Chapter - TST
CHAPTER - TESTING AND COMMISSIONING (TST)
An indicative list of tests is given below. Contractor shall perform any additional test
based on specialties of the items as per the field Q.P./instructions of the equipment
supplier or Employer without any extra cost to the Employer. The Contractor shall
arrange all instruments required for conducting these tests alongwith calibration
certificates and shall furnish the list of instruments to the Employer for approval.
All pre-commissioning checks as per POWERGRID Doc. No. OS/T&C/Bay/95
(rev. 0) shall be carried out.
2.0 CAPACITORS
(a) Insulation resistance test between terminals and between terminals and
container.
(b) Capacitance measurement of units.
4.0 ISOLATORS
In case of optical CTs, the tests shall be finalized before placement of award.
6.0 MOV
The phasing out of all supplies in the station system shall be carried out.
12.0 INSULATORS
a) Hardware Checks
b) Hardware Interface Tests
c) Digital Input & Output Checks
d) Power Supply Checks
e) Functional Performance Test