995, Bases Conversion Development Authority Corporation.8chanroblesvirtuallawlibrary
(BCDA) entered into a Joint Venture Agreement 1 with Philippine
National Railways (PNR) and other foreign On February 8, 1996, the Joint Venture Agreement was
corporations.2chanroblesvirtuallawlibrary amended to include D.M. Consunji, Inc. and/or its
nominee as party.9 Under the amended Joint Venture
Under the Joint Venture Agreement, the parties agreed to Agreement, D.M. Consunji, Inc. shall be an additional investor
construct a railroad system from Manila to Clark with possible of Northrail.10 It shall subscribe to 20% of the increase in
extensions to Subic Bay and La Union and later, possibly to Northrail's authorized capital stock.11chanroblesvirtuallawlibrary
Ilocos Norte and Nueva Ecija.3 BCDA shall establish North Luzon
Railways Corporation (Northrail) for purposes of constructing, On February 8, 1996, BCDA and the other parties to the Joint
operating, and managing the railroad system.4 The Joint Venture Agreement, including D.M. Consunji, Inc. and/or its
Venture Agreement contained the following provision: nominee, entered into a Memorandum of
Agreement.12 Under this agreement, the parties agreed that
ARTICLE XVI the initial seed capital of P600 million shall be infused to
ARBITRATION Northrail.13 Of that amount, P200 million shall be D.M.
Consunji, Inc.'s share, which shall be converted to equity upon
NorthraiPs privatization.14 Later, D.M. Consunji, Inc.'s share
was increased to P300 million.15chanroblesvirtuallawlibrary
16. If any dispute arise hereunder which cannot be
settled by mutual accord between the parties to
Upon BCDA and Northrail's request,16 DMCI Project Developers,
such dispute, then that dispute shall be referred
Inc. (DMCI-PDI) deposited P300 million into NorthraiPs account
to arbitration. The arbitration shall be held in
with Land Bank of the Philippines.17 The deposit was made on
whichever place the parties to the dispute decide
August 7, 199618 for its "future subscription of the Northrail
shares of stocks."19 In NorthraiPs 1998 financial statements
submitted to the Securities and Exchange Commission, this b) DMCI PDI/FBDC was privy to all the deliberations of the
amount was reflected as "Deposits For Future Northrail Board and participated in the decisions made and
Subscription."20 At that time, NorthraiPs application to increase policies adopted to pursue the project.
its authorized capital stock was still pending with the Securities
and Exchange Commission.21chanroblesvirtuallawlibrary c) DMCI PDI/FBDC had full access to the financial statements of
Northrail and was regularly informed of the corporation's
In letters22dated April 4, 1997, D.M. Consunji, Inc. financial condition.30chanrobleslaw
informed PNR and the other parties that DMCI-PDI shall
be its designated nominee for all the agreements it
Upon BCDA's request, the Office of the Government Corporate
entered and would enter with them in connection with Counsel (OGCC) issued Opinion No. 116, Series of 2001 31 on
the railroad project. Pertinent portions of the letters provide:
June 27, 2001. The OGCC stated that "since no increase in
capital stock was implemented, it is but proper to return the
[I]n order to formalize the inclusion of [DMCI Project
investments of both FBDC and
Developers, Inc.] as a party to the JVA and MOA, DMCI would
DMCI[.]"32chanroblesvirtuallawlibrary
like to notify all the parties that it is designating PDI as its
nominee in both agreements and such other agreements that
In a January 19, 2005 letter,33 DMCI-PDI reiterated the request
may be signed by the parties in furtherance of or in connection
for the refund of its P300 million deposit for future Northrail
with the PROJECT. By this nomination, all the rights,
subscription. On March 18, 2005, BCDA denied34 DMCI-PDI's
obligations, warranties and commitments of DMCI under the
request:
JVA and MOA shall henceforth be assumed performed and
delivered by PDI.23 (Emphasis supplied)
We regret to say that we are of the position that the P300
[million] contribution should not be returned to DMCI for the
Later, Northrail withdrew from the Securities and Exchange following reasons:
Commission its application for increased authorized capital
stock.24 Moreover, according to DMCI-PDI, BCDA applied for a. the P300 million was in the nature of a
Official Development Assistance from Obuchi Fund of contribution, not deposits for future subscription;
Japan.25 This required Northrail to be a 100% government- and
owned and controlled corporation.26chanroblesvirtuallawlibrary
b. DMCI, as a joint venture partner, must share in
On September 27, 2000, DMCI-PDI started demanding from profits and losses.35
BCDA and Northrail the return of its P300 million
deposit.27 DMCI-PDI cited Northrail's failure to increase its
authorized capital stock as reason for the demand.28 BCDA and On August 17, 2005,36 DMCI-PDI served a demand for
Northrail refused to return the deposit29 for the following arbitration to BCDA and Northrail, citing the arbitration clause
reasons: in the June 10, 1995 Joint Venture Agreement.37 BCDA and
Northrail failed to respond.38chanroblesvirtuallawlibrary
a) At the outset, DMCI PDI/FBDC's participation in Northrail was
as a joint venture partner and co-investor in the Manila Clark DMCI-PDI filed before the Regional Trial Court of Makati 39 a
Rapid Railway Project, and as such, was granted corresponding Petition to Compel Arbitration40 against BCDA and Northrail,
representation in the Northrail Board.
pursuant to the alleged arbitration clause in the Joint Venture BCDA filed a Rule 45 Petition before this court, assailing the
Agreement.41 DMCI-PDI prayed for "an order directing the February 9, 2006 trial court Order granting DMCI-PDI's Petition
parties to proceed to arbitration in accordance with the terms to Compel Arbitration and the June 9, 2006 Order denying
and conditions of the agreement."42chanroblesvirtuallawlibrary BCDA and Northrail's Motion for
Reconsideration.52chanroblesvirtuallawlibrary
BCDA filed a Motion to Dismiss43 on the ground that there was
no arbitration clause that DMCI-PDI could enforce since DMCI- The issue in this case is whether DMCI-PDI may compel BCDA
PDI was not a party to the Joint Venture Agreement containing and Northrail to submit to arbitration.
the arbitration clause.44 Northrail filed a separate Motion to
Dismiss45 on the ground that the court did not have jurisdiction BCDA argued that only the parties to an arbitration agreement
over it and that DMCI-PDI had no cause for arbitration against can be bound by that agreement.53 The arbitration clause that
it.46chanroblesvirtuallawlibrary DMCI-PDI sought to enforce was in the Joint Venture
Agreement, to which DMCI-PDI was not a party.54 There was
In the Decision47 dated February 9, 2006, the trial court denied also no evidence that the right to compel arbitration under the
BCDA's and Northrail's Motions to Dismiss and granted DMCI- Joint Venture Agreement was assigned to DMCI-
PDI's Petition to Compel Arbitration. The dispositive portion of PDI.55 Assuming that there was such an assignment, BCDA did
the decision reads: not consent to or recognize it.56 Therefore, the trial court's
conclusion that DMCI-PDI was D.M. Consunji, Inc.'s assignee
WHEREFORE, the petition is granted. The parties are ordered to had no basis.57 In BCDA's view, DMCI-PDI had no right to
present their dispute to arbitration in accordance with Article compel BCDA to submit to
XVI of the Joint Agreement. arbitration.58chanroblesvirtuallawlibrary

SO ORDERED.48chanrobleslaw BCDA also argued that the trial court decided the Motion to
Dismiss in violation of the parties' right to due process. The trial
The trial court ruled that the arbitration clause in the Joint court should have conducted a hearing so that the parties could
Venture Agreement should cover all subsequent documents have presented their respective positions on the issue of
including the amended Joint Venture Agreement and the assignment. The trial court merely accepted DMCI-PDI's
Memorandum of Agreement. The three (3) documents allegations, without basis.59chanroblesvirtuallawlibrary
constituted one contract for the formation and funding of
Northrail.49chanroblesvirtuallawlibrary In a separate Petition for Review,60 Northrail argued that it
cannot be compelled to submit itself to arbitration because it
The trial court also ruled that even though DMCI-PDI was not a was not a party to the arbitration
signatory to the Joint Venture Agreement and the Memorandum agreement.61chanroblesvirtuallawlibrary
of Agreement, it was an assignee of D.M. Consunji, Inc.'s
rights. Therefore, it could invoke the arbitration clause in the Northrail also argued that DMCI-PDI cannot initiate an action to
Joint Venture Agreement.50chanroblesvirtuallawlibrary compel BCDA and Northrail to arbitration because DMCI-PDI
itself was not a party to the arbitration agreement. DMCI-PDI
In an Order51 dated June 9, 2006, the trial court denied BCDA was not D.M. Consunji, Inc.'s assignee because BCDA did not
and Northrail's Motion for Reconsideration of the February 9, consent to that assignment.62chanroblesvirtuallawlibrary
2006 trial court Decision.
In its Comment63 on BCDA's Petition, DMCI-PDI argued that
Rule 45 was a wrong mode of appeal.64 The issues raised by raised before this court involved purely questions of law.
BCDA did not involve questions of In Villamor v. Balmores:73chanroblesvirtuallawlibrary
law.65chanroblesvirtuallawlibrary
[t]here is a question of law "when there is doubt or controversy
DMCI-PDI pointed out that BCDA breached their agreement as to what the law is on a certain [set] of facts." The test is
when it failed to apply the P300 million deposit to Northrail "whether the appellate court can determine the issue raised
subscriptions. It turned out that such application was rendered without reviewing or evaluating the evidence." Meanwhile,
impossible by the alleged loan requirement that Northrail be there is a question of fact when there is "doubt ... as to the
wholly owned by the government and by Northrail's withdrawal truth or falsehood of facts." The question must involve the
from the Securities and Exchange Commission of its application examination of probative value of the evidence
for an increase in authorized capital presented.74chanroblesvirtuallawlibrary
stock.66chanroblesvirtuallawlibrary
BCDA and Northrail primarily ask us to construe the arbitration
DMCI-PDI also argued that it is an assignee and nominee of clause in the Joint Venture Agreement. They assert that the
D.M. Consunji, Inc., which is a party to the contracts. clause does not bind DMCI-PDI and Northrail. This issue is a
Therefore, it is also a party to the arbitration question of law. It does not require us to examine the probative
clause.67chanroblesvirtuallawlibrary value of the evidence presented. The prayer is essentially for
this court to determine the scope of an arbitration clause.
DMCI-PDI contended that the arbitration agreement extended
to all documents relating to the project.68 Even though the Arbitration is a mode of settling disputes between
agreement was expressed only in the Joint Venture Agreement, parties.75 Like many alternative dispute resolution processes, it
its effect extends to the amendment to the Joint Venture is a product of the meeting of minds of parties submitting a
Agreement and Memorandum of pre-defined set of disputes. They agree among themselves to a
Agreement.69chanroblesvirtuallawlibrary process of dispute resolution that avoids extended litigation.
DMCI-PDI emphasized that BCDA had always recognized it as The state adopts a policy in favor of arbitration. Republic Act
D.M. Consunji's assignee in its correspondences with the OGCC No. 928576 expresses this policy:
and with the President of DMCI, Mr. Isidro Consunji.70 In those
letters, BCDA described DMCI-PDI's participation as being the SEC. 2. Declaration of Policy. - It is hereby declared the policy
"joint venture partner . . . and co-investor in the Manila Clark of the State to actively promote party autonomy in the
Rapid Railway Project[.]"71 Hence, it is now estopped from resolution of disputes or the freedom of the parties to make
denying its personality in this case.72chanroblesvirtuallawlibrary their own arrangements to resolve their disputes. Towards this
end, the State shall encourage and actively promote the use of
We rule for DMCI-PDI.chanRoblesvirtualLawlibrary Alternative Dispute Resolution (ADR) as an important means to
achieve speedy and impartial justice and declog court
I dockets. As such, the State shall provide means for the use of
The state has a policy in favor of arbitration ADR as an efficient tool and an alternative procedure for the
resolution of appropriate cases. Likewise, the State shall enlist
At the outset, we must state that BCDA and Northrail invoked active private sector participation in the settlement of disputes
the correct remedy. Rule 45 is applicable when the issues through ADR. This Act shall be without prejudice to the
adoption by the Supreme Court of any ADR system, such as
mediation, conciliation, arbitration, or any combination thereof BCDA and Northrail to submit to arbitration proceedings in light
as a means of achieving speedy and efficient means of of the policy in favor of arbitration.
resolving cases pending before all courts in the Philippines
which shall be governed by such rules as the Supreme Court BCDA and Northrail assail DMCI-PDI's right to compel them to
may approve from time to time. (Emphasis supplied) submit to arbitration based on the assumption that DMCI-PDI
was not a party to the agreement containing the arbitration
Our policy in favor of party autonomy in resolving disputes has clause.
been reflected in our laws as early as 1949 when our Civil Code
Three documents — (a) Joint Venture Agreement, (b) amended
was approved.77 Republic Act No. 87678 later explicitly
Joint Venture Agreement, and (c) Memorandum of Agreement
recognized the validity and enforceability of parties' decision to
submit disputes and related issues to — represent the agreement between BCDA, Northrail, and D.M.
Consunji, Inc. Among the three documents, only the Joint
arbitration.79chanroblesvirtuallawlibrary
Venture Agreement contains the arbitration clause. DMCI-PDI
Arbitration agreements are liberally construed in favor of was allegedly not a party to the Joint Venture Agreement.
proceeding to arbitration.80 We adopt the interpretation that
To determine the coverage of the arbitration clause, the
would render effective an arbitration clause if the terms of the
relation among the three documents and DMCI-PDI's
agreement allow for such interpretation.81 In LM Power
Engineering Corporation v. Capitol Industrial Construction involvement in the execution of these documents must first be
understood.
Groups, Inc.,82 this court said:

Consistent with the above-mentioned policy of encouraging The Joint Venture Agreement was executed by BCDA, PNR, and
alternative dispute resolution methods, courts should liberally some foreign corporations.84 The purpose of the Joint Venture
construe arbitration clauses. Provided such clause is susceptible Agreement was for the construction of a railroad system from
of an interpretation that covers the asserted dispute, an order Manila to Clark with a possible extension to Subic Bay and later
to arbitrate should be granted. Any doubt should be resolved in to San Fernando, La Union, Laoag, Ilocos Norte, and San Jose,
favor of arbitration.83chanrobleslaw Nueva Ejica.85 Under the Joint Venture Agreement, BCDA
agreed to incorporate Northrail, which shall have an authorized
capital stock of F5.5 billion.86 The parties agreed that
This manner of interpreting arbitration clauses is made explicit BCDA/PNR shall have a 30% equity with Northrail.87 Other
in Section 25 of Republic Act No. 9285: Filipino partners shall have a total of 50% equity, while foreign
partners shall have at most 20% equity.88 Pertinent provisions
SEC. 25. Interpretation of the Act.-In interpreting the Act, the of the Joint Venture Agreement are as follows:
court shall have due regard to the policy of the law in favor of
arbitration. Where action is commenced by or against multiple JOINT VENTURE AGREEMENT
parties, one or more of whom are parties to an arbitration
agreement, the court shall refer to arbitration those parties who KNOW ALL MEN BY THESE PRESENTS:
are bound by the arbitration agreement although the civil action
may continue as to those who are not bound by such arbitration This Joint Venture Agreement (JVA) made and executed at
agreement. Makati, Metro Manila, this__ day of June 1995 by and between:

Hence, we resolve the issue of whether DMCI-PDI may compel The BASES CONVERSION DEVELOPMENT AUTHORITY
with a possible extension to Subic Bay and later to San
. . . hereinafter referred to as BASECON; Fernando, La Union, as the second phase, and finally to Laoag,
Ilocos Norte and to San Jose, Nueva Ecija, as the third phase of
The PHILIPPINE NATIONAL RAILWAYS ...; the project, hereinafter referred to as the PROJECT;

The following corporations collectively referred to as ARTICLE I


the Foreign Group: DEFINITION OF TERMS

a) CONSTRUCCIONES Y AUXILIAR DE ....


