Sunteți pe pagina 1din 24

Ref. Title Page No. Ref. Title Page No.

2.1  Clearing and Grubbing 2-1  2.3.4 Method of Measurement 2-6


2.3.5 Basis of Payment 2-6
2.1.1  Description 2-1 
2.3.6 Items in the Bill of Quantities 2-7
2.1.2 Construction Requirements 2-1
2.1.3 Method of Measurement 2-1 2.4  Borrow Materials 2-7 
2.1.4 Basis of Payment 2-1
2.4.1 Description 2-7
2.1.5 Items in the Bill of Quantities 2-1
2.4.2 Location of Borrow Pits 2-7
2.2  Removal of Structures and 2.4.3 Borrow Material 2-7
Obstructions 2-1  2.4.4 Method of Measurement 2-7
2.4.5 Basis of Payment 2-7
2.2.1 Description 2-1
2.4.6 Items in the Bill of Quantities 2-7
2.2.2 Construction Requirements 2-1
2.2.2.1  General 2-1  2.5  Embankments 2-7 
2.2.2.2  Removal of Bridges, Culverts
2.5.1 Description 2-7
and Ditches 2-2 
2.5.2 Materials 2-8
2.2.2.3  Removal of Pipes 2-2 
2.5.3 Construction Requirements 2-8
2.2.2.4  Removal of Walls, Rocks and Boulders 2-2 
2.5.3.1  General 2-8 
2.2.2.5  Removal of Fences and Gates 2-2 
2.5.3.2  Trial Embankments Sections 2-9 
2.2.2.6  Removal of Wells and Shafts 2-2 
2.5.3.3  Foundation Preparation 2-10 
2.2.2.7  Removal of Utilities 2-2 
2.5.3.4  Embankment Construction 2-10 
2.2.2.8  Removal of Existing Pavement 2-3 
2.5.4 Testing 2-11
2.2.3 Method of Measurement 2-3
2.5.4.1  General 2-11 
2.2.4 Basis of Payment 2-3
2.5.4.2  Standards of Compaction for Soil
2.2.5 Items in the Bill of Quantities 2-3
and Granular Materials 2-11 
2.3  Roadway Excavation 2-4  2.5.4.3  Degree of Compaction for Rock Fill
Materials 2-11 
2.3.1 Description 2-4
2.5.4.4  Monitoring Settlement of Rockfill 2-12 
2.3.2 Classification of Roadway Excavation 2-4
2.5.5 Method of Measurement 2-12
2.3.3 Construction Requirements 2-4
2.5.6 Basis of Payment 2-12
2.3.3.1  Utilization of Excavated Materials 2-4 
2.5.7 Items in the Bill of Quantities 2-12
2.3.3.2  Drainage of Excavation Areas 2-4 
2.3.3.3  Obliteration of Disused Roadways 2-4  2.6  Subgrade Construction 2-12 
2.3.3.4  Rock Blasting 2-5 
2.6.1 Description 2-12
2.3.3.5  Excavation of Unsuitable Material 2-5 
2.6.2 Materials 2-13
2.3.3.6  Slopes, Subgrade and Ditches 2-5 
2.6.3 Construction Requirements 2-13
2.3.3.7  Unstable Materials outside
2.6.3.1  Subgrade in Cut 2-13 
Right-of-Way 2-6 
2.6.3.2  Subgrade in Embankment 2-14 
2.3.3.8  Disposal of Unsuitable and Surplus
2.6.3.3  Surface Tolerances 2-14 
Material 2-6
2.6.3.4  Maintenance of Finished Subgrade 2-14
Ref. Title Page No.
2.6.3.5 Drainage Blanket 2-14 
2.6.3.6 Subgrade Construction on Sabkha
and Gypsum Rich Soils 2-14
2.6.3.7 Subgrade Construction on top
of Dune Sand 2-15
2.6.4 Method of Measurement 2-15
2.6.5 Basis of Payment 2-15
2.6.6 Items in the Bill of Quantities 2-15

2.7  Excavation and Backfilling


for Structures 2-15 
2.7.1 Description 2-15
2.7.2 Excavation 2-15
2.7.2.1  General 2-15 
2.7.2.2  Temporary Support System 2-16 
2.7.2.3  Excavation for Major Structures 2-16 
2.7.2.4  Excavation for Box Culverts, Pipe
Culverts and Miscellaneous Structures 2-16 
2.7.3 Backfilling 2-17
2.7.3.1  General 2-17 
2.7.3.2  Backfilling for Box Culverts, Pipe
Culverts and Miscellaneous Structures 2-18 
2.7.4 Method of Measurement 2-19
2.7.5 Basis of Payment 2-19
2.7.6 Items in the Bill of Quantities 2-19

2.8  Earthwork for Pipe Trenches 2-19 


2.8.1 Description 2-19
2.8.2 Materials 2-20
2.8.2.1  Backfill Material 2-20 
2.8.3 Construction 2-20
2.8.3.1  Excavation for Pipe Trenches 2-20 
2.8.3.2  Backfilling 2-21 
2.8.3.3  Restoration of Surfaces 2-21 
2.8.4 Method of Measurement 2-21
2.8.5 Basis of Payment 2-21
2.8.6 Items in the Bill of Quantities 2-22
2.1 Clearing and Grubbing 2.1.3 Method of Measurement
1 Clearing and grubbing is measured in square meters
2.1.1 Description of the cleared area within the limits described in Item 1 of
1 This Sub-section describes removal and satisfactory Clause 2.1.1 above and approved by the Engineer.
disposal of all vegetation, surface debris and scattered 2 Trees with a trunk diameter 300mm or more when
stones and rocks within the limits of the actual road width measured 750mm above existing ground level are
(including the toes of fill and cut slopes and an additional measured by the number removed and delivered to the
5m wide band from both sides), easement areas and Employer or disposed of as directed by the Engineer.
borrow pits.
2 Removal of structures and similar obstructions and 2.1.4 Basis of Payment
removal of utilities are specified in Sub-section 2.2 -
1 The area of completed and accepted clearing and
"Removal of Structures and Obstructions".
grubbing work measured as provided for above, will be
paid at the unit rates stated in the Bill of Quantities, which
2.1.2 Construction Requirements rates shall be full compensation for labor, equipment and
1 The Contractor shall set out the approved other items necessary for completion of the work..
construction limits and the Engineer will designate all 2 Removal of trees with trunk 300mm diameter or
trees, shrubs, plants, vegetation, etc and other items that greater will be paid for by the number removed as stated
are to remain within the right-of-way (ROW). The above. Removal of trees with trunk less than 300mm
Contractor shall carefully preserve all such items from diameter is deemed to be included in the rate for clearing
damage or defacement. Trees to be removed and and grubbing
delivered for replanting shall be carefully handled. 3 Rates for all clearing and grubbing and tree removal
2 All surface objects, trees, stumps, roots, stones and shall include for filling holes and depressions with
rocks (up to 0.2 cu.m. or 500 kg individual size or weight), material as specified
and other protruding obstructions not designated to be
retained shall be cleared or grubbed to ground level. Non- 2.1.5 Items in the Bill of Quantities
perishable solid objects (such as boulders, rocks, concrete
i. Clearing and grubbing
blocks, etc.) which will be a minimum of 2m below the
ii. Removal and delivery or disposal of trees of
sub-grade or finished ground level may be left
300mm trunk diameter or greater
undisturbed at the Engineer’s discretion. If such non-
perishable objects are encountered within 2m below the
sub-grade or finished ground level, they will be removed 2.2 Removal of Structures and
and considered as unsuitable material, paid under Obstructions
Unclassified Excavation.
3 Stump holes and other holes from which 2.2.1 Description
obstructions are removed within the limits of construction,
1 This Sub-section describes the removal, wholly or in
shall be backfilled with suitable material and compacted in
part, and satisfactory disposal of all buildings, fences,
accordance with Sub-section 2.5 - "Embankments". Small
structures, abandoned pipelines, and any other
holes that are inaccessible to compaction / tamping
obstructions, as shown on the Drawings or directed by the
equipment shall be filled and tamped manually using a
Engineer, which are not designated or permitted to remain,
steel rod with a 10-15cm diameter steel disc attached to its
including salvaging of designated materials and backfilling
end.
the resulting trenches, holes and pits.
4 Perishable material shall be disposed of or burned
2 The Contractor shall examine the Site and record for
under the constant care of competent watchmen at such
himself all obstructions and utilities before the
times and in such a manner that any vegetation or other
commencement of the Works.
items designated to remain in the ROW, or other adjacent
property, will not be jeopardized. Burning shall be carried
2.2.2 Construction Requirements
out in accordance with applicable laws and ordinances.
5 Materials, stones, rocks, and debris which cannot be 2.2.2.1 General
burned and perishable materials, shall be removed from
1 The Contractor shall raze, remove and dispose of all
the ROW and disposed of at dumping areas off the Site,
buildings, foundations, structures, fences and other
approved by the concerned authorities, provided
obstructions, any portions of which are on the ROW,
permission of the respective property owners has been
except utilities and items for which other arrangements for
obtained in writing to dump such materials on their land.
removal have been made. All designated salvageable
The Contractor shall make all necessary arrangements
material shall be removed, without causing unnecessary
with property owners for obtaining such written
damage, and in sections or pieces which may be readily
permission at his own expense.

♦ 2-1 ♦
transported, and shall be stored by the Contractor at 2.2.2.4 Removal of Walls, Mortared and Loose Riprap,
approved locations, for later use or possession of others. Gabions, Rocks and Boulders
2 Unusable perishable material shall be destroyed.
Non-perishable material may be disposed of off the Site, 1 Masonry walls, mortared and loose riprap, gabions
provided permission of the respective property owners and accumulated stones, large rocks and boulders of
has been obtained in writing to dump such materials on individual size greater than 0.2 cu.m.or greater than 500 kg
their land. in weight which lie within the limits of the Works, shall be
removed and disposed of as directed.
3 Basements or cavities left by structure removal shall
be filled to the level of the surrounding ground and, if 2.2.2.5 Removal of Fences and Gates
within the prism of construction, shall be compacted to
the type of compaction within the range for the adjacent 1 When fences and gates enclosing pasture land or
roadway embankment as specified in Sub-section 2.5 – farm land are to be removed, the Contractor shall notify
‘Embankments’. the Engineer sufficiently in advance to permit the property
owner reasonable time to construct alternative fencing or
4 Salvaged pipe culverts and other re-usable materials
make other suitable arrangements.
shall be stored at accessible approved locations on Site
and shall become the property of the Employer. 2.2.2.6 Removal of Wells, Shafts and Falajs

2.2.2.2 Removal of Bridges, Culverts and Ditches 1 Existing wells and shafts, abandoned or active, which
lie within the limits of the Works, shall be dismantled,
1 Bridges, culverts and other drainage structures in
backfilled, and compacted. All salvageable materials shall
locations traversed by traffic shall not be removed until
be removed and stored at approved locations on Site. All
arrangements, detours and traffic management plans have
salvageable material shall become the property of the
been made by the Contractor and approved by ROP to
Employer. Wells shall be filled to the level of the
maintain the flow of traffic.
surrounding ground and, if within the prism of
2 Substructures in watercourses shall be removed construction, shall be compacted after obtaining the
down to the level of the natural stream bed. Those parts Engineer's permission to the type of compaction within
outside the stream shall be removed to 300 mm below the range designated.
natural ground surface. Where such portions of existing
structures lie wholly or in part within the limits for a new 2.2.2.7 Removal of Utilities
structure, they shall be removed to the extent necessary to
1 The Contractor shall liaise with the Engineer and
accommodate construction of the proposed structure.
shall notify all Utility Authorities and co-operate and
3 Steel bridges and timber bridges, designated to be coordinate with them in respect of removals and
salvaged shall be dismantled without causing unnecessary relocations.
damage. Steel members shall be match marked, unless
2 Unless shown otherwise on the Drawings,
this requirement is waived by the Engineer. All salvaged
realignment or relocation of active utilities will be to the
material shall be stored as previously specified for reuse
approval of the respective authorities and such work shall
or possession of others.
be coordinated by the Contractor. The Contractor shall
4 Blasting or other operations necessary for removal of perform the necessary coordination with the relevant
existing structures or other obstructions, and which may utility authorities ahead of time in order to avoid
damage new construction in the vicinity, shall be unnecessary delay to the Works.
completed prior to commencing the new construction.
3 The removal of all disconnected or abandoned
Explosives shall be used only as permitted by the
utilities within the ROW shall be performed by the
appropriate security authorities and shall be approved by
Contractor as directed by the Engineer, unless the utility
the Engineer. The Contractor shall observe the
authorities indicate their intention to carry out such
requirements of Section 1, Sub-section 1.9, Clause 1.9.2
removal and salvaging of materials, fittings, parts, etc.
for all blasting operations
4 The Contractor shall liaise with the Engineer and
5 The Contractor shall carry out a structural survey of
shall advise each affected utility authority in writing of his
all the existing buildings and structures located within the
proposed construction schedule and shall arrange for
blasting influence distance. The survey shall include
inspection, disconnection or interruption of services by the
detailed photographic records for the adjacent buildings
utility authorities as appropriate.
and structures before and after blasting, in order to avoid
later claims by public. 5 The Contractor shall be responsible for supporting
and protecting realigned utilities and existing utilities that
2.2.2.3 Removal of Pipes are to remain in place, for the duration of the Contract and
shall provide all necessary Temporary Works in this
1 All pipes unless otherwise directed shall be removed
respect, all in compliance with Section 1, Sub-section 1.8,
and precautions taken to avoid breaking or damaging the
Clause 1.8.3…..and the requirements of the relevant utility
pipes. The Contractor shall exercise utmost care during
owner. Any damage caused to utilities and attributable to
the removal of pipes so as to avoid unnecessary damage.
the Contractor shall be repaired at his expense.

