Sunteți pe pagina 1din 72

Ref. Title Page No. Ref. Title Page No.

5.1 Concrete Materials and Mixes 5-1 5.1.4.2  Job-Site Mixing 5-9 
5.1.4.3  Ready-Mixed Concrete 5-9 
5.1.1  Description 5-1 
5.1.4.4  Quality Control and Testing – General 5-10 
5.1.1.1  Definitions 5-1 
5.1.4.5  Quality Control – Testing
5.1.1.2  References 5-1 
on Fresh Concrete 5-10 
5.1.1.3  Submittals 5-2 
5.1.4.6  Quality Control – Testing on Hardened
5.1.1.4  Quality Assurance 5-2 
Concrete 5-11 
5.1.2  Materials 5-3 
5.1.5  Method of Measurement 5-12 
5.1.2.1  Portland Cement 5-3 
5.1.5.1  Measured Items 5-12 
5.1.2.2  Silica Fume 5-3 
5.1.5.2  Items Not Measured 5-12 
5.1.2.3  Supplementary Cementing
5.1.6  Basis of Payment 5-12 
Material (SCM) 5-4 
5.1.7  Items in the Bill of Quantities 5-13 
5.1.2.4  Blended Hydraulic Cement 5-4 
5.1.2.5  Aggregates 5-4  5.2 Reinforcing Steel 5-13
5.1.2.6  Water 5-5 
5.2.1  Description 5-13 
5.1.2.7  Admixtures 5-5 
5.2.1.1  References 5-13 
5.1.2.8  Fiber Reinforcement 5-6 
5.2.1.2  Submittals 5-13 
5.1.3  Concrete Mixes 5-6 
5.2.1.3  Quality Assurance 5-13 
5.1.3.1  Design Mixes 5-6 
5.2.1.4  Delivery, Storage and Handling 5-13 
5.1.3.2  Testing Agency 5-6 
5.2.2  Materials 5-13 
5.1.3.3  Reports 5-6 
5.2.2.1  Steel Reinforcement 5-13 
5.1.3.4  Concrete Classes 5-6 
5.2.2.2  Reinforcement Accessories 5-14 
5.1.3.5  Threshold Values for Supplementary
5.2.2.3  Fabricating Reinforcement 5-14 
Cementing Materials (SCM) 5-6 
5.2.3  Construction Requirements 5-14 
5.1.3.6  Limit Values for Supplementary
5.2.3.1  General 5-14 
Cementing Materials (SCM) 5-7 
5.2.3.2  Shipping, Storage and Cleaning 5-14 
5.1.3.7  Water-Cementitious Materials Ratio 5-7 
5.2.3.3  Placing 5-15 
5.1.3.8  Slump Limits 5-7 
5.2.3.4  Concrete Cover 5-15 
5.1.3.9  Total Salt Content 5-7 
5.2.4  Method of Measurement 5-15 
5.1.3.10  Initial Setting Time 5-8 
5.2.5  Basis of Payment 5-15 
5.1.3.11  Test Mixes – Structural Grade
5.2.6  Items in the Bill of Quantities 5-16 
Concrete 5-8 
5.1.3.12  Test Mixes – Blinding and Plain 5.3 Reinforced Concrete
Concrete 5-8  Structures 5-16
5.1.3.13  Adjustments to Concrete Mixes 5-8 
5.3.1  Description 5-16 
5.1.3.14  Absorption Test 5-8 
5.3.1.1  Definitions 5-16 
5.1.3.15  Permeability Tests 5-8 
5.3.1.2  References 5-16 
5.1.3.16  Synthetic Fiber 5-9 
5.3.1.3  Submittals 5-16 
5.1.3.17  Admixtures 5-9 
5.3.1.4  Quality Assurance 5-17 
5.1.4  Construction Requirements 5-9 
5.3.2  Materials 5-17
5.1.4.1  Concrete Mixing 5-9 
Ref. Title Page No. Ref. Title Page No.
5.3.2.1  Form Materials 5-17  5.4.3.3  Placement of Anchorages 5-31 
5.3.2.2  Waterstops 5-18  5.4.3.4  Identification and Testing 5-31 
5.3.2.3  Concrete Curing Cover Sheets 5-18  5.4.3.5  Protection of Prestressing Steel 5-32 
5.3.2.4  Curing Compounds 5-19  5.4.3.6  Ducts 5-32 
5.3.2.5  Concrete Accessories 5-19  5.4.3.7  Grout 5-33 
5.3.2.6  Repair Materials 5-19  5.4.3.8  Tensioning 5-34 
5.3.3  Construction Requirements 5-19  5.4.3.9  Pretension Construction 5-35 
5.3.3.1  Formwork 5-19  5.4.3.10  Post-Tension Construction 5-36 
5.3.3.2  Falsework 5-20  5.4.3.11  Grouting 5-37 
5.3.3.3  Embedded Items 5-20  5.4.4  Method of Measurement 5-39 
5.3.3.4  Removing and Reusing Forms 5-20  5.4.5  Basis of Payment 5-40 
5.3.3.5  Vapor Retarders 5-21  5.4.6  Items in the Bill of Quantities 5-40 
5.3.3.6  Construction Joints 5-21 
5.5 Concrete Bridges and Erection
5.3.3.7  Contraction and Expansion Joints 5-21 
Procedures 5-40
5.3.3.8  Waterstops 5-22 
5.3.3.9  Concrete Placement 5-22  5.5.1  Description 5-40 
5.3.3.10  Hot-Weather Concreting 5-24  5.5.1.1  Scope 5-40 
5.3.3.11  Finishing Plastic Concrete 5-25  5.5.1.2  References 5-40 
5.3.3.12  Curing Concrete 5-25  5.5.2  Materials 5-40 
5.3.3.13  Formed Finishes 5-26  5.5.3  Construction Requirements 5-41 
5.3.3.14  Tolerances 5-26  5.5.3.1  Balanced Cantilever Construction
5.3.4  Method of Measurement, Basis with In-Situ Concrete 5-41 
of Payment and Bill of Quantities 5-27  5.5.3.2  Glued Precast Segmental
Construction 5-42 
5.4 Prestressed Concrete
5.5.3.3  Precast Beam and slab Construction 5-43 
Structures 5-27
5.5.3.4  In-Situ Construction 5-43 
5.4.1  Description 5-27  5.5.4  Method of Measurement, Basis of
5.4.1.1  Scope 5-27  Payment and Items in the Bills
5.4.1.2  Definitions 5-27  of Quantities 5-43 
5.4.1.3  References 5-27 
5.6 Vehicular and Pedestrian
5.4.1.4  Submittals 5-28 
Underpasses and Animal
5.4.2  Materials 5-28 
Crossings 5-44
5.4.2.1  Concrete 5-28 
5.4.2.2  Reinforcing Steel 5-29  5.6.1  Description 5-44 
5.4.2.3  Prestressing Steel 5-29  5.6.1.1  Scope 5-44 
5.4.2.4  Post-Tensioning Anchorages 5.6.1.2  References 5-44 
and Couplers 5-29  5.6.2  Materials 5-44 
5.4.2.5  Epoxy-Bonding Agents for Precast 5.6.3  Construction Requirements 5-44 
Segmental Construction 5-29  5.6.3.1  Excavation 5-44 
5.4.3  Construction Requirements 5-29  5.6.3.2  Structural Concrete 5-45 
5.4.3.1  Placement of Ducts 5-29  5.6.3.3  Concrete Piles 5-45 
5.4.3.2  Placement of Prestressing Steel 5-30  5.6.3.4  Waterproofing 5-45
Ref. Title Page No. Ref. Title Page No.
5.6.3.5  Concrete Pavement Construction 5-45  5.7.3.20  Pavement Marking 5-57 
5.6.3.6  Bituminous Pavement Construction 5-45  5.7.3.21  Field Quality Control 5-57 
5.6.3.7  Electrical Works 5-45  5.7.3.22  Repairs and Protection 5-58 
5.6.4  Method of Measurement 5-45  5.7.3.23  Determination of Concrete Thickness 5-59 
5.6.5  Basis of Payment 5-45  5.7.4  Method of Measurement 5-59 
5.6.6  Items in the Bill of Quantities 5-45  5.7.5  Basis of Payment 5-59 
5.7.6  Items in the Bill of Quantities 5-59 
5.7 Cement Concrete Pavement 5-45
5.8 Joint Sealers for Concrete
5.7.1  Description 5-45 
Pavement 5-59
5.7.2  Materials 5-45 
5.7.2.1  Forms 5-46  5.8.1  Description 5-59 
5.7.2.2  Steel Reinforcement 5-46  5.8.2  Materials 5-59 
5.7.2.3  Concrete Materials 5-46  5.8.2.1  Materials, General 5-59 
5.7.2.4  Admixtures 5-47  5.8.2.2  Elastomeric Hot-Poured Joint Sealants 5-60 
5.7.2.5  Curing Materials 5-47  5.8.2.3  Joint Sealant Backing 5-60 
5.7.2.6  Related Materials 5-47  5.8.2.4  Miscellaneous Materials 5-60 
5.7.2.7  Concrete Mixes 5-47  5.8.3  Construction Requirements 5-60 
5.7.2.8  Concrete Mixing 5-48  5.8.3.1  Examination 5-60 
5.7.2.9  Limitations of Mixing: 5-48  5.8.3.2  Preparation 5-60 
5.7.3  Construction Requirements 5-48  5.8.3.3  Installation of Joint Sealers 5-60 
5.7.3.1  Preparation 5-48  5.8.3.4  Cleaning 5-61 
5.7.3.2  Edge Forms and Screed Construction 5-49  5.8.3.5  Protection 5-61 
5.7.3.3  Steel Reinforcement 5-49  5.8.4  Method of Measurement, Basis
5.7.3.4  Placement of Reinforcement 5-49  of Payment and Bill of Quantities 5-61 
5.7.3.5  Joints 5-49 
5.9 Reinforced Concrete Box Culverts
5.7.3.6  Conditioning of Underlying Course,
and Headwalls, Wingwalls,
Slip-Form Construction 5-52 
Cut-Off Walls and Aprons 5-61
5.7.3.7  Conditioning of Underlying Course,
Side-Form Construction 5-52  5.9.1  Description 5-61 
5.7.3.8  Handling, Measuring, and Batching 5.9.2  Materials 5-61 
Material 5-52  5.9.3  Construction Requirements 5-61 
5.7.3.9  Concrete Protection and Curing 5-53  5.9.4  Method of Measurement 5-62 
5.7.3.10  Concrete Placement 5-53  5.9.5  Basis of Payment 5-62 
5.7.3.11  Concrete Finishing 5-55  5.9.6  Items in Bill of Quantities 5-62 
5.7.3.12  Final Strike-Off, Consolidation
5.10 Waterproofing for Structures 5-62
and Finishing 5-55 
5.7.3.13  Surface Texture 5-56  5.10.1  Description 5-62 
5.7.3.14  Skid Resistant Surfaces 5-56  5.10.1.1  Scope 5-62 
5.7.3.15  Surface Test 5-56  5.10.1.2  References 5-62 
5.7.3.16  Removing Forms 5-57  5.10.2  Materials 5-62 
5.7.3.17  Sealing Joints 5-57  5.10.2.1  Asphalt 5-62 
5.7.3.18  Opening to Traffic 5-57  5.10.2.2  Bitumen 5-62 
5.7.3.19  Pavement Tolerance 5-57  5.10.2.3  Waterproofing Fabric 5-62
Ref. Title Page No. Ref. Title Page No.
5.10.2.4  Self-Adhesive Polyethylene Sheet 5-62  5.11.4  Method of Measurement, Basis
5.10.2.5  Tar for Absorptive Treatment 5-62  of Payment and Bill of Quantities 5-67 
5.10.2.6  Tar Seal Coat 5-63 
5.12 Bridge Load Testing 5-67
5.10.2.7  Proprietary Waterproofing Systems 5-63 
5.10.2.8  Epoxy Coating System 5-63  5.12.1  Description 5-67 
5.10.3  Construction Requirements 5-63  5.12.2  Load Application 5-67 
5.10.3.1  Surface Preparation 5-63  5.12.2.1  Composition of Applied Load 5-67 
5.10.3.2  Inspection, Delivery and Storage 5-63 5.12.2.2  Testing by Static Load 5-68 
5.10.3.3  Asphalt and Bitumen Waterproofing 5.12.2.3  Testing by Moving Load 5-68 
Fabric 5-63  5.12.3  Visual Inspection 5-68 
5.10.3.4  Proprietary Waterproofing 5.12.4  Measurements 5-68 
Membranes 5-64  5.12.5  Method of Measurement 5-68 
5.10.3.5  Damage Patching of Waterproofing 5.12.6  Basis of Payment 5-68 
Fabrics 5-64  5.12.7  Items in the Bill of Quantities 5-68 
5.10.3.6  Dampproofing 5-64 
5.10.3.7  Protection of Waterproofing and
Dampproofing 5-64 
5.10.3.8  Testing 5-65 
5.10.4  Method of Measurement 5-65 
5.10.5  Basis of Payment 5-65 
5.10.6  Items in the Bill of Qquantities 5-65 

5.11 Protective Coating for Concrete 5-65


5.11.1  Description 5-65 
5.11.1.1  Scope 5-65 
5.11.1.2  Submittals 5-65 
5.11.1.3  Performance Requirements 5-65 
5.11.1.4  Quality Assurance 5-65 
5.11.1.5  Testing 5-66 
5.11.2  Materials 5-66 
5.11.2.1  General 5-66 
5.11.2.2  Primer 5-66 
5.11.2.3  Topcoat 5-66 
5.11.2.4  Specifications 5-66 
5.11.3  Construction Requirements 5-66 
5.11.3.1  General 5-66 
5.11.3.2  Inspection of Concrete 5-66 
5.11.3.3  Surface Preparation 5-67 
5.11.3.4  Approval Prior to Coating Application 5-67 
5.11.3.5  Application 5-67 
5.1 Concrete Materials and Mixes ASTM C 114 Standard Test Methods for Chemical
Analysis of Hydraulic Cement
5.1.1 Description ASTM C 117 Standard Test Method for Materials
Finer Than 75 Micrometer (No. 200)
5.1.1.1 Definitions Sieve in Mineral Aggregates by
1 Concrete shall consist of a mixture of cementitious Washing
materials, aggregates, water and additives. ASTM C 127 Standard Test Method for Density,
2 Cementitious Materials: Portland cement alone or in Relative Density (Specific Gravity) and
combination with one or more of blended hydraulic Absorption of Coarse Aggregate
cement, fly ash and other pozzolans, ground granulated ASTM C 128 Standard Test Method for Density,
blast-furnace slag and silica fume. Relative Density (Specific Gravity) and
Absorption of Fine Aggregate
5.1.1.2 References
ASTM C 131 Standard Test Method for Resistance to
AASHTO T26 Standard Method of Test for Quality of Degradation of Small-Size Coarse
Water to be used in Concrete Aggregate by Abrasion and Impact in
1 American Association of State Highways and the Los Angeles Machine
Transportation Officials (AASHTO): ASTM C 142 Standard Test Method for Clay Lumps
2 American Concrete Institute (ACI): and Friable Particles in Aggregates

ACI 117 Specifications for Standard Tolerances ASTM C 143 Standard Test Method for Slump of
for Concrete Construction and Hydraulic Cement Concrete
Materials ASTM C 150 Standard Specification for Portland
ACI 301 Specifications for Structural Concrete Cement
for Buildings ASTM C 172 Standard Practice for Sampling Freshly
ACI 304 Guide for Measuring, Mixing, Mixed Concrete
Transporting, and Placing Concrete ASTM C 186 Standard Test Method for Heat of
3 American National Standards Institute (ANSI): Hydration of Hydraulic Cement

ANSI Q9001 Quality Systems – Model for Quality ASTM C 191 Standard Test Method for Time of
Assurance in Design, Development, Setting of Hydraulic Cement by Vicat
Production, Installation, and Servicing Needle

ANSI Q9002 Quality Systems – Model for Quality ASTM C192/C192M Standard Practice for Making
Assurance in Production, Installation, and Curing Concrete Test Specimens in
and Servicing the Laboratory (AASHTO T126)

4 American Society for Testing and Materials (ASTM): ASTM C 219 Standard Terminology Relating to
Hydraulic Cement
ASTM A 820 Standard Specification for Steel Fibers
for Fiber-Reinforced Concrete ASTM C 227 Standard Test Method for Potential
Alkali Reactivity of Cement-Aggregate
ASTM C31/C31M Standard Practice for Making and
Combinations (Mortar-Bar Method)
Curing Concrete Test Specimens in the
Field (AASHTO T23) ASTM C 289 Standard Test Method for Potential
Reactivity of Aggregates (Chemical
ASTM C 33 Standard Specification for Concrete
Method)
Aggregates
ASTM C 295 Standard Guide for Petrographic
ASTM C39/C39M Standard Test Method for Compressive
Examination of Aggregates for
Strength of Cylindrical Concrete
Concrete
Specimens (AASHTO T22)
ASTM C 311 Standard Test Methods for Sampling
ASTM C 40 Standard Test Method for Organic
and Testing Fly Ash or Natural
Impurities in Fine Aggregates for
Pozzolans for Use as a Mineral
Concrete
Admixture in Portland-Cement
ASTM C 42 Standard Test Method for Obtaining Concrete
and Testing Drilled Cores and Sawed
ASTM C 494 Standard Specifications for Chemical
Beams of Concrete
Admixtures for Concrete
ASTM C 88 Standard Test Method for Soundness of
ASTM C 586 Standard Test Method for Potential
Aggregates by Use of Sodium Sulfate
Alkali Reactivity of Carbonate Rocks for
or Magnesium Sulfate
Concrete Aggregates (Rock Cylinder
ASTM C 94 Standard Specifications for Ready- Method)
Mixed Concrete

♦ 5-1 ♦
ASTM C 595 Standard Specifications for Blended BS EN 12350 Testing Fresh Concrete
Hydraulic Cements BS EN 12390 Testing Hardened Concrete
ASTM C 618 Standard Specifications for Coal Fly BS EN 12620 Specification for Aggregates
Ash and Raw or Calcined Natural
BS EN 197 Cement Specification
Pozzolan for Use as a Mineral
Admixture in Concrete Part 1: Composition and specification

ASTM C 989 Standard Specification for Ground Part 2: Conformity evaluation


Granulated Blast-Furnace Slag for Use 6 Commercial Standards (CS):
in Concrete and Mortars Concrete Plant Manufacturers Bureau - Concrete Plant
ASTM C 1064 Standard Test Method for Temperature Standards
of Freshly Mixed Portland Cement National Ready-Mixed Concrete Association (NRMCA) -
Concrete Check List
ASTM C 1077 Standard Practice for Laboratories 7 Corps of Engineers (CE):
Testing Concrete and Concrete
CE CRD-C119 Test for Flat and Elongated Particles
Aggregates for Use in Construction and
Criteria for Laboratory Evaluation 8 National Standard of Canada:
ASTM C 1105 Standard Test Method for Length CAN/CSA A23.5-M86 Supplementary Cementing
Change of Concrete Due to Alkali- Materials
Carbonate Rock Reaction
5.1.1.3 Submittals
ASTM C 1116 Standard Specification for Fiber-
Reinforced Concrete and Shotcrete 1 Product Data: For proprietary materials and items.
ASTM C 1202 Test Method for Electrical Indication of 2 Design Mixes: For each concrete mix. Include
Concrete’s Ability to Resist Chloride Ion alternative mix designs when characteristics of materials,
Penetration (AASHTO T 277) project conditions, weather, test results, or other
circumstances warrant adjustments.
ASTM D 512 Standard Test Methods for Chloride Ion
in Water 3 Qualification Data: For firms and persons specified in
Paragraph 5.1.1.4 "Quality Assurance" to demonstrate
ASTM D 516 Standard Test Method for Sulfate Ion in
their capabilities and experience. Include lists of
Water
completed projects with project names and addresses,
ASTM E 329 Standard Specification for Agencies names and addresses of engineers and owners, and any
Engaged in the Testing and/or other information required by the Engineer.
Inspection of Materials used in
4 Material Test Reports: From a qualified testing
Construction
agency indicating and interpreting test results for
ASTM E 548 Standard Guide for General Criteria compliance of the following with requirements indicated,
Used for Evaluating Laboratory based on comprehensive testing of current materials:
Competence
5 Material Certificates: Signed by manufacturers and
5 British Standards: Contractor certifying that each of the following items
BS 812 Testing Aggregates complies with specified requirements:
BS 1881 Methods of Testing Concrete i. Cementitious materials and aggregates.
BS 1199 and 1200 Specification for Building Sands from ii. Fiber reinforcement.
Natural Sources iii. Admixtures: Material certificates in lieu of
material laboratory test reports when permitted
BS 4027 Specification for Sulfate-Resisting
by the Engineer. Material certificates shall be
Portland Cement
signed by the manufacturer and the Contractor,
BS 5328 Methods for Specifying Concrete certifying that each material item complies with
Including Ready-Mixed Concrete specified requirements. Provide certification
BS EN 932 Tests of Aggregates for General from admixture manufacturers that chloride
Properties content complies with specified requirements.
BS EN 933 Tests of Aggregates for Geometric 6 Minutes of pre-installation conference.
Properties
5.1.1.4 Quality Assurance
BS EN 1097 Tests of Aggregates for Mechanical
Properties 1 Quality System: Comply with ISO 9001/9002 Quality
BS EN 1367 Tests of Aggregates for Thermal and System and ISO 14001 Environmental Management
Weathering Properties Systems as a minimum. Incorporate all the standard
procedures supplied by the Engineer and the Employer.
BS EN 1744 Tests of Aggregates for Chemical
Properties

♦ 5-2 ♦
2 Codes and Standards: Comply with the latest version submittals, status of coordinating work, and availability of
of ACI Manual of Concrete Practice Parts 1, 2, 3, 4 & 5, and materials. Establish preliminary work progress schedule
CRSI "Manual of Standard Practice” except where more and procedures for materials inspection, testing, and
stringent requirements are shown or specified. certifications. Require representatives of each entity
3 Concrete Quality Control Engineer: Appoint a full- directly concerned with cast-in-place concrete to attend
time Concrete Quality Control Engineer (CQCE) to ensure conference, including, but not limited to, the following:
that concrete is properly produced, placed, cured and - Contractor’s superintendent.
protected. The CQCE shall be equivalent to a Member of - Agency responsible for concrete design mixes.
the Institute of Concrete Technology (MICT) or as
- Agency responsible for field quality control.
approved by the Engineer and shall be responsible for the
maintenance and submission of all specified records. The - Ready-mix concrete producer.
CQCE shall not report to the site construction - Concrete subcontractor.
management but to the Contractor’s management and to - Primary admixture manufacturers
the Engineer. The CQCE shall set standards of quality and
insist that these standards be followed, prepare a Quality
5.1.2 Materials
Control Program for the inspection and testing of concrete
and the maintenance of all reports and records to meet the 5.1.2.1 Portland Cement
specified requirements and requirements of the Engineer.
Depending on the quantity of concrete works in specific 1 Portland Cement: Cement shall be low alkali with
project, the Special Specifications may waive this chemical composition in accordance with Table 1 of ASTM
requirement. C 150 or BS EN 197: Part 1. The magnesia content shall be
limited to 4 percent by weight of cement, as tested in
4 The Contractor shall operate a Quality Assurance
accordance with ASTM C 114. Use one brand of cement
System in accordance with ANSI Q9002. The Quality
throughout Project unless otherwise approved by the
Assurance Manager shall be responsible for the
Engineer. Manufacturer’s test certification shall be
preparation of a Quality Plan for approval of the
supplied for each delivery of cement and shall confirm
operations specified in this Section. The Quality Plan shall
that the cement complies with the above requirements
include, among other things, the list and schedule of the
and shall be submitted by the Contractor not later than the
Quality Control audits that the Quality Assurance Manager
day of delivery of the cement. The Engineer shall have the
shall make.
right to call for tests, the cost of which is to be borne by
5 Concrete Manufacturer Qualifications: A firm the Contractor, on each delivery of cement to confirm that
experienced in manufacturing ready-mixed concrete the cement meets the following requirements.
products complying with ASTM C 94/C94M requirements
i. Ordinary Portland cement (OPC) conforms to
for production facilities and equipment.
ASTM C 150, Type I or BS EN 197. The heat of
6 Engage an independent testing agency acceptable to hydration shall not exceed 325 kj/kg when tested
the Engineer to perform material evaluation tests and in accordance with ASTM C 186. C3A content
qualified according to ASTM C 1077 and ASTM E 329 to shall be a minimum of 5 percent and a maximum
conduct the testing indicated, as documented according to of 13 percent.
ASTM E 548 and to design concrete mixes. ii. Sulfate-resisting Portland cement conforms to
i. Personnel conducting field tests shall be ASTM C 150, Type V or BS 4027; C3A content
qualified as ACI concrete field testing technician, shall not be more than 3.5 percent.
Grade 1 according to ACI CP-1 or an equivalent iii. Moderate Sulfate: conforms to ASTM C 150 type
certification program approved by the Engineer. II or BS EN 197. C3A content shall be a minimum
of 3.5 percent and a maximum of 8 percent.
7 Materials and installed work may require testing and
retesting at any time during progress of work, if instructed 2 Sampling shall be carried out in accordance with BS
by the Engineer. Tests, including retesting of rejected EN 196: Part 7.
materials for installed work, shall be done at the 3 Test cement for fineness by air permeability
Contractor’s expense. apparatus in accordance with ASTM C 204 to meet the
8 Source Limitations: Obtain each type or class of requirements of ASTM C 150.
cementitious material of the same brand from the same 4 Test cement for soundness. Autoclave expansion in
manufacturer's plant, each aggregate from one source, accordance with ASTM C 151.
and each admixture from the same manufacturer.
5.1.2.2 Silica Fume
9 Pre-installation Conference: Conduct conference at
Project site to comply with requirements as follows: 1 Silica fume (SF), also referred to as microsilica, used
At least 35 days prior to submitting design mixes, conduct as a cement replacement shall be in accordance with
a meeting to review detailed requirements for preparing Type U, specified in Canadian National Standard
concrete design mixes and to determine procedures for CAN/CSA-A23.5 - M86. The silica fume shall be
satisfactory concrete operations. Review requirements for obtained from an approved supplier.

♦ 5-3 ♦
2 The approved supplier shall provide documentation source and shall not contain substances that cause
to establish the following: spalling. Only aggregates not susceptible to alkali
i. That the silica fume complies with Type U of aggregate reaction shall be used. The Contractor shall
CAN/CSA-A23.5 - M86. supply samples of the materials for approval by the
ii. The silica fume results from the production of Engineer and each aggregate source shall be subject to
silicon or ferro-silicon alloys containing at least monitoring by the Engineer. Grading of aggregate shall be
85 percent silicon dioxide. That source of supply to the compliance of BS EN 12620.
shall remain the same for the construction 2 Coarse aggregate for structural concrete shall be
period of the project. 20mm nominal size, free from material passing a 5mm
iii. That the supply shall be adequate to meet the sieve, and shall consist of crushed stone, selected, re-
anticipated peak requirement. crushed, finish screened and washed with water meeting
iv. Chemical analyses to give the percentages of the the requirements of Paragraph 5.1.2.6 as necessary, and
following materials: shall comply with the following:
Si O2 C
Freq. of
Ca O Fe2 O3 Tests Test Description Standard Limit
Al2 O3 Na2 O (min)

K2 O Mg O Los Angeles ASTM 25%


Initial Abrasion Loss
SO3 C 131 maximum
(Grading A or B)
v. Loss on ignition. Ratio of Los
vi. Percentage of particles greater than 44 μm. Angeles Abrasion ASTM
vii. Specific surface area and method of test, Loss at 100 & 500 0.25%
Initial C 131
together with corresponding particle size. Revolutions maximum
(100/500 Note 6
3 Delivery of silica fume to the concrete batching plant
Revolutions Value)
shall be in dry powder form, with a bulk density between
200 and 650 kg/cu m. Clay Lumps and ASTM 1.0%
1 per day
Friable Particles C 142 maximum
4 Manufacturer's test certification shall be supplied for
each delivery of silica fume and shall confirm that the Material Finer than ASTM 1.0%
1 per day
silica fume complies with the above requirements and 75 Microns C 117 maximum
shall be submitted by the Contractor no later than the day 1 per 7 ASTM 2.0%
of delivery of the silica fume. Water Absorption
days C 127 maximum
5 The Engineer shall have the right to call for tests, the 1 per 3 0.03%
cost of which are to be borne by the Contractor, on each Chlorides as Cl BS 812
days max *
delivery of silica fume, if necessary to establish or confirm
1 per 3 0.3% max
that the silica fume meets the above requirements. Sulfates as SO3 BS 812
days *
5.1.2.3 Supplementary Cementing Material (SCM) Magnesium ASTM
1 per 30 12%
Sulfate Soundness
1 Supplementary cementing materials, if permitted by days C 88 maximum
Loss (5 cycles)
the Engineer, shall be selected from subparagraphs below.
1 per 3 25%
Blending of fly ash or slag with Portland cement shall be Flakiness Index BS 812
days maximum
done at mixing plant.
1 per 3 25%
i. Pulverized Fly Ash: ASTM C 618, Class C or F. Elongation Index BS 812
days maximum
ii. Ground Granulated Blast-Furnace Slag: ASTM C
Per
989, Grade 100 or 120. Each Appendix
ASTM
production Reactive Silica X1.3.7 of
5.1.2.4 Blended Hydraulic Cement C 227
sample ASTM C
1 Blended Hydraulic Cement: conforming to ASTM C 33
595 shall be used solely for grouts if specified or approved 1 per 7 ASTM Minimum
Specific Gravity
by the Engineer. It shall not to be used for making days C 127 2.6
structural concrete. 1 per 2 BS EN
Moisture Content
days 1097-5
5.1.2.5 Aggregates
Each
1 Aggregates shall be normal-weight and shall be from 3%
production Shell Content BS812
maximum
approved sources and shall conform to the requirements sample
of ASTM C 33 and BS EN 12620. Petrographic analyses
Table 5.1.2.1: Coarse Aggregate Specifications and Testing
shall be made in accordance with ASTM C 295.
Aggregates for exposed concrete shall be from a single

♦ 5-4 ♦
* Additionally, the limits specified in Paragraph 5.1.3.9 for tons of fine aggregate and every 80 tons
total salt content shall not be exceeded of coarse aggregate.
3 Fine aggregate, shall pass a 5mm sieve and shall - Chemical analyses shall be carried out on
consist of crushed gravel, crushed stone or natural sand every 100 tons of aggregate.
with rounded or surrounded particles, washed as ii. The Engineer shall have the right to call for
necessary, and shall comply with the following: additional samples at any time for testing of
aggregates delivered to the Site or of aggregates
Test Description Standard Limit at the source of supply in order to confirm that
Clay Lumps and the aggregates meet the above requirements.
ASTM C 142 1.0% maximum
Friable Particles 6 Transportation: During transportation to the Site, all
maximum 3% for aggregates shall be protected from wind-borne
Material Finer natural sand and 5% contaminants. If these contaminants are present at time
ASTM C 117
than 75 Microns for crushed sand of delivery, the aggregates shall be washed with water
with no plastic fines meeting the requirement of Paragraph 5.1.2.6. Transport
Water vehicles shall be cleaned to remove possible
ASTM C 128 1.0% maximum
Absorption contamination due to previous use.
Chlorides as Cl BS 812 0.06% maximum* 7 Storage: Aggregates shall be stored (under shade) on
hard concrete floors or other approved surface having
Sulfates as SO3 BS 812 0.30% maximum*
sufficient slope to ensure adequate drainage of aggregate
Organic Lighter than before being used for concrete. Each size and type shall be
ASTM C 40
Impurities Standard stored in separate heaps without intermixing. Storage
Sand Equivalent AASHTO T176 75% minimum shall prevent contamination of the aggregates by foreign
material including windblown dust. Fine and coarse
Five Cycles of
aggregates shall be separated by permanent substantial
Soundness in
BS 812 15% maximum partitions. Methods of storing, shading and cooling
Magnesium
Sulfate aggregates shall be approved by the Engineer.

Table 5.1.2.2: Fine Aggregate Specifications and Testing 8 Plums used in cyclopean concrete shall consist of
non-reactive broken stone spalls or boulders ranging in
* Additionally, the limits specified in Paragraph 5.1.3.9 for size from 200mm to 300mm. They shall be free from sharp
total salt content shall not be exceeded or angular edges and shall not form more than 30 percent
4 Certification: Obtain from each proposed source of of the total volume of concrete. They shall be evenly
supply test certification to confirm that the aggregates graded and shall be soaked in water prior to incorporation
comply with the above requirements. The following in the mix. Plums shall be evenly distributed in the
information shall be provided: concrete mix with a minimum cover of 100mm.
i. Quarry location. 5.1.2.6 Water
ii. Aggregate type.
iii. Petrographic analysis report. 1 Water used for mixing concrete, ice production,
iv. Grading curve. washing and cooling aggregates, and curing concrete
v. Shape and surface texture. shall be free from impurities, oil, acid, salts, alkali, organic
vi. Flakiness index. matter, and other potentially deleterious substances when
vii. 10 percent fines value. tested in accordance with AASHTO T26, ASTM D 512 and
viii. Impact test. ASTM D 516. Additionally, the limits specified in
ix. Shell content. Paragraph 5.1.3.9 for the total salt content of the concrete
x. Chloride and sulfate content. shall not be exceeded.
xi. Relative density. 2 Once a source of satisfactory supply has been
xii. Water absorption value and moisture content. established, further tests shall be made daily with a
xiii. Silt, clay, and dust content. portable electrical conductivity probe calibrated against
xiv. Results of reactive silica tests. the satisfactory supply. If the conductivity exceeds that of
xv. Organic impurities (fine aggregate only). the satisfactory supply, then further chemical tests shall be
5 Testing: performed.
i. When a source of supply for each aggregate type 5.1.2.7 Admixtures
has been established, samples of materials
delivered to the Site shall be taken for testing in 1 Admixtures containing chlorides shall not be used.
accordance with BS 812 as follows: 2 No admixture shall be used in the concrete without
- Tests for clay, silt and dust, and sieve the Engineer's written approval and under no
analysis shall be carried out for every 40 circumstances shall admixtures containing chlorides or

♦ 5-5 ♦
other corrosive agents be allowed. Admixture i. Fiber: Type 1, cold-drawn wire, or Type 2, cut
compatibility with the type of cement used shall be proven. sheet.
3 The Contractor shall perform a trial batch and casting 2 Synthetic Fiber: Fibrillated or monofilament
to substantiate the manufacturer’s claims of workability, polypropylene fibers engineered and designed for use in
retardation as specified in Clause 5.1.3 Admixtures shall concrete, complying with ASTM C 1116, Type III. Project to
comply with the following standards: ASTM C494/C494 M, specify length.
BS EN 934 and BS EN 480. Also, admixture shall comply
with BS EN 12878 for pigments of cement. 5.1.3 Concrete Mixes
4 Air-Entraining Admixture: No air entraining agent
5.1.3.1 Design Mixes
shall be used.
5 Admixtures shall be incorporated into the mix design 1 Prepare design mixes for each type and strength of
strictly in accordance with the manufacturer’s written concrete determined by either laboratory trial mix or field
instructions. test data bases, according to ACI 211.1 and ACI 301.
6 High-Range Water-Reducing Admixture 5.1.3.2 Testing Agency
(Superplasticizer): ASTM C 494, Type G.
1 Use a qualified independent testing agency
i. If necessary, and only with the Engineer’s
acceptable to the Engineer for preparing and reporting
approval, a naphthalene sulphonate retarding
proposed mix designs for the laboratory trial mix basis.
superplasticizer shall be used to increase
workability of the concrete and retard the initial 2 Do not use the same testing agency for field quality
set. control.
ii. Products: Superplaticizer shall produce fluid,
5.1.3.3 Reports
easily flowing concrete with a slump value at
least 200 mm, but free from segregation, and 1 Submit written reports to the Engineer of each
having the same water/cement ratio as that of a proposed mix for each class of concrete at least 15 days
no slump concrete with admixture. The product prior to start of work. Do not begin concrete production
shall result in concrete that remains workable for until proposed mix designs have been reviewed and
a minimum of 3 hours at +20 deg.C and for a approved by the Engineer.
minimum of 1.5 hours at +40 deg. C.
iii. Obtain from the retarding superplasticizer 5.1.3.4 Concrete Classes
supplier, details of the material for review by the
Concrete class

Engineer and confirmation that it is in Minimum Cement Maximum


accordance with specified requirements. compressive content Water-
Confirmation shall be obtained that the retarding strength at 28 (kg/m3) Cementitious
superplasticizer is compatible with any pozzolan days (MPa) Minimum Materials
that is used. Cylinder / cube / Maximum Ratio

7 Water-Reducing Admixture (Plasticizer): ASTM C 494,


15 15 / 18.5 250 / 350 0.70
Type A.
25 25 / 31 300 / 400 0.52
8 Water-Reducing and Accelerating Admixture: ASTM
C 494, Type E. 30 30 / 37.5 350 / 450 0.50
9 Water-Reducing and Retarding Admixture: ASTM C 35 35 / 43.5 425 / 475 0.48
494, Type D. 40 40 / 50 425 / 500 0.45
10 Corrosion-Inhibiting Admixture: Commercially 45 45 / 56 450 / 500 0.42
formulated, mixed cathodic and anodic inhibitor based on
50 50 / 62.5 450 / 500 0.40
amines and alcohol; capable of forming a protective
barrier and absorbed on the reinforcement surface of 60 60 / 75 450 / 500 0.38
concrete for protecting steel bars and minimizing chloride Table 5.1.3.1: Concrete Classes
reactions with steel reinforcement in concrete.
5.1.3.5 Threshold Values for Supplementary
11 Glare-Reducing Agent: For landscape concrete
paving, provide material for reducing glare. Comply with Cementing Materials (SCM)
ASTM D 209.
1 Add SCM to the mix as necessary to achieve the
5.1.2.8 Fiber Reinforcement strength and durability requirements of the concrete
classes with due account of the maximum water-
1 Carbon-Steel Fiber: ASTM A 820, deformed, cementitious materials ratios specified in Table 5.1.3.1 and
minimum 60 mm long, and of diameter or effective Paragraph 5.1.3.7.
diameter indicated. 2 All the supplementary cementing materials (SCM)
have threshold values of addition below which significant

♦ 5-6 ♦
durability or strength parameters do not develop. Nominal
(Equation 2)
threshold addition values are indicated in Table 5.1.3.2 for:
i. Silica fume
5.1.3.7 Water-Cementitious Materials Ratio
ii. Ground granulated blast-furnace slag (GGBFS)
iii. Pulverized fly ash (PFA) 1 The maximum water-cementitious materials ratio
shall be the lower of the values listed in Table 5.1.3.1 for
SCM Nominal threshold value
the concrete classes and the following values for the
01 Silica fume 7% on [cement + silica fume] exposure:
02 GGBFS 50% on [cement + GGBFS] i. 0.45 for concrete required to have low water
03 PFA 25% on [cement + PFA] permeability.
ii. 0.40 for corrosion protection of steel
Table 5.1.3.2Threshold Addition Values for SCM
reinforcement in concrete exposed to chlorides
3 The actual amount will depend on the quality of the from salt, saltwater, brackish water, seawater, or
supplementary cementing material and mix design spray from these sources.
parameters. iii. 0.45 for concrete subject to moderate sulfate
exposure.
5.1.3.6 Limit Values for Supplementary Cementing iv. 0.42 for concrete subject to severe or very severe
Materials (SCM) sulfate exposure.

1 The upper limiting addition percentage values for 2 The water-cementitious materials ratio shall be
each supplementary cementing material shall be as Table continuously checked at the mixer with due allowance
5.1.3.3. made for water contained in the aggregates. Under no
circumstance shall water be added between the mixer and
Max. the place of concrete placement. The Engineer may
SMA Applicable conditions
% require that the water-cementitious materials ratio be
Silica checked during tests performed on fresh concrete samples
01 10 For all exposures taken at the time of placement as specified in Paragraph
fume
For permanent dry [RH ≤ 50%] 5.1.4.4.
02 GGBFS 55 or damp [RH ≥ 85%]
conditions 5.1.3.8 Slump Limits
For underground damp
03 PFA 30 1 The slump of concrete mixes shall be such that the
exposures [RH ≥ 85%]
concrete can be transported, placed into the forms, and
04 GGBFS 70
For concrete buried in compacted without segregation in accordance with Sub-
05 PFA 45 permanently wet conditions Section 5.3. If no superplasticizer is required, the slump at
time of placement shall be 50-75 mm as measured in
Table 5.1.3.3: Limit Addition Values for SCM accordance with ASTM C 143. The concrete shall be
RH is the relative humidity. sufficiently workable to enable placement in its position
with minimum difficulty.
2 When mixtures of supplementary cementing
materials are designed into the same mix, calculations 5.1.3.9 Total Salt Content
based on proportionate replacement based on the limiting
values shown in Table 5.1.3.3 shall be derived by the use 1 Chlorides: The total chloride content (sum of both
of Equations 1 and 2. acid soluble and water soluble chlorides) of the concrete
from all sources, expressed as chloride ion, shall not
The following equations shall be used for calculating the
exceed the following percentages by weight of dry cement,
limiting partial proportions of each mineral additive in the
inclusive of pozzolan, when tested in accordance with BS
mix design:
1881:
Where
i. Unreinforced concrete 0.60%
x is the % of Silica fume incorporated ii. Concrete made with sulfate resisting
y is the % of GGBFS incorporated and cement 0.15%
z is the % of PFA incorporated iii. Concrete containing embedded metal (reinforced
concrete) made with ordinary Portland
For normal concrete (Table 5.1.3.3: conditions 01, 02 and
cement 0.30%
03)
iv. Prestressed concrete 0.06%
v. Heat cured concrete containing embedded metal
(Equation 1) (reinforced concrete) 0.10%
2 Sulfates: The total sulfate content of the concrete
For wet or dry situations (Table 5.1.3.3: conditions 01, 04 from all sources, expressed as SO3, when tested in
and 05) accordance with BS 1881, shall not exceed the lesser of 0.4

♦ 5-7 ♦
percent by weight of aggregates or 3 percent by weight of Laboratory test data for revised mix design and strength
dry cement, inclusive of pozzolan. results shall be submitted to and approved by the
Engineer before using in the work.
5.1.3.10 Initial Setting Time
5.1.3.14 Absorption Test
1 The initial setting time shall be not less than 90
minutes after the production concrete is discharged into 1 Hardened concrete from the trial mixes for structural
the form. With a maximum time between mixing and grades shall be tested for absorption to establish the
placing concrete of 90 minutes, the total time between concrete’s ability to resist the ingress of aggressive salts.
mixing and initial set shall be a minimum of 2 hours. No absorption tests shall be required for blinding, plain
Maximum setting time shall be 6 hours. concrete or cyclopean concrete. Absorption tests shall be
2 When trial mixes are made to determine the in accordance with modified BS 1881: Part 122 as follows:
workability of the concrete, the initial setting time of the i. After trial mixes have been accepted, three 150
cement paste shall be determined using the method mm cylinders shall be cast from each grade of
defined in ASTM C 191 at the maximum allowable concrete and immersed in water at 20 deg. C for
temperature and with same proportions of pozzolan and 7 days.
retarding superplasticizer as specified in this Specification. ii. At the end of the curing period, 75 mm diameter
core specimens shall be cut along the
5.1.3.11 Test Mixes – Structural Grade Concrete longitudinal axis of each cylinder to a depth of
1 When the proposed workability, proportions of 75 mm.
aggregates and superplasticizer, and strength for each iii. The specimens shall be dried in an oven at 105
grade of concrete have been established, test concrete deg. C for 72 hours.
shall be produced for approval by the Engineer. The iv. The specimens shall be cooled in a dry airtight
following shall be performed for each grade of concrete: vessel for 24 hours, weighed, and then
immediately immersed in a tank containing
i. Six separate test mixes shall be made and cured
water at 20 deg. C with the longitudinal axis of
in accordance with ASTM C 192 and tested in
the cores horizontal, and with 25 mm depth of
accordance with ASTM C 39.
water over the specimens.
ii. The 36 cylinders for each grade of concrete shall
v. The specimens shall be immersed for 24 hours,
be tested for compressive strength at 28 days
then removed, shaken, surface dried, and
and the mean strength and standard deviation
reweighed. The water absorption shall be
established for each grade. The test mixes shall
calculated as the increase in mass resulting from
be accepted provided that:
immersion, expressed as a percentage of the dry
- The mix proportions and workability are mass.
in accordance with this Specification. vi. If the cores lengths differ from 75 mm, a
- The standard deviation for each grade is correction factor (graph given in BS 1881) shall
3.5 MPa or less. be applied.
- The mean strength for structural concrete vii. The mean of the corrected absorption figure for
exceeds the specified design strength by each concrete grade shall be calculated and the
6 MPa. absorption of the concrete mixes shall be
acceptable if the mean absorption is less than 2
5.1.3.12 Test Mixes – Blinding and Plain Concrete percent at 30 minutes. The mean absorption
figure and the lowest absorption figure shall be
1 Concrete for blinding, plain concrete or cyclopean
recorded for each grade and used for
concrete shall be a designed mix with design strength of
comparison purposes with absorption tests
15 MPa. The trial mix proportions shall be at the
carried out on cores cut from in-situ concrete, as
discretion of the Contractor. Once they have been chosen,
scheduled in Paragraph 5.1.4.6.
three separate test mixes shall be made with those
proportions and three test cylinders shall be made from 5.1.3.15 Permeability Tests
each mix for testing at 28 days. The trial mix proportions
and water/cement ratio shall be approved if the average 1 Depth of penetration tests shall be carried out to
strength of the nine cylinders is not less than 14 MPa. establish the water permeability of concrete on prototype
samples of different components of the structure before
2 No production test shall be made for this grade of
the mix design or manufacturing method are approved.
concrete but the Engineer will monitor the mix
The prototype samples shall be short sections of not less
proportions and water/cement ratio.
than 1.0m x 1.0m x full thickness. The samples shall be
5.1.3.13 Adjustments to Concrete Mixes fully reinforced and cast in similar environment as the
actual structure. The tests shall be carried out in
1 Mix design adjustments may be required by the accordance with DIN 1048 at age 28 days and the
Engineer when characteristics of materials, job conditions, maximum value of penetration shall not exceed the
weather, test results, or other circumstances warrant. following limits:

♦ 5-8 ♦
In-situ construction: Less than 25 mm. 5.1.4 Construction Requirements
Precast units: Less than 20 mm.
5.1.4.1 Concrete Mixing
2 Chloride permeability of the concrete shall be
determined using cores taken from the prototype samples, 1 Concrete production shall be in accordance with ACI
in accordance with AASHTO T277 ‘Rapid Determination of 304. A checklist for concrete production shall be produced,
the Chloride Permeability of Concrete’. The following such as that used by the NRMCA or approved equal.
limits shall not be exceeded: 2 Batching of materials shall be by weight. All
In-situ construction: 1500 coulombs. weighing equipment shall be calibrated and
documentation shall be provided to establish that the
Precast units: 1000 coulombs.
accuracy is continuously maintained in accordance with
3 The concrete will be deemed to comply with the the requirements of ACI 304. Batching scale accuracy
permeability requirements of this specification if all test shall be in accordance with the Concrete Plant Standards
results comply with the limits indicated in Points 1 and 2. of the Concrete Plant Manufacturers Bureau, or approved
4 If any of the DIN 1048 and the rapid chloride equal.
permeability test results of unprotected surfaces of a 3 Furnish equipment and establish accurate
sample fail to meet the above requirements, then all the procedures for determining the quantities of free moisture
concrete work represented by such sample shall be in the aggregates. Moisture determinations shall be made
deemed not to comply with the permeability requirements. daily and whenever there is an apparent change in the
5 If, in the opinion of the Engineer, the concrete that moisture content. The moisture content shall be recorded
has failed to meet the permeability requirements of this and shall be taken into account in adjusting the weight of
Specification is likely to cause durability problems, three aggregate and the quantity of water incorporated in the
cores shall be cut from the area represented by failed mix.
samples for additional DIN 1048 and rapid chloride
permeability testing. The location of the cores shall be 5.1.4.2 Job-Site Mixing
decided by the Engineer. 1 All concrete mixed on Site shall be in a batch mixer
of approved size and design complying with ACI 304 and
5.1.3.16 Synthetic Fiber
producing a uniform distribution of the materials
1 Uniformly disperse in concrete mix at manufacturer's throughout the mixed concrete in accordance with ASTM
recommended rate, but not less than 0.60 kg/cu. m. C 94 uniformity test. The contents of the drum shall be
completely discharged before re-charging. After all the
5.1.3.17 Admixtures materials are in the mixer, mixing shall continue until the
1 Use admixtures according to the manufacturer's whole of the materials are uniformly distributed and the
written instructions and in the proportions recommended. mass is of uniform color and consistency. In the case of
concrete that contains silica fume with a density between
2 Use water-reducing admixture or high-range water-
400-650 kg/cu.m, the mixing time shall be 50 percent
reducing admixture (superplasticizer) in concrete, as
greater than the requirement for concrete without silica
required, for placement and workability.
fume.
3 Use water-reducing and retarding admixture when
2 Whenever mixing is to be suspended for half an hour
required by high temperatures, low humidity, or other
or longer, the drum of the mixer shall be thoroughly
adverse placement conditions.
washed out with clean water. Provide a competent
4 Use water-reducing admixture in pumped concrete, operator who shall be in continuous control of the mixer.
concrete required to be watertight, and concrete with a No re-tempering of concrete, which has partially hardened,
water-cementitious materials ratio below 0.50. by the addition of cement, aggregate, or water shall be
5 Use corrosion-inhibiting admixture in concrete mixes allowed.
where indicated. 3 Provide batch ticket for each batch discharged and
6 All admixtures shall be used as required and used in the work, indicating Project identification name
approved by the Engineer for placement and workability and number, date, mix type, mix time, quantity, and
of concrete, and shall be used in accordance with the amount of water introduced as well as the load printout,
manufacturer’s instructions. The equipment used for delivery printout, temperature readout and measured
dispensing and the method of incorporating the admixture slump.
into the concrete shall be subject to approval. The
5.1.4.3 Ready-Mixed Concrete
dispensing unit shall be translucent so that the operator
can see the discharge of the admixture. 1 Ready-mixed concrete shall comply with the
requirements of ASTM C 94 or BS EN 206 and as follows:
i. Concrete shall be centrally mixed off site and
transported in an agitator truck. Truck mixing
shall not be permitted.

♦ 5-9 ♦
ii. The plant and trucks shall be certified as meeting i. Sampling, curing and testing shall be performed
the requirements of the NRMCA Check List, or using the relevant procedures in ASTM C 31,
approved equal. ASTM C 39, and ASTM C 172 or BS EN 12350.
iii. Details and information regarding the supplier - Samples for production concrete cylinders
proposed by the contractor shall be submitted to (or cubes if approved by the Engineer) shall
the Engineer for approval. be taken at the point of placement at the
iv. The approved supplier of ready mixed concrete average rate of one per 100 cu. m of concrete
shall not subsequently be changed without placed or one for each major placement, with
further approval of the Engineer. a minimum of one sample taken every day
2 When air temperature is between 30 deg. C and 32 that the mix is used. A sample shall consist
deg. C, delivery time from the time that water is added to of eight 150 mm cylinders molded and stored
the mix until it is placed in its final position in the form for laboratory-cured test specimens except
shall not exceed 90 minutes. When air temperature is when field-cured test specimens are required.
above 32 deg. C, delivery time shall not exceed 45 minutes. Three cylinders are for testing at 7 days after
Further time extension may be given if approved by the casting, three for testing at 28 days after
Engineer. casting, and two reserved for later testing if
3 Before discharging concrete at the point of delivery, required.
provide the Engineer with a delivery ticket for each batch - If frequency of testing provides fewer than 5
of concrete containing the following information as a strength tests for a given class of concrete,
minimum: conduct testing from at least 5 randomly
i. Name or number of off-site concrete depot. selected batches or from each batch if fewer
ii. Serial number for ticket. than 5 are used.
iii. Date. - When total quantity of a given class of
iv. Time of dispatch. concrete is less than 100 cu. m, the Engineer
v. Truck number. may waive strength testing if adequate
vi. Name of supplier. evidence of satisfactory strength is provided
vii. Grade or mix description of concrete. but not less than one sample per day.
viii. Type of cementitious materials. - When strength of field-cured cylinders is less
ix. Cementitious materials content and constitution. than 85 percent of companion laboratory-
x. Water/cementitious materials ratio. cured cylinders, re-evaluate current on-site
xi. Nominal maximum size of aggregate. operations and provide corrective procedures
xii. Source of aggregate, maximum size, weight of for protecting and curing the in-place
fine and coarse aggregate. concrete.
xiii. Type or name of admixture, if included.
ii. Records shall be kept of the mix details and
xiv. Percentage variation between design and actual
position in the works of all batches of concrete
values for all ingredients.
and of all samples taken for cylinders and other
xv. Quantity of concrete in cubic meters.
specimens and of their test results. A copy shall
xvi. Certifying that chlorides and sulfate contents are
be supplied to the Engineer within 24 hours after
within specified limits and stating their values.
recording/testing. Records shall contain, but not
5.1.4.4 Quality Control and Testing – General be limited to, the following information:
- Date, time, location, and volume of pour.
1 Testing Laboratory:
- Ambient temperature and humidity.
i. Employ an independent testing agency to
perform tests and to submit test reports. - Concrete temperature (at time of placement).
ii. Be responsible for taking, identifying and - Cementitious materials content and
delivering to the test laboratory all test samples constitution.
called for in this Specification. The testing - Types of manufacturers of cementitious
laboratory shall be responsible for the testing. materials.
Collect all test results and deliver them to the
- Concrete type and class.
Engineer in the format and detail as specified.
- Aggregate type and source.
2 Testing Laboratory Qualifications: The testing
laboratory shall be approved by the Engineer and shall - Admixture details.
have a Quality System in accordance with ANSI Q9001. - Water/cementitious materials ratio.
- Identification of test cylinder.
5.1.4.5 Quality Control – Testing on Fresh Concrete
- Name of concrete testing service.
1 Compressive Strength Test for Structural Concrete:
- Date and time of sampling.
- Method of compaction.

♦ 5-10 ♦
- Date of testing and results of test. 4 Cementitious Materials Content and Water/
- Age of sample in days, weight in grams, Cementitious Materials Ratio: Samples of freshly mixed
density in kg/cu. m. concrete shall be chosen by the Engineer at least once per
month from each structural grade and determination
- Crushing load in Newtons and crushing
made of cement content and water/cement ratio in
strength in MPa.
accordance with BS 1881. If the cement content is less
- Signatures of person preparing cylinder and than 90 percent of the requirement in Paragraph 5.1.3.4 or
of person crushing cylinder. the water/cement ratio is greater than 110 percent of the
- Results of testing. requirement in Paragraphs 5.1.3.4 and 5.1.3.7 the
iii. For the 28 day tests, the concrete will be deemed Contractor and the Engineer shall investigate to establish
to comply with the specified design strength if the cause and the Engineer may reject the cast concrete
the average strength determined from all sets of for the pour from which the samples were taken. The
3 consecutive tests is at least equal to the Engineer may request an analysis of fresh concrete from
specified design strength and no individual any pour. No analysis of freshly mixed concrete is
strength test falls below the specified design required for blinding or plain concrete.
strength by more than 3.5 MPa. Any concrete 5 Salt Content: The total concentration of sulfates and
not complying with the specified design strength chlorides in fresh concrete shall be measured at least once
shall be at risk for removal and replacement at a week for all structural grades of concrete. Tests shall be
the Contractor’s expense. in accordance with BS 1881. Concentrations of each ion
iv. The 28-day cylinder crushing results shall be shall not exceed the limits specified in Paragraph 5.1.3.9. If
grouped consecutively in groups of 40 and each these limits are exceeded, the concrete pour from which
group shall have a standard deviation less than the samples were taken shall be rejected and further tests
3.5 MPa. If the standard deviation is greater than performed on the cast concrete in accordance with
or equal to 3.5 MPa, then concrete production paragraph 5.1.4.6 to determine the total extent of the
shall be investigated by the Engineer and further problem.
tests on trial mixes may be required. 6 Slump: Slump tests shall be performed in accordance
v. Tests shall be carried out at 7 days to establish a with ASTM C 143. A minimum of one test shall be done at
relationship between the 7 day and 28 day the point of discharge for each day's pour for each type of
strengths. This relationship shall be used to concrete. Additional tests shall be performed when
interpret future test results in order to predict the concrete consistency appears to have changed.
corresponding 28 day strength. The Engineer
shall be advised without delay if any 7 day test 5.1.4.6 Quality Control – Testing on Hardened
result indicates that the corresponding 28 day Concrete
strength is likely to fail to meet the specified
strength so that any necessary action can be 1 General: The Engineer may instruct samples to be
taken to minimize the effect of such possible taken and tests carried out on any hardened structural
failure. grade concrete as specified below if he suspects that the
concrete does not meet the specified requirements. If the
2 Compressive Strength Test for Blinding or Plain
tests confirm that the concrete does not meet the
Concrete: No production tests on blinding or plain
requirements of this Specification, then the Engineer may
concrete are required. The Engineer may require
require the concrete to be removed at the Contractor’s
compressive strength tests if it is believed that the
expense. If the tests confirm that the concrete meets the
characteristic strength is below 15 MPa. Characteristic
requirements of this Specification, then the cost of taking
strength is defined as the minimum value of cube strength
the samples shall not be at the Contractor’s expense.
achieved by 95 percent of all possible test results. If the
tests confirm that the characteristic strength is less than 15 2 Compressive Strength Tests: The Engineer may
MPa, then the Engineer will require revisions to the mix instruct cores to be drilled from a particular pour. 100 mm
design to ensure that the concrete meets the specified diameter cores shall be drilled as requested, in accordance
requirements. with ASTM C 42, and sent for crushing. If the cores from
that pour have an average compressive strength less than
3 Measurement of Concrete Temperature: Temperature
85 percent of the characteristic strength or if any
measurements shall be in accordance with ASTM C 1064.
individual core has a compressive strength less than 75
Concrete temperature shall be measured 50 mm below
percent of the characteristic strength, it shall be evidence
the surface prior to and at the point of placement and
that the concrete from which it was taken is not in
recorded on the pour card for each pour. One reading
accordance with the specified requirements.
shall be taken each hour when air temperature is 4 deg.C
and below and when air temperature is 27 deg.C and 3 Concrete Cover: The Engineer may check the
above, and one reading for each set of compressive- concrete cover over the reinforcement with a cover meter.
strength specimens. Concreting shall stop if the Any indication that the cover is generally less than the
temperature of the concrete does not meet the requirements specified in Paragraph 5.2.3.4 shall be
requirements of Paragraph 5.3.3.10 checked by limited surface concrete removal. If it is

♦ 5-11 ♦
confirmed that the actual cover is generally less than 5 Concrete of the same class requiring the same
specified, then the concrete shall be removed at the falsework but with a different class of surface finish are
Contractor’s expense. In the case of localized lack of cover each measured separately.
and where appearance is not important, a repair shall be 6 Voids, openings or gaps 0.05 cubic meters or more
effected by removal of the inadequate cover and cutting shall be deducted from the volume of concrete in which
back of concrete for 50 mm behind the reinforcement. they occur.
Resurfacing of the concrete with the specified cover shall
7 All service ducts, irrespective of diameter, shall be
be carried out as a repair by a specialist subcontractor.
measured and deducted from the volume of concrete in
4 Absorption: A sample of three 75 mm diameter cores, which they are located.
75 mm long, shall be taken from hardened concrete if
directed by the Engineer and tested in accordance with 5.1.5.2 Items Not Measured
Paragraph 5.1.3.14. Should the absorption of any core
1 Volume of reinforcing bars is not deducted from the
exceed by more than 1 percent the highest approved test
measured volume of concrete.
result, the concrete from which it was cut shall be
removed. No absorption test shall be required for 2 Volume of prestressing ducts, anchors, cones,
blinding or plain concrete. couplers and grouting tubes is not deducted from the
measured volume of concrete.
5 Salt Content: Engineer may request samples to be
taken from two 20 mm diameter drillings into the concrete 3 Volume of embedded metals, bolts, nuts, anchorages,
surface, spaced 75 mm apart. Each drilling shall proceed hooks etc. is not deducted from the measured volume of
in 25 mm increments for a total depth of 100 mm and the concrete.
dust from the 4 samples in each hole shall be sent for 4 Holes introduced, with the consent of the Engineer,
sulfate and chloride content analysis in accordance with by the Contractor for the convenience of transportation,
BS 1881. Should the tests show that the limits specified in erection or construction shall not be deducted from the
Paragraph 5.1.3.9 are exceeded, the concrete shall be measured volume of concrete irrespective of the size of
removed. the holes and whether or not the holes are made good.
6 Nondestructive Testing: Impact hammer, sonoscope, 5 Additional concrete placed, with the consent of the
or other nondestructive device may be used but shall not Engineer, by the Contractor solely for the purpose of
be used as the sole basis for acceptance or rejection of facilitating his work shall not be measured for payment.
cast concrete.
7 Additional Tests: The testing agency shall make 5.1.6 Basis of Payment
additional tests of in-place concrete, as directed by the
1 The amount of completed and accepted work,
Engineer, when test results indicate that specified concrete
measured as provided above, will be paid for at the unit
strengths or other characteristics have not been attained
rate for the types and classes of concrete in the Bill of
in the structure. Testing agency may conduct tests to
Quantities, which rate shall be full compensation for:
determine adequacy of concrete by cored cylinders
complying with ASTM C 42, or by other methods as - Cement and other cementitious materials,
directed. aggregates, water and admixtures including
their testing, storage, handling and
transportation.
5.1.5 Method of Measurement
- Washing of aggregates, if required.
5.1.5.1 Measured Items
- Ice, if required, added in the mix water.
1 Concrete is measured by the cubic meter for each - Plant, machinery and equipment required for
type and class, based on dimensions shown on the the production of concrete.
Drawings or as otherwise directed by the Engineer. - Design of mixes, taking samples and testing.
2 Concrete works shall include mass, reinforced and - Transportation and delivery of concrete to work
prestressed concrete of both in-situ and precast areas.
construction of a general nature, but shall not include
- Placing, compacting, vibrating and finishing of
specific components of highway structures, such as
concrete.
concrete pavement, concrete piles, concrete parapets and
safety barriers, precast concrete curbs and tiles etc., which - All formwork irrespective of the material used
are separately prescribed for measurement and payment and the quality of surface finish specified.
in other Sections. - All falsework supporting and stabilizing
3 Different classes of concrete are measured separately. formwork.
4 Concrete formed by different types of form and/or - Curing of concrete.
falsework are each measured separately. - Tooling, if required, to achieve the specified
surface finish.

♦ 5-12 ♦
- Corrective measures and the means of carrying 3 British Standards (BS):
them out required in the event of the concrete BS 4449 Specification for Carbon Steel Bars for
being not in accordance with the Drawings the Reinforcement of Concrete
and/or specification.
BS 4483 Steel Fabric for the Reinforcement of
- Handling, transportation and erection of Concrete
precast concrete members.
4 Concrete Reinforcing Steel Institute (CRSI):
- Grout and/or epoxy used in precast
CRSI Manual of Standard Practice
construction including material and equipment
for temporary prestress, if required. 5.2.1.2 Submittals
- Material, plant and equipment associated with
1 Steel Reinforcement Shop Drawings: Details of
particular methods of construction.
fabrication, bending, and placement, prepared according
- Joint fillers, joint sealants, weep holes, water to ACI 315, ‘Details and Detailing of Concrete
stops, dowel bars and other accessories as Reinforcement.’ Include material, grade, bar schedules,
shown on the Drawings including material, stirrup spacing, bent bar diagrams, arrangement, and
plant handling, transportation testing, storage, supports of concrete reinforcement. Include special
workmanship and associated ancillaries. reinforcement required for openings through concrete
- Protective coating. structures.
- All labor, materials and equipment. 2 Welding Certificates: Copies of certificates for
welding procedures and personnel.
5.1.7 Items in the Bill of Quantities 3 Material Certificates: Signed by manufacturers and
i Concrete (class) in (type of structure), Contractor certifying that the following items comply with
specified requirements:
(location) and (finish) cu.m.
i. Steel reinforcement and reinforcement
accessories: a copy of the manufacturer’s test
5.2 Reinforcing Steel certificate for ultimate strength, elongation and
cold bending, together with the chemical
5.2.1 Description analysis of the steel shall be submitted to the
Engineer for each consignment of reinforcing
5.2.1.1 References
steel delivered to the Site.
1 American Concrete Institute (ACI):
5.2.1.3 Quality Assurance
ACI 315 Standard Practice for Detailing
Reinforced Concrete Structures 1 Welding: Comply with AWS D1.4, ‘Structural Welding
ACI 318 Building Code Requirements for Code--Reinforcing Steel’ for procedures and qualification
Reinforced Concrete of personnel for welding operations.

2 American Society for Testing and Materials (ASTM): 5.2.1.4 Delivery, Storage and Handling
ASTM A 82 Standard Specification for Steel Wire
1 Deliver, store, and handle steel reinforcement to
Reinforcement, Plain, for Concrete
prevent bending and damage. Avoid damaging coatings
Reinforcement
on steel reinforcement.
ASTM A 185 Standard Specification for Steel Welded
Wire Fabric, Plain, for Concrete 5.2.2 Materials
Reinforcement
ASTM A 496 Standard Specification for Steel Wire, 5.2.2.1 Steel Reinforcement
Deformed, for Concrete Reinforcement 1 Reinforcing Bars: ASTM A 615M, Grade 60 (420 MPa)
ASTM A 497 Standard Specification for Steel Welded specified yield strength, or BS 4449 grade 460 Type 2
Wire Reinforcement, Deformed, for deformed, uncoated. One test per 5000 m length
Concrete Reinforcement delivered to site.
ASTM A 615M Standard Specification for Deformed 2 Higher strength reinforcement bars may be used
and Plain Billet- Steel Bars for Concrete subject to approval of the Engineer.
Reinforcement 3 Low-Alloy-Steel Reinforcing Bars: ASTM A 706M,
ASTM A 706M Standard Specification for Low-Alloy deformed.
Steel Deformed and Plain Bars 4 Plain-Steel Wire: ASTM A 82, as drawn.
ASTM A 780 Practice for Repair of Damaged and 5 Plain-Steel Wire: ASTM A 82, galvanized.
Uncoated Areas of Hot-Dip Galvanized
6 Deformed-Steel Wire: ASTM A 496 and Steel welded
Coatings.
wire reinforcement to ASTM A 497.

♦ 5-13 ♦
7 Welded Wire Fabric: ASTM A 185, welded steel wire 5.2.2.3 Fabricating Reinforcement
fabric.
1 Fabricate steel reinforcement according to CRSI's
8 All reinforcement shall be new material on delivery
‘Manual of Standard Practice’.
to the Site and at time of installation, material shall be free
from loose rust and loose mill scale, deleterious amounts
of salts and coatings that reduce or destroy bond. Tight
5.2.3 Construction Requirements
rust and mill scale or surface irregularities are acceptable 5.2.3.1 General
if the weight and dimensions, including height of
deformations and tensile properties, of a test specimen 1 Accurately position, support, and secure
that has been wire-brushed by hand, are not less than reinforcement against displacement. Locate and support
those required by the applicable standards. reinforcement with bar supports to maintain minimum
concrete cover. Do not tack weld crossing reinforcing bars.
9 Galvanized steel shall not be used
2 Shop- or field-weld reinforcement according to AWS
10 Reinforcement shall be accurately bent, cut or
D1.4, where indicated.
formed to the dimensions and configuration shown on
Drawings and within the tolerances specified in ACI 315. 3 Set wire ties with ends directed into concrete, not
Reinforcement shall be bent cold using approved bending toward exposed concrete surfaces.
equipment in accordance with ACI 318. Bars may be 4 Install welded wire fabric in longest practicable
preheated only if prior approval is given by the Engineer. lengths on bar supports spaced to minimize sagging. Lap
Reinforcement shall not be rebent or straightened without edges and ends of adjoining sheets at least one mesh
prior approval. spacing. Offset laps of adjoining sheet widths to prevent
i. Reinforcement having a reduced section, kinks, continuous laps in either direction. Lace overlaps with
visible transverse cracks at bends, or otherwise wire
damaged in any way shall not be used. 5 Avoid cutting or puncturing vapor retarder/barrier
ii. Reinforcement shall not be welded unless and waterproofing membranes during reinforcement
specifically shown on Drawings or permitted as placement and concreting operations. Repair damages
an exception and then only after approval of the before placing concrete.
welding method appropriate to the grade of steel
and the type of welding rod to be used. 5.2.3.2 Shipping, Storage and Cleaning

5.2.2.2 Reinforcement Accessories 1 Reinforcement shall be handled and shipped in a


manner to avoid bending or other damage to the bars.
1 Provide and fix bar supports: bolsters, chairs, spacers, Bars shall be bundled, separated in sizes and clearly
and other devices for spacing, supporting, and fastening marked by diameter size preferably for one placement, in
reinforcing bars and welded wire fabric in place. Provide accordance with the placement schedule and as follows:
bar supports according to CRSI's ‘Manual of Standard i. Bars for separate structures shall not be bundled
Practice’ from steel wire, plastic, or precast concrete or together. Bars for small structures may be
fiber-reinforced concrete of greater compressive strength bundled together but each bar or group of bars
than concrete, and as follows: that have the same piece mark shall be tagged
i. For concrete surfaces exposed to view where and coded.
legs of wire bar supports contact forms, use ii. Metal tags or approved equal shall be provided
CRSI Class 1 plastic-protected or CRSI Class 2 and labeled with legible markings.
stainless-steel bar supports. iii. All bundles shall be tagged at each end. Tags
ii. Other reinforcement supports shall consist of shall show piece marks corresponding to the
concrete spacer blocks made of the same mark numbers on the placement drawings and
materials, to the same specified requirements on the bar list.
and with the same inherent properties as the iv. Bars shall be bundled in the largest size practical
parent material with the exception that the for handling and shipping.
maximum aggregate size shall be appropriate for 2 Reinforcement shall be stored 1m above ground on
the thickness of cover to the reinforcement. platforms, skids or other approved supports and suitably
2 Joint Dowel Bars: Plain-steel bars, ASTM A 615M, spaced. Contact with the soil shall be avoided. Proper
Grade 60 (420 MPa). Cut bars true to length with ends drainage and protection from the elements shall be
square and free of burrs. provided to minimize corrosion.
3 Mechanical splices (couplers) of deformed high yield 3 Clean reinforcement of loose rust and mill scale,
steel bars are to consist of two seamless steel sleeves and earth, ice, and other materials that reduce or destroy bond
interconnecting high tensile steel stud with plastic with concrete.
protection caps for threaded section of sleeve and shall
be tested to exceed 135% of the specified yield strength of
grade 60 bar (or higher if higher strength bars are used).

