Sunteți pe pagina 1din 39

Ref. Title Page No. Ref. Title Page No.

4.1  Materials for Bituminous 4.2.5.2  Prime Coat Application 4-11 


Construction 4-1 4.2.5.3  Tack Coat Application 4-12 
4.2.5.4  Polymer Modified Tack Coat 4-12 
4.1.1  Description 4-1 
4.2.6 Method of Measurement 4-12
4.1.2  Aggregate Materials Generally 4-1 
4.2.7 Basis of Payment 4-12
4.1.2.1  Sources and Production 4-1 
4.2.8 Items in the Bill of Quantities 4-12
4.1.2.2  Stockpiling 4-1 
4.1.2.3  Sampling and Testing 4-1  4.3 Bituminous Courses 4-12
4.1.3 Aggregates for Bituminous Paving Mixes 4-1
4.3.1 Description 4-12
4.1.4 Aggregates for Seal Coats 4-3
4.3.2 Materials 4-13
4.1.5 Bitumen Generally 4-3
4.3.3 Job Mixes and Project Mixes 4-13
4.1.5.1  Type and Grade 4-3 
4.3.4 Equipment 4-14
4.1.5.2  Transporting Bitumen 4-4 
4.3.4.1  General 4-14 
4.1.5.3  Storage of Bitumen 4-4 
4.3.4.2  Mixing Plant 4-14 
4.1.5.4  Heating of Bitumen 4-4 
4.3.4.3  Spreading and Finishing Equipment 4-14 
4.1.5.5  Sampling and Testing 4-4 
4.3.5 Construction of Trial Sections 4-15
4.1.6 Bitumen Products 4-4
4.3.6 Mixing Procedures 4-15
4.1.6.1  Penetration Graded Bitumen 4-4 
4.3.7 Surface Preparation 4-15
4.1.6.2  Bitumen Modifier and Modified
4.3.8 Delivery, Spreading and Finishing 4-16
Bituminous Material 4-5 
4.3.8.1  Delivery of Mix to Site 4-16 
4.1.6.3  Rapid-Curing (RC) Cutback Bitumen 4-7 
4.3.8.2  Setting Out and Reference Lines 4-16 
4.1.6.4  Medium-Curing (MC) Cutback Bitumen 4-7 
4.3.8.3  Spreading and Finishing 4-16 
4.1.6.5  Slow-Curing (SC) Cutback Bitumen 4-7 
4.3.8.4  Joints and Edges 4-17 
4.1.6.6  Emulsified Bitumens Generally 4-7 
4.3.8.5  Compaction 4-17 
4.1.6.7  Anionic Emulsified Bitumen 4-8 
4.3.9 Sampling and Testing 4-18
4.1.6.8  Cationic Emulsified Bitumen 4-10 
4.3.10 Surface Tolerances 4-20
4.1.7 Method of Measurement and Basis
4.3.11 Determination of Thickness of Courses 4-20
of Payment 4-10
4.3.12 Method of Measurement 4-20
4.2 Prime and Tack coats 4-10 4.3.13 Basis of Payment 4-21

4.2.1 Description 4-10 4.4 Bituminous Base Course 4-21


4.2.2 Materials 4-10
4.4.1 Description 4-21
4.2.2.1  Medium Curing Cutback Bitumen 4-10 
4.4.2 Materials 4-21
4.2.2.2  Rapid-Curing Cutback Bitumen 4-10 
4.4.3 Job Mix and Project Mix 4-21
4.2.2.3  Slow-Curing Emulsified Bitumen 4-10 
4.4.4 Equipment 4-21
4.2.3 Equipment 4-11
4.4.5 Construction of Trial Sections 4-21
4.2.4 Construction of Trial Sections 4-11
4.4.6 Mixing Procedures 4-21
4.2.5 Application Procedures 4-11
4.4.7 Surface Preparation 4-22
4.2.5.1  Medium Curing Cutback Bitumen 4-11

♦ 4-0 ♦
Ref. Title Page No. Ref. Title Page No.
4.4.8 Delivery, Spreading and Finishing 4-22 4.6.6.3  Heating of Bitumen 4-26
4.4.8.1  General 4-22  4.6.6.4  Spreading Slurry Seal 4-26 
4.4.8.2  Rollers 4-22  4.6.6.5  Spraying of Bitumen 4-26 
4.4.8.3  Standard of Compaction 4-22  4.6.6.6  Application of Aggregate 4-26 
4.4.9 Sampling and Testing 4-22 4.6.6.7  Rolling and Brooming 4-27 
4.4.10 Surface Tolerances 4-22 4.6.6.8  Maintenance and Protection of Sealed
4.4.11 Determination of Thickness 4-22 Surfaces 4-27 
4.4.12 Method of Measurement 4-22 4.6.7 Tolerances and Records 4-27
4.4.13 Basis of Payment 4-22 4.6.8 Method of Measurement 4-28
4.4.14 Items in the Bill of Quantities 4-23 4.6.9 Basis of Payment 4-28
4.6.10 Items in the Bill of Quantities 4-28
4.5 Bituminous Binder and Wearing
Courses 4-23 4.7 Bituminous Leveling Course and
Patching Work 4-28
4.5.1 Description 4-23
4.5.2 Materials 4-23 4.7.1 Description 4-28
4.5.3 Job Mix and Project Mix 4-23 4.7.2 Materials 4-28
4.5.4 Equipment 4-23 4.7.3 Job Mix and Project Mix 4-28
4.5.5 Construction of Trial Sections 4-23 4.7.4 Equipment 4-28
4.5.6 Mixing Procedures 4-23 4.7.5 Construction of Trial Sections 4-28
4.5.7 Surface preparation 4-23 4.7.6 Mixing Procedures 4-28
4.5.8 Delivery, Spreading and Finishing 4-23 4.7.7 Surface Preparation 4-28
4.5.8.1  General 4-23  4.7.8 Delivery, Spreading and Finishing 4-29
4.5.8.2  Rollers 4-23  4.7.9 Sampling and Testing 4-29
4.5.8.3  Standard of Compaction 4-24  4.7.10 Surface Tolerances 4-29
4.5.8.4  Skid Resistance and Surface Texture 4-24  4.7.11 Determination of Thickness 4-29
4.5.9 Sampling and Testing 4-24 4.7.12 Method of Measurement 4-29
4.5.10 Surface Tolerances 4-24 4.7.13 Basis of Payment 4-29
4.5.11 Determination of Thickness 4-24 4.7.14 Items in the Bill of Quantities 4-29
4.5.12 Method of Measurement 4-24
4.8 Bituminous Cold Mix Courses 4-29
4.5.13 Basis of Payment 4-24
4.5.14 Items in the Bill of Quantities 4-24 4.8.1 Description 4-29
4.8.2 Materials 4-29
4.6 Bituminous Seal Coats – Surface
4.8.3 Job Mix and Project Mix 4-29
Dressings 4-25
4.8.4 Equipment 4-29
4.6.1 Description 4-25 4.8.5 Construction of Trial Sections 4-29
4.6.2 Materials 4-25 4.8.6 Mixing Procedures 4-30
4.6.2.1  Bitumen 4-25  4.8.7 Surface Preparation 4-30
4.6.2.2  Aggregates 4-25  4.8.8 Delivery, Spreading and Finishing 4-30
4.6.3 Equipment 4-25 4.8.9 Sampling and Testing 4-30
4.6.4 Construction of Trial Sections 4-25 4.8.10 Surface Tolerances 4-30
4.6.5 Rates of Application 4-25 4.8.11 Determination of Thickness 4-30
4.6.6 Construction Requirements 4-25 4.8.12 Method of Measurement 4-30
4.6.6.1  General 4-25 4.8.13 Basis of Payment 4-30
4.6.6.2  Surface Preparation 4-26 4.8.14 Items in the Bill of Quantities 4-30

♦ 4-0 ♦
Ref. Title Page No. Ref. Title Page No.
4.9 Pavement Repairs and 4.12.2 Reference Documents for Profiler
Reinstatement 4-30 Rideability Testing 4-34
4.12.3 Terminology 4-34
4.9.1 Description 4-30
4.12.4 Testing Equipment 4-34
4.9.2 Materials 4-30
4.12.5 Testing Procedure 4-34
4.9.3 Equipment 4-30
4.12.6 Submittals 4-35
4.9.4 Preparation of Pavement 4-30
4.12.7 Required Rideability 4-35
4.9.5 Placing and Finishing Repair Materials 4-31
4.12.8 Method of Measurement 4-35
4.9.6 Sampling and Testing 4-31
4.12.9 Basis of Payment 4-35
4.9.7 Surface Tolerances 4-31
4.12.10 Items in the Bill of Quantities 4-35
4.9.8 Method of Measurement 4-31
4.9.9 Basis of Payment 4-31
4.9.10 Items in the Bill of Quantities 4-32

4.10 Bituminous Pavement Widening 4-32


4.10.1 Description 4-32
4.10.2 Materials 4-32
4.10.3 Construction Requirements 4-32
4.10.3.1 Construction 4-32
4.10.3.2 Traffic Control 4-32
4.10.4 Method of Measurement 4-32
4.10.5 Basis of Payment 4-32
4.10.6 Items in the Bill of Quantities 4-32

4.11 Recycled Bituminous Mixes 4-32


4.11.1 Description 4-32
4.11.2 Materials 4-33
4.11.3 Job Mix and Project Mix 4-33
4.11.4 Equipment 4-33
4.11.5 Construction of Trial Sections 4-33
4.11.6 Mixing Procedures 4-33
4.11.7 Surface Preparation 4-33
4.11.8 Delivery, Spreading and Finishing 4-33
4.11.9 Sampling and Testing 4-33
4.11.10 Surface Tolerances 4-33
4.11.11 Determination of Thickness 4-33
4.11.12 Method of Measurement 4-34
4.11.13 Basis of Payment 4-34
4.11.14 Items in the Bill of Quantities 4-34

4.12 Surface Rideability


Measurement 4-34
4.12.1 Description 4-34

♦ 4-0 ♦
♦ 4-0 ♦
4.1 Materials for Bituminous stockpile quantities. The areas shall be adequately drained
Construction at all times.
2 Stockpiling procedures shall not result in degradation
4.1.1 Description or segregation of the stockpiled material, or introduction
of foreign materials into the stockpile. Heights of
1 This Sub-section includes specifications for materials aggregate stockpiles shall not exceed 5 m.
for use in the construction of the various bituminous
pavement courses including the following: 4.1.2.3 Sampling and Testing
i. Coarse and fine mineral aggregates and filler.
1 Sampling and testing procedures shall conform to
ii. Bitumen products including penetration graded the relevant requirements of this Specification.
bitumens, cutback bitumens, emulsified
2 The Contractor shall submit to the Engineer, 30 days
bitumens, modified bitumens, and rejuvenating
prior to the scheduled start of crushing and screening
agents for use in bituminous courses and surface
operations, a statement of origin and composition of all
treatments.
aggregates proposed for use in the work.
iii. Polymers for bitumen modification, Elastomers
such as Styrene-Butadiene-Styrene (SBS) 3 In order to ascertain the properties of aggregate
copolymers or Plastomers such as Polyethylene materials, the Contractor shall submit for testing,
(PE) polymer, as shown on the drawings. representative samples of all materials intended for
incorporation in the work, prior to starting quarry
2 All materials sources and the quality of materials
operations. The representative samples shall be taken by
proposed for use in the work shall be approved prior to
the Contractor in the presence of the Engineer. Tests shall
procuring or processing material from such sources.
be performed by the Contractor at his laboratory or at an
Inspection, sampling, testing and retesting as necessary,
approved outside laboratory
shall be at the Contractor's expense.
4 Test results shall be utilized by the Contractor in
3 Storage and handling of all materials shall conform
assessing the locations, extent of deposits and quantities
to the relevant requirements of these specifications.
of materials which will conform to the Specification when
Materials shall be stored on hard, clean surfaces.
properly processed. Any special tests that may be required
by the Engineer shall be carried out by the Contractor, in
4.1.2 Aggregate Materials Generally his own laboratory, or an outside laboratory, approved by
4.1.2.1 Sources and Production the Engineer. Engineer’s approval of test results shall in
no way obviate the need for further testing if required by
1 The Contractor shall satisfy himself as to the location the Engineer. Approval of specific sources of materials
of the sources of aggregate materials, the length of haul to shall not be construed as final approval and acceptance of
the site, the suitability and quantity of materials available; materials from such sources.
extent of work necessary to obtain the material available; 5 Processed materials shall be tested and approved
the work required to open the quarry and to crush, screen before being stockpiled on Site or incorporated in the
and wash (if necessary) the materials to meet the specified work and may be inspected and tested at any time by the
gradation. Engineer during their preparation, storage and use.
2 Prior to starting quarry operations, the Contractor Questionable materials awaiting testing and approval,
shall obtain written permission from the authorities or shall not be unloaded and mixed with materials previously
owners concerned. approved. If the grading and quality of any materials
3 Crushing and screening plants shall not be put into delivered to the Site do not conform to the grading and
operation prior to their approval. If, after any plant is put quality of the established control samples, the Engineer
into operation, it fails to perform as intended, the will reject such materials.
Contractor shall either rectify the defects in the existing 6 Samples shall satisfy all specified test requirements.
plant to the satisfaction of the Engineer, or shall provide The Contractor shall permit the Engineer to inspect any
alternative approved plant. and all materials used or to be used, at any time during or
4 Approval of the crushing and screening plants and after their preparation, or while being used during
other equipment shall in no way relieve the Contractor of progress of the work. Unsatisfactory materials, whether in
his responsibilities in respect of producing aggregates place or not, shall be removed promptly from the Site.
which conform to the Specifications and in the quantities The Contractor shall furnish all necessary materials, labor,
required for the completion of the work. tools and equipment and transport required by the
Engineer for such inspections.
4.1.2.2 Stockpiling

1 Stockpile areas shall be surveyed prior to stockpiling


4.1.3 Aggregates for Bituminous Paving
to establish control points and to obtain a record of
Mixes
existing cross sections for future use in determining 1 Aggregates for use in bituminous base course,
binder course, leveling, wearing and cold mix courses

♦ 4-1 ♦
shall consist of crushed stone. The coarse fraction of the 11 Combined coarse and fine aggregates for bituminous
aggregates for use in bituminous wearing course shall mixes, including mineral filler, when tested in accordance
consist of 100% crushed stone from a hard, high quality with AASHTO T 27 and T11, shall conform to the
Gabbro and/or non-vesicular Basalt. gradations shown in Table 4.1.3.3. For the Gradation of
2 Coarse aggregate shall be the fraction of crushed Leveling Course, this should be provided in the Special
aggregate material retained on 4.75 mm (No. 4) sieve. Specifications depending on the particular conditions of
Fine aggregate shall be the fraction of crushed aggregate the Project.
material passing 4.75 mm (No. 4) sieve. Mineral filler shall
Percent passing
be added when the combined grading of coarse and fine Sieve
aggregates is deficient in material passing 0.075 mm (No. Size Base course Wearing course
Binder
200) sieve. (mm) Class Class course Class Class
3 The material from hot bins passing the number 40 A B A B
sieve (0.425mm) when tested in accordance with AASHTO 25 100 100 100 - -
T 90 shall be non plastic. In addition the material from cold 90-
19 60-90 65-100 100 100
bins should not have PI greater than 4. 100
90-
4 Aggregates shall be free of gypsum and the coarse 12.5 - - - -
100
fraction of the aggregate shall not contain more than 5%
9.5 42-67 60-80 47-72 56-80 73-93
chert when tested in accordance with AASHTO T113.
5 Aggregates shall be of uniform quality, free from 4.75 25-50 40-60 30-56 35-56 51-71
decomposed stone, organic matter and shale. 2.36 - 28-48 - - 34-54
6 The percentage by weight of friable particles, clay 2.00 15-31 - 19-36 22-36 -
lumps, and other deleterious matter shall not exceed 1%
1.18 - 20-36 - - 22-38
as determined by AASHTO T 112.
0.600 - 14-26 - - 18-30
7 Aggregate particles shall be clean, hard, durable and
sound. Crushing shall result in a product such that, for 0.425 8-20 - 8-20 8-20 -
particles retained on 4.75 mm (No. 4) sieve, at least 90% 0.300 - 8-20 - - 10-22
by weight shall have 2 or more fractured faces, when
tested in accordance with ASTM D5821. 0.150 - 7-15 - - 9-17

8 The flakiness index and the elongation index test 0.075 2-15 2-8 2-8 2-8 2-8
shall be conducted in accordance with BS 812, the Table 4.1.3.3: Gradation of Aggregates for Bituminous
following are maximum limits: Mixes
Bituminous Bituminous
12 The loss in weight of aggregate after 500 revolutions,
Index Wearing Binder & Base
Course Courses when tested in accordance with AASHTO T 96, shall not
Flakiness Index F.I 25 30 exceed 35% for binder and base courses, and 25% for
Elongation Index E.I 25 30 wearing course.