♦ 2-2 ♦
6 All excavation and backfill shall conform to the will not be paid for directly but will be considered as
requirements of Sub-sections 2.3 - ’Road Excavation‘, 2.5 – subsidiary work related to other items in the Bill of
’Embankments’ and Sub-section 2.7 - ’Excavation and Quantities.
Backfilling for Structures‘, as appropriate.
2.2.4 Basis of Payment
2.2.2.8 Removal of Existing Pavement
1 The quantities of completed and accepted work,
1 The Contractor shall remove, wholly or in part, as measured as provided for above, will be paid for at the
shown on the Drawings or directed by the Engineer, relevant unit rates stated in the Bill of Quantities , which
existing asphalt, tiles and/or concrete pavement layers, rates shall be full compensation for equipment, tools,
and any granular or stabilized base courses., including labor, materials, transporting and dumping, and for other
disposal of debris and salvaging of designated materials, items necessary for the proper completion of the work.
and backfilling the resulting holes where and as instructed
by the Engineer. 2.2.5 Items in the Bill of Quantities
2 The Contractor shall examine the Site and record all
i. Removal of existing building (type and
obstructions and utilities that may be affected by removal
description), (Nr. or Length /
of existing pavements at the commencement of the Works.
Area / Volume as appropriate).
3 The Contractor shall raze, remove and dispose of old
ii. Removal of reinforced concrete (type,
pavement of different types, (i.e. down to the bottom of location, and dimensions), (cu.m).
the base course) or as directed by the Engineer, for the
iii. Removal of mass concrete (type, location
portions which are within the limit of Works.
and dimensions), ( cu.m).
4 Unusable perishable material shall be disposed of in iv. Removal of pre-stressed concrete (type,
accordance with the applicable laws and ordinances. Non- location and dimensions), ( cu.m.)
perishable material may be disposed of off the Site, v. Removal of curbs (Type), (lin.m.)
provided permission of the concerned authorities and/or vi. Removal of Tiles (Type and Size), (sq.m).
the respective property owner has been obtained in vii. Removal of pipe culverts (type
writing to dump such materials on their land. and diameter) , (lin.m.)
5 Cavities left by pavement removal shall be filled to viii. Removal of existing pavement
the level of the surrounding ground and, if within the (description and type), (cu.m).
prism of construction, shall be compacted to the type of ix. Removal of reusable road studs, (nr).
compaction specified in Sub-section 2.6 – ‘Subgrade x. Removal of steel safety barrier including
Construction’. post and foundations (dimensions and
Type), (lin.m).
6 The Contractor shall be responsible for supporting
xi. Removal of concrete safety barrier
and protecting existing Utilities that are to remain in place,
including foundations
for the duration of the Contract and shall provide all
(dimensions and Type), (lin.m.)
necessary Temporary Works in this respect. Any damage
xii. Removal of sign boards including
caused to utilities and attributable to the Contractor shall
post and foundations (size), (nr).
be repaired at his expense.
xiii. Removal of Floodway marker posts and
7 The Contractor shall be responsible for and shall foundations (size), (nr.)
ensure that pavement removal operations are completed xiv. Removal of re-usable steel safety barrier
without applying extreme vibration and heavy loading that including post and foundations
might damage the existing underground utilities. (dimensions and Type), (lin.m.)
2.2.2.9 Removal of Existing Road Furniture xv. Removal of re-usable concrete safety
barrier including foundations (dimensions
1 Road Furniture items such as curbs, tiles, steel and and Type), (lin.m).
concrete safety barriers, lighting poles, sign boards, etc. xvi. Removal of re-usable sign board including
which lie within the limits of the Works, shall be removed post and foundations (size), (nr.)
and disposed of as directed. xvii. Removal of reusable Floodway marker
posts including foundations (size), (nr).
2.2.3 Method of Measurement xviii. Removal of drainage protection
works (type), (sq.m.)
1 Removal of structures and obstructions is measured
xix. Removal of existing fences and
by number, length, area or volume as appropriate for the
gates (description and type), (lin.m.)
relevant work, unless Item 2.2.3 (2), applies. The rates
xx. Removal of existing block and
shall include in full for the removal, storage, protection
masonry walls (Size and Type) (cu.m)
and disposal of the structure or obstruction, including
xxi. Removal of ditches (Type and
items necessary for the proper completion of the work.
width), (lin.m).
2 If the Bill of Quantities does not contain separate xxii. Removal of bridges (dimensions,
items for removal of structures and obstructions, this work

♦ 2-3 ♦
type and description) (nr). ii. Material too wet to be compacted and where
xxiii. Removal of rocks and boulders circumstances prevent suitable in-place drying
larger than 0.2cu.m. or 500 kg prior to incorporation into the work.
(description), (cu.m). iii. Materials which are otherwise unsuitable for
xxiv. Removal of wells and shafts (description use in or under the embankment.
and location), (nr).
3 No excavation material shall be wasted without
xxv. Removal of sand dunes (location
written permission from the Engineer.
and description) (cu.m.)
xxvi. Removal of Light Poles including 4 If the Contractor chooses to excavate suitable
cabling and foundation (Size), (nr). material to waste or put it to other uses, and replace it by
borrow excavation for embankment areas, this shall be
undertaken at no extra cost to the Employer.
2.3 Roadway Excavation
5 Excavated rock which is not immediately suitable for
2.3.1 Description incorporation in the works can either be broken down to
acceptable sizes or wasted at Contractor's own expense. If
1 This Sub-section describes excavation in the cut such material is wasted or used in concrete, granular
sections of the roadway, including watercourses, ditches subbase, aggregate base, asphalt mixtures or any other
and wadi relocations (but excluding borrow pits and works, the Contractor shall replace it by borrow
structural excavation) all as and where shown on the excavation for embankment at no extra cost to the
Drawings, and hauling the excavated material either to Employer.
locations for roadway embankments or to stockpiles or to
6 Where shown on the Drawings or directed by the
waste.
Engineer, salvaged materials such as existing concrete,
2 The work also includes any necessary excavations bituminous or other pavements shall, be stockpiled for a
outside the ROW ordered by the Engineer to safeguard specific purpose or for future use. Such materials shall be
and protect the Works, including diversion of existing excavated and handled in a manner that will exclude
wadi channels; excavation of materials obstructing or foreign or undesirable material. Stockpiles shall be neatly
impairing the flow along stream channels; and excavation formed and maintained in an approved manner.
of unstable materials which may slide or encroach into
7 Where specified or directed by the Engineer, suitable
ditches or onto the ROW. Disposal of all such excavated
topsoil material shall be stockpiled during excavation
materials shall be as instructed by the Engineer.
operations and shall subsequently be spread and
compacted on embankment slopes and elsewhere as
2.3.2 Classification of Roadway Excavation directed, to facilitate re-growth of vegetation.
1 Road excavation shall be considered as ’Unclassified
2.3.3.2 Drainage of Excavation Areas
Excavation’ which includes all materials encountered of
any nature including silts, clays, sand, gravel, granular 1 During construction, surfaces in excavation areas
materials, all cohesive and fractured, jointed cohesionless shall be adequately drained at all times. Side ditches or
materials and/or massive rock and unsuitable material. gutters emptying from cut to embankment shall be so
2 Any information concerning properties of the soil constructed as to avoid damage to embankments by
which may be shown on the Drawings, in the Bill of erosion.
Quantities, in supplementary reports, or as a result of 2 The Contractor shall, at an early stage of the Works,
discussion with the Engineer or others shall be considered provide adequate drainage by scheduling ditch and other
as gratis and shall not be a basis for the Contractor's construction so as to prevent saturation or erosion of
determination of his bid prices. embankments and cut slopes. All such drainage ditches
and construction grades shall be cleaned and trimmed at
2.3.3 Construction Requirements regular intervals and when directed to maintain an
unobstructed runoff of stormwater during construction.
2.3.3.1 Utilization of Excavated Materials
3 Damage to the Works attributable to saturation or
1 All materials removed from the excavation shall be erosion of slopes during the period of execution through
used in the formation of the embankment, sub-grade, failure to provide adequate drainage shall be repaired by
shoulder, dykes, and at such other places as directed, the Contractor at his own expense.
unless it is declared unsuitable and ordered to be wasted 4 Whenever groundwater is encountered which may
by the Engineer. adversely affect construction, the Contractor shall advise
2 Unsuitable material shall include: the Engineer who will evaluate the situation and order
i. Unstable materials incapable of being necessary remedial measures.
compacted to the specified density using
mechanical compaction methods at optimum 2.3.3.3 Obliteration of Disused Roadways
moisture content for the equipment being used 1 Obliteration of roadways which are no longer in use
for compaction. shall include filling of all ditches and rough grading of the