FERROCARRILES, S.A... .;
1.5 "PROJECT" means the construction, operation and
b) ENTRECANALES Y TAVORA, SA . . .; management of a double-track railway system from Manila to
Clark with an extension to Subic Bay, and a possible extension
c) CUBIERTAS MZOV, S.A. . . .; to San Fernando, La Union, as the second phase, and finally to
Laoag, Ilocos Norte and to San Jose, Nueva Ecija, as the third
d) COBRA, S.A....; and phase of the PROJECT.

e) Others who may later participate in the 1.6 "North Luzon Railways Corporation
JVA.chanRoblesvirtualLawlibrary (NORTHRAIL)["] means the joint venture corporation to be
established in accordance with Article II hereof.
-and- . . . .chanRoblesvirtualLawlibrary

EUROMA DEVELOPMENT CORPORATION . . . ARTICLE II


THE NORTH LUZON RAILROAD CORPORATION
WITNESSETH:

2.1 BASECON shall establish and incorporate in accordance


.... with the laws of the Republic of the Philippines a corporation to
be known as NORTH LUZON RAILWAYS CORPORATION
WHEREAS, a project identified pursuant to the aforesaid policy (NORTHRAIL) with an initial capitalization of one hundred
is the establishment of a Premier International Airport Complex million pesos (PI 00,000,000.00).
located at the former Clark Air Base as expressed in Executive
Order 174 s. 1994 in order to accommodate the expected 2.2 NORTHRAIL shall eventually have an authorized capital
heavy flow of passenger and cargo traffic to and from the stock of FIVE BILLION FIVE HUNDRED MILLION PESOS (P 5.5
Philippines, to start the development of the Northern Luzon Grid Billion) divided into 55,000,000 shares with par value of P 100
and to accelerate the development of Central Luzon and finally per share.
to decongest Metro Manila of its vehicular traffic; . . . .chanRoblesvirtualLawlibrary

WHEREAS, in order to implement and provide such a mass ARTICLE III


transit and access system, the parties hereto agreed to
construct a double-trac[k] railway system from Manila to Clark PURPOSE OF NORTHRAIL
supplemented by the Rules of Conciliation and Arbitration of the
A. PRIMARY PURPOSE International Chamber of Commerce. All award of such
arbitration shall be final and binding upon the parties to the
3.1 To construct, operate and manage a railroad system to dispute.
serve Northern and Central Luzon; and to develop, construct,
manage, own, lease, sublease and operate establishments and ARTICLE XVII
facilities of all kinds related to the railroad system; ASSIGNMENT
. . . .chanRoblesvirtualLawlibrary

ARTICLE IV 17.1 No party to this Agreement may assign, transfer or


convey this Agreement, create or incur any encumbrance of its
PARTICIPATION/TRANSFER/ENCUMBRANCE OF SHARES rights or any part of its rights and obligations hereunder or any
shares of stocks of NORTHRAIL to any person, firm or
4.1 NORTHRAIL shall increase its authorized capital stock upon corporation without the prior written consent of the other
the subscription thereon by the parties to this JVA in parties or except as provided in the Articles of Incorporation
accordance with the following equity proportion/participation: and By-Laws of NORTHRAIL and this Agreement.

Foreign Group up to 20% 17.2 This Agreement shall inure to the benefit of and be
Euroma/Filipino partners 50% binding upon the parties hereto and their respective successors
BASECON/PNR 30% and permitted assignees and designees or nominees whenever
possible.89chanrobleslaw
....
The Joint Venture Agreement was amended on February 8,
4.4 The shares owned by Filipino stockholders including 199690 to include D.M. Consunji, Inc. and/or its nominee as
BASECON, PNR, EUROMA Development Corporation and party.91 The participations of the parties in Northrail were also
hereinafter to be owned by Filipino corporations shall not be modified. Pertinent provisions of the amended Joint Venture
less than sixty percent (60%) at any given time. Agreement are reproduced as follows:
. . . .chanRoblesvirtualLawlibrary
This Amendment to the Joint Venture Agreement dated 10th of
ARTICLE XVI June 1995 (the Agreement) made and executed
at_____________ , Metro Manila, on this 8th day of February
ARBITRATION 1996 by and among:chanRoblesvirtualLawlibrary

16. If any dispute arise hereunder which cannot be settled by BASES CONVERSION DEVELOPMENT AUTHORITY . . .
mutual accord between the parties to such dispute, then that hereinafter referred to as BASECON;
dispute shall be referred to arbitration. The arbitration shall be
held in whichever place the parties to the dispute decide and with
failing mutual agreement as to a location within twenty-one
(21) days after the occurrence of the dispute, shall be held in PHILIPPINE NATIONAL RAILWAYS ...
Metro Manila and shall be conducted in accordance with the
Philippine Arbitration Law (Republic Act No. 876) as and
companies selected by BASECON, PNR and
The following corporations collectively referred to as the Lead Group on the basis of its
the FOREIGN GROUP: qualifications for the implementation of
the Project.
CONSTRUCCIONES Y AUXILIAR DE FERROCARRILES, S.A..
. .; 2. Article 4.1 should read as follows:

ENTRECANALES Y TAVORA, S.A....; CUBIERTAS Y MZOV, "NORTHRAIL shall increase its authorized
S.A. . . .; capital stock upon the subscription
thereon by the Parties to this JVA in
COBRA INSTALACIONES Y SERVICIOS, S.A.. . .; and accordance with the following equity
proportion/participation:
Other investors who may later participate in the Joint
Venture;chanRoblesvirtualLawlibrary SRG...........................................
... up to 10%
and DMCI..........................................
........... 20%
BASECON/PNR.............................
Other local investors to be represented by EUROMA up to 30%
DEVELOPMENT CORPORATION . . . Others........................................
............. 40%
and

P.M. CONSUNJI. INC. and/or its nominee . . .


3. In Article 4.4, the Filipino corporations
WITNESSETH THAT whose total shares in NORTHRAIL's capital
stock, which should not be less than sixty
WHEREAS, a Joint Venture Agreement (JVA) was executed on percent (60%) at any given time, shall
the 10th of June 1995 between BASECON, PNR, FOREIGN include D.M. CONSUNJI,
GROUP, and EUROMA; INC.93 (Underscoring supplied)
....

NOW, THEREFORE, for and in consideration of the foregoing On February 8, 1996, the same date of the execution of the
premises and of the mutual covenant contained therein, THE amended Joint Venture Agreement, the same parties executed
PARTIES HEREBY AGREE that the JVA should be amended as a Memorandum of Agreement94 "to set up the mechanics for
follows: raising the seed capitalization needed by
NORTHRAIL[.]"95 Pertinent provisions of the Memorandum of
1. In Article 1.3, D.M. CONSUNJI, INC. Agreement are reproduced as follows:
shall be included as strategic partner,
being one of the Philippine registered WITNESSETH THAT
ARTICLE I
WHEREAS, the Manila - Clark Rapid Railway System Project, PURPOSE
hereinafter referred to as the Project, was identified as one of
the major infrastructure projects to accelerate the development 1.1 Purpose. This Agreement is entered into by the Parties in
of Central Luzon, particularly the former U.S. bases at Clark order to set up the mechanics for raising the seed capitalization
and Subic; needed by NORTHRAIL to accelerate the implementation of the
.... Project.
. . . .chanRoblesvirtualLawlibrary
WHEREAS, the North Luzon Railways Corporation
(NORTHRAIL) was organized and incorporated to implement the ARTICLE II
development, construction, operation and maintenance of the TERMS OF AGREEMENT
railway system in Northern Luzon;
....
WHEREAS, NORTHRAIL is wholly owned and controlled by
BASECON; 2.1 The Parties agree to put up the necessary seed
capitalization needed by NORTHRAIL to fast-track the
WHEREAS, the privatization of NORTHRAIL is necessary in implementation of the Rapid Rail Transit System Project
order to accelerate the implementation of the Project by according to the following schedule:
tapping the financial resources and expertise of the private
sector; BCDA/PNR...................... PHP 300 Million
.... DMCI..................................................... PHP 200 Million
SRG...................................................... PHP 100 Million
WHEREAS, the Parties of the Joint Venture Agreement (JVA) of TOTAL................................................... PHP 600 Million
10 June 1995, namely BASECON, PNR, SPANISH RAILWAY ....
GROUP and EUROMA, agreed to invite other private investors to
help in the financing and implementation of the Project, and to 2.3 The amounts contributed by BCDA/PNR, DMCI, SRG, and
raise the required equity in order to accelerate the privatization others are committed to be converted to equity when
of NORTHRAIL; NORTHRAIL is privatized.96chanroblesvirtuallawlibrary
WHEREAS, DMCI and other private investors. . . have
manifested their desire to be strategic partners in implementing There is no rule that a contract should be contained in a single
the Project; document.97 A whole contract may be contained in several
documents that are consistent with one
WHEREAS, DMCI and other private investors have the financial other.98chanroblesvirtuallawlibrary
capability to implement the Project;
Moreover, at any time during the lifetime of an agreement,
WHEREAS, Phase I of the Project covers the Manila - Clark circumstances may arise that may cause the parties to change
section of the North Luzon railway network as defined by the or add to the terms they previously agreed upon. Thus,
JVA of 10 June 1995 . . .[;] amendments or supplements to the agreement may be
. . . .chanRoblesvirtualLawlibrary executed by contracting parties to address the circumstances or
issues that arise while a contract subsists.
accelerate the implementation of the same project defined in
When an agreement is amended, some provisions are changed. the first agreement.
Certain parts or provisions may be added, removed, or
corrected. These changes may cause effects that are The Memorandum of Agreement is an implementation of the
inconsistent with the wordings of the contract before the Joint Venture Agreement and the amended Joint Venture
changes were applied. In that case, the old provisions shall be Agreement. It could not exist without referring to the provisions
deemed to have lost their force and effect, while the changes of the original and amended Joint Venture Agreements. It
shall be deemed to have taken effect. Provisions that are not assumes a prior knowledge of its terms. Thus, it referred to
affected by the changes usually remain effective. "North Luzon railway network as defined by the JVA of 10 June
1995[.]"99chanroblesvirtuallawlibrary
When a contract is supplemented, new provisions that are not
inconsistent with the old provisions are added. The nature, In other words, each document of agreement represents a step
scope, and terms and conditions are expanded. In that case, toward the implementation of the project, such that the three
the old and the new provisions form part of the contract. agreements must be read together for a complete
understanding of the parties' whole agreement. The Joint
A reading of all the documents of agreement shows that they Venture Agreement, the amended Joint Venture Agreement,
were executed by the same parties. Initially, the Joint Venture and the Memorandum of Agreement should be treated as one
Agreement was executed only by BCD A, PNR, and the foreign contract because they all form part of a whole agreement.
corporations. When the Joint Venture Agreement was amended
to include D.M. Consunji, Inc. and/or its nominee, D.M. Hence, the arbitration clause in the Joint Venture Agreement
Consunji, Inc. and/or its nominee were deemed to have been should not be interpreted as applicable only to the Joint Venture
also a party to the original Joint Venture Agreement executed Agreement's original parties. The succeeding agreements are
by BCDA, PNR, and the foreign corporations. D.M. Consunji, deemed part of or a continuation of the Joint Venture
Inc. and/or its nominee became bound to the terms of both the Agreement. The arbitration clause should extend to all the
Joint Venture Agreement and its amendment. agreements and its parties since it is still consistent with all the
terms and conditions of the amendments and
Moreover, each document was executed to achieve the single supplements.chanRoblesvirtualLawlibrary
purpose of implementing the railroad project, such that
documents of agreement succeeding the original Joint Venture II
Agreement merely amended or supplemented the provisions of
the original Joint Venture Agreement. BCDA and Northrail argued that they did not consent to D.M.
Consunji, Inc.'s assignment of rights to DMCI-PDI. Therefore,
The first agreement — the Joint Venture Agreement — defined DMCI-PDI did not validly become a party to any of the
the project, its purposes, the parties, the parties' equity agreement. Section 17.1 of the Joint Venture Agreement
participation, and their responsibilities. The second agreement provides that rights under the agreement may not be assigned,
— the amended Joint Venture Agreement —- only changed the transferred, or conveyed without the consent of the other
equity participation of the parties and included D.M. Consunji, party.100 Thus:
Inc. and/or its nominee as party to the railroad project. The
third agreement — the Memorandum of Agreement — raised 17.1 No party to this Agreement may assign, transfer or
the seed capitalization of Northrail from P100 million as convey this Agreement, create or incur any encumbrance of its
indicated in the first agreement to P600 million, in order to rights or any part of its rights and obligations hereunder or any
shares of stocks of NORTHRAIL to any person, firm or MEMORANDUM OF AGREEMENT
corporation without the prior written consent of the other
parties or except as provided in the Articles of Incorporation This Agreement made and executed at Pasig, Metro Manila,
and By-Laws of NORTHRAIL and the Philippines on this 8[th] day of February 1996 by and among:
Agreement.101chanroblesvirtuallawlibrary
BASES CONVERSION DEVELOPMENT AUTHORITY . .
However, Section 17.2 of the Joint Venture Agreement provides .chanRoblesvirtualLawlibrary
that the agreement shall be binding on nominees:
with
17.2 This Agreement shall inure to the benefit of and be
binding upon the parties . . . and their respective successors
and permitted assignees and designees or nominees whenever PHILIPPINE NATIONAL
applicable.102 (Emphasis supplied) RAILWAYS ...chanRoblesvirtualLawlibrary

and
The principal parties to the agreement after its amendment
include D.M. Consunji, Inc. and/or its nominee:
D.M. CONSUNJI, INC. and/or its nominee, a domestic
AMENDMENT TO THE JOINT VENTURE AGREEMENT corporation duly organized and created pursuant to the laws of
the Republic of the Philippines . . .104 (Emphasis supplied)
This Amendment to the Joint Venture Agreement dated 10th of
June 1995 (the Agreement) made and executed at
Based on DMCI-PDFs letter to BCDA and Northrail dated April 4,
_____________ , Metro Manila, on this 8th day of February
1997, D.M. Consunji, Inc. designated DMCI-PDI as its nominee
1996 by and among:
for the agreements it entered into in relation to the project:
BASES CONVERSION DEVELOPMENT AUTHORITY . . .
[I]n order to formalize the inclusion of [DMCI Project
Developers, Inc.] as a party to the JVA and MOA, DMCI would
with
like to notify all the parties that it is designating PDI as its
PHILIPPINE NATIONAL RAILWAYS . . nominee in both agreements and such other agreements that
may be signed by the parties in furtherance of or in connection
.chanRoblesvirtualLawlibrary
with the PROJECT. By this nomination, all the rights,
and obligations, warranties and commitments of DMCI under the
JVA and MOA shall henceforth be assumed performed and
.... delivered by PDI.105 (Emphasis supplied)

D.M. CONSUNJI, INC. and/or its nominee, a domestic Thus, lack of consent to the assignment is irrelevant because
corporation duly organized and created pursuant to the laws of there was no assignment or transfer of rights to DMCI-PDI.
the Republic of the Philippines . . .103 (Emphasis DMCI-PDI was D.M. Consunji, Inc.'s nominee.
supplied)chanRoblesvirtualLawlibrary
Section 17.2 of the Joint Venture Agreement clearly shows an III
intent to treat assignment and nomination differently.
Northrail, although not a signatory to the contracts, is also
17.2 This Agreement shall inure to the benefit of and be bound by the arbitration agreement.
binding upon the parties . . . and their respective successors
and permitted assignees and designees or nominees whenever In Lanuza v. BF Corporation,109 we recognized that there are
applicable.106 (Emphasis supplied) instances when non-signatories to a contract may be compelled
to submit to arbitration.110 Among those instances is when a
Assignment involves the transfer of rights after the perfection non-signatory is allowed to invoke rights or obligations based
of a contract. Nomination pertains to the act of naming the on the contract.111chanroblesvirtuallawlibrary
party with whom it has a relationship of trust or agency.
The subject of BCDA and D.M. Consunji, Inc.'s agreement was
In Philippine Coconut Producers Federation, Inc. (COCOFED) v. the construction and operation of a railroad system. Northrail
Republic,107 this court defined "nominee" as follows: was established pursuant to this agreement and its terms, and
for the same purpose, thus:
In its most common signification, the term "nominee'' refers to
one who is designated to act for another usually in a limited ARTICLE III
way; a person in whose name a stock or bond certificate is
registered but who is not the actual owner thereof is considered PURPOSE OF NORTHRAIL
a nominee." Corpus Juris Secundum describes a nominee as
one:
A. PRIMARY PURPOSE
". . . designated to act for another as his representative in a
rather limited sense. It has no connotation, however, other 3.1. To construct, operate and manage a railroad system to
than that of acting for another, in representation of another or serve Northern and Central Luzon; and to develop, construct,
as the grantee of another. In its commonly accepted meaning manage, own, lease, sublease and operate establishments and
the term connoted the delegation of authority to the nominee in facilities of all kinds related to the railroad
a representative or nominal capacity only, and does not system[.]112chanrobleslaw
connote the transfer or assignment to the nominee of any
property in, or ownership of, the rights of the person Northrail's capitalization and the composition of its subscribers
nominating him."108 (Citations omitted) are also subject to the provisions of the original and amended
Joint Venture Agreements, and the subsequent Memorandum of
Contrary to BCDA and Northrail's position, therefore, the Agreement. It was pursuant to the terms of these agreements
agreement's prohibition against transfers, conveyance, and that Northrail demanded from D.M. Consunji, Inc. the infusion
assignment of rights without the consent of the other party of its share in subscription.
does not apply to nomination.
Therefore, Northrail cannot deny understanding that its
DMCI-PDI is a party to all the agreements, including the existence, purpose, rights, and obligations are tied to the
arbitration agreement. It may, thus, invoke the arbitration agreements. When Northrail demanded for the amount of D.M.
clause against all the parties.chanRoblesvirtualLawlibrary Consunji, Inc.'s subscription based on the agreements and later
accepted the latter's funds, it proved that it was bound by the
agreements' terms. It is also deemed to have accepted the 2006 Regional Trial Court Decision and the June 9, 2006
term that such funds shall be used for its privatization. It Regional Trial Court Order are AFFIRMED.
cannot choose to demand the enforcement of some of its
provisions if it is in its favor, and then later by whim, deny SO ORDERED.cralawlawlibrary
being bound by its terms.

