Sunteți pe pagina 1din 6

Proceedings of the Marine Operations Specialty Symposium 2008

MOSS-26

ANALYSIS OF AN ALTERNATIVE PIPELINE INSTALLATION PROCEDURE THAT


COMBINES ONSHORE DEFLECTION AND OFFSHORE TRANSPORTATION

Danilo Machado Lawinscky da Silva1 Rodrigo Almeida Bahiense1 Breno Pinheiro Jacob1

Fernando Gomes da Silva Torres2 Antonio Roberto Medeiros2

1
LAMCSO – Laboratory of Computational Methods and Offshore Systems – PEC/COPPE/UFRJ
danilo@lamcso.coppe.ufrj.br, rodrigo@lamcso.coppe.ufrj.br, breno@lamcso.coppe.ufrj.br
2
PETROBRAS – Petróleo Brasileiro S.A.
ftorres@petrobras.com.br, robertomedeiros.nsg@petrobras.com.br

ABSTRACT installation in shallow water is the S-Lay method. In this


method, the welded pipeline is supported on the rollers of the
Conventional offshore pipeline installation operations in vessel and the stinger, forming the over-bend. Then it is
Brazil have been performed in an S-Lay procedure employing suspended in the water all the way to seabed, forming the sag-
the BGL-1 barge, owned by Petrobras. However, this procedure bend. The over-bend and sag-bend form the shape of an “S”.
has some limits, and may not be feasible in some particular The BGL-1 (a pipeline launching barge owned by the
scenarios. Brazilian state oil company - Petrobras) is used to perform S-
An alternative procedure used by Petrobras is the so-called Lay pipeline installation operations. The BGL-1 is a second
lateral deflection procedure, which basically consists of generation lay barge that performs installation operations by
performing the pipeline assembly on shore, and then deflecting moving forward using its own mooring lines. This involves the
it to the sea using a tugboat. After that, the pipeline is towed to definition of a complex mooring procedure, as a sequence of
its installation area. operations that determine the mooring line positions and induce
The objective of this work is to present numerical the lay barge movement as it lays the pipeline. Basically,
simulations of both stages of this procedure (the lateral tugboats drop anchors at some predefined positions; then the
deflection procedure itself and the pipeline transportation). The barge winches release the stern mooring cables, and collect the
simulations were performed to help planning an actual mooring cables located at the bow. This is a delicate operation
operation that was scheduled to occur in the Xaréu field, at the essential to keeping the position and direction of the lay barge
state of Ceará, northeast Brazil. These simulations employ the in accordance with the planned route. The loss of a mooring
SITUA-Prosim computational tool, which is able to incorporate anchor during such operation can cause sudden yawing or
the correct definition of the seabed and shore from bathymetric drifting of the barge, which in turn can result in buckling of the
curves. pipe at the end of the stinger due the excessive bending.
Regarding the transportation stage, typically it is The procedure described above has some limits, such as: i)
performed using a front and a rear tugboat aligned at the it has a very restrictive limitation according to the weather
transportation route. As a result of the simulations, a different conditions; ii) the procedure is extremely complex when
scheme was proposed, using only one tugboat. performed in congested areas [1].
Therefore, Petrobras has considered an alternative
procedure that combines onshore lateral deflection and offshore
INTRODUCTION transportation. This work is focused in the numerical
simulation of this procedure. Several analyses are performed in
The installation of pipelines is among the most challenging order to assess the behavior of this alternative pipeline
offshore operations. The most common method of pipeline installation procedure.

1
LATERAL DEFLECTION PROCEDURE Therefore, the simulation takes into account the actual
bathymetric information and obstacle positions [3,4].
The lateral deflection procedure basically consists of Three-dimensional frame elements were employed in the
performing the pipeline assembly on shore and deflecting it to generation of the numerical model for the pipeline. Three-
the sea using a tugboat. The characterization of this procedure dimensional frame elements were employed also for the
involves the determination of the better velocity and direction representation of the pipe segments with buoys. An equivalent
of the tugboat, in order to minimize the efforts on the pipeline element was used to represent both the pipeline physical
(especially due to the curvatures). properties and the buoy hydrodynamic properties. The
characteristics of the equivalent pipeline+buoy element are
Scenario and characteristics of pipeline shown in Table 3.

