Sunteți pe pagina 1din 16

Ref. Title Page No. Ref. Title Page No.

3.1 Materials for Sub-Base 3.3.3.8 Maintenance of Completed Base 3-7


and Base Courses 3-1 3.3.3.9 Testing 3-7
3.3.4 Method of Measurement 3-8
3.1.1 Description 3-1
3.3.5 Basis of Payment 3-8
3.1.2 Materials 3-1
3.3.6 Items in the Bill of Quantities 3-8
3.1.3 General Requirements for Materials 3-1
3.1.3.1 Sources and Production 3-1 3.4 Stabilized Base Courses 3-8
3.1.3.2 Stockpiling 3-1
3.4.1 Description 3-8
3.1.3.3 Sampling and Testing 3-1
3.4.2 Materials 3-8
3.2 Granular Sub-Base Course 3-2 3.4.2.1 Soil for Cement Stabilisation 3-8
3.4.2.2 Cement as Stabilising Agent 3-8
3.2.1 Description 3-2
3.4.2.3 Bitumen as Stabilising Agent 3-9
3.2.2 Materials 3-2
3.4.2.4 Lime as Stabilising Agent 3-9
3.2.3 Construction Requirements 3-2
3.4.2.5 Water 3-9
3.2.3.1 Subgrade Surface Preparation 3-2
3.4.2.6 Mix Design 3-9
3.2.3.2 Equipment 3-3
3.4.3 Construction Requirements 3-9
3.2.3.3 Construction of Trial Sections 3-3
3.4.3.1 Surface Preparation 3-9
3.2.3.4 Stockpiling of Granular Material 3-3
3.4.3.2 Construction of Trial Section 3-9
3.2.3.5 Mixing and Spreading 3-3
3.4.3.3 Cement Stabilisation Procedures –
3.2.3.6 Compaction 3-3
Plant Mixing 3-10
3.2.3.7 Tolerances 3-4
3.4.3.4 Cement Stabilisation Procedures -
3.2.3.8 Maintenance of Completed Sub-base 3-4
Batch Mixing 3-10
3.2.3.9 Testing 3-4
3.4.3.5 Cement Stabilisation Procedures -
3.2.4 Method of Measurement 3-4
Continuous Mixing 3-10
3.2.5 Basis of Payment 3-4
3.4.3.6 Cement Stabilisation Procedures -
3.2.6 Items in the Bill of Quantities 3-4
Mixed in Place Procedures 3-10
3.3 Aggregate Base Course 3-5 3.4.3.7 Cement Stabilisation Procedures -
Placing of Stationary Plant Mixes 3-11
3.3.1 Description 3-5
3.4.3.8 Cement Stabilisation Procedures -
3.3.2 Materials 3-5
Compaction and Finishing 3-11
3.3.2.1 Crushed Stone Aggregate 3-5
3.4.3.9 Curing of Cement Stabilised Courses 3-12
3.3.3 Construction Requirements 3-6
3.4.3.10 Testing of Cement Stabilised Courses 3-12
3.3.3.1 Surface Preparation 3-6
3.4.3.11 Bitumen Stabilisation Procedures -
3.3.3.2 Equipment 3-6
Mix Design 3-12
3.3.3.3 Construction of Trial Sections 3-6
3.4.3.12 Bitumen Stabilisation Procedures -
3.3.3.4 Stockpiling of Aggregate Materials 3-6
Stationary Plant Mixing 3-12
3.3.3.5 Mixing and Spreading 3-6
3.4.3.13 Bitumen Stabilisation Procedures -
3.3.3.6 Compaction 3-6
Mixed in Place Procedures 3-12
3.3.3.7 Tolerances 3-7

♦ 3-0 ♦
Ref. Title Page No.
3.4.3.14 Bitumen Stabilisation Procedures -
Placing and Spreading Stationary
Plant Mixes 3-12
3.4.3.15 Bitumen Stabilisation Procedures -
Compaction and Finishing 3-12
3.4.3.16 Bitumen Stabilisation Procedures -
Tolerances and Replacement
of Unsatisfactory Areas 3-12
3.4.3.17 Bitumen Stabilisation Procedures -
Testing of Bitumen Stabilised Courses 3-13
3.4.3.18 Lime Stabilisation Procedures -
Mix Design 3-13
3.4.3.19 Lime Stabilisation Procedures - Safety
Precautions 3-13
3.4.3.20 Lime Stabilisation Procedures -
Stationary Plant Mixing 3-13
3.4.3.21 Lime Stabilisation Procedures - Mixed
in Place Procedures 3-13
3.4.3.22 Lime Stabilisation Procedures - Placing
and Spreading Stationary Plant Mixes 3-13
3.4.3.23 Lime Stabilisation Procedures -
Compaction and Finishing 3-13
3.4.3.24 Lime Stabilisation Procedures –
Tolerances and Replacement
of Unsatisfactory Areas 3-13
3.4.3.25 Testing of Lime Stabilised Courses 3-14
3.4.4 Method of Measurement 3-14
3.4.5 Basis of Payment 3-14
3.4.6 Items in the Bill of Quantities 3-14

♦ 3-0 ♦
3.1 Materials for Sub-Base and Base 3.1.3.2 Stockpiling
Courses 1 Stockpile areas shall be surveyed prior to stockpiling
to establish control points and to obtain a record of
3.1.1 Description existing cross sections for future use in determining
1 This Sub-section describes general requirements for stockpile quantities. The areas shall be adequately drained
materials for construction of granular sub-base, aggregate at all times.
base and stabilised base courses, all as and where shown 2 Stockpiling procedures shall not result in noticeable
on the drawings. degradation or segregation of the stockpiled material, or
introduction of foreign materials into the stockpile, or
3.1.2 Materials coning. Heights of granular material and aggregate
stockpiles shall not exceed 3 m berms.
1 Materials for use in the construction of the sub-base
and base courses for flexible and rigid pavements may 3.1.3.3 Sampling and Testing
include any or all of the following:
1 The Contractor shall submit to the Engineer, 10 days
i. Screened or partially crushed granular material,
prior to the scheduled beginning of crushing and
consisting of well graded gravel including sand
screening operations, a statement of origin indicating the
and silt, or crushed stone or crushed gravel for
aggregate source and the quarry location and
sub-base course construction.
qualifications, as well as the types and composition of all
ii. Crushed stone for base course construction.
stone and/or gravel aggregates and granular materials
2 All material sources and the quality of materials shall proposed for use in the work.
be approved prior to procuring or processing material
2 Samples for testing shall be taken by the Contractor,
from such sources. Inspection, sampling, testing and
in the presence of the Engineer. Duplicate samples shall
retesting as necessary, shall be as specified hereunder for
be submitted to the Engineer for future reference, if
specific materials.
instructed. Sampling shall be in accordance with AASHTO
3 Storage and handling of all materials shall conform T2. The Contractor shall conduct the tests in the site
to the relevant requirements of this specification and as laboratory, or have the tests carried out at an approved
approved by the Engineer. Materials shall be stored on external laboratory.
hard, clean surfaces or as directed by the Engineer.
3 In order to ascertain the properties of granular and
aggregate materials, the Contractor shall submit for
3.1.3 General Requirements for Materials
testing representative samples of all materials intended
3.1.3.1 Sources and Production for incorporation in the work, prior to starting quarry or
borrow pit operations. The representative samples shall
1 The Contractor shall be responsible for locating be taken by the Contractor in the presence of the Engineer.
sources and manufacturers of materials in accordance
4 Tests performed by the Contractor shall be utilized in
with the requirements of this Specification in the
assessing the locations, extent of deposits and quantities
quantities and rates of production needed to complete the
of materials which, when properly processed, will conform
work on time.
to this Specification, and shall in no way obviate the need
2 The Contractor shall satisfy himself as to the location, for further testing by the Engineer. Approval of specific
suitability and quantity of materials available; extent of sources of materials shall not be construed as final
work necessary to obtain the materials, and to crush, approval and acceptance of materials from such sources.
screen and wash them; and the length of haul to the Site.
5 Processed materials shall be tested and approved
3 Prior to starting quarry or borrow pit operations; the before being stockpiled on Site or incorporated in the
Contractor shall obtain written permission from the work and may be inspected and tested at any time during
authorities or owners concerned. their preparation, storage and use. Materials awaiting
4 Screening plants or crushing and screening plants testing and approval shall not be unloaded and mixed
shall not be put into operation until approved by the with materials previously approved. If the grading and
Engineer. If, after any plant is put into operation, it fails to quality of any materials delivered to the Site do not
perform as intended, the Contractor shall either rectify the conform to the grading and quality of the established
defects in the existing plant to the satisfaction of the control samples, the Engineer will reject such materials.
Engineer, or shall provide alternative approved plant. 6 The Contractor shall permit the Engineer to inspect
5 Approval of the crushing and screening plants and any and all materials used or to be used, at any time
other equipment shall in no way relieve the Contractor of during or after their preparation, or while being used..
his responsibilities in respect of producing granular Unsatisfactory materials, whether in place or not, shall be
materials and aggregates which conform to this removed promptly from the Site. The Contractor shall
Specification and in the quantities required for the furnish all necessary labor, transport, tools and equipment
completion of the work on time. required by the Engineer for such inspections.