♦ 5-14 ♦
5.2.3.3 Placing 5.2.4 Method of Measurement
1 Comply with CRSI's ‘Manual of Standard Practice’ for 1 Bar and mesh reinforcement is measured by the
placing reinforcement. theoretical quantity in metric tonnes complete in place as
shown on the Drawings or placed as ordered by the
2 Accurately position, support, and secure
Engineer. No allowance is made for clips, wire or other
reinforcement against displacement. Locate and support
fastening devices, reinforcement chairs to separate slab
reinforcement on concrete blocks of a size to give the
steel or similar reinforcement or to retain wall steel or
correct cover to the reinforcement
similar. The rates in the Bill of Quantities shall be deemed
3 Where cathodic protection is utilized, reinforcement to cover for the above.
shall be isolated from the electrical grounding system.
2 Measurement of splices or laps in reinforcement
4 Chairs made of reinforcement shall be used to not shown on the Drawings will not be made.
support the top mats of slab reinforcement and shall be so
3 Calculated weights for high tensile and mild steel
dimensioned as to be stable during concreting operations.
reinforced bars shall be based upon the following Table:
The chairs shall themselves be supported on concrete
blocks as specified in Clause 5.2.2.2.
5 Place reinforcement to maintain minimum coverage

Diameter

Diameter

Diameter
Weight

Weight

Weight
as indicated for concrete protection. Arrange, space, and

Kg/m

kg/m

kg/m
mm

mm

mm
securely tie bars and bar supports to hold reinforcement in
position during concrete placement operations. Ties at
intersections shall be made with 1.5 mm diameter
annealed wire with wire ends directed into concrete, not 5 0.154 18 2.000 34 7.130
toward exposed concrete surfaces. 6 0.222 20 2.470 36 7.990
6 All lap splices shall be in accordance with ACI 318 7 0.302 22 2.980 38 8.900
class B tension lap splice unless otherwise shown on
8 0.395 24 3.550 40 9.870
Drawings. All reinforcement bars shall be cut bent and
fixed in accordance with ACI 318 unless otherwise shown 10 0.617 26 4.170 45 12.500
on Drawings. 12 0.888 28 4.830 50 15.400
7 Welded wire fabric shall be lapped 1.5 mesh 14 1.210 30 5.550
(opening size) plus the extension on the wires unless 16 1.580 32 6.310
otherwise shown on Drawings. Table 5.2.4.1 Reinforcing Bars Weights

5.2.3.4 Concrete Cover 4 No separate measurement is made for bars of


different diameters. The unit rates in the Bill of Quantities
1 Concrete cover to reinforcement shall be as indicated
shall be deemed to cover for all diameters.
on Drawings but shall not be less than the following:
5 Fabric mesh reinforcement is measured separately
i. Concrete exposed to salt water and
by weight based on the theoretical quantity of metric
splash zone 100 mm
tonnes complete in place as shown on the Drawings or
ii. Concrete of all substructure elements cast
placed as ordered by the Engineer. No separate
against earth 100 mm
measurement is made for different mesh sizes or different
iii. Concrete of all substructure elements exposed to
wire diameters. For standard fabric, the weight will be
weather 75 mm
based on the mass in kg/sq.m. listed in Table A.1 of BS
iv. Apron slabs 60 mm
4483.
v. Superstructure cast-in-situ concrete exposed to
weather 60 mm 6 The quantity of steel reinforcing bars and fabric mesh
vi. Interior faces of superstructure cast-in-place reinforcement shall be calculated to the nearest three
concrete except slabs 40 mm decimal places.
vii. Cast-in-situ slabs 30 mm
viii. Precast superstructure elements, exposed 5.2.5 Basis of Payment
surfaces 40 mm
1 The amount of completed and accepted material,
ix. Precast superstructure elements, interior
measured as provided above, will be paid for at the unit
faces 30 mm
rate for reinforcing steel (bar and mesh), in the Bill of
x. Precast parapets, concrete barriers, curbs,
Quantities, which rate shall be full compensation for
etc. 30 mm
supplying, fabricating, transporting, delivering, erecting
2 Cover to reinforcement shall be checked before any and fixing, materials, labor, equipment, tools and other
concrete is cast. The bending of reinforcement at a cold items necessary for the proper completion of the work as
joint is not permitted. Concrete cover shall be checked specified in Sub-Section 5.2.
with a cover meter as soon as formwork is removed.

♦ 5-15 ♦
5.2.6 Items in the Bill of Quantities ASTM C 171 Standard Specification for Sheet
Materials for Curing Concrete (AASHTO
i Mild steel bar reinforcement of any
M 171)
diameter t.
ASTM C 219 Standard Terminology Relating to
ii High tensile steel bar reinforcement
Hydraulic Cement
of any diameter t.
ASTM C 309 Standard Specification for Liquid
iii Fabric wire mesh reinforcement of
Membrane-Forming Compounds for
any size t.
Curing Concrete (AASHTO M 148)
ASTM C 881 Standard Specification for Epoxy-Resin-
5.3 Reinforced Concrete Structures Base Bonding Systems for Concrete
ASTM C 920 Standard Specification for Elastomeric
5.3.1 Description
Joint Sealants
5.3.1.1 Definitions ASTM C 1315 Specification for Liquid Membrane –
Forming compounds having Special
1 Forms and Formwork: Temporary works used to give
Properties for Curing and Sealing
the required shape and support to poured concrete,
Concrete
constructed mainly of sheet material, such as wood,
plywood, metal sheet or plastic sheet, in direct contact ASTM C 1059 Specification for Latex Agents for
with the concrete, and joists or stringers to support the Bonding Fresh To Hardened Concrete
sheeting. For bridges it is recommended to use only metal ASTM D 448 Classification for Sizes of Aggregates
sheets. for Road and Bridge Construction
2 Falsework: Temporary structure used to support a ASTM D 1751 Standard Specification for Preformed
permanent concrete structure while it is not self- Expansion Joint Filler for Concrete
supporting. Paving and Structural Construction
3 Scaffold: Temporary structure to provide access, to (AASHTO M213)
work under construction. ASTM D 1752 Specification for Preformed sponge
4 Tower: Composite structure to provide access to high Rubber and Cork Expansion Joint Fillers
work under construction and to carry vertical loading. for Concrete Paving and Structural
Construction (AASHTO M153).
5 Camber: Upward curvature of the formwork,
designed to compensate for subsequent deflection under ASTM D 994 Specification for Preformed Expansion
load. Joint Filler for Concrete (AASHTO M33).
ASTM D 4397 Specification for Polyethylene Sheeting
5.3.1.2 References
for Construction, Industrial, and
1 American Association of State Highway and Agricultural Applications
Transportation Officials (AASHTO): ASTM E 154 Test Methods for Water Vapor
AASHTO M182 Standard Specification for Burlap Cloth Retarders used in Contact with Earth
Made from Jute or Kenaf under Concrete Slabs, on Walls or as
Ground Cover.
2 American Concrete Institute (ACI):
ASTM E 1745 Specification for Plastic Water Vapor
ACI 117 Specifications for Standard Tolerances
Retarders used in Contact with Soil or
for Concrete Construction and Materials
Granular Fill under Concrete Slabs.
ACI 304 Guide for Measuring, Mixing,
4 Corps of Engineers (CE):
Transporting, and Placing Concrete
CE CRD-C300 Curing Compound
ACI 305 Hot Weather Concreting
CE CRD-C513 Rubber Waterstops
ACI 309 Guide for Consolidation of Concrete
CE CRD-C572 PVC Waterstops
ACI 347 Formwork for Concrete
ACI 504R Guide to Joint Sealants for Concrete 5.3.1.3 Submittals
Structures
1 Formwork Shop Drawings: Prepare shop drawings
3 American Society for Testing and Materials (ASTM): for formwork indicating fabrication and erection of forms
ASTM C 33 Specification for Concrete Aggregates for specified finish concrete surface. Show form
ASTM C 109/C109M Test Method for Compressive construction including jointing, especial form joints or
Strength of Hydraulic Cement Mortars reveals, location and pattern of form tie placement.
(Using 2-in. or 50 mm Cube Specimens i. Design of formwork includes design of
ASTM C 150 Standard Specification for Portland falsework, scaffold and towers as defined in
Cement Paragraph 5.3.1.1.

♦ 5-16 ♦
ii. Prepare formwork drawings by or under the i. Without prejudice to the Engineer’s rights to
supervision of a qualified professional engineer inspect, approve or reject or suspend any work,
detailing fabrication, assembly, and support of the CQCE shall be authorized to:
formwork. - Postpone concreting operations until
iii. Design and engineering of formwork for outstanding requirements are corrected.
structural stability and efficiency are the
- Reject materials or workmanship that do
Contractor's responsibility.
not conform to this Specification.
iv. Indicate proposed schedule and sequence of
stripping formwork, removing supports and re- - Prevent the use of equipment that could
shoring. cause improper construction relative to
v. If the Contractor intends to use readymade this Specification.
proprietary formwork and falsework, he shall - Stop any work that is not being done in
submit all relevant data, including independent accordance with specified requirements.
test certificates, to enable the Engineer to - Report within 24 hours and provide
determine if the proposals are acceptable. records to and as required by the
Engineer’s review of formwork design is limited Engineer upon discovery of non-
to architectural aspects only and shall not be compliance.
construed as approval of structural or other
3 Implement a Quality Assurance System as specified
matters, all of which are the Contractor’s sole
in Paragraph 5.1.1.4.
responsibility
4 Mockups: Before casting concrete that is exposed to
2 Material Certificates: Signed by manufacturers and
view in the completed structure, cast a mockup for each
Contractor certifying that each of the following items
exposed element to demonstrate typical joints, surface
complies with specified requirements:
finish, texture, color, tolerances, quality of materials and
i. Waterstops. standard of workmanship in the completed work. Where
ii. Curing materials. specified or directed by the Engineer, the mock up shall be
iii. Bonding agents. a trial construction representative of the actual structure
iv. Adhesives. (pier, cross-head, part of deck) in dimensions and all
v. Vapor retarders. details including reinforcement, using the Contractor’s
vi. Epoxy joint filler. proposed construction technique, concrete mix, formwork,
vii. Joint-filler strips. cutting and placing of reinforcement, etc.
viii. Repair materials.
i. Build mockups in the location and of the size
3 Samples: Samples of materials as requested by the indicated or, if not indicated, as directed by the
Engineer, with names, sources, and descriptions, Engineer.
including, but not limited to, the following: ii. Notify the Engineer seven days in advance of
i. Color finishes. dates and times when mockups will be
ii. Reglets. constructed.
iii. Waterstops, reinjectable hosing, water swelling iii. In the presence of the Engineer, damage parts of
gaskets. exposed surfaces as selected by the Engineer,
iv. Vapor retarder/barrier. and demonstrate materials and techniques
v. Form liners. proposed for repairs to match adjacent
vi. Joint fillers. undamaged surfaces.
vii. Sealants. iv. Obtain the Engineer's approval of mockups
before starting cast-in-place concrete elements
5.3.1.4 Quality Assurance exposed to view.
1 Codes and Standards: Comply with the latest edition v. If the Engineer determines that any mockup does
of not meet requirements, demolish and remove
from the site and cast another until the mockup
i. AASHTO LRFD Bridge Construction
is approved.
Specifications.
vi. Maintain mockups during construction in an
ii. ACI Manual of Concrete Practice Parts 1, 2, 3, 4 &
undisturbed condition as a standard for judging
5.
the completed work.
iii. CRSI "Manual of Standard Practice” except
vii. Demolish and remove mockups when directed.
where more stringent requirements are shown
or specified.
5.3.2 Materials
2 Concrete Quality Control Engineer: Appoint a full-
time Concrete Quality Control Engineer (CQCE) as 5.3.2.1 Form Materials
specified in Paragraph 5.1.1.4
1 Forms for Exposed Finish Concrete: Plywood, metal,
metal-framed plywood faced, or other acceptable panel-

♦ 5-17 ♦
type materials to provide continuous, straight, smooth, 5.3.2.2 Waterstops
exposed surfaces. Furnish in largest practicable sizes to
minimize number of joints and to conform to joint system 1 Waterstops: Provide flat, dumbbell-type waterstops
shown on Drawings. at construction joints and other joints in accordance with
AASHTO LRFD Bridge Construction Specifications Article
i. Use overlaid plywood complying with U.S.
8.9.2.6 or as specified herein. Waterstops shall be sized to
Product Standard PS-1 "A-C or B-B High Density
suit joints and shall be of the profiles shown on the
Overlaid Concrete Form," Class I.
Drawings or as directed or appropriate for the particular
ii. Use plywood complying with U.S. Product
application. Fittings for angles junctions etc shall be
Standard PS-1 ‘B-B (Concrete Form) Plywood,’
factory formed.
Class I, Exterior Grade or better, mill-oiled and
edge-sealed, with each piece bearing legible i. Flexible Rubber Waterstops: CE CRD-C 513, for
inspection trademark. embedding in concrete to prevent passage of
fluids through joints.
2 Forms for Unexposed Finish Concrete: Plywood,
ii. Flexible PVC Waterstops: CE CRD-C 572, for
lumber, metal, or another acceptable material. Provide
embedding in concrete to prevent passage of
lumber dressed on at least two edges and one side for
fluids through joints.
tight fit.
2 Self-Expanding Strip Waterstops: Proprietory
3 Forms for Textured Finish Concrete: Units of face
rectangular or trapezoidal strip, sodium bentonite or other
design, size, arrangement, and configuration to match the
hydrophylic material for adhesive bonding to concrete.
Engineer's control sample. Provide solid backing and
form supports to ensure stability of textured form liners. 3 Re-injectable Hosing: Proprietary re-injectable hosing
complying with the following requirements:
4 Forms for Cylindrical Columns and Supports: Metal,
glass-fiber-reinforced plastic, or paper or fiber tubes that - The hose shall consist of a hollow PVC core
will produce smooth surfaces without joint indications. with lateral openings covered by neoprene
Provide units with sufficient wall thickness to resist wet valves. The hose shall be laid and injected by
concrete loads without deformation. an approved applicator. in 10 to 12 m lengths
with entry port and vent ends terminating in
5 Pan-Type Forms: Glass-fiber-reinforced plastic or
junction boxes.
formed steel, stiffened to support weight of placed
concrete without deformation. - Joints shall be hydraulically tested to a
pressure at least 2.0 bar higher than the
6 Carton Forms: Biodegradable paper surface, treated
expected local conditions. If the hose fails to
for moisture-resistance, structurally sufficient to support
hold the pressure for 10 minutes, it shall be
weight of plastic concrete and other superimposed loads.
injected with a vinyl ester based flexible resin
7 Form Release Agent: Proprietary form release agent as required to seal the joint and then retested.
with a maximum of 350 g/L volatile organic compounds
(VOCs) that will not bond with, stain, or adversely affect 5.3.2.3 Concrete Curing Cover Sheets
concrete surfaces and will not impair subsequent
1 Vapor retarding sheet materials shall be one of the
treatments of concrete surfaces.
types specified in paragraphs 2 to 5 below or as directed
i. Release agent for steel faced formwork shall by the Engineer.
incorporate rust inhibitor.
2 ASTM E 1745, Class C, of one of the following
8 Form Ties: Factory-fabricated, adjustable-length, materials; or polyethylene sheet 0.25mm thick
removable or snap-off metal form ties designed to prevent
i. Nonwoven, polyester-reinforced, polyethylene
form deflection and to prevent spalling of concrete upon
coated sheet; 0.25 mm thick.
removal. Provide units that leave no embedded metal
ii. Three-ply, nylon- or polyester-cord-reinforced,
closer than 38 mm to the surface of the exposed concrete.
laminated, high-density polyethylene sheet; 0.18
No permanent metallic part shall have less concrete cover
mm thick.
than the reinforcement. Provide ties that, when removed,
will not leave holes larger than 25 mm in diameter in the 3 Vapor retarder: ASTM E 1745, Class B, five-ply,
concrete surface. Provide ties with integral water-barrier nylon- or polyester-cord-reinforced, high-density
plates for walls indicated to receive damp-proofing or polyethylene sheet; 0.25 mm thick.
waterproofing. 4 Vapor retarder: ASTM E 1745, Class A, three-ply,
9 Void Forms: Biodegradable paper surface, treated for nylon- or polyester-cord-reinforced, high-density
moisture resistance structural sufficient to support weight polyethylene sheet; laminated to a nonwoven geotextile
of plastic concrete and other superimposed loads. fabric, 0.76 mm thick.

10 Chamfer Strips: Wood, metal, PVC, or rubber strips of 5 Vapor retarder: 2.8 mm thick, semi-flexible, seven-ply
the size indicated on the Drawings. sheet membrane consisting of reinforced core and carrier
sheet with fortified asphalt layers, protective
weathercoating, and removable plastic release liner.

♦ 5-18 ♦
Furnish manufacturer's accessories including bonding 7 Reglets: Fabricated from not less than 0.55 mm thick
asphalt, pointing mastics, and self-adhering joint tape. galvanized steel sheet. Temporarily fill or cover face
i. Water-Vapor Permeance: ASTM E 154. opening of reglet to prevent intrusion of concrete or debris.

ii. Tensile Strength: 24.5 kN/m; ASTM E 154. 8 Dovetail Anchor Slots: Hot-dip galvanized steel sheet,
not less than 0.85 mm thick, with bent tab anchors.
iii. Puncture Resistance: 400 N; ASTM E 154.
Temporarily fill or cover face opening of slots to prevent
6 Absorptive Cover: Burlap cloth made from jute or intrusion of concrete or debris.
kenaf weighing approximately 0.29 kg/sq.m and
complying with AASHTO M182, Class 2. 5.3.2.6 Repair Materials
7 Moisture Retaining Cover: ASTM C 171. polyethylene 1 Repair Underlayment: Cement-based, polymer-
sheet, polyethylene coated burlap or Kraft paper. modified, self-leveling product that can be applied in
thicknesses from 3 mm and that can be feathered at edges
5.3.2.4 Curing Compounds
to match adjacent floor elevations.
1 Curing compounds shall be one of the types i. Cement Binder: ASTM C 150, Portland cement
specified in paragraphs 2 to 6 below, or as directed by the or hydraulic or blended hydraulic cement as
Engineer defined in ASTM C 219.
2 Evaporation Retarder: Waterborne, monomolecular ii. Primer: Product of underlayment manufacturer
film forming, manufactured for application to fresh recommended for substrate, conditions, and
concrete application.
3 Clear, solvent-borne, membrane-forming curing iii. Aggregate: Well-graded, washed gravel, 3 to 6
compound: ASTM C 309, Type 1, Class B. mm or coarse sand as recommended by
4 Clear, waterborne, membrane-forming curing underlayment manufacturer.
compound: ASTM C 309, Type 1, Class B. iv. Compressive Strength: Not less than 30 MPa at
5 Clear, solvent-borne, membrane-forming curing and 28 days when tested according to ASTM C
sealing compound: ASTM C 1315, Type 1, Class A. 109M.
6 Clear, waterborne, membrane-forming curing and 2 Repair Topping: Traffic-bearing, cement-based,
sealing compound: ASTM C 1315, Type 1, Class A. polymer-modified, self-leveling product that can be
applied in thicknesses from 6 mm.
5.3.2.5 Concrete Accessories
i. Cement Binder: ASTM C 150, Portland cement
1 Joint-Filler Strips: ASTM D 1751, asphalt-saturated or hydraulic or blended hydraulic cement as
cellulosic fiber. defined in ASTM C 219.
2 Joint-Filler Strips: ASTM D 1752, cork or self- ii. Primer: Product of topping manufacturer
expanding cork. recommended for substrate, conditions, and
3 Joint-Filler Strips: ASTM D 1751, asphalt-saturated application.
cellulosic fiber, or ASTM D 1752, cork or self-expanding iii. Aggregate: Well-graded, washed gravel, 3 to 6
cork. mm or coarse sand as recommended by
4 Epoxy Joint Filler: Two-component, semi-rigid, 100 topping manufacturer.
percent solids, epoxy resin with a Shore A hardness of 80 iv. Compressive Strength: Not less than 40 MPa at
per ASTM D 2240. 28 days when tested according to ASTM C
5 Bonding Agent: ASTM C 1059, Type II, non- 109M.
redispersible, acrylic emulsion or styrene butadiene.
5.3.3 Construction Requirements
6 Epoxy-Bonding Adhesive: ASTM C 881, two-
component epoxy resin, capable of humid curing and 5.3.3.1 Formwork
bonding to damp surfaces, of class and grade to suit
requirements, and as follows: 1 Design, erect, shore, brace, and maintain formwork,
according to ACI 301, to support vertical, lateral, static,
i. Type II, non-load bearing, for bonding freshly
and dynamic loads, and construction loads that might be
mixed concrete to hardened concrete.
applied, until concrete structure can support such loads.
ii. Types I and II, non-load bearing, for bonding Design of formwork shall be the sole responsibility of the
hardened or freshly mixed concrete to Contractor.
hardened concrete.
2 Construct formwork so that concrete members and
iii. Types IV and V, load bearing, for bonding structures are of size, shape, alignment, elevation, and
hardened or freshly mixed concrete to position indicated, within tolerance limits of ACI 117.
hardened concrete.
3 Limit concrete surface irregularities, designated by
ACI 347R as abrupt or gradual, as follows:
i. Class A, 4 mm.

♦ 5-19 ♦
ii. Class B, 6 mm. load. Falsework shall not be supported on any part of the
iii. Class C, 10 mm. structure, except the footings, without the written
permission of the Engineer. The number and spacing of
iv. Class D, 25 mm.
falsework columns, the adequacy of sills, caps and
4 Construct forms rigid and tight enough to prevent stringers and the amount of bracing in the falsework
loss of concrete mortar. framing shall be subject to approval of the Engineer.
5 Fabricate forms for easy removal without hammering 2 Timber for falsework shall be sound, in good
or prising against concrete surfaces. Provide crush or condition and free from defects that might impair its
wrecking plates where stripping may damage cast strength. If the vertical members are of insufficient length
concrete surfaces. Provide top forms for inclined surfaces to cap at the desired elevation for the horizontal members,
steeper than 1.5 horizontal to 1 vertical. Kerf wood inserts they shall preferably be capped and frames constructed to
for forming keyways, reglets, recesses, and the like, for the proper elevation. Ends of the vertical members shall
easy removal. be cut square for full bearing to preclude the use of
i. Do not use rust-stained steel form-facing wedges. If vertical splices are necessary, the abutting
material. members shall be of the same approximate size, the ends
6 Set edge forms, bulkheads, and intermediate screed shall be cut square for full bearing, and the splices shall be
strips for slabs to achieve required elevations and slopes scabbed in a manner approved by the Engineer.
in finished concrete surfaces. Provide and secure units to 3 The Contractor shall compute falsework settlement
support screed strips; use strike-off templates or and deflection for bridges so that when the final
compacting-type screeds. settlement is complete, the structure will conform to the
7 Provide temporary openings for cleanouts and required camber, section and grade as shown on the
inspection ports where interior area of formwork is Drawings.
inaccessible. Close openings with panels tightly fitted to 4 The Contractor shall provide means for accurately
forms and securely braced to prevent loss of concrete measuring settlement in falsework during placement of
mortar. Locate temporary openings in forms at concrete, and shall provide a competent observer to
inconspicuous locations. observe and correct the settlement.
8 Chamfer exterior corners and edges of concrete 5 Screw jacks, if used, shall be designed for use with a
receiving applied waterproofing membranes. slenderness ratio not exceeding 60. The slenderness ratio
9 Unless otherwise indicated, provide 20x20 mm shall be taken as the ratio of the clear distance between
chamfer on all exposed corners and edges of concrete. effective bracing in both horizontal directions to the
diameter of the screw jack measured at the root of the
10 Form openings, chases, offsets, recesses, keyways,
thread. The manufacturers' certificate showing the
grooves, blocking, screeds, and bulkheads required in the
ultimate load capacity of the screw jack shall be submitted
work.
with the design calculations for the falsework. If directed
11 Clean forms and adjacent surfaces to receive by the Engineer, the Contractor shall furnish a test
concrete. Remove chips, wood, sawdust, dirt, and other certificate carried out at an approved independent
debris just before placing concrete. laboratory.
12 Retighten forms and bracing before placing concrete, 6 Props and towers supporting forms or partially
to prevent mortar leaks and maintain proper alignment. completed structures shall be interconnected in plan
13 Coat contact surfaces of forms with specified form orthogonally at levels to be determined in the design.
release agent approved by the Engineer, according to the They shall also be interconnected by diagonal bracings in
manufacturer's written instructions, before placing orthogonal vertical planes.
reinforcement Petrol oil may be used. 7 If the concrete is required to be post-tensioned in the
14 Where it is required to use internal ties and spacers, field, the falsework shall be designed to support any
their type, spacing and use shall be to the approval of the increased or readjusted loads caused by the prestressing
Engineer. In no circumstances shall these ties protrude out forces.
of the finished concrete, all ties must be cut back into the
5.3.3.3 Embedded Items
structural concrete and the surface made good to satisfy
the requirements of the minimum spacing and cover. 1 Place and secure anchorage devices and other
embedded items required for adjoining work that is
5.3.3.2 Falsework
attached to or supported by cast-in-place concrete. Follow
1 Falsework and centering shall be designed to provide templates, diagrams, instructions, and directions
the necessary rigidity to support all vertical and horizontal furnished with items to be embedded.
loads placed upon it without settlement or deformation in
5.3.3.4 Removing and Reusing Forms
excess of the permissible tolerance for the structure given
in the Specifications. Falsework columns shall be 1 General: Formwork, for sides of beams, walls,
supported on hardwood, concrete pads or metal bases if columns, and similar parts of the work, that does not
the underlying ground is liable to sink under the column

♦ 5-20 ♦
support weight of concrete may be removed after 5.3.3.6 Construction Joints
cumulatively curing at not less than 10 deg.C for 24 hours
after placing concrete provided concrete is hard enough to 1 Follow the requirements of AASHTO LRFD Bridge
not be damaged by form-removal operations and Construction Specifications Sub-Section 8.8 as
provided curing and protection operations are maintained. complemented herein.

2 The Engineer shall be notified when the Contractor 2 Construct joints true to line with faces perpendicular
intends to remove any formwork at least 6 hours in to surface plane of concrete.
advance 3 Construction joints shall be made only where
i. Leave formwork, for beam soffits, joists, slabs, specified in the contract documents, or shown in the
and other structural elements that supports pouring schedule, unless otherwise approved by the
weight of concrete in place until concrete has Engineer.
achieved: At least 70 percent of 28-day design 4 Unless otherwise specified in the contract documents,
compressive strength but not less than 7 days horizontal joints may be made without keys, and vertical
after casting. joints shall be constructed with shear keys in accordance
ii. Determine compressive strength of in-place with AASHTO LRFD Bridge Construction Specifications
concrete by testing representative field- or Article 8.8.2.
laboratory-cured test specimens according to 5 All construction joints shall be cleaned of surface
ACI 301. laitance, curing compound, and other foreign materials
iii. Remove forms only if shores have been before fresh concrete is placed against the surface of the
arranged to permit removal of forms without joint. Abrasive blast or other approved methods shall be
loosening or disturbing shores. used to clean horizontal construction joints to the extent
that clean aggregate is exposed. All construction joints
3 Clean and repair surfaces of forms to be reused in
shall be flushed with water and allowed to dry to a surface
the work. Split, frayed, delaminated, or otherwise
dry condition immediately prior to placing concrete.
damaged form-facing material will not be acceptable for
exposed surfaces. Apply new form release agent. 6 Bonding and doweling to existing structures shall be
as specified in AASHTO LRFD Bridge Construction
When forms are reused, clean surfaces, remove fins and
Specifications Article 8.8.3.
laitance, and tighten to close joints. Align and secure
joints to avoid offsets. Do not use patched forms for 7 The use of expanded metal or other perforated
exposed concrete surfaces unless approved by the material is prohibited in construction joints.
Engineer. 8 Place construction joints perpendicular to main
reinforcement. Continue reinforcement across
5.3.3.5 Vapor Retarders construction joints except as indicated otherwise. Do not
1 Vapor Retarder: Place, protect, and repair vapor continue reinforcement through sides of strip placements.
retarder sheets according to ASTM E 1643 and 9 Where needed, unscheduled, construction joints shall
manufacturer's written instructions. Cover with fine be placed as directed by the Engineer and, if directed,
graded granular material or fill as specified in paragraphs additional reinforcement steel dowels shall be placed
2 or 3 below. across the joint. Such additional steel shall be furnished
2 Fine-Graded Granular Material: Cover vapor retarder and placed at the Contractor’s expense.
with fine-graded granular material, moisten, and compact 10 Space vertical joints in walls as indicated, or as
with mechanical equipment to elevation tolerances of plus required by the Engineer.
0 mm or minus 20 mm. 11 Use a bonding agent at locations where fresh
3 Granular Fill: Cover vapor retarder with granular fill, concrete is placed against hardened or partially hardened
moisten, and compact with mechanical equipment to concrete surfaces.
elevation tolerances of plus 0 mm or minus 20 mm. 12 Use epoxy-bonding adhesive at locations where
i. Place and compact a 15 mm thick layer of fine- fresh concrete is placed against hardened or partially
graded granular material over granular fill. hardened concrete surfaces.
4 Place vapor retarder/barrier sheeting in position with 13 Waterstops/Re-injectable Hoses: Provide waterstops
longest dimension parallel with direction of pour. or re-injectable hoses in construction joints as indicated.
Lap joints 150 mm and seal with manufacturer's Install waterstops to form a continuous diaphragm in each
recommended mastic or pressure-sensitive tape. Cover joint. Support and protect exposed waterstops during
vapor retarder/barrier with sand cushion and compact to progress of work. .
depth indicated.
5.3.3.7 Contraction and Expansion Joints

1 Follow the requirements of AASHTO LRFD Bridge


Construction Specifications Sub-section 8.9 as
complemented herein.

♦ 5-21 ♦
2 Expansion and contraction joints shall be constructed iii. Polyethylene foam strip, for use when shown
at the locations and in accordance with the details in the contract documents, shall be of
specified in the contract documents. Such joints include commercial quality with a continuous,
open joints, filled joints, joints sealed with sealants or impervious, glazed top surface, suitable for
waterstops, and joints with combinations of these features. retaining the liquid sealant at the proper
3 Contraction Joints in Slabs-on-Grade: Form elevation in the joint while hardening.
weakened-plane contraction joints, sectioning concrete
5.3.3.8 Waterstops
into areas as indicated. Construct contraction joints for a
depth equal to at least one-fourth of concrete thickness, as 1 Install waterstops in accordance with AASHTO LRFD
follows: Bridge Construction Specifications Sub-section 8.9.3.4.
i. Grooved Joints: Form contraction joints after 2 Flexible Waterstops: Install in construction joints as
initial floating by grooving and finishing each indicated to form a continuous diaphragm. Install in
edge of joint to a radius of 3 mm. Repeat longest lengths practicable. Support and protect exposed
grooving of contraction joints after applying waterstops during progress of work.
surface finishes. Eliminate groover tool marks 3 Self-Expanding Strip Waterstops: Install in
on concrete surfaces. construction joints and at other locations indicated,
ii Sawed Joints: Form contraction joints with according to manufacturer's written instructions, bonding
power saws equipped with shatterproof or mechanically fastening and firmly pressing into place.
abrasive or diamond-rimmed blades. Cut 3 Install in longest lengths practicable.
mm wide joints into concrete when cutting
action will not tear, abrade, or otherwise 5.3.3.9 Concrete Placement
damage surface and before concrete develops
1 General: Comply with AASHTO LRFD Bridge
random contraction cracks.
Construction Specifications Sub-sections 8.6 and 8.7 as
4 Isolation Joints in slabs-on-grade: After removing complemented herein for protection from environmental
formwork, install joint-filler strips at slab junctions with conditions during placing and curing and for handling and
vertical surfaces, such as column pedestals, foundation placement of concrete.
walls, grade beams, and other locations, as indicated.
2 Concrete shall be handled, placed, and consolidated
i. Extend joint-filler strips full width and depth of by methods that will not cause segregation of the mix and
joint, terminating flush with finished concrete will result in a dense homogeneous concrete that is free of
surface, unless otherwise indicated. voids and rock pockets. The methods used shall not cause
ii. Terminate full-width joint-filler strips not less displacement of reinforcing steel or other materials to be
than 12 mm or more than 25 mm below embedded in the concrete. Concrete shall be placed and
finished concrete surface where joint sealants, consolidated prior to initial set and in no case more than
are indicated. 1.5 hours after the water was added to the mix. Concrete
iii. Install joint-filler strips in lengths as long as shall not be re-tempered.
practicable. Where more than one length is 3 Inspection: Before placing concrete, inspect and
required, lace or clip sections together. complete formwork installation, reinforcing steel, and
5 Dowel Joints: Install dowel sleeves and dowels or items to be embedded or cast in. Notify other trades to
dowel bar and support assemblies at joints where permit installation of their work. Concrete shall not be
indicated. placed until the condition of the reinforcement, other
embedded items, and the formwork has been inspected
i. Use dowel sleeves or lubricate or asphalt-coat
and approved by the Engineer. All mortar from previous
one-half of dowel length to prevent concrete
placements, debris, and foreign material shall be removed
bonding to one side of joint.
from the forms and steel prior to commencing placement.
6 Pourable sealants for placement along top edges of The forms and subgrade shall be thoroughly moistened
contraction or filled expansion joints shall be one of the with water immediately before concrete is placed against
following: them. Temporary form spreader devices may be left in
i. Hot-poured sealants shall conform to ASTM D place until concrete placement precludes their need, after
3406 (AASHTO M 282), except when the which they shall be removed.
sealant will be in contact with asphaltic 4 Transportation: Concrete, after being discharged
material, it shall conform to AASHTO M 301. from the mixer, shall be transported as rapidly as possible
ii. Cold-poured sealant shall be silicone type, as to its final position in the Work by agitator trucks, which
specified in AASHTO LRFD Bridge Construction shall prevent adulteration, segregation, loss of workability
Specifications Article 8.9.2.4. The sealant shall or contamination of the ingredients. The containers that
be a one-part, low-modulus silicone rubber convey the concrete shall be kept clean and free from
type with an ultimate elongation of 1200 hardened or partially hardened concrete.
percent.

♦ 5-22 ♦
i. The addition of water at the point of discharge i. Concrete for T-beam or deck girder spans
is prohibited and trucks shall have the water whose depth is less than 1200 mm may be
tank completely disconnected from the drum. placed in one continuous operation or may be
ii. The use of chutes, spouts, skips and pumps placed in two separate operations; first, to the
shall be permitted if approval is obtained. top of the girder stems, and second, to
Under no circumstances shall any aluminum completion. For T-beam or deck girder spans
pipe or other conveying equipment containing whose depth is 1200 mm or more, and unless
aluminum be allowed to contact fresh concrete the falsework is non-yielding, such concrete
when it is conveyed to its point of placement. shall be placed in two operations, and at least
five days shall elapse after placement of stems
iii. Method of pouring and pouring sequence shall
before the top deck slab is placed.
be submitted by the Contractor to the
Engineer’s approval. ii. Concrete for box girders may be placed in two
or three separate operations consisting of
5 Concrete exposed to salt or brackish water shall
bottom slab, girder stems, and top slab. In
follow the requirements of AASHTO LRFD Bridge
either case, the bottom slab shall be placed
Construction Specifications Sub-section 8.6.6.
first and, unless otherwise permitted by the
6 Do not add water to concrete during delivery, at Engineer, the top slab shall not be placed until
Project site, or during placement, unless approved by the the girder stems have been in place for at least
Engineer. five days.
7 Placement of concrete for each section of the 12 Placement of Box Culverts: In general, the base slab
structure shall be done continuously without interruption or footings of box culverts shall be placed and allowed to
between planned construction or expansion joints. The set before the remainder of the culvert is constructed. For
delivery rate, placing sequence, and methods shall be culverts whose wall height is 1500 mm or less, the
such that fresh concrete is always placed and consolidated sidewalls and top slab may be placed in one continuous
against previously placed concrete before initial set has operation. For higher culvert walls, the requirements for
occurred in the previously placed concrete. vertical members shall apply.
8 During and after placement of concrete, care shall be 13 Placement of Precast Elements: The sequence of
taken not to damage the concrete or break the bond with placement for concrete in precast elements shall be such
reinforcing steel. Workers shall not walk in fresh concrete. that sound, well-consolidated concrete that is free of
Platforms for workers and equipment shall not be settlement or shrinkage cracks is produced throughout the
supported directly on any reinforcing steel. Once the member.
concrete is set, forces shall not be applied to the forms or
14 Placing Methods: Concrete shall be placed as nearly
to reinforcing bars which project from the concrete until
as possible in its final position, and the use of vibrators for
the concrete is of sufficient strength to resist damage.
extensive shifting of the weight (mass) of fresh concrete
9 Sequence of Placement: Whenever a concrete will not be permitted.
placement plan or schedule is specified or approved, the
i. Concrete shall be placed in horizontal layers of
sequence of placement shall conform to the plan.
a thickness not exceeding the capacity of the
10 Placement of Vertical Members: Concrete for vibrator to consolidate the concrete and merge
columns, substructure and culvert walls, and other similar it with the previous lift. In no case shall the
vertical members shall be placed and allowed to set and depth of a lift exceed 600 mm. The rate of
settle for a period of time before concrete for integral concrete placement shall not exceed that
horizontal members, such as caps, slabs, or footings, is assumed for the design of the forms as
placed. Such period shall be adequate to allow completion corrected for the actual temperature of the
of settlement due to loss of bleed water and shall be not concrete being placed.
less than 12 h for vertical members over 4500 mm in
ii. When placing operations would involve
height and not less than 30 min for members over 1500
dropping the concrete more than 1500 mm, the
mm but not over 4500 mm in height. When friction collars
concrete shall be dropped through a tube fitted
or falsework brackets are mounted on such vertical
with a hopper head or through other approved
members and unless otherwise approved, the vertical
devices, as necessary to prevent segregation of
member shall have been in place at least seven days and
the mix and spattering of mortar on steel and
shall have attained its specified strength before loads from
forms above the elevation of the lift being
horizontal members are applied
placed.
11 Placement of Superstructure: Unless otherwise
15 Equipment:
permitted, no concrete shall be placed in the
superstructure until substructure forms have been i. All equipment used to place concrete shall be
stripped sufficiently to determine the character of the of adequate capacity and designed and
supporting substructure concrete. operated so as to prevent segregation of the
mix or loss of mortar. Such equipment shall

♦ 5-23 ♦
not cause vibrations that might damage the degree that the concrete ceases to be plastic
freshly placed concrete. No equipment shall under vibration. Vibrators shall not be used to
have aluminum parts which come in contact transport concrete in the forms.
with the concrete. Between uses, the mortar vii. Vibration shall be supplemented by such
coating inside of placing equipment which sets spading as is necessary to ensure smooth
or dries out shall be cleaned from the surfaces and dense concrete along form
equipment before use is resumed. surfaces and in corners and locations
ii. Chutes shall be lined with smooth watertight impossible to reach with the vibrators.
material and, when steep slopes are involved, viii. When approved by the Engineer, concrete for
shall be equipped with baffles or reverses. small noncritical elements may be consolidated
iii. Concrete pumps shall be operated such that a by the use of suitable rods and spades.
continuous stream of concrete without air 17 Underwater Concreting:
pockets is produced. When pumping is
i. Only concrete used in cofferdams to seal out
completed, the concrete remaining in the
water may be placed under water, unless
pipeline, if it is to be used, shall be ejected in
otherwise specified in the contract documents
such a manner that there will be no
or specifically approved by the Engineer.
contamination of the concrete or separation of
the ingredients. ii. If other than concrete class 50 or 60 is to be
placed under water, the minimum cement
16 Consolidation:
content of the mix shall be increased by ten
i. All concrete, except concrete placed under percent to compensate for loss due to wash.
water and concrete otherwise exempt, shall be
iii. A tremie shall consist of a watertight tube
consolidated by mechanical vibration
having a diameter of not less than 250 mm and
immediately after placement.
fitted with a hopper at the top. The tremies
ii. Except as noted herein, vibration shall be shall be supported so as to permit free
internal. External form vibrators may be used movement of the discharge end over the entire
for thin sections when the forms have been top surface of the work and so as to permit
designed for external vibration. rapid lowering when necessary to retard or
iii. Vibrators shall be of approved type and design stop the flow of concrete. The discharge end
and of a size appropriate for the work. They shall be sealed closed at the start of work so as
shall be capable of transmitting vibration to the to prevent water from entering the tube before
concrete at frequencies of not less than 75 Hz. the tube is filled with concrete.
iv. The Contractor shall provide a sufficient iv. After placement has started, the tremie shall be
number of vibrators to properly compact each kept full of concrete to the bottom of the
batch of concrete immediately after it is placed hopper. If water enters the tube after
in the forms. The Contractor shall also have at placement is started, the tremie shall be
least one spare vibrator immediately available withdrawn, the discharge end resealed, and the
in case of breakdown. placement restarted.
v. Vibrators shall be manipulated so as to v. When a batch is dumped into the hopper, the
thoroughly work the concrete around the flow of concrete shall be induced by slightly
reinforcement and embedded fixtures and into raising the discharge end, always keeping it in
the corners and angles of the forms. Vibration the deposited concrete. The flow shall be
shall be applied at the point of deposit and in continuous until the work is completed. When
the area of freshly deposited concrete. The cofferdam struts prevent lateral movement of
vibrators shall be inserted and withdrawn out tremies, one tremie shall be used in each bay.
of the concrete slowly. The vibration shall be of vi. Concrete pumps used to place concrete under
sufficient duration and intensity to thoroughly water shall include a device at the end of the
consolidate the concrete but shall not be discharge tube to seal out water while the tube
continued so as to cause segregation. Vibration is first being filled with concrete. Once the flow
shall not be continued at any one point to the of concrete is started, the end of the discharge
extent that localized areas of grout are formed. tube shall be kept full of concrete and below
Application of vibrators shall be at points the surface of the deposited concrete until
uniformly spaced and not farther apart than 1.5 placement is completed.
times the radius over which the vibration is
visibly effective. 5.3.3.10 Hot-Weather Concreting
vi. Vibration shall not be applied either directly to, 1 When hot weather conditions exist that would impair
or through the reinforcement, or to sections or quality and strength of concrete, place concrete complying
layers of concrete which have hardened to the with ACI 305 and as specified.

