Sunteți pe pagina 1din 30

Ref. Title Page No. Ref. Title Page No.

9.1 Riprap 9-1 9.4.3.3 Pull Out Tests for Anchored Bolts 9-6
9.4.3.4 Pull Out Tests for Untensioned Bolts 9-7
9.1.1 Description 9-1
9.4.3.5 Rock Anchoring Procedures 9-7
9.1.2 Materials 9-1
9.1.3 Construction Requirements 9-1 9.4.3.6 Tensioning Tendons 9-7
9.4.3.7 Grouting for Rock Anchors 9-8
9.1.4 Method of Measurement 9-2
9.4.3.8 Testing of Rock Anchors 9-8
9.1.5 Basis of Payment 9-2
9.1.6 Items in the Bill of Quantities 9-2 9.4.3.9 Application of Sprayed Concrete
and Mortar 9-8
9.2 Gabions 9-2 9.4.3.10 Reinforcement Mesh 9-9
9.2.1 Description 9-2 9.4.3.11 Paint 9-9
9.2.2 Materials 9-2 9.4.3.12 Wire Netting 9-9
9.2.3 Construction Requirements 9-2 9.4.4 Method of Measurement 9-10
9.2.4 Method of Measurement 9-3 9.4.5 Basis of Payment 9-10
9.2.5 Basis of Payment 9-3 9.4.6 Items in the Bill of Quantities 9-10
9.2.6 Items in the Bill of Quantities 9-3 9.5 Rock Grouting 9-10
9.3 Slope Netting 9-5 9.5.1 Description 9-10
9.3.1 Description 9-3 9.5.2 Materials 9-10
9.3.2 Materials 9-3 9.5.3 Construction Requirements 9-10
9.3.3 Construction Requirements 9-3 9.5.4 Method of Measurement 9-11
9.3.4 Method of Measurement 9-3 9.5.5 Basis of Payment 9-12
9.3.5 Basis of Payment 9-3 9.5.6 Items in the Bill of Quantities 9-12
9.3.6 Items in the Bill of Quantities 9-4 9.6 Reinforced Concrete Slope
9.4 Rock Bolts, Anchors Protection 9-12
and Sprayed Concrete 9-4 9.6.1 Description 9-12
9.4.1 Description 9-4 9.6.2 Materials 9-12
9.4.2 Materials 9-4 9.6.2.1 Concrete 9-12
9.4.2.1 Cement Grout 9-4 9.6.2.2 Reinforcement 9-12
9.4.2.2 Rock Bolts Generally 9-4 9.6.3 Construction Requirements 9-12
9.4.2.3 Resin-Anchored Rock Bolts 9-4 9.6.4 Method of Measurement 9-12
9.4.2.4 Mechanically Anchored Rock Bolts 9-4 9.6.5 Basis of Payment 9-12
9.4.2.5 Drain Holes 9-4 9.6.6 Items in the Bill of Quantities 9-12
9.4.2.6 Rock Anchors 9-4 9.7 Sacked Concrete Revetment 9-12
9.4.2.7 Sprayed Concrete and Mortar 9-5
9.4.2.8 Wire Netting 9-5 9.7.1 Description 9-12
9.7.2 Materials 9-12
9.4.3 Construction Requirements 9-5
9.7.2.1 Sacks 9-12
9.4.3.1 General 9-5
9.4.3.2 Rock Bolting Procedures 9-5 9.7.2.2 Concrete 9-12
Ref. Title Page No. Ref. Title Page No.
9.7.3 Construction Requirements 9-12 9.11.3.2 Stabilization with Bituminous
9.7.4 Method of Measurement 9-13 Materials 9-16
9.7.5 Basis of Payment 9-13 9.11.3.3 Stabilization with Vegetative
9.7.6 Items in the Bill of Quantities 9-13 Treatment 9-16
9.11.3.4 Blankets 9-16
9.8 Paving Tile Slope Protection 9-13
9.11.4 Method of Measurement 9-16
9.8.1 Description 9-13 9.11.5 Basis of Payment 9-16
9.8.2 Materials 9-13 9.11.6 Items in the Bill of Quantities 9-16
9.8.3 Construction Requirements 9-13
9.8.4 Method of Measurement 9-13
9.12 Mechanically Stabilized Earth
9.8.5 Basis of Payment 9-13
Retaining Walls 9-16
9.8.6 Items in the Bill of Quantities 9-13
9.12.1 Description 9-16
9.9 Ditch Lining 9-13
9.12.1.1 General 9-16
9.9.1 Description 9-13 9.12.1.2 Standards and Codes 9-17
9.9.2 Materials 9-13 9.12.2 Materials 9-17
9.9.3 Construction Requirements 9-13 9.12.2.1 General 9-17
9.9.3.1 General 9-13 9.12.2.2 Concrete Face Panels 9-17
9.9.3.2 Precast Slabs 9-14 9.12.2.3 Concrete Footings 9-18
9.9.3.3 Stone Ditch Lining and Wash Checks 9-14 9.12.2.4 Steel Reinforcing and Tie Strips 9-18
9.9.4 Method of Measurement 9-14 9.12.2.5 Reinforced (Polymer) Grids 9-18
9.9.5 Basis of Payment 9-14 9.12.2.6 Fasteners 9-19
9.9.6 Items in the Bill of Quantities 9-14 9.12.2.7 Non Metallic Friction Ties and Fixings 9-19

9.10 Filter Layers 9-14 9.12.2.8 Joint Filler (For Use with Concrete Face
Panels) 9-19
9.10.1 Description 9-14
9.12.2.9 Joint Filler (For Use with Concrete Face
9.10.2 Materials 9-14 Panels 9-19
9.10.3 Construction Requirements 9-14
9.12.3 Construction Requirements 9-20
9.10.3.1 Granular Filter 9-14
9.12.3.1 Wall Excavation 9-20
9.10.3.2 Fabric Membrane 9-15 9.12.3.2 Foundation Preparation 9-20
9.10.4 Method of Measurement 9-15
9.12.3.3 Erection of Concrete Face Panels 9-20
9.10.5 Basis of Payment 9-15
9.12.3.4 Backfill Placement 9-20
9.10.6 Items in the Bill of Quantities 9-15 9.12.3.5 Trial Embankment 9-20
9.11 Barriers for Sand Dunes 9-15 9.12.4 Monitoring 9-21
9.12.4.1 General 9-21
9.11.1 Description 9-15
9.12.4.2 Selected Backfill 9-21
9.11.2 Materials 9-15
9.12.4.3 Settlements 9-21
9.11.2.1 Fences 9-15
9.12.4.4 Horizontal Displacements 9-21
9.11.2.2 Bituminous Materials 9-15
9.12.4.5 Durability 9-21
9.11.2.3 Vegetative Materials 9-15
9.12.4.6 Testing Frequency 9-21
9.11.2.4 Water 9-15
9.12.5 Method of Measurement 9-22
9.11.2.5 Blanket Covers 9-15
9.12.6 Basis of Payment 9-22
9.11.3 Construction Requirements 9-15
9.12.7 Items in the Bill of Quantities 9-22
9.11.3.1 Fencing 9-15
Ref. Title Page No.
9.13 Coastal Protection 9-22
9.13.1 Description 9-22
9.13.2 Materials 9-23
9.13.2.1 Quarried Stone for Armour Layers and
Underlayers 9-23
9.13.2.2 Core Material 9-23
9.13.2.3 Filter Fabric – Geotextiles 9-24
9.13.3 Construction Requirements 9-24
9.13.3.1 General 9-24
9.13.3.2 Placement of Core Material 9-24
9.13.3.3 Placement of Armour and Underlayer
Stones 9-25
9.13.3.4 Surveying Technique 9-25
9.13.3.5 Storage, Handling, and Laying of
Geotextiles 9-25
9.13.4 Method of Measurement 9-26
9.13.4.1 Marine Works Generally 9-26
9.13.4.2 Underlayer, rock armour, quarry run and
bedding layer 9-26
9.13.4.3 Dredging for embedded toe protection 9-26
9.14.4.4 Fabrics and membranes ( Geotextile) 9-26
9.13.5 Basis of Payment 9-26
9.13.5.1 Marine Works Generally 9-26
9.13.5.2 Underlayer, rock armour, quarry run and
bedding layer 9-26
9.13.5.3 Dredging for embedded toe protection 9-26
9.13.5.4 Fabrics and membranes ( Geotextile) 9-26
9.13.6 Items in the Bill of Quantities 9-26
9.1 Riprap ASTM Standard D1751, Specification for Preformed
Expansion Joint Fillers for Concrete Paving and Structural
9.1.1 Description Construction.

1 The Sub-section describes requirements for 9.1.3 Construction Requirements


construction of loose or mortared riprap slope protection
and riprap Cut-off walls or watercourse channel protection. 1 The stones shall be wetted and hand-laid with the
flattest face uppermost and parallel to the prepared slope,
9.1.2 Materials starting from the toe and progressing upwards. Stones
shall be arranged in close contact so as to minimize voids,
1 Stone for loose and mortared riprap shall consist of the largest being placed in the lower courses. Spaces
natural stones of broad flat shapes as far as practicable. between large stones shall be filled with smaller stones of
All stone shall be hard, sound, durable, and highly suitable size. The surface of the riprap protection shall be
resistant to weathering and shall be suitable as protection trimmed and prepared as shown on the Drawings.
material for the intended purpose.
2 The mortar bed shall be progressively spread ahead
2 Samples of the stone material proposed for use shall of stone placing. Stones faces in contact with the mortar
be submitted to the Engineer for approval prior to its use shall be clean and free from any defects that will impair
in the work. the bond with the mortar. Stones shall be washed to
3 The minimum apparent specific gravity of the stone remove any dirt or dust immediately before applying
material shall be 2.5 and the maximum absorption shall be mortar. Mortar shall be spaded and rodded between the
6% when tested in accordance with AASHTO T 85. The stones until the voids are completely filled.
stone shall have an abrasion loss not greater than 45% 3 Expansion joints shall be constructed where the
when tested in accordance with AASHTO T 96. riprap is placed against any structure, or where directed
4 The weight of individual stones for the various by the Engineer. A 13 mm thick fiber joint filler (as
classes of riprap shall be as follows: specified in Item 8 of Clause 9.1.2) shall be installed in
expansion joints. The fiber joint shall extend from the base
% of Total
of the grout layer up to 13 mm below the grout surface. A
Weight
Weight of Stone (kilograms) Smaller than bond breaker, as approved by the Engineer, shall be
Weight placed along the bottom of the 13 mm deep by 13 mm
Shown wide notch, and the top shall be filled with flexible joint
Class sealant in accordance with the manufacturer's
Class B Class C Class D
A recommended procedures, as approved by the Engineer.
50 200 1,000 5,000 95-100
4 The completed work shall be cured for at least 7 days
20 100 400 2,000 50-100
5 20 100 500 0-50 by a curing method approved by the Engineer. After the
1 5 20 100 0-10 expiry of this period, the exposed surfaces shall be cleared
of loose mortar and broken stone fragments.
Table 9.1.2.1: Classes of riprap stones and rocks
5 Loose riprap stone shall be placed in the same
5 Unless otherwise indicated on the Drawings or manner as for mortared riprap. The stones shall be
directed by the Engineer, stones for loose and mortared properly selected and placed so as to minimize voids
riprap shall conform to Class B gradation. Stones shall which shall be filled with pieces of the largest possible size.
generally weigh between 20 and 70 kg. with at least 60%
6 After completion and approval of the loose riprap
weighing more than 45 kg.. Nevertheless, any of the
placement, the surface voids of the riprap in the footing
classes shown in Table 9.1.2.1 above can be used for loose
trench and on the lower portions of the slope shall be
riprap, as indicated on the drawings. For mortared riprap,
filled with excavated material, compacted to 95% max. dry
stones of classes A or B only can be used, as indicated on
density and dressed to the satisfaction of the Engineer.
the Drawings.
7 Unless otherwise shown on the Drawings, the
6 Mortar for mortared riprap shall consist of 1 part
thickness of the loose or mortared riprap layer shall not be
Portland cement to 3 parts sand by volume. Water added
less than 1.5 times the nominal stone size and is
shall be the least amount which will yield a workable mix.
commonly 1.8 - 2.0 times the nominal stone size.
Sand and cement shall conform to the relevant
requirements of Sub-section 5.1. The 28 day compressive 8 Where shown on the Drawings, a filter layer (as
strength of the mortar shall be not less than 15 MPa specified in Sub-section 9.10) or an approved construction
measured in accordance with BS 1881, Part 108. fabric shall be laid on the prepared surface to receive
loose riprap. Thickness of filter layer shall be as shown on
7 Filter material for use under loose or mortared riprap,
the Drawings or directed by the Engineer. The slope shall
as shown on the Drawings shall comply with the
be prepared, trimmed and excavated to the surface
requirements of Sub-section 9.10 “Filter Layers”.
approved by the Engineer and as the cross sections and
8 Expansion joint filler shall be rot-proof and of the
levels shown on the Drawings. The filter material shall
preformed, non-extruding, resilient type made with a
bituminous fiber and shall conform to the requirements of