♦ 3-1 ♦
3.2 Granular Sub-Base Course accordance with AASHTO T 96 (Los Angeles Abrasion
Test).

3.2.1 Description 6 The granular material shall have a 4-day soaked CBR
of not less than 60% when compacted at 100% of modified
1 This Sub-section specifies standards for granular proctor AASHTO (T 180-D) and tested in accordance with
sub-base material, mixing, spreading on prepared AASHTO T 193.
subgrade, compacting and finishing.
7 When tested for soundness in accordance with
AASHTO T 104, the material shall not show signs of
3.2.2 Materials
disintegration, and the percentage loss in weight after 5
1 Granular material for use in sub-base courses shall cycles shall not exceed 12% in the case of the sodium
be naturally occurring gravel, blended as necessary with sulfate test and 18% in the case of the magnesium sulfate
fine or coarse material and screened to produce the test.
specified gradation. Crushing of natural granular material 8 The portion of granular material, including any
shall not normally be required, unless for the purpose of blended material, passing the 0.425 mm (No. 40) mesh
meeting the gradation requirements, or, when shown on sieve shall have a liquid limit (L.L.) of not more than 25
the Drawings, to produce a higher quality sub-base with and a plasticity index (P.I.) not greater than 6 when tested
improved mechanical stability. in accordance with AASHTO T 89 and T 90.
2 Gravel shall consist of hard, durable and sound 9 If additional fine material is required to correct the
stones, free from dirt, organic matter, shale or other gradation of the granular material, or for adjusting the L.L.
deleterious substances. or P.I. of the fraction passing 0.425 mm (No 40) sieve, it
3 Granular materials shall meet the requirements of shall be uniformly blended and mixed with the granular
Class A, B or C shown in Table 3.2.2.1, and as specified on material. Additional fine material for these purposes shall
the Drawings, when tested in accordance with AASHTO T- be obtained from the crushing of stone, gravel, or slag.
27 after dry mixing and just before spreading and 10 The granular material shall not contain more than
compacting. The class of granular material shall be as 3 % gypsum and shall be free from organic content.
shown on the Drawings or otherwise as selected by the
11 The granular material shall have a minimum sand
Engineer based upon the test results of the materials
equivalent value of 28, when tested in accordance with
survey, and projected traffic. The actual gradation shall, in
ASTM D2419.
all cases, be continuous and smooth within the specified
limits for each class. 12 The maximum permitted swell for the granular
material used in the sub-base courses shall be 1.0%, when
Percent by weight passing tested in accordance with ASTM D4829.
Sieve Designation
(square openings) 13 The Granular Sub-base Course material shall have
Class A Class B Class C
chloride content of less than 3.5 percent and sulphate
content of less than 2.0 percent when tested in accordance
63 mm 100 - -
with BS 812.
50 mm 90 - 100 100 - 14 Only potable water shall be used for mixing granular
sub-base material.
37.5 mm - 70 - 100 -

25 mm - 55 - 85 100 3.2.3 Construction Requirements

19 mm - 50 - 80 - 3.2.3.1 Sub-grade Surface Preparation

1 Prior to subgrade surface preparation, the sub-grade


9.5 mm - 40 - 70 50 - 85
shall be constructed in accordance with the requirements
4.75 mm 35 - 70 30 - 60 35 - 65 of Sub-section 2.6 and properly maintained and kept well
2.00 mm - 20 - 50 25 - 50 drained thereafter.

0.425 mm - 10 - 30 15 - 30 2 At all special grade control points, such as at bridge


structures, existing pavements, etc the sub-grade shall be
0.075 mm 0 - 10 5 - 15 5 - 15
lowered to a depth sufficient to permit construction of the
Table 3.2.2.1: Gradation of Granular Sub-Base Material by sub-base course to the specified elevations and thickness.
Class Transitions shall be of sufficient length to avoid abrupt
changes of grade and shall be within plus or minus 3% of
4 The material shall not contain more than 5% clay the final design grade unless otherwise directed. Surplus
content at any stage of construction when tested in the material shall be removed and disposed of.
Hydrometer Test in accordance with AASHTO T88.
3 The sub-grade shall be inspected and approved
5 The loss in weight of granular material shall not immediately prior to commencement of sub-base
exceed 40% after 500 revolutions, when tested in construction. Any soft, yielding material shall be removed

