Sunteți pe pagina 1din 16

Bayla v. Silang Traffic Co. Aerospace Chemical Industries v.

Court of
G.R. 48195 & 48196 | May 1, 1942 | Oblicon | Appeals
Case 1 | Delay G.R 108129 | Sept 23, 1999 | Oblicon | Case 2 |
Facts Delay
 circumstances of the Facts
obligation it shall appear that  June 27, 1986 – Petitioner purchased sulfuric
the designation of the time at acid from Private Respondent which was made
which the thing was to be in a letter form stating the said agreement
delivered or service rendered between the two parties.
was the principal inducement
o The said agreement was set to begin in
to the creation of the
July 1986 which provides that the
obligation.
Petitioner shall pay its purchases in
equivalent of Philippine Currency five
days prior to the shipment date.
Petitioner is also committed to secure
the means of transport of the said
items from the port of private
respondent located in Basay, Negros
and Sangi, Cebu
 Aug 6, 1986 – Private Respondent sent a letter
to petitioner withdrawing the sulfuric acid at
Basay because Private Respondent had been
incurring expense of 2,000 pesos per day for
each day of delay in shipment.
 Oct 3, 1986 – Petitioner paid 553,280 for the
500 tons of sulfuric acid which it ordered.
 Nov. 19, 1986 – Petitioner chartered a ship, the
ship was assigned to carry the volume of the
sulfuric acid to the loading-port of Private
Respondent from Basay. However, the ship
withdrew only 70 metric tons of the said item
because the ship tilted while carrying the said
cargo
o The ship then underwent repairs.
 Dec 12, 1986 – Private Respondent demanded
petitioner through a letter to retrieve the
remaining acid in the Basay Tanks so that it
can be emptied on or before Dec 15, 1986
Respondent states that it would charge
petitioner the storage and costs for the Basay
tanks including all other expenses due to
loading delay if petitioner fails to comply.
 Dec 15, 1986 – the ship chartered by petitioner
docked in Cebu but withdrew only 157 tons of
the sulfuric acid. The vessel tilted again, and
loading was aborted.
o After the said incident, the chartered
Ship M/T Sultan Kayumanggi sank with
227.51 Metric tons of sulfuric acid on
board.
 Petitioner then chartered another vessel with a
bigger capacity. Then on the dates of Jan 26
and Mar 20, 1987. Melecio Hernandez acting
for the petitioner, addressed letters to private
respondent concerning additional orders of
sulfuric acid to replace its sunken purchases.
With no reply, Petitioner sent another letter on
May 15, 1987.
 January 25, 1988 – Petitioner’s Counsel sent a  The Prescriptive period to
demand letter to private respondent for the institute action upon written
delivery of sulfuric acid paid by his client or the contract was interrupted by the
return of the purchase price of 307,530 pesos. issuance of an injunctive write.

o Private Respondent replied on March 8,  In this case, the court ruled that the appellants
could not have prospered in any suit to compel
1988 and instructed petitioner to lift
performance or payment from the appellees-
the remaining 30 MT of sulfuric acid
buyers, because appellants were in no position to
from Basay or pay maintenance and
perform their own corresponding obligation to
storage expenses commencing August deliver to and maintain said buyers in possession
1, 1986. of the lots.
 July 6, 1988 – Petitioner wrote another letter o A party unable to comply with own
insisting on picking up the 272.49 MT and an obligations under a contract cannot
additional 227.51 MT of acid as Petitioner demand rescission thereof. The right to
already paid a chartered vessel for the full rescind a contract can be demanded only
capacity. Debtor delays performance if a party thereto is ready, willing and
able to comply with his own obligations.
o Creditor requires the performance
( Art. 1191 NCC)
judicially or extrajudicially.
 IN a contract of sale, the vendor is bound to
Binalbagan Tech Inc v. Court of Appeals
transfer the ownership of and deliver as well as
G.R 100594 | Mar. 10, 1993 | Oblicon | Case 3 | Kinds warrant the thing which is the object of the sale.
of Delay
o Additionally, from the years 1974 to
Facts 1982, Private Respondent’s warranty
 May 11, 1967 – Private Respondents through a against eviction given to buyer Petitioner
certain Angelina Echaus in her capacity as was breached though it was not her fault.
administrator of the intestate of Mr. Puetevella Thus, on the period of 1974 to 1982,
private respondent was not in a legal
 nd damages. position to demand compliance of the
RTC Decision prestation of petitioner to pay the price of
said subdivision rights. Her right to
 The RTC declared that the case had not fraud and
demand payment was suspended during
on top of that, the action on the written contract
1974 to 1982.
had already long prescribed, judgment is
rendered in favor of the defendants and against  Lastly, the Court cited the principle against unjust
the plaintiffs, dismissing the complaint. enrichment where a situation of unjust
enrichment would result if petitioner is allowed to
o The counterclaim filed was also dismissed
own the lots without full payment.
for lack of proof.
Court of Appeals Ruling
 The Court of Appeals reversed the decision of the
RTC. A new one was made ordering the Petitioner
through any of its officers execute a deed of
conveyance transferring and returning the
Agcaoili v. GSIS
ownership of the lands to Private Respondent.
Issue G.R L-30056 |Aug. 30, 1988 | Oblicon | Case 4 |
Delay
 Whether or not Respondent’s cause of action is
barred by prescription. Facts

Ruling  Defendant approved the application of Plaintiff


for the purchase a house and lot in the GSIS
 The Court denies the Petition and affirms
Housing Project at Nangka subject to the
the Decision of the Court of Appeals.
condition that the house be occupied by
 For the first issue, the court ruled that the Plaintiff. However, Plaintiff failed to fulfill this
prescriptive period to institute an action upon a condition as according to him, the house was
written contract is 10 years. IN this case, the deed uninhabitable.
of sale whereby Private Respondent transferred
the ownership of the lots was executed on May  After paying the first installment and other fees
1967, she then filed the case on Oct. 1982 which and also refusing to make further payment of
is 15 years. the other stipulated installments until
o However, the Court ruled that the period Defendant had made the house habitable as
from 1974 to 1982 should be deducted in according to him, the house was nothing more
computing the period because Private than a shell and that civilized occupation was
Respondent was not in a legal position to not possible, due to this, Plaintiff asked a
initiate action against petitioner. homeless
 but found it so uninhabitable that he had to o The said contract also stipulated
leave it the following day, however, he left a amounts to be paid and maturity dates
friend to live there who is homeless even if the in the following dates:
house is rudimentary who only agreed because
of his homelessness.  Mar. 31, 1981 – 2.200,000

 June 30, 1981 – 3,209,968.75

 Balance of 11,500,000.00 to be
paid by means of an
assumption by Private
Respondent of Petitioner’s
mortgage liability to the
Philippine Savings Bank or to
be made in cash.