♦ 2-4 ♦
old roadway to produce within the ROW a neat and well for potential failure planes and the necessary remedial
drained ground surface. measures shall be taken, as approved by the Engineer, at
the Contractor’s expense.
2.3.3.4 Rock Blasting
2.3.3.5 Excavation of Unsuitable Material
1 Rock blasting explosives may comprise a diversity of
systems, including dynamite explosives, watergels, slurry 1 Unsuitable materials are materials that do not
explosives and slurry blasting agents, pumpable blasting comply with the requirements for suitable materials as
agents, emulsion explosives and aluminized explosives. described under Clause 2.5.2 below.
Whenever instructed by the Engineer, blasting shall be 2 Where excavation to finished grades and cross
carried out after pre-splitting the rock mass by using small sections exposes unsuitable material in the sub-grade,
localized charges in pre-drilled holes. slopes or ditch inverts, etc the Engineer may require the
2 When blasting of rock slopes is carried out, a Contractor to remove the unsuitable material and backfill
reasonably uniform face shall be left, regardless of the excavated areas using approved material. The
whether or not the excavation is carried beyond the Contractor shall plan his operations so that necessary
specified side slopes as shown on the Drawings. All cross section measurements are taken before such backfill
breakage and slides shall be removed and disposed of as is placed.
directed. A dust control system shall be designated by the 3 Unsuitable material shall be disposed off as directed.
Contractor and shall be implemented during rock blasting Wasted unsuitable material shall not be deposited on any
after obtaining the Engineer’s approval. cropland.
3 All drilling and blasting shall be done in such a 4 When the Contractor is directed to excavate
manner as will most nearly complete the excavation to the unsuitable material below the surface of the original
required grade lines, and produce the least possible ground in fill areas, other than that required for clearing
disturbance of the material to be left in place. Blasting by and grubbing, the depth to which unsuitable material shall
means of drill holes, tunnels, or any other methods shall be removed will be determined by the Engineer. The
be entirely at the Contractor's risk. Explosive materials Contractor shall plan the excavation so that cross sections
shall be stored and kept under the constant surveillance of are taken before and after material has been removed.
the Royal Oman Police.
2.3.3.6 Slopes, Sub-grade and Ditches
4 Where necessary or directed, the Contractor shall
provide heavy mesh blasting mats or controlled blasting 1 All excavated slopes, sub-grade and ditches shall be
for protection of persons, properties, and the Works. If, in finished true to lines, grades and cross sections as shown
the opinion of the authorities and the Engineer, blasting on the Drawings.
would be dangerous to persons or adjacent structures, or 2 Slopes, except in massive rock or other material
is being carried out in an unsafe or unacceptable manner, which require special treatment, shall be trimmed to
the Engineer may prohibit blasting and order the rock to slopes not steeper than the specified slope angles and
be excavated by other means. rounded at top and bottom to a smooth profile to blend in
5 During explosion works, traffic shall be suspended with the adjacent terrain. Material shall not be loosened
from the routes linking to the Site and all diversions and beyond the specified slope lines. High cut areas shall
other arrangements shall be carried out in full continuously be monitored by an engineering geologist or
coordination with the Royal Oman Police. The Contractor a geotechnical engineer.
shall secure approval of his schedule for such 3 In cuts where earth overlays a rock formation, slopes
interruptions and his proposed methods for safeguarding shall be benched in an approved manner.
the public and property.
4 Ditches of all types shall be excavated and trimmed
6 Excessive blasting will not be permitted. neatly in conformity with the specified grades and cross
Overbreakage and the backfilling thereof shall be at the sections. All projecting rock, stumps, roots or similar shall
Contractor’s expense. Any material outside the approved be removed. Ditches include side ditches, interception
cross section limits which may be shattered or loosened ditches in the berm of cut slopes, furrow ditches, irrigation
because of blasting shall be removed by the Contractor at ditches, wadi relocations, etc.
his own expense. All rock slopes with loose material shall
5 Where the sub-grade is composed of rock as defined
be scaled by workmen and all loose material removed at
in Sub-section 2.6 – ‘Sub-grade Construction’, it shall be
the Contractor’s expense.
undercut to a depth of 200 mm below top of sub-grade to
7 Backfilling of overbreakage shall be carried out as allow for subsequent placing and compaction of the
directed, using approved soil or crushed materials or other leveling sub-grade layer in accordance with Sub-section
special aggregate or cyclopean concrete, as shown on the 2.6 – ‘Sub-grade Construction’, paragraph 2.6.3.1.
Drawings or as directed by the Engineer. Undrained
6 The sub-grade in cut, where the soil is unsuitable for
pockets shall not be left in the surface of the rock.
retention as the sub-grade layer, shall be sub-excavated to
8 Following blasting, cleaning and scaling rock slopes, a depth of 200 mm below top of sub-grade to allow for
the face, benches and back of the slope shall be inspected subsequent placing and compaction of the sub-grade layer.

♦ 2-5 ♦
If the material of the sub-grade is suitable for retention as 2 Unclassified Excavation shall be measured by cu.m.
sub-grade layer then it shall be scarified to the required of material excavated, hauled away and either wasted,
depth, watered and compacted in accordance with Section stockpiled, or deposited on or in vicinity of roadway
2.6 – ‘Sub-grade Construction’, paragraph 2.6.3.1. embankments and dykes. Measurements shall be of
7 The Engineer will periodically check all or any part of volumes computed from the cross sections shown on the
the work, to determine conformance to the correct lines, Drawings and the original ground elevations taken jointly
grades and elevations. Tolerances on finished sub-grade by the Engineer and the Contractor after clearing and
levels and on levels of the surface at the underside of the grubbing operations. Rates shall include for costs of
sub-grade layer shall be as specified in Sub-section 2.6 – supporting sides of excavation where necessary, keeping
‘Sub-grade Construction’, Paragraph 2.6.3.3. excavations free from water, proper formation of
embankments, trimming of slopes, preparation and
8 In cases where rock or soil excavations reveal that
completion of the roadway, sub-grade, dykes and
the adopted cut slopes are not suitable and if failures
shoulders and scarifying for suitable sub-grade material.
occur during or after completion of the excavation works
and while the Contractor is still on Site, the Engineer may 3 Excavation of unstable material (from areas outside
request the Contractor to re-excavate according to the the ROW) shall be measured by cu.m. of material
newly established cut slopes, the extra work will be excavated, hauled away and disposed of as directed,
measured and valued as Unclassified Excavation at the completed and accepted. Measurements shall be of
same rate given in the Contract. However, in such case, volumes computed from surveyed cross sections of
the Contractor may submit a proposal for any other original and final ground elevations. When cross
alternative solution for the stability of the cut slopes, for sectioning is impractical in the opinion of the Engineer,
the Engineer’s appraisal and final decision. approval may be given to measure volumes in the
vehicles removing such excavated material.
2.3.3.7 Unstable Materials outside Right-of-Way 4 Ditch excavation and excavation of unstable material
1 Materials outside the ROW or ditch slopes which, in are considered part of the unclassified excavation.
the opinion of the Engineer, are potentially unstable and 5 Rock blasting, backfilling of overbreakage, trimming
liable to slide or encroach into the ROW or into the ditches, and grading of cut slopes, ditches and of other below-sub-
shall be excavated and disposed of as specified for grade surfaces, drainage of excavation areas, obliteration
unsuitable material, unless it is approved for use as of disused roadways, and other ancillary excavation
embankment fill. Works shall not be measured for direct payment, but shall
be considered as subsidiary work the costs of which will
2.3.3.8 Disposal of Unsuitable and Surplus Material be deemed to be included in the rates for Unclassified
1 Unsuitable and surplus materials disposed of within Excavation
approved areas shall be spread, leveled and shaped as 6 Excavation under water shall be measured by cu.m.
directed so as to present a neat and tidy appearance. No of material excavated, hauled away and disposed of as
materials shall be disposed of in such a way as to directed, completed and accepted (including any side
adversely affect natural drainage courses or to cause support or other enabling works). Measurements shall be
damage to the highway or adjacent public or private of volumes computed from surveyed cross sections of
property. original and final ground elevations. When cross
2 If approved by the Employer, Government land may sectioning is impractical in the opinion of the Engineer,
be used for disposal to the maximum extent practicable. If approval may be given to measure volumes in the
private land is used for disposal, the Contractor shall vehicles removing such excavated material.
secure the consent of the landowner or tenant and, if 7 Hauling of excavated materials shall not be
necessary, and at his own expense, pay for the use of such measured for direct payment, but shall be considered as
land. The use of cropland for disposal purposes will not subsidiary work the cost of which will be deemed to be
be permitted. included in the rates for Unclassified Excavation,
regardless of the distance required for hauling the
2.3.4 Method of Measurement materials to an approved dumping area.

1 All excavated material of whatever type (except for 8 Excavation, Stockpiling and recompaction of suitable
unauthorized undercut below top of sub-grade or topsoil material shall be measured by cubic meter, laid,
excavations taken wider than required) shall be measured completed and accepted as directed by the Engineer.
as ‘Unclassified Excavation’ which shall be deemed to
include all materials encountered of any nature, including 2.3.5 Basis of Payment
silts, clays, sand, gravel and granular materials and 1 The amount of completed and accepted work,
fractured, jointed and massive rock, whether weak or measured as provided for above, will be paid for at the
strong, and unsuitable material, as approved and unit rates for the various items in the Bill of Quantities,
instructed by the Engineer. which rate shall be full compensation for equipment, tools,

♦ 2-6 ♦
labor, materials, transporting and hauling, and for other stockpiled in the vicinity, ready for re-use prior to
items necessary for the proper completion of the work. abandonment of the pit.
7 Prior to abandonment of any borrow pit or borrow
2.3.6 Items in the Bill of Quantities area, the Contractor shall spread and level the original
overburden over the exposed surfaces and clean up, grade
i. Unclassified Excavation
and contour the pit or area and the adjoining properties
ii. Excavation of unstable material
occupied during execution of borrow operations, whether
outside Right-of-Way
Government, or privately-owned, all to the satisfaction of
iii. Unclassified Excavation under water
the Engineer.
iv. Excavate and Stockpile Suitable topsoil and
recompact as directed
2.4.3 Borrow Material
2.4 Borrow Materials 1 Borrow shall be material approved by the Engineer
as meeting the requirements for the particular
2.4.1 Description embankment, backfill or other use for which the material
is intended.
1 This Sub-section describes excavation of suitable 2 The Contractor shall submit representative samples
material from borrow pits, channels and designated of materials from each of the proposed borrow pits or
borrow areas and hauling to locations of embankments or borrow areas. A minimum of three sets of tests shall be
to stockpiles, all as shown on the Drawings, or as directed performed for each borrow area for each type of material.
by the engineer. No borrow material shall be brought to the site or used in
2 The Contractor shall be responsible for locating the Works before its approval.
suitable borrow pits and for the suitability and sufficiency 3 The Engineer will periodically require follow-up
of borrow materials to meet the specified embankment testing of borrow materials to verify that no change in
and other backfilling requirements. quality has occurred since the original approval.
3 Borrow pits shall be utilized if there is insufficient
suitable excavated material to satisfy the embankment 2.4.4 Method of Measurement
and other backfilling requirements or if the Contractor
chooses to excavate suitable material to waste or put it to 1 Borrow Excavation shall be measured by cu.m. of
other uses, and replace it by suitable material excavated suitable material excavated, hauled and used in the proper
from borrow pits at the Contractor’s expense. formation of embankments, including trimming of slopes,
preparation and completion of the roadway sub-grade,
shoulders and dykes.
2.4.2 Location of Borrow Pits
2 The quantity of borrow excavation shall be
1 Generally, the borrow pits shall not be located within determined by calculating the total quantity of filling after
50 m from the toe of embankment slope or top of cut or compaction and deducting therefrom the total quantity of
formed slope, unless otherwise approved by the Engineer. unclassified excavation less an allowance for material
2 In no case shall borrow pits be located within 200 m condemned by the Engineer as unsuitable for filling.
downstream of a drainage structure without the written
approval of the Engineer. Unauthorized borrow pits shall 2.4.5 Basis of Payment
be backfilled and compacted, as directed by the Engineer,
1 The amount of completed and accepted work,
at the Contractor's expense. measured as provided for above, will be paid for at the
3 In each case where a borrow pit is proposed within unit rates for borrow excavation in the Bill of Quantities ,
privately-owned property, the Contractor shall secure the which rate shall be full compensation for equipment, tools,
consent of the landowner in writing, if necessary, and labor, materials, transporting hauling and placing, and for
shall, pay for the use of the material and land. The other items necessary for the proper completion of the
work.
Contractor shall be solely responsible for any claims for
compensation or complaints arising out of borrow pit
operations.
2.4.6 Items in the Bill of Quantities
4 The Contractor shall be responsible for the stability i. Borrow excavation.
of the side slopes of borrow pits and channels at all times,
until the pit or channel is abandoned. 2.5 Embankments
5 Details of the Contractor's proposed haul routes and
traffic arrangements in relation to borrow pit operations 2.5.1 Description
shall be submitted for approval before any borrow
1 This Sub-section describes construction of roadway
excavation commences. embankments, including preparation of the areas upon
6 Overburden and any unsuitable top layers within which they are to be placed; placing and compacting
each borrow pit shall be completely removed and approved material within areas where unsuitable material
has been removed; and placing and compacting approved