♦ 3-2 ♦
and replaced by approved topping material. Holes, control guide wire requirements. Where the required
depressions and other irregularities shall be made good as thickness is greater than 200 mm but less than 400 mm,
directed and the subgrade re-compacted as necessary and the material shall be placed in layers of equal thickness.
finished ready to receive the sub-base course. 3 If approved by the Engineer, when heavy duty
vibratory compaction equipment is used the maximum
3.2.3.2 Equipment layer thickness may be increased up to 300 mm (after
compaction) provided compaction tests with appropriate
1 Equipment used to handle, place, spread, water, testing equipment based on successful Site trials indicate
compact and finish sub-base shall conform with the that the specified compaction standard will be attained
requirements of Section 19 of these Specifications and and will be uniform through the thickness.
with the Contractor's approved equipment list.
4 The sub-base material shall be placed to the required
3.2.3.3 Construction of Trial Sections width using an approved paver/finisher or grader if
approved by the Engineer. However, any pavers or
1 If directed by the Engineer, before commencement of graders used for placing the sub-base material shall be
sub-base construction, the Contractor shall lay and equipped with calibrated sensors to maintain the design
compact trial sections of varying thickness of sub-base. levels and thicknesses. Water shall be applied by
Each trial section shall be 2 lanes wide by 50 m long, at approved spraying equipment and thoroughly mixed with
approved locations on or close to the Site. Each trial the sub-base material.
section shall be laid using the same materials, mix
5 The material shall not be handled in such a way as to
proportions, mixing, spreading and compaction
cause segregation. If the spreading equipment causes
equipment, and construction procedures, proposed for
segregation in the material, or leaves ridges or other
use in the work.
objectionable marks on the surface which cannot be
2 The objectives of these trials shall be to determine readily eliminated or prevented by adjustment of the
the adequacy of the Contractor's equipment and the loose equipment, the use of such equipment shall be
depth measurements that will result in the specified discontinued and it shall be replaced by a spreader or
compacted layer depths, to verify the field moisture grader capable of spreading the material in a proper
content, and to identify the relationship between the manner.
number of compaction passes and the resulting density of
6 All segregated material shall be removed and
the sub-base material.
replaced with well-graded material. ‘Skin’ patching will
3.2.3.4 Stockpiling of Granular Material not be permitted. Only minor surface manipulation and
watering to achieve the required surface tolerances will be
1 Stockpiling procedures shall conform to the permitted during the compaction process.
requirements of Sub-section 3.1.
7 Neither hauling nor placement of material will be
2 Methods used for stockpiling granular material and permitted when, in the judgment of the Engineer, the
removing it from stockpiles shall not result in significant weather or surface conditions are such that hauling
degradation or segregation or the introduction of operations will cause cutting or rutting of the subgrade or
significant amounts of foreign materials or extraneous cause contamination of the sub-base material.
matter.
3 Granular material adversely affected, in the opinion 3.2.3.6 Compaction
of the Engineer, by stockpiling or handling procedures, 1 The Contractor shall plan the sequence of operations
shall not be incorporated in the work regardless of so that the least amount of water will be lost by
previous approval of such material, until the deficiencies evaporation from uncompleted surfaces. If the
have been rectified in an acceptable manner. uncompleted surface material loses water due to
evaporation, the Contractor shall apply additional water as
3.2.3.5 Mixing and Spreading
required to prevent raveling or excessive drying.
1 Mixing shall generally be performed in batching 2 The sub-base material shall be compacted by means
plants. Mixing in stockpiles shall be done only if approved of approved compaction equipment, progressing
by the Engineer and under his supervision. The amount of gradually from the outside towards the center, with each
water added, as approved by the Engineer, shall be such succeeding pass uniformly overlapping the previous pass.
that the material will be uniform and within the specified
3 Rolling shall continue until the entire thickness of
moisture content range at the time of compaction.
each sub-base layer is thoroughly and uniformly
Wetting of granular material in trucks before or during
compacted to 100% AASHTO T 180 (Method D) maximum
delivery to the Site will not be permitted. However, water
density. Final rolling of the completed course shall be by
shall be added to the material, if necessary, during placing
means of an approved self-propelled roller. Rolling shall
and compaction of sub-base material.
be accompanied by sufficient blading, to insure a smooth
2 The sub-base material shall be placed on the surface, free from ruts or ridges and having the proper
subgrade in a uniform layer or layers not exceeding 200
mm thickness (after compaction) with the necessary

♦ 3-3 ♦
shape. When additional water is required, it shall be 3.2.3.8 Maintenance of Completed Sub-base
applied in an approved manner.
1 Following completion and acceptance of the sub-
4 Any areas inaccessible to normal compaction
base course, it shall be maintained in good condition prior
equipment shall be compacted by use of portable
to laying the base course.. The sub-base shall be bladed,
mechanical tampers until the required standard of
broomed and otherwise maintained, keeping it free from
compaction is achieved.
raveling and other defects until such time as the base
5 Each layer shall be completely compacted and course is placed. Water shall be applied at such times and
approved prior to delivery of materials for the subsequent in such quantities as directed by the Engineer.
layer.
6 Prior to placing a subsequent layer, the existing 3.2.3.9 Testing
surface shall be made sufficiently moist as directed, to 1 Every 1000 cu.m. of sub-base material, or whenever
ensure proper bond between the layers. there is a change in the material source, shall be subject to
7 The edges and edge slopes of the sub-base course a full set of tests as listed in Table 3.3.3.1 after placing and,
shall be bladed or otherwise dressed to conform to the if found satisfactory, shall be approved for compaction.
lines and dimensions shown on the Drawings and to This approval shall not be deemed to constitute
present straight, neat lines and slopes as free of loose acceptance of the sub-base course.
material as practicable. 2 Sampling and testing shall conform with the relevant
8 Material which has dried out prior to final requirements of this specification and to the satisfaction of
compaction, or which has dried and de-compacted the Engineer.
subsequent to final compaction, shall be watered and re- 3 Compaction shall be tested in accordance with
compacted using approved equipment and procedures. If AASHTO T 191 or AASHTO T 205. If there is a delay
the Contractor is unable to return the material to its between the construction of any layer and the following
original or specified condition with respect to compaction, layer, if necessary and required by the Engineer the
thickness and surface tolerances, the Contractor shall compaction of the lower layer may be re-verified to ensure
remove the material and reconstruct the sub-base course that it has not loosened due to traffic, passage of
on a re-approved subgrade. construction equipment, adverse weather conditions or
9 The water shall be clean and free from deleterious otherwise.
substances. Water from doubtful sources shall not be used
until tested in accordance with AASHTO T26 and approved. 3.2.4 Method of Measurement
10 Sea, brackish or saline water shall not be used in the 1 Granular sub-base course is measured by cu.m. of
mixing, spreading and compacting operations for compacted sub-base. Measurement shall be of volumes
aggregate sub-base course. computed from the cross sections shown on the Drawings
and shall be calculated from the top surface area of each
3.2.3.7 Tolerances
layer, excluding the tapered edges..
1 The fully compacted and completed sub-base course 2 No measurement shall be made for direct payment of
shall conform to the lines, grades and cross sections as overdepth construction, regardless of the Engineer's
shown on the Drawings. permission for it to remain in place.
2 The elevations of the finished sub-base course shall
be checked by the Contractor in the presence of the 3.2.5 Basis of Payment
Engineer at maximum intervals of 20 m and at
1 The amount of completed and accepted work,
intermediate points as directed.
measured as provided for above, will be paid for at the
3 The tolerances on elevations of finished surface shall unit rates for the various items in the Bill of Quantities,
be plus 10 mm to minus 20 mm. Minus tolerance shall be which rate shall be full compensation for equipment, tools,
compensated by the subsequent layer. labor, locating sources of supply, supplying materials,
4 When the finished surface is tested with a 3 m long sampling and testing, screening, crushing, transporting,
straightedge, placed parallel to, or at right angles to the stockpiling, laying, mixing and compacting and for extra
centerline, the maximum deviation of the surface from the material in tapered edges, and other items necessary for
testing edge between any 2 contact points shall not the proper completion of the work.
exceed 10 mm.
5 All areas which exceed the specified tolerances shall 3.2.6 Items in the Bill of Quantities
be corrected by removing the defective sections of sub-
i. Granular Sub-Base Course (Class A) cu.m
base and reconstructing them or, if approved, by
scarifying, adding new material, or removing extra ii. Granular Sub-Base Course (Class B) cu.m
material, mixing and re-compacting and finishing to the
iii. Granular Sub-Base Course (Class C) cu.m
specified standard.

