Sunteți pe pagina 1din 47

MUNICIPALIDAD DISTRITAL DE QUIQUIJANA

GERENCIA MUNICIPAL
OFICINA DE SUPERVISION Y LIQUIDACION DE PROYECTOS DE INVERSION

Informe Mensual de Supervisor de Obra No 001


"SETIEMBRE"

META : 188

"CONSTRUCCION DE PISTAS Y VEREDAS DE LA CALLE URANCALLE EN LA C. C.


DE CCOLCCA, DISTRITO DE QUIQUIJANA - QUISPICANCHI - CUSCO "

Region: Cusco Provincia: Quispicanch Distrito: Quiquijana

Residente de Obra Ing. : Cesar Augusto Macedo Mostajo


Supervisor de Obra Ing. : Victor Hugo Santander Collantes

2013
FORMATO No 01

CONTENIDO

Informe Mensual de Supervisor de Obra No 001


"SETIEMBRE"
META : 188
"CONSTRUCCION DE PISTAS Y VEREDAS DE LA CALLE URANCALLE EN LA C. C.
DE CCOLCCA, DISTRITO DE QUIQUIJANA - QUISPICANCHI - CUSCO "

Residente de Obra Ing: Cesar Augusto Macedo Mostajo


Supervisor de Obra Ing: Victor Hugo Santander Collantes Año: 2013

No DESCRIPCION FORMATO CONTROL

1 Contenido F-1
2 Informe Mensual F-2
3 Valorización
3.1. Resumen de las Valorizaciones F-3
3.2. Valorización Programada F-31
3.3. Valorización de Mayores Metrados F-32
3.4. Valorización de Partidas Nuevas F-33
3.5. Valorización de Deductivos F-34
4 Control Diario de Metrados F-4
5 Movimiento de Almacén Valorizado
6.1. Resumen de los Movimiento de Almacén F-6
6.2. Movimiento de Almacén de Materiales Programados F-61
6.3. Movimiento de Almacén de Materiales de períodos anterio F-62
6.4. Movimiento de Almacén de Materiales Transferidos F-63
6 Movimiento de Maquinaria Valorizada F-7
7.1. Resumen de Movimiento de Maquinaria F-71
7.2. Control Diario de Maquinaria F-72
7 Manifiesto de Gasto F-8
8 Hojas de Tareo de Personal Obrero F-9
9 Control de Calidad F-10
10 Registro Fotográfico F-12
11 Cuaderno de Obra (Copias) F-13
12 Registro Digitalizado (disket/CD)
13 Anexos
P:Presentado N : No presentado X: No corresponde
FORMATO No 02
Informe Mensual de Supervisor de Obra No 001
"SETIEMBRE"

"CONSTRUCCION DE PISTAS Y VEREDAS DE LA CALLE URANCALLE EN LA C. C.


DE CCOLCCA, DISTRITO DE QUIQUIJANA - QUISPICANCHI - CUSCO "
A GENERALIDADES

A.1 RESIDENTE DE OBRA: Cesar Augusto Macedo Mostajo


Especialidad : Ingeniero Civil
Colegiatura : 84688
Dirección : Urbanización Santa Ursula G-5
A.2 SUPERVISOR DE OBR: Victor Hugo Santander Collantes
Especialidad : Ingeniero Civil
Colegiatura : 39031

A.3 FECHA REPORTADA : Del 01 al 31 de Julio del 2013

A.4 DATOS DEL PROYECTO

Unidad Ejecutora :Gobierno Regional Cusco


Función : 22 Educacion y Cultura
Programa : 047 Educacion Basica
Sub Programa : 0104 Educacion Primaria
Proy y/o Actividad : 2.060002 Mejoramiento de la Infraestructura I.E. N° 50152 El Carmen.
Componente : 2.000345 Mejoramiento de la Infraestructura I.E. N° 50152 El Carmen.
Finalidad : 04415 Construccion De Infraestructura Educativa
Meta : 188 Mejoramiento de la Infraestructura I.E. N° 50152 El Carmen- Calca.
Fuente de Financiamien: Canon y Sobrecanon.
Modalidad de Ejecución : Ejecución Presupuestaria Directa

A.5 FINANCIERO
Presupuesto Región Cusco % Convenio %
Base Expediente Técnico (Costo 905,284.70
Base Expediente Técnico 0.00
Presupuesto Total Asignado ###
Presupuesto Ejecutado en el M 329,753.41
Presupuesto Total Ejecutado 594,916.91

A.6 VALORIZACIONES

Valorizacione Programada % Mayor Metra % Partida Nueva % Deductivo %


Ejecutado - 0.00% - 0.00% - 0.00%
Acumulado ### 42.96% 2,919.14 0.32% 11,642.39 1.29%
Saldo ### - -

A.7 CRONOGRAMA DE OBRA


Cronograma Ejecucion : 8 (Meses)
Inicio Real : 4/12/2010
Paralizacion de Obra : 5/28/2010
Reinicio de Obra : 6/7/2010
Ejecutado total : 3.5 (Meses)
Saldo : 4.5 (Meses)
Terminación Teorico : 12/12/2010
Ampliacion Solicitada : Ninguna
Fecha Probable de Conc: 12/12/2010

A.8 UBICACIÓN
Departamento Provincia Distrito: Lugar
Cusco Cusco Quispicanchi Quiquijana
B ASPECTOS TECNICO
B.1 El
BREVE DESCRIPCION
proyecto DE LA en
en mención consiste META ANUAL
el diseño, calculo para la construcción de 18 aulas, construcción
de salones para el centro de computo, biblioteca, ambientes para administración como son secretaria
dirección, sala de profesores con 03 escaleras debajo de las cuales se adecuaran depósitos. Se
construirán también 01 modulo de cocina comedor que consta de 01 comedor, deposito, SS.HH.
cocina y 01 ambiente de guardianía, se prevé también por otro lado la construcción de 01 cerco
perimétrico. Equipamiento de mobiliario y computadoras para el centro de computo y la dotación de
200 carpetas unipersonales para educación de conformidad al Reglamento Nacional de
Construcciones y las Normas Técnicas de Diseño para Centros Educativos Urbanos elaborado por la
Dirección de Proyectos de la Dirección Técnica Financiera del Instituto Nacional de Infraestructura
Educativa y la implementación de los estándares básicos para edificaciones alto andinas proponiendo
áreas de circulación interna semiabiertas bajo techo (pasadizo) y áreas para las actividades lectivas
que impliquen volúmenes de aire necesarios (con al altura de edificación) tipologías constructivas de
la zona (edificación de dos niveles con solución de techo a dos aguas con el uso de tijerales
enchaclado y teja andina cerámica o teja decorativa), las mismas que se distribuyen de la siguiente
manera:
- Construcción de 18 Aulas (56.00 m2.)
- Construcción de biblioteca de 90 m2
- Construcción de Centro de Computo de 70 m2.
- Construcción de ambientes para administración que consta de:
Secretaria (12.37 m2), Dirección (12.81 m2) y sala de Prof. (27.35 m2).
- Modulo cocina comedor que consta de:
Comedor (42.38 m2), Cocina (13.60 m2), Deposito (5.00 m2), SS.HH. (3.23 m2), Guardianía
(12.68 m2).
- Construcción de cerco perimétrico en 120.15 ml.
- Equipamiento y Mobiliario de centro de computo que consta de:
34 PCs P-IV super ATX 550W, Intel corel duo 2.0 ghz , HD 80 GB, Monitor. 17”, teclado.
Mouse Óptico.
34 Modulos Escritorio - Computo de 0.60X0.80X1.00 Melamine c/silla inc.
- Mobiliario para biblioteca que consta de 07 modulo tablero inclinado doble de 2.40X1.50X1.10
de Melamine con 42 sillas de madera aguano simple, modulo de atención de 6.25X3.06 con una
puerta contra placada de acceso (2.10X0.90) y stanteria para libros de 04 pisos 10 metros lineales
ancho 0.40 mts.
B.2 -DOCUMENTOS
Dotación de 200TECNICOS
carpetas unipersonales.

DOCUMENTO NUMERO FECHA OBSERV.


Resolución de Aprobacion Expediente
Codigo SNIP 53505 9/24/2007
Acta de Apertura de Cuaderno Obra 4/12/2010
Acta de Entrega de Terreno 4/12/2010
Acta de Inicio de Obra 4/12/2010
Acta de Terminacion Obra - -
Acta de Paralización/Corte - 5/28/2010
Acta de Reinicio de Obra - 6/7/2010

B.3 RECURSOS UTILIZADOS


B.3.1 RECURSOS HUMANOS
CATEGORIA COSTO DIRECTOGASTO GENERAL SUPERV. TOTAL
Residente de Obra 1 1
Supervisor de Obra 1 1
Asistente Técnico 1 1
Asistente Administrativo 1 1
Almacenero de Obra 1 1
Guardian 1 1
Chofer 1 1
Maestro de Obra 1 1
Operario 10 10
Oficial 6 6
Peones 15 15
Total 32 6 1 39

COMENTARIO
La cantidad de Mano de Obra correspondiente al numero de operarios, oficiales y peones, mostrado
en el cuadro son cantidades promedio debido a que durante el presente mes se tomo personal de
acuerdo a la apertura de frentes, por otro lado hubo personal que se retiro voluntariamente.

B.3.2 PLANILLA DE TAREOS


DESCRIPCION PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO
COSTO DIRECTO 303,564.06 76,236.30 73,886.81 150,123.11 ###
GASTO GENERAL 128,563.14 - ###
-Gasto General Directo - -
-Gasto General Indirecto -
SUPERVISION 31,469.90 - ###
TOTAL 463,597.10 76,236.30 73,886.81 ### ###
B.3.2 RECURSOS DE MAQUINARIA Y EQUIPO

EQUIPO Y/O MAQUINARIA REGION ALQUILADOBENEFICIARIOS


Vibradora de Concreto Kaili 6.5H.P. 1
Vibradora de Concreto Honda 5.5H.P. 1
Mezcladora de Concreto Kolher de 8 H.P. 1
Mezcladora de Concreto Honda GX 270 de 9 P3 1
Camion Hiunday WZ 6732 1
Camion Volquete WZ 5180 1
Motobomba Gasolinero GX 160 de 5.5 HP 1
Camioneta Toyota PGN 1
Total 8 0

COMENTARIO
En almacen de obra se encuentra: 01 Mezcladora de Concreto Kohler y 01 Vibradora de
Concreto marca Kaili usadas transferidas de la Obra "Construccion Infraestructura
Escuela Superior Bellas Artes de Calca", 01 Mezcladora de Concreto de 9 P3 marca
Honda y 01 Motobomba Gasolinera GX 160 de 5.5 HP Usadas Transferidas de la Obra
"Reposicion I. E. Jose Gabriel Condorcanqui Tupac Amaru II- Yanaoca se encuentran
operativas.
B.3.3 VALORIZACION DE MAQUINARIA Y EQUIPO

DESCRIPCION PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO


Region 22,889.88 3189.92 2544.17 5734.09 17155.79
Convenio
Beneficiarios
TOTAL 22889.88 3189.92 2544.17 5734.09 17155.79

COMENTARIO
Se presenta la valorizacion de las Horas Maquina trabajadas por la Mezcladoras de
Concreto, Vibradoras de Concreto, Motobomba, Camion Hiunday y 02 Volquetes.

B.4 AVANCE FISICO

B.4.1 BREVE APRECIACION SOBRE LA VALORIZACION MENSUAL


El porcentaje de valorizacion alcanzado en el presente mes asciende a 8.15 % alcanzando
un porcentaje acumulado de 17.68%, cabe aclarar que este porcentaje que se ha
alcanzado es gracias a que se ha gestionado materiales (fierro corrugado de 3/4) en
calidad de transferencia y/o prestamo, en vista de que hasta la fecha no se nos atiende el
requerimiento de fierro corrugado de 3/4" de diametro, material sumamente necesario en
la construccion de la obra.

B.4.2 VALORIZACION DE OBRA

DESCRIPCION PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO


Programado 905,284.70 388,909.32 0.00 388909.32 516,375.38
Mayor Metrad 0.00 2,919.14 0.00 2919.14 0.00
Partidas Nuev 0.00 11,642.39 0.00 11642.39 0.00
Deductivos 0.00 0.00 0.00 0.00 0.00
TOTAL 905,284.70 403,470.86 0.00 403,470.86 501,813.85

B.4.3 VALORIZACIONES ACUMULADAS ANUALES

DESCRIPCION PERIODOS DE GESTION TOTAL SALDO


Año 2008 Año 2009 Año 2010
Programado - 0.00 388,909.32 388909.32 516,375.38
Mayor Metrad - 0.00 2,919.14 2919.14 (2,919.14)
Partidas Nuev - 0.00 11,642.39 11642.39 (11,642.39)
Deductivos - 0.00 - 0.00 0.00
TOTAL - 0.00 403,470.86 403,470.86 501,813.85
B.4.5 MODIFICACIONES DE OBRA

Descripción Presupuesto Mayor Partidas Deductivo Total


Base( Costo Directo) Metrado Nuevas Modificación
S/. 905,284.70 2919.14 11642.39 0 14,561.53
% 0.32 1.29 0 1.61

COMENTARIO
Se han generado Adicionales por Mayores Metrados, debido a que en algunos metrados del
expediente tecnico presenta errores las mismas que se observan durante la consecucion de
obra.
Por otro lado se ha generado Adicionales por Partida Nueva, debido a que se han ejecutado
actividades no previstas en el expediente tecnico los mismos que eran necesarias su
ejecucion para proseguir con el proceso constructivo de la obra. Cabe señalar que las
creacion
B.4.6 de las partidas
AVANCE Nuevas se encuentran debidamente
DEL CRONOGRAMA DE OBRA autorizadas
(Meses) por el Supervisor
de Obra
PROGRAMADO 8 CORTE/PARALIZADO 5/28/2010 SALDO 4.5
INICIADO 4/12/2010 REINICIADO 6/7/2010 ESTADO -
EJECUTADO 3.5 AMPLIACION PLAZO 0 FINAL TEORICA 12/12/2010

COMENTARIO
Con referencia al cronograma de obra se ha realizado una reprogramacion acelerada de
obra en vista de que en los dos primeros meses el avance fisico alcanzado por el Anterior
Residente fue minimo ( 3.28%), reprogramacion acelerada que se adjunta en el anexo del
presente informe.
C. ASPECTO FINANCIERO

C.1.1 EJECUCION DE META FINANCIERA 2009

EJECUTADO ASIGNADO SALDO


DESCRIPCION PROGRAMADO 2009 2009 BALANCE TOTAL
Region - - - - -

C.1.2 EJECUCION DE META FINANCIERA 2010

DESCRIPCION PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO


Region 1,197,762.00 265,163.50 329,753.41 594,916.91 602,845.09
Convenio
TOTAL ### 265,163.50 ### 594,916.91 ###

C.1.3 EJECUCION DE META FINANCIERA ACUMULADA

DESCRIPCION PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO


Region 1,197,762.00 265,163.50 329,753.41 594,916.91 602,845.09
Convenio
TOTAL ### 265,163.50 ### 594,916.91 ###

C.1.4 EJECUCION DE METAS FINANCIERA ANUALES

PRESUPUESTO PERIODOS DE GESTION TOTAL SALDO


BASE Año 2008 Año 2009 Año 2010
- - - 594,916.91 594,916.91 ###
D MEMORIA DESCRIPTIVA VALORIZADA

D.1.1 PROGRAMADO

05.02.00 COLUMNAS
05.02.02 COLUMNAS - CONCRETO 210kg/cm2

Esta partida se realizo preparando concreto con un f´c=210Kg/cm2 con un revenimiento


que garantize la trabajabilidad del concreto, el colocado del concreto se realizo con ayuda
de baldes de plastico y el transporte medante buguis.
Metrado 9.99 M3 Costo 3919.48

05.02.03 COLUMNAS - ENCOFRADO Y DESENCOFRADO

Con referencia a esta partida se realizo utilizando madera corriente, clavos de diferentes
tamaños y listones para la preparacion de formas, las cuales se colocaron cuidando que
estas esten alineadas y aplomadas, siendo fijadas con ayuda de arriostres y puntales de
madera. M2
Metrado 422.63 Costo 10447.46

05.04.00 VIGAS
05.04.01 VIGAS - CONCRETO 210kg/cm2

Para esta partida se preparo concreto con un f´c=210Kg/cm2 , según la dosificacion de


concreto dado por el laboratorio de mecanica de materiales de la institucion, el transporte
se realizo mediante buguis, cuidando evitar la segregacion, se coloco con ayuda de
vibradoras, previamente se limpio todas las superficies donde debia haber contacto con el
concreto. M3
Metrado 35.50 Costo 14666.12

