NAME: POSITION:
SIGNATURE: DATE:
List plant, List hazardous MSDS available? List PPE to be used (Tick) List hazards to (Tick)
(Tick) consider
equipment and substances to be
tools to be used used or handled
Struck by moving
Inhalation of dust
Cuts
Other (specify):
Death or permanent
1 1 2 3 Using the risk table, rate the identified risks.
disability
List what controls you will implement to reduce the risks to the lowest possible
Long term illness or
1 2 3 4 level.
serious injury
Rate the level of risk once those controls have been implemented (must be 4-6
Medical attention
and several days off 2 3 4 5
before you can start work).
work
List the names or positions of the persons responsible for ensuring that the
controls are implemented.
First aid needed 3 4 5 6
A separate SWMS is required for each work activity
Job Activity What can harm you What can Happen Causes which need to be managed (Controlled). Person who
(Tasks) (Hazards) (Risks) will ensure this
Decide what controls to use to eliminate or minimise the risks. will happen.
Rating (1 – 6)
Break the activity Identify any potential Detail the risks in this column, Detail the controls in this column, and enter the revised risk
rating in the next column. Note: If the risk rating is still 1-3, do
Initial risk
down into steps. List hazards associated with and enter the risk rating in
the steps in this the next column. not begin work.
each step.
column.
General Planning Inadequate training, Task specific injuries due Sufficient skills to complete the required task Sub contractor.
consultation, planning to inexperience, correctly. Adequate consultation with relevant
& improvisation. inadequate consultation employees. Competent person used for scaffold
or failure to provide erection up to 4 metres in height. Qualified
appropriate equipment. scaffolder used to erect scaffold in excess of 4
metres in height or where complex configurations
are involved.
Unstable scaffold due Injury due to scaffold Competent person used for scaffold erection up to 4 Sub contractor.
to lack of competency collapse. metres in height. Qualified scaffolder used to erect
in erection. scaffold where the working platform exceeds 4
metres in height or if the scaffold has cantilevers or
outriggers. Foundation or ground suitable for
scaffold. Different scaffold systems not mixed
together. (Mix & match problems).
Overload of scaffold Collapse causing fall Appropriate type of scaffold used for the job. Light, Sub contractor.
components. from height. medium or heavy duty. Scaffold components not
overloaded beyond the design limits. Different
scaffold systems not mixed together. (Mix & match
problems).
Unstable or incorrect Injury due to scaffold Instructions provided to be clear. Scaffold Supplier, sub
erection of scaffold. collapse or partial maintained in good condition by supplier. Visual contractor &
collapse. checks for defects on every installation & workers onsite.
dismantle. A scaffold inspection every week on
continuous hire.
Planning by Live electricity too close Electric shock or Earth leakage switch installed on mains supply or Head
principal to scaffold erection or electrocution. portable generator. No working on or moving contractor, sub
contractor or completed scaffold is scaffold too close to live power lines. No scaffold contractor &
components or material handled are over 4 workers onsite.
subcontractor. moved too close during
meters in length. No scaffold components or
use. material contacts power lines. Tiger tails
(insulation) not in place on power lines or wet
conditions make them ineffective. Be wary of
strong winds that cause power lines to swing
closer to work area. No scaffold components
being handled striking and shatters unprotected
light bulb.
Erection of base Unsupported frames or Frames or standards falls Sole boards to be correct length for soft ground. Sub contractor
frames, standards standards being over striking person Bracing or team member used to support first & workers
and bracing. erected at ground level. erecting scaffold or frames or standards. Base plates or screw jacks onsite.
other person close to used under all frames and standards. Foundation
the work area. to be level or screw jacks to be used. Castor
wheels locked and fitted correctly.
Erection of 2nd Climbing unbraced Scaffold tips over No climbing unbraced scaffold. Sub contractor
level frames, scaffold during causing fall. 2 persons used to assist in scaffold erection. & workers
standards and erection. Foundation to be level or screw jacks to be used. onsite.
bracing.
Base frames or standards Instability / collapse of Scaffold to be built square with plan bracing installed. Sub contractor
not adequately braced or scaffold causing fall. Sufficient and correctly fixed diagonal bracing. & workers
supported. onsite.
Scaffold exceeds height to Scaffold topples over General height of scaffold not to exceed 3 times the Sub contractor
base ratio. causing a fall from height. base width unless out riggers are used or the scaffold & workers
is tied to a secure structure. onsite.
Erection of working Manual handling. Strains, sprains or injuries 2 persons used to pass materials to higher lifts. Sub contractor
platforms such as back damage. & workers
onsite.
Split (uneven) decks Step backward off higher Working decks to be at same height. Sub contractor
installed. deck causing fall from & workers
height. onsite.
Erection of edge Climbing on the outside Scaffold moves 2 persons to assist in scaffold erection. Sub contractor
protection, ladder of scaffold. unexpectedly or tips over & workers
and toe boards. causing fall. onsite.
Movement of scaffold. Fall from unprotected Scaffold adequately braced to prevent movement Sub contractor
working platform. whilst edge protection is fixed. & workers
onsite.
Edge protection Fall from the edge of the Handrail positioned not below 900mm and above Sub contractor
incomplete. working platform. 1100mm the working platform on all sides. & workers
Mid rail to be installed. onsite.
Ladder access hatch (trap Fall through ladder access Hatch to be closed whilst working on deck Sub contractor
door) in working deck. hatch & workers
onsite.
Inappropriate access to Fall whilst gaining access No climbing up or down the outside of the scaffold. Sub contractor
working deck. to working platform. Ladder access to be installed. Ladder to be positioned & workers
internally for scaffold more than 3 meters in height onsite
and at the appropriate angle 1:4 i.e. for every 4 metres
in height 1 metre out from the base. Ladder to be
secured at the top and bottom. Ladder to project at
least 1 metre above the working platform. Ladder to
access the working platform through a trap door.
MELBOURNE - Prahran scaffolding collapse - February 24th, 2009 CHINA - Guangdong province, Dec. 13, 2004.
MIDDLESBROUGH – Odeon Cinema Wednesday 12th July, 2006 Buckinghamshire - Witan Gate 2006
I the undersigned have read and fully understand the Australian Scaffold Pty Ltd Rubbish Chute Installation SWMS. If at any time I feel
that the SWMS is not being adhered to, or that my safety is being compromised, I will bring it to the attention of Australian Scaffold the
first practical opportunity and will discuss the matter with the intention of finding a solution to the problem. I will at all times abide by
and use this SWMS in carrying out my duties while working at this site. I will help Australian Scaffold Pty and its workers in reviewing
any additions to this SWMS by making constructive suggestions at toolbox meetings or any other site meeting regarding safety.
This work method statement was not intended just to meet O.H&S regulations. Its principal design is to ensure the health and safety of
workers on site. Please use it as intended.
QUALIFICATIONS:
TRAINING: