01.03 DEMOLICIONES
01.03.01 DEMOLICION CONSTRUCCION EXISTENTE m3 5.00 296.60
PICADO DE REBABAS EN CIMIENTOS Y SOBRECIMIENTOS DE CONSTRUCCION
01.03.02 m2 30.00 56.14
ADYACENTE
01.04 MOVIMIENTO DE TIERRAS
01.04.01 LIMPIEZA DE TERRENO MANUAL m2 355.00 2.61
01.04.02 EXCAVACION PARA CIMIENTOS HASTA 1.00 mTERRENO NORMAL m3 66.00 23.11
01.05.02 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3 66.00 128.71
01.05.03 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO HASTA 0.30 m m2 45.00 28.63
01.06.02 COLUMNAS
01.06.02.01 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS kg 2,248.00 2.27
01.06.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 126.00 43.25
01.06.02.03 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 18.00 300.25
01.06.03 VIGAS
01.06.03.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 96.00 61.65
01.06.03.02 ACERO fy=4200 kg/cm2 GRADO 60 en VIGAS kg 9,000.00 2.27
01.06.03.03 CONCRETO EN VIGAS f'c=210 kg/cm2 m3 24.00 241.41
01.06.04 LOSAS ALIGERADAS
01.06.04.02 LADRILLO HUECO DE ARCILLA h=15 cm PARA TECHO ALIGERADO pza 5,830.00 1.01
02.03 CIELORRASOS
02.05 CONTRAZOCALOS
02.05.01 CONTRAZOCALO DE MADERA CEDRO DE 3/4" X 2" CON RODON DE 3/4" m 870.00 17.64
02.06 ZOCALOS
02.07 REVESTIMIENTOS
02.08 CUBIERTAS
02.08.01 LADRILLO PASTELERO 0.25x0.25x0.03 m.ASENTADO CON MORTERO 1:4 m2 290.00 27.84
02.11 CERRAJERIA
02.13 PINTURA
02.14.03 DUCHA CROMADA DE CABEZA GIRATORIA Y LLAVE MEZCLADORA und 9.00 26.33
03 INSTALACIONES ELECTRICAS
03.04 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE + L.T. A PRUEBA DE AGUA pto 66.00 85.94
03.11 TABLEROS DISTRIBUCION CAJA METALICA CON 12 POLOS und 10.00 849.15
04 INSTALACIONES SANITARIAS
04.02.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 O 1/2" pto 27.00 71.98
04.02.02 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2" m 76.00 27.79
04.02.03 RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 3/4" m 98.00 15.34
04.02.07 TANQUE DE AGUA DE ETERNIT DE 1000 LITROS INCLUYE ACC. INTERNOS und 3.00 967.38
04.03.01 SALIDA AGUA CALIENTE TUBERIA CPVC O 1/2" pto 27.00 101.57
04.03.02 RED DE DISTRIBUCION DE AGUA CALIENTE CON TUBERIA CPVC DE 1/2" m 120.00 22.30
COSTO DIRECTO
UTILIDAD 10%
SUBTOTAL
TOTAL PRESUPUESTO
168,526.81
10,097.00
1,800.00
1,800.00
1,800.00
77.00
4,620.00
22,000.00
22,000.00
3,167.20
1,483.00
1,684.20
5,397.51
926.55
1,525.26
510.40
2,435.30
21,066.03
308.88
8,494.86
1,288.35
5,455.24
5,518.70
106,799.07
9,680.08
4,907.40
456.62
2,542.40
227.57
878.71
667.38
15,956.96
5,102.96
5,449.50
5,404.50
32,142.24
5,918.40
20,430.00
5,793.84
45,107.18
19,119.24
5,888.30
7,491.00
12,608.64
3,912.61
1,261.20
1,180.40
1,471.01
264,900.67
83,242.30
74,512.60
8,729.70
25,799.73
1,946.91
20,028.00
3,824.82
19,566.30
19,566.30
47,503.09
17,678.40
5,346.00
2,702.99
21,775.70
15,346.80
15,346.80
8,089.20
8,089.20
304.47
304.47
8,073.60
8,073.60
24,990.11
18,781.28
3,525.15
2,683.68
1,381.45
1,381.45
2,913.80
2,046.24
322.76
236.28
308.52
1,466.64
1,466.64
19,436.64
6,794.70
9,276.00
2,311.74
163.20
891.00
6,786.54
4,887.63
1,153.53
236.97
223.47
142.47
142.47
33,259.16
14,151.60
615.23
543.72
5,672.04
189.12
346.14
229.08
722.52
102.42
2,195.79
8,491.50
21,119.62
5,960.16
1,009.35
1,131.30
2,068.20
801.00
222.57
727.74
9,552.58
1,943.46
2,112.04
1,503.32
342.65
670.77
78.20
2,902.14
5,606.88
2,742.39
2,676.00
188.49
487,806.26
61,115.29
48,780.63
------------
597,702.18
113,563.41
========
711,265.59