05.04.02 VIGAS - ENCOFRADO Y DESENCOFRADO

Esta partida se realizo utilizando madera corriente, clavos de diferentes tamaños y


listones para la preparacion de formas, las cuales se colocaron cuidando que estas esten
alineadas y aplomadas, siendo fijadas con ayuda de arriostres y puntales de madera, sobre
pies derechos que se fijaron previamente.
Metrado 273.54 M2 Costo 7210.44

05.04.03 VIGAS - ACERO FY=4200 kg/cm2

Esta partida se realizo utilizando varillas de acero de diferentes diametros distribuidos


según lo especificado en los planos de estructuras, con un fy´=4200 Kg/cm2 amarrados
con alambre negro N° 16. Incluye: la habilitacion y doblado de fierro, la habilitacion de
estribos, el armado de las estructuras, el izado de las mismas asi como el alineamiento y
aplome de estas. KG
Metrado 6152.51 Costo 29224.43

05.05.00 LOSAS ALIGERADAS


05.05.01 LOSAS ALIGERADAS - CONCRETO 210kg/cm2

Para esta partida se preparo concreto con una f´c=210Kg/cm2 , según la dosificacion de
concreto dado por el laboratorio de mecanica de materiales de la institucion, el transporte
se realizo mediante buguis, cuidando evitar la segregacion, se coloco con ayuda de
vibradoras, previamente se limpio todas las superficies donde debia haber contacto con el
concreto.
Metrado 15.20 M3 Costo 5614.28

05.05.02 LOSAS ALIGERADAS - ENCOFRADO Y DESENCOFRADO

Esta partida se realizo utilizando madera corriente, clavos de diferentes tamaños y


listones, las cuales se colocaron cuidando que estas esten alineadas y aplomadas sobre
soleras de listones de madera colocadas fijas en el encofrado de vigas, siendo fijadas con
ayuda de clavos , sobre pies derechosM2
que se fijaron previamente.
Metrado 197.48 Costo 4804.63
D MEMORIA DESCRIPTIVA VALORIZADA

05.05.03 LOSAS ALIGERADAS FY=4200 kg/cm2

Esta partida se realizo utilizando varillas de acero de 1/2" de diametro para el refuerzo en
las viguetas y 1/4" de diametro para el acero de temperatura distribuidos según lo
especificado en los planos de estructuras, con un fy´=4200 Kg/cm2 amarrados con
alambre negro N° 16. Incluye: la habilitacion y doblado de fierro, el armado de las
estructuras, asi como el alineamientoKG y aplomo de estas.
Metrado 1628.13 Costo 7733.61

05.05.04 LOSAS ALIGERADAS- LADRILLO HUECO 15x30x30cm

Para aligerar la losa de entrepiso se coloco ladrillo tipo pandereta de 15cm x 30cm. X
30cm. De medidas, los cuales se distribuyen conforme a lo especificado en el expediente
tecnico de obra.
Metrado 1800.00 UND Costo 2466.00

05.07.00 COLUMNETAS
05.07.01 Columnetas. - Concreto 210 kg/cm2

Durante el presente mes se ha realizado el vaciado Columnetas de amarre de 0.15 X 0.20


cm de seccion en el Primer Nivel Bloque IIIy Bloque IV ,Segundo Nivel del bloque II,
utilizando para este fin un concreto F´c=210 kg/cm2
Metrado 10.86 m3 Costo 3877.68

05.07.02 Columnetas. - Encofrado y Desencofrado

Con referencia a esta partida durante el presente mes se ha realizado el encofrado de


Columnetas de Amarre de 0.15 X 0.20 cm de seccion en el Primer Nivel del Bloque III
;Bloque IV, y Segundo Nivel Bloque II utilizando para este fin madera corriente de
11/2"x8"x10' , fijadas con listones de 2"x3"x10', aseguradas con alambre Nº 8.
Metrado 86.57 m2 Costo 2405.88

05.07.03 Acero grado 60 en columnetas de amarre

Durante el presente mes se ha efectuado la habilitacion y colocado de acero fy=4200


kg/cm2 en Columnetas de Amarre en el Segundo Nivel del Bloque II, colocado que se
efectua de acuerdo a lo especificado en e los planos del expediente tecnico.
Metrado 26.69 kg Costo 126.78

08.01.00 TRANSPORTE DE MATERIALES CUSCO - CALCA

Con referencia a esta partida se realizo el traslado de Cemento Portland Tipo I, Pies
Derechos en calidad de prestamo asi como Fierro Corrugado de 3/4" de diametro en
calidad de transferencia y prestamo desde la ciudad del Cusco hasta la obra.
Metrado 170.00 M3 Costo 20400.00

09.00.00 MUROS TABIQUES DE ALBAÑILERÍA


09.01.00 MURO DE CABEZA LADRILLO CON CEMENTO - ARENA

Se hicieron trabajos en el Segundo Nivel del Bloque III (ambientes destinado a Aulas ), los
mismos que se han ejecutado tomando en consideracion todas las indicaciones señaladas
en el expediente tecnico
Metrado 178.47 m2 Costo 2673.48
D MEMORIA DESCRIPTIVA VALORIZADA

09.01.00 MURO DE SOGA LADRILLO CON CEMENTO - ARENA

En el presente mes se ha ejecutado el tarrajeo de las Vigas (Cara Interior),


Correspondientes al Primer Nivel del bloque I, las mismas que se han ejecutado tomando
en consideracion todas las indicaciones señaladas en el expediente tecnico .
Metrado 9.24 m2 Costo 161.88

10.00.00 REVOQUES ENLUCIDO Y MOLDURAS


10.02.00 Tarrajeo en Interiores Mezcla C:A 1:5

En el mes se ha realizado el tarrajeo de paredes interiores de los ambientes destinados a


Aulas del primer nivel del bloque I, La misma que previo al tarrajeo se efectuo la limpieza
correspondiente para obtener buena adherencia.
Metrado 178.47 m2 Costo 2673.48

10.05.00 Tarrajeo de Vigas

En el presente mes se ha ejecutado el tarrajeo de las Vigas (Cara Interior),


Correspondientes al Primer Nivel del bloque I, las mismas que se han ejecutado tomando
en consideracion todas las indicaciones señaladas en el expediente tecnico .
Metrado 24.48 m2 Costo 428.97

11.00.00 CIELORRASO
11.01.00 CIELORRASOS CON TARRAJEO DE CEMENTO SOBFRE LOSA ALIGERADA

En el presente mes se ha efectuado el tarrajeo de cemento sobre losa aligerada del Primer
Nivel del Bloque I (ambiente destinado a Aulas y Area Administrativa), las mismas que se
han ejecutado tomando en consideracion todas las indicaciones señaladas en el
expediente tecnico .
Metrado 54.91 m2 Costo 1015.80

29.00.00 SALIDA DE INSTALACIONES INTERIORES


29.01.00 SALIDA PARA CENTRO DE LUZ TECHO

Se realizo dejando antes del vaciado de la losa aligerada cajas octogonales de 2"x2"x4"
las cuales se fijaron al encofrado con alambre negro Nro 16.
Metrado 18.00 UND Costo 360.90

29.02 Salida de tomacorriente doble c/linea a Tierra

Se realizo dejando antes del vaciado de la losa aligerada cajas octogonales de 2"x2"x4"
las cuales se fijaron al encofrado con alambre negro Nro 16.
Metrado 18.00 PTO Costo 360.90

30.00.00 CONDUCTORES Y/O CABLES


35.00.00 TUBERIA PVC- SEL DE 3/4"

En la ejecucion de esta partida se realizo el replanteo de la zona donde se colocaria la


tuberia, se coloco tubo PVC SEL de 20mm según lo especificado en los planos del
expediente tecnico, estos se unieron con
M pegamento a los accesorios.
Metrado 210.00 Costo 506.10
E. ASPECTO ADMINISTRATIVO

* Existe la negativa por parte de los proveedores en entregar los materiales de


construccion en obra, en vista de la necesidad con la que requerimos los materiales,
estos se vienen trasladando con recursos propios de la obra.

* La falta de abastecimiento oportuno de materiales generado por el retraso en la entrega


de las oficinas encargadas, perjudican el normal avance de obra.

F. OBSERVACIONES Y RECOMENDACIONES

Se ha realizado algunas modificaciones no sustanciales en diferentes partidas del


* expediente tecnico asi como se han creado partidas nuevas, las cuales se han efectuado
con autorizacion del inspector de obra, tal como consta en los diferentes asientos del
cuaderno de obra.
Se tiene conocimiento de que el inspector de obra envia semanalmente un reporte del
* estado situacional de obra, en la misma que señala algunas observaciones, documento
del cual esta residencia solicita una copia para levantar las observaciones en su debido
momento.

* Se recomienda sugerir a la Oficina de Administración implementar un sistema más


efectivo para atender los materiales solicitados.

* La obra en el año 2009 se ejecuto POR CONTRATA alcanzando un avance de 16.73% tal como
señala la ultima valorizacion de supervision (Setiembre 2009), En el presente año 2010 la
ejecucion cambia de modalidad a ADMINISTRACION DIRECTA, por lo que la oficina de Estudios y
Proyectos efectuo un Expediente cambiando la modalidad presupuestal de la obra alcanzando
este expediente un monto de S/. 1'675,635.76, la cual se encuentra en proceso de aprobacion.

* Hasta la fecha se continua a la espera de fierro corrugado de 3/4" de diametro


solicitado en el requerimiento presentado con fecha 02 de Julio del 2010,
desabastecimiento que viene causando retraso en la ejecucion de obra.
RESUMEN DESAGREGADO DE VALORIZACIONES PROGRAMADAS DE OBRA Nº 005
SETIEMBRE 2017.

FUNCIÓN : 18 Saneamiento
CATEGORIA PRESUPUESTAL : 0083 Programa Nacional de Saneamiento Rural
PROYECTO : 2325002 Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco
ACTIVIDAD : 4000041 Instalacion del Sistema de Agua Potable
META : 013 "Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco"
FTE. FTO. : Recursos Determinados
MONTO TOTAL EXP. TEC. : S/. 1,098,519.37
PRESUPUESTO ASIGNADO 2017 : S/. 608,670.00

AVANCES
PRESUPUESTO SALDO
ITEM VALORIZACION ANTERIOR ACTUAL ACUMULADO 
S/. Valorizado S/. % Valorizado S/. % Valorizado S/. % Valorizado S/. %

1 PROGRAMADO 905,284.70 388,909.32 42.96% 0.00 0.00% 388,909.32 42.96% 516,375.38 57.04%
PROGRAMADO 905,284.70 388,909.32 42.96% 0.00 0.00% 388,909.32 42.96% 516,375.38 57.04%

2 MAYOR METRADOS 2,919.14 0.32% 0.00 0.00% 2,919.14 0.32% (2,919.14) -0.32%
MAYORES METRADOS 2,919.14 0.00 2,919.14 0.00

3 PARTIDAS NUEVAS 11,642.39 1.29% 0.00 0.00% 11,642.39 1.29% (11,642.39) -1.29%
PARTIDAS NUEVAS 11,642.39 0.00 11,642.39 0.00

4 DEDUCTIVOS 0.00 0.00% 0.00 Err:522 0.00 Err:522 0.00 0.00%


(Costo Directo) 0.00 0.00 0.00 0.00

TOTAL (COSTO DIRECTO) 905,284.70 403,470.86 44.57% 0.00 0.00% 403,470.86 44.57% 501,813.85 55.43%
GASTOS GENERALES (11.48 % ) 103,903.20 46,307.99 0.00 46,307.99 57,595.21
GASTOS DE INSPECCION (6.03 % ) 54,557.22 24,315.28 0.00 24,315.28 30,241.94
GASTOS DE EXPEDIENTE TECNICO (2.43 % ) 22,000.00 9,805.05 0.00 9,805.05 12,194.95
GASTOS DE LIQUIDACION (1.41 % ) 12,774.25 5,693.28 0.00 5,693.28 7,080.97
TOTAL ( CD + CI ) 1,098,519.37 489,592.45 44.57% 0.00 0.00% 489,592.45 44.57% 608,926.93 55.43%
VALORIZACIÓN DE AVANCE DE OBRA PROGRAMADA N° 005
SETIEMBRE 2017.
FUNCIÓN : 18 Saneamiento
CATEGORIA PRESUPUESTAL : 0083 Programa Nacional de Saneamiento Rural
PROYECTO : 2325002 Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco
ACTIVIDAD : 4000041 Instalacion del Sistema de Agua Potable
META : 013 "Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco"
FTE. FTO. : Recursos Determinados
MONTO TOTAL EXP. TEC. : S/. 1,098,519.37
PRESUPUESTO ASIGNADO 2017 : S/. 608,670.00

ANTERIOR MES ACUMULADO SALDO


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL
METR PARCIAL % METR PARCIAL % METR PARCIAL % METR PARCIAL %

01 EFICIENTE INFRAESTRUCTURA DEL SISTEMA DE AGUA POTABLE


01.01 OBRAS PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.00 X 2.00 M und 1.00 801.21 801.21 1.00 801.21 100.00% 0.00 0.00 0.00% 1.00 801.21 100.00% 0.00 0.00 0.00%
01.01.02 ALMACEN DE OBRA EN AREAS URBANAS mes 6.00 235.00 1,410.00 1.50 352.50 25.00% 0.00 0.00 0.00% 1.50 352.50 25.00% 4.50 1,057.50 75.00%
01.01.03 CAMPAMENTO DE ROLLIZOS CON TECHO CALAMINA m2 135.00 69.94 9,441.90 97.00 6,784.18 71.85% 0.00 0.00 0.00% 97.00 6,784.18 71.85% 38.00 2,657.72 28.15%

01.02 CAPTACION DE MANANTE (5.00 UND)


01.02.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 9.33 1.25 11.66 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.33 11.66 100.00%
01.02.02 DEMOLICION DE CAPTACION EXISTENTE und 4.00 206.00 824.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 824.00 100.00%
01.02.03 ZANJA DE INFILTRACION (TUB. PVC CRIBADA, CAPA ARCILLA) m 35.00 121.18 4,241.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.00 4,241.30 100.00%
01.02.04 EXCAVACION MANUAL PARA ESTRUCTURAS m3 13.05 14.00 182.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.05 182.70 100.00%
01.02.05 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 16.31 10.50 171.26 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.31 171.26 100.00%
01.02.06 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.08 26.24 185.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.08 185.78 100.00%
01.02.07 ENCOFRADO Y DESENCOFRADO m2 65.90 16.95 1,117.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 65.90 1,117.01 100.00%
01.02.08 ACERO DE REFUERZO 3/8" FY=4200 KG/CM2 kg 289.80 5.67 1,643.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 289.80 1,643.17 100.00%
01.02.09 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 0.50 273.86 136.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.50 136.93 100.00%
01.02.10 CONCRETO FC=175 KG/CM2 m3 6.78 432.90 2,935.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.78 2,935.06 100.00%
01.02.11 FILTRO DE GRAVA (MAT. SELECCIONADO) m3 5.00 133.50 667.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 667.50 100.00%
01.02.12 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 13.80 27.79 383.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.80 383.50 100.00%
01.02.13 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 31.15 18.00 560.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 31.15 560.70 100.00%
01.02.14 PINTURA EN MUROS m2 20.50 7.65 156.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.50 156.83 100.00%
01.02.15 ACCESORIOS PARA CAPTACION DE 1" GLB 5.00 485.34 2,426.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 2,426.70 100.00%

01.02.16 TRABAJOS DE PROTECCION DE CAPTACIONES( 02 UND)


01.02.16.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.90 14.00 12.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.90 12.60 100.00%
01.02.16.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 1.17 10.50 12.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.17 12.29 100.00%
01.02.16.03 CONCRETO FC=175 KG/CM2 m3 0.90 432.90 389.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.90 389.61 100.00%
01.02.16.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 25.00 55.75 1,393.75 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.00 1,393.75 100.00%
01.02.16.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 X COCADAS DE m 54.00 90.00 4,860.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 54.00 4,860.00 100.00%
01.02.16.06 PUERTA METALICA S/DISEÑO und 5.00 200.00 1,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 1,000.00 100.00%

01.03 LINEA DE CONDUCCION (3,527.00 ML)


01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 TRAZO NIVELACION Y REPLANTEO DURANTE LA CONSTRUCCION m 3527.00 1.03 3,632.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,527.00 3,632.81 100.00%

01.03.02 MOVIMIENTO DE TIERRAS


01.03.02.01 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 3527.00 4.20 14,813.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,527.00 14,813.40 100.00%
01.03.02.02 REFINE Y NIVELACION DE ZANJAS m 3527.00 1.68 5,925.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,527.00 5,925.36 100.00%
01.03.02.03 CAMA DE APOYO PARA TUBERIAS MENORES DE 6" (e=1") m 3527.00 1.35 4,761.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,527.00 4,761.45 100.00%
01.03.02.04 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 3527.00 6.56 23,137.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,527.00 23,137.12 100.00%