The pipeline was installed to rehabilitate a 10” pipeline TABLE 1. 10” PIPELINE DATA
that was in the end of its lifetime. The pipeline is located at the Parameter Value Unit
Xaréu field, interconnecting the PXA-1 platform to the buoy Outside Diameter 0.27305 m
frame, with the basic purpose of transporting the oil production Inside Diameter 0.2445 m
of Xaréu, Atum and Curimã fields, in Ceará State (northeast of Yield Stress of steel 414000 kN/m2
Brazil), to the NT ALIANZA Ship. Modulus of Elasticity of steel 207000 MPa
The pipeline has a total length of 721m and was assembled Axial Stiffness (EA) 2402252.49 kN
at Canto Beach, in Paracuru city, deflected from shore to the Flexional Stiffness (EI) 20169.39 kN*m2
sea, and transported with buoys to the installation location, Poisson Coefficient 0.3 -
where it was positioned on the guideline and sunk by flooding Density of steel 77 kN/m3
the buoys. Corrosion Protection 0.0027 m
During assembly, the pipeline was positioned on "big- Corr. Protection Specific Mass 9.32 kN/m3
bags" (bags of sand) as shown in Figure 1. Hydrodynamic Diameter 0.27875 m
Tube Length 12 m
Weight in Air 0.91099 kN/m
Weight in Water 0.32220 kN/m

TABLE 2. 10” BUOY DATA


Parameter Value Unit
Diameter 0.762 m
Length 1.129 m
Weight in Air 1.2851 kN
Buoyancy 3.4138 kN

TABLE 3. PIPELINE + BUOY DATA


FIGURE 1. PIPELINE ASSEMBLY SCHEME Parameter Value Unit
Outside Diameter 0.27305 m
The physical and geometric properties of the pipeline and Inside Diameter 0.2445 m
of the buoys are presented in the following tables. The buoys Axial Stiffness (EA) 2402252.49 kN
were fastened to the pipeline at every 8m measured from the Flexional Stiffness (EI) 20169.39 kN*m2
center of each buoy. Hydrodynamic Diameter 0.762 m
Weight in Air 2.23530 kN/m
Numerical Models Weight in Water -3.06225 kN/m

To perform the analyses of the lateral deflection procedure,


Petrobras considered the use of the SITUA-Prosim system. Performed Analyses
This system has been developed since 1997 [2], in cooperation
by Petrobras and LAMCSO (Laboratory of Computational Several numerical simulations were performed to guide the
Methods and Offshore Systems, at the Civil Eng. Dept. of lateral deflection procedure. The objective of these parametric
COPPE/UFRJ, Federal Univ. of Rio de Janeiro). It is a Finite- studies was to define adequate combinations of tugboat route
Element based nonlinear dynamic solver, that performs the and velocity for the lateral deflection procedure, Figure 2.
calculations with an interface with the Petrobras SGO, that
comprises a database with the seabed bathymetry and obstacles.

2
Von Mises (KN/m2)
800000 Direction (-5)
Direction (0)
700000
Direction (5)
600000 Direction (10)
500000 Direction (15)
400000 Direction (20)
Yield Stress
300000
200000
100000
0
0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0
Pipeline Length (m)

FIGURE 4. VON MISES STRESS IN PIPELINE – 2 KM/H

Von Mises (KN/m2)


800000 Direction (-5)
Direction (0)
700000
Direction (5)
600000 Direction (10)
500000 Direction (15)
400000 Direction (20)
Yield Stress
300000
200000
100000
0
0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0
Pipeline Length (m)

FIGURE 5. VON MISES STRESS IN PIPELINE – 1 KM/H


FIGURE 2. DIFFERENT TUGBOAT ROUTES
Traction (KN)

