I will let you know when you can go.

It's a lot of beams so pay more attention to the long span


beams, the top hogging steel (over the support) and the bottom bending steel (at mid span)

Be quick to identify the detailed main bars and sizes and advise if not properly placed

On links know the spacing required and see if it’s done right. You can measure one of them and use
visual to see if they are generally ok

Or you can count them in comparison to the scheduled diagram

They should give you their hard copies when you arrive and you locate each and every beam

On plan and schedule