Documente Academic
Documente Profesional
Documente Cultură
MOSS-26
Danilo Machado Lawinscky da Silva1 Rodrigo Almeida Bahiense1 Breno Pinheiro Jacob1
1
LAMCSO – Laboratory of Computational Methods and Offshore Systems – PEC/COPPE/UFRJ
danilo@lamcso.coppe.ufrj.br, rodrigo@lamcso.coppe.ufrj.br, breno@lamcso.coppe.ufrj.br
2
PETROBRAS – Petróleo Brasileiro S.A.
ftorres@petrobras.com.br, robertomedeiros.nsg@petrobras.com.br
1
LATERAL DEFLECTION PROCEDURE Therefore, the simulation takes into account the actual
bathymetric information and obstacle positions [3,4].
The lateral deflection procedure basically consists of Three-dimensional frame elements were employed in the
performing the pipeline assembly on shore and deflecting it to generation of the numerical model for the pipeline. Three-
the sea using a tugboat. The characterization of this procedure dimensional frame elements were employed also for the
involves the determination of the better velocity and direction representation of the pipe segments with buoys. An equivalent
of the tugboat, in order to minimize the efforts on the pipeline element was used to represent both the pipeline physical
(especially due to the curvatures). properties and the buoy hydrodynamic properties. The
characteristics of the equivalent pipeline+buoy element are
Scenario and characteristics of pipeline shown in Table 3.
The pipeline was installed to rehabilitate a 10” pipeline TABLE 1. 10” PIPELINE DATA
that was in the end of its lifetime. The pipeline is located at the Parameter Value Unit
Xaréu field, interconnecting the PXA-1 platform to the buoy Outside Diameter 0.27305 m
frame, with the basic purpose of transporting the oil production Inside Diameter 0.2445 m
of Xaréu, Atum and Curimã fields, in Ceará State (northeast of Yield Stress of steel 414000 kN/m2
Brazil), to the NT ALIANZA Ship. Modulus of Elasticity of steel 207000 MPa
The pipeline has a total length of 721m and was assembled Axial Stiffness (EA) 2402252.49 kN
at Canto Beach, in Paracuru city, deflected from shore to the Flexional Stiffness (EI) 20169.39 kN*m2
sea, and transported with buoys to the installation location, Poisson Coefficient 0.3 -
where it was positioned on the guideline and sunk by flooding Density of steel 77 kN/m3
the buoys. Corrosion Protection 0.0027 m
During assembly, the pipeline was positioned on "big- Corr. Protection Specific Mass 9.32 kN/m3
bags" (bags of sand) as shown in Figure 1. Hydrodynamic Diameter 0.27875 m
Tube Length 12 m
Weight in Air 0.91099 kN/m
Weight in Water 0.32220 kN/m
2
Von Mises (KN/m2)
800000 Direction (-5)
Direction (0)
700000
Direction (5)
600000 Direction (10)
500000 Direction (15)
400000 Direction (20)
Yield Stress
300000
200000
100000
0
0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0
Pipeline Length (m)
300.0
Some typical results are shown in the figures that follow: 250.0
Direction (-5)
Direction (0)
Figures 3, 4 and 5 show the maximum values of Von Mises 200.0 Direction (5)
stresses along the pipeline for several directions and three Direction (10)
150.0
tugboat velocities (the red line indicates the allowable stress); Direction (15)
Figures 6, 7 and 8 show the time-history of the tugboat forces 100.0
Direction (20)
for the same directions and velocities. The complete description 50.0
300.0
600000 Direction (10)
Direction (-5)
500000 Direction (15) 250.0
Direction (0)
400000 Direction (20)
200.0 Direction (5)
Yield Stress
300000
150.0 Direction (10)
200000 Direction (15)
100000 100.0 Direction (20)
0 50.0
0.0 100.0 200.0 300.0 400.0 500.0 600.0 700.0
Pipeline Length (m) 0.0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
Time (s)
FIGURE 3. VON MISES STRESS IN PIPELINE – 3 KM/H
FIGURE 7. TENSION IN THE CABLE – 2 KM/H
3
Traction (KN)
300.0
Direction (-5)
250.0
Direction (0)
200.0 Direction (5)
0.0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
Time (s) FIGURE 12. TRANSPORT – TYPICAL CONFIGURATION
FIGURE 8. TENSION IN THE CABLE – 1 KM/H The objective of the numerical simulations performed for
this transportation stage was to verify the pipeline behavior
Lateral Deflection Operation under environmental loadings with the transport configuration
defined by Petrobras.
Later, when the actual lateral deflection operation was In this configuration, shown in Figure 12, two cables with
performed, it could be observed that the pipeline behavior was 250m length connect the pipeline and the two tugboats. The
the same as predicted by the numerical simulations. Different tugboats velocities are about 5km/h (aligned at 355o from
stages of this procedure are shown in Figures 9, 10 and 11. north). The environmental loads are shown in Table 4. As the
pipeline remains totally submerged and the buoys at least 50%
submerged, wind effect was not considered.
OFFSHORE TRANSPORTATION
4
during the whole operation. In such cases, maximum tensions
in the tugboat cable are approximately 51.1kN (5km/h velocity)
and 223.9kN (9.26km/h velocity).
It was also analyzed a situation in which the back tugboat
is disconnected and only the front tugboat is pulling the
pipeline. This configuration simulates a situation in which one
of the tugboats loses control and its cable is disconnected.
The results of the analyses indicated that, for all cases, the
maximum values of Von Mises stresses are not an issue, always
staying well below the yield stress of the material. The
objective then was to minimize tugboat forces.
The smaller values of cable tensions were found in
configurations where the back tugboat is disconnected. In such
cases, tensions in the cable are approximately 19.9kN (5km/h FIGURE 15. LOWER TRANSPORT VELOCITY
velocity) and 61.0kN (9.26km/h velocity). Therefore,
significant reductions were obtained in the cable tension: 61%
for the velocity of 5m/s, and 72.8% for the velocity of
9.26km/h.
Therefore, the results of the analyses indicated that the best
situation occurs when the back tugboat does not tension the
pipe, or simply when it is not connected to the pipe. Another
smaller boat can accompany the transport operation for safety
reasons, and to perform the maneuvers needed for the
subsequent pipeline launching process.
The pipeline transportation was performed by Petrobras
using only one tugboat and all numerical predictions related to
the pipeline behavior were confirmed. Different stages of the
pipeline transportation are shown in Figures 14, 15, 16 and 17.
5
FINAL REMARKS
REFERENCES