11KV CABLE (SEQUENCE OF ACTIVITY) UNDER DEWA DAM

28-Jul-19
S. NO. DESCRIPTION REQUIREMENTS REMARKS

11KV CABLE - STRUCTURE INSPECTION

1 SCHEDULE FOR CABLE WORKS


APPROVAL FOR 11KV CABLE INSTALLATION ENGINEER AND TESTING
2 MOS FOR DRUM TEST, CABLE LAYING & TERMINATION WORKS ENGINEER

3 STRUCTURE INSPECTION FOR INCOMER, CAP. BANK AND OUTGOING FEEDER CABLES

11KV CABLE - LAYING WORKS

4 CLEARANCE CHECKLIST FOR CABLE LAYING REFER DAM STANDARD DOCUMENT

5 RE-INSPECTION OF STRUCTURE ON AFTER DEWA COMMENTS ARE COMPLIED


IR TEST KIT - 5KV AND HVDC TEST KIT - 10KV (SKILLED TECHNICIAN FOR
6 DRUM TEST AND CABLE LAYING PREPARATION OF CABLE)

7 GLAND PLATE HOLE MARKING & CUTTING FOR SWGR & IDT END AVAILABILITY OF JOINTER FOR MARKING

8 CHECKING OF TERMINATION LUG HOLE SIZE MATCH WITH BUS BAR HOLE SIZE 1NO OF LUG SAMPLE FROM SUPPLIER

9 CHECKING OF TERMINATION LUG SANDWICHED IN DAMPING REACTOR TERMINAL 1NO OF LUG SAMPLE FROM SUPPLIER

10 CHECKING OF TERMINATION LUG SANDWICHED IN SWGR AND IDT BUS BAR 1NO OF LUG SAMPLE FROM SUPPLIER

11 CHECKING OF BOLT SIZE AND LENGTH AS PER REQUIREMENT

12 ORDERING OF SS LABEL FOR CABLE REFER DAM STANDARD DOCUMENT

13 PROPOSAL FOR JOINTER APPROVAL CONFIRM THE SUB-CONTRACTOR FOR PROJECT WISE APPROVAL

14 MOS FOR 11KV CABLE HV TEST

15 CABLE CLAMPING WORKS ENGAGE 2SET OF TEAM

16 PROTECTION OF ENTIRE CABLE WITH RUBBER SHEET AVAILABILITY OF MATERIAL AT SITE

11KV CABLE - TERMINATION WORKS

17 CLEARANCE CHECKLIST FOR CABLE TERMINATION WORKS REFER DAM STANDARD DOCUMENT

18 ENSURING OF INTERNAL SHEATH TEST FOR CABLES IR TEST KIT - 5KV AND HVDC TEST KIT - 10KV AS PER DAM

19 CABLE TERMINATION JOINTER APPROVAL COPY (MINIMUM 2)


DURING TERMINATION CABLE GLAND ISSUE FOR BRAND OF A1 ELECTRICAL (ITS NOT PERFECT) AND REQUIRED OF ADDITIONAL QUANTITY FOR COMPENSATING FAULTY
20 BRAND OF BRACO (ITS PERFECT) GLANDS

21 ORDERING OF PVC LABEL FOR CABLE REFER DAM STANDARD DOCUMENT


AS PER APPROVED BASEMENT DRAWING (ID-198 & 280) IN
22 DELIVERY OF WALK WAY BRIDGE FOR BASEMENT COORDINATION WITH CIVIL TEAM
23 CABLE CLAMPING ON AFTER TERMINATION

24 INSTALLATION OF MACHANICAL SEALANT AT IDT END AVAILABILITY OF MATERIAL AT SITE

25 STARTING OF FIRE RETARDANT PAINT AND FIRE SEALANT WORKS MATERIAL AND APPLICATOR AVAILABILITY AT SITE

26 INSTALLATION OF LABEL AND RYB PAINTING AS PER DAM DOCUMENTS

27 REQUEST OF PRE-CHECK INSPECTION FOR TESTING ACTIVITY

11KV CABLE - TESTING ACTIVITY

28 CLEARANCE CHECKLIST FOR TESTING ACTIVITY OF CABLE REFER DAM STANDARD DOCUMENT
5KV IR TEST KIT, HVDC TEST KIT (DIGITAL-25.4KV), MULTIMETER, THERMO
29 CABLE HV TEST METER, SHROUD AND TEST CLIP
TORQUE CHART FOR SWGR AND REACTOR; TORQUE WRENCH WITH
30 INSPECTION OF TORQUE TIGHTNESS FOR SWGR AND CAP. BANK SIDE WITH DAM CALIBRATION CERTIFICATE
TORQUE CHART FOR IDT AND ET; TORQUE WRENCH WITH CALIBRATION
31 INSPECTION OF TORQUE TIGHTNESS FOR IDT AND ET END (LV/HV) WITH TCD CERTIFICATE

32 REQUEST OF SNAG BANK VERIFICATION FOR CABLE READINESS AND ROOM CLEARANCE

33 REQUEST OF RED MARK UP DRWG AND ASBUILT DRWG VERIFICATION FOR CABLE COMPLETION OF CABLE INSTALLATION WORKS

34 REQUEST OF O&M MANUAL AND MMS DATA VERIFICATION FOR CABLE ALL THE ABOVE TO COMPLETE