 On the same date above, the parties executed


a supplemental agreement providing that
Private Respondent would pay to petitioner
amounts of 55,364.68 on the balance of down
payment for the period from Mar 31 to June 30,
1981.

 While the agreement was made, Private


Respondent was only able to pay Petitioner the
sum of 1,334,443.21. Meanwhile the parties
continued to negotiate for a possible
modification of their agreement although
nothing conclusive happened.

 Oct. 12, 1981 – Petitioner through its legal


counsel sent Private Respondent a notice of
cancellation of contract sent a notice of
cancellation of contract on account of Private
Respondent’s failure to pay the installment due
on June 30, 1981. However, Petitioner advised
Private respondent that it still had the right to
pay its arrearages within 30 days or the actual
cancellation of the contract would take place.

 Sept 26, 1983 – Private Respondent through


counsel demanded the refund of their various
payments made to Petitioner which amounts to
2,455,497.71 with interest or in lieu of a cash
payment assigned to them an equivalent
number of unencumbered lots at the same
price fixed in the contracts. Petitioner did not
heed the demand; hence, Private Respondent
started an action with the Court.

Bricktown Development Corp. v. Amor Tierra RTC Ruling


Dev’t Corp.
G.R 112182 | Dec 12, 1994 | Oblicon | Case 5 |  The trial Court rescinded the supplemental
Delay agreement of the two parties and ordering
Facts Petitioner to return the amount of 1,334,443.21
with interest and to pay attorney’s fees and
 Mar. 31, 1981 – Petitioner represented by its dismissing petitioner’s counterclaim for lack of
President and co-petitioner Velarde executed merit.
two contracts to sell in favor of Private
Court of Appeals Ruling
Respondent who was represented by its Vice-
President, the said contract covers 96  The Court of Appeals affirmed the trial court’s
residential lots situated at a subdivision located findings and judgment.
in Manila.
Issue
 Whether or not the contracts to sell were would be unconscionable to sanction the
rescinded or cancelled validly by Petitioner forfeiture by petitioner of payments made to it
by private respondent.
 Whether or not the amounts remitted by
Private Respondent were rightly forfeited by  Lastly, the relationship between parties in any
Petitioner Corporation contract must always be characterized and
punctuated by good faith and fair dealing. In
Ruling this case, petitioners fell from the said
standard of good faith and fair dealing. As it
 The appealed decision is affirmed insofar as it
was not equitable for petitioners to adjudge
declared valid the cancellation of the contracts
any interest payment on the amount to be
in question but modified by ordering the refund
refunded.
by Petitioner of 1,334,443.21 with interest to
commence from the finality of the decision.

 While the terms of the payment agreed upon


by the parties of the contract were not met by
Private Respondent, the fact that private
respondent was only able to remit the sum of
1,334,443.21 which was short of the initial
payment of 2,200,000.00, no additional
payments were made, and a notice of
Enriquez v. Ramos
cancellation was ultimately made after the
G.R L-23616 | Sept 30, 1976 | Oblicon | Case 6 |
lapse of the contracted grace period.
Delay
 The Court in this case defined Grace Period. Facts

o According to the Court, a grace period  Nov. 24, 1958 – Plaintiffs sold to defendant 20
is a right, not an obligation of the subdivision lots for a sum of 235,036 of which
debtor. When unconditionally conferred only 35,056 had been paid by defendants. The
such as in this case, the grace period is said balance of 200,000 was to be liquidated
effective without further need of within two years from the date of the execution
demand either calling for the payment of the deed of sale with interest until fully paid.
of the obligation or for honoring the
o To secure the payment of the said
right.
balance, defendant executed a deed of
o The grace period must not be likened mortgage in favor of the vendors’
to an obligation, the non-payment of seven parcels of land.
which under Art. 1169 of the Civil Code
 The deed of mortgage has
would still require judicial or
certain stipulations which
extrajudicial demand before default
states that if the mortgagor
can arise.
should fail to pay the amount
 In the case at bar, the 60-day secured by the mortgage or
grace period in the contract any part of the terms and
became ipso-facto operative conditions, the mortgagee shall
from the moment the due have the right to foreclose the
payments were not met at their mortgage extrajudicially where
stated maturities. Thus, Art. mortgagee is appointed as the
1169 of the Civil Code would attorney-in-fact of the
not apply in this case. mortgagor with full power of
substitution to enter and take
 Furthermore, the cancellation of the contracts possession of the properties
to sell by Petitioner accord with the contractual without order of any court or
covenants of the parties, thus the cancellation any authority other than what
must be respected. is granted.

o In a contract to sell, the non-payment  In this second case, the plaintiffs state that in
of the purchase price can prevent the pursuance to their agreement made in the first
obligation to convey title from case of L-18077 the defendants violated the
acquiring any obligatory force. terms of their agreement in the following
aspects:
 While the court concludes that Petitioner acted
within its legal right to declare the contracts to o Defendant refused to pay the sum of
sell rescinded, the peculiar circumstances 200,000 within the stipulated period
found in this case and confirmed by the C.A, it
o The mortgage on the property in o The effect of the demand retroacts to
Bulacan was not registered the day of the constitution of
defendant’s obligation. It is provided in
o The realty tax for the lots mortgaged Art 1187 that the effects of a
were not paid by defendant. conditional obligation to give, once the
condition has been fulfilled shall
 While defendant admits that she has not paid
retroact to the day of the constitution
the realty taxes and has not registered the
of the obligation.
mortgage on the property, defendant argues
that the said matters were only minor ones  In this instant case, the
which was explained by her in the first case contracted obligation of
invoking the rule of res judicata. appellee was to pay the
balance of 200,000 within two
o In addition to this, defendant does not
years from the date of the
dispute that she did not pay the sum of
roads in question are
200,000. However, she contends that
completed.
the roads have not yet been completed
in accordance with the ordinance of
Quezon City which states that there
should be water facilities and tree
plantings in the subdivision which
according to defendant are not yet in
the roads, thus, the roads are not yet
completed.