Hence, when BCDA and Northrail decided not to proceed with


Northrail's privatization and the transfer of subscriptions to
D.M. Consunji, Inc., any obligation to return its supposed
subscription attached not only to BCDA as party to the
agreement but primarily to Northrail as beneficiary that
impliedly accepted the terms of the agreement and received
D.M. Consunji, Inc.'s funds.

There is, therefore, merit to DMCI-PDI's argument that if the


Civil Code113 gives third party beneficiaries to a contract the
right to demand the contract's fulfillment in its favor, the
reverse should also be true.114 A beneficiary who communicated
his or her acceptance to the terms of the agreement before its
revocation may be compelled to abide by the terms of an
agreement, including the arbitration clause. In this case,
Northrail is deemed to have communicated its acceptance of
the terms of the agreements when it accepted D.M. Consunji,
Inc.'s funds.

Finally, judicial efficiency and economy require a policy to avoid


multiplicity of suits. As we said in Lanuza:

Moreover, in Heirs ofAugusto Salas, this court affirmed its


policy against multiplicity of suits and unnecessary delay. This
court said that "to split the proceeding into arbitration for some
parties and trial for other parties would "result in multiplicity of
suits, duplicitous procedure and unnecessary delay." This court
also intimated that the interest of justice would be best
observed if it adjudicated rights in a single proceeding. While
the facts of that case prompted this court to direct the trial
court to proceed to determine the issues of that case, it did not
prohibit courts from allowing the case to proceed to arbitration,
when circumstances warrant.115chanrobleslaw

WHEREFORE, the petitions are DENIED. The February 9,


preexisted the dispute or a subsequent submission
agreement.—Resort to arbitration is voluntary. It requires
consent from both parties in the form of an arbitration clause
that preexisted the dispute or a subsequent submission
agreement. This written arbitration agreement is an
independent and legally enforceable contract that must be
complied with in good faith. By entering into an arbitration
agreement, the parties agree to submit their dispute to an
arbitrator (or tribunal) of their own choosing and be bound by
the latter’s resolution.

Same; The contractual and consensual character of arbitration


means that the parties cannot implead a third party in the
proceedings even if the latter’s participation is necessary for a
complete settlement of the dispute.—However, this contractual
and consensual character means that the parties cannot
implead a third party in the proceedings even if the latter’s
participation is necessary for a complete settlement of the
dispute. The tribunal does not have the power to compel a
G.R. No. 204197 person to participate in the arbitration proceedings without that
person’s consent. It also has no authority to decide on issues
FRUEHAUF ELECTRONICS PHILIPPINES that the parties did not submit (or agree to submit) for its
CORPORATION, Petitioner, resolution.
vs.
TECHNOLOGY ELECTRONICS ASSEMBLY AND Same; As a purely private mode of dispute resolution,
MANAGEMENT PACIFIC CORPORATION, Respondent. arbitration proceedings, including the records, the evidence,
and the arbitral award, are confidential.—As a purely private
Arbitration; Arbitration is an alternative mode of dispute mode of dispute resolution, arbitration proceedings, including
resolution outside of the regular court system. Although the records, the evidence, and the arbitral award, are
adversarial in character, arbitration is technically not confidential unlike court proceedings which are generally public.
litigation.—Arbitration is an alternative mode of dispute This allows the parties to avoid negative publicity and protect
resolution outside of the regular court system. Although their privacy.
adversarial in character, arbitration is technically not litigation.
It is a voluntary process in which one or more arbitrators — Same; The contractual nature of arbitral proceedings affords
appointed according to the parties’ agreement or according to the parties substantial autonomy over the proceedings. The
the applicable rules of the Alternative Dispute Resolution (ADR) parties are free to agree on the procedure to be observed
Law — resolve a dispute by rendering an award. during the proceedings.—The contractual nature of arbitral
proceedings affords the parties substantial autonomy over the
Same; Resort to arbitration is voluntary. It requires consent proceedings. The parties are free to agree on the procedure to
from both parties in the form of an arbitration clause that be observed during the proceedings. This lends considerable
flexibility to arbitration proceedings as compared to court Arbitration; As a contractual and consensual body, the arbitral
litigation governed by the Rules of Court. tribunal does not have any inherent powers over the parties. It
has no power to issue coercive writs or compulsory
Same; The parties likewise appoint the arbitrators based on processes.—As a contractual and consensual body, the arbitral
agreement. There are no other legal requirements as to the tribunal does not have any inherent powers over the parties. It
competence or technical qualifications of an arbitrator.—The has no power to issue coercive writs or compulsory processes.
parties likewise appoint the arbitrators based on agreement. Thus, there is a need to resort to the regular courts for interim
There are no other legal requirements as to the competence or measures of protection and for the recognition or enforcement
technical qualifications of an arbitrator. Their only legal of the arbitral award.
qualifications are: (1) being of legal age; (2) full enjoyment of
their civil rights; and (3) the ability to read and write. The
parties can tailor-fit the tribunal’s composition to the nature of
their dispute. Same; The term “Voluntary Arbitrator” does not refer to an
ordinary “arbitrator” who voluntarily agreed to resolve a
Same; As an alternative to court proceedings, arbitration is dispute. It is a technical term with a specific definition under
meant to be an end, not the beginning, of litigation. Thus, the the Labor Code.—The term “Voluntary Arbitrator” does not refer
arbitral award is final and binding on the parties by reason of to an ordinary “arbitrator” who voluntarily agreed to resolve a
their contract — the arbitration agreement.—The errors of an dispute. It is a technical term with a specific definition under
arbitral tribunal are not subject to correction by the judiciary. the Labor Code.
As a private alternative to court proceedings, arbitration is
meant to be an end, not the beginning, of litigation. Thus, the Same; Commercial arbitration is a purely private system of
arbitral award is final and binding on the parties by reason of adjudication facilitated by private citizens instead of
their contract — the arbitration agreement. government instrumentalities wielding quasi-judicial powers.—
Commercial relationships covered by our commercial arbitration
laws are purely private and contractual in nature. Unlike labor
relationships, they do not possess the same compelling state
Quasi-Judicial Power; Quasi-judicial or administrative interest that would justify state interference into the autonomy
adjudicatory power is the power: (1) to hear and determine of contracts. Hence, commercial arbitration is a purely private
questions of fact to which legislative policy is to apply, and (2) system of adjudication facilitated by private citizens instead of
to decide in accordance with the standards laid down by the law government instrumentalities wielding quasi-judicial powers.
itself in enforcing and administering the same law.—Quasi-
judicial or administrative adjudicatory power is the power: (1) Same; Arbitral tribunals and the Regional Trial Court (RTC) are
to hear and determine questions of fact to which legislative not coequal bodies because the RTC is authorized to confirm or
policy is to apply, and (2) to decide in accordance with the to vacate (but not reverse) arbitral awards.—Arbitral tribunals
standards laid down by the law itself in enforcing and and the RTC are not coequal bodies because the RTC is
administering the same law. Quasi-judicial power is only authorized to confirm or to vacate (but not reverse) arbitral
exercised by administrative agencies — legal organs of the awards. If we were to deem arbitrators as included in the scope
government. of Rule 43, we would effectively place it on equal footing with
the RTC and remove arbitral awards from the scope of RTC
review.
Same; Appeals; The right to an appeal is neither a natural right Same; Same; An arbitral award is not appealable via Rule 43
nor an indispensable component of due process; it is a mere because: (1) there is no statutory basis for an appeal from the
statutory privilege that cannot be invoked in the absence of an final award of arbitrators; (2) arbitrators are not bodies; and
enabling statute. Neither the Arbitration Law nor the Alternative (3) the Special Alternative Dispute Resolution (ADR) Rules
Dispute Resolution (ADR) Law allows a losing party to appeal specifically prohibit the filing of an appeal to question the
from the arbitral award.—The right to an appeal is neither a merits of an arbitral award.—As established earlier, an arbitral
natural right nor an indispensable component of due process; it award is not appealable via Rule 43 because: (1) there is no
is a mere statutory privilege that cannot be invoked in the statutory basis for an appeal from the final award of
absence of an enabling statute. Neither the Arbitration Law nor arbitrators; (2) arbitrators are not quasi-judicial bodies; and (3)
the ADR Law allows a losing party to appeal from the arbitral the Special ADR Rules specifically prohibit the filing of an appeal
award. The statutory absence of an appeal mechanism reflects to question the merits of an arbitral award.
the State’s policy of upholding the autonomy of arbitration
proceedings and their corresponding arbitral awards. Same; Same; The Special Alternative Dispute Resolution (ADR)
Rules allow, the Regional Trial Court (RTC) to correct or modify
Same; Same; Grounds for vacating a domestic arbitral an arbitral award pursuant to Section 25 of the Arbitration
award.—The grounds for vacating a domestic arbitral award Law.—The Special ADR Rules allow the RTC to correct or modify
under Section 24 of the Arbitration Law contemplate the an arbitral award pursuant to Section 25 of the Arbitration Law.
following scenarios: (a) when the award is procured by However, this authority cannot be interpreted as jurisdiction to
corruption, fraud, or other undue means; or (b) there was review the merits of the award.
evident partiality or corruption in the arbitrators or any of
them; or (c) the arbitrators were guilty of misconduct that Same; Same; Because an arbitral tribunal is not a government
materially prejudiced the rights of any party; or (d) the organ exercising judicial or quasi-judicial powers, it is removed
arbitrators exceeded their powers, or so imperfectly executed from the ambit of Rule 65.—A losing party is likewise precluded
them, that a mutual, final and definite award upon the subject from resorting to certiorari under Rule 65 of the Rules of Court.
matter submitted to them was not made. Certiorari is a prerogative writ designed to correct errors of
jurisdiction committed by a judicial or quasi-judicial body.
Same; Same; The Regional Trial Court (RTC) may also set Because an arbitral tribunal is not a government organ
aside the arbitral award based on Article 34 of the United exercising judicial or quasi-judicial powers, it is removed from
Nations Commission on International Trade Law (UNCITRAL) the ambit of Rule 65.
Model Law. The RTC may also set aside the arbitral award
based on Article 34 of the UNCITRAL Model Law. These grounds Same; Same; Constitutional Law; Not even the Court’s
are reproduced in Chapter 4 of the Implementing Rules and expanded certiorari jurisdiction under the Constitution can
Regulations (IRR) of the 2004 ADR Act. justify judicial intrusion into the merits of arbitral awards.—Not
even the Court’s expanded certiorari jurisdiction under the
Same; Same; The grounds for vacating an arbitral award are Constitution can justify judicial intrusion into the merits of
exclusive. These grounds for vacating an arbitral award are arbitral awards. While the Constitution expanded the scope of
exclusive. Under the ADR Law, courts are obliged to disregard certiorari proceedings, this power remains limited to a review of
any other grounds invoked to set aside an award. the acts of “any branch or instrumentality of the Government.”
As a purely private creature of contract, an arbitral tribunal
remains outside the scope of certiorari.
Same; Same; The only remedy against a final domestic arbitral appointed by parties by mutual agreement or contract to settle
award is to file petition to vacate or to modify/correct the award their differences would have to be a voluntary arbitrator
not later than thirty (30) days from receipt of the award.—In “authorized by law” — that is, Article 2042 of the Civil Code.
sum, the only remedy against a final domestic arbitral award is This simple legal tenet should dispel any notion that
to file petition to vacate or to modify/correct the award not “commercial arbitration is a purely private system of
later than thirty (30) days from the receipt of the award. Unless adjudication facilitated by private citizens instead of
a ground to vacate has been established, the RTC must confirm government instrumentalities wielding quasi-judicial powers.”
the arbitral award as a matter of course.
Same; Appeals; View that the Special Alternative Dispute
Resolution (ADR) Rules tends to support the availability of the
remedies of a petition for review and a petition for certiorari.—A
Same; Same; Once the Regional Trial Court (RTC) orders the profound examination of RA 9285 which came into effect in
confirmation, vacation, or correction/modification of a domestic 2004, the ABS-CBN Broadcasting Corporation v. World
arbitral award, the aggrieved party may move for Interactive Network Systems (WINS) Japan Co., Ltd., 544 SCRA
reconsideration within a non-extendible period of fifteen (15) 308, case which was promulgated in 2008, and the Special ADR
days from receipt of the order. The losing party may also opt to Rules (Special Rules of Court on Alternative Dispute Resolution)
appeal from the RTC’s ruling instead.—Once the RTC orders the which was issued in 2009, would reveal that there is no conflict.
confirmation, vacation, or correction/modification of a domestic In particular, the Special ADR Rules cannot be said to have
arbitral award, the aggrieved party may move for superseded the pronouncement in the ABS-CBN case; quite the
reconsideration within a non-extendible period of fifteen (15) contrary, the latter merely echo the conclusions arrived at in
days from receipt of the order. The losing party may also opt to the former. In fact, the Special ADR Rules tends to support my
appeal from the RTC’s ruling instead. position on the availability of the remedies of a petition for
review and a petition for certiorari.
Same; Same; Simple errors of fact, of law, or of fact and law
committed by the arbitral tribunal are not justiciable errors in Same; View that the Arbitral Tribunal’s imperfect execution of
this jurisdiction.—In other words, simple errors of fact, of law, powers and “excessive exercise of arbitral power” are valid
or of fact and law grounds for vacating the arbitral award.—Finally, I am aware
that an arbitral award can be assailed based on limited
DEL CASTILLO, J., Dissenting Opinion: grounds, among which is when “the arbitrators exceeded their
powers, or so imperfectly executed them, that a mutual, final
and definite award upon the subject matter submitted to them
Arbitration; View that any arbitrator/s appointed by parties by
was not made.” This is exactly what happened in this case and
mutual agreement or contract to settle their differences would
this was the ground upon which the vacation of the arbitral
have to be a voluntary arbitrator “authorized by law” — that is,
award should be anchored on. The Arbitral Tribunal’s imperfect
Article 2042 of the Civil Code.—Rule 43 covers decisions of a
execution of powers and “excessive exercise of arbitral power”
voluntary arbitrator “authorized by law.” Under Article 2042 of
are valid grounds for vacating the arbitral award.
the Civil Code, arbitration is allowed as a mode of settling
controversies, and for this purpose, “[t]he same persons who
may enter into a compromise may submit their controversies to
one or more arbitrators for decision.” Applied well, basic logic
should enable one to reach the conclusion that any arbitrator/s
DECISION million pesos as unpaid rent (for the period of December 1986
to June 1988).
BRION, J.:
They also entered a 15-year lease contract4 (expiring on June
The fundamental importance of this case lies in its delineation 9, 2003) that was renewable for another 25 years upon mutual
of the extent of permissible judicial review over arbitral awards. agreement. The contract included an arbitration agreement: 5
We make this determination from the prism of our existing laws
on the subject and the prevailing state policy to uphold the 17. ARBITRATION
autonomy of arbitration proceedings.
In the event of any dispute o~ disagreement between the
This is a petition for review on certiorari of the Court of parties hereto involving the interpretation or implementation of
Appeals' (CA) decision in CA-G.R. SP. No. 112384 that any provision of this Contract of Lease, the dispute or
reversed an arbitral award and dismissed the arbitral complaint disagreement shall be referred to arbitration by a three (3)
for: lack of merit.1 The CA breached the bounds of its member arbitration committee, one member to be appointed by
jurisdiction when it reviewed the substance of the arbitral the LESSOR, another member to be appointed by the LESSEE,
award outside of the permitted grounds under the Arbitration and the third member to be appointed by these two members.
Law.2 The arbitration shall be conducted in accordance with the
Arbitration Law (R.A. No. 876).
Brief Factual Antecedents
The contract also authorized TEAM to sublease the property.
In 1978, Fruehauf Electronics Philippines TEAM subleased the property to Capitol Publishing
Corp. (Fruehauf) leased several parcels of land in Pasig City to House (Capitol) on December 2, 1996 after notifying Fruehauf.
Signetics Filipinas Corporation (Signetics) for a period of 25
years (until May 28, 2003). Signetics constructed a On May 2003, TEAM informed Fruehauf that it would not be
semiconductor assembly factory on the land on its own renewing the lease. 6
account.
On May 31, 2003, the sublease between TEAM and Capitol
In 1983, Signetics ceased its operations after the Board of expired. However, Capitol only vacated the premises on March
Investments (BOI) withdrew the investment incentives granted 5, 2005. In the meantime, the master lease between TEAM and
to electronic industries based in Metro Manila. Fruehauf expired on June 9, 2003.