01.03.03 TUBERIAS
01.03.03.01 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1 1/2" NT m 677.00 6.32 4,278.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 677.00 4,278.64 100.00%
01.03.03.02 SUMINISTRO DE ACCESORIOS L.C 1 1/2" GLB 1.00 240.00 240.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 240.00 100.00%
01.03.03.03 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1" NTP I m 2850.00 5.18 14,763.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,850.00 14,763.00 100.00%
01.03.03.04 SUMINISTRO DE ACCESORIOS L.C 1" GLB 1.00 350.00 350.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 350.00 100.00%
01.03.03.05 INSTALAC. DE ACCESORIOS PROMEDIO und 110.00 2.63 289.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 110.00 289.30 100.00%

01.03.04 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION


01.03.04.01 PRUEBA HIDRAULICA+DESINFECCION TUB.< 4" A ZANJA TAPADA m 3527.00 0.83 2,927.41 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,527.00 2,927.41 100.00%
01.04 PASE AEREO L=6.00 ML EN LINEA DE CONDUCCION (2.00 UND)
01.04.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 16.00 1.25 20.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.00 20.00 100.00%
01.04.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.44 14.00 20.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.44 20.16 100.00%
01.04.03 CONCRETO FC=175 KG/CM2 m3 1.44 432.90 623.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.44 623.38 100.00%
01.04.04 ENCOFRADO Y DESENCOFRADO m2 9.60 16.95 162.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.60 162.72 100.00%
01.04.05 SUMINISTRO DE ACCESORIOS SANITARIOS GLB 2.00 149.80 299.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 299.60 100.00%

01.05 CAMARA DE REUNION ( 2.00 UND)


01.05.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 2.32 1.25 2.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.32 2.90 100.00%
01.05.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.94 14.00 13.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.94 13.16 100.00%
01.05.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 2.36 10.50 24.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.36 24.78 100.00%
01.05.04 ENCOFRADO Y DESENCOFRADO m2 10.08 16.95 170.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.08 170.86 100.00%
01.05.05 ACERO DE REFUERZO FY=4200 kg 52.82 4.76 251.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 52.82 251.42 100.00%
01.05.06 CONCRETO FC=175 KG/CM2 m3 0.77 432.90 333.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.77 333.33 100.00%
01.05.07 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 5.04 27.79 140.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.04 140.06 100.00%
01.05.08 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.76 18.00 103.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.76 103.68 100.00%
01.05.09 PINTURA EN MUROS m2 6.40 7.65 48.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.40 48.96 100.00%
01.05.10 SUMINISTRO DE ACCESORIOS CAMARA DE REUNION GLB 2.00 218.45 436.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 436.90 100.00%

01.05.11 CAJA DE VALVULAS DE CAMARA DE REUNION (2.00 UND)


01.05.11.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.49 14.00 6.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.49 6.86 100.00%
01.05.11.02 ENCOFRADO Y DESENCOFRADO m2 2.24 16.95 37.97 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.24 37.97 100.00%
01.05.11.03 ACERO DE REFUERZO FY=4200 kg 4.65 4.76 22.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.65 22.13 100.00%
01.05.11.04 CONCRETO FC=175 KG/CM2 m3 0.18 432.90 77.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.18 77.92 100.00%
01.05.11.05 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 0.48 18.00 8.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.48 8.64 100.00%
01.05.11.06 PINTURA EN MUROS m2 0.48 7.65 3.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.48 3.67 100.00%
01.05.11.07 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE C.R. (1") GLB 1.00 191.45 191.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 191.45 100.00%
01.05.11.08 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE C.R. (11/2") GLB 1.00 245.45 245.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 245.45 100.00%

01.06 CAMARA DE DISTRIBUCION DE CAUDALES (4.00 UND)


01.06.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.60 1.25 9.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.60 9.50 100.00%
01.06.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 4.18 14.00 58.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.18 58.52 100.00%
01.06.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 4.18 10.50 43.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.18 43.89 100.00%
01.06.04 FILTRO DE GRAVA (MAT. SELECCIONADO) m3 0.06 133.50 8.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.06 8.01 100.00%
01.06.05 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 0.20 273.86 54.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.20 54.77 100.00%
01.06.06 CONCRETO FC=175 KG/CM2 m3 0.21 432.90 90.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.21 90.91 100.00%
01.06.07 CONCRETO FC=210 KG/CM2 m3 5.29 494.88 2,617.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.29 2,617.92 100.00%
01.06.08 ENCOFRADO Y DESENCOFRADO m2 51.78 16.95 877.67 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.78 877.67 100.00%
01.06.09 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 58.44 27.79 1,624.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 58.44 1,624.05 100.00%
01.06.10 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 30.92 18.00 556.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.92 556.56 100.00%
01.06.11 PINTURA EN MUROS m2 30.92 7.65 236.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.92 236.54 100.00%
01.06.12 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 01 GLB 1.00 844.00 844.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.13 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 02 GLB 1.00 844.00 844.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.14 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 03 GLB 1.00 844.00 844.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%
01.06.15 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. 04 GLB 1.00 844.00 844.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 844.00 100.00%

01.07 CAMARA DE FILTRO PARA TRATAMIENTO DE AGUA POTABLE (1.00 UND)


01.07.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.26 1.25 1.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.26 1.58 100.00%
01.07.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.76 14.00 10.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.76 10.64 100.00%
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 0.95 10.50 9.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.95 9.98 100.00%
01.07.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 1.26 26.24 33.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.26 33.06 100.00%
01.07.05 ENCOFRADO Y DESENCOFRADO m2 6.00 16.95 101.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.00 101.70 100.00%
01.07.06 ACERO DE REFUERZO FY=4200 kg 36.68 4.76 174.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.68 174.60 100.00%
01.07.07 CONCRETO FC=175 KG/CM2 m3 0.43 432.90 186.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.43 186.15 100.00%
01.07.08 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 2.16 27.79 60.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.16 60.03 100.00%
01.07.09 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 3.91 18.00 70.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.91 70.38 100.00%
01.07.10 PINTURA EN MUROS m2 3.91 7.65 29.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.91 29.91 100.00%
01.07.11 MATERIAL SELECCIONADO PARA FILTRO m3 0.42 133.50 56.07 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.42 56.07 100.00%
01.07.12 SUMINISTRO DE ACCESORIOS CAMARA DE FILTRO GLB 1.00 503.80 503.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 503.80 100.00%
01.08 RESERVORIO DE CONCRETO ARMADO DE V=5.00 M3 (1.00 UND)
01.08.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.29 1.25 9.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.29 9.11 100.00%
01.08.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.83 14.00 81.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.83 81.62 100.00%
01.08.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 7.58 10.50 79.59 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.58 79.59 100.00%
01.08.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.29 26.24 191.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.29 191.29 100.00%
01.08.05 CONCRETO FC=210 KG/CM2 m3 3.99 494.88 1,974.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.99 1,974.57 100.00%
01.08.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C-H m2 4.00 26.24 104.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 104.96 100.00%
01.08.07 ENCOFRADO Y DESENCOFRADO m2 31.58 16.95 535.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 31.58 535.28 100.00%
01.08.08 ACERO DE REFUERZO FY=4200 kg 152.35 4.76 725.19 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 152.35 725.19 100.00%
01.08.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=5.00 M3 GLB 1.00 639.00 639.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 639.00 100.00%
01.08.10 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 16.40 27.79 455.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.40 455.76 100.00%
01.08.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.47 18.00 368.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.47 368.46 100.00%
01.08.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 103.05 100.00%
01.08.13 PINTURA EN MUROS m2 20.47 7.65 156.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.47 156.60 100.00%

01.08.14 CAJA DE VALVULAS DE RESERORIO DE V=5.00 M3 ( 01 UND)


01.08.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.24 1.55 100.00%
01.08.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.05 14.70 100.00%
01.08.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 1.31 10.50 13.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.31 13.76 100.00%
01.08.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.90 150.86 100.00%
01.08.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 45.85 283.81 100.00%
01.08.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.70 303.03 100.00%
01.08.14.07 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO V=5.00 M GLB 1.00 321.34 321.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 321.34 100.00%
01.08.14.08 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO V=5 M3 GLB 1.00 699.52 699.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 699.52 100.00%
01.08.14.09 SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE RESERVORIO V GLB 1.00 439.34 439.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.34 100.00%
01.08.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 155.45 100.00%
01.08.14.11 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 3.30 27.79 91.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.30 91.71 100.00%
01.08.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.71 102.78 100.00%
01.08.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%

01.08.15 TRABAJOS DE PROTECCION DE RESERVORIO V=5.00 M3( 01 UND)


01.08.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.43 14.00 6.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.43 6.02 100.00%
01.08.15.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 0.56 10.50 5.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.56 5.88 100.00%
01.08.15.03 CONCRETO FC=175 KG/CM2 m3 0.43 432.90 186.15 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.43 186.15 100.00%
01.08.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 12.00 55.75 669.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 669.00 100.00%
01.08.15.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 X COCADAS DE m 32.40 90.00 2,916.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.40 2,916.00 100.00%
01.08.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 200.00 100.00%

01.08.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO


01.08.16.01 EQUIPO DE CLORACION POR GOTEO (INCLUYE CASETA, TANQUE D und 1.00 3611.24 3,611.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,611.24 100.00%

01.09 RESERVORIO DE CONCRETO ARMADO DE V=3.00 M3 (1.00 UND)


01.09.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.02 1.25 8.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.02 8.78 100.00%
01.09.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.62 14.00 78.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.62 78.68 100.00%
01.09.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 7.30 10.50 76.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.30 76.65 100.00%
01.09.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.02 26.24 184.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.02 184.20 100.00%
01.09.05 CONCRETO FC=210 KG/CM2 m3 3.96 494.88 1,959.72 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.96 1,959.72 100.00%
01.09.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C-H m2 3.80 26.24 99.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.80 99.71 100.00%
01.09.07 ENCOFRADO Y DESENCOFRADO m2 31.72 16.95 537.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 31.72 537.65 100.00%
01.09.08 ACERO DE REFUERZO FY=4200 kg 224.80 4.76 1,070.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 224.80 1,070.05 100.00%
01.09.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=3.00 M3 GLB 1.00 639.00 639.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 639.00 100.00%
01.09.10 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 15.89 27.79 441.58 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.89 441.58 100.00%
01.09.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.85 18.00 375.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.85 375.30 100.00%
01.09.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 103.05 100.00%
01.09.13 PINTURA EN MUROS m2 20.85 7.65 159.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.85 159.50 100.00%

01.09.14 CAJA DE VALVULAS DE RESERORIO DE V=3.00 M3 ( 01 UND)


01.09.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.24 1.55 100.00%
01.09.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.05 14.70 100.00%
01.09.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 1.31 10.50 13.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.31 13.76 100.00%
01.09.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.90 150.86 100.00%
01.09.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 45.85 283.81 100.00%
01.09.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.70 303.03 100.00%
01.09.14.07 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO V=3.00 M GLB 1.00 321.34 321.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 321.34 100.00%
01.09.14.08 SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO V=3.00 M3 GLB 1.00 576.52 576.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 576.52 100.00%
01.09.14.09 SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE RESERVORIO V GLB 1.00 439.34 439.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 439.34 100.00%
01.09.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 155.45 100.00%
01.09.14.11 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 3.30 27.79 91.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.30 91.71 100.00%
01.09.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.71 102.78 100.00%
01.09.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%
01.09.15 TRABAJOS DE PROTECCION DE RESERVORIO V=5.00 M3( 01 UND)
01.09.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.29 14.00 4.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.29 4.06 100.00%
01.09.15.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 0.37 10.50 3.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.37 3.89 100.00%
01.09.15.03 CONCRETO FC=175 KG/CM2 m3 0.29 432.90 125.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.29 125.54 100.00%
01.09.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 8.00 55.75 446.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 446.00 100.00%
01.09.15.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 X COCADAS DE m 21.60 90.00 1,944.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.60 1,944.00 100.00%
01.09.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 200.00 100.00%

01.09.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO


01.09.16.01 EQUIPO DE CLORACION POR GOTEO (INCLUYE CASETA, TANQUE D und 1.00 3611.24 3,611.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 3,611.24 100.00%

01.10 RESERVORIO DE CONCRETO ARMADO DE V=2.00 M3 (2.00 UND)


01.10.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 10.58 1.25 13.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.58 13.23 100.00%
01.10.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 8.46 14.00 118.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.46 118.44 100.00%
01.10.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 11.00 10.50 115.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.00 115.50 100.00%
01.10.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 10.58 26.24 277.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.58 277.62 100.00%
01.10.05 CONCRETO FC=210 KG/CM2 m3 6.25 494.88 3,093.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.25 3,093.00 100.00%
01.10.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C-H m2 5.12 26.24 134.35 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.12 134.35 100.00%
01.10.07 ENCOFRADO Y DESENCOFRADO m2 51.72 16.95 876.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 51.72 876.65 100.00%
01.10.08 ACERO DE REFUERZO FY=4200 kg 366.92 4.76 1,746.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 366.92 1,746.54 100.00%
01.10.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=2.00M3 GLB 1.00 592.00 592.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 592.00 100.00%
01.10.10 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 24.96 27.79 693.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 24.96 693.64 100.00%
01.10.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 33.90 18.00 610.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 33.90 610.20 100.00%
01.10.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 103.05 100.00%
01.10.13 PINTURA EN MUROS m2 33.90 7.65 259.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 33.90 259.34 100.00%

01.10.14 CAJA DE VALVULAS DE RESERORIO DE V=2.00 M3 ( 2.00 UND)


01.10.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 2.47 1.25 3.09 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.47 3.09 100.00%
01.10.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.10 14.00 29.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.10 29.40 100.00%
01.10.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 2.62 10.50 27.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.62 27.51 100.00%
01.10.14.04 ENCOFRADO Y DESENCOFRADO m2 17.80 16.95 301.71 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.80 301.71 100.00%
01.10.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 91.70 6.19 567.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 91.70 567.62 100.00%
01.10.14.06 CONCRETO FC=175 KG/CM2 m3 1.40 432.90 606.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.40 606.06 100.00%
01.10.14.07 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO V=2.00 M GLB 2.00 269.17 538.34 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 538.34 100.00%
01.10.14.08 SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO V=2.00 M3 ( GLB 1.00 384.17 384.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 384.17 100.00%
01.10.14.09 SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO V=2.00 M3 ( GLB 1.00 339.52 339.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 339.52 100.00%
01.10.14.10 SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE RESERVORIO V GLB 2.00 407.00 814.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 814.00 100.00%
01.10.14.11 SUMINISTRO DE TAPA METALICA GLB 2.00 155.45 310.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 310.90 100.00%
01.10.14.12 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 10.60 27.79 294.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.60 294.57 100.00%
01.10.14.13 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 11.41 18.00 205.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 11.41 205.38 100.00%
01.10.14.14 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%

01.10.15 TRABAJOS DE PROTECCION DE RESERVORIO 2.00 m3( 2.00 UND)


01.10.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.58 14.00 8.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.58 8.12 100.00%
01.10.15.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 0.75 10.50 7.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.75 7.88 100.00%
01.10.15.03 CONCRETO FC=175 KG/CM2 m3 0.58 432.90 251.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.58 251.08 100.00%
01.10.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 16.00 55.75 892.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 16.00 892.00 100.00%
01.10.15.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 X COCADAS DE m 43.20 90.00 3,888.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 43.20 3,888.00 100.00%
01.10.15.06 PUERTA METALICA S/DISEÑO und 2.00 200.00 400.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 400.00 100.00%

01.10.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO


01.10.16.01 EQUIPO DE CLORACION POR GOTEO (INCLUYE CASETA, TANQUE D und 2.00 3611.24 7,222.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 7,222.48 100.00%