Issue

 Whether or not Ramos should pay her balance


to Enriquez and spouses Dizon even though
she is not yet fully satisfied with her demand?

Ruling

 The court order dated December 3, 1963 is set


aside and judgment is hereby rendered
ordering the defendant-appellee to pay
plaintiffs the sum of 200,000, interest, and
amount equivalent to 5% of the mortgage
indebtedness of attorney’s fees and the costs.

 The Court ruled that the deed of sale with


mortgage makes it the express duty of the
defendant to pay the realty taxes on the
mortgaged lots, to register the mortgaged lots
and to contribute 50,000 for the construction of
the roads. In its express terms, the appellee
failed to fulfill the conditions of her entire
obligation which means that the mortgagee
has the option to foreclose the mortgage. The
terms of the contract have the force of law
between the parties.

 The court ruled that the opinions of the


Supreme Court cannot be taken as license for Leaño v. Court of Appeals
continued non-fulfillment of defendant of her G.R. 129018 | Nov. 15, 2001 | Oblicon | Case 7 |
contractual obligations. The court did not Delay
intend to allow or enable the litigants to use Facts
the first decision as an instrument to avoid the  Nov. 13, 1985 – Hermogenes Fernando, as
obligations of the parties. vendor, and Petitioner Leaño, as vendee
executed a contract to sell involving a piece of
 Lastly, the court states that the filing of the
land in Bulacan.
case is sufficient notice to defendant f the
completion of the roads in question and of the o In the said contract, Petitioner bound
appellant’s desire to be paid the purchase price herself to pay Fernando the sum of
of the questioned lots. 107,750.00 pesos as the total purchase
price of the lot. According to the
contract, the sum of 10,775 shall be defendant and to pay attorney’s fees and the
paid at the signing of the contract as costs of the suit.
down payment. The remaining balance
o A motion for reconsideration was filed
shall be paid within a period of 10
by Respondent. However, the court
years at a monthly amortization of
increased the amount to be paid by
1,747.30 starting from Dec. 7, 1985.
Petitioner to 183,687 and ordered
 IN addition to this, the contract provided for a petitioner to pay attorney’s fees.
grace period of one month within which to
o The trial court reasoned out that the
make payments, together with the one
transaction between the parties was an
corresponding to the month of grace.
absolute sale, making petitioner the
o Should the grace period expire without owner of the lot upon actual and
installments for both months having constructive delivery thereof.
been satisfied an interest of 18% per Respondent was divested of his
annum shall be charged on the unpaid ownership and cannot recover unless
installments. the contract is rescinded in pursuance
to Art. 1592 of the Civil Code which
o Additionally, should a period of 90 days
requires a judicial or notarial
elapse from the expiration of the grace
demand.
period without the overdue and unpaid
installments been paid. Respondent o For the issue of delay, the trial
Fernando, as vendor is authorized to court ruled that the contract
declare the contract cancelled and to clearly specifies that the purchase
dispose the parcel of land as if the price shall be payable in monthly
contract had not been entered to, the installments for which the
payments shall be considered as rents corresponding penalty shall be
for the use and occupation of the imposed in case of default.
premises. Plaintiff’s failure to pay the
amortization is a clear default on
 After the execution of the contract, Petitioner
Plaintiff’s part therefore she
made payments in lump sum. She then built a
should be liable for interests and
house on the lot valued 800,000. The last
penalties.
payment according to the facts of the case was
on April 1, 1989. Court of Appeals ruling
o Due to her non-payment of the  The Court of Appeals affirmed the decision of
subsequent payments, Respondent the RTC.
filed a case for ejectment against Issue
Petitioner to vacate the premises.
 Whether the transaction between the parties is
MTC Ruling (Ejectment Case by Respondent)
an absolute sale or a conditional sale
 The trial court ordered Petitioner to vacate the
 Whether or not there was a proper cancellation
premises and to pay 250.00 per month by way
of the contract to sell
of compensation for the use and occupation of
the property from May 27, 1991 until she  Whether petitioner was in delay in the payment
vacates the premises of the property. A writ of of the amortizations.
execution was issued on August 24, 1993 Ruling
which was served to Petitioner.
 The Court denies the Petition and affirms
o IN response to this, Petitioner filed a
the decision of the Court of Appeals
specific performance complaint against
Respondent on Sept. 27, 1993 and to  The Court ruled that even if the contract
assail the decision of the court as the provided that the total purchase price is
order was violative to the intentions of payable within a ten-year period, specifying the
R.A 6552 which afford buyers of lots on price shall be paid in monthly installments for
installments protection. which the corresponding penalty shall be
imposed in case of default, the vendee cannot
RTC Ruling (Specific Performance Case by
ignore the provision on the payment of
Petitioner)
monthly installments by stating that the 10
 The preliminary injunction issued by the RTC is year period has not elapsed.
made permanent. Furthermore, the plaintiff is
 In reciprocal obligations, neither party incurs in
ordered to pay the defendant the sum of
delay if the other does not comply or is not
103,090.70 corresponding to her outstanding
ready to comply in a proper manner with what
obligations under the contract to sell with
is incumbent upon him, but from the moment
one of the parties fulfills his obligation, delay services ordered, the sales for such
by the other begins (Art 1169) vehicles, parts or services shall be at
the option of Motorcars Inc. refund o
o In this case, Respondent performed his
the deposits shall be made upon
part of the obligation by allowing
request and without undue delay
Petitioner to continue in possession
should the option be exercised.
and use of the property. Petitioner did
not pay the monthly amortizations in  Due to the said stipulation in the said order,
accordance with their contract, thus Respondent Company offered to refund the
she was in delay and liable for deposit of 1,000 made by Petitioner. However,
damages. it was revealed that the sales order contains:
 Lastly, it is a cardinal rule in the interpretation o Order is not valid unless signed and
of contracts that if the terms are clear and accepted by the dealer principal,
leave no doubt upon the intention of the President, Executive Vice President or
contracting parties, the literal meaning of its General Sales Manager of the
stipulations shall control. If there is no dealership.
ambiguity in the language, there is no room for
RTC Ruling
construction only compliance.
 The Trial Court rendered a judgment in favor of
Respondent by ordering Petitioner to pay 5,000
as damages and attorney’s fees.
Court of Appeals Ruling
 The Court of Appeals reversed the decision of
the RTC stating that there was a perfected
contract of sale, and that there was the
undisputed signature of Mr. Tapas, the branch
manager of Motorcars.
o Respondent was ordered to deliver to
Petitioner the vehicle upon payment of
149,7000 and the amount of 8,833 for
Lee v. De Guzman miscellaneous expenses and other
G.R 90926 | Jul 6, 1990 | Oblicon | Case 8 | Delay charges. Respondent then appealed to
the Supreme Court in another case.
Facts
G.R 77992 (Related Case; Case filed by
 Nov. 8, 1983 – Freelance salesman of Respondent)
Respondent Motorcars Inc named Arsemio
Tumibay signed in half of the branch manager  The Court in the said case ruled that there was
of Respondent Company a price quotation and indeed a contract of sale between the parties.
delivered to Petitioner one Toyota Corolla, Thus, it denied the petition and affirmed the
1983 with the price of 149,7000 plus decision of the Court of Appeals, furthermore,
miscellaneous expenses of 10,033. after the case was remanded, Petitioner filed a
motion for writ of execution.
o Petitioner then signed the sales order
of the vehicle. Delivery was then  However, Respondent company filed a motion
scheduled to be within the Nov. 1983. to quash the said writ of execution stating that
the obligation has become impossible to
 Nov. 10, 1983 – Petitioner made a deposit of comply on the ground that Delta Motors had
1,000 which was required in the agreed price closed shop.
quotation. After depositing the said amount,
petitioner then wrote that Motorcars had o Petitioner opposed the motion of
acknowledgment receipt of the delivery receipt Respondent, but Respondent continued
for petitioner. to defy the order of the court.
Petitioner then filed a motion for
 Dec 15, 1983 – Petitioner’s counsel wrote to contempt of court for the stance that
the Executive Vice-president of Motorcars what Respondent did was contempt.
demanding for the delivery of the said Toyota
Car. Respondent Company replied that due to o Respondent trial court then issued the
the sudden change of prices by the assailed order where it favored
manufacturer of the car, they decided to respondent company’s contention that
exercise the option in the vehicles order which they cannot comply with the
states: obligations.

