Overview and recap
• Timing in ST3 Plan - start 2024, open 2031.
Estimated 3400 daily boardings.
4
Financial impact (2017-2041 in 2018$)
5
Options for consideration
1. No further work, return to original ST3 Plan schedule
2. Advance incrementally
• Complete final design of entire project
• Complete construction of foundation/guideway and
platform/canopy packages
• Determine timing for final construction package
3. Advance fully, open ~2025
• Complete final design of entire project
• Complete construction of all packages
• Open ~2025
6
Option 1 – Original ST3 Plan
Return to ST3 Plan schedule
Re-start project in 2024
Complete and open by 2031
Effects
• Separate station structures
• Results in service disruption &
neighborhood impacts
7
Option 2 – Advance incrementally
• Feb 2020: Authorize final design and
Construction Packages
construction of & Estimates
Foundation & guideway: ~$XXM
Foundation/Guideway. Platform & canopy: ~$XXM
• Q2 2021: Authorize construction ofPlaza & finishes: ~$115M
Platform/Canopy. Consider
TOTAL: ~ $143M
schedule for Plaza/Finishes.
Effects
• Minimizes service &
neighborhood disruptions
• Integrated design
• Choices for timing of
plaza/finishes and
opening
8
Option 3 – Advance fully
• Feb 2020: Authorize final design, authorize construction of
Foundation/Guideway. Provide direction to complete the station
early and open in ~2025.
• Q2 2021: Authorize construction of Platform/Canopy and
Plaza/Finishes packages.
Effects
• Avoids most service &
neighborhood disruptions
2025
• Integrated design
• Open station early
9
Summary
Comparison of options 1, 2 and 3
Option 1 Option 2 Option 3
Issue ST3 Plan Advance Advance fully
schedule incrementally
Integrated design No Yes Yes
Service disruption No Minimized Mostly avoided
addressed
Neighborhood No Minimized Mostly avoided
impact addressed
Open for service 2031 TBD ~2025
10
Service disruption and
neighborhood impacts
Impacts of infill construction (ST3 plan timing)
Over 60k daily riders affected, nearly 90% from
Snohomish and North King subareas
• Potential system-wide delays could
affect many more riders
• Service delays due to single-tracking
• Restricted construction window –
nighttime construction and higher cost
• Repeated neighborhood impacts
• Mitigation expenses
12
Choices and trade-offs
Assess impacts to riders, the local neighborhood and
to the project to inform approach
• Truncate one line at Northgate to set headways and minimize delays
• Single-tracking service
• Modify construction hours – evening/overnight/weekends
• Coordinate additional service with transit partners
Issue Option 1 Option 2 Option 3
Service disruption addressed No Minimized Mostly
avoided
Neighborhood impact No Minimized Mostly
addressed avoided
13
Financial effects
Early Full Build Impact on Debt Capacity
Change in Debt Capacity
$25 "Pinch point" -
Principal Balance - 130th ST3 Timing $6M or 0.2%
Principal Balance - 130th Early Full Build decrease in
Total Debt Capacity debt capacity
$20
Billions of YOE$
$15
$10
$5
$-
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041
15
Key Takeaways
• Change in debt capacity in pinch year is relatively small
• 0.2% ($6M) decrease in 2032 (pinch year)
• However, any decrease to capacity lessens agency’s
ability to respond to risks (recession, capital cost
increase, etc.)
• Many economic and other factors could have significant
impact on the financial capacity at any given time.
• Example: a small recession could consume the remaining capacity
which could lead to potential program adjustments within in a few
years.
16
Near term recession scenario
Debt Capacity - Fall 2019 vs Scenario with Near Term Recession
$30
Principal Balance, Fall 2019 Forecast Fall 2019 Forecast
With Near Term
Principal Balance Forecast with Near Term Recession Recession
$25
Debt Capacity, Fall 2019 Forecast
Debt Capacity Forecast with Near Term Recession
$20
Billions of YOE$
$15
$10
$5
$-
2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041
17
Committee options and
actions
Options for consideration
19
Committee actions
20
Limited funding authorization
Allows 130th project to stay in sync with LLE
construction schedule
21
Thank you.
soundtransit.org
Summary
Comparison of options 1, 2 and 3
Option 1 Option 2 Option 3
Issue ST3 Plan Advance Advance fully
schedule incrementally
Integrated design No Yes Yes
Service disruption No Minimized Mostly avoided
addressed
Neighborhood No Minimized Mostly avoided
impact addressed
Open for service 2031 TBD ~2025
23
NE 130th Street Infill Station
Resolution No. R2020-01 and Motion No. M2020-14
2/13/2020
Illustrative - Not to Scale
NE 130th STREET INFILL STATION: Authorized Project Allocation $6.8M
ALLOCATION
F/D & Construction $ COMMITMENTS
$6.8M
Dvt.
Pjt
Dvt.
Pjt
Dvt.
Pjt