♦ 3-4 ♦
3.3 Aggregate Base Course 9 The crushed aggregate base course material shall
have a 4-day soaked CBR of not less than 80% when
3.3.1 Description compacted at 100% of modified proctor AASHTO (T180-D)
and tested in accordance with AASHTO T 193.
1 This Sub-section specifies standards for crushed
aggregate base course material, mixing, spreading on
prepared sub-base course or sub-grade, compacting and Per cent by weight passing
Sieve Designation
finishing. (square openings) Class A Class B Class C
3.3.2 Materials
63 mm 100 - -
3.3.2.1 Crushed Stone Aggregate
50 mm 90 - 100 - -
1 Aggregate for use in base course construction shall
be either crushed stone or crushed gravel. The fine 37.5 mm 60 - 90 100 -
aggregate shall consist of screenings obtained from 25 mm 42 - 77 60 - 100 100
crushed stone, gravel, or sand. Aggregate may be washed,
if directed, to remove excessive quantities of clay, silty 19 mm 35 - 70 55 - 85 80 - 100
clay or salts.
12.5 mm 25 - 60 - -
2 Crushed stone shall consist of hard, durable particles
or fragments of stone, free from dirt or other objectionable 4.75 mm 15 - 40 35 - 60 30 - 60
matter, and shall contain no more than 8% of flat, 2.00 mm 10 - 25 25 - 50 20 - 45
elongated particles when tested according to ASTM D4791
0.425 mm 5 - 15 15 - 30 -
and, soft, or disintegrated pieces when tested according to
ASTM C235 and C123. 0.075 mm 2-9 8 - 15 3 - 10
3 Crushed gravel shall consist of hard durable stones, Table 3.3.2.1: Gradation by Class of Aggregate Base
rocks, and boulders crushed to specified sizes and shall be Course
free from excess flat, elongated, soft or disintegrated
pieces, dirt, or other objectionable matter 10 When tested for soundness in accordance with
AASHTO T 104, the material shall not show signs of
4 The method used in production of crushed gravel
disintegration and the loss by weight shall not exceed 12%
shall be such that the finished product shall be as uniform
in the case of the sodium sulfate test and 18% in the case
as practicable. The crushing of the gravel shall result in a
of the magnesium sulfate test.
product, which shall have at least 90% by weight of
particles with at least one fractured face. All stones, rocks, 11 The aggregate material shall not contain more than
and boulders of inferior quality occurring in the pit shall 2% gypsum and shall be free from organic content.
be wasted. 12 The aggregate material shall have a minimum sand
5 Any material passing 4.75 mm (No. 4) sieve and equivalent value of 50, when tested in accordance with
produced in the crushing process shall be incorporated in ASTM D2419.
the base material up to the gradation limits required for 13 The maximum permitted swell for the aggregate
the base course aggregate. material used in the base courses shall be 0.5%, when
6 Crushed aggregate for base course delivered to road tested in accordance with ASTM D4829.
site shall meet the requirements of Class A, B or C 14 The portion of aggregate, including any blended
gradations as shown in Table 3.3.2.1 when tested in material, passing the 0.425 mm (No. 40) mesh sieve shall
accordance with AASHTO T 27 after mixing with water have a liquid limit (L.L.) of not more than 25 and plasticity
and just before spreading and prior to compacting. The index (P.I) of not more than 6 when tested in accordance
class of aggregate shall be as shown on the Drawings. The with AASHTO T 89 and T 90.
actual gradation shall, in all cases, be continuous and 15 If additional fine material is required to correct the
smooth within the specified limits for each class. Gap aggregate gradation, or for adjusting the L.L. or P.I. of the
graded aggregate will not be accepted. If gradation is fraction passing the 0.425 mm (No. 40) sieve, it shall be
tested after compaction a tolerance of 3% is allowed in uniformly blended and mixed with the aggregate material
upper limit for percentage of material passing sieve 200. plant at the crushing plant or by an approved plant.
7 The amount of the fraction of material passing the Reworking of the material in situ to obtain the specified
0.075mm (No. 200) mesh sieve shall not exceed one half gradation will not be permitted. Additional fine material
the fraction passing the 0.425mm (No. 40) mesh sieve. for these purposes shall be obtained from the crushing of
stone, gravel, or slag.
8 The loss in weight shall not exceed 40% after 500
revolutions, when tested in accordance with AASHTO T 96 16 The Aggregate Base Course material shall have
(Los Angeles Abrasion Test). chloride content of less than 3.5 percent and sulphate
content of less than 2.0 percent when tested in accordance
with BS 812.

♦ 3-5 ♦
17 Only potable water shall be used for mixing 3.3.3.5 Mixing and Spreading
aggregate base material.
1 All components of base course material shall be
premixed with water in a pugmill mixing plant. The
3.3.3 Construction Requirements
amount of water added, as determined, shall be such that
3.3.3.1 Surface Preparation the material will be uniform and within the specified
moisture content range at the time of compaction. Other
1 The sub-base course shall be in accordance with the methods of mixing will be allowed only if directed by the
requirements of Sub-section 3.2 and properly maintained Engineer, provided such method(s) do not reduce the
and kept well drained thereafter. quality of work. The Contractor shall demonstrate, in the
2 The sub-base surface shall be inspected and presence of the Engineer, his ability to attain the
approved prior to commencement of base construction. requirement given in this Specification.
Holes, depressions and other irregularities shall be made 2 The premixed material shall be placed on the sub-
good as directed and the sub-base re-compacted as base in a uniform layer or layers not exceeding 200 mm in
necessary and finished ready to receive the base course. thickness (after compaction) with the necessary control
3 Where no sub-base course is required or shown on guide wire requirements. Where the required thickness is
the Drawings, and the aggregate base course is placed greater than 220 mm but less than 400 mm, the material
directly on completed sub-grade, preparation of the shall be placed in layers of equal thickness.
subgrade surface shall be as specified in Paragraph 3.2.3.1. 3 If approved by the Engineer when heavy duty
vibratory compaction equipment is used, the maximum
3.3.3.2 Equipment
layer thickness may be increased up to 300 mm (after
1 Equipment used to handle, place, spread, water, compaction) provided compaction tests with appropriate
compact and finish base course shall conform with the testing equipment based on successful Site trials indicate
requirements of Section 19 and with the Contractor's that the specified compaction standard will be attained
approved equipment list. and will be uniform through the thickness.
4 The base course material shall be placed to the
3.3.3.3 Construction of Trial Sections
required width using an approved paver/finisher. However,
1 If directed by the Engineer, the Contractor shall lay any pavers or finishers used for placing the base material
and compact trial sections of varying thickness of base. shall be equipped with calibrated sensors to maintain the
Each trial section shall be 2 lanes wide by 50 m long, at design levels and thicknesses. The material shall be
approved locations on or close to the Site. Each trial delivered such that it is ready for compaction without
section shall be laid using the same materials, mix further shaping.
proportions, mixing, spreading and compaction 5 The material shall not be handled in such a way as to
equipment, and construction procedures, proposed for cause segregation. If the spreader causes segregation in
use in the Works. the material, or leaves ridges or other objectionable marks
2 The objectives of these trials shall be to determine on the surface which cannot be readily eliminated or
the adequacy of the Contractor's equipment and the loose prevented by adjustment of the spreader operation, the
depth measurements that will result in the specified use of such spreader shall be discontinued and it shall be
compacted layer depths, to verify the field moisture replaced by a spreader capable of spreading the material
content for compaction, and to identify the relationship in a proper manner.
between the number of compaction passes and the 6 All segregated material shall be removed and
resulting density of the base course material. replaced with well-graded material. ‘Skin’ patching will
not be permitted. Only minor surface manipulation and
3.3.3.4 Stockpiling of Aggregate Materials
watering to achieve the required surface tolerances will be
1 Stockpiling procedures shall conform to the relevant permitted during the compaction process.
requirements of Sub-section 3.1. 7 Hauling or placement of material will not be
2 Methods used for stockpiling aggregate materials permitted when, in the judgment of the Engineer, the
and removing them from stockpiles shall not result in weather or surface conditions are such that hauling
significant degradation or introduction of significant operations will cause cutting or rutting of the sub-base or
amounts of foreign materials or extraneous matter. subgrade or cause contamination of the base course
3 Aggregate materials adversely affected, in the material.
opinion of the Engineer, by stockpiling or handling 3.3.3.6 Compaction
procedures, shall not be incorporated in the work
regardless of previous approval of such material, until the 1 The Contractor shall plan the sequence of operations
deficiencies have been rectified in an acceptable manner. so that the least amount of water will be lost by
evaporation from uncompleted surfaces. If the
uncompleted surface loses water due to evaporation, the