♦ 5-24 ♦
2 Cool ingredients before mixing to maintain concrete Hand-finishing methods may be used if
temperature at time of placement to below 25 deg.C. approved by the Engineer for short bridges 15
Mixing water may be chilled or chopped ice may be used m or less in length or for irregular areas where
to control temperature, provided water equivalent of ice is the use of a machine would be impractical.
calculated to total amount of mixing water. ii. Straightedging, Sub-section 8.10.2.2.
3 Concrete temperature shall not exceed 32 degree C iii. Texturing, Sub-section 8.10.2.3
and the temperature differential shall not exceed 25
iv. Surface testing and correction, Sub-section
degree C.
8.10.2.4.
4 No concreting operation shall be carried out at
3 Pedestrian Walkway Surface Finish: comply with
ambient temperature of 40 deg. C or more.
AASHTO LRFD Bridge Construction Specifications Sub-
5 For bridge decks that are located over or adjacent to section 8.10.3.
salt water the maximum temperature of the concrete at
4 Troweled and Brushed Finish: comply with AASHTO
time of placement shall be 27 deg. C.
LRFD Bridge Construction Specifications Sub-section
6 Cover reinforcing steel with water-soaked burlap if it 8.10.4.
becomes too hot, so that steel temperature will not exceed
5 Surface under Bearings: comply with AASHTO LRFD
the ambient air temperature immediately before
Bridge Construction Specifications Sub-section 8.10.5.
embedding in concrete.
7 Fog spray forms, reinforcing steel, and subgrade just 5.3.3.12 Curing Concrete
before placing concrete. Keep subgrade moisture uniform
1 All newly placed concrete shall be cured so as to
without puddles or dry areas.
prevent loss of water by use of one or more of the
8 Use water-reducing retarding admixture when
methods specified in AASHTO LRFD Bridge Construction
required by high temperatures, low humidity, or other
Specifications Sub-section 8.11. Unless otherwise
adverse placing conditions, as acceptable to the Engineer.
specified in the contract documents, curing shall
9 Shade mixing plant and trucks, aggregates, water commence immediately after the free water has left the
tank, and cement silo. surface and finishing operations are completed. If the
10 Paint the mixing plant, trucks, water tank, and surface of the concrete begins to dry before the selected
cement silo with white or reflective paint curing method can be applied, the surface of the concrete
11 Insulate the water tank and supply piping. shall be kept moist by a fog spray applied so as not to
damage the surface.
12 Protect concrete during pouring, and formwork, from
direct sunlight by use of shades and keep shades in 2 Curing shall continue uninterrupted for seven days
position for 7 days from time of pouring, . except for when pozzolans in excess of ten percent, by
weight (mass), of the Portland cement are used in the mix.
13 Concrete placing shall be completed as quickly as
When such pozzolans are used, the curing period shall be
possible to reduce transit time.
ten days.
14 Curing of exposed concrete shall be immediately
3 For other than top slabs of structures serving as
carried out.
finished pavements, the above curing periods may be
5.3.3.11 Finishing Plastic Concrete reduced and curing terminated when test cylinders cured
under the same conditions as the structure indicate that
1 General: Unless otherwise specified in the contract concrete strengths of at least 70 percent of that specified
documents, after concrete has been consolidated and have been reached but not in any case less than 3 days.
prior to the application of cure, all surfaces of concrete
4 When directed by the Engineer during periods of hot
that are not placed against forms shall be struck-off to the
weather, water shall be applied to concrete surfaces being
planned elevation or slope and the surface finished by
cured by the liquid membrane method or by the forms-in-
floating with a wooden float sufficiently to seal the surface.
place method, until the Engineer determines that a cooling
While the concrete is still in a workable state, all
effect is no longer required. Such application of water will
construction and expansion joints shall be carefully tooled
be paid for as extra work.
with an edger. Joint filler shall be left exposed.
5 Methods:
2 Roadway Surface Finish: All bridge decks, approach
slabs, and other concrete surfaces for use by traffic shall i. Forms-in Place Method: Formed surfaces of
be finished to a smooth skid-resistant surface in concrete may be cured by retaining the forms
accordance with AASHTO LRFD Bridge Construction in place for the required time without
Specifications Sub-section 8.10.2 for the following loosening.
sequence of operations: ii. Water Method: Concrete surface shall be kept
i. Striking-off and floating, Article 8.10.2.1. Bridge continuously wet by ponding, spraying, or
decks or top slabs of structures serving as covering with absorptive materials that are
finished pavements shall be finished using kept continuously and thoroughly wet.
approved power-driven finishing machines.

♦ 5-25 ♦
iii. Liquid Membrane Curing Compound Method: as fins and surface discoloration shall, however, be made
The liquid membrane method shall not be good as and when required by the Engineer,
used on surfaces where a rubbed finish is 4 Class F4. No special requirements. To be used in the
required or on surfaces of construction joints earth-face or below ground structures if no waterproofing
unless it is removed by sand blasting prior to membrane will be applied.
placement of concrete against the joint. Type 2,
5 Permanently exposed concrete surfaces to classes F1,
white pigmented, liquid membranes may be
F2 and F3 finish shall be protected from rust marks and
used only on the surfaces of bridge decks, on
stains of all kinds. Internal ties and embedded metal parts
surfaces that will not be exposed to view in the
will not be permitted.
completed work, or on surfaces where their
use has been approved by the Engineer. 5.3.3.14 Tolerances
Details of the application are set in AASHTO
LRFD Bridge Construction Specifications Sub- 1 In-Situ Construction
section 8.11.3.3. i. Length: The horizontal and vertical dimensions
iv. Waterproof Cover Method: This method shall of in-situ concrete members, but not cross-
consist of covering the surface with a sections, shall be within the following
waterproof sheet material so as to prevent tolerances:
moisture loss from the concrete. This method Length (mm) Tolerance (mm)
may be used only when the covering can be Up to 3000 ±3
secured adequately to prevent
3001-4500 ±6
moisture loss. Details of the application are set
in AASHTO LRFD Bridge Construction Vertical lines out of plane ± 5 + (1 for every 3000 out
Specifications Sub-section 8.11.3.4. of true line)
v. Steam or Radiant-Heat Curing Method: This ii. Cross-Section: Slab and wall thicknesses and
method may be used only for precast concrete the cross-sectional dimensions of beams,
members manufactured in established plants. columns, piers etc., shall be within the
Details of the application are set in AASHTO following tolerances:
LRFD Bridge Construction Specifications Sub- Member Dimensions (mm) Tolerance (mm)
section 8.11.3.5. Up to 500 ±6
6 Bridge Decks: The top surfaces of bridge decks shall 501-750 ± 10
be cured by a combination of the liquid membrane curing
Additional for every subsequent
compound method and the water method. The liquid
100 mm ± 1 mm
membrane shall be Type 2, white pigmented, and shall be
applied from finishing bridges progressively and 2 Precast Construction
immediately after finishing operations are complete on i. Length: The horizontal and vertical dimensions
each portion of the deck. The water cure shall be applied of members, but not cross-sections, shall be
not later than 4 h after completion of deck finishing or, for within the following tolerances:
portions of the decks on which finishing is completed.
Length (mm) Tolerance (mm)
5.3.3.13 Formed Finishes Up to 3000 ±2
3000 and over ±5
1 Class F1. This class of surface finish denotes a
special finish required from aesthetic considerations as ii. Cross-Section: Slab and wall thicknesses and
stated in the Special Specification. the cross-sectional dimensions of beams,
columns, piers etc., shall be within the
2 Class F2. Formwork shall be lined with a material
following tolerances:
approved by the Engineer to provide a smooth finish of
uniform appearance. This material shall leave no stain on Member Dimensions (mm) Tolerance (mm)
the concrete and shall be so joined and fixed to its backing Up to 500 ±6
so that it imparts no blemishes. It shall be of the same
501-750 ±9
type and obtained from only one source for any one
structure. The Contractor shall make good any Additional for every subsequent
imperfections in the finish as directed by the Engineer. 250 mm ± 3 mm
Internal ties and embedded metal parts will not be 3 Squareness: For in-situ and precast construction the
permitted unless otherwise approved by the Engineer. tolerance between the short side and the long side shall
3 Class F3. Irregularities in the finish shall be no be within the following limits:
greater than those resulting from the use of wrought thick Member Size (mm) Tolerance (mm)
square edged boards arranged in a uniform pattern. The Up to 3000 ±3
finish is intended to be left as struck. Imperfections such
3000 and over ±6

♦ 5-26 ♦
4 Straightness: For in-situ and precast construction the 3 Pretensioning: The process when the prestressing
straightness or bow, defined as deviation from the steel is tensioned against independent anchorages before
intended line, shall be within the following tolerances: the concrete is placed round it. The prestressing strand or
Member Length (mm) Tolerances (mm) tendons are stressed prior to casting the concrete. After
the concrete has attained the required strength, the
Up to 3000 ±3
prestressing force is released from the external
3000 and over ±6 anchorages and transferred, by bond, into the concrete.
5 Alignment: The alignment of members shall be 4 Combined Method: Part of the reinforcement is
within the following tolerances: pretensioned and part post-tensioned.
Columns and piers. : 1:400 of column or pier 5 Cable and Tendon: Cable and tendon both refer to a
length. bundle of prestressing steel of the same type and size
Others. : 1:600 of length bundled together to be contained within a duct and
6 Flatness: The flatness of a surface, measured with a stressed, individually or collectively, from the same
straight edge of 1.5 meter, shall be not greater than 6 mm anchorage.
at any point. 6 Prestressing System: A proprietary system of
7 Twist: Twist, measured as the deviations of any applying prestress and includes anchorages, couplers and
corner from the plane containing the other three corners, jacks but does not necessarily include prestressing steel
shall be within the following limits: and cable ducts.
Member Length (mm) Tolerance (mm)
5.4.1.3 References
Up to 6000 ± 6
1 American Association of State Highway and
Above 6000 ± 12
Transportation Officials (AASHTO):
AASHTO 2008 AASHTO LRFD Bridge Construction
5.3.4 Method of Measurement, Basis of
Specifications, 2nd Edition, 2004, 2008
Payment and Bill of Quantities
Interim Revisions.
1 No separate items are measured or included in the AASHTO 2008 AASHTO LRFD Bridge Design
Bill of Quantities for any part of Sub-section 5.3 and no specifications, 3rd Edition, 2004, 2008
separate payment will be made therefore. The costs are Interim Revisions.
deemed to be covered in the rates and prices in the Bill of
AASHTO 1999 Guide Specifications for Design and
Quantities for Sub-sections 5.1 and 5.2.
Construction of Segmental Concrete
Bridges, 2nd Edition.
5.4 Prestressed Concrete Structures
2 American Society for Testing and Materials (ASTM):

5.4.1 Description ASTM A 416/A 416 M Specification for Steel Strand,


Uncoated Seven-Wire for Prestressed
5.4.1.1 Scope Concrete (AASHTO M 203).

1 This Sub-section specifies the requirements for ASTM A 421/A 421 M Specification for Uncoated
prestressing precast or cast-in-situ concrete by furnishing, Stress-Relieved Steel wire for
placing, and tensioning of prestressing steel. It includes Prestressed Concrete (AASHTO M 204).
prestressing by either the pre-tensioning or post- ASTM A 722/ A 722 M Specification for Uncoated
tensioning methods or by a combination of these methods. High-Strength Steel Bars for
2 This work includes furnishing and installation of any Prestressing Concrete (AASHTO M 275).
appurtenant items necessary for the particular ASTM C 939 Test Method for Flow of Grout for
prestressing system to be used, including but not limited Preplaced-Aggregate Concrete (Flow
to ducts, anchorage assemblies, and grout used for Cone Method).
pressure grouting ducts. ASTM C940 Test Method for Expansion and
Bleeding of Freshly Mixed Grouts for
5.4.1.2 Definitions
Preplaced-Aggregate Concrete in the
1 Prestressing Steel: Steel wire, strand or bars used for Laboratory.
prestressing of concrete. ASTM C1202 Test Method for Electrical Indication of
2 Post-Tensioning: The process when the prestressing concrete’s Ability to Resist Chloride Ion
steel is tensioned after the concrete has hardened. The Penetration (AASHTO T 277)
tendons are installed in voids or ducts within the concrete 3 British Standards:
and are stressed and anchored against the concrete after
BS4447 Specification for the Performance of
the development of the required concrete strength. As a
Prestressing Anchorages for Post-
final operation under this method, the voids or ducts are
Tensioned Construction
pressure-grouted.

♦ 5-27 ♦
BS EN 5896 Specification for High Tensile Steel Engineer and correction by the Contractor of
Wire and Strand for the Prestressing of the drawings without delaying the work.
Concrete. iv. Shop drawings for post-tensioning and other
embedments, such as expansion joints,
5.4.1.4 Submittals
bearings, and anchor bolts submitted by
1 Design: suppliers shall be reviewed and approved by
i. Where the design for the prestressing work is the Engineer for conformance with the design
not fully detailed in the contract documents, concept and compliance with the design
the Contractor shall determine the details or drawings and Specifications.
type of prestressing system for use and select v. Where contract-document information on post-
materials and details conforming to this tensioning systems is modified by the
Specification as needed to satisfy the Contractor, or where contract drawings do not
prestressing requirements specified. The provide detailed dimensional information on
system selected shall provide the magnitude the post-tensioning system, it is the
and distribution of pre-stressing force and Contractor's responsibility to coordinate the
ultimate strength required by the contract placement of the post-tensioning system with
documents without exceeding allowable other embedments, and to correct any
temporary stresses. interferences created by the Contractor-
ii. Unless otherwise shown in the contract supplied prestressing system or other
documents, all design procedures, coefficients substitutions. The post-tensioning layout shall
and allowable stresses, friction, and prestress govern the layout of the secondary
losses, as well as tendon spacing and nonprestressed reinforcement. Where
clearances, shall be in accordance with either necessary, location of nonpre-stressed
or both the AASHTO LRFD Bridge Design reinforcement should be adjusted to clear
Specifications. tendons, subject to the approval of the
Engineer.
2 Working Drawings and Shop Drawings
3 Integrated Drawings: Where required by the contract
i. Where the contract documents do not include
documents, in addition to all required working drawings,
complete details for a prestressing system and
the Contractor shall prepare composite placing drawings
its method of installation, or where complete
to scale and in sufficient detail to show the relative
details are provided in the contract documents
positions of all items that are to be embedded in the
and the Contractor wishes to propose any
concrete, and their embedment depth, for the portions of
change, the Contractor shall prepare and
the structure that are to be prestressed. Such embedded
submit to the Engineer working drawings of
items shall include the prestressing ducts, vents,
the prestressing system proposed for use.
anchorage reinforcement and hardware, reinforcing steel,
Fabrication or installation of prestressing
anchor bolts, earthquake restrainers, deck joint seal
material shall not begin until the Engineer has
assemblies, drainage systems, utility conduits, and other
approved the drawings.
such items. Such drawings shall be in sufficient detail to
ii. The working drawings of the prestressing confirm that there will be no conflict between the planned
system shall show complete details and positions of any embedded items and that concrete cover
substantiating calculations of the method, will be adequate.
materials, and equipment the Contractor
4 Material Certificates: Signed by manufacturers and
proposes to use in the prestressing operations,
contractor certifying that each of the following items
including any additions or rearrangement of
complies with specified requirements:
reinforcing steel and any revision in concrete
dimensions from that specified in the contract i. Prestressing steel
documents. Such details shall outline the ii. Prestressing system.
method and sequence of stressing and shall iii. Records for the anchorage device acceptance
include complete specifications and details of test as specified in AASHTO LRFD Bridge
the prestressing steel and anchoring devices, Construction Specifications Article 10.3.2.3.12.
working stresses, anchoring stresses, tendon
elongations, type of ducts, and all other data 5.4.2 Materials
pertaining to the prestressing operation,
including the proposed arrangement of the 5.4.2.1 Concrete
prestressing steel in the members.
1 Concrete for prestressed construction shall be
iii. Working drawings shall be submitted produced and supplied in accordance with the relevant
sufficiently in advance of the start of the requirements of Section 5.1 “Concrete Materials and
affected work to allow time for review by the Mixes”.

♦ 5-28 ♦
5.4.2.2 Reinforcing Steel strength greater than the concrete. In addition, the epoxy
bonding agents shall function as a lubricant during the
1 Non-prestressed reinforcing steel shall be supplied, joining of the match cast segments, as a filler to accurately
cut, bent and fixed in accordance with the relevant match the surface of the segments being joined, and as a
requirements of Section 5.2 “Reinforcing Steel”. durable, watertight bond at the joint.
5.4.2.3 Prestressing Steel 3 The physical, chemical and mechanical properties of
epoxy bonding agents shall satisfy the recommendations
1 Steel Wire: Steel wire shall comply with ASTM A of the AASHTO LRFD Bridge Design Specifications or the
421/A 421 M (AASHTO M 204), or with BS 5896. Federation Internationale de la Precontrainte (FIP)
2 Stress-Relieved Seven-Wire Strand: Stress-Relieved "Proposals for a standard for acceptance tests and
Seven-Wire Strand shall comply with ASTM A 416/A416 M verifications of epoxy bonding agents for segmental
low relaxation (AASHTO M 203) or with BS 5896 low construction".
relaxation.
3 High Tensile Steel Bar: High tensile steel bars for 5.4.3 Construction Requirements
prestressed concrete shall comply with ASTM A 722/A 722
M (AASHTO M 275) or with BS 4486. 5.4.3.1 Placement of Ducts

5.4.2.4 Post-Tensioning Anchorages and Couplers 1 Ducts shall be rigidly supported at the proper
Iocations in the forms by ties to reinforcing steel which are
1 Post-tensioning anchorages and couplers shall be in adequate to prevent displacement during concrete
accordance with the requirements of AASHTO LRFD placement. Supplementary support bars shall be used
Bridge Construction Specifications Article 10.3.2. where needed to maintain proper alignment of the duct.
2 Prestressing components, such as cable ducts, Hold-down ties to the forms shall be used when the
anchorages and couplers, shall be of approved types buoyancy of the ducts in the fluid concrete would lift the
suitable for types of cables and bars used. reinforcing steel.
3 All anchorages and couplers shall develop at least 96 2 Polyethylene duct and metal duct for longitudinal or
percent of the actual ultimate strength of the prestressing transverse post-tensioning in the flanges shall be
steel, when tested in an unbonded state, without supported at intervals not to exceed 600 mm. Polyethylene
exceeding anticipated set. duct in webs for longitudinal post-tensioning shall be tied
to stirrups at intervals not to exceed 600 mm, and metal
4 The coupling of tendons shall not reduce the
duct for longitudinal post-tensioning in webs shall be tied
elongation at rupture below the requirements of the
to stirrups at intervals not to exceed 1200 mm.
tendon itself. Couplers and/or coupler components shall
be enclosed in housings long enough to permit the 3 Joints between sections of duct shall be coupled with
necessary movements. Couplers for tendons shall be used positive connections which do not result in angle changes
only at locations specifically indicated in the contract at the joints and will prevent the intrusion of cement paste.
documents and/or approved by the Engineer. Couplers Joints in adjacent ducts shall be staggered by at least 300
shall not be used at points of sharp tendon curvature mm.
5 If the Engineer is not satisfied with the testing 4 After placing of ducts, and reinforcement and
certificates submitted for the prestressing system, he may forming is complete, an inspection shall be made to locate
request post-tensioning anchorages and couplers to be possible duct damage. All unintentional holes or openings
tested in accordance with AASHTO LRFD Bridge in the duct shall be repaired prior to concrete placing.
Construction Specifications Article 10.3.2 at no extra cost. 5 Grout openings and vents shall be securely anchored
to the duct and to either the forms or to reinforcing steel
5.4.2.5 Epoxy-Bonding Agents for Precast Segmental
to prevent displacement during concrete-placing
Construction operations.
1 Epoxy bonding agents for match cast joints shall be 6 After installation in the forms, the ends of ducts shall
thermosetting 100 percent solid compositions that do not at all times be sealed as necessary to prevent the entry of
contain solvent or any nonreactive organic ingredient water or debris.
except for pigments required for coloring. Epoxy bonding 7 Where members are made up of precast units
agents shall be of two components, a resin and a hardener. stressed together, the ducts in the joints between the units
The two components shall be distinctly pigmented, so that shall be in perfect alignment and joined securely so as to
mixing produces a third color similar to the concrete in the allow unimpeded cable threading and pulling and prevent
segments to be joined, and shall be packaged in pre- the ingress of the epoxy mortar used for gluing the several
portioned, labeled, ready-to-use containers. units together before stressing. Details of such joints shall
2 Epoxy bonding agents shall be insensitive to damp first be approved by the Engineer. The tolerance in the
conditions during application and, after curing, shall location of the sheath shall be plus or minus 3 mm.
exhibit high bonding strength to cured concrete, good 8 Additionally the following shall apply:
water resistivity, low creep characteristics, and tensile

♦ 5-29 ♦
i. Entrance and exit angles of tendon paths at pressurize the tendon to 345 kPa and lock-off the outside
anchorages and/or at faces of concrete shall be air source. Record pressure loss for 1 minute. A pressure
within ± 3 degrees of desired angle measured loss of 170 kPa is acceptable for tendons having a length
in any direction and any deviations in the of equal to or less than 45 m and a pressure loss of 100
alignment are accomplished with smooth kPa is acceptable for tendons longer than 45 m. If the
transitions without any kinks. pressure loss exceeds the allowable, repair the leaking
ii. Angle changes at duct joints shall not be connections using methods approved by the Engineer and
greater than ±3 degrees in any direction and re-test.
must be accomplished with smooth transitions 13 The ends of all ducts shall be sealed and protected until
without any kinks. the tendon is threaded through and the stressing
iii. Locate anchorages within ± 3 mm of desired operations are commenced. Where tendons in sheaths or
position laterally and ±25 mm along the tendon sheath on its own are left exposed to atmosphere, rust
except that minimum cover requirements shall inhibitors shall be used as per the maker's specification to
be maintained. prevent rusting and corrosion of the inside of sheaths.
They shall be flushed with clean water before the tendons
iv. Position anchorage confinement reinforcement
are grouted. The Contractor is responsible for carrying
in the form of spirals, multiple U-shaped bars
out these measures at his own expense
or links to be properly centered around the
duct and to start within 12 mm of the back of 5.4.3.2 Placement of Prestressing Steel
the main anchor plate.
1 General:
v. If conflicts exist between the reinforcement and
post-tensioning duct, position the post- i. All wires or strands stressed at the same time
tensioning duct and adjust the reinforcement shall be taken from the same parcel. Each
locally with the Engineer's approval. cable shall be tagged with its number and the
coil number of the steel used.
9 Ducts shall be kept free of any matter detrimental to
the bond between the sheath and the grout and, except for ii. Tendons shall not be welded within the length
material sealing a sheath joint, between the sheath and to be tensioned and, unless other methods of
the concrete. cutting are approved by the Engineer, tendons
shall be sawn or cropped using an abrasive
10 All ducts for continuous structures shall be supplied
disc cutter.
with outlets at the high and low points of the duct profile,
except where the profile changes are small, as in iii. Tendons shall be built into the work strictly in
continuous slabs, and at additional locations as specified accordance with the system which is being
in the contract documents. Low-point outlets shall remain employed.
open until grouting is started. iv. Tendons shall not be kinked or twisted and
11 Upon completion of concrete placement, the individual wires or strands shall be readily
Contractor shall prove that the post-tensioning ducts are identifiable at each of the members. No strand
free and clear of any obstructions or damage and are able which has become unravelled shall be used in
to accept the intended post-tensioning tendons by passing the work.
a torpedo through the ducts. The torpedo shall have the 2 Placement for Pretensioning:
same cross-sectional shape as the duct, and 6 mm smaller i. Prestressing steel shall be accurately installed
all around than the clear nominal inside dimensions of the in the forms and held in place by the stressing
duct. No deductions shall be made to the torpedo section jack or temporary anchors and, when tendons
dimensions for tolerances allowed in the manufacture or are to be draped, by hold-down devices. The
fixing of the ducts. For straight ducts, a torpedo at least hold-down devices used at all points of change
600 mm long shall be used. For curved ducts, the length in slope of tendon trajectory shall be of an
shall be determined so that when both ends touch the approved low-friction type.
outermost wall of the duct, the torpedo is 6 mm clear of
ii. Prestressing steel shall not be removed from
the innermost wall. If the torpedo will not travel
its protective packaging until immediately prior
completely through the duct, the Engineer shall reject the
to installation in the forms and placement of
member, unless a workable repair can be made to clear
concrete. Openings in the packaging shall be
the duct, to the satisfaction of the Engineer. Upon
resealed as necessary to protect the unused
completion of the repairs, the torpedo shall pass through
steel. While exposed, the steel shall be
the duct easily, by hand, without resorting to excessive
protected as needed to prevent corrosion.
effort or mechanical assistance.
3 Placement for Post-Tensioning:
12 Before stressing and grouting internal or external
tendons, install all grout caps, inlets and outlets and test i. All prestressing steel preassembled in ducts
the tendon with compressed air to determine if duct and installed prior to the placement of concrete
connections require repair. In the presence of the Engineer, shall be accurately placed and held in position
during concrete placement.

♦ 5-30 ♦
ii. When the prestressing steel is installed after iv. When steam curing is used, unless anchorage
the concrete has been placed, the Contractor systems mandate its installation, steel for post-
shall demonstrate to the satisfaction of the tensioning shall not be installed until the steam
Engineer that the ducts are free of water and curing is completed.
debris immediately prior to installation of the v. Such tendons shall be protected against
steel. The total number of strands in an corrosion by means of a corrosion inhibitor
individual tendon may be pulled into the duct placed in the ducts or on the steel, or shall be
as a unit, or the individual strand may be stressed and grouted within seven days after
pulled or pushed through the duct. steam curing.
iii. Anchorage devices or block-out templates for vi. Whenever electric welding is performed on or
anchorages shall be set and held so that their near members containing prestressing steel,
axis coincides with the axis of the tendon and the welding ground shall be attached directly
anchor plates are normal in all directions to the to the steel being welded. All prestressing steel
tendon. and hardware shall be protected from weld
iv. The prestressing steel shall be distributed so spatter or other damage.
that the force in each girder stem is equal or as
5.4.3.3 Placement of Anchorages
required by the contract documents, except as
provided herein. 1 The Contractor is responsible for the proper
v. For box girders with more than two girder placement of all materials according to the design
stems, at the Contractor's option, the documents of the Engineer and the requirements
prestressing force may vary up to five percent stipulated by the anchorage device supplier. The
from the theoretical required force per girder Contractor shall exercise all due care and attention in the
stem provided the required total force in the placement of anchorage hardware, reinforcement,
superstructure is obtained and the force is concrete and consolidation of concrete in anchorage zones.
distributed symmetrically about the centerline 2 Modifications to the local zone details verified under
of the typical section. provisions of AASHTO LRFD Bridge Design Specifications
4 Protection of Steel after Installation: Article 5.10.9.7.3 and AASHTO LRFD Bridge Construction
Specifications Article 10.3.2.3, ‘Special Anchorage Device
i. Prestressing steel used in post tensioned
Acceptance Test’, shall be approved by both the Engineer
concrete members that is not grouted within
and the anchorage device supplier.
the time limit specified below, shall be
continuously protected against rust or other 5.4.3.4 Identification and Testing
corrosion by means of a corrosion inhibitor
placed in the ducts or directly applied to the 1 All wire, strand, or bars to be shipped to the site shall
steel. The prestressing steel shall be so be assigned a lot number and tagged for identification
protected until grouted or encased in concrete. purposes. Anchorage assemblies to be shipped shall be
Prestressing steel installed and tensioned in likewise identified.
members after placing and curing of the 2 Before approval, at least two samples of the
concrete and grouted within the time limit prestressing steel shall be tested at the Contractor's
specified below will not require the use of a expense, at an approved independent laboratory for
corrosion inhibitor described herein and rust chemical composition, mechanical strength, relaxation
which may form during the interval between and physical characteristics.
tendon installation and grouting will not be 3 Subsequently, each lot of wire or bars and each reel
cause for rejection of the steel. of strand reinforcement shall be accompanied by a
ii. The permissible interval between tendon manufacturer's certificate of compliance, a mill certificate,
installation and grouting without use of a and a test report. The mill certificate and test report shall
corrosion inhibitor for various exposure include:
conditions shall be taken as follows: i. Chemical composition (not required for strand),
- Very Damp Atmosphere or over saltwater ii. Cross-sectional area,
(Humidity > 70 percent) 7 days
iii. Yield and ultimate strengths,
- Moderate Atmosphere (Humidity from 40
iv. Elongation at rupture,
percent to 70 percent) 15 days
v. Modulus of elasticity, and
- Very Dry Atmosphere (Humidity < 40
percent) 20 days vi. Stress strain curve for the actual prestressing
steel intended for use.
iii. After tendons are placed in ducts, the openings
at the ends of the ducts shall be sealed to All values certified shall be based on test values and
prevent entry of moisture. nominal sectional areas of the material being certified

♦ 5-31 ♦
4 The Contractor shall furnish to the Engineer for type packaging material, or when permitted by the
verification testing samples selected at random from each Engineer, may be applied directly to the steel. Packaging
lot as follows. The actual strength of the prestressing steel or forms damaged from any cause shall be immediately
shall not be less than specified by the applicable ASTM replaced or restored to original condition.
Standard stated in Paragraph 5.4.2.3. 3 The shipping package or form shall be clearly marked
i. Pretensioning Tendons: one sample at least with a statement that the package contains high-strength
1500 mm long shall be furnished in accordance prestressing steel, and the type of corrosion inhibitor used,
with the requirements of Sub-Section 9.1 of including the date packaged.
ASTM A 416/A 416M. 4 All anchorages, end fittings, couplers, and exposed
ii. Post-Tensioning Tendons: for 20 tonnes, or tendons, which will not be encased in concrete or grout in
portion thereof, lot of material used in the the completed work, shall be permanently protected
work: against corrosion.
- For wires not requiring heading: sufficient 5 Corrosion Inhibitor:
length to make up one parallel-lay cable 1500 i. The corrosion inhibitor shall have no
mm long consisting of the same number of deleterious effect on the steel or concrete or
wires as the cable to be furnished. bond strength of steel to concrete or grout.
- For strand to be furnished with fittings: 1500 ii. Corrosion inhibitor shall consist of a vapor
mm between near ends of fittings. phase inhibitor (VPI) powder conforming to the
- For bars to be furnished with threaded ends provisions of Federal Specification MIL-P-
and nuts: 1500 mm between threads at ends. 3420F-87 or as otherwise approved by the
5 Anchorages: Engineer.

i. Before approval, at least two anchorages shall iii. When approved, water soluble oil may be used
be tested at the Contractor's expense, at an on tendons as a corrosion inhibitor.
approved laboratory to BS 4447. Subsequently,
5.4.3.6 Ducts
the Engineer may require additional samples,
selected at random from materials on site, to 1 Ducts formed by sheath left in place shall be a type
be similarly tested. that will not permit the intrusion of cement paste. They
ii. For each anchorage type used in the Works, the shall transfer bond stresses as required and shall retain
characteristic value of anchorage efficiency, shape under the weight (mass) of the concrete and shall
determined in accordance with BS 4447, shall have sufficient strength to maintain their correct
be not less than 90%. alignment without visible wobble during placement of
concrete.
6 For prestressing systems previously tested and
approved on projects having the same tendon 2 Metal Ducts:
configuration, the Engineer may waive the anchorage i. Sheathing for ducts shall be metal, except as
testing. provided herein. Such ducts shall be
7 Epoxy Bonding Agents: Epoxy bonding agents shall galvanized ferrous metal and shall be
be tested for and satisfy the requirements of all the tests fabricated with either welded or interlocked
listed in the recommendations of FIP "Proposal for a seams. Galvanizing of welded seams will not
standard for acceptance tests and verification of epoxy be required.
bonding agents for segmental construction". ii. Rigid ducts shall have smooth inner walls and
shall be capable of being curved to the proper
5.4.3.5 Protection of Prestressing Steel configuration without crimping or flattening.
1 All prestressing steel shall be protected against iii. Semi-rigid ducts shall be corrugated and, when
physical damage and rust or other results of corrosion at tendons are to be inserted after the concrete
all times from manufacture to grouting. Prestressing steel has been placed, their minimum wall thickness
shall also be free of deleterious material such as grease, shall be as follows: 0.45 mm for ducts less than
oil, wax or paint. Prestressing steel that has sustained or equal to 65 mm diameter 0.60 mm for ducts
physical damage at any time shall be rejected. The greater than 65 mm diameter.
development of pitting or other results of corrosion, other iv. When bar tendons are preassembled with such
than rust stain, shall be cause for rejection. ducts, the duct thickness shall not be less than
2 Prestressing steel shall be packaged in containers or 0.25 mm.
shipping forms for the protection of the strand against 3 Plastic Ducts:
physical damage and corrosion during shipping and
i. For locations in saltwater environment, plastic
storage. A corrosion inhibitor which prevents rust or other
duct material shall be considered and is
results of corrosion shall be placed in the package or form,
recommended.
or shall be incorporated in a corrosion inhibitor carrier-

♦ 5-32 ♦
ii. Corrugated plastic duct to be completely metal polyolefin (polyethylene or
embedded in concrete shall be constructed polypropylene), and shall be air and watertight
from either polyethylene or polypropylene. The and of sufficient strength to prevent distortion
minimum acceptable radius of curvature shall or displacement of the ducts during concrete
be established by the duct supplier according placement and/or tendon grouting.
to standard test methods. The duct shall have a ii. All ducts or anchorage assemblies shall be
thickness as below: provided with pipes or other suitable
Duct Shape Duct Diameter Duct Thickness connections at each end of the duct for the
in millimeters in millimeters injection of grout after prestressing. As
specified in Article 5.4.3.1(10), ducts shall also
Flat any size 2.0
be provided with ports for venting or grouting
Round 23 2.0 at high points and for draining at intermediate
Round 60 2.0 low points.
Round 75 2.5 iii. Vent and drain pipes shall be at least 20 mm
Round 85 2.5 diameter for strand and at least 12 mm
diameter for single-bar tendons and three or
Round 100 3.0
four strand flat duct tendons. Connection to
Round 115 3.5 ducts shall be made with metallic or plastic
Round 130 4.0 structural fasteners. The vents and drains shall
Round 145 4.0 be mortar tight, taped as necessary, and
constructed with either mechanical or shrink
iii. Ducts shall have a white coating on the outside
wrap connections. Vents and drains shall
or shall be of white material with ultraviolet
provide means for injection of grout through
stabilizers added.
the vents and for sealing to prevent leakage of
iv. Polyethylene duct shall be fabricated from grout.
resins meeting or exceeding the requirements
of ASTM D 3350 with a cell classification of 5.4.3.7 Grout
345464A.
1 Grout shall be in accordance with the requirements
v. Polypropylene duct shall be fabricated from of AASHTO LRFD Bridge Construction Specifications Sub-
resins meeting or exceeding the requirements section 10.9.
of ASTM D 4101 with a cell classification range
2 Grouts may be either a unique design for the project
of PP0340B14541 to PP0340B67884.
or supplied in a pre-bagged form by a grout manufacturer.
vi. Use resin containing antioxidant(s) with a
3 Unless otherwise directed or agreed as a result of
minimum Oxidation Induction Time (OIT)
grouting trials, uniquely designed grouts shall consist only
according to ASTM D 3895 of not less than 20
of ordinary Portland cement and water. The water-cement
minutes. The OIT test shall be performed on
ratio shall be as low as possible consistent with necessary
samples taken from the finished product.
workability and under no circumstances be higher than
vii. Rigid smooth black polyethylene ducts for use 0.45 and not be subject to bleeding in excess of 2 percent
where the tendon is not embedded in concrete after 3 hours, or 4 percent maximum. When measured at
shall be rigid pipe manufactured from 100 18 degrees C in a covered glass cylinder approximately
percent virgin polyethylene resin meeting the 100 mm water shall be reabsorbed after 24 hours.
requirements of ASTM D 3350 with a minimum
4 Grout shall be mixed for a minimum of two minutes
cell class of 344464C. A resin containing
and until a uniform consistency is obtained. The
antioxidant(s) with a minimum oxidation
pumpability of the grout may be determined in
induction time (OIT) according to ASTM D 3895
accordance with the US Corps of Engineers Method CRD-
of not less than 40 min shall be used. The OIT
C79 in which case the efflux time of the grout sample
test shall be performed on samples taken from
immediately after mixing shall not be less than 11 seconds.
the finished product. The duct shall be
manufactured with a dimensional ratio (DR) of 5 Admixture containing chlorides or nitrates shall not
17.0 as established by either ASTM D 3350 or be used. Other admixtures may be used only with the
ASTM F 714 as appropriate for the written permission of the Engineer and shall be applied
manufacturing process used. strictly in accordance with the manufacturer's instruction.