Table 4.1.3.1: Flakiness and Elongation Indices of 13 When tested for soundness in accordance with
AASHTO T 104 the coarse aggregate (retained on No.4
Aggregates for Bituminous Mixes
sieve) shall not show signs of disintegration and the loss
9 Aggregates shall be washed if directed, to remove by weight after 5 cycles shall not exceed 10% in the case
any clay lumps, organic matter, adherent dust or clay films of the sodium sulfate test and 12% in the case of the
or other extraneous or deleterious matter that may magnesium sulfate test.
prevent or detract from proper adhesion of bitumen to the 14 When tested for resistance to stripping in accordance
aggregate particles. with the AASHTO T-182 at least 95% coated particles
10 Mineral filler shall consist of finely divided mineral should be achieved. If resistance to stripping is not
matter such as limestone dust, hydrated lime; other non- achieved then anti-stripping agent should be used. For
plastic mineral filler, free from clay and organic impurities; additional stripping resistance requirements for wearing
or Portland cement, conforming to AASHTO M 17. The course layer, refer to Sub-section 4.5.
gradation of the mineral filler shall comply with the 15 Polish stone value (PSV) of coarse aggregates used
requirements of Table 4.1.3.2: in the wearing course mix when tested according to BS
812 shall be at least 60%.
Sieve Size Percent Passing by Mass
16 The sand equivalent for fine aggregates, when tested
0.600 mm (No. 30) 100
in accordance with AASHTO T45, shall be a minimum of
0.300 mm (No. 50) 95 - 100
75.
0.075 mm (No. 200) 70 - 100
Table 4.1.3.2: Gradation of Mineral Filler for Bituminous
Mixes

♦ 4-2 ♦
4.1.4 Aggregates for Seal Coats 7 The loss in weight of aggregate after 500 revolutions,
when tested in accordance with AASHTO T 96 (Los
1 Cover aggregates for bituminous seal coats shall Angeles Test), shall not exceed 35%.
consist of screenings of crushed stone. Aggregate for
8 When tested for soundness in accordance with
slurry seals shall consist of crushed stone fines or natural
AASHTO T 104, the aggregates shall not show signs of
sand blended with not less than 50% crushed stone fines.
disintegration and the loss by weight shall not exceed 10%
For heavy-duty applications slurry aggregate shall consist
in the case of the sodium sulphate test or 12% in the case
of 100% crushed fines. Wadi gravels shall not be used for
of the magnesium sulphate test.
seal coats, suitability of suggested crushed stone fines for
use in slurry seal shall be demonstrated prior to use. 9 When tested for resistance to stripping in accordance
with AASHTO T 182, at least 95% of the aggregate surface
2 Aggregates shall be free of crystalline or amorphous
area shall remain coated with a bitumen film. If resistance
gypsum (expressed as SO3), and shall not contain more
to stripping is not achieved then anti-stripping agent
than 5% chert when tested in accordance with AASHTO
should be used.
T113.
10 Polish stone value (PSV) of coarse aggregates used
3 Aggregate particles shall be clean, hard, durable and
in the upper layer of seal coats when tested according to
sound. For particles retained on 4.75 mm (No. 4) sieve, at
BS 812 shall be at least 60%.
least 90% by weight shall have 2 or more fractured faces
and 100% by weight shall have one or more fractured 11 The sand equivalent for fine aggregates, when tested
faces, when tested in accordance with ASTM D5821. in accordance with AASHTO T45, shall be a minimum of
75.
4 Flakiness index and elongation index tested in
12 Table 4.1.4.2 below summarizes the required
accordance with BS 812 shall not exceed 25% for each of
aggregate properties listed under items 7 to 11 above:
flakiness and elongation index. The percentage by weight
of clay lumps and friable particles as determined by Standard Test Specification
Aggregate Property
AASHTO T 112 shall not exceed 3%. Light weight Method Requirements
aggregate of specific gravity of 2 or less shall not exceed Loss in weight of
3% as determined by AASHTO T 113. aggregate after 500
5 If necessary aggregates shall be washed, or revolutions AASHTO T96 Max. 35%
processed by an approved alternative method, to remove (Los Angeles
any clay lumps, organic matter, adherent dust or clay films Abrasion)
or other extraneous or deleterious matter that may
Soundness in
prevent or detract from proper adhesion of bitumen to the AASHTO T 104 Max. 10%
Sodium Sulphate
aggregate particles.
6 Cover aggregates and aggregate for slurry seals, Soundness in
when tested in accordance with AASHTO T 27 and T 11, Magnesium AASHTO T 104 Max. 12%
Sulphate
shall conform to the gradations given in Table 4.1.4.1.
Resistance to
Double Bituminous Surface AASHTO T 182 Min. 95%
Sieve stripping
Treatment Aggregate Slurry
Designation Polish Stone Value
1st 2nd Aggregat
(Square Application Application e (PSV) of coarse BS 812 Min. 60%
openings) (Grading B) (Grading C) aggregates

25 mm 100 - - Sand Equivalent for


AASHTO T175 Min. 75
Fine Aggregate
19 mm 90-100 - -
12.5 mm 20-55 100 - Table 4.1.4.2: Properties of Aggregates for Seal Coats

9.5 mm 0-15 58-100 100


4.1.5 Bitumen Generally
4.75 mm 0-5 10-30 90-100
4.1.5.1 Type and Grade
2.36 mm - 0-10 65-90
1.18 mm - 0-5 45-70 1 Bitumen shall be petroleum derivative penetration
grade 60-70 (unless otherwise shown in the Special
0.60 mm - - 30-50 Specification), conforming to the requirements of
0.30 mm - - 18-30 AASHTO M20. When more than one type or grade is
specified under any item, the Engineer will select the type
0.15 mm - - 10-20
and grade to be used in the work. If the specified grade is
0.075 mm 0-0.5 0-0.5 5-15 not locally available in the market, the Contractor shall be
Table 4.1.4.1: Gradation of Aggregates for Seal Coats deemed to have considered any additional costs
associated with the import of bitumen in his contract price.

♦ 4-3 ♦
4.1.5.2 Transporting Bitumen temperature of bitumen, weigh buckets, spray bars, and
other containers.
1 All transporting of bitumen shall be by conveyances
3 Thermometers of approved type and adequate range
that are free from contamination. Tank cars or tank trucks
(calibrated in 2 degrees C increments) for accurately
used for transporting bitumen shall be carefully inspected,
measuring the temperature of the bitumen while heating,
drained, and cleaned if necessary, before loading, to
shall be located so as to be readily visible and shall be
prevent contamination of the bitumen from residues of
kept clean and in proper working order at all times.
previous loads. Bitumen may also be delivered and
transported in metal drums. 4 Where storage tanks are required, their capacity shall
be sufficient for at least one day's production.
2 Tank trucks or trailers used to transport bitumen shall
be equipped with an approved sampling device which 5 Bitumen materials, wasted through careless handling
shall be built into the tank or re-circulating or discharge or rendered unsuitable for use by overheating shall not be
line in such a manner that a sample can be drawn during used in the work.
circulation or discharge.
4.1.5.5 Sampling and Testing
4.1.5.3 Storage of Bitumen
1 Procedures for sampling of bituminous materials
1 The Contractor shall provide an adequate storage shall conform to AASHTO T 40.
facility for bitumen, at the site of the mixing plant. This 2 General requirements and procedures for sampling
facility shall be clean and stable and provided with cover and testing of the various types of bitumen shall conform
and shelter from excessive temperatures. to the requirements of the relevant sections of these
2 No open fires or smoking shall be allowed in or specifications.
around the storage facility. 3 Testing for conformity of bitumen products shall be
3 The storage capacity shall be sufficient to maintain a carried out to AASHTO Standard Methods listed in
uniform operation while allowing for delayed shipments AASHTO M 20 and other specified standards.
and time for testing. Different batches of bitumen shall be
separated, so as to allow for easy identification. 4.1.6 Bitumen Products
4 If the bitumen is delivered to the site in metal drums, 4.1.6.1 Penetration Graded Bitumen
on arrival the drums shall be inspected for perforations,
rusting, melting or any other defects that could cause 1 The various grades of penetration graded bitumen
pollution or chemical changes to the bitumen. material shall conform generally with the requirements of
AASHTO M 20 as given in Table 4.1.6.1.
Depending on the severity of each case, the Engineer shall
decide whether to retain or reject the affected drums. Penetration Grade
5 The stored bitumen products should be protected
40 - 50 60 - 70 80 - 100
from temperatures which may exceed the range of -5 Requirement
degrees C to +50 degrees C. Min Max Min Max Min Max

4.1.5.4 Heating of Bitumen Ductility at 25 ̊C


100 - 100 - 100 -
(cm)
1 Heating equipment shall be of an approved type. Kinematic Viscosity
280 - 240 - 200 -
Any method of agitation or heating that introduces free at 135 ̊C (cSt)
steam or moisture into the bitumen will not be approved. Penetration at 25 ̊C
40 50 60 70 85 100
(0.1mm)
During the process of its manufacture, conveyance,
storage, or construction use, bitumen of whatever type Softening Point ( ̊C) 50 58 48 56 46 48
shall not be heated to temperatures more than 10 degrees Specific Gravity at
1.01 1.06 1.01 1.06 1.0 -
C above the maximum application temperature specified 25 ̊C
Loss on heating to
for the respective type of bitumen nor above 170 degrees - 0.8 - 0.8 - 1.0
163 ̊C (% wt)
C, whichever is the lower. Materials heated in excess of
Penetration of
these temperatures will be rejected and shall not be used residue % of 58 - 54 - 50 -
in the work. original
2 Tanks for heating and storage of bitumen shall be Solubility in
capable of heating the material, under effective and Trichloroethylene 99 - 99 - 99 -
(% wt)
positive control at all times, to the specified temperature.
The system shall provide uniform heating for the entire Ash content (% wt) - 1.0 - 1.0 - 1.0
contents of the tank. The circulation system shall be of Flashpoint
adequate size to ensure proper and continuous circulation (Cleveland Open 250 - 250 - 225 -
of the bitumen during the entire operating period. Cup) ( ̊C)
Suitable means shall be provided, either by steam or oil
Table 4.1.6.1: Properties of Penetration Grade Bitumen
jacketing, or other insulation, for maintaining the required

♦ 4-4 ♦
2 Sampling and testing shall be in accordance with the i. Compatibility with original bitumen: The
AASHTO standard method listed in AASHTO M 20. modified bitumen shall be tested for
3 Penetration bitumen application temperature range compatibility with the polymer modifier to
shall be as given in table 4.1.6.2. Actual Mixing and ASTM D5892 for both softening point and
Compacting Temperature of Asphalt Concrete shall be dynamic shear (DSR). The difference in deg C
determined from Kinematic Viscosity of Bitumen as shown between the softening points of the respective
in MS-2. top and bottom portions of the tube sample
shall not exceed 4 deg C. The separation ratio
Pen 40/50 60/70 80/100 based on G* shall have an average G* value
Application [(top + bottom) / 2] within 0.8 to 1.2 of the
150-170 145-165 140-160
Temperature ( ̊C) initial G* value. Alternative compatibility test
Table 4.1.6.2: Application Temperature by Bitumen Grade according to ASTM D5841 can be carried out in
lieu of ASTM D5892, only in cases where the
4.1.6.2 Bitumen Modifier and Modified Bituminous Contractor and supplier can prove that the
Material ASTM D5892 cannot be adopted for the type of
polymer proposed.
1 An approved modifier shall be incorporated in all
penetration graded bituminous material immediately prior
to the time of use, unless otherwise shown on the ii. Mixing and compaction temperatures: The
Drawings. mixing and compaction temperatures shall be
established in the laboratory by determining
2 The types and penetration grades of the original
the Brookfield viscosity of the approved
bituminous materials shall be submitted by the polymer
polymer modified bitumen at three different
supplier/contractor for the Engineer’s approval.
temperatures 135 deg C, 165 deg C and 195
3 The Contractor shall provide evidence of his deg C. The established mixing and compaction
experience to prove that he is currently supplying and temperatures shall then be evaluated and
using polymer modified bitumen on similar projects with finalized based upon successful site trials.
successful results and performance. The Contractor shall
submit data, which indicate that the product has a proven
iii. Proportion of modifier in the mix: Depending
record of performance regarding compatibility with
upon the results of the tests specified in Table
asphaltic concrete mixtures, blending of the product with
4.1.6.3 below, the proportion of modifier to be
the asphalt cement and placing and compacting the
used and the quality control procedures during
mixture.
mixing shall be determined in accordance with
4 The modified bitumen shall demonstrate significantly the manufacturer’s recommendations to
reduced temperature susceptibility and/or improved provide the optimum characteristics of the mix
adhesive qualities. The workability of the modified as specified below.
bitumen shall be unchanged from that of unmodified
7 The minimum requirements and tests to be
bitumen.
performed on the modified bitumen shall be as follows:
5 Unless specified otherwise under this Specification,
mixing and preparation of modified bitumen shall be
carried out in accordance with the modifier manufacturer’s i. If Styrene-Butadiene-Styrene (SBS) polymer is
instructions, and to the approval of the Engineer. used, it shall have the following properties:
- Butadiene-Styrene Ratio = 70/30.
6 The Contractor shall submit a method statement for
- Block Styrene = 30%.
the preparation of polymer modified bitumen (PMB)
- Hardness Shore A = 80.
blending, including the type of polymer intended for use,
- Density ASTM D792 = 0.93 – 0.95 g/cm3.
for the Engineer’s approval. The Contractor shall propose
the type of polymer he intends to use and shall ii. If Polyethylene polymer is used, it shall be
demonstrate through testing that the modified asphalt polyolefinic, primarily low density polyethylene
meets all the specification requirements. Blending of the and shall meet the following requirements:
asphalt cement and the modifier shall be done by the
Test Property Criterion Specification
supplier of the modifier in a mobile mixing plant adjacent
to the Contractor’s asphalt plant on Site. The Contractor Density 0.910 min ASTM D 792
shall submit for the Engineer’s approval a comprehensive
0.940 max
QA/QC program to ensure that the pre-blended polymer
modified asphalt is delivered, stored in suitable conditions, Melt Index 1.0 – 15.0 ASTM D 1238
incorporated in the bitumen mix and laid in strict
accordance with the manufacturer’s instructions. The Melting Point 110° – 135° C
minimum requirements for this program shall include but iii. The ratio of modifier to bitumen in the
shall not be limited to the following: completed mix shall be between 4 and 8 parts
of modifier for 100 parts of bitumen, according

♦ 4-5 ♦
to the manufacturer’s recommendations, which
must confirm that the modified bitumen will
meet the requirements of Table 4.1.6.3 and will
prove the optimized properties of the modified
binder at the proposed proportion of modifier.

iv. The modified bitumen properties shall comply


with the requirements of the latest revision of
AASHTO M320 specifications and to the
requirements of Table 4.1.6.3 below.

v. The Contractor shall obtain from the


manufacturer and provide to the Engineer
periodical certificates stating that the modifier
is being incorporated in the bitumen mix in
accordance with the with the approved QA/QC
program.

Frequency of
Ref Property Test Standard Requirements
Testing
to be agreed with the
1. Penetration, 25° C, 100g, 5s, dmm ASTM D5 at each batch
Manufacturer
ASTM D36,
2. Softening Point, °C Min. 65 at each batch
AASHTO T53
3. Viscosity (Brookfield) at 135° C, max °C ASTM D4402 3000 CP at each batch
4. Flash Point Temp, min °C AASHTO T48 230 °C every 500 t
Dynamic Shear before RTFOT, G*/sin ∂,
Min. 1.00 kPa, test temperature @ 10
5. AASHTO TP5 76 °C every 500 t
rad/s, °C, (Where G* = Dynamic Shear
Modulus and ∂ = phase angle)
Rolling Thin Film Oven (RTFO) Mass
6. AASHTO T240 1% at each batch
Loss, max, %
1
Elastic Recovery , 25° C, 10cm ASTM D6084,
7. 75 at each batch
elongation, % after RTFOT AASHTO T301

Dynamic Shear after Rolling Thin Film


8. Oven Test (RTFOT), G*/sin ∂, Min. 2.2 AASHTO TP5 76 °C every 500 t
kPa, test temperature @ 10 rad/s, °C
See requirements
9. Compatibility Test ASTM D5892 under Item 6 of every 500 t
Paragraph 4.1.6.2

Table 4.1.6.3: Modified Bitumen (Performance Grade)


Properties

Continued on page 4-7

♦ 4-6 ♦
8 The elastic recovery specified under Item 7 of Table RC Cutback Spraying
4.1.6.3 above corresponds to modified bitumen with either Grade Temp °C
an elastomer or a blend of elastomer and plastomer
RC - 70 40 - 75
polymers. Should the Contractor opt to use plastomer
type polymer only, for the asphalt modification, then the RC - 250 65 - 105
elastic recovery requirement can be replaced by a set of RC - 800 90 - 115
tests that shall be carried out at the start of the project,
RC - 3000 105 - 135
with each set containing three samples, and the results
shall conform to the following Table 4.1.6.4: 4.1.6.4 Medium-Curing (MC) Cutback Bitumen

Property Test Standard Requirements 1 MC cutback shall conform to the requirements of


AASHTO M 82, which covers Grades MC-30, MC-70, MC-
Pressure Aging Vessel Residue 250, MC-800 and MC-3000 and are listed in Table 4.1.6.6.
2 Sampling and testing shall be in accordance with the
Pressure Aging AASHTO standard methods listed in AASHTO M 82.
Vessel (PAV)
AASHTO R28 110 °C 3 MC cutback bitumen spraying temperature ranges
Aging
Temperature, °C. shall be as follows:
Dynamic Shear, MC Cutback Spraying
G*sin∂,
Grade Temp °C
Maximum 5000
37 °C
kPa, AASHTO T315 MC - 30 21 - 63
Test temperature
@ 10 rad/s, °C. MC - 70 45 - 80
Physical MC - 250 70 - 110
Report
Hardening
Creep Stiffness, MC - 800 95 - 125
S, Maximum 300 MC - 3000 110 - 145
MPa m-value,
0 °C
minimum 0.300 AASHTO T313 4.1.6.5 Slow-Curing (SC) Cutback Bitumen
Test temperature
@ 60 s, °C. 1 SC cutback shall conform to the requirements of
Direct tension, ASTM D 2026 which covers Grades SC-70, SC-250, SC-800,
Failure strain, and SC-3000, and are shown in Table 4.1.6.7.
minimum 1.0%
AASHTO T314 0 °C 2 Sampling and testing shall be in accordance with the
Test temperature
appropriate ASTM standard methods.
@ 1.0 mm/min,
°C. 3 SC cutback bitumen spraying temperature ranges
Table 4.1.6.4: Additional Tests Required for Plastomer shall be as follows:
Type Polymer SC Cutback Spraying
Grade Temp °C
9 The percentage of the polymer to be mixed with the
conventional bitumen to modify the latter shall be based SC - 70 45 - 80
on tests to satisfy the job mix formula. SC - 250 70 - 110
10 The modifier shall be pre-blended into the SC - 800 95 - 125
conventional bitumen before mixing with the aggregate in
the hot mix plant. SC - 3000 110 – 145

11 Blending Equipment: The production of the modified 4.1.6.6 Slow-Setting (SS and CSS) Emulsified
bitumen shall require a specialized high shear blending Bitumens Generally
machinery to ensure complete and controlled dispersion
and chemical reaction of the modifiers with the 1 Selection and use of emulsified bitumens shall
conventional bitumen. generally be in accordance with the recommendations in
AASHTO R 5, subject to the following requirements.
4.1.6.3 Rapid-Curing (RC) Cutback Bitumen
2 The manufacturer shall furnish samples of the base
1 RC cutback shall conform to the requirements of bitumen used in the emulsion.
AASHTO M 81, which covers Grades RC-70, RC-250, RC- 3 When samples of undiluted emulsion are not readily
800, and RC-3000 and are listed in Table 4.1.6.5. available for test purposes, tests may be made on the
2 Sampling and testing shall be in accordance with the diluted emulsion and the respective specifications
AASHTO standard methods listed in AASHTO M 81. modified to reflect the changes in properties resulting
from dilution of the bitumen.
3 RC cutback bitumen spraying temperature ranges
shall be as follows:

♦ 4-7 ♦
4 All emulsified bitumens shall adhere firmly to the
surface of the mineral aggregate or the highway surface
as appropriate. Failure of the emulsified bitumen to
perform satisfactorily on the job shall be deemed cause
for its rejection regardless of satisfactory laboratory test
results.