♦ 2-7 ♦
embankment material in holes, pits and other depressions also be used in these conditions, except for the top
within the constructed area, all in accordance with the 600mm of the embankment.
lines, grades and cross sections shown on the Drawings. 6 Where embankments are to be constructed using
material classified as A3 (AASHTO M 145) or other
2.5.2 Materials material subject to side slope erosion or requiring
confinement for stabilization purposes, the embankment
1 Materials suitable for embankment shall be of classes
A-1, A-2-4, A-2-5 or A3 ‘when confined’ groups as in plating or confining layer shall be constructed using
AASHTO M145 and complying with Table 2.5.2.1, and AASHTO M 145 Class A-1-a, A-1-b, or A-2-4 materials or as
shall be used when available, except for rock fill otherwise approved.
embankments. If material of this character is not available, 7 The material used in rockfill embankments shall
then material from A-2-6, A-2-7, A-4, A-5, groups (AASHTO consist predominantly of rock fragments of such size that
M145) may be used provided it complies with the the material can be placed in layers of the thickness
requirements of Table 2.5.2.1; however, special attention prescribed conforming to the requirements stated in Table
shall be given to its suitability for the particular 2.5.2.2. The size distribution of rockfill shall be determined
construction according to CIRIA Special Publication 83: Manual on the
Requirements use of Rock in Coastal and Shoreline Engineering –
1 Maximum dry density not less than 1.7 Appendix 2.
(AASHTO T-180 Method D)
2 Organic matter not more than 5% (AASHTO T- Requirements
267) 1 Maximum particle size ........1/2 loose layer
3 thickness
Gypsum content not more than 5%.
2
4 Passing 0.42mm (Sieve # 40) ........25% maximum
No use of A-6, A-7 soil (AASHTO M-145)
Uniformity coefficient, Cu.......5 minimum, where
5 Maximum size not more than 1/2 of the layer Cu = D60/D10
thickness 3 D60 = the Particle size at which 60% passes
6
Plasticity Index (P.I.) less than 20% D10 = the Particle size at which 10% passes
4-day soaked C.B.R. should not be less than 8%
Table 2.5.2.2: Rock Suitable for Embankment
. 7 (AASHTO T-193) when compacted at 100%
maximum dry density in accordance with 8 Rockfill material shall be obtained from quarries and
AASHTO T-180 Method D.
shall be sound, dense, hard and durable rock capable of
Table 2.5.2.1: Soil Suitable for Embankment being spread and compacted as specified. Individual
2 The 200 mm depth of embankment sub-grade layer pieces are to be clean and angular. It shall be the
immediately below the bottom of sub base shall consist of Contractor's responsibility to excavate material from rock
selected sub-grade material having a 4-day soaked C.B.R. cuts, whether by blasting or other means, so that all
of at least 25% when tested in accordance with AASHTO excavated materials are of suitable size.
T193 and when compacted at 100% Modified Proctor 9 When suitable materials of widely divergent
Density in accordance with AASHTO T-180D, with a characteristics are drawn from different sources, such
gradation and P.I. as specified under Sub-section 2.6 – materials may, if approved, be mixed to meet the
‘Sub-grade Construction’. embankment requirements. Rock and other materials shall
3 The 600 mm depth of embankment immediately be incorporated in such manner as to avoid segregation
below the sub-grade layer shall consist of suitable and an accumulation of boulders, etc., at the toe of
material having a 4-day soaked C.B.R of at least 15% when embankment slopes.
compacted to 95% maximum dry density in accordance 10 Logs, trees, stumps, weeds, heavy grass, vegetable
with AASHTO T-180D and tested in accordance with matter or other undesirable and non compatible materials
AASHTO T-193 with a P.I. not more than 15%. If rockfill is shall not be placed in embankments.
used for the bottom 400 mm depth then these
11 Rocks larger than 100 mm in any dimension shall not
requirements shall apply to the top 200 mm depth below
be used as fill material in areas where piling works are to
the sub-grade layer.
be carried out.
4 Rockfill shall not be used in the top 200 mm of the
embankment below the sub-grade. If found necessary and 2.5.3 Construction Requirements
if approved by the Engineer, water may be added as
required to achieve maximum compaction. 2.5.3.1 General
5 In areas subject to flooding and prolonged inundation 1 Prior to placing embankment material on any area,
of the embankment, such as at bridge and culvert sites, the ground shall have been cleared and grubbed as
the material used in embankment shall conform to specified in Sub-section 2.1 – ‘Clearing and Grubbing’, and
AASHTO M 145, Class A-1-a, A-1-b, A-2-4. Rockfill can the foundation prepared as specified herein.

♦ 2-8 ♦
2 Equipment used for foundation preparation and for 11 All embankment side slopes shall be neatly finished
placing, spreading and compacting embankment materials true to the lines and not steeper than the slope angles as
shall be of approved types and furnished in sufficient shown on the Drawings. The bottom (toe) of side slopes
numbers for the purposes intended. Provision and use of shall be graded to a well rounded, smooth profile to blend
such equipment shall conform with Section 19 ‘Plant and in with the adjacent terrain.
Equipment’ 12 Where directed by the Engineer, the side slopes of
3 Draglines shall not be used to construct embankment rockfill embankments shall be thoroughly blanketed with
unless approval is given and only when special A-1, A-2-4 material, and compacted to the satisfaction of
procedures are adopted to keep the layers uniform and the the Engineer
embankment properly graded and well-drained at all times. 13 The Engineer may permit the Contractor to utilize
4 Surfaces of embankment layers shall be kept suitable surplus material at his own expense to widen
properly shaped and drained at all times. The Contractor embankments or flatten slopes, etc within the right-of-way.
shall utilize a sufficient number of motor graders or Surplus material used in such manner shall be compacted
tractors to level and maintain the surface of each layer of to 90 per cent of maximum density. When widening
embankment during all placing and compacting embankments, the Contractor shall bear the cost of
operations. modifying the culverts and any protection work necessary.

5 Whenever feasible, trucks, scrapers, tractors, loaders 14 Rockfill shall not be used within 5m of a structural
and other heavy hauling equipment shall be routed over element (next to bridge abutments footings, etc). In some
the embankment in such a manner as will contribute specific cases, rock fragments not exceeding 75mm
effectively to compaction of the fill material. particle size may be used next to structural elements, but
only after obtaining the Engineer’s approval on the
6 Where an embankment is to be constructed over an
location and extent of the work.
area previously occupied by a building basement, cellar,
irrigation canal, well, any previous excavation, or adjacent 15 Rockfill shall not be used within 600 mm of top and
to structures, and where the proper use of normal bottom of box and pipe culverts. Subgrade material shall
compaction equipment is not practicable, the be used in these areas up to width excavated for
embankment shall be constructed and compacted in structures.
accordance with the backfilling requirements of Sub- 16 Potable or sea water can be used for all embankment
section 2.7 – ‘Excavation and Backfilling for Structures’ construction works, except that only potable water shall
until the use of normal compaction equipment is be used for compaction of fill material within 1m from all
practicable. Layers shall not exceed 200 mm thickness surfaces of structures.
(before compaction) and shall be compacted to the degree
of compaction specified for the embankment. The 2.5.3.2 Trial Embankments Sections
embankment construction under this item shall be 1 If shown on the Drawings, or if required by the
measured and paid under the requirements of Clause Engineer, a trial embankment shall be constructed. The
2.7.4.8:’“Unclassified Structural Excavation’ trial section shall be at least 2 lanes wide by 100 m long at
7 Each embankment layer shall be tested and approved approved locations at or adjacent to the Site. Compaction
prior to placing the following layer in accordance with and other equipment used shall be as specified in Section
Clause 2.5.4 ‘Testing’. 19 ‘Plant and Equipment’.
8 The Engineer may at any time order suspension of 2 The initial sections of rock embankment shall serve
delivery of materials to the embankment sites until as the trial sections for rock fill, in order to establish the
previously delivered materials have been properly placed optimum degrees of consolidation for the different layer
and preceding layers are leveled and uniformly compacted thickness. This shall be obtained by compaction trials
to the specified density. correlating number of passes of the roller with settlement
9 Unacceptable material placed in any embankment of the layer, or by different approved methods. The
shall be removed and disposed of by the Contractor at his maximum permitted layer thickness shall be related to the
own expense, immediately after receiving the Engineer’s unit weight of the vibratory roller and for compaction, as
instructions in this regard. Any expected delay with the given in Table 2.5.3.1 and shall not exceed 800 mm loose
removal of such material shall be coordinated and agreed thickness.
with the Engineer.
10 The Contractor shall be responsible for the stability
of all embankments and shall replace all embankment
sections which, in the opinion of the Engineer, have been
damaged or displaced due to carelessness or neglect on
the part of the Contractor, or due to normally occurring
natural causes, such as storms, and not attributable to the
unavoidable movement of the natural ground upon which
the embankment is constructed.

♦ 2-9 ♦
Maximum Thickness of 6 Rockfill shall not be placed on any slopes steeper
Minimum Roller Mass*
Layer than 1:1. All slopes steeper than 1:1 shall therefore be re-
(Kg/m Width)
(Loose Thickness) graded to a slope of 1:1 or milder and all vertical faces and
400 mm 2300 - 2900 overhangs removed.
500 mm 2900 - 3600
2.5.3.4 Embankment Construction
600 mm 3600 - 4300
700 mm 4300 - 5000 1 Roadway embankment consisting of soil or granular
800 mm > 5000 material shall be placed in horizontal layers not exceeding
* For multiple rollers, this shall be assumed as 200 mm compacted thickness, compacted as specified and
approved prior to placing the next layer. The thickness of
the high axle load.
the first layer over areas of Class A-3 dune sand may
Table 2.5.3.1: Maximum Layer Thickness / Minimum Roller exceed 250 mm in order to bridge these areas.
Approximately uniform thickness of each layer shall be
Mass Requirements
achieved prior to compaction. As the compaction of each
2.5.3.3 Foundation Preparation layer progresses, continuous leveling and working of the
material shall be carried out to ensure uniform density.
1 If the original surface upon which embankment is to The correct moisture content shall be maintained at all
be placed is an existing pavement, the surface shall be times.
ploughed, scarified, or otherwise broken up regardless of
2 Where embankments are to be constructed to a
the height of the embankment to be placed thereon.
height in excess of 1.5 m above top of original ground
2 Clearing and grubbing, and removal of tree stumps, level, the Engineer may approve layers up to 250 mm
shall be undertaken. The degree of compaction for the compacted thickness if these layers are located at depths
area to be cleared shall then be determined. The top 150 greater than 1.5m from the final elevation of embankment
mm of the surface on which the embankment is to be and if the Contractor's equipment and the nature of the
placed shall be scarified, brought to a uniform moisture material result in the required density throughout the layer
content within the specified range, and compacted to the thickness.
density specified for the embankment. Hard and smooth
3 When the moisture content of the embankment
surfaces are to be roughened before filling is placed.
material does not fall within the required moisture range,
3 Where embankment is to be placed over topsoil (optimum moisture ± 2%) water shall be added and
containing unsuitable organic material which does not thoroughly mixed into the soil by approved methods or
meet the requirements of Table 2.5.2.1, the ground shall the material shall be aerated, whichever is necessary to
be stripped off to a depth of 200mm and the cleared adjust the material to the required moisture content.
surface shall be scarified to a minimum depth of 200mm
4 When water is added to embankment material, the
or as directed by the Engineer, brought to a uniform
amount added shall be sufficient to provide a moisture
moisture content within the specified range, and
content within the required range plus a reasonable
compacted to the density specified for the embankment.
additional amount to compensate for evaporation and
4 Where embankment is to be placed and compacted other unavoidable losses. Water added in excess of this
on hillsides or where new embankment is to be amount shall be removed by aeration or other approved
compacted against existing embankments or where means at the Contractor's expense. Satisfactory methods
embankment is built part width at a time, the slopes and sufficient equipment shall be used for the furnishing
steeper than 3:1 (H:V) when measured at right angles to and handling of the water in a manner that will minimize
the road centerline shall be continuously benched as the loss due to evaporation or waste.
embankment is brought up in layers. Benching shall be of
5 Embankments that consist of rock-soil material with
sufficient width to permit operation of spreading and
sufficient soil to make rolling feasible shall be placed and
compaction equipment, and in any case not less than 2 m
compacted in an approved manner and to the required
wide except where insufficient width is available between
degree of compaction. Water shall be added as and when
existing and new embankments. Each horizontal cut shall
directed to assist in the compaction of such materials.
begin at the intersection of the original ground and the
vertical sides of the previous cuts. The vertical face of 6 In the case of embankments which are to be formed
each bench shall not be less than 1 m in height and not of approved rock-soil material containing an appreciable
exceed 2 m. Approved benching shall be measured as quantity of rock fragments (normally not exceeding 30%
unclassified excavation. greater than 80mm) and which cannot be placed in layers
of the thickness prescribed without crushing, pulverizing,
5 Where embankment is to be placed and compacted
or otherwise breaking down the fragments, the
on wadi slopes, the entire slope area shall be graded and
embankment may be constructed in layers not exceeding
trimmed to remove any vertical faces and overhangs. The
in thickness twice the average size of the largest rock
final graded slope shall not be steeper than 1.5H:1V. The
fragments and in any case not exceeding 600 mm (before
slope shall then be continuously benched as the
compaction).
embankment is brought up in layers, all as described
above for embankment on hillsides.