01.11 RESERVORIO DE CONCRETO ARMADO DE V=1.00 M3 (1.00 UND)


01.11.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 4.62 1.25 5.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.62 5.78 100.00%
01.11.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 3.70 14.00 51.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3.70 51.80 100.00%
01.11.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 4.81 10.50 50.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.81 50.51 100.00%
01.11.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 4.62 26.24 121.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.62 121.23 100.00%
01.11.05 CONCRETO FC=210 KG/CM2 m3 2.65 494.88 1,311.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.65 1,311.43 100.00%
01.11.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C-H m2 2.10 26.24 55.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.10 55.10 100.00%
01.11.07 ENCOFRADO Y DESENCOFRADO m2 21.50 16.95 364.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.50 364.43 100.00%
01.11.08 ACERO DE REFUERZO FY=4200 kg 160.62 4.76 764.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.62 764.55 100.00%
01.11.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=1.00M3 GLB 1.00 592.00 592.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 592.00 100.00%
01.11.10 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 10.22 27.79 284.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.22 284.01 100.00%
01.11.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 14.30 18.00 257.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.30 257.40 100.00%
01.11.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 103.05 100.00%
01.11.13 PINTURA EN MUROS m2 14.30 7.65 109.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.30 109.40 100.00%
01.11.14 CAJA DE VALVULAS DE RESERORIO DE V=1.00 M3 ( 1.00 UND)
01.11.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.24 1.55 100.00%
01.11.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.05 14.70 100.00%
01.11.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 1.31 10.50 13.76 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.31 13.76 100.00%
01.11.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.90 150.86 100.00%
01.11.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 45.85 283.81 100.00%
01.11.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.70 303.03 100.00%
01.11.14.07 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERVORIO V=1.00 M GLB 1.00 269.17 269.17 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 269.17 100.00%
01.11.14.08 SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORIO V=1.00 M3 GLB 1.00 339.52 339.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 339.52 100.00%
01.11.14.09 SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOSE RESERVORIO V GLB 1.00 407.00 407.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 407.00 100.00%
01.11.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 155.45 100.00%
01.11.14.11 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 5.30 27.79 147.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.30 147.29 100.00%
01.11.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.71 102.78 100.00%
01.11.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.04 38.56 100.00%

01.11.15 TRABAJOS DE PROTECCION DE RESERVORIO V=1.00 m3( 01 UND)


01.11.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.29 14.00 4.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.29 4.06 100.00%
01.11.15.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 0.37 10.50 3.89 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.37 3.89 100.00%
01.11.15.03 CONCRETO FC=175 KG/CM2 m3 0.29 432.90 125.54 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.29 125.54 100.00%
01.11.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 8.00 55.75 446.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 446.00 100.00%
01.11.15.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 X COCADAS DE m 21.60 90.00 1,944.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 21.60 1,944.00 100.00%
01.11.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 200.00 100.00%

01.11.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO


01.11.16.01 EQUIPO DE CLORACION POR GOTEO (INCLUYE CASETA, TANQUE Y und 1.00 1611.24 1,611.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,611.24 100.00%

01.12 RED DE DISTRIBUCION (5,952.00 ML)


01.12.01 TRABAJOS PRELIMINARES
01.12.01.01 TRAZO NIVELACION Y REPLANTEO DURANTE LA CONSTRUCCION m 5952.00 1.03 6,130.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,952.00 6,130.56 100.00%

01.12.02 MOVIMIENTO DE TIERRAS


01.12.02.01 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 5952.00 4.20 24,998.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,952.00 24,998.40 100.00%
01.12.02.02 REFINE Y NIVELACION DE ZANJAS m 5952.00 1.68 9,999.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,952.00 9,999.36 100.00%
01.12.02.03 CAMA DE APOYO PARA TUBERIAS MENORES DE 6" (e=1") m 5952.00 1.35 8,035.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,952.00 8,035.20 100.00%
01.12.02.04 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 5952.00 6.56 39,045.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,952.00 39,045.12 100.00%

01.12.03 TUBERIAS
01.12.03.01 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 2" NTP IS m 110.00 8.37 920.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 110.00 920.70 100.00%
01.12.03.02 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1 1/2" NT m 283.00 6.32 1,788.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 283.00 1,788.56 100.00%
01.12.03.03 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1" NTP I m 1170.00 5.18 6,060.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,170.00 6,060.60 100.00%
01.12.03.04 SUMINISTRO E INSTALAC.DE TUB. PVC CLASE A-10 DE 3/4" NTP m 1310.00 4.47 5,855.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,310.00 5,855.70 100.00%
01.12.03.05 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 DE 1/2" NTP I m 3079.00 3.83 11,792.57 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,079.00 11,792.57 100.00%

01.12.04 ACCESORIOS
01.12.04.01 SUMINISTRO DE ACCESORIOS RED DE DISTRIBUCION GENERAL GLB 1.00 1512.70 1,512.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,512.70 100.00%
01.12.04.02 INSTALAC. DE ACCESORIOS PROMEDIO und 140.00 2.63 368.20 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 140.00 368.20 100.00%
01.12.05 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION
01.12.05.01 PRUEBA HIDRAULICA+DESINFECCION TUB.< 4" A ZANJA TAPADA m 5952.00 0.83 4,940.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,952.00 4,940.16 100.00%

01.13 CAJA DE VALVULAS DE VALVULAS DE CONTROL +ACCESORIOS (19.00 UND)


01.13.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.38 14.00 33.32 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.38 33.32 100.00%
01.13.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 2.85 10.50 29.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.85 29.93 100.00%
01.13.03 ENCOFRADO Y DESENCOFRADO m2 42.18 16.95 714.95 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 42.18 714.95 100.00%
01.13.04 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 80.43 6.19 497.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 80.43 497.86 100.00%
01.13.05 CONCRETO FC=175 KG/CM2 m3 2.76 432.90 1,194.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.76 1,194.80 100.00%
01.13.06 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 22.80 18.00 410.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.80 410.40 100.00%
01.13.07 PINTURA EN MUROS m2 22.80 7.65 174.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.80 174.42 100.00%
01.13.08 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE CONTROL DE 2" GLB 1.00 350.90 350.90 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 350.90 100.00%
01.13.09 SUMINISTRO DE ACCESORIOS PARA CAJA DE VALVULAS DE CONTROL GLB 2.00 263.90 527.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 527.80 100.00%
01.13.10 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE CONTROL DE 3/ GLB 7.00 212.90 1,490.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.00 1,490.30 100.00%
01.13.11 SUMINISTRO DE ACCESORIOS PARA CAJA DE VALVULA DE CONTROL D und 9.00 200.00 1,800.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 9.00 1,800.00 100.00%

01.14 CAJA DE VALVULAS DE VALVULAS DE PURGA +ACCESORIOS (14.00 UND)


01.14.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.52 14.00 35.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.52 35.28 100.00%
01.14.02 ENCOFRADO Y DESENCOFRADO m2 36.40 16.95 616.98 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 36.40 616.98 100.00%
01.14.03 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 89.25 6.19 552.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 89.25 552.46 100.00%
01.14.04 CONCRETO FC=175 KG/CM2 m3 2.28 432.90 987.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.28 987.01 100.00%
01.14.05 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.16 18.00 362.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.16 362.88 100.00%
01.14.06 PINTURA EN MUROS m2 20.16 7.65 154.22 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.16 154.22 100.00%
01.14.07 SUMINISTRO DE ACCESORIOS PARA VALVULA DE PURGA DE 1/2" und 12.00 200.00 2,400.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.00 2,400.00 100.00%
01.14.08 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE PURGA DE 3/4" GLB 2.00 218.90 437.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 437.80 100.00%
01.15 PASE AEREO L=18.00 ML EN RED DE DISTRIBUCION (1.00 UND)
01.15.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 25.00 1.25 31.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.00 31.25 100.00%
01.15.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.00 14.00 70.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.00 70.00 100.00%
01.15.03 CONCRETO FC=210 KG/CM2 m3 0.35 494.88 173.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.35 173.21 100.00%
01.15.04 CONCRETO FC=175 KG/CM2 m3 1.60 432.90 692.64 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.60 692.64 100.00%
01.15.05 ENCOFRADO Y DESENCOFRADO m2 5.60 16.95 94.92 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5.60 94.92 100.00%
01.15.06 ACERO DE REFUERZO FY=4200 kg 107.99 4.76 514.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 107.99 514.03 100.00%
01.15.07 SUMINISTRO DE CABLE DE 1/4" m 27.05 13.00 351.65 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 27.05 351.65 100.00%
01.15.08 SUMINISTRO DE ACCESORIOS DE CERRAJERIA GLB 1.00 740.40 740.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 740.40 100.00%
01.15.09 SUMINISTRO DE ACCESORIOS SANITARIOS PASE AEREO L=18.00 ML GLB 1.00 272.00 272.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 272.00 100.00%

01.16 PASE AEREO L=6.00 ML EN RED DE DISTRIBUCION (1.00 UND)


01.16.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 8.00 1.25 10.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 8.00 10.00 100.00%
01.16.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.72 14.00 10.08 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.72 10.08 100.00%
01.16.03 CONCRETO FC=175 KG/CM2 m3 0.72 432.90 311.69 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.72 311.69 100.00%
01.16.04 ENCOFRADO Y DESENCOFRADO m2 4.80 16.95 81.36 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.80 81.36 100.00%
01.16.05 SUMINISTRO DE ACCESORIOS SANITARIOSS GLB 1.00 120.80 120.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 120.80 100.00%

01.17 CAJA DE VALVULAS DE PASO DE CONEX. DOMICIL. VALVULA ESFERICA ( 65.00 UND)
01.17.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 6.50 14.00 91.00 5.80 81.20 89.23% 0.00 0.00 0.00% 5.80 81.20 89.23% 0.70 9.80 10.77%
01.17.02 ENCOFRADO Y DESENCOFRADO m2 61.10 16.95 1,035.65 53.58 908.18 87.69% 0.00 0.00 0.00% 53.58 908.18 87.69% 7.52 127.46 12.31%
01.17.03 CONCRETO FC=175 KG/CM2 m3 4.05 432.90 1,753.25 3.49 1,510.82 86.17% 0.00 0.00 0.00% 3.49 1,510.82 86.17% 0.56 242.42 13.83%
01.17.04 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 46.80 18.00 842.40 40.32 725.76 86.15% 0.00 0.00 0.00% 40.32 725.76 86.15% 6.48 116.64 13.85%
01.17.05 PINTURA EN MUROS m2 46.80 7.65 358.02 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 46.80 358.02 100.00%
01.17.06 ACCESORIOS PARA CONEXION DOMICILIARIA 1/2" und 65.00 186.30 12,109.50 58.00 10,805.40 89.23% 0.00 0.00 0.00% 58.00 10,805.40 89.23% 7.00 1,304.10 10.77%

01.18 PILETAS DOMICILIARIAS (65.00 UND)


01.18.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 31.20 1.25 39.00 27.84 34.80 89.23% 0.00 0.00 0.00% 27.84 34.80 89.23% 3.36 4.20 10.77%
01.18.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.95 14.00 27.30 1.95 27.30 100.00% 0.00 0.00 0.00% 1.95 27.30 100.00% 0.00 0.00 0.00%
01.18.03 SUMINISTRO DE ACCESORIOS DE PILETA GLB 65.00 91.45 5,944.25 58.00 5,304.10 89.23% 0.00 0.00 0.00% 58.00 5,304.10 89.23% 7.00 640.15 10.77%
01.18.04 ENCOFRADO Y DESENCOFRADO m2 215.96 16.95 3,660.52 192.89 3,269.49 89.32% 0.00 0.00 0.00% 192.89 3,269.49 89.32% 23.07 391.04 10.68%
01.18.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 307.13 6.19 1,901.13 274.08 1,696.56 89.24% 0.00 0.00 0.00% 274.08 1,696.56 89.24% 33.05 204.58 10.76%
01.18.06 CONCRETO FC=175 KG/CM2 m3 5.66 432.90 2,450.21 5.30 2,294.37 93.64% 0.00 0.00 0.00% 5.30 2,294.37 93.64% 0.36 155.84 6.36%
01.18.07 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 35.10 273.86 9,612.49 18.94 5,186.91 53.96% 0.00 0.00 0.00% 18.94 5,186.91 53.96% 16.16 4,425.58 46.04%
01.18.08 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5CM MEZCLA 1:2 m2 96.36 27.79 2,677.84 86.09 2,392.44 89.34% 0.00 0.00 0.00% 86.09 2,392.44 89.34% 10.27 285.40 10.66%
01.18.09 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 90.35 18.00 1,626.30 80.70 1,452.60 89.32% 0.00 0.00 0.00% 80.70 1,452.60 89.32% 9.65 173.70 10.68%

02 ADECUADA INFRAESTRUCTURA PARA DISPOSICION DE EXCRETAS Y AGUAS SERVIDAS


02.01 LETRINAS DOMICILIARIAS CON BIODIGESTOR (63.00 UND)
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 606.06 1.25 757.58 557.96 697.45 92.06% 0.00 0.00 0.00% 557.96 697.45 92.06% 48.10 60.13 7.94%

02.01.02 MOVIMIENTO DE TIERRAS


02.01.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 85.05 14.00 1,190.70 78.30 1,096.20 92.06% 0.00 0.00 0.00% 78.30 1,096.20 92.06% 6.75 94.50 7.94%
02.01.02.02 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 453.60 4.20 1,905.12 187.20 786.24 41.27% 0.00 0.00 0.00% 187.20 786.24 41.27% 266.40 1,118.88 58.73%
02.01.02.03 RELLENO Y COMPACION MANUAL DE ZANJAS m 453.60 3.44 1,560.38 187.20 643.97 41.27% 0.00 0.00 0.00% 187.20 643.97 41.27% 266.40 916.42 58.73%
02.01.02.04 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 567.00 10.50 5,953.50 97.18 1,020.39 17.14% 0.00 0.00 0.00% 97.18 1,020.39 17.14% 469.82 4,933.11 82.86%

02.01.03 OBRAS DE CONCRETO SIMPLE


02.01.03.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PI m3 85.05 306.43 26,061.87 78.30 23,993.47 92.06% 0.00 0.00 0.00% 78.30 23,993.47 92.06% 6.75 2,068.40 7.94%
02.01.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTOS m2 247.59 27.38 6,779.01 227.94 6,241.00 92.06% 0.00 0.00 0.00% 227.94 6,241.00 92.06% 19.65 538.02 7.94%
02.01.03.03 CONCRETO FC=140 KG/CM2 + 30 % PM EN SOBRECIMIENTOS m3 18.43 366.30 6,750.91 17.04 6,241.75 92.46% 0.00 0.00 0.00% 17.04 6,241.75 92.46% 1.39 509.16 7.54%

02.01.04 OBRAS DE CONCRETO ARMADO


02.01.04.01 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 49.14 27.38 1,345.45 45.24 1,238.67 92.06% 0.00 0.00 0.00% 45.24 1,238.67 92.06% 3.90 106.78 7.94%
02.01.04.02 ACERO DE REFUERZO 3/8" FY=4200 KG/CM2 EN VIGAS kg 190.01 5.67 1,077.36 190.01 1,077.36 100.00% 0.00 0.00 0.00% 190.01 1,077.36 100.00% 0.00 0.00 0.00%
02.01.04.03 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 126.00 6.19 779.94 107.75 666.97 85.52% 0.00 0.00 0.00% 107.75 666.97 85.52% 18.25 112.97 14.48%
02.01.04.04 CONCRETO FC=210 KG/CM2 m3 3.28 494.88 1,623.21 2.43 1,202.56 74.09% 0.00 0.00 0.00% 2.43 1,202.56 74.09% 0.85 420.65 25.91%

02.01.05 ALBAÑILERIA
02.01.05.01 MURO DE BLOQUE HUECO DE CONCRETO 15 X 20 X 40 CM MEZCLA m2 812.39 55.74 45,282.62 747.99 41,692.96 92.07% 0.00 0.00 0.00% 747.99 41,692.96 92.07% 64.40 3,589.66 7.93%

02.01.06 PISOS Y PAVIMENTOS


02.01.06.01 BASE DE PIEDRA m2 152.46 19.79 3,017.18 140.36 2,777.72 92.06% 0.00 0.00 0.00% 140.36 2,777.72 92.06% 12.10 239.46 7.94%
02.01.06.02 PISO DE 2" CONCRETO F'C 140 KG/CM2 X 4 CM.+ PULIDO 1:2 X 1C m2 152.46 28.40 4,329.86 140.36 3,986.22 92.06% 0.00 0.00 0.00% 140.36 3,986.22 92.06% 12.10 343.64 7.94%

02.01.07 REVESTIMIENTOS
02.01.07.01 TARRAJEO INTERIOR Y EXTERIOR CON CEMENTO-ARENA 1:5 m2 1676.56 22.23 37,269.93 1,543.96 34,322.23 92.09% 0.00 0.00 0.00% 1,543.96 34,322.23 92.09% 132.60 2,947.70 7.91%
02.01.07.02 CIELORRASOS CON YESO CON CINTA L=1 CM. m2 328.86 14.96 4,919.75 328.86 4,919.75 100.00% 0.00 0.00 0.00% 328.86 4,919.75 100.00% 0.00 0.00 0.00%
02.01.07.03 m2
02.01.08 COBERTURAS
02.01.08.01 COBERTURA CON TEJA ANDINA m2 388.08 56.56 21,949.80 357.28 20,207.76 92.06% 0.00 0.00 0.00% 357.28 20,207.76 92.06% 30.80 1,742.05 7.94%
02.01.08.02 CORREAS DE MADERA DE 2"X2" p2 771.75 3.28 2,531.34 541.34 1,775.60 70.14% 0.00 0.00 0.00% 541.34 1,775.60 70.14% 230.41 755.74 29.86%
02.01.08.03 VIGUETAS DE MADERA DE 2"X3" p2 909.72 3.30 3,002.08 909.72 3,002.08 100.00% 0.00 0.00 0.00% 909.72 3,002.08 100.00% 0.00 0.00 0.00%