♦ 9-1 ♦
then be laid and compacted to 95% max. dry density, to Engineer’s approval. Samples and manufacturer’s
the satisfaction of the Engineer. certificates shall accompany the proposal.
4 Gabion dimensions shall be as shown on the
9.1.4 Method of Measurement Drawings. A tolerance of ±5% on width and height, and
1 Riprap work shall be measured by the cubic meter of ±3% on length shall be allowed. Gabion shall have
material placed in position. Measurement shall be based diaphragms at 1m centers.
on the dimensions shown on the Drawings. 5 The edges of gabion panels shall be selvedged to
2 Filter material shall be measured by square meter of prevent unraveling of the mesh. Steel wire core used for
the thickness placed in position. Measurement shall be selvedges shall have a nominal diameter of not less than
based on the dimensions shown on the Drawings. 3.5mm. Lacing wire shall have a nominal diameter of not
less than 2.2mm for the wire core. Wire for selvedges and
3 Filter membrane shall be measured in square meter
lacing shall otherwise comply with the same specification
of the material placed in position. Measurement shall be
for the wire used in the mesh.
the area shown on the Drawings.
6 Where shown on the Drawings wire shall be coated
9.1.5 Basis of Payment with a minimum thickness of 0.55mm of dark green or
black PVC, or any other color to the approval of the
1 The amount of completed and accepted work Engineer, which shall be capable of resisting the effects of
measured as provided for above will be paid for at the unit immersion in sea water and exposure to ultra violet light
rates indicated in the Bill of Quantities, which rate shall be and abrasion, when tested for a period not less than 3000
full compensation for selection of materials and removal hours in accordance with ASTM Test G23.
of discarded material, slope preparation, excavation, 7 Stones for gabion filling shall be hard, sound,
backfilling, placing, trimming, finishing and protection of
durable and highly resistant to erosion, to the approval of
finished work and expansion joints and for materials, the Engineer. The specific gravity of the stones shall be
transportation, hauling, labor, equipment, tools, supplies
not less than 2.5. The stone size distribution in each
and other items necessary for the proper completion of
individual box shall be as given in Table 9.2.2.1.
the works.
Size of stones (mm) % of total (by no.)
9.1.6 Items in the Bill of Quantities
80-125 7% maximum
i. Loose stone riprap (class). (cu.m)
ii. Mortared stone riprap (class) (cu.m) 125-200 88% minimum

iii. Filter material (thickness) (sq.m) 200-250 5% maximum


iv. Filter membrane (sq.m)
Table 9.2.2.1: Stones for Gabions

9.2 Gabions 8 Mastic asphalt constituents shall be sand,


penetration grade bitumen and filler. The mastic shall
have the characteristics given in Table 9.2.2.2.
9.2.1 Description
% of total (by
1 This Sub-section describes requirements for gabions Constituents Material Type
mass)
consisting of supplying, building and placing of stone- Sand (5mm Natural sand or
filled galvanized steel wire mesh baskets (or other 55-72
nominal size) crushed rock
approved types of heavy duty plastic mesh) as slope or
Bitumen 80-100 Pen 15-18
watercourse channel protection.
Portland
Filler cement or 13-16
9.2.2 Materials
hydrated lime
1 Gabion boxes shall be made of a hexagonal woven Table 9.2.2.2: Characteristics of Mastic Asphalt
mesh of double twisted hot-dip galvanized steel wire. The Constituents
nominal mesh size shall be 80mm x 100 mm. details of the
type of mesh proposed for use shall be submitted to the 9 Sand-cement grout shall be composed of one part of
Engineer for approval. Portland cement and four parts of sand measured by
volume, mixed with sufficient water to a consistency so
2 Wire used in the fabrication of the gabion shall be
that the grout can flow into and completely fill the voids.
mild steel to ASTM A390 Class 3 or to BS 1052 having an
average tensile strength, before coating of 380 to
500N/mm2. The core wire diameter shall be 3.00 mm 9.2.3 Construction Requirements
before galvanizing. Galvanizing shall comply with BS 443. 1 Gabions shall be placed and built to the lines, levels
3 Non-metallic material for gabion boxes, such as and patterns shown on the Drawings, on a prepared
extruded polypropylene, may be proposed for the

♦ 9-2 ♦
horizontal foundation surface for gabion boxes and 9.2.6 Items in the Bill of Quantities
mattresses and/or sloping foundation surface for gabion
i. Gabions (size). (cu.m)
mattresses, excavated as required, and compacted as
ii. Mastic asphalt grout. (cu.m)
instructed by the Engineer.
iii. Sand-cement grout. (cu.m)
2 Gabion cages shall be securely wired together at
corners and edges, and where there is more than one
course of gabions, the upper course cages shall be laced
9.3 Slope Netting
to the lower course. Before filling, the cage shall be in its
permanent position and laced to adjoining previously 9.3.1 Description
filled cages. 1 This Sub-section describes requirements for
3 Non-metallic gabion cages of proprietary type shall supplying and installing steel wire mesh netting as rock
be constructed according to the manufacturer’s slope protection.
instructions.
4 Stones shall be packed by hand inside the cages as 9.3.2 Materials
tight as practicable with the minimum of voids. The wires 1 Wire slope netting shall consist of a hexagonal
shall be fixed inside the compartments and the units woven mesh of double twisted hot-dip galvanized steel
tensioned in accordance with the manufacturer’s wire. The nominal mesh size shall be 80mm x 100mm.
instructions.
2 All wires shall be mild steel conforming to BS 1052,
5 The cages shall be overfilled with stones to allow for having a minimum nominal diameter of 2.7mm. The wire
subsequent settlement and the lid laced down with shall be hot-dip galvanized in accordance with ASTM A
binding wire to the top of each of the four sides and to the 767, Class II (610g Zinc/sq.m., 2.0 oz. Zinc psf), after
top of the diaphragm panels. fabrication and bending.
6 Where shown on the Drawings, the Contractor shall 3 Spikes for wire slope netting attachment shall be as
grout gabions with hot poured mastic asphalt. The mastic shown on the Drawings and the steel shall comply with
shall be mixed at a temperature of 160-200˚C and poured the relevant requirements of Section 6.
to fill the voids between the stones for the depth shown.
The actual rate of application shall be as approved by the 9.3.3 Construction Requirements
Engineer during construction.
1 The wire netting shall be securely anchored to the
7 Where shown on the Drawings, the Contractor shall
rock face with the driven steel spikes spaced at an average
grout gabions with sand-cement grout. Immediately
of not more than 5m vertically and horizontally around the
before pouring the grout, the stones should be wetted by
perimeter of each section.
sprinkling. The grout shall be poured to fill the voids
between the stones for the depth shown. The actual rate 2 For rock slope faces in excess of 5m high, the netting
of application shall be as approved by the Engineer during shall be hung from hooked rock bolts installed
construction. The grout shall be allowed to set and harden untensioned as specified in Sub-section 9.4 at spacing
before any stormwater is received. The grout shall be kept between 5m and 10m horizontally and vertically.
moist with water for a period of not less than 72 hours. 3 The rock slope face shall be trimmed to the profile
shown on the Drawings and in accordance with the
9.2.4 Method of Measurement relevant requirements of these specifications. The
proposed new section dimensions and fixing points shall
1 Gabions shall be measured by the cubic meter of
be submitted for prior approval by the Engineer. Intact
installed gabion, based on the dimensions shown on the
sound rock masses shall be selected for the bolts and
Drawings. Rates shall be deemed to include for provision
spikes positioning.
and installing all materials, protection of finished work and
all preparatory work including excavation and preparation
9.3.4 Method of Measurement
of ground.
2 Where grouting is required, it shall be measured by 1 The approved wire netting slope protection work
the cubic meter of sand-cement or of mastic asphalt shall be measured by the square meter of the area
applied. installed. Preparation of the rock face and spikes and
fixation accessories shall not be separately measured, but
9.2.5 Basis of Payment shall be deemed included in the rate for wire netting slope
protection.
1 The amount of completed and accepted work
measured as provided for above will be paid at the unit 9.3.5 Basis of Payment
rate for “Gabion” in the Bill of Quantities, which rate shall
be full compensation for slope preparation, protection, 1 The amount of completed and accepted work
drainage, excavation, backfilling, and for materials, labor, measured as provided for above will be paid for at the unit
equipment, tools, supplies and other items necessary for rate for “Wire Slope Netting” in the Bill of Quantities
the proper completion of the work. which rates shall be full compensation for slope and

♦ 9-3 ♦
foundation preparation, drilling, fixing and for materials, shall be flat mild steel plate 150 by 150 by 8mm thick with
labor, equipment, tools, supplies and other items free fit holes. Nuts shall conform to BS 490 and washers
necessary for the proper completion of the work. shall conform to BS 4320.
3 Rock bolts may consist of tensioned or untensioned
9.3.6 Items in the Bill of Quantities dowel bars anchored by resin or grout or mechanically
i. Wire netting slope protection (sq.m) anchored.
4 Protection of rock bolts against corrosion shall be as
9.4 Rock Bolts, Anchors and Sprayed shown on Drawings.

Concrete 9.4.2.3 Resin-Anchored Rock Bolts

9.4.1 Description 1 The point resin anchor shall be formed using a


cartridge system. The remaining length of the bolt shall be
1 This Sub-section describes stabilization of cut or grouted with cement if required by the Engineer. The
natural slopes in soil or rock by one or combination of the grout may be injected after the installation of the bolt and
following methods: rock bolting, rock anchoring and anchor, or the resin and cement grout may be placed in
grouting, shotcreting or guniting, and wire netting. the hole and the bar pushed through the cement grout
into the resin.
9.4.2 Materials 2 If the Engineer so directs, rock bolts shall be de-
9.4.2.1 Cement Grout bonded along the length of bar which is not required for
anchorage purposes by means of a suitable plastic sheath
1 Grout for use in rock bolting and rock anchors, shall preventing the formation of a bond between the grout and
normally consist of a mixture of cement and water only. the bar.
Fine sand aggregate passing No. 16 sieve may be added, if
3 If untensioned dowel bars are used, all voids shall be
approved, for grouting of large holes, etc.
completely filled with grout.
2 Admixtures and filler may be used only if approved
4 If resin-anchored rock bolts are used, the tests
by the Engineer and shall be free from chlorides..
specified in ASTM D4435 shall be carried out. The
3 Cement, sand and water shall conform to the Contractor shall ensure that the resin is not adversely
requirements of Section 5. Sulfate resisting and rapid affected by the cement grout.
hardening cements shall be used only if specified and
approved. 9.4.2.4 Mechanically Anchored Rock Bolts
4 The compressive strength of 150 x 150 mm cubes 1 These shall be of the expansion shell type and full
made of grout and measured in accordance with BS1881 details of the type of bolt and anchorage to be used shall
shall not be less than 17 MPa. at 7 days. Cubes shall be be submitted for approval prior to installation. If approved,
cured in a moist atmosphere for the first 24 hours and mechanical anchorage bolts shall be used in accordance
subsequently under water. with the manufacturer's instructions as approved or
5 Grout mixes shall have good fluidity and low modified by the Engineer who may require mechanically
sedimentation or bleeding in the plastic state, good anchored rock bolts to be cement grouted.
durability and density with low shrinkage in the hardened
state, in order to bond with the side of boreholes and to 9.4.2.5 Drain Holes
provide protection for bolts and anchors, etc. Mix 1 Drain holes shall be drilled into the rock slope to
proportions shall be as specified for the various relieve water pressure buildup in the rock slope. The drain
applications of grout, and grouting trials shall be holes shall be lined with slotted PVC drain pipe and
undertaken as directed by the Engineer. plumbing systems shall be installed to direct water flows
6 All materials shall be proportioned by weight. away from the rock slope, as shown on the Drawings or as
directed by the Engineer.
9.4.2.2 Rock Bolts Generally
9.4.2.6 Rock Anchors
1 All bolts, required to provide support for excavated
or natural rock faces, shall be deformed high tensile steel 1 Rock anchors required to provide support for
bars conforming to the relevant requirements of Sub- excavated or natural rock faces, and at tunnel portals, shall
section 5.2 "Reinforcing Steel" or other type in accordance consist of steel tendons in excess of 10 m in length and
with Drawings. shall conform to AASHTO M204: "Uncoated Stress
2 Rock bolts can be continuously threaded or threaded Relieved Wire for Pre-stressed Concrete".
to allow extension to be fitted as required. One end of the 2 Corrosion protection shall be as shown on the
bolt shall be threaded for a tensioning locking nut, Drawings.
sufficient to ensure that a 10 to 50mm thread length
extends beyond the locking nut. The thread on the bolt
shall be ISO metric coarse series to BS 4190. The washer

♦ 9-4 ♦
9.4.2.7 Sprayed Concrete and Mortar 8 Prior to proceeding with the shotcreting works, the
Contractor shall prepare three test panels for approval,
1 Sprayed concrete (Shotcrete) shall be a mixture of
using the proposed materials, mix design and equipment.
water, cement, sand and aggregate, projected onto the
Each test panel shall be approximately 750mm square,
area of placement, without interruption, by means of a
using plywood or other similar material for the back form
purpose made machine. Sprayed concrete (Shotcrete)
against which the shotcrete is to be sprayed. The
with 28 day cube compressive strength of 25 MPa with an
thickness of sprayed material shall be a minimum of
aggregate smaller than 12.5 mm particle size shall be used.
75mm or the thickness that is to be used in the structure,
2 Sprayed mortar (Gunite) shall be a mixture of water, whichever is greater.
cement and sand projected onto the area of placement
9 After curing the test panels, cores shall be taken for
without interruption, by means of a purpose - made
compression testing at 7 and 28 days. The cores shall be
machine Sprayed mortar (Gunite) with 28 day cube
at least 75mm in diameter and shall be measured and
compressive strength of 25 MPa with sand of maximum
tested in accordance with AASHTO T 22. In addition to
particle size 7mm shall be used.
compression testing, the cores shall be carefully examined
3 Materials, equipment and application procedures visually for soundness or evidence of non-uniformity in
shall generally conform to the latest revision of ACI 506.2 - the consistency of the concrete or mortar.
"Specifications for Shotcreting" unless otherwise specified
hereunder. 9.4.2.8 Wire Netting
4 Portland cement, fine aggregate, coarse aggregate 1 All wires shall be mild steel conforming to BS 1052,
and mixing water shall conform to the requirements of having a minimum nominal diameter of 2.7mm. The
Sub-section 5.1 - "Concrete Materials and Mixes”. The maximum mesh shall be 100mm x 80mm, the wire shall
mixture of coarse and fine aggregate for applications up to be hot-dip galvanized in accordance with ASTM A 767,
250 mm in thickness and applications exceeding 250 mm Class II (610g zinc/sq.m., 2.0 oz. zinc psf), after fabrication
in thickness shall conform to the following grading and bending.
requirements:
2 The hexagonal wire mesh netting shall be triple
Percent Passing By Weight twisted and suitably woven to produce a flexible uniform
net pattern, free of any damage. Both longitudinal sides
Standard Sieve Size Thickness of the netting sheets shall be edged with a wire of
Thickness up
exceeds 250 equivalent standard to that of the netting but greater in
to 250 mm diameter. The lacing-wire used for fixing adjacent netting
mm
sheets shall also be of equivalent standard.
12.5 mm (1/2 in.) 100
9.4.3 Construction Requirements
9.5 mm (3/8 in.) 100 90-100
9.4.3.1 General
4.75 mm (No. 4) 95-100 65-82
1 Before any of the works is commenced, the
2.36 mm (No. 8) 80-95 45-68 Contractor shall submit a detailed method statement to
the Engineer for his approval. The method statement shall
1.18 mm (No. 16) 45-80 30-53 include adequate details concerning the materials, work
procedures, means and methods and frequency of testing
0.600 mm (No. 30) 30-60 20-38 for grouts and anchors; intended by the Contractor, to
carry out the work and achieve the specified requirements.
0.300 mm (No. 50) 10-30 7-22
9.4.3.2 Rock Bolting Procedures
0.150 mm (No. 100) 2-10 2-10
1 After drilling holes of the required diameter and
0.075 mm (No. 200) 0-3 0-3 depth, and after inspection and approval of the holes and
their locations, rock bolts shall be installed and anchored
Table 9.4.2.1: Gradation of Sprayed Concrete Combined
by one of the approved means as described below,
Aggregates depending upon the type of rock bolts being installed.
5 The Cement content per cu.m. of aggregate shall be 2 Grouting equipment shall be of a type capable of
not less than 375 kg.. producing a grout of colloidal consistency by means of
6 If approved by the Engineer, water-reducing, non- high local turbulence while imparting only a slow motion
chloride accelerator admixture, complying with ASTM to the body of the grout. The injection equipment shall be
C494, Type E, and containing not more than 0.1 percent capable of continuous operation with little variation of
chloride ions, may be used. pressure and shall include a system for re-circulating the
grout while actual grouting is not in progress.
7 Reinforcement shall conform to the requirements of
Sub-section 5.2 – “Reinforcing Steel”.