In 1986, Team Holdings Limited (THL) bought Signetics. THL On March 9, 2004, Fruehauf instituted SPProc.
later changed its name to Technology Electronics Assembly and No.11449 before the Regional Trial
Management Pacific Corp. (TEAM). Court (RTC) for "Submission of an Existing Controversy for
Arbitration." 7 It alleged: (1) that when the lease expired, the
In March 1987, Fruehauf filed an unlawful detainer case against property suffered from damage that required extensive
TEAM. In an effort to amicably settle the dispute, both parties renovation; (2) that when the lease expired, TEAM failed to
executed a Memorandum of Agreement (MOA) on June 9, turn over the premises and pay rent; and (3) that TEAM did not
1988.3 Under the MOA, TEAM undertook to pay Fruehauf 14.7 restore the property to its original condition as required in the
contract. Accordingly, the parties are obliged to submit the
dispute to arbitration pursuant to the stipulation in the lease 1. Who is liable for the expenses of arbitration, including
contract. arbitration fees?

The RTC granted the petition and directed the parties to comply 2. Whether or not TEAM has the obligation to return the
with the arbitration clause of the contract. 8 premises to Fruehauf as a "complete, rentable, and fully
facilitized electronic plant."
Pursuant to the arbitration agreement, the dispute was referred
to a three-member arbitration tribunal. TEAM and Fruehauf The Arbitral Award12
appointed one member each while the Chairman was appointed
by the first two members. The tribunal was formally constituted On December 3, 2008, the arbitral tribunal awarded Fruehauf:
ion September 27, 2004 with retired CA Justice Hector L. (1) 8.2 million pesos as (the balance of) unpaid rent from June
Hofileña, as chairman, retired CA Justice Mariano M. Umali and 9, 2003 until March 5, 2005; and (2) 46.8 million pesos as
Atty. Maria Clara B. Tankeh-Asuncion as members.9 damages. 13

The parties initially submitted the following issues to the The tribunal found that Fruehauf made several demands for the
tribunal for resolution: 10 return of the leased premises before and after: the expiration of
the lease14 and that there was no express or implied renewal of
1. Whether or not TEAM had complied with its obligation to the lease after June 9, 2003. It recognized that the sub-lessor,
return the leased premises to Fruehauf after the expiration of Capitol, remained in possession of the lease. However, relying
the lease on June 9, 2003. on the commentaries of Arturo Tolentino on the subject, the
tribunal held that it was not enough for lessor to simply vacate
1.1. What properties should be returned and in the leased property; it is necessary that he place the thing at
what condition? the disposal of the lessor, so that the latter can receive it
without any obstacle. 15
2. Is TEAM liable for payment of rentals after June 9, 2003?
For failing to return the property' to Fruehauf, TEAM remained
2.1. If so, how much and for what period? liable for the payment of rents. However, if it can prove that
Fruehauf received rentals from Capitol, TEAM can deduct these
from its liability. 16 Nevertheless, the award of rent and
3. Is TEAM liable for payment of real estate taxes, insurance,
damages was without prejudice to TEAM's right to seek redress
and other expenses on the leased premises after June 9, 2003?
from its sub-lessee, Capitol. 17
4. Who is liable for payment of damages and how much?
With respect to the improvements on the land, the tribunal
viewed the situation from two perspectives:
5. Who is liable for payment of attorney's fees and how much?
First, while the Contract admitted that Fruehauf was only
Subsequently, the following issues were also submitted for leasing the land and not the buildings and improvements
resolution after TEAM proposed 11 their inclusion: thereon, it nevertheless obliged TEAM to deliver the buildings,
installations and other improvements existing at the inception
of the lease uponits expiration. 18
The other view, is that the MOA and the Contract recognized TEAM moved for reconsideration28 which the tribunal
that TEAM owned the existing improvements on the property denied. 29 Thus, TEAM petitioned the RTC to partially vacate or
and considered them as separate from the land for the initial modify the arbitral award.30 It argued that the tribunal failed to
15-year term of the lease. 19 However, Fruehauf had a vested properly appreciate the facts and the terms of the lease
right to become the owner of these improvements at the end of contract.
the 15-year term. Consequently, the contract specifically
obligated TEAM not to remove, transfer, destroy, or in any way The RTC Ruling
alienate or encumber these improvements without prior written
consent from Fruehauf. 20 On April 29, 2009, the RTC31 found insufficient legal
grounds under Sections 24 and 25 of the Arbitration Law to
Either way, TEAM had the obligation to deliver the existing modify or vacate the award.32 It denied the petition and
improvements on the land upon the expiration of the lease. CONFIRMED, the arbitral award. 33 TEAM filed a Notice of
However, there was no obligation under the lease to return the Appeal.
premises as a "complete, rentable, and fully facilitized
electronics plant."21Thus, TEAM's obligation was to vacate the On July 3, 2009,34 the RTC refused to give due course to the
leased property and deliver to Fruehauf the buildings, Notice of Appeal because according to Section 29 35 of the
improvements, and installations (including the machineries and Arbitration Law, an ordinary appeal under Rule 41 is not the
equipment existing thereon) in the same condition as when the proper mode of appeal against an order confirming an arbitral
lease commenced, save for what had been lost or impaired by award. 36
1the lapse of time, ordinary wear and tear, or any other
inevitable cause. 22
TEAM moved for reconsideration but the R TC denied the
motion on November 15, 2009.37 Thus, TEAM filed a petition
The tribunal found TEAM negligent in the maintenance of the for certiorari38before the CA arguing that the RTC gravely
premises, machineries, and equipment it was obliged to deliver abused its discretion in: (1) denying due course to its notice of
to Fruehauf. 23 For this failure to conduct the necessary repairs appeal; and (2) denying the motion to partially vacate and/or
or to notify Fruehauf of their necessity, the tribunal held TEAM modify the arbitral award.39
accountable for damages representing the value of the repairs
necessary to restore the premises to a condition "suitable for
TEAM argued that an ordinary appeal under Rule 41 was the
the use to which it has been devoted' less their depreciation
proper remedy against the RTC's order confirming, modifying,
expense.24
correcting, or vacating an arbitral award. 40 It argued that Rule
42 was not available because the order denying its motion to
On the other issues, the tribunal held that TEAM had no vacate was not rendered in the exercise of the RTC's appellate
obligation to pay real estate taxes, insurance, and other jurisdiction. Further, Rule 43 only applies to decisions of quasi-
expenses on the leased premises considering these obligations judicial bodies. Finally, an appeal under Rule 45 to the Supreme
can only arise from a renewal of the contract. 25 Further, the Court would preclude it from raising questions of fact or mixed
tribunal refused: to award attorney's fees, finding no evidence questions of fact and law.41
that either party acted in bad faith. 26 For the same reason, it
held both parties equally liable for the expenses of litigation,
TEAM maintained that it was appealing the RTC's order denying
including the arbitrators' fees. 27
its petition to partially vacate/modify the award, not the
arbitral award itself. 42 Citing Rule 41, Section 13 of the
Rules of Court, the RTC's authority to dismiss the appeal is Appeals,51the CA held that the aggrieved party may resort to a
limited to instances when it was filed out of time or when the petition for certiorari when the R TC to which the award was
appellant fails to pay the docket fees within the reglementary submitted for confirmation Has acted without jurisdiction, or
period.43 with grave abuse of discretion and there is no appeal, nor any
plain, speedy remedy in the course of law.52
TEAM further maintained that the RTC gravely abused its
discretion by confirming the Arbitral Tribunal's award when it The CA further held that the mere filing of a notice of appeal is
evidently had legal and factual errors, miscalculations, and sufficient as the issues raised in the appeal were not purely
ambiguities. 44 questions of law. 53 It further cited Section 46 of the Alternative
Dispute Resolution
The petition was docketed as CA-G.R. SP. No.112384.
(ADR) Law:54
The CA decision 45

SEC. 46. Appeal from Court Decisions on Arbitral


The CA initially dismissed the petition. 46
As the RTC did, it cited Awards. - A decision of the regional trial court confirming,
Section 29 of the Arbitration Law: vacating, setting aside, modifying or correcting an arbitral
award may be appealed to the Court of Appeals in accordance
Section 29. Appeals. - An appeal may be taken from an with the rules of procedure to be promulgated by the Supreme
order made in a proceeding under this Act, or from a judgment Court.
entered upon an award through certiorari proceedings, but
such appeals shall be limited to questions of law. The The losing party who appeals from the judgment of the court
proceedings upon such appeal, including the judgment thereon confirming an arbitral award shall be required by the appellant
shall be governed by the Rules of Court in so far as they are court to post counterbond executed in favor of the prevailing
applicable. party equal to the amount of the award in accordance with the
rules to be promulgated by the Supreme Court. 55
It concluded that the appeal contemplated under the law is an
appeal by certiorari limited only to questions of law.47 However, the CA made no further reference to A.M. No. 07-11-
08-SC, the Special Rules of Court on Alternative Dispute
The CA continued that TEAM failed to substantiate its claim as Resolution (Special ADR Rules) which govern the appeal
to the "evident miscalculation of figures." It further held that procedure.
disagreement with the arbitrators' factual determinations and
legal conclusions does not empower courts to amend or The CA further revisited the merits of the arbitral award and
overrule arbitral judgments.48 found several errors in law and in fact. It held: (1) that TEAM
was not obliged to pay rent because it was Capitol, not TEAM,
However, the CA amended its decision on October 25, 2012 that remained in possession of the property upon the expiration
upon a motion for reconsideration.49 of the lease;56 and (2) that Fruehauf was not entitled to
compensation for the repair$ on the buildings because it did not
become the owner of the building until after the expiration of
The CA held that Section 29 of the Arbitration Law does not
the lease. 57
preclude the aggrieved party from resorting to other judicial
remedies.50 Citing Asset Privatization Trust v. Court of
Also citing Tolentino, the CA opined: (1) that a statement by TEAM counters that the CA correctly resolved the substantive
the lessee that he has abandoned the premises should, as a issues of the case and that the arbitral tribunal's errors were
general rule, constitute sufficient compliance with his duty to sufficient grounds to vacate or modify the award.67 It insists
return the leased premises; and (2) that any new arrangement that the RTC's misappreciation of the facts from a patently
made by the lessor with another person, such as the sub- erroneous award warranted an appeal under Rule 41.68
lessor, operates as a resumption of his possession.58
I
On the issue of damages, the CA held that TEAM can never be
liable for the damages for the repairs of the improvements on TEAM reiterates that it "disagreed with the arbitral award
the premises because they were owned by TEAM itself (through mainly on questions of fact and not only on questions of
its predecessor, Signetics) when the lease commenced. 59 law," specifically, "on factual matters relating to
specificprovisions in the contract on ownership of
The CA REVERSED AND SET ASIDE the arbitral award structures and improvements thereon, and the improper
and DISMISSED the arbitral complaint for lack of merit.60 award of rentals and penalties."69Even assuming that it
availed of the wrong mode of appeal, TEAM posits that its
This CA action prompted Fruehauf to file the present petition for appeal should still have been given due course in the interest of
review. substantial justice. 70

The Arguments TEAM assails the inconsistencies of Fruehauf’s position as to the


available legal remedies against an arbitral award.71 However, it
Fruehauf argues that courts do riot have the power to maintains that Section 29 of the Arbitration Law does not
substitute their judgment for that of the arbitrators.61 It also foreclose other legal remedies (aside from an appeal
insists that an ordinary appeal is not the proper remedy against by certiorari) against the RTC's order confirming or vacating an
an RTC's order confirming, vacating, correcting or modifying an arbitral award pursuant to Insular Savings Bank WINS) Japan
arbitral &ward but a petition for review on certiorari under Rule Co., Ltd. 72
45. 62
The Issues
Furthermore, TEAM's petition before the CA went beyond the
permissible scope of certiorari - the existence of grave abuse of This case raises the following questions:
discretion or errors jurisdiction - by including questions of fact
and law that challenged the merits of the arbitral award.63 1. What are the remedies or the modes of appeal
against an unfavorable arbitral award?
However, Fruehauf inconsistently argues that the remedies
against an arbitral award are (1) a petition to vacate the award, 2. What are the available remedies from an RTC decision
(2) a petition for review under Rule 43 raising questions of fact, confirming, vacating, modifying, or correcting an arbitral
of law, or mixed questions of fact and law, or (3) a petition award?
for certiorari under Rule 65.64 Fruehauf cites an article from the
Philippine Dispute Resolution Center65 and Insular Savings Bank 3. Did the arbitral tribunal err in awarding Fruehauf
v. Far East Bank and Trust, Co.66 damages for the repairs of the building and rental fees
from the expiration of the lease?
Our Ruling devised a judicial remedy to prevent or prohibit the
unauthorized disclosure of confidential information obtained
The petition is meritorious. therefrom. 75

