QUESTION: 1
You are in process of identifying and documenting the project roles and responsibilities and
create staffing management plan. All of the following should be addressed when listing the roles
and responsibilities EXCEPT:

A. Competency
B. Authority
C. Responsibility
D. Compliance
E. Role

Answer: D

QUESTION: 2
Reserve analysis is a tool /technique in all of the following processes EXCEPT:

A. Cost budgeting
B. Activity resource estimation
C. Risk monitoring and control
D. Activity duration estimation
E. Cost estimation

Answer: B

QUESTION: 3
Which of the following are NOT outputs of the Activity Duration Estimation process?

A. Activity Duration Estimates


B. Schedule baseline
C. None of the choices are correct
D. Updates to activity attribute

Answer: B

QUESTION: 4
Which of the following statements are FALSE regarding the project scope management plan?

http://www.testkiller.com
2 http://www.troytec.com
PMP

A. The project scope management plan describes how the project scope will be defined and
managed by the project scope management team
B. The project scope management plan specifies how formal verification and acceptance of the
project deliverables will be satisfied.
C. The project scope management plan is contained within the project management plan.
D. The project scope management plan identifies the influence and interest of the stakeholders
and documents their expectations
E. The project scope management plan is an output of the Scope
Planning process

Answer: D

QUESTION: 5
Which of the following statements are TRUE regarding various Activity Scheduling tools?

A. PDM allows for conditional branching and iteration of activities


B. PDM uses activity-on-node (AON) diagramming method.
C. PDM allows for conditional branching and iteration of activities
D. PDM uses analogous methods as an estimation technique.

Answer: B

QUESTION: 6
Which of the following can be used to determine what work is included in each work package for
each of your team members?

A. None of the choices are correct


B. WBS dictionary
C. RBS
D. Project scope statement
E. Project schedule

Answer: B

QUESTION: 7

http://www.testkiller.com
3 http://www.troytec.com
PMP

Which of the following statements are FALSE regarding rolling wave plan?

A. Rolling Wave Planning is a phased iterative approach to project development


B. Rolling Wave Planning is a cost and schedule planning technique used in the Activity
Definition process
C. Rolling Wave Planning is the process of decomposing each work package within the WBS
into the corresponding schedule activities required to produce the work package deliverables
D. Rolling Wave Planning describes a form of progressive elaboration planning where the work to
be performed in the near time is planned in detail at a low level of the WBS, while work far in
future is planned for WBS components that are relatively at a high level of WBS.

Answer: C

QUESTION: 8
Which of the following statements are FALSE regarding Expected Monetary Value Analysis
(EMV)?

A. EMV is a statistical concept that calculates the average outcome of project outcomes based on
various assumptions and scenarios.
B. Decision tree analysis is a type of EMV analysis
C. EMV is a tool/ technique of Qualitative Risk Analysis
D. EMV is calculated by multiplying the value of each possible outcome by its probability of
occurrence, and summing them together

Answer: C

QUESTION: 9
Which of the following describes a group of elated schedule activities aggregated at some
summary level, displayed reported as a single activity at summary level?

A. Work activity
B. Control account
C. Planning package
D. Milestone activity
E. Hammock activity

Answer: E

http://www.testkiller.com
4 http://www.troytec.com
PMP

QUESTION: 10
Which of the following are NOT tools/ techniques of the Activity Definition Process?

A. Expert judgment
B. Decomposition, templates
C. Rolling wave planning
D. Planning component
E. Schedule network templates

Answer: E

QUESTION: 11
You are in process of developing an approximation of the costs of resources needed to complete
each schedule activity. Which of the following is the LEAST helpful input?

A. WBS, WS dictionary
B. Market place conditions, commercial databases
C. Cost estimating policies/ templates, historical information, project team knowledge
D. Schedule management plan, staffing management plan, risk register
E. Activity cost estimates, activity cost estimate supporting detail

Answer: E

QUESTION: 12
Planning components are tools/ techniques of the Activity Definition Process. Which of the
following are planning components?