♦ 9-5 ♦
Compressed air shall only be used if approved. an even bearing surface for the cover plate. Where this
Equipment shall have a delivery pressure not exceeding 1 procedure is not possible, a conical aligning seating shall
MN/sq.m. All baffles to the pump shall be fitted with 1.2 be used. Epoxy mortar packing between the bearing plate
mm sieve strainers. All equipment and piping shall be and rock shall be used where directed.
thoroughly washed with clean water after every series of 9 Anchored rock bolts shall be tensioned by either
operations and more frequently if directed. Intervals applying a specified torque to the nut or by using a
between washings shall not exceed 3 hours. hydraulic jack. The Engineer shall instruct the Contractor
3 Mixing of grout shall proceed by water being added as to which method is to be used in particular cases.
to the mixer first, followed by the cement. When these are 10 Where the torque method of tensioning is used, the
thoroughly mixed any admixture or sand shall be added. required tension shall be agreed by the Engineer and tests
Mixing shall continue for at least 2 minutes until a uniform shall be carried out to establish the applied torque
consistency is obtained. The water: cement ratio of the required to achieve this load. Care shall be taken to
mix shall not exceed 0.45 by weight. Mixing by hand will ensure that the threads on the bar and nut are clean and
not be permitted. free from obstructions.
4 Grout shall be injected continuously and in such 11 Where tension is to be applied by hydraulic jack, the
manner as to avoid causing segregation of the grout. The Engineer may require tests to establish the jack gauge
method of injection shall ensure complete filling of the calibration. In calculating the initial load to be applied,
boreholes and complete immersion of the bolt in the grout. loss of tension due to the transfer of load to the locking
The volume of the spaces to be filled by the injected grout nut and washer shall be allowed for.
shall be compared with the quantity of grout injected.
12 Permanent load measuring instruments shall be
Grout shall be allowed to flow from the free end of the
incorporated in selected rock bolts as directed and the
borehole until its consistency is equivalent to that of the
tension in these bolts shall be monitored. Monitoring
grout injected. The opening shall then be firmly closed.
shall be carried out at hourly intervals for the first 4 hours,
Injection tubes shall be sealed off under pressure until the
then at 4-hour intervals up to the first 24 hours, then at
grout has set.
daily intervals up to 20 days after tensioning or at such
5 Polyester resin gel and cure times shall be suited to other times as may be directed.
the working temperature and method of installation of the
13 Where the Engineer directs that the lengths or part of
bolt. The main resin and filler content shall be enclosed in
the length of a rock bolt shall be de-bonded from the
an outer sheath or skin and the catalyst shall be enclosed
surrounding grout, this de-bonding shall be achieved by
in a separate container within the main sheath. The resin
means of a plastic sheath closely fitting around the steel
and catalyst shall be mixed by rotating the bolt by means
bolt.
of a power tool for such time and at such speed as will
ensure the thorough intermixing of the two constituents. 14 All relevant data shall be recorded and presented in
The viscosity of the resin shall be such that complete an approved form. If the Engineer is not satisfied that the
disintegration of the resin sheath is achieved and the anchorage of the bolt is adequate, the Contractor shall
pieces of sheath material do not have a detrimental effect take approved remedial measures to ensure adequate
on the final strength of the anchorage. anchorage.

6 Expansion shells for mechanical anchorage shall be 9.4.3.3 Pull Out Tests for Anchored Bolts
of an approved type and shall be installed in accordance
with the manufacturer's instructions as approved or 1 Before commencement of any work requiring rock
modified by the Engineer. Where such bolts are used in bolts, pull out trials shall be carried out to measure the
close proximity to a rock face where blasting is taking ultimate load carrying capacity of all types of bolts to be
place, the security of the anchorages shall be checked used. Pull out tests shall be carried out according to ASTM
after blasting and the bolts re-tightened or replaced, if Standard method D4435 or BS equivalent.
necessary in a new hole. 2 Trials shall be carried out in rock of a similar nature
7 Each hole shall be drilled straight and each bar shall to that in which the rock bolts will be used. The
lie centrally in the hole and not be in contact with the rock. deformation of rock bolts and the load shall be continually
The diameter shall be 10 mm greater than the bolt monitored until failure. A minimum of 4 tests on each
diameter if grouted with cement. For resin anchored bolts, type of bolt to be used shall be performed. Details of
the hole size shall be determined according to the proposed procedures shall be submitted for approval
anchorage or cartridge size and in accordance with the before commencement of the trials. The anchorage must
manufacturer's recommendations. Allowance shall be be capable of carrying twice the specified working load.
made for the hole size to be slightly greater than the bit 3 These tests will be used to assess the suitability of
size. Tolerance on the diameter of hole shall be plus or proposed anchorage systems in the particular location
minus 2 mm. The hole shall be thoroughly flushed and where the bolts are to be used. Where rock conditions
cleaned after drilling. change, such that anchorage characteristics are affected,
8 The rock surface around each hole shall be trimmed further trials shall be carried out as directed.
flat in a plane normal to the axis of the rock bolt to ensure

♦ 9-6 ♦
4 During construction approximately 5% of all bolt 6 Pre-stressing bars as delivered shall be straight. Any
types shall be tested to twice the specified working load. If small adjustments for straightness necessary on Site shall
significant failures are obtained in the tests results, the be made by hand under the supervision of the Engineer.
Contractor shall carry out further tests and shall take Bars bent in the threaded portion will be rejected. Any
approved remedial measures as directed by the Engineer. straightening of bars shall be carried out cold.
5 A protective barrier (wire netting) shall be erected 7 All cutting to length and trimming of ends shall be by
around the testing equipment to protect and safeguard high speed abrasive cutting wheel, friction saw or any
against any injury to any personnel involved in the testing other mechanical method approved by the Engineer. In
works and any other measures as deemed necessary by rock anchor systems, the cutting action shall be not less
the Engineer. than one diameter from the anchor, and the heating effect
on the tendon shall be kept to a minimum.
9.4.3.4 Pull Out Tests for Untensioned Bolts
8 The tendon or tendons shall be accurately located
1 The efficiency of grouting shall be checked by pulling and maintained in position. Spacers are to be used to
out the bolts (according to ASTM D4435) after such time keep the tendons in their correct position in the borehole.
as will ensure that the cement grout or mortar remains 9 The tendon or tendons shall terminate at the back of
bonded to the bolt when the bolt is withdrawn from its the hole in the rock secured in a ribbed steel cylindrical
hole. A total of 10% of all untensioned bolts shall be anchorage block or be grouted into place over the
tested in this way. The grouted boreholes shall then be 'anchorage length' defined for the working load required.
cleaned out and bolts free from hardened grout reinstalled The end of the borehole shall be filled with a polyester
to the Engineer's satisfaction. resin or cement mortar. The length of anchorage shall be
2 If, in the Engineer's opinion, an unacceptably high sufficient to take the load on the tendons with a safety
percentage of the initial 10% selection of bolts is not fully factor of 2. The remaining length of tendon, (the free
grouted along their length, the Engineer will require length) shall be encased in a corrosion-protected grease-
further tests to be carried out. packed, plastic de-bonding sheet.

9.4.3.5 Rock Anchoring Procedures 9.4.3.6 Tensioning Tendons

1 Care shall be taken to avoid mechanically damaging, 1 All wires or strands stressed in one operation shall
work hardening or heating tendons while handling. All be taken, where possible, from the same parcel. Each
tendons shall be stored clear of the ground and protected cable shall be tagged with its number and the coil number
from the weather, from any other materials and from or numbers of the steel used. Cables shall not be kinked
splashes from the cutting operation of an oxy-acetylene or twisted, and individual wires and strands shall be
torch, or arc-welding processes in the vicinity. In no readily identifiable at the end of the member. No strand
circumstances shall tendons be subjected to any welding that becomes unraveled shall be used.
operation, or on-site heat treatment or metallic coating 2 A tendon when tensioned contains a considerable
such as galvanizing. amount of stored energy, which, in the event of any failure
2 When tendons have been stored on site for a of the tendon, anchorage or jack, may be released
prolonged period, the Engineer may require tests to show violently. The Contractor shall ensure that adequate
that the quality of the tendons has not been significantly precautions are taken during and after tensioning to
impaired by corrosion, stress-corrosion, loss of cross- safeguard persons from injury and equipment from
sectional area or changes in any other mechanical damage which may be caused by the sudden release of
characteristics. this energy.
3 All tendons shall be free from loose mill scale, loose 3 Hydraulic jacks shall be used for tensioning tendons.
rust, oil, paint, grease, soap or other lubricants, or other The tensioning apparatus shall meet the following general
harmful matter at the time of incorporation in the rock requirements:
anchor. Cleaning of tendons shall be carried out either by i. The means of attachment of the tendon to the
wire brushing or by passing through a pressure box jack shall be safe and secure.
containing carborundum powder. Solvent solutions shall ii. Where two or more wires or strands are
not be used for cleaning without approval. stressed simultaneously, care shall be taken
4 Low relaxation and normal relaxation wire shall be in that they are of approximately equal lengths
sufficiently large diameter coils to ensure that the wire between anchorage points at the datum of load
pays off straight. In cases where, in the opinion of the and extension measurement. The degree of
Engineer, straight as-drawn wire is not essential, wire in variation shall be small compared with the
small diameter coils corresponding to the diameter of the expected extension.
blocks in the drawing machine may be used. iii. Tensioning shall be such that a controlled total
5 Pre-stressing strand, however manufactured, shall be force is imposed gradually and no dangerous
in sufficiently large diameter coils to ensure that the secondary stresses are induced in the tendons,
strand pays off straight. anchorage or concrete.

♦ 9-7 ♦
iv. The force in the tendons during tensioning 3 Grouting procedures, injection of grout and strength
shall be measured by direct reading load cells of grout shall be as specified for rock bolting.
or obtained indirectly from gauges fitted in the
hydraulic system to determine the pressure in 9.4.3.8 Testing of Rock Anchors
the jacks. Facilities shall be provided for the 1 Before commencement of any part of the permanent
measurement of the extension of the tendon anchorage works, two trial anchors shall be installed and
and of any movement of the tendon in the tested to ensure that they can carry the specified load with
gripping devices. The load-measuring device a safety factor of 2. Anchor pull tests shall be performed
shall be calibrated to an accuracy within plus according to ASTM D4435 Standard method or BS
or minus 2% and checked at frequent intervals equivalent
agreed with the Engineer. Elongation of the
2 Load/elongation curves shall be plotted and
tendon shall be measured to an accuracy
interpreted by the Contractor and presented with all
within 22% or 2 mm, whichever is more
relevant data in a form approved by the Engineer.
accurate.
v. Complete records shall be kept of all tensioning 3 If either of the trial tests shows that the anchor has a
operations, including the measured extensions, safety factor of less than 2, then the anchorage length and
pressure-gauge, or load-cell readings and the formation shall be modified and two further tests shall be
amount of pull-in at each anchorage. carried out.

vi. Anchorage of the tendons at the rock face end 9.4.3.9 Application of Sprayed Concrete and Mortar
of the borehole shall conform to BS 4447.
vii. The form of anchorage system shall facilitate 1 Carry out shotcreting in a sequence and according to
the even distribution of stress in the concrete a program to be approved by the Engineer
bearing pad. 2 Provide good lighting, rigid and sufficiently wide
viii. Split wedge and barrel-type anchors shall be of working platforms in area where shotcreting is taking
such material and construction that, under the place
loads imposed during the tensioning operation, 3 Protect properly surfaces which are not to be coated
the strain in the barrel will not allow such and keep them free from sprayed concrete.
movement of the wedges to reach the limit of 4 Clean and wet all surfaces thoroughly with a strong
their travel before causing sufficient lateral blast of air and water, immediately prior to the application
force to grip the tendon, or before the limit of of sprayed concrete.
travel of the wedges causes an excessive force
5 Safety: if the exposed rock profile is considered by
in the tendon.
the Engineer to be unsafe, then ensure that the personnel
ix. If proprietary forms of anchorage are used, the
manning the sprayed concrete operation are protected
anchoring procedure shall be in accordance
from falling rock. In this respect the Contractor is advised
with the manufacturer's instructions and
to consider the use of a remote controlled-sprayed
recommendations and as approved by the
concrete machine.
Engineer.
6 Control the thickness and the alignment of the
x. All bearing surfaces of the anchorages of
sprayed material by either guide wires, mortar spotting or
whatever form shall be clean prior to the
plastic studs, to indicate depth. Drill through the concrete
tensioning operation.
lining to establish the thickness of the lining at points
xi. Any allowance for draw-in of the tendon during
selected by the Engineer. Build up each layer of sprayed
anchoring shall be in accordance with the
concrete or mortar by making several passes of the nozzle
Engineer's instructions and the actual slip
over the working area. Project the sprayed concrete or
occurring shall be recorded for each individual
mortar from the nozzle in a steady uninterrupted flow.
anchorage.
Should the flow become intermittent for any reason, the
xii. After tendons have been anchored, the force nozzle man shall direct it away from the work until it again
exerted by the tensioning apparatus shall be becomes constant.
decreased gradually and steadily so as to avoid
7 Layer thickness is governed mainly by the
shock to the tendon or the anchorage.
requirement that the concrete or mortar should not sag.
xiii. Provision shall be made for the protection of
Where thick layers are applied it is important that the top
anchorages against corrosion.
surface be maintained at approximately a 45 degree slope.
9.4.3.7 Grouting for Rock Anchors The minimum allowable thickness of layer according to
the American Shotcrete Association ASA
1 The space in the borehole around the tendons shall recommendations is 25mm. There is no stated maximum
be grouted with a cement grout such that the void shall be thickness for shotcrete layer.
completely filled.
2 Grouting shall be carried out as soon as practicable
after the tendons have been stressed.