♦ 3-6 ♦
Contractor shall apply additional water as required to 5 The tolerances on layer thickness, after being
prevent raveling or excessive drying.. compacted and finished, shall not exceed +10mm and -
2 The base course material shall be compacted by 5mm.
means of approved compaction equipment, progressing 6 The thickness of the finished base course shall be
gradually from the outside towards the center, with each checked at 20m intervals along the road by taking levels
succeeding pass uniformly overlapping the previous pass. on the centerline and both shoulders.
3 Rolling shall continue until the entire thickness of 7 All areas which exceed the specified tolerances shall
each base layer is thoroughly and uniformly compacted to be corrected by removing the defective sections of base
100% AASHTO T 180 (Method D) maximum density. Final course and reconstructing them or if approved, by
rolling of the completed course shall be by means of an scarifying and adding new material, or removing extra
approved self-propelled roller. Rolling shall be material, and re-compacting and finishing to the specified
accompanied by sufficient blading, to ensure a smooth standard.
surface, free from ruts or ridges and having the proper
shape. When additional water is required, it shall be 3.3.3.8 Maintenance of Completed Base Course
applied in an approved manner. 1 Following completion and acceptance of the base
4 Any areas inaccessible to normal compaction course, it shall be maintained by the Contractor until the
equipment shall be compacted by use of portable subsequent pavement layers are laid.. The surface shall be
mechanical tampers until the required standard of broomed, rolled and otherwise maintained, keeping it free
compaction is achieved, or to the satisfaction of the from raveling and other defects until such time as the
Engineer. following course is placed. Water shall be applied at such
5 Each layer shall be completely compacted and times and in such quantities as directed.
approved prior to delivery of materials for the following
3.3.3.9 Testing
layer.
6 Prior to placing a following layer, the surface shall be 1 Every 1000 cu.m. of base course material, or
made sufficiently moist as directed, to ensure proper bond whenever there is a change in the material source, shall be
between the layers. subject to a full set of tests as listed in Table 3.3.3.1 after
placing and if satisfactory shall be approved for
7 The edges and edge slopes of the base course shall
compaction and use. This approval shall not be deemed
be bladed or otherwise dressed to conform to the lines
to constitute acceptance of the base course for full
and dimensions shown on the Drawings and to present
payment purposes.
straight, neat lines and slopes as free of loose material as
practicable.
8 Material which has dried out prior to final Source of Materials Control on Site (The Road)
compaction, or which has dried and de-compacted Repetition
Repetition
subsequent to final compaction, shall be watered and re- Required Required Required
Required for
compacted using approved equipment and procedures. If Tests for all Tests
all Tests in
the Contractor is unable to return the material to its (A) Tests in (B)
(B)
(A)
original or specified condition with respect to compaction,
1.Gradation Minimum 1. Proctor Minimum
thickness and surface tolerances, for the final layer only of Materials one test AASHTO one test for
the Contractor shall scarify the material and reconstruct AASHTO for each T180-D every 1000
the base course on a re-approved sub-base surface or to T27 source cu.m. of
the satisfaction of the Engineer. every layer,
2.Plasticity or
3.3.3.7 Tolerances Index whenever
AASHTO " Materials
1 The fully compacted and completed base course T89 & T90 changed,
shall conform to the lines, grades and cross sections as whichever is
shown on the Drawings. less
3.Abrasion 2.
2 The elevations of the finished base course shall be AASHTO Gradation
checked by the Contractor in the presence of the Engineer T96 " of Materials
at intervals of 20m on straight lines and of 10 m on curves, AASHTO "
and at intermediate points as directed. T27
4. C.B.R.
3 The tolerances (for final layer only) on elevations of
AASHTO
finished surface shall not exceed +5mm or -10mm. T193 " 3. Plasticity
4 When the finished surface is tested with a 4 m long Index
straightedge, placed parallel to, or at right angles to the AASHTO "
centerline, the maximum deviation of the surface from the 5.Sand T89 & T90
equivalent
testing edge between any 2 contact points shall not "
ASTM
exceed 10mm.

♦ 3-7 ♦
Source of Materials Control on Site (The Road) 3.3.5 Basis of Payment
Repetition 1 The amount of completed and accepted work,
Repetition
Required Required Required measured as provided for above, will be paid for at the
Required for
Tests for all Tests unit rates for the various items in the Bill of Quantities,
all Tests in
(A) Tests in (B) which rate shall be full compensation for equipment, tools,
(B)
(A)
labor, locating sources of supply, supplying materials,
D2419 4. C.B.R.
sampling and testing, screening, crushing, transporting,
AASHTO "
T193 stockpiling, laying, mixing and compacting and for extra
6.Percentag material in tapered edges, and other items necessary for
e of the proper completion of the work.
fractured 5. Abrasion
Grains AASHTO 3.3.6 Items in the Bill of Quantities
T96 "
i. Aggregate Base Course (Class A) cu.m
7.Thin and
elongated 6. Sand ii. Aggregate Base Course (Class B) cu.m
pieces equivalent
ASTM ASTM " iii. Aggregate Base Course (Class C) cu.m
D4791 D2419
3.4 Stabilized Base Courses
7. Clay
lumps & 3.4.1 Description
friable
1 This Sub-section specifies stabilized base courses
particles "
ASTM C235 composed of sand, sandy gravel, sandy clay soil or similar,
and C123 stabilized with cement or bitumen or lime as appropriate
and as shown on the Drawings.
8. Field
Density " 3.4.2 Materials
3.4.2.1 Soil for Stabilization
9. Test for every
Thickness 2000 sq.m. 1 Sand and gravel soils shall have the following
and for every particle size distribution given in Table 3.4.2.1.
layer
Table 3.3.3.1: Required Tests and Minimum Repetition for AASHTO Sieve % passing (by mass)
50 mm 100
Base and Sub-Base Course Materials
4.75 mm 50 - 100
2 Sampling and testing shall conform to the 1.80 mm 37 - 80
requirements of this specification. 425 μm 15 - 50
3 Compaction shall be tested in accordance with 75 μm 0 - 20
AASHTO T 191, AASHTO T 205 or any acceptable method. 2 μm 0-3
If there is a significant delay between the construction of Table 3.4.2.1: Soil for Stabilization
any layer and the following layer, the Engineer may
require the compaction of the lower layer to be re-verified 2 The mix-in-place method of construction shall be
to ensure that it has not loosened due to traffic, passage of used only on sites with naturally occurring sand and
construction equipment, adverse weather conditions or gravel mixture. For the central plant method of
otherwise. construction, the materials shall be selected by the
Contractor from other sources complying with the
3.3.4 Method of Measurement requirements of this Clause and shall be subject to the
1 Aggregate base course shall be measured by cu.m. approval of the Engineer.
of compacted base course. Measurements shall be of 3.4.2.2 Cement as Stabilizing Agent
volumes computed from the cross sections shown on the
Drawings and shall be calculated from the top surface area 1 Cement for stabilization shall be ordinary Portland
of each layer, excluding the tapered edges.. cement or sulfate resisting cement, as shown on the
2 No measurement shall be made for direct payment of Drawings, or as instructed by the Engineer. Portland
overdepth construction, regardless of the Engineer's cement shall conform to the requirements of BS12 Part 2
permission for it to remain in place. or AASHTO M85 Type I for ordinary and rapid hardening
types, and BS4027 Part 2 or AASHTO M85 Type V for
sulfate resisting cement.