o Whenever deposits are made by Issue


customers for vehicles, parts and
 Whether or not the decision rendered by the Tanguilig v. Court of Appeals
C.A and affirmed by the S.C is capable of G.R. 117190 | Jan 2, 1997 | Oblicon | Case 9 |
performance and can be executed. Delay
Ruling Facts
 Respondent is ordered to give petitioner
the sum of 100,000 as damages.  April 1987 – Petitioner under the name of JMT
Engineering and General Merchandising
 The Court agrees with the contention that proposed to Respondent Herce to construct a
Respondent could not comply with the writ of windmill system for him. The parties
execution as Delta Motors who manufactured negotiated and agreed on the construction of
the 19883 models of the Liftback had already the windmill for 60,000 pesos with a one-year
closed shop. However, there is no question that guaranty from the date of completion and
there was a perfected contract between acceptance by Respondent Herce
Petitioner and Respondent. o In pursuance to the agreement,
o The relief that Petitioner left can do is respondent paid Petitioner 30,000 as
provided under Art. 1170 of the Civil downpayment and installment
Code where those who in the payment of 15,000 leaving a balance of
performance of their obligations are 15,000.
guilty of fraud, negligence or delay,  March 14, 1988 – Respondent refused to pay
and those who in any manner the balance. This prompted Petitioner to file a
contravene the tenor thereof, are liable complaint to collect the amount.
for damages.
Private Respondent’s Arguments
 In this case, there was delay in the delivery of
the subject vehicle which was stated in the  For his reply, Respondent denies the claim
letter of Respondent Company addressed to made by Petitioner. According to Private
Petitioner by stating the sudden change of Respondent, he already paid the said balance
prices by the car manufacturer as what was to San Pedro General Merchandising which
agreed upon by the parties is the delivery of made the deep well connected to the windmill
the subject vehicle within November 1983. system.
o Since the said deep well is a part of th
e system, the payment he gave to
SPGMI should be credited to his
account by petitioner. The balance he
owes to Petitioner should be offset by
the defects in the windmill which
caused its collapse after strong winds.

Petitioner’s Reply

 Petitioner denies that the construction of the


deep well was included in the agreement to
build the windmill system. According to
Petitioner the price of 60,000 was solely for the
windmill assembly and its installation,
exclusive of other incidental materials needed
for the project.
 Furthermore, petitioner disowns any obligation
to repair or rebuild the system as he delivered
the said windmill in good and working condition
to respondent. According to Petitioner, the
collapse was attributable to a typhoon, a force
majeure which relieves him from any liability.