02.01.09 PINTURA
02.01.09.01 PINTURA EN EXTERIORES E INTERIORES m2 1676.56 6.60 11,065.30 718.20 4,740.12 42.84% 0.00 0.00 0.00% 718.20 4,740.12 42.84% 958.36 6,325.18 57.16%

02.01.10 CARPINTERIA DE MADERA


02.01.10.01 PUERTA DE MADERA CORRIENTE P/ LETRINA und 63.00 231.50 14,584.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.00 14,584.50 100.00%
02.01.10.02 VENTANA DE MADERA AGUANO 0.50 X 0.60M und 126.00 61.30 7,723.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 126.00 7,723.80 100.00%

02.01.11 VEREDAS DE CONCRETO


02.01.11.01 ENCOFRADO Y DESENCOFRADO m2 97.02 19.54 1,895.77 97.02 1,895.77 100.00% 0.00 0.00 0.00% 97.02 1,895.77 100.00% 0.00 0.00 0.00%
02.01.11.02 BASE DE PIEDRA m2 245.70 19.79 4,862.40 226.20 4,476.50 92.06% 0.00 0.00 0.00% 226.20 4,476.50 92.06% 19.50 385.91 7.94%
02.01.11.03 CONCRETO FC=175 KG/CM2 m3 245.70 442.49 108,719.79 226.20 100,091.24 92.06% 0.00 0.00 0.00% 226.20 100,091.24 92.06% 19.50 8,628.56 7.94%

02.01.12 INSTALACIONES SANITARIAS


02.01.12.01 ACCESORIOS PARA LETRINAS GLB 63.00 499.10 31,443.30 23.20 11,579.12 36.83% 0.00 0.00 0.00% 23.20 11,579.12 36.83% 39.80 19,864.18 63.17%

02.01.13 INSTALACIONES ELECTRICAS


02.01.13.01 INSTALACIONES ELECTRICAS EN LETRINA GLB 63.00 90.50 5,701.50 28.00 2,534.00 44.44% 0.00 0.00 0.00% 28.00 2,534.00 44.44% 35.00 3,167.50 55.56%

02.01.14 BIODIGESTOR PARA LETRINAS


02.01.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 189.00 1.25 236.25 174.00 217.50 92.06% 0.00 0.00 0.00% 174.00 217.50 92.06% 15.00 18.75 7.94%
02.01.14.02 EXCAVACION DE ZANJAS MANUAL m3 195.30 13.73 2,681.47 124.00 1,702.52 63.49% 0.00 0.00 0.00% 124.00 1,702.52 63.49% 71.30 978.95 36.51%
02.01.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN BUGGIE m3 244.13 10.50 2,563.37 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 244.13 2,563.37 100.00%
02.01.14.04 RELLENO DE POZO DE ABSORCION CON MATERIAL SELECCIONADO m3 63.00 96.60 6,085.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 63.00 6,085.80 100.00%
02.01.14.05 BIODIGESTOR DE 600 LT PARA LETRINA und 63.00 1387.25 87,396.75 32.00 44,392.00 50.79% 0.00 0.00 0.00% 32.00 44,392.00 50.79% 31.00 43,004.75 49.21%
02.01.14.06 CAJA DE VALVULAS PARA EXTRACCION DE LODOS und 63.00 212.49 13,386.87 32.00 6,799.68 50.79% 0.00 0.00 0.00% 32.00 6,799.68 50.79% 31.00 6,587.19 49.21%

02.02 MITIGACION DE IMPACTO AMBIENTAL


02.02.01 LIMPIEZA FINAL DE OBRA GLB 1.00 1503.80 1,503.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 1,503.80 100.00%

02.03 FLETES
02.03.01 FLETE TERRESTRE GLB 1.00 10000.00 10,000.00 0.20 2,000.00 20.00% 0.00 0.00 0.00% 0.20 2,000.00 20.00% 0.80 8,000.00 80.00%
02.03.02 FLETE RURAL GLB 1.00 10000.00 10,000.00 0.30 3,000.00 30.00% 0.00 0.00 0.00% 0.30 3,000.00 30.00% 0.70 7,000.00 70.00%
02.03.03 ACARREO DE MATERIALES A ZONAS SIN ACCESO VEHICULAR GLB 1.00 6120.00 6,120.00 0.30 1,836.00 30.00% 0.00 0.00 0.00% 0.30 1,836.00 30.00% 0.70 4,284.00 70.00%

02.04 PRUEBAS DE LABOTARIO


02.04.01 DISEÑO DE MEZCLA DE CONCRETOS und 5.00 360.00 1,800.00 3.00 1,080.00 60.00% 0.00 0.00 0.00% 3.00 1,080.00 60.00% 2.00 720.00 40.00%
02.04.02 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 20.00 40.00 800.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 20.00 800.00 100.00%

02.05 PLACA RECORDATORIA


02.05.01 PLACA RECORDATORIA DE ALUMINIO DE 0.40 X 0.60M und 1.00 600.00 600.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 600.00 100.00%

03 SERVICIOS
03.01 EN GESTION DEL SERVICIO A LA JASS GLB 1.00 20999.10 20,999.10 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 20,999.10 100.00%

04 MEJOR EDUCACION SANITARIA DE LA POBLACION


04.01 CAMPAÑA DE EDUCACION SANITARIA LOCAL GLB 1.00 4489.08 4,489.08 0.30 1,346.72 30.00% 0.00 0.00 0.00% 0.30 1,346.72 30.00% 0.70 3,142.36 70.00%

COSTO DIRECTO 905,284.70 388,909.32 42.96% 0.00 0.00% 388,909.32 42.96% 516,375.38 57.04%
GASTOS GENERALES (11.48 % ) 103,903.20 44,636.70 0.00 44,636.70 59,266.50
GASTOS DE INSPECCION (6.03 % ) 54,557.22 23,437.72 0.00 23,437.72 31,119.50
GASTOS DE EXPEDIENTE TECNICO (2.43 % ) 22,000.00 9,451.18 0.00 9,451.18 12,548.82
GASTOS DE LIQUIDACION (1.41 % ) 12,774.25 5,487.80 0.00 5,487.80 7,286.45
TOTAL 1,098,519.37 471,922.73 42.96% 0.00 0.00% 471,922.73 42.96% 626,596.65 57.04%
METRADO DIARIOS DE AVANCE DE OBRA PROGRAMADA N° 005
SETIEMBRE 2017.
FUNCIÓN : 18 Saneamiento
CATEGORIA PRESUPUESTAL : 0083 Programa Nacional de Saneamiento Rural
PROYECTO : 2325002 Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco
ACTIVIDAD : 4000041 Instalacion del Sistema de Agua Potable
META : 013 "Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco"
FTE. FTO. : Recursos Determinados
MONTO TOTAL EXP. TEC. : S/. 1,098,519.37
PRESUPUESTO ASIGNADO 2017 : S/. 608,670.00

PPTO VI SA D LU M MI JU VI SA D LU MA MI JU VI SA D LU MA MI JU VI SA D LU MA MI JU VI SA
ITEM DESCRIPCIÓN TOTAL
UND METRA PREC PARCIAL 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 26 29 30

01.01 OBRAS PROVISIONALES


01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.00 X 2. und 1.00 801.21 801.21 0.00
01.01.02 ALMACEN DE OBRA EN AREAS URBANAS mes 6.00 235.00 1,410.00 0.00
01.01.03 CAMPAMENTO DE ROLLIZOS CON TECHO CALAMINA m2 135.00 69.94 9,441.90 0.00

01.02 CAPTACION DE MANANTE (5.00 UND)


01.02.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 9.33 1.25 11.66 0.00
01.02.02 DEMOLICION DE CAPTACION EXISTENTE und 4.00 206.00 824.00 0.00
01.02.03 ZANJA DE INFILTRACION (TUB. PVC CRIBADA, CAPA A m 35.00 121.18 4,241.30 0.00
01.02.04 EXCAVACION MANUAL PARA ESTRUCTURAS m3 13.05 14.00 182.70 0.00
01.02.05 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 16.31 10.50 171.26 0.00
01.02.06 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.08 26.24 185.78 0.00
01.02.07 ENCOFRADO Y DESENCOFRADO m2 65.90 16.95 1,117.01 0.00
01.02.08 ACERO DE REFUERZO 3/8" FY=4200 KG/CM2 kg 289.80 5.67 1,643.17 0.00
01.02.09 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 0.50 273.86 136.93 0.00
01.02.10 CONCRETO FC=175 KG/CM2 m3 6.78 432.90 2,935.06 0.00
01.02.11 FILTRO DE GRAVA (MAT. SELECCIONADO) m3 5.00 133.50 667.50 0.00
01.02.12 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 13.80 27.79 383.50 0.00
01.02.13 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 31.15 18.00 560.70 0.00
01.02.14 PINTURA EN MUROS m2 20.50 7.65 156.83 0.00
01.02.15 ACCESORIOS PARA CAPTACION DE 1" GLB 5.00 485.34 2,426.70 0.00

01.02.16.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.90 14.00 12.60 0.00


01.02.16.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 1.17 10.50 12.29 0.00
01.02.16.03 CONCRETO FC=175 KG/CM2 m3 0.90 432.90 389.61 0.00
01.02.16.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 25.00 55.75 1,393.75 0.00
01.02.16.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 m 54.00 90.00 4,860.00 0.00
01.02.16.06 PUERTA METALICA S/DISEÑO und 5.00 200.00 1,000.00 0.00

01.03 LINEA DE CONDUCCION (3,527.00 ML)


01.03.01 TRABAJOS PRELIMINARES
01.03.01.01 TRAZO NIVELACION Y REPLANTEO DURANTE LA CO m 3527.00 1.03 3,632.81 0.00

01.03.02 MOVIMIENTO DE TIERRAS


01.03.02.01 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 3527.00 4.20 14,813.40 0.00
01.03.02.02 REFINE Y NIVELACION DE ZANJAS m 3527.00 1.68 5,925.36 0.00
01.03.02.03 CAMA DE APOYO PARA TUBERIAS MENORES DE 6" (e m 3527.00 1.35 4,761.45 0.00
01.03.02.04 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 3527.00 6.56 23,137.12 0.00

01.03.03 TUBERIAS
01.03.03.01 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 m 677.00 6.32 4,278.64 0.00
01.03.03.02 SUMINISTRO DE ACCESORIOS L.C 1 1/2" GLB 1.00 240.00 240.00 0.00
01.03.03.03 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A- m 2850.00 5.18 14,763.00 0.00
01.03.03.04 SUMINISTRO DE ACCESORIOS L.C 1" GLB 1.00 350.00 350.00 0.00
01.03.03.05 INSTALAC. DE ACCESORIOS PROMEDIO und 110.00 2.63 289.30 0.00

01.03.04 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION


01.03.04.01 PRUEBA HIDRAULICA+DESINFECCION TUB.< 4" A Z m 3527.00 0.83 2,927.41 0.00
01.04 PASE AEREO L=6.00 ML EN LINEA DE CONDUCCION (2.00 UND)
01.04.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 16.00 1.25 20.00 0.00
01.04.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.44 14.00 20.16 0.00
01.04.03 CONCRETO FC=175 KG/CM2 m3 1.44 432.90 623.38 0.00
01.04.04 ENCOFRADO Y DESENCOFRADO m2 9.60 16.95 162.72 0.00
01.04.05 SUMINISTRO DE ACCESORIOS SANITARIOS GLB 2.00 149.80 299.60 0.00

01.05 CAMARA DE REUNION ( 2.00 UND)


01.05.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 2.32 1.25 2.90 0.00
01.05.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.94 14.00 13.16 0.00
01.05.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 2.36 10.50 24.78 0.00
01.05.04 ENCOFRADO Y DESENCOFRADO m2 10.08 16.95 170.86 0.00
01.05.05 ACERO DE REFUERZO FY=4200 kg 52.82 4.76 251.42 0.00
01.05.06 CONCRETO FC=175 KG/CM2 m3 0.77 432.90 333.33 0.00
01.05.07 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 5.04 27.79 140.06 0.00
01.05.08 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.76 18.00 103.68 0.00
01.05.09 PINTURA EN MUROS m2 6.40 7.65 48.96 0.00
01.05.10 SUMINISTRO DE ACCESORIOS CAMARA DE REUNION GLB 2.00 218.45 436.90 0.00

01.05.11 CAJA DE VALVULAS DE CAMARA DE REUNION (2.00 UND)


01.05.11.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.49 14.00 6.86 0.00
01.05.11.02 ENCOFRADO Y DESENCOFRADO m2 2.24 16.95 37.97 0.00
01.05.11.03 ACERO DE REFUERZO FY=4200 kg 4.65 4.76 22.13 0.00
01.05.11.04 CONCRETO FC=175 KG/CM2 m3 0.18 432.90 77.92 0.00
01.05.11.05 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 0.48 18.00 8.64 0.00
01.05.11.06 PINTURA EN MUROS m2 0.48 7.65 3.67 0.00
01.05.11.07 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DEGLB 1.00 191.45 191.45 0.00
01.05.11.08 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DEGLB 1.00 245.45 245.45 0.00

01.06 CAMARA DE DISTRIBUCION DE CAUDALES (4.00 UND)


01.06.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.60 1.25 9.50 0.00
01.06.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 4.18 14.00 58.52 0.00
01.06.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 4.18 10.50 43.89 0.00
01.06.04 FILTRO DE GRAVA (MAT. SELECCIONADO) m3 0.06 133.50 8.01 0.00
01.06.05 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 0.20 273.86 54.77 0.00
01.06.06 CONCRETO FC=175 KG/CM2 m3 0.21 432.90 90.91 0.00
01.06.07 CONCRETO FC=210 KG/CM2 m3 5.29 494.88 2,617.92 0.00
01.06.08 ENCOFRADO Y DESENCOFRADO m2 51.78 16.95 877.67 0.00
01.06.09 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 58.44 27.79 1,624.05 0.00
01.06.10 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 30.92 18.00 556.56 0.00
01.06.11 PINTURA EN MUROS m2 30.92 7.65 236.54 0.00
01.06.12 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. GLB 1.00 844.00 844.00 0.00
01.06.13 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. GLB 1.00 844.00 844.00 0.00
01.06.14 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. GLB 1.00 844.00 844.00 0.00
01.06.15 SUMINISTRO Y COLOCACION DE ACCESORIOS C.D.C. GLB 1.00 844.00 844.00 0.00

01.07 CAMARA DE FILTRO PARA TRATAMIENTO DE AGUA POTABLE (1.00 UND)


01.07.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.26 1.25 1.58 0.00
01.07.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.76 14.00 10.64 0.00
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 0.95 10.50 9.98 0.00
01.07.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 1.26 26.24 33.06 0.00
01.07.05 ENCOFRADO Y DESENCOFRADO m2 6.00 16.95 101.70 0.00
01.07.06 ACERO DE REFUERZO FY=4200 kg 36.68 4.76 174.60 0.00
01.07.07 CONCRETO FC=175 KG/CM2 m3 0.43 432.90 186.15 0.00
01.07.08 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 2.16 27.79 60.03 0.00
01.07.09 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 3.91 18.00 70.38 0.00
01.07.10 PINTURA EN MUROS m2 3.91 7.65 29.91 0.00
01.07.11 MATERIAL SELECCIONADO PARA FILTRO m3 0.42 133.50 56.07 0.00
01.07.12 SUMINISTRO DE ACCESORIOS CAMARA DE FILTRO GLB 1.00 503.80 503.80 0.00
01.08 RESERVORIO DE CONCRETO ARMADO DE V=5.00 M3 (1.00 UND)
01.08.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.29 1.25 9.11 0.00
01.08.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.83 14.00 81.62 0.00
01.08.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 7.58 10.50 79.59 0.00
01.08.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.29 26.24 191.29 0.00
01.08.05 CONCRETO FC=210 KG/CM2 m3 3.99 494.88 1,974.57 0.00
01.08.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C m2 4.00 26.24 104.96 0.00
01.08.07 ENCOFRADO Y DESENCOFRADO m2 31.58 16.95 535.28 0.00
01.08.08 ACERO DE REFUERZO FY=4200 kg 152.35 4.76 725.19 0.00
01.08.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=5.00 M GLB 1.00 639.00 639.00 0.00
01.08.10 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 16.40 27.79 455.76 0.00
01.08.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.47 18.00 368.46 0.00
01.08.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00
01.08.13 PINTURA EN MUROS m2 20.47 7.65 156.60 0.00