♦ 3-8 ♦
2 At least two silos shall be used for cement storage. water to be used with the naturally occurring soil so as to
Before recharging a silo it shall be emptied completely obtain a stabilized mixture with the following properties:
and cleaned out. During the time of charging a silo shall
i. The minimum cube compressive strength shall
not be used for batching.
be 5.0 N/mm2 after molding and storage at a
3 The stored cement shall be free-flowing and free of minimum humidity of 95% for a period of 7
lumps. Cement shall not be stored for longer than 4 days. The molding shall be in accordance with
months. Cement that has remained in store for a period AASHTO T134 and the strength testing shall be
greater than 4 months, or of which there is doubt as to in accordance with BS 1881. The cement
quality shall be re-tested by standard mortar tests to content of trial mixes shall be adjusted until
determine whether it still meets the requirements of the this strength is achieved.
standards.
ii. The maximum volume change (swelling) shall
4 Curing seal shall consist of approved proprietary be 2% and the maximum loss in weight shall
curing compound, or MC-70 cutback bitumen to prime be not more than 8%, when cylinders are
coat standard as specified in Section 4. molded and tested in accordance with AASHTO
T 135, Method B.
3.4.2.3 Bitumen as Stabilizing Agent
iii. Cement content and water content of the mix
1 Bitumen may include straight run (penetration grade) on the Site shall each be within - 0.2% to +2%
bitumen; RC cutback bitumen, MC cutback bitumen, or of the approved mix design.
cationic emulsified bitumen, Type SS. Penetration grade, iv. The total salt content of the cement stabilized
cutback bitumen and emulsified bitumen shall conform to base course mixture shall meet the following
all relevant requirements herein. requirements: The total chloride content (sum
2 The selection of suitable bitumen will depend on the of both acid soluble and water soluble
properties of the material to be stabilized and shall be chlorides) expressed as chloride ion, when
subject to laboratory and field trials by the Contractor, tested in accordance with BS 1881, shall not
under the supervision of the Engineer. exceed 0.10 percent by weight of dry cement.
The total sulfate content expressed as SO3,
3 When the material moisture content is high, the
when tested in accordance with BS 1881, shall
material must be dried before the use of penetration grade
not exceed 3 percent by weight of dry cement.
bitumen or viscous cutback bitumen and plant mixing of
materials as appropriate.
3.4.3 Construction Requirements
4 When the natural moisture content of the material is
low, use cutback bitumens or emulsified bitumens as 3.4.3.1 Surface Preparation
appropriate.
1 Prior to placing of stabilized base on sub-base or
subgrade, the subgrade shall have been properly
3.4.2.4 Lime as Stabilizing Agent completed and approved as specified in Sub-section 2.6
1 Hydrated lime (calcium hydroxide) and quicklime and the sub-base shall have been properly completed and
(calcium oxide) shall conform to AASHTO M216. Mixing of approved as specified in Sub-section 3.2.
different brands of lime or use of lime from different mills
3.4.3.2 Construction of Trial Section
will not be permitted.
2 Lime slurry shall be a homogeneous pumpable 1 If instructed by the Engineer before commencement
mixture of lime and water. Slurry shall be a premixed of stabilization work and after completion of laboratory
material in which the lime solids content shall be not less mix design, the Contractor shall lay a trial section of
than 30% by weight. stabilized material 2 lanes wide by 50m long, at an
approved location on or near to the Site.
3.4.2.5 Water 2 This trial section shall be laid using the same
1 The water shall be clean and free from impurities, oil, materials, mix proportions, mixing, spreading and
acid, salts, alkali, organic matter, and other potentially compaction equipment, and construction procedures that
deleterious substances. Water from doubtful sources shall are proposed for use in the work.
not be used until tested in accordance with AASHTO T26 3 The trial section shall serve as a field verification of
and approved. the laboratory mix design. The results of the dry density
and moisture content measurements made in the trial
3.4.2.6 Mix Design for Cement Stabilized Base section will be used in association with the laboratory
1 Before starting the work of stabilization, soil-cement tests to establish the moisture content and minimum per
trial mixes shall be carried out. The proposed mix design cent compaction to be attained in the stabilization work.
shall be submitted by the Contractor for approval by the 4 The trial section shall also demonstrate the adequacy
Engineer. It shall show the percentage of cement and of mixing, spreading and compaction equipment and the
suitability of the methods and organization proposed.

♦ 3-9 ♦
3.4.3.3 Cement Stabilization Procedures - Plant Mixing feeders which continuously supply the correct amount of
granular material in proportion to the cement and so
1 When cement and granular or crushed material are arranged that the proportion of each size of granular
to be mixed in a stationary plant, the plant shall be an material can be separately adjusted if more than one size
approved type pugmill mixing plant of either the batch is used. Storage facilities containing fine material shall be
mix type with revolving blade or rotary drum, or the equipped with vibrating units which shall vibrate the side
continuous mixing type. Proportioning of materials and of walls of the feeder to prevent any hang-up of materials
water may be by either weight or volume. while the plant is operating.
2 Cement shall be added in such a manner that it is 2 A control system shall be provided that will
uniformly distributed during the mixing operation. Safe, automatically close down the plant when the material in
convenient facilities shall be provided for sampling any storage facility approaches the strike-off capacity of
cement in the supply line to the weigh hopper or pugmill. the feed gate. The plant will not be permitted to operate
3 Means shall be provided whereby the Engineer may unless the control system is in proper working order.
verify the amount of water per batch or the rate of flow for 3 The feeder for the granular material shall be
continuous mixing. The time of the addition of water and mechanically or electrically driven. Mechanically driven
the points at which it is introduced into the mixer shall be feeders shall be directly connected with the drive on the
as approved. cement feeder. The drive shaft on the feeder shall be
4 The charge in a batch mixer, or the rate of feed to a equipped with a revolution counter reading to 0.1 of a
continuous mixer, shall not exceed that which will permit revolution. Electrically driven feeders shall be actuated
complete mixing of all of the material. Dead areas in the from the same circuit that services the motor driving the
mixer, in which the material does not move or is not cement feeder.
sufficiently agitated, shall be corrected. 4 The cement feeder and the granular material feeders
5 The moisture content of the completed mixture shall shall be equipped with devices by which the rate of feed
be not more than one per cent below optimum moisture can be determined while the plant is in full operation.
content at the point of delivery to the work area.
3.4.3.6 Cement Stabilization Procedures - Mixed in
3.4.3.4 Cement Stabilization Procedures - Batch Mixing Place Procedures
1 Batch mixing plants shall be equipped with a 1 Mixed in place procedures will normally be permitted
sufficient number of paddles of a type and arrangement to when the granular material to be stabilised is in-situ site
produce a uniformly mixed batch. material.
2 The mixer platform shall be of ample size to provide 2 Plant and equipment for pulverizing (if required) and
safe and convenient access to the mixer and other for mixing all materials will be approved on the basis of
equipment. preliminary trials to establish that such plant and
3 The mixer shall be equipped with a timing device equipment are capable of producing the specified degree
which will indicate by a definite audible or visual signal of mixing and uniformity of stabilized material for the full
the expiration of the mixing period. The device shall be thickness of each layer. Single pass or multi-pass
accurate to within 2 seconds. equipment may be used.
4 The time of mixing a batch shall begin after all 3 The mixing equipment shall be equipped with a
ingredients are in the mixer and shall end when the mixer device for controlling the depth of processing and the
is half emptied. Mixing shall continue until a mixing blades shall be maintained or reset periodically so
homogeneous mixture of uniformly distributed and that the correct depth of mixing is obtained at all times.
properly coated materials of uniform appearance is Cement shall be spread ahead of the mixer by means of a
produced. The time of mixing shall not be less than 30 cement spreader, fitted with a device to ensure a uniform
seconds. When blending of different sizes is required, the and controllable rate of spread of cement transversely and
materials shall be blended as they enter the mixer. longitudinally.
5 Cement for each batch shall be weighed on scales 4 If multi-pass equipment is utilized, the fine cohesive
separate from the aggregate batching scales. Each fraction (if any) of the material shall first be pulverized to
cement scale graduation shall be approximately 0.001 the required depth with successive passes and the
times the total capacity of the scales. The total capacity moisture content adjusted if it is more than 3% below the
shall not be greater than twice the amount of cement value required for compaction. Cement shall then be
required when the plant is operated at full capacity. No spread and mixing continued with successive passes until
scale shall be used with a capacity less than 500 kg. the required depth and uniformity have been achieved.
5 If it is necessary to adjust the moisture content of the
3.4.3.5 Cement Stabilization Procedures - Continuous
material to the optimum for compaction, water shall be
Mixing added during the mixing operation using a water sprayer
1 Continuous mixing plants shall be designed such that of such design that the water is added in a uniform and
granular materials are drawn from the storage facility by controllable manner both transversely and longitudinally.