♦ 2-10 ♦
7 Rockfill materials shall be placed in such a manner materials. The ‘maximum density’ of soil type materials
that the larger rocks are well distributed and the voids are shall be the modified maximum density determined in
filled to the maximum practical extent by smaller particles accordance with AASHTO T 180 (Method D). The ‘relative
of rocks, gravel or approved granular materials. Each layer density’ shall be the relative density determined in
shall be bladed into a neat and homogeneous mass prior accordance with ASTM D 4254, which identifies the state
to compaction. Any rocks found protruding from the of compactness of the material with respect to its loosest
leveled surface shall be removed and replaced by smaller and densest state. The relative density shall be the
particles. Initial breakdown compaction shall be standard to which the field density is referred for
performed with heavy bulldozers. The top level of each comparison in the case of cohesionless, free draining
layer must be surveyed before and after compaction and granular materials.
approved by the Engineer before the next layer is placed. 2 Soil type materials shall be compacted to at least
Oversize rock pieces (i.e. exceeding the maximum particle 90% modified maximum density for the full depth of
size defined in Table 2.5.2.2 by not more than 10%) may embankment; except for the 600 mm of embankment
be used in high rockfill embankments to a level 3 meters material immediately below the sub-grade layer that shall
below sub-grade. be compacted to at least 95% modified maximum density.
Moisture content shall be within plus or minus 2% of
2.5.4 Testing optimum at the time of compaction.
3 Cohesionless, free draining granular materials (of 75
2.5.4.1 General
mm maximum size, with not more than 15% passing 0.075
1 For verification of material, moisture content, mm (No. 200) sieve and a plasticity index (PI) not
compaction, thickness and other properties of the exceeding 20%) shall be compacted to at least 70% of
materials or workmanship the Engineer shall at all times relative density for the full depth of embankment. The 600
have access to all parts of the Works and Site. All mm depth of such material immediately below the sub-
sampling and testing of material and work shall be carried grade layer shall be compacted to at least 75% of relative
out as specified to the satisfaction the Engineer. density.
2 Materials shall be tested in accordance with BS 930, 4 Minimum soil tests required during the construction
AASHTO T96, AASHTO T204, AASHTO T205, AASHTO of sub-grade and/or embankment are:
T104, AASHTO T176, BS 1377, AASHTO M145, ASTM - One sample for CBR, classification (AASHTO
D1556 and other applicable and relevant standards. M145), and laboratory (Moisture - density) or
3 The Engineer shall test the compaction of relative density compaction from each source
embankment materials in accordance with the prior to use. Each sample shall represent not
Specification to ensure that adequate compaction or more than 5,000 cubic meters.
consolidation has been achieved. All such tests shall be - One sample for classification representing not
fully documented by the Contractor, in an approved more than 3,000 cubic meters of the material in
manner. use.
- For every completed layer, one field density
4 In the case of cohesionless, free draining rock-soil
shall be determined for each 1500 square
materials, where maximum density tests fail to produce a
meters or 100 linear meters, whichever is less.
well defined moisture/density relationship, the relative
Testing shall be in accordance with ASTM D
density test shall be used. Alternatively an electronic
1556 or ASTM D 2167 or BS 1377 Part 9.
compaction meter or any other approved test equipment
shall be provided by the Contractor and used to determine 2.5.4.3 Degree of Compaction for Rock Fill Materials
the degree of compaction achieved.
1 To ensure proper compaction of rockfill
5 To determine the degree of compaction for
embankments, the Contractor shall conduct compaction
embankment consisting of rock fill, average differential
tests such as the plate load bearing test or other approved
settlement values shall also be determined from surveys
equivalent tests using equipment and materials available
of an adequate number of grid point elevations as directed
in order to determine the best compaction control criteria.
by the Engineer at the commencement of, during and after
embankment construction. (Refer to Item 6 of Paragraph 2 A rockfill test section shall be placed on a firm
2.5.4.3 below). surface approved by the Engineer, and the material and
layer thickness shall conform to the requirements of these
6 For rockfill embankments, the modulus of soil
specifications.
reaction shall be determined by the plate bearing test;
using the method given in AASHTO T222. 3 The test section shall be of sufficient dimensions to
permit the establishment of at least twenty leveling points
2.5.4.2 Standards of Compaction for Soil and Granular on a 5 meter (5m) square grid, and no fewer than 3 points
Materials on any one line and no point less than three meters from
the edge of the layer. The arrangement of the leveling
1 The following compaction standards shall apply to points shall be approved by the Engineer.
embankment materials other than predominantly rock

♦ 2-11 ♦
4 Compaction shall then commence with a minimum 2 The volume of embankment displaced by pipe
of three passes of a vibratory roller, as shown in Table culverts, box culverts and associated end walls shall be
2.5.3.1. Leveling points shall then established, short deducted from the measured volume of embankment. No
lengths of painted steel bars hammered flush with the deduction shall be made for pipes less than 500 mm in
surface of the rockfill are suitable for this purpose. A level diameter and associated end walls.
reading shall be taken at each leveling point on top of a 3 Surplus materials utilized at the Contractor's option
moveable 300 mm square flat steel plate with a hole within the ROW but, beyond the cross sections shown on
drilled in the center of the plate to enable a visual check to the Drawings, are not measured as part of the
be made that the plate is located centrally over the bar. embankment.
5 Further readings shall be taken at the leveling points 4 Benching described under Item 4 of Paragraph 2.5.3.3
after two additional passes with the roller. If the average is measured as Unclassified Excavation, under Clause
settlement is less than half of one per cent (0.5%) of the 2.3.4.
average compacted layer thickness, or as determined by
5 No adjustments or allowances are made in respect of
the Engineer, the rockfill compaction test is deemed
expansion or shrinkage of earthwork volumes which may
complete.
occur during excavation and compaction..
6 If the average settlement is more than half of one
6 Embankment foundation treatment such as stripping,
percent (0.5%), two additional passes of the roller are
scarifying and re-compaction of topsoil containing
required and the leveling procedure shall be repeated. If
unsuitable organic material, as detailed in Item 3 of
the average settlement is then less than half of one
Paragraph 2.5.3.3 is not measured but shall be considered
percent (0.5%), of the average compacted layer thickness
as subsidiary work the costs of which are deemed to be
the test is deemed complete. If not, this step shall be
included in the rates for excavation and borrow excavation
repeated.
in Sub-sections 2.3 and 2.4
7 The total number of passes of the rolling equipment
7 Scarifying old pavement beds, construction of the
necessary to obtain the required result will establish the
trial embankment section if it is outside the pavement,
minimum number of passes to be used on the rock
foundation, preparation, testing, including furnishing and
embankments. However, in no case shall the number of
using an approved type electronic compaction meter and
passes be less than five (5).
grid pattern consolidation surveys, and all other ancillary
8 This verification procedure shall be conducted for embankment work are not measured, but shall be
each change of material and at least once each week considered as subsidiary work the costs of which are
during the initial stages of construction until a reliable deemed to be included in the rates for excavation and
rolling pattern is established. The frequency verification borrow excavation in Sub-sections 2.3 and 2.4
procedure can then be reduced as approved by the
Engineer. 2.5.6 Basis of Payment
9 Documentation of the rockfill compaction tests shall
1 No separate payment will be made for any work in
be maintained by the Contractor in the project records and
this Sub-section 2.5. The cost of all work for embankments
shall be copied to the Engineer.
is deemed to be included under Sub-sections2.3 and 2.4.
2.5.4.4 Monitoring Settlement of Rockfill
2.5.7 Items in the Bill of Quantities
1 On completion of the embankment, the Contractor
shall carry out precise leveling of the crest of the 1 No items are included in the Bill of Quantities. All
embankment. This shall consist of leveling transverse items under Sub-section 2.5 are subsidiary to other items.
sections (a minimum of five points) at a maximum spacing
of 30 m along the embankment. These shall be referenced 2.6 Sub-grade Construction
to a stable approved datum. Leveling shall be carried out
at suitable time intervals until the average rate of 2.6.1 Description
settlement over a period of one month does not exceed
0.1 mm per day. No permanent pavement construction 1 This Subsection describes construction of the sub-
will be permitted until the specified criteria are achieved. grade layer and preparing the sub-grade surface ready to
Adequate time shall be allowed in the construction receive the pavement structure including shoulders, all as
program for the settlement survey. shown on the Drawings.
2 The sub-grade layer is the 200 mm minimum depth
2.5.5 Method of Measurement of selected material immediately below the sub-grade
surface, or as defined in the Drawings or directed by the
1 No separate items are included in the Bill of
Engineer.
Quantities for embankments. The cost is deemed to be
included in the items for excavation and borrow 3 Wherever shallow ground water is expected under
excavation stated in Sub-sections 2.3 and 2.4.. the roadway and wherever damage to the pavement
layers is potential due to water impact, a suitable
subsurface drainage blanket shall be installed under the

♦ 2-12 ♦
sub-grade of the roadway. Drainage blanket is a course of 5 The layer directly underneath the drainage blanket
washed granular material placed to cut off upward and the one directly above it shall satisfy the following
capillary flow of pore water under paved areas, where and filter criteria:
as shown on the Drawings.
i. The 15% size of filter (D15 Filter) shall not be
2.6.2 Materials greater than 4 times the 85% size of the
1 Sub-grade material shall consist of suitable materials surrounding material (D85 Surrounding
of Classes A-1, A-2-4 or A-2-5 having a 4-day soaked CBR material):
of not less than 25% when tested in accordance with D15 Filter < 4 D85 Surrounding material.
AASHTO T 193 when compacted at 100% of modified ii. The 15% size of filter (D15 Filter) shall not be
proctor AASHTO (T-180-D) and having a maximum P.I. of less than 4 times the 15% size of the
12% and Gypsum Content not exceeding 3%. The surrounding material (D15 Surrounding
Maximum Dry Density of Sub-grade material shall be material):
equal or greater than 1.9 t/cu.m. Sub-grade gradation shall D15 Filter > 4 D15 Surrounding material.
be reasonably smooth without gap grading. All material iii. The 50% size of filter (D50 Filter) shall not
shall pass 75 mm sieve. The percent of material passing exceed 25 times the 50% size of the
the 0.075 mm (No. 200) sieve shall not exceed 18% and surrounding material (D50 Surrounding
shall not be less than 5%. Where directed by the Engineer, material):
the Contractor shall screen the sub-grade material at his
D50 Filter < 25 D50 Surrounding material.
own expense. The top 200mm sub-grade material shall
iv. The plasticity index of the portion of all filter
not contain more than 0.2% total Sulphate content and
materials passing sieve # 40 shall not exceed
0.05% total Chloride content.
6%.
2 If a drainage blanket is shown on the Drawings to be
The filter materials shall not contain more than
installed directly underneath the sub-grade, the sub-grade
5% material passing through sieve # 200.
material shall respect the filter criteria specified under
Item 5 of this Clause 2.6.2.
2.6.3 Construction Requirements
3 Aggregate material for use in drainage blanket shall
be rapid draining crushed stone, or crushed or uncrushed 2.6.3.1 Sub-grade in Cut
gravel conforming to the properties stated in Table 2.6.2.1
1 Where the sub-grade is located in rock, the sub-grade,
below:
unless shown otherwise on the Drawings, shall be
Property Range undercut to a depth of 200 mm by drilling or blasting as
Permeability in m/day – ASTM D2434 300 - 1500 directed. No rock shall project more than 50 mm above
the undercut surface elevation. The sub-grade layer shall
Effective Porosity 0.25
then be constructed using approved sub-grade material.
% Fractured Faces – (COE Method) Min. 75%
Cu (D60/D10) > 3.5 2 Where the sub-grade is on in-situ soil which is of a
L.A. Abrasion – AASHTO T96 < 40 quality and CBR value at least equal to those specified for
California Bearing Ratio (CBR) – sub-grade, the 200 mm depth of such material
> 30% immediately below top of sub-grade shall be scarified and
AASHTO T193
Table 2.6.2.1: Properties of Rapid Draining Materials for all roots, sod, vegetable and other undesirable matter and
stones larger than 75 mm in any dimension shall be
use in Drainage Blanket
removed. The material shall then be brought to uniform
4 The gradation of the rapid draining material for use moisture content within the specified range and
in drainage blanket shall be as provided in Table 2.6.2.2 compacted to 100% AASHTO T 180 (Method D) maximum
below: density.
3 Where the sub-grade is on in-situ soil which is
Sieve Designation (mm) Percent Passing unsuitable for retention as the sub-grade layer, such
38.0 (1-1/2 in.) 100 material immediately below the top of sub-grade layer
25.0 (1 in.) 70 – 100 shall be sub-excavated to a depth of 200 mm, hauled away
19.0 (3/4 in.) 55 – 100 and disposed of unless approved for use as embankment
fill. The sub-grade layer shall then be constructed using
12.5 (1/2 in.) 40 – 80
approved sub-grade material, as specified for sub-grade in
9.5 (3/8 in.) 30 – 65 embankment. If the material below sub-grade does not
4.75 (No. 4) 10 – 50 consist of suitable materials satisfying the requirements of
2.4 (No. 8) 0 – 25 top 600mm embankment, it shall be excavated for further
1.2 (No. 16) 0–5 200mm and replaced by suitable material to satisfy the
requirements of the top 600mm of the embankment.
Table 2.6.2.2: Gradation of Rapid Draining Materials for
use in Drainage Blanket