♦ 9-8 ♦
8 Where necessary a layer of sprayed concrete or Paragraph 9.4.2.7) shall be made on a daily basis and shall
mortar may be covered by succeeding layers, but it shall represent each application crew, change in mix design, or
first be allowed to take its initial set. All laitance, loose change in procedure. After curing along with and in the
material and rebound must first be removed. Remove any same manner as the structure, the panels shall be cored in
laitance, which has taken final set by grit blasting. Finally the same manner as described for preliminary testing and
clean and wet the surface using adequate blast of air and shall be tested in accordance with AASHTO T 22. Should
water. The time between applications of successive layer cores from any of the test panels fail to meet strength
shall not exceed 24 hours. A longer break may be requirements, the materials in the structure itself shall be
accepted if it can be shown by tests that sufficient bond cored, taking at least 4 cores for each 100 sq.m.
can be achieved represented by the failed test panel. If the average
9 Under no circumstances shall rebound material be strength of these cores meets strength requirements and
worked back into the construction. Keep the work no single core is less than 75% of design strength, the
continually free of rebounded material, by use of a high materials shall be accepted; otherwise the materials in the
pressure air jet or any other necessary means. structure shall be cut out and replaced.

10 The distance of the nozzle from the work shall be 19 Cut and replace any work which is not accepted by
between 600mm and 1000mm. It shall be, as a general the Engineer
rule, aimed perpendicular to the application surface.
9.4.3.10 Reinforcement Mesh
Commence application for vertical or near vertical
surfaces, at the bottom. Embed completely the 1 The reinforcing mesh shall be made up from 5mm
reinforcement, at least, in the first layer. diameter steel bars. Weld the bars to form a 150mm
11 Provide suitable screening of the nozzle and the square grid and fix it firmly to the rock by an approved
application surface during windy and draughty conditions. means such that it is rigidly held during the subsequent
application of sprayed concrete. Ties, anchors and
12 Keep the spraying equipment in good condition by
supports shall be of a material approved by the Engineer.
cleaning frequently. This shall be done at least once per
shift. The spraying nozzle shall be in such condition that 2 Avoid spraying through the reinforcement as the
an even and continuous flow of material is obtained. reinforcement can make hollows and arching effect, which
Change nozzle cover as soon as excessive wear is found in hinder the production of a homogeneous concrete layer.
the cover. The arrangement for the addition of water at Fix reinforcement as late as possible. If a number of
the nozzle must give a uniform wetting of the material. If reinforcement layers are used then they shall be fixed and
the dry mix process is used, add liquid admixtures, if concreted one at a time. When shooting through bars is
approved, with the mixing water at the nozzle. If dry unavoidable, hold the nozzle closer than usual and at a
admixture is used, add it into the dry mix at the latest slight angle in order to permit better encasement, and
possible time. In either case, employ accurately calibrated facilitate the removal of rebound. Clean reinforcement of
and adjustable mechanical means to dispense the any previously deposited rebound material which may
admixture in the correct approved proportions. prevent a proper bond.

13 The capacity of the compressor plant and water 3 The method of fixing shall be such that sprayed
supply shall be large enough to ensure a constant and concrete can be compacted soundly behind the
sufficiently high pressure. The water pressure should be reinforcement at all points.
somewhat higher than the air pressure. Manometers 4 The minimum cover of mesh reinforcement to the
should be provided to measure the air and water pressure. rock surface is to be 25mm. The minimum cover to mesh
14 Damp cure sprayed concrete or mortar for at least 7 reinforcement from the required finished surface of the
days. sprayed concrete is to be 20mm.

15 Make the profile of the finished surface even. Fill any 9.4.3.11 Paint
area of excessive overbreak with sprayed concrete, or
other approved cavity filler, to bring the finished surface 1 Wherever shown on the Drawings, sprayed concrete
level with the general profile of the surrounding finished shall be painted with the indicated material type and color,
sprayed concrete or mortar. to the Engineer’s approval.

16 Sprayed concrete or mortar surfaces shall not be 9.4.3.12 Wire Netting


trowelled, screeded or disturbed in any way unless
specified otherwise. 1 Wire netting is to be used to secure loose rock on the
cut slopes it may be used in conjunction with rock bolts
17 Construction joints shall be tapered to a thin edge
and sprayed concrete. The netting is to be secured to the
over a width of approximately 300mm, unless specifically
rock face in a manner approved by the Engineer.
instructed by the Engineer. No square joints are allowed.
Clean and wet the entire joint thoroughly prior to the
placement of adjacent sprayed material.
18 Testing of sprayed concrete: During the work, three
test panels as described for preliminary testing (under

♦ 9-9 ♦
9.4.4 Method of Measurement 9.5 Rock Grouting
1 Rock bolts shall be measured by lin.m. of each
9.5.1 Description
category installed, including borehole drilling, grouting
and de-bonding if required.. 1 This Sub-section describes installation, drilling and
2 Rock anchors shall be measured by lin.m. of each grouting rock as slope stabilization.
specified capacity installed including borehole drilling,
tensioning, securing and grouting. 9.5.2 Materials
3 Drilling boreholes, de-bonding of rock bolts, trial 1 Grout shall consist of a mixture of cement and water.
bolts and trial rock anchors, testing and monitoring of rock For grouting of large holes fine sand aggregate passing
bolts and rock anchors, grouting of rock bolts and rock 1.18mm AASHTO standard sieve may be added if
anchors, and other ancillary items and work shall not be approved by the Engineer. Chemical admixture and filler
measured separately for direct payment, but shall be may only be used with prior approval of the Engineer.
considered as subsidiary work the costs of which will be
2 The compressive strength of the grout measured in
deemed to be included in the rates for rock bolts and
accordance with BS 1881 shall exceed 15 MPa at 7 days.
anchors.
3 Grout mixes shall have the minimum cement content
4 Shotcrete (concrete) or gunite (mortar) shall be
consistent with the required workability. The grout shall
measured by the cubic meter, applied, The area and
not be subject to bleeding in excess of 2% after 3 hours,
thickness shall be computed from the Drawings unless
nor 4% maximum, when measured at 18˚C in a covered
otherwise directed by the Engineer. The rates shall be
cylinder approximately 100 mm diameter with a height of
deemed to include for all ancillary work, including
grout of approximately 100 mm, and the water shall be
preparation of rock surfaces, provision and maintenance
reabsorbed by the grout during the 24 hours after mixing.
of spraying equipment, finishing and protection of
surfaces and all tests.
9.5.3 Construction Requirements
5 Reinforcing mesh shall be measured by the sq.m of
net area, installed, based on the Drawings unless 1 Rock grouting is the injection under pressure of grout
otherwise directed by the Engineer. Rates are deemed to to consolidate areas of fractured rock. Grouting shall
include for all fixings and laps at joints in the mesh normally proceed from the bottom of the rock slope
upwards.
6 Painting of the shotcrete (if required) shall be
measured by the sq.m. of area painted, based on the 2 Details of methods to be adopted and materials to be
Drawings unless otherwise directed by the Engineer. Rates used, sequence, spacing, diameter and depth of holes to
shall include for all primers and preparatory work. be adopted shall be submitted to the Engineer for prior
approval before proceeding with any pressure grouting.
7 Wire netting shall be measured by the sq.m. of net
Grouting work shall be under the direct control of skilled
area , installed, based on the Drawings unless otherwise
and experienced operatives.
directed by the Engineer. Rates are deemed to include for
all fixings and laps at joints.. 3 The rock slope shall be trimmed and prepared as
specified in Section 2, Paragraph 2.3.3.6 before grouting is
9.4.5 Basis of Payment begun.
4 Clean water shall be used as the flushing medium for
1 The amount of completed and accepted work
drilling, with flows not less than 15 l/minute.
measured as provided for above will be paid for at the unit
rates for the various items stated in the Bill of Quantities 5 The Contractor shall ensure that, at all times,
which rates shall be full compensation for slope and grouting work is under the direct control of skilled and
foundation preparation, drilling, fixing and for materials, experienced operatives. The Engineer may vary the
labor, equipment, tools, supplies and other items methods, materials and grouting pressures if, in his
necessary for the proper completion of the work. opinion, the conditions dictate a change of technique. All
holes to be grouted shall be numbered, as directed and
9.4.6 Items in the Bill of Quantities grouting operations shall take place in the following order:

i. Rock Bolts (lin.m) i. Drilling of holes


ii. Rock Anchors (lin.m) ii. Washing of holes
iii. Shotcrete (cu.m) iii. Water testing
iv. Gunite (cu.m) iv. Pressure grouting
v. Wire Netting for Shotcrete (sq.m)
vi. Reinforcing Mesh (sq.m) 6 The hole spacing shall normally be 1.6m to 5.0m with
additional holes as required to intersect individual weaker
vii. Painting (sq.m)
areas. Hole depth shall be limited to the range 3-10m and
hole diameter shall be within the range 38-78mm, drilled
with either rotary or rotary-percussive drilling equipment.

♦ 9-10 ♦
Water or air flush may be used unless otherwise directed 12 Grouting can be considered complete when the
by the Engineer. absorption of grout at the required pressure is less than 2 l
7 Holes shall be jetted using a water flow, under such per min over a period of 10 minutes.
pressure as may be directed. The injection of water shall 13 Grouting shall proceed with caution until experience
be followed by injection of air under pressure, these of the ground conditions has been gained. Thereafter, if
operations alternating until air bubbles appear at an conditions allow, injection shall proceed at high pressure
adjacent hole. All other holes shall be capped and water to achieve maximum flow from the start of injection.
forced under pressure into the first hole, until unwanted Grout pressure, as measured at the mouth of the hole,
material from fissures washes out from the uncapped hole. shall correspond to 0.4 bar/ per meter depth of hole for
This process shall continue until no more fine material is those areas where the strata to be treated have no
removed, or until directed. The outlet hole shall then be structures in the vicinity. In the vicinity of structures the
capped and the other holes opened. The sequence shall pressure shall be 0.25 bar per meter depth. Uplift gages
be repeated until connections between all holes have been shall be installed and continuously monitored as grouting
established and all fine material removed. After washing, proceeds.
all holes shall be capped. 14 If the required grouting pressure is not attained using
8 Holes shall be water tested in stages or as the a sand-cement mix, grouting shall be suspended and the
Engineer may require. For stage testing, a twin packer hole washed. After several hours, grouting may proceed
and nozzle pipe system shall be used. Water testing again using the sand-cement mix until the desired
equipment shall be capable of ensuring steady pressures pressure is achieved. Should there be any grout leakage
and a delivery of water of 100 l/min at the required between two holes occurs, both holes shall be grouted
pressure. The equipment shall include all necessary tanks, concurrently or the initial hole grouted whilst the second
gauges and water meters. Water shall be pumped at the hole is capped. When injection is interrupted before it is
proposed grouting pressure into the hole to be tested and complete, the hole shall be washed using not less than
the flow measured for 5 or 10 minutes as directed. The 500 liters of clean water.
Contractor shall keep a record of the water flow expressed 15 After grout consumption has reached the limits
in l/min for each stage tested. Additional testing may be previously specified, the Engineer will require additional
required as the grouting operation proceeds. holes to be core drilled. The diameter of the retrieved
9 All grout mixes shall be prepared using high speed, grouted rock cores shall not be less than 50 mm. Three
high shearing action mixers to ensure uniform consistency. representative samples for each 3 m of core shall be taken
When storing mixed grout for short periods, prior to and unconfined compression tests shall be carried out on
pumping, only purpose made agitator tanks shall be used. each core sample. The mean strength of each group of
Where clay or bentonite are incorporated in the grout, cores shall not be less than 3 MN/sq.m. If this value is not
separate mixing tanks shall be provided in which the reached then additional grouting of the rock shall be
bentonite-water mix can be prepared and kept agitated performed until further tests indicate that the strength of
until required. grouted rock cores achieves 3 MN/sq.m. For every 8
10 Ram type pressure pumps shall be used for grouting. treatment holes or at the Engineer's discretion, at least
Precise control of pump pressure and delivery over the one hole shall be cored and the cores tested as outlined
whole range of pressures and volumes are required. above. In the core drilled hole the Engineer may require a
Valves shall be readily accessible for ease of maintenance. water test to be carried out.
All hoses and piping should be of small diameter to 16 Complete details of drilling, water testing and
ensure high velocity flow without segregation. Injection grouting operations including pressures, mixes and grout
may be carried out by either the single line or circulating takes, shall be recorded on daily progress sheets. A
system. Each borehole shall be provided with a short graphical record of such results shall be compiled and
standpipe threaded at its outer end to accept a manifold copies of all progress sheets and records shall be
with a pressure gauge, relief valve and valve enabling submitted promptly for approval.
delivery from the pump to be cut off from the hole.
Pressure gauges shall also be provided at pumps. 9.5.4 Method of Measurement
11 Once grouting has commenced, it shall be continued
1 Rock grouting shall be measured by the volume of
without interruption until completion. Grouting shall
grout used and the linear meter of rock drilling carried out
commence with a mix of 8:1 water: solids ratio. The mix
at the diameter required. Measurement shall be based on
shall be thickened progressively until pressure begins to
the actual quantities of grout material used and boreholes
build up. If pressure build up occurs too quickly, the mix
drilled, as approved by the Engineer. The rates shall be
may be thinned again. The final injection shall use a 1.5:1
deemed to include for water jetting of rock faces and
water: solids mix. If no pressure build up occurs with a
boreholes, and any other ancillary work.
1.5:1 mix, sand may be mixed with the grout, provided
that the sand: cement ratio does not exceed 2:1 by weight.
When the desired pumping pressure is achieved, with
extremely low grout flows, final injection shall take place
with a neat 1:1 water: solids mix

♦ 9-11 ♦
9.5.5 Basis of Payment 7 Concrete shall be cured using water curing with wet
burlap for 7 days. Curing compound can be used in
1 The amount of completed and accepted work
urgent conditions only, to the approval of the Engineer.
measured as provided for above will be paid for at the unit
rate in the Bill of Quantities for ‘Rock Grouting’, which rate
9.6.4 Method of Measurement
shall be full compensation for drilling, pumping, testing,
and materials, labor, equipment, tools supplies and other 1 Reinforced concrete slope protection shall be measured
items necessary for the proper completion of the work. by cu.m. Measurement shall be based on the area and
thickness shown on the Drawings.
9.5.6 Items in the Bill of Quantities
9.6.5 Basis of Payment
i. Drillholes for grouting rock (dia) (lin.m)
ii. Rock grout (cu.m) 1 The amount of completed and accepted work
measured as provided for above will be paid for at the unit
9.6 Reinforced Concrete Slope rates indicated in the Bill of Quantities, which rate shall be
full compensation for slope preparation, excavation,
Protection backfilling, supply, mixing, testing, laying, finishing,
curing, protection of concrete, provision and fixing of
9.6.1 Description reinforcement, and for materials, transportation, hauling,
1 This Sub-section describes requirements for labor, equipment, tools, supplies and other items
construction of reinforced concrete slope protection. necessary for the proper completion of the works.

