Documente Academic
Documente Profesional
Documente Cultură
Classification of beam
Simple beam –
sometimes called
semi-supported
beam. It refers to a Cantilever Beam
single span beam
supported at its end
T-Beam – When the floor slab and beams are poured
without restraint at
with concrete simultaneously to produce a
the support.
monolithic structure where the portion of the slab at
Restraint means a
both sides of the beam serves as flanges of the T-
rigid connection or
beam. The beam below the slab serves as the web
anchorage at the Simple Beam member and is sometimes called stem.
support.
T - Beam
Reference:
Max Fajardo; Simplified Methods on Building Construction pg.
276-278
Cont. Beam
Semi-continuous beam – refers to a beam with two Ribbed (Waffle) Slab System
span with or without restraint at the two extreme Ribbed floors consisting of equally spaced
ends. ribs are usually supported directly by
columns. They are either one-way spanning
systems known as ribbed slab or a two-way
ribbed system known as a waffle slab.
This form of construction is not very
common because of the formwork costs
and the low fire rating.
BT-5 Lecture Part 1 “FLOOR SYSTEMS” by ART ( Ar. Dept. Faculty Mem, T.I.P. Q.C.) ©2015
A 120-mm-thick slab with a minimum rib Disadvantages of Ribbed/Waffle Slab:
thickness of 125 mm for continuous ribs is a. Depth of slab between the ribs may control
required to achieve a 2-hour fire rating.
the fire rating
A rib thickness of greater than 125 mm is
usually required to accommodate tensile b. Requires special or proprietary formwork
and shear reinforcement. c. Greater floor-to-floor height
Ribbed slabs are suitable for medium to d. Large vertical penetrations are more difficult
heavy loads, can span reasonable distances, to handle.
and are very stiff and particularly suitable Reference:
http://civildigital.com/ribbed-waffle-slab-system-advantages-
where the soffit is exposed. disadvantages/
Slab depths typically vary from 75 to 125
mm and rib widths from 125 to 200 mm.
Rib spacing of 600 to 1500 mm can be used.
The overall depth of the floor typically
varies from 300 to 600 mm with overall
spans of up to 15 m if reinforced, longer if
post-tensioned.
The use of ribs to the soffit of the slab
reduces the quantity of concrete and
reinforcement and also the weight of the
floor.
The saving of materials will be offset by the
complication in formwork and placing of Ribbed Floor Slab
reinforcement. However, formwork
complication is minimized by use of
standard, modular, reusable formwork,
usually made from polypropylene or
fiberglass and with tapered sides to allow
stripping.
For ribs at 1200-mm centers (to suit
standard forms) the economical reinforced
concrete floor span ‘L’ is approximately D x
15 for a single span and D x 22 for a multi-
span, where D is the overall floor depth.
The one-way ribs are typically designed as
T-beams, often spanning in the long
direction.
Waffle Slab
A solid drop panel is required at the
columns and load bearing walls for shear Lift Slab
and moment resistance. A precast method of construction of slab.
Lift slab construction is a method of
Advantages of Ribbed/Waffle Slab: constructing concrete buildings by casting
a. Savings on weight and materials. the floor or roof slab on top of the previous
slab and then raising the slab up with
b. Long spans.
hydraulic jacks, so being cheaper and faster
c. Attractive soffit appearance if exposed. as it does not need forms & shores as it is
d. Economical when reusable formwork pans needed for cast-in-place slabs.
used. Lift-slab construction can be more
e. Vertical penetrations between ribs are easy. economic than conventional construction
when the building is vertically uniform, such
as for hotels, apartment buildings, and
BT-5 Lecture Part 1 “FLOOR SYSTEMS” by ART ( Ar. Dept. Faculty Mem, T.I.P. Q.C.) ©2015
dormitories, and where the slab designs are edge columns and where cantilevers for
repetitive. balconies.
Lift-slab buildings have certain limitations This system produces a structure where a
that need to be recognized early in the flush slab floor is most appropriate and for
planning process, thus, for the traditional this type of structure the lift slab
organization of a construction project, construction may well be cheaper than any
where the owner retains an architect to other form of structure.
design a building. The architect should It can be employed for beam and slab or
retain his structural engineer early in the waffle slab floors, but the forms necessary
design process and both should contact a between each take much of the advantage
lift-slab contractor for design advice at that of simple repetitive casting at ground level.
time. When the owner contracts with a firm Compare to cast-in-place concrete slab, lift
to both design and construct a project, the slab does not require extensive formwork.
firm should also contact a lift-slab Good for the buildings with similar floor
contractor for early advice plans throughout the height of the building.
May employed with ribbed slabs.
Lift Slab Historical Background
The method was invented and Sequence of lifting slabs is influenced by the
developed in the early 1950s by a following:
a. Weigh of the slabs.
collaboration of Philip N. Youtz and
b. Height of the building.
Thomas B. Slick resulting Youtz-Slick
c. Lifting capacity of jacks.
Lift-Slab Method of Construction in d. Cross sectional area of columns during the lifting.
1955.
The method was first used at Trinity Slabs are lifted by jacks, operating on the top of the
University in San Antonio, Texas in building columns, this jack lift a pair of steel rods
1952. attached to each lifting collar in the slab being
raised.
Reference:
http://theconstructor.org/concrete/lift-slab-construction/6824/
Flat Slab
A flat slab is a one-way or two-way system with
thickening in the slab at the columns and load
bearing walls called ‘drop panels’. Drop panels act as
Lift Slab Construction (Trinity T-beams over the supports. They increase the shear
Campus) capacity and the stiffness of the floor system under
Advantages of Lift Slab: vertical loads, thus increasing the economical span
The advantage of this system is that the range.
only formwork required is to the edges of
the slabs and no centering is required to the The plan dimensions of the drop panels are a
soffit of the slabs. minimum of 1/3 of the span in the direction
Also, the slabs are cast monolithically and under consideration, usually rounded to the nearest
can be designed to span continuously 100 mm. The overall depth of the drop panel is
between the points of support and so typically taken as 1.75 to 2 times the depth of the
employ the least thickness of slab. Where it slab, again rounded to suit timber sizes or the
is convenient to cantilever slabs beyond the nearest 25 mm.
BT-5 Lecture Part 1 “FLOOR SYSTEMS” by ART ( Ar. Dept. Faculty Mem, T.I.P. Q.C.) ©2015
The slab is reinforced on both directions and on the Advantages of Flat Slab:
line of columns grid the reinforcement bars are more 1) Simple formwork
closely spaced forming ‘column bonds’. 2) No beams – simplifying under-floor services
outside the drops.
Linear supports: 3) Minimum structural depth
4) Building height can be reduced.
- As no beam is used, floor height can be
reduced and consequently the building
height will be reduced.
- Approximately 10% in the vertical member
could be saved.
- Foundation load will also reduce.
5) A flat soffit (clean finishes)
6) Flexible arrangement for services distribution as
a) Column-beam support services does not have to divert around structural
b) Column-wide beam support (dropped slab strip) elements.
support 7) Usually does not require shear reinforcement at
c) Column (without head) the column.
d) Column with fungi form column head
Disadvantages of Flat Slab:
In flat slab, the total load intensity should be carried 1) Span length is medium.
in both perpendicular directions. Beside this, due to 2) Not suitable in supporting brittle (masonry)
shear problems at column heads, the thickness of partitions.
flat slab is greater. 3) Use of drop panels may interfere with larger
mechanical ducting.
4) Critical middle strip deflection.
5) Higher slab thickness.
6) Vertical penetration need to avoid area around
columns.
BT-5 Lecture Part 1 “FLOOR SYSTEMS” by ART ( Ar. Dept. Faculty Mem, T.I.P. Q.C.) ©2015
Disadvantages of Flat Plate System:
1) Medium spans
2) Limited lateral load capacity as part of moment
frame
3) May need shear heads or shear reinforcement at
the columns or larger columns for shear
4) Long-term deflection may be controlling factor
5) May not be suitable for supporting brittle
(masonry) partitions
6) May not be suitable for heavy loads
Reference:
http://civildigital.com/flat-slab-floor-system-advantages-
disadvantages-flat-slabs/
Advantages of Flat Plate System: From foundation to rooftop of even the very tallest
1) Simple formwork and suitable for direct fix or projects, with the system’s hydraulic jacks, installing
sprayed ceiling. steel reinforcement and pouring concrete become
2) No beams- simplifying under-floor services. much easier and faster, plus can be more efficiently
3) Minimum structural depth are reduced floor-to- controlled to assure the highest quality finished
floor height. cement structure. SLIPFORM technology virtually
eliminates unnecessary waste and hazards, making
this construction system even more efficient and
economical
BT-5 Lecture Part 1 “FLOOR SYSTEMS” by ART ( Ar. Dept. Faculty Mem, T.I.P. Q.C.) ©2015
Benefits Standby plant and equipment should be
Careful planning of construction process available though cold jointing may
can achieve high production rates occasionally be necessary.
Slip form does not require the crane to
move upwards, minimising crane use.
Since the formwork operates
independently, formation of the core in
advance of the rest of the structure takes it
off the critical path – enhancing main
structure stability.
Availability of the different working
platforms in the formwork system allows
the exposed concrete at the bottom of the
rising formwork to be finished, making it an
integral part of the construction process.
Certain formwork systems permit
construction of tapered cores and towers. Tower erection using Slipform (CADD
Slip form systems require a small but highly Presentatation)
skilled workforce on site.
Safety
Working platforms, guard rails, ladders and
wind shields are normally built into the
completed system.
Less congested construction site due to
minimal scaffolding and temporary works.
Completed formwork assembly is robust.
Strength of concrete in the wall below must
be closely controlled to achieve stability
during operation.
Site operatives can quickly become familiar
with health and safety aspects of their job
High levels of planning and control mean
that health and safety are normally
addressed from the beginning of the work.
Other considerations
BT-5 Lecture Part 1 “FLOOR SYSTEMS” by ART ( Ar. Dept. Faculty Mem, T.I.P. Q.C.) ©2015