4 Duct Area: The provisions of AASHTO LRFD Bridge 6 The design for grout mix shall be tested in
Design Specifications, Article 5.4.6.2, ‘Size of Ducts,’ shall accordance with ASTM C 49 for longitudinal change. Each
apply. design mix and each batch mix shall be tested for vertical
dimensional change.
5 Duct Fittings:
7 Daily field testing of the grout for the following
i. Coupling and transition fittings for ducts
properties shall be required:
formed by sheathing shall be of either ferrous

♦ 5-33 ♦
i. Fluidity to ASTM C 939 or the modified test iii. Documentary proof shall be provided
described in AASHTO LRFD Bridge confirming that all jacks have been fully
construction Specification Table 10.9.3-2, overhauled and checked by an agent approved
ii. Bleed at 3 h to ASTM C 940 as modified in by the manufacturer of the equipment. Each
AASHTO LRFD Bridge construction jack shall be accompanied by a test certificate
Specification Table 10.9.3-2, indicating that it has been tested and calibrated
by the manufacturer or by an approved testing
iii. Permeability to ASTM C1202 (AASHTO T 277).
laboratory up to a load equal to the full
8 Manufacturers of pre-bagged post-tensioning grout capacity of the jack within a period of six
shall submit for approval certified test reports from an months prior to the commencement of
audited and independent Cement Concrete Research prestressing.
Laboratory (CCRL) which shows the material meets all the
iv. The jacking system shall provide an
requirements specified herein.
independent means by which the tendon
9 Preapproved pre-bagged grout shall be mixed in elongation can be measured. The pressure
accordance with the Manufacturer's recommendations. gage shall have an accurate reading dial at
10 Grouts shall achieve a non-bleeding characteristic. least 150 mm in diameter or a digital display,
Grout shall not contain aluminum powder or gas and each jack and its gage shall be calibrated
generating system that produces hydrogen, carbon as a unit with the cylinder extension in the
dioxide, or oxygen. Cementitious grout shall meet or approximate position that it will be at final
exceed the specified physical properties stated herein as jacking force, and shall be accompanied by a
determined by the following standard and modified ASTM certified calibration chart or curve.
test methods. v. All gages, load cells, dynamometers and other
11 Grout Classes shall be taken as specified in AASHTO devices used for measuring the stressing force
LRFD Bridge Construction Specifications Table 10.9.3-1 shall have an accuracy of within plus or minus
and Grout Properties shall be as specified in AASHTO 1.5 percent. Pressure gages shall have a
LRFD Bridge Construction Specifications Table 10.9.3-2. capacity and calibrated cell such that the
working pressure required to stress the
5.4.3.8 Tensioning tendons to the fully stated load lies within the
1 Tensioning may be accomplished by pre-tensioning, central half of the range of the gage.
post-tensioning, or the combined method; as specified in vi. Each gage shall have a calibration certificate
the contract documents, or on the approved working issued by an approved test laboratory. All
drawings, or approved in writing by the Engineer. pressure gages shall be so constructed that
2 During stressing of strand, individual wire failures they may be calibrated, either directly by an
may be accepted by the Engineer, provided not more than approved testing laboratory, or by
one wire in any strand is broken and the area of broken compressing with a meter gage which has
wires does not exceed two percent of the total area of the itself been calibrated by an approved testing
prestressing steel in the member. laboratory.

3 Concrete Strength: Prestressing forces shall not be vii. All pressure gages shall be re-calibrated before
applied or transferred to the concrete until the concrete use and at intervals of 14 days during the
has attained the strength specified for initial stressing. In prestressing operation. The Engineer will
addition, cast-in-place concrete for other than segmentally order re-calibration of any pressure gage at any
constructed bridges shall not be post-tensioned until at time should he have reason to suspect damage
least ten days after the last concrete has been placed in to or faulty operation of the gage.
the member to be post-tensioned. viii. The accuracy of all prestressing and load
4 Prestressing Equipment: measuring equipment shall be checked
whenever required by the Engineer. The
i. Hydraulic jacks used to stress tendons shall be
Contractor shall provide a rig suitable in the
capable of providing and sustaining the
opinion of the Engineer, for all checking and
necessary forces and shall be equipped with
calibration of any jacking system consisting of
either a pressure gage or a load cell for
jacks and associated load devices, pressure
determining the jacking stress.
gages and dynamometers.
ii. All jacks used for prestressing shall be of the
5 Sequence of Stressing: When the sequence of
type applicable to the system adopted. The
stressing individual tendons is not otherwise specified in
accuracy of the load metering equipment shall
the contract documents or on the approved working
be checked to the satisfaction of the Engineer
drawings, the stressing of post-tensioning tendons and
at the start of the work each day it has to be
the release of pretensioned tendons shall be done in a
used and whenever the equipment is moved to
sequence that produces a minimum of eccentric force in
a different job.
the member.

♦ 5-34 ♦
6 Measurement of Stress: the length of the casting bed and the size and number of
i. A record of gage pressures and tendon tendons in the group to be tensioned.
elongations for each tendon shall be provided 5 Draped Pretensioned Tendons:
by the Contractor for review and approval by i. Draped pretensioned tendons shall either be
the Engineer. Elongations shall be measured to tensioned partially by jacking at the end of the
an accuracy of 1.5 mm. Stressing tails of post- bed and partially by uplifting or depressing
tensioned tendons shall not be cut off until the tendons, or they shall be tensioned entirely by
stressing records have been approved. jacking, with the tendons being held in their
ii. The stress in tendons during tensioning shall draped positions by means of rollers, pins, or
be determined by the gage or load-cell other approved methods during the jacking
readings and shall be verified with the operation.
measured elongations. Calculations of ii. Approved low-friction devices shall be used at
anticipated elongations shall utilize the all points of change in slope of tendon
modulus of elasticity, based on nominal area, trajectory when tensioning draped
as furnished by the Manufacturer for the lot of pretensioned strands, regardless of the
steel being tensioned, or as determined by a tensioning method used.
bench test of strands used in the work.
iii. If the load for a draped strand, as determined
iii. All tendons shall be tensioned to a preliminary by elongation measurements, is more than five
force as necessary to eliminate any take-up in percent less than that indicated by the jack
the tensioning system before elongation gages, the strand shall be tensioned from both
readings are started. This preliminary force ends of the bed, and the load as computed
shall be between 5 and 25 percent of the final from the sum of elongation at both ends shall
jacking force. The initial force shall be agree within five percent of that indicated by
measured by a dynamometer or by other the jack gages.
approved method, so that its amount can be
6 When ordered by the Engineer, prestressing steel
used as a check against elongation as
strands in pretensioned members, if tensioned
computed and as measured. Each strand shall
individually, shall be checked by the Contractor for loss of
be marked prior to final stressing to permit
prestress not more than 3 hours prior to placing concrete
measurement of elongation and to ensure that
for the members. The method and equipment for checking
all anchor wedges set properly.
the loss of prestress shall be subject to approval by the
5.4.3.9 Pretension Construction Engineer. All strands that show a loss of prestress in
excess of three percent shall be retensioned to the original
1 The strand stress prior to seating (jacking stress) computed jacking stress.
shall not exceed 80 percent of the minimum ultimate
7 Stress on all strands shall be maintained between
tensile strength of the prestressing steel. This allowable
anchorages until the concrete has reached the
stress, which slightly exceeds the values allowed in
compressive strength required at time of transfer of stress
AASHTO LRFD Bridge Design Specifications, Article 5.9.3,
to concrete.
may be permitted to offset seating losses and to
accommodate compensation for temperature differences 8 When prestressing steel in pretensioned members is
specified below. tensioned at a temperature more than 14 deg. C lower
than the estimated temperature of the concrete and the
2 In pretensioned members where tendons are
prestressing steel at the time of initial set of the concrete,
specified as debonded from the concrete, they shall be
the calculated elongation of the prestressing steel shall be
covered with sleeves of PVC or other material approved by
increased to compensate for the loss in stress due to the
the Engineer. The ends of the sleeves shall be taped to
change in temperature, but in no case shall the jacking
the tendon to prevent the ingress of grout.
stress exceed 80 percent of the specified minimum
3 Stressing shall be accomplished by either single- ultimate tensile strength of the prestressing steel.
strand stressing or multiple-strand stressing. The amount
9 Members shall be free to accommodate the
of stress to be given to each strand shall be as shown in
horizontal and vertical movements due to the application
the contract documents or on the approved working
of prestress. Side and flange forms that restrain deflection
drawings.
shall be removed before release of pre-tensioning
4 All strands to be stressed in a group (multiple-strand reinforcement.
stressing) shall be brought to a uniform initial tension
10 When the concrete has attained the specified
prior to being given their full pre-tensioning. The amount
strength, the load shall be transferred gradually without
of the initial tensioning force shall be within the range
severance of the tendons
specified in Article 5.4.3.8 (6) Measurement of Stress, and
shall be the minimum required to eliminate all slack and to 11 Except when otherwise shown in the contract
equalize the stresses in the tendons as determined by the documents, all pretensioned prestressing strands shall be
Engineer. The amount of this force will be influenced by cut off flush with the end of the member, and the exposed

♦ 5-35 ♦
ends of the strand and a 25 mm strip of adjoining concrete iv. The tendons shall be stressed at a gradual and
shall be cleaned and painted. Cleaning shall be by wire steady rate until they attain the force and
brushing or abrasive blast cleaning to remove all dirt and extension specified.
residue that is not firmly bonded to the metal or concrete v. If the measured extension differs by more than
surfaces. The surfaces shall be coated with one thick coat 5 percent from the estimated extension,
of zinc-rich paint conforming to the requirements of U.S. corrective action shall be taken as directed by
Military Specification MIL-P-24441/20. The paint shall be the Engineer.
thoroughly mixed at the time of application, and shall be
vi. The force in the tendons shall be obtained from
worked into any voids in the strands.
reading on a load cell or pressure gage, and
12 All members shall be indelibly marked to show the the extension of the tendons measured. Due
specified member mark, the production line on which they allowance must be made for taking up slack in
were manufactured, the date on which the concrete was the tendons.
cast, the load applied and, if they are of symmetrical
vii. Stressing shall be from both ends unless
section, the face which will be uppermost when the
otherwise specified or agreed by the Engineer.
member is in its correct position in the work. The
markings shall be so located that they are not exposed to viii. Where stressing from one end only, the pull-in
view when the member is in its permanent position. at the end remote from the jack shall be
accurately measured and the appropriate
5.4.3.10 Post-Tension Construction allowance made in the measured extension at
the jacking end.
1 The standard stress prior to seating (jacking stress)
and the stress in the prestressing steel immediately after ix. When the specified force, including any
seating shall not exceed the values allowed in AASHTO overload of short duration, has been applied, to
LRFD Bridge Design Specifications, Sub-section 5.9.3. the satisfaction of the Engineer, the tendons
shall be anchored. The jack pressures shall
2 Immediately before tensioning, the Contractor shall
then be released in such a way as to avoid
demonstrate to the satisfaction of the Engineer that all
shock to the anchorage of tendons.
tendons are free to move between jacking points and that
members are free to accommodate the horizontal and x. If the pull-in of the tendons at completion of
vertical movements due to the application of prestress. anchoring is greater than that stipulated by the
Engineer, tensioning shall be carried out afresh.
3 Unless otherwise specified, concrete shall not be
stressed until it has reached the age at which at least 2 test xi. If it is necessary to cut the tendons to enable
specimens taken from it attain the specified transfer the ducts to be grouted, this shall be delayed
strength. The test specimens shall be cured in similar as long as practicable up to the time of
conditions to the concrete to which they relate. The grouting. In all other cases, unless agreed
Contractor shall cast sufficient specimens to demonstrate otherwise by the Engineer, the tendons shall
that the required strength of the concrete at transfer has not be cropped less than 3 days after grouting.
been reached. 6 Records: A record of the following post-tensioning
4 Where members consist of jointed elements the operations shall be kept for each tendon installed:
strength at transfer of the jointing material shall be at least i. Project name, number,
equivalent to the specified transfer strength of the ii. Contractor and/or subcontractor,
member.
iii. Tendon location, size and type,
5 Tension Procedures:
iv. Date tendon was first installed in ducts,
i. The Contractor shall establish the datum point
v. Coil/reel number for strands or wires and heat
for measuring extension and jack pressure to
number for bars and wire,
the satisfaction of the Engineer.
vi. Assumed and actual cross-sectional area,
ii. The Contractor shall add to the specified forces
an allowance where necessary for anchorage vii. Assumed and actual modulus of elasticity,
friction, wedge pull-in, jack losses and friction viii. Date stressed,
due to duct alignment and curvature. The total ix. Jack and gage numbers per end of tendon,
forces and calculated extensions shall be
x. Required jacking force,
agreed with the Engineer before stressing is
commenced. xi. Gage pressures,
iii. Immediately after anchoring, the stresses in the xii. Elongations (anticipated and actual),
tendons shall not exceed 75 percent of their xiii. Anchor sets (anticipated and actual),
ultimate tensile strength or as defined in the xiv. Stressing sequence (i.e., tendons before and
contract documents. During stressing the after this tendon),
value shall not exceed 80 percent.
xv. Stressing mode (one end/two
ends/simultaneous),

♦ 5-36 ♦
xvi. Witnesses to stressing operation (Contractor viii. Mixing and pumping procedures;
and Inspector), ix. Direction of grouting;
xvii. Date grouted, days from stressing to grouting, x. Sequence of use of the inlets and outlet pipes;
grouting pressure applied, and injection end,
xi. Procedures for handling blockages; and
xviii. Record any other relevant information
xii. Procedures for possible post grouting repair.
including pour back and bitumastic installation
dates. Before grouting operations begin, a joint meeting of
the Contractor, grouting crew and the Engineer shall
The Engineer shall be provided with a complete copy of
be conducted. At the meeting, the grouting operation
stressing operations, and the jack calibration forms within
plan, required testing, corrective procedures, and any
24 hours of each tensioning operation.
other relevant issues shall be discussed.
7 Protection of Tendons: Within 4 hours after stressing
5 Preparation of Ducts:
and prior to grouting, tendons shall be protected against
corrosion or harmful effects of debris by temporarily i. Each duct shall be air pressure tested prior to
plugging or sealing all openings and vents; cleaning rust the installation of the prestressing steel into the
and other debris from all metal surfaces which will be ducts. If leaks are indicated during the test, the
covered by the grout cap; and placing the grout cap, duct shall be repaired to eliminate the leakage
including a seal, over the wedge plate until the tendon is or minimize the consequences of the leakage.
grouted. ii. All ducts shall be clean and free of deleterious
materials that would impair bonding or
5.4.3.11 Grouting interfere with grouting procedures.
1 Grout should be injected from low points pumping iii. Ducts with concrete walls (cored ducts) shall be
toward the high-point vent. For segmental, span-by-span flushed to ensure that the concrete is
construction, grout shall be injected through a grout inlet thoroughly wetted. Metal ducts shall be flushed
at midspan. if necessary to remove deleterious material.
2 Ducts shall be grouted as soon as practicable after iv. Water used for flushing ducts may contain
the tendons have been stressed and the Engineer's slack lime (calcium hydroxide) or quicklime
permission to commence has been obtained. The ducts (calcium oxide) in the amount of 0.012 kg/l.
shall be completely filled with grout. Grout shall be v. After flushing, all water shall be blown out of
injected in one continuous operation and allowed to flow the duct with oil-free compressed air.
from the vents until the consistency is equivalent to that
6 Equipment:
being injected or more than 11 seconds.
i. The grouting equipment shall include a high-
3 Grout shall not be above 32 deg. C during mixing or
speed shear mixer capable of continuous
pumping. If necessary, cool the mixing water.
mechanical mixing which will produce a grout
4 A grouting operation plan shall be submitted for free of lumps and undispersed cement, a grout
approval at least 45 days in advance of any scheduled pump, and stand-by flushing equipment with
grouting operations. Written approval of the grouting water supply. The equipment shall be able to
operation plan by the Engineer shall be required before pump the mixed grout in a manner which will
any grouting of the permanent tendons in the structure comply with all requirements.
takes place. At a minimum, the following items shall be
ii. The equipment shall be as per ASTM LRFD
provided in the grouting operation plan:
Bridge Construction Specification Article
i. Provide names, and proof of training and 10.11.3.
experience records for the grouting crew and
7 Mixing of Grout:
the crew supervisor in conformance with this
Specification; i. Water shall be added to the mixer first,
followed by cement grout.
ii. Type, quantity, and brand of materials used in
grouting including all required certifications; ii. Grout shall be mixed in accordance with the
manufacturer's instructions using a colloidal
iii. Type of equipment furnished, including
mixer to obtain homogeneous mixture. A
capacity in relation to demand and working
fluidity test shall be performed on the mixed
condition, as well as back-up equipment and
grout prior to beginning the injection process.
spare parts;
Target flow rates as a function of mixer type
iv. General grouting procedure; used and ambient temperatures shall be
v. Duct pressure test and repair procedures; obtained from the grout manufacturer. The
vi. Method to be used to control the rate of flow
within ducts;
vii. Theoretical grout volume calculations;

♦ 5-37 ♦
grouting process shall not be started until the
proper grout properties have been obtained. Property Test Value Test Method
iii. Mixing shall be of such duration as to obtain a Max. 0.08% by
uniform, thoroughly blended grout, without Total Chloride weight of ASTM
Ions cementitious C1152/C1152M
excessive temperature increase or loss of
material
expansive properties of the admixture. The Fine Aggregate Max. Size ≤ No. ASTM C 33
grout shall be continuously agitated until it is (if utilized) 50 Sieve
pumped. Volume
0.0% to+0.2% at ASTM C 1090*
iv. Water shall not be added to increase grout Change at 28
24 h and 28 days
days
flowability which has been decreased by
≤2.0% for up to 3
delayed use of the grout. Expansion ASTM C 940
h
8 Injection of Grout: Compressive
i. All grout vents shall be opened before grouting Strength ASTM C 942
≥6 ksi
28 day (average
starts. Injection and ejection vents with
of 3 cubes)
positive shut-offs shall be provided. Grout shall
Initial Set of Min. 3 h ASTM C 953
be allowed to flow from the first injection vent
Grout Max. 12 h
until any residual flushing water or entrapped
Fluidity Test**
air has been removed prior to closing that vent.
Efflux Time
Remaining vents shall be closed in sequence in from Flow Min 11 s
the same manner. A continuous flow of grout ASTM C 939
Cone Max. 30 s or
at a rate between 10 000 mm and 15 000 mm ASTM C
a) Immediately Min. 9 s
939***
of duct per minute shall be maintained. after Mixing Max. 20 s
ASTM C 939
b) 30 min after Max. 30 s or
ii. The pumping pressure at the injection vent ASTM C
Mixing with Max. 30 s
should not exceed 1.0 MPa. Normal operations 939***
Remixing
shall be performed at approximately 0.5 MPa. for 30 s
If the actual grouting pressure exceeds the ASTM C
Bleeding at 3 h Max. 0.0%
maximum allowed, the injection vent shall be 940****
closed and the grout shall be injected at the Permeability at Max. 2500 AASHTO T 277
next vent that has been, or is ready to be 28 days coulombs at 30 (ASTM C 1202)
closed, as long as a one-way flow is volts for 6 h
maintained. Grout shall not be injected into a Table 5.4.3.1 Grout Properties for
succeeding vent from which grout has not yet Volume Change at 28 Days
flowed. Table 5.4.3-1 Notes
*Modify ASTM C 1090 to include verification at both
Iii Grout shall be pumped through the duct and
24 h and 28 days.
continuously wasted at the ejection vent until
no visible slugs of water or air are ejected. A **Adjustments to flow rates will be achieved by strict
fluidity test shall be performed on each tendon compliance with the manufacturer’s
recommendations.
in accordance with paragraph 5.4.3.7 (7)
measuring the grout fluidity from the discharge ***Grout fluidity shall meet either the standard ASTM
outlet. The measured grout efflux time shall C 939 flow cone test or the modified test described
not be faster than the efflux time measured at herein. Modify the ASTM C 939 test by filling the cone
the inlet or the minimum efflux time to the top instead of to the standard level. The efflux
time is the time to fill a 1.0 liter container placed
established in Table 5.4.3.1. If the grout efflux
directly under the flow cone.
time is not acceptable, additional grout shall be
discharged from the discharge outlet. Grout ****Modify ASTM C 940 to conform with the wick
efflux time shall be tested. This cycle shall be induced bleed test described below:
continued until acceptable grout fluidity is a) Condition dry ingredients, mixing water,
achieved. To ensure that the tendon remains prestressing strand and test apparatus overnight
filled with grout, the ejection and injection at 21 to 25 deg. C.
vents shall be closed in sequence, respectively, b) Insert 800 milliliters of mixed conditioned grout
with conditioned water into the 1000 milliliters
under pressure when the tendon duct is
graduated cylinder. Mark the level of the top of
completely filled with grout. The positive shut- the grout.
offs at the injection and ejection vents shall not c) Wrap the strand with 50 mm wide duct or
be removed or vents opened until the grout electrical tape at each end prior to cutting to
has set. avoid splaying of the wires when it is cut.
iv. The maximum allowable ambient temperature
to start grouting is 32 degrees C.

♦ 5-38 ♦
Degrease (with acetone or hexane solvent) and be used to construct all pour-backs located at
wire brush to remove any surface rust on the anchorages of expansion joints or other areas
strand before temperature conditioning. Insert exposed to the elements.
completely a 500 mm length of conditioned,
cleaned, ASTM A 416/A 416M seven wire strand ii. All laitance, grease, curing compounds, surface
12.7 mm diameter into the 1000 milliliter treatments, coatings, and oils shall be removed
graduated cylinder. Center and fasten the strand by grit blasting or water blasting using a
so it remains essentially parallel to the vertical minimum 70.0 MPa nozzle pressure. The
axis of the cylinder (possibly using a centralizer). surface shall be flushed with water and blown
Mark the level of the top of the grout. dry. Surfaces shall be clean, sound, and
d) Store the mixed grout at the temperature range
without any standing water. In case of dispute,
listed above in (a).
e) Measure the level of the bleed water every 15 min ACl 503 shall be followed for substrate testing
for the first hour and hourly afterward for 2 h. and a minimum of 1.2 MPa tension (pull-off
f) Calculate the bleed water, if any, at the end of the value) be developed.
3 h test period and the resulting expansion per
iii. Epoxy shall be mixed and applied as
the procedures outlined in ASTM C 940, with the
quantity of bleed water expressed as a percent of manufacturer's current standard technical
the initial grout volume. Note if the bleed water guidelines. All pour-backs shall be in leak proof
remains above or below the top of the grout. forms creating neat lines. The pumping of
9 Vertical Grouting: In lieu of a positive shut-off, epoxy grout shall be permitted for proper
vertical or near vertical tendon ducts for grouting shall installation. Forms shall be constructed to
terminate in reservoirs at the upper-most point. The maintain a liquid head to insure intimate
reservoir shall have sufficient capacity to store excess contact with the concrete surface. Vents shall
grout bleed water. Visible grout level shall be maintained be used as needed to provide for the escape of
in the reservoirs. The reservoirs shall be maintained until air to insure complete filling of the forms.
the grout has set. Grout shall be injected at a rate of 5000 iv. The exposed surfaces of pour-backs or grout
mm of duct per minute. caps, except on transverse tendons, shall be
10 Post-Grouting Inspection: Vacuum grouting shall be coated with an elastomeric coating system
used to fill any voids that expose strands discovered in the having a thickness of 760 to 1140 μm. Concrete,
grouting process. Where possible, all anchorages and grout caps or other substrates shall be
high-point vents shall be drilled and probed 48 hours after structurally sound, clean, and dry. Concrete
grouting, until the Engineer is assured that no bleed water shall be a minimum of 28 days old. Laitance,
or subsidence (settlement) voids exist. After the Engineer grease, curing compounds, surface treatments,
is assured that voids do not exist, only one or two coatings, and oils shall be removed by grit
anchorages per span shall be drilled and probed to ensure blasting or water blasting using a minimum
quality grouting. Any voids discovered should be filled 70.0 MPa nozzle pressure to establish the
immediately with the approved grout. anchor pattern. Surfaces shall be blown with
compressed air to remove the dust or water.
11 Finishing:
v. A 600 x 1200-mm concrete test block shall be
i. Valves, caps and vent pipes shall not be
constructed with a similar surface texture to
removed or opened until the grout has set.
the surfaces to be coated and a vertical face
ii. The ends of vents shall be removed at least 25 shall be coated with the elastomeric coating
mm below the concrete surface after the grout system chosen. The number of coats required
has set. to achieve a coating thickness between 760 to
iii. The void shall be filled with epoxy grout. All 1140 μm without runs and drips shall be
miscellaneous material used for sealing grout determined. The elastomeric coating shall be
caps shall be removed before carrying out mixed and applied as per Manufacturer's
further work to protect end anchorages. current standard technical specifications. Spray
or roller application may be permitted; spray
12 Protection of End Anchorages: Permanent grout caps
application is preferred. Coatings shall be
constructed from either stainless steel or polymer shall be
applied using approved and experienced
specified. The following requirements apply:
personnel with a minimum of 3 years
i. Within seven days upon completion of the
experience applying similar polyurethane
grouting, the anchorage of post-tensioning
systems. Credentials of these persons shall be
bars and tendons shall be protected as
submitted to the Engineer for review and
indicated in the contract documents. The
consideration for approval.
application of the elastomeric coating may be
delayed up to 90 days after grouting. Plastic or
5.4.4 Method of Measurement
stainless steel threaded caps shall be used to
plug all grout inlets/outlets. A sand-filled epoxy 1 Concrete shall be measured under the provisions of
grout suitable for machinery base plate shall Section 5.1.

♦ 5-39 ♦
2 Non-prestressed reinforcing steel shall be measured iv. Plant, equipment and labor for all stressing and
under the provisions of Section 5.2 . grouting operations, including making good all
3 Prestressing steel shall be measured by the weight in anchorage pockets as shown on the Drawings
metric tonnes for each size and quality of wire, strands or or as directed by the Engineer.
bar furnished, installed, completed and accepted. The v. All testing required in the Specifications.
weight shall be calculated based on the nominal mass of
each diameter wire, strand or bar as stated in the 5.4.6 Items in the Bill of Quantities
standards listed in Paragraph 5.4.21.3.
i Prestressing wires
4 In post-tensioning work, the prestressing steel shall
(state size and type) t.
be measured in t based on the actual length between the
ii Prestressing strands
outermost surfaces of the anchorages except where
(state size and type) t.
couplers are used in which case, the prestressing steel
shall be assumed to be continuous, without any flares, iii Prestressing bars
through the coupler. (state size and type) t.
5 In pre-tension work, the prestressing steel shall be
measured in t based on the actual length between the 5.5 Concrete Bridges and Erection
outermost faces of the member. Procedures
6 Items not measured: Measurement of prestressed
concrete is restricted to the items stated in items 1, 2 and 3 5.5.1 Description
above. No separate measurement is made for any other
5.5.1.1 Scope
component or work.
i. Cable ducts, duct couplers, grout tubes and 1 This Sub-section describes requirements for erection
steel chairs for the correct duct/tendon location of concrete bridge structures and decks in conformity with
are not measured for payment. the lines, grades and dimensions shown on the Drawings
ii. Anchor blocks for use in pre-tension work are and in accordance with the Specifications. These
not measured for payment. requirements are additional to the requirements for
concrete work generally as specified in the preceding Sub-
iii. Prestressing steel used in connection with
sections of this Section
temporary works is not measured for payment
even if such steel is left permanently in the 5.5.1.2 References
member.
1 American Association of State Highway and
iv. Epoxy bonding agent used in precast
Transportation Officials (AASHTO):
segmental construction shall not be measured
for payment. AASHTO 2008 AASHTO LRFD Bridge Construction
Specifications, 2nd Edition, 2004, 2008
v. Shear keys and location dowels used in precast
Interim Revisions.
segmental construction shall not be measured
for payment. AASHTO 2008 AASHTO LRFD Bridge Design
specifications, 3rd Edition, 2004, 2008
vi. Prestressing steel and anchorages used for
Interim Revisions.
applying temporary prestress to glued
segments shall not be measured for payment. AASHTO 1999 Guide Specifications for Design and
Construction of Segmental Concrete
vii. Anchorages and couplers shall not be
Bridges, 2nd Edition.
measured for payment.
2 Fédération Internationale de la Précontrainte (FIP)
5.4.5 Basis of Payment FIP Proposal for a Standard for Acceptance
Tests and Verification of Epoxy Agents
1 The amount of completed and accepted work for Segmental Construction.
measured as provided for above shall be paid at the rates
in the Bill of Quantities. These rates shall be full
5.5.2 Materials
compensation for the provision of materials, equipment,
labor, tools, testing and other items necessary for proper 1 Materials shall conform to the relevant requirements
completion of the Work. The rates shall include: of the following Sub-sections of the Specification:
i. Items not measured as described in Item 5.4.4 - Concrete Sub-section 5.1 Concrete
(6). Materials and
ii. Cement, water and additive used in making the Mixes
grout. - Reinforcing Steel Sub-section 5.2 Reinforcing
iii. All prestressing equipment and its calibration. Steel

♦ 5-40 ♦
- Pre-stressing Sub-section 5.4 Pre-stressed each stage of construction at the check points
Concrete listed below, or an alternative of his choice and
Structures submit the same for the Engineer's approval.
The check points are:
5.5.3 Construction Requirements - One of the lowest corners at the top surface
of any temporary bearing pad which is to
5.5.3.1 Balanced Cantilever Construction with In-Situ
be used as datum during construction.
Concrete
- All four corners of the top slabs of the pier
1 General: units to establish grade and top levels.
i. This work consists of installing temporary - Two points on the longitudinal center line
bearings, casting concrete units in-situ and of each pier unit, one on each end to
setting the superstructure on permanent establish alignment.
bearings. The Contractor shall submit - One point on the longitudinal center line,
complete details and descriptions of all and at least on one corner of each unit
methods, arrangements and equipment which along every joint between cast-in-place
he intends to adopt, for approval before units to establish elevations and
construction work is started. alignments at every stage of construction.
ii. The construction method statement shall ii. The alignment and elevations of the cantilever
include casting of units, method of the tie- shall be checked by the Contractor and the
down of superstructure during cantilever Engineer independently within 1 hour of
construction, method of application of all sunrise on each day that the units are to be
temporary forces to be used for adjusting cast. The measurements made by the Engineer
horizontal and vertical alignment and to place and the Contractor shall agree to within 5 mm.
the structure on permanent bearings, details of
iii. The temporary bearing pads at the piers shall
work plans and safety measures. It shall also
be carefully placed. The top surface of these
include control methods to ensure the accuracy
pads must have the correct elevations,
of alignments of the constructed superstructure.
alignments and slopes as required by the
iii. Work equipment includes all machinery, working drawings and as established by the
devices, labor and material which are to be procedure described above. Shims may be
used for construction but which will not used underneath the pads to accomplish
become a permanent part of the completed accuracy. The Contractor shall check
superstructure. Construction equipment and elevations and alignment of the structure at
other loads shall not be placed upon any part every stage of construction and shall maintain
of the superstructure at any stage of a record of all these checks and of all
construction other than that which specifically adjustments and corrections made.
meets the requirements of total working load
3 Casting Procedures:
per unit, or has the approval of the Engineer.
This includes the post-tensioning, jointing, i. Casting of the units shall not begin until
jacking, grouting equipment, any other approval of the shop drawings, calculations
equipment whatsoever, workmen and and the post-tensioning system has been given.
materials of any kind. ii. Sequence. The units shall be match cast
iv. Unbalanced Load: During construction the beginning with each pier unit. After the pier
cantilever may be unbalanced by only one unit unit is cast all units on either side of the pier
at any time and be consistent with the holding- unit may be cast in order so long as match
down method adopted. In addition to the casting is maintained.
unbalanced load due to one unit, 0.5 kN/m2 iii. Care shall be taken in the set-up of each unit.
load is permissible anywhere on the cantilever. All materials to be encased within the concrete
This load includes workmen, miscellaneous of the segment shall be properly positioned
equipment and stored materials. The and supported. Before any concrete is placed,
Contractor shall take care to ensure that this the set up will be inspected and checked by the
allowable load is not exceeded. Engineer. All ducts shall be located within
2 Construction Schedule: 3mm of the location given on approved
drawings. The top surface of the units shall be
i. The Contractor shall submit a construction
free of depressions or high spots.
schedule showing the order of every phase and
stage of erection and construction of the iv. Forms shall not be removed until the concrete
superstructure. The Contractor shall prepare a has achieved the specified compressive
table of elevations and alignments required at strength has been proved by test cylinders
made and cured in the same manner as the

♦ 5-41 ♦
unit. Care shall be taken in removing the forms iv. Each batch of resin mixed shall be tested for
to prevent spalling and chipping of the setting by compression and shear tests as
concrete. described below. No permanent prestress
4 Tolerances: shall be applied to a joint until the epoxy has
achieved the required strength. Should this
i. Formwork for box girder segments must satisfy
test show that the resin is not setting the joint
the following tolerances:
shall be broken and the resin removed. Set
- Web thickness, +10 mm or -5 mm. resin shall be removed by grit blasting. Further
- Thickness of bottom slab +5 mm, but 0 tests may be requested by the Engineer at
reduction in depth. various times to ensure that the material as
- Thickness of top slab +5 mm, but 0 mixed is complying with the Specification.
reduction in depth. v. All the instructions of the manufacturer and/or
- Overall width of unit, ±5 mm. the formulator shall be submitted to the
Engineer for agreement. Such agreed
- Overall depth of unit, ±5 mm.
instructions shall be adhered to in all respects.
- Length of match cast unit, ±10 mm, but not
vi. The supplier shall carry out a program of
cumulative and a maximum of 50 mm per
testing as described in FIP "Proposal for a
span.
standard for acceptance tests and verification
- Diaphragm dimensions, +10 mm or -5 mm. of epoxy bonding agents for segmental
- Grade at top and bottom flanges, ±3. construction", after consultation with the
ii. After erection, final post-tensioning, final Engineer on the range of temperatures and
corrections and adjustments are completed work cycles that are to be considered in the
and the structure has been placed on its tests. The Engineer may require the tests to be
permanent bearings, the superstructure shall witnessed either in person or by an approved
conform to the grade and alignment shown on independent authority.
the Drawings with due consideration for creep 3 Surface Preparation: The interface of the units shall
and superimposed load and dead load be lightly grit blasted before erection to remove laitance.
deflections within a tolerance of ± 5 mm Before applying the epoxy the interfaces must be clean
horizontally and ± 10 mm vertically. and free from laitance or any bond breaking material. Any
oil or grease which may be harmful shall be removed.
5.5.3.2 Glued Precast Segmental Construction The surface shall have no free moisture.
1 Where bridge decks are precast in segments and 4 Application of Epoxy: Application shall begin
assembled in position for glueing and stressing, the immediately after a batch has been mixed. Application
Contractor shall satisfy the Engineer that his proposed shall be to both interfaces to a total nominal thickness of 2
construction method will achieve the required standard of mm with a spatula or by hand. No epoxy may be applied
workmanship and finish. The Contractor shall submit within 25mm of any duct.
details for approval of all his forms, falsework, precasting 5 Preliminary Prestress: Immediately after the
factory and his method of lifting, transporting, assembling, interfaces are coated with epoxy, the unit shall be brought
supporting, threading cables, glueing and stressing the into position and the preliminary prestress applied. This
precast units before commencement of any work. preliminary prestress is to be just sufficient to start
2 Epoxy Adhesive: squeezing epoxy resin out of the joint. The amount of
i. The epoxy resin adhesive shall be supplied by prestress required will depend on the formulation of resin
an approved manufacturer. chosen by the Contractor. If this operation is not
completed within the life time of the first batch of epoxy to
ii. It shall be made up and packaged by approved
be applied, the units shall be moved apart. All the epoxy
formulators and to specifications agreed by the
on both interfaces shall be removed with spatulas and an
Engineer.
approved solvent. No epoxy may be applied to the joint
iii. The material shall be supplied in accurately until 24 hours after a solvent has been used. The life time
measured packs with the pack containing the shall be reckoned from the end of the pot life unless the
hardener clearly distinguished by both size and manufacturer's instructions direct otherwise. All excess
labelling. The pack containing the resin shall epoxy shall be cleaned off from the outer faces of the
be large enough to permit the addition of the webs and the soffit in such a way as not to smear the
hardener. Resin and hardener shall be concrete face.
pigmented with dissimilar colours to indicate
6 Records of Joining: The Contractor shall keep a
when even mixing has been completely
record of each joint with the following details:
attained and to produce an even gray colour to
match the concrete. i. Joint Number
ii. Date and Time of jointing

♦ 5-42 ♦
iii. Batch number of resin and hardener containing the other 3 corners) 6 mm
iv. Weather conditions (temperature and - Flatness (the maximum deviation
humidity) continuously recorded from a 1.5 meter straight-edge
v. Results of tests. placed in any position on
nominally plane surface) 6 mm
7 Tolerances: These shall be similar to those
prescribed for balanced cantilever construction. - Cover to reinforcement +5 or -0 mm
- Prestressing tendons 3 mm in any direction
5.5.3.3 Precast Beam and slab Construction
- Dowel holes 3 mm in any direction
1 Manufacture of Prestressed Beams: 4 Composite Slab Construction:
i. The details of method of manufacture shall be i. Where in-situ concrete deck is cast to act
approved by the Engineer before work is compositely with precast beams, the beams
started. No changes shall subsequently be shall be installed to correct line and level,
made without the consent of the Engineer. starting from the outermost beam and working
ii. The Contractor shall inform the Engineer in inwards progressively. When the beams are
advance of the date of commencement of laid side by side just before erection the
manufacture and the dates when tensioning of difference in soffit level between adjacent
tendons, casting of members and transfer of beams shall nowhere exceed 6 mm. Where
stress will be undertaken for the first time for permanent soffit shutters are used, they shall
each type of beam. be to the approval of the Engineer and they
iii. The Contractor shall submit to the Engineer, shall be fixed securely so that there is no
not more than 7 days after the transfer of movement or grout loss during deck
stress, a certificate showing the force and concreting.
strain in the tendons immediately after they ii. The in-situ concrete deck over any one span
were anchored, the strength and age of the test shall be poured in one continuous operation
cylinders cast in accordance with this and shall be placed in such a sequence that the
Specification, and the minimum age in hours advancing edge of the freshly deposited
of the concrete at the time stress was applied concrete over the full width of deck or between
to the members. Copies of all 28 day cylinder longitudinal construction joints is
test results relating to the work shall be kept so approximately parallel to the deck supports.
that the identity of those who stressed the Lateral displacement of beams shall be
tendons, cast the concrete and transferred the prevented during the placing of in-situ concrete.
stress, on any member or line of members, can iii. The width of the in-situ deck shall be within
be traced. +25 mm of that specified. On curved bridge
iv. Where the Engineer requires tests to be carried deck, the in-situ deck may be in a series of
out on beams, the beams to which these tests straights such that the width is within +25 mm
related, shall not be dispatched to Site until the of that specified.
tests have been satisfactorily completed.
5.5.3.4 In-Situ Construction
2 Storage and Handling of Prestressed Members:
Members shall be firmly supported at such bearing 1 Where bridge decks are constructed in-situ, the
positions as will ensure that the stresses induced in them details of all forms and falsework shall first be approved
are always less than the permissible design stresses. by the Engineer. Dimensional variations shall not exceed
Members shall be lifted or supported only at the points the following tolerances:
specified and shall be handled and placed without impact. - Length ± 12 mm
3 Tolerance in Precast Members: - Width ± 10 mm
i. Dimensional variations shall not exceed the - Thickness ± 6 mm
tolerances given below:
- Levels + 10 mm or -0 mm
- Length ±12 mm
- Void Location 6 mm in any direction
- Width and depth ± 6 mm
- Cover to reinforcement + 5 mm or -0 mm
- Bow in the vertical plane +15 mm or -0 mm
- Prestressing tendons 5 mm in any direction
- Bow in the horizontal plane ±12 mm
- Difference between longest and 5.5.4 Method of Measurement, Basis of
shortest dimensions (check for Payment and Items in the Bills of
squareness of beam) in any plane 6 mm Quantities
- Twist (measured by the deviation
1 Concrete bridge construction is measured and
of any corner from the plane
identified in the Bill of Quantities in accordance with

♦ 5-43 ♦
Clause 5.1.7. Measurement and basis of payment will be in 2 Finishes to floors and walls, including tiles, plaster
accordance with the stipulations for the corresponding paint and special finishes shall be as described in the
items in Sub-sections 5.1, 5.2 and 5.4. No direct payment Special Specification.
will be made for the stipulations of this Sub-section 5.5,
which work is considered to be subsidiary to the 5.6.3 Construction Requirements
requirements of Sub-sections 5.1, 5.2 and 5.4. The rates
and prices for the relevant items of Sub-sections 5.1, 5.2 5.6.3.1 Excavation
and 5.4 shall be deemed to include for all the stipulations
1 The Contractor shall provide the Engineer with
of this Sub-section 5.5. detailed written proposals of construction methods of
temporary and permanent works for the underpass
5.6 Vehicular and Pedestrian excavation. Details of ground water lowering, excavation
Underpasses and Animal support and support of adjacent existing structures shall
Crossings be accompanied by relevant shop drawings and
calculations. The work shall not proceed until the
Engineer has given approval to these construction
5.6.1 Description
proposals together with the relevant construction program
5.6.1.1 Scope for these works. Such approval, when given, shall not
relieve the Contractor of his responsibility for the
1 This Sub-section specifies the requirements for
correctness, safety and adequacy of such proposal.
concrete underpasses and animal crossings. These
2 Excavation and earthwork shall comply with the
requirements are additional to the requirements for
requirements of Section 2.
concrete generally, as described in the preceding Sub-
sections of this Section. 3 The Contractor shall comply with arrangements to
maintain the flow of pedestrian and vehicular traffic as
5.6.1.2 References stated in Section 1 of the Specification and as detailed on
the Drawings or as instructed by the Engineer. The
1 The relevant stipulations of the following Sections or
Contractor's attention is specifically drawn to his
Sub-sections of this Specification shall apply to this Sub-
responsibilities regarding the safety of such traffic near to
section.
open excavations for the works and the operation of heavy
Section 2 Earthworks plant and equipment and the provision and maintenance
Section 5 Concrete and Concrete Structures of adequate fences and barriers.
Section 6 Structural Steel and Other Metalwork 4 The Contractor shall protect and support existing
Section 8 Drainage statutory services during the excavation works as stated in
Section 1 and Section 18 of the Specification and co-
Section 10 Piling
operate with all statutory services to ensure efficiency of
Section 12 Sidewalks, Paved Areas and Curbs diversion of such services where necessary. In the event
Section 15 Road Lighting and Electrical that services are uncovered during excavation that have
Installations not been previously located on Drawings, the Engineer's
attention shall be drawn to the matter without delay.
5.6.2 Materials 5 Particular care shall be taken by the Contractor to
1 Materials shall conform to the relevant requirements minimize noise, dust and vibration caused by excavation
of the following Sections and Sub-sections of the operations especially where such nuisances prove
Specification: hazardous to existing structures.

Piles Section 10 6 Where ground water lowering operations prove


necessary the phasing of pumping operations and their
Concrete Sub-section 5.1
termination on completion of the underpass structure
Reinforcing Steel Sub-section 5.2 shall be approved by the Engineer.
Structural Steel and Other Metal Section 6 7 Where the Drawings show the use of piles or
Backfilling Sub-section 2.7 diaphragm walls to support the underpass structure or
Road Pavement Sections 3, 4 retain the subsoil the Contractor shall submit to the
Engineer for his approval a detailed method statement
Concrete Pavement Sub-section 5.7
and work program for this work together with the names
Waterproofing Sub-section 5.10 of any specialist firms he intends to use for this work.
Pipe culverts Sub-section 8.1
Drainage Section 8
Sidewalks, Paved Areas Section 12
Electrical Installations Section 15

♦ 5-44 ♦
5.6.3.2 Structural Concrete 5.6.3.6 Bituminous Pavement Construction

1 The Contractor shall provide the Engineer with 1 Bituminous pavement construction shall be in
detailed written proposals for the formwork design of all accordance with all relevant requirements of Section 4
major parts of the underpass structure together with “Bituminous Pavement”.
proposals for transporting, placing and curing concrete 2 Drainage works shall be constructed in accordance
and sizes of pours. The works shall not proceed until the with all relevant requirements of Sub-Section 8.4
Engineer has given approval to these proposals; such “Drainage of Structures”.
approval when given shall not relieve the Contractor of his
responsibility for the efficacy of such proposals. 5.6.3.7 Electrical Works
2 The structural concrete work shall generally comply 1 The installation of lighting and electrical works for
with the relevant requirements of the following sections: shall be in accordance with details shown on the Drawings
Section 5.1 Concrete Materials and Mixes and the general requirements of Section 15 "Electrical
Section 5.2 Reinforcing Steel Installations".

Section 5.3 Reinforced Concrete Structures


5.6.4 Method of Measurement
Section 5.4 Prestressed Concrete Structures
1 Excavation, backfilling, piling, concrete,
5.6.3.3 Concrete Piles reinforcement, road pavement, sidewalks and paved areas,
drainage, ducts, waterproofing of concrete and electrical
1 The reinforced concrete construction of piling works
work shall be measured in accordance with the relevant
shown as the Drawings to support the underpass structure
Sections of this Specification.
or retain the subsoil shall comply with the relevant
requirements of Section 10. 2 Floor and wall finishes shall be measured in
accordance with the Special Specification for the
5.6.3.4 Waterproofing particular work.
1 The waterproofing of the underpass structure shall
be generally carried out in compliance with Section 5.10 5.6.5 Basis of Payment
"Waterproofing for Structures". 1 The amount of completed and accepted work,
2 Where membrane materials are specified on the measured as provided for above, will be paid for at the
Drawings for special use, such as P.V.C. membranes, the unit rates for the various items in the Bill of Quantities,
manufacturer's instructions for storage, handling and which rate shall be full compensation for supplying
installation of such membranes shall be strictly complied materials, transporting and placing, labor, equipment,
with. Where special details of junctions of such tools and other items necessary for the proper completion
membranes with walls and piles are necessary, drawings of the work.
shall be submitted to the Engineer for approval before
work commences. 5.6.6 Items in the Bill of Quantities
3 Tucks and seals for waterproofing shall be provided All work in underpasses and animal crossings is
at points of discontinuity such as edges, expansion joints separately identified in the Bill of Quantities and the
and rainwater drains. Sharp internal and external edges relevant items, as stated in the respective Sections of the
shall be chamfered with minimum 40mm x 40mm fillets. Specification are included.
The waterproofing membrane shall be protected from
damage during the execution of the work.
5.7 Cement Concrete Pavement
4 Where the Drawings show the use of waterstops in
concrete walls and slabs at construction joints and
5.7.1 Description
expansion joints the Contractor shall supply samples of
waterstop material for approval and provide details of 1 This Sub-section specifies the requirements for
waterstop assembly for approval. cement concrete pavement, with or without reinforcement,
5 The standard of acceptance of waterproofing shall be on a prepared base all as and where shown on the
that there shall be no damp patches or visible leaks on the Drawings. These requirements are additional to the
inside face of walls, roof or floor of the underpass requirements for concrete generally contained in the
structure. preceding Sub-sections of this Section

5.6.3.5 Concrete Pavement Construction 5.7.2 Materials


1 Concrete pavement construction shall be in 1 Cementitious Materials: Portland cement alone or in
accordance with all relevant requirements of Section 5.7 combination with one or more of blended hydraulic
“Concrete Pavement”. cement, expansive hydraulic cement, fly ash and other
pozzolans, ground granulated blast-furnace slag, and silica
fume.

♦ 5-45 ♦
2 Base Course: Cement treated base course or throughout the work, unless otherwise accepted by
aggregate base course placed beneath the concrete Engineer.
pavement. 2 Portland Cement: ASTM C 150, Type I. In particular
cases, where the design requires the use of Sulfate
5.7.2.1 Forms
Resistant Cement (SRC), the Contractor shall submit to the
1 Form Materials: Plywood, metal, metal-framed Engineer’s approval an SRC material complying with the
plywood, or other approved panel-type materials to requirements of ASTM C 150, Type II.
provide full-depth, continuous, straight, smooth exposed 3 Aggregate: ASTM C33 or BS EN 12620, shall consist
surfaces. Use flexible or curved forms for curves of a of crushed stone, crushed or uncrushed gravel, or natural
radius 30 m or less. sand. The aggregate shall be composed of sound, tough,
2 Form-Release Agent: Commercially formulated durable particles and shall meet the requirements for
form-release agent that will not bond with, stain, or deleterious substances given in ASTM C33 or BS EN 12620.
adversely affect concrete surfaces and will not impair The aggregate in any size group shall not contain more
subsequent treatment of concrete surfaces. than 8 percent by weight of flat or elongated pieces when
tested in accordance with ASTM D4791. A flat or
5.7.2.2 Steel Reinforcement elongated particle is one having a ratio between the
1 Reinforcement Bars: ASTM A 615, Grade 60, maximum and the minimum dimensions of a
deformed. circumscribing rectangular prism exceeding 5 to 1.
Uniformly graded, from a single source, with coarse
2 Plain Steel Wire: ASTM A 82, cold-drawn steel.
aggregate as follows:
3 Welded Deformed Steel Wire fabric: ASTM A497.
4 Fine Aggregate: Conform to the requirements of
4 Joint Dowel Bars: Plain steel bars, ASTM A 615, ASTM C33 (Table 5.7.2.1) or BS EN 12620.
Grade 60. Cut bars true to length with ends square and
free of burrs. Sieve Designation Percentage by Weight
5 Dowel Bars: High tensile plain steel bars conforming (square openings) Passing Sieves
to BS 4449, ASTM A615, ASTM A616, or ASTM A617, and 3/8 in (9.5 mm) 100
shall be free from burring or other deformation restricting No. 4 (4.75 mm) 95-100
slippage in the concrete. Before delivery to the
No. 8 (2.36 mm) 80-100
construction site, a minimum of two-thirds of the length of
each dowel bar shall be painted with one coat of zinc- No. 16 (1.18 mm) 50- 85
chromate. If plastic or epoxy-coated steel dowels are used, No. 30 (600 micro-m) 25- 60
no zinc-chromate coating is required, except when No. 50 (300 micro-m) 10- 30
specified for a particular situation on the contract plans. No. 100 (150 micro-m) 2- 10
Coated dowels shall conform to the requirements given in
No. 200 (75 micro-m) 0- 3
AASHTO M254.
6 Tie Bars: ASTM A 615M, Grade 60, deformed. Table 5.7.2.1: Gradation for Fine Aggregate ASTM C33

7 Sleeves: Metal, of an approved design to cover 50 1 Coarse Aggregate: Conform to the requirements of
mm to 75 mm of the dowel, with a closed end and with a ASTM C33 (Table 5.7.2.2) or BS EN 12620.
suitable stop to hold the end of the bar at least 25 mm
from the closed end of the sleeve. Sleeves shall be of Sieve Designation Percentage by Weight
such design that they will not collapse during construction. (square openings) Passing Sieves
in (mm) 19 mm – 2.36 mm
8 Hook Bolts: ASTM F 568M, Property Class 4.6,
internally and externally threaded. Design hook-bolt joint 1 (25) 100
assembly to hold coupling against pavement form and in 3/4 (19) 90 - 100
position during concreting operations, and to permit
1/2 (12.5) -
removal without damage to concrete or hook bolt.
3/8 (9.5) 20 - 55
9 Bar Supports: Bolsters, chairs, spacers, and other
devices for spacing, supporting, and fastening No. 4 (4.75) 0 – 10
reinforcement bars, welded wire fabric, and dowels in
No. 8 (2.36) 0–5
place. Use wire bar type supports complying to CRSI's
"Manual of Standard Practice". Table 5.7.2.2: Gradation for Coarse Aggregate ASTM C33
10 Epoxy Repair Coating: Liquid two-part epoxy repair The percentage of wear shall be no more than 30% when
coating, compatible with epoxy coating on reinforcement. tested in accordance with ASTM C131.

5.7.2.3 Concrete Materials 6 Water: Water used in mixing or curing shall be as


clean and free of oil, salt, acid, alkali, sugar, vegetable, or
1 General: Use the same brand and type of other substances injurious to the finished product as
cementitious material from the same manufacturer possible. Water will be tested in accordance with the

♦ 5-46 ♦
requirements of AASHTOT26, ASTM C94. Water known to cellulosic fiber, or ASTM D 1752 for cork or self-expanding
be of potable quality may be used without testing. cork.
2 Joint filler shall be furnished in a single piece for the
5.7.2.4 Admixtures
full depth and width required for the joint, unless
1 General: Admixtures certified by manufacturer to otherwise specified by Engineer. When the use of more
contain not more than 0.1 percent water-soluble chloride than one piece is authorized for a joint, the abutting ends
ions by mass of cement and to be compatible with other shall be fastened securely and held accurately to shape by
admixtures. stapling or other positive fastening means satisfactory to
2 Approval Process: The use of any material added to Engineer.
the concrete mix shall be approved by Engineer. Submit 3 Joint sealer shall: meet the requirements of Sub-
certificates indicating that the material to be furnished section 5.8 of the Specification and shall be of the type(s)
meets all of the requirements indicated below. In addition, specified on drawings.
the Engineer may require the submittal of complete test 4 Dowels: Galvanized steel, to the dimensions shown
data from an approved laboratory showing that the on drawings.
material to be furnished meets all of the requirements of
5 Bonding Agent: ASTM C 1059, Type II, non-re-
the cited specifications. Subsequent tests will be made of
dispersible, acrylic emulsion or styrene butadiene.
samples taken by Engineer from the supply of the material
being furnished or proposed for use on the work to 5.7.2.7 Concrete Mixes
determine whether the admixture is uniform in quality
with that approved. 1 Prepare design mixes, proportioned according to ACI
211.1 and ACI 301, for each type and strength of normal-
3 Chemical Admixtures: Water reducing, set-retarding,
weight concrete determined by either laboratory trial
and set-accelerating admixtures shall meet the
mixes or field experience.
requirements of ASTM C494.
2 Use a qualified independent testing agency for
i. Water-Reducing Admixture: ASTM C 494,
preparing and reporting proposed mix designs for the trial
Type A. batch method. Do not use Employer’s field quality-control
ii. High-Range, Water-Reducing Admixture: testing agency as the independent testing agency.
ASTM C 494, Type F. 3 Proportion mixes to provide concrete with the
iii. Water-Reducing and Accelerating Admixture: following properties using test specimens prepared in
ASTM C 494, Type E. accordance with ASTM C31 and tested with ASTM C78:
iv. Water-Reducing and Retarding Admixture: i. Flexural Strength (28 Days): 4.6 MPa
ASTM C 494, Type D. ii. Compressive Strength (28 Days): 35 MPA.
5.7.2.5 Curing Materials iii. The minimum cementitious material content
shall be 300 kg. per cubic meter. The ratio of
1 Absorptive Cover: AASHTO M 182, Class 2, burlap water to cementitious material, including free
cloth made from jute or kenaf, weighing approximately. surface moisture on the aggregates but not
305 g/sq.m. dry. including moisture absorbed by the aggregates
2 Moisture-Retaining Cover: ASTM C 171, shall not be more than 0.50 by weight.
polyethylene film or white burlap-polyethylene sheet. 4 Slump Limit:
3 Water: Potable. i. The mix determined shall be workable concrete
4 Evaporation Retarder: Waterborne, monomolecular having a slump for side-form concrete between
film forming, manufactured for application to fresh 25 mm and 50 mm as determined by ASTM
concrete. C143.
5 Clear Solvent-Borne Liquid-Membrane-Forming ii. Slump Limit for Concrete Containing High-
Curing Compound: ASTM C 309, Type 1, Class B. Range Water-Reducing Admixture: Not more
6 Clear Waterborne Membrane-Forming Curing than 200 mm after adding admixture to plant-
Compound: ASTM C 309, Type 1, Class B. or site-verified, 50- to 75-mm slump.

7 White Waterborne Membrane-Forming Curing iii. Absorption and permeability tests on hardened
Compound: ASTM C 309, Type 2, Class B. concrete shall be carried out in accordance
with ASTM C642.
5.7.2.6 Related Materials 5 Chemical Admixtures: Water-reducing and set-
1 Pre-molded joint filler shall conform to the controlling admixtures shall be added to the mix in the
requirements of ASTM D1751 and shall be punched to manner recommended by the manufacturer and in the
admit the dowels where called for on the plans. amount necessary to comply with the specification
Expansion and isolation joint-filler strips shall conform to requirements. Tests shall be conducted on trial mixes,
the requirements of ASTM D 1751 for asphalt-saturated during the mix design, in accordance with ASTM C494.

♦ 5-47 ♦
6 Slip-form Construction: A high degree of uniformity iii. An overload up to 10 percent above the mixer's
in the plastic concrete is required. Some edge slump of nominal capacity may be permitted provided
the wet concrete behind the side form on the paving concrete test data for segregation and uniform
machine will occur, even with low slump concrete. This consistency are satisfactory, and provided no
may continue, though very slowly, until initial set has spillage of concrete takes place.
taken place. 5 Batch: Constituents shall be charged into the drum so
that a portion of the mixing water enters in advance of the
5.7.2.8 Concrete Mixing
cement and aggregates. The flow of water shall be
1 Ready-Mixed Concrete: Comply with requirements uniform, and all water shall be in the drum by the end of
and with ASTM C 94 and ASTM C 1116. Discharge of the the first 15 seconds of the mixing period. The throat of the
concrete shall be completed within a maximum of 1½ drum shall be kept free of such accumulations as may
hours, or before the drum has revolved 300 revolutions, restrict the free flow of materials into the drum.
whichever comes first. Mixing time shall be measured 6 Mixed Concrete:
from the time all materials, except water, are emptied into
i. Central mixing plant concrete shall be
the drum. However, when air temperature is between 30
transported in truck mixers, truck agitators, or
deg. C and 32 deg. C, reduce mixing and delivery time
non- agitating trucks. Non-agitating trucks are
from 1½ hours to 75 minutes; and when air temperature is
allowed to be used only when the location of
above 32 deg. C, reduce mixing and delivery time to 60
the mixing plant is very close to the site and to
minutes.
the approval of the Engineer.
i. The minimum required revolutions of the
ii. The time elapsing from the time water is added
mixing speed for transit mixed concrete may
to the mix until the concrete is deposited in
be reduced to not less than that recommended
place at the work site shall not exceed 30
by the mixer manufacturer.
minutes when the concrete is hauled in non-
ii. The number of revolutions recommended by agitating trucks, nor 45 minutes when the
the mixer manufacturer shall be indicated on concrete is hauled in truck mixers or truck
the manufacturer's serial plate attached to the agitators. All these operations must be
mixer. performed within 45 minutes after the initial
2 Concrete: mixing operations and the water-cement ratio
i. Concrete may be mixed at the work site must not be exceeded.
location in a central mix plant approved by the iii. Admixtures for increasing the workability or for
Engineer and shall be transported in truck accelerating the set will be permitted only
mixers. The mixer shall be of an approved when specified for in the contract.
type and capacity.
5.7.2.9 Limitations of Mixing:
ii. Furnish test data acceptable to Engineer
verifying that the model of the mixer will 1 No concrete shall be mixed, placed, or finished when
produce uniform concrete conforming to the the natural light is insufficient, unless an adequate and
provisions of ASTM C 94 at the reduced approved artificial lighting system is operated.
number of revolutions shown on the serial 2 During periods of hot weather when the maximum
plate. daily air temperature exceeds 30 deg. C, the following
3 When mixed at the work site or in a central mixing precautions shall be taken: the forms and/or the
plant, the mixing time shall not be less than 50 seconds underlying material shall be sprinkled with water
nor more than 90 seconds. Mixing time ends when the immediately before placing the concrete. The concrete
discharge chute opens. Transfer time in multiple drum shall be placed at the coolest temperature practicable, and
mixers is included in mixing time. The contents of an in no case shall the temperature of the concrete when
individual mixer drum shall be removed before a placed exceed 32 deg, C. The aggregates and/or mixing
succeeding batch is emptied therein. water shall be cooled as necessary to maintain the
4 Mixer: concrete temperature at or not more than the specified
max. Refer to ACI 305 R-77 for Hot Weather Concreting.
i. The mixer shall be operated at the drum speed
recommended by the manufacturer as stated
nameplate on the mixer. Any concrete mixed
5.7.3 Construction Requirements
less than the specified time shall be discarded 5.7.3.1 Preparation
at Contractor’s own expense.
1 Proceed with pavement layers only after
ii. The volume of concrete mixed per batch shall
nonconforming conditions have been corrected and
not exceed the mixer's nominal capacity, as
subgrade is ready to receive pavement.
shown on the manufacturer's standard rating
plate on the mixer. 2 Remove loose material from compacted sub-base
surface immediately before placing concrete.

♦ 5-48 ♦
5.7.3.2 Edge Forms and Screed Construction matter that may adversely affect or reduce
bond. Reinforcing steel with rust, mill scale, or
1 Set, brace, and secure edge forms, bulkheads, and
a combination of both will be considered
intermediate screed guides for paving to required lines, satisfactory, provided the minimum
grades, and elevations. Install forms to allow continuous
dimensions, weight, and tensile properties of a
progress of work and so that forms can remain in place at
hand wire-brushed test specimen are not less
least 24 hours after concrete placement. than the applicable ASTM specification
2 Forms shall be securely set so that they can requirements.
withstand impacts and vibration of consolidating and ii. Accurately position, support, and secure
finishing equipment without visible spring or settlement.
reinforcement against displacement by
Extend flange braces on the base outward for not less
formwork, construction, or concrete placement
than two thirds of the height of the form. Remove bent, operations. Locate and support reinforcing
twisted or broken forms, and forms with damaged top
bars by metal chairs, runners, bolsters, spacers,
surfaces. Use repaired forms only with inspection and
and hangers, as required.
approval. Built-up forms will not be allowed, unless
iii. Arrange, space, and securely tie bars and bar
specifically approved. The top faces of forms are not to
supports to hold reinforcement in position
vary from a true plane by more than 3 mm in 3m. The
during concrete placement operations. Set wire
upstanding leg shall be perpendicular to the base and is
ties so ends are directed into concrete, not
not to vary horizontally from true alignment by more than
toward exposed concrete surfaces.
6 mm at any point. The ends of abutting sections lock
together tightly for secure setting. Local defects, such as iv. Install welded wire fabric in as long lengths as
kinks in steel forms, will not be allowed. practicable. Lap adjoining pieces at least one
full mesh and lace splices with wire. Offset end
3 Setting: Forms shall be set ahead of concrete
laps in adjacent widths to prevent continuous
placement and staked into place with at least three pins
laps in either direction.
for each 3 m section. A pin shall be placed at each side of
every joint. Form sections shall be tightly locked and free 5.7.3.5 Joints
from movement in any direction. Excessive settlement or
springing from operation of the finishing machine will not 1 General: Form construction, expansion, and
be allowed. Forms shall be cleaned and oiled before contraction joints and tool edgings true to line with faces
concrete placement. The alignment and grade elevations perpendicular to surface plane of concrete. Construct
of the forms shall be checked, and corrections made transverse joints at right angles to centerline, unless
immediately before placing concrete. Reset and recheck otherwise indicated. When joining existing pavement,
forms when they have been disturbed, or when the grade place transverse joints to align with previously placed
has become unstable. joints, unless otherwise indicated.
4 Clean forms after each use and coat with form 2 Construction Joints: Set construction joints at side
release agent as required, to ensure separation from and end terminations of pavement and at locations where
concrete without damage. pavement operations are stopped for more than one-half
5 Removal: Do not remove forms until the concrete hour, unless pavement terminates at isolation joints.
has set for at least 12 hours, unless otherwise approved or 3 Expansion Joints: Form expansion joints of
where auxiliary forms are used temporarily in widened preformed joint-filler strips abutting concrete curbs, catch
areas. Remove forms carefully to avoid damaging the basins, manholes, inlets, structures, walks, other fixed
pavement, and after removal, the side of the slab shall be objects, and where indicated.
cured by the method specified in the current specification. i. Locate expansion joints at intervals indicated
on drawings.
5.7.3.3 Steel Reinforcement
ii. Extend joint fillers full width and depth of joint.
1 General: Comply with CRSI's ‘Manual of Standard
iii. Terminate joint filler not less than 12 mm or
Practice’ for fabricating reinforcement and with
more than 25 mm below finished surface if
recommendations in CRSI's "Placing Reinforcing Bars" for
joint sealant is required.
placing and supporting reinforcement.
iv. Place top of joint filler flush with finished
5.7.3.4 Placement of Reinforcement concrete surface if joint sealant is not indicated.