9.6.2 Materials 9.6.6 Items in the Bill of Quantities

9.6.2.1 Concrete i. Reinforced concrete slope protection (cu.m)

1 Concrete for reinforced concrete slope protection 9.7 Sacked Concrete Revetment
shall be Class 25 as specified in Sub-section 5.1 and
Clause 5.1.3. The slump limits shall comply with the
9.7.1 Description
requirements stipulated in Sub-section 5.7, Paragraph
5.7.2.7. 1 This Sub-section describes requirements for
construction of sacked concrete revetments at
9.6.2.2 Reinforcement embankment slopes, bridge abutments and similar
1 Reinforcement for reinforced concrete slope locations.
protection and elsewhere if required, shall conform to the
relevant requirements of Sub-section 5.2 - “Reinforcing 9.7.2 Materials
Steel ".
9.7.2.1 Sacks

9.6.3 Construction Requirements 1 Sacks for sacked concrete revetments shall be made
from burlap of minimum 200 gm per sq.m. . Sack
1 Reinforced concrete slope protection shall be
dimensions shall be approximately 0.6 m by 0.9 m
constructed at the locations shown on the Drawings.
measured when empty. Relatively clean reclaimed sacks
Placing, finishing and curing of concrete shall conform to
may be used if approved.
all relevant requirements of Section 5, except that only
hand finishing methods will be required.
9.7.2.2 Concrete
2 After the slopes have been properly trimmed and
prepared according to the Drawings, and before laying 1 Concrete for sacked concrete revetments shall be
concrete , the Contractor shall furnish screed rails or other Class 15 as specified in Sub-section 5.1.
grade-indicating devices to control the minimum depth of
concrete and uniformity of the top surface. 9.7.3 Construction Requirements
4 Reinforcing steel shall be cut and fixed in accordance 1 The sacks shall be filled with concrete loosely
with the requirements of Sub-section 5.2. (uncompacted) placed so as to leave room for tying and
5 Joints shall be laid out or referenced accurately. sewing. Approximately 0.035 cu.m. of concrete shall be
Construction joints shall be placed at designated placed in each sack. The sacks shall be closed by sewing,
contraction joints where possible. or at expansion joints if tied with strong twine. Immediately after closing, the
the construction joint falls within 5 m from a free edge or sacks shall be placed and trampled lightly to cause them
expansion joint. Joints for poured joint filler may be
formed in place or sawn in the fresh concrete.
6 Surface finish shall be either a uniform floated or
broomed finish, as directed by the Engineer..

♦ 9-12 ♦
to conform to the earth surface and the adjacent sacks 2 Embankment slopes at bridge abutments and
already in place. elsewhere as shown on the Drawings shall be trimmed to
2 After the slopes have been properly prepared and proper line and grade. A blinding layer of Class 15
approved, the sacked concrete elements shall be placed. concrete, as specified in Sub-section 5.1, shall be placed
The sacks shall be laid in accordance with the details over the full area of surface to be paved, to a minimum
shown on the Drawings. All dirt and debris shall be depth of 50 mm. Precast tiles shall then be laid to the
removed from the top of the sacks before the next course lines and levels shown on the Drawings, on a bedding of
is laid. Sacks shall be placed so that the tied ends will not 20 mm thick, 1:3 cement: sand mortar and joints shall be
be adjacent to one another. Not more than 6 courses of properly aligned and finished, all as specified in Section 12.
sacks shall be placed in any tier until initial set in the first
course of any such tier has taken place. 9.8.4 Method of Measurement
3 Care shall be taken in placing and shaping the sacks 1 Paving tile slope protection shall be measured by
so that the minimum dimensions shown on the Drawings sq.m. of tiles, laid, including all necessary base course,
are obtained, and the finished sacked concrete revetment bedding, blinding and joint filling. Measurement shall be
has minimum voids. based on the dimensions shown on the Drawings.

9.7.4 Method of Measurement 9.8.5 Basis of Payment


1 Sacked concrete revetment shall be measured by 1 The amount of completed and accepted work
cu.m. of concrete filled sacks , installed. Measurement measured as provided for above will be paid for at the unit
shall be based on the dimensions shown on the Drawings. rates indicated in the Bill of Quantities, which rate shall be
full compensation for slope preparation, excavation,
9.7.5 Basis of Payment backfilling, and for materials, transportation, labor,
equipment, tools, supplies and other items necessary for
1 The amount of completed and accepted work
the proper completion of the works.
measured as provided for above will be paid for at the unit
rates indicated in the Bill of Quantities, which rate shall be
9.8.6 Items in the Bill of Quantities
full compensation for slope preparation, excavation,
backfilling, and for materials, transportation, labor, i. Paving Tile Slope Protection (sq.m)
equipment, tools, supplies and other items necessary for
the proper completion of the works. 9.9 Ditch Lining
9.7.6 Items in the Bill of Quantities 9.9.1 Description
i. Sacked concrete revetment (cu.m)
1 This Sub-section describes requirements for stone,
concrete and concrete paving slabs laid as linings to
9.8 Paving Tile Slope Protection ditches and water courses.

9.8.1 Description 9.9.2 Materials


1 This Sub-section describes requirements for paving 1 Paving slabs for channel and ditch lining shall be
tiles, laid as protection to embankments, bridge Class 25 concrete fabricated in accordance with the
abutments and similar locations. relevant requirements of Sub-section 5.1 and to the
dimensions shown on the Drawings.
9.8.2 Materials 2 Stone for ditch lining and wash checks shall be as
1 Precast paving tiles (slabs) used for slope protection specified for riprap in Sub-section 9.1.
shall be manufactured as specified in Section 12. 3 Grout for ditch lining and wash checks shall consist
2 Preformed joint filler shall conform to AASHTO M 33: of 1:3 cement:sand mortar, by volume.
"Preformed Expansion Joint Filler for Concrete". Hot- 4 In situ concrete for ditch lining and wash checks shall
poured joint filler shall conform to AASHTO M 282: "Joint be Class 25, as specified in Section 5.
Sealants, Hot Poured, Elastomeric Type, for Portland
Cement Concrete Pavements". 9.9.3 Construction Requirements

9.8.3 Construction Requirements 9.9.3.1 General

1 Embankment slopes where precast tiles are to be laid 1 Ditch and watercourse channel sides shall be
shall first be rolled. Close to any structures, to prevent trimmed to profiles as shown on the Drawings.
possible damage, a hand rammer shall be used; otherwise
use of a mechanical roller shall be permitted.

♦ 9-13 ♦
9.9.3.2 Precast Slabs shall have a loss on abrasion value of no more than 40%
measured by AASHTO T 96.
1 Precast concrete slabs shall be laid to the lines and
levels shown on the Drawings, on a bedding of 20mm 2 Filter material particle size distribution shall be as
thick 1:3 cement:sand mortar. Joints shall be 10mm wide given in Table 9.10.2.1.
and filled with 1:3 cement:sand mortar. Joints shall be
AASHTO Sieve % passing (by mass)
cured by an approved method for at least 4 days.
50 mm 100
9.9.3.3 Stone Ditch Lining and Wash Checks
37.5 mm 95 - 100
1 Ditch lining and wash check stones shall be placed
with ends and sides abutting and the joints between each 19 mm 50 - 100
row breaking with the joints in the preceding row. The 9.5 mm 15 - 55
larger spaces between stones shall be filled with
4.75 mm 0 - 25
fragments. The stones shall be rammed and compacted.
2.36 mm 0 - 10
2 After the stone surface has been approved the spaces
between stones shall be completely filled with grout, 75 μm 0-5
brushed or broomed into the spaces. The grout shall be Table 9.10.2.1: Filter Material Gradation
cured as specified in Sub-section 9.1.
3 Filter membrane shall be a thermally bonded non-
9.9.4 Method of Measurement woven fabric produced from continuous filament synthetic
fibers. The hydraulic properties shall allow water passage
1 The approved ditch lining works shall be measured of 50-100 l per sq.m.per sec under a 100mm head. The
by the square meter of lining of paving slabs or wash pore size distribution shall be 50% not greater than 70 μm.
checks installed. Measurement of slabs or wash checks
4 The mechanical properties of the membrane fabric
shall be made perpendicular to the ditch centerline along
(that will have a minimum thickness of 1.0mm) shall be as
the top surface at the upstream edge of each wash check.
given in Table 9.10.2.2.
Blinding and bedding will not be separately measured, but
shall be deemed included with the rate for ditch lining. Allowable
Property Test Method
Value
9.9.5 Basis of Payment
Grab Strength 82Kg. ASTM D 4632
1 The amount of completed and accepted work
measured as provided for above will be paid for at the unit Seam Strength 73Kg. ASTM D 4632
rate for ‘Ditch Lining’ in the Bill of Quantities, which rate Puncture Strength 36Kg. ASTM D 751
shall be full compensation for slope preparation, laying, 2
Burst Strength 2N/mm ASTM D 3766
grouting, blinding, bedding, and for materials, labor,
equipment, tools, supplies and other items necessary for Trapezoid Tear 23 Kg. ASTM D 4533
the proper completion of the work.
Apparent Opening Size ASTM D 4571

9.9.6 Items in the Bill of Quantities 1. Soil with 50% or less


particles by mass <0.6mm
i. Paving slab protection and ditch
lining (type, thickness) (sq.m) passing 75 μm sieve
ii. Grouted stone ditch lining 2. Soil with more than
(type, thickness) (sq.m) <0.927mm
50% particles by
iii. Grouted stone wash checks
weight
(type, thickness) (sq.m)
passing 75 μm sieve KFabric>KSoil ASTM D 4491

9.10 Filter Layers Permeability, K 70% ASTM D 4355


Strength
Ultraviolet Degradation
9.10.1 Description at 150 hours
Retained

1 This Sub-section describes requirements for granular


Table 9.10.2.2: Fabric Filter Membrane Properties
filter material or filter membrane as an underlayer to loose
riprap or gabions.
9.10.3 Construction Requirements
9.10.2 Materials 9.10.3.1 Granular Filter
1 Granular filter material shall be a mixture of sand and 1 Sand and gravel filter material shall be spread evenly
hard, clean gravel or crushed rock. The coarser material on a prepared bedding avoiding segregation of particle
sizes. The layer shall be lightly compacted and finished to

♦ 9-14 ♦
an even surface. Bedding and filter layer shall be of the plastic sheets bound together and attached to vertical or
thickness shown on the Drawings. horizontal supports, and presenting up to 50 percent
openings. Samples of the fencing material shall be
9.10.3.2 Fabric Membrane submitted to the Engineer for approval.
1 The surface to receive the fabric membrane shall be
9.11.2.2 Bituminous Materials
smooth and free from sharp projections. The membrane
shall be loosely laid with its long dimension parallel to the 1 Petroleum resin emulsion shall be 1 part petroleum
length of the protection work. Adjoining sheets of fabric resin emulsion diluted with 4 parts of water.
membrane shall be overlapped a minimum of 0.5m or 2 Asphalt emulsion: The proportion of water to dilute
15% of the sheet width, whichever is less. To prevent an asphalt emulsion shall be according to the
slippage of the fabric the areas of overlap shall be secured manufacturer’s recommendation for the type of asphalt
as recommended by the manufacturer and approved by emulsion to be used.
the Engineer.
3 The technical data sheet of the proposed emulsion
shall be submitted to the Engineer for approval.
9.10.4 Method of Measurement
9.11.2.3 Vegetative Materials
1 Granular filter layers shall be measured by the
square meter, of the thickness installed on the basis of the 1 Slow growing perennial shrubs shall be drought
area shown on the Drawings.. Rates are deemed to resistant and adapted to the climate and soil and shall be
include for preparation of the ground. as described in Section 16”
2 Fabric membrane filter that shall be measured by the 2 Long-lived trees shall be of species recommended in
square meter of net area laid, based on the dimensions “Planting list for proposed highway landscape”.
shown on the Drawings. Rates are deemed to include for
preparation of the ground and overlaps at joints. 9.11.2.4 Water

1 Water shall be clean and free of deleterious


9.10.5 Basis of Payment
substances.
1 The amount of completed and accepted work
9.11.2.5 Blanket Covers
measured as provided for above will be paid for at the unit
rate for ‘Filter Layers’ in the Bill of Quantities, which rate 1 Blanket covers shall be made of bituminous or
shall be full compensation for ground preparation, placing concrete pavements, prefabricated landing mats,
and fixing and for materials, labor, equipment, tools membranes, aggregate, and seashells, as shown on
supplies and other items necessary for the proper Drawings.
completion of the work.
9.11.3 Construction Requirements
9.10.6 Items in the Bill of Quantities
9.11.3.1 Fencing
i. Granular filter layer (thickness) (sq.m)
1 The fence bottom shall be installed about 30cm
ii. Fabric membrane. (sq.m)
above ground level
2 The entire windward surface of the dune shall be
9.11 Barriers for Sand Dunes stabilized with dust-control materials, such as bituminous
material (refer to Paragraph 9.11.2.2), prior to erecting the
9.11.1 Description first fence.
3 To maintain the effectiveness of the fencing system,
1 This Sub-section describes requirements for
a second fence shall be installed on the crest of the sand
construction of barriers for sand dunes, to protect against
accumulation.
wind erosion and adverse weather conditions, formed of
fences, bituminous blankets and vegetation generally as 4 Existing old fences shall not be removed during or
shown on the Drawings or as directed by the Engineer. after the addition of new fences.

