( BENTANG - 20 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.45 = 0.290 8.50 2.00 4.930
2 0.20 * 0.85 = 0.170 8.50 2.00 2.890
0.60 A 0.60
1 1.15 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
0.85 2 139.937
8 0.30 5 5.50 * 0.60 = 3.300 8.50 2.00 56.100
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
7.15 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
5.50 8.95
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO II
( BENTANG - 20 M )
0.00 0.56
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.30
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO II
( BENTANG - 20 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO II
( BENTANG - 20 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO II
( BENTANG - 20 M )
TOTAL : 52,442.63
POLOS : 6,592.42
ULIR : 45,850.21
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUM I
( BENTANG - 20 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.45 = 0.290 8.50 2.00 4.930
2 0.20 * 0.85 = 0.170 8.50 2.00 2.890
0.60 A 0.60
1 1.15 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
0.85 2 129.737
8 0.30 5 4.50 * 0.60 = 2.700 8.50 2.00 45.900
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
6.15 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
4.50 7.95
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUM I
( BENTANG - 20 M )
0.00 0.56
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.30
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUM I
( BENTANG - 20 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUM I
( BENTANG - 20 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUM I
( BENTANG - 20 M )
TOTAL : 50,392.76
POLOS : 6,380.79
ULIR : 44,011.96
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.20 = 0.240 8.50 2.00 4.080
2 0.20 * 0.60 = 0.120 8.50 2.00 2.040
0.60 A 0.60
1 0.90 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
0.60 2 128.037
8 0.30 5 4.50 * 0.60 = 2.700 8.50 2.00 45.900
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
5.90 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
4.50 7.70
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
0.00 0.50
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.30
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
TOTAL : 45,364.33
POLOS : 5,662.06
ULIR : 39,702.27
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.30 = 0.260 8.50 2.00 4.420
2 0.20 * 0.70 = 0.140 8.50 2.00 2.380
0.60 A 0.60
1 1.00 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
0.70 2 128.717
8 0.30 5 4.50 * 0.60 = 2.700 8.50 2.00 45.900
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
6.00 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
4.50 7.80
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
0.00 0.50
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.30
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TIFEN
( BENTANG - 18 M )
TOTAL : 45,959.68
POLOS : 5,759.88
ULIR : 40,199.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 15 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.10 = 0.220 8.50 2.00 3.740
2 0.20 * 0.50 = 0.100 8.50 2.00 1.700
0.60 A 0.60
1 0.80 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
0.50 2 122.257
8 0.30 5 4.00 * 0.60 = 2.400 8.50 2.00 40.800
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
5.30 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
4.00 7.10
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 15 M )
0.00 0.45
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.25