1 Reinforced Concrete Pavement: Comply with v. Furnish joint fillers in one-piece lengths.
Concrete Reinforcing Steel Institute's recommended Where more than one length is required, lace
practice for ‘Placing Reinforcing Bars’, for details and or clip joint-filler sections together.
methods of reinforcement placement and supports, and as vi. Protect top edge of joint filler during concrete
herein specified: placement with metal, plastic, or other
i. At the time concrete is placed the reinforcing temporary preformed cap. Remove protective
bars shall be free of mud, oil or other organic

♦ 5-49 ♦
cap after concrete has been placed on both 7 Dowel Bars: Dowel bars or other load-transfer units
sides of joint. of an approved type shall be placed across transverse or
4 Longitudinal and Transverse Joints: Construct as other joints in the manner as specified on the Drawings.
indicated on the Drawings and in accordance with the i. They shall be of the dimensions and spacing as
following requirements: shown and held rigidly in the middle of the
i. All joints shall be constructed true to line with slab depth in the proper horizontal and vertical
their faces perpendicular to the surface of the alignment by an approved assembly device left
pavement. permanently in place.

ii. Joints shall not vary more than 12mm from a ii. The dowel or load-transfer and joint devices
true line or from their designated position. shall be rigid enough to permit complete
assembly as a unit ready to be lifted and placed
iii. The vertical surface of the pavement adjacent
into position.
to all expansion joints shall be finished to a
true plane and edged to a radius of 6mm or as iii. A metal, or other type dowel expansion cap or
shown on the plans. sleeve shall be furnished for each dowel bar
used with expansion joints.
iv. The surface across the joints shall be tested
with a 3m straightedge as the joints are iv. These caps shall be substantial enough to
finished and any irregularities in excess of prevent collapse and shall be placed on the
6mm shall be corrected before the concrete has ends of the dowels as shown on the Drawings.
hardened. v. The caps or sleeves shall fit the dowel bar
v. Transverse joints shall be at right angles to the tightly and the closed end shall be watertight.
centerline of the pavement and shall extend the 8 Fix dowel bars and support assemblies at joints
full width of the slab. where indicated. Lubricate or asphalt-coat one-half of
vi. The transverse joints in succeeding lanes shall dowel length to prevent concrete bonding to one side of
be placed in line with similar joints in the first joint.
lane. All joints shall be so prepared, finished, 9 Joints Installation:
or cut to provide a groove of the width and i. The top of an assembled joint device shall be
depth shown on the plans. set at the proper distance below the pavement
5 Slip-Form Construction: Transverse joints with surface and the elevation shall be checked.
dowels shall be carefully placed to ensure the dowels are Such devices shall be set to the required
accurately placed and not disturbed during concrete position and line and shall be securely held in
placement. place by stakes or other means during the
i. Transverse dowels will require use of an pouring and finishing of the concrete. The pre-
apparatus to firmly hold the dowels molded joint material shall be placed and held
perpendicular to the joint and parallel to the in a vertical position; if constructed in sections,
slab surface. there shall be no offsets between adjacent
units. Dowel bars shall be checked for exact
ii. During the concrete placement operation, it is
position and alignment as soon as the joint
advisable to place plastic concrete directly on
device is staked in place, and the device shall
the dowel assembly immediately prior to
be tested to determine whether it is firmly
passage of the paver to help maintaining dowel
supported. The maximum permissible
alignment.
tolerance on dowel bar alignment in each plane,
6 Tie Bars: Deformed bars shall be fixed in longitudinal horizontal and vertical, shall not exceed 2
joints as shown on the Drawings. percent or 6mm per 300 mm of a dowel bar.
i. Tie bars shall be placed at right angles to the The most effective way to obtain proper
centerline of the concrete slab and shall be alignment is with well-fabricated dowel baskets
spaced at intervals shown on Drawings. and dowel assemblies.
ii. Tie bars shall be held in position parallel to the ii. When joints in concrete pavements are sawed,
pavement surface and midway between the the joints shall be cut as shown on the
surfaces of the slab. Drawings. The circular cutter shall be capable
iii. When tie bars extend into an unpaved lane, of cutting a groove in a straight line and shall
they may be bent at right angles against the produce a slot at least 3mm wide and to the
form at longitudinal construction joints, unless depth shown on the plans. When shown on the
threaded bolt or other assembled tie bars are plans or required by the specifications, the top
specified. portion of the slot groove shall be widened by
means of a second shallower cut or by suitable
iv. Tie bars shall not be painted, greased, or
and approved beveling to provide adequate
enclosed in sleeves.
space for joint sealers. Sawing of the joints

♦ 5-50 ♦
shall commence as soon as the concrete has material is used, the installation and edge
hardened sufficiently to permit cutting without finish shall be according to the manufacturer's
chipping, spalling, or tearing. Sawing shall be instructions. The sawed groove shall be
carried on both during the day and night as straight and of uniform width and depth. In
required. The joints shall be sawed at the either case, the groove shall be clean cut so
required spacing consecutively in sequence of that spalling will be avoided at intersections
the concrete placement, unless otherwise with transverse joints. Tie bars shall be
approved by Engineer. installed across these joints where indicated on
10 Contraction Joints: Form weakened-plane the plans.
contraction joints, sectioning concrete into areas as iii. Expansion type: longitudinal joints shall be
indicated. Construct contraction joints for a depth equal to informed as indicated on the Drawings. The
at least one-fourth of the concrete thickness, as follows: pre-molded filler, of the thickness shown shall
i. Grooved Joints: Form contraction joints after extend for the full depth and width of the slab
initial floating by grooving and finishing each at the joint, except for space for sealant at the
edge of joint with groover tool to the radius top of the slab. The filler shall be securely
shown on drawings. Repeat grooving of staked or fastened into position perpendicular
contraction joints after applying surface to the proposed finished surface. A metal cap
finishes. Eliminate groover marks on concrete shall be provided to protect the top edge of the
surfaces. filler and to permit the concrete to be placed
and finished. After the concrete has been
ii. Sawed Joints: Form contraction joints with
placed and struck off, the cap shall be carefully
power saws equipped with shatterproof
withdrawn leaving the space over the pre-
abrasive or diamond-rimmed blades. Cut
molded filler. The edge of the joint shall be
joints into concrete to the width shown on
finished and tooled while the concrete is still
drawings, when cutting action will not tear,
plastic.
abrade, or otherwise damage surface and
before developing random contraction cracks. 12 Transverse Joints:

11 Longitudinal Joints: i. Expansion Type:

i. Construction type: longitudinal construction - Transverse expansion joints shall be


joints necessary for lane construction shall be installed at the locations and spacing as
formed against suitable side forms as indicated shown on the plans. The joints shall be
in the plans. Wooden forms may be used installed at right angles to the centerline
under special conditions, when approved by and perpendicular to the surface of the
Engineer. Where butt-type joints with dowels pavement. The joints shall be formed and
are designated, the dowels for this type shall finished to ensure complete separation of
be painted and greased. The edges of the joint the slabs. Joint filler shall be of a pre-
shall be finished with a grooving tool or edging molded type as specified and shown on the
tool, and a space or slot shall be formed along Drawings and shall extend the full width of
the joint of the dimensions, as indicated, to the pavement strip.
receive the joint sealing material. Longitudinal - All concrete shall be cleaned from the top
construction joints shall be sawed to provide a of the joint material. Before the pavement
groove at the top conforming to the details and is opened to traffic, it shall be swept clean
dimensions indicated on the plans. Provisions and filled with approved joint sealing
shall be made for the installation of tie bars as material.
noted on the plans. - All devices used for the fixing expansion
ii. Contraction or weakened - plane type: joints shall be approved by the Engineer.
longitudinal groove-formed or sawed joints in They shall be easily removable without
the top of the slab shall be formed where disturbing the concrete and held in proper
indicated on the Drawings. The groove shall transverse and vertical alignment.
be formed in the plastic concrete with suitable Immediately after forms are removed, any
tools or material to obtain the width and depth concrete bridging the joint space at the
specified, or it shall be sawed with approved ends shall be removed for the full width
equipment in the hardened concrete to the and depth of the joint.
dimensions required. When the groove is - When specified, expansion joints shall be
formed in plastic concrete, it shall be true to equipped with dowels of the dimensions
line with not more than 6mm variation in 3m; it and at the spacing and location indicated
shall be uniform in width and depth; and the on the Drawings. The dowels shall be
sides of the groove shall be finished even and firmly supported in place and accurately
smooth with an edging tool. If an insert aligned parallel to the subgrade and the

♦ 5-51 ♦
centerline of the pavement by means of a 2 If damage occurs to the base course, it shall be relaid
dowel assembly, which will remain in the for the full depth, or the damaged areas filled with
pavement and will ensure that the dowels concrete integral with the pavement.
are not displaced during construction. 3 A multiple-pin template weighing not less than 454
ii. Transverse contraction joints, weakened-plane kg. per 6 m or other approved template shall be provided
joints, or both, shall be formed at the locations and operated on the forms immediately in advance of the
and spacing as shown on the Drawings by placing of the concrete. The template shall be propelled
forming a groove or cleft in the top of the slab only by hand and not attached to a tractor or other power
while the concrete is still plastic or by sawing a unit. Templates shall be adjustable so that they may be
groove into the concrete surface after the set and maintained at the correct contour of the
concrete has hardened in the same manner as underlying course. The adjustment and operation of the
specified. Dowel bar assemblies shall be template shall be such as to provide an accurate re-test of
installed as shown on the Drawings. the grade before placing the concrete thereon. All excess
iii. Transverse construction joints shall be formed material shall be removed. Low areas may be filled with
at the end of each day's placing operations and concrete integral with the pavement.
at any other points within a paving lane when
5.7.3.8 Handling, Measuring, and Batching Material
concrete placement is interrupted for more
than 30 minutes or it appears that the concrete 1 Batch plant site: layout, equipment, and provisions
will obtain its initial set before fresh concrete is for transporting material shall assure a continuous supply
placed. Construction joints planned in advance of material to the work.
shall be located at a contraction or expansion 2 Stockpiles: Build up stockpiles in layers of not more
joint where possible but they shall not be than 900 mm in thickness. Each layer shall be completely
located within 2500 mm of a regular spaced in place before beginning the next layer and shall not be
transverse joint. If the pouring of the concrete allowed to "cone" down over the next lower layer.
is stopped, causing a joint to fall within this Aggregates from different sources and of different grading
limit, it shall not be formed, and the fresh shall not be stockpiled together. Improperly placed
placed concrete shall be removed back to the stockpiles will not be accepted by Engineer.
2500 mm limit.
3 Aggregates: Handle from stockpiles or other sources
13 Edging: Tool edges of pavement, gutters, curbs, and to the batching plant in such manner to secure the
joints in concrete after initial floating with an edging tool specified grading of the material. Aggregates that have
to the radius shown on drawings. Repeat tooling of edges become segregated or mixed with earth or foreign
after applying surface finishes. Eliminate tool marks on material shall not be used. All aggregates produced or
concrete surfaces. handled by hydraulic methods, and washed aggregates,
shall be stockpiled or binned for draining at least 12 hours
5.7.3.6 Conditioning of Underlying Course, Slip-Form
before being batched.
Construction
4 Cement: Store in weather tight structures with raised
1 The base course on which the pavement will be floors or in suitable silos. Different consignments of
placed shall extend approximately 900 mm beyond the bagged cement shall be used separately and in the order
paving machine track, or wider if required, to support the of delivery. Cement manufactured more than twelve
paver without any noticeable deformation. months prior to proposed use on site shall not be used. If
2 If damage occurs to the base course, it shall be relaid cement becomes partially set or contains lumps of caked
for the full depth or the damaged areas filled with concrete cement, it shall be rejected. Cement salvaged from
integral with the pavement. If traffic is allowed to use the discarded or used bags shall not be used.
prepared grade, the grade shall be checked and corrected 5 Aggregate: Fine and coarse aggregate shall be
immediately before the placement of concrete. separately weighed into hoppers in the respective
3 The prepared grade shall be well moistened with amounts approved by Engineer in the job mix. Cement
water, without saturating, immediately ahead of concrete shall be measured by weight. Separate scales and hopper,
placement to prevent rapid loss of moisture from concrete. with a device to positively indicate the complete discharge
of the batch of cement into the batch box or container,
5.7.3.7 Conditioning of Underlying Course, Side-Form shall be used for weighing the cement.
Construction 6 When required by the contract or when permitted,
batching plants shall be equipped to proportion
1 The prepared grade shall be well moistened with
aggregates and bulk cement, by weight, automatically
water, without saturating, immediately ahead of concrete
using interlocked proportioning devices of an approved
placement to prevent rapid loss of moisture from the
type.
concrete.
7 Water shall be measured either by volume or by
weight accurately measured to within plus or minus 1

♦ 5-52 ♦
percent of required amounts. Unless the water is to be application of curing compound by hand-operated
weighed, the water-measuring equipment shall include an pressure sprayers will be permitted only on small widths
auxiliary tank from which the measuring tank shall be or shapes of slabs as approved, and on concrete surfaces
filled. The measuring tank shall be equipped with an exposed by removal of forms. When application is made
outside tap and valve to provide for checking the setting, by hand-operated sprayer, apply the second coat in a
unless other means are provided for readily and direction approximately at right angles to the direction of
accurately determining the amount of water in the tank. the first coat. The compound shall form a uniform,
The volume of the auxiliary tank shall be at least equal to continuous, cohesive film that will not check, crack or peel,
that of the measuring tank and is free of pinholes and other discontinuities. Apply an
8 Methods and equipment for adding air-entraining additional coat, if pinholes, abrasions or other
agent or other admixtures to the batch, when required, discontinuities exist, to the affected areas within 30
shall be approved by Engineer. All admixtures shall be minutes. Re-spray concrete surfaces that are subjected to
measured into the mixer with an accuracy of plus or heavy rainfall or abrasive wind-blown sand within three
minus 3 percent. hours after the curing compound has been applied. Re-
spray areas where the curing membrane is damaged by
5.7.3.9 Concrete Protection and Curing subsequent construction operations within the curing
period.
1 General: Protect concrete against loss of moisture
and rapid temperature changes for at least seven days i. Precautions shall be taken to ensure that
from beginning of the curing operation. Unhardened concrete is properly cured at sawed joints, but
concrete shall be protected from rain and flowing water. that no curing compound enters the joints.
All equipment needed for adequate curing and protection Tightly seal top of joint opening and joint
of the concrete shall be on hand, ready to use before groove at exposed edges before concrete
concrete placement begins. A standby water truck adjacent to the joint is re-sprayed. Seal joint
capable of dispensing a fine spray of water shall be groove by using method that will prevent loss
continuously available during paving operations to keep of moisture from the joint during the specified
the concrete moist until the curing compound has been curing period.
applied. Provide protection as necessary to prevent ii. Provide approved standby facilities for curing
cracking of the pavement due to temperature changes concrete pavement at an accessible location at
during the curing period. the jobsite for use in the event of failure of the
2 Membrane Curing: Apply a uniform coating of white spraying equipment, or other conditions that
pigmented-type membrane curing compound to the entire might prevent correct application of curing
exposed surface of the concrete by means of an approved compound at the proper time.
automatic spraying machine as soon as free water has iii. Protect concrete surfaces to which curing
disappeared from the finished surface. Coat formed compounds have been applied from pedestrian
surfaces immediately after the forms are removed and in and vehicular traffic and from any other
no case longer than one hour after removal of forms. Do possible damage to the continuity of the
not allow concrete to dry before application of the membrane, during the curing period except as
membrane. If any drying has occurred, moisten the required for joint-sawing operations and
surface of the concrete with a fine spray of water and surface testing.
apply curing compound as soon as the free water 3 Protection: Protect pavement and its appurtenances
disappears. The spraying machine shall be self-propelled from damage caused by traffic. The Engineer will decide
and shall ride on the side forms, or previously constructed when the pavement may be cleaned and opened to traffic,
pavement straddling the newly paved lane. The machine but not earlier than 14 days after concrete placing. Protect
shall have one or more spraying nozzles that can be freshly placed concrete from premature drying and
controlled and operated to completely and uniformly excessive cold or hot temperatures. Comply with the
cover the pavement surface with the required amount of recommendations of ACI 306R for cold weather protection
curing compound. The curing compound shall be and ACI 305R for hot weather protection during curing.
thoroughly and continuously mechanically agitated in the
drum used for the spraying operation throughout the full 5.7.3.10 Concrete Placement
depth of the drum during application. Air agitation may
1 Inspection: Before placing concrete, inspect and
be used only to supplement mechanical agitation. Provide
complete formwork installation, reinforcement steel, and
sufficient spraying pressure to produce a fine spray to
items to be embedded or cast in. Notify other trades to
cover the surface thoroughly and completely with a
permit installation of their work.
uniform film. Maintain spray equipment in good
mechanical condition, and provide adequate wind guard 2 Moisten subbase to provide a uniform dampened
to the spray nozzle. Apply curing compound with an condition at the time concrete is placed. Do not place
overlapping coverage that will give a two-coat application concrete around manholes or other structures until they
at a coverage rate of not more than 0.1 Liter per/sq.m. for are at the required finish elevation and alignment.
each coat or as recommended by the manufacturer. The

♦ 5-53 ♦
3 Comply with requirements and with joint assemblies by means of vibrators inserted
recommendations in ACI 304R for measuring, mixing, in the concrete. Vibrators shall not be
transporting, and placing concrete. permitted to come in contact with a joint
4 Do not add water to concrete during delivery, at Site, assembly, the grade, or a side form. In no case
or during placement. shall the vibrator be operated longer than 15
seconds in any one location, nor shall the
5 Deposit and spread concrete in a continuous
vibrators be used to move the concrete.
operation between transverse joints. Do not push or drag
concrete into place or use vibrators to move concrete into iv. Concrete shall be deposited as near to
place. expansion and contraction joints as possible
without disturbing them but shall not be
6 Consolidate concrete by mechanical vibrating
dumped from the discharge bucket or hopper
equipment supplemented by hand-spading, rodding, or
onto a joint assembly unless the hopper is well
tamping. Use equipment and procedures to consolidate
centered on the joint assembly.
concrete according to recommendations in ACI 309R.
Consolidate concrete along face of forms and adjacent to v. Should any concrete materials fall on or be
transverse joints with an internal vibrator. Keep vibrator worked into the surface of a completed slab,
away from joint assemblies, reinforcement, or side forms. they shall be removed immediately by
Use only square-faced shovels for hand-spreading and approved methods.
consolidation. Consolidate with care to prevent 10 Slip-Form Method:
dislocating reinforcement, dowels, and joint devices. i. The concrete shall be placed with an approved
7 Following the placing of the concrete, it shall be crawler-mounted, slip-form paver designed to
struck off to conform to the cross section shown on the spread, consolidate, and shape the freshly
Drawings and to level such that when the concrete is placed concrete in one complete pass of the
properly consolidated and finished, the surface of the machine so that a minimum of hand finishing
pavement shall be at the level shown on the Drawings. will be necessary to provide a dense and
8 Screed pavement surfaces with a straightedge and homogeneous pavement in conformance with
strike off. Commence initial floating using bull floats or requirements of the plans and specifications.
darbies to form an open textured and uniform surface The concrete should be placed directly on top
plane before excess moisture or bleed water appears on of the joint assemblies to prevent them from
the surface. Do not further disturb concrete surfaces moving when the paver moves over them. Side
before beginning finishing operations or spreading dry- forms and finishing screeds shall be adjustable
shake surface treatments. to the extent required to produce the specified
pavement edge and surface tolerance. The side
9 Side Form Method:
forms shall be of dimensions, shape, and
i. The concrete shall be deposited on the strength to support the concrete laterally for a
moistened grade to require as little re-handling sufficient length of time so that no appreciable
as possible. Unless truck mixers, truck agitators, edge slumping will occur. Final finishing shall
or non agitating hauling equipment are be accomplished while the concrete is still in
equipped with means for discharge of concrete the plastic state.
without segregation of the materials, the
ii. In the event that slumping or sloughing occurs
concrete shall be unloaded into an approved
behind the paver or if there are any other
spreading device and mechanically spread on
structural or surface defects, which, in the
the grade to prevent segregation of the
opinion of the Engineer, cannot be corrected
materials. Placing shall be continuous between
within permissible tolerances, the Engineer
transverse joints without the use of
may halt paving operations until proper
intermediate bulkheads. Necessary hand
adjustment of the equipment or procedures
spreading shall be done with shovels - not
have been made. In the event that satisfactory
rakes. Workmen shall not be allowed to walk in
pavement procedures are not achieved after
the freshly mixed concrete with boots or shoes
more than 600 m of single lane paving, the
coated with earth or foreign substances.
balance of the work shall be completed with
ii. When concrete is to be placed adjoining a the use of standard metal forms and the
previously constructed lane of pavement and formed method of placing and curing.
when mechanical equipment will be operated
11 Slip-Form Pavers: When automatic machine
upon the existing lane of pavement, the
placement is used for pavement, submit revised mix
concrete shall be at least 7 days old and at a
design and laboratory test results that meet or exceed
flexural strength approved by Engineer.
requirements. Produce pavement to required thickness,
iii. Concrete shall be thoroughly consolidated lines, grades, finish, and jointing as required for formed
against and along the faces of all forms and pavement. Compact subbase and prepare subgrade of
along the full length and on both sides of all

♦ 5-54 ♦
sufficient width to prevent displacement of paver machine 5.7.3.12 Final Strike-Off, Consolidation and Finishing
during operations.
1 Sequence: The sequence of operations shall be the
12 When adjoining pavement lanes are placed in
strike-off and consolidation, floating and removal of
separate pours, do not operate equipment on concrete
laitance, straight edging, and final surface finish. The
until pavement has attained 85 percent of its 28-day
addition of superficial water to the surface of the concrete
compressive strength.
to assist in finishing operations generally will not be
13 Hot-Weather Placement: Place concrete according to permitted. If the application of water to the surface is
recommendations in ACI 305R and as follows when hot- permitted, it shall be applied as a fog spray by means of
weather conditions exist: approved spray equipment.
i. Cool ingredients before mixing to maintain 2 Strike-Off of Concrete: Following the placing of the
concrete temperature at time of placement concrete, it shall be struck off to conform to the cross
below 32 deg. C. Chilled mixing water or section shown on the plans and to an elevation such that
chopped ice may be used to control when the concrete is properly consolidated and finished,
temperature, provided water equivalent of ice the surface of the pavement shall be at the elevation
is calculated to total amount of mixing water. shown on the plans.
Using liquid nitrogen to cool concrete is
3 Finishing at Joints:
Contractor's option.
i. Concrete adjacent to joints shall be compacted
ii. Cover reinforcement steel with water-soaked
or firmly placed without voids or segregation
burlap so steel temperature will not exceed
against the joint material; it shall be firmly
ambient air temperature immediately before
placed without voids or segregation under and
embedding in concrete.
around all load-transfer devices, joint assembly
iii. Fog-spray forms, reinforcement steel, and / or units, and other features designed to extend
stabilized base just before placing concrete. into the pavement.
Keep aggregate base moisture uniform without
ii. Concrete adjacent to joints shall be
standing water, soft spots, or dry areas.
mechanically vibrated. After the concrete has
iv. Concreting shall not be permitted when the been placed and vibrated adjacent to the joints,
rate of evaporation exceed 1.0 kg./sq.m./h. (ACI the finishing machine shall be operated in a
305R "Hot Weather Concreting"). The rate of manner to avoid damage or misalignment of
evaporation can be estimated from Fig. 2.1.5 of joints.
ACI 305R with the prevailing temperature,
iii. If uninterrupted operations of the finishing
relative humidity, and wind speed. The
machine, to, over, and beyond the joints, cause
evaporation rate can also be determined more
segregation of concrete, damage to, or
accurately by evaporating water from a cake
misalignment of the joints, the finishing
pan having an area of approximately 1 ft2
machine shall be stopped when the screed is
(0.093 sq.m.). The pan is filled with water and
approximately 200mm from the joint.
the mass determined every 15 to 20 min to
iv. Segregated concrete shall be removed from
determine .the evaporation rate, which is equal
the front of and off the joint, the screed shall be
to the loss of water mass from the pan. A
balance of at least 2500 g capacity is lifted and set directly on top of the joint, and
the forward motion of the finishing machine
satisfactory.
shall be resumed. Thereafter, the finishing
v. No concreting shall take place when the
machine may be run over the joint without
ambient temperature exceeds 40 deg. C.
lifting the screed, provided there is no
5.7.3.11 Concrete Finishing segregated concrete immediately between the
joint and the screed or on top of the joint.
1 General: Wetting of concrete surfaces during 4 Machine Finishing:
screeding, initial floating, or finishing operations is
i. The concrete shall be spread as soon as it is
prohibited.
placed, and it shall be struck off and screeded
2 Float Finish: Begin the second floating operation
by an approved finishing machine. The
when bleed-water sheen has disappeared and the machine shall go over each area as many times
concrete surface has stiffened sufficiently to permit
and at such intervals as necessary to give the
operations. Float surface with power-driven floats, or by
proper consolidation and to leave a surface of
hand floating if area is small or inaccessible to power units. uniform texture.
Finish surfaces to true planes. Cut down high spots, and
ii. Excessive operation over a given area shall be
fill low spots. Refloat surface immediately to uniform
avoided. When side forms are used, the tops
granular texture.
of the forms shall be kept clean by an effective
device attached to the machine, and the travel

♦ 5-55 ♦
of the machine on the forms shall be iii. Any depressions shall be immediately filled
maintained true without lift, wobbling, or other with freshly mixed concrete, struck off,
variation tending to affect the precision finish. consolidated, and refinished. High areas shall
During the first pass of the finishing machine, a be cut down and refinished.
uniform ridge of concrete shall be maintained iv. Special attention shall be given to assure that
ahead of the front screed for its entire length. the surface across joints meets the
iii. When in operation, the screed shall be moved requirements for smoothness. Straightedge
forward with a combined longitudinal and testing and surface corrections shall continue
transverse shearing motion, always moving in until the entire surface is found to be free from
the direction in which the work is progressing, observable departures from the straightedge
and so manipulated that neither end is raised and until the slab conforms to the required
from the side forms during the striking-off grade and cross section.
process. If necessary, this shall be repeated v. The use of long-handled wood floats shall be
until the surface is of uniform texture, true to confined to a minimum; they may be used only
grade and cross section, and free from porous in emergencies and in areas not accessible to
areas. finishing equipment.
5 Hand Finishing: Hand finishing methods will not be
permitted, except under the following conditions: 5.7.3.13 Surface Texture

i. In the event of breakdown of the mechanical 1 Brush or Broom Finish:


equipment, hand methods may be used to i. A brush or broom finish shall be formed on all
finish the concrete already deposited on the newly constructed concrete pavements when
grade; the water sheen has practically disappeared,
ii. In areas of narrow widths or of irregular using mechanical texturing equipment.
dimensions where operation of the mechanical ii. The equipment shall operate transversely
equipment is impractical. across the pavement surface, providing
Concrete, as soon as placed, shall be struck off and corrugations that are uniform in appearance
screeded. An approved portable screed shall be used. A and approximately 2 mm in depth.
second screed shall be provided for striking off the bottom iii. The equipment must not tear or unduly
layer of concrete when reinforcement is used. roughen the pavement surface during the
The screed for the surface shall be at least 600 mm longer operation. Any imperfections resulting from
than the maximum width of the slab to be struck off. It the texturing operation shall be corrected.
shall be of approved design, sufficiently rigid to retain its
shape, and shall be constructed either of metal or of other 5.7.3.14 Skid Resistant Surfaces
suitable material covered with metal. Consolidation shall 1 Wire Combing: A skid resistant surface shall be
be attained by the use of a suitable vibrator. provided by wire combing in plastic concrete. The wire
6 Floating: After the concrete has been struck off and combing technique shall use steel combs or tines of
consolidated, it shall be further smoothed, trued, and various dimensions to form groove-like texture in the
consolidated by means of a longitudinal float, using plastic concrete pavement and shall provide grooves that
approved hand or machine methods. are approximately 3 mm by 3 mm spaced 13 mm center-
7 Straight-Edge Testing and Surface Correction: to-center.

i. After the pavement has been struck off and 5.7.3.15 Surface Test
consolidated and while the concrete is still
plastic, it shall be tested for trueness with a 1 As soon as the concrete has hardened sufficiently,
4.8m straightedge. Furnish and use an the pavement surface shall be tested with a 4.8 m
accurate 4.8m straightedge swung from straightedge or other specified device. Areas in a slab
handles 900 mm longer than one-half the width showing high spots of more than 6 mm but not exceeding
of the slab. 12 mm in 4.8 m shall be marked and immediately ground
down with an approved grinding machine to l within the
ii. The straightedge shall be held in contact with
tolerance of 6 mm or less. Where the departure from
the surface in successive positions parallel to
correct cross section exceeds 12 mm, the pavement shall
the centerline and the whole area gone over
be removed and replaced when so directed by Engineer.
from one side of the slab to the other, as
necessary. Advancing shall be in successive 2 Any area or section so removed, shall not be less
stages of not more than one-half the length of than 3 m in length, nor less than the full width of the lane
the straightedge. Any excess water and involved. When it is necessary to remove and replace a
laitance shall be removed from the surface of section of pavement, any remaining portion of the slab
the pavement. adjacent to the joints that is less than 3 m in length shall
also be removed and replaced.

♦ 5-56 ♦
5.7.3.16 Removing Forms shall submit for the Engineer’s approval the appropriate
testing instrument(s) and test methodology for the surface
1 Unless otherwise specified, forms shall not be roughness test.
removed from freshly placed concrete until it has set for at
3 Tolerances. The following tolerances are applicable:
least 12 hours, except where auxiliary forms are used
temporarily in widened areas. Forms shall be removed i. Lateral deviation from established alignment of
carefully to avoid damage to the pavement. After the the pavement edge shall not exceed plus or
forms have been removed, the sides of the slab shall be minus 30 mm in any lane.
cured. Major honeycombed areas shall be considered as ii. Vertical deviation from established grade shall
defective work and shall be removed and replaced. Any not exceed plus or minus 12 mm at any point.
area or section so removed shall not be less than 3 m in iii. Surface smoothness deviations shall not
length nor less than the full width of the lane involved. exceed 6 mm from a 4.8 m straightedge placed
When it is necessary to remove and replace a section of in any direction, including placement along and
pavement, any remaining portion of the slab adjacent to spanning any pavement joint or edge.
the joints that is less than 3 m in length shall also be
removed and replaced. 5.7.3.20 Pavement Marking

5.7.3.17 Sealing Joints 1 Do not apply pavement marking paint until layout,
colors and placement have been verified by the Engineer.
1 The joints in the pavement shall be sealed as shown
2 Allow concrete pavement to harden and gain
on Drawings and as specified in Sub-Section 5.8.
strength for 28 days and be dry before starting pavement
5.7.3.18 Opening to Traffic marking.
3 Sweep and clean surface to eliminate loose material
1 The Engineer shall decide when the pavement shall
and dust.
be opened to traffic. The pavement will not be opened to
traffic until test specimens molded and cured in 5.7.3.21 Field Quality Control
accordance with ASTM C31 have attained the specified
flexural strength when tested in accordance with ASTM 1 Slump: Minimum one test at point of discharge for
C78, unless otherwise acceptable to Engineer. each day's pour of concrete. Additional tests when
concrete consistency seems to have changed.
5.7.3.19 Pavement Tolerance
2 Concrete Temperature: Test hourly when air
1 Comply with tolerances of ACI 117 and as follows: temperature is 4 deg C and below, and when 27 deg C and
above, and each time a set of flexural test beams are
i. Level: Plus 6 mm, no minus.
made.
ii. Thickness: Plus 9 mm, minus 6 mm.
3 Flexural Strength:
iii. Surface: Gap below 3-m long, unleveled
i. Flexural test beams shall be made for each
straightedge not to exceed +6 mm.
day's pour exceeding 4 cu.m, plus additional
iv. Lateral Alignment and Spacing of Tie Bars and sets for each 40 cu.m. over and above the first
Dowels: +/-25 mm. 20 cu.m. Each group of test beams shall be
v. Vertical Alignment of Tie Bars and Dowels: molded from the same batch of concrete and
+/-6 mm. shall consist of a sufficient number of
specimens to provide two flexural strength
vi. Alignment of Tie-Bar End Relative to Line
tests at each test age. The specimens shall be
Perpendicular to Pavement Edge: +/-13 mm.
made in accordance with ASTM C31. At the
vii. Alignment of Dowel-Bar End Relative to Line start of paving operations and when the
Perpendicular to Pavement Edge: Length of aggregate source, aggregate characteristics, or
dowel +/-6 mm per 300 mm. mix design is changed, additional groups of
viii. Joint Spacing: +/-75 mm. test beams may be required until Engineer is
ix. Contraction Joint Depth: Plus 6 mm, no minus. satisfied that the concrete mix complies with
the strength requirements of these
x. Joint Width: Plus 3 mm, no minus.
specifications. Test ages shall be 7 days and
2 Surface Roughness: The International Roughness 28 days.
Index (IRI) for roads shall be complied with on all concrete
ii. The flexural strength of the concrete shall meet
finished surfaces. The acceptable range of IRI test results
the following requirements:
shall vary between 0 and 1.5 mm/m for highways and
primary roads and between 0 and 3.0 mm/m for secondary, - The average of any 4 consecutive strength
tertiary and other access roads. Adopt contact type test tests, tested at the end of 28 days, shall be
instruments for test stretches not exceeding 400 m in equal to or greater than the specified
length and non-contact test instruments (optical or sonic) flexural strength;
for stretches exceeding 400 m in length. The Contractor

♦ 5-57 ♦
- Not more than 20 percent of the beams vi. When frequency of testing will provide fewer
tested at the end of 28 days shall have a than five compressive-strength tests for a given
flexural strength less than the specified class of concrete, testing shall be conducted
strength; from at least five randomly selected batches or
- No specimen shall have a flexural strength from each batch if fewer than five are used.
less than 90% of the specified flexural vii. When strength of field-cured cylinders is less
strength. than 85 percent of companion laboratory-cured
iii. Specimens, which are obviously defective, cylinders, current operations shall be evaluated
shall not be considered in the determination of and corrective procedures shall be provided for
the strength. When it appears that the test protecting and curing in-place concrete.
specimens will fail to conform to the viii. Strength level of concrete will be considered
requirements for strength, Engineer shall have satisfactory if averages of sets of three
the right to order changes in the concrete mix consecutive compressive-strength test results
sufficient to increase the strength to meet the equal or exceed specified compressive strength
requirements. When a satisfactory relationship and no individual compressive-strength test
between 7-days and 28-day strengths has been result falls below specified compressive
established and approved, the 7-day test strength by more than 3.4 MPa.
results may be used as an indication of the 28- 6 Test results shall be reported in writing to Engineer,
day strengths. However, the 7-day test results concrete manufacturer, and Contractor within 24 hours of
will not replace the results of the 28-day tests if testing. Reports of compressive-strength tests shall
the 28-day results fall below the requirements. contain Project identification name and number, date of
4 Testing Agency: Engage a qualified independent concrete placement, name of concrete testing agency,
testing and inspection agency to sample materials, concrete type and class, location of concrete batch in
perform tests, and submit test reports during concrete pavement, design compressive strength at 28 days,
placement according to requirements specified in this concrete mix proportions and materials, compressive
Clause. breaking strength, and type of break for both 7- and 28-
5 Testing Services: Testing shall be performed day tests.
according to the following requirements: 7 Nondestructive Testing: Impact hammer, sonoscope,
i. Sampling Fresh Concrete: Representative or other nondestructive device may be permitted by
samples of fresh concrete shall be obtained Engineer but will not be used as the sole basis for
according to ASTM C 172, except modified for approval or rejection.
slump to comply with ASTM C 94. 8 Additional Tests: Testing agency shall make
ii. Slump: ASTM C 143; one test at point of additional tests of the concrete when test results indicate
placement for each flexural and/or slump, air entrainment, concrete strengths, or other
compressive-strength test, but not less than requirements have not been met, as directed by Engineer.
one test for each day's pour of each type of Testing agency may conduct tests to determine adequacy
concrete. Additional tests will be required of concrete by cored cylinders complying with ASTM C 42,
when concrete consistency changes. or by other methods as directed.

iii. Concrete Temperature: ASTM C 1064; one test 5.7.3.22 Repairs and Protection
hourly when air temperature is 4 deg C and
below and when 27 deg C and above, and one 1 Remove and replace concrete pavement that is
test for each set of flexural and/or compressive- broken, damaged, or defective, or does not meet
strength specimens. requirements in the Specification

iv. Compression Test Specimens: ASTM C 31/C 2 Drill test cores where directed by Engineer when
31M; one set of four standard cylinders for necessary to determine magnitude of cracks or defective
each compressive-strength test, unless areas. Fill core holes in satisfactory pavement areas with
otherwise indicated. Cylinders shall be molded Portland cement concrete bonded to pavement with epoxy
and stored for laboratory-cured test specimens adhesive.
unless field-cured test specimens are required. 3 Protect concrete from damage. Exclude traffic from
v. Compressive-Strength Tests: ASTM C 39; one pavement for at least 14 days after placement. When
set for each day's pour of each concrete class construction traffic is permitted, maintain pavement as
exceeding 4 cu.m., but less than 19 cu.m., plus clean as possible by removing surface stains and spillage
one set for each additional 38 cu.m. One of materials as they occur.
specimen shall be tested at 7 days and two 4 Maintain concrete pavement free from stains,
specimens at 28 days; one specimen shall be discoloration, dirt, and other foreign material. Sweep
retained in reserve for later testing if required.

♦ 5-58 ♦
concrete pavement not more than two days before date the joint shall be removed and replaced at the Contractor's
scheduled for Substantial Completion inspections. expense.

5.7.3.23 Determination of Concrete Thickness


5.7.4 Method of Measurement
1 Thickness of concrete pavement shall be determined
1 Unreinforced concrete pavement shall be measured
by average caliper measurement of cores taken from in cubic meters computed as the paved area multiplied by
sections of the pavement as stated in Item 2 below,
the executed slab thickness as approved by the Engineer.
rounded upwards taken to the nearest mm.
2 Reinforced concrete pavement shall be measured in
2 Pavement sections shall consist of each 300 lin.m.
cubic meters of the paved area multiplied by the executed
length in each paver lane. The last section in each lane
slab thickness (as approved by the Engineer) and shall
shall be 300 m plus the fractional part of 300 m remaining. include the same items detailed in Item 1 of Clause 5.7.4
Other areas such as intersections, entrances, ramps, etc
above plus the reinforcement steel material furnished,
shall be measured as one section each and the thickness
spliced, jointed and placed all as shown on the
of each shall be determined separately. Small irregular Contractor’s shop drawings that are approved by the
unit areas may be included as part of another section,
Engineer.
3 One core shall be taken from each section by the
3 The rates in the Bill of Quantities shall be deemed to
Contractor at approved locations and in the presence of
include furnishing of all associated concrete and joint
the Engineer. When the measurement of the core from component materials, preparation of bases, concrete
any pavement section is not deficient by more than 5 mm
mixing, placing, compacting, finishing and curing, as well
from the specified thickness, the core will be deemed to be
as all joint sawing, cutting and cleaning operations,
of the specified thickness as shown on the Drawings. drilling and installing dowels and deformed tie bars and
4 When the measurement of the core from any other joint accessories, and all tests, all as detailed on
pavement section is deficient by more than 5 mm but not Drawings and in the Specifications.
more than 20 mm, 2 additional cores spaced at not less
than 100 mm shall be taken and used together with the 5.7.5 Basis of Payment
first core to determine the average thickness of such
section. 1 The amount of completed and accepted work,
measured as provided for above, will be paid for at the
5 When the measurement of the core from any
unit rates for the various items in the Bill of Quantities,
pavement section is less than the specified thickness by
which rate shall be full compensation for supplying
more than 20 mm, the average thickness of such section
materials, transporting and placing, for labor, equipment,
shall be determined by taking additional cores at not less
tools and other items necessary for the proper completion
than 5 m intervals parallel to the centerline in each
of the work.
direction from the affected location until, in each direction,
a core is taken which is not deficient by more than 20 mm.
Exploratory cores for deficient thickness will not be used
5.7.6 Items in the Bill of Quantities
in average thickness determinations. i. Unreinforced Cement Concrete
6 Where the average thickness of concrete pavement is Pavement (cu.m.)
deficient by more than 5 mm but not more than 20 mm ii. Reinforced Cement Concrete
adjustments shall be made in the area measurements as Pavement (cu.m.)
shown in Table 5.7.3.1.