Arbitration is an alternative mode of dispute resolution outside The contractual nature of arbitral proceedings affords the
of the regular court system. Although adversarial in parties I substantial autonomy over the proceedings. The
character, arbitration is technically not litigation. It is a parties are free to agree on the procedure to be
voluntary process in which one or more arbitrators - appointed observed during the proceedings. 76 This lends considerable
according to the parties' agreement or according to the flexibility to arbitration ; proceedings as compared to court I
applicable rules of the Alternative Dispute Resolution (ADR) Law litigation governed by the Rules of Court.
- resolve a dispute by rendering an award. 73 While arbitration
carries many advantages over court litigation, in :many ways The parties likewise appoint the arbitrators based on
these advantages also translate into its disadvantages. agreement. There are no other legal requirements as to the
competence or technical qualifications of an arbitrator. Their
Resort to arbitration is voluntary. It requires consent from only legal qualifications are: (1) being of legal age; (2) full-
both parties in the form of an arbitration clause that pre- enjoyment of their civil rights; and (3) the ability to read and
existed the dispute or a subsequent submission write.77 The parties can tailor-fit the tribunal's composition to
agreement. This written arbitration agreement is an the nature of their dispute. Thus, a specialized dispute can be
independent and legally enforceable contract that must be resolved by experts on the subject.
complied with in good faith. By entering into an arbitration
agreement, the parties agree to submit their dispute to an However, because arbitrators do not necessarily have a
arbitrator (ortribunal) of their own choosing and be bound by background in law, they cannot be expected to have the legal
the latter's resolution. mastery of a magistrate. There is a greater risk that an
arbitrator might misapply the law or misappreciate the facts en
However, this contractual and consensual character means that route to an erroneous decision.
the parties cannot implead a third-party in the proceedings
even if the latter's participation is necessary for a complete I
settlement of the dispute. The
This risk of error is compounded by the absence of an
tribunal does not have the power to compel a person to effective appeal mechanism. The errors of an; arbitral
participate in the arbitration proceedings without that person's tribunal are not subject to correction by the judiciary. As a
consent. It also has no authority to decide on issues that the private alternative to court proceedings, arbitration is meant
parties did not submit (or agree to submit) for its resolution. to be an end, not the beginning, of litigation. 78Thus, the
arbitral award is final and binding on the parties by reason of
As a purely private mode of dispute resolution, arbitration their contract - the arbitration agreement. 79
proceedings, including the records, the evidence, and the
arbitral award, are confidential 74 unlike court proceedings An Arbitral Tribunal does not exercise
which are generally public. This allows the parties to avoid quasi-judicial powers
negative publicity and protect their privacy. Our law highly
regards the confidentiality of arbitration proceedings that it
Quasi-judicial or administrative adjudicatory power is the We are aware of the contrary view expressed by the late Chief
power: (1) to hear and determine questions of fact to which Justice Renato Corona in ABS-CBN Broadcasting Corporation v.
legislative policy is to apply, and (2) to decide in accordance World Interactive Network Systems (WINS)Japan Co., Ltd. 87
with the standards laid down by the law itself in enforcing and
administering the same law.80Quasi-judicial power is only The ABS-CBN Case opined that a voluntary arbitrator is a
exercised by administrative agencies - legal organs of the "quasi-judicial instrumentality" of the government 88 pursuant
government. to Luzon Development Bank v. Association of Luzon
Development Bank Employees, 89 Sevilla Trading Company v.
Quasi-judicial bodies can only exercise such powers and Sernana, 90 Manila Midtown Hotel v. Borromeo, 91 and Nippon
jurisdiction as are expressly or by necessary implication Paint Employees Union-Olalia v. Court of Appeals. 92 Hence,
conferred upon them by their enabling statutes.81 Like courts, a voluntary arbitrators are included in the Rule 43 jurisdiction of
quasi-judicial body's jurisdiction over a subject matter is the Court of Appeals:
conferred by law and exists independently from the will of the
parties. As government organs necessary for an effective legal SECTION 1. Scope.-This Rule shall apply to appeals from
system, a quasi-judicial tribunal's legal existence, continues judgments or final orders of the Court of Tax Appeals and from
beyond the resolution of a specific dispute. In other words, awards, judgments, final orders or resolutions of or authorized
quasi-judicial bodies are creatures of law. by any quasi-judicial agency in the exercise of its quasi-judicial
functions. Among these agencies are the Civil Service
As a contractual and consensual: body, the arbitral tribunal Commission, Central: Board of Assessment Appeals, Securities
does not have any inherent powers over the parties. It has no and Exchange Commission, Office of the President, Land
power to issue coercive writs or compulsory processes. Thus, Registration Authority, Social Security Commission, Civil
there is a need to resort to the regular courts for interim Aeronautics Board, Bureau of Patents, Trademarks and
measures of protection 82 and for the recognition or Technology Transfer, National Electrification Administration,
enforcement of the arbitral award. 83 Energy Regulatory Board, National Telecommunications
Commission, Department of Agrarian Reform under Republic
The arbitral tribunal acquires jurisdiction over the parties and Act No. 6657, Government Service Insurance System,
the subject matter through stipulation. Upoh the rendition of Employees Compensation Commission, Agricultural Inventions
the final award, the tribunal becomes functus officio and - save Board, Insurance Commission, Philippine Atomic Energy
for a few exceptions84 - ceases to have any further jurisdiction Commission, Board of Investments, Construction Industry
over the dispute.85 The tribunal's powers (or in the case of ad Arbitration Commission, and voluntary arbitrators
hoc tribunals, their very existence) stem from the obligatory authorized by law.93 (emphasis supplied)
force of the arbitration agreement and its ancillary
stipulations.86 Simply put, an arbitral tribunal is a creature Citing Insular Savings Bank v. Far East Bank and Trust
of contract. Co., 94 the ABS-CBN Case pronounced that the losing party in
an arbitration proceeding may avail of three alternative
Deconstructing the view that arbitral remedies: (1) a petition to vacate the arbitral award before the
tribunals are quasi-judicial agencies RTC; (2) a petition for review with the CA under Rule 43 of the
Rules of Court raising questions of fact, of law, or of both; and
(3) a I petition for certiorari under Rule 65 should the arbitrator
act beyond its jurisdiction or with grave abuse of discretion. 95
At first glance, the logic of this position appears to be sound. Borromeo, and Nippon Paint Employees Union-Olalia v. Court of
However, a critical examination of the supporting authorities Appeals with the term "arbitrator/arbitration tribunal."
would show that the conclusion is wrong.
The first rule of legal construction, verba legis, requires that,
First, the pronouncements made in the ABS-CBN Case and in wherever possible, the words used in the Constitution or in the
the Insular Savings Bank Case (which served as the authority statute must be given their ordinary meaning except where
for the ABS-CBN Case) were both obiter dicta. technical terms are employed. 100Notably, all of the cases cited
in the ABS-CBN Case involved labor disputes.
In the ABS-CBN Case, we sustained the CA's dismissal of the
petition because it was filed as an "alternative petition for The term "Voluntary Arbitrator" does not refer to an
review under Rule 43 or petition for certiorari under Rule ordinary "arbitrator" who voluntarily agreed to: resolve a
65." 96 We held that it was an inappropriate mode of appeal dispute. It is a technical term with a specific definition under
because, a petition for review and a petition for certiorari are the Labor Code:
mutually exclusive and not alternative or successive.
Art. 212 Definitions. xxx
In the Insular Savings Bank case, the lis mota of the case
was the RTC's jurisdiction over an appeal from an arbitral 14. "Voluntary Arbitrator" means any' person accredited by the
award. The parties to the arbitration agreement agreed that the Board as such or any person named or designated in the
rules of the arbitration provider97 - which stipulated that the R Collective Bargaining Agreement by the parties to act as their
TC shall have jurisdiction to review arbitral awards - will govern Voluntary Arbitrator, or one chosen with or without the
the proceedings.98 The Court ultimately held that the RTC does assistance of the National Conciliation and Mediation Board,
not have jurisdiction to review the merits of the award because pursuant to a selection procedure agreed upon in the Collective
legal jurisdiction is conferred by law, not by mere agreement of Bargaining Agreement, or any official that may be authorized
the parties. by the Secretary of Labor and Employment to act as Voluntary
Arbitrator upon the written request and agreement of the
In both cases, the pronouncements as to the remedies against parties to a labor dispute. 101
an arbitral award were unnecessary for their resolution.
Therefore, these are obiter dicta - judicial comments made, in Voluntary Arbitrators resolve labor disputes and grievances
passing which are not essential to the resolution of the case arising from the interpretation of Collective Bargaining
and cannot therefore serve as precedents.99 Agreements. 102 These disputes were specifically excluded: from
the coverage of both the Arbitration Law103 and the ADR
Second, even if we disregard the obiter dicta character of both Law. 104
pronouncements, a more careful scrutiny deconstructs their
legal authority. Unlike purely commercial relationships, the relationship
between capital and labor are heavily impressed with public
The ABS-CBN Case committed the classic fallacy of interest. 105Because of this, Voluntary Arbitrators authorized to
equivocation. It equated the term "voluntary arbitrator" used resolve labor disputes have been clothed with quasi-judicial
in Rule 43, Section 1 and in the cases of Luzon Development authority.
Bank v. Association of Luzon Development Bank Employees,
Sevilla Trading Company v. Semana, Manila Midtown Hotel v.
On the other hand, commercial relationships covered by our on equal footing with the RTC and remove arbitral awards from
commercial arbitration laws are purely private and contractual the scope of RTC review.
in nature. Unlike labor relationships, they do not possess the
same compelling state interest that would justify state All things considered, there is no legal authority supporting the
interference into the autonomy of contracts. Hence, commercial position that commercial arbitrators are quasi-judicial bodies.
arbitration is a purely private system of adjudication facilitated
by private citizens instead of government instrumentalities What are remedies from a final domestic
wielding quasi-judicial powers. arbitral award?

Moreover, judicial or quasi-judicial jurisdiction cannot be The right to an appeal is neither' a natural right nor an
conferred upon a tribunal by the parties alone. The Labor Code indispensable component of due process; it is a mere statutory
itself confers subject-matter jurisdiction to Voluntary privilege that cannot be invoked in the absence of an enabling
Arbitrators. 106 statute. Neither the Arbitration Law nor the ADR Law allows a
losing party to appeal from the arbitral award. The statutory
Notably, the other arbitration body listed in Rule 43 - the absence of an appeal mechanism reflects the State's policy of
Construction Industry Arbitration Commission (CIAC) - is also a upholding the autonomy of arbitration proceedings and their
government agency107 attached to the Department of Trade and corresponding arbitral awards.
Industry. 108 Its jurisdiction is likewise conferred by
statute. 109 By contrast, the subject-matter jurisdiction of This Court recognized this when we enacted the Special Rules
commercial arbitrators is stipulated by the parties. of Court on Alternative Dispute Resolution in 2009: 112

These account for the legal differences between "ordinary" or Rule 2.1. General policies. -- It is the policy of the State to
"commercial" arbitrators under the Arbitration Law and the ADR actively promote the use of various modes of ADR and to
Law, and "voluntary arbitrators" under the Labor Code. The two respect party autonomy or the freedom of the parties to make
terms are not synonymous with each other. Interchanging them their own arrangements in the resolution of disputes with the
with one another results in the logical fallacy of equivocation - greatest cooperation of and the least intervention from the
using the same word with different meanings. courts. xxx

Further, Rule 43, Section 1 enumerates quasi-judicial tribunals The Court shall exercise the power of judicial review as
whose decisions are appealable to the CA instead of the RTC. provided by these Special ADR Rules. Courts shall intervene
But where legislation provides for an appeal from decisions of only in the cases allowed by law or these Special ADR
certain administrative bodies to the CA, it means that such Rules. 113
bodies are co-equal with the RTC in terms of rank and stature,
logically placing them beyond the control of the latter. 110
xxxx

However, arbitral tribunals and the RTC are not co-equal bodies
Rule 19.7. No appeal or certiorari on the merits of an arbitral
because the RTC is authorized to confirm or to vacate (but not
award - An agreement to refer a dispute to arbitration shall
reverse) arbitral awards. 111 If we were to deem arbitrators as
mean that the arbitral award shall be final and binding.
included in the scope of Rule 43, we would effectively place it'
Consequently, a party to an arbitration is precluded from
filing an appeal or a petition for certiorari questioning If the Regional Trial Court is asked to set aside an arbitral
the merits of an arbitral award. 114 (emphasis supplied) award in a domestic or international arbitration on any ground
other than those provided in the Special ADR Rules, the
More than a decade earlier in Asset Privatization Trust v. court shall entertain such ground for the setting aside or non-
Court of Appeals, we likewise defended the autonomy of recognition of the arbitral award only if the same amounts
arbitral awards through our policy of non-intervention on their to a violation of public policy.
substantive merits:
The court shall not set aside or vacate the award of the
As a rule, the award of an arbitrator cannot be set aside for arbitral tribunal merely on the ground that the arbitral
mere errors of judgment either as to the law or as to the facts. tribunal committed errors of fact, or of law, or of fact and
Courts are without power to amend or overrule merely law, as the court cannot substitute its judgment for that
because of disagreement with matters of law or facts of the arbitral tribunal.116
determined by the arbitrators. They will not review the
findings of law and fact contained in an award, and will not The grounds for vacating a domestic arbitral award under
undertake to substitute their judgment for that of the Section 24 of the Arbitration Law contemplate the following
arbitrators, since any other rule would make an award the scenarios:
commencement, not the end, of litigation. Errors of law and
fact, or an erroneous decision of matters submitted to the (a) when the award is procured by corruption, fraud, or
judgment of the arbitrators, are insufficient to invalidate an other undue means; or
award fairly and honestly made. Judicial review of an
arbitration is, thus, more limited than judicial review of a (b) there was evident partiality or corruption in the
trial. 115 arbitrators or any of them; or

Nonetheless, an arbitral award is not absolute. Rule 19.10 of (c) the arbitrators were guilty of misconduct that
the Special ADR Rules - by referring to Section 24 of the materially prejudiced the rights of any party; or
Arbitration Law and Article 34 of the 1985 United Nations
Commission on International Trade Law (UNCITRAL) Model Law
(d) the arbitrators exceeded their powers, or so
- recognizes the very limited exceptions to the autonomy of
imperfectly executed them, that a mutual, final and
arbitral awards:
definite award upon the subject matter submitted to
them was not made. 117
Rule 19.10. Rule on judicial review on arbitration in the
Philippines. - As a general rule, the court can only vacate or
The award may also be vacated if an arbitrator who was
set aside the decision of an arbitral tribunal upon a clear
disqualified to act willfully refrained from disclosing his
showing' that the award suffers from any of the infirmities or
disqualification to the parties. 118 Notably, none of these
grounds for vacating an arbitral award under Section 24 of
grounds pertain to the correctness of the award but relate to
Republic Act No. 876 or under Rule 34 of the Model Law
the misconduct of arbitrators.
in a domestic arbitration, or for setting aside an award in an
international arbitration under Article 34 of the Model Law, or
for such other grounds provided under these Special Rules. The RTC may also set aside the arbitral award based on Article
34 of the UNCITRAL Model Law. These grounds are reproduced
in Chapter 4 of the Implementing Rules and Regulations (IRR) (bb) the award is in conflict with the public
of the 2004 ADR Act: policy of the Philippines. 119

(i) the party making the application furnishes proof that: Chapter 4 of the IRR of the, ADR Act applies particularly to
International Commercial Arbitration. However, the
(aa) a party to the arbitration agreement was abovementioned grounds taken from the UNCITRAL, Model Law
under some incapacity; or the said agreement is are specifically made applicable to domestic arbitration by the
not valid under the law to which the parties have Special ADR Rules. 120
subjected it or, failing any indication thereon,
under the law of the Philippines; or Notably, these grounds are not concerned with the correctness
of the award; they go into the validity of the arbitration
(bb) the party making the application was not agreement or the regularity of the arbitration proceedings.
given proper notice of the appointment of an
arbitrator or of the arbitral proceedings or was These grounds for vacating an arbitral award are exclusive.
otherwise unable to present his case; or Under the ADR Law, courts are obliged to disregard any other
grounds invoked to set aside an award:
(cc) the award deals with a dispute not
contemplated by or not falling within the terms of SEC. 41. Vacation Award. - A party to a domestic arbitration
the submission to arbitration, or contains may question the arbitral award with the appropriate regional
decisions on matters beyond the scope of the trial court in accordance with the rules of procedure to be
submission to arbitration, provided that, if the promulgated by the Supreme Court only on those grounds
decisions on matters submitted to arbitration can enumerated in Section 25 of Republic Act No. 876. Any other
be separated from those not so submitted, only ground raised against a domestic arbitral award shall be
the part of the award which contains decisions on disregarded by the regional trial court. 121
matters not submitted to arbitration may be set
aside; or Consequently, the winning party can generally expect the
enforcement of the award. This is a stricter rule that makes
(dd) the composition of the arbitral tribunal or Article 2044122 of the Civil Code regarding the finality of an
the arbitral procedure was not in accordance with arbitral award redundant.
the agreement of the parties, unless such
agreement was in conflict with a provision of ADR As established earlier, an arbitral: award is not appealable via
Act from which the parties cannot derogate, or, Rule 43 because: (1) there is no statutory basis for an appeal
failing such agreement, was not in accordance from the final award of arbitrators; (2) arbitrators are not
with ADR Act; or quasi-judicial bodies; and (3) the Special ADR Rules specifically
prohibit the filing of an appeal to question the merits of an
(ii) The Court finds that: arbitral award.

