In reference to SLA agreement between TP-DP and other coordinated meetings, 11kv cables commissioning handed
over w.e.f Jan. 2018 to D.A.M-C&L for all 132/11kv primary substations under commissioning.
Based on lessons learnt in 2018 and for continuous improvement, D.A.M have created checklist clearance
templates for each work stage, such as (Cable Laying, cable termination and cable testing).
The contractor will not be eligible to start a new wok stage unless fulfilled the corresponding checklist clearance
requirement.
We appreciate your usual support by circulating attached checklists to all contractors of primary 132/11KV SS for
their compliance.
Hassan Al Hammadi
Actg.VP-Dist Asset Management
PR# 15875 (Signed on 30-01-2019 11:46:02)
CC: VP-(TP-projects)
Encl: 3 CHECKLISTS
Internal
DP DIVISION – DISTRIBUTION ASSET MANAGEMENT DEPARTMENT
CLEARENCE FOR 11kv CABLE LAYING – PRIMARY 132/11 KV SS
DP-DAM/C&L/QC/SLA-2018/01-Rev1
DP DIVISION – DISTRIBUTION ASSET MANAGEMENT DEPARTMENT
CLEARENCE FOR 11kv CABLE TERMINATIONS - PRIMARY 132/11 KV SS
All cables laid, clamped & cleating work done as per Yes No
approved drawings & DAM comments have complied.
SRC available for cable termination kits. Yes No
Lug hole Size and Busbar hole size are matched. Yes No
Lug hole size and capacitor bank’ L’connector hole size Yes No
are matched.
DP-DAM/C&L/QC/SLA-2018/02-Rev1
DP DIVISION – DISTRIBUTION ASSET MANAGEMENT DEPARTMENT
CLEARENCE FOR 11kv CABLE TESTING- PRIMARY 132/11 KV SS
DP-DAM/C&L/QC/SLA-2018/03-Rev1