Deficiency in Thickness as Proportion of Area 5.8 Joint Sealers for Concrete


Determined by Cores (mm) Measured for Payment Pavement
0.0 to 5.0 100%
5.1 to 10.0 90% 5.8.1 Description
10.1 to 15.0 75%
1 This Sub-section describes joint sealers for concrete
15.1 to 20.0 50%
pavement as shown on Drawings.
> 20.0 0%
Table 5.7.3.1: Concrete Thickness Deficiency 5.8.2 Materials
7 When the pavement is more than 20 mm deficient in 5.8.2.1 Materials, General
thickness, the Contractor shall remove such deficient areas
and replace them with concrete pavement of the specified 1 Compatibility: Provide joint sealers, joint fillers and
quality and thickness, all at his own expense. other related materials that are compatible with one
another and with joint substrates under conditions of
8 When the limits of a deficient area to be removed
service and application, as demonstrated by sealant
and replaced are within 3 m of an expansion, contraction
manufacturer based on testing and field experience.
or construction joint, the entire concrete pavement up to

♦ 5-59 ♦
5.8.2.2 Elastomeric Hot-Poured Joint Sealants i. Remove all foreign material from joint
substrates which could interfere with adhesion
1 ASTM D 3569 - Joint Sealants, Hot-Poured, of joint sealer, including dust; paints, except for
Elastomeric, Jet-Fuel-Resistant type, for Portland Cement permanent, protective coatings tested and
Concrete Pavements. approved for sealant adhesion and
compatibility by sealant manufacturer; old joint
5.8.2.3 Joint Sealant Backing
sealers; oil; grease; waterproofing; water
1 General: Provide sealant backings of material and repellants; water and surface dirt.
type which are non-staining; are compatible with joint ii. Remove laitance and form release agents from
substrates, sealants, primers and other joint fillers; and are concrete.
approved for applications indicated by sealant
2 Joint Priming: Prime joint substrates where
manufacturer based on field experience and laboratory
indicated or where recommended by joint sealer
testing.
manufacturer based on preconstruction joint sealer-
2 Plastic Foam Joint Fillers: Preformed, compressible, substrate tests or prior experience. Apply primer to
resilient, non-waxing, non-extruding strips of flexible, non- comply with joint sealer manufacturer's recommendations.
gassing plastic foam of material indicated below; Confine primers to areas of joint sealer bond, do not allow
nonabsorbent to water and gas; and of size, shape and spillage or migration onto adjoining surfaces.
density to control sealant depth and otherwise contribute
3 Masking Tape: Use masking tape where required to
to producing optimum sealant performance.
prevent contact of sealant with adjoining surfaces which
3 Bond-Breaker Tape: Polyethylene tape or other otherwise would be permanently stained or damaged by
plastic tape as recommended by sealant manufacturer for such contact or by cleaning methods required to remove
preventing sealant from adhering to rigid, inflexible joint sealant smears. Remove tape immediately after tooling
filler materials or joint surfaces at back of joint where such without disturbing joint seal.
adhesion would result in sealant failure. Provide self-
adhesive tape where applicable. 5.8.3.3 Installation of Joint Sealers

5.8.2.4 Miscellaneous Materials 1 General: Comply with joint sealer manufacturers'


printed installation instructions applicable to products and
1 Primer: Provide type recommended by joint sealer applications indicated, except where more stringent
manufacturer where required for adhesion of sealant to requirements apply.
joint substrates indicated, as determined from
2 Hot poured Sealants:
preconstruction joint sealer substrate tests and field tests.
i. The joint sealant shall be applied solid,
2 Cleaners for Nonporous Surfaces: Provide non-
uniformly from bottom to top and shall be
staining, chemical cleaners of type which are acceptable to
filled without formation of entrapped air or
manufacturers of sealants and sealant backing materials,
voids. A backing material shall be placed as
which are not harmful to substrates and adjacent
shown on the plans and shall be non-adhesive
nonporous materials, and which do not leave oily residues
to the concrete or the sealant material. The
or otherwise have a detrimental effect on sealant adhesion
heating kettle shall be an indirect heating type,
or in-service performance.
constructed as a double boiler. A positive
3 Masking Tape: Provide non-staining, nonabsorbent temperature control and mechanical agitation
type compatible with joint sealants and to surfaces shall be provided. The sealant shall not be
adjacent to joints. heated to more than 11°C below the safe
heating temperature. The safe heating
5.8.3 Construction Requirements temperature can be obtained from the
manufacturer's shipping container. A direct
5.8.3.1 Examination
connecting pressure type extruding device with
1 Examine joints for compliance with requirements for nozzles shaped for insertion into the joint shall
joint configuration, installation tolerances and other be provided. Any sealant spilled on the surface
conditions affecting joint sealer performance. Do not of the pavement shall be removed immediately.
proceed with installation of joint sealers until ii. Backup materials and bond breakers shall be
unsatisfactory conditions have been corrected. compatible with the sealant, shall not adhere to
the sealant, shall be compressible without
5.8.3.2 Preparation
extruding the sealant, and shall recover to
1 Surface Cleaning of Joints: Clean out joints maintain contact with the joint faces when the
immediately before installing joint sealers to comply with joint is open.
recommendations of joint sealer manufacturers and the
following requirements:

♦ 5-60 ♦
5.8.3.4 Cleaning 5.9.3 Construction Requirements
1 Clean off excess sealants or sealant smears adjacent 1 Construction work shall comply with the relevant
to joints as work progresses by methods and with requirements of the following sections:
cleaning materials approved by manufacturers of joint Section 2 Earthwork
sealers and of products in which joints occur. Sub-section 5.2 Reinforcing Steel
5.8.3.5 Protection Sub-section 5.3 Reinforced Concrete Structures.
2 Box culverts, headwalls, wing walls, cut-off walls and
1 Protect joint sealers during and after curing period
aprons shall be to the lines and levels shown on the
from contact with contaminating substances or from
Drawings. Unless otherwise shown, culverts shall have a
damage resulting from construction operations or other
constant fall of 1:100 along their centerline.
causes so that they are without deterioration or damage at
time of Substantial Completion. If, despite such protection, 3 Box culverts shall be constructed in sections such
damage or deterioration occurs, cut out and remove that expansion joints are located at intervals which shall
damaged or deteriorated joint sealers immediately and be so spaced as to prevent the box culvert from behaving
reseal joints with new materials to produce joint sealer as a long beam unless such structural action has been
installations with repaired areas indistinguishable from allowed for in the design. Unless shown on the Drawings
original work. or directed by the Engineer, the spacing of expansion
joints shall be no greater than 35 meters.
5.8.4 Method of Measurement, Basis of 4 Unless otherwise indicated, expansion joints shall
Payment and Bill of Quantities also be used at the culvert ends where the culvert meets
the wing walls and apron slabs.
1 No separate measurement is made for joint sealers
and no items are included in the Bill of Quantities. The 5 Where box culverts are located in road embankments,
work is considered as subsidiary to the concrete pavement the embankments shall first be constructed in accordance
and its cost is deemed to be included under payment for with Paragraph 2.5.3.4 "Embankment Construction". The
concrete pavement items as measured under Clauses 5.7.4, compacted embankments shall then be excavated in
5.7.5 and 5.7.6. trenches for the culverts. This requirement may be
dispensed with by a written permission from the Engineer
to so do. Where a culvert is to be constructed under a
5.9 Reinforced Concrete Box Culverts high embankment, this requirement may be relaxed or
and Headwalls, Wingwalls, Cut- dispensed with provided the fill is designed to arch over
Off Walls and Aprons the culvert or the culvert is specially designed for an
increased surcharge load from the embankment.
5.9.1 Description Embankments may be constructed to within 1 m above
the culvert then construction carried out as above.
1 This Sub-section describes the requirements for
construction of reinforced concrete box culverts, in-situ or 6 For culverts located below firm ground, the
precast, and headwalls, wing walls, cut-off walls and excavation shall be carried out in trenches in accordance
aprons for box and pipe culverts, including earthworks, with Section 2 “Earthwork”.
structural concrete and all other ancillary items necessary 7 Backfilling and compaction shall be carried out in
for the completion of the structures to the lines, grades layers not exceeding 150 mm compacted thickness and
and dimensions as shown on the Drawings. These the difference in the levels of backfill on either side of the
requirements are additional to the requirements of culvert shall at no time exceed 500 mm. Start backfilling
preceding Sections of the Specification. after having attained 75 percent of the culvert 28-day
concrete strength.
5.9.2 Materials 8 All concreting shall be carried out in dry conditions.
1 Materials shall conform to the relevant requirements 9 Unless otherwise shown on the Drawings or
of the following Sub-sections of the Specification: instructed by the Engineer, the base slab of the box culvert
for its entire length shall first be completed before
- Concrete Sub-section 5.1
proceeding with the walls and roof slab. The construction
“Concrete Materials and Mixes” joints in the walls shall be located at not less than 100 mm
- Reinforcing Steel Sub-section 5.2 above the top of the base slab. Unless shown otherwise
“Reinforcing Steel” on the Drawings or directed by the Engineer, the walls and
roof slabs shall be concreted in one pour between
2 Concrete classes shall be those prescribed on the
expansion joints.
relevant Drawings.
10 Unless otherwise shown on the Drawings or
3 Backfill shall be as specified in Section 2 “Earthwork”.
instructed by the Engineer, the cut-off wall shall be cast
against earth.

♦ 5-61 ♦
11 Concrete placing, forms, finishing, curing and ASTM D 173 Specification for Bitumen-Saturated
jointing shall be done in accordance with Section 5.3 Cotton Fabrics Used in Roofing and
“Reinforced Concrete Structures”. Waterproofing (AASHTO M 117)
ASTM D 449 Specifications for Asphalt Used in
5.9.4 Method of Measurement Dampproofing, and Waterproofing
(AASHTO M 115)
1 The work shall be measured according to the
dimensions shown on the Drawings in accordance with ASTM D 450 Specification for Coal-Tar Pitch Used in
the rules for measurement stated in Sub-section 5.1 Roofing, Dampproofing, and
‘Concrete Materials and Mixes’ and Sub-section Waterproofing (AASHTO M 118)
5.2 ’Reinforcing Steel’. ASTM D 490 Specifications for Road Tar (AASHTO M
2 Where the Contractor uses precast units as an 52)
alternative, any extra material and quantity necessary
shall not be measured. 5.10.2 Materials
3 All other work such as excavation for the cut-off walls
5.10.2.1 Asphalt
formwork, construction and expansion joints and the like,
shall be included as subsidiary work whose costs are 1 Waterproofing asphalt shall conform to AASHTO M
deemed to be included in the rates and prices for concrete 115 (ASTM D 449); Type I for use below ground, and Type
and reinforcement. II for use above ground.
2 Primer for use with asphalt in waterproofing shall
5.9.5 Basis of Payment conform to AASHTO M 116 (ASTM D 41).
1 The amount of completed and accepted work, 5.10.2.2 Bitumen
measured as provided for above, shall be paid for at the
unit rates in the Bill of Quantities, which rates shall be full 1 Waterproofing bitumen shall conform to AASHTO M
compensation for supplying, curing, finishing concrete 118 (ASTM D 450); Type II unless otherwise specified.
and cutting, shaping and fixing reinforcing steel and for 2 Primer for use with coal-tar bitumen in dampproofing
labor, materials, equipment, tools and other items and waterproofing shall conform to AASHTO M 121
necessary for the proper completion of the works. (ASTM D 43). It shall be a distillate of coal-gas tar or coke-
oven tar.
5.9.6 Items in Bill of Quantities
5.10.2.3 Waterproofing Fabric
1 Reinforced concrete box culverts, head walls, wing
walls and cut-off walls are separately identified in the Bill 1 Waterproofing fabric shall conform to AASHTO M
of Quantities and the relevant items as stated in Sub- 117 (ASTM D 173).
sections 5.1 and 5.2 are included.
5.10.2.4 Self-Adhesive Polyethylene Sheet

5.10 Waterproofing for Structures 1 Flexible, preformed waterproof membrane


comprising strong, high-density polyethylene film with
5.10.1 Description self-adhesive rubber/bitumen compound, and having the
following minimum properties:
5.10.1.1 Scope - Total thickness : 1.5 mm
2
1 This Sub-section describes waterproofing membrane, - Weight : 1.6 kg/m
sand dampproofing courses to external concrete surfaces 2
- Tensile strength : 42 N/mm
in contact with earth and epoxy coating to internal
- Elongation : 210% long.; 160% trans.
surfaces of concrete walls, slabs, and beds, all as shown
on the Drawings or as directed by the Engineer. - Tear resistance : 340 N/mm long.; 310
N/mm trans.
5.10.1.2 References - Puncture resistance : 220 N 65 mm
1 American Society for Testing and Materials (ASTM):
5.10.2.5 Tar for Absorptive Treatment
ASTM D 41 Specification for Asphalt Primer Used in
Roofing, Dampproofing, and 1 Tar for absorptive treatment shall be a liquid water-
Waterproofing (AASHTO M 116) gas tar that conforms to the following requirements:

ASTM D 43 Specification for Coat Tar Primer Used - Specific gravity, 25ºC 1.030 to 1.100
in Roofing, Dampproofing, and - Specific viscosity at 40ºC (Engler),
Waterproofing (AASHTO M 121) not more than 3.0
- Total distillate, percent by
weight, to 300ºC, not more than 50.0

♦ 5-62 ♦
- Bitumen (soluble in carbon disulfide) When necessary the Engineer may require the surface to
not less than, percent 98.0 be scrubbed with water and a stiff brush, after which the
- Water, not more than, percent 3.0 surface shall be allowed to dry before application of the
primer.
5.10.2.6 Tar Seal Coat
5.10.3.2 Inspection, Delivery and Storage
1 Tar seal coat shall conform to AASHTO M 52, Grade
RTCB-5 (ASTM D 490). 1 All waterproofing materials shall be tested before
shipment. Unless otherwise ordered by the Engineer, they
5.10.2.7 Proprietary Waterproofing Systems shall be tested at the place of manufacture, and, when so
tested, a copy of the test results shall be sent to the
1 Proprietary waterproofing systems shall be
Engineer by the chemist or inspection bureau which has
bituminous membranes reinforced with layers of suitable
been designated to make the tests, and each package shall
reinforcement, bituminous coated polythene sheet,
have affixed to it a label, seal, or other mark of
plasticized polyvinyl chloride sheet, other approved
identification, showing that it has been tested and found
membranes or applications of resinous reinforced
acceptable, and identifying the package with the
coatings. The type to be used shall be as indicated on the
laboratory tests.
Drawings and shall be chosen according to its location
and serviceability. The specific system shall be approved 2 Factory inspection is preferred, but in lieu thereof
after site trials, should the Engineer decide these to be and/or addition thereof, the Engineer may order that
necessary. representative samples, properly identified, be sent to him
for test prior to shipment of the materials. After delivery
5.10.2.8 Epoxy Coating System of the materials, representative check samples shall be
taken which shall determine the acceptability of the
1 An approved epoxy coating system shall be
materials.
furnished and applied to the internal concrete surfaces of
culverts and open channels as shown on the Drawings or 3 All materials shall be delivered to the work in original
as directed by the Engineer. The thickness of the epoxy containers, plainly marked with the manufacturer's brand
coating shall be at least 400 microns in accordance with or label.
the manufacturer's recommendations. 4 Waterproofing and dampproofing material shall be
stored in a dry, protected place. Rolls of waterproofing
5.10.3 Construction Requirements fabric and membranes shall not be stored on end.

5.10.3.1 Surface Preparation 5.10.3.3 Asphalt and Bitumen Waterproofing Fabric

1 Waterproofing: 1 Asphalt shall be heated to a temperature between


150 degrees C and 175 degrees C and tar for hot
i. All concrete surfaces to be waterproofed shall
application shall be heated to a temperature between 93
be reasonably smooth and free from
degrees C and 120 degrees C with frequent stirring to
projections or holes which might cause
avoid local overheating. The heating kettles shall be
puncture of the membrane. The surface shall
equipped with thermometers.
be dry, so as to prevent the formation of steam
when the hot asphalt or tar is applied, and, 2 In all cases, the waterproofing shall begin at the low
immediately before the application of the point of the surface to be waterproofed, so that water will
waterproofing, the surface shall be thoroughly run over and not against or along the laps.
cleaned of dust, projecting tying wire and loose 3 The first strip of fabric shall be of half-width; the
material. second shall be full-width, lapped the full-width of the first
ii. No waterproofing shall be done in wet weather, sheet; and the third and each succeeding strip shall be full-
nor when the temperature is below 4 degrees C, width and lapped so that there will be two layers of fabric
without special authorization from the Engineer. at all points with laps not less than 50 mm wide. All end
Should the surface of the concrete become laps shall be at least 300 mm.
temporarily damp, it shall be covered with a 50 4 Beginning at the low point of the surface to be
mm layer of hot sand, which shall be allowed waterproofed, a coating of primer shall be applied and
to remain in place from 1 to 2 hours, or long allowed to dry before the first coat of asphalt is applied.
enough to produce a warm and surface-dried The waterproofing shall then be applied as follows.
condition, after which the sand shall be swept
5 Beginning at the low point of the surface to be
back, uncovering sufficient surface for
waterproofed, a section about 500 mm wide and the full
beginning work, and the operation repeated as
length of the surface shall be mopped with the hot asphalt
the work progresses.
or tar. Immediately following the mopping, the first strip
2 Dampproofing: The surface to which the of fabric, or half-width, shall be rolled and pressed into
dampproofing coating shall be applied shall be cleaned of place so as to eliminate all air bubbles and obtain close
all loose and foreign material and dirt and shall be dry. conformity with the surface. This strip and an adjacent

♦ 5-63 ♦
section of the surface of a width equal to slightly more 5.10.3.4 Proprietary Waterproofing Membranes
than half of the width of the fabric being used shall then
be mopped with hot asphalt or tar, and a full width of the 1 Proprietary waterproofing membranes shall be
installed strictly in accordance with the manufacturer's
fabric shall be rolled into this, completely covering the first
instructions and shall be laid so that no air is trapped
strip, and pressed into place as before. This second strip
and an adjacent section of the concrete surface shall then between it and the concrete surface or between successive
layers of sheeting.
be mopped with hot asphalt or tar and the third strip of
fabric "shingled" on so as to lap the first strip not less than 2 Unless otherwise specified, joints between sheets
50 mm. This process shall be continued until the entire shall be lapped with end laps of at least 150 mm and side
surface is covered, each strip of fabric lapping at least 50 laps of at least 100 mm. The joints shall be arranged so
mm over the last strip. The entire surface shall then be that, at no points, are there more than three thicknesses of
given a final mopping of hot asphalt or tar. sheeting and, as far as possible so that water will drain
away from the exposed edge.
6 The completed waterproofing shall be a firmly
bonded membrane composed of two layers of fabric and 5.10.3.5 Damage Patching of Waterproofing Fabrics
three moppings of asphalt or tar, together with a coating
of primer. Under no circumstances shall one layer of 1 Care shall be taken to prevent injury to the finished
fabric touch another layer at any point or touch the surface, fabric membrane by workmen or wheelbarrows, or by
as there must be at least three complete moppings of throwing any material on it. Any damage which may
asphalt or tar. occur shall be repaired by patching. Patches shall extend
7 In all cases the mopping on concrete shall cover the at least 300 mm beyond the outermost damaged portion
surface so that no gray spots appear, and on cloth it shall and the second ply shall extend at least 75 mm beyond the
be sufficiently heavy to completely conceal the weave. On first.
horizontal surfaces not less than 49 liters of asphalt or tar 2 Proprietary waterproofing membranes shall be
shall be used for each 10 square meter of finished work, repaired according to the manufacturer's specifications
and on vertical surfaces not less than 61 liters shall be and as directed by the Engineer.
used for each 10 square meter. The work shall be so
5.10.3.6 Dampproofing
regulated that, at the close of a day's work, all cloth that is
laid shall have received the final mopping of asphalt or tar. 1 Concrete, brick, or other surfaces to be protected by
Special care shall be taken at all laps to see that they are dampproofing shall be thoroughly cleaned before the
thoroughly sealed down. primer is applied. The surfaces shall then be brush or
8 At the edges of the membrane and at any points spray painted with two or more coats (as indicated on the
where it is punctured by such appurtenances as drains or Drawings) of tar or asphalt for absorptive treatment.
pipes, suitable provisions shall be made to prevent water Below ground not less than two coats shall be applied,
from getting between the waterproofing and the using 0.56 L/square meter of surface. On the well-primed
waterproofed surface. surface one application of tar or asphalt seal coat shall be
9 All flashing at curbs and against girders, spandrel applied by brush, using 0.45 L/square meter.
walls, etc., shall be done with separate sheets lapping the 2 Care shall be taken to confine all paints to the areas
main membrane not less than 300 mm. Flashing shall be to be waterproofed and to prevent disfigurement of any
closely sealed either with a metal counter-flashing or by other parts of the structure by dripping or spreading of the
embedding the upper edges of the flashing in a groove tar or asphalt.
poured full of joint filler.
5.10.3.7 Protection of Waterproofing and Dampproofing
10 Joints which are essentially open joints but which are
not designed to provide for expansion shall first be 1 Waterproofing membranes and dampproofing
caulked with oakum and lead wool and then filled with hot courses shall be covered by a protective layer which,
joint filler. unless otherwise specified or shown on the Drawings,
11 Expansion joints, both horizontal and vertical, shall shall be a 50 mm coat of mortar composed of one part
be provided with sheet copper or lead in "U" or "V" form in Portland cement and two parts sand, reinforced midway
accordance with approved details. After the membrane between its top and bottom surfaces with wire netting of
has been placed, the joint shall be filled with hot joint filler. 150 mm mesh and No. 12 gauge, or an approved
The membrane shall be carried continuously across all equivalent. The top surface shall be troweled to a smooth,
expansion joints. hard finish and, where required, true to grade.

12 At the ends of the structure the membrane shall be 2 The protection course shall follow the waterproofing
carried well down on the abutments and suitable so closely that the latter will not be exposed without
provision made for all movement. protection for more than 24 hours.
3 Unless otherwise shown on the Drawings or directed
by the Engineer, vertical faces waterproofed or
dampproofed shall be protected by a porous concrete
block wall of not less than 225 mm thickness. If approved

♦ 5-64 ♦
by the Engineer, a proprietary synthetic sheeting may be construction in corrosive or marine environments or other
used as the protective layer in lieu of the porous concrete severe exposure conditions as shown on the Drawings.
block wall. 2 The coating system shall be used for the protection
of reinforced concrete structures against carbonation or
5.10.3.8 Testing
chloride induced corrosion. Work includes, but not
1 Unless otherwise agreed by the Engineer in writing, necessarily limited to coating for:
at least one site trial application of the waterproofing - Piers, columns, frames and exposed surfaces
system shall be carried out to determine the suitability of of abutments and retaining walls.
the surface preparation, method of application and
- Deck soffit and sides and other exposed
effectiveness of the protective layer. The size of
surfaces of deck.
membrane laid shall be not less than 2.0 meters wide and
5.0 meters long. - Precast concrete girders and other precast
concrete elements.
5.10.4 Method of Measurement - Concrete parapets.

1 Waterproofing membrane shall be measured by the 5.11.1.2 Submittals


square meter of each type, furnished, laid, completed and
accepted. 1 Proprietary special coating system for the protection
of exposed concrete surfaces shall be proposed by the
2 Tar or bituminous painting to surfaces permanently
Contractor and shall be subject to the Engineer's approval.
in contact with backfilled material shall be measured by
Submittal shall include the details of the coating type and
the square meter of surface area so painted.
coating manufacturer and a list of projects, executed in
3 Epoxy coating to internal surfaces of concrete shall environmental conditions similar to those experienced in
be measured by the square meter of the surface area so the project site, in which the same protective coating
coated. system was successfully used.
4 Protection to waterproofing membrane and 2 The Contractor's submittal shall be accompanied by
dampproofing course shall not be measured for direct the manufacturer's detailed product specifications
payment but shall be deemed to be included in the rates together with application instructions, and guarantee that
for waterproofing and dampproofing. the product is suitable for use at the operating
5 Site trials of waterproofing membranes shall not be temperatures in the Sultanate.
measured for direct payment but shall be deemed to be 3 Trial Panels as specified in Paragraph 5.11.1.4 (1)
included in the rates for waterproofing. shall be provided.

5.10.5 Basis of Payment 5.11.1.3 Performance Requirements

1 The amount of completed and accepted Work 1 The coating system shall provide in-depth protection
measured as provided for above will be paid at the unit against carbonation and chloride penetration while
rates as specified in the Bill of Quantities, which unit rates permitting water vapor transmission from the concrete.
shall be full compensation for furnishing all materials, 2 Final color shall be selected by the Engineer.
labor, equipment, tools, supplies and all other items
necessary for the completion of the Work. 5.11.1.4 Quality Assurance

1 Trial Panels:
5.10.6 Items in the Bill of Qquantities
i. Prior to applying the system, trial applications
i Tar or bituminous paint sq.m. shall be carried out on trial panels made by the
(State type, number of coats) Contractor to the specified finishes. The trial
ii Membrane waterproofing sq.m. shall demonstrate the method proposed for
(State type, thickness) applying the system, coverage, coating
thickness, color and final appearance of the
iii Epoxy coating to internal
coating. Representatives of the coating
surfaces of concrete
manufacturer shall be present at the trials and
(State type, thickness) sq.m.
the surface preparation and application of the
coating shall be carried out under their
5.11 Protective Coating for Concrete direction. The Contractor shall, at his own
expense, coat as many panels as required by
5.11.1 Description the Engineer until a trial panel has been
accepted by the Engineer as satisfactory. The
5.11.1.1 Scope coated panel, when accepted, will form the
1 This Sub-section describes protective coating on standard against which the corresponding
exposed surfaces of reinforced and prestressed concrete coating in the works shall be judged. No

♦ 5-65 ♦
application of the coating in the works shall be 5.11.2.3 Topcoat
undertaken until trials have been completed to
1 The topcoat shall be a pure aliphatic acrylic resin,
the Engineer’s satisfaction.
decorative, high performance water based, pigmenting
ii. Trial panels shall be tested for permeability in coating. It shall have resistance to water, carbon dioxide
accordance with DIN 1048 and AASHTO T 277 and other air-borne acids and have the ability to allow
as defined in Paragraph 5.1.3.15 as a check on passage of water vapor from within the structure. The
the effectiveness of the coating. Acceptance of topcoat shall have elastomeric and flexural capabilities.
the coating shall be based on compliance with The color shall be selected by the Engineer.
the following acceptance limits. Based on this
result, the Engineer may reject the work or 5.11.2.4 Specifications
require additional coating.
1 The material employed for the coating shall comply
- DIN 1048 results for coated surfaces: one with the following requirements:
fifth of the limits for the unprotected
- Wet film thickness 650 microns
surfaces defined in Paragraph 5.1.3.15.
- Dry film thickness 400 microns
- AASHTO T 277 test results for coated
surfaces: charge passed should be less - Carbon dioxide diffusion
than 500 coulombs. resistance R value at 325μ
greater than 161
5.11.1.5 Testing m
1 Testing of the coating shall conform to the following: - Water vapor transmission greater than 13
g/m2.day
- Carbon dioxide diffusion resistance (R
value) - Chloride ion diffusion 3.63 x 10-10
Taywood Engineering Laboratories cm2/sec
- Water vapor transmission - Reduction in chloride ion
Taywood Engineering Laboratories penetration minimum 94 %
at 28 days
- Chloride ion diffusion
- Tear resistance 7.3 kN/mm2
Taywood Engineering Laboratories
- Crack bridgeability 1.5 mm
- Reduction in chloride ion penetration
BS 1881: Part 124 - Adhesion minimum 1.0
N/mm2
- Tear resistance
ASTM D624 - Reduction in water absorption minimum 82
(measured against a control % at 28 days
- Crack bridgeability concrete sample) when tested at a
BRE method water-cement
2 Where test methods are not specified, the procedure ratio 0.5
for establishing compliance with the specification
requirements shall be agreed with the Engineer. 5.11.3 Construction Requirements
5.11.3.1 General
5.11.2 Materials
1 The Contractor shall adhere strictly to the
5.11.2.1 General
manufacturer's recommendations regarding the use,
1 The coating system shall consist of a penetrating, storage, application and safety rules in respect of the
reactive primer and an acrylic topcoat system to minimize approved materials.
ingress of acidic gases, chlorides and water. 2 During storage, mixing and application, the
Contractor shall comply with the health and safety and
5.11.2.2 Primer
environmental protection recommendations of the
1 The primer shall be a low viscosity silane-siloxane manufacturer and governing authorities.
acrylic blend dissolved in a penetrating organic carrier.
5.11.3.2 Inspection of Concrete
The primer shall have the capability to penetrate and
produce a chemically bound hydrophobic barrier to 1 The Contractor shall not proceed with the surface
prevent the passage of chloride and sulfate ions. The finish or making good of concrete surfaces until he has
primer shall also be film forming to condition and stabilize received the Engineer’s permission to do so and he shall
the substrate prior to the application of the topcoat. The not apply cement slurry or mortar or any other coating to
primer shall be applied in full accordance with the the concrete surfaces from which the formwork has been
manufacturer’s instructions. struck until the Engineer has inspected and approved the
concrete.

♦ 5-66 ♦
5.11.3.3 Surface Preparation 5.12 Bridge Load Testing
1 Before application, all surfaces must be dry and free
from oil, grease, loose particles, decayed matter, moss or
5.12.1 Description
algae growth and general curing compounds. 1 All bridges shall be load tested unless otherwise
2 All such contamination and laitance must be agreed by the Engineer.
removed by the use of sweep sand blasting, high pressure 2 The aim of the testing is not to measure the actual
jetting or equivalent mechanical means. factor of safety of the bridge but intended to verify the
3 Before proceeding to apply the protective coatings, design and construction of the bridge under normal
all surfaces which are not to be coated, but which may be loading conditions. Measurements are, accordingly, meant
affected by the application of the coating shall be fully to give an order of magnitude and fine precision is not
masked. required.
4 Blow holes and areas of pitting shall be made good 3 The date of conducting the load testing shall be fixed
with a one part modified cementitious material and by the Engineer and shall be at least 90 days after all
allowed to cure in accordance with the manufacturer’s concrete structural elements are constructed. Load testing
recommendations. In particular, the application shall be in may be carried out before or after opening the bridge for
accordance with the manufacturer’s recommendations, traffic.
with respect to the maximum application thickness. 4 If the bridge is open to traffic before being load
tested, the Engineer may impose restrictions on highway
5.11.3.4 Approval Prior to Coating Application
loading over the bridge until testing is satisfactorily
1 The Engineer’s approval must be obtained prior to completed, such as banning the passage of heavy traffic
applying the coating system in the works. Before giving loading of the order of the Oman Special Truck, or any
the approval, the Engineer will need to be satisfied as to other measures.
the following: 5 Load testing comprises:
i. All construction work in the immediate vicinity of i. Application of load as described in Clause 5.12.2.
the structure to be coated has been completed. ii. Detailed visual inspection before, during and
ii. The surface preparation of the structure has after the testing as described in Clause 5.12.3.
been completed. iii. Measurement of deflections and other quantities
iii. The whole of the structure can be coated in a as described in Clause 5.12.4.
continuous operation. 6 If the Works include a number of similar bridges
iv. Adequate measures have been taken to protect testing may be limited as follows:
the property of third parties, including vehicles,
i. At least one bridge shall be tested for all the
from coating splatters.
tests specified in this Sub-Section.
v. The weather conditions accord with the coating
ii. The other bridges may be subject only to testing
manufacturer’s directions for coating application.
by static loads.
5.11.3.5 Application iii. The latter test may be further simplified by
reducing the number of tests. It is
1 The exposed concrete surfaces shall be conditioned recommended, however, to measure the
by the application of the penetrating hydrophobic primer. deflection at, at least, one point per span.
The primer shall be allowed to dry in accordance with the
7 Bridges are considered similar when their
manufacturer’s requirements.
superstructures have the same design, same material
2 The Contractor shall then apply two coats of the specifications and are constructed by the same contractor.
pigmented topcoat in accordance with the manufacturer’s
8 If the results of the load testing are unfavorable, and
instructions. The finished coating shall be pinhole free.
leave some doubt as to the ability of the bridge to
The color and finish shall be agreed with the Engineer.
withstand the loads it is supposed to carry, more elaborate
3 The coating shall be applied by spray, roller or brush testing shall be considered, including non-destructive full-
to achieve a finish acceptable to the Engineer. scale testing.

5.11.4 Method of Measurement, Basis of 5.12.2 Load Application


Payment and Bill of Quantities
5.12.2.1 Composition of Applied Load
1 No separate measurement is made for protective
coating and no items are included in the Bill of Quantities 1 The applied load shall consist of a number of loaded
for direct payment. The work is considered as subsidiary trucks sufficient to satisfy the requirements of this Clause.
work, the cost of which will be deemed to be included in 2 The loads shall be applied in two types of tests: by
the unit rates for the relevant BOQ Items for concrete static loads and moving loads.
described and measured for payment under the provisions
3 The loads shall be restricted to the carriageways and
of Section 5.1 “Concrete Materials and Mixes”.
no load is applied on the sidewalks.

♦ 5-67 ♦
4 The stipulations of this Clause are set as minimum 3 After the completion of testing, a detailed visual
requirements. In particular cases, when there is doubt inspection shall also be carried out to all accessible parts
about the quality of the bridge, the Engineer may impose of the bridge.
more severe loads. 4 Visual inspections shall be complemented with
photographs.
5.12.2.2 Testing by Static Load

1 The loaded trucks shall be positioned on the 5.12.4 Measurements


carriageways and grouped together in the longitudinal
1 As a minimum the deflections of each span and the
and transverse directions such that the straining actions
deformation of the bearings shall be measured.
they develop are between 67 and 75 percent of the
maximum straining actions developed by all unfactored 2 Measurement of the deflections will be carried out by
loading cases. topographic equipment or by deflectometers installed on
scaffoldings independent of the structure as instructed by
2 The straining actions considered do not include any
the Engineer.
load factor magnification.
3 If specified or instructed by the Engineer, additional
3 The test starts by loading the bearings before
measurements may be requested such as the strains in
applying any loads on the spans in order to activate
the steel reinforcement and/or concrete surface.
immediately the bearing deformation, and then the
measured deflections will be significant. 4 Digital recording of measurements by electronic
means is encouraged for important structures, particularly
4 Bridges with simply supported spans shall have the
for strain measurements and moving load testing. It may
loads applied independently on every span.
be imposed by instruction of the Engineer.
5 Bridges with continuous spans shall have the loads
5 The ambient temperature shall be recorded with
applied independently on every span, then on every two
every measurement made.
adjacent spans, with no loads on the others, to obtain the
maximum hogging (negative) bending moment over the 6 A report shall be prepared by the Contractor
support. The latter loading shall be repeated for every including the testing procedure, measurements,
intermediate support. interpretation and conclusion.
6 The loads shall be applied gradually, one truck at a
time. After each load increment, there will be a 5.12.5 Method of Measurement
consolidation period of one hour, or as instructed by the 1 Load testing of the bridge shall be measured by the
Engineer, during which no load is applied. Measurements number of bridges tested as instructed by the Engineer,
shall be recorded at the beginning and end of the loading inclusive of all static load cases and moving load testing
increment period and of the consolidation period. and inclusive of the provision and operation of the loaded
7 Removal of the load shall also be done by equal trucks, measuring and recording equipment of any type
decrements with a consolidation period of one hour, or as and their calibration, platforms and scaffoldings for visual
instructed by the Engineer. Measurements shall be inspection and of accepted testing report.
recorded at the beginning and end of the loading
decrement period and of the consolidation period. 5.12.6 Basis of Payment
5.12.2.3 Testing by Moving Load 1 The amount of completed and accepted work
measured as provided for above shall be paid at the unit
1 Out of the loaded trucks used for static loading of the
rates in the Bill of Quantities. These rates shall be full
bridge, a number shall be selected equal to the number of
compensation for the provision of labor, materials,
traffic lanes. The selection shall consider those with the equipment, tools and other items necessary for proper
heaviest axle loads. The trucks shall travel in one direction
completion of the Work.
along the whole length of the bridge at the largest
possible speed with due consideration of safety measures.
5.12.7 Items in the Bill of Quantities
2 Measurements shall be recorded during passage of
the moving load. i Bridge loading test nr.

5.12.3 Visual Inspection


1 All parts of the structure that can be accessed by
platforms, scaffoldings or other means shall be visually
inspected jointly by the Engineer and the Contractor
before start of testing.
2 During static load testing, visual inspection shall also
be carried out in the consolidation periods at reasonable
at intervals.

♦ 5-68 ♦

S-ar putea să vă placă și