01.08.14 CAJA DE VALVULAS DE RESERORIO DE V=5.00 M3 ( 01 UND)


01.08.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00
01.08.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00
01.08.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 1.31 10.50 13.76 0.00
01.08.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00
01.08.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00
01.08.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00
01.08.14.07 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERV GLB 1.00 321.34 321.34 0.00
01.08.14.08 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERV GLB 1.00 699.52 699.52 0.00
01.08.14.09 SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOS GLB 1.00 439.34 439.34 0.00
01.08.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00
01.08.14.11 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1. m2 3.30 27.79 91.71 0.00
01.08.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00
01.08.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00

01.08.15 TRABAJOS DE PROTECCION DE RESERVORIO V=5.00 M3( 01 UND)


01.08.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.43 14.00 6.02 0.00
01.08.15.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 0.56 10.50 5.88 0.00
01.08.15.03 CONCRETO FC=175 KG/CM2 m3 0.43 432.90 186.15 0.00
01.08.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 12.00 55.75 669.00 0.00
01.08.15.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 m 32.40 90.00 2,916.00 0.00
01.08.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00

01.08.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO


01.08.16.01 EQUIPO DE CLORACION POR GOTEO (INCLUYE CAS und 1.00 3611.24 3,611.24 0.00

01.09 RESERVORIO DE CONCRETO ARMADO DE V=3.00 M3 (1.00 UND)


01.09.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 7.02 1.25 8.78 0.00
01.09.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.62 14.00 78.68 0.00
01.09.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 7.30 10.50 76.65 0.00
01.09.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 7.02 26.24 184.20 0.00
01.09.05 CONCRETO FC=210 KG/CM2 m3 3.96 494.88 1,959.72 0.00
01.09.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C m2 3.80 26.24 99.71 0.00
01.09.07 ENCOFRADO Y DESENCOFRADO m2 31.72 16.95 537.65 0.00
01.09.08 ACERO DE REFUERZO FY=4200 kg 224.80 4.76 1,070.05 0.00
01.09.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=3.00 M GLB 1.00 639.00 639.00 0.00
01.09.10 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 15.89 27.79 441.58 0.00
01.09.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.85 18.00 375.30 0.00
01.09.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00
01.09.13 PINTURA EN MUROS m2 20.85 7.65 159.50 0.00

01.09.14 CAJA DE VALVULAS DE RESERORIO DE V=3.00 M3 ( 01 UND)


01.09.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00
01.09.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00
01.09.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 1.31 10.50 13.76 0.00
01.09.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00
01.09.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00
01.09.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00
01.09.14.07 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERV GLB 1.00 321.34 321.34 0.00
01.09.14.08 SUMINISTRO DE ACCESORIOS DE SALIDA RESERVO GLB 1.00 576.52 576.52 0.00
01.09.14.09 SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOS GLB 1.00 439.34 439.34 0.00
01.09.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00
01.09.14.11 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1. m2 3.30 27.79 91.71 0.00
01.09.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00
01.09.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00
01.09.15 TRABAJOS DE PROTECCION DE RESERVORIO V=5.00 M3( 01 UND)
01.09.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.29 14.00 4.06 0.00
01.09.15.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 0.37 10.50 3.89 0.00
01.09.15.03 CONCRETO FC=175 KG/CM2 m3 0.29 432.90 125.54 0.00
01.09.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 8.00 55.75 446.00 0.00
01.09.15.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 m 21.60 90.00 1,944.00 0.00
01.09.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00

01.09.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO


01.09.16.01 EQUIPO DE CLORACION POR GOTEO (INCLUYE CAS und 1.00 3611.24 3,611.24 0.00

01.10 RESERVORIO DE CONCRETO ARMADO DE V=2.00 M3 (2.00 UND)


01.10.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 10.58 1.25 13.23 0.00
01.10.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 8.46 14.00 118.44 0.00
01.10.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 11.00 10.50 115.50 0.00
01.10.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 10.58 26.24 277.62 0.00
01.10.05 CONCRETO FC=210 KG/CM2 m3 6.25 494.88 3,093.00 0.00
01.10.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C m2 5.12 26.24 134.35 0.00
01.10.07 ENCOFRADO Y DESENCOFRADO m2 51.72 16.95 876.65 0.00
01.10.08 ACERO DE REFUERZO FY=4200 kg 366.92 4.76 1,746.54 0.00
01.10.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=2.00M3 GLB 1.00 592.00 592.00 0.00
01.10.10 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 24.96 27.79 693.64 0.00
01.10.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 33.90 18.00 610.20 0.00
01.10.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00
01.10.13 PINTURA EN MUROS m2 33.90 7.65 259.34 0.00

01.10.14 CAJA DE VALVULAS DE RESERORIO DE V=2.00 M3 ( 2.00 UND)


01.10.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 2.47 1.25 3.09 0.00
01.10.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.10 14.00 29.40 0.00
01.10.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 2.62 10.50 27.51 0.00
01.10.14.04 ENCOFRADO Y DESENCOFRADO m2 17.80 16.95 301.71 0.00
01.10.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 91.70 6.19 567.62 0.00
01.10.14.06 CONCRETO FC=175 KG/CM2 m3 1.40 432.90 606.06 0.00
01.10.14.07 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERV GLB 2.00 269.17 538.34 0.00
01.10.14.08 SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORGLB 1.00 384.17 384.17 0.00
01.10.14.09 SUMINISTRO DE ACCESORIOS DE SALIDA RESERVORGLB 1.00 339.52 339.52 0.00
01.10.14.10 SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOS GLB 2.00 407.00 814.00 0.00
01.10.14.11 SUMINISTRO DE TAPA METALICA GLB 2.00 155.45 310.90 0.00
01.10.14.12 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1. m2 10.60 27.79 294.57 0.00
01.10.14.13 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 11.41 18.00 205.38 0.00
01.10.14.14 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00

01.10.15 TRABAJOS DE PROTECCION DE RESERVORIO 2.00 m3( 2.00 UND)


01.10.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.58 14.00 8.12 0.00
01.10.15.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 0.75 10.50 7.88 0.00
01.10.15.03 CONCRETO FC=175 KG/CM2 m3 0.58 432.90 251.08 0.00
01.10.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 16.00 55.75 892.00 0.00
01.10.15.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 m 43.20 90.00 3,888.00 0.00
01.10.15.06 PUERTA METALICA S/DISEÑO und 2.00 200.00 400.00 0.00

01.10.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO


01.10.16.01 EQUIPO DE CLORACION POR GOTEO (INCLUYE CAS und 2.00 3611.24 7,222.48 0.00

01.11 RESERVORIO DE CONCRETO ARMADO DE V=1.00 M3 (1.00 UND)


01.11.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 4.62 1.25 5.78 0.00
01.11.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 3.70 14.00 51.80 0.00
01.11.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 4.81 10.50 50.51 0.00
01.11.04 SOLADO PARA CIMIENTOS E= 2" MEZCLA 1:12 C-H m2 4.62 26.24 121.23 0.00
01.11.05 CONCRETO FC=210 KG/CM2 m3 2.65 494.88 1,311.43 0.00
01.11.06 CONFORMACION DE PENDIENTE E= 2" MEZCLA 1:12 C m2 2.10 26.24 55.10 0.00
01.11.07 ENCOFRADO Y DESENCOFRADO m2 21.50 16.95 364.43 0.00
01.11.08 ACERO DE REFUERZO FY=4200 kg 160.62 4.76 764.55 0.00
01.11.09 SUMINISTRO DE ACCESORIOS RESERVORIO V=1.00M3 GLB 1.00 592.00 592.00 0.00
01.11.10 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 10.22 27.79 284.01 0.00
01.11.11 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 14.30 18.00 257.40 0.00
01.11.12 PRUEBA HIDRAULICA, LIMPIEZA Y DESINFECCION GLB 1.00 103.05 103.05 0.00
01.11.13 PINTURA EN MUROS m2 14.30 7.65 109.40 0.00
01.11.14 CAJA DE VALVULAS DE RESERORIO DE V=1.00 M3 ( 1.00 UND)
01.11.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 1.24 1.25 1.55 0.00
01.11.14.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.05 14.00 14.70 0.00
01.11.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 1.31 10.50 13.76 0.00
01.11.14.04 ENCOFRADO Y DESENCOFRADO m2 8.90 16.95 150.86 0.00
01.11.14.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 45.85 6.19 283.81 0.00
01.11.14.06 CONCRETO FC=175 KG/CM2 m3 0.70 432.90 303.03 0.00
01.11.14.07 SUMINISTRO DE ACCESORIOS DE ENTRADA RESERV GLB 1.00 269.17 269.17 0.00
01.11.14.08 SUMINISTRO DE ACCESORIOS DE SALIDA RESERVO GLB 1.00 339.52 339.52 0.00
01.11.14.09 SUMINISTRO DE ACCESORIOS DE LIMPIA Y REBOS GLB 1.00 407.00 407.00 0.00
01.11.14.10 SUMINISTRO DE TAPA METALICA GLB 1.00 155.45 155.45 0.00
01.11.14.11 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1. m2 5.30 27.79 147.29 0.00
01.11.14.12 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 5.71 18.00 102.78 0.00
01.11.14.13 PINTURA EN MUROS m2 5.04 7.65 38.56 0.00

01.11.15 TRABAJOS DE PROTECCION DE RESERVORIO V=1.00 m3( 01 UND)


01.11.15.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.29 14.00 4.06 0.00
01.11.15.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 0.37 10.50 3.89 0.00
01.11.15.03 CONCRETO FC=175 KG/CM2 m3 0.29 432.90 125.54 0.00
01.11.15.04 TUBERIA FIE.GALVANIZADO DE 2" X 2.40 DE ALTURA und 8.00 55.75 446.00 0.00
01.11.15.05 MALLA METALICA PROTECTORA CON ALAMBRE N.12 m 21.60 90.00 1,944.00 0.00
01.11.15.06 PUERTA METALICA S/DISEÑO und 1.00 200.00 200.00 0.00

01.11.16 IMPLEMENTACION CON EQUIPO DE CLORACION POR GOTEO


01.11.16.01 EQUIPO DE CLORACION POR GOTEO (INCLUYE CAS und 1.00 1611.24 1,611.24 0.00

01.12 RED DE DISTRIBUCION (5,952.00 ML)


01.12.01 TRABAJOS PRELIMINARES
01.12.01.01 TRAZO NIVELACION Y REPLANTEO DURANTE LA CO m 5952.00 1.03 6,130.56 0.00

01.12.02 MOVIMIENTO DE TIERRAS


01.12.02.01 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 5952.00 4.20 24,998.40 0.00
01.12.02.02 REFINE Y NIVELACION DE ZANJAS m 5952.00 1.68 9,999.36 0.00
01.12.02.03 CAMA DE APOYO PARA TUBERIAS MENORES DE 6" (e m 5952.00 1.35 8,035.20 0.00
01.12.02.04 RELLENO Y COMPACTACION MANUAL DE ZANJAS m 5952.00 6.56 39,045.12 0.00

01.12.03 TUBERIAS
01.12.03.01 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 m 110.00 8.37 920.70 0.00
01.12.03.02 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 m 283.00 6.32 1,788.56 0.00
01.12.03.03 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A- m 1170.00 5.18 6,060.60 0.00
01.12.03.04 SUMINISTRO E INSTALAC.DE TUB. PVC CLASE A-1 m 1310.00 4.47 5,855.70 0.00
01.12.03.05 SUMINISTRO E INSTALAC. DE TUB. PVC CLASE A-10 m 3079.00 3.83 11,792.57 0.00

01.12.04 ACCESORIOS
01.12.04.01 SUMINISTRO DE ACCESORIOS RED DE DISTRIBUC GLB 1.00 1512.70 1,512.70 0.00
01.12.04.02 INSTALAC. DE ACCESORIOS PROMEDIO und 140.00 2.63 368.20 0.00

01.12.05.01 PRUEBA HIDRAULICA+DESINFECCION TUB.< 4" A Z m 5952.00 0.83 4,940.16 0.00

01.13 CAJA DE VALVULAS DE VALVULAS DE CONTROL +ACCESORIOS (19.00 UND)


01.13.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.38 14.00 33.32 0.00
01.13.02 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m EN m3 2.85 10.50 29.93 0.00
01.13.03 ENCOFRADO Y DESENCOFRADO m2 42.18 16.95 714.95 0.00
01.13.04 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 80.43 6.19 497.86 0.00
01.13.05 CONCRETO FC=175 KG/CM2 m3 2.76 432.90 1,194.80 0.00
01.13.06 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 22.80 18.00 410.40 0.00
01.13.07 PINTURA EN MUROS m2 22.80 7.65 174.42 0.00
01.13.08 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE GLB 1.00 350.90 350.90 0.00
01.13.09 SUMINISTRO DE ACCESORIOS PARA CAJA DE VALVULA GLB 2.00 263.90 527.80 0.00
01.13.10 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE GLB 7.00 212.90 1,490.30 0.00
01.13.11 SUMINISTRO DE ACCESORIOS PARA CAJA DE VALVULA und 9.00 200.00 1,800.00 0.00

01.14 CAJA DE VALVULAS DE VALVULAS DE PURGA +ACCESORIOS (14.00 UND)


01.14.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2.52 14.00 35.28 0.00
01.14.02 ENCOFRADO Y DESENCOFRADO m2 36.40 16.95 616.98 0.00
01.14.03 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 89.25 6.19 552.46 0.00
01.14.04 CONCRETO FC=175 KG/CM2 m3 2.28 432.90 987.01 0.00
01.14.05 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 20.16 18.00 362.88 0.00
01.14.06 PINTURA EN MUROS m2 20.16 7.65 154.22 0.00
01.14.07 SUMINISTRO DE ACCESORIOS PARA VALVULA DE PURG und 12.00 200.00 2,400.00 0.00
01.14.08 SUMINISTRO DE ACCESORIOS CAJA DE VALVULAS DE GLB 2.00 218.90 437.80 0.00
01.15 PASE AEREO L=18.00 ML EN RED DE DISTRIBUCION (1.00 UND)
01.15.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 25.00 1.25 31.25 0.00
01.15.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 5.00 14.00 70.00 0.00
01.15.03 CONCRETO FC=210 KG/CM2 m3 0.35 494.88 173.21 0.00
01.15.04 CONCRETO FC=175 KG/CM2 m3 1.60 432.90 692.64 0.00
01.15.05 ENCOFRADO Y DESENCOFRADO m2 5.60 16.95 94.92 0.00
01.15.06 ACERO DE REFUERZO FY=4200 kg 107.99 4.76 514.03 0.00
01.15.07 SUMINISTRO DE CABLE DE 1/4" m 27.05 13.00 351.65 0.00
01.15.08 SUMINISTRO DE ACCESORIOS DE CERRAJERIA GLB 1.00 740.40 740.40 0.00
01.15.09 SUMINISTRO DE ACCESORIOS SANITARIOS PASE AERE GLB 1.00 272.00 272.00 0.00

01.16 PASE AEREO L=6.00 ML EN RED DE DISTRIBUCION (1.00 UND)


01.16.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 8.00 1.25 10.00 0.00
01.16.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.72 14.00 10.08 0.00
01.16.03 CONCRETO FC=175 KG/CM2 m3 0.72 432.90 311.69 0.00
01.16.04 ENCOFRADO Y DESENCOFRADO m2 4.80 16.95 81.36 0.00
01.16.05 SUMINISTRO DE ACCESORIOS SANITARIOSS GLB 1.00 120.80 120.80 0.00

01.17 CAJA DE VALVULAS DE PASO DE CONEX. DOMICIL. VALVULA ESFERICA ( 65.00 UND)
01.17.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 6.50 14.00 91.00 0.00
01.17.02 ENCOFRADO Y DESENCOFRADO m2 61.10 16.95 1,035.65 0.94 0.94
01.17.03 CONCRETO FC=175 KG/CM2 m3 4.05 432.90 1,753.25 0.12 0.12
01.17.04 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 46.80 18.00 842.40 1.44 1.44
01.17.05 PINTURA EN MUROS m2 46.80 7.65 358.02 6.48 5.04 5.04 5.04 5.04 5.04 5.04 5.04 41.76
01.17.06 ACCESORIOS PARA CONEXION DOMICILIARIA 1/2" und 65.00 186.30 12,109.50 0.00