2 The Engineer will determine the types and locations 5 The proper spacing and number of fences required to
of the protective barriers to be constructed in particular protect a specific area shall be determined by trial and
areas, based on trials and studies of the prevailing observation.
conditions. 6 Mock-ups of the proposed fencing system shall be
constructed to the Engineer’s satisfaction prior to final
9.11.2 Materials approval of the fencing system.

9.11.2.1 Fences

1 Fences shall be made of rolled prefabricated bundles


made of wood slats, slender poles, stalks or perforated

♦ 9-15 ♦
equipment, tools supplies and other items necessary for
9.11.3.2 Stabilization with Bituminous Materials
the proper completion of the work.
1 Trial section shall be laid over an area of 25 square
meters, using approved bituminous material, at the 9.11.6 Items in the Bill of Quantities
specified rate below and to the satisfaction of the Engineer, i. Fences for dune stabilization
prior to commence the actual works.
(height, type). (lin.m)
2 Destroy the dune symmetry by spraying the
ii. Bituminous stabilization of dunes. (sq.m)
bituminous materials at either the center or the ends of
the dune. iii. Vegetative stabilization of dunes. (sq.m)

3 Spray the bituminous emulsion at the rate of 2.25 iv. Dune stabilization with blankets. (sq.m)
liters per meter square to obtain the desired stickiness of
the sand.
9.12 Mechanically Stabilized Earth
9.11.3.3 Stabilization with Vegetative Treatment Retaining Walls
1 The upwind boundaries of the vegetated area shall
be protected by fences or dikes, to prevent the engulfment 9.12.1 Description
of the vegetation.
9.12.1.1 General
2 Selected seed shall be spread as directed and
protected by mulch sprayed with a bituminous material. 1 This work shall consist of constructing retaining walls
using a proprietary system of precast concrete panels
3 Seed on slopes shall be anchored by mulch or restrained by tie-backs into a compacted earth fill, as
matting. approved by the Engineer. They shall be constructed in
accordance with the manufacturer’s drawings and
9.11.3.4 Blankets
specifications and be within the tolerances for lines,
1. After placement of blanket covers, a spray grades and dimensions shown in the Contract Documents
application of bituminous material shall be required to or as established by the Engineer. The wall shall consist of
prevent blanket decomposition and subsequent dust. a type of mechanically stabilized earth wall system
acceptable to the Engineer, and which must be
9.11.4 Method of Measurement constructed by a specialized firm having a minimum of
five years of documented successful experience in the
1 Fencing shall be measured by the linear meter
design and construction of such wall systems. The
installed.
Contractor shall provide a complete set of typical detailed
2 Stabilization with bituminous materials shall be
shop drawings and complete specifications of the
measured by the square meter of area sprayed.
proposed wall system for the approval of the Engineer 90
3 Stabilization with vegetative treatment shall be days prior to ordering materials to construct these walls.
measured by the square meter of area, installed (to the
approved frequency by the Engineer), watered, completed, 2 The design shall address the climate and soil
and accepted. All trials ordered by the Engineer prior to conditions existing in Oman and provide a minimum
the final vegetative treatment works shall not be paid design life of seventy-five years. The specification as
separately, but shall be deemed to be included in the rate presented to the Engineer shall also state any
for the approved final treatment works.
requirements for the thickness of reinforcing strips and/or
4 Stabilization with blankets shall be measured by the limitations on the backfill used in the structure to ensure
square meter of area, installed, using the specified the design life. The final thickness shall be subject to the
materials and to the dimensions shown on the Drawings, approval of the Engineer.
or ordered by the Engineer. All trials ordered by the
Engineer prior to the installation of the final blanket works 3 The term “reinforced soil wall” shall be deemed to
shall not be paid separately, but shall be deemed to be have the same meaning as “mechanically stabilized earth
included in the rate for the approved final blanket works. retaining walls”.

9.11.5 Basis of Payment 4 The works shall include the following:


1 The amount of completed and accepted work i. Reinforced Earth components (panels, high
measured as provided for above will be paid for at the unit adherence galvanized steel strips, connection
rate for ‘Barriers for Sand Dunes’’ in the Bill of Quantities, and joint materials)
which rate shall be full compensation for ground ii. Selected backfill
preparation, placing and fixing and for materials, labor, iii. Pre-casting panels
iv. Leveling pads

♦ 9-16 ♦
v. Wall erection 2 Materials and construction of reinforced earth
vi. Monitoring components shall comply with Section 5 of these
Specifications.
5 Only materials supplied by accredited sub-contractor
or supplier shall be used as Reinforced Earth Components. 9.12.2.2 Concrete Face Panels

6 The Contractor shall submit for prior approval a 1 Concrete shall be Class 30 in accordance with Section
detailed Method Statement that describes all means, 5 of these Specifications, except as specified herein.
method and techniques to be adopted for construction
and installation of the “mechanically stabilized earth 2 All appurtenances and lifting and handling devices
retaining walls”. The Method Statement shall include shall be set in place to the dimensions and tolerances
details of equipment to be used, method of installation of shown on the approved shop drawings prior to casting.
each reinforced earth component taking into consideration
the manufacturer’s recommendations, backfill materials to i. Reinforcing steel shall comply with Sub-
be used backside of wall, testing and reporting, work Section 5.2 of the Specifications.
program and any other information required by the ii. Concrete Finish – The concrete surface
Engineer. pattern and finish for the exposed faces
shall conform to Section 5 of the
9.12.1.2 Standards and Codes Specifications. The rear face of the panel
shall be roughly screeded to eliminate
1 The following standards and codes in their latest surface distortions in excess of 6.5 mm. The
edition shall be particularly applied to works covered color and texture of the finish shall be
by this Specification. approved by the Engineer based on three
trial panels provided by the Contractor prior
i. A 36M (AASHTO M183) - Structural Steel to producing the final panels.
ii. A 123M - Zinc (Hot Galvanized) Coating on iii. Tolerances – All units shall be
Products Fabricated from Rolled, Pressed manufactured within the following
and Forged Steel Shapes, Plates Bars and tolerances:
Strips a- All dimensions within +5 mm.
iii. A 153M - Zinc Coating (Hot Dip) on Iron and b- Angular distortion with regard to the
height of the panel shall not exceed 7
Steel Hardware
mm in 2 m.
iv. A 325 - High Strength Bolts for Structural
iv. Compressive Strength – Acceptance of the
Steel Joints Including Suitable Nuts and
concrete face panels with respect to
Plain Hardened Washers
compressive strength will be determined in
v. A 1011M - Standard Specification for Steel,
accordance with Section 5 of the
Sheet and Strip, Hot-Rolled, Carbon,
Specifications, except that a minimum of
Structural, High-Strength Low-Alloy and one set of test cubes shall be taken from
High-Strength Low-Alloy with Improved each lot of 50 panels or part thereof.
Formability v. Additional Compressive Tests: An
vi. A 615 - Deformed and Plain Billet-Steel Bars additional 4 specimens shall be field-cured
for Concrete Reinforcement in the same manner as the concrete facing
vii. D 1752 - Preformed Sponge Rubber and panels. Compression tests on these
Cork Expansion Joint Fillers for Concrete specimens shall be used to determine the
Paving and Structural Construction length of curing time required and
viii. AASHTO T90 - Determining the Plastic Limit acceptability. Panels will be accepted after
and Plasticity Index of Soils 7 days, provided the compressive strength
of field-cured cylinders exceeds 65% of the
required 28-day strength. Panels with
9.12.2 Materials defects that indicate imperfect molding,
honeycombing, or open texture concrete, or
9.12.2.1 General that do not correspond with the quality of
the approved test panel will be rejected.
1 The Contractor shall make his own arrangements to vi. Rejection – Units shall be subject to
provide the face panels, reinforcing and tie strips, rejection by the Engineer if not in
fasteners, joint filler, and all necessary attachments as conformance with these Specifications or if
recommended by the Manufacturer and approved by the any of the following defects are evident by
Engineer. visual inspection:
a- Defects that indicate imperfect
moulding.

♦ 9-17 ♦
b- Defects indicating honeycombed or carefully inspected to ensure they are true to size and free
open texture concrete. from defects that may impair their strength and durability.
vii. Marking – The date of manufacture shall be 4 The Contractor shall furnish the Engineer with a
clearly scribed on the rear face of each Certificate of Compliance certifying that these materials
panel. comply with the applicable Specifications.
viii. Handling, Storage and Shipping – All units
5 Physical and Mechanical Properties: Reinforcing
shall be handled, stored and shipped in
strips and tie strips shall have a minimum yield point of
such manner as to eliminate the danger of
2,400 kg/sq.cm (235 MN/sq.m); minimum tensile strength
chipping, cracks, fractures and excessive
of 3,700 - 4,500 kg/sq.cm (363-441 MN/sq.m); 0.06%
bending stresses. Panels in storage shall be
maximum phosphorus; and 0.05% maximum sulfur. The
supported on firm blocking located
weight of zinc coating shall be not less than 500 gm/sq.m.
immediately adjacent to tie strips or toggles
to avoid damage to these tie strips and 9.12.2.5 Reinforced (Polymer) Grids
toggles. Any panels, including fastening
hardware, damaged during handling, 1 General: Shapes and dimensions of these elements
storage, or shipping shall be rejected by the shall conform to the dimensions and tolerances shown on
Engineer. the Drawings.
ix. Joint spacing and details for expansion,
contraction, construction and control joints 2 Grid reinforcing elements shall be manufactured by
in the coping and the concrete barrier stretching a punched polyethylene sheet in one direction
parapet shall be as recommended by the under controlled conditions to produce a high tensile
manufacturer and as approved by the
strength orientated structure.
Engineer.
x. Test Panels: The Contractor shall construct 3 Mechanical Properties: The grid shall have a short
and submit at least 3 test panels. The
term strength of not less than 79 kN/m width, determined
materials, including formwork, used in
from tensile testing at 20 degrees Celsius under a constant
construction of all test panels shall be as for
rate of extension of 50 mm/minute. For each batch of
those proposed for use in the Works. The
reinforcing material delivered to Site, or at such other
test panel finish shall be approved by the
times as may be required by the Engineer, the Contractor
Engineer prior to production of any panels
shall submit a test certificate from an approved
for incorporation in the Works. The rear
face of each panel shall have a dense, independent testing laboratory confirming that the
rough texture without honeycombed areas. required strength characteristics have been met. The
The approved panels shall remain available 120 year characteristic strength shall be not less than
on Site throughout the duration of the 29 kN/m width.
Contract, as a standard for judging the
completed works. 4 Physical Properties: The weight of grid shall not be
less than 0.85 kg/sq.m. It shall be immune to attack from
9.12.2.3 Concrete Footings ultra-violet light for a minimum period of 3 years and shall
be immune to attack from all chemicals naturally found in
1 The class of concrete shall be as shown on the soils and to biological attack from micro-organisms. The
approved shop drawings and shall conform to Section 5 of Contractor shall furnish the Engineer with the
these Specifications. manufacturer's warranty to this effect. The minimum roll
width shall be 1 m. Methods of joining reinforcing
9.12.2.4 Steel Reinforcing and Tie Strips
material shall be approved and in accordance with the
1 Tie strips shall be shop fabricated of hot rolled steel manufacturer's instructions.
conforming to the minimum requirements of ASTM A-
1101M, Grade 36 or equivalent. Reinforcing strips shall be 5 Upon manufacture, the reinforcing elements shall be
hot rolled steel and shall conform to the requirements of placed in approved wrapping material which shall prevent
ASTM A-36M or equivalent. The tie strips and reinforcing ultra-violet light from reaching the reinforcing elements.
strips shall be hot dip galvanized conforming to the The reinforcing elements shall be identified with their date
requirements of ASTM A-123M. of manufacture. Upon delivery to Site the Contractor shall
2 The properties of the backfill material to be used provide the Engineer with copies of the manufacturer's
shall be one of the main factors in determining the strip certificates clearly stating the dates of manufacture of the
thickness required to meet the specified design life. reinforcing elements. No reinforcing elements shall be
3 Prior to galvanizing, the tie strips and reinforcing incorporated into the Works if at the time of proposed
strips shall be cut to length and tolerances shown on the incorporation the elements are more than three years old.
plans and the holes for bolts shall be punched in the
locations shown. All reinforcing and tie strips shall be