4.1.6.7 Anionic Slow-Setting (SS) Emulsified Bitumen

1 Anionic emulsified bitumens shall, prior to dilution,


conform to the requirements of AASHTO M 140, for Types
SS-1 and SS-1h and as listed in Table 4.11.
2 Sampling and testing shall be in accordance with
AASHTO T 59.
3 Emulsified bitumen spraying temperature range shall
be set so that appropriate viscosity for each application is
achieved, if specific viscosity curves are not available the
range values, generally considered as guidance, shall be
25 - 65 degrees C. The temperature range for pugmill
mixing for medium and slow setting types shall be 15-65
degrees C.

RC-70 RC-250 RC-800 RC-30


Parameter/Test
Min Max Min Max Min Max Min Max
Kinematic Viscosity at 60 oC
70 140 250 500 800 1600 3000 6000
centistokes
Flash Point (Tag, open-cup) oC - - 27 - 27 - 27 -
Water percent - 0.2 - 0.2 - 0.2 - 0.2
Distillation Test:
Distillate percentage by volume of total
distillate to 360 oC
To 190 oC 10 - - - - - - -
To 225 oC 50 - 35 - 15 - - -
To 260 oC 70 - 60 - 45 - 25 -
To 315 oC 85 - 80 - 75 - 70 -
Residue from distillation to 360 oC volume
55 - 65 - 75 - 80 -
percentage of sample by difference
Tests on residue from distillation:
Absolute viscosity at 600 2400 600 2400 600 2400 600 2400
60 oC poises
Ductility, 5 cm/min.
100 - 100 - 100 - 100 -
at 25 oC cm
Solubility in Trichloroethylene,
99 - 99 - 99 - 99 -
percent
Spot test with:
- Standard Naphta Negative for all grades
- Naphtha-xylene solvent,
Negative for all grades
percent xylene
- Heptane-xylene solvent,
Negative for all grades
percent xylene

Table 4.1.6.5: Properties of R.C. Cutback Bitumen

♦ 4-8 ♦
MC-30 MC-70 MC-250 MC-800 MC-3000
Parameter/Test
Min Max Min Max Min Max Min Max Min Max

Kinematic Viscosity at 60 °C
30 60 70 140 250 500 800 1600 3000 6000
centistokes
Flash Point (Tag, open-cup) °C 38 - 38 - 66 - 66 - 66 -
Water percent - 0.2 - 0.2 - 0.2 - 0.2 - 0.2
Distillation Test:
Distillate percentage by
volume of total distillate to
360 °C
To 225 °C - 25 0 20 0 10 - - - -
To 260 °C 40 70 20 60 15 55 0 35 0 15
To 315 °C 75 93 65 90 60 87 45 80 15 75
Residue from distillation to
360 °C volume percentage of 50 - 55 - 67 - 75 - 80 -
sample by difference
Tests on residue from
distillation:
300 1200 300 1200 300 1200 300 1200 300 1200
Absolute viscosity at 60 °C
poises
Ductility, 5 cm/min. at 25 °C
100 - 100 - 100 - 100 - 100 -
cm
Solubility in Trichloroethylene,
99 - 99 - 99 - 99 - 99 -
percent
Spot test with:
- Standard Naphtha Negative for all grades
- Naphtha-xylene solvent,
Negative for all grades
percent xylene
- Heptane-xylene solvent,
Negative for all grades
percent xylene

Table 4.1.6.6: Properties of M.C. Cutback Bitumen

SC-70 SC-250 SC-800 SC-3000


Parameter/Test
Min Max Min Max Min Max Min Max
Kinematic Viscosity at 60 °C
70 140 250 500 800 1600 3000 6000
cSt
Flash Point (Cleveland open
66 - 79 - 93 - 107 -
cup) degrees °C
Distillation Test:
10 30 4 20 2 12 - 5
total distillate to 360 °C
Volume % Solubility in
99 - 99 - 99 - 99 -
trichloroethylene %
Kinematic viscosity on
4 70 8 100 20 160 40 350
distillation residue at 60°C,St
Asphalt residue:
50 - 60 - 70 - 80 -
Residue of 100 penetration, %
Ductility of 100 penetration 100 - 100 - 100 - 100 -

residue at 25°C, cm Water, % - 0.5 - 0.5 - 0.5 - 0.5

Table 4.1.6.7: Properties of S.C. Cutback Bitumen

♦ 4-9 ♦
range values, generally considered as guidance shall be
25-65 degrees C. The temperature range for pugmill
Slow-Setting
mixing for medium and slow setting types shall be 15-65
SS-1 SS-1h degrees C.
Min Max Min Max
Viscosity, Saybolt 4.1.7 Method of Measurement and Basis of
20 100 20 100
Furol at 25 °C, s Payment
Storage stability
- 1 - 1 1 No separate measurement and no items are included
test, 24-h, %
in the Bill of Quantities for the materials described in this
Cement mixing test,
- 2 - 2 Sub-section. Measurement and payment provisions are
%
included in the appropriate Sub-sections of this Section 4.
Sieve test, % - 0.1 - 0.1
Residue by
57 - 57 - 4.2 Prime and Tack coats
distillation, %
Tests on residue
from distillation 4.2.1 Description
100 200 40 90
test: Penetration, 25
1 This Sub-section describes requirements for
°C,100 g, 5 s
furnishing and applying MC cutback bitumen prime coat
Ductility, 25°C, 5 to a previously constructed sub-base or aggregate base
cm/min, cm 40 - 40 - course, highway shoulders, or concrete pavement; and
furnishing and applying RC cutback bitumen or emulsified
Solubility in bitumen as a tack coat to a previously constructed
trichloroethylene % 97.5 - 97.5 - bituminous base or wearing surface to provide bond for a
superimposed bituminous course; all as and where shown
Table 4.1.6.8: Properties of Anionic Emulsified Bitumen on the Drawings.

4.1.6.8 Cationic Slow-Setting (CSS) Emulsified 4.2.2 Materials


Bitumen
4.2.2.1 Medium Curing Cutback Bitumen
1 Cationic emulsified bitumens shall, prior to dilution,
1 MC cutback bitumen (for prime coats) shall be as
conform to the requirements of AASHTO M 208, for Types
recommended by ASTM D 2399. Generally MC 70 shall be
CSS-1 and as listed in Table 4.1.6.9.
used unless otherwise specified.
Slow Setting
4.2.2.2 Rapid-Curing Cutback Bitumen
CSS-1
Min Max 1 RC cutback bitumen (for tack coats) shall be Grades
Tests on emulsions: RC-70 or RC-250 as appropriate and as specified in Sub-
Viscosity, Saybolt Furol at 20 100 section 4.1 – ‘Materials for Bituminous Construction’, or as
25°C, s required by the Engineer.
Storage stability test, 24-h,
1 - 4.2.2.3 Slow-Setting Emulsified Bitumen
%
Particle charge test Positive 1 Slow-setting emulsified bitumen (for tack coats)
Sieve test, % - 0.10 shall be slow setting Grades SS-1, SS-1h or CSS-1, as
Cement mixing test, % - 2.0 appropriate and as specified in Sub-section 4.1 –
Distillation: ‘Materials for Bituminous Construction’, or as required by
57 -
Residue, % the Engineer.
Tests on residue from
distillation test: 100 250 4.2.2.4 Polymer Modified Bituminous Tack Coat
Penetration, 25°C, 100 g, 5 s 1 The polymer modified tack coat material shall be as
Ductility, 25°C, 5 cm/min, cm 40 - specified in Sub-section 4.1, the original base binder
Solubility in (before polymer modification) shall be penetration grade
97.5 -
trichloroethylene % bitumen and the polymer modified bitumen binder shall
Table 4.1.6.9: Properties of Cationic Emulsified Bitumen be as specified under paragraph 4.1.6.2. The viscosity of
the binder used for the polymer modified tack coat
2 Sampling and testing shall be in accordance with
(Brookfield viscosity determined as per ASTM D4402) at
AASHTO T 59.
application temperature shall range between 200 and 400
3 Emulsified bitumen spraying temperature range shall
CP. The softening point and elastic recovery at 25° C (after
be set so that appropriate viscosity for each application is
RTFOT) of the polymer modified tack coat shall not be less
achieved, if specific viscosity curve is not available the
than 80° C and 90% respectively.

♦ 4-10 ♦
4.2.3 Equipment 5 Traffic shall not be permitted on surfaces after they
have been cleaned and prepared for prime or tack coat
1 Equipment used for diluting emulsified bitumen,
application.
heating cutback bitumen, spraying cutback and emulsified
bitumen, and for application of blotting material to prime 6 If there are undue delays in scheduling priming or
coats, shall conform with the relevant requirements of this subsequent paving after priming, the surface tolerances
Specification and with the Contractor's approved list of and compaction of the granular course shall be re-verified
equipment. and deficient areas corrected or replaced in an approved
manner at the Contractor's expense.
7 The Contractor shall maintain prime coats and tack
4.2.4 Construction of Trial Sections coats intact until they are covered by the subsequent
1 The Engineer may require trial sections to be pavement course. Any area where the coats have been
constructed prior to the commencement of on-site prime damaged shall be cleaned of all loose material, any
or tack coat applications. The Contractor shall construct surface defects repaired and the coat re-applied at the
trial sections using varying application rates of bitumen, Contractor's expense. Traffic control measures shall
as selected by the Engineer. Each trial section shall be 2 conform to the requirements of the relevant Sections of
lanes wide by 50 m long, at approved locations on or close this Specification.
to the site.
4.2.5.2 Prime Coat Application
2 Each trial section shall be constructed using the same
materials, mixing and spraying equipment, and 1 If required by the Engineer, when the surface is an
construction procedures, proposed for use in the Works. untreated subgrade or a granular surface, the cleaned
3 The objectives of these trials shall be to determine surface shall be given a light application of water and
the adequacy of the Contractor's equipment and the most allowed to dry to the condition deemed appropriate by the
suitable application rates for cutback bitumen prime and Engineer before the bituminous material is applied.
tack coats, or emulsified bitumen tack coats. 2 Heating of MC cutback bitumen and its temperature
4 The Contractor shall not proceed with any on-site at the time of application shall conform to the relevant
coat applications until the methods and procedures requirements of Sub-section 4.1.
established in the trials have been approved. 3 Areas to be primed shall be as shown on the
Drawings and including 200 mm widths outside the edges
4.2.5 Application Procedures of the pavement line; top of embankment slopes to
pavement lines; and between curbs or gutter edges for
4.2.5.1 Medium Curing Cutback Bitumen bridge checks.
1 All equipment used for surface cleaning, heating 4 Application rates for prime coat will be determined
bitumen (if required) and application of prime and tack by the Engineer from the trial sections, and shall be
coats, shall be adequate for the purposes intended and generally within the following ranges:
shall be approved before use.
Range of Application Rates for Prime Coat
2 All surfaces to receive prime or tack coats shall
conform to the specified tolerances and compaction Type of Surface kg./sq.m.
requirements and shall be properly cleaned using power Untreated subgrade surfaces,
brooms or power blowers. The surfaces shall be 0.8 - 1.75
shoulders sub-base and base courses
approved before applying any bitumen material.
Bridge wearing surfaces, asphalt
3 Application of prime coats and tack coats shall be overlay on existing concrete 0.1- 0.4
performed only when the surface to be treated is pavements
sufficiently dry for tack coat and sufficiently moist for as determined
prime coat, and when the atmospheric temperature is Other surfaces from field tests
above 10ºC for the application of tack coat, 15ºC for the or trials
application of prime coat. No application is to be
Table 4.2.5.1: Range of Application Rates for Prime Coat
performed if there is fog, rain, strong winds, dusty
conditions, or dust storms. 5 The Engineer may order additional trial sections
4 The surfaces of all structures, curbs, gutters and and/or alter the previously established rates of application
other highway appurtenances shall be protected in an during progress of the work.
approved manner to prevent them from being splattered 6 Prime coat (MC-70) cutback, or other grade if ordered
or stained with bitumen or damaged during equipment by the Engineer, shall be applied at the rate selected by
operation. The Contractor shall be responsible for making the Engineer, using approved type pressure distributors
good any such staining or damage to the satisfaction of operated by skilled workmen. The spray nozzles and
the Engineer. spray bar shall be adjusted and frequently checked so that
uniform distribution is ensured. Spraying shall cease
immediately upon any clogging or interference of any

♦ 4-11 ♦
nozzle, and corrective measures taken before spraying is to the satisfaction of the Engineer. The rate of application
resumed. shall be between 0.25 and 0.5 kg./sq.m.
7 Hand spraying will be approved only for priming 2 The polymer modified tack coat shall be applied at a
small patches or inaccessible areas that cannot be primed temperature ranging from 180° C to 190° C.
by normal operation of the pressure distributor.
8 Application of prime at the junction of spreads shall 4.2.6 Method of Measurement
not be excessive. Any excess shall be removed from the 1 Bituminous prime coat shall be measured by the
surface and any skipped areas or recognized deficiencies square meter of the areas shown on the cross section at
shall be corrected by use of hand sprays. the appropriate rate specified by the Engineer.
9 When required by the Engineer, a light covering of
2 Bituminous tack coat shall be measured by the
blotting material shall be applied to the prime coat 48
square meter of the areas shown on the cross section at
hours after spraying and when it has not dried sufficiently
the appropriate rate specified by the Engineer.
to withstand damage by traffic. The blotting material shall
be smooth fine sand, or other approved material. 3 Polymer Modified Bituminous tack coat shall be
measured by the square meter of the areas shown on the
10 Prime coats shall be cured for 3 days before
cross section at the appropriate rate specified by the
construction traffic is allowed on it or before the
Engineer.
succeeding pavement layer is placed, or as directed by the
Engineer, depending on weather conditions. 4 Surface preparation, protective measures to avoid
staining or damage to appurtenances, blotting of prime
4.2.5.3 Tack Coat Application coats when required, and cleaning stains and repairing
damage caused by equipment, priming or spraying tack
1 Tack coat shall be applied to the areas shown on the
coat at areas outside the edge of the pavement line, etc.,
Drawings on clean dry surface, and the rate shall be as
shall not be measured for direct payment, but shall be
ordered by the Engineer. Emulsified bitumen shall be
considered as subsidiary work, the costs of which are
diluted and thoroughly mixed with an equal amount of
deemed to be included in the rates stated in the Bill of
water before application.
Quantities.
2 Heating of RC cutback bitumen and its temperature at
the time of application shall conform to the relevant 4.2.7 Basis of Payment
requirements of Sub-section 4.1 ‘Materials for Bituminous
Construction’. Where slow-setting emulsified bitumen (SS 1 The amount of completed and accepted work,
or CSS Type) is used for tack coat, it shall not normally measured as provided for above, will be paid for at the
require heating except in temperatures below 20 degrees unit rates for the various items in the Bill of Quantities ,
C. which rate shall be full compensation for supplying
materials, transporting and placing, labor, equipment,
3 The rate of application shall be approved by the
tools and other items necessary for the proper completion
Engineer and after trial tests are carried out it shall be
of the work.
between 0.1 and 0.5 kg./sq.m, depending on whether RC
cutback or emulsified bitumen is used and on the surface
condition of the bituminous course on which the tack coat 4.2.8 Items in the Bill of Quantities
is to be sprayed. The resulting bitumen residue shall be at i. Bituminous prime coat.
least 0.35 kg./sq.m. The Engineer may alter the previously ii. Bituminous tack coat.
established rates of application during progress of the
iii. Polymer modified tack coat.
work, if he deems it necessary.
4 The tack coat shall be allowed to dry only until it is in
4.3 Bituminous Courses
a suitable tacky condition to receive the superimposed
bituminous course. Tack coat application shall not
proceed so far in advance of the following course that it
4.3.1 Description
dries out completely. 1 This Sub-section describes requirements for
5 Spraying procedures shall be as specified for prime furnishing materials, mixing at a central mixing plant, and
coat application. spreading and compacting various bituminous concrete
and other bituminous mixes, all as and where shown on
6 Blotting material shall not be applied to tack coats.
the Drawings.
4.2.5.4 Polymer Modified Tack Coat 2 Requirements with particular application to
bituminous base course, binder and wearing courses,
1 Polymer modified tack coat shall be hot applied over
leveling course, cold mix courses or recycled bituminous
the prepared polymer modified or unmodified bituminous
courses are specified in the respective Sub-sections
layers to receive the polymer modified bituminous layer,
relating to such courses.
as indicated on Drawings. The type of tack coat and its
rate of application shall be compatible with the polymer
modified bituminous layer that will be applied on top of it,

♦ 4-12 ♦
4.3.2 Materials 7 In order to meet the requirements, an approved
additive such as Portland cement, hydrated lime or liquid
1 Bituminous plant mixes shall generally be composed anti-strip agent, may be required in the job mix. Portland
of coarse mineral aggregate, fine mineral aggregate, cement shall meet the requirements of AASHTO M 85.
mineral filler or cement if required, and penetration Hydrated lime shall meet the requirements of ASTM C 207,
graded bitumen, polymer modified bitumen (for Type N. Cement or hydrated lime will normally be
performance graded bitumens) with mix additives if required in the approximate range of 2-3% by weight of
specified, cutback bitumen or emulsified bitumen the aggregates and shall be added at the cold feed in dry
appropriate to the type of bituminous course to be or slurry form as directed. Liquid anti-striping agent, if
constructed. needed, will normally be required in the approximate
2 All materials shall conform to the relevant range of 0.6-1.0% by weight of the bitumen, or according
requirements of Sub-section 4.1. to the manufacturer’s specifications.
8 Upon receipt of approval of the job mix formula, the
4.3.3 Job Mixes and Project Mixes Contractor shall adjust his mixing plant to proportion the
1 At least 30 days prior to the date on which the individual aggregates, mineral filler and bitumen to
Contractor intends to begin production at the mixing plant, produce a final mix within the tolerances given in Table
and after receiving approval of the aggregates, and 4.3.3.1. The approved final mix that shall be used in the
delivery to the Site of the bitumen specified, the daily production is called the ’project mix’.
Contractor shall submit for approval his proposed job mix
Specified Tolerances
formula.
Sieve Designation
2 The job mix formula shall stipulate a single (square openings) Aggregate Aggregate
combined grading of all aggregate and filler materials Class A Class B
showing the specific percentage by weight passing each
9.5 mm and above + or - 5.0% + or - 5.0%
sieve size and the specific percentage by weight of each
material to be used in the total mix. 4.75 mm + or - 4.0% + or - 4.0%
3 The job mix formula shall be established by the 2.36 mm - + or - 4.0%
Contractor, under the supervision of the Engineer, in the
field laboratory. Mix design procedures shall conform to 2.00 mm + or - 4.0% -
the Marshall method of mix design and relevant
procedures contained in Asphalt Institute Manual MS-2. 0.15 mm (No. 80) - + or - 3.0%
All trial mixes shall be prepared and tested by the 0.075 mm (No. 200) + or - 1.0% + or - 1.0%
Contractor in the presence of the Engineer.
4 The job mix formula shall specify a combination of Bitumen Content + or - 0.2%
mineral aggregates, including filler and bitumen (plus Temperature of Mix
+ or - 5.0%
bitumen modifier if any) in such proportions as to produce on discharge
a job mix which is within the limits of the specified Table 4.3.3.1: Maximum Variations of Project Mix from
gradation and bitumen content ranges and which meets
Approved Job Mix
the Marshall Test requirements, as prescribed for each
particular type of bitumen course. It shall also stipulate the 9 Any deviation from these limits shall be made only
mixing temperature at discharge from the mixer which, with the approval of the Engineer.
unless otherwise directed, shall be 170 degrees C (for the 10 Conformance to gradation requirements will be
conventional unmodified asphalt). determined on the extracted aggregate in accordance with
5 The Marshall Test procedure shall be used to AASHTO T 30. The bitumen content shall be determined
determine the percentage of bitumen to be incorporated in in accordance with AASHTO T 164 or AASHTO T 308.
the mix. The job mix formula shall take into consideration 11 The Engineer will test the project mix at least twice
the absorption of bitumen into the aggregates. Air voids daily during plant operation and, if necessary, direct the
shall be calculated in accordance with the procedure given Contractor to readjust the plant to conform to the job mix
in the Asphalt Institute Manual, MS-2. The recommended formula. If, due to differing cold feed or hot bin
range of bitumen content is as follows: gradations, the Contractor cannot consistently produce a
project mix meeting the job mix requirements, production
i. Bituminous base and binder courses: 3% to shall cease, the job mix shall be redesigned and
3.8%. reapproved and the plant readjusted to produce a new job
ii. Bituminous wearing course: 3.2% to 4.0%. mix.
12 The participation of the Engineer in the preparation
6 When compacting specimens in accordance with the
of the job mix formula shall in no way relieve the
Marshall Test procedure, the number of blows applied
Contractor of responsibility for producing project mixes
with the compaction hammer shall be 75 on each side,
meeting the specified requirements.
unless otherwise specified.

♦ 4-13 ♦
4.3.4 Equipment appropriate shall be issued to each of the Contractor's
senior staff involved in bituminous course work. At the
4.3.4.1 General end of the Contract all the copies shall become the
property of the Employer.
1 Plant and equipment for mixing, transporting,
spreading and compacting bituminous mixes, shall 4.3.4.3 Spreading and Finishing Equipment
conform with the requirements of the relevant subsections
of these specifications and to the Contractor's approved 1 Bituminous courses shall be spread and finished
equipment list. using approved type, self-contained, power-propelled
pavers of sufficient capacity to be capable of laying up to
4.3.4.2 Mixing Plant 80 ton/hr. Pavers shall be provided with electronically
controlled vibratory screed or strike-off assembly with
1 Bituminous mixes shall be produced in an approved
devices for heating the screed, and shall be capable of
batch mixing plant of adequate size with a minimum
spreading and finishing the various courses of bituminous
capacity of not less than 80 ton/hr and a mixer capacity of
plant mix to the proper thickness and in lane and shoulder
not less than 750 kg. batch. The plant shall conform to the
widths applicable to the typical cross sections shown on
relevant requirements of AASHTO M 156.
the Drawings, and in incremental widths between 2.4 m
2 A mechanical batch counter shall be installed as part and 8 m. If the geometry of the cross section allows, wider
of the timing device and shall be designed to register only pavers will be required to cover the full width of the
completely mixed batches. pavement section in order to avoid longitudinal
3 The mixing plant shall be fully equipped to control construction joints.
the gradation of hot dry aggregates and of cold damp 2 The pavers shall be equipped with calibrated sensors
aggregates. A suitable dust collection system shall be to control the road profile in accordance with the design
installed, capable of returning all dust to the mixture shown on the Drawings.
whenever required. Suitable filters shall be incorporated
3 The pavers shall employ mechanical devices such as
whenever the mixing plant is in the vicinity of town, or
equalizing runners, straightedge runners, evener arms or
whenever they are required by law.
other compensating devices, to maintain trueness of
4 The cold feed system shall be of continuous belt feed grade and confine the edges of the mix to true lines
type or other approved system. It should be easily without the use of stationary side forms. Joint leveling
modified to allow hydrated lime slurry to be added to the devices shall be provided for smoothing and adjusting
mix prior to heating, and dry powdered lime added after longitudinal joints between lanes.
heating.
4 The paver shall be equipped with a receiving hopper
5 An approved automatic weighing, cycling and having sufficient capacity for a uniform spreading
monitoring system shall be installed as part of the operation. The hopper shall be equipped with a
batching equipment. Facilities for easy sampling of the distribution system to place the mix uniformly in front of
aggregates from the hot bins whilst the plant is in the full length of the screed.
operation shall also be provided.
5 The screed or strike-off assembly and extensions
6 The Contractor shall systematically inspect and verify, shall effectively produce a finished surface of the required
in the presence of the Engineer, on a weekly basis and evenness and texture without tearing, shoving, or gouging
also whenever suspect the following key operational the mix.
aspects of the mixing plant:
6 The paver shall be capable of being operated at
- State of repair of the screens, and their frame
forward speeds consistent with satisfactory laying of the
mountings.
mix. Speed shall be fully adjustable between 3 m/min and
- Proper working of cold and hot bin gates.
6 m/min.
- Accuracy of batching scales for filler,
aggregates and bitumen. 7 The automatic controls shall consist of an automatic
- Proper working of the nozzles of the mixer linkage arrangement such that, through the process of
bitumen sprayer. automatically adjusting the screed thickness control, the
- State of repair of the paddle tips and liners of mix can be placed and finished to a predetermined grade
the mixer. and a uniform crown or cross section. Articulated
averaging beams utilized for grade control shall be at least
7 The Contractor shall furnish, for reference and
9 m in length.
retention by the Engineer, one complete set of the
8 If during construction, the spreading and finishing
manufacturer's instruction and operating manuals for the
equipment in operation leaves in the pavement surface
mixing plant intended for use.
tracks or indented areas or other objectionable
8 At the commencement of the contract, 2 copies each irregularities that are not satisfactorily corrected by
of the latest editions of Asphalt Institute Specification SS-1 scheduled operations, the use of such equipment shall be
and Manuals MS-2, MS-3, MS-8 and MS-22 shall be discontinued and other satisfactory spreading and
furnished by the Contractor for use by the Engineer's finishing equipment shall be provided by the Contractor.
supervisory staff and, in addition, one copy of each as

♦ 4-14 ♦
9 The Contractor shall make available, for reference by Unless otherwise directed, the bitumen temperature shall
the Engineer, the manufacturer's instruction and operating be as given in Table 4.3.6.1.
manuals for each paver intended for use. Max.
Type and Temperature °C
4.3.5 Construction of Trial Sections Grade of immediately after
1 Immediately prior to finalization of the job mix Asphalt discharge from
formula, the Contractor shall lay trial sections of the Pugmill
various bituminous mixes intended for use in the work. 80 - 100 pen. 160
Each trial section shall be 2 lanes wide by 100 m long at
60 - 70 pen. 165
approved locations close to the Site. Each trial section
shall be laid using the same materials, proposed job mix, 40 – 50 pen. 170
mixing, spreading and compaction plant and spreading Table 4.3.6.1: Bitumen Temperature
and compaction procedures, proposed for use in the work.
5 Any conventional (unmodified) bituminous mix
2 Each trial section shall serve as a field verification of
subjected to higher temperature than those shown in
the job mix design. The mix density achievable and the air
Table 4.3.6.1 shall be rejected.
voids at that density shall be determined and, if less than
required, the job mix formula shall be adjusted 6 The mixing temperature for the polymer modified
accordingly. bituminous mixture shall be as determined under Sub-
section 4.1, paragraph 4.1.6.2.
3 Each trial section shall also demonstrate the
adequacy of hauling, spreading and compaction 7 The mixing time required in order to obtain a
equipment and the suitability of the construction methods homogeneous mix and adequate coating of the
and organization proposed. aggregates with bitumen shall be determined by the
Contractor in the presence of the Engineer. This time shall
4 If the trial section meets the required specification,
be determined whenever the source of aggregate for the
the job mix formula will be approved.
mix changes.
5 The trial section shall be carried out at the
8 In batch plants, mixing time shall begin upon entry of
Contractor's expense and is to be removed from Site, if
bitumen into the pugmill.
required by the Engineer.
9 Mixing time for mixing plants will be determined by
4.3.6 Mixing Procedures the following formula or other approved methods: Mixing
time (sec) = Pugmill dead capacity (kg.) divided by pugmill
1 Each aggregate ingredient shall be heated and dried output (kg./sec)
such that the temperature recorded in the hot fines bin
after screening does not exceed 170 degrees C. If any 4.3.7 Surface Preparation
aggregates contain excess moisture so as to cause
foaming in the mixture or their temperature is in excess of 1 When the bituminous mix is to be placed on a
170 degrees C, they shall be removed from the bins and prepared subbase, or base, the surface shall be prepared
disposed of as directed. to meet the appropriate specified compaction and surface
tolerance requirements. The surface shall then be primed
2 Immediately after heating, the aggregates shall be
as specified in Sub-section 4.2 – ‘Prime and Tack Coats’.
screened into at least 3 sizes and conveyed into separate
No bituminous mix shall be laid on a prime coat until it
bins ready for batching and mixing with the bitumen.
has been inspected and approved.
When the aggregates furnished are of such size and
grading that separating into 3 bins is impractical, the 2 When the bituminous mix is to be placed on an
number of required separations may, if approved, be existing bituminous surface, the surface shall be cleaned
reduced to 2 only. Screening operations shall produce, at of all foreign material and broomed free of dust. Any
plant operating capacity, gradations in each of the sizes of loose, broken or shattered bituminous material along the
heated and dried aggregates that are reasonably uniform edges of the existing surface shall be removed and the
and will result in the production of a mix conforming to exposed surface, and a sufficient width of the shoulder
the job mix requirements. adjacent to the edge of the existing surface, shall be
shaped, bladed, compacted and broomed to provide a
3 The dried and heated aggregate and (cold) mineral
uniform firm layer for the new surface course.
filler shall be combined in the plant in the proportionate
3 Broken, soft, or unstable areas of existing bituminous
amounts as determined by the job mix. Just prior to
surface, aggregate base or granular subbase shall be
bitumen entering the mixer, the anti-stripping additive, if
removed and replaced. The areas shall be excavated to a
required, shall be thoroughly mixed with the bitumen
depth as directed and refilled with the specified
which shall then be introduced into the pugmill mixer in
bituminous mix.
the proportionate amount determined by the job mix.
4 Prior to placing of the bituminous mix on an existing
4 The temperature of the bitumen upon entering the
bituminous surface when required, a tack coat as specified
pugmill shall be within 15ºC of the aggregate temperature.
in Sub-section 4.2 – ‘Prime and Tack Coats’ shall be

♦ 4-15 ♦
applied to the existing surface at the rate determined by grade line such that conformance with the required
the Engineer. No mixture shall be laid on a tack coat until geometrics, surface tolerance and minimum thickness
it has been inspected and approved. requirements shall be ensured. The reference line shall be
supported at 8m maximum spacing unless there is
4.3.8 Delivery, Spreading and Finishing noticeable sag in the line or the pavement surface, in
which case the maximum spacing shall be 4m.
4.3.8.1 Delivery of Mix to Site 2 The reference line shall be maintained taut and free
1 A sufficient number of haul vehicles shall be from sags at all times during spreading and initial
provided so that adequate supplies of mix are delivered to compacting operations.
ensure that continuous paving will be achieved. 3 Except where the paver is matching a previously
2 Hauling equipment for aggregates and bituminous placed layer, a wire or cord reference line shall be installed
mixes shall consist of vehicles having dump bodies on both sides of the paver for the initial bituminous course
suitable for dumping materials in a windrow or in being laid. Thereafter only one reference line will
spreader boxes. The bodies shall be so constructed that normally be required, if the paver is equipped with
their volume measurement can be accurately determined. adequate automatic super elevation control.
They shall be constructed and maintained such that loss of
4.3.8.3 Spreading and Finishing
materials during hauling operations will not occur. Dump
controls shall be capable of operation from the driver's 1 Bituminous mixes shall be laid only when the air
seat. temperature is at least 5 degrees C or above, when the
3 Hauling equipment for hot bituminous mixes shall existing surface is free from moisture, and when the
have tight, clean, smooth metal beds which are weather is not foggy, rainy, dusty or excessively windy
periodically thinly coated with a lime solution or other (particularly at low temperatures).
approved material to prevent adherence of the mix. All 2 After completion of surface preparation, the
hauling units shall be equipped with a canvas or other bituminous mix shall be spread and finished true to crown
approved type of cover which shall be used to cover the and grade by approved automatically controlled
hot material upon loading at the mixing plant and shall bituminous pavers. The mix may be spread and finished
not be removed until the mix is discharged into the paver. by approved hand methods only where the Engineer
Hot mix material may be transported without such cover determines that machine methods are impracticable.
only if permitted by the Engineer in special circumstances. Hand methods include heated hand tampers of at least 10
4 The dispatching of the hauling vehicles to the Site kg. weight and approved type mechanical (vibratory)
shall be so scheduled that all material delivered is placed tampers.
at least 90 minutes before sunset to allow sufficient time 3 The paver shall spread the bituminous mix without
for compaction, unless the use of artificial light is tearing the surface and shall strike a finish that is smooth,
approved. Delivery of material shall be at a uniform rate true to cross section, uniform in density and texture and
and in an amount well within the capacity of the paving free from hollows, transverse corrugations and other
and compacting equipment. irregularities.
5 The mix at delivery to the paver shall be not more 4 The paver shall be operated at a speed which gives
than 10ºC below discharge temperature at the mixing the best results for the type of paver being used and which
plant. The minimum temperature for the commencement coordinates satisfactorily with the rate of delivery of the
of breakdown rolling is 120ºC. Mix loads of temperature mix to the paver. A uniform rate of placement shall be
less than 120ºC shall not be accepted, and the load shall achieved without repeated intermittent operation of the
be disposed of and another load used. If there is paver.
consistent failure to meet the temperature requirement the 5 The mix shall be delivered to the paver in time to
Engineer shall order paving operations to stop until permit completion of spreading, finishing and compaction
suitable measures are taken by the Contractor to ensure of the mix during daylight hours.
that temperature requirements are met.
6 If during laying, the paver is repeatedly delayed
6 Each haul vehicle shall be weighed after each loading because of lack of mix or if the paver stands at one
at the mixing plant and accurate records shall be kept of location for an extended period, resulting in the (unrolled)
the gross weight and net weight of each load, for each mat under and adjacent to the rear of the spreader falling
vehicle and dates and time of loading. below the minimum temperature for breakdown rolling,
the affected portion of mat shall be cut out and discarded
4.3.8.2 Setting Out and Reference Lines
and a transverse joint shall be constructed. Paving shall
1 The Contractor shall survey the centerline profile and not recommence until the Engineer is satisfied that paving
crown of the existing surface or base and determine a will proceed without interruptions.
reference grade line which will be submitted for approval. 7 Contact surfaces of curbing, gutters, manholes, and
A reference line of wire or suitable cord shall be installed similar structures shall be painted with a thin, uniform
at a uniform grade parallel to the approved reference coating of tack coat material. The bituminous mixture

♦ 4-16 ♦
shall be placed uniformly high near the contact surfaces of the joint. As a minimum, the leading lane shall not be
so that after compaction it will be 10 mm above the edge laid in advance of the adjacent trailing lane by more than
of such structure. one half day of paving, and in no case shall the leading
8 If during the paving operations the spreading and lane be more than 0.5 km ahead of the trailing lane
finishing equipment in operation leaves in the pavement without approval. In the event of failure to conform to
surface tracks or indented areas or other objectionable these requirements, the Engineer may temporarily
irregularities that are not satisfactorily corrected by the suspend paving on the leading lane.
scheduled operations, the use of the equipment shall be 4 Unsupported edges of bituminous layers shall be
discontinued, until faults are corrected to the approval of rolled immediately following the rolling of the longitudinal
the Engineer. If this is not possible, other satisfactory joint. The material along the unsupported edge may, if
spreading and finishing equipment shall be provided by approved, be raised slightly by hand methods, to ensure
the Contractor. that the full weight of the roller will bear fully on the edge
9 Unless otherwise directed by the Engineer, where material.
successive bituminous layers are to be placed, the surface 5 On completion, the longitudinal edges of bituminous
of each existing layer shall be swept clean with a power pavement shall be true to the width and alignment as
broom, or by other approved means and a tack coat shown on the Drawings. The edges shall be cut back if
applied at the rate designated by the Engineer and in necessary prior to rolling, additional mix placed manually
accordance with the relevant requirements of Sub-section in a longitudinal strip adjoining each pavement edge, and
4.2. the edge rolled down to a neat 3:1 (horizontal:vertical)
10 Transverse joints in succeeding layers shall be offset slope or as shown on drawings.
by at least 2 m. Longitudinal joints shall be offset at least 6 Transverse joints shall be carefully constructed and
150 mm. thoroughly compacted to provide a smooth riding surface.
11 Bituminous mix shall be spread in one or more Joints shall be straight-edged and string-lined to assure
layers so that, after rolling, the nominal thickness of each smoothness and true alignment. If the joint is formed with
layer of the compacted bituminous material shall be a bulkhead, such as a board, to provide a straight line and
between 2 and 3 times maximum size of aggregate. This vertical face, it shall be checked with a straight edge
maximum thickness may be increased slightly when such before fresh material is placed against it to complete the
increase is more appropriate to total pavement thickness joint. If a bulkhead is not used to form the joint and the
and provided the Engineer determines that such increased roller is permitted to roll over the end of the new material,
thickness will not be detrimental to the quality of the the line shall be located back of the rounded edge a
finished bituminous course, and the Contractor can show sufficient distance to provide a true surface and cross-
that the required density is attained throughout the layer section. If the joint has been distorted by traffic or by
thickness. other means, it shall be trimmed to line. In either case, the
joint face shall be painted with a thin coating of
12 Transitions and structure approaches shall meet the
bituminous material before the fresh material is placed
design criteria for geometrics, the surface tolerance
against it.
specifications, and shall not be visually discontinuous or
abrupt in appearance. 4.3.8.5 Compaction
13 Side roads, entrances and lay-bys shall be paved in
1 Rollers shall be operated by competent and
accordance with the details shown on the Drawings.
experienced operators in accordance with the
4.3.8.4 Joints and Edges manufacturer's instructions, copies of which shall be
submitted to the Engineer. Rollers shall be kept in
1 All joints between old and new pavements or operation continuously if necessary, so that all parts of the
between successive days' work shall be such as to ensure pavement receive substantially equal compaction at the
thorough and continuous bond between the old and new time desired.
material.
2 After spreading and strike-off, and as soon as the mix
2 Before placing fresh mix against previously laid conditions permit the rolling to be performed without
asphalt layers or against old pavement, the contact excessive shoving or tearing, the mixture shall be
surface shall be saw-cut to a near vertical face, and shall thoroughly and uniformly compacted, using approved
be sprayed or painted with a thin uniform coat of tack coat types, sizes and numbers of rollers. Rolling shall not be
material unless otherwise directed. Longitudinal joints prolonged to the point where cracks appear or shoving or
shall be made by overlapping the paver screed on the displacement occurs.
previously laid material (cut back as necessary) and
depositing a sufficient amount of fresh mix so that the
joint formed will be smooth and tight.
3 The Contractor shall schedule paving operations so
as to minimize the exposure of the leading lane of
longitudinal joints prior to the completion and compaction

♦ 4-17 ♦
3 Rollers shall be of self-propelled 2-axle tandem or successive trips by at least one half the width of the rear
three wheel steel-tired, pneumatic-tired and vibratory steel wheels. Alternate trips of the rollers shall be of slightly
wheel types, in proper operating condition, capable of differing lengths.
reversing without backlash or tearing of the surface, and 12 The speed of the rollers, rolling pattern and, in the
shall be operated at speeds slow enough to avoid case of vibratory rollers, the frequency and amplitude of
displacement of the bituminous mix. vibration, shall be approved by the Engineer. To prevent
4 Initial breakdown rolling shall be carried out by use adhesion of the mix to the rollers, the wheels shall be kept
of 2 dual-drum vibrating steel-wheeled vibratory rollers properly and lightly moistened with water. An excessive
each of minimum weight 7,000 kg. and with vibrating use of water will not be permitted.
frequency of 2,000-3,000 cycles/min. These rollers shall be 13 The rolling pattern, type and number of rollers shall
purpose made for compaction of hot bituminous courses. be established by a site trial so as to achieve the required
5 Intermediate rolling shall be carried out by use of at compaction. The approved rolling pattern shall be
least 2 self-propelled, tandem pneumatic smooth-tired followed.
rollers each capable of exerting contact pressures of up to 14 The initial or breakdown rolling shall be followed by
690 KN./sq.m. (100 psi) and ballast - adjustable to ensure intermediate rolling involving 3 coverages with
uniform wheel loadings. pneumatic-tired rollers unless otherwise specified.
6 Final rolling shall be carried out by use of two, 2-axle 15 Finishing rolling shall then be carried out by means
tandem steel-tired static rollers each of minimum weight of 2-axle tandem power steel rollers unless otherwise
10,000 kg., capable of exerting contact pressures of up to designated. If, the specified density is not achieved,
65 kg./cm2 (350 lb/in.). changes shall be made in size and number of rollers being
7 Prior to use on Site of pneumatic-tired rollers, the used to ensure the compaction requirements are met.
Contractor shall furnish, for reference and retention by the 16 The average compacted density for all bituminous
Engineer, manufacturers' charts or tabulations showing courses shall be equal to or greater than 98% of the
the contact areas and contact pressures for the full range average Marshall bulk specific gravity for each day's
of tire inflation pressures and for the full range of tire production unless otherwise directed by the Engineer. It is
loadings for each type and size of compactor tire to be also required that 90% of the results shall be greater than
used. The Contractor shall ensure that tire pressures are the minimum specification tolerance limit of 96.3%.
maintained at all times in conformity with such charts or
17 Any mix that becomes loose, broken, mixed with
tabulations. The maximum allowable tolerances shall be
foreign material, or which is in any way defective in finish
plus or minus 35 KN./sq.m. (5 psi).
or density, or which does not conform in all other respects
8 Rollers shall move at a slow but uniform speed, with the specified requirements shall be removed,
generally with the drive roll or wheels nearest to the paver. replaced with suitable material and properly finished.
Recommended speeds are shown in Table 4.3.8.1 (km/h.).
4.3.9 Sampling and Testing
Speed of Rollers (Km./hr.)
Roller Type Breakdown Intermediate Finish 1 Sampling and testing shall conform to the
Rolling Rolling Rolling requirements of the relevant Sub-sections of the
Steel Tired Specification and Table 4.3.9.1.
3 5 5
Static Rollers 2 The Marshall bulk specific gravity shall be
Pneumatic determined in accordance with AASHTO T 166. The
5 5 9
Tired Rollers Marshall specimens shall be prepared from the same
Vibratory material used in construction, taken from samples of fresh
4.5 4.5 -
Rollers bituminous mix at the mixing plant or from trucks
Table 4.3.8.1: Recommended Speeds of Rollers delivering mix to the Site. Oven heating for up to 30
minutes to maintain the heat of the sample is permissible.
9 If vibratory rollers are used, when it is required to
3 The bulk specific gravity of the mix as placed and
change direction the vibration shall be turned off before
compacted in situ shall be determined from 100 mm
the roller is stopped, and turned on after motion in the
nominal diameter core samples, or slab samples cut from
new direction begins.
each compacted layer on the road at locations designated
10 Rolling shall begin as soon as the mixture will bear by the Engineer who may require additional tests to
the roller weight without undue displacement. The determine limits of areas deficient in density, or for
minimum temperature of the mat at which rolling shall be recheck.
allowed to start is 120ºC.
4 Samples for in-situ bulk specific gravity
11 Breakdown rolling shall consist of 3 complete determinations shall be taken in sets of 2 from each
coverages of each of the 2 rollers specified in Item 4 above pavement location. Minimum frequency of sampling for
unless otherwise directed. Rolling shall be longitudinal, each bituminous layer shall be one set/lane/500 m, with a
beginning at the low side of the spread of material and minimum of one set per day of placing bituminous layers.
proceeding towards the high side, overlapping on

♦ 4-18 ♦
Frequency of Tests Required
(A) (B)
Work item Tests at source of Frequency for all tests Tests at road site Frequency for all
material mentioned under (A) tests mentioned
under (B)
4-1
Materials used in 1. Specific gravity
bituminous mix (at & water absorption
- Test for each
batching plant)
Source
2. Abrasion Test - Test for each 1,000
cu.m of asphalt
3. Chert content
produced
4. Clay lumps & - When materials
friable materials quality changes
5. Flaky and elongated - As requested
particles
6. Soundness
4-2
Materials used in
1. Gradation
bituminous mix (from
hot bins)
2. Specific gravity - Test for each source
and water - When materials
absorption quality changes
3. Plasticity index - As requested

4. Sand equivalent
5. Stripping with
asphalt
4-3 1. Complete mix - For each project
Bituminous mix design in accordance -When results are not
design for each with American Asphalt consistent with the mix
course (from hot bins) Institute (MS2) design results.
2. Loss of stability -As requested
4-4
Bituminous Mix
At batching plant
Marshall stability for
each layer
1. Stability - Test for each day’s 1. Stability
2. Flow production 2. Flow
- Test each 3
3. Extraction (binder - Test for every 200 3. Extraction (binder working days
content & gradation) cu.m of asphalt content & gradation) - Test for each
4. Air voids produced per day 4. Air voids batching plant
- Test for each
5. Voids in mineral 5. Voids in mineral - As requested
batching plant
aggregates aggregates
- As requested
6. Daily Marshall 6. Daily Marshall
density density
-Test each 200
7. Compaction
lin.m., per lane
density
7. Loss of stability - Once a week and for batch
& thickness (after
layer
final compaction)
- As requested
- Test each 3
8. Loss of stability working days
- As requested
Table 4.3.9-1 Frequency of Testing for Bituminous 6 The Contractor shall, when necessary, furnish and
Pavement apply cold water, ice, or other cooling substance to the
surface of the pavement to prevent the sampling from
5 The Contractor shall cut the samples with an
shattering or disintegrating. The Contractor shall fill and
approved core drill in the presence of the Engineer. The
compact all test holes at his own expense.
equipment shall be capable of cutting the mixture without
shattering the edges or otherwise disturbing the density of
the specimen.

♦ 4-19 ♦
4.3.10 Surface Tolerances 5 One core shall be taken from each section by the
Contractor at approved locations and in the presence of
1 The fully compacted and completed bituminous
the Engineer. When the measurement of the core from
course shall conform to the lines, grades and cross
any paved section is not deficient by more than 5 mm
sections as shown on the Drawings.
from the specified thickness, the core will be deemed to be
2 The elevations of the finished course shall be of the specified thickness as shown on the Drawings.
checked by the Contractor in the presence of the Engineer
6 When the measurement of the core from any paved
at maximum intervals of 10m and at intermediate points
section is deficient by more than 5 mm but not more than
as directed.
20 mm, 2 additional cores spaced at not less than 100 m
3 The finished surface is tested with a 3 m long shall be taken and used together with the first core to
straightedge, placed parallel to, or at right angles to the determine the average thickness of such section.
centerline, the maximum deviation of the surface from the
7 When the measurement of the core from any paved
testing edge between any 2 contact points shall not
section is less than the specified thickness by more than
exceed the tolerances specified for each type of
20 mm, the average thickness of such section shall be
bituminous course laid, as shown under Paragraphs
determined by taking additional cores at not less than 5 m
4.4.10.1 and 4.5.10.1 for the bituminous base and wearing
intervals parallel to the centerline in each direction from
courses, respectively. All areas which exceed the specified
the affected location until, in each direction, a core is taken
tolerances shown under Paragraphs 4.4.10.1 and 4.5.10.1
which is not deficient by more than 20 mm. Exploratory
shall be corrected by removing the defective sections of
cores for deficient thickness will not be used in average
bituminous course and reconstructing them, or if
thickness determinations.
approved by the Engineer, by increasing the thickness of
the succeeding course(s). 8 Any deficiencies in the total thickness of bituminous
courses shall be subject to a proportional reduction in the
4 The finished surface shall also be tested using the
volume of final (surface) course measured for payment, or
rolling straight edge, and the areas which exceed the
complete removal and replacement, as shown in Table
specified tolerances shown under Paragraphs 4.4.10.2 and
4.3.11.1 below. Alternatively, the Contractor shall
4.5.10.2 shall be corrected by removing the defective
construct at his own expense, a surface course overlay, if
sections of bituminous course and reconstructing them, or
practicable in the judgment of the Engineer. Any such
if approved by the Engineer, by increasing the thickness of
overlay shall be a minimum of 40 mm compacted
the succeeding course(s).
thickness and to the specified standard of the course it is
5 The tolerances specified for evenness of finished overlaying.
surfaces for all types of bituminous courses, shall not 9 If the deficiency in total thickness of the asphalt
invalidate the tolerances specified for construction layers is from 0 to 3mm, full payment will be made, on
thickness and elevations of such courses. condition that deficiencies are not found in more than 10%
of the total project. Deficiencies between 3mm and 10mm,
4.3.11 Determination of Thickness of 80% of the full payment for the bituminous courses will be
Courses made.
1 The Contractor shall compensate for minor
Deficiency in the
deficiencies in the thickness of any bituminous course in Deficiency in the
Thickness of
the pavement structure by increasing the thickness of the Thickness of Total Action
Individual Asphalt
subsequent bituminous course. After completion of the Asphalt Layers
Layers
final (wearing) course any deficiencies in the thickness of
any course which have not been compensated for by ≤ 5mm ≤ 3mm Full payment
increasing the thickness of a subsequent course, will be 5 – 20mm 3 – 10mm 80% payment
considered deficiencies in the final (wearing) course.
> 20mm (or 25% > 10mm (or 15%
2 Cylinder core samples shall be taken as specified for Remove and
of design of design
in- situ bulk specified gravity core samples. replace
thickness) thickness)
3 Thickness of bituminous courses shall be determined Table 4.3.11-1: Tolerances in bituminous concrete layer
by average caliper measurement of cores, rounded
thicknesses
upwards to the nearest mm.
4 Paved sections to be measured separately shall 4.3.12 Method of Measurement
consist of each 300 lin.m. section in each traffic lane. The
last section in each traffic lane shall be 300 m plus the 1 Conventional and polymer modified bituminous
fractional part of 300 m remaining. Other areas such as courses are measured in the respective Sub-sections for
intersections, entrances, crossovers, ramps, etc. shall be each type of bituminous course transported, furnished,
measured as one section and the thickness of each shall spread, compacted, completed and accepted.
be determined separately. Small irregular unit areas may Measurement shall not include the rolled down edge
be included as part of another section. strips of bituminous courses placed outside the edge of
paving shown on the Drawings.

♦ 4-20 ♦
2 Bituminous prime and tack coats are measured as 4.4.3 Job Mix and Project Mix
prescribed in Sub-section 4.2. 1 The job mix formula shall be established by the
3 Bituminous overlays constructed by order of the Contractor in accordance with the procedures and
Engineer to correct deficiencies in total thickness of requirements of Sub-section 4.3.
bituminous courses or to compensate for major 2 The job mix for bituminous base course shall
deficiencies in the thickness of any underlying bituminous conform to the following composition limits as shown in
course, shall not be measured for direct payment, but Table 4.4.3.1.
shall be considered as subsidiary work the costs of which
will be deemed to be included in the respective rates for Parameter Value
bituminous courses. stated in the Bill of Quantities.
Marshall stability at 80ºC (Kg.) 1200
4 Establishment of the job mix formula, surface
preparation, construction of joints, hand painting of Flow (mms) 2- 3.5
contact surfaces, remedial treatment of surface 12%
irregularities, cutting of cores and slabs for testing or Voids in mineral aggregate, (VMA)
(minimum)
measurement purposes, reinstatement of core and slab
areas of pavement, rolled down longitudinal bituminous Air voids 4-7%
edge strips, additional thickness of bituminous course in Voids filled with bitumen, (VFB) 50 to 70%
excess of the specified thickness, and other ancillary items
Loss of Marshall stability by
shall not be measured for direct payment, but shall be
submerging specimens in water at 60°C
considered as subsidiary work the costs of which will be
for 24 h. compared to stability Max. 25%
deemed to be included in the respective rates for
measured after submersion in water at
bituminous courses stated in the Bill of Quantities.
60°C for 30 minutes

4.3.13 Basis of Payment


% Air voids at refusal Min. 2%
1 The amount of completed and accepted work,
measured as provided for above and as measured in the Table 4.4.3.1: Job Mix Requirements for Bituminous Base
various Sub-sections of Section 4, will be paid for at the Course
unit rates for the various items in the Bill of Quantities,
3 Prior to final approval, the proposed job mix, but
which rate shall be full compensation for supplying
with a bituminous content at the upper percentage limits
materials, transporting and placing, labor, equipment,
shall be compacted to refusal, (400, 500 and 600 blows)
tools and other items necessary for the proper completion
and the resulting voids in the mix shall not be less than
of the work.
2%.
4 After the job mix formula has been established and
4.4 Bituminous Base Course
approved, all mixes furnished shall conform to it within
the stated tolerances.
4.4.1 Description
5 The job mix formula shall be re-established if the
1 This Sub-section describes requirements for source of aggregate, filler or bitumen changes.
furnishing materials, mixing at a central mixing plant, and
spreading and compacting conventional or polymer 4.4.4 Equipment
modified bituminous base course on an approved
aggregate base course or granular subbase, as shown on 1 Plant and equipment for mixing, hauling, placing and
the Drawings. compacting bituminous base course material, shall
conform to the relevant requirements of Sub-section 4.3.
4.4.2 Materials
4.4.5 Construction of Trial Sections
1 All materials shall conform to the relevant
requirements of Sub-section 4.1. 1 Trial sections shall be constructed as and where
directed and in accordance with the relevant requirements
2 Unless otherwise shown on the Drawings, bitumen
of Sub-section 4.3.
for base course construction shall be 60/70 penetration
graded bitumen.
4.4.6 Mixing Procedures
3 For modified bitumen, unless otherwise shown on
the Drawings, bitumen for base course construction shall 1 Handling and mixing of bitumen (including modifier
not be lower than 60/70 penetration graded bitumen and anti-stripping agent, if any) and aggregates (including
modified with one of the polymers specified in Sub- mineral filler if required) shall be in accordance with the
section 4.1, Paragraph 4.1.6.2 and as per these same relevant requirements of Sub-section 4.3.
specification requirements.