♦ 3-10 ♦
6 Te mixing equipment shall be set so that it cuts be provided with a fully automatic and adjustable screed
slightly into the edge of any adjoining completed lane so that strikes off and distributes the material to the full width
as to ensure that all material forming the layer has been being spread and to the surface tolerances specified.
properly processed. The Engineer may approve the use of 9 The spreader shall be equipped with grade sensing
scarifiers or preparizers ahead of the mixing equipment. controls to automatically control the longitudinal grade
The output of the mixing equipment shall be such that a and transverse slopes of the screed. Screed action
minimum rate of 20 lin.m./h measured longitudinally of includes any cutting, crowding, or otherwise that produces
completed stabilized layer can be maintained in order to a finished surface texture of uniform appearance.
permit satisfactory compaction of the mix.
3.4.3.8 Cement Stabilization Procedures - Compaction
3.4.3.7 Cement Stabilization Procedures - Placing of
and Finishing
Stationary Plant Mixes
1 Immediately upon completion of spreading or
1 Immediately prior to depositing the mix, the surface spreading and mixing in place operations, and completion
area to be covered shall be moistened and kept moist. of shaping, the mix shall be initially compacted by one
2 The cement stabilized mix shall be protected against complete pass using approved type rollers.
moisture loss during transporting, by use of suitable 2 If the finished surface after initial compaction is
covers. The mix shall be deposited on the roadbed at a outside the specified tolerance, all high spots shall be
prescribed quantity which shall provide the compacted trimmed off to within the specified tolerance. Filling of
thickness for the width being spread without resort to low areas by drifting or hauling of trimmed material will
spotting, picking up, or otherwise shifting the mixture. not be permitted.
Segregation shall be prevented and the mix shall be free
3 Following trimming, the finished surface shall be
from pockets of coarse or fine materials.
finally compacted to not less than 100% of the laboratory
3 The mix shall be spread in widths of not less than 2 density of the approved job mix specimens as determined
lanes, insofar as the width of surface permits. by AASHTO T 134. Final compaction shall be
Longitudinal construction joints shall fall within 300 mm of accomplished in such a manner that no loose material
lane lines. The mix shall be spread by one or more remains on the surface and all tear marks are eliminated.
spreaders operating in a staggered position across the
4 The surface tolerances shall conform with the
surface. If traffic conditions require that less than 2 lanes
tolerance requirements for Aggregate Base Course.
be spread, not more than 2 hours shall elapse between the
Where any areas are lower than the allowable tolerance,
times of placing the material in adjacent lanes.
the stabilised layer shall be removed and fresh stabilised
4 The compacted thickness of any one layer shall not mix placed and properly compacted and finished, unless
exceed 200 mm and shall be not less than 80 mm. When filling of the low areas with bituminous concrete or
more than one layer is placed, the surface of the lower cement concrete is approved.
layer of compacted mix shall, until covered with the next
5 If the superimposed course will be cement concrete,
layer, be kept moist with water or a curing seal as
the low areas may, if approved, be filled with concrete at
specified.
the time and during the same operation that the concrete
5 In the case of areas inaccessible to mechanical pavement is placed.
spreading equipment, the mix may be spread in one layer
6 When the superimposed course will be bituminous
by approved methods only. After spreading, the material
concrete, the low areas may, if approved, be filled with
shall be thoroughly compacted to the required lines,
bituminous concrete to the same standard. This filling
grades, and cross section by means of pneumatic tampers,
shall be carried out as a separate operation prior to
or other approved compacting equipment.
placing the bituminous concrete course (unless the
6 Use of motor graders will not be permitted during thickness to be placed is too small to make this
spreading or compacting operations. Motor graders may practicable).
be used only to trim the edges and surface after
7 Not more than 2 hours shall elapse between the time
compaction in order to finish within the specified
water is added to the mixed materials and the time of
tolerances.
completion of initial compaction. Final compaction shall
7 A motor grader may be classified as a self-propelled be completed within 30 minutes of initial compaction.
mechanical spreader if it has been equipped with end
8 At the end of each day's work and when operations
wings on the blade, has the blade locked in a position
are delayed or stopped for more than 2 hours, a vertical
perpendicular to the direction of travel, and is equipped
construction joint shall be made in the fully compacted
with cross slope and automatic grade controls that meet
layer, perpendicular to the centerline. Additional mix shall
the requirements for the specified type of spreading.
not be placed until the construction joint has been
8 Each layer of the mix shall be spread in one approved.
operation with an approved type self-propelled
9 One hour after the stabilized mix has been finally
mechanical spreader such that the layer is made ready for
compacted; vertical longitudinal joints shall be
compaction without further shaping. The spreader shall
constructed by cutting into the existing edge to a depth of

♦ 3-11 ♦
approximately 100 mm. The mix cut away shall be 3.4.3.12 Bitumen Stabilization Procedures - Stationary
discarded. The face of the cut joints shall be moistened in Plant Mixing
advance of placing the adjacent lane.
1 When approval is given to utilize stationary plant for
3.4.3.9 Curing of Cement Stabilized Courses mixing, whether batch mixing plant or continuous type
mixing plant, the plant and equipment and handling and
1 Curing seal as specified shall be applied uniformly to
mixing procedures shall conform with the relevant
the completed surface at a rate of between 0.5 and 1.2
kg./sq.m., or as determined by the Engineer. The curing requirements of Section 4 - "Bituminous Pavement" and
with the appropriate requirements specified herein for
seal shall be applied on the same day that final
plant mixing of cement stabilized materials.
compaction is performed and as soon as practicable
thereafter. The surface shall be kept moist until the seal is 3.4.3.13 Bitumen Stabilization Procedures - Mixed in
applied.
Place Procedures
2 Damage to the curing seal or stabilized surface shall
be promptly repaired by an approved manner. 1 Approved type multi-pass or approved type purpose-
built, single-pass equipment shall be utilized for on Site
3.4.3.10 Testing of Cement Stabilised Courses mixing and placing. Operators shall be trained and fully
experienced in the operation of such equipment.
1 For every 5,000 sq.m. of each stabilised layer or for
each day's completed area (whichever is smaller) the 2 Multi-pass equipment may consist of suitable
following sampling and testing shall be carried out: bitumen distributor and motor graders or as otherwise
- In situ density of a minimum of 3 samples approved.
(taken immediately after final compaction) 3 The process of pulverizing the fine grained cohesive
determined in accordance with AASHTO T 191 fraction (if any) of the granular material shall be as
or T 205 and which shall be not less than 100% specified for cement stabilized courses. Bitumen, of the
of the density of the approved laboratory mix. type and grade selected by the Engineer, shall then be
- Cement content in accordance with AASHTO T applied to the surface using approved type heating and
211. pressure distribution equipment. Emulsified bitumen shall
- Gradation of mix in accordance with AASHTO not normally require heating.
T 27. 4 Spreading and mixing of the bitumen and granular or
- Moisture - density relationship for mix sampled other material shall be carried out as specified for cement
fresh from the Site, in accordance with stabilized courses.
AASHTO T 134 if the source of the material is
changed. 3.4.3.14 Bitumen Stabilization Procedures – Placing and
- Compressive strength of a set of 3 test Spreading Stationary Plant Mixes.
specimens molded and cured in accordance
1 The placing and spreading of stationary plant mixes
with AASHTO T 134 and T 126, and tested in
shall be as specified for cement stabilized courses.
accordance with AASHTO T 22.
3.4.3.15 Bitumen Stabilization Procedures - Compaction
3.4.3.11 Bitumen Stabilization Procedures - Mix Design
and Finishing
1 The material to be stabilized shall be a sand, sandy
1 Compaction of bitumen stabilized courses to 100% of
gravel or silty or clayey gravel and sand material with a P.I.
laboratory density of approved job mix specimens,
not exceeding 12% and L.L. not exceeding 25% and with
finishing, and provision of longitudinal joints, shall be as
not more than 30% passing a 0.075 mm (No. 200) sieve.
specified for cement stabilized courses.
2 Bitumen-soil mix proportions shall be established by
field laboratory trial mixes, carried out in the presence of 3.4.3.16 Bitumen Stabilization Procedures - Tolerances
the Engineer. The compressive strength shall be and Replacement of Unsatisfactory Areas
determined in accordance with AASHTO T 167 and in such
a way as to ensure that the optimum composition of the 1 Finished surface tolerances and the rectification
mix is established. procedures for any areas which fail to meet such
tolerances, shall be as specified for cement stabilized
3 The laboratory trial mixes, after being air cured for a
courses.
period of 7 days and tested in accordance with AASHTO T
167, shall have a minimum compressive strength at 25 2 Where high spots require trimming after initial
degrees C, of 2 MN/sq.m. (20 kg/sq.cm.) and a Marshall compaction, raking or similar procedures may be required.
stability at 60 degrees C, of 2,000 N (204 kg). The Index of If the area is unduly damaged or pitted, the stabilized mix
Retained Strength when tested using a Marshall mould shall be removed and replaced with fresh stabilized mix
shall be not less than 70%. spread and properly compacted and finished.