RTC Ruling

 The Trial Court held that the deep well was not
part of the windmill. This is evidenced by the
proposals submitted by Petitioner to
Respondent. Due to the absence of the
agreement regarding the construction of the
deep well, the trial court concluded that it was
not part of the project of Petitioner.
o The Court adds that Plaintiff is not SPGMI has been established regarding the
liable for the collapse of the windmill as deep well.
it was not proven that the system fell o Proprietor also states that he entered
down because of defect. into a contract with petitioner for the
construction of deep well.
Court of Appeals Ruling  Art 1174
o For the second issue, the Court ruled
 Court of Appeals reversed the trial court ruling. that in order for a party to claim
Stating that the deep well was included in the exemption by reason of fortuitous
agreement of the parties because the term was event under 1174 of the Civil Code.
mentioned in the two proposals. Furthermore, The event should be the sole and
testimony of respondent who is the proprietor proximate cause of the loss or
of SPGMI, the company which installed the destruction of the object of the
deep well stated that Petitioner told him that contract.
the cost of the deep well would be deducted
 4 Requisites of Fortuitous Event
from the contract price of 60,000.
o Cause of breach must be independent
 Due to this, the Court of Appeals ruled that the
of the will of debtor
payment of 15,000 to SPGMI should be applied
o Event must be unforeseeable or
to his remaining balance.
unavoidable
 Furthermore, the Court of Appeals rejects the o Event must render the debtor to fulfill
claim of force majeure, ordering Petitioner to
his obligation in a normal manner
rebuild the windmill in accordance with the one
o Debtor must be free from any
year guarantee.
participation in or aggravation to the
Issue creditor.
 Art 1167
 Whether or not the payment of 15,000 for the o Petitioner’s argument that Respondent
deep well should be included in the 60,000 for was already in default, hence, he
the windmill assembly. should bear his own loss is untenable.
 Whether or not Petitioner is obligated to rebuild This is because in reciprocal
the said windmill obligations, neither party incurs in
delay if the other does not comply or is
Ruling not ready to comply.
o When the windmill failed to function,
 The Court modifies the decision ordering Petitioner is supposed to repair it in
Respondent to pay Petitioner the balance accordance with the guaranty. As
of 15,000 with interest at the legal rate. provided in Article 1167, that if a
Petitioner is ordered to reconstruct the person is obliged to do something and
windmill subject to the one-year guaranty fails to do it, the same shall be
and to complete the reconstruction within executed at his cost.
3 months.
 The Court took notice that the proposal made
by Petitioner does not mention the installation
of a deep well, even remotely. Vernen Realty v. Court of Appeals
o In addition to this, in the itemization or G.R 101762 | Jul 6, 1993 | Oblicon | Case 10 |
description of the materials to be used. Delay
There is no mention of the two Facts
documents  Mar. 2, 1981 – Petitioner and Private
o While there is a mention of deep well Respondent entered into a contract called an
and deep well pump, they do not offsetting agreement. The said contract
indicate that the said object is part of stipulates the different payments and the
the windmill. AS the description only agreement regarding the delivery of
describes that the pump is suitable for construction materials for the purposes of the
the proposed windmill. condominium units that are being built by
 Furthermore, it is a rule in the interpretation of Petitioner.
contracts that the intention of then parties
shall be accorded primordial consideration and o Private Respondent had paid Petitioner
in case of doubt, their contemporaneous and the amount of 110,151.75 and at the
subsequent acts shall be considered. same time, delivered construction
 The Court ruled that payments made by a third materials worth 219,727. Pending the
person does not apply as there is no creditor – completion of the Phase 2 of the
debtor relationship between Petitioner and Condominiums, Petitioner delivered to
Private Respondent Units 601 and 602
of the Phase 1 of the Condominiums.
 1982 – Petitioner repossessed unit 602, as a Agreement prayed by Private Respondent
consequence of the repossession, Private when he instituted the case before the RTC.
Respondent had to rent another unit for their Ruling
use when they went to Baguio.
 The Court denies the petition for lack of
 May 10, 1982 – Officers of Private Respondent merit, costs against petitioner.
requested for clarification of the petitioner’s
action of preventing them and their families  In this case, the court ruled that after a perusal
from occupying condominium unit 602. of the offsetting agreement, it is not a question
that the said agreement is reciprocal in nature.
o Petitioner replied that the room was
leased to another tenant because o Reciprocal obligations are those
Private Respondent had not paid created or established at the same
anything for purchase of the time, out of the same cause and which
condominium unit. results in a mutual relationship of
creditor and debtor between parties.
o Petitioner then demanded payment of
27,848.25 representing the balance of  In this type of obligation, the
the purchase price of Room 601. performance of one is
conditioned on the
 1983 – the loan application for the construction simultaneous fulfillment of the
of the Phase 2 of the condominiums was other obligation.
denied which resulted into the stoppage of the
construction of the condominium project.  Article 1191 of the Civil Code provides the
remedy of a rescission in case of reciprocal
 June 21, 1985 – Private Respondent field a obligations where one of the obligors fail to
complaint with the RTC for rescission of the comply with what is incumbent upon him.
Offsetting Agreement with damages. Private
Respondent alleges that petitioner had stopped  The general rule is that rescission of a contract
issuing purchase orders of construction will not be permitted for a slight or casual
materials after April 1982 without valid reason breach, but only for such substantial and
which violated the offsetting agreement fundamental breach as would defeat the very
between the two parties. object of the parties in executing the
agreement.
o For its reply, Petitioner alleges that it
was private respondent who could not o However, the question of whether a
deliver the supplies stated in their breach of contract is substantial
agreement according to Petitioner, depends upon the attendant
Respondent stated that the supplies circumstances of the case.
were out of stock. Furthermore,  In this case, while petitioner argues that it was
Respondent had given a higher price private respondent who failed to perform the
quote for the materials which resulted obligation in the agreement. It averred that
to Petitioner seeking other suppliers. contrary to the C. A’s ruling, the stoppage of
For the issue of unit 602, petitioner the loan for the phase 2 of the condominiums
states that his was done because should not have any effect on the obligations in
private respondent had not paid the Offsetting agreement.
anything for it.
o On the other hand, private respondent
 Dec. 16, 1986 – Private Respondent had paid states that the subject of the offsetting
110,151.75 in cash and made deliveries of agreement is phase 2 of the
construction materials worth 219,727 leaving a condominiums, which means that since
balance of 27,848.25 which represents the the construction of the phase 2 of the
purchase price of unit 601. condominiums failed to start, Private
RTC Decision Respondent had reason to rescind the
contract as it cannot wait forever for
 The trial court dismissed the complaint and the delivery of the condominium units.
ordered Private Respondent to pay Petitioner
its counterclaim the balance due on the  The Court ruled in this case that Private
purchase price of unit 601. Respondent did not fail to fulfill its obligation in
the offsetting agreement. The discontinuance
Court of Appeals Decision
of the delivery of construction materials was
 The Court of Appeals reversed the trial court’s rooted on the failure of petitioner to send
decision. purchase orders to private respondent.
Issue o In this case, Petitioner failed to produce
the purchase orders of Petitioner with
 Whether or not the circumstance of the case
Private Respondent, however,
warrants a rescission of the Offsetting
Petitioner failed to produce the same to  Apr. 27, 1990 – Parties failed to reach an
the Court. agreement, thus, Private Respondents field a
complaint for specific performance with
 The non-fulfillment of the obligation of
damages against Petitioners before the RTC.
Petitioner constitutes a substantial breach of
the offsetting agreement. Since the o According to Petitioners, their father
construction of the Phase 2 of the conveyed to them that he had no
condominiums has stopped, it is impossible to interest to exercise the option because
fulfill the obligation, thus, Private Respondent of insufficiency of funds, they were
was correct to rescind the contract. surprised to learn of private
respondent’s demand, thus, they
requested that private respondent pay
the purchase price in full, but they
refused, and the amount deposited by
Respondent was insufficient.
Furthermore, what was presented by
Private Respondent was a bank
Heirs of Luis Bacus v. Court of Appeals certificate which is not legal tender
G.R 127695 | Dec. 3, 2001 | Oblicon | Case 11 | Delay
 Oct 30, 1990 – Private Repsondents manifested
Facts
in court that they caused the issuance of a
 Jun. 1, 1984 – Luis Bacus leased to Private cashier’s check in 650,000 payables to
Repsondent Duray a parcel of agricultural land petitioners at any time upon demand.
in Talisay Cebu. The said lease was for 6 years RTC Ruling
which ended on May 31, 1990. In the said
contract, an option to buy clause was provided.  RTC Ruled in favor of Private Respondents,
finding that defendants should perform their
o Under the said option to buy, the
obligation in the option to buy and to execute a
lessee had the exclusive and document of sale over the property in issue.
irrevocable right to buy 2,000 square
miles of the property within 5 years C.A Ruling
from a year after the effectivity of the
contract at 200 / sqm. Rate shall be  The Court of Appeals denied the appeal of
also adjusted in proportion to the petitioners on the ground that private
exchange rate of Peso and USD. respondents exercised their option to buy the
leased the property before the expiration of the
 Oct. 10, 1989 – Luis Bacus died. contract of lease.

