Engineering, Procurement, Construction and

Installation of Wellhead Platform(S1), Submarine


Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 2 of 15

TABULATION OF REVISED PAGES


REVISIONS REVISIONS
SHEET
C0 C1 C2 C3 C0 C1 C2 C3
1 X 36
2 X 37
3 X 38
4 X 39
5 X X 40
6 X 41
7 X 42
8 X 43
9 X 44
10 X 45
11 X 46
12 X 47
13 X X 48
14 X 49
15 X 50
16 51
17 52
18 53
19 54
20 55
21 56
22 57
23 58
24 59
25 60
26 61
27 62
28 63
29 64
30 65
31 66
32 67
33 68
34 69
35 70
Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 3 of 15

TABLE OF CONTENTS

1 INTRODUCTION ............................................................................................................ 4
2 DEFINITIONS ................................................................................................................ 4
3 Abbreviations ................................................................................................................... 5
4 REFERENCES............................................................................................................... 5
5 SCOPE OF WORK ........................................................................................................ 6
6 Responsibilities and authorities ................................................................................. 6
7 Procedure ..................................................................................................................... 6
8 WELDING POSITIONS .................................................................................................. 7
9 TEST COUPON PREPARATION ................................................................................ 10
10 QUALIFICATION OF WELDERS AND WELDING OPERATORS .............................. 10

APPENDICES

APPENDIX 1 VISUAL TEST REPORT

APPENDIX 2 WELDERS MONTHLY PERFORMANCE FORM

APPENDIX 3 WELDER CERTIFICATE FORM

APPENDIX 4 WELDER DART


Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 4 of 15

1 INTRODUCTION
This project involves work in two locations; new facilities in satellite wellhead platform, S1, over the
Salman reservoir and additions to the existing Salman Complex. The modifications to Salman Complex
facilities are intended to increase the predictability of the oil wells by increasing gas lift capabilities in S1
facilities.

Salman Oil and Gas Field is an active oil producing complex in the Persian Gulf, in Iranian waters some
144 km south of Lavan Island. This field straddles the Iran – Abu Dhabi border with approximately two-
thirds of the producing structure lying in Iranian waters.

The existing offshore facilities at the Salman oil and gas field have been producing since 1968. The
extracted crude oil is processed and exported via a subsea pipeline to onshore facilities at Lavan Island.

The project scope includes:


 A new offshore platform and facilities,S1
 Production and test lines from S1 satellite platform to existing Salman Complex
 Gas lift line from existing Salman Complex to new S1 satellite platform
 Subsea cabling between existing Salman Complex and S1 satellite platform
 Tie-ins to existing offshore facilities
 Modification of existing platform

Item No. Description Location Depth


N: 2827565.5
1 Wellhead platform - S1 23 m
E: 715569.7
N: 2826165
2 Salman Complex - FP Platform
E: 716185
N: 2826323
3 Salman Complex - PP3 Platform
E: 716272

2 DEFINITIONS
PROJECT NAME Transportation, Engineering, Procurement,
Installation of S1 Topside for Salman Field
CLIENT Iranian Off-shore Oil Company (IOOC)
EPCIC CONTRACTOR Asfalt Tous Company (ATC)
INSTALLATION SUB-CONTRACTOR Sanaye Daryafan Qeshm (SADAF)
Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 5 of 15

INSTALLATION ENGINEERING SUB-CONTRACTOR Farazan Saze Darya (FARDA)


 TPA: Iranian Classification Society(I.C.S)
 MWS: Iranian Classification Society(I.C.S)
 SITE: Salman Oil Filed

3 ABBREVIATIONS
INSPECTION AND TEST PLAN
ITP:
Quality control
QC:
Visual Test
VT:
MAGNETIC TEST
MT:
ULTRASONIC TEST
UT:
PENETRATION TEST
PT:
NON DESTRUCTIVE TEST
NDT:

4 REFERENCES

The documents that are referred in this procedure are (but not limited to) as below

Standard: AWS D1.1


API RP2X
API RP2A
ASME SEC XI

Approved WPS, PQR and WPQ’s


Specification for fabrication of offshore structures (SL-EST-SP-WPS1-3104-D1)
Topside_Standard_Welding_Details (SL-EST-DR-WPS1-2030-B2-S1)
Material specification (SL-EST-DB-WPS1-2003-B3)
Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 6 of 15

5 SCOPE OF WORK
This procedure covers qualification requirements applicable to welder performance for structure installation
& sea fastening of S1 topside for SALMAN field

6 RESPONSIBILITIES AND AUTHORITIES


The responsibilities will be explained as follows:

6.2 QA\QC Manager is responsible for the preparation of the WQT report, qualification of welder and
welding operators in accordance with this procedure and standard.

6.3 Welding school supervisor and QC inspector are responsible for witnessing of welder qualification
test.

6.4 QC Engineer and QA\QC Manager are responsible for the review and approval of the documentation
required for qualifying welders and welding operators.

6.5 Inform QC inspector when fit-up and weld of test piece is completed.

6.6 Inform QC inspector when weld and NDT is finished.

7 PROCEDURE

7.1 Properly documented evidence of previous qualification of previous performance qualification of


welder to be accepted for working when submitted to company and get their approval.

7.2 The welder qualification test shall be performed in accordance with qualified WPS.

7.3 Re-qualification of welder is required when changes are made with respect to any of essential
variables and supplementary variables (if applicable) as per referenced codes and Company
specifications or the properly documented evidence of previous qualification of welding procedure
and poor performance.

7.4 Welding and welder qualification test shall be witnessed and approved by contractor, TPA and
Company representative (As per approved ITP).