♦ 3-12 ♦
3.4.3.17 Bitumen Stabilization Procedures - Testing of operators. Working operations should take into account
Bitumen Stabilized Courses the wind direction to minimize the dust problem and
consequent eye or skin irritation to any personnel in the
1 For every 5,000 sq.m. of each stabilized layer or for vicinity.
each day's completed area (whichever is the smaller) the 3 When hydrated lime is used, precautions shall also
following sampling and testing shall be carried out: be taken against the effects of prolonged exposure to the
i. In situ density of a minimum of 3 samples skin.
(taken immediately after completion of final
compaction) determined in accordance with 3.4.3.20 Lime Stabilization Procedures - Stationary Plant
AASHTO T 191 or T 205 and which shall be not Mixing
less than 100% of the density of the approved
laboratory mix. 1 When approval is given to utilize stationary plant for
ii. Composition of the mix by extraction in mixing, whether batch mixing plant or continuous type
accordance with AASHTO T 164. The variation mixing plant, the plant and equipment and handling and
from the approved job-mix, based on results of mixing procedures shall be as specified for cement
4 tests, shall not exceed the following: stabilization and as specified herein for plant mixing of
- Aggregates passing lime stabilized materials.
No. 200 (0.075 mm) +1 percent 3.4.3.21 Lime Stabilization Procedures - Mixed in Place
- Asphalt content +0.2 percent
Procedures
iii. Compressive strength in accordance with
1 Mixed in place procedures will normally be permitted
AASHTO T 167, of samples before compaction.
when the soil to be stabilized is in-situ site material.
The minimum compressive strength value shall
be not less than the value specified under Item 2 Spreading and mixing of the lime and soil material
3 of Paragraph 3.4.3.11. shall be carried out as specified for cement stabilized
iv. Marshall stability in accordance with AASHTO courses.
T245, of samples before compaction. The
3.4.3.22 Lime Stabilization Procedures - Placing and
minimum Marshall stability value shall be not
Spreading Stationary Plant Mixes
less than the value specified under Item 3 of
Paragraph 3.4.3.11. 1 Placing and spreading of stationary plant mixes shall
be as specified for cement stabilized courses.

3.4.3.18 Lime Stabilization Procedures - Mix Design 3.4.3.23 Lime Stabilization Procedures - Compaction
and Finishing
1 The material to be stabilized shall be a clayey gravel,
clayey sand or lean clay soil with not more than 50% 1 Compaction of lime stabilized courses to 100% of
passing 0.425 mm (No. 40) sieve and plasticity index laboratory density of approved job mix specimens,
greater than 10%. finishing and provision of longitudinal joints, shall be as
2 The lime content and optimum moisture content specified for cement stabilized courses with the following
shall be determined in the field laboratory and in the modifications:
presence of the Engineer. Cylinders molded in accordance i. When quick lime is used, the layer shall not be
with AASHTO T 220 shall be cured and tested at 7 days compacted immediately after spreading the lime,
and 28 days. Load rate of application shall be in as hydration of the lime will cause damage to the
accordance with AASHTO T 22. The minimum compacted layer. The time within which the
compressive strength at 7 days after molding shall be one compaction shall be completed will be as
MN/sq.m. (10 kg./sq.cm.). estimated in the laboratory.
3 Lime content and water content of the mix shall each ii. Compaction shall not take place after lime
be within -0.2% to +2.5% of the approved mix design hydration. Any lime stabilized material that has
percentages. been mixed or deposited after lime hydration,
shall be removed and replaced with fresh
3.4.3.19 Lime Stabilization Procedures - Safety
material, mixed and treated as specified.
Precautions

1 Special precautions shall be taken when handling


3.4.3.24 Lime Stabilization Procedures - Tolerances and
quicklime as it will rapidly corrode equipment and can
inflict severe skin burns to personnel coming in contact Replacement of Unsatisfactory Areas
with it. 1 Finished surface tolerances and the rectification
2 Suitable methods for handling quicklime shall be procedures for any areas which fail to meet such
adopted, including fully mechanized or bottom dump tolerances shall be as specified for cement stabilized
handling equipment and protective clothing worn by the courses.

♦ 3-13 ♦
3.4.3.25 Testing of Lime Stabilized Courses

1 For every 5,000 sq.m. of each stabilized layer or for


each day's completed area (whichever is the smaller) the
following sampling and testing shall be carried out:
i. In situ density of a minimum of 3 samples
(taken immediately after completion of final
compaction) determined in accordance with
AASHTO T 191 or T 205 and which shall be not
less than 100% of the density of the approved
laboratory mix.
ii. Lime content in accordance with AASHTO T
232.
iii. Gradation of mix in accordance with AASHTO
T 27.
iv. If the source of materials changes, the moisture
- density relationship in accordance with
AASHTO T 134 and gradation of the new mix in
accordance with AASHTO T27.
v. Compressive strength of a set of 3 test
specimens molded and cured in accordance
with AASHTO T 134 and T 126, and tested in
accordance with AASHTO T 22.

3.4.4 Method of Measurement


1 Cement stabilized course, bitumen stabilized course
and lime stabilized course shall each be measured by cu.m.
of compacted stabilized course. Measurements shall be of
the area and thickness dimensions shown on the
Drawings.
2 Curing seal shall be measured by sq.m. of areas
computed from the length and width of the completed
sections shown on the Drawings.

3.4.5 Basis of Payment


1 The amount of completed and accepted work,
measured as provided for above, will be paid for at the
unit rates for the various items in the Bill of Quantities,
which rate shall be full compensation for equipment, tools,
labor, locating sources of supply, supplying materials,
sampling and testing, screening, crushing, transporting,
stockpiling, laying, mixing and compacting and for extra
material in tapered edges, and other items necessary for
the proper completion of the work.

3.4.6 Items in the Bill of Quantities


i. Cement Stabilized Base Course
(thickness) cu.m

ii. Bitumen Stabilized Base Course


(thickness) cu.m

iii. Lime Stabilized Base Course


(thickness). cu.m

iv. Curing Seal sq.m

♦ 3-14 ♦

S-ar putea să vă placă și