 Mar 15, 1990 – The Duray spouses informed Issue


one of the heirs of Luis Bacus that they were
willing and ready to purchase the property  Whether or not Private Respondents incurred
under the option to buy the clause. Thus, they delay when they did not deliver the purchase
requested that the heir prepare the necessary price or consign it on or before the expiry of
documents such as a Special Power of Attorney contract.
authorizing him to enter into a contract of sale
Ruling
on behalf of his sisters.
 The Court denies the petition and affirms the
 Mar 30, 1990 – Petitioners refused to sell the
C.A Ruling
property, due to this, Private Respondent had
an adverse claim annotated by the Register of  The Court ruled that obligations under an
Deeds of Cebu. option to buy are reciprocal obligations.
Performance of one obligation is conditioned
 Apr 5, 1990 – Duray filed a complaint for
on the simultaneous fulfillment of the other
specific performance against Petitioners with
obligation; notice of the creditor’s decision to
the Lupon Tagapamayapa, asking that he be
exercise his option to buy need not be coupled
allowed to purchase the lot specifically referred
with actual payment of the price, so long as
to in the lease contract with option to buy.
this is delivered to the owner of the property
o Private Respondent presented a upon performance of his part of the
certification from a bank stating that agreement. Where the obligation is not yet
arrangements were being made to due, consignation in court of the purchase
allow Mr. Duray to borrow funds of price is not yet required.
700,000 to be able to meet his
o In this case, when private respondents
obligations under the contract with Luis
opted to buy the property, their
Bacus
obligation was to advise petitioners of deliver and sell at its own price any
their decision and their readiness to number or volume of its products
pay the price. They were not yet exclusively to Petitioner. Petitioner, in
obliged to make actual payment. Only turn would exclusively sell and
upon petitioners’ actual execution and distribute the products to the open
delivery of the deed were they required market, whole sale or retail at a price
to pay. set by Private Respondent.

 Consignation  The said agreement, however, was terminated


unilaterally by Private Respondent causing
o Act of depositing the thing due with the damages to Petitioner.
court or judicial authorities whenever
the creditor cannot accept or refuses to o Private Respondent replied by denying
accept payment and it generally that the exclusive distributorship with
requires a prior tender of payment. Petitioner. Private Respondent alleges
that Petitioner is indebted to them as
 Furthermore, in reciprocal obligations, neither of Sept. 30, 1965 a sum of 320,220.25
party incurs in delay if the other does not plus interest representing the unpaid
comply or is not ready to comply in a proper purchase price of Private Respondent’s
manner with what is incumbent upon him. products.
o In this case, private respondents did  The drift of the companies started when on
not incur in delay when they did not February 17, 1962, a majority of the members
yet deliver payment nor make a of the board of directors of Petitioner company
consignation before the expiration of approved an amendment to its articles of
the contract. incorporation thereby authorizing the said
corporation to engage in the merchandizing
business as one of its secondary purposes and
also increasing the product types it could
manufacture.

o The said amendment was approved,


and a written contract was made
regarding the exclusive distributorship
for two years starting Nov 16, 1962
over two products made by Private
Respondent

RTC Ruling

 The trial court ruled in favor of petitioner. The


trial court considered the amount Petitioner
owed to Private Respondent which represented
the unpaid purchase price of Private
Respondent sold and delivered to petitioner
and that the damages due to Petitioner was
fixed in 189,908.76, the court ordered
Petitioner to pay 14,946.74 with interest.