7.5 All welders shall be qualified with approved WPS.

7.6 Welder qualification for TKY joints will be qualified in 6GR position.

7.7 The installation sub-contractor can use a pre-qualified welder or welding operator if they meet the
standard and WPS.
Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 7 of 15

8 WELDING POSITIONS
Because various welding position will be encountered in actual construction, each procedure qualification
shall be tested in the manner stated for each position for which it is to be qualified. Therefore, when WPQT
and Welder Test are performed, understanding of various welding position shall be very important. Welding
position for each type of weld shall be represented by the following figures and as per AWS D1.1 standards
and Company specification requirements.

8.1 Fillet and Groove weld


Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 8 of 15

Figure 1. Positions of test plate for fillet welds

Figure 2. Positions of test plate for groove welds


Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 9 of 15

Figure 3. Positions of test pipe or tubing for groove welds


Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 10 of 15

9 TEST COUPON PREPARATION


Test coupon for testing shall be prepared as per the AWS D1.1 for structure.

10 QUALIFICATION OF WELDERS AND WELDING OPERATORS

10.1 Qualification of new welders for construction should be in accordance with flow chart for new welder
qualification flow chart.

10.1.1 Welders, welding operators and tack welders shall be qualified in accordance with AWS D1-1
for structure & Project fabrication specification.

10.1.2 If the test does not meet the requirement, the welder shall carry out a new test of same type as
the one retested in accordance with the reference code.

10.1.3 A welder is qualified when a complete WPS is carried out by the welder (all passes)

10.1.4 The certificate according to AWS D1-1 shall be prepared for each welder who passes the test
successfully. For starting the test welder I.D shall be available.

10.1.5 Re-Qualification is required whenever a welder has not used for any related welding process
for a period of more than 3 months.

10.1.6 A retest may be made, provided there is evidence that the welder or welding operator in need
of further training or practice and paragraph 10.1.8 this document.

10.1.7 QA keeps records of periods and type of work for each certified welder and welding operator.
Welder’s ID card shall be issued by the contractor for company approval.

10.1.8 High repair rate within % (2-3) the welder shall be notified and retested for more than 5% the
welder shall be disqualified and taken off from the project.
10.1.9 Repair rate shall be reported officially to company representative weekly and or any time in his
consider necessity.

Formulas of repair rate follow up to:


Σ total length of weld rejected by RTorUT
Repair rate =100 *
Total length of weld inspected by RTorUT
or UT
13.1.9 List of welders who are welding on project, should be issued and after each
Time to be updated.

10.2 WELDING OPERATOR


Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 11 of 15

Welding operator using fully merchandised or fully automatic process need to pass a qualification
TEST

10.3 TEST COUPON

The dimensions of test coupon shall provide sufficient materials for test in accordance with the
reference documents. All test coupons shall be paint marked /hard line with the assigned welder I.D
number on the test coupon before welding.

Type and Position for welder qualification shall conform to the requirement of AWS D1-1 for structure.

10.4 TEST TO BE APPLIED

Each test piece shall be inspected as below:

• 100% VISUAL INSPECTION,


• 100% RT or UT

10.5 ACCEPTANCE CRITERIA FOR TEST

Structural test coupon shall conform to requirement of AWS D1-1 and project specification.

10.6 TEST METHODE


10.6.1 Each welder introduced for test must be trained and pass a preliminary test successfully.

10.6.2 The candidate will be introduced to QA for arrange the test. Training may be given by training
center &Production / welding department.

10.6.3 The test coupon should be prepared in accordance with WPS and AWS D1-1. For structure.

10.6.4 QC Engineer shall prepare the notice and records as per shown in flow chart.

10.6.5 After welding and necessary testing, the record shall be prepared and submitted to
Company for approval.

10.6.6 QA documentation shall keep the records and certificates and renewal documents and their
registration.
10.6.7 Qualified welders shall receive ID card and they shall keep it by themselves during welding.
Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 12 of 15

10.6.8 In accordance with WPS, welding engineer shall determine the necessary procedure
qualification tests
APPENDIX 1: VISUAL INSPECTION REPORT
Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 13 of 15

APPENDIX 2: WELDER QUALIFICATION TEST RECORD

TRANSPORTATION , ENGINEERING, PROCUREMENT,


INSTALLATION OF S1 TOPSIDE FOR SALMAN FIELD

REPORT Number:
WELDERS MONTHLY PERFORMANCE FORM DATE:
TYPE OF REPAIR
TOTAL WELDED

REPAIR (mm)

PERCENT (%)
WELDER ID

LENGTH OF

REPAIR
LENGTH

Other defect
(mm)

LOF

LOP

UC
PO

GP

RC
CP

CR

OL
EP

BT

SA
SI

Type of Imperfection:
SI: Slag Inclusion PO: Porosity GP: Gas Pore OL: Over Lapping
LOF: Lack of Fusion CR: Crack or Linear Type RC: Root Concavity
LOP: Lack of Penetration EP: Excess Penetration BT: Burn-through
CP: Crater pipe UC: Undercut SA: Stray Arc

Company
Contractor (SADAF) TPA
Inspection Rep IOOC Rep
Name Name: Name: Name:

Date: Date: Date: Date:

Sign Sign Sign Sign


Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 14 of 15

APPENDIX 3: WELDER & WELDING OPERATOR CERTIFICATE FORM


Engineering, Procurement, Construction and
Installation of Wellhead Platform(S1), Submarine
Cables and Pipelines Between S1 and Salman
Complex
S1-TOPSIDE WELDER QUALIFICATION PROCEDURE

AREA DISCIPL. DOC. SCOPE SEQ. REV.

Project Code: 4545 SL ELT PR WPS1 4107 C2 Page 15 of 15

APPENDIX 4: WELDER ID CARD