01.18 PILETAS DOMICILIARIAS (65.00 UND)


01.18.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 31.20 1.25 39.00 0.00
01.18.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 1.95 14.00 27.30 0.00
01.18.03 SUMINISTRO DE ACCESORIOS DE PILETA GLB 65.00 91.45 5,944.25 0.00
01.18.04 ENCOFRADO Y DESENCOFRADO m2 215.96 16.95 3,660.52 0.00
01.18.05 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 307.13 6.19 1,901.13 0.00
01.18.06 CONCRETO FC=175 KG/CM2 m3 5.66 432.90 2,450.21 0.00
01.18.07 CONCRETO CICLOPEO FC=140 KG/CM2 MEZCLA 1:10 m3 35.10 273.86 9,612.49 0.00
01.18.08 TARRAJEO INTERIOR C/ IMPERMEABILIZANTE E=1.5C m2 96.36 27.79 2,677.84 0.00
01.18.09 TARRAJEO EXTERIOR E=1.5 CM MEZCLA 1:4 m2 90.35 18.00 1,626.30 0.00

02 ADECUADA INFRAESTRUCTURA PARA DISPOSICION DE EXCRETAS Y AGUAS SERVIDAS


02.01 LETRINAS DOMICILIARIAS CON BIODIGESTOR (63.00 UND)
02.01.01 TRABAJOS PRELIMINARES
02.01.01.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 606.06 1.25 757.58 0.00

02.01.02 MOVIMIENTO DE TIERRAS


02.01.02.01 EXCAVACION MANUAL PARA ESTRUCTURAS m3 85.05 14.00 1,190.70 0.00
02.01.02.02 EXCAVACION EN TIERRA ZANJA DE 0.50 X 0.70 m 453.60 4.20 1,905.12 21.60 21.60 21.60 21.60 21.60 21.60 21.60 21.60 28.80 28.80 230.40
02.01.02.03 RELLENO Y COMPACION MANUAL DE ZANJAS m 453.60 3.44 1,560.38 21.60 21.60 21.60 21.60 21.60 21.60 21.60 21.60 28.80 28.80 230.40
02.01.02.04 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 567.00 10.50 5,953.50 0.00

02.01.03 OBRAS DE CONCRETO SIMPLE


02.01.03.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HO m3 85.05 306.43 26,061.87 0.00
02.01.03.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO m2 247.59 27.38 6,779.01 0.00
02.01.03.03 CONCRETO FC=140 KG/CM2 + 30 % PM EN SOBREC m3 18.43 366.30 6,750.91 0.00

02.01.04 OBRAS DE CONCRETO ARMADO


02.01.04.01 ENCOFRADO Y DESENCOFRADO EN VIGAS m2 49.14 27.38 1,345.45 0.00
02.01.04.02 ACERO DE REFUERZO 3/8" FY=4200 KG/CM2 EN VI kg 190.01 5.67 1,077.36 0.00
02.01.04.03 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 126.00 6.19 779.94 0.00
02.01.04.04 CONCRETO FC=210 KG/CM2 m3 3.28 494.88 1,623.21 0.00

02.01.05 ALBAÑILERIA
02.01.05.01 MURO DE BLOQUE HUECO DE CONCRETO 15 X 20 X m2 812.39 55.74 45,282.62 0.00

02.01.06 PISOS Y PAVIMENTOS


02.01.06.01 BASE DE PIEDRA m2 152.46 19.79 3,017.18 0.00
02.01.06.02 PISO DE 2" CONCRETO F'C 140 KG/CM2 X 4 CM.+ P m2 152.46 28.40 4,329.86 0.00

02.01.07 REVESTIMIENTOS
02.01.07.01 TARRAJEO INTERIOR Y EXTERIOR CON CEMENTO-AR m2 1676.56 22.23 37,269.93 0.00
02.01.07.02 CIELORRASOS CON YESO CON CINTA L=1 CM. m2 328.86 14.96 4,919.75 0.00
02.01.08 COBERTURAS
02.01.08.01 COBERTURA CON TEJA ANDINA m2 388.08 56.56 21,949.80 0.00
02.01.08.02 CORREAS DE MADERA DE 2"X2" p2 771.75 3.28 2,531.34 0.00
02.01.08.03 VIGUETAS DE MADERA DE 2"X3" p2 909.72 3.30 3,002.08 0.00

02.01.09 PINTURA
02.01.09.01 PINTURA EN EXTERIORES E INTERIORES m2 1676.56 6.60 11,065.30 66.50 53.20 53.20 79.80 53.20 53.20 66.50 53.20 53.20 53.20 79.80 39.90 39.90 39.90 39.90 824.60

02.01.10 CARPINTERIA DE MADERA


02.01.10.01 PUERTA DE MADERA CORRIENTE P/ LETRINA und 63.00 231.50 14,584.50 0.00
02.01.10.02 VENTANA DE MADERA AGUANO 0.50 X 0.60M und 126.00 61.30 7,723.80 0.00

02.01.11 VEREDAS DE CONCRETO


02.01.11.01 ENCOFRADO Y DESENCOFRADO m2 97.02 19.54 1,895.77 0.00
02.01.11.02 BASE DE PIEDRA m2 245.70 19.79 4,862.40 0.00
02.01.11.03 CONCRETO FC=175 KG/CM2 m3 245.70 442.49 108,719.79 0.00

02.01.12 INSTALACIONES SANITARIAS


02.01.12.01 ACCESORIOS PARA LETRINAS GLB 63.00 499.10 31,443.30 0.00

02.01.13 INSTALACIONES ELECTRICAS


02.01.13.01 INSTALACIONES ELECTRICAS EN LETRINA GLB 63.00 90.50 5,701.50 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 1.00 29.00

02.01.14 BIODIGESTOR PARA LETRINAS


02.01.14.01 TRAZO NIVELES Y REPLANTEO DE ESTRUCTURAS m2 189.00 1.25 236.25 0.00
02.01.14.02 EXCAVACION DE ZANJAS MANUAL m3 195.30 13.73 2,681.47 18.60 12.40 12.40 12.40 55.80
02.01.14.03 ELIMINACION DE MATERIAL EXCEDENTE D= 30 m m3 244.13 10.50 2,563.37 18.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 12.00 174.00
02.01.14.04 RELLENO DE POZO DE ABSORCION CON MATERIAL m3 63.00 96.60 6,085.80 6.40 4.80 4.80 4.80 3.20 3.20 4.80 4.80 4.80 4.80 46.40
02.01.14.05 BIODIGESTOR DE 600 LT PARA LETRINA und 63.00 1387.25 87,396.75 2.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 26.00
02.01.14.06 CAJA DE VALVULAS PARA EXTRACCION DE LODOS und 63.00 212.49 13,386.87 2.00 3.00 3.00 3.00 3.00 3.00 2.00 1.00 2.00 2.00 2.00 26.00

02.02 MITIGACION DE IMPACTO AMBIENTAL


02.02.01 LIMPIEZA FINAL DE OBRA GLB 1.00 1503.80 1,503.80 0.00

02.03 FLETES
02.03.01 FLETE TERRESTRE GLB 1.00 10000.00 10,000.00 0.00
02.03.02 FLETE RURAL GLB 1.00 10000.00 10,000.00 0.00
02.03.03 ACARREO DE MATERIALES A ZONAS SIN ACCESO VEH GLB 1.00 6120.00 6,120.00 0.00

02.04 PRUEBAS DE LABOTARIO


02.04.01 DISEÑO DE MEZCLA DE CONCRETOS und 5.00 360.00 1,800.00 0.00
02.04.02 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA C und 20.00 40.00 800.00 0.00

02.05 PLACA RECORDATORIA


02.05.01 PLACA RECORDATORIA DE ALUMINIO DE 0.40 X 0.60M und 1.00 600.00 600.00 0.00

MEJOR ORGANIZACION PARA OPERACION, MANTENIMIENTO Y GESTION DE LOS


03
SERVICIOS
ELABORACION DEL PLAN DE CAPACITACION Y PROGRAMA DE CAPACITACION
03.01 GLB 1.00 20999.10 20,999.10 0.00
EN GESTION DEL SERVICIO A LA JASS

04 MEJOR EDUCACION SANITARIA DE LA POBLACION


04.01 CAMPAÑA DE EDUCACION SANITARIA LOCAL GLB 1.00 4489.08 4,489.08 0.00

905,284.70
GASTOS GENERALES (11.48 % ) 103,903.20
GASTOS DE INSPECCION (6.03 % ) 54,557.22
GASTOS DE EXPEDIENTE TECNICO (2.43 % ) 22,000.00
GASTOS DE LIQUIDACION (1.41 % ) 12,774.25
TOTAL 1,098,519.37
VALORIZACIÓN DE AVANCE DE OBRA POR MAYORES METRADOS N° 005

SETIEMBRE 2017.

FUNCIÓN : 18 Saneamiento
CATEGORIA PRESUPUESTAL : 0083 Programa Nacional de Saneamiento Rural
PROYECTO : 2325002 Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco
ACTIVIDAD : 4000041 Instalacion del Sistema de Agua Potable
META : 013 "Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco"
FTE. FTO. : Recursos Determinados

PRESUPUESTO ANTERIOR MES ACUMULADO SALDO


ÍTEM DESCRIPCIÓN
UND METRADO PRECIO PARCIAL METR PARCIAL % METR PARCIAL % METR PARCIAL % METR PARCIAL %

01.18 PILETAS DOMICILIARIAS (65.00 UND)


01.18.02 EXCAVACION MANUAL PARA ESTRUCTURAS m3 0.24 14.00 3.36 0.24 3.36 100.00% 0.00 0.00 0.00% 0.24 3.36 100.00% 0.00 0.00 0.00%

02.01.04 OBRAS DE CONCRETO ARMADO


02.01.04.02 ACERO DE REFUERZO 3/8" FY=4200 KG/CM2 E kg 11.83 5.67 67.08 11.83 67.08 100.00% 0.00 0.00 0.00% 11.83 67.08 100.00% 0.00 0.00 0.00%

02.01.07 REVESTIMIENTOS
02.01.07.02 CIELORRASOS CON YESO CON CINTA L=1 CM. m2 101.50 14.96 1,518.44 101.50 1,518.44 100.00% 0.00 0.00 0.00% 101.50 1,518.44 100.00% 0.00 0.00 0.00%

02.01.08 COBERTURAS
02.01.08.03 VIGUETAS DE MADERA DE 2"X3" p2 366.28 3.30 1,208.72 366.28 1,208.72 100.00% 0.00 0.00 0.00% 366.28 1,208.72 100.00% 0.00 0.00 0.00%

02.01.11 VEREDAS DE CONCRETO


02.01.11.01 ENCOFRADO Y DESENCOFRADO m2 6.22 19.54 121.54 6.22 121.54 100.00% 0.00 0.00 0.00% 6.22 121.54 100.00% 0.00 0.00 0.00%

COSTO DIRECTO 2,919.14 2919.14 100.00% 0.00 0.00% 2,919.14 100.00% 0.00 0.00%
GASTOS GENERALES (11.48 % ) 335.04 335.04 0.00 335.04 0.00
GASTOS DE INSPECCION (6.03 % ) 175.92 175.92 0.00 175.92 0.00
GASTOS DE EXPEDIENTE TECNICO (2.43 % ) 70.94 70.94 0.00 70.94 0.00
GASTOS DE LIQUIDACION (1.41 % ) 41.19 41.19 0.00 41.19 0.00
TOTAL 3,542.23 3,542.23 100.00% 0.00 0.00% 3,542.23 100.00% 0.00 0.00%
VALORIZACIÓN DE AVANCE DE OBRA POR PARTIDA NUEVA N° 003
SETIEMBRE 2017.

FUNCIÓN : 18 Saneamiento
CATEGORIA PRESUPUESTAL : 0083 Programa Nacional de Saneamiento Rural
PROYECTO : 2325002 Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco
ACTIVIDAD : 4000041 Instalacion del Sistema de Agua Potable
META : 013 "Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco"
FTE. FTO. : Recursos Determinados

ANTERIOR MES ACUMULADO SALDO


ITEM DESCRIPCION UND METRADO PRECIO PARCIAL
METR PARCIAL % METR PARCIAL % METR PARCIAL % METR PARCIAL %

02.01.07 REVESTIMIENTOS
02.01.07.0 ENCARRIZADO DE CIELO RAZO m2 403.06 19.87 8,008.80 403.06 8,008.80 100.00% 0.00 0.00 0.00% 403.06 8,008.80 100.00% 0.00 0.00 0.00%

02.01.15 CAJA DE REGISTRO


02.01.15.0 ENCOFRADO Y DESENCOFRADO m2 22.32 14.82 330.78 22.32 330.78 100.00% 0.00 0.00 0.00% 22.32 330.78 100.00% 0.00 0.00 0.00%
02.01.15.0 CONCRETO FC=210 KG/CM2 m3 1.89 469.44 887.24 1.89 887.24 100.00% 0.00 0.00 0.00% 1.89 887.24 100.00% 0.00 0.00 0.00%

02.01.16 TAPAS PARA CAJAS DE REGISTRO


02.01.16.0 ENCOFRADO Y DESENCOFRADO m2 4.77 14.82 70.69 4.77 70.69 100.00% 0.00 0.00 0.00% 4.77 70.69 100.00% 0.00 0.00 0.00%
02.01.16.0 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 36.25 10.81 391.86 36.25 391.86 100.00% 0.00 0.00 0.00% 36.25 391.86 100.00% 0.00 0.00 0.00%
02.01.16.0 CONCRETO FC=210 KG/CM2 m3 0.54 469.44 253.50 0.54 253.50 100.00% 0.00 0.00 0.00% 0.54 253.50 100.00% 0.00 0.00 0.00%

02.01.17 TAPA PARA CAJA DE LODO


02.01.17.0 ENCOFRADO Y DESENCOFRADO m2 7.83 14.82 116.04 7.83 116.04 100.00% 0.00 0.00 0.00% 7.83 116.04 100.00% 0.00 0.00 0.00%
02.01.17.0 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 80.04 10.81 865.23 80.04 865.23 100.00% 0.00 0.00 0.00% 80.04 865.23 100.00% 0.00 0.00 0.00%
02.01.17.0 CONCRETO FC=210 KG/CM2 m3 1.53 469.44 718.24 1.53 718.24 100.00% 0.00 0.00 0.00% 1.53 718.24 100.00% 0.00 0.00 0.00%

COSTO DIRECTO 11,642.39 11,642.39 100.00% 0.00 0.00% 11,642.39 100.00% 0.00
GASTOS GENERALES (11.48 % ) 1,336.24 1,336.24 0.00 1,336.24 0.00
GASTOS DE INSPECCION (6.03 % ) 701.63 701.63 0.00 701.63 0.00
GASTOS DE EXPEDIENTE TECNICO (2.43 % ) 282.93 282.93 0.00 282.93 0.00
GASTOS DE LIQUIDACION (1.41 % ) 164.28 164.28 0.00 164.28 0.00
TOTAL 14,127.48 14,127.48 0.00 14,127.48 0.00
METRADO DIARIOS DE AVANCE DE OBRA POR PARTIDAS NUEVAS N° 003
SETIEMBRE 2017.