Court of Appeals Ruling


Pacmac v. IAC
 The Court of Appeals ordered Petitioner to pay
G.R. L-72405 | May 29, 1987 | Oblicon | Case 1 | Respondent 304,855 with legal interest as the
Contravention of Tenor of Obligations said amount was agreed between the parties
Facts during the pre-trial proceedings which was the
balance due to the defendant from plaintiff.
 The controversy of the case started in a civil
Issue
case wherein Petitioner alleged that by virtue
of an existing contract and arrangement with  What is the actual business relationship
Respondent, since 1953 to Aug. 3, 1965 has between Petitioner and Private Respondent on
been the exclusive distributor of the latter’s Aug 3, 1965 when the deliveries stopped?
products.
Ruling
o In the said arrangement, Private
Respondent was obliged to periodically
 The Court grants the petition and the
questioned decision of the IAC is reversed and
set aside. Trial Court’s decision is reinstated.

 The Court ruled that the IAC erred when it


failed to consider the evidence proving that the
exclusive contract of distributorship between
the parties went beyond the expiration of the
two year written contract between the parties.
Llorente Jr. v. Sandiganbayan
 The records establish that after the termination G.R 122166 | Mar 11, 1998 | Oblicon | Case 2 |
of the two-year written contract, the parties Contravention of Tenor of Obligations
agreed on another term regarding the Facts
distributorship arrangement would remain in  The case is about Petitioner, who is the mayor of
full force until one year from and after notice of Sindangan, Zamboanga Del Norte was charged
its termination would have given to Petitioner. with violating Section 3 (e) of R.A 3019 or the
Anti-Graft and Corrupt Practices Act, wherein he
 The parties’ contract of exclusive refused to sign and approve payrolls and
distributorship arrangement was still in vouchers representing the payments of the
existence on Aug 13, 19654 when Private salaries and emoluments of an employee without
Respondent decided to stop its deliveries of its valid cause and due process of law causing injury
products to Petitioner, Private Respondents to the employee.
unilateral act of terminating the contract
 The case had two versions of its antecedent facts:
without legal justification makes it liable for
damages suffered by Petitioner in pursuance to Prosecution’s Version
Art 1170 of the Civil Code.  According to the Prosecution, the controversy
started when the Petitioner, presiding over the
Sangguniang Bayan passed a resolution which he
vehemently objecting to the assignment of the
complainant or employee as the Assistant
Municipal Treasurer of Singan.
 After this, Petitioner received a letter from the SB
demanding from the private complainant return of
the amount overpaid to her as salaries.
 After the said demand, a petition was filed against
the accused mayor before the RTC for Petitioner’s
unjustified refusal to sign and or approve her
payrolls and vouchers representing her salaries
and other emoluments.
 Later on, Petitioner did not file an answer but
instead, he negotiated for an amicable settlement
of the case. Then on August 27, 1991, Petitioner
and Complainant executed a compromise
agreement which states that Petitioner binds
himself to sign all vouchers and payrolls and other
emoluments and that the parties renounce their
claims against each other.
o While the said compromise agreement
was signed by the parties, Private
complainant states that she was only able
to receive her payments on January 1993,
in checks dated Dec. 29, 1992. Her other
emoluments were also delayed.
Petitioner’s Version
 While Petitioner admits that there were delays in
the payment of the claims of complainant,
Petitioner sought to prove that the delay was in
good faith because according to Petitioner,
Private Complainant failed to submit the money
and property clearance to the SB’s delayed
enactment of a supplemental budget to cover
Private Complainant’s claims.
Sandiganbayan’s Ruling o actual damages are primarily intended to
simply make good or replace the loss
 The Sandiganbayan held that the delay or
caused by the wrong. Furthermore,
withholding of Complainant’s salaries and
damages must not only be capable of
emoluments was unreasonable and caused undue
proof but must be actually proven with
injury to Private Complainant as being the sole
reasonable certainty or upon speculation,
breadwinner of the family, the withholding of her
conjecture or guesswork it cannot include
salaries resulted in difficulties in meeting her
any speculative damages, which are too
family’s financial obligations.
remote in an accurate estimate of the
o According to the Sandiganbayan, the injury.
defense of Petitioner that complainant
 In this case, the court ruled that after an
failed to attach the clearance was held to
employee, whose salary was withheld fully
be an afterthought that was brought
received her monetary claims, there is no longer
about by his own failure to issue any
any basis for compensatory damages or undue
memorandum requiring its submission.
injury, there being nothing more the compensate.
o Furthermore, the Sandiganbayan ruled
 Undue injury entails damages that are more than
that the Petitioner’s bad faith was the
necessary or are excessive or illegal.
direct and proximate cause of Fuertes’
undue injury. Complainant’s salaries and o In this case, the prosecution failed to
allowances were withheld for no valid or prove any other loss or damage sustained
justifiable reason. The delay of Petitioner by complainant, while it is noted that
was intended to harass complainant complainant suffered from the
because Petitioner wanted to replace withholding of her salary and
Complainant with his political protégé. emoluments, the inconvenience is not
Furthermore, bad faith was further constitutive of undue injury.
evidenced by the instruction of Petitioner
 The Court does not agree that the imputed act
to the outgoing treasurer not to give
does not fall under Sec. 3 (e) as according to
complaining witnesses any work
Petitioner it requires a positive act. The Court
assignment, not to provide her with office
clarified that causing means to be the cause or
table and chair and not to act on her DTR.
occasion of, causing does not limit itself to
Issue positive acts, it can be passive acts or inaction
which cause undue injury. What is essential is that
 Whether or not petitioner acted in bad faith in
the injury is quantifiable and demonstrable.
refusing to sign the vouchers and implement the
compromise agreement until the SB had enacted
the appropriation ordinance.
Ruling
 Petition is GRANTED, Petitioner is Acquitted of violating
Sec 3 (e) of R.A 3019
 In this case, the court ruled that unlike in action
for torts, undue injury in Section 3 (e) cannot be
presumed even after a wrong or a violation of a
right has been established – its existence must be
proven as one of the elements of the crim, and FGU Insurance v. G.P Sarmiento Trucking
that the undue injury be specified, quantified and G.R 141910 | Aug 6, 2002 | Oblicon | Case 3 |