♦ 4-21 ♦
4.4.7 Surface Preparation 4 The longitudinal regularity of the surfaces of base
course as measured by the rolling straight-edge set at 5
1 Preparation of the surface upon which the
mm shall be such that the number of surface irregularities
bituminous base course mix is to be laid, shall be
is within the relevant limits stated in Table 4.4.10-2. No
appropriate to the type and condition of such surface and
irregularity exceeding 10 mm shall be permitted.
shall conform with the relevant requirements of Sub-
section 4.3.
Length 300m 75m
4.4.8 Delivery, Spreading and Finishing
Max. permitted number of
20 9
4.4.8.1 General surface irregularities

1 The delivery, spreading and finishing of bituminous Table 4.4.10.2: Tolerances on bituminous base course
mix for base course shall conform with the relevant surface irregularity when tested by rolling straight-edge
requirements of Sub-section 4.3 and to the following
particular requirements.
4.4.11 Determination of Thickness
4.4.8.2 Rollers 1 Procedures for determining the average compacted
1 The rollers, rolling sequence, pattern and speed shall thickness of bituminous base course shall conform with
be as stipulated in Sub-section 4.3, Paragraph 4.3.8.5. the relevant requirements of Sub-section 4.3 and to the
following particular requirements.
2 The number of rollers used for any stage of rolling
may be reduced by the Engineer to one, provided that the 2 Cores for thickness measurements shall be used to
base course width being compacted is less than 5.5 m and determine if changes are necessary in the constructed
provided an equivalent standby roller is available on Site thickness of succeeding bituminous layers to rectify any
as replacement in the event of breakdown of the operating thickness deficiencies in the bituminous base course.
roller. 3 In cases where the bituminous base course will not
be covered by superimposed binder or wearing courses,
4.4.8.3 Standard of Compaction the base course shall be deemed to be the final (wearing)
1 The compacted density of the bituminous base course for the purposes of determining the proportion of
course shall be equal to or greater than 98% of the wearing course volume measured for payment or for the
average Marshall bulk density for each day's production or purposes of any overlay ordered to correct deficiencies. In
otherwise as directed by the Engineer. such cases, the surface base course layer shall meet the
Surface Tolerance requirements specified under Clause
4.4.9 Sampling and Testing 4.5.10 for wearing courses.

1 Sampling and testing shall conform to the relevant 4.4.12 Method of Measurement
requirements of Sub-section 4.3, and Table 4.3.9.1.
1 Conventional or polymer modified bituminous base
4.4.10 Surface Tolerances course shall each be measured in cubic meters of mix
furnished, spread, compacted, completed and accepted.
1 Surface tolerances shall conform with the relevant Measurement shall be based on the areas and thickness as
requirements of Sub-section 4.3 and to the following shown on the Drawings or otherwise directed by the
particular requirements. Engineer.
2 The tolerances on elevations of finished bituminous 2 Where bituminous base course is intended to serve
base course surface shall be not greater than + 6 mm. as a wearing course, any deficiencies in thickness shall,
3 When the finished surface is tested with a 3 m long unless an overlay is constructed at the Contractor's
straightedge, placed parallel to, or at right angles to the expense, result in a proportion only of the base course
centerline, the maximum deviation of the surface from the volume being measured for payment. Proportions shall
testing edge between any two contact points shall not be determined in accordance with the thickness
exceed 5 mm (Table 4.4.10.1). deficiencies stated in Sub-section 4.3, Table 4.3.11.1.

Property Tolerance Action 4.4.13 Basis of Payment


Max. Replace (min. 15m 1 The amount of completed and accepted work,
Surface elevation measured as provided for above, will be paid for at
6mm length of road)
the unit rates for the various items in the Bill of
Surface irregularity Max. Replace (min. 15m Quantities, which rate shall be full compensation for
(3m straight edge) 5mm length of road) supplying materials, transporting and placing, for
Table 4.4.10.1: Tolerances on bituminous base course labor, equipment, tools and other items necessary for
surface elevation and straight edge irregularity the proper completion of the work.

♦ 4-22 ♦
4.4.14 Items in the Bill of Quantities 3 After the job mix formula has been established and
approved, all subsequent mixes shall conform to it within
i. Bituminous base course (Class A, B). the allowable tolerances, as shown in Table 4.5.3.1.
ii. Polymer modified bit. base course (Class A, B). 4 The Job mix formula shall be re-established if the
source of aggregate, filler or bitumen is changed.
4.5 Bituminous Binder and Wearing 5 When tested for resistance to water damage in
Courses accordance with AASHTO T-283 ‘Resistance of Compacted
Asphalt Mixtures to Moisture-Induced Damage’, the
4.5.1 Description conventional and polymer modified bituminous wearing
course mixtures shall have a retained tensile strength
1 This Sub-section describes requirements for
greater than or at least equal to 80%. In cases where the
furnishing materials, mixing at a central mixing plant, and
anti-stripping agents are not successful in providing the
spreading and compacting bituminous binder course and
specified tensile strength ratio, the Contractor shall
bituminous wearing course on an approved base course,
consider alternative means, such as the use of hydrated
as shown on the Drawings.
lime to achieve this purpose.

4.5.2 Materials
4.5.4 Equipment
1 All materials shall conform to the relevant
1 Plant and equipment for mixing, hauling, placing and
requirements of Sub-section 4.1
compacting bituminous binder and wearing courses
2 Unless otherwise shown on the Drawings, bitumen material shall conform to the relevant requirements of
for binder and wearing courses construction shall be 60/70 Sub-section 4.3.
penetration graded bitumen, or any other suitable grade
for the climatic condition of the project. 4.5.5 Construction of Trial Sections
3 For polymer modified bitumen, unless otherwise
1 Trial sections shall be constructed as and where
shown on the Drawings, bitumen for binder and wearing
directed and in accordance with the relevant requirements
courses construction shall not be lower than 60/70
of Sub-section 4.3..
penetration graded bitumen modified with one of the
polymers specified in Sub-section 4.1, Paragraph 4.1.6.2..
4.5.6 Mixing Procedures
4.5.3 Job Mix and Project Mix 1 Handling and mixing of bitumen (including modifier
and anti-stripping agent, if any) and aggregates (including
1 The job mix formula shall be established by the
mineral filler if required) shall be in accordance with the
Contractor in accordance with the procedures and
relevant requirements of Sub-section 4.3.
requirements of Sub-section 4.3.
2 The job mix for bituminous binder and wearing 4.5.7 Surface preparation
courses shall conform to the following composition limits
as shown in Sub-section, Table 4.5.3.1. 1 Preparation of the surface upon which the
bituminous binder and wearing course mixes are to be
Binder Wearing laid, shall be appropriate to the type and condition of such
Property
Course Course surface and shall conform to the relevant requirements of
Marshall stability at 80ºC (Kg.) 1300 1400 Sub-section 4.3.

Flow (mms) 2- 4.5 2- 5 4.5.8 Delivery, Spreading and Finishing


Voids in mineral aggregate
13- 14% 14- 15% 4.5.8.1 General
(VMA)
Air voids 4- 7% 4- 7% 1 The delivery, spreading and finishing of bituminous
mix for binder and wearing courses shall conform with the
50 to 50 to
Voids filled with bitumen, (VFB) relevant requirements of Sub-section 4.3 and to the
70% 70%
following particular requirements.
Loss of Marshall stability by
submerging specimens in water 4.5.8.2 Rollers
at 60°C for 24 h. compared to Max Max
stability measured after 25% 25% 1 The rollers, rolling sequence, pattern and speed shall
submersion in water at 60°C for be as stipulated in Sub-section 4.3, Paragraph 4.3.8.5.
30 minutes 2 The number of rollers used for any stage of rolling
% Air voids at refusal Min 2% Min 2% may be reduced by the Engineer to one, provided that the
course width being compacted is less than 5.5 m in width,
Table 4.5.3-1: Job Mix Requirement for Bituminous Binder and provided an equivalent stand-by roller is available on
and Wearing Course

♦ 4-23 ♦
Site as replacement, in the event of breakdown of the 5 The combination of the permitted tolerances in the
operating roller. levels of the different pavement layers, excluding
aggregate base and sub-base courses, shall not result in a
4.5.8.3 Standard of Compaction reduction of thickness by more than 10 mm from the
1 The compacted density of the bituminous binder and specified thickness, as shown on the Drawings, nor a
wearing courses shall be not less than 98% of the average reduction in the final wearing course thickness by more
Marshall bulk density for each day's production. than 5 mm from that specified or shown on the Drawings.

4.5.8.4 Skid Resistance and Surface Texture 4.5.11 Determination of Thickness


1 Surface Texture: Conventional and polymer modified 1 Procedures for determining the average compacted
bituminous wearing course layer shall have a texture thickness of bituminous binder and wearing courses shall
depth of at least 0.8mm tested in accordance with the conform to the relevant requirements of Sub-section 4.3,
Sand Patch Test ASTM E 965. One Test shall be done Clause 4.3.11 and the tolerances/deficiencies shall comply
every 500m length of constructed road. with the relevant requirements of Table 4.3.11.1 and with
the requirements of Item 2 following.
4.5.9 Sampling and Testing 2 Cores for thickness measurements of the binder
1 Sampling and testing shall conform to the relevant course shall be used to determine if changes are
requirements of Sub-section 4.3 and Table 4.3.9.1. necessary in the constructed thickness of the wearing
course to rectify any thickness deficiencies in the binder
4.5.10 Surface Tolerances course.

1 Surface tolerances shall conform with the relevant 4.5.12 Method of Measurement
requirements of Sub-section 4.3 and to the following
particular requirements. 1 Conventional and polymer modified bituminous
binder course and bituminous wearing courses shall each
2 Tolerances on elevations of finished bituminous
be measured by the cubic meter of mix transported,
binder and wearing course surfaces shall be not greater
furnished, spread, compacted, completed and accepted.
than + 6 mm when compared to the design profile shown
Measurement shall be based on the areas and thickness as
on the drawings.
shown on the Drawings or otherwise directed by the
3 When the finished binder or wearing course surface Engineer.
is tested with a 3 m long straightedge, placed parallel to,
2 Deficiencies in thickness of the wearing course shall,
or at right angles to the centerline, the maximum
unless an overlay is constructed at the Contractor's
deviation of the surface from the testing edge between
expense, result in a proportion only of the wearing course
any two contact points shall not exceed 3 mm (Table
area being measured for payment. Proportions shall be
4.5.10-1).
determined in accordance with the thickness deficiencies
stated– in Sub-section 4.3, Table 4.3.11.1
Property Tolerance Action
Surface Replace (minimum 4.5.13 Basis of Payment
Max. 6mm
elevation 15m length of road)
1 The amount of completed and accepted work,
Surface
Replace (minimum measured as provided for above, will be paid for at the
irregularity (3m Max. 3mm
15m length of road) unit rates for the various items in the Bill of Quantities ,
straight edge)
which rate shall be full compensation for supplying
Table 4.5.10.1: Tolerances on bituminous wearing course materials, transporting and placing, labor, equipment,
surface elevation and straight edge irregularity tools and other items necessary for the proper completion
of the work.
4 The longitudinal regularity of the surfaces of the
finished binder or wearing course as measured by the
rolling straight-edge set at 5 mm shall be such that the
4.5.14 Items in the Bill of Quantities
number of surface irregularities is within the relevant i. Bituminous binder course.
limits stated in Table 4.5.10-2. No irregularity exceeding 10 ii. Bituminous wearing course (Class A, B).
mm shall be permitted.
iii. Polymer modified bituminous binder course.
Length 300m 75m iv. Polymer modified bituminous wearing course
(Class A, B).
Max. permitted number of
15 7
surface irregularities

Table 4.5.10.2: Tolerances on bituminous wearing course


surface irregularity when tested by rolling straight-edge

♦ 4-24 ♦
4.6 Bituminous Seal Coats – Surface 4.6.4 Construction of Trial Sections
Dressings 1 Before commencement of Site seal coat applications,
the Contractor shall construct trial sections using varying
4.6.1 Description application rates for bitumen and for aggregates, as
selected by the Engineer. Each trial section shall be two
1 This Sub-section describes requirements for
lanes wide by 50 m long, at approved locations on or close
furnishing of materials and one or more applications of
to the Site.
cutback bitumen and cover material, or a single
application of emulsified bitumen, or spreading emulsified 2 Each trial section shall be constructed using the same
bitumen slurry, to previously prepared base course or materials, mixing, spraying, spreading, rolling and
wearing course surfaces, as shown on the Drawings. brooming equipment, and construction procedures,
proposed for use in the Works. Trial sections for slurry
2 Bituminous slurry seal coat (BSSC) shall consist of
seals shall be along existing bituminous pavements in the
spreading and screeding a mixture of emulsified bitumen,
vicinity of the Site.
sand aggregate and water.
3 The objectives of these trials shall be to determine
3 Single bituminous surface treatment (SBST) shall
the adequacy of the Contractor's equipment, the most
consist of a single application of cutback or straight run
suitable application rates for cutback bitumen, emulsified
bitumen, and sand aggregate or as specified.
bitumen and the various gradations of aggregate, and the
4 Double bituminous surface treatment (DBST) shall most suitable consistency of slurry seal to fill cracks and
consist of an application of cutback or straight run leave a residual coating of 3 mm over the entire
bitumen and coarse graded cover aggregate followed not bituminous wearing surface.
less than 5 days later by a second application of cutback or
4 The Contractor shall not proceed with any seal coat
straight run bitumen and medium graded aggregate, or as
applications until the methods and procedures established
specified.
in the trials have been approved.

4.6.2 Materials
4.6.5 Rates of Application
4.6.2.1 Bitumen
1 Application rates for cutback and emulsified bitumen
1 Bitumen for SBSD and DBSD (surface dressing) and for the various cover aggregate gradations, will be
applications shall be rapid-curing RC-800 grade, determined by the Engineer from the trial sections and
conforming to the relevant requirements of Sub-section shall be generally within the ranges given in Table 4.6.5.1.
4.1 and AASHTO M-81.
2 Bitumen for BSSC (slurry) applications shall be a Approx. Rate of Application
cationic, slow setting emulsified bitumen Grade CSS-1 Types of Seal Coat
Aggregate Binder
conforming to the relevant requirements of Sub-section
(kg/sq.m.) (kg/sq.m.)
4.1.
Coarse aggregate Seal
12.5- 20.0 1.00-1.80
4.6.2.2 Aggregates coat (DBST)
Slurry aggregate Seal
1 Cover aggregates shall consist of screenings of 10.0-15.0 0.90-1.80
coat
crushed stone or crushed gravel. Aggregate for slurry
Generally 5-6 kg./sq.m.
seals shall consist of crushed stone or gravel fines or Slurry seal (SBSC)
for the mix
natural sand blended with not less than 50% crushed fines.
For heavy duty applications slurry aggregate shall consist Table 4.6.5-1: Application Rates
of 100% crushed fines. 2 The Engineer may order additional trial sections and
2 The properties of cover and slurry seal aggregates alter the previously established rates of application during
and their gradations shall be in accordance with the progress of the work.
relevant requirements of Sub-section 4.1.
4.6.6 Construction Requirements
4.6.3 Equipment
4.6.6.1 General
1 All plant and equipment used for pugmill mixing of
slurry mixes, heating and spraying of cutback and 1 Applications of bitumen and aggregate and
emulsified bitumen, spreading, rolling and brooming of subsequent rolling shall be completed between sunrise
cover aggregate, and applying and spreading slurry seals, and sunset and under favorable weather conditions as
shall conform with the requirements of the relevant determined by the Engineer. The atmospheric
sections of this Specification and with the Contractor's temperature shall be above 15 degrees C and the weather
approved equipment list. shall not be foggy, rainy, dusty or unduly windy.
2 Generally, where the seal coat is to carry traffic prior
to final sweeping, speed signs shall be erected to control

♦ 4-25 ♦
the speed of traffic. Provision for traffic control shall be in 3 The slurry seal coat shall be uniform and
accordance with the requirements of Section 1, Sub- homogeneous after spreading and shall not show signs of
section 1.8. separation of the emulsion and aggregate after setting.
3 When bituminous coatings are applied to sections of
4.6.6.5 Spraying of Bitumen
highway which are to be promptly opened to traffic, and
the ambient temperature is contributing to slow curing 1 The bitumen cutback or emulsified bitumen for fog
and excessive pickup, the Contractor shall suspend and seal coats shall be applied by means of a pressure
operations until the Engineer approves continuation of distributor uniformly and continuously over the section to
sealing work. be treated. The rate of application shall be as designated
4 The surface to be treated shall be dry or slightly by the Engineer.
damp and the moisture content of aggregates at the time 2 A strip of building paper or heavy polyethylene
of application to the coated surface shall not exceed 3% by sheeting, at least one m in width, and with a length equal
weight. to that of the spray bar of the distributor plus 300 mm,
5 Unless otherwise directed, the minimum time shall be used at the beginning of each application. If the
interval between successive seal coats, in DBSD cut-off is not positive, the paper shall be used at the end of
applications, shall be 5 days. each spread. The paper shall be removed and disposed of
after use. The distributor shall be moving forward at
4.6.6.2 Surface Preparation proper application speed at the time the spray bar is
opened. Any skipped areas or deficiencies shall be
1 Granular surfaces shall be primed in accordance with
corrected immediately as directed.
the requirements of Sub-section 4.2 prior to application of
the surface treatment. If there are delays in scheduling the 3 The length of spray run shall not exceed that which
seal coating, which results in deterioration of the surface, can be covered by the aggregate spreading equipment.
the Engineer may order appropriate repairs or corrective 4 The application width of bitumen shall be not more
treatment prior to seal coating. than 150 mm wider than the width covered by the
2 When coatings are applied to existing pavement aggregate spreader. Under no circumstances shall
surfaces, all pavement repairs shown on the Drawings operations proceed in such a manner that the bitumen will
shall first be completed. Where applicable, the positions be allowed to chill, set up, dry, or otherwise impair
of traffic markings shall be surveyed and recorded to retention of the cover aggregate.
enable their accurate replacement after the seal coatings 5 The Contractor shall keep a complete record of
have been applied. bitumen used, based on distributor tank measurements
3 Immediately before applying any bituminous and on areas to which the bitumen has been applied.
material, all dirt, dust and other objectionable material These records shall be submitted to the Engineer as
shall be removed from the surface and cracks shall be verification of the accuracy of the tachometer as well as
repaired or sealed as directed. If required, the surface verification of application rates designated by the
shall be slightly dampened with a light application of Engineer.
water immediately prior to application of bitumen. 6 Distribution of bitumen shall be so regulated and
4 Surfaces to be slurry sealed shall be lightly sprayed, sufficient material left in the distributor at the end of each
immediately prior to spreading the slurry, with a slow- application, that there will be a uniform distribution across
setting 3:1 water/emulsion mixture applied at the rate of the spray bar. In no case shall the distributor be allowed
0.4-0.8 kg./sq.m. to expel air with the bitumen, thereby causing uneven
coverage.
4.6.6.3 Heating of Bitumen 7 The angle of the spray nozzles and the height of the
1 The temperature of cutback bitumen and of spray bar shall be adjusted and regularly checked to
emulsified bitumen at the time of application shall be as ensure uniform distribution. The height of the spray bar
specified in Sub-section 4.1. above the pavement surface should remain constant
throughout the spraying process. Distribution shall cease
4.6.6.4 Spreading Slurry Seal immediately upon any clogging or partial blocking of any
nozzle and corrective measures shall be taken before
1 Spreading of slurry seal shall be by means of an
application is resumed.
approved type spreader box which shall be capable of
spreading at least one traffic lane width. It shall have 4.6.6.6 Application of Aggregate
flexible rubber or similar strips fastened on each side to
prevent loss of slurry and shall have baffles incorporated 1 If directed, aggregates shall be washed prior to use in
in the box to ensure uniform application. A rear, flexible, order to eliminate or reduce any dust coating or salts
adjustable strike-off blade shall be fitted to the box. before delivery to the spreader.

2 Areas inaccessible to the slurry spreader box shall be 2 Operation of the aggregate spreader at speeds which
slurry sealed using hand or other approved methods. cause the particles to roll over after striking the bitumen
covered surface will not be permitted.

♦ 4-26 ♦
3 Immediately upon application of bitumen, aggregate dislodged. This brooming shall result in uniform
of the required gradation shall be spread at the rate distribution of loose screenings over the surface which
designated by the Engineer. Spreading shall be shall then be re-rolled using pneumatic-tired rollers until
accomplished in such a manner that the tires of the at least 2 complete coverages have been achieved.
hauling units or aggregate spreader do not come in 8 Light drag brooming and re-rolling shall be repeated
contact with the uncovered bitumen surface. 24 hours after the initial brooming, if so directed.
4 Where adjacent spreads are to be made, the first 9 Excess screenings shall be salvaged and stockpiled
aggregate spread shall not extend closer than 150 mm to or disposed of as directed.
the edge of bitumen application. The adjacent spread of
bitumen shall overlap this 150 mm and complete 4.6.6.8 Maintenance and Protection of Sealed Surfaces
aggregate coverage shall be achieved on the second
1 BSSC shall be protected from traffic until such time
spread promptly upon completion of the first spread to
as the coatings have cured sufficiently and will not be
ensure a smooth riding surface.
damaged by, adhere to or be picked up by, the tires of
5 Immediately after aggregate has been spread, vehicles.
deficient areas shall be covered by additional aggregate.
2 Each coat of SBSD and DBSD shall be maintained
Humps, ridges or uneven distributions of aggregate shall
and protected from traffic for at least 3 days after
be removed and corrected to ensure that there are no
completion of rolling.
permanent ridges, bumps, or depressions in the
completed surface. Additional aggregate shall be spread 3 At the end of the 3-day maintenance period for each
in whatever quantities necessary to prevent pick-up by seal coat, or earlier if directed, the surface shall be finally
rollers or traffic, after which the surface shall be rolled as swept, using a rotary broom, to remove loose screenings.
directed. Surplus screenings shall be stockpiled or disposed of as
6 Care shall be taken to prevent aggregate from directed.
entering ditches or inlets of any type. The Contractor shall
be responsible for removing any such aggregate materials 4.6.7 Tolerances and Records
or other accumulated debris arising out of his operations.
1 The Contractor shall be responsible for ensuring the
4.6.6.7 Rolling and Brooming accurate calibration of pressure distributors and for the
correct rates of application of bitumen as designated by
1 Aggregate shall not be spread more than 150 m the Engineer.
ahead of initial rolling operations. 2 Readings shall be taken of bitumen tanker contents
2 Rollers shall not stop, start or turn on the surface and temperature immediately prior to, and immediately
being rolled. Any damage to the surface arising out of upon completion of each spraying run and the actual
non-compliance with these requirements shall be made application rate in kg./sq.m. shall be calculated. Complete
good as directed, at the Contractor's expense. records shall be maintained of all such measurements and
3 Initial breakdown rolling shall proceed behind the the specific locations, width and lengths of the respective
spreader (after any adjustments by hand methods to runs.
correct for uneven distribution, etc). One complete 3 The tolerances on temperature-adjusted application
coverage shall be achieved using 2-axle self-propelled rates of cutback bitumen shall be plus or minus 5% of the
steel-wheeled rollers of 6-8 tons weight and operating at a designated rate.
maximum speed of 5 km/h. Initial rolling shall be 4 Applications of cutback bitumen varying by more
completed within 30 minutes of spreading aggregate. than 5% but less than 10%, after temperature adjustment,
4 The Engineer may order the alternative use of below the specified rate of application shall, if accepted,
pneumatic-tired rollers for initial rolling if adequate be subject to a 10% reduction in quantity or area
embedment of the aggregate is liable to result in measurements as appropriate.
excessive crushing when steel-wheeled rollers are used. 5 Applications of cutback bitumen varying by more
5 Immediately following completion of the initial than 10%, after temperature adjustment, above or below
rolling, the surface shall be rolled using self-propelled the specified rate of application shall be rejected and the
pneumatic-tired rollers operated at a maximum speed of 8 unsatisfactory material replaced or made good as directed,
km/h, until at least 3 complete coverages have been at the Contractor's expense.
achieved. 6 The Contractor shall maintain, on a daily basis,
6 If necessary during rolling operations, additional complete records of the volumes and tonnage of each
screenings shall be lightly spread by hand methods and type of aggregate delivered to the Site and used in each
re-rolled, to make good any small areas visibly deficient in section of the Works for seal coat applications.
cover material. 7 All records and calculations of bitumen applications,
7 Light drag brooming of the surface shall be carried and aggregate delivery and use, shall be submitted to the
out 24 hours after completion of rolling and in such a Engineer at the end of each day when seal coat
manner that embedded aggregate particles will not be applications have been carried out. No measurements will

♦ 4-27 ♦
be made of bitumen applications which are not supported 4.7.4 Equipment
by adequate, verifiable records.
1 Plant and equipment for mixing, hauling, placing and
compacting bituminous leveling course materials shall
4.6.8 Method of Measurement
conform to the relevant requirements of Sub-section 4.3.
1 Single bituminous surface treatment, double
bituminous surface treatment and bituminous slurry seal 4.7.5 Construction of Trial Sections
coat shall each be measured in square meters of net area
1 Trial sections shall be constructed as and where
covered as shown on the Drawings or directed by the
directed and in accordance with the relevant requirements
Engineer. Rates are deemed to include for all related work,
of Sub-section 4.3.
including, without limitation, trial sections, tests and
reports and wastage of materials.
4.7.6 Mixing Procedures
4.6.9 Basis of Payment 1 Handling and mixing of bitumen (including modifier
and anti-stripping agent, if any) and aggregates (including
1 The amount of completed and accepted work,
mineral filler if required) shall be in accordance with the
measured as provided for above, will be paid for at the
relevant requirements of Sub-section 4.3.
unit rates for the various items in the Bill of Quantities ,
which rate shall be full compensation for supplying
materials, transporting and placing, labor, equipment,
4.7.7 Surface Preparation
tools and other items necessary for the proper completion 1 Damaged pavement surfaces shall, where directed,
of the work. be repaired by patching prior to receiving the bituminous
leveling course. The extent of patching shall be as shown
4.6.10 Items in the Bill of Quantities on the Drawings or as directed.
2 Areas of existing pavement to be patched shall be cut
i. Single bituminous surface treatment.
out to neat lines to a depth ordered by the Engineer,
ii. Double bituminous surface treatment.
thoroughly cleaned, and the exposed edges of pavement
iii. Bituminous slurry seal coat. painted or sprayed with a thin coat of rapid curing cutback
bitumen grade RC-70 or RC-250 in accordance with the
4.7 Bituminous Leveling Course and relevant requirements of Sub-section 4.2. The cut out
Patching Work pavement shall be patched with bituminous material as
shown on the Drawings or as directed and conforming
4.7.1 Description with the relevant requirements of Sub-section 4.1.
3 Patching shall be carried out in accordance with the
1 This Sub-section describes requirements for
relevant requirements of Sub-section 4.3.
furnishing materials, mixing at a central mixing plant, and
spreading and compacting bituminous leveling course on 4 Patching shall be carried out in layers not exceeding
an existing pavement surface, as shown on the Drawings 80 mm in thickness. Each layer shall be thoroughly
or directed. compacted by means of approved pneumatic tampers
prior to placing the succeeding layer. Each layer shall be
2 Patching works shall be limited to localized deficient
protected from damage and all dirt or foreign material
areas as jointly determined by the Engineer and the
shall be removed before placing subsequent layers. The
Contractor. These areas are usually not exceeding 3m in
final layer shall be rolled with a heavy roller. Each layer
length and one lane width and the distance between two
shall be approved prior to placement of subsequent layers.
individual patches is normally not less than 5m.
5 All cut-out pavement material and surplus patching
4.7.2 Materials material shall be removed from the site and disposed of
by the Contractor prior to placing the leveling courses.
1 All materials shall conform to the requirements of
6 In areas where leveling courses are required, as
Sub-section 4.1.
shown on the Drawings or directed, the Contractor shall
take cross sections of the existing pavement after
4.7.3 Job Mix and Project Mix completing any patching. The cross sections shall be
1 The job mix formula shall be established by the taken at intervals of 12.5 meters or as directed. When the
Contractor in accordance with the procedures and survey is approved, the Engineer will determine and
requirements of Sub-section 4.3. inform the Contractor of the locations, grades and
thicknesses of leveling courses to obtain the desired
2 The job mix for bituminous leveling shall conform to
surface.
the requirements for binder course as provided in Sub-
section 4.5. 7 Prior to placing the leveling courses, the existing
pavement surface shall be prepared in accordance with
the relevant requirements of Sub-section 4.3, including the
use of prime and tack coats as appropriate.

♦ 4-28 ♦
4.7.8 Delivery, Spreading and Finishing tools and other items necessary for the proper completion
of the work.
1 Delivery, spreading and finishing of leveling courses,
including compaction, shall conform to the relevant 4.7.14 Items in the Bill of Quantities
requirements of Sub-section 4.5.
i. Bituminous Leveling Course.
2 In areas where a specific grade and super-elevation
ii. Bituminous Patching Work.
are to be achieved by the leveling courses, setting out and
level control shall be based on a reference line installed in
accordance with the relevant requirements of Sub-section 4.8 Bituminous Cold Mix Courses
4.3. In areas of minor leveling such as filling of pits or
small isolated areas, a mobile reference line or alternative 4.8.1 Description
control system may be approved.
1 This Sub-section describes requirements for
furnishing materials, mixing manually or at a central
4.7.9 Sampling and Testing
mixing plant, or in a travel-mix plant and spreading and
1 Sampling and testing of leveling courses shall compacting bituminous cold mix courses comprising
conform to the relevant requirements of Sub-section 4.3 - unheated mineral aggregate or cut-back asphalt on a
and Table 4.3.9.1. prepared surface, as shown on the Drawings or directed
2 Where sampling and testing are not feasible due to by the Engineer.
thickness or other constraints, the Engineer will determine
specification compliance based on an approved rolling 4.8.2 Materials
pattern or other basis. 1 All materials shall conform to the relevant
requirements of Sub-section 4.1.
4.7.10 Surface Tolerances
2 The type and grade of bitumen for the paving
1 Surface tolerances for leveling courses shall conform mixture shall be as shown on the Drawings or as directed.
to the relevant requirements for binder courses in Sub- The bitumen shall conform to the relevant requirements of
section 4.5. AASHTO M 81,M 82, M 140 or M 208.

4.7.11 Determination of Thickness 4.8.3 Job Mix and Project Mix


1 The Engineer may use thickness measurements, 1 The job mix formula shall be established by the
spread rates, cross section or other methods to verify Contractor in accordance with the procedures and
quantities placed. Thickness measurements shall be in requirements of Sub-section 4.3.
accordance with the relevant requirements of Sub-section 2 The job mix shall conform to the relevant
4.3. requirements of Sub-section 4.4 or Sub-section 4.5, as
appropriate.
4.7.12 Method of Measurement
1 Bituminous leveling courses shall be measured by 4.8.4 Equipment
the cu.m. of mix furnished, spread, compacted, completed 1 Plant and equipment for mixing, hauling, placing and
and accepted. Measurements shall be based on the areas compacting bituminous cold mix courses shall conform to
and thicknesses shown on the Drawings or as directed. the relevant requirements of Sub-section 4.3. In the
2 Bituminous patching work shall be measured by the continuous mixing plant, the devices feeding bituminous
cu.m. of mix furnished, spread, compacted, completed material, aggregate and water shall be interlocked to
and accepted. Measurements shall be based on the areas maintain automatically the correct proportions. In a travel
and thicknesses shown on the Drawings or as directed. No mix plant, the equipment used may be either a hopper
measurements will be made of unauthorized areas or type, or a rotary type mixer. Both types of equipment
extra thickness. shall be capable of thoroughly mixing the bituminous
3 The rates for bituminous leveling course and for material and aggregate, uniformly dispersing the
patching work shall be deemed to include for all incidental bituminous material, and adequately coating the
costs as stated in Sub-section 4.3, Clause 4.3.12. aggregate particles to produce a uniform mix.

4.7.13 Basis of Payment 4.8.5 Construction of Trial Sections

1 The amount of completed and accepted work, 1 Trial Sections shall be constructed as and where
measured as provided for above, will be paid for at the directed and in accordance with the relevant requirements
unit rates for the various items in the Bill of Quantities , of Sub-section 4.3.
which rate shall be full compensation for supplying
materials, transporting and placing, for labor, equipment,

♦ 4-29 ♦
4.8.6 Mixing Procedures 4.8.12 Method of Measurement
1 Handling and mixing of bitumen and aggregate shall 1 Bituminous cold mix courses shall be measured by
be in accordance with the relevant requirements of Sub- the cubic meter of mix furnished, spread, compacted,
section 4.3, with the following exceptions: completed and accepted. Measurements shall be based
on the areas and thicknesses as shown on the Drawings.
i. Aggregates shall not be heated but shall be fed 2 Deficiencies in thickness of bituminous cold mix
cold to the plant. The temperature of the wearing course shall, unless an overlay is constructed at
bitumen upon entering the pugmill shall be the Contractor's expense, result in a proportion only of the
adequate to ensure uniform application to the wearing course volume being measured for payment.
cold aggregate. The bitumen temperature shall Proportions shall be determined in accordance with the
be designated by the Engineer and shall thickness deficiencies and volume proportions stated Sub-
generally be in accordance with the relevant section 4.3, Table 4.3.11.1.
requirements of Sub-section 4.1.
ii. Mixing time shall be the shortest time necessary 4.8.13 Basis of Payment
to remove excess volatiles or water and to
1 The amount of completed and accepted work,
produce a satisfactory mixture.
measured as provided for above, will be paid for at the
unit rates for the various items in the Bill of Quantities ,
4.8.7 Surface Preparation
which rate shall be full compensation for supplying
1 Preparation of the surface upon which bituminous materials, transporting and placing, labor, equipment,
cold mix courses are to be laid, and the use of prime and tools and other items necessary for the proper completion
tack coats shall be appropriate to the type and condition of of the work.
such surfaces and shall conform to the relevant
requirements of Sub-section 4.3. 4.8.14 Items in the Bill of Quantities
i. Bituminous cold mix course.
4.8.8 Delivery, Spreading and Finishing
1 Delivery, spreading and finishing of bituminous cold 4.9 Pavement Repairs and
mix courses shall conform to the relevant requirements of
Reinstatement
Sub-section 4.3.
2 Requirements for rolling and compaction shall 4.9.1 Description
comply with the relevant requirements of Sub-section 4.4 -
or Sub-section 4.5, as appropriate. 1 This Sub-section describes requirements for surface
milling, removing defective bituminous pavement,
4.8.9 Sampling and Testing preparing surfaces to receive repairs, furnishing materials,
placing and finishing new pavement, as shown on the
1 Sampling and testing shall conform to the relevant Drawings or directed.
requirements of Sub-section 4.3 and Table 4.3.9.1.
4.9.2 Materials
4.8.10 Surface Tolerances
1 Subgrade materials shall conform to the relevant
1 Surface Tolerances shall conform to the relevant requirements of Sub-section 2.6.
requirements of Sub-section 4.4.
2 Aggregate sub-base and base course materials shall
2 Finished elevations and straight edge tolerances shall conform to the relevant requirements of Sub-section 3.1.
conform to the relevant requirements of Sub-section 4.4 -
3 Bituminous pavement materials shall conform to the
or Sub-section 4.5, as appropriate.
relevant requirements of Sub-section 4.1.