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 15 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 15 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 15 M )
TOTAL : 42,026.92
POLOS : 5,063.69
ULIR : 36,963.23
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IBOH II
( BENTANG - 15 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 0.95 = 0.190 8.50 2.00 3.230
2 0.20 * 0.35 = 0.070 8.50 2.00 1.190
0.60 A 0.60
1 0.65 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
0.35 2 136.537
8 0.30 5 5.50 * 0.60 = 3.300 8.50 2.00 56.100
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
6.65 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
5.50 8.45
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IBOH II
( BENTANG - 15 M )
0.00 0.45
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.25
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IBOH II
( BENTANG - 15 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IBOH II
( BENTANG - 15 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IBOH II
( BENTANG - 15 M )
TOTAL : 43,087.43
POLOS : 4,860.56
ULIR : 38,226.88
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUN II
( BENTANG - 12 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 0.95 = 0.190 8.50 2.00 3.230
2 0.20 * 0.35 = 0.070 8.50 2.00 1.190
0.60 A 0.60
1 0.65 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
0.35 2 131.437
8 0.30 5 5.00 * 0.60 = 3.000 8.50 2.00 51.000
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
6.15 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
5.00 7.95
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUN II
( BENTANG - 12 M )
0.00 0.45
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.25
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUN II
( BENTANG - 12 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUN II
( BENTANG - 12 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN IMSUN II
( BENTANG - 12 M )
TOTAL : 42,062.50
POLOS : 4,754.74
ULIR : 37,307.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 10 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 0.95 = 0.190 8.50 2.00 3.230
2 0.20 * 0.35 = 0.070 8.50 2.00 1.190
0.60 A 0.60
1 0.65 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
0.35 2 121.237
8 0.30 5 4.00 * 0.60 = 2.400 8.50 2.00 40.800
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
5.15 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
4.00 6.95
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 10 M )
0.40 0.00
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.25
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 10 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 10 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN YARIO
( BENTANG - 10 M )
TOTAL : 37,922.92
POLOS : 4,104.65
ULIR : 33,818.27
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN FIANE
( BENTANG - 8 M )
0.40 0.00
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN FIANE
( BENTANG - 8 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN FIANE
( BENTANG - 8 M )
2 3 0.00
0.00
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN FIANE
( BENTANG - 8 M )
SUB TOTAL : -
Ø UKURAN (cm) PANJANG / JUMLAH / PANJANG BERAT / m JUMLAH BERAT TOTAL
TULANGAN TYPE VOLUME BETON (m )
a b c d Kait BUAH (m) BALOK TOTAL (m) (kg / m) BALOK (kg)
(mm)
10 A4 54 10 0.64 511 327.04 0.617 0 0.00
25 B1 594 50 15 6.59 142 935.78 3.853 0 0.00
TIANG ABUT 25 B1' 594 50 15 6.59 24 160.36 3.853 0 0.00
16 B2 694 54 10 7.58 42 318.36 1.578 0 0.00