proven to the point of moral certainty.
Contravention of Tenor of Obligations
o The causing of undue injury or giving of
any unwarranted benefits through Facts
manifest partiality, evident bad faith or  June 18, 1994 – Respondent undertook to deliver
gross inexcusable negligence constitutes 30 units of Condura S.D. white refrigerators
the very act punished under the section. aboard one of its Isuzu trucks, driven by Mr.
Eroles from the plant site of Concepcion Industries
 Undue injury definition
in Manila to Dagupan City.
o The invasion of any legally protected o While the truck was traversing the
interest of another. In this context. Undue highway, it collided with an unidentified
injury can also be defined as actual truck causing it to fall into a deep canal
damage. resulting in damage to the cargoes.
 The court additionally states that it is  Petitioner, an insurer of the shipment paid to
fundamental in the law on damages that one Respondent the value of 204,450.00 being the
injured by a breach of a contract or by a wrongful subrogee of the rights industries of Concepcion
or negligent act or omission shall have a fair and Industries sought reimbursement of the amount it
just compensation commensurate to the loss paid from Respondent. Since the trucking
sustained as a consequence of the defendant’s company failed to heed the claim, Petitioner filed
act.
a complaint for damages and breach of contract  The Court affirms the decision of the C.A and
against Respondent RTC insofar as Respondent Driver is
Respondent’s Reply concerned, but the assailed order of the
trial court and decision of appellate court
 Respondent replied that they have been the only
are reversed as regards to Respondent
hauler of Concepcion Industries since 1988 and it
which is ordered to pay Petitioner 204,450
was not engaged in business as a common
for the lost and damaged cargoes.
carrier. Furthermore, respondents assert that the
cause of damage was accidental.  On the first issue, the court finds that the
conclusion of the lower courts was justified as
 Respondent also filed a leave of court with motion
Respondent is an exclusive contractor and hauler
to dismiss the complaint by way of demurrer on
of Concepcion Industries. A trucking company
the ground that petitioner failed to prove that
which is an exclusive contractor and hauler of
Respondent was a common carrier.
another company, rendering or offering its
RTC Ruling services to no other individual or entity, cannot be
 The RTC granted the motion to dismiss stating considered a common carrier.
that petitioner did not present any single o Common carriers are persons,
evidence that would prove that Respondent is a corporations, firms or associations iin the
common carrier. business of carrying or transporting
o The RTC added that under the law on passengers or goods or both by land
obligations and contracts, negligence or water or air for hire or compensation,
fault is not presumed. The law on quasi offering their services to the public,
delict provides for some presumption of whether to the public in general or to a
negligence but only upon the attendance limited clientele in particular, but never
of some circumstances. on an exclusive basis.
o Thus, Art 2185 provides that a person o The test of a common carrier is the
driving a motor vehicle has been carriage of passengers or goods providing
negligent if at the time of the mishap he space for those who opt to avail
was violating any traffic regulation. themselves of its transportation service
for a fee.
 In this case, there was no proof
that Respondent had been  In culpa contractual, the mere proof of the
violating traffic regulation, existence of the contract and the failure of its
hence, the negligence does not compliance justify prima facie, a corresponding
apply. right of relief; indeed, agreements can accomplish
little, either for their makers or for society unless
Court of Appeals Ruling
they are made the basis for action – the effect of
 The Court of appeals rejected the appeal of every infraction is to create a new duty, that is, to
Petitioner and ruled in favor of Respondent. In its make recompense to the one who has been
ruling, the C.A stated the following: injured by the failure of another to observe his
o In order for the presumption of contractual obligation unless there is a showing of
negligence provided for under the law extenuating circumstances like proof of due
governing common carriers to arise, diligence or the attendance of a fortuitous event
petitioner must prove that respondent is which can excuse him from liability.
a common carrier. Failing to do so would  In this case, the driver, who is not a party to the
mean that the presumption would not contract of carriage may not be held liable under
arise. the agreement – action against the driver can
o The Court of Appeals added that basing only be based on culpa aquiline which unlike
from the facts presented, Respondent culpa contractual would require the claimant for
had been the trucking corporation of damages to prove negligence or fault on his part.
Petitioner exclusively since 1079, thus, o The court applied the latin maxim of “res
Respondent had no choice but to comply inter alios acta aliis neque nocet prodest”
with the directive of its principal, that or “a thing done between others does not
Respondent is a private carrier. harm or benefit others" which means that
Issue such contract can neither favor nor
 Whether or not Respondent may be considered as prejudice a third person.
a common carrier  While Petitioner invokes the doctrine of Res Ipsa
 Whether or not Respondent either as a common Loquitur, the said doctrine is not a rule of
carrier or a private carrier may be presumed to substantive law and as such it does not create an
have been negligent when the goods it undertook independent ground of liability – instead the said
to transport safely were damaged while in its doctrine is a mode of proof and relieves the
protective custody and possession. plaintiff of the burden of producing specific proof
of negligence.
 Whether or not Res Ipsa Loquitor is applicable in
o The doctrine is allowed in the following
the case at bar.
cases only:
Ruling
 Event is of a kind which does not
ordinarily occur in the absence of
negligence
 Other responsible causes
including the conduct of plaintiff
and third persons are eliminated
by the evidence
 Indicated negligence is within the
scope of defendant’s duty to
plaintiff.
 While Res Ipsa Loquitur generally finds relevance
whether or not a contractual relationship exists
between the plaintiff and the defendant – for the
inference of negligence arises from the
circumstances and nature of the parties – the
requirement that responsible other than those
due to defendant’s conduct must first be
eliminated for res ipsa loquitur to apply. As it
should be understood as being confined only to
cases of pure tort or non-contractual ones
because negligence in culpa contractual
immediately attaches a failure of the convenant
or its tenor.

S-ar putea să vă placă și