♦ 2-13 ♦
4 The underlying natural material shall be scarified, ii. Place drainage blanket in layers not exceeding
leveled and rolled. The surface of the natural soil shall be 150mm compacted thickness each, with no
approved by the Engineer before placement of suitable layer less than 75 mm thick when compacted.
material.
2.6.3.6 Preparation of Sub-grade Construction on
2.6.3.2 Sub-grade in Embankment Sabkha and Gypsum Rich Soils
1 The 200 mm minimum depth of embankment 1 Where the road sub-grade passes over sabkha areas
immediately below top of sub-grade shall consist of or gypsum-rich soils with a high water table the
selected, approved sub-grade material. The material shall Contractor shall take the special precautions mentioned
be spread in one layer over the full width of the top of below if the sabkha or the gypsum-rich soils are
embankment, brought to a uniform moisture content encountered within the top 1m below the sub-grade level.
within the specified range and compacted to 100%
2 These precautions shall include but shall not be
AASHTO T 180 (Method D) maximum density.
limited to the construction of suitable temporary haul
2.6.3.3 Surface Tolerances roads for all construction plant operating in the area. Such
haul roads shall be constructed, at the Contractor’s
1 All finished levels, lines and grades shall be in expense. using rock fill and geotextiles as necessary to
accordance with the details shown on the Drawings. Each ensure a safe stable surface,
cross section shall be checked at maximum intervals of 20
3 If directed by the Engineer the Contractor shall
m, at each change in cross slope and elsewhere as
construct sub-grade and embankment (where applicable)
directed.
over sabkha areas or gypsum-rich soils with a surcharge
2 The tolerances on levels of finished sub-grade, top of of excess material that shall remain in place till all
embankment under the sub-grade layer and sub- appreciable settlement has stopped. The Contractor shall
excavated (undercut) surface shall be as given in Table provide a means of monitoring the settlement. The
2.6.3.1. Engineer shall decide when appreciable settlement has
stopped.
Surface Tolerances
4 Unless a specific treatment for using geotextiles,
Finished Sub-grade Soil +10 or -30 mm geogrids or geosynthetics is described elsewhere in the
contract, work over sabkha or gypsum-rich soils shall
Rock (if approved) +50 or -50 mm
consist of initially stabilizing the existing weak soil by
Top of Embankment or Sub- laying and rolling rock fill layer type 1 according to Table
+10 or -30mm
excavated Surface Soil 2.6.3.2 below. This operation should be continued by
Table 2.6.3.1: Tolerances on Elevations of Finished Sub- adding and rolling type 1 rock fill layer with steel vibratory
grade roller till the layer is completely stabilised.
5 A layer of geotextile fabric shall be laid over the
3 If instructed by the Engineer, when the finished sub-
compacted type 1 pervious material. A layer of 50mm
grade surface is tested with a 4 m long straightedge
pervious backfill type 2 according to Table 2.6.3-2 shall be
placed parallel to, or at right angles to the centerline, the
laid over the stabilised layer to protect the geotextile fabric.
maximum depression of the surface from the straight
edge shall be 30 mm.
US Standard Percentage Passing
2.6.3.4 Maintenance of Finished Sub-grade Sieve Size Type 1 Type 2
6 inch 100 -
1 The finished and approved sub-grade shall be
5 inch 85 - 100 -
continuously maintained in a smooth, well compacted and
4 inch 75 - 90 -
properly drained condition until the sub-base (or base)
2 inch 45 - 65 -
course is constructed. Reapproval of the sub-grade will be
required if the overlying course is not constructed within 1 1/2 inch 35 - 55 -
14 days of sub-grade completion or if the sub-grade layer 3/4 inch 20 - 35 100
is damaged by traffic or any other causes prior to the 1/2 inch 10 - 25 95 - 100
placement of the sub-base layer. 3/8 inch 5 - 20 70 - 100
No.4 - 0 - 55
2.6.3.5 Drainage Blanket No.8 - 0 - 10
1 Wherever and as shown on the drawings, place No. 16 - -
drainage blanket under roadway pavements on prepared No. 200 - 0-3
sub-grade as follows: Table 2.6.3.2: Definition of Type 1 and Type 2 Rockfill
i. Compact drainage blanket to required cross Materials for Sabkha Treatment
sections and thickness to not less than 95
percent of maximum dry density according to
ASTM D 1557.

♦ 2-14 ♦
6 A layer of 200mm thick capillary break rock fill type 1 2.6.5 Basis of Payment
shall be laid over type 2 pervious backfill to receive the
1 The amount of completed and accepted work,
required road layers after the above operation.
measured as provided for above, will be paid for at the
unit rates for the relevant items in the Bill of Quantities ,
2.6.3.7 Preparation of Subgrade Construction on top of which rate shall be full compensation for supplying
Dune Sand materials, transporting, hauling and placing, for labor,
equipment, tools and other items necessary for the proper
1 Dune sand roadbed shall be compacted only after
completion of the work.
being confined by special means and methods that shall
be approved by the Engineer. These methods may include
the construction of an edge dyke of various materials on
2.6.6 Items in the Bill of Quantities
both sides of the road to provide the necessary i. Sub-grade preparation in cut (sq.m.)
confinement. ii. Drainage blanket (cu.m.)
2 Dune sand material will be allowed to receive dry iii. Preparation of sub-grade
compaction only if the material is tested and proven to be construction on sabkha or
A-3 type and only in case where the Proctor test showed a gypsum-rich soils (sq.m.)
maximum dry density at 0 % moisture. Otherwise, the iv. Preparation of sub-grade construction on top of
material shall be brought to uniform moisture content dune sand (sq.m.)
within the specified range and shall be compacted to 100%
AASHTO T 180 (Method D) maximum density. 2.7 Excavation and Backfilling for
Structures
2.6.4 Method of Measurement
1 Sub-grade layer in embankment is not measured 2.7.1 Description
separately but is included as part of the computation for
1 This Sub-section describes excavation in any
the volume of embankment.
material for buildings and pump houses; bridges, culverts,
2 Sub-grade preparation in cut is be measured by sq.m. pipe culverts, under-drains; drainage and utility
of top width of sub-grade layer computed from cross structures; flood areas cut-off-walls; retaining walls of all
sections shown on the Drawings. The rate shall include for types; and for other major and minor structures; including
all excavation below top of sub-grade, scarifying removing all necessary clearing and grubbing; bailing; drainage;
undesirable matter and compacting of replaced matter pumping; dewatering; sheeting; temporary shoring and
where necessary. cribbing; construction of temporary cofferdams or cribs;
3 Drainage blanket shall be measured by cubic meters backfilling with suitable approved material to the level of
of aggregate materials, furnished, screened, washed, original ground or to the top level of any adjacent
placed, spread, compacted, completed and accepted. embankment; and disposal of all surplus or unsuitable
Measurement shall be of volumes computed from the excavated material, all as shown on the Drawings, or as
cross sections shown on the Drawings and of the field directed by the Engineer.
measurements of area and compacted depth of each trial 2 The work also includes removal of those portions of
section. No allowance shall be made in the measurement existing structures below ground which would in any way
for overdepth and/or overwidth construction, regardless of obstruct or interfere with construction of new structures.
the Engineer’s permission for it to remain in place.
3 The Contractor will be deemed to have satisfied
4 Sub-grade construction on sabkha or gypsum-rich himself, at the time of tendering, as to the type and nature
soils shall be measured by sq.m. of top width of sub-grade of soils and rock that will be encountered in structural
layer computed from the cross sections shown on the excavations.
Drawings The rates shall include for all excavation below
top of sub-grade, scarifying, removing undesirable matter, 2.7.2 Excavation
construction of temporary haul roads, any rockfill,
geotextile or geo-synthetics used, surcharge materials, 2.7.2.1 General
compaction and completion and any accessories all as
1 The Contractor shall notify the Engineer a sufficient
specified in Paragraph 2.6.3.6 and as shown on the
time in advance of the beginning of any excavation for
relevant drawings,.
structures so that the Engineer may, where necessary,
5 Sub-grade construction on top of dune sand shall be survey and record the cross sectional or longitudinal
measured by sq.m. of top width of sub-grade layer elevations and measurements of the existing ground and
computed from cross sections shown on the Drawings. existing structures affected by the proposed structure.
The rates shall include for all excavation below top of sub- Any materials removed or excavated before these
grade, scarifying removing undesirable matter, installation measurements have been taken and approved by the
and dismantling of the confinement structure or side Engineer will not be paid for.
embankment and compacting the soil layers as specified