4.8.11 Determination of Thickness


4.9.3 Equipment
1 Procedures for determining the average compacted
1 All plant and equipment shall conform to the
thickness of bituminous cold mix courses shall conform to
requirements of the relevant Sections of this Specification.
the relevant requirements of Sub-section 4.3.
2 Cores for thickness measurements of bituminous 4.9.4 Preparation of Pavement
cold mix courses shall be used to determine if changes are
necessary in the thickness of succeeding layers in 1 Cracks in bituminous pavement which, in the opinion
accordance with the relevant requirements of Sub-section of the Engineer, do not require reconstruction shall be
4.4 or Sub-section 4.5, as appropriate. prepared by wire brushing and blowing out with
compressed air.
2 Prior to the application of bituminous overlays, the
existing pavement shall be planed or milled out by

♦ 4-30 ♦
approved equipment to the depth shown on the Drawings be compacted by steel wheeled roller, first compacting the
to remove the asphalt surface that contains hardened 150 mm strips adjacent to the traffic edges, then rolling in
asphalt, contaminated material, fuel spots, rubber the direction of traffic.
deposits, laitance and any undesirable material that 6 New utility trenches shall be backfilled to the details
prevents proper bonding and adhesion with the new shown on the Drawings, or ordered, including any
asphalt overlay. surrounds, haunching or protective materials.
3 Defective bituminous pavement which, in the opinion Construction of subgrade and pavement shall be as for
of the Engineer, requires reconstruction shall be cut back pavement repairs.
to good material using pneumatic cutting tools. The cut 7 No excavated areas shall remain open overnight
area shall be square or rectangular and in line with the without adequate safety and protection measures subject
direction of traffic. The depth of cut shall be determined to the approval of authorities.
by the Engineer and may include bituminous layers, base
and sub-base layers and subgrade layers (in the case of 4.9.6 Sampling and Testing
failed pavement, excavation shall include a minimum of
300 mm of subgrade material). All excavated materials 1 Testing of repair materials shall conform to the
shall be removed and disposed of off-site. When the relevant requirements of Sub-section 3.3 and Table 4.3.9.1.
bottom of the excavation consists of earth or granular Sampling shall be as ordered by the Engineer.
material it shall be thoroughly compacted using
mechanical compactors to the satisfaction of the Engineer. 4.9.7 Surface Tolerances
Exposed bituminous surfaces shall be thoroughly cleaned
1 Levels shall be checked by straight edge in relation to
and wire brushed prior to receiving repair materials.
the adjacent existing pavement.
4 Utility trench reinstatements in bituminous pavement
2 Surface tolerances for bituminous layers shall
shall be prepared in the same way as defective bituminous
conform to the relevant requirements of Sub-section 4.4
pavement. Excavation depth shall be a minimum of 300
and Sub-section 4.5 as appropriate.
mm from the top of subgrade layer.
3 Any deficiency in the wearing course surface shall be
4.9.5 Placing and Finishing Repair corrected by cutting out and replacing.
Materials
4.9.8 Method of Measurement
1 Cracks of 3 mm to 7mm width or wider shall be filled
with clean, coarse sand then saturated with 1:1 diluted 1 Sealing of cracks shall be measured by lin.m. of
emulsified bitumen, or as directed by the Engineer. Cracks cracks sealed and approved by the Engineer.
of less than 3 mm shall be filled with emulsified bitumen, 2 Milling shall be measured by the sq.m. of the area
or as directed. Cracks shall be filled to the road surface. milled to the specified depth, including equipment,
Any excess bitumen shall be removed with a squeegee application, removal and disposal of the milled material
and the bitumen surface shall be sprinkled liberally with off the site.
coarse sand. 3 Pavement repairs shall be measured by the sq.m. of
2 Excavations below subgrade level shall be filled to a repair, prepared, filled, compacted, completed and
level specified by the Engineer with subgrade material in accepted. Measurement shall be of the areas shown on
layers not exceeding 150 mm and compacted using the Drawings or ordered.
mechanical compactors to conform to the requirements of 4 Trench reinstatements shall be measured by the
Sub-section 2.6 and to the satisfaction of the Engineer. sq.m. of reinstatement prepared, filled, compacted,
3 Subbase and/or base course, if required, shall be completed and accepted. Measurement shall be of the
placed in layers not exceeding 150 mm and compacted areas shown on the Drawings or ordered. New utility
using mechanical compactors. They shall conform with trench construction will not be measured under this item.
the relevant requirements of Sub-section 3.2 or Sub- 5 No separate measurement will be made for
section 3.3, - as appropriate, and shall be to the grading excavation, prime or tack coats, pavement materials,
shown on the Drawings or specified by the Engineer. subgrade, subbase, or base courses.
4 Prior to receiving bituminous material, the 6 All other incidental items shall not be measured for
excavations shall be thoroughly cleaned. Subgrade, sub- direct payment, as prescribed in Sub-section 4.3 - but
base or base course material shall be primed with a light shall be considered as subsidiary work, the costs of which
coating of MC cutback bitumen and existing bituminous will be deemed to be included in the rates and prices
surfaces shall be lightly painted with emulsified bitumen, stated in the Bill of Quantities.
all in accordance with the requirements of Sub-section 4.2
5 The excavation shall be filled with bituminous 4.9.9 Basis of Payment
pavement materials placed in layers not exceeding 70 mm
1 The amount of completed and accepted work,
and compacted using vibratory compactors. Unless
measured as provided for above, will be paid for at the
ordered to the contrary by the Engineer, the top layer shall
unit rates for the various items in the Bill of Quantities ,

♦ 4-31 ♦
which rate shall be full compensation for supplying 5 Quality control tests for density, thickness and mix
materials, transporting and placing, labor, equipment, properties shall be performed as instructed by the
tools and other items necessary for the proper completion Engineer.
of the work. 6 Any work needed to road shoulders, earthworks, side
slopes, road drainage and services shall be carried out as
4.9.10 Items in the Bill of Quantities shown on the Drawings and in accordance with the
i. Surface milling. relevant clauses of Sections 2, 8 and 18.

ii. Crack sealing. 4.10.3.2 Traffic Control


iii. Pavement repairs (overlay and surface
preparation). 1 Traffic control arrangements shall be implemented in
accordance with Section 1, Sub-section 1.8.
iv. Pavement repairs (complete reconstruction).
v. Trench reinstatement. 2 Widening shall be carried out only on one side of the
pavement at a time. The work shall be programmed to
permit continuity of excavation, placing widening material,
4.10 Bituminous Pavement Widening
rolling and finishing with minimum time of disruption to
traffic flow.
4.10.1 Description
3 Reflector barricades shall be placed along open
1 This Sub-section describes requirements for trenches. Lighting shall be placed at each barricade at
widening existing pavements, including excavation night Adequate provision shall be made to enable traffic to
adjacent to existing bituminous pavements and placing a cross at intersecting roads and at commercial, industrial
mixture of aggregates and bituminous binder in and private entrances.
compacted layers.
4.10.4 Method of Measurement
4.10.2 Materials
1 The approved work shall be measured in square
1 Materials for the construction of pavement widening meters of new asphalt surface. Excavation and removal of
shall conform to the requirements of Sub-sections 4.1, 4.2 curb and road drainage elements will not be measured
and 4.3 as appropriate. separately but will be considered subsidiary work, the cost
of which is deemed to be included in the rates for
4.10.3 Construction Requirements pavement widening.

4.10.3.1 Construction 2 Relocation of services will be measured separately


under the relevant items of Sub-section 18.2.
1 The edge of the existing road pavement shall be
excavated to the extent and depth shown on the Drawings, 4.10.5 Basis of Payment
Existing curbs, gullies and drain pipes shall be removed as
shown on the Drawings or instructed by the Engineer. The 1 The amount of completed and accepted work,
bottom of the excavation shall be compacted with suitable measured as provided for above, will be paid for at the
rollers or power rammers to the density specified in Sub- unit rate for Pavement Widening in the Bill of Quantities,
sections 2.5 and 2.6. Adequate provisions shall be made which rate shall be full compensation for excavation,
for drainage of the trench to prevent damage to the trimming, compacting of the excavation, shoulders and
existing road subgrade. side slopes, mixing, placing and compacting bituminous
material and for supplying materials, labor, equipment,
2 The excavation shall be cleaned of loose material and
tools and other items necessary for the proper completion
the edge of the existing pavement shall be cleaned. The
of the work.
excavated base shall be approved by the Engineer prior to
placement of bituminous material. If unsuitable or
4.10.6 Items in the Bill of Quantities
unstable soil is exposed on the excavation bottom it shall
be replaced with suitable material and compacted to the i. Pavement widening.
depth instructed.
3 Prior to placing bituminous material, the edge of the 4.11 Recycled Bituminous Mixes
existing asphalt road layers shall be painted or sprayed
with a thin coat of cut-back bitumen RC-70 or bitumen 4.11.1 Description
emulsion SS-1.
1 This Sub-section describes requirements for
4 Bituminous material shall be placed in the prepared
recycling existing pavement material, including removal,
excavation in layers not exceeding 80mm thick. Machine
crushing and stockpiling existing bituminous pavement,
laying shall be used except for confined areas where the
mixing with new aggregate, bitumen (and, if specified, an
use of a machine would be impracticable. Completion
approved modifying agent) at a central hot mixing plant,
shall be by roller as specified in Sub-sections 4.3, 4.4 or
and spreading and compacting recycled bituminous base
4.5.

♦ 4-32 ♦
course on a prepared surface, as shown on the Drawings required) shall be in accordance with the relevant
or directed. requirements of Sub-section 4.3.
2 Crushing of existing pavement materials for recycling
4.11.2 Materials may be accomplished by portable or stationary crushers
1 Recycled material shall consist of existing or may be the direct result of the pavement removal
bituminous pavement, processed such that 100% will pass method such as cold milling.
a 38 mm (1.5 inch) sieve. 3 Crushed pavement material shall be separated into a
2 If the Engineer determines that recycled bituminous minimum of two sizes prior to heating and mixing. The
material is causing degradation of the aggregate, he shall fine size shall have a minimum of 80% passing a 4.75mm
revise the job-mix as required. (No.4) sieve. The coarse size shall have a minimum of
60% retained on a 4.75mm (No.4) sieve.
3 New materials shall conform to the relevant
requirements of Sub-section 4.1. 4 Heated and dried new aggregate shall be combined
in the appropriate proportions and gradations with the
4 Unless shown otherwise on the Drawings, bitumen
recycled bituminous material and mixed at such
for recycled bituminous base course shall be graded to
temperature and for such time necessary to achieve a
suit the project climatic condition and type of work. If not
thorough coating of the new aggregate. New bitumen
specified, or shown on the Drawings, grade 60-70
and/or modifier shall then be incorporated into the
penetration conforming to the requirements of AASHTO M
mixture and mixed to produce a homogenous mixture
20 shall be used.
with satisfactory coating of all aggregate.
5 Modifying agent used to soften the old bitumen shall
be used in accordance with the manufacturer’s 5 If both bitumen and modifier are used they shall be
instructions and approved by the Engineer. introduced into the mixing area through separate
metering devices.
6 Existing pavement shall be removed in such a
manner as to prevent unnecessary intermixing with the 6 Preheating of the crushed recycled bituminous
underlying base, sub-base or subgrade material. material immediately before introduction to the mixer may
be permitted subject to the approval of the Engineer.
7 The stockpile height shall not be greater than 3
Preheating methods shall not result in loss of bitumen
meters. Construction equipment will not be permitted on
from the recycled material.
the stockpiles.

4.11.7 Surface Preparation


4.11.3 Job Mix and Project Mix
1 Preparation of the surface upon which the recycled
1 The job mix formula shall be established by the
bituminous base course is to be laid shall be appropriate
Contractor in accordance with the procedures and
to the type and condition of such surface and shall
requirements of Sub-section 4.3..
conform to the relevant requirements of Sub-section 4.3.
2 The properties of the new modified mix shall meet all
the requirements of Sub-sections 4.1, 4.3 and 4.4, as 4.11.8 Delivery, Spreading and Finishing
appropriate.
1 The delivery, spreading and finishing of recycled
4.11.4 Equipment bituminous base course shall conform to the relevant
requirements of Sub-section 4.4
1 Plant and equipment for recycled bituminous base
course shall conform to the relevant requirements of Sub- 4.11.9 Sampling and Testing
section 4.4, subject to any modifications by the Engineer.
1 Sampling and testing of recycled bituminous base
2 Plant and equipment for mixing, hauling, placing and
course shall conform to the relevant requirements of
compacting recycled bituminous base course materials
Section 4.3, and Table 4.3.9.1.
shall conform to the relevant requirements of Sub-section
4.3.
4.11.10 Surface Tolerances
4.11.5 Construction of Trial Sections 1 Surface tolerances shall conform to the relevant
requirements of Sub-section 4.4.
1 Trial sections shall be constructed as and where
directed and in accordance with the relevant requirements
4.11.11 Determination of Thickness
of Sub-section 4.3.
1 Procedures for determining the average compacted
4.11.6 Mixing Procedures thickness of recycled bituminous base course shall be in
accordance with the requirements of Sub-section 4.4.
1 Handling and mixing of bitumen (including modifier
and anti-stripping agent, if any) and aggregate (including
recycled material, new aggregate and mineral filler if

♦ 4-33 ♦
4.11.12 Method of Measurement v. AASHTO Designation PP 52-02: Standard
Practice for Operating Inertial Profilers and
1 Recycled bituminous base course shall be measured
Evaluating Pavement Profiles.
by the cubic meter of mix furnished, spread, compacted,
vi. AASHTO Designation PP 53-02: Standard
completed and accepted. Measurement shall be based on
Practice for a Pavement Ride Quality
the areas and thickness shown on the Drawings or as
Specification when Measured Using Inertial
directed.
Profiling System.
2 Removal and crushing of existing pavement
materials for incorporation in recycled bituminous base 4.12.3 Terminology
course shall not be measured for direct payment, but shall
be considered as subsidiary work, the costs of which will 1 The current rideability specifications are based on
be deemed to be included in the rates for recycled International Roughness Index (IRI). As an internationally
bituminous base course stated in the Bill of Quantities. accepted scale for ride quality, IRI is a standardized
3 Bituminous prime and tack coats shall be measured measure of the response of a standard vehicle to
as prescribed in Sub-section 4.2 "Bituminous Prime and pavement profile. IRI is an index computed from a single
Tack Coats". longitudinal profile using a quarter-car model at a
simulated travel speed of (80 km/h). Lane IRI is the
4 All other incidental items shall not be measured for
average of the left and right wheel path IRI values.
direct payment, but shall be considered as subsidiary work,
the costs of which will be deemed to be included in the
4.12.4 Testing Equipment
rates and prices stated in the Bill of Quantities.
1 The rideability testing shall be conducted using a
4.11.13 Basis of Payment high-speed profiler (HSP). The HSP should conform to the
requirements of Class I equipment as defined in ASTM E
1 The amount of completed and accepted work, 950 and to the requirements specified in AASHTO
measured as provided for above, will be paid for at the Designation PP 50-02 and PP 51-02.
unit rates for the various items in the Bill of Quantities ,
2 Prior to testing, calibration and verification
which rate shall be full compensation for supplying
procedures should be in accordance with the
materials, transporting and placing, for labor, equipment,
recommendations provided by the profiler manufacturer.
tools and other items necessary for the proper completion
The equipment should be operated in accordance with the
of the work.
recommendations provided by the manufacturer and
AASHTO PP 52-02.
4.11.14 Items in the Bill of Quantities
i. Recycled bituminous base course 4.12.5 Testing Procedure
1 Continuous and rigorous scrutiny of profiler output is
4.12 Surface Rideability Measurement required. A constant testing speed shall be maintained
through the lead-in distance (100 m minimum) and the
4.12.1 Description test section. Two driving speeds of 65 to 95 km/h are
required.
1 This Sub-section summarizes testing procedures and
road surface rideability specifications for asphalt and 2 The profiles measured for each run should be used to
concrete surfaced pavements. The specifications are compute the IRI value for each wheel path of each 150m
based on the International Roughness Index (IRI) values subsection within the test section. After three runs, the
(average value from three runs and in units of m/km) test data (IRI values) should be reviewed by calculating the
measured using a high-speed profiler tugged by a utility average, standard deviation, and coefficient of variance
vehicle. A minimum lead-in distance of 100 m and a (COV) for each subsection wheel path. If a value of
segment length of 150 m are suggested. standard deviation is greater than 0.016m/km or COV is
greater than 5%, then the test shall be repeated. Additional
4.12.2 Reference Documents for Profiler testing should be done until standard deviation is less
Rideability Testing than 0.016m/km or COV is less than 5% (with obvious
outliers excluded).
i. ASTM E 867 Terminology Relating to Vehicle-
3 After five runs, if a value of standard deviation is
Pavement Systems.
larger than 0.016 m/km or COV is greater than 5%,
ii. ASTM E 950 Test Method for Measuring compare the profiles from the five runs and attempt to
Pavement Roughness Using a Profiler. identify possible equipment or operational problems.
iii. AASHTO Designation PP 50-02: Standard Recalibrate if necessary. Record all data.
Equipment Specification for an Inertial Profiler.
iv. AASHTO Designation PP 51-02: Standard
Practice for Certification of Inertial Profiling
System.

♦ 4-34 ♦
4.12.6 Submittals 4.12.9 Basis of Payment
1 Data for each test shall be stored on media such as 1 The amount of completed and accepted work,
CDs. measured as provided for above, will be paid for at the
2 Hard copy reports shall be provided for each test unit rates for the various items in the Bill of Quantities ,
section. The following information be reported and stored: which rate shall be full compensation for labor, equipment,
tools, materials, transportation and other items necessary
i. Date and time of day.
for the proper completion of the work.
ii. Operator(s) and equipment used.
iii. Weather conditions: temperature, cloud cover,
4.12.10 Items in the Bill of Quantities
and wind.
iv. Surface description: type of pavement and i. International Roughness Index (IRI)
condition. for asphalt pavement (length)
v. Location and description of section: Job ID, ii. International Roughness Index (IRI)
lane, beginning and ending stationing (or other for concrete pavement (length)
location information), and direction.
vi. Total section length.
vii. Data filter settings: High-pass filter setting =
100m.
viii. IRI value of each wheel path and the average of
the two wheel paths for each 150 m subsection.
ix. Raw data.

4.12.7 Required Rideability


1 The IRI value representing the rideability of each
road subsection shall not exceed 1.2 m/km.
2 The schedule provided in Table 4.12.7.1 shall be used
for payment adjustments to the final quantities of the top
layer of the bituminous wearing course paid under Clause
4.5.14 or the final quantities of concrete pavement paid
under Clause 5.7.6. Price adjustments are based on the
average IRI value of the two wheel paths (lane IRI) for each
150m subsection.

Final Roughness
Price Adjustment
IRI (m/km)
≤ 1.2 100%
1.2 – 1.4 98%
1.4 – 1.6 96%
1.6 – 1.9 92%
1.9 – 2.4 85%
Mill, remove and replace the top
2.4 and above wearing course layer
Plane concrete surface
Table 4.12.7.1: Wearing Course Price Adjustment for
Rideability

4.12.8 Method of Measurement


1 The IRI test shall be measured in linear meters for the
total length of pavement tested in each pavement lane
(covering two wheel paths per lane).The rates shall be
deemed to include for all costs including testing
equipment, calibration, interpretation of data and
reporting of results.

♦ 4-35 ♦

S-ar putea să vă placă și