Site plan check / go or no go check/ dumps from tool

Batch file :- pre check of site

Alarm check, call check(UECNT Command)

System backup (LSMR LOGIN, at TOP system backup.. just click)

Secure crt login to take back up (IP LOGIN TO SITE)

Pld(programming logig device) tool:- Site backup while cdu to rdu onversion/ enb site dump.

Once pld done ask FE to start the activity.

Once RDU installed and backhaul connected then FE inform to NOC to start RDU integration.

RDU Integration:-

Again login to Secure CRT

First ping GW ip

Enb ip ping

If both ping successful

Then RUN RDU Script.

Wait for few minute to come up the site.

Once site came up

SW/FW update…. LSMR @ TOP OPTION upgrade SW/FW

RET configuration.

Batch file run… @LSMR batch file available just click for run

Batch file run:- MOCN, PI, Carrier aggregation (CA), Graceful, …

Multicarrier run from parameter option,…..

Post check & Alarm check

Compare pre and post alarm via excel tool.

ATP 11b closed for RDU.

END