♦ 2-15 ♦
2 The Contractor shall be responsible for the safety of 2.7.2.3 Excavation for Major Structures and Bridges
all foundation and trench excavations whether supported
or not. Approval of the Contractor's support system or 1 Foundations for buildings, pump houses and other
omission of a support system for any excavations will not major structures and bridges, shall be excavated in
absolve the Contractor from his sole responsibility in this accordance with the dimensions as shown on the
regard. Drawings and shall be of sufficient size to permit placing
of the full width and lengths of the footings.
3 The Contractor shall take all necessary precautions,
including shoring or other means, to protect employees 2 Excavation shall be carried down to the levels shown
and others in the excavation and on the ground above. on the Drawings or as established by the Engineer based
on previous investigations. No concrete shall be placed
4 The sides of all foundation pits and trenches
prior to approval of the excavation pit.
shallower than 1.5m shall be vertical and adequately
supported unless otherwise shown on the Drawings. Sides 3 Unless shown otherwise on the Drawings, the
more than 1.5 m in depth shall be sloped at a stable slope bottom of all excavations shall be covered with a 75mm
or supported in an approved manner unless the material minimum depth of lean (blinding) concrete Class 15 to
through which the pit or trench is cut is deemed to be serve as a working platform.
sufficiently self-supporting and not requiring support. 4 Foundation pits or trenches shall be of sufficient size
5 Pits and trenches shall be kept free from water until and provide minimum sufficient working space to permit
footing concrete has been placed or pipes have been construction of structures or structure footings of the full
installed. The Contractor shall minimize, as far as width and length shown on the Drawings.
practicable, the length of time excavated areas are open. 5 Where footings are constructed using formwork, the
The Contractor shall be responsible for repair of damage excavations shall generally not extend more than 500 mm
due to weather, equipment, and other causes during beyond the maximum dimension on each side of the
periods when the excavations are left open. proposed footing unless additional working space is
6 The Contractor shall plan the Works so that no clearly required and approved by the Engineer. Any
excavation is left in an exposed condition for a period unauthorized overwidth of excavation beyond the lateral
greater than 30 days unless otherwise approved. limits or depths shown on the drawings or approved by
the Engineer shall be backfilled with selected fill or lean
7 Where excavation is adjacent to public highways and
concrete as directed by the Engineer at the Contractor’s
walkways, warning lights, barriers and barricades shall be
expense.
provided to the Engineer’s satisfaction. No excavation
shall be left in an exposed condition for more than 7 days 6 Where footings are located, in or adjacent to firm,
unless otherwise approved. original ground and where formwork is not required or
ordered, any unauthorized overdepth excavation below
8 For excavation in material sensitive to moisture (stiff
the approved elevation of base of footing shall be
clays, marls, etc.) the excavation shall be cleaned and a
backfilled with blinding concrete.
concrete blinding layer cast immediately on completion of
the excavation. 7 Where excavation to rock foundation is required, the
excavation shall proceed in such a manner as to allow the
9 The Contractor shall notify the Engineer of any sign
solid rock to be exposed and prepared in horizontal beds
of failure or cracks within or around the excavation
or properly serrated for receiving the concrete. All loose
immediately when such signs are noticed.
and disintegrated rock and thin strata shall be removed.
2.7.2.2 Temporary Support System 8 When unstable material or other unsuitable material
is encountered below foundation elevation, the Contractor
1 When a temporary support system is required to
shall excavate such material and replace it with suitable
protect adjacent property or to protect the public during
backfill material or concrete to the depth as directed by the
construction, the Contractor's design for such support
Engineer.
system shall be submitted for approval prior to
commencing its construction. 9 If temporary works are required for maintaining the
excavation dry, the Contractor shall be responsible for the
2 All temporary support systems shall be designed
design and execution of the works. The proposed design
with adequate factors of safety to serve with minimal
shall be submitted to the Engineer for approval but, such
maintenance, for the duration of its intended use, and
approval shall not relieve the Contractor of his sole
shall include adequate safety provisions to protect the
responsibility in this regard.
public from construction activities.
3 Notwithstanding any approval of temporary support 2.7.2.4 Excavation for Box Culverts, Pipe Culverts and
systems, the Contractor shall be solely responsible for the Miscellaneous Structures
adequacy of their design and construction and for
maintenance and all necessary safety precautions 1 Excavation shall be carried out to the limits required
associated therewith. for construction and to the depth required for bedding
material or removal of unsuitable material. All trench

♦ 2-16 ♦
excavation shall proceed upgrade, commencing at the expense by provision of an in situ concrete cradle or
downstream end. increased thickness of concrete bedding as directed, or by
2 Foundation material supporting the bedding or the use of other approved suitable materials.
structure shall be AASHTO M 145 Class A-1-a, A-1-b or A- 10 Over width excavation for in situ concrete pipes shall
2-4 compacted to 95% AASHTO T 180 maximum density. be made good at the Contractor's expense by concrete
If the natural material does not meet the classification bedding brought up to the external haunch of the pipe or
requirements, it shall be sub-excavated to a depth of at by the use of other approved suitable materials.
least 200mm and replaced with material meeting the 11 Over depth excavation for metal pipes shall be made
specified requirements. Any rock or hard material within well by furnishing and backfilling an approved, fine
200 mm of the bottom of the pipes shall be similarly sub- granular material containing not more than 0.5% of
excavated and replaced with material meeting the combined chlorides and sulfates.
specified requirements.
3 If no special bedding material is required, the 2.7.3 Backfilling
foundation for precast and prefabricated culverts shall be
formed to the shape of the culvert, including all 2.7.3.1 General
protrusions. The shaping shall extend to 25% of the 1 The Contractor shall obtain approval for his proposed
height of culvert. method and rate of placing of backfill before work
4 Where rock is encountered in the toe wall excavation commences.
for concrete box culverts or concrete cut-off-walls for 2 Backfill materials shall be uniformly graded granular
floodway, embankment protection and pipe culverts and material, capable of being compacted to required
the rock is of such quality as will prevent erosion, part of compaction, and having adequate permeability to permit
the toe wall may be eliminated in the rock strata as free drainage through it. Backfill material shall also
directed and the toe wall shall be keyed into the rock strata conform to the requirements listed in Table 2.7.3.1 below:
in a satisfactory manner. The minimum thickness of the
key shall be as shown on Drawings or as instructed by the Surface Requirements
Engineer.
Minimum D10 value 1 mm
5 Precast concrete pipes and metal pipes shall be
installed in trenches cut into previously constructed and Maximum Plasticity Index 10 per cent
compacted embankment or from top of sub-grade. Unless
Requirements for bridges, culverts etc. shall be as
otherwise shown on the Drawings, trench width shall not
specified in subsequent sections
be greater than the external diameter of the pipe plus 500
mm on each side. Table 2.7.3.1: Requirements for Backfill Materials
6 In the case of metal pipes, the bottom of the trench 3 Backfill material shall not be placed against any
shall be shaped to a template so that at least 10% of the structure until approval is given. Unless otherwise shown
overall height of pipe or arch will be in contact with the on the Drawings structures shall be backfilled to the same
bottom of the trench as excavated. Recesses shall be requirements as specified for the adjacent embankment.
excavated to receive any parts of the pipe which extend
4 Backfill shall be placed in level layers for the full
below the outside perimeter. Where rock, hardpan or
width of the excavated area until the elevation of the
other unyielding material is encountered it shall be
original ground or surrounding embankment is reached.
removed below design grade or as ordered by the
Backfill next to walls, between columns or in other
Engineer for a depth of at least 200 mm and backfilled as
confined areas, shall be compacted by approved hand or
specified.
portable equipment.
7 Trenches for cast in-situ pipes shall be cut into
5 Each successive layer of backfill shall contain only
previously constructed and compacted embankment from
sufficient material to ensure proper compaction and in no
top of sub-grade or embankment height or twice the
case shall any layer be greater than 150 mm thickness
nominal span of the pipe whichever is less. Trench width
(after compaction). The moisture content of the backfill
shall not be greater than the external diameter or span of
material shall be uniform and within the moisture range
pipe plus 500 mm on each side when external forms are
designated. Backfill material shall be compacted to 95% of
used, or the external span of pipe including protection
the maximum density as determined by AASHTO T 180
plus 100 mm on each side when external forms are not
(Method D).
used.
6 Jetting of fills or other hydraulic methods involving
8 When excavation is required for installation of ducts,
or likely to involve liquid or semi-liquid pressure will not
the Contractor shall notify the Engineer upon completion
be permitted.
of the excavation. No duct shall be laid until the depth
and cross section of the excavation has been approved. 7 Water shall be drained from the areas to be backfilled
wherever practicable. In cases where, in the opinion of
9 Over-width or over-depth excavation for precast
the Engineer, it is not practicable to drain the areas to be
concrete pipes shall be made good at the Contractor's
backfilled, the initial backfill material shall consist of

♦ 2-17 ♦
crushed, open graded material conforming to the 5 Unless shown otherwise on the Drawings, when
gradation given in Table 2.7.3.2 below: special permeable backfill (sheathing) is to be placed
against the back faces of retaining walls or wing walls, it
ASTM Sieve Percentage Passing Size shall consist of a continuous covering of approved type
3/8" 100 proprietary filter cloth protected by a continuous wall of
200mm minimum thickness precast, porous (no-fines)
No. 4 < 85 concrete blocks laid with dry joints. Prior to construction
of the block wall, ensure that all underdrains or perforated
No. 30 < 45
pipes are laid along the base of the wall under the
<5 sheathing, as shown on the Drawings.
No. 200
6 Backfill material for culverts, pipe culverts and
Table 2.7.3.2: Requirements for Open Graded Backfill - miscellaneous structures within 300 mm of any part of the
Gradation structure shall be Class A-1-a, A-1-b or A-2-4. The 200 mm
minimum thickness of sub-grade layer shall consist of
Such material may be deposited below the standing water
approved sub-grade material placed and compacted to
level without compaction. Above the water level normal
100% maximum density as specified under Sub-section
laying and compaction will be considered.
2.6 – ‘Sub-grade Construction’. The backfill shall be
8 Additional water to be added during placement of completed to the level of the original ground or to the top
backfill material to achieve required compaction shall be elevation of any adjacent embankment.
fresh water or brackish water approved by the Engineer.
7 Backfilling around and over pipe culverts shall not
9 Minimum tests required during backfilling operations commence until headwalls and wingwalls have been
to verify material are: constructed and attained the specified 28-day strength.
- One Proctor test for each structure.
8 Water used for compaction of backfill around metal
- One gradation of materials when materials
pipes and reinforced concrete structures shall be from an
changed.
approved source and shall not contain more than 0.5%
- One plasticity index and field density for 50%
combined chlorides and sulphates nor contain other
of the layers and for each footing and
potentially harmful minerals.
abutment as instructed by the Engineer.
9 When pipes or other structures temporarily extend
2.7.3.2 Backfilling for Box Culverts, Pipe Culverts, above the grade of the partially constructed embankment,
Bridge and Building Foundations, Walls, the Contractor shall construct the fill over the structure of
sufficient depth to protect the structure from any damage
Abutments and Miscellaneous Structures
resulting from construction or other traffic.
1 Structures shall not be subject to the pressures of 10 The Contractor shall complete the backfill around box
backfilling or to live loads until the 28-day strength of the culverts to the level of the original ground line and to the
concrete has been reached, unless a shorter period is full width of excavation area. If the top of culvert extends
approved in special circumstances where the load is above the original ground line the Contractor shall
sufficiently small as not to constitute a risk of any damage continue the backfill to the top of culvert and for a width of
to the structure in the opinion of the Engineer. This period 3 m on each side of the culvert for the full width of
may be extended if subnormal curing conditions exist. roadway embankment. If the embankment is in place at
2 Backfill placed around culverts shall be deposited on the time of backfilling, the Contractor shall backfill around
both sides to approximately the same level at the same the culvert to the top of embankment.
time. Special care shall be taken to prevent any wedging 11 Backfill around pipe culverts shall be completed to
action against the structure and slopes bounding the the level of original ground line and to the full width of
excavation shall be stepped, where necessary, to prevent excavation area. If the top of the culvert extends above
such wedge action occurring. the original ground line the Contractor shall continue the
3 All backfill intended to support false work loads, backfill to the top of culvert for a width of 1.5 times the
including temporary fills shall be selected to support the maximum external width of the culvert on each side of the
required load. As a minimum, such material shall be culvert centerline to the full width of the roadway
AASHTO M 145, Class A-1-a, A-1-b or A-2-4, compacted to embankment. If the embankment is in place at the time of
90% of the maximum density as determined by AASHTO T backfilling, the Contractor shall backfill around the culvert
180 (Method D). to the top of culvert or as shown on the Drawings.
4 Backfill around bridge and building foundations, 12 Any existing roadway pavement cut through,
abutment walls and retaining walls shall be completed to damaged or removed during excavation for pipe culvert
the level of the original ground line and to such heights installation shall be reinstated, after pipe installation and
above original ground line or to the levels as shown on trench backfilling, using approved base and surfacing
the Drawings. Care shall be exercised to prevent forward course materials at least equivalent to those in the original
movement of the wall. pavement. Materials and construction shall conform to the

