SCOPE OF WORK
Item Description Quantity Unit Unit Cost Total
Number Amount
PART A FACILITIES FOR
THE ENGINEER
PART OFFICE AND
A.1.1 LABORATORY FOR
THE ENGINEER
A1.1(8) Provision of Field 6.00 Mo. 29,400.00 176,400.00
Office for the
Engineer (Rental
Basis)
PART B OTHER GENERAL
REQUIREMENTS
B.5 Project Billboard/ 3.00 Ea. 5,292.00 15,876.00
Signboard
B.7(2) Occupational Safety 1.00 l.s 134,907.35 134,907.35
and Health Program
B.8(1) Traffic Management 6.00 Mo. 13,608.00 81,648.00
B.9 Mobilization/ 1.00 l.s 189,756.00 189,756.00
Demobilization
B.12 Removal and 1.00 l.s 277,200.00 277,200.00
Relocation of Utilities
B.15(1) Detour 1.00 l.s 1,577.375.0 1,577.375.00
0
PART C EARTHWORK
101(1) Removal of Structures 1.00 l.s 278,360.00 278,360.00
and Obstruction
101(3)b6 Removal of Actual 240.70 Sq.m 141.80 34,131.26
Structures/
Obstruction (0.30m.
thick PCCP
Unreinforced)
103(1)a Structure Excavation 128.50 Cu. 227.30 29,208.05
(Common Soil) m
103(5)b Shoring, Cribbing and 1.00 l.s 133,567.00 133.567.00
Related Works
(Cribbing
/Cofferdamming)
104(2)a Embankment from 447.00 Cu. 795.45 355,566.15
borrow (Common m
Soil)
104(7) Embankment from 90.00 Cu. 95.15 8,563.50
structure excavation m
PART D SUBBASE AND
BASE COURSE
200(1) Aggregate Subbase 44.30 Cu. 725.80 32,152.94
Course m
PART E SURFACE
COURSES
311(1)c1 PCC Pavement 125.30 Sq.m 1,450.00 181,685.00
(Unreinforced) 0.23m
thick, 14 days
311(2)f1 PCC Pavement 59.00 Sq.m 5,387.00 317,833.00
(Reinforced) 0.30m
thick, 14 days
400(17)c Concrete Piles cast in 140.00 m. 35,485.42 4,967,958.80
Drilled Holes (1.00m)
400(23)c Permanent Casing 24.00 m. 23,205.00 556,920.00
1 (1.00m, 10mm thick)
400(26)b Pile Integrity Testing 2.00 Ea. 44,100.00 88,200.00
(Low Strain)
400(27) High Strain Dynamic 2.00 Ea. 243,886.00 487,772.00
Testing (P.D.A)
401(2)a Concrete Railing 24.00 m. 5,749.00 137,976.00
(Standard, Double)
PART F BRIDGE
CONSTRUCTION
404(1)a Reinforcing Steel 2381.00 Kg. 75.35 179,408.35
Grade 40
404(1)b Reinforcing Steel 26,962.00 Kg. 76.20 2,056,028.40
Grade 60
405(1)b3 Structural Concrete 150.00 Cu. 10,890.95 1,633,642.50
(27.58 Mpa, Class A) m
411(2) Paint 351.70 Sq.m 103.45 36,383.36
FOR ABUTMENT
CONCRETE SLOPE
PROTECTION
404(1)a Reinforcing Steel 306.90 Kg. 76.20 23,385.78
Grade 40
405(1)b3 Structural Concrete 5.20 Cu. 7,845.00 40,794.00
(20.68 Mpa, Class A) m
509(1)b1 Sheet Piles (U-Type) 504.00 l.m 3,912.00 1,971,774.00
510(2) Concrete Slope 57.40 Cu. 10,472.35 601,112.89
Protection m
PART G DRAINAGE AND
SLOPE
PROTECTION
STRUCTURES
404(1)a Reinforcing Steel 790.20 Kg. 76.20 60,213.24
Grade 40
405(1)a3 Structural Concrete 13.40 Cu. 7,845.00 105,123.00
(20.68 Mpa, Class A) m
509(1)b1 Sheet Piles (U-Type) 1,320.00 l.m 3,791.30 5,003,516.00
510(2) Concrete Slope 143.70 Cu. 10,383.70 1,492,137.69
Protection m
PART H MISCELLANEOUS
STRUCTURE
612(1) Reflectorized 4.30 Sq.m 931.15 4,003.94
Thermoplastic
Pavement Markings
(White)
612(2) Reflectorized 3.20 Sq.m 1,068.75 3,420.00
Thermoplastic
Pavement Markings
(Yellow)
GRAND TOTAL 23,275,000.00
Very Satisfactory 5
Satisfactory 4
Fair 3
Poor 2
Very Poor 1