(aa) the subject-matter of the dispute is not The Special ADR Rules allow, the RTC to correct or modify an
capable of settlement by arbitration under arbitral award pursuant to Section 25 of the Arbitration Law.
the law of the Philippines; or However, this authority cannot be interpreted as jurisdiction to
review the merits of the award. The RTC can modify or correct Rule 22.1. Applicability of Rules of Court. - The provisions of
the award only in the following cases: the Rules of Court that are applicable to the proceedings
enumerated in Rule 1.1 of these Special ADR Rules have either
a. Where there was an evident miscalculation of figures been included and incorporated in these Special ADR
or an evident mistake in the description of any person, Rules or specifically referred to herein.
thing or property referred to in the award;
In Connection with the above proceedings, the Rules of
b. Where the arbitrators have awarded upon a matter Evidence shall be liberally construed to achieve the objectives
not submitted to them, not affecting the merits of the of the Special ADR Rules. 127
decision upon the matter submitted;
Contrary to TEAM's position, the Special ADR Rules actually
c. Where the arbitrators have omitted to resolve an forecloses against other remedies outside of itself. Thus, a
issue submitted to them for resolution; or losing party cannot assail an arbitral award through; a petition
for review under Rule 43 or a petition for certiorari under Rule
d. Where the award is imperfect in a matter of form not 65 because these remedies are not specifically permitted in the
affecting the merits of the controversy, and if it had Special ADR Rules.
been a commissioner's report, the defect could have
been amended or disregarded by the Court. 123 In sum, the only remedy against; a final domestic arbitral
award is to file petition to vacate or to modify/correct the award
A losing party is likewise precluded from resorting not later than thirty (30) days from the receipt of the
to certiorari under Rule 65 of the Rules of Court. 124 Certiorari is award. 128 Unless a ground to vacate has been established, the
a prerogative writ designed to correct errors of jurisdiction RTC must confirm the arbitral award as a matter of course.
committed by a judicial or quasi-judicial body. 125 Because an
arbitral tribunal is not a government organ exercising judicial The remedies against an order
or quasi-judicial powers, it is removed from the ambit of Rule Confirming, vacating, correcting, or
65. modifying an arbitral award

Not even the Court's expanded certiorari jurisdiction under the Once the RTC orders the confirmation, vacation, or
Constitution 126 can justify judicial intrusion into the merits of correction/modification of a domestic arbitral award, the
arbitral awards. While the Constitution expanded the scope aggrieved party may move for reconsideration within a non-
of certiorari proceedings, this power remains limited to a extendible period of fifteen (15) days from receipt of the
review' of the acts of "any branch or instrumentality of the order. 129 The losing party may also opt to appeal from the
Government." As a purely private creature of contract, an RTC's ruling instead.
arbitral tribunal remains outside the scope of certiorari.
Under the Arbitration Law, the mode of appeal was via petition
Lastly, the Special ADR Rules are a self-contained body of rules. for review on certiorari:
The parties cannot invoke remedies and other provisions from
the Rules of Court unless they were incorporated in the Special Section 29. Appeals. - An appeal may be taken from an order
ADR Rules: made in a proceeding under this Act, or from a judgment
entered upon an award through certiorari proceedings, but
such appeals shall be limited to questions of law. The We have deliberately refrained from passing upon the merits of
proceedings upon such appeal, including the judgment thereon the arbitral award - not because the award was erroneous - but
shall be governed by, the Rules of Court in so far as they are because it would be improper. None of the grounds to vacate
applicable.130 an arbitral award are present in this case and as already
established, the merits of the award cannot be reviewed by the
The Arbitration Law did not specify which Court had jurisdiction courts.
to entertain the appeal but left the matter to be governed by
the Rules of Court. As the appeal was limited to questions of Our refusal to review the award is not a simple matter of
law and was described as "certiorari proceedings," the mode of putting procedural technicalities over the substantive merits of
appeal can be interpreted as an Appeal By Certiorari to this a case; it goes into the very legal substance of the issues.
Court under Rule 45. There is no law granting the judiciary authority to review the
merits of an arbitral award. If we were to insist on reviewing
When the ADR Law was enacted in 2004, it specified that the correctness of the award: (or consent to the CA's doing
the appeal shall be made to the CA in accordance with the rules so), it would be tantamount to expanding our jurisdiction
of procedure to be promulgated by this Court. 131 The Special without the benefit of legislation. This translates to judicial
ADR Rules provided that the mode of appeal from the RTC's legislation - a breach of the fundamental principle of separation
order confirming, vacating, or correcting/modifying a domestic of powers.
arbitral award was through a petition for review with the
CA. 132 However, the Special ADR Rules only took effect on The CA reversed the arbitral award - an action that it has no
October 30, 2009. power to do - because it disagreed with the tribunal's factual
findings and application of the law. However, the alleged
In the present case, the R TC disallowed TEAM' s notice of incorrectness of the award is insufficient cause to vacate the
appeal from the former's decision confirming the arbitral award award, given the State's policy of upholding the autonomy of
on July 3, 2009. TEAM moved for reconsideration which was arbitral awards.
likewise denied on November 15, 2009. In the interim, the
Special ADR Rules became effective. Notably, the Special ADR The CA passed upon questions such as: (1) whether or not
Rules apply retroactively in light of its procedural TEAM effectively returned the property upon the expiration of
character. 133 TEAM filed its petition for certiorari soon after. the lease; (2) whether or not TEAM was liable to pay rentals
after the expiration of the lease; and (3) whether or not TEAM
Nevertheless, whether we apply, Section 29 of the Arbitration was liable to pay Fruehauf damages corresponding to the cost
Law, Section 46 of the ADR Law, or Rule 19.12 of the Special of repairs. These were the same questions that were specifically
ADR Rules, there is no legal basis that an ordinary appeal (via submitted to the arbitral tribunal for its resolution. 134
notice of appeal) is the correct remedy from an order
confirming, vacating, or correcting an arbitral award. Thus, The CA disagreed with the tribunal's factual determinations and
there is no merit in the CA's ruling that the RTC gravely abused legal interpretation of TEAM's obligations under the contract -
its discretion when it refused to give due course to the notice of particularly, that TEAM's obligation to turn over the
appeal. improvements on the land at the end of the lease in the same
condition as when the lease commenced translated to an
The correctness or incorrectness obligation to make ordinary repairs necessary for its
of the arbitral award preservation. 135
Assuming arguendo that the tribunal's interpretation of the If the Regional Trial Court is asked to set aside an arbitral
contract was incorrect, the errors would have been simple award in a domestic or international arbitration on any ground
errors of law.1âwphi1 It was the tribunal - not the RTC or the other than those provided in the Special ADR Rules, the court
CA - that had jurisdiction and authority over the issue by virtue shall entertain such ground for the setting aside or non-
of the parties' submissions; the CA's substitution of its own recognition of the arbitral award only if thesame amounts to
judgment for the arbitral award cannot be more compelling a violation of public policy.
than the overriding public policy to uphold the autonomy of
arbitral awards. Courts are precluded from disturbing an The court shall not set aside or vacate the award of the
arbitral tribunal's factual findings and interpretations of arbitral tribunal merely on the ground that the arbitral
law. 136 The CA's ruling is an unjustified judicial intrusion in tribunal committed errors of fact, or of law, or of fact and
excess of its jurisdiction - a judicial overreach. 137 law, as the court cannot substitute its judgment for that
of the arbitral tribunal.
Upholding the CA's ruling would weaken our alternative dispute
resolution mechanisms by allowing the courts to "throw their In other words, simple errors of fact, of law, or of fact and law
weight around" whenever they disagree with the results. committed by the arbitral tribunal are not justiciable errors in
It erodes the obligatory force of arbitration agreements by this jurisdiction. 139
allowing the losing parties to "forum shop" for a more favorable
ruling from the judiciary. TEAM agreed to submit their disputes to an arbitral tribunal. It
understood all the risks - including the absence of an appeal
Whether or not the arbitral tribunal correctly passed upon the mechanism - and found that its benefits (both legal and
issues is irrelevant. Regardless of the amount, of the sum economic) outweighed the disadvantages. Without a showing
involved in a case, a simple error of law remains a simple error that any of the grounds to vacate the award exists or that the
of law. Courts are precluded from revising the award in a same amounts to a violation of an overriding public policy, the
particular way, revisiting the tribunal's findings of fact or award is subject to confirmation as a matter of course. 140
conclusions of law, or otherwise encroaching upon the
independence of an arbitral tribunal. 138At the risk of WHEREFORE, we GRANT the petition. The CA's decision
redundancy, we emphasize Rule 19.10 of the Special ADR Rules in CA-G. R. SP. No. 112384 is SET ASIDE and the RTC's
promulgated by this Court en banc: order CONFIRMING the arbitral award in SP. Proc. No.
11449 is REINSTATED.
Rule 19.10. Rule on judicial review on arbitration in the
Philippines. - As a general rule, the court can only vacate or SO ORDERED.
set aside the decision of an arbitral tribunal upon a clear
showing that the award suffers from any of the
infirmities or grounds for vacating an arbitral award
under Section 24 of Republic Act No. 876 or under Rule
34 of the Model Law in a domestic arbitration, or for
setting aside an award in an international arbitration under
Article 34 of the Model Law, or for such other grounds provided
under these Special Rules.
enforceable, and irrevocable parties’ decision to submit their
controversies, including incidental issues, to arbitration.

Same; Same; In view of our policy to adopt arbitration as a


manner of settling disputes, arbitration clauses are liberally
construed to favor arbitration.—In view of our policy to adopt
arbitration as a manner of settling disputes, arbitration clauses
are liberally construed to favor arbitration. Thus, in LM Power
Engineering Corporation v. Capitol Industrial Construction
Groups, Inc., 399 SCRA 562 (2003), this court said: Being an
inexpensive, speedy and amicable method of settling disputes,
arbitration — along with mediation, conciliation and negotiation
— is encouraged by the Supreme Court. Aside from unclogging
judicial dockets, arbitration also hastens the resolution of
disputes, especially of the commercial kind. It is thus regarded
as the “wave of the future” in international civil and commercial
disputes. Brushing aside a contractual agreement calling for
arbitration between the parties would be a step backward.
Consistent with the above mentioned policy of encouraging
alternative dispute resolution methods, courts should liberally
construe arbitration clauses. Provided such clause is susceptible
G.R. No. 174938 October 1, 2014 of an interpretation that covers the asserted dispute, an order
to arbitrate should be granted. Any doubt should be resolved in
favor of arbitration.
GERARDO LANUZA, JR. AND ANTONIO O.
OLBES, Petitioners,
vs. Same; Same; If there is an interpretation that would render
BF CORPORATION, SHANGRI-LA PROPERTIES, INC., effective an arbitration clause for purposes of avoiding litigation
ALFREDO C. RAMOS, RUFO B. COLAYCO, MAXIMO G. and expediting resolution of the dispute, that interpretation
LICAUCO III, AND BENJAMIN C. RAMOS, Respondents. shall be adopted.—If there is an interpretation that would
render effective an arbitration clause for purposes of avoiding
litigation and expediting resolution of the dispute, that
Civil Law; Arbitration; Arbitration allows the parties to avoid
interpretation shall be adopted. Petitioners’ main argument
litigation and settle disputes amicably and more expeditiously
arises from the separate personality given to juridical persons
by themselves and through their choice of arbitrators.—This
vis-à-vis their directors, officers, stockholders, and agents.
jurisdiction adopts a policy in favor of arbitration. Arbitration
Since they did not sign the arbitration agreement in any
allows the parties to avoid litigation and settle disputes
capacity, they cannot be forced to submit to the jurisdiction of
amicably and more expeditiously by themselves and through
the Arbitration Tribunal in accordance with the arbitration
their choice of arbitrators. The policy in favor of arbitration has
agreement. Moreover, they had already resigned as directors of
been affirmed in our Civil Code, which was approved as early as
Shangri-La at the time of the alleged default.
1949. It was later institutionalized by the approval of Republic
Act No. 876, which expressly authorized, made valid,
Corporations; Separate Legal Personality; A corporation, in the therefore, a corporation’s representative who did not personally
legal sense, is an individual with a personality that is distinct bind himself or herself to an arbitration agreement cannot be
and separate from other persons including its stockholders, forced to participate in arbitration proceedings made pursuant
officers, directors, representatives, and other juridical to an agreement entered into by the corporation. He or she is
entities.—A corporation is an artificial entity created by fiction generally not considered a party to that agreement. However,
of law. This means that while it is not a person, naturally, the there are instances when the distinction between personalities
law gives it a distinct personality and treats it as such. A of directors, officers, and representatives, and of the
corporation, in the legal sense, is an individual with a corporation, are disregarded. We call this piercing the veil of
personality that is distinct and separate from other persons corporate fiction.
including its stockholders, officers, directors, representatives,
and other juridical entities. The law vests in corporations rights, Same; Same; Piercing the Veil of Corporate Fiction; Piercing the
powers, and attributes as if they were natural persons with corporate veil is warranted when “[the separate personality of a
physical existence and capabilities to act on their own. For corporation] is used as a means to perpetrate fraud or an illegal
instance, they have the power to sue and enter into act, or as a vehicle for the evasion of an existing obligation, the
transactions or contracts. circumvention of statutes, or to confuse legitimate issues.”—
Piercing the corporate veil is warranted when “[the separate
Same; Same; A corporation’s representatives are generally not personality of a corporation] is used as a means to perpetrate
bound by the terms of the contract executed by the fraud or an illegal act, or as a vehicle for the evasion of an
corporation. They are not personally liable for obligations and existing obligation, the circumvention of statutes, or to confuse
liabilities incurred on or in behalf of the corporation.—Because a legitimate issues.” It is also warranted in alter ego cases
corporation’s existence is only by fiction of law, it can only “where a corporation is merely a farce since it is a mere alter
exercise its rights and powers through its directors, officers, or ego or business conduit of a person, or where the corporation is
agents, who are all natural persons. A corporation cannot sue so organized and controlled and its affairs are so conducted as
or enter into contracts without them. A consequence of a to make it merely an instrumentality, agency, conduit or
corporation’s separate personality is that consent by a adjunct of another corporation.” When corporate veil is pierced,
corporation through its representatives is not consent of the the corporation and persons who are normally treated as
representative, personally. Its obligations, incurred through distinct from the corporation are treated as one person, such
official acts of its representatives, are its own. A stockholder, that when the corporation is adjudged liable, these persons,
director, or representative does not become a party to a too, become liable as if they were the corporation. Among the
contract just because a corporation executed a contract through persons who may be treated as the corporation itself under
that stockholder, director or representative. Hence, a certain circumstances are its directors and officers.
corporation’s representatives are generally not bound by the
terms of the contract executed by the corporation. They are not Same; Same; Same; Section 31 of the Corporation Code
personally liable for obligations and liabilities incurred on or in provides the instances when directors, trustees, or officers may
behalf of the corporation. become liable for corporate acts.—Section 31 of the Corporation
Code provides the instances when directors, trustees, or
Same; Same; Arbitration; As a general rule, therefore, a officers may become liable for corporate acts: Sec. 31. Liability
corporation’s representative who did not personally bind himself of directors, trustees or officers.—Directors or trustees who
or herself to an arbitration agreement cannot be forced to willfully and knowingly vote for or assent to patently unlawful
participate in arbitration proceedings made pursuant to an acts of the corporation or who are guilty of gross negligence or
agreement entered into by the corporation.—As a general rule, bad faith in directing the affairs of the corporation or acquire
any personal or pecuniary interest in conflict with their duty as there are allegations of bad faith or malice against corporate
such directors or trustees shall be liable jointly and severally for directors or representatives, it becomes the duty of courts or
all damages resulting therefrom suffered by the corporation, its tribunals to determine if these persons and the corporation
stockholders or members and other persons. When a director, should be treated as one. Without a trial, courts and tribunals
trustee or officer attempts to acquire or acquires, in violation of have no basis for determining whether the veil of corporate
his duty, any interest adverse to the corporation in respect of fiction should be pierced. Courts or tribunals do not have such
any matter which has been reposed in him in confidence, as to prior knowledge. Thus, the courts or tribunals must first
which equity imposes a disability upon him to deal in his own determine whether circumstances exist to warrant the courts or
behalf, he shall be liable as a trustee for the corporation and tribunals to disregard the distinction between the corporation
must account for the profits which otherwise would have and the persons representing it. The determination of these
accrued to the corporation. (n) circumstances must be made by one tribunal or court in a
proceeding participated in by all parties involved, including
Same; Same; Same; Cases When a Director, Trustee, or Officer current representatives of the corporation, and those persons
of a Corporation May Be Made Solidarily Liable With it for All whose personalities are impliedly the same as the corporation.
Damages Suffered by the Corporation, its Stockholders or This is because when the court or tribunal finds that
Members, and Other Persons.—A director, trustee, or officer of circumstances exist warranting the piercing of the corporate
a corporation may be made solidarily liable with it for all veil, the corporate representatives are treated as the
damages suffered by the corporation, its stockholders or corporation itself and should be held liable for corporate acts.
members, and other persons in any of the following cases: a) The corporation’s distinct personality is disregarded, and the
The director or trustee willfully and knowingly voted for or corporation is seen as a mere aggregation of persons
assented to a patently unlawful corporate act; b) The director undertaking a business under the collective name of the
or trustee was guilty of gross negligence or bad faith in corporation.
directing corporate affairs; and c) The director or trustee
acquired personal or pecuniary interest in conflict with his or Remedial Law; Civil Procedure; Actions; Splitting Single Cause
her duties as director or trustee. Solidary liability with the of Action; Dismissal of Actions; Institution of more than one
corporation will also attach in the following instances: a) “When suit for the same cause of action constitutes splitting the cause
a director or officer has consented to the issuance of watered of action, which is a ground for the dismissal of the others.—
stocks or who, having knowledge thereof, did not forthwith file Under the Rules of Court, filing of multiple suits for a single
with the corporate secretary his written objection thereto”; b) cause of action is prohibited. Institution of more than one suit
“When a director, trustee or officer has contractually agreed or for the same cause of action constitutes splitting the cause of
stipulated to hold himself personally and solidarily liable with action, which is a ground for the dismissal of the others. Thus,
the corporation”; and c) “When a director, trustee or officer is in Rule 2: Section 3. One suit for a single cause of action.—A
made, by specific provision of law, personally liable for his party may not institute more than one suit for a single cause of
corporate action.” action. (3a) Section 4. Splitting a single cause of action; effect
of.—If two or more suits are instituted on the basis of the same
Same; Same; Same; When there are allegations of bad faith or cause of action, the filing of one or a judgment upon the merits
malice against corporate directors or representatives, it in any one is available as a ground for the dismissal of the
becomes the duty of courts or tribunals to determine if these others.
persons and the corporation should be treated as one. Without
a trial, courts and tribunals have no basis for determining Civil Law; Arbitration; Parties; Only parties to an arbitration
whether the veil of corporate fiction should be pierced.—When agreement may be compelled to submit to arbitration;
Assignees and heirs may be considered parties to an arbitration be made to participate in the arbitration proceedings in order to
agreement entered into by their assignor because the determine if such distinction should indeed be disregarded and,
assignor’s rights and obligations are transferred to them upon if so, to determine the extent of their liabilities.
assignment.—In ruling that petitioners may be compelled to
submit to the arbitration proceedings, we are not overturning DECISION
Heirs of Augusto Salas, Jr. v. Laperal Realty Corporation, 320
SCRA 610 (1999), wherein this court affirmed the basic LEONEN, J.:
arbitration principle that only parties to an arbitration
agreement may be compelled to submit to arbitration. In that
Corporate representatives may be compelled to submit to
case, this court recognized that persons other than the main
arbitration proceedings pursuant to a contract entered into by
party may be compelled to submit to arbitration, e.g.,
the corporation they represent if there are allegations of bad
assignees and heirs. Assignees and heirs may be considered
faith or malice in their acts representing the corporation.
parties to an arbitration agreement entered into by their
assignor because the assignor’s rights and obligations are
transferred to them upon assignment. In other words, the This is a Rule 45 petition, assailing the Court of Appeals' May
assignor’s rights and obligations become their own rights and 11, 2006 decision and October 5, 2006 resolution. The Court of
obligations. In the same way, the corporation’s obligations are Appeals affirmed the trial court's decision holding that
treated as the representative’s obligations when the corporate petitioners, as director, should submit themselves as parties
veil is pierced. tothe arbitration proceedings between BF Corporation and
Shangri-La Properties, Inc. (Shangri-La).
Same; Same; Same; Solidary Liability; In cases alleging
solidary liability with the corporation or praying for the piercing In 1993, BF Corporation filed a collection complaint with the
of the corporate veil, parties who are normally treated as Regional Trial Court against Shangri-Laand the members of its
distinct individuals should be made to participate in the board of directors: Alfredo C. Ramos, Rufo B.Colayco, Antonio
arbitration proceedings in order to determine if such distinction O. Olbes, Gerardo Lanuza, Jr., Maximo G. Licauco III, and
should indeed be disregarded and, if so, to determine the Benjamin C. Ramos.1
extent of their liabilities.—When the courts disregard the
corporation’s distinct and separate personality from its directors BF Corporation alleged in its complaint that on December 11,
or officers, the courts do not say that the corporation, in all 1989 and May 30, 1991, it entered into agreements with
instances and for all purposes, is the same as its directors, Shangri-La wherein it undertook to construct for Shangri-La a
stockholders, officers, and agents. It does not result in an mall and a multilevel parking structure along EDSA.2
absolute confusion of personalities of the corporation and the
persons composing or representing it. Courts merely discount Shangri-La had been consistent in paying BF Corporation in
the distinction and treat them as one, in relation to a specific accordance with its progress billing statements.3 However, by
act, in order to extend the terms of the contract and the October 1991, Shangri-La started defaulting in payment.4
liabilities for all damages to erring corporate officials who
participated in the corporation’s illegal acts. This is done so that BF Corporation alleged that Shangri-La induced BF Corporation
the legal fiction cannot be used to perpetrate illegalities and to continue with the construction of the buildings using its own
injustices. Thus, in cases alleging solidary liability with the funds and credit despite Shangri-La’s default.5 According to BF
corporation or praying for the piercing of the corporate veil, Corporation, ShangriLa misrepresented that it had funds to pay
parties who are normally treated as distinct individuals should for its obligations with BF Corporation, and the delay in
payment was simply a matter of delayed processing of BF in accordance with the rules and procedures of the Philippine
Corporation’s progress billing statements. 6 Arbitration Law.

BF Corporation eventually completed the construction of the xxx xxx xxx


buildings.7 Shangri-La allegedly took possession of the buildings
while still owing BF Corporation an outstanding balance.8 (6) The award of such Arbitrators shall be final and binding on
the parties. The decision of the Arbitrators shall be a condition
BF Corporation alleged that despite repeated demands, precedent to any right of legal action that either party may
Shangri-La refused to pay the balance owed to it.9 It also have against the other. . . .12 (Underscoring in the original)
alleged that the Shangri-La’s directors were in bad faith in
directing Shangri-La’s affairs. Therefore, they should be held On August 19, 1993, BF Corporation opposed the motion to
jointly and severally liable with Shangri-La for its obligations as suspend proceedings.13
well as for the damages that BF Corporation incurred as a result
of Shangri-La’s default.10 In the November 18, 1993 order, the Regional Trial Court
denied the motion to suspend proceedings.14
On August 3, 1993, Shangri-La, Alfredo C. Ramos, Rufo B.
Colayco, Maximo G. Licauco III, and Benjamin C. Ramos filed a On December 8, 1993, petitioners filed an answer to BF
motion to suspend the proceedings in view of BF Corporation’s Corporation’s complaint, with compulsory counter claim against
failure to submit its dispute to arbitration, in accordance with BF Corporation and crossclaim against Shangri-La.15 They
the arbitration clauseprovided in its contract, quoted in the alleged that they had resigned as members of Shangri-La’s
motion as follows:11 board of directors as of July 15, 1991.16

35. Arbitration After the Regional Trial Court denied on February 11, 1994 the
motion for reconsideration of its November 18, 1993 order,
(1) Provided always that in case any dispute or difference shall Shangri-La, Alfredo C. Ramos, Rufo B. Colayco,Maximo G.
arise between the Owner or the Project Manager on his behalf Licauco III, and Benjamin Ramos filed a petition for certiorari
and the Contractor, either during the progress or after the with the Court of Appeals.17
completion or abandonment of the Works as to the construction
of this Contract or as to any matter or thing of whatsoever On April 28, 1995, the Court of Appeals granted the petition for
nature arising there under or inconnection therewith (including certiorari and ordered the submission of the dispute to
any matter or thing left by this Contract to the discretion of the arbitration.18
Project Manager or the withholding by the Project Manager of
any certificate to which the Contractor may claim to be entitled
Aggrieved by the Court of Appeals’ decision, BF Corporation
or the measurement and valuation mentioned in clause
filed a petition for review on certiorari with this court.19 On
30(5)(a) of these Conditions or the rights and liabilities of the
March 27, 1998, this court affirmed the Court of Appeals’
parties under clauses 25, 26, 32 or 33 of these Conditions), the
decision, directing that the dispute be submitted for
owner and the Contractor hereby agree to exert all efforts to
arbitration.20
settle their differences or dispute amicably. Failing these efforts
then such dispute or difference shall be referred to arbitration
Another issue arose after BF Corporation had initiated
arbitration proceedings. BF Corporation and Shangri-La failed to
agree as to the law that should govern the arbitration as directors of the defendant corporation, [they], in accordance
proceedings.21 On October 27, 1998, the trial court issued the with Art. 1217 of the Civil Code, stand to be benefited or
order directing the parties to conduct the proceedings in injured by the result of the arbitration proceedings, hence,
accordance with Republic Act No. 876.22 being necessary parties, they must be joined in order to have
complete adjudication of the controversy. Consequently, if
Shangri-La filed an omnibus motion and BF Corporation an [they were] excluded as parties in the arbitration proceedings
urgent motion for clarification, both seeking to clarify the term, and an arbitral award is rendered, holding [Shangri-La] and its
"parties," and whether Shangri-La’s directors should be board of directors jointly and solidarily liable to private
included in the arbitration proceedings and served with respondent BF Corporation, a problem will arise, i.e., whether
separate demands for arbitration.23 petitioners will be bound bysuch arbitral award, and this will
prevent complete determination of the issues and resolution of
Petitioners filed their comment on Shangri-La’s and BF the controversy.31
Corporation’s motions, praying that they be excluded from the
arbitration proceedings for being non-parties to Shangri-La’s The Court of Appeals further ruled that "excluding petitioners in
and BF Corporation’s agreement.24 the arbitration proceedings . . . would be contrary to the policy
against multiplicity of suits."32
On July 28, 2003, the trial court issued the order directing
service of demands for arbitration upon all defendants in BF The dispositive portion of the Court of Appeals’ decision reads:
Corporation’s complaint.25 According to the trial court, Shangri-
La’s directors were interested parties who "must also be served WHEREFORE, the petition is DISMISSED. The assailed orders
with a demand for arbitration to give them the opportunity to dated July 28, 2003 and January 19, 2005 of public respondent
ventilate their side of the controversy, safeguard their interest RTC, Branch 157, Pasig City, in Civil Case No. 63400, are
and fend off their respective positions."26 Petitioners’ motion for AFFIRMED.33
reconsideration ofthis order was denied by the trial court on
January 19, 2005.27 The Court of Appeals denied petitioners’ motion for
reconsideration in the October 5, 2006 resolution.34
Petitioners filed a petition for certiorari with the Court of
Appeals, alleging grave abuse of discretion in the issuance of On November 24, 2006, petitioners filed a petition for review of
orders compelling them to submit to arbitration proceedings the May 11, 2006 Court of Appeals decision and the October 5,
despite being third parties to the contract between Shangri-La 2006 Court of Appeals resolution.35
and BF Corporation.28
The issue in this case is whether petitioners should be made
In its May 11, 2006 decision,29 the Court of Appeals dismissed parties to the arbitration proceedings, pursuant to the
petitioners’ petition for certiorari. The Court of Appeals ruled arbitration clause provided in the contract between BF
that ShangriLa’s directors were necessary parties in the Corporation and Shangri-La.
arbitration proceedings.30 According to the Court of Appeals:
Petitioners argue that they cannot be held personally liable for
[They were] deemed not third-parties tothe contract as they corporate acts or obligations.36 The corporation is a separate
[were] sued for their acts in representation of the party to the being, and nothing justifies BF Corporation’s allegation that
contract pursuant to Art. 31 of the Corporation Code, and that they are solidarily liable with Shangri-La.37 Neither did they
bind themselves personally nor did they undertake to shoulder agreement because they are being sued as Shangri-La’s
Shangri-La’s obligations should it fail in its obligations.38 BF representatives, under Section 31 of the Corporation Code.52
Corporation also failed to establish fraud or bad faith on their
part.39 BF Corporation further argued that because petitioners were
impleaded for their solidary liability, they are necessary parties
Petitioners also argue that they are third parties to the contract to the arbitration proceedings.53 The full resolution of all
between BF Corporation and Shangri-La.40 Provisions including disputes in the arbitration proceedings should also be done in
arbitration stipulations should bind only the parties.41 Based on the interest of justice.54
our arbitration laws, parties who are strangers to an agreement
cannot be compelled to arbitrate.42 In the manifestation dated September 6, 2007, petitioners
informed the court that the Arbitral Tribunal had already
Petitioners point out thatour arbitration laws were enacted to promulgated its decision on July 31, 2007.55 The Arbitral
promote the autonomy of parties in resolving their Tribunal denied BF Corporation’s claims against
disputes.43 Compelling them to submit to arbitration is against them.56 Petitioners stated that "[they] were included by the
this purpose and may be tantamount to stipulating for the Arbitral Tribunal in the proceedings conducted . . .
parties.44 notwithstanding [their] continuing objection thereto. . .
."57 They also stated that "[their] unwilling participation in the
Separate comments on the petition werefiled by BF arbitration case was done ex abundante ad cautela, as
Corporation, and Maximo G. Licauco III, Alfredo C.Ramos and manifested therein on several occasions."58 Petitioners informed
Benjamin C. Ramos.45 the court that they already manifested with the trial court that
"any action taken on [the Arbitral Tribunal’s decision] should be
Maximo G. Licauco III Alfredo C. Ramos, and Benjamin C. without prejudice to the resolution of [this] case." 59
Ramos agreed with petitioners that Shangri-La’sdirectors, being
non-parties to the contract, should not be made personally Upon the court’s order, petitioners and Shangri-La filed their
liable for Shangri-La’s acts.46 Since the contract was executed respective memoranda. Petitioners and Maximo G. Licauco III,
only by BF Corporation and Shangri-La, only they should be Alfredo C. Ramos, and Benjamin C. Ramos reiterated their
affected by the contract’s stipulation.47 BF Corporation also arguments that they should not be held liable for Shangri-La’s
failed to specifically allege the unlawful acts of the directors default and made parties to the arbitration proceedings because
that should make them solidarily liable with Shangri-La for its only BF Corporation and Shangri-La were parties to the
obligations.48 contract.

Meanwhile, in its comment, BF Corporation argued that the In its memorandum, Shangri-La argued that petitioners were
courts’ ruling that the parties should undergo arbitration impleaded for their solidary liability under Section 31 of the
"clearly contemplated the inclusion of the directors of the Corporation Code. Shangri-La added that their exclusion from
corporation[.]"49 BF Corporation also argued that while the arbitration proceedings will result in multiplicity of suits,
petitioners were not parties to the agreement, they were still which "is not favored in this jurisdiction."60 It pointed out that
impleaded under Section 31 of the Corporation Code.50 Section the case had already been mooted by the termination of the
31 makes directors solidarily liable for fraud, gross negligence, arbitration proceedings, which petitioners actively participated
and bad faith.51 Petitioners are not really third parties to the in.61 Moreover, BF Corporation assailed only the correctness of
the Arbitral Tribunal’s award and not the part absolving Thus, we rule that petitioners may be compelled to submit to
Shangri-La’s directors from liability.62 the arbitration proceedings in accordance with Shangri-Laand
BF Corporation’s agreement, in order to determine if the
BF Corporation filed a counter-manifestation with motion to distinction between Shangri-La’s personality and their
dismiss63 in lieu of the required memorandum. personalities should be disregarded.

In its counter-manifestation, BF Corporation pointed out that This jurisdiction adopts a policy in favor of arbitration.
since "petitioners’ counterclaims were already dismissed with Arbitration allows the parties to avoid litigation and settle
finality, and the claims against them were likewise dismissed disputes amicably and more expeditiously by themselves and
with finality, they no longer have any interest orpersonality in through their choice of arbitrators.
the arbitration case. Thus, there is no longer any need to
resolve the present Petition, which mainly questions the The policy in favor of arbitration has been affirmed in our Civil
inclusion of petitioners in the arbitration proceedings."64 The Code,69 which was approved as early as 1949. It was later
court’s decision in this case will no longer have any effect on institutionalized by the approval of Republic Act No.
the issue of petitioners’ inclusion in the arbitration 876,70 which expressly authorized, made valid, enforceable, and
proceedings.65 irrevocable parties’ decision to submit their controversies,
including incidental issues, to arbitration. This court recognized
The petition must fail. this policy in Eastboard Navigation, Ltd. v. Ysmael and
Company, Inc.:71
The Arbitral Tribunal’s decision, absolving petitioners from
liability, and its binding effect on BF Corporation, have rendered As a corollary to the question regarding the existence of an
this case moot and academic. arbitration agreement, defendant raises the issue that, even if
it be granted that it agreed to submit its dispute with plaintiff to
The mootness of the case, however, had not precluded us from arbitration, said agreement is void and without effect for it
resolving issues so that principles may be established for the amounts to removing said dispute from the jurisdiction of the
guidance of the bench, bar, and the public. In De la Camara v. courts in which the parties are domiciled or where the dispute
Hon. Enage,66 this court disregarded the fact that petitioner in occurred. It is true that there are authorities which hold that "a
that case already escaped from prison and ruled on the issue of clause in a contract providing that all matters in dispute
excessive bails: between the parties shall be referred to arbitrators and to them
alone, is contrary to public policy and cannot oust the courts of
jurisdiction" (Manila Electric Co. vs. Pasay Transportation Co.,
While under the circumstances a ruling on the merits of the
57 Phil., 600, 603), however, there are authorities which favor
petition for certiorari is notwarranted, still, as set forth at the
"the more intelligent view that arbitration, as an inexpensive,
opening of this opinion, the fact that this case is moot and
speedy and amicable method of settling disputes, and as a
academic should not preclude this Tribunal from setting forth in
means of avoiding litigation, should receive every
language clear and unmistakable, the obligation of fidelity on
encouragement from the courts which may be extended without
the part of lower court judges to the unequivocal command of
contravening sound public policy or settled law" (3 Am. Jur., p.
the Constitution that excessive bail shall not be required.67
835). Congress has officially adopted the modern view when it
reproduced in the new Civil Code the provisions of the old Code
This principle was repeated in subsequent cases when this court on Arbitration. And only recently it approved Republic Act No.
deemed it proper to clarify important matters for guidance.68
876 expressly authorizing arbitration of future sector participation in the settlement of disputes through ADR.
disputes.72 (Emphasis supplied) This Act shall be without prejudice to the adoption by the
Supreme Court of any ADR system, such as mediation,
In view of our policy to adopt arbitration as a manner of settling conciliation, arbitration, or any combination thereof as a means
disputes, arbitration clauses are liberally construed to favor of achieving speedy and efficient means of resolving cases
arbitration. Thus, in LM Power Engineering Corporation v. pending before all courts in the Philippines which shall be
Capitol Industrial Construction Groups, Inc.,73 this court said: governed by such rules as the Supreme Court may approve
from time to time.
Being an inexpensive, speedy and amicable method of settling
disputes, arbitration — along with mediation, conciliation and ....
negotiation — is encouraged by the Supreme Court. Aside from
unclogging judicial dockets, arbitration also hastens the SEC. 25. Interpretation of the Act.- In interpreting the Act, the
resolution of disputes, especially of the commercial kind. It is court shall have due regard to the policy of the law in favor of
thus regarded as the "wave of the future" in international civil arbitration.Where action is commenced by or against multiple
and commercial disputes. Brushing aside a contractual parties, one or more of whomare parties who are bound by the
agreement calling for arbitration between the parties would be arbitration agreement although the civil action may continue as
a step backward. to those who are not bound by such arbitration agreement.
(Emphasis supplied)
Consistent with the above-mentioned policy of encouraging
alternative dispute resolution methods, courts should liberally Thus, if there is an interpretation that would render effective an
construe arbitration clauses. Provided such clause is susceptible arbitration clause for purposes ofavoiding litigation and
of an interpretation that covers the asserted dispute, an order expediting resolution of the dispute, that interpretation shall be
to arbitrate should be granted. Any doubt should be resolved in adopted. Petitioners’ main argument arises from the separate
favor of arbitration.74 (Emphasis supplied) personality given to juridical persons vis-à-vis their directors,
officers, stockholders, and agents. Since they did not sign the
A more clear-cut statement of the state policy to encourage arbitration agreement in any capacity, they cannot be forced to
arbitration and to favor interpretations that would render submit to the jurisdiction of the Arbitration Tribunal in
effective an arbitration clause was later expressed in Republic accordance with the arbitration agreement. Moreover, they had
Act No. 9285:75 already resigned as directors of Shangri-Laat the time of the
alleged default.
SEC. 2. Declaration of Policy.- It is hereby declared the policy of
the State to actively promote party autonomy in the resolution Indeed, as petitioners point out, their personalities as directors
of disputes or the freedom of the party to make their own of Shangri-La are separate and distinct from Shangri-La.
arrangements to resolve their disputes. Towards this end, the
State shall encourage and actively promote the use of A corporation is an artificial entity created by fiction of
Alternative Dispute Resolution (ADR) as an important means to law.76 This means that while it is not a person, naturally, the
achieve speedy and impartial justice and declog court dockets. law gives it a distinct personality and treats it as such. A
As such, the State shall provide means for the use of ADR as an corporation, in the legal sense, is an individual with a
efficient tool and an alternative procedure for the resolution of personality that is distinct and separate from other persons
appropriate cases. Likewise, the State shall enlist active private including its stockholders, officers, directors,
representatives,77 and other juridical entities. The law vests in 8. To enter into merger or consolidation with other
corporations rights,powers, and attributes as if they were corporations as provided in this Code;
natural persons with physical existence and capabilities to act
on their own.78 For instance, they have the power to sue and 9. To make reasonable donations, including those for the
enter into transactions or contracts. Section 36 of the public welfare or for hospital, charitable, cultural,
Corporation Code enumerates some of a corporation’s powers, scientific, civic, or similar purposes: Provided, That no
thus: corporation, domestic or foreign, shall give donations in
aid of any political party or candidate or for purposes of
Section 36. Corporate powers and capacity.– Every corporation partisan political activity;
incorporated under this Code has the power and capacity:
10. To establish pension, retirement, and other plans for
1. To sue and be sued in its corporate name; the benefit of its directors, trustees, officers and
employees; and
2. Of succession by its corporate name for the period of
time stated in the articles of incorporation and the 11. To exercise such other powers asmay be essential or
certificate ofincorporation; necessary to carry out its purpose or purposes as stated
in its articles of incorporation. (13a)
3. To adopt and use a corporate seal;
Because a corporation’s existence is only by fiction of law, it
4. To amend its articles of incorporation in accordance can only exercise its rights and powers through itsdirectors,
with the provisions of this Code; officers, or agents, who are all natural persons. A corporation
cannot sue or enter into contracts without them.
5. To adopt by-laws, not contrary to law, morals, or
public policy, and to amend or repeal the same in A consequence of a corporation’s separate personality is that
accordance with this Code; consent by a corporation through its representatives is not
consent of the representative, personally. Its obligations,
6. In case of stock corporations, to issue or sell stocks to incurred through official acts of its representatives, are its own.
subscribers and to sell treasury stocks in accordance A stockholder, director, or representative does not become a
with the provisions of this Code; and to admit members party to a contract just because a corporation executed a
to the corporation if it be a non-stock corporation; contract through that stockholder, director or representative.

7. To purchase, receive, take or grant, hold, convey, Hence, a corporation’s representatives are generally not bound
sell, lease, pledge, mortgage and otherwise deal with by the terms of the contract executed by the corporation. They
such real and personal property, including securities and are not personally liable for obligations and liabilities incurred
bonds of other corporations, as the transaction of the on or in behalf of the corporation.
lawful business of the corporation may reasonably and
necessarily require, subject to the limitations prescribed Petitioners are also correct that arbitration promotes the
by law and the Constitution; parties’ autonomy in resolving their disputes. This court
recognized in Heirs of Augusto Salas, Jr. v. Laperal Realty
Corporation79 that an arbitration clause shall not apply to
persons who were neither parties to the contract nor assignees legitimate issues."85 It is also warranted in alter ego cases
of previous parties, thus: "where a corporation is merely a farce since it is a mere alter
ego or business conduit of a person, or where the corporation is
A submission to arbitration is a contract. As such, the so organized and controlled and its affairs are so conducted as
Agreement, containing the stipulation on arbitration, binds the to make it merely an instrumentality, agency, conduit or
parties thereto, as well as their assigns and heirs. But only adjunct of another corporation."86
they.80 (Citations omitted)
When corporate veil is pierced, the corporation and persons
Similarly, in Del Monte Corporation-USA v. Court of who are normally treated as distinct from the corporation are
Appeals,81 this court ruled: treated as one person, such that when the corporation is
adjudged liable, these persons, too, become liable as if they
The provision to submit to arbitration any dispute arising were the corporation.
therefrom and the relationship of the parties is part of that
contract and is itself a contract. As a rule, contracts are Among the persons who may be treatedas the corporation itself
respected as the law between the contracting parties and under certain circumstances are its directors and officers.
produce effect as between them, their assigns and heirs. Section 31 of the Corporation Code provides the instances when
Clearly, only parties to the Agreement . . . are bound by the directors, trustees, or officers may become liable for corporate
Agreement and its arbitration clause as they are the only acts:
signatories thereto.82 (Citation omitted)
Sec. 31. Liability of directors, trustees or officers. - Directors or
This court incorporated these rulings in Agan, Jr. v. Philippine trustees who willfully and knowingly vote for or assent to
International Air Terminals Co., Inc.83 and Stanfilco Employees patently unlawful acts of the corporation or who are guilty of
v. DOLE Philippines, Inc., et al.84 gross negligence or bad faith in directing the affairs of the
corporation or acquire any personal or pecuniary interest in
As a general rule, therefore, a corporation’s representative who conflict with their duty as such directors or trustees shall be
did not personally bind himself or herself to an arbitration liable jointly and severally for all damages resulting therefrom
agreement cannot be forced to participate in arbitration suffered by the corporation, its stockholders or members and
proceedings made pursuant to an agreement entered into by other persons.
the corporation. He or she is generally not considered a party to
that agreement. When a director, trustee or officer attempts to acquire or
acquires, in violation of his duty, any interest adverse to the
However, there are instances when the distinction between corporation in respect of any matter which has been reposed
personalities of directors, officers,and representatives, and of inhim in confidence, as to which equity imposes a disability
the corporation, are disregarded. We call this piercing the veil upon him to deal in his own behalf, he shall be liable as a
of corporate fiction. trustee for the corporation and must account for the profits
which otherwise would have accrued to the corporation. (n)
Piercing the corporate veil is warranted when "[the separate
personality of a corporation] is used as a means to perpetrate Based on the above provision, a director, trustee, or officer of a
fraud or an illegal act, or as a vehicle for the evasion of an corporation may be made solidarily liable with it for all damages
existing obligation, the circumvention of statutes, or to confuse
suffered by the corporation, its stockholders or members, and in a proceeding participated in by all parties involved, including
other persons in any of the following cases: current representatives of the corporation, and those persons
whose personalities are impliedly the sameas the corporation.
a) The director or trustee willfully and knowingly voted This is because when the court or tribunal finds that
for or assented to a patently unlawful corporate act; circumstances exist warranting the piercing of the corporate
veil, the corporate representatives are treated as the
b) The director or trustee was guilty of gross negligence corporation itself and should be held liable for corporate acts.
or bad faith in directing corporate affairs; and The corporation’s distinct personality is disregarded, and the
corporation is seen as a mere aggregation of persons
undertaking a business under the collective name of the
c) The director or trustee acquired personal or pecuniary
corporation.
interest in conflict with his or her duties as director or
trustee.
Hence, when the directors, as in this case, are impleaded in a
case against a corporation, alleging malice orbad faith on their
Solidary liability with the corporation will also attach in the
part in directing the affairs of the corporation, complainants are
following instances:
effectively alleging that the directors and the corporation are
not acting as separate entities. They are alleging that the acts
a) "When a director or officer has consented to the or omissions by the corporation that violated their rights are
issuance of watered stocks or who, having knowledge also the directors’ acts or omissions.90 They are alleging that
thereof, did not forthwith file with the corporate contracts executed by the corporation are contracts executed
secretary his written objection thereto";87 by the directors. Complainants effectively pray that the
corporate veilbe pierced because the cause of action between
b) "When a director, trustee or officer has contractually the corporation and the directors is the same.
agreed or stipulated to hold himself personally and
solidarily liable with the corporation";88 and In that case, complainants have no choice but to institute only
one proceeding against the parties.1âwphi1 Under the Rules of
c) "When a director, trustee or officer is made, by Court, filing of multiple suits for a single cause of action is
specific provision of law, personally liable for his prohibited. Institution of more than one suit for the same cause
corporate action."89 of action constitutes splitting the cause of action, which is a
ground for the dismissal ofthe others. Thus, in Rule 2:
When there are allegations of bad faith or malice against
corporate directors or representatives, it becomes the duty of Section 3. One suit for a single cause of action. — A party may
courts or tribunals to determine if these persons and the not institute more than one suit for a single cause of action.
corporation should be treated as one. Without a trial, courts (3a)
and tribunals have no basis for determining whether the veil of
corporate fiction should be pierced. Courts or tribunals do not Section 4. Splitting a single cause of action;effect of. — If two
have such prior knowledge. Thus, the courts or tribunals must or more suits are instituted on the basis of the same cause of
first determine whether circumstances exist towarrant the action, the filing of one or a judgment upon the merits in any
courts or tribunals to disregard the distinction between the one is available as a ground for the dismissal of the others. (4a)
corporation and the persons representing it. The determination
of these circumstances must be made by one tribunal or court
It is because the personalities of petitioners and the corporation all purposes, is the same as its directors, stockholders, officers,
may later be found to be indistinct that we rule that petitioners and agents. It does not result in an absolute confusion of
may be compelled to submit to arbitration. personalities of the corporation and the persons composing or
representing it. Courts merely discount the distinction and treat
However, in ruling that petitioners may be compelled to submit them as one, in relation to a specific act, in order to extend the
to the arbitration proceedings, we are not overturning Heirs of terms of the contract and the liabilities for all damages to erring
Augusto Salas wherein this court affirmed the basic arbitration corporate officials who participated in the corporation’s illegal
principle that only parties to an arbitration agreement may be acts. This is done so that the legal fiction cannot be used to
compelled to submit to arbitration. In that case, this court perpetrate illegalities and injustices.
recognizedthat persons other than the main party may be
compelled to submit to arbitration, e.g., assignees and heirs. Thus, in cases alleging solidary liability with the corporation or
Assignees and heirs may be considered parties to an arbitration praying for the piercing of the corporate veil, parties who are
agreement entered into by their assignor because the normally treated as distinct individuals should be made to
assignor’s rights and obligations are transferred to them upon participate in the arbitration proceedings in order to determine
assignment. In other words, the assignor’s rights and ifsuch distinction should indeed be disregarded and, if so, to
obligations become their own rights and obligations. In the determine the extent of their liabilities.
same way, the corporation’s obligations are treated as the
representative’s obligations when the corporate veil is pierced. In this case, the Arbitral Tribunal rendered a decision, finding
Moreover, in Heirs of Augusto Salas, this court affirmed its that BF Corporation failed to prove the existence of
policy against multiplicity of suits and unnecessary delay. This circumstances that render petitioners and the other directors
court said that "to split the proceeding into arbitration for some solidarily liable. It ruled that petitioners and Shangri-La’s other
parties and trial for other parties would "result in multiplicity of directors were not liable for the contractual obligations of
suits, duplicitous procedure and unnecessary delay."91 This Shangri-La to BF Corporation. The Arbitral Tribunal’s decision
court also intimated that the interest of justice would be best was made with the participation of petitioners, albeit with their
observed if it adjudicated rights in a single proceeding.92 While continuing objection. In view of our discussion above, we rule
the facts of that case prompted this court to direct the trial that petitioners are bound by such decision.
court to proceed to determine the issues of thatcase, it did not
prohibit courts from allowing the case to proceed to arbitration, WHEREFORE, the petition is DENIED. The Court of Appeals'
when circumstances warrant. decision of May 11, 2006 and resolution of October 5, 2006 are
AFFIRMED.
Hence, the issue of whether the corporation’s acts in violation
of complainant’s rights, and the incidental issue of whether SO ORDERED.
piercing of the corporate veil is warranted, should be
determined in a single proceeding. Such finding would
determine if the corporation is merely an aggregation of
persons whose liabilities must be treated as one with the
corporation.

However, when the courts disregard the corporation’s distinct


and separate personality from its directors or officers, the
courts do not say that the corporation, in all instances and for

S-ar putea să vă placă și