SUB TOTAL : -
10 A2 85 10 0.95 84 79.80 0.617 2 98.40
10 A2' 94 10 1.04 231 240.24 0.617 2 296.23
10 A1 294 10 3.04 42 127.68 0.617 2 157.44
25 A3 100 25 15 1.65 21 34.65 3.853 2 267.04
16 B1 844 85 10 9.39 12 112.68 1.578 2 355.69
POER ABUT
16 B2 844 94 10 9.48 20 189.60 1.578 2 598.51
16 B3 844 294 10 11.48 4 45.92 1.578 2 144.95
25 C1 294 67 15 4.43 58 255.46 3.853 2 1968.78
25 D 194 57 15 3.23 58 186.26 3.853 2 1435.48
SUB TOTAL : 5,322.53
12 A1 244 10 2.54 3 7.62 0.888 0 0.00
19 A2 244 11.4 2.554 3 7.66 2.226 0 0.00
12 A3 710 10 7.2 14 97.20 0.888 0 0.00
12 B 710 44 24 45 10 8.33 14 112.46 0.888 0 0.00
SAYAP ABUT
16 A4 290 10 3.00 82 246.00 1.578 0 0.00
16 C 44 55 10 1.64 9 14.76 1.578 0 0.00
19 D 245 105 550 11.4 9.114 3 27.34 2.226 0 0.00
SUB TOTAL : -
12 A 694 10 7.04 22 154.88 0.888 2 275.01
12 C 161 14 34 80 10 2.99 36 107.64 0.888 2 191.13
BANTALAN
12 B 14 165 10 3.54 36 127.44 0.888 2 226.29
SUB TOTAL : 692.42
16 A 15 285 10 3.1 31 96.1 1.578 0 0.00
16 B 15 285 27 10 3.37 24 80.88 1.578 0 0.00
12 C 50 10 0.6 12 7.2 0.888 0 0.00
SUMURAN
12 C 151 10 1.605714286 12 19.26857143 0.888 0 0.00
16 D 15 45 9.6 0.846 8 6.768 1.578 0 0.00
SUB TOTAL : 0.00
TOTAL : 12,037.12
POLOS : 2,575.11
ULIR : 9,462.01
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TUBUN I
( BENTANG - 8 M )
0.40 0.00
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TUBUN I
( BENTANG - 8 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TUBUN I
( BENTANG - 8 M )
2 3 0.00
0.00
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TUBUN I
( BENTANG - 8 M )
SUB TOTAL : -
Ø UKURAN (cm) PANJANG / JUMLAH / PANJANG BERAT / m JUMLAH BERAT TOTAL
TULANGAN TYPE VOLUME BETON (m )
a b c d Kait BUAH (m) BALOK TOTAL (m) (kg / m) BALOK (kg)
(mm)
10 A4 54 10 0.64 511 327.04 0.617 0 0.00
25 B1 594 50 15 6.59 142 935.78 3.853 0 0.00
TIANG ABUT 25 B1' 594 50 15 6.59 24 160.36 3.853 0 0.00
16 B2 694 54 10 7.58 42 318.36 1.578 0 0.00
SUB TOTAL : -
10 A2 85 10 0.95 84 79.80 0.617 2 98.40
10 A2' 94 10 1.04 231 240.24 0.617 2 296.23
10 A1 294 10 3.04 42 127.68 0.617 2 157.44
25 A3 100 25 15 1.65 21 34.65 3.853 2 267.04
16 B1 844 85 10 9.39 12 112.68 1.578 2 355.69
POER ABUT
16 B2 844 94 10 9.48 20 189.60 1.578 2 598.51
16 B3 844 294 10 11.48 4 45.92 1.578 2 144.95
25 C1 294 67 15 4.43 58 255.46 3.853 2 1968.78
25 D 194 57 15 3.23 58 186.26 3.853 2 1435.48
SUB TOTAL : 5,322.53
12 A1 244 10 2.54 3 7.62 0.888 0 0.00
19 A2 244 11.4 2.554 3 7.66 2.226 0 0.00
12 A3 710 10 7.2 14 97.20 0.888 0 0.00
12 B 710 44 24 45 10 8.33 14 112.46 0.888 0 0.00
SAYAP ABUT
16 A4 290 10 3.00 82 246.00 1.578 0 0.00
16 C 44 55 10 1.64 9 14.76 1.578 0 0.00
19 D 245 105 550 11.4 9.114 3 27.34 2.226 0 0.00
SUB TOTAL : -
12 A 694 10 7.04 22 154.88 0.888 2 275.01
12 C 161 14 34 80 10 2.99 36 107.64 0.888 2 191.13
BANTALAN
12 B 14 165 10 3.54 36 127.44 0.888 2 226.29
SUB TOTAL : 692.42
16 A 15 285 10 3.1 31 96.1 1.578 0 0.00
16 B 15 285 27 10 3.37 24 80.88 1.578 0 0.00
12 C 50 10 0.6 12 7.2 0.888 0 0.00
SUMURAN
12 C 151 10 1.605714286 12 19.26857143 0.888 0 0.00
16 D 15 45 9.6 0.846 8 6.768 1.578 0 0.00
SUB TOTAL : 0.00
TOTAL : 12,037.12
POLOS : 2,575.11
ULIR : 9,462.01
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO I
( BENTANG - 8 M )
0.40 0.00
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO I
( BENTANG - 8 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO I
( BENTANG - 8 M )
2 3 0.00
0.00
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO I
