Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 1 of 5
Panel/Bay No:GT1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

A. General Data and Information

MAKE Landis+Gyr CT RATIO 2000/1A


MODEL E650 PT RATIO 33/0.120KV
ACCURACY CLASS 0.2S HZ 60 HZ
SERIAL NO. 51301877

B. Function Test

NO FUNCTIONS
1 Physical /Visual Inspection.
2 Electrical check.
3 Metering Minimum Current
4 Current Measurement
5 Voltage Measurement
6 POWER(MW-MVAR) Measurement
7 Accuracy Test
8 Maximum Demand

1. Mechanical Check and Visual Inspection

Item Description Remark


1 Inspect for physical damage and defects. DONE

2 All connection check according to the wiring diagram. DONE

3 Verify tightness for external wiring. DONE

2. Electrical Checks:

Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED
Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 2 of 5
Panel/Bay No:GT1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

Item Description Remark


1 Wiring check as per Ref (approved) Drawing DONE

2 Auxiliary power supply checked for rating and polarity DONE

3 Test Switch checked for correct function DONE

3. Metering

- CREEP TEST

APPLIED VOLTAGE APPLIED CURRENT REMARKS


69.28 0.0 A No Increment In Energy Values
69.28 0.1A Minimum current value.

4- CURRENT MEASUREMENTS:

Current (KA) measurement Current (KA) measurement


3 ph Secondary Expected Actual
Current injected (A)
A B C A B C

0.00 0.00 0.00 0.00 0 0 0

0.25 0.5 0.5 0.5 0.5 0.5 0.5

0.50 1 1 1 1 1 1

1.00 2 2 2 2 2 2

5- Voltage Measurements:

Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED
Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 3 of 5
Panel/Bay No:GT1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

3Ph Phase Voltage (KV) meas. Phase Voltage (KV) meas


Secondary Expected Actual
Voltage applied
(V) PH-N VA VB VC VA VB VC

0.00 0.00 0.00 0.00 0.3 0.3 0.3

34.64 9.5 9.5 9.5 9.5 9.5 9.5

51.96 14.2 14.2 14.2 14.2 14.2 14.2

69.28 19.05 19.05 19.05 19 19 19

6- Power & Energy Measurements:

3 ph
3 Ph Phase Power factor MW meas. MVAR meas.
current
Voltage Angle
injected
applied (V) set @ Exp Actual Exp Actual Exp Actual
(A)

69.28 1.00 0.0 1 0.99 114.312 114.326 0 0

1.00 45 0.707 0.70 80.818 80.855 80.818 80.833


69.28
1.00 90 0 0 0 0 114.312 114.333
69.28
1.00 180 -1 -0.99 -114.312 -114.333 0 0
69.28
1.00 270 0 0 0 0 -114.312 -114.329
69.28
1.00 315 0.707 0.70 80.818 80.826 -80.818 -80.862
69.28

7. Accuracy Test:

Accuracy Test of Meter (Active Energy).


Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED
Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 4 of 5
Panel/Bay No:GT1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

Result Result
IEC 62053-22
Test # Test Description Import Export
Limitations
(Error %) (Error %)
1 10% In, 100%Vn UPF ± 0.2 0.0132 0.0135
2 100% In, 100%Vn UPF ± 0.2 0.0030 0.0004
3 300% In, 100%Vn UPF ± 0.2 -0.0086 0.0278
4 600% In, 100%Vn UPF ± 0.2 0.0694 -0.0112
5 10% In, 100%Vn 0.5Lag ± 0.3 0.0602 0.0770
6 100% In, 100%Vn 0.5Lag ± 0.3 0.0391 0.0516
7 300% In, 100%Vn 0.5Lag ± 0.3 -0.0107 0.0062
8 600% In, 100%Vn 0.5Lag ± 0.3 -0.0562 -0.0155
9 10% In, 100%Vn 0.8Lead ± 0.3 -0.0003 -0.0046
10 100% In, 100%Vn 0.8Lead ± 0.3 0.0025 0.0040
11 300% In, 100%Vn 0.8Lead ± 0.3 0.0401 0.0375
12 600% In, 100%Vn 0.8Lead ± 0.3 0.0401 0.0444

Accuracy Test of Meter (Reactive Energy).

Result Result
IEC 62053-23
Test # Test Description Import Export
Limitations
(Error %) (Error %)
1 10% In, 100%Vn UPF ± 2% 0.0190 0.0204
2 100% In, 100%Vn UPF ± 2% 0.0174 0.0174
3 300% In, 100%Vn UPF ± 2% -0.0086 0.0347
4 600% In, 100%Vn UPF ± 2% 0.0781 -0.0086
5 10% In, 100%Vn 0.5Lag ± 2% 0.0058 0.0096
6 100% In, 100%Vn 0.5Lag ± 2% 0.0025 0.0025
7 300% In, 100%Vn 0.5Lag ± 2% 0.0025 0.0025
8 600% In, 100%Vn 0.5Lag ± 2% 0.0326 0.0401
9 10% In, 100%Vn 0.8Lead ± 2% 0.0577 0.0629
10 100% In, 100%Vn 0.8Lead ± 2% 0.0397 0.0406
11 300% In, 100%Vn 0.8Lead ± 2% 0.0154 0.0154
12 600% In, 100%Vn 0.8Lead ± 2% -0.0105 -0.0105

Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED
Site Acceptance Test Report Date : 28-01-18

Contractor’s Name: SEPCO III Customer: NGSA

Name Of Substation: AL ZULFI 9064-380/132/33KV BSP Contract No: 4400006712


ENERGY METER Page 5 of 5
Panel/Bay No:GT1 Equip. No.: Dwg. Ref.:CA-808637 Record No.:

8.Maximum Demand Test:

Phase
3 Ph Voltage 3 ph current MW meas. MVAR meas.
Angle
applied (V) injected (A)
set @ Exp Actual Exp Actual

69.28 1.00 60 57.156 57.174 98.99 99.013

Test Inst. Used :

EQ: OMICRON CMC 256+ Serial No.: RJ921T


Cal. Due: 10/05/2018

Date :
TESTING ENGINEER SEC- CSD - Engineer

Signature: ___________________ Signature: ________________


Name : A. SALMAN FAREES Name :ENGR.FAYAZ AHMED