♦ 2-18 ♦
relevant requirements Sections 3 and 4 of this 7 Unless specified otherwise in the special
specification. specifications, temporary cofferdams, temporary support
13 Miscellaneous structures other than pipe culverts system, bailing, drainage, dewatering, pumping, sheeting,
shall be backfilled in accordance with the methods concrete blinding layers and all other Temporary Works
specified. Compaction of backfill when structures are shall not be measured for direct payment, but shall be
outside the roadway right-of-way or in approach roads, considered as subsidiary work the costs of which will be
minor roads or similar areas, shall be to 90% of maximum deemed to be included in the rates for structural
density as determined by AASHTO T 180 (Method D). excavation.
8 Backfilling to structural excavation shall not be
2.7.4 Method of Measurement measured separately but is considered as subsidiary work
the cost of which are deemed to be included in the rates
1 All structural excavation, of whatever type, shall be
for structural excavation
measured as ‘unclassified’ which shall be deemed to
include all materials encountered of any nature, including 9 Any blinding concrete used at the bottom of
silts, clays, sand, gravel and granular materials and excavations, as shown on the Drawings or as instructed by
fractured, jointed and solid rock. the Engineer shall be measured and paid for in accordance
with the relevant method of measurement under Clause
2 Structural excavation is measured by cubic meter of
5.1.5 of Section 5 ‘Concrete and Concrete Structures’.
material excavated for the major structures hauled away
and disposed of as directed, or stockpiled. Measurement
2.7.5 Basis of Payment
of structural excavation shall be from original ground
levels or ground levels after removal of all unclassified 1 The amount of completed and accepted work,
highway excavation. Limits shall not be greater than measured as provided for above, will be paid for at the
vertical planes 500 mm from the maximum dimension, on unit rates for the various items in the Bill of Quantities ,
each side of the footing or other controlling portion of the which rate shall be full compensation for equipment, tools,
structure. Where structures are constructed against labor, materials, transporting, hauling, placing, and for
natural ground or rock, excavation limits shall be the other items necessary for the proper completion of the
dimensions of the structure as shown on the Drawings. work.
Bottom limits shall be the ordered foundation levels. Only
material excavated from its original position shall be 2.7.6 Items in the Bill of Quantities
measured for payment. No measurements shall be made
of structural excavation in embankments previously i. Unclassified structural excavation
constructed by the Contractor. (depth 0 to 2m) (cu.m.)
3 Additional excavation in unstable material or other ii. Unclassified structural excavation
unsuitable material encountered below foundation level (2m < depth < 4m) (cu.m.)
shall be measured as part of the unclassified structural iii. Unclassified structural excavation
excavation.
(depth > 4m) (cu.m.)
4 Structural Excavation under Water shall be measured
iv. Structural Excavation under Water (cu.m.)
by cu.m. of material excavated for the major structures,
hauled away and disposed of as directed, or stockpiled on
or in the vicinity of the Works, and the excavated areas
backfilled, completed and accepted. 2.8 EARTHWORK FOR PIPE
5 Unauthorized overdepth and overwidth excavation in
TRENCHES
soil and rock and the backfill material including blinding
concrete required in such cases, shall not be measured for 2.8.1 Description
direct payment, but shall be considered as subsidiary work 1 This Sub-section describes requirements for
the costs of which will be deemed to be included in the excavation of trenches in any material for water supply,
rates for structural excavation sewage, stormwater drainage and irrigation pipes, and all
6 Structural excavation in any material or under water other associated works, including all necessary clearing
for box culverts less than one sq.m. in external cross and grubbing, bailing, draining, shoring, planking,
section, and structural excavation for pipe culverts, strutting and supporting the sides of excavation. The work
underdrains (subsoil drains), pits, catchbasins, manholes, includes backfilling with suitable approved material and
inlets, energy dissipaters, slope protection, fence posts, disposal of the excess material to designated and
guardrail posts, lighting columns, sign posts, signal approved tip locations.
supports and all other minor structures, shall not be
measured for direct payment, but shall be considered as
subsidiary work the costs of which will be deemed to be
included in the rates and prices for the relevant items..

♦ 2-19 ♦
2.8.2 Materials i. For pipes not exceeding 65 mm diameter:
Nominal diameter plus 300 mm.
2.8.2.1 Backfill Material ii. For pipes over 65 mm and not exceeding 600
1 Initial backfill (up to 300 mm above the top of the mm diameter: Nominal diameter + 600 mm.
pipe) shall be selected fill, sand or other approved material iii. For pipes over 600 mm diameter: Nominal
and shall conform to the following: diameter + 1000 mm.
7 Where the above specified trench widths are
Standard Percent by Weight Percent by exceeded; the Contractor shall provide additional pipe
Sieve Size Passing for Pipes Weight Passing
protection or pipes of increased strength if the Engineer
(mm) other than uPVC for uPVC Pipes
calls for such measures, all at his own expense.
19 100 -
8 Excavation of trenches with battered sides will not be
4.76 25 – 100 100 permitted within 4m of any building or other structure.

1.19 10 – 75 25 – 75 9 When the pipes are to be laid in embankments or


other fill areas, the embankment or fill area shall first be
0.354 5 – 30 10 – 30 filled and compacted as specified to the proposed finished
grade or to a height of at least 300 mm above the top of
0.177 3 – 10 3 – 10
pipe whichever is lower. The trench shall then be
0.074 0–5 0–5 excavated as in undisturbed material.
10 When pipes are to be laid under existing pavements,
Table 2.8.2-1: Requirements for Initial Backfill - Gradation
trenches shall be excavated carefully and to minimum
2 For GRP pipes, graded crushed stone 2.83-8 mm shall widths. Methods that will give straight and vertical face
be used for initial backfilling. shall be used. The pavement shall be kept at its original
level and condition.
3 The remainder of the trench shall be backfilled with
suitable material either from material removed in the 11 In combined trenches where one pipe is at a lower
course of excavating the trench, or imported from level than an adjacent pipe the following shall be applied:
approved borrow pit. In either case the backfill material i. The whole trench shall have a depth related to
shall be non-plastic. The percentage by weight passing a the lower pipe and the thickness of the bedding
No. 200 (0.075 mm) sieve shall not exceed 15%. The shall be increased to the upper pipe as
percentage passing a 63 mm sieve shall be 100. necessary.
ii. The lower pipe shall be backfilled with
2.8.3 Construction thoroughly compacted granular material up to
a level of 0.30 meters above the higher pipe.
2.8.3.1 Excavation for Pipe Trenches
12 Final excavation to the correct grade level for trench
1 The Contractor shall not commence excavation of beds shall be carried out immediately before laying beds
any section of work until a full supply of pipes and fittings or pipes. Unstable material, rock projections, boulders and
is available for that section. hard spots shall be removed and replaced with approved
2 During excavation, material suitable for backfilling filling material, that will be compacted as instructed. Local
shall be piled at sufficient distance from the sides of the soft spots shall be compacted by tamping in bedding
trench as to avoid overloading and prevent cave in. All material.
excavated material not required, or unsuitable for 13 The bottoms of trenches shall be accurately graded
backfilling shall be removed and carted away to an to provide uniform bearing and support for the bottom
approved dumping area. quadrant of each section of the pipe. Bell holes shall be
3 Trenches shall be excavated to such depths as will excavated to the necessary size at each joint or coupling to
permit the pipes to be laid at elevations, slopes or depths eliminate point bearing. Any material that may cause point
of cover indicated on the drawings, and at uniform slopes bearing shall be removed.
between indicated elevations. 14 The Contractor shall report to the Engineer any
4 Where excavation depth exceeds the level indicated unsuitable or weak ground material that may be found
on the drawings and is not authorized in writing by the below the indicated excavation levels before executing
Engineer, the Contractor shall place backfill or concrete to any trimming of the excavation, pipe laying, concreting, or
the required bottom level, as instructed by the Engineer, other work. Where, in the judgment of the Engineer the
all at his own expense. bottom of the trench is unsuitable, such material shall be
removed to the width and depth ordered by the Engineer.
5 Trenches shall be excavated with vertical sides
The trench shall then be made up by backfilling with
between the bottom level and 300 mm above the top of
approved material.
the pipe.
15 Where rock is encountered, the trench shall be
6 Trench width up to 300 mm above the crown of the
excavated to 150 mm below bed level and replaced with
pipe shall not exceed the following:
granular material, concrete, or blinding grade as directed.

♦ 2-20 ♦
2.8.3.2 Backfilling 2.8.4 Method of Measurement
1 Trenches shall not be backfilled at joints until after 1 Trench excavation and backfill shall be paid for per
that section of the pipeline has successfully passed the cu.m. measured in horizontal layers for the different depth
specified tests. categories shown in the Bill of Quantities. Trench length
shall be measured between outer surfaces of manholes or
2 Initial backfill or surround up to a level of 300 mm
chambers. Trench width shall be as specified or shown on
above top of the pipe, shall be placed and hand
Drawings. Depth of excavation shall be the depth of every
compacted in 150 mm layers. The backfill shall be brought
horizontal layer. Excavation for bedding is included as
up evenly on both sides of the pipe for the full length of
trench excavation.
the pipe. Care shall be taken to ensure thorough
compaction of the fill under the haunches of the pipe. 2 Rates for trench excavation and backfill shall include
for:
3 Suitable backfill shall be placed and well compacted
i. Excavating in any material encountered
in layers not exceeding 150 mm thick after compaction.
including rock.
Heavy compactors shall not be used until there is 600 mm
ii. Blasting, barring, wedging or other quarrying
cover over pipes.
methods for rock excavation.
4 Unless otherwise specified each layer shall be iii. Excavation at any level.
compacted to at least 95% maximum density for iv. Excavating curved on plan.
cohesionless soils and 90% maximum density for cohesive v. Allowance for working space.
soils. vi. Increase in bulk for excavating.
5 Backfilling trenches for pipes with concrete beds and vii. Excavating below water table and dewatering
or surrounds shall not start before 24 hours after placing as necessary.
concrete. Heavy compactors shall not be used and traffic viii. Keeping excavations free from water.
shall not be allowed before the elapse of 72 hours after ix. Leveling, compacting, trimming and grading
placing the concrete. bottoms and trimming sides and bottoms of
6 When the backfill material is too wet from rain or excavation.
excessive application of water, no compaction shall be x. Supporting the sides of excavation.
done. In this case the work shall be suspended until the xi. Filling with material as specified and
previously placed and new materials have dried compacting around pipes and beds multiple
sufficiently to permit proper compaction. Other measures handling of excavated material and excavation
shall be taken if necessary to obtain proper compaction. from borrows and transporting about the Site.
xii. Segregation of the various classes of excavated
7 Temporary crossing are to be provided over trenches
spoil and stock piling as may be directed by the
to prevent construction traffic damaging pipes after
Engineer.
backfilling.
xiii. Disposal of surplus excavated material
2.8.3.3 Restoration of Surfaces including depositing and consolidating where
directed on Site or removing from Site and
1 Restoration of asphalt, concrete, gravel pavements depositing at a tip to be provided and paid for
and the likes shall be of materials and thickness to match by the Contractor.
the existing pavement. Materials and workmanship shall xiv. Pipe bedding, initial backfill or gravel, and final
be in accordance with local authority requirements and as backfill.
directed by the Engineer. xv. Filling over-excavation with material as
2 Restoration of pavement shall be done according to specified
the existing pavement quality and level to ensure that new xvi. Consolidation of primary backfill (initial
pavement matches the existing to provide uniform surface backfill) material using water or hand tamping.
with the existing profile. xvii. Compaction of secondary backfill (main
3 Grassed areas shall be restored by spreading backfill) material.
approved fertile soil over affected area after backfilling. xviii. Reinstatement of unpaved surfaces.
Seeding, fertilizers and water shall be applied until grass is (Reinstatement of paved surfaces shall be
restored to its former condition. made and paid for according to Sections 4 or
12 as appropriate)
4 Surface grading shall be carried out to restore all un-
surfaced areas and any adjoining areas disturbed to
2.8.5 Basis of Payment
provide a level, smooth surface.
5 The Contractor shall proceed with restoration of 1 The amount of completed and accepted work,
surfaces as soon after completion of other work as is measured as provided for above, will be paid for at the
practicable, but in no case more than 10 days after unit rates for the various items in the Bill of Quantities,
backfilling of trenches and other excavated areas. which rate shall be full compensation for equipment, tools,
Restoration shall be completed within 20 days from the labor, materials, transporting, hauling, placing, and for
start of restoration.

♦ 2-21 ♦
other items necessary for the proper completion of the
work.

2.8.6 Items in the Bill of Quantities


i. Trench excavation and backfilling (Depth up to 2m)
ii Trench excavation and backfilling (Depth > 2m < 3m)
iii Trench excavation and backfilling (Depth > 3m < 4m)
iv Trench excavation and backfilling (Depth > 4m)

♦ 2-22 ♦

S-ar putea să vă placă și