Documente Academic
Documente Profesional
Documente Cultură
A THESIS
SUBMITTED TO THE COLLEGE OF ENGINEERING
OF THE UNIVERSITY OF BAGHDAD IN
PARTIAL FULFILLMENT OF THE
REQUIREMENTS FOR THE
DEGREE OF DOCTOR OF
PHILOSOPHY IN CIVIL
ENGINEERING
1.1 General:
Composite construction consists of using two materials together in one
structural unit and using each material to its best advantage. The number
of combinations is almost endless; steel and concrete, timber and
concrete, timber and steel, precast and cast-in-place concrete, etc.
Composite construction is generally economic when a floor or
bridge deck is desired to be in situ, as opposed to precast, and its total
depth is required to be less than for in situ reinforced concrete
construction, or when durability (absence of cracks at working loads) is
required (e.g. bridge decks).
1
cast-in-place slab be
h
precastbeam
precast beam
bw
2
Cast-in-place
Cast-in-place
Precast
Precast
Cast-in-place Cast-in-place
Precast Precast
Cast-in-place Cast-in-place
Precast Precast
Cast-in-place Cast-in-place
Hollow
Precast box
Precast
x No interaction
L Full interaction
ds slip
dx
x x
δmax
L x
No interaction
Partial interaction
Fig. (1.3) Slip and partial interaction for two rectangular beams
(Johnson, 1975).
Fig. (1.4) shows the strain diagram in composite concrete beam with
different types of interaction. It can be seen that for the case of no
interaction, each of the beam and slab act separately (Fig. (1.4a)). While
the composite beam with full interaction behave as a single monolithic
beam (Fig. (1.4c)). The behavior of a partially composite beam is in
between (Fig. (1.4b)).
The evaluation of the strength of the joint between precast concrete
beams and cast-in-place concrete slabs has been the subject of
considerable research. However, the behavior of the joint during the
loading has not been well studied by previous researchers. When the joint
in a composite concrete girder is unable to transmit all internal forces
from one part of the section to the other part in the same manner as if the
entire section were structural concrete cast in one piece, the girder is only
partially composite with stiffness characteristics between those of a fully
composite and a two-piece girder.
Current design methods rely heavily on empirically derived
equations based on experimental results of ultimate strength tests of the
joint.
4
(a) (b) (c)
5
7. Precast beam can be inspected before it is erected and there is an
opportunity to reject any substandard work before incorporation in the
structure.
In addition to that, the principal advantage of composite construction
is that significantly stiffer and stronger beams can be obtained as
compared to the same members without composite action. Also when
using precast construction in seismic zones, the composite slab or topping
is normally required in order to serve as a diaphragm connecting the
varies units.
1.2.2 Disadvantages:
There are, of course, disadvantages, which may be summarized as
follows:
1. The joint between the precast beam and the cast-in-situ deck needs a
special design and a preparation before casting the deck.
2. Some additional reinforcement may be required for lifting and
transporting precast beams. It has to be appreciated that a precast
beam has to be designed not only to function as part of a total
structure but also for the load condition pertaining during lifting and
transport.
3. If the beams are large in size problems can arise concerning
transportation and lifting costs.
6
The present work is devoted to the study of the behavior of
reinforced concrete composite beams during short term loading using
finite element method to analyze them.