( BENTANG - 8 M )
SUB TOTAL : -
Ø UKURAN (cm) PANJANG / JUMLAH / PANJANG BERAT / m JUMLAH BERAT TOTAL
TULANGAN TYPE VOLUME BETON (m )
a b c d Kait BUAH (m) BALOK TOTAL (m) (kg / m) BALOK (kg)
(mm)
10 A4 54 10 0.64 511 327.04 0.617 0 0.00
25 B1 594 50 15 6.59 142 935.78 3.853 0 0.00
TIANG ABUT 25 B1' 594 50 15 6.59 24 160.36 3.853 0 0.00
16 B2 694 54 10 7.58 42 318.36 1.578 0 0.00
SUB TOTAL : -
10 A2 85 10 0.95 84 79.80 0.617 2 98.40
10 A2' 94 10 1.04 231 240.24 0.617 2 296.23
10 A1 294 10 3.04 42 127.68 0.617 2 157.44
25 A3 100 25 15 1.65 21 34.65 3.853 2 267.04
16 B1 844 85 10 9.39 12 112.68 1.578 2 355.69
POER ABUT
16 B2 844 94 10 9.48 20 189.60 1.578 2 598.51
16 B3 844 294 10 11.48 4 45.92 1.578 2 144.95
25 C1 294 67 15 4.43 58 255.46 3.853 2 1968.78
25 D 194 57 15 3.23 58 186.26 3.853 2 1435.48
SUB TOTAL : 5,322.53
12 A1 244 10 2.54 3 7.62 0.888 0 0.00
19 A2 244 11.4 2.554 3 7.66 2.226 0 0.00
12 A3 710 10 7.2 14 97.20 0.888 0 0.00
12 B 710 44 24 45 10 8.33 14 112.46 0.888 0 0.00
SAYAP ABUT
16 A4 290 10 3.00 82 246.00 1.578 0 0.00
16 C 44 55 10 1.64 9 14.76 1.578 0 0.00
19 D 245 105 550 11.4 9.114 3 27.34 2.226 0 0.00
SUB TOTAL : -
12 A 694 10 7.04 22 154.88 0.888 2 275.01
12 C 161 14 34 80 10 2.99 36 107.64 0.888 2 191.13
BANTALAN
12 B 14 165 10 3.54 36 127.44 0.888 2 226.29
SUB TOTAL : 692.42
16 A 15 285 10 3.1 31 96.1 1.578 0 0.00
16 B 15 285 27 10 3.37 24 80.88 1.578 0 0.00
12 C 50 10 0.6 12 7.2 0.888 0 0.00
SUMURAN
12 C 151 10 1.605714286 12 19.26857143 0.888 0 0.00
16 D 15 45 9.6 0.846 8 6.768 1.578 0 0.00
SUB TOTAL : 0.00
TOTAL : 12,037.12
POLOS : 2,575.11
ULIR : 9,462.01
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN KROMSA
( BENTANG - 6 M )
0.30 0.00
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN KROMSA
( BENTANG - 6 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN KROMSA
( BENTANG - 6 M )
2 3 0.00
0.00
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN KROMSA
( BENTANG - 6 M )
SUB TOTAL : -
Ø UKURAN (cm) PANJANG / JUMLAH / PANJANG BERAT / m JUMLAH BERAT TOTAL
TULANGAN TYPE VOLUME BETON (m )
a b c d Kait BUAH (m) BALOK TOTAL (m) (kg / m) BALOK (kg)
(mm)
10 A4 54 10 0.64 511 327.04 0.617 0 0.00
25 B1 594 50 15 6.59 142 935.78 3.853 0 0.00
TIANG ABUT 25 B1' 594 50 15 6.59 24 160.36 3.853 0 0.00
16 B2 694 54 10 7.58 42 318.36 1.578 0 0.00
SUB TOTAL : -
10 A2 85 10 0.95 84 79.80 0.617 2 98.40
10 A2' 94 10 1.04 231 240.24 0.617 2 296.23
10 A1 294 10 3.04 42 127.68 0.617 2 157.44
25 A3 100 25 15 1.65 21 34.65 3.853 2 267.04
16 B1 844 85 10 9.39 12 112.68 1.578 2 355.69
POER ABUT
16 B2 844 94 10 9.48 20 189.60 1.578 2 598.51
16 B3 844 294 10 11.48 4 45.92 1.578 2 144.95
25 C1 294 67 15 4.43 58 255.46 3.853 2 1968.78
25 D 194 57 15 3.23 58 186.26 3.853 2 1435.48
SUB TOTAL : 5,322.53
12 A1 244 10 2.54 3 7.62 0.888 0 0.00
19 A2 244 11.4 2.554 3 7.66 2.226 0 0.00
12 A3 710 10 7.2 14 97.20 0.888 0 0.00
12 B 710 44 24 45 10 8.33 14 112.46 0.888 0 0.00
SAYAP ABUT
16 A4 290 10 3.00 82 246.00 1.578 0 0.00
16 C 44 55 10 1.64 9 14.76 1.578 0 0.00
19 D 245 105 550 11.4 9.114 3 27.34 2.226 0 0.00
SUB TOTAL : -
12 A 694 10 7.04 22 154.88 0.888 2 275.01
12 C 161 14 34 80 10 2.99 36 107.64 0.888 2 191.13
BANTALAN
12 B 14 165 10 3.54 36 127.44 0.888 2 226.29
SUB TOTAL : 692.42
16 A 15 285 10 3.1 31 96.1 1.578 0 0.00
16 B 15 285 27 10 3.37 24 80.88 1.578 0 0.00
12 C 50 10 0.6 12 7.2 0.888 0 0.00
SUMURAN
12 C 151 10 1.605714286 12 19.26857143 0.888 0 0.00
16 D 15 45 9.6 0.846 8 6.768 1.578 0 0.00