♦ 9-18 ♦
9.12.2.6 Fasteners Sieve Size % Passing
250 mm 100
1 Fasteners: Bolts and nuts shall have hexagonal heads
100 mm 75-100
and conform to AASHTO M 164, Type 2, except as
0.075 mm 0-15
modified hereunder. Bolts shall be 12 mm in diameter,
30 mm in length with 20 mm of thread length. Fasteners
ii. The Contractor may request that the
shall be hot dip galvanized to AASHTO M 232, Class C. acceptance limits be increased for material
Bolts shall have a minimum yield point of 6,400 kg/sq.cm not meeting the requirement for % passing
(627 MN/sq.m); minimum tensile strength of a 0.075 mm sieve provided an analysis is
8,000 kg/sq.cm (784 MN/sq.m); and minimum elongation submitted, showing that the material
of 12%. passing the 0.075 mm sieve is less than
10% smaller than 0.015 mm, or
9.12.2.7 Non Metallic Friction Ties and Fixings
alternatively that the material is less than
20% smaller than 0.015 mm and the angle
1 The stabilized earth wall structure shall be reinforced
of internal friction as determined by ASTM
with friction strips of polyethylene coated polyester fiber
D 2850 is 25 degrees minimum.
strips or similar material approved by the Engineer. The
iii. Materials shall have a minimum resistivity
reinforcing strips shall have the ultimate strength
when measured in accordance with
indicated on the Drawings, and manufacturer’s test ASTM G 57 of 5,000 ohm-cm.
certificates shall be provided to verify this. iv. Materials having a resistivity less than the
above but greater than 1,000 ohm-cm may
2 Reinforcing strips shall be fixed to the facing panels be acceptable provided that the pH value of
using plastic coated steel anchor loops and toggles, unless the material measured in water extracted
otherwise noted on the approved shop drawings and in from a water-soil mixture is between 5 and
accordance with approved samples. The Contractor shall 10 when tested in accordance with
furnish the Engineer with a Certificate of Compliance ASTM G 51, and that the water extracted
certifying that these materials comply with the applicable from the water-soil mixture has a chloride
Specifications. content of less than 200 ppm and a
sulphates content of less than 1,000 ppm
9.12.2.8 Joint Filler (For Use with Concrete Face Panels)
when tested in accordance with AASHTO T
1 Filler for vertical joints between panels shall be 26.
flexible open cell polyethylene foam strips, unless v. The total sulphide content of the fill shall be
otherwise noted on the approved shop drawings. less than 0.3 gm/kg.
vi. Organic matter content, (difference
2 Filler for horizontal joints between panels shall be between total carbon content and mineral
resin bonded cork filler conforming to ASTM D 1752 (Type carbon content) shall not be greater than
II) unless otherwise noted on the approved drawings. 100 ppm.
vii. If required by the Engineer, the Contractor
9.12.2.9 Joint Filler (For Use with Concrete Face Panels)
shall carry out a test for Biochemical
1 Reinforced Earth selected backfill material can be Oxygen Demand (BOD). The BOD value
either natural soil or material of industrial origin. Backfill shall not exceed 0.004 gm/liter.
shall not contain chalk, unburnt colliery shale, pulverized
full ash, material from swamps, marshes or bogs, organic 4 Backfill for Reinforcing Polymer Grid System
or other materials which, in the opinion of the Engineer,
would result in the structure becoming unfit for its i. Frictional Fill: This material shall contain a
intended use. Prior to placing the granular fill, the maximum of 10% passing the 0.075 mm
Contractor shall certify to the Engineer that the material (No.200) sieve.
conform to the requirements as per specifications and ii. Gradation Requirements: Backfill material
drawings. shall conform to the following gradations:
Sieve Size %(byweight Passing
2 Selected Filter Material for Drainage Layers: Filter
backfill material shall conform to the relevant 125 mm 100
requirements of Section 2. 90 mm 85-100

3 Backfill for Steel Reinforcing Strip System 9.5 mm 25-100


0.600 mm 10-65
i. The selected fill shall conform to the
0.075 mm 0-10
following gradation and shall have a
coefficient of uniformity not less than 2
(Cu=D60/D10 2) :

♦ 9-19 ♦
9.12.3 Construction Requirements 3 Backfill shall be placed in accordance with Section 2
of these Specifications and compacted in accordance with
9.12.3.1 Wall Excavation
the requirements shown below and on the Drawings. The
1 Structure excavation shall be in accordance with the maximum lift thickness shall not exceed 250 mm (before
requirements of Section 2. Limits and construction stages compaction) and shall closely follow panel erection. The
shall be as shown on the Drawings. Contractor shall decrease this lift thickness if necessary to
obtain the specified density.
9.12.3.2 Foundation Preparation
4 At the end of each day’s operations, the Contractor
1 The foundation for the structure shall be graded level shall shape the last level of backfill so as to permit run-off
for a width equal to or exceeding the length of reinforcing of rainwater away from the wall face.
material or as shown on the plans. Prior to wall
construction, except where constructed on rock, the 5 Backfill outside roadway embankment areas shall be
foundation shall be compacted with a smooth wheel compacted to at least 90% AASHTO T 180 maximum
vibratory roller. density. Backfill within roadway embankment areas shall
be compacted to 95% AASHTO T 180 maximum density
2 Any foundation soils found to be unsuitable shall be except for backfill in sub-grade zones which shall be
removed and replaced in accordance with the procedures compacted to 100% AASHTO T 180 maximum density.
in Section 2.
6 The acceptance criteria for control of compaction
3 When concrete face panels are specified, at each shall be given by first the equivalent Relative Density as
panel foundation level a concrete leveling footing shall be determined by ASTM D-2049. Then by large-scale plate
provided as shown on the plans. The footing shall be bearing test, which defines the type of the equipment,
cured a minimum of 24 hours before placement of wall energy, lift thickness, etc ... before beginning compaction,
panels. it is necessary to check that the moisture of the backfill
material is the optimum (± 1.5%) value of modified
9.12.3.3 Erection of Concrete Face Panels
AASHTO standard.
1 Precast concrete panels shall be aligned vertically
using inserts cast into the top edge of panels. Panels shall 7 The compaction shall be carried out in such a way as
be placed in successive horizontal lifts in the sequence to obtain a uniform density, rollers shall move to and from,
shown on the approved plans as backfill placement always parallel to the wall and assuring that the
proceeds. As fill material is placed behind a panel, the overlapping between one run and the next shall not be
panels shall be maintained in vertical position by means of less than 10% of the roller width. Backfill compaction shall
clamps placed at the junction of adjacent panels and be accomplished without disturbance or distortion of
temporary wooden wedges placed in the horizontal or reinforcements and panels. Compaction in a strip one
vertical joint at the junction of the two adjacent panels on meter wide adjacent to the backside of the wall shall be
the external side of the wall. External bracing may also be achieved using an approved manually operated vibrating
required for the initial lift. Vertical tolerances (plumbness) compactor.
and horizontal alignment tolerances shall not exceed 25
8 If a reinforcing polymer grid and connections are
mm when measured along a three meter straight edge.
used, they shall be handled and installed in accordance
The maximum allowable offset in any panel joint shall be
with the manufacturer's instructions and
25 mm. The overall vertical tolerance of the wall
recommendations, copies of which shall be submitted to
(plumbness from top to bottom) shall not exceed 25 mm
the Engineer before commencement of these Works. The
per three meter of wall height.
reinforcing grid shall not contain any cuts, kinks, twists,
9.12.3.4 Backfill Placement blisters or other defects which, in the opinion of the
Engineer, would render it unsuitable for its intended use.
1 Backfill placement shall closely follow the erection of
each lift of panels. The filling material will be graded and 9.12.3.5 Trial Embankment
compacted before the placement of a new layer. The
1 If shown on the Drawings, or if required by the
gradation of the selected granular backfill should be tested
Engineer, a trial embankment shall be constructed prior to
periodically during construction to assure compliance with
start filling. The Contractor shall perform a full scale trial
specifications. This gradation testing should be performed,
compaction test.
at least once for every 500 cubic meter of material placed
and/or whenever the appearance or behavior of the 2 The allocation of the testing area, the system for the
material changes noticeably. Material shall be laid with execution of the embankment and the testing program
layers of uniform thickness, taking care to avoid shall be fixed by the Engineer considering the following:
segregation and water content variations.
i. The equipment shall be the same to be
2 As shown on the shop drawings, reinforcements used during all the construction.
shall be placed normal to the face of the wall.

♦ 9-20 ♦
ii. The trial area shall be leveled and 4 Foundation settlements shall be monitored using
compacted, at approved locations or at steel bars fixed on concrete at a distance of 1-2 meters
locations adjacent to the Site. from the wall facing. The vertical steel bar is to be
protected by means of pipes. Measurements shall be
3 The Engineer shall approve the materials and
taken from the top of the steel bars.
procedures on the basis of the trial results.
9.12.4.4 Horizontal Displacements
9.12.4 Monitoring
1 Possible horizontal displacements will be measured
9.12.4.1 General
within the foundation soil and on the wall surface.
1 The scope of the required monitoring is related to Inclinometers shall be placed in similar locations to the
verifying and certifying the compliance of the work with settlements devices. They shall be installed within the
the design assumptions and construction procedures. In solid bedrock. The measurements shall be frequent and
the meantime, some monitoring is devoted to guide the related to the construction program. Possible horizontal
construction phases of the embankment in order to displacements can easily be checked by a pendulum
minimize the effect of settlements. Those aspects will (plumb bob).
control the following:
9.12.4.5 Durability
i. Selected backfill
1 These investigations are only related to reinforcing
ii. Settlements
strips and are generally carried out at the time of the
iii. Horizontal displacements and overall
regular detailed inspections of the structure, with a
stability
frequency of approximately 10 to 15 years. It may also be
iv. Material durability
opportune to make such investigations if the structure has
9.12.4.2 Selected Backfill serious anomalies, the origin of which is likely to be
sought in the mechanical failure of the strips.
1 Each layer must be subjected to control tests and
meet the requirements before placement of the following 2 The investigation method may vary according to
layer. whether the structure is or is not equipped with durability
test samples. This monitoring and investigation is
2 The testing frequency, as specified, must be performed with special techniques and investigation
considered as a minimum and must be increased method. In order to collect reliable and complete
whenever the appearance and/or behavior of the material information in long term, it is vital that these operations
noticeably changes, be entrusted to a qualified specialist laboratory.

3 The location of testing and/or sampling will be 3 At every investigation, a certain number of test
determined by the Engineer, Test certificates in proper samples are extracted and the backfill sample is taken in
forms shall be promptly sent to the Engineer during the the vicinity of these test samples. Durability test samples
construction, are samples of reinforcing strips of 60 cm long, of the
same type as those used in the structure. They are placed
4 As indicated in the following table, the frequency of
3 in the backfill of the Reinforced Earth mass during the
the testing can be reduced after 5000 m . However, this
construction and can be extracted for the monitoring of
can be done only when the gradation and physical
corrosion phenomena.
properties of the material becomes practically constant.
4 As a general rule, durability test samples are located
9.12.4.3 Settlements
either at the lower part of the structure or, if the latter is at
1 Survey of settlements will be done during the considerable height, at each change in the section of the
construction, particularly where the embankments lay on strips.
compressive soils intending to settle. Settlements shall be
5 At every investigation, one indicator is extracted
monitored by means of two different procedures:
from each zone in which test samples are located. In case
i. Topographic measurements on the wall of abnormal corrosion development, complementary
face investigations must be made; excavations must be opened
ii. Vertical settlements on the foundation for examining the first beds of reinforcements.

2 Topographic measurements will be performed with 9.12.4.6 Testing Frequency


leveling instruments and reference points installed on the
Testing shall be as follows in Table 9.12.4.1:
wall face and with benchmarks located in stable areas.

3 An appropriate quantity of fixed reference points


(steel plates) shall be installed on the panels every 7.5
meters elevation within each selected cross-section, For
those measurements, a tolerance of ± 2 mm is required.

♦ 9-21 ♦
ii. Standard Coping on MSERW (lin.m)
TEST Within first After first iii. Conc. Barrier Parapet on MSERW (lin.m)
3 3
5000 m 5000 m
Grain Size 500 5000 9.13 Coastal Protection
Resistivity 500 5000
9.13.1 Description
pH 500 5000
1 Quarried stone shall consist of natural rock imported
Soluble Salt Content 500 5000
to site from approved quarry sites complying with the
In-situ Density 500 5000 requirements of this section.
Plate Bearing 250 1000 2 Quarry run shall consist of natural rock fragments
Water Content 1000 5000 and complying with the requirements of this section.

Table 9.12.4.1 – Testing Requirements 3 Armour rock shall be the quarried stone placed in the
top or outer layer(s) of the structure exposed to sea
9.12.5 Method of Measurement conditions.

4 Underlayer shall be the quarried stone placed under


1 Mechanically Stabilized Earth Retaining Walls,
the armour rock layer(s)
including concrete face panels and footings shall be
measured by the sq.m of net area of as shown on the 5 Core means the quarry run material forming the bulk
Drawings. portion of the slope and erosion protection fill sections
protected by underlayers and/or armour rock.
2 Vertical limits of each wall for measurement
6 Filter fabric (geotextile) shall be a membrane placed
purposes shall be between the top of the foundation on
between the underlayer and the seabed soil or the core
the outer face (low side) of the stabilized earth wall and
stone that shall allow passage of water while retaining of
the top of the proposed grade at the backside (high side)
seabed soil or core stone in place without clogging.
of such walls. Horizontal limits for measurement purposes
shall be from end of wall to abutment or from end to end 7 The Contractor shall submit for the Engineer’s
of walls. approval a Quality Control Manual for the proposed slope
and erosion protection construction.
3 Standard coping, including concrete, reinforcement,
joint filler, incidentals and erection shall be measured by 8 The Contractor shall submit the following method
linear meter, complete and in place. statements for the Engineer’s approval at least 45 days
prior to the commencement of work on site:
4 Concrete barrier parapet (on stabilized earth walls),
including concrete, reinforcement, fasteners, joint filler i. Method for preparation of seabed as the base.
and incidentals and erection shall be measured by linear ii. Method for placement of core material,
meter of concrete barrier, complete and in place. underlayers and rock armour protection.
iii. Method for surveying procedures to establish
9.12.6 Basis of Payment lines and levels of the various slope and erosion
protection components.
1 The amount of completed and accepted work
iv. Method of quarry selection and armour stone
measured as provided for above will be paid for at the unit
production.
rate for ‘Mechanically Stabilized earth Retaining Walls’ in
the Bill of Quantities, which rate shall be full
compensation for ground preparation, placing and fixing 9 The Contractor shall submit the following test reports
of reinforcement, fasteners, joint filler, material testing directly to Engineer from approved testing services:
and certificates, trial embankment, excavation, backfill,
compaction, waterproofing, integral incidentals (such as i. grading size of material
light pole foundations, sign structure foundations, ii. aspect ratio of material
drainage structures and appurtenances), erection, and for iii. apparent oven dry density of quarried stone
materials, transportation, hauling, labor, equipment, tools, iv. Los Angeles abrasion
supplies and other items necessary for the proper v. water absorption
completion of the work. vi. sodium sulphate soundness
vii. unconfined compressive strength
9.12.7 Items in the Bill of Quantities viii. methylene blue absorption

i. Mechanically Stabilised Earth


Retaining Walls (MSERW) (sq.m)