A. Rolling wave planning, decomposition


B. Control account, planning package
C. Milestone list, schedule network templates
D. Control package, planning account

Answer: B

http://www.testkiller.com
5 http://www.troytec.com
PMP

QUESTION: 13
You are in process of numerically analyzing the effects of identified risks. Which of the following
are NOT tools/ techniques you can use in the process?

A. Sensitivity analysis
B. Reserve analysis
C. Expected monetary value analysis
D. Modeling and simulation
E. Decision tree analysis

Answer: B

QUESTION: 14
Which of the following describes tool/ technique where expenditure of funds is reconciled with
the funding limits imposed by the performing organization?

A. Forecasting
B. Cost reconciliation
C. Funding limit reconciliation
D. Reserve reconciliation
E. Cost aggregation

Answer: C

QUESTION: 15
Which of the following situations will cause schedule activity duration estimates to directly
influence the cost estimates EXCEPT:

A. When resource cost rate information is unavailable from commercial databases


B. When resources are applied per unit of time of duration of schedule activity
C. When union labor with regularly expiring collective bargaining agreements are involve
D. When seasonal cost variations are involve
E. When project budget includes interest rate changes

Answer: A

http://www.testkiller.com
6 http://www.troytec.com
PMP

QUESTION: 16
Which of the following statements are FALSE regarding cost- reimbursable contracts?

A. cost-reimbursable contracts generally carry the highest risks to the buyer, as the total costs are
uncertain
B. cost-reimbursable contracts often includes incentives for meeting or exceeding project
objectives
C. cost-reimbursable contracts resemble fix unit agreements when the unit rates are preset by the
buyer and seller
D. cost-reimbursable contracts are contracts that involves payments to the seller for actual costs,
plus a fee representing the sellers profit

Answer: C

QUESTION: 17
You have been hired as a project manager for a small local bank. The bank wants you to design
and develop custom online bill pay software so that its customers can pay their bills online. You
are ready to begin the activity definition of your project. You have identifies the scope statement,
the WBS, and talked with the SME’s. In addition, for security reason, you have been informed
that project team members must NOT have criminal history with the FICO score of 700 or above.
In addition you’ve requested that the bank purchase the necessary transaction processing software,
although the software is not yet available. What else do you need before you begin activity
definition?

A. Identify the historical information on previous projects


B. Identify the activity attributes
C. Identify the constraints and assumptions of the project
D. Identify the activities lists
E. Identify the milestone list

Answer: A

QUESTION: 18
You are the project manager at a software company developing the next-gen OODBMS (Object
Oriented Data Base Management System). As software development can be very chaotic, your
company has elected to follow a more rigorous approach to software development. Specifically
your company has chosen to adopt the extreme programming XP methodology for your current
software project. The XP methodology is highly iterative, and produces numerous deliverables
include UML diagrams, architecture diagrams, prototypes and test-cases. Assume you are in the

http://www.testkiller.com
7 http://www.troytec.com
PMP

Activity Sequencing phase of the project. Which of the following sequencing methods should you
use to identify the logical relationships between tasks, so that the activities can be sequenced
correctly?

A. ADM
B. PDM
C. GERT
D. AOA

Answer: C

QUESTION: 19
All of the statements regarding control accounts and planning packages are true EXCEPT:

A. Control accounts and planning packages are tools / techniques of Schedule Development
process.
B. A control account is an assigned WBS level used to monitor cost and schedule performance of
significant element of work.
C. Planning packages reflect a future segment of work within a control account that has not yet
been decomposed into detailed work packages.
D. As work becomes more clearly defined, planning packages are converted into work packages.

Answer: A

QUESTION: 20
Reverse analysis is a tool/ technique in all of the following processes EXCEPT:

A. Risk monitoring and control


B. Activity resource estimation
C. Cost estimation
D. Cost budgeting

Answer: B