SUB TOTAL : 0.00
TOTAL : 10,664.56
POLOS : 2,322.46
ULIR : 8,342.10
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TUBUN II
( BENTANG - 6 M )
0.30 0.00
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TUBUN II
( BENTANG - 6 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TUBUN II
( BENTANG - 6 M )
2 3 0.00
0.00
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN TUBUN II
( BENTANG - 6 M )
SUB TOTAL : -
Ø UKURAN (cm) PANJANG / JUMLAH / PANJANG BERAT / m JUMLAH BERAT TOTAL
TULANGAN TYPE VOLUME BETON (m )
a b c d Kait BUAH (m) BALOK TOTAL (m) (kg / m) BALOK (kg)
(mm)
10 A4 54 10 0.64 511 327.04 0.617 0 0.00
25 B1 594 50 15 6.59 142 935.78 3.853 0 0.00
TIANG ABUT 25 B1' 594 50 15 6.59 24 160.36 3.853 0 0.00
16 B2 694 54 10 7.58 42 318.36 1.578 0 0.00
SUB TOTAL : -
10 A2 85 10 0.95 84 79.80 0.617 2 98.40
10 A2' 94 10 1.04 231 240.24 0.617 2 296.23
10 A1 294 10 3.04 42 127.68 0.617 2 157.44
25 A3 100 25 15 1.65 21 34.65 3.853 2 267.04
16 B1 844 85 10 9.39 12 112.68 1.578 2 355.69
POER ABUT
16 B2 844 94 10 9.48 20 189.60 1.578 2 598.51
16 B3 844 294 10 11.48 4 45.92 1.578 2 144.95
25 C1 294 67 15 4.43 58 255.46 3.853 2 1968.78
25 D 194 57 15 3.23 58 186.26 3.853 2 1435.48
SUB TOTAL : 5,322.53
12 A1 244 10 2.54 3 7.62 0.888 0 0.00
19 A2 244 11.4 2.554 3 7.66 2.226 0 0.00
12 A3 710 10 7.2 14 97.20 0.888 0 0.00
12 B 710 44 24 45 10 8.33 14 112.46 0.888 0 0.00
SAYAP ABUT
16 A4 290 10 3.00 82 246.00 1.578 0 0.00
16 C 44 55 10 1.64 9 14.76 1.578 0 0.00
19 D 245 105 550 11.4 9.114 3 27.34 2.226 0 0.00
SUB TOTAL : -
12 A 694 10 7.04 22 154.88 0.888 2 275.01
12 C 161 14 34 80 10 2.99 36 107.64 0.888 2 191.13
BANTALAN
12 B 14 165 10 3.54 36 127.44 0.888 2 226.29
SUB TOTAL : 692.42
16 A 15 285 10 3.1 31 96.1 1.578 0 0.00
16 B 15 285 27 10 3.37 24 80.88 1.578 0 0.00
12 C 50 10 0.6 12 7.2 0.888 0 0.00
SUMURAN
12 C 151 10 1.605714286 12 19.26857143 0.888 0 0.00
16 D 15 45 9.6 0.846 8 6.768 1.578 0 0.00
SUB TOTAL : 0.00
TOTAL : 10,664.56
POLOS : 2,322.46
ULIR : 8,342.10
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO III
( BENTANG - 6 M )
0.30 0.00
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO III
( BENTANG - 6 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO III
( BENTANG - 6 M )
2 3 0.00
0.00
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN UMRIO III
( BENTANG - 6 M )
SUB TOTAL : -
Ø UKURAN (cm) PANJANG / JUMLAH / PANJANG BERAT / m JUMLAH BERAT TOTAL
TULANGAN TYPE VOLUME BETON (m )
a b c d Kait BUAH (m) BALOK TOTAL (m) (kg / m) BALOK (kg)
(mm)
10 A4 54 10 0.64 511 327.04 0.617 0 0.00
25 B1 594 50 15 6.59 142 935.78 3.853 0 0.00
TIANG ABUT 25 B1' 594 50 15 6.59 24 160.36 3.853 0 0.00
16 B2 694 54 10 7.58 42 318.36 1.578 0 0.00
SUB TOTAL : -
10 A2 85 10 0.95 84 79.80 0.617 2 98.40
10 A2' 94 10 1.04 231 240.24 0.617 2 296.23
10 A1 294 10 3.04 42 127.68 0.617 2 157.44
25 A3 100 25 15 1.65 21 34.65 3.853 2 267.04
16 B1 844 85 10 9.39 12 112.68 1.578 2 355.69
POER ABUT
16 B2 844 94 10 9.48 20 189.60 1.578 2 598.51
16 B3 844 294 10 11.48 4 45.92 1.578 2 144.95
25 C1 294 67 15 4.43 58 255.46 3.853 2 1968.78
25 D 194 57 15 3.23 58 186.26 3.853 2 1435.48
SUB TOTAL : 5,322.53
12 A1 244 10 2.54 3 7.62 0.888 0 0.00
19 A2 244 11.4 2.554 3 7.66 2.226 0 0.00
12 A3 710 10 7.2 14 97.20 0.888 0 0.00
12 B 710 44 24 45 10 8.33 14 112.46 0.888 0 0.00
SAYAP ABUT
16 A4 290 10 3.00 82 246.00 1.578 0 0.00
16 C 44 55 10 1.64 9 14.76 1.578 0 0.00
19 D 245 105 550 11.4 9.114 3 27.34 2.226 0 0.00
SUB TOTAL : -