♦ 9-22 ♦
10 The Contractor shall submit detailed design drawings, 7 Sodium sulphate soundness carried out in
plans, longitudinal profiles and cross-sections across the accordance with BS 812: Part 121 using the 63-125mm
slope and erosion protection at 50m intervals and at crushed rock and a 50mm sieve to determine losses shall
transition zones between the different design sections. be less than 12%.
The drawings shall be based on the up-dated survey
8 The average point load index Is (50) in the planar
carried out at the slope and erosion protection area.
direction of the most pronounced layering, should any
11 The Contractor shall submit bathymetric charts at the visible anisotropy exist, and for sampling testing and
slope and erosion protection at suitable scales of 1:1000 reporting in accordance with ISRM 1986 recommended
and 1:500 including ACAD computer file diskettes in the method, shall be not less than 4.0 MPa with the average
form of point No., x, y, z. minus the standard deviation of the point load index at
least 3.0 MPa; where at least ten valid test results obtained
12 The work shall be performed in accordance with:
from pieces originating from ten randomly selected stones
i. The requirements of the Authorities have been used to calculate the average and standard
ii. BS 6349, BS 812 and ASTM D 1557. deviation.
iii. Recommendations of Construction Industry
9 Methylene blue absorption tests shall be carried out
Research and Information Association (CIRIA)
in accordance with CIRIA SP 83, Appendix 2, in order to
Special Publication No.83 (SP 83).
indicate the presence of deleterious clay minerals, the
13 The Contractor shall employ and pay for a competent results of this test shall not exceed 1.0g/100g.
independent geotechnical testing laboratory with proven
10 The contractor shall carry out for each quarry the
track records to perform testing on rock material to be
three sets of tests as listed in the relevant Clauses above.
placed in the core, underlayers and armour layers of the
The contractor shall submit the results for the Engineer's
structure.
approval of the source of quarried stone for underlayers
and armour layers.
9.13.2 Materials
11 The contractor shall carry out at least three sets of
9.13.2.1 Quarried Stone for Armour Layers and the tests listed in the above Clauses on each consignment
Underlayers of quarried stone for under-layers and armour layers
1 The Contractor shall use armour and underlayer imported to site. A higher frequency of testing may be
stones consisting of quarried rock, dense, sound, fresh, required as instructed by the Engineer, if this, in the
strong, free from weathering, mechanical weaknesses or opinion of the Engineer, is deemed necessary.
chemical decomposition. The stones shall not be liable to 12 Materials failing to comply with any of the
decomposition under the action of sea water. They shall requirements listed above shall not be used in the Works
also be free from any visible defects such as joints, and shall be considered not in compliance with this
discontinuities, fractures, clay seams or bands and water specifications.
soluble material.
9.13.2.2 Core Material
2 The contractor shall use rock materials in armour
layers and underlayers conforming to the classes defined 1 The contractor shall use core material consisting of
by the engineer well graded quarry run complying with the gradation
defined by the engineer.
3 The contractor shall use quarry stone containing no
more than 5% of stones with a length to thickness (l/d) 2 The used fill material shall be quarry run material
ratio greater than 3, where the length (1), is defined as the with percentage of fines (passing sieve 0.075mm) shall not
greatest distance between two points on the stone and the be more than 20%.
thickness,(d), as the minimum distance between two
3 The contractor shall use selected quarry run with
parallel straight lines through which the stone can just
material percentage lighter than 1.0 kg (80mm of
pass. Carry out the test in accordance with CIRIA SP 83,
equivalent diameter) not exceeding 10% and complying
Appendix 2.
with the size gradation defined by the engineer.
4 The contractor shall use quarry stone for armour and
4 The contractor shall use quarry run material
underlayers for testing having a minimum apparent oven
3 complying with the following requirements:
dry density of 2560 kg/m with 90% of the stones having a
density of at least 2600 kg/m3 in accordance with CIRIA SP i. Apparent oven dry density > 2.3 t/m3
83. ii. Water Absorption < 3.0 %
iii. Sodium Sulphate Soundness < 12.0 %
5 The loss of material using the Los Angeles Abrasion
iv. Los Angeles Abrasion < 35.0 %
test in accordance with ASTM C-131 shall not exceed 35%.

6 The water absorption of quarry stone, carried out in


accordance with BS 812: Part 2 shall be less than 3%.

♦ 9-23 ♦
v. Methylene blue absorption < 1.0g/100g 9.13.3 Construction Requirements
5 The contractor shall carry out for each quarry three 9.13.3.1 General
sets of the tests as listed in the above Clauses. The
1 The contractor shall carry out sounding of the seabed
selection of the quarry source will be based on the results
at the slope and erosion protection site in order to
submitted and subject to Engineer's approval.
produce a detailed seabed profile using echo sounder or
6 During construction, the contractor shall take side-scan sonar together with a surface-towed sub-bottom
sufficient sample for every 5000 t of material produced or or similar seismic profiler and a tide gauge and collecting
production for a working day whichever is greater. Three seabed samples. Obtain approval of the Engineer on the
sets of the tests as listed in the above Clauses shall be results of soundings and bathymetry as well as seabed
carried out and submitted to the Engineer. A higher samples before the works commence, and finally
frequency of testing may be required as instructed by the incorporate the same in the drawings.
Engineer, if this, in the opinion of the Engineer, is deemed
2 Seabed clearances: Remove prior to commencing
necessary.
filling works, all unsuitable material, wrecks, floating
7 Materials failing to comply with any of the debris, silt, clay, loose sand and loose material over the
requirements listed above shall not be used in the Works whole area of the slope and erosion protection. Dispose of
and shall be considered not in compliance with this unsuitable material as directed by the Engineer.
specification.
3 The contractor shall remove, in accordance with the
9.13.2.3 Filter Fabric - Geotextiles instructions of the Engineer any silt, loose sand or clay
that exists in the top layers of the seabed. Remove any silt,
1 The work shall consist of furnishing and placing a
loose sand and clay layers to the levels and areas as
geotextile. The geotextile is designed to allow passage of
instructed by Engineer.
water while retaining seabed soil without clogging. The
suitability of used geotextile should be checked against 4 The contractor shall relocate or redirect, at his own
these functional requirements before laying taking into expense, all underwater services, installations etc. that
consideration the seabed soil conditions. may lie in the area to receive rockfilling. He shall carry out
all such redirection or relocation in accordance with
2 Non-woven TERRAM 4000 or equivalent material can
requirements of the relevant local authorities.
be used with the following properties:
2 5 The contractor shall ensure that the founding bed for
i. Weight : 350 g/m
2 slope and erosion protection is natural seabed material
ii. Tensile strength : 23 kN/ m
when working in the sea, consisting of sand, a mixture of
iii. O85 (diameter of holes in a fabric): a suitable
sand and gravel or rock. No filling on silt, loose sand or
hole diameter to prevent the wash out of seabed
clay layers shall be allowed.
and core material ant to retain them in place
without clogging. 6 The contractor shall make his own arrangements for
the supply and transport of slope and erosion protection
3 The contractor shall provide evidence of the
material either by land or sea or both and use appropriate
resistance to deterioration of the geotextiles from
marine and/or land operated plants for filling.
exposure to ultraviolet light and seawater.
7 The contractor shall protect all placed material from
4 The contractor shall carry out sampling of geotextiles
erosion by the action of sea during construction. The
for testing in accordance with sampling procedures
Contractor shall be held responsible for all loss of material
indicated in ASTM - D4354-99.
and displacements that may arise, and shall make good
5 The contractor shall carry out for geotextiles three such losses and displacements at his own expense.
sets of tests to certify the required properties and submit Furthermore, the Contractor shall be responsible for any
the results for the approval of the Engineer. obstruction that may be caused by the deposition of any
material washed out from the filling and remove the same
6 The contractor shall carry out at least three sets of in accordance to the instructions of the Engineer.
tests to verify the required properties on each
consignment of geotextile imported in the site. A higher 8 The contractor shall take all the necessary
frequency of testing may be required as instructed by the precautions to protect the environment and any damage
Engineer, if this, in the opinion of the Engineer is deemed to the environment arise from the Works shall be the
necessary. Contractor's responsibility.

7 Materials failing to comply with any of the 9.13.3.2 Placement of Core Material
requirements listed above shall not be used in the works 1 The contractor shall place materials used to form the
and shall be considered not in compliance with these core to the profiles and levels shown on the Drawings with
specifications. a tolerance of zero above the theoretical level.

♦ 9-24 ♦
2 The contractor shall take measurement of each
material profile as placed before any subsequent layer of All Armour
Design
material is placed to ensure compliance with the specified Depth of Placing Layers and
Profile to
tolerances. Below Low Water Individual
Actual Mean
3 The contractor shall carry out placement of core Level Measurements
Profile(m)
material underwater in such a manner to minimize (m)
segregation of material and to ensure its proper mixing.
The placement methods are subject to Engineer's Dry: above water + 0.35 Dn 50
approval. ± 0.3 Dn 50
level - 0.25 Dn 50
4 The contractor shall place core material 0.75m above
mean sea level and higher in layers not more than 1.0m in + 0.6 Dn 50
loose depth and compact as specified. Less than 5m ± 0.5 Dn 50
5 Before compaction, the contractor shall moisten each - 0.4 Dn 50
layer as necessary. He shall compact each layer with the
More than 5m ± 0.5 Dn 50 ± 1.0m
minimum number of roller passes as agreed with the
Engineer. Where, Dn50 is the diameter of a placement with
6 The contractor shall carry out compaction by heavy equivalent volume to the block with median weight.
vibratory compactor not less than 12 t capacity.
Table 9.13.3.1: Vertical Placing Tolerances
9.13.3.3 Placement of Armour and Underlayer Stones
5 The tolerance on two consecutive mean actual
1 For placing above high low water level, the
profiles shall not be negative. Notwithstanding any
contractor shall place the stone to grade and in such a
accumulation of positive tolerances on underlying layers,
manner to ensure that the larger rock fragments are
the thickness of the layer shall not be less than 80% of the
uniformly distributed and the smaller rock fragments fill
nominal thickness when calculated using mean actual
the spaces between the larger fragments to achieve a well
profiles
keyed, densely packed structure of the specified
dimensions. Hand placing or barring will be required only 9.13.3.4 Surveying Technique
to the extent necessary to secure the results specified.
1 The contractor shall carry out survey measurements
2 The contractor shall not drop or tip into position
using a probe with a spherical end of diameter 0.5 (Dn 50).
quarried stone, but shall place them individually into the
For land-based survey this shall be connected to a staff;
structure in order to achieve an adequate stability and
for underwater survey it will be a weighted ball on the end
deformation to maintain lines and levels shown on
of a sounding chain.
Drawings. He shall tightly pack the stones together so as
to achieve as near as possible a target unit weight of stone 2 The contractor shall carry out measurement profiles
placed of 1.6 t/m3 and do not place them so that they can at intervals of 25m along the length of the structure and at
rock or obtain their stability on a plane by frictional intervals of 3m across the measurement profile.
resistance alone prior to placing further stones.
3 The contractor shall make provisions for diving
3 The contractor shall fill any void below finished
inspections for any part of the structure where
profile level in excess of mean rock size with an
achievement of tolerances may otherwise appear in doubt.
appropriate stone or stones.
4 The contractor shall place rock materials to the levels, 9.13.3.5 Storage, Handling, and Laying of Geotextiles:
dimensions and slopes shown on drawings, and the
1 The contractor shall store and handle geotextile in
surface profile measured in accordance with the surveying
accordance with ASTM D4873-02
procedure outlined in Paragraph 9.13.3.4, to be within the
vertical placing tolerances given in Table 9.13.1.1. 2 For Geotextiles placement, the contractor shall use
overlaps in accordance with manufacture requirements,
and in no case less than 50 cms.

3 The contractor shall place bedding layer as soon as


possible after placement of the geotextile, according to the
approved method statement of the construction procedure.

4 Where seams are required, the contractor shall make


them in accordance with the manufacture requirements.
All seams shall be subjected to the approval of the
Engineer.

5 The contractor shall remove and replace any


damaged or punctured section before or after laying.

♦ 9-25 ♦
9.13.4 Method of Measurement supply of materials, fabrics and membranes, sampling and
testing, ground preparation for laying on horizontal,
1 Underlayer, Rock Armour, Quarry Run and Bedding
sloping, vertical and curved planes, transportation, placing,
Layer shall be measured by the Cu.m of BUND material
protection, labor, equipment, tools, supplies and other
and rubble base (Quarry run), rock armour, and bedding
items necessary for the proper completion of the works.
layer, placed to the lines and levels as shown on the
Drawings.
9.13.6 Items in the Bill of Quantities
2 Dredging for embedded toe protection shall be
measured by the cu.m of material dredged in sand, clay or i. Underlayer (cu.m)
any other material except rock to the lines and levels as ii. Quarry Run (cu.m)
shown on Drawings. Rates inserted by the Contractor shall iii. Rock Armour (cu.m)
be deemed to include for all over cutting in width and iv. Dredging (cu.m)
depth and for sweeping the dredged areas. v. Fabrics and Membranes(type) (sq.m)

3 Fabrics and membranes (geotextile) shall be


measured by the sq.m of the area covered to any width or
girth including extra material for lapping and jointing. No
deduction is made for voids not exceeding 1.00 m2.

9.13.5 Basis of Payment


1 General: In addition to basis of payment of each
particular item, all marine works are also deemed to
include:
i. all surveying works and seabed sounding
ii. clearance of the seabed; removal of unsuitable
material, objects or obstructions,
iii. inspection for and relocation of any existing
underwater services,
iv. protection from sea action,
v. losses due to erosion or damage,
vi. losses/damage due to wave conditions which
may occur during the Contract period including
the Period of Maintenance.
2 The amount of completed and accepted work
measured as underlayer, quarry run, rock armour, and
bedding layer will be paid for at the unit rates indicated in
the Bill of Quantities which rate shall be full compensation
for selection and supply of materials, stone/rockfill,
crushing, screening, testing, transportation, hauling,
stockpiling, relocation, placing, compacting, trimming the
underlying material and slope preparation, removal of
discarded material, excavation and backfilling, finishing
and protection, labor, equipment, tools, supplies and other
items necessary for the proper completion of the works.
3 The amount of completed and accepted work
measured as Dredging for Embedded Toe Protection will
be paid for at the unit rates indicated in the Bill of
Quantities which rate shall be full compensation for
supply and installation of all plant and equipment required
to carry out dredging, pumping and transportation of
dredged material to whatever distance required, hauling,
stockpiling, disposal of discarded material to approved
locations, protection, labor, equipment, tools, supplies and
other items necessary for the proper completion of the
works..
4 The amount of completed and accepted work
measured as Fabric and Membranes (Geotextile) will be
paid for at the unit rates indicated in the Bill of Quantities
which rate shall be full compensation for selection and

♦ 9-26 ♦

S-ar putea să vă placă și