FUNCIÓN : 18 Saneamiento
CATEGORIA PRESUPUESTAL : 0083 Programa Nacional de Saneamiento Rural
PROYECTO : 2325002 Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco
ACTIVIDAD : 4000041 Instalacion del Sistema de Agua Potable
META : 013 "Mejoramiento, Ampliacion del Sistema de Agua Potable y Saneamiento en la Comunidad Campesina de Cuyuni, Distrito de Ccatcca - Quispicanchi - Cusco"
FTE. FTO. : Recursos Determinados

PPTO VI SA D LU M MI JU VI SA D LU MA MI JU VI SA D LU MA MI JU VI SA D LU MA MI JU VI SA
ITEM DESCRIPCIÓN TOTAL
UND METRA PREC PARCIAL 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

02.01.07 REVESTIMIENTOS
02.01.07.03 ENCARRIZADO DE CIELO RAZO m2 0.00 19.87 0.00 0.00

02.01.15 CAJA DE REGISTRO


02.01.15.01 ENCOFRADO Y DESENCOFRADO m2 13.64 14.82 202.14 2.48 1.86 1.86 1.86 1.86 1.24 1.24 1.24 13.64
02.01.15.02 CONCRETO FC=210 KG/CM2 m3 1.16 469.44 544.55 0.11 0.16 0.16 0.16 0.16 0.16 0.15 0.11 1.16

02.01.16 TAPAS PARA CAJAS DE REGISTRO


02.01.16.01 ENCOFRADO Y DESENCOFRADO m2 2.90 14.82 42.98 0.92 0.66 0.66 0.66 2.90
02.01.16.02 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 0.00 10.81 0.00 0.00
02.01.16.03 CONCRETO FC=210 KG/CM2 m3 0.31 469.44 145.53 0.10 0.07 0.07 0.07 0.31

02.01.17 TAPA PARA CAJA DE LODO


02.01.17.01 ENCOFRADO Y DESENCOFRADO m2 4.80 14.82 71.14 1.31 1.31 1.31 0.87 4.80
02.01.17.02 ACERO DE REFUERZO 1/4" FY=4200 KG/CM2 kg 0.00 10.81 0.00 0.00 0.00
02.01.17.03 CONCRETO FC=210 KG/CM2 m3 0.68 469.44 319.22 0.17 0.17 0.17 0.17 0.68

COSTO DIRECTO 1,325.55


GASTOS GENERALES (11.48 % ) 152.14
GASTOS DE INSPECCION (6.03 % ) 79.88
GASTOS DE EXPEDIENTE TECNICO (2.43 % ) 32.21
GASTOS DE LIQUIDACION (1.41 % ) 18.70
TOTAL 1,608.50
Folio 11 de 25

VALORIZACIÓN DE DEDUCTIVOS N° 001

DESCRIPCIÓN ANTERIOR MES ACUMULADO SALDO


UND METRADO PRECIO PARCIAL
METR PARCIAL % METR PARCIAL % METR PARCIAL % METR PARCIAL %

COSTO DIRECTO 0.00 0.00 0.00 0.00 0.00


GASTOS GENERALES (12.00 %) 0.00 0.00 0.00 0 0.00
GASTOS DE SUPERVISIÓN (2.50%) 0.00 0.00 0.00 0 0.00
TOTAL 0.00 0.00 0.00 0.00 0.00
Folio 11 de 25

METRADO DIARIOS DE AVANCE DE OBRA POR PARTIDAS NUEVAS N°


MARZO 2006.
Folio 11 de 25

DE OBRA POR PARTIDAS NUEVAS N° 002 ESTRUCTURAS


MARZO 2006.
RESUMEN DE MANIFIESTO DE GASTO CORRESPONDIENTE AL MES DE NOVIEMBRE

FUNCIÓN : 09 EDUCACION Y CULTURA MONTO SNIP : 1´278,801.00


PROGRAMA : 061 INFRAESTRUCTURA EDUCATIVA MONTO EJECUTADO MES #REF!
SUB PROGRAMA : 0174 EDIFICACIONES ESCOLARES SALDO BALANCE 2007 : 964,551.00
PROYECTO : 2042872 MEJORAMIENTO INFRAESTRUCTURA INSTITUCION EDUCATIVA INTEGRADO FECHA REINICIO DE OBRA : 23 DE ENERO 2008
COMPONENTE : 2007389 MEJORAMIENTO DE INFRAESTRUCTURA EDUCATIVA
FINALIDAD : 06587 MEJORAMIENTO DE CENTROS EDUCATIVOS
META : 0126 CONCLUSION I.E. INDEPENDENCIA AMERICANA
FTE. FTO. : CANON Y SOBRECANON

CODIGO ESPECIFICA DE GASTO PROGRAMADO ANTERIOR ACTUAL ACUMULADO SALDO


65.11.10 RETRIBUCIONES COMPLEMENTARIAS 319,227.69 364,324.45 41,666.63 405,991.08 (86,763.39)
65.11.11 OBLIGACIONES DEL EMPLEADOR 34,749.73 41,991.57 4,802.64 46,794.21 (12,044.48)
65.11.13 GASTOS VARIABLES Y OCASIONALES 18,622.14 47,462.70 6,527.76 53,990.46 (35,368.32)
65.11.18 ESCOLARIDAD, AGUINALDOS Y GRATIFICACIONES 9,359.84 9,421.74 - 9,421.74 (61.90)
65.11.20 VIATICOS 4,103.00 607.50 1,824.00 2,431.50 1,671.50
65.11.22 VESTUARIO 735.00 6,183.00 - 6,183.00 (5,448.00)
65.11.23 COMBUSTIBLE Y LUBRICANTES 1,155.00 13,747.20 - 13,747.20 (12,592.20)
65.11.29 MATERIALES DE CONSTRUCCION 665,829.07 586,558.26 13,926.00 600,484.26 65,344.81
65.11.30 MATERIAL DE CONSUMO 18,912.82 49,642.43 2,000.00 51,642.43 (32,729.61)
65.11.39 OTROS SERVICIOS PERSONAS JURIDICAS 165.60 8,450.84 3,000.00 11,450.84 (11,285.24)
65.11.45 MEDICAMENTOS 34.00 1,304.20 - 1,304.20 (1,270.20)
65.11.49 MATERIALES DE ESCRITORIO 1,251.97 937.59 - 937.59 314.38
65.11.51 EQUIPO Y MATERIAL DURADERO 1,750.00 4,697.00 - 4,697.00 (2,947.00)
65.11.53 MATERIALES ELECTRICOS - 46,098.30 3,445.00 49,543.30 (49,543.30)
65.11.78 UTILIDADES - 300.00 - 300.00 (300.00)

TOTAL 1,075,895.86 1,181,726.78 77,192.03 1,258,918.81 (183,022.95)


REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Curado de losa del Bloque II al dia siguiente del vaciado.

Inspeccion de trabajos realizados en losa del Bloque II por el supervor


de obra
Inspeccion de trabajos por el supervisor de obra

REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Inspeccion de trabajos en asentado de muros del 2do Nivel


Bloque II

Encofrado de Columnas en Segundo Nivel del Bloque II


Inspeccion de trabajos en asentado de muros del 2do Nivel
Bloque II

REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Corte de ladrillo para llegar al nivel ,manteniendo las


especificaciones tecnicas y alturas propuestas en planos de obra.

Asentado de ladrillo ,manteniendo las


especificaciones tecnicas y alturas propuestas en planos de obra.
Columnas , columnetas y viguetas de confinamiento vaciadas en
Segundo Nivel Bloque II , siguiendo las especificaciones
tecnicas.
REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Tarrajeo en exteriores del Primer Nivel Bloque I, con mezcla de


cemento arena

Tarrajeo en exteriores del Primer Nivel Bloque I,


con mezcla de Cemento - Arena
Inspeccion de trabajos en tarrajeo de exteriores del Primer Nivel
Bloque I.

REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Encofrado y colocado de fierro en vigas de techo del Bloque I

Encofrado y colocado de fierro en vigas de techo del Bloque I


Encofrado y colocado de fierro en vigas de techo del Bloque I

REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Encfrado de losa aligerada en Bloque III

Tendido de ladrillo pandereta, acero de temperatura e


instalaciones electricas. Inicio de vaciado de vigas en Bloque
III
Inspeccion de trabajos realizados en vaciado de losa en losa
aligerada delBloque III, por el Residente de obra y Supervisor

REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Prueba de slump, y elaboracion de testigos del concreto utilizado


en el vaciado de losa del bloque III

Vaciado de vigas en Segundo Nivel del Bloque III


Vaciado de losa en Segundo Nivel del Bloque III

REPORTE FOTOGRAFICO

Inicio de vaciado de vigas de techo en Ssegundo Nivel Bloque I

Utlizacion de mezcaldora en elaboracion de concreto para el vaciado de


elementos estructurales
Prueba de slump, y elaboracion de testigos del concreto utilizado
en el vaciado de viga s de techo del bloque I

REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Vaciado de vigas de techo del Bloque I con concreto fc' =


210kg/cm2

Encofrado de vigas de techo del 2do Nivel del Bloque I


Vista del encofrado y fierro armado en vigas de techo del bloque I

REPORTE FOTOGRAFICO

CORRESPONDIENTE AL MES DE JULIO 2010

Transporte en buguis del concreto para el vaciado de vigas de


techo en bloque I.

Vaciado de vigas de techo en el 2do nivel


del Bloque I
Vaciado de vigas de techo en el 2do nivel
del Bloque I

8:00 pm fin del vaciado de vigas de techo del Bloque I


Folio 24 de 25

F-13
CUADERNO DE OBRA
GENERALIDADES
a.- La recomendación se base en las Resoluciones de contraloría No 195-88-CG y 072-98-CG y la Directiva de Supervisión de Obras 010-02-MPC
b.- El Cuaderno debe estar legalizado antes del inicio de obra y foliado en todas sus hojas, debiendo ser correlativo los cuadernos siguientes
c.- Se debe aperturar el Cuaderno por el Residente en el primer Asiento de obra, esto por cada cuaderno utilizado.
e.- Se debe transcribir en el cuaderno, el Acta de Entrega de Terreno , Acta de Inicio , Actas de Paralizaciones y Acta de Terminación /Corte de obra.
f.- Se debe evitar enmendaduras , borrones y dejar espacios en blanco excepto para la firma del Residente de Obra a la finalización de
g.- cada asiento
El registro diario.
del cuaderno de obra es de forma diaria desde el inicio y finalización del proyecto, debiendo ser firmado solamente por el Residente de Obra.
h.- A la finalización de cada mes se debe transcribir los metrados ejecutados del mes, diferenciando por partidas programadas, mayores
metrados, partidas nuevas adicionales de ser el caso, para que la inspección de el visto bueno para efectuar la valorización
i.- Se debe solicitar en forma oportuna los adicionales de obra de acuerdo a las normas establecidas en el cuaderno de obra.
j.- A la conclusión de obra se debe registrar la valorización final del proyecto.
k.- La Inspección de Obra registrara de forma correlativa el número de asiento en función del Residente de Obra; solamente efectuará
un Asiento Provisional de Cuaderno por parte de la Inspección en caso de fuerza mayor como lo indica la Directiva de Supervisi

l.- Solamente el Residente de Obra y el Inspector de Obra podrar efectuar registros en el cuaderno de obra.
m.- El cuaderno deberá permanecer en obra en todo momento para ser evaluado por la Inspección de Obra y asentar los registro
correspondientes.
n.- Se adjunta el modelo de registro del Cuaderno de Obra:
MODELO DE REGISTRO DE CUADERNO DE OBRA
"NOMBRE DEL PROYECTO"
Asiento No..... DEL RESIDENTE DE OBRA Fecha: Día, mes y año
1 PERSONAL DE OBRA
-Se debe registrar de forma detallada el personal con su categoría y cantidad, debiendo desagregar en ítem aparte cuando
corresponda a un convenio aporte de beneficiarios esto de forma diaria, el mismo que debe coincidir con su plantilla de reporte
mens
2 ALMACEN DE OBRA
-Se debe registrar de forma detallada el material, con su unidad y cantidad, adjunto con el número de nota de salida /entrada donde
se registro el movimiento.
-Se debe indicar la procedencia del material si es de transferencia, préstamo recibido y/o recibidos de otras obras, aporte beneficiarios, ejemplo:
2.1 INGRESOS 2.1 SALIDA
100 Bls de cemento YURTA (préstamo Obra ......) N/I 3978 50 Blas de cemento YURTA (préstamo Obra ......) N/S 4978
023 m3 de Hormigón de río (Aporte Beneficiario) N/I 3980 13 m3 de Hormigón de río (Aporte Beneficiario) N/S 4980
-El movimiento registrado en el cuaderno de obra debe concordar con lo registrado en los formatos F-67
3 MOVIMIENTO DE MAQUINARIA
-Se debe registrar de forma detallada la maquinaria que se utilizada en obra de forma diaria de acuerdo al modelo siguiente:
Cantidad Equipo HM Combustible Actividad realizada
1 Motoniveladora Cat 120 4.5 10 gl petróleo Perfilado y compactado de base 00+10
-El movimiento registrado en el cuaderno de obra debe concordar con lo registrado en los formatos F-72 y los partes Diarios
-En caso de maquinaria alquilada se debe especificar su procedencia y número de contrato.
4.- MODIFICACIONES DEL PROYECTO
-Se debe indicar claramente las causales de forma detallada por partidas y su incidencia presupuestal debiendo ser de forma
independiente los adicionales de obra por mayores metrados, partias nuevas y deductivos.
-Se debe determinar la necesidad de la ejecución de los Adicionales de obra antes de procedre a solicitar su autorización por la Inspección.
-Toda ejecución de partidas adicionales debe contar con la opinión del proyectista, solicitudes por parte del Residente de Obra, autorización y
conocimiento de la Inspección de Obra y/o entidad debidamente registrado en el cuaderno de obra de estos actos.
-Se debe formular el Expediente Técnico de acuerdo a las Resoluciones de contraloría No 195-88, 072-98,36-01-CG, para su trámite
de aprobación por la entidad, considerando que se debe adjuntar las copias de cuaderno de obra donde se tenga las solicitudes

-Se tiene el siguiente orden del Expediente Técnico de Modificaciones:


1.- Memoria Descriptiva 5.-Hoja de Metrados 10.-Presupuesto Analítico.
2.-Justificación Técnica con copias de 6.-Presupuesto de Obra 11.-Cronograma de Obra
cuaderno de obra 7.-Precios Unitarios 12.-Cronograma de Recursos
3.-Especificaciones Técnicas 8.-Relación de Insumos 13.-Planos.
4.-Memorias de Cálculo 9-Fórmula Polinómica
5.- CONTROL DE CALIDAD
-Se debe registrar las pruebas efectuadas en campo detalladamente con los antecedentes correspondientes indicando la ubicación,
estructura evaluada, comparandola con las normas establecidas, así mismo registrando los resultados obtenidos de acuerdo al fo
6.- AVANCE DE OBRA
-Se debe registrar de forma detallada el avance indicando el nombre de actividad (Partida) con la descripción de sus progresivas,ejes, según sea
el tipo de obra considerando que equipo se utiliza, como el ejemplo siguiente:
" Perfilado y compactado de la sub rasante con rodillo neumático y motoniveladora en la progresiva 00+10 al 00+50 en una
longitud de 400 ml y ancho de 20 ml "
" Vaceado de concreto fc 210 kg/cm2 de muro de sostenimiento de la cimentación con mezcladora y vibradora de la progresiva 00+20 en una longitud
de 5 m, ancho de 1.20 m y espesor de 0.50 m."

7.- METRADOS
-Se debe indicar el tipo de metrado a registrar: Programado, Mayor Metrado y Partidas Nuevas
-Se registrara el código, nombre de la partida, unidad formulada del expediente técnico y el metrado ejecutado del día, como ejemplo,
7.1 PROGRAMADO
04.02.03 Concreto fc 210 kg/cm2 losa 23 m2
7.1 MAYOR METRADO
04.02.03 Perfilado y compactado de sub rasante 450 m2
-Esta información debe ser compatible con lo formulado en el formato F-4 del Informe Mensual y la valorización correspondiente.
8.- OBSERVACIONES Y RECOMENDACIONES
-Se indica los problemas del proceso constructivo, logros, solicitudes, y otros que el Residente de Obra viera por conveniente.
ESTADO SITUACIONAL DE OBRA DICIEMBRE 2009

FUNCIÓN : 09 Educacion y Cultura


PROGRAMA : 061 Infraestructura Educativa
SUB PROGRAMA : 0174 Edificaciones Escolares
PROYECTO :Reposicion Infraestructura I.E. Jose Gabriel Condorcanqui Tupac Amaru ll Yanaoca - Cusco.
COMPONENTE : 2000345 construccion de infraestructura
FINALIDAD : 04415 Construccion De Infraestructura Educativa
META : 0342 Construccion de Dos Bloques En Dos Plantas , Un Bloque De Un Nivel y Refaccion De Un Pabellon Existente.
FTE. FTO. :Canon y Sobrecanon y Regalias.

RESUMEN OCTUBRE 2009

AVANE FISICO 0.00 0.00%


VALORIZADO AL MES DE DICIEMBRE 2007 0.00 0.00%
MOVIMIENTO DE ALMACEN 0 0.00%

AVANCE FINANCIERO 0.00 0.00% 0.00%

RESUMEN OCTUBRE 2009

AVANE FISICO 0 0.00%


VALORIZADO AL MES DE AGOSTO 0 0.00% 0.00%
SALDO DE ALMACEN 0 0.00%
MATERIALES EN TRANSITO 0 0.00%

AVANCE FINANCIERO 0.00 0.00%

FECHA DE CULMINACION DE OBRASEGÚN PROGRAMACION 2/19/2010


FECHA PROBABLE DE CULMINACION DE OBRA 12/12/2010
RETRASO SI
FACTORES QUE INFLUYEN EN EL RETRASO DE OBRA
DESABASTECIMIENTO DE MATERIALES
CASOS FORTUITOS (FACTORES CLIMATICOS DE LA ZONA)

MATERIALES EN PROCESO

AMPLIACION PRESUPUESTAL
MONTO QUE FALTO POR ASIGNAR
AMPLIACION PROPIAMENTE DICHA S/. 0.00