12 A 694 10 7.04 22 154.88 0.888 2 275.01
12 C 161 14 34 80 10 2.99 36 107.64 0.888 2 191.13
BANTALAN
12 B 14 165 10 3.54 36 127.44 0.888 2 226.29
SUB TOTAL : 692.42
16 A 15 285 10 3.1 31 96.1 1.578 0 0.00
16 B 15 285 27 10 3.37 24 80.88 1.578 0 0.00
12 C 50 10 0.6 12 7.2 0.888 0 0.00
SUMURAN
12 C 151 10 1.605714286 12 19.26857143 0.888 0 0.00
16 D 15 45 9.6 0.846 8 6.768 1.578 0 0.00
SUB TOTAL : 0.00
TOTAL : 10,664.56
POLOS : 2,322.46
ULIR : 8,342.10
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.65 = 0.330 8.50 2.00 5.610
2 0.20 * 1.05 = 0.210 8.50 2.00 3.570
0.60 A 0.60
1 1.35 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
1.05 2 136.197
8 0.30 5 5.00 * 0.60 = 3.000 8.50 2.00 51.000
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
6.85 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
5.00 8.65
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
0.00 0.65
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.30
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (21 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
TOTAL : 55,208.38
POLOS : 6,835.45
ULIR : 48,372.93
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.70 = 0.340 8.50 2.00 5.780
2 0.20 * 1.10 = 0.220 8.50 2.00 3.740
0.60 A 0.60
1 1.40 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
1.10 2 136.537
8 0.30 5 5.00 * 0.60 = 3.000 8.50 2.00 51.000
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
6.90 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
5.00 8.70
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
0.00 0.70
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.30
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
TOTAL : 56,683.32
POLOS : 7,006.14
ULIR : 49,677.18
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.75 = 0.350 8.50 2.00 5.950
2 0.20 * 1.15 = 0.230 8.50 2.00 3.910
0.60 A 0.60
1 1.45 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
1.15 2 136.877
8 0.30 5 5.00 * 0.60 = 3.000 8.50 2.00 51.000
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
6.95 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
5.00 8.75
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
0.00 0.70
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.30
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
TOTAL : 58,417.99
POLOS : 7,166.55
ULIR : 51,251.44
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
###
###
2.10 0.20 0.20 ~ ABUTMENT (BETON BERTULANG)
1 0.20 * 1.75 = 0.350 8.50 2.00 5.950
2 0.20 * 1.15 = 0.230 8.50 2.00 3.910
0.60 A 0.60
1 1.45 3 0.70 * 1.43 = 1.001 8.50 2.00 17.017
4 { 0.50 * ( 1.43 + 0.60 )} * 0.30 = 0.305 8.50 2.00 5.177
1.15 2 136.877
8 0.30 5 5.00 * 0.60 = 3.000 8.50 2.00 51.000
6 { 0.50 * ( 3.50 + 0.60 )} * 0.30 = 0.615 8.50 2.00 10.455
3 0.70
6.95 7 3.50 * 0.70 = 2.450 8.50 2.00 41.650
4 0.30 8 1.03 * 0.30 = 0.309 1.39 4.00 1.718
B 0.53 0.30 ~ LANTAI KERJA (BETON)
0.60 I 0.10 * 3.50 = 0.350 8.50 2.00 5.950 5.950
5.00 8.75
ABUTMEN - 01+02
0.30
A'
0.20
0.20
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
0.00 0.70
PJG. TOT. BALOK UTAMA = 20.80 M
PJG. B1 TIAP UJUNG BLK = 0.00 M
0.30
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
1.00 1.00
0.05 0.20
0.25
TROTOAR (25 M')
0.76
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
2 3 1.90
2.50
0.16
~ LINING (PASANGAN BATU)
1 1.00 * 3.00 = 3.000 0.50 4.00 6.000 6.000
1.00 1 1 0.55
2
1.00
0.80
PERHITUNGAN VOLUME PEKERJAAN JEMBATAN ISAIT
( BENTANG - 22 M )
TOTAL : 60,299.35
POLOS : 7,212.48
ULIR : 53,086.87