300.0

Some typical results are shown in the figures that follow: 250.0
Direction (-5)
Direction (0)
Figures 3, 4 and 5 show the maximum values of Von Mises 200.0 Direction (5)
stresses along the pipeline for several directions and three Direction (10)
150.0
tugboat velocities (the red line indicates the allowable stress); Direction (15)
Figures 6, 7 and 8 show the time-history of the tugboat forces 100.0
Direction (20)

for the same directions and velocities. The complete description 50.0

and results of these parametric studies is presented in reference 0.0


[5]. 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
Time (s)

FIGURE 6. TENSION IN THE CABLE – 3 KM/H


Von Mises (KN/m2)

800000 Direction (-5)


Direction (0)
700000
Direction (5)
Traction (KN)

300.0
600000 Direction (10)
Direction (-5)
500000 Direction (15) 250.0
Direction (0)
400000 Direction (20)
200.0 Direction (5)
Yield Stress
300000
150.0 Direction (10)
200000 Direction (15)
100000 100.0 Direction (20)
0 50.0
0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0
Pipeline Length (m) 0.0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
Time (s)
FIGURE 3. VON MISES STRESS IN PIPELINE – 3 KM/H
FIGURE 7. TENSION IN THE CABLE – 2 KM/H

3
Traction (KN)

300.0
Direction (-5)
250.0
Direction (0)
200.0 Direction (5)

150.0 Direction (10)


Direction (15)
100.0 Direction (20)
50.0

0.0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
Time (s) FIGURE 12. TRANSPORT – TYPICAL CONFIGURATION

FIGURE 8. TENSION IN THE CABLE – 1 KM/H The objective of the numerical simulations performed for
this transportation stage was to verify the pipeline behavior
Lateral Deflection Operation under environmental loadings with the transport configuration
defined by Petrobras.
Later, when the actual lateral deflection operation was In this configuration, shown in Figure 12, two cables with
performed, it could be observed that the pipeline behavior was 250m length connect the pipeline and the two tugboats. The
the same as predicted by the numerical simulations. Different tugboats velocities are about 5km/h (aligned at 355o from
stages of this procedure are shown in Figures 9, 10 and 11. north). The environmental loads are shown in Table 4. As the
pipeline remains totally submerged and the buoys at least 50%
submerged, wind effect was not considered.

TABLE 4. ENVIROMENTAL LOADS


Load Azimuth Value
Current 315o 1.19m/s
Wave 30o Hs = 1.6m; Tp = 9.5s
FIGURE 9. LATERAL DEFLECTION: INITIAL STAGE
The minimum and maximum velocities of tow were
defined by Petrobras as 5km/h and 9.26km/h. The maximum
velocity was defined to prevent buoy movement on the
pipeline. It was verified in previews operations, under similar
conditions, that buoys can slip if the tow velocity exceed
9.26km/h. This movement of the buoys makes the pipeline lose
buoyancy, and may experience excessively higher curvatures at
FIGURE 10. LATERAL DEFLECTION: INTERMEDIATE STAGE these points.
After several parametric studies, a second configuration
was proposed. In this configuration the two tugboats are not
aligned, as indicates in Figure 13.

FIGURE 11. LATERAL DEFLECTION: FINAL STAGE

OFFSHORE TRANSPORTATION

After the inicial lateral deflection operation was concluded,


the pipeline installation procedure proceeded by towing the FIGURE 13. TRANSPORT - ALTERNATIVE
pipe using a front and a back tugboat aligned at the CONFIGURATION
transportation route, as shown in Figure 12.
It was observed that, in such configurations, smaller values
of cable tensions are obtained when the pipeline is nearly
aligned to the resultant direction of the environmental
conditions. However, the cable tensions are still relatively high

4
during the whole operation. In such cases, maximum tensions
in the tugboat cable are approximately 51.1kN (5km/h velocity)
and 223.9kN (9.26km/h velocity).
It was also analyzed a situation in which the back tugboat
is disconnected and only the front tugboat is pulling the
pipeline. This configuration simulates a situation in which one
of the tugboats loses control and its cable is disconnected.
The results of the analyses indicated that, for all cases, the
maximum values of Von Mises stresses are not an issue, always
staying well below the yield stress of the material. The
objective then was to minimize tugboat forces.
The smaller values of cable tensions were found in
configurations where the back tugboat is disconnected. In such
cases, tensions in the cable are approximately 19.9kN (5km/h FIGURE 15. LOWER TRANSPORT VELOCITY
velocity) and 61.0kN (9.26km/h velocity). Therefore,
significant reductions were obtained in the cable tension: 61%
for the velocity of 5m/s, and 72.8% for the velocity of
9.26km/h.
Therefore, the results of the analyses indicated that the best
situation occurs when the back tugboat does not tension the
pipe, or simply when it is not connected to the pipe. Another
smaller boat can accompany the transport operation for safety
reasons, and to perform the maneuvers needed for the
subsequent pipeline launching process.
The pipeline transportation was performed by Petrobras
using only one tugboat and all numerical predictions related to
the pipeline behavior were confirmed. Different stages of the
pipeline transportation are shown in Figures 14, 15, 16 and 17.

FIGURE 16. HIGHER TRANSPORT VELOCITY

The maneuvers at installation area are shown in Figure 17.


At this time an auxiliary boat is already connected to the
pipeline.

FIGURE 14. PIPELINE LEAVING BEACH

The pipeline assumes different configurations depending


on transport velocity. The pipeline configuration for the
minimum tugboat velocity is shown in Figure 15; the
configuration for the maximum tugboat velocity is shown in
Figure 16.

FIGURE 17. MANEUVERS AT INSTALLATION AREA

5
FINAL REMARKS

This work presented the results of numerical simulations


and parametric studies on the pipeline behavior during some
stages of the installation procedure for the pipeline that
interconnect Xaréu-1 (PXA-1) platform to the buoy frame near
the coast of Ceará state, Brazil.
Such analyses were intended to verify the pipeline
behavior during the lateral deflection (when the pipeline leaves
the beach), and during transport to the installation area.
The results of the parametric studies allowed the definition
of the most suitable conditions for each stage of the operation.
Regarding the transport stage, it was noticed that the best
configuration to transport the pipeline, where tensions in the
tugboat cable are minimized, occurs when the pipeline
direction is close to the resultant of environmental loads and
the back tugboat is disconnected. The pipeline transportation
was performed using only the front tugboat and all numerical
predictions related to the pipeline behavior were confirmed. A
small boat was used just for safety reasons and to help
performing the necessary maneuvers during the pipeline
installation.

REFERENCES

[1] Masetti, I.Q., Barros, C.R.M., Jacob, B.P., Albrecht, C.H.,


Lima, B.S.L.P., Sparano, J. V., “Numerical Simulation of
the Mooring Procedures of the BGL-1 Pipeline Launching
Barge”. Procs of the 23rd International Conference on
Offshore Mechanics and Arctic Engineering – OMAE,
June 20-25, Vancouver, Canada, 2004.
[2] Jacob, B.P., Masetti, I.Q., “PROSIM: Coupled Numerical
Simulation of the Behavior of Moored Units” (in
Portuguese), COPPETEC-Petrobras Internal Report, Rio
de Janeiro, 1997.
[3] __, “SITUA-Prosim Program: Coupled Numerical
Simulation of the Behavior of Moored Floating Units –
User Manual, ver. 3.0” (in Portuguese), LAMCSO/
PEC/COPPE, Rio de Janeiro, 2005.
[4] SGO User Manual (in Portuguese) – Petrobras, Rio de
Janeiro, 2002.
[5] Silva, D.M.L., Bahiense, R. A., Jacob, B.P., Torres, F.G.S.,
Medeiros, A.R., Costa, M.N.V., “Numerical Simulation of
Offshore Pipeline Installation by Lateral Deflection
Procedure”. Procs of the 26rd International Conference on
Offshore Mechanics and Arctic Engineering – OMAE,
June 10-15, San Diego, USA